Harrisburg Overpass Construction Update

Transcription

Harrisburg Overpass Construction Update
Harrisburg Overpass Construction Update
December 1, 2015
All Utility Work
East of Union Pacific Railroad
Utilities Completed
Total
Installed
% Completed
3,800 LF
2095 LF
55%
Utilities Remaining to be Relocated
East of Union Pacific Railroad
Concrete Paving
East of Union Pacific Railroad
Current Sidewalk Detour Plan
5
All Utility Work
West of Union Pacific Railroad
Total
Utilities Completed
4,150 LF
Installed
3,210 LF
% Completed
73%
Utilities Remaining to be Relocated
West of Union Pacific Railroad
Concrete Paving
West of Union Pacific Railroad
Progress and Planned Activities
• Pavement Operations are beginning in the Northeast Quadrant
• McCarthy will maintain driveways by adding crushed stone as required
• Relocated Street Lighting during construction to be maintained and illuminate along new
roadway
• METRO/McCarthy are working to adjust schedule activities to keep the project on schedule
• Select construction activities will be built concurrently with major bridge activities during the third phase of
construction
• McCarthy will be working extended hours to expedite completion of roadway pavement
• The placing, finishing, curing, and saw cutting new pavement requires extended work hours
• Utility crews started 12 hour days instead of 10 hours
• To make up time due to rain, McCarthy chose to work on one Sunday in November
• McCarthy plans to work extra shifts during the drilling of the 6 major bridge bents in Phase II
of the project
• Weather permitting, this work will begin in January 2016
9
30 Day Look Ahead
West of UPRR






Complete 24” Storm east of Caylor
Water line and Sanitary Sewer Service Taps
Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place
concrete, cure, and saw cut for new roadway, intersection and driveway pavement
Install curbs and sidewalks
Install underground conduit for bridge lighting
Install temporary asphalt transitions from existing roadway to new concrete pavement
East of UPRR






Complete all storm sewer lines
Complete 8” waterlines
Complete Sanitary sewer lines
Wet connects for water services
Clear and grub right of way for new roadway pavement
Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place
concrete, cure, and saw cut for new roadway, intersection and driveway pavement

Traffic control switch from south to north side of Harrisburg to complete utility work in southeast
quadrant
10
Marketing Update for East End Businesses
• Collaborated with the EEMD, the EECOC, Business Owners, and Residential
Stakeholders
• Final Product is the East End Calendar of Events scheduled to start on
Wednesday, December 2
•
•
•
•
•
We have produced 5,000 flyers ( English/Spanish)
Posters printed and distributed
Banners – facilities will install
Radio Buys with Univision ( Estereo Latino)
Print ads with two week run of the front cover and two page spread due December 2
– (Que Onda)
• Foam Arrows for business visibility
• Individual Store flyers
• Direct Mail/Door hangers
11
Radio Spots
12