Task 12: Laboratory Compaction
Transcription
Task 12: Laboratory Compaction
APPENDIX L Technical Memorandum Updating Bituminous Stabilized Materials Guidelines: Mix Design Report, Phase II Task 12: Laboratory Compaction AUTHORS: KJ Jenkins RWC Kelfkens 1 1. INTRODUCTION Background The purpose of this report is to provide results and conclusion as well as any possible recommendations with regard to an alternative method of compaction of granular material in the laboratory. In the civil engineering practice, properties of granular materials are tested in various ways, including triaxial testing, CBR (California Bearing Ratio) etc. Prior to these tests taking place, specimens of material first have to be prepared. That is to say it has to be compacted into some or other form so that the tests may be carried out. Samples are typically compacted into a cylindrical form for triaxial tests and into block form for MMLS type tests i.e. accelerated testing. Laboratory results and experience have shown that the results of material properties achieved in the laboratory are not as fair and consistent a representation of the field results as the industry would like. This is believed to be as a result of laboratory compaction methodologies currently being used. In the laboratory, compaction procedures include methods such as Mod AASHTO compaction (the densities achieved in the field are typical measured against the density achieved when using this compaction method), Marshall Hammer, Gyratory compaction and Vibratory Table compaction etc. These procedures all have their advantages and disadvantages. The factor affecting the final outcome of the material properties on site is that on site high amplitude and frequency vibratory compaction is used as apposed to impact compaction, which influences particle orientation, packing and other factors Mod AASHTO compaction and Marshall Hammer compaction are both impact compaction methods. Site compaction is done by means of vibratory compaction. This poses a problem when trying to compare the properties of the site compacted material to the properties of the laboratory compacted material. There are various differences in the sample structure when comparing impact and vibratory compaction: • the arrangement of the material particles is different (i.e. a different skeleton structure), • there may be a vary clear differences in the void contents of the two compaction methods, and • the final densities on site may be much higher than that which is achieved in the laboratory (e.g. site compaction may be as high as 104% of Mod AASHTO compacted density). Gyratory compaction allows for the particles to be kneaded against each other, thus giving a different skeletal structure and particle orientation to that of Mod AASHTO and Marshall Hammer compaction as well as different voids content. This however still differs from the results on site and as a result also yields different material properties from those achieved on site. According to results from research done by the CSIR (HL Theyse, 2004), vibratory table compaction provides the best results in terms of producing the same material properties in the laboratory as those which are obtained on site. The 2 skeleton structure and voids content are more similar than that of the other compaction methodologies when compared to site compacted material. As a result of the inconsistencies occurring between the field and laboratory properties of the compacted material, it was proposed that an alternative compaction method be identified and researched, one that would allow field compaction results to be simulated a closely as possible in the laboratory. Feedback received during the launch of TG2 (Technical Guidelines 2) (2002) indicated that vibratory compaction could provide a possible alternative. The research of the viability of the compaction method was to be assigned to a student at master’s level. Objectives The objectives of the research were as follows: 1. Identify an appropriate refusal density compaction procedure, similar to the one currently used internationally e.g. in the United Kingdom (UK) on asphalt material, that can possibly be adapted to compaction of Bitumen Stabilised Materials (BSMs) in South Africa. At the same time identify the different compaction requirements of BSMs relative to HMA. 2. Investigate refusal density compaction procedure for BSMs, i.e. bitumen emulsion and foamed bitumen stabilised material. 3. Establish a correlation between the refusal density compaction procedure and Mod AASHTO in order to provide a reliable link to field densities. 4. To enable the compaction of a specimen of 150mm diameter and 300mm height for use in triaxialtype testing. Currently specimens of this diameter can only be produced to a height of 125mm. 5. Establish a compaction protocol for the refusal density compaction method Layout of the report The report begins with an executive summary of the research, followed by Section 1, the Introduction. In the introduction, background to the research is given as well as providing the objectives and giving a brief layout of the structure of the report. Section 2 follows which is the Literature Study. Here a summary of various literatures that was studied for background on materials and compaction methods is made. This is followed by Section 3, the Methodology. This chapter explains how the various objectives will be achieved. Section 4 then provides the results, which include statistical results, of the experiments performed and provides for the interpretation of these results. Conclusion and Recommendations are then made in Sections 5 and 6 respectively, with Section 7 providing all references. 3 2. LITERATURE STUDY This Section of the report will look at various pieces of literature regarding compaction. Literature on foamed and emulsion mixes will also be addressed and the respective properties of both bitumen emulsion and foamed bitumen i.e. the material properties of the bitumen emulsion and foamed bitumen as well as the effect these two cold mixes have on the material properties of granular materials. Emulsion There are three main types of emulsion (US Patent, 2002): 1. Cationic emulsions: surfactants are constituted by polar molecules; formula RNH3+ X-. R is the hydrocarbon chain which constitutes the lipophilic portion of the molecule. NH3+ is the hydrophilic portion and X- is any anion from a strong acid. 2. Anionic emulsions: the general formula is R--Y-- C+. R is the hydrocarbon chain which constitutes the lipophilic portion. The hydrophilic chain is given by Y- C+. Y- is a carboxylic, sulphonic, sulphuric, phsphonic or phosphoric group. C+ is a metal cat-ion, often alkaline or ammonium. 3. Non-ionic emulsions: In this type of emulsion, surfactants are constituted by the R-(EO)n –OH molecule type. R is again the hydrocarbon chain which constitutes the lipophilic portion of the molecule. The hydrophilic portion is constituted by the (EO)n – OH radical; EO represents Ethylene Oxide. Typically either an anionic or cationic bitumen emulsion is used. Emulsion mixes are used in the base layer of the pavement structure as well as for a surfacing course (Miller Group et al, 2004). The application rates of the emulsion mix vary from 50mm to 200mm. Binder within the BSM-Emulsion coats the smaller particles selectively and the stiffness of the emulsion mix is less than that of the hot mix asphalt. For BSM-Emulsion voids range between 12% and 15% where in the open grade emulsion mixes it varies between 20% and 30%. The surface of an emulsion mix is also relatively fragile when it is compared to the surface of Hot mix Asphalt. Waterproofing is not provided for in unsealed emulsion mixes and the surface cohesion may also not be sufficient to withstand tangent stresses. The sealing of the surface of 4 unsealed emulsion mixes provides waterproofing and the inherent performance of the emulsion mix is not compromised in terms of premature stripping, oxidation and ravelling. Foam Mr. KM Muthen of the CSIR shows the following advantages of foam mixes in the Contract Report CR-98/077 (1998). Foam binder increases the shear strength properties of the treated material; it also reduces the moisture susceptibility of granular materials. In foamed bitumen stabilized material (BSM-foam) the strength properties approach those of cemented material, the BSM-foam is however flexible and fatigue resistant. When compared to other cold mix processes, foam treatment material can be used with a wider range of aggregate types. There is a saving in time, because foamed mixes may be compacted immediately and may carry traffic almost directly after compaction. Energy is also conserved because the aggregates remain cold while only the bitumen is heated. Curing of foam mixes does not result in the release of volatiles; therefore environmental side-effects are avoided. Usual time constraints for achieving compaction, shaping and finishing of the layers are also avoided. This is because foam mixes remain workable for extended periods of time. Foamed mixes may also be stockpiled without the risk of binder runoff and leeching. The last advantage listed is that the foam mixes may be constructed in adverse weather conditions such as cold weather or light rain, this is because the workability or quality of the finished layer is not really affected. 5 Compaction of Emulsion and Foamed BSMs Some of the early investigations into the compactability of BSMs were carried out at Stellenbosch University by Weston (1998), where he investigated Marshall, Mod AASHTO, Gyratory and roller compaction of foamed mixes. The CSIR also performed compaction experimentation on both BSM-foam and BSM-emulsion to determine the compactability of the types of mixes (Theyse, 2004). They used three methods of compaction i.e. Mod AASHTO, Gyratory and vibratory compaction. They found that there appears to be some logic governing the compaction of material but the rules seem to change from situation to situation. Factors such as the nature of the aggregate (grading and Atterberg Limits) compaction method, the type of bituminous binder (foam or emulsion) as well as the filler types used and filler contents all seem to have an effect. These factors, state the CSIR, make it very difficult to formulate a set of consistent guidelines that will ensure that the most appropriate compaction equipment, binder type, filler type and binder and filler content levels are achieved and are used. The CSIR also found that the difference between the grading and Atterberg Limits of the materials used in the investigation resulted in different optimal compaction methods for the different materials. One of the materials (Crushed hornfels) had a continuous grading and a low PI, this material was more conducive to vibratory table compaction. The other material, the decomposed granite, had a more uniform grading and it was more conducive to gyratory compaction. It is postulated that it may be because the crushed hornfels may have insufficient fines to form a paste in which the larger particles are suspended, orientated and moulded during compaction. During the CSIR’s investigation some observations were made. They are as follows: Compaction of Crushed hornfels using Vibratory Table compaction When low to intermediate emulsion contents (below 1.5 %) were used without filler, there was a strong positive effect on the compaction of the crushed hornfels. Where cement was used in combination with emulsion, there was a negative effect on the compaction of the crushed hornfels. When cement was used in combination with foamed bitumen, there was no effect on the compaction of the material. Compaction of crushed Hornfels using Mod AASHTO compaction The use of cement and fly-ash alone had a negative effect on the compaction of the material. Significant minimums occurred in the filled volume and volume of solids in the samples containing either 1 percentage fly ash or 1 percent cement. 6 Where the binder content was increased, there was a negative effect for both BSM-foam and BSM-emulsion. This negative effect was on the volume of solids; here significant reductions took place at the highest binder contents for both BSM-emulsion and BSM-foam. When filler was used in combination with foam, there was a reduction in the negative effect of increasing the binder content mentioned above. The effect of adding filler to the BSMemulsion was found to be insignificant, only the individual effects of the binder and filler were reflected in the case of the BSM-emulsion. Compaction of Gauteng granite (decomposed Granite) using Vibratory Table compaction When the binder contents were increased, using both foam and emulsion, there was a slight negative effect on the compaction in terms of the volume of solids. Compaction of Gauteng granite (decomposed Granite) using Mod AASHTO compaction In the case of both cement and fly-ash, there was no discernable influence on the compaction; Emulsion and foam both had the same negative impact in terms of a decrease in volume of solids with an increase in binder content. When looking at the vibratory compaction of the crushed Hornfels, the CSIR noted that the intermediate percentage of emulsified bitumen acted as a compaction lubricant, this was in terms of both volume filled and volume of solids results. This benefit of the lubricant was not found when using Mod AASHTO or Gyratory compaction. The vibratory type of compaction is, however, the preferred compaction method for this type of material; this in both the laboratory and in the field compaction. Emulsified bitumen at low to intermediate binder content levels (<1.5 %) may therefore assist as a compaction aid for crushed stone. It may also assist to improve the workability of recycled old crushed stone bases With regard to engineering properties the following observations were made by the CSIR: • The Unconfined Compressive Stress (UCS) of the crushed Hornfels increased with increased cement content regardless of the negative impact of cement on the compaction of the material. • As the binder content was increased there was a negative effect on the UCS of the material but less so for foam than emulsion. The Indirect Tensile Strength (ITS) observations were the same as for the UCS. Some of the conclusions drawn by the CSIR were, other than adding emulsified bitumen at an intermediate level to act as a compaction lubricant, there was little motivation to use either foamed or emulsified bitumen with crushed stone from a strength point of view. 7 The CSIR stated that there may be other considerations in favour of adding bituminous binder. Such considerations as to the improvement of the workability of an old crushed stone base layer that is being recycled, the retention of the fines in the layer in the long-term, and/or improving the water resistance of the material may be looked at when adding bituminous binder. The CSIR also noted that there was a definite benefit in using foam or emulsion in combination with cement. They state that the UCS and ITS requirements of the TG2 document could be achieved using these bituminous binders in combination with cement. From the validation phase of their research the effect of aggregate grading on the compaction of the material was again confirmed. They indicate that it is not only the deviation of the grading from the maximum density grading curve that determines the level of density that is achieved but also the grading of the material. The grading determines the preference of the material in terms of the type of compaction that will result in the highest possible density being achieved Comparison of different compaction methods using X-ray Computer Tomography (CT) In report No. 113/12 (EMPA No. FE 840544), March 2002 EMPA performed research to compare the difference in compaction methods using X-ray Computer Tomography (CT). The change that takes place as well as the difference in homogeneity & isotropy in asphalt concrete was examined, using the same mix but with different compaction methods. Three methods of compaction were used during this research: a) Marshall compaction, b) Gyratory compaction and c) LCPC Rolling wheel compaction. The investigation was carried out using the standard Air Void content determination (AV) and X-ray CT. Under the gyratory compaction it was found that the material loses heat in the centre (20C) and where it is in contact with the outside walls of the mould (100C). Although heat is lost in the centre of the specimen it was found that after the compaction the temperature in the centre was 50C higher than the temperature of the material near the top or bottom of the specimen. The results of the gyratory compaction showed that the material had a tendency to flow radially towards the side of the specimen. Under Marshall Compaction the pins used in the X-ray CT test did not move significantly in the horizontal plane, however, a few of the pins showed a slight tendency to move away radially, indicating that the material, during compaction is squeezed to the side. The air void content under the gyratory compaction was in some cases found to be 8 negative where the Marshall compaction gives a rather even air void distribution in the vertical direction, the bottom core pieces however have a slightly higher void content. EMPA noted the after 20 blows the difference in air void content using Marshall Compaction almost vanishes. The results from the three compaction methods showed that none of the compaction processes was able to produce homogeneous asphalt concrete specimens. Structurally different specimens are produced; therefore, state EMPA, there is no reason to expect these methods to produce specimens comparable to real life or to be used on alternate bases. Vibratory Compaction In the Example Paper: One-Point Vibrating Hammer Compaction Test for Granular Soils, Adam B. Prochaska and Vincent P. Drnevich (2005) show that there is great promise for the use of vibratory hammer compaction for the preparation of samples in the laboratory. They state that a One-Point Vibrating Hammer test on an oven dried sample will provide the maximum dry unit weight of the material and moisture content range for effective field compaction of granular soils. The results from this procedure were found to produce consistent and reproducible results. The test method is also applicable to a broader range of material than current vibratory table tests. The test results from the compaction of sandy soils indicated that the values for the dry unit weight in the densest condition are comparable to that obtained from the vibratory table tests. Mr. Thorsten Frobel of Fulton Hogan Ltd. in New Zealand provided information on the vibratory hammer compaction method used in New Zealand. In New Zealand the Mod AASHTO compaction procedure has been replaced by the Vibratory Hammer compaction test. The reason for this is that New Zealand has fairly soft aggregates, and the heavy dynamic compaction of the Mod AASHTO compaction method causes a change in the grading and this intern influences the Maximum Dry Density (MDD) and Optimum Moisture Content (OMC) significantly. The Vibratory Hammer compaction is used to specify the MDD and this is used to specify the target Dry Density for site. In the case of unbound granular materials no adjustment needs to be made to the target Dry Density, but in the case of stabilized material a correction needs to be made, therefore a sample is usually taken and compacted, either in the lab or on site at that moisture content so as to get an idea of the shift; the unbound pavement layer specification of New Zealand does however call for plateau testing. The New Zealand Specifications (TNZ, 2005) provide target compaction levels for two site types: 1. Greenfield sites The target Dry Density is quoted as: “The Maximum Dry Density (MDD) for construction shall be the higher of the maximum laboratory dry density at optimum water content (OWC) and the plateau density at optimum water content (OWC).” 9 Note that in New Zealand the term OWC is the same as the term OMC used in South Africa. 2. Overlay sites The target Dry Density is quoted as: “The Maximum Dry Density (MDD) for construction shall be the maximum laboratory dry density at optimum water content (OWC).” These compaction levels are expressed as percentage of the MDD achieved using the vibrating hammer, these levels are provided in table L. Lit 1 (TNZ, 2005). Table L. Lit 1: Mean an Minimum Level of Compaction of Pavement Layers as %MDD of Vibrating Hammer Values Sub-basecourse Pavement Basecourse Pavement Layers Layer Mean Value ≥ 95% ≥ 98% Minimum Value ≥ 92% ≥ 95% These compaction levels in table L. Lit1 are checked by testing five (5) randomly selected areas on site with a frequency of one (1) MDD per 5000m3 of material laid. Should the tested areas conform to the criterion in table L. Lit 1 the compaction levels are accepted (TNZ, 2005). The samples prepared in New Zealand are also used for UCS testing; this is in the case of stabilized material samples. The procedure followed by the New Zealanders is briefly outlined below; this is taken from NZS 4402: 1986 Test 4.1.3. • Hammer Specifications o Frequency = 25 to 60 blows per minute o Rating = 60 to 1200 Watt power consumption o Mass of Loading Frame + hammer and Downward Force = 300N ± 50N. The Hammer may also be operated manually by experienced personnel provided the hammer is held in an upright position and that the total downward force is also in the order of 300N ± 50N. For inexperienced personnel the hammer may be placed on a scale and a downward force be applied till the scale reads 30 or 40kg; this is done prior to compaction while the machine is switched off. o • Foot Piece Diameter = 145mm Mould Specifications 10 o Non-corrodible cylindrical metal mould = 152mm ± 0.5mm inside Diameter o A Metal Spacer = 150mm ± 0.5mm diameter. This is placed inside the mould prior to compaction. o • Final specimen height = 125 to 127mm high. Compaction Procedure o Mass of Material used for a sample = 5.5 kg o Assess the moisture contents required for the compaction. Adjust these content so that there are different moisture contents across the samples which span the OMC with in the required range. o Compaction time = 180sec ± 10sec per layer. o Number of layers compacted per sample = 2 layers The procedure described above is the procedure used to determine the Dry Density vs. Moisture content curve and the graphic image of the mounted hammer is shown on the following page in figure L.A: Mounting of vibrating hammer for the New Zealand vibrating hammer compaction procedure. There is also a procedure developed to determine whether or not the hammer which is being used is adequate. This is as follows: • A 10kg sample of Leighton Buzzard silica sand is taken, of which at least 75% passes the 600μm test sieve. The coarse fraction is discarded. Sufficient water is mixed with the sand finer than 600μm to raise the moisture content to 25% ± 5%. The material is compacted according to the procedure described above, excluding varying moisture contents, for a total of three samples, the mean Dry Density is then determined. If the mean Dry Density of the sand exceeds 1.74 t/m3 the hammer may be considered suitable for the compaction procedure. 11 Figure L. Lit 1: Mounting of vibrating hammer for the New Zealand vibrating hammer compaction procedure 12 In 2007 ASTM published a standard test method for the vibratory hammer, this is found in ASTM D7328-07. The procedure followed differs from the procedure developed and followed by the New Zealanders. The procedure described in ASTM D7328-07 has two methods, the first (method A) uses a mould of 152.4mm diameter and the second procedure (method B) uses a mould of 279.4mm diameter. For purposes of this research method B of this procedure may be ignored. The procedure described in method A is as follows: • Hammer Specifications o Frequency = 3200 to 3500 beats per minute o Impact energy (manufacturers rating) = 9.5 to 12 Joule o Weight of hammer = 53 to 89N excluding the weight of the tamper. A list of potential hammers and their characteristics are provided by the ASTM and is shown in table L. Lit 1 below: Table L. Lit 2: Potential vibratory hammers for ASTM vibratory hammer compaction procedure Bosch Bosch Milwaukee Milwaukee 11248EVS 11318EVS 5327-21 5336-22 Volts 120 120 120 120 Amps 11 11 11 13 1700-3300 1300-3300 3400 1300-3450 28-55 22-55 57 22-58 Impact Energy (J) 10 12 11 12 Length (cm) 46 45 44 47 Weight (N) 14.4 12.5 12.9 15 Beats/min Hz 13 • Hammer Frame Specifications o The frame shall have a metal clamp assembly to firmly hold the vibrating hammer that moves on guide rods that allows for free vertical movement. The guide rods are fastened to a metal base so as to keep them vertical and parallel. o The frame is designed to securely hold the vibrating hammer and clamp assembly in a vertical position during the removal and insertion of the mould. o The total applied surcharge of the clamp assembly + the vibrating hammer and tamper shall be 19.3kPa ± 0.7 kPa. The figures below were taken from ASTM D 7382 – 07 and the dimensions shown are in inches. Pins and/or clamps will be needed to secure the clamp assembly, vibrating hammer, and tamper above the mould to allow inserting the mould, adding soil to the mould, and removing the mould. Metal clamp Assembly Figure L. Lit 2: Mounting frame for ASTM vibrating hammer compaction 14 Figure L. Lit 3: Metal clamp assembly to firmly hold the vibrating hammer • • Mould Specifications o Cylindrical mould made of rigid metal o Average inside diameter = 152.4mm ± 0.7mm. o Height = 116.4mm ± 0.5mm. o Volume = 2124 ± 25cm3. Compaction Procedure o Material passing the 19mm sieve shall be used for the preparation of samples. o Samples are compacted in three layers. o A compaction time of 60sec ± 5sec per layer is used to compact each layer. The ASTM also has a procedure in order to check the suitability of a vibratory hammer for the compaction process. This procedure is in some ways similar to the New Zealand procedure for checking the suitability of a vibratory hammer. The procedure is as follows: • Standard sand shall be tested and is to conform to the requirements for 20-30 sand. These specifications are found in the ASTM specifications C778. Before the test is performed the material should be stored in such a way that freezing and/or contamination does not occur, if the material was previously used it should not be re-used. A required dry specimen mass of 7kg is required and must have a moist mass of at least 9kg. A representative sample meeting this specification is selected using a riffler or splitter or any such method quartering included. The vibratory hammer and mould (152mm diameter mould) are then prepared. The sand is then compacted according to method A described above. After compaction the Dry Density is calculated and should the sample meet or exceed a dry density of 1.76 ton/m3 (17.29 kN/m3) then the vibratory hammer may accepted as having sufficient energy. 15 Critical comments on the Literature In terms of the purpose of this research the procedure used in New Zealand is not an adequate procedure from which to work. The compaction time of 180 seconds per layer is long, although the samples may be reaching very high Dry Densities the coarse aggregate materials used in New Zealand are of a soft quality, it is as a result of this that New Zealand has moved away from the Mod AASHTO compaction method and adopted the vibrating hammer compaction method. The compaction method used by New Zealand does serve well in that it shows that the vibratory hammer compaction may be used to specify field densities as well as moisture levels in the field. The ASTM method for vibratory hammer compaction appears to be a newly developed method as it was only published toward the end of 2007. This procedure serves well to show what level of compaction time per layer may be necessary when preparing samples. It also helps identify what the total mass (i.e. all components of the set up; hammer, foot piece, mounting head etc.) of the set up should be. The ASTM methods identify a total mass of ±34kg; the New Zealand method identifies a total mass of 30-40kg. Both these masses are similar to the procedure followed in the British Standards (this method is discussed in sub section 3.1.2 of the methodology section), which shows a mass also in the order of 35kg ± 5kg. This is a good indication of what the order of the total mass of the vibratory hammer set up should be for our research. The total masses of New Zealand and the United Kingdom compaction procedure include the force applied by an operator, which shows what the mass of an applied dead load should be in order to achieve a total mass of ± 30kg, this is beneficial as less physical labour is needed by the operator to compact the material if a surcharge load is applied. From the literature on the ASTM vibratory hammer compaction method and the New Zealand compaction method a table analyzing the compaction energies was set up. Table L.Lit 3: Comparison of Total Compaction Energy – New Zealand vs. ASTM (Bosch 11248EVS) Vibratory Hammer New Zealand Bosch 11248EVS® Lower Limit (kJ) 63 51 Upper Limit (kJ) 151.2 99 Table L.Lit 4: Comparison of Average Compaction Energy per Layer – New Zealand vs. ASTM (Bosch 11248EVS) Vibratory Hammer New Zealand Bosch 11248EVS® Lower Limit (kJ) 31.5 17 Upper Limit (kJ) 75.6 33 16 The New Zealand specifications do not clearly state what the order of the impact energy should be, however by noting that the frequency of 25 to 60 blows per second (1500 to 3600 blows per minute) is similar to the ASTM standard of 3200 to 3500 blows per minute, which provides an impact energy of 9.5 to 12 Joule, a rough estimate of 7 Joule impact energy was made. The upper limit and lower limit indicate the range in which the energy should be. The ASTM method does show a lower impact energy both in terms of the total and per layer energy used, but this is due to the fact that compaction time is only 60 seconds, i.e. 1/3 of the New Zealand procedure. This shows that a higher point energy (energy per blow) may require less total energy to compact the sample, i.e. for a higher point energy less compaction time per layer is need to compact a sample and hence less total energy. 17 3. METHODOLOGY 3.1 COMPACTION This chapter provides a description of the methodologies used and followed in order to perform the required experimentation so as to determine the viability of the vibratory hammer as a means of compacting Granular materials in the laboratory. For this methodology either a clean untreated G1 or G2 material could be used to perform the experiments, both these materials are a good quality granular material used in the base course of pavements. Material would also be collect form site and this site material would be used to establish a correlation between the compaction of material in the laboratory and the compaction on site. A G2 material was finally taken; the fact that fine material from a source other than the parent rock could be added to a G2 quality material seemed more adequate because the material being taken from the site would have material present that was not from the original material itself. Two and three tests would be performed for a single experiment and the experiments were measured against the Mod AASHTO compaction method. Three experiments were typically done as this accounted for the variability of the results better than what two experiments would have. Two mix conditions were studied i.e. BSM-emulsion and BSM-foam. Under both mix conditions the moisture content of the material, the surcharge load on the vibratory hammer and the temperature of the material were the conditions under which the compaction experimentation would take place. These conditions were chosen as they are all factors which affect the compaction of granular materials. Under the conditions of moisture variation and surcharge load variation experiments were performed using time as measure to obtain both density equal to the Mod AASHTO density of the material at specific moisture content (100% Mod AASHTO) and the material’s refusal density. From these results a fixed moisture content and fixed dead load were decided on and the time to 100%Mod AASHTO was taken and experimentation on the material under varying temperature conditions was carried out as well as the correlation experiments. The results obtained from the experimentation were then compared to the results of vibratory table compaction, excluding the correlation experiment results. A full flow chart of the experimental design is provided for under the results section of this report. 3.1.1 Mod AASHTO Mod AASHTO compaction is the compaction method against which the vibratory hammer will be referenced. That is to say all results will be measured relative to Mod AASHTO densities. 18 3.1.2 Vibratory Hammer 3.1.2.1 Existing Procedures United Kingdom (UK) In the UK a compaction procedure for the vibratory hammer has already been developed, this can be found in BSEN12697-32-2003. The procedure is as follows: 1. The vibrating hammer is fitted with a circular steel tamper of 146 mm diameter 2. Each layer is compacted for a period of 60 seconds ± 2s. 3. During compaction a firm downward force is applied so that the resulting force (which includes the mass of the hammer is 350N ± 50N. 4. It is recommended that for inexperienced persons, that the hammer is placed on a scale and a downward force be applied till a reading of 35kg ± 5kg be achieved. This gives an indication of how force is needed to be applied by the person during compaction Comment: The tolerance of 50kN allowed for the applied downward force is very lenient. The result is that there is a large variability of the achieved densities. Delft University of Technology (TU Delft) TU Delft in the Netherlands also developed a compaction procedure regarding the vibratory hammer, refer PhD. Student Patrick Muraya. The procedure followed is long; therefore only a basic description of the procedure followed at TU Delft is provided here: 1. The exact mass of material of each layer is weighed off. 2. The thickness to which the layer will be compacted is also determined. 3. The mass of material is then poured into the mould, not spilling any material. 4. The compacting unit is then set up accordingly. The height adjusting rings are loosened and the compacting bar is lowered till it touches the material. The material is first compacted by hand (8 blows). The 19 height adjusting rings are then fastened X mm down from the nylon rings – X being the calculated thickness of the layer. 5. The hammer is then turned on and a small amount of pressure is applied till the nylon rings meet the height adjusting rings - i.e. the height of the layer is achieved. 6. The surface is then roughened (scarified) up using a bar with a rounded head and the next layer is added and compacted in the same way. This is done until compaction of the sample is completed. Figure 1 below shows a visual of the compaction set up at TU Delft. Vibratory Hammer Compacting Nylon Ring Bar Adjusting Ring Figure L.1: Compaction set up at TU Delft 20 3.1.2.2 Kango 637 ® Figure L.2A: Kango 637®_Vibratory Hammer The Kango 637 ® Vibratory Hammer was the first Vibratory Hammer that was tested in South Africa. Its technical specifications are provided in the table below: Table L.1: Technical details of Kango 637® Hammer Kango 637 Rated power Impact Impact rate at input energy rated speed 750 W uncertain 2750 1/min Frequency Weight 45.83 Hz 7.5 kg 21 3.1.2.3 Bosch GSH 11E ® During the course of experimentation, the Kango 637 ® experienced technical difficulties and as a result became unusable. The replacement part for the hammer could not be located in South Africa and hence a new hammer was purchased, the Bosch GSH 11E. Figure 2 below shows the Bosch GSH 11E Figure L.2B: Bosch GSH 11E ® Vibratory Hammer Replacement of the Kango Hammer 637 ® during the research became necessary due to the fact that it is no longer supported with parts and back up service in South Africa; therefore adjustments had to be made for the new implement i.e. the Bosch Hammer. A comparison of the Kango 637 ® and Bosch GSH 11E ® technical specifications are provided below: Table L.2: Comparison between Bosch GSH 11E® hammer and Kango 637® Hammer Rated power input Impact energy Impact rate at rated speed Frequency Weight Kango 637 Bosch GSH 11E 750 W uncertain 2750 1/min 45.83 Hz 7.5 kg 1500 W 6-25 J 900 – 1890 1/min 15 – 31.5 Hz 10.1 kg 22 3.1.3 Design of the mounting frame for the vibratory hammer 3.1.3.1 Kango 637 ® With the aid of technical/mechanical support at the University of Stellenbosch i.e. Mr Johan Muller, a mounting system for the Kango 637® was developed. Below is given a schematic of the frame as well as figures of the constructed frame Figure L.3: Top view of mounting frame for Kango Hammer ® 23 Figure L.4: Front view of the mounting frame for Kango Hammer ® Figure L.5: Front view of mounting frame for Kango Hammer ® 24 Figure L.6: Left view of mounting frame Figure L.7: Rear view of mounting frame for Kango Hammer ® Figure L.8: Full view of the frame for Kango Hammer ® 25 3.1.3.2 Bosch GSH 11E ® The mounting frame designed for the Bosch GSH 11E was effectively a modification of the existing Kango frame. The mounting head which is attached to the hammer was modified. This modification design was developed and executed by the workshop at the University of Stellenbosch Civil Engineering Department. This modification was necessary due to the fact that the size and shape of the Bosch GSH 11E® differs from that of the Kango 637®. The design appears a follows: Positioning of dead weight Sleeve Rubber fitting 113 127 112 870 Sleeve 64 50 Figure L.9: Schematic of the mounting head of the Bosch GSH 11E ® In both the original design and the modified deign, rubber was placed between the areas where the steel plates of the frame come into contact with the vibratory hammer. Due to the vibratory effect, the steel is constantly vibrating against the hammer; this could easily result in damages to the hammer. The rubber insertions protect the hammer from these damages. 26 Figure L.10: Front view of Bosch mounting Figure L.11: Rear view of Bosch mounting Figure L.12: Left view of Bosch mounting head Figure L.13: Full view of mounting head 3.1.3.3 Modifications to mounting system Further modifications were later made to the rods and base. A frame was designed by Mr. Dion Viljoen of Stellenbosch University Civil Engineering workshop in order to better stabilize the entire system. A pulley system was also fixed to the mounting head and frame to minimize the labour intensity of the compaction operation. During experimentation, questions regarding the mounting system arose. Specifically, how accurately are measurements being taken and how perpendicular is the footplate to the material mould when compacting. In 27 addition, after one layer of the specimen had been compacted, the hammer would be physically raised and removed from the rods. When the next layer was ready to be compacted, the hammer was then placed on the steel rods and physically lowered into position. This raises an issue concerning the amount of physical effort and time needed to raise and lower the hammer. The modifications stated in the first paragraph of this subsection (3.1.3.3) addressed these questions. The pulley system allows the vibratory hammer to be raised with less physical effort and allows it to be suspended once raised, so as to allow preparation of the next layer. This results in the hammer never being removed from the vertical shafts, whilst material for an additional layer is added. The hammer may then be lowered onto the material and compaction may commence. Furthermore, the stabilized frame results in less “wobble effect” of the mounting head thus more consistent and accurate readings may be taken and the hammer is more perpendicular during compaction. Figure L.14: Bottom of pulley Figure L.15: Top of Pulley Position where guides Stability frame Figure L.16: Left view of Stabilizing Frame are fastened to the Figure L.17: Front view of Stabilizing Frame 28 Mounted guide Figure L.18: Pulley system Figure L.19: Wooden base and mounted guide Figure L.20: Suspended Bosch Vibratory hammer 3.1.4 Vibratory table For both BSM-foam and BSM-emulsion an experiment using the vibratory table was to be done. The standard procedure for the vibratory table compaction method is found in the TMH 1: Revised Addition (1990). The specifications of the TMH 1 vibratory table compaction method are amplitude of 0.5mm, a frequency of 50Hz, a dead load surcharge of 50kg and a compaction time of 120sec (2min); for the purposes of this research compaction was done until the layer being compacted reached a layer thickness of 60mm. Measuring from the foot piece up, markings were made at intervals of 60mm and were labelled layer 1 through to layer 5, these markings are shown in figure L.21B. While the sample was compacted the operator watched to see at what point in time the marking, for the layer being compacted, become level with the top of the mould (not the extension piece). A steel rule was then placed across the top of the mould with the surcharge still inside the mould to verify that the marking for the respective layer was in fact level with the top of the mould (image on the right in figure L.21B); this was done for layer 1 through 4. An extension piece was fitted to the mould prior to compacting layer 5 but no marking was made for layer 5 on the surcharge; this was because the operator physically held the surcharge in place and could see when the footing of the surcharge reached the top of the mould. The compaction time to 100% Mod AASHTO density of the vibratory hammer was to be measured against the compaction time to 100% Mod AASHTO density using the vibratory table. 29 Three (3) samples were prepared for each mix (BSM-emulsion and BSM-foam) and again the moisture content was decided on and the target dry density was obtained from that; using the Mod AASHTO curves initially set up for each mix. The samples were then compacted till a layer thickness of 60mm was achieved and the time noted. The results from the experiment were then compared to the results of the vibratory hammer. 50 kg dead load 300mm x 150mm mould Vibratory table Figure L.21A: Vibratory table set up 30 The left image shows 50kg Surcharge how and where the markings were made on the surcharge. The image on the right shows how the height 300 x 150 mm of a layer is checked Steel Mould (in this case layer 2) after the compaction Steel Rule Layer Layer Layer Layer Foot Piece 1 2 3 4 of 60mm Layer 2 Layer 1 that layer was completed i.e. a layer thickness of 60mm was achieved. Figure L.21B: 60mm intervals marked on the 50kg Surcharge Frequency dial On/Off Neck extension Figure L.22: Vibratory table during compaction of the final layer 31 3.2 Experimentation 3.2.1 Material Type and Properties 3.2.1.1 Material Type The material type chosen to be used for experimentation purposes was a G2 material. This was acquired from Lafarge at their Tygerberg Quarry. For purposes of correlation to site compaction, material from a recycling project taking place along the N7 (between Cape Town and Malmsbury) was used. This material was acquired in two states. 1. Untreated milled material. 2. BSM-emulsion: milled material. The N7 material is also a G2 material but due to the milling process RAP (Recycled Asphalt Pavement) was present in the material make up. After completion of the G2 and N7 experimentation, a G5 material was used to perform repeatability experiments so as to establish whether or not the compaction procedure developed from the G2 material would be compatible with other granular materials, the G5 material was acquired from Lafarge at their Eesrte River Quarry. 3.2.1.2 Material Properties The following material properties for the G2, G5 and N7 Material were obtained. • Mod AASHTO curve of untreated material Table L.3: Technical Information of untreated G2 Material G2 Material: Untreated OMC Max Dry Density 6.15% 2260 kg/m3 32 Table L.4: Technical Information of untreated G5 Material G5 Material: Untreated OMC Max Dry Density 6.7% 2228 kg/m3 Table L.5: Technical Information of untreated N7 Material N7 Material: Untreated OMC Max Dry Density 5.12% 2138 kg/m3 • Mod AASHTO curve of Bitumen Stabilized Material (BSM) Table L.6: Technical Information of BSM-emulsion G2 Material G2 Material: BSM-emulsion OMC Max Dry Density 4.0% 2188 kg/m3 Table L.7: Technical Information of BSM-emulsion G5 Material G5 Material: BSM-emulsion OMC Max Dry Density 6.8% 2217 kg/m3 Table L.8: Technical Information of BSM-emulsion N7 Material N7 Material: Material Treated with BSMemulsion on Site OMC Max Dry Density 5.6% 2130 kg/m3 33 Table L.9: Technical Information of BSM-foam G2 Material G2 Material: BSM-foam OMC Max Dry Density 4.8% 2132 kg/m3 Table L.10: Technical Information of BSM-foam G5 Material G5 Material: BSM-foam OMC Max Dry Density 6.95% 2149.5 kg/m3 Atterberg limits of the G2, G5 and N7 material Table L.11: Atterberg Limits of Granular Materials used for experimentation Atterberg Limit G2 G5 N7 Linear Shrinkage Non Plastic 3.3% 2% Liquid Limit Non Plastic 24% 20% Plastic Limit Non Plastic 20.7% 16.3% Plasticity Index Non Plastic 3.3% 3.7% Grading curves: the first haul of G2 material was brought in bags, where the second haul was a large stock pile of material. Therefore to check the consistency of the grading 2 bags were selected and a grading done on them and a grading was done on the stockpile material. The grading between the selected bags and stockpile varied very little. The grading curve for the N7 material was obtained from MSc. Student Mr. Percy Moloto. 34 Grading curve: G2 material 120.0 Sample 1 Sample 1 Stock Pile Random Bag 100.0 % Passing 80.0 60.0 40.0 20.0 0.0 0.01 0.1 1 10 Seive Sizes (mm) 100 Figure L.23: Grading curve G2 material N7 Graded Crushed Stone: Wet Grading Curve UPPER LIMIT (Unsuitable: Too Fine) IDEAL (Suitable) LOWER LIMIT (Unsuitable: Too Coarse) N7 GRADED CRUSHED STONE 120.0 100.0 Upper Limit: Too Fine % Passing 80.0 Ideal: Suitable 60.0 40.0 20.0 Lower Limit: Too Coarse 0.0 0.0 0.1 1.0 10.0 100.0 Sieve Size (mm) Figure L.24: N7 Grading Curve 35 From the grading curves, material from the G2 stock pile and N7 were sieved into fractions and reconstituted. The N7 had a different grading to the G2 material and after reconstitution the differences could be seen. G2 Stock Pile & Quarry Grading Curve vs. N7 Material Grading Curve 120.0 100.0 G2 Stock Pile (US) N7 Material G2 Quarry Grading % Passing 80.0 60.0 40.0 20.0 0.0 0.01 0.1 1 Sieve Size (mm) 10 100 Figure L.25: Comparison of G2 Stock Pile & Quarry Grading to N7 Material Grading Figure L.26: Visual N7 Material Figure L.27: Visual N7 Material < 13.2mm ≥13.2mm 36 Figure L.28: Visual G2 Material Figure L.29: Visual G2 Material < 13.2mm ≥13.2mm Similar to the way in which the G2 and N7 material samples were prepared so to were the G5 materail samples prepared from a grading curve, the curve used to reconstitute the G5 sieved fractions into a sample is provided below. 100.0 90.0 Grading Curve G5 Material: Quarry Grading vs. US Adjusted Grading Curve Quarry Grading of G5 Material US Adjusted Grading 80.0 70.0 % Passing 60.0 50.0 40.0 30.0 20.0 10.0 0.0 0.01 0.1 1 Sieve Size (mm) 10 100 Figure L.30: Grading Curve G5 Material: Quarry Grading vs. US Adjusted Grading Curve Lafarge quarry provided a grading curve (the blue line in figure L.30), there curve however included fractions of material retained on the 26mm sieve. For purposes carried out during experimentation of the G5 material the grading curve was adjusted to include only material retained on the 19mm sieve and smaller sieves (the pink line); the curve was adjusted using a dry grading. 37 3.2.2 Technical Aspects of Experiments 3.2.2.1 Compaction procedure for experimentation performed Based on the two existing methods stated in sub section 3.1.2.1 a design procedure for the compaction experiments was developed. 1. A Mod AASHTO curve for the given material would be done. Form this curve the OMC value of the material was determined. 2. A BSM-emulsion Mod AASHTO curve and a BSM-foam Mod AASHTO curve were then done. From the GEMS manual it was found that for the moisture contents of BSM-emulsion a target moisture content of 60% OMC was used. This is due to the fact that the bitumen acts as a lubricant during compaction. So the final fluids content during compaction is then 60%OMC added to the % bitumen binder in the BSM-emulsion. For this Mod AASHTO curve the following moisture contents were used for BSM-emulsion: • 60%, 70%, 80%, 90% and 100% OMC For the BSM-foam Mod AASHTO curve the same moisture contents were used. 3. The targeted moisture content during compaction would then be decided on, e.g. compact at 80% OMC. From this, referring to the Mod AASHTO curve for the specific mix (BSM-emulsion or BSM-foam), the target dry density was then determined. 4. From step 3 the final mass of material and the mass of material per layer could then be determined. Only the moisture content needs to be taken out of the target dry density because the Mod AASHTO curve of the specific mix accounts for the presence of bitumen. The mass of material for each individual layer is then determined and weighed off. This is done because by controlling the mass of material per layer the thickness of the layer which will yield the equivalent dry density for 100% Mod AASHTO dry density is known and can be identified during compaction. 38 The sample was compacted in 5 layers to a height of 300mm, therefore the equivalent dry density for 100% Mod AASHTO dry density is at 60mm layer thickness for each layer. The decision to use five layers was based on ITT Report 18.1-1997 (van de Ven et al, 1997) where five layers were used during vibratory table compaction. Prior to compaction the vibratory hammer is placed on the steel rods and allowed to rest on the base plate. Where the bottom of the sleeve rests on the rod, a mark is made using masking tape. This is the zero line. The hammer is then raised and 60mm is measured upward from the zero line and another mark is made. When, during compaction the sleeve reaches the 60mm marked off line then it is known that 100% Mod AASHTO dry density has been reached. After compaction, a mark is made where the sleeve is at its final resting place, the hammer is raised and 60mm is measured up from that point again, and so it continues till the compaction of the sample as whole is completed; figure L.31 provides a visual of how this procedure looks. Figure L.31 is a visual of the procedure used to perform the compaction experiments on the G2, G5 and N7 material. The line marked 100% Mod AASHTO (60mm) is the position of the foot piece at the point in time when the sleeve reaches the 60mm marked off line on the guide rod. This point, based on the relevant calculations, is the point when 100% Mod AASHTO is achieved. The dashed line marked final position is the point where the refusal density of the material is reached, in the case of experiments performed where time was taken as a factor and not as a fixed value. The experiments were at first run so as to determine the compaction density plot over time, therefore compaction was done to the point where it was decided that no further compaction was possible without crushing the aggregate; refusal density, this point was decided on when it appeared that the sleeve no longer moved down the guide rods. After a layer had reached refusal density a mark was made on the guide rod and 60mm was measured up from that point. This 60mm mark was then the point at which the following layer reached 100% Mod AASHTO. It should be noted that during the compaction time to refusal density, the compaction was stopped at regular time intervals and the layer thickness at that point in time was noted. This was done by making a mark on the sleeve at that specific position and measuring the distance from that point to either the zero line in the case of layer 1 or the refusal density line of the previously compacted layer in the case of the subsequent layers. 39 In the case of the experiments where time was fixed and not taken as a factor, the 60mm position of the first layer was determined. Compaction of the layer took place as described previously but this time for an allocated time. After compaction of the first layer the thickness was measured by measuring from the final position of the sleeve, after the allocated compaction time, to the zero line, a mark was also made and termed final position. The hammer was then raised and 60mm was measured up from the point marked off as final position. The subsequent layers were then compacted according to their allocated times and the final positions noted. These layer thicknesses were then determined by measuring from their respective final positions to the final position of the previously compacted layer. This compaction procedure allowed the individual compacting to note whether or not the targeted 100% Mod AASHTO or site achieved density could be achieved in the allocated time. 5. Between the compaction of layers, the surface of the previously compacted layer is scarified (±10mm) using a chisel, this is done before the next layer’s material is added. This is done so that interlocking of the particles may take place. 6. The standard oven drying method is used to check the moisture content of the compacted sample. For each experiment a minimum number of two samples were used and a maximum of three samples was used. Two samples were used in the event that the variability of results was at a minimum (for e.g. Layer 1 of sample 1 takes 60 sec to compact and layer 1 of sample 2 takes 61 sec to compact). Typically though, three samples were used because this gave more accurate results and the variability of the results could be seen more clearly. 40 Initial Sleeve Zero Line Vibratory Hammer Step: determining the Zero Line Side of Mould Steal Rod Base Plate Wooden base Next 60mm 100% Mod AASHTO (60mm) Final position Zero Line Step: determining the 60mm Line for the first layer 100% Mod AASHTO(60mm) Final position 60mm Remaining 100% Mod AASHTO (60mm) Final position Zero Line Steps: determining the 60mm Line for the Final position 100% Mod AASHTO (60mm) next layer Figure L.31: Measurement of layer thicknesses 41 3.2.3 BSM-emulsion On the N7 recycling site a 60/40 anionic bitumen emulsion (stable grade) was used for the recycling. The content of emulsion added to treat the material was 3.3% bitumen emulsion. Therefore, in order to correlate the laboratory compaction to the site compaction as accurately as possible, the type of bitumen emulsion and emulsion content used on site was also used for the laboratory experiments. The bitumen emulsion was acquired from Colas. 3.2.4 BSM-foam Rehabilitation of the N7 highway between Cape Town and Malmsbury using BSMfoam took place around 2002/2003. 60/70 penetration bitumen was used with a content of 2.3% (Theyse, 2003), the First Level Analysis Report: HVS Testing of Foamed bitumen-treated crushed stone base on N7/1 near Cape Town. The material type of the base layer was a G2 material. For purposes of testing in the Laboratory an 80/100 penetration bitumen was used with a binder content of 1.98% (2%). The binder content of 1.98% was used because that was the binder content being used on site during rehabilitation using BSM-emulsion. The result is that a comparison of the compaction of BSM-emulsion to BSM-foam can be done with the binder content being the same. Below are pictures of the foam plant WLB 10 at the University of Stellenbosch. Figure L.32: Foam Nozzle Figure L. 33: Foam plant WLB 10 42 Figure L.34: Twin shaft pug mill mixer Figure L.35: Twin shaft pug mill mixer with dome 3.2.5 Further Experimentation It is thought that this compaction method will also be used to compacted untreated granular material. Therefore experimentation using clean granular material having only water added will also be investigated. 43 3.3 Material Property Tests 3.3.1 C.T. Scanning CT scanning was to be performed on a series of samples compacted under the Vibratory hammer and Mod AASHTO compaction. The samples were two (2) vibratory hammer compacted samples: 1 BSM-emulsion sample and 1 BSM-foam sample. The other sample was a BSM-emulsion sample compacted using Mod AASHTO compaction. The purpose of this scanning was to determine what the particle orientation of the samples was like and what the voids of the compacted sample looked like. TU Delft in the Netherlands agreed to perform the tests for the University of Stellenbosch. Transporting the samples oversees was made difficult due the mass of each sample. A single sample compacted using the vibratory hammer had a mass of around 11kg. Therefore the samples were cut into two sections of ±75mm thick and the Mod AASHTO sample was section in half (this sample a massed to ±5kg). The sectioning is indicated schematically below. 150mm Top: S1B Middle: S1A 150mm 150mm 75mm Piece Sent: S2 ±60mm 75mm Top: S3B 75mm Middle: S3A 75mm Emulsion Mix: Mod Aashto BSM-emulsion: Mod Compaction AASHTO Compaction Emulsion Mix: BSM-emulsion: Vibratory Hammer Vibratory Foam Mix: Vibratory BSM-foam: Hammer Vibratory Hammer Figure L.36: Sectioned samples for CT Scanning 44 3.4 Statistical Analysis Statistical analyses were performed on the N7 site results. This was done to determine the target dry density to which the samples in the laboratory would be compacted when using the N7 material. The full statistical analysis performed on the N7 material can be viewed in Appendix A. For the BSM-emulsion, compaction densities on site were reaching as high as 110% Mod AASHTO and the lowest result found was at 101% Mod AASHTO. Therefore it was decided to use the 75th percentile to which compaction would be targeted. The 100% Mod AASHTO dry density was then determined. • 75th percentile = 104.61% Mod AASHTO = 2255kg/m3 • The 100%Mod AASHTO target dry density = 2159.05kg/m3 From the CSIR report stated in sub section 3.2.4 it was found that the BSM-foam layer never reached 100% Mod AASHTO compaction. Therefore to correlate the compacted laboratory sample to the site results the mean density achieved on site was used as the target compaction dry density. • Mean density achieved on site = 2177.33kg/m3 A statistical analysis will also be performed on the experimentation results of both N7 and G2 material. 45 4 Results and Interpretations This section of the report presents the results of the experiments performed as well as the interpretations there of. The moisture content provided in the figures in this section of the report are expressed as a percentage of the OMC of the clean or untreated material from the Mod AASHTO compaction (OMC (MOD-U)), e.g. 70% OMC is 70% of the OMC of the untreated material from the Mod AASHTO compaction. Below is a flow chart depicting the experimentation planning: Untreated G2 Material: OMC - Mod AASHTO Curve BSM: Bitumen Stabilised Material BSM-emulsion BSM-foam Mod AASHTO OMC Curve Compaction type Kango 637®/Bosch GSH 11E® TMH 1 Procedure Surcharge 10 kg 20 kg Vibratory Table 15/30 kg Moisture Content (%) 70%OMC 80%OMC 90%OMC Choose Best Result Temperature 0(Celsius) 5 15 35 Compaction of N7 Material: Field Correlation Flow Chart L.1: Experimentation Structure for G2 Granular Materials 46 4.1 Mod AASHTO Curves Prior to the commencement of the experiments, moisture curves were set up. First a moisture curve was set up using the clean untreated G2 material. The result is a follows: Moisture Curve of Untreated G2 Material: Mod AASHTO 2280.0 2260.0 Dry Density (kg/m3) 2240.0 2220.0 2200.0 2180.0 2160.0 2140.0 2120.0 2100.0 0.0 1.0 2.0 3.0 4.0 5.0 OMC: 6.15% 6.0 7.0 8.0 9.0 Moisture Content (%) Figure L.37: Mod AASHTO Moisture Curve of Untreated G2 Material From the figure it is found that the OMC (MOD-U) of the G2 material is 6.15% with a maximum dry density of 2260kg/m3. From the OMC, two new figures were set up using the G2 material. A moisture curve for material treated with emulsion and a moisture curve for material treated with foamed bitumen. The BSM-emulsion was prepared using a 60/40 bitumen emulsion with 3.3% emulsion added to the material. The figures are as follows: 47 Moisture Curve of BSM-emulsion G2 Material: Mod AASHTO 2200 Dry Density (kg/m3) 2186 2180 2160 2140 2120 2100 2080 2060 0.00 2.00 OMC: 3.8% 4.00 6.00 8.00 Moisture Content (%) Figure L.38: Moisture Curve of BSM-emulsion G2 Material – Mod AASHTO Moisture Curve of BSM-foam G2 Material: Mod AASHTO 2140.00 Mod Curve of BSM-foam G2 2131.00 Dry Density (kg/m3) 2120.00 2100.00 2080.00 2060.00 2040.00 2020.00 2000.00 0.00 1.00 2.00 3.00 OMC: 4.8% 4.00 5.00 6.00 7.00 8.00 9.00 10.00 Moisture Content (%) Figure L.39: Moisture Curve of BSM-foam G2 Material – Mod AASHTO From the BSM-emulsion figure and the BSM-foam figure it is found that the optimum moisture contents are 3.8% and 4.8% respectively. It is to be expected that the moisture content of the BSM-emulsion is lower than that of the BSM-foam. This is because in the BSM-emulsion the bitumen itself acts a compaction lubricant, where in the BSM-foam it does not. Therefore more moisture may be required 48 during compaction of the BSM-foam. For the BSM-emulsion the total fluid content is taken as the moisture content plus the bitumen binder content, in the BSM-foam it is only the moisture that acts as a compacting lubricant. Therefore for moisture content of 3.8% the bitumen emulsion will have a fluid content of 5.78%, much higher than the foam mix moisture of 4.8%. Comparative figures are provided below to show how the BSM-emulsion and BSMfoam moisture curves look in comparison to the moisture curve of the untreated G2 material. Comparative curves for both BSM-emulsion and BSM-foam material were also set up so as to compare the Mod AASHTO OMC moisture curve to the OMC moisture curve of the Vibratory Hammer, these curves are provided and discussed at a later stage in this section of the report. Comparison between Mod AASHTO curve of Untreated G2 and BSM-emulsion G2 Material - Mod AASHTO 2300 Density kg/m3 2260 2250 2.35% Mod AASTHO Untreated G2 BSM-emulsion G2 2200 2186 2150 2100 2050 0.00 1.00 2.00 3.00 3.80 4.00 5.00 6.15 6.00 7.00 8.00 9.00 Moisture % Figure L.40: Comparative Moisture Curve of Untreated G2 and BSM-emulsion G2 Material – Mod AASHTO 49 Comparison between Mod AASHTO curve of Untreated G2 and BSMfoam G2 Material - Mod AASHTO 2300 Dry Density (kg/m3) 2260 2250 2200 1.35 Mod curve of untreated G2 Mod Curve of BSM-foam G2 2150 2135 2100 2050 2000 0.00 2.00 4.00 4.80 6.15 6.00 8.00 10.00 Moisture Content (%) Figure L.41: Comparative Moisture Curve of BSM-foam and Untreated G2 Material – Mod AASHTO 50 4.2 Compaction of Site treated Material – BSM-emulsion: Kango 637 At the beginning of 2007, i.e. between February 2007 and April 2007 material was obtained from the N7 site while the recycling project was underway. This material had already been milled and treated with bitumen emulsion and was used to produce samples for triaxial testing that needed to be performed on the material, the triaxial set up at the University of Stellenbosch does not accommodate a sample height in excess of 250mm, therefore the samples prepared were to have dimensions of 250mm x Ф 150mm. The vibratory hammer was used to produce these samples; therefore initial experimentation of the vibratory hammer compaction set up took place on this material. For these experiments the Kango 637® was used. Samples were compacted in five layers (van de Ven, 1997) and the target Dry Density was known before hand (site compaction results were obtained from Soil Lab and these were used to determine the target Dry Density of 100% Mod AASHTO), therefore the mass of material per layer could be determined and the time to the target Dry Density could be measured; once a layer reached a thickness of 50mm the 100% Mod AASHTO target Dry Density was achieved. The marking procedure described in the methodology section was not used for the experiments on the site treated BSMs, rather at regular time intervals the hammer was raised and the height of the sample was measured using a tape measure by measuring from the surface of the compacted layer to the top of the mould and subtracting that measurement from either 250mm (in the case of layer 1) or the sum height of the previously compacted layers. 51 4.2.1 0kg Surcharge %Mod AASHTO vs. Time: 0kg Surcharge Kango 637® N7 Site Treated Material 120.0 % Mod AASHTO 100.0 80.0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 60.0 40.0 20.0 0.0 0 20 40 60 80 100 120 Time (seconds) Figure L.42: 0kg surcharge - %Mod AASHTO vs. Time of separate layers site treated material, Kango 637® From Figure L.42 it is found that with no surcharge (i.e. the hammer is compacting under its own weight and that of the frame) it takes around 60 seconds to compact the site treated material to 100% Mod AASHTO (from information provided in the methodology chapter, 100% Mod AASHTO for this experiment is given as 2130kg/m3). The compaction curve plateaus out between 101% and 103% Mod AASHTO (depending on the layer). That plateau is taken as the refusal density. The material compacted for layer one reached a higher refusal density than the remaining four layers. This is possibly due to it being compacted against the steel base plate. From the figure it appears that when the material is compacted against other layers the density is not as high as layer one’s refusal density but they appear more consistent, this is possibly due to the softer surface of the underlying layer against which it is compacted when compared to the hard steel base plate. 52 4.2.2 10kg Surcharge %Mod AASHTO vs. Time: 10kg surcharge Kango 637® N7 Site Treated Material 120.0 % Mod AASHTO 100.0 80.0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 60.0 40.0 20.0 0.0 0 20 40 60 80 100 120 140 160 Time (sec) Figure L.43: 10kg Surcharge - %Mod AASHTO vs. Time of separate layers of sample of site treated material, Kango 637® Figure L.43 shows a slightly different trend from Figure L.42. Here the layers do not all reach 100% Mod AASHTO in the same time. Layer 1, 3, and 5 all are at 100% Mod AASHTO after ± 45 sec of compaction (although layer 5 reaches 100% Mod AASHTO after only 30seconds). Layers 2 and 4 achieve 100% Mod AASHTO after 90 seconds of compaction. The final refusal densities are also more distributed varying from 109.5% Mod AASHTO for layer 5 to 100.7% Mod AASHTO for layers 2 and 4. It is not certain why layer 5 achieved such a high refusal density in comparison to the remaining layers. Small amounts of material were lost when emptying the bag of weighed of material for layer 5. therefore it is possible that the assumed mass of material of layer 5, when performing calculations, is in fact less and could yield a higher density calculation, this because, say for example 2000gm of material is weighed off for the layer and when it is emptied into the mould assume 100gm is lost to side of the mould, because there is a small space between the neck extension and the top of the mould, when the material is compacted to 55mm the actual density is less due the loss of material than what it would be because there is less mass in that volume of the layer, but for the calculations the original mass per layer is assumed. 53 4.3 Influence of Compaction over Time with Varying Moisture Content: G2 Material A factor that affects compaction quite significantly is moisture content. Moisture acts as a lubricant between particles and therefore aids in the shifting and orientation of particles during compaction. Therefore experiments were carried out using varying moisture contents and varying the applied dead load so as to asses the outcome of the compaction. 4.3.1 BSM-emulsion G2 Material 4.3.1.1 10kg Surcharge – Kango 637 70% OMC (MOD-U) Experiments performed on the BSM-emulsion G2 material at 70% OMC (MODU) were performed by civil engineering student Rojean Hanekom (Hanekom, 2007). Time To 100% Mod AASHTO Compaction: BSM-emulsion G2 Material 70% OMC (Mod-U) 10kg Surcharge, Kango 637® 60 50 Time (Sec) 40 30 20 10 0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 Layer Figure L.44: Time to 100% Mod AASHTO compaction at 70% OMC (MOD-U) – 10kg Surcharge BSM-emulsion G2 Material, Kango 637® 54 The results provided in Figure L.44 are the average result of three samples. The figure shows a variation in the time it takes to compact to 100% Mod AASHTO with layer 1 compacted the fastest to 100% Mod AASHTO (30 seconds). This is possibly due to the hard steel base against which the first layer is compacted. Layers 2 and 4 took the longest with both taking 50 seconds to compact to 100% Mod AASHTO. Layer 3 and 5 were also very close to each other at 40 seconds and 39 seconds respectively. These results show that there is only a 10 second variation in time with regard to the compaction of the final 4 layers. %Mod AASHTO vs. Time: BSM-emulsion G2 Material 70% OMC (Mod-U) 10kg Surcharge - Kango 637® 110.0 108.0 % Mod AASHTO 106.0 104.0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 102.0 100.0 98.0 96.0 94.0 92.0 0 50 100 150 200 Time (Sec) Figure L.45: Mod AASHTO Density over time of 70% OMC (MOD-U) BSM-emulsion G2 Material – 10kg Kango 637® Figure L.45 shows a relatively large variation in the achieved refusal density, with densities ranging from 103.3 % Mod AASHTO to 109% Mod AASHTO. Layers 1 through 4 all took 180 seconds (3 minutes) to compact to refusal density, but layer 5 took the least amount of time, requiring 150 seconds (2.5 minutes) to achieve refusal density. 55 80% OMC (MOD-U) Time to 100% Mod AASHTO Compaction: BSM-emulsion G2 Material 80% OMC(Mod-U) 10kg Surcharge, Kango 637® 70.00 60.00 Time (S) 50.00 40.00 30.00 20.00 10.00 0.00 Layer1 Layer2 Layer3 Layer4 Layer5 Layers Figure L.46: Time to 100% Mod AASHTO compaction at 80% OMC (MOD-U) – 10kg Surcharge BSM-emulsion, Kango 637® Figure L.46 shows a very consistent compaction profile for the time to 100% Mod AASHTO result. Only layer 4 is significantly out when compared to the remaining layers. When compared to Figure L.44, it appears that at 80% OMC (MOD-U) the compaction of the material is more consistent. 56 %Mod AASHTO vs. Time: BSM-emulsion G2 Material 80% OMC (Mod-U) 10kg Surcharge, Kango 637® 112.0 110.0 % Mod AASHTO 108.0 Layer1 Layer2 Layer3 Layer4 Layer5 106.0 104.0 102.0 100.0 98.0 0 50 100 150 200 250 Time (sec) Figure L.47: Mod AASHTO Density over time of 80% OMC (MOD-U) BSM-emulsion– 10kg Surcharge BSM-emulsion, Kango 637® The profile for the refusal density (Figure L.47) shows a slightly different result in terms of consistency of the results. The achieved refusal densities vary considerably, ranging from 103.5% Mod AASHTO to about 111% Mod AASHTO. Compaction times to refusal density also vary, ranging from 155 seconds to 240 seconds. The main reason for this could be the grading. Although the grading of each sample is the same, the grading of the various weighed off layers may differ from each other; this trend is seen in the other experiments. The mass of material required for one sample is decided before hand (Typically 13kg of material for a sample) and the separate layers are weighed of from this mass. The grading of the 13kg of material across the samples is consistent but because the layers are scooped out of this source using either a scoop or small spade, the grading of each layer may vary – some layers having more fines than others. If this is the case it could explain the variability in the refusal density. 57 90% OMC (MOD-U) Time to 100% Mod AASHTO Compaction: BSM-emulsion G2 ®Material 90% OMC(Mod-U) 10kg Surcharge, Kango 637 16.00 14.00 Time (s) 12.00 10.00 8.00 6.00 4.00 2.00 0.00 Layer1 Layer2 Layer3 Layer4 Layer5 Layers Figure L.48: Time to 100% Mod AASHTO compaction at 90% OMC (MOD-U) – 10kg Surcharge BSM-emulsion, Kango 637® Figure L.48 also shows a relatively consistent compaction profile for the time to 100% Mod AASHTO result. The times vary by no more than about 2 seconds across the sample. The compaction times range from 11 to 13 seconds, depending on the layer, this is however are too short to allow for adequate particle orientation. The result is that quality of site representation may not be adequate enough. The appearance of the material was very ‘slushy’ when compared to the 80% OMC (MOD-U) material. 58 %Mod AASHTO vs. Time : BSM-emulsion G2 Material 90% OMC (Mod-U) 10kg Surcahrge - Kango 637® 116.0 114.0 % Mod AASHTO 112.0 110.0 Layer1 Layer2 Layer3 Layer4 Layer5 108.0 106.0 104.0 102.0 100.0 98.0 0 50 100 150 200 250 300 350 Time (sec) Figure L.49: %Mod AASHTO Density over time of 90% OMC (MOD-U) BSM-emulsion G2 Material – 10kg Surcharge, Kango 637® Once again the refusal density profile (Figure L.49) shows high variability with densities ranging from 109% Mod AASHTO to about 115% Mod AASHTO. Compaction times to refusal density also vary, ranging from 210 seconds to 300 seconds. A clear result is that moisture content has an affect on the compaction of the material. From this result it was decided not to investigate compaction at 90% OMC (MOD-U) any further. As with the 80% OMC (MOD-U) the main reason for the variation in refusal density and time to refusal density could be the grading of the individual layers. 4.3.1.2 20kg Surcharge – Kango 637 70% OMC (MOD-U) Results are provided with reference to Rojean Hanekom (2007). The results obtained by Mr. Hanekom indicate that for a 20kg surcharge the compaction time to 100% Mod AASHTO took longer than that of the 10kg surcharge for the same moisture content (Figure L.50 and Figure L.44). The result appears interesting because it would be expected that for a higher surcharge the compaction time would be less. It was noted during experimentation that the Kango 637® did not rebound off the material (therefore having lower amplitude) as well with the 20kg surcharge as it did with the 10kg surcharge, 59 i.e. there was less of impact/vibratory affect on the material and more of a general vibratory affect. This could be a possible reason for this result. Time To 100% Mod AASHTO: BSM-emulsion G2 Material 70% OMC (Mod-U) 20kg Surcharge, Kango 637® 160 140 Time (Sec) 120 100 80 60 40 20 0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 Layer Figure L.50: Time to 100% Mod AASHTO compaction at 90% OMC (MOD-U) – 10kg Surcharge BSM-emulsion G2 Material, Kango 637® 60 %Mod AASHTO vs. Time: BSM-emulsion G2 Material 70% OMC (Mod-U) 20kg Surcharge - Kango 637® 106.0 104.0 %Mod AASHTO 102.0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 100.0 98.0 96.0 94.0 92.0 0 50 100 150 200 250 Time (Sec) Figure L.51: Mod AASHTO Density over time of 70% OMC (MOD-U) BSM-emulsion– 20kg Surcharge BSM-emulsion G2 Material, Kango 637® The refusal density profile of Figure L.51 also shows variability in the refusal densities achieved, with densities ranging from 101% Mod AASHTO to about 105% Mod AASHTO. The figure indicates that the time to refusal density is consistent. As with the 80% OMC (MOD-U) 10kg surcharge the main reason for the variation in refusal density could be the grading of the individual layers but interestingly the time to refusal density is consistent. 61 80% OMC (MOD-U) Time To 100% Mod AASHTO: BSM-emulsion G2 Material 80%OMC (Mod-U) 20kg Surcharge, Kango 637 ® 30 25 Time (sec) 20 15 10 5 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layer Figure L.52: Time to 100% Mod AASHTO compaction at 80% OMC (MOD-U) – 20kg Surcharge BSM-emulsion G2 Material, Kango 637® The result of 80% OMC (MOD-U) BSM-emulsion with a 20kg surcharge is a very consistent time to 100% Mod AASHTO. The 70% OMC (MOD-U) result for the same criteria (Figure L.50) showed a more variable result; Layers 1 and 4 taking 150 and 90 seconds respectively while layers 2, 3 and 5 took 60 seconds each). The assumption that a higher surcharge would result in less compaction time proved to be correct in the experiment at 80% OMC (MOD-U) (Mod-U) (taking less than half the time of 70% OMC (MOD-U) with the 10kg surcharge) but for the moisture content of 70% OMC (MOD-U) (figureL.50) it proved to be incorrect. 62 %Mod AASHTO vs. Time : BSM-emulsion G2 Material 80% OMC (Mod-U) 20kg Surcahrge - Kango 637 ® 112.0 110.0 %Mod AASHTO 108.0 Layer1 Layer2 Layer3 Layer4 Layer5 106.0 104.0 102.0 100.0 98.0 0 50 100 150 200 250 300 350 Time (Seconds) Figure L.53: Mod AASHTO Density over time of 80% OMC (MOD-U) BSM-emulsion G2 Material – 20kg Surcharge, Kango 637® The refusal density profile of Figure L.53 also shows variability in the refusal densities achieved, with densities ranging from 107% Mod AASHTO to about 111% Mod AASHTO. The figure also indicates that the time to refusal density is variable – between 210 seconds and 300 seconds depending on the layer. As with the 80% OMC (MOD-U) 10kg surcharge the main reason for the variation in refusal density results could be the grading of the individual layers. Another possible reason for the variation is the cushioning effect of subsequent layers. Layer 1 is compacted on the stiffest anvil (the steel base plate) while each layer following layer 1 is compacted on the scoured surface of the previous layer, the scoured surface creates a softer anvil on which the next layer will be compacted, the cushioning effect may also be a factor that influences the time to 100% Mod AASHTO compaction. 63 4.3.1.3 15kg Surcharge – Kango 637® Time to 100% Mod AASHTO: BSM-emulsion G2 Material 80% OMC (Mod-U) 15kg Surcharge, Kango 637 ® 80 70 Time (Sec) 60 50 40 30 20 10 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layers Figure L.54: Time to 100% Mod AASHTO compaction at 80% OMC (MOD-U) – 15kg Surcharge BSM-emulsion G2 Material, Kango 637® Figure L.54 indicates an interesting trend. The 15 kg surcharge at 80% OMC (MOD-U) shows times to 100% Mod AASHTO generally fall in between the 10kg and 20kg surcharge. The results, as with the 10kg and 20kg surcharge, are very consistent, only layer one has a notable variation, taking almost 70 seconds to reach 100% Mod AASHTO. Readings were taken at 180 seconds for the 15kg surcharge so as to determine what density could be expected at an extended compaction time from the time to 100% Mod AASHTO. 64 4.3.1.4 Comparison between Various BSM-emulsion Experiments-Kango 637® Timeto to100% 100% Mod Aashto compaction: Comparison 70%, 80%OMC & Time AASHTO: Comparison between between 70%, 80% & 90% 90% OMC - 10kg, 15kg and 20kg Surcharge BSM-emulsion G2 Emulsion Material –Mix 10kg, 15kg & 20kg Surcharge, Kango 637® 160 10kg 20kg 10kg 15kg 20kg 10kg 140 Time (Sec) 120 100 Surcharge Surcharge Surcharge Surcharge Surcharge Surcharge (70% (70% (80% (80% (80% (90% OMC) OMC) OMC) OMC) OMC) OMC) 80 60 40 20 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layers Figure L.55: Comparison of Time to 100% Mod AASHTO Compaction For varying Moisture Contents and Surcharges, BSM-emulsion G2 Material, Kango 637® The trend described in the previous sub section (4.3.1.3) between the 10kg, 15kg and 20 surcharges at 80% OMC (MOD-U) is evident in Figure L.55. The results of Mr. Hanekom’s experiments indicate a similar trend for the 70% OMC (MOD-U) moisture content in the opposite direction. The result is that the best time to 100% Mod AASHTO compaction that will also allow for sufficient time for good particle orientation is at 80% OMC (MOD-U) moisture content with a 10kg surcharge. 65 4.3.1.5 Bosch GSH 11E vs. Kango 637® Kango 637® vs. Bosch GSH 11E® : Time to 100% Mod AASHTO BSM-emulsion G2 Material 80% OMC (Mod-U) - 10kg Surcharge 70 60 Time to 100% Mod AASHTO: Bosch GSH 11E® Time to 100% Mod AASHTO: Kango 637® Time (sec) 50 40 30 20 10 0 1 2 3 Layer 4 5 Figure L.56: Comparison between Compaction times of Bosch GSH 11E® and Kango 637® Figure L.56 provides a comparative view between the Bosch® and the Kango® vibratory hammer with regard to BSM-emulsion. It is seen that the Bosch hammer also provides consistent results with only layer 4 and 5 varying. The difference in compaction time between the Bosch® and Kango® seems to remain consistent; a difference of 40 seconds is generally noted with the Bosch® compacting much faster. This reduction in compaction time by the Bosch GSH 11E® indicates that it exerts more compacting energy than the Kango 637®. 66 4.3.2 BSM-foam 4.3.2.1 10kg Surcharge – Bosch GSH 11E Compaction experiments carried out on the BSM-foam G2 material were performed using the Bosch GSH 11E®. This was due, as was indicated earlier in the report, to the fact that the Kango 637 ® had become permanently unavailable due to technical difficulties. Only experiments performed on BSM-foam by Mr. Rojean Hanekom were done using the Kango 637®, this was because at the time of his experimentation the Kango 637® had not experienced the technical difficulties which resulted in a replacement hammer. 70% OMC (MOD-U) - Kango 637® Experiments performed on BSM-foam material at 70% OMC (MOD-U) were performed by Rojean Hanekom (Rojean Hanekom, 2007). Time To 100% Mod AASHTO Compaction: BSM-foam G2 Material 70% OMC (Mod-U) 10kg Surcharge, Kango 637® 70 Sample1 Sample2 Average 60 Time (Sec) 50 40 30 20 10 0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 Layer Figure L.57: Time to 100% Mod AASHTO compaction at 70% OMC (MOD-U) 10kg Surcharge, BSM-foam G2 Material, Kango 637® The work done by Mr. Hanekom is shown in Figure L.57 and L.58 Figure L.57 indicates that there is considerable variability in the compaction of BSM-foam material when using the vibratory hammer. Samples used for 67 experimentation show the extent to which compaction of the foam mixes may vary. It is clear from this figure that the way in which the foam mixes behave is considerably different from the BSM-emulsion. The result of the 70% OMC (MOD-U) foam mix shows that each individual layer requires a separate compaction time. The middle layer appears to require the most time to achieve 100% of Mod AASHTO density. %Mod AASHTO vs. Time: BSM-foam G2 Material 70% OMC (Mod-U) - 10kg Surcharge, Kango 637® 110.0 108.0 %Mod AASHTO 106.0 104.0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 102.0 100.0 98.0 96.0 94.0 0 50 100 150 200 250 300 Time (Sec) Figure L.58: Mod AASHTO Density over time of 70% OMC (MOD-U) 10kg Surcharge, BSM- foam G2 Material, Kango 637® The refusal density plot of Figure L.58 is again indicative of what was seen in the BSMemulsion. The final refusal densities are variable, and vary from 105% Mod AASHTO to 108% Mod AASHTO. All these densities are achieved in the plateau stage of the figure, consistently at 180 seconds. Layer 1 reaches the highest refusal density at 108% Mod AASHTO; this is possibly due to the hard steel base against which it is compacted. Once again the main factor affecting this variability may be the variability of the grading of the individual layers. 80% OMC (MOD-U) – Bosch GSH 11E® The 80% OMC (MOD-U) BSM-foam shows a similar trend to that of the 70% OMC (MOD-U). There is much variability of the samples used for compaction, but the nature of the curve when viewing the average result is again a clime 68 to the middle layers and then a tapering off of the final layer. In the 80% OMC (MOD-U) BSM-foam Layer 4 requires the most amount of time to reach 100% Mod AASHTO. These results again indicate that when compacting foam mixes with the vibratory hammer each individual layer requires its own specified time. Figure L.59: Time to 100% Mod AASHTO compaction at 80% OMC (MOD-U) 10kg Surcharge, Time To 100% Mod AASHTO: BSM-foam G2 Material 80%OMC (Mod-U), 10kg Surcharge, Bosch GSH 11E® 40 35 Time (Sec) 30 Average between 3 Samples Sample 1 Sample 2 Sample 3 25 20 15 10 5 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layers BSM-foam Bosch GSH 11E® 69 %Mod AASHTO Vs. Time: BSM-foam G2 Material 80% OMC (Mod-U) - 10kg Surcharge, Bosch GSH 11E® 118.0 116.0 114.0 %Mod AASHTO 112.0 Layer1 Layer2 Layer3 Layer4 Layer5 110.0 108.0 106.0 104.0 102.0 100.0 98.0 0 50 100 150 200 250 300 350 Time (Sec) Figure L.60: Mod AASHTO Density over time of 80% OMC (MOD-U) 10kg Surcharge, BSMfoam Bosch GSH 11E® The refusal density plot of Figure L.60 shows again that the final refusal density is variable. In this case refusal densities vary from 110% Mod AASHTO to 116% Mod AASHTO. Layer 1 reaches the highest refusal density at 116% Mod AASHTO; this is possibly due to the hard steel base against which it is compacted. The result of this experiment shows how the moisture content influences the densities. Refusal densities for 80% OMC (MOD-U) are higher than for 70% OMC (MOD-U). 70 90% OMC (MOD-U) – Bosch GSH 11E® Time to 100% Mod AASHTO: BSM-foam G2 Material 90% OMC (Mod-U) -10kg surcharge, Bosch GSH 11E® 35 30 Average between 3 Samples Sample 1 Sample 2 Sample 3 Time (Sec) 25 20 15 10 5 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layers Figure L.61: Time to 100% Mod AASHTO compaction at 90% OMC (MOD-U) 10kg Surcharge, BSM-foam Bosch GSH 11E® As with the 70% and 80% OMC (MOD-U) BSM-foam curves, the 90% OMC (MODU) curves (Figure L.61) shows the same trend of climbing to the middle layers and then tapering off at the final layer also there is clear variability in the compaction of the various samples. The 90% OMC (MOD-U) requires the least amount of time to reach 100% Mod AASHTO but varies vary little from the 80% OMC (MOD-U) time to 100% Mod AASHTO. The refusal density plot of Figure L.62 shows a slightly different trend from the previous two refusal density plots. Here Layer 1 again reaches the highest refusal density (115.8% Mod AASHTO), but the remaining layers are all concentrated around the same refusal density point of ± 113% Mod AASHTO. The result of this experiment also shows that the refusal densities achieved are in the same bracket as that of the 80% OMC (MOD-U) refusal density plot. Therefore it may be assumed that there is vary little influence in the compaction for both time and density when going from 80% to 90% OMC (MOD-U) moisture content. 71 % Mod AASHTO vs. Time: BSM-foam G2 Material 90% OMC (Mod-U) - 10kg Surcharge, Bosch GSH 11E® 118.0 116.0 114.0 % Mod AASHTO 112.0 Layer1 Layer2 Layer3 Layer4 Layer5 110.0 108.0 106.0 104.0 102.0 100.0 98.0 96.0 0 50 100 150 200 250 300 350 Time (Sec) Figure L.62: Mod AASHTO Density over time of 90% OMC (MOD-U) 10kg Surcharge, BSMfoam Bosch GSH 11E® 72 4.3.2.2 15kg Surcharge – Bosch GSH 11E Time to 100% Mod AASHTO: BSM-foam G2 Material 80% OMC (Mod-U) -15kg surcharge, Bosch GSH 11E® 40 Average between 3 Samples Sample 1 Sample 2 Sample 3 35 Time (Sec) 30 25 20 15 10 5 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layers Figure L.63: Time to 100% Mod AASHTO compaction at 80% OMC (MOD-U) 15kg Surcharge, BSM-foam Bosch GSH 11E® The results presented in Figure L.63 show a variation in the behaviour of the material when compacting under a higher surcharge. Here the curve climbs, but as apposed to peaking in the middle layer it drops off and the climbs to the final layer. The characteristic that each layer requires an individual time to reach 100% Mod AASHTO is still present in this experiment. 73 %Mod AASHTO vs. Time: BSM-foam G2 Material 80% OMC (Mod-U) - 15kg Surcharge, Bosch GSH 11E® 120.0 118.0 % Mod AASHTO 116.0 114.0 Layer1 Layer2 Layer3 Layer4 Layer5 112.0 110.0 108.0 106.0 104.0 102.0 100.0 0 50 100 150 200 250 300 350 Time (Sec) Figure L.64: Mod AASHTO Density over time of 80% OMC (MOD-U) 15kg Surcharge, BSMfoam Bosch GSH 11E® The refusal density plot of Figure L.64 also shows that the final refusal density is variable. Here the refusal densities vary from 112% of Mod AASHTO density to 118% of Mod AASHTO density. Layer 1 reaches the highest refusal density at 118% Mod AASHTO; this is possibly due to the hard steel base against which it is compacted. From this experiment it may be seen that the result of increasing the surcharge weight has little affect on the refusal densities achieved, it is seen that after 300 seconds compaction time densities are still increasing. For the BSM-foam the compaction was stopped after 5 minutes (300sec) as it is believed that compaction exceeding 5 minutes is not likely to take place in preparation of samples. The bracket of refusal densities from this experiment is similar to that of the 80% and 90% OMC (MOD-U) BSM-foam with the 10kg surcharge. 74 4.3.3 Comparison between BSM-emulsion and BSM-foam G2 Material Figures L.65 and L.66 provide a graphic view of the difference in the response of BSM-emulsion and BSM-foam G2 material to vibratory hammer compaction. The BSM-emulsion has a more consistent time to 100% Mod AASHTO compaction where the BSMfoam has a clear curve to it indicating that each layer requires a different time to reach 100% Mod AASHTO compaction. Time to 100% Mod AASHTO Compaction: BSM-emulsion G2 Material 80% OMC(Mod-U) 10kg Surcharge, Kango 637® 70.00 60.00 Time (S) 50.00 40.00 30.00 20.00 10.00 0.00 Layer1 Layer2 Layer3 Layer4 Layer5 Layers Figure L.65: Time to 100% Mod AASHTO compaction at 80% OMC (MOD-U) – 10kg Surcharge BSM-emulsion, Kango 637® 75 Time To 100% Mod AASHTO: BSM-foam G2 Material 80%OMC (Mod-U), 10kg Surcharge, Bosch GSH 11E® 35.00 30.00 100% Mod AASHTO Poly. (100% Mod AASHTO) Time (Sec) 25.00 20.00 15.00 10.00 5.00 0.00 Layer1 Layer2 Layer3 Layer4 Layer5 Layer Figure L.66: Time to 100% Mod AASHTO compaction at 80% OMC (MOD-U) 10kg Surcharge, BSM-foam Bosch GSH 11E® 76 4.4 Time as a Fixed Unit with a Constant Moisture Content and Set Dead Load: G2 Material 4.4.1 Vibratory Table: 50kg Dead Load 4.4.1.1 BSM-emulsion The criteria used for the vibratory table was taken from the TMH1 Revised Addition (1990). The frequency for the table was set at 0.5Hz. Vibratory table compaction was done using a dead load of 50kg and the samples were compacted in 5 layers until 100% Mod AASHTO density was achieved. The experiment was conducted using two samples for an experiment and the average time to obtain 100% Mod AASHTO Density of the three samples was used to plot Figure L.67. Figure L.67: Comparison of Vibratory Table to Kango 637® Vibratory Hammer 10kg Time to 100% Mod AASHTO - Vibratory Table vs. Kango 637® with 10kg Surcharge: BSM-emulsion G2 Material 80% OMC (Mod-U) 70 Vibratory Table Kango 637 ® 60 Time (Sec) 50 40 30 20 10 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layer Surcharge: 80% OMC (MOD-U) BSM-emulsion G2 Material The results of Figure L.67 show a consistency in the time to 100% Mod AASHTO compaction. The vibratory table requires less time to compact to the target density of 100% Mod AASHTO when compared to the vibratory hammer, but the physical labour involved in using the vibratory table was much more than for the vibratory hammer. Typical problems that arose during compaction 77 were that the cross bars used to fasten the mould to the table frequently came loose and the 50kg surcharge (deadweight placed in the mould) was difficult to keep perpendicular to the material surface, this resulted in layers not necessarily being level after compaction but rather have a sloping effect. The end result of this is that although the vibratory table requires less compaction time per layer, the overall time to prepare a single sample was much more for the vibratory table (± 45 – 60min) than for the vibratory hammer (±30 – 35min) – almost double the time. 78 4.4.1.2 BSM-foamed The same procedure for the BSM-emulsion material (sub section 4.3.4.1) was applied to the BSM-foam material. Time to 100% Mod AASHTO - Vibratory Table vs. Bosch GSH 11E® 10kg surcharge: BSM-foam G2 Material 80% OMC (Mod-U) 90 Vibratory Table Bosch GSH 11E 80 Time (Sec) 70 60 50 40 30 20 10 0 Layer1 Layer2 Layer3 Layer4 Layer5 Layer Figure L.68: Comparison of Vibratory Table to Bosch ® Vibratory Hammer 10kg Surcharge: 80% OMC (MOD-U) BSM-foam G2 Material Upon comparing the vibratory table to the vibratory hammer for the BSMfoam a similar trend is noted in the vibratory table compaction. The compaction curve with time climbs and then tapers off at the final layer. The difference being where in Layer 4 of the BSM-foam the peak occurs for the vibratory hammer, this same peak occurs at Layer 2 of the vibratory table. The time it takes for the vibratory table to achieve 100% mod AASHTO is much higher than for the vibratory hammer, this is the exact opposite what is seen in Figure L.67 of the BSM-emulsion where less time is required by the vibratory table to achieve this target density of 100% Mod AASHTO. It must be remembered that although a difference between the results of the BSM-foam and BSM-emulsion is evident, the BSM-foam was compacted using the Bosch® hammer where the BSM-emulsion was compacted using the Kango 637®. The results of the correlation experiment between the two 79 vibratory hammers (Figure L.56) indicates that the same trend will occur for the BSM-emulsion as in the BSM-foam should the Bosch® hammer be used to compact the BSM-emulsion. Vibratory Table vs. Bosch GSH 11E® 10kg surcharge: BSM-foam G2 Material 80% OMC (Mod-U) - Final %Mod AASHTO Density 110.00 Vibratory Table Bosch GSH 11E % Mod AASHTO 108.00 106.00 104.00 102.00 100.00 98.00 96.00 Layer1 Layer2 Layer3 Layer4 Layer5 Layer Figure L.69: %Mod AASHTO Compaction after 120sec Compaction Time relative to Bosch GSH 11E® 100% Mod AASHTO Figure L.69 provides a Graphic view of the relationship of the vibratory table, when compacting according to the full specification of TMH1 (1990), compared to the result of compacting the BSMfoam to 100% Mod AASHTO using the vibratory hammer. Not much variation is noted in the density of the various layers –from Layer 1 to Layer3; a difference of about 1% is notable. Layer 4, however, shows significant increase in the density, no explanation can be given for this increase. Layer 5 shows that the material did not compact any further than the 100% Mod AASHTO density mark. As with the BSM-emulsion experiment, the vibratory table required much more time (±40 – 45min) to prepare a single sample than that of the Bosch ® vibratory hammer (±25 – 30min). 80 4.4.2 Temperature Variation: BSM-emulsion From the results of experiments performed earlier the criterion for these experiments were set up. Results showed that compaction moisture content of 80% OMC (MOD-U) with a surcharge of 10kg for the Bosch vibratory hammer, was the best criterion for representative compaction and was therefore selected for the performance of further experimentation. From the result of time to 100% Mod AASHTO compaction for this criterion and the correlation experiment (Figure L.56), times were allocated to each layer as to what would yield 100% Mod AASHTO compaction. Figure L.70: % Mod AASHTO Compaction at Fixed Time Units: 80% OMC (MOD-U) 10kg 109.0 % Mod AASHTO At Fixed Time Units: Temperature Variation BSMemulsion G2 Material 80% OMC (Mod-U) - Bosch GSH 11E ® 10kg Surcharge 5 Deg C 15 Deg C 35 Deg C 108.0 %Mod AASHTO 107.0 106.0 105.0 104.0 103.0 102.0 101.0 100.0 Layer1 (10 sec) Layer2 (15 sec) Layer3 (15 sec) Layer4 (15 sec) Layer5 (15 sec) Layer (Time sec) Surcharge, BSM-foam Bosch GSH 11E® The temperature of material is a factor which affects compaction; Figure L.70 shows the effect of the temperature on the compaction of the material. It is intuitive that at lower temperatures the material would not compact as well as it would at higher temperatures. This trend is not seen when comparing the results of the 50C to 350C experiment. For the 50C and 150C experiments, material was cooled in a fridge. The material was allowed to stand over night and was then removed from the fridge and the temperature measured. When the two bags marked off for the 50C 81 experiment measured 50C a single bag was taken to compact and the remaining bags placed in the fridge; this kept the bags at their target temperature as the temperature of the fridge measured around 50C. The bags marked off for the 150C experiment were allowed to stand out side of the fridge to warm up to 150C (±20C), this was done was they had also reached 50C. The trend from the experiment shows a reversal in the expected trend with the compatibility of the material becoming poorer as the temperature is increased. 82 4.4.3 Temperature Variation: BSM-foam As in sub section 4.4.1 the results of experiments performed earlier were used to establish the criterion against which these experiments for the BSM-foam would take place. Results showed that a moisture content of 80% OMC (MOD-U) with a surcharge of 10kg was the best criterion and as such was used to perform these experiments. From the result of time to 100% Mod AASHTO compaction for this criterion times were allocated to each layer as to what would yield 100% Mod AASHTO compaction. %Mod AASHTO At Fixed Time Units: Temperature Variation BSM-foam G2 Material 80% OMC (Mod-U) - Bosch GSH 11E® 10kg Surcharge 108.00 % Mod AASHTO 106.00 5 Deg C 15 Deg C 35 Deg C 104.00 102.00 100.00 98.00 96.00 94.00 L1 (10sec) L2 (28sec) L3 (30sec) L4 (34sec) L5 (30sec) Layer (Time sec) Figure L.71: %Mod AASHTO Compaction at Fixed Time Units: 80% OMC (MOD-U) 10kg Surcharge, BSM-foam Bosch GSH 11E® As in sub section 4.4.1 the trend of how material compacts at different temperatures is seen in layers 1 and 2 and when comparing the 50C to 350C experiment. Material for the 50C and 150C experiment were again prepared by cooling them in a fridge, however the fridge temperature was not adjusted for the 150C material. Instead it was cooled to 50C and allowed to stand in the bags outside the fridge for roughly 30 – 40 minutes. A thermometer and temperature probe was used to check the material temperature. Once a bag reached the target temperature of 150C ± 20C, the bag was taken and the material compacted. Therefore no 83 excess water was acquired by the material as a result of melting ice and no moisture was lost; moisture content readings show that the moisture obtained for the 150C experiment was around 74%OMC (MOD-U). It cannot be explained why the compaction trend of Layers 3, 4 and 5 indicates a drop off in the density achieved at 150C compared with 5ºC. 84 4.5 Moisture Curves of the Vibratory Hammer 4.5.1 BSM-emulsion The criterion of surcharge mass and compaction time per layer used in sub section 4.4.1 was applied to this experiment. Here moisture contents of 60, 70, 80, 90 and 100% OMC (MOD-U) were used. Compaction was done using the Bosch GSH 11E® and the results are provided in Figure L.72. The curves provided are the Mod AASHTO curve for the BSM-emulsion and the moisture content curve for the vibratory hammer compacted BSM-emulsion. Moisture Curve Mod AASHTO vs. Vibratory Hammer - Bosch GSH 11E® 10 kg Surcharge: BSM-emulsion G2 Material 2300.00 Vibratory Hammer Mod AASHTO 2263.00 Poly. (Vibratory Hammer) Dry Density (kg/m3) 2250.00 2200.00 2190.00 2150.00 2100.00 63.4% OMC 2050.00 0 2 3.9% 4 91.1% OMC 5.6% 6 8 10 12 Moisture Content (%) Figure L.72: Moisture Curve of Mod AASHTO vs. Vibratory Hammer: BSM-emulsion G2 Material The result of the BSM-emulsion experiment shows that the OMC (Vib Treated) point of the vibratory hammer is much higher (almost 30%OMC (MOD-U) higher) than for the Mod AASHTO OMC (Treated) point. The vibratory hammer curves at 5.6% moisture content where the Mod AASHTO curves at 3.9% moisture content, this almost 2% more moisture for the vibratory hammer before it curves. Analysing the densities, the vibratory hammer achieved a density of 2263kg/m3; this is much higher than the Mod AASHTO peak density of 2190kg/m3. Another interesting point is that the 85 curve shows that the vibratory hammer is more sensitive to moisture than the Mod AASHTO compaction. For the information provided in the table below, the moisture contents ranging from 80% OMC to 100% OMC yield an average density of 102.86% Mod AASHTO. Taking this average and referring to sub section 4.7.1 Site Results: BSM-emulsion, the procedure used achieved the 95th percentile of the site compaction results of 102.71% Mod AASHTO at these three moisture contents. Table L.12: %Mod AASHTO Compaction Achieved Using the Vibratory Hammer – BSM-emulsion G2 Material Sample M.C %OMC Achieved Dry Density (kg/m3) % Mod AASHTO 3 4.96 80.65 2206.76 101.23 4 5.53 89.92 2257.19 103.78 5 6.2 100.81 2245.76 103.59 The average density for the last three samples is 102.86% Mod AASHTO 86 4.5.2 BSM-foam The criterion of surcharge mass and compaction time per layer used in sub section 4.4.2 was applied to this experiment. As in sub section 4.5.1 moisture contents of 60, 70, 80, 90 and 100% OMC (MOD-U) were used. Compaction was done using the Bosch GSH 11E® and the results are provided in Figure L.73. The curves provided are the Mod AASHTO curve for the Foam mix material and the moisture content curve for the vibratory hammer compacted foam mix material. Moisture Curve Mod AASHTO vs. Vibratory Hammer - Bosch GSH 11E® 10 kg Surcharge: BSM-foam G2 Material 2320.00 2298.00 Mod AASHTO Vibratory Hammer Dry Density (kg/m3) 2270.00 2220.00 2170.00 2138.00 2120.00 2070.00 2020.00 78% OMC 71.5% OMC 1970.00 2 3 4 4.4 4.8 5 6 7 8 Moisture Content (%) Figure L.73: Moisture Curve of Mod AASHTO vs. Vibratory Hammer: BSM-foam G2 Material Contrary to sub section 4.5.1 the OMC (Vib BSM-foam) point of the vibratory hammer is lower than that of the Mod AASHTO OMC (BSM-foam) point; the difference is not significant, only 7%OMC (MOD-U) i.e. 0.4% moisture per mass of material. However when the achieved densities are viewed a clear difference is seen. The vibratory hammer achieved a density of 2298kg/m3; this is much higher than the Mod AASHTO peak density of 2138kg/m3. The figure shows that the vibratory hammer achieves higher densities than the Mod AASHTO compaction at the same moisture contents. 87 Figure L.40 shows, as in Figure L.39, that the vibratory hammer is more sensitive to moisture than the Mod AASHTO compaction. The maximum dry density achieved with the Bosch vibratory hammer using the BSM-foam (2298kg/m3) is slightly higher than the maximum dry density achieved for the BSM-emulsion (2263 kg/m3: Figure L.72). The reason for this could be that the compaction times per layer of the BSM-emulsion were generally around 15 seconds per layer, where the BSM-foam experienced longer compaction time, varying from 28 to 34 seconds depending on the layer. The BSM-emulsion and BSM-foam show a similar level of sensitivity to the moisture content. If the incline is taken as a straight line then the gradients are 2% for the BSM-emulsion and 1.835% for the BSM-foam. From this the BSM-emulsion does appear slightly more sensitive to moisture. Table L.10 indicates that the longer compaction time for the BSM-foam does in fact have an influence on the extent to which the samples were compacted. The compaction densities achieved for the above curve exceed 100% Mod AASHTO very comfortably; the density achieved near the peak is 108.4% Mod AASHTO. Table L.13: %Mod AASHTO Compaction Achieved Using the Vibratory Hammer – BSM-foam G2 Material Sample M.C %OMC Achieved Dry Density (kg/m3) % Mod AASHTO 1 3.32 53.97 2110.62 103.72 2 3.72 60.55 2215.71 107.14 3 4.09 66.52 2224.55 106.03 4 4.8 78.07 2262.49 105.97 5 5.53 89.9 2178.32 104.48 The average density achieved was 105.47% Mod AASHTO As with the BSM-emulsion material, these results indicate that at higher moisture contents higher compaction, in terms of %Mod AASHTO, is achievable. 88 4.6 Correlation to Site Material and Site Achieved Compaction In order to correlate the compaction experimentation of the G2 material to compaction being achieved in the field material was acquired from a Cold in Place Recycling (CIPR) Project along the N7. On this specific site a CIPR Project had taken place in 2002/2003 where a lane was treated using BSM-foam. In 2007 a CIPR Project took place again, but in this specific project BSM-emulsion was used to treat the appropriate lanes. The field compaction results for the BSM-foam CIPR were obtained from HL Theyse, CR-2003/23. The field compaction results and relevant field information for the BSM-emulsion CIPR were respectively obtained from Soil Lab and the engineers responsible for the project. The field results for the respective mixes are provided in the statistical analysis section of this report. Under this section (4.6) results marked N7 material are the results of the milled N7 material treated with either bitumen emulsion or foamed bitumen and then compacted in the laboratory. 4.6.1 BSM-emulsion The criteria of moisture content, surcharge mass and compaction time per layer used in sub section 4.4.1 was applied to this experiment. Compaction was done using the Bosch GSH 11E® and the results are provided in Figure L.74 The figure indicates how the N7 material correlates to the G2 material when using the same criterion when both materials have been treated with bitumen emulsion. From the statistical analysis results of site compacted material, the 85th percentile was chosen as the target density mark, this in tern showed that the target dry density of the site compacted material which would give its equivalent 100% Mod AASHTO was 2138kg/m3 , this is the target dry density of the N7 BSM-emulsion. 89 Comparison Between G2 & N7 Compacted Material: 80% OMC (Mod-U), Bosch GSH 11E® 10kg Surcharge, BSM-emulsion N7 Material 110.0 5 Deg C G2 108.0 15 Deg C G2 % Target Dry Density 106.0 35 Deg C G2 104.0 102.0 100.0 98.0 96.0 94.0 92.0 90.0 Layer1 (10 sec) Layer2 (15 sec) Layer3 (15 sec) Layer4 (15 sec) Layer5 (15 sec) Layers (Compaction Time in seconds) Figure L.74: Comparison of G2 and N7 Material: BSM-emulsion What becomes immediately clear is that the criterion for the clean G2 material does not work for the N7 material. The N7 material never reaches 100% of the achieved site density. The main reason for this is the grading. From the grading curves presented in the Methodology section it is clear that the grading between the G2 material and N7 material differ. Material properties also differ, this because although the N7 material is of G2 quality, it contains RAP in it as a result of the milling process; traces of cement may also be present should the base have been treated with cement during the initial construction of the road. 4.6.2 BSM-foam The criterion of surcharge mass and compaction time per layer used in sub section 4.4.2 was applied to this experiment. Compaction was done using the Bosch GSH 11E® Hammer and the results are provided in Figure L.75. The figure shows how the N7 material correlates to the G2 material when using the same criterion when both materials have been treated with foamed bitumen. A statistical analysis was also performed on the results of site compacted material taken from the CSIR report CR 2003/23 (Theyse, 2003); the mean dry density was chosen as the target density to which the N7 material would be compacted. This is due to the fact that on the 90 BSM-foam CIPR site compaction never reached 100% Mod AASHTO compaction. The mean density was found to be 2177.33kg/m3. Figure L.75: Comparison of G2 and N7 Material: BSM-foam Comparison Between G2 & N7 Compacted Material: 80% OMC (Mod-U), Bosch GSH 11E® 10kg Surcharge, BSM-foam 108.0 Comparison between G2 & N7 compacted Material: Foamed Mix 108.00 106.00 % Target Dry Density 104.00 102.00 100.00 N7 Material 98.00 5 Deg C G2 96.00 15 Deg C G2 94.00 35 Deg C G2 92.00 90.00 Layers (Compaction Time in seconds) 88.00 L1 (10s) L2(28s) L3 (30s) L4 (34s) L5 (30s) Layer (time sec) As in sub section 4.6.1 it is immediately clear that the criterion for the clean G2 material does not work for the N7 material. Once again the N7 material never reaches 100% of the achieved site density. The main reason for this is the reason discussed in sub section 4.6.1 regarding the grading and material properties. It is also clear that the mix type, BSM-foam or BSM-emulsion, is not the cause of this behaviour of the N7 material. Densities achieved for both mixes of the N7 material are similar e.g. layer 1 in both cases is around 96% of the of the achieved site density. 91 4.7 Statistical Results 4.7.1 Site Results: BSM-emulsion Statistical Calculations: N7 Site Information Emulsion Mix n 1 2 3 4 5 6 7 8 9 10 11 12 Dry Density 2181 2227 2255 2255 2272 2287 2305 2323 2345 2345 2350 2367 %Mod Aashto 101.6 103.6 104.2 104.7 106.1 106.2 107.4 107.5 108.9 109.6 110.1 110.7 %Mod Aashto Percentile Mean = Std Dev = COV = 106.72 % 2.83 % 2.65 % 75th : 85th : 95th : 104.61 % 103.99 % 102.71 % Outliers n= 12 x0 = 101.6 1.81 |T0| = T= 2.29 |T0|<T Therefore there are no outliers Dry Density Percentile Mean = Std Dev = COV = 3 2292.67 kg/m 3 56.76 kg/m 2.48 % 75th : 85th : 95th : 3 2255 kg/m 3 2245.2 kg/m 3 2206.3 kg/m From the manual Standard Specifications for Road and Bridge Works (CSRA 1987) Ф = 15% (pg: 8200-9 Table 8206/1). Therefore the Dry Density is taken a the 85th percentile 92 The results of this statistical analysis show that the compaction results on site have vary little variation; this is seen in COV value of 2.48%. It is interesting to note that on average, the dry density achieved on site was in the order of 106% of Mod AASHTO density, these are very high levels of compaction and the level of variation was also very low, COV equalling 2.65%. 93 4.7.2 Site Results: BSM-foam Foam Mix on N7 First Level analysis report: HVS Testing of the Foamed Bitumen-Treated crushed Stone Base on N7/1 near Cape Town Version: 1st draft CSIR transportek Pages 13, 14, 15 Fig 14 and Fig 15 Summary of ofof the test Summary of the the pavement pavementand andinstrumentation instrumentationdetail detail the tstsections sections 60/70 Binder type Binder Content 2.50 % Field Dry Density (Fig 14) Field Dry Density (Fig 15) 2137 kg/m3 2166 kg/m3 Appendix C: rehabilitation investigation Distance (km) Field Dry Density 17.7 2109 kg/m3 16 2148 kg/m3 14 2146 kg/m3 11.99 2224 kg/m3 10 2218 kg/m3 7.8 2219 kg/m3 Mean = 2177.33 kg/m3 St Deviation = 49.15 kg/m3 C.O.V = 2.26 % Mod AASHTO Dry Density 2260 kg/m3 The results of this statistical analysis show, as in the analysis of the BSM-emulsion CIPR, that the compaction results on site have very little variation; The COV value for the BSM-foam is 2.26%. In contrast to the field compaction of the BSM-emulsion, the BSMfoam never obtained its 100% Mod AASHTO level of compaction; on average a compaction density of 96.34% Mod AASHTO was achieved. Overall, the statistical results from field compaction indicate that the extent to which field compaction varies is very low. The BSMemulsion and BSM-foam CIPR results had COV’s of 2.48% and 94 2.26% respectively. 95 4.7.3 Laboratory BSM-emulsion G2 Material 10kg Surcharge 70% OMC Sample1 Layer Sample2 Time to 100% Time to 100% Mod AASHTO Mod AASHTO (sec) (sec) Mean STD Dev C.O.V (%) 10.61 31.82 10.61 10.61 0.00 47.14 84.85 20.20 28.28 0.00 Layer1 Layer2 Layer3 Layer4 Layer5 30 60 45 30 30 15 15 60 45 30 22.50 37.50 52.50 37.50 30.00 Mean STD Dev C.O.V (%) 39.00 13.42 34.40 33.00 19.56 59.27 36.00 16.49 46.83 80% OMC Sample1 Layer Sample2 Sample3 Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer1 Layer2 Layer3 Layer4 Layer5 35 41 51.1 60 25 55.37 60.73 55.82 62.01 58.41 50.28 36 29.86 122 75.37 46.88 45.91 45.59 81.34 52.93 Mean STD Dev C.O.V (%) 42.42 13.65 32.17 58.47 2.93 5.01 62.70 37.49 59.79 54.53 18.02 32.32 STD Dev C.O.V (%) 10.60 13.08 13.83 35.23 25.63 22.61 28.48 30.33 43.31 48.42 96 90% OMC Sample1 Sample2 Sample3 Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer Layer1 Layer2 Layer3 Layer4 Layer5 12.52 15.77 9.47 10.45 11.72 11.65 12.77 13.29 17.19 14.9 10.93 9.81 9.6 12.57 13.07 11.70 12.78 10.79 13.40 13.23 Mean STD Dev C.O.V (%) 11.99 2.42 20.16 13.96 2.15 15.41 11.20 1.58 14.08 12.38 2.05 16.55 Sample2 Sample3 STD Dev C.O.V (%) 0.80 2.98 2.17 3.45 1.60 6.80 23.31 20.11 25.71 12.06 STD Dev C.O.V (%) 14.43 8.65 9.01 7.87 9.69 21.39 28.06 26.30 25.80 35.89 15kg Surcharge 80% OMC Sample1 Layer Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer1 Layer2 Layer3 Layer4 Layer5 67.44 28.68 35.74 25.89 18.24 53 23.47 24.59 26 25.33 81.85 40.37 42.42 39.57 37.4 67.43 30.84 34.25 30.49 26.99 Mean STD Dev C.O.V (%) 35.20 19.08 54.21 30.48 12.63 41.42 48.32 18.83 38.97 38.00 16.85 44.87 97 20kg Surcharge 70% OMC Sample1 Layer Sample2 Sample3 Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer1 Layer2 Layer3 Layer4 Layer5 130 25 25 63 32 210 90 46 45 60 110 86 165 170 145 150.00 67.00 78.67 92.67 79.00 Mean STD Dev C.O.V (%) 55.00 44.77 81.40 90.20 69.39 76.93 135.20 36.23 26.80 93.47 50.13 61.71 Sample2 Sample3 STD Dev 52.92 36.43 75.50 67.57 58.85 C.O.V (%) 35.28 54.37 95.98 72.92 74.49 80% OMC Sample1 Layer Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer1 Layer2 Layer3 Layer4 Layer5 17.3 12.8 16.32 13 24.91 18.87 22 28.03 22.3 18.37 20 20.99 12.28 23.13 16.44 18.72 18.60 18.88 19.48 19.91 Mean STD Dev C.O.V (%) 16.87 4.92 29.15 21.91 3.85 17.58 18.57 4.27 22.98 19.12 4.35 23.24 STD Dev 1.36 5.05 8.18 5.62 4.44 98 C.O.V (%) 7.24 27.13 43.34 28.88 22.30 The statistical results of the laboratory experimentation provided on the previous two pages show that for a 10kg surcharge the moisture content of 90% OMC (Mod-U) required, on average, the least amount of time to compact a layer to 100% Mod AASHTO, 12.38sec. The interesting result from this analysis is that on average at 70% OMC (Mod-U) less time is required to compact a layer to 100% Mod AASHTO density when compared to 80% OMC (Mod-U); at 70% OMC (Mod-U) 36sec is the average time to compact a layer to 100% Mod AASHTO where at 80% OMC (ModU) it is 54.53sec, this is not what is expected as the moisture content is increased. It is also notable that for the 10kg surcharge the 90% OMC (ModU) has a lower standard deviation (Std Dev) and coefficient of variation (COV). The Std Dev is only 2 seconds and the COV is 16.55%. The COV may be regarded as high, but when compared to the 70% and 80% OMC (Mod-U) of 46.83% and 32.32% respectively, it is much lower. The 15kg surcharge at 80% OMC (Mod-U) shows a consistency, statisticaly, to the 10kg surcharge of 70% OMC (Mod-U). The mean time to 100% Mod AASHTO differs by only 2 sec and the Std Dev for 15kg surcharge is 16.85sec compared to the 16.49sec of the 10kg surcharge at 70% OMC (Mod-U). The COV’s are also very similar, 44.87% for the 15kg surcharge and 46.83% for the 10kg surcharge at 70% OMC (Mod-U). This result of the 15kg surcharge indicates that similar behaviour of the material will occur when it is compacted at 70% OMC (Mod-U) with a 10kg surcharge. The trend differs when a 20kg surcharge is used. At 70% OMC (Mod-U) the mean time to 100% Mod AASHTO more than doubles, from 36sec at 10kg surcharge to 93.47 sec at 20kg. The Standard Deviation and COV also increase dramatically from 16.49sec to 50.13sec and from 46.83% to 61.71% respectively. The resulting effect is that as the surcharge load is increased, the material becomes less responsive to compaction at 70% OMC (Mod-U). This is due to the effect that at a higher surcharge load there is less vibratory/impact affect and more of a general vibratory effect. 99 The trend for 80% OMC (Mod-U) with a 20kg surcharge has the opposite effect to that of the 70% OMC (Mod-U) of the previous paragraph. The mean time to 100% Mod AASHTO more than halves and the Std Dev is almost one quarter of the Std Dev for the 10kg surcharge. The COV however does not drop as dramatically as the Standard Deviation and mean time to 100% Mod AASHTO; it does however drop significantly, i.e. by 10%. 100 Temperature Variation: 10kg Surcharge 80% OMC (MOD-U) 5 Deg Celscius Sample1 Layer Layer1 Layer2 Layer3 Layer4 Layer5 (10s) (15s) (15s) (15s) (15s) Mean STD Dev C.O.V (%) Sample2 % Mod AASHTO % Mod AASHTO Achieved Achieved 108.59 106.66 107.62 105.73 107.62 107.39 106.44 106.44 105.51 106.44 107.24 1.09 1.01 106.45 0.67 0.63 Mean 107.99 106.55 107.03 105.62 107.03 STD Dev C.O.V (%) STD Dev C.O.V (%) STD Dev C.O.V (%) 0.84 0.16 0.83 0.15 0.83 0.78 0.15 0.77 0.15 0.77 106.84 0.88 0.82 15 Deg Celscius Sample1 Layer Layer1 Layer2 Layer3 Layer4 Layer5 (10s) (15s) (15s) (15s) (15s) Mean STD Dev C.O.V (%) Sample2 % Mod AASHTO % Mod AASHTO Achieved Achieved 105.30 107.18 105.30 105.30 107.18 107.54 108.50 105.65 105.65 106.58 106.05 1.03 0.97 106.78 1.24 1.16 Mean 106.42 107.84 105.48 105.48 106.88 1.58 0.93 0.25 0.25 0.42 1.48 0.87 0.23 0.23 0.40 106.42 1.13 1.07 35 Deg Celscius Sample1 Layer Layer1 Layer2 Layer3 Layer4 Layer5 (10s) (15s) (15s) (15s) (15s) Mean STD Dev C.O.V (%) Sample2 % Mod AASHTO % Mod AASHTO Achieved Achieved 105.13 103.32 107.01 103.32 106.06 104.99 103.15 102.25 103.15 103.15 104.97 1.65 1.57 103.34 1.00 0.97 Mean 105.06 103.23 104.63 103.23 104.61 0.10 0.12 3.36 0.12 2.06 0.09 0.11 3.21 0.11 1.97 104.15 1.32 1.27 101 The statistical results of the temperature variation experiment for the BSM-emulsion show the reverse of the expected trend. The trend is expected to show that as the material becomes warmer the compaction will become better, but the opposite of this is reflected from the results of this experiment. The reason for this is unclear. The COV values across the samples show that the variability of the results is very low, COV being in the order of 1 for all three temperatures. When viewed independently, the 350C experiment produced the largest amount of variation (COV averaging 1.27%) and the 50C experiment showed the least amount of variation (COV averaging 0.82%), but the difference in COV values between the 350C and the 50C experiment is 0.45%, this is extremely small and may even be ignored. This shows that the temperature at which samples are prepared does not influence the variability of the samples, i.e. the variation in the level of compaction across samples prepared at 50C will not be more or less variable than the variation in the level of compaction across samples prepared at 350C in terms of the COV values. 102 4.7.4 Laboratory BSM-foam G2 Material 10kg Surcharge 70% OMC Sample1 Layer Sample2 Sample3 Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer1 Layer2 Layer3 Layer4 Layer5 150 180 180 180 180 150 150 180 180 180 180 180 210 150 150 160.00 170.00 190.00 170.00 170.00 Mean STD Dev C.O.V (%) 174.00 13.42 7.71 168.00 16.43 9.78 174.00 25.10 14.43 172.00 18.32 10.64 Sample2 Sample3 STD Dev C.O.V (%) 17.32 17.32 17.32 17.32 17.32 10.83 10.19 9.12 10.19 10.19 STD Dev C.O.V (%) 0.29 1.18 11.55 8.94 11.88 5.10 5.61 45.63 30.63 43.02 STD Dev C.O.V (%) 1.23 3.43 8.05 4.51 2.73 18.62 19.75 38.70 25.17 15.78 80% OMC Sample1 Layer Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer1 Layer2 Layer3 Layer4 Layer5 5.44 19.67 37.92 29.46 14.26 6.02 21.78 22.73 38 37 5.81 21.64 15.26 20.12 31.61 5.76 21.03 25.30 29.19 27.62 Mean STD Dev C.O.V (%) 21.35 12.71 59.55 25.11 13.12 52.26 18.89 9.42 49.89 21.78 11.75 53.90 Sample2 Sample3 90% OMC Sample1 Layer Time to 100% Time to 100% Time to 100% Mod AASHTO Mod AASHTO Mod AASHTO (sec) (sec) (sec) Mean Layer1 Layer2 Layer3 Layer4 Layer5 5.62 16.63 14.71 12.94 14.15 8 14.33 17.77 21.73 18.83 6.25 21.07 29.93 19.1 18.93 6.62 17.34 20.80 17.92 17.30 Mean STD Dev C.O.V (%) 12.81 4.23 33.05 16.13 5.26 32.61 19.06 8.46 44.40 16.00 5.98 36.69 103 15kg Surcharge 80% OMC Layer Sample1 Time to 100% Mod AASHTO (sec) Sample2 Time to 100% Mod AASHTO (sec) Sample3 Time to 100% Mod AASHTO (sec) Layer1 Layer2 Layer3 Layer4 Layer5 8.93 31.65 21.42 27.27 35.11 6.92 21.67 17.41 26.57 19.99 8.38 25.45 16.94 19.92 26.16 Mean STD Dev C.O.V (%) 24.88 10.28 41.32 18.51 7.29 39.39 19.37 7.25 37.41 20.92 8.27 39.37 Mean STD Dev C.O.V (%) 8.08 26.26 18.59 24.59 27.09 1.04 5.04 2.46 4.06 7.60 12.86 19.19 13.24 16.50 28.07 The statistical results of the BSM-foam experiments show the expected trend with regard to the moisture content. Under the 10kg surcharge, the mean time it takes to compact a layer to 100% Mod AASHTO density decreases as the moisture content increases. The 70% OMC (Mod-U) has a mean time of 172sec, at 80% OMC (ModU) the mean time is 21.78sec and at 90% OMC (Mod-U) the mean time is 16sec. From this it is evident that at 70% OMC (Mod-U) compaction time to 100% Mod AASHTO is too high and therefore inadequate to be used to produce samples. The mean time for the 80% and 90% OMC (Mod-U) moisture contents are much smaller and differ by 5.78 sec. The 80% OMC (Mod-U) is the best option in this case as the extra 5.78sec do not hamper production time and will provide time to allow for adequate particle orientation during compaction. From the results it is also seen that as the moisture content increases under the 10kg surcharge the Standard deviation also reduces as des the mean time to 100% Mod AASHTO. As with the BSM-emulsion experiments the 90% OMC (Mod-U) has the lowest Standard deviation under the 10kg surcharge. Interestingly, where the 70% OMC (Mod-U) of the BSM-emulsion under the 10g surcharge has the highest COV, this is not the case with the BSMfoam. Instead at 70% OMC (Mod-U) the BSM-foam has the lowest COV with the 80% OMC (Mod-U) having the highest COV. This indicates that although the 80% OMC (Mod-U) provides the most 104 adequate compaction time to 100% Mod AASHTO, it is also the moisture content that provides the most variable results, where, although the 70% OMC (Mod-U) takes the longest to compact to 100% Mod AASHTO, it also provides the results with the least variation. The 15kg surcharge at 80% OMC (Mod-U) has a mean time to 100% Mod AASHTO compaction similar to the 10kg surcharge at 80% OMC (Mod-U); less than 1 second difference between the two surcharges. The Std dev and COV under this surcharge are however much lower than the Std dev and COV under the 10kg surcharge. This means less variability in the compaction results. The results also indicate that the 15kg surcharge may be used as an alternative surcharge mass to the 10kg surcharge at 80% OMC (Mod-U); this may be done to reduce the variability of the compaction results. 105 Temperature Variation: 80% OMC (Mod-U) 10kg Surcharge 5 Deg Celscius Sample1 Layer Layer1 Layer2 Layer3 Layer4 Layer5 (10s) (28s) (30s) (34s) (30s) Mean STD Dev C.O.V (%) Sample2 Sample3 % Mod AASHTO % Mod AASHTO % Mod AASHTO Achieved Achieved Achieved Mean 96.36 101.18 104.67 105.58 108.41 96.98 100.21 103.67 100.21 101.91 103.19 103.19 101.46 102.32 104.08 98.84 101.53 103.26 102.70 104.80 103.24 4.63 4.49 100.60 2.48 2.46 102.85 1.00 0.97 102.23 2.70 2.64 Sample2 Sample3 STD Dev C.O.V (%) STD Dev C.O.V (%) STD Dev C.O.V (%) 3.78 1.52 1.64 2.70 3.31 3.82 1.50 1.59 2.63 3.16 15 Deg Celscius Sample1 Layer Layer1 Layer2 Layer3 Layer4 Layer5 (10s) (28s) (30s) (34s) (30s) % Mod AASHTO % Mod AASHTO % Mod AASHTO Achieved Achieved Achieved Mean Mean STD Dev C.O.V (%) 100.96 105.39 104.47 101.82 102.69 105.67 102.96 102.09 102.09 104.75 103.32 104.18 103.28 101.95 103.72 103.07 1.84 1.78 103.51 1.62 1.57 103.29 1.73 1.68 Sample2 Sample3 3.33 1.72 1.69 0.19 1.46 3.22 1.65 1.63 0.19 1.41 35 Deg Celscius Sample1 Layer Layer1 Layer2 Layer3 Layer4 Layer5 (10s) (28s) (30s) (34s) (30s) Mean STD Dev C.O.V (%) % Mod AASHTO % Mod AASHTO % Mod AASHTO Achieved Achieved Achieved Mean 101.20 106.53 105.60 105.97 103.80 100.55 105.84 105.84 104.63 107.73 107.85 105.96 105.96 105.96 105.96 103.20 106.11 105.80 105.52 105.83 104.62 2.17 2.07 104.92 2.68 2.56 106.34 0.85 0.80 105.29 1.90 1.81 4.04 0.37 0.18 0.77 1.97 106 3.92 0.34 0.17 0.73 1.86 The expected compactability trend between the 50C and 350C is seen, as the 350C experiment had a mean dry density of 105.29% Mod AASHTO and the 50C experiment had a mean dry density of 102.23% Mod AASHTO across the three samples of both temperatures. The statistical results show that the influence of the variation of the 150C experiment from the expected trend was from Sample 1. At 150C Samples 2 and 3 both produced mean densities of 103% Mod AASHTO, this is consistent with the expected trend, but Sample 1 produced a mean layer density of 99.37% of Mod AASHTO density, this is completely out of the expect compaction trend therefore another sample should be prepared and compacted so as to establish the trend. Looking at the average COV of the three samples, excluding sample1 of the 150C experiment, for each temperature the statistical results for the temperature variation experiments of the BSM-foam indicate that at 150C variability of the compaction results are the lowest while the temperature that produced the most variable results is at 50C. 107 4.7.5 COV values of the vibratory hammer for BSM specimens after determining the actual final mass and Dry Density The statistical calculations provided previously were all based on specimens in ideal circumstances, i.e. the calculated mass of material placed into the mould is the mass of the specimen that is produced. This is in reality not the case. Excessively wet samples tended to loose mass as material seeped out between the mould walls and the vibratory hammer foot piece (tamping foot). Therefore the final actual mass and Dry Density of each BSM specimen was noted, the Dry Density was then calculated. The results for the temperature variation experiments were then statistically analysed and the COV values for each temperature was determined. The results are as follows: Table L14: COV of vibratory hammer Temperature COV* of BSM Emulsion Foam 50C 0.13 0.24 150C 0.39 0.42 0.84 2.34 0 35 C *COV is of the vibratory hammer compaction The results show, as the previous statistical analysis showed, that as the temperature at which compaction takes place increases so to does the variability of the mixes increase. Generally the COV values are very low, i.e. they are comfortably below 1. The BSM-foam at 350C however is well above 2, this jump is significant. The reason for this is that of the three specimens compacted the third specimen produced a final Dry Density almost 4% higher than the first 2 specimens. The results shown in Table L14 also show that the BSM-emulsion produced specimens with less variability than did the BSM-foam. At 150C however the variability between the two mixes is very similar. 108 4.7.6 Comparing the COV values of the vibratory hammer to the COV value of the Mod AASHTO compaction method The COV determined in Table L14, was then compared to the COV of the Mod AASHTO compaction method. The COV of the Mod AASHTO was determined by taking G5 material and compacting 4 specimens at the same moisture content. This was done so as to determine the repeatability of the Mod AASHTO compaction method. The G5 material was not treated with cold mix bitumen, only water was added. The COV of the Mod AASHTO is shown below: • COVModAASHTO = 0.45% When this COV is compared to the vibratory hammer COV values, it is found that generally the vibratory hammer COV is less than the Mod AASHTO COV. This is however not the case when the vibratory hammer was used to compact material warmer than room temperature (250C). COV of the vibratory hammer: BSM-emulsion and BSM-foam 2.5 BSM-emulsion BSM-foam COV (%) 2 Poly. (BSM-foam) Poly. (BSM-emulsion) 1.5 1.12 1 0.63 0.5 0 0 5 10 15 20 25 30 35 40 Temperature (Degrees Celcius) Figure L.76: Projection of COV values of vibratory hammer at room temperature Figure L.76 shows that the COV of the vibratory hammer at room temperature is higher than the Mod AASHTO COV. The BMSemulsion produces a COV of 0.63 which is close to the Mod AASHTO COV of 0.45. The BSM-foam however produces a COV of 109 1.12. This is significantly higher than the Mod AASHTO COV although it is still statistically low. 110 4.8 CT Scanning CT scanning was used to determine the voids condition of the various compacted samples. The sections shown in this report are of the middle scans of each of the samples scanned. Sample 1: S1 Section 150mm Middle scan Top: S1B 75mm Middle scan Middle: S1A 75mm Emulsion Mix: BSM-emulsion: Vibratory Hammer Vibratory Hammer Figure L.77: CT scan S1B - Middle scan Figure L.78: CT scan S1A - Middle scan From Figure L.77 and figure L.78 it appears that the voids content in S1A are in fact higher than in S1B. 111 S1B 85 E 75 Scan slice nummer (boorkern lengte in mm). 65 55 45 35 25 15 S voids Mortar Stone 5 -5 0 20 40 60 80 100 Volume in % Figure L.79: CT scan S1B – Graphic Plot, BSM-emulsion, vibratory hammer compaction From Figure L.79 the voids condition and content may clearly be seen. The analysis of the figure is taken from the point marked “S” to the point marked “E” (this is done for each of the CT scan graphic plots). This is done as a result of the anomalies present at the top and bottom of the specimen, the reason for these anomalies is that the top and bottom sections of the sample are the sections that 112 were either cut or were the pieces that were the most frequently handled, this may lead to the loss of aggregate in the sample at these points (this was seen to happen on the surface of the section being cut). The figure for S1B shows that the voids content is quite consistent, with only a temporary increase near the top. The mortar (Emulsion) and stone configuration differ quite extensively. The figure shows that as the mortar content increases so the stone content decreases and the opposite is also true. Figure L.81 shows a different picture; here the voids increase quite consistently till the middle of the section and then decrease until the end. The reason for this high increase at the centre of S1A is that the centre of this section falls extremely close to the intersection of the last two layers of the original sample, therefore this voids condition may in fact give an indication of the voids condition of the scarified surface after compaction of the next layer, this reasons may also provide an explanation for the bulge in S1B, Figure L.80 shows graphically where the scarified surfaces sit relative to the section points of S1A and S1B (this diagram is also applicable to the BSM-foam results). When the dimensions provided in the diagram of Figure L.80 are projected onto the Figures L.79 and L.81, assuming that the scans were performed from the top end of the sample moving downwards, the bulge of S1B fits almost perfectly in place with the position of the scarified surface. The bulge of S1A is slightly out, but this may be attributed to some form of compaction variability, i.e. that the scarified surface of S1A was possibly scarified to extensively, leaving a larger area for compaction. 113 The visual of the difference in voids at the centre of S1A and S1B may be seen in Figures L.77 and L.78. S1A is the middle section of the specimen, so the fact that the voids show an increase as apposed to a drastic decrease, it may be concluded that no further compaction of sub layers takes place when compacting the top layers (in this case S1B). The same would be true should the voids content remain consistent throughout the sample length. When the mortar and stone content is S1A: 75mm 15mm 45mm S1B: 75mm 60mm viewed, the same trend is seen as is seen in figure L.81. 60mm* Scarified area 60mm 30mm 60mm Scarified area * The 60mm sections are the original layers of the sample when it was initially compacted Figure L.80: Graphical illustration of the scarified surface relative to the section points for the CT scanned samples 114 S1A 85 75 E Scan slice nummer (boorkern lengte in mm). 65 55 45 35 25 15 voids Mortar stone S 5 -5 0 20 40 60 80 100 Volume in % Figure L.81: CT scan S1A – Graphic Plot, BSM-emulsion, vibratory hammer compaction 115 Sample 2: S2 Section 150mm Middle scan Piece Sent: S2 ±60mm Emulsion Mix: Mod Mod Aashto BSM-emulsion: Compaction AASHTO Compaction Figure L.82: CT scan S2 - Middle scan The CT scan performed on the Mod AASHTO compacted sample (Figure L.83) showed a more consistent voids content. There is a slight increase in the voids near to the bottom of the sample but not really significant. The mortar and stone content show the trend again that as the mortar content increases so to does the stone content decrease. The increase decrease rate is not extensively high, so that there is a frequent cross over between the two plots, there is however only one point at which the two plots intersect. 116 s2 85 75 Scan slice nummer (boorkern lengte in mm). 65 E 55 45 35 25 15 S voids Mortar stone 5 -5 0 20 40 60 80 100 Volume in % Figure L83: CT scan S2 – Graphic Plot, BSM-emulsion, Mod AASHTO compaction 117 Sample 3: S3 Section 150mm Middle scan Top: S3B 75mm Middle scan Middle: S3A 75mm Foam Mix: Vibratory BSM-foam: Hammer Vibratory Hammer Figure L.84: CT scan - S3B Middle scan, BSMfoam Figure L.85: CT scan - S3A Middle scan, BSMfoam The BSM-foam was compacted close to refusal density, while the BSM-emulsion material was compacted to a target density of 100% Mod AASHTO. Figures L.84 and L.85 show that the top and middle section of the BSM-foam differ less extensively in their voids content than does the BSM-emulsion. 118 S3B 85 E75 Scan slice nummer (boorkern lengte in mm). 65 55 45 35 25 15 voids Mortar Stone S 5 -5 0 20 40 60 80 100 Volume in % Figure L.86: CT scan S3B – Graphic Plot, BSM-foam, vibratory hammer compaction Figure L84 shows that the voids content of sample S3B varies very little, it is in fact very consistent. In principle the trend of higher voids content at the points where scarification of the layers took place should be applicable for the BSM-foam, yet this trend (as was seen in 119 the BSM-emulsion) is not found in sample S3B and S3A. This is due to the fact that the BSM-foam was compacted for an excessively long period of time (3 minutes per layer) the scarified layer would have had more time to be compacted and allow the particles to orientate more thus reducing the voids at these points. The mortar and stone content of the BSM-foam is also more consistent than in the BSM-emulsion. Figure L.86 shows the same results as Figure L.87; the only difference is that the mortar and stone content of Figure L.86 is less consistent near the top of the sample than in Figure L.86. The voids content in both Figures L.86 and L.87 are consistently low, there is no excessive decrease in the voids at any one point, and this indicates that no further compaction of the subsequent layers takes place. This also indicates that no crushing of the aggregate takes place; this is because at a refusal state the only time that further compaction may transpire is when the aggregate begins to be crushed. 120 S3A 85 75 Scan slice nummer (boorkern lengte in mm). 65 55 45 35 25 15 voids Mortar Stone 5 -5 0 20 40 60 80 100 Volume in % Figure L.87: CT scan S3A – Graphic Plot, BSM-foam, vibratory hammer compaction 121 4.9 Experimentation on Untreated G2 Material Experimentation was carried out on untreated G2 material so as to determine what the compaction trend is when only moisture is added to the material. This could also provide a possible guide to develop an O.M.C. curve procedure for the vibratory hammer. Moisture Curve: Untreated G2 Material - Bosch GSH 11E® 10kg Surcharge 2360.00 Dry Density (kg/m3) 2340.00 2338.00 2320.00 2300.00 2280.00 2260.00 2240.00 2220.00 2.0 3.0 4.0 5.0 5.9 6.0 7.0 8.0 9.0 10.0 Moisture Content (%) Figure L.88: Dry Density vs. Moisture Content: Untreated G2 Material – Bosch GSH 11E ® The compaction curve show in figure L.88 indicates that the vibratory hammer compaction is quite sensitive to the moisture content. The climb to the peak at first sight is quite steep. The gradient of the incline is 77.42; this is high as it is very close to 100 (which in the case of this graph would be a vertical line). The decline after the peak moisture content has a gradient of -25, the negative merely indicates the direction of the line, where as the value of 25 shows that the gradient is less steep than the initial incline. This indicates that after the peak moisture content the compaction densities achieved are not as sensitive to the moisture content as the initial compaction densities. A possible reason for this is that as the moisture increases the effect of any pore pressure within the sample would increase, as the moisture content is already high the effect of pore pressures would become more prevalent, this would have an effect on compaction, possibly making the sample less sensitive to the compaction. This is because more of the compaction energy exerted by the hammer would be taken up by the moisture, transferring less compaction energy to the material. In the 122 case of the incline the moisture is acting more as lubricant, aiding in particle movement, rather than an energy absorber. Moisture Curve: Untreated G2 Material - Mod AASHTO vs. Vibratory Hammer Bosch GSH 11E® 10kg Surcharge 2350.00 2338.00 Dry Density (kg/m3) 2300.00 2260.00 2250.00 2200.00 2150.00 Mod AASHTO Vibratory Hammer 2100.00 0.0 1.0 2.0 3.0 5.9 6.15 4.0 5.0 6.0 7.0 Moisture Content (%) 8.0 9.0 Figure L.89: Dry Density vs. Moisture Content: Untreated G2 Material - Bosch ® Hammer Compaction vs. Mod AASHTO The above figure (Figure L.89) shows the comparison between the Mod AASHTO compacted, untreated G2 material and the Vibratory hammer compacted untreated G2 material. The first point that is evident is that the compaction densities achieved by the vibratory hammer are significantly higher than the Mod AASHTO densities for the same moisture content. Table L.15 shows the densities achieved at the various moisture contents; the densities are expressed as a percentage of the Mod AASHTO density. It is seen that compacting layer 1 for 10 seconds and the remaining four layers for 15 seconds each yields densities in excess of 100% Mod AASHTO density. 123 The difference in the moisture content at the peak of the two curves, the OMC value, is very small, only 0.25%. This indicates that for the procedure used that the OMC of the Mod AASHTO and the OMC of the vibratory hammer are very similar. The curve also shows that at lower moisture contents higher Dry Densities may be achieved. Table L.15: %Mod AASHTO Compaction Achieved Using the Vibratory Hammer – Untreated G2 Material Sample M.C %OMC Achieved Dry Density 3 (kg/m ) % Mod AASHTO 1 4.24 68.98 2238.01 102.38 2 5.07 82.51 2269.32 101.67 3 5.73 93.10 2336.3 103.56 4 6.26 101.83 2329.61 103.08 5 7.4 120.27 2302.56 102.79 The average density achieved is 102.7% Mod AASHTO 124 4.10 Repeatability Experimentation: G5 Material The purpose of the repeatability experimentation was to determine how well the vibratory hammer compaction procedure developed using a G2 quality material would perform using a different material; in this case a G5 granular material was chosen. 4.10.1 Mod AASHTO Compaction of G5 Material 4.10.1.1 Untreated G5 Material Moisture Curve: Untreated G5, Mod AASHTO 2240.00 OMC Mod AASHTO 2228.00 2220.00 Dry Density (kg/m3) 2200.00 2180.00 2160.00 2140.00 2120.00 2100.00 2080.00 2060.00 2.0 3.0 4.0 5.0 6.7 6.0 7.0 8.0 Moisture Content (%) 9.0 10.0 11.0 12.0 Figure L.90: Moisture Curve: Untreated G5 Material – Mod AASHTO Figure L.90 shows the Mod AASHTO moisture curve used to determine the OMC of the Untreated G5 material. The Max Dry Density was found to be 2228 kg/m3 with an OMC of 6.7%. 125 4.10.1.2 BSM-emulsion G5 Material Moisture Curve: BSM-emulsion G5 Material, Mod AASHTO 2240.00 OMC Mod AASHTO Dry Density (kg/m3) 2220.00 2217.00 2200.00 2180.00 2160.00 2140.00 2120.00 2100.00 2080.00 2060.00 3.0 4.0 5.0 6.0 6.8 7.0 8.0 9.0 10.0 11.0 Moisture Content (%) Figure L.91: Moisture Curve: BSM-emulsion G5 Material – Mod AASHTO Moisture Curve: Untreated G5 vs. BSM-emulsion G5 Material Mod AASHTO Dry Density (kg/m3) 2240.00 2228.00 2220.00 2217.00 2200.00 ∆OMC = 0.1% 2180.00 2160.00 2140.00 2120.00 2100.00 2080.00 2060.00 2.0 3.0 4.0 5.0 6.7 6.8 6.0 7.0 8.0 Moisture (%) Untreated G5 BSM-emulsion G5 9.0 10.0 11.0 12.0 Figure L.92: Moisture curve: Untreated G5 vs. BSM-emulsion G5 Material– Mod AASHTO 126 Figure L.91 shows the Mod AASHTO curve determined for the BSM-emulsion G5 material; this curve was plotted against the untreated G5 moisture curve and is shown in Figure L.92. The results of comparing the two curves shows that the OMC value of the BSM-emulsion was 0.1% higher than for the untreated G5 material. The max Dry Density of the untreated G5 material was however 11kg/m3 higher than for the BSM-emulsion G5 material. It is also seen from the result of comparing the two curves that the gradient of BSM-emulsion is steeper when compared to the untreated material. The same point may be noted, with regard to the gradient steepness of the two mixes, in the G2 material. This indicates that the compaction of the BSM-emulsion is more sensitive to moisture than the untreated material. 4.10.1.3 BSM-foam G5 Material Moisture Curve: BSM-foam G5 Material, Mod AASHTO 2160.00 OMC Mod AASHTO Dry Density (kg/m3) 2150.00 2149.50 2140.00 2130.00 2120.00 2110.00 2100.00 3.0 4.0 5.0 6.0 6.95 7.0 8.0 9.0 10.0 11.0 12.0 Moisture Content (%) Figure L.93: Moisture Curve: BSM-foam G5 Material – Mod AASHTO 127 Moisture Curve: Untreated G5 vs. BSM-foam G5 Material Mod AASHTO Dry Density (kg/m3) 2240.00 2228.00 2220.00 ∆ OMC = 0.25 Untreated G5 BSM-foam G5 2200.00 2180.00 2160.00 2149.50 2140.00 2120.00 2100.00 2080.00 2060.00 3.00 4.00 5.00 6.70 6.95 6.00 7.00 8.00 9.00 10.00 11.00 12.00 Moisture (%) Figure L.94: Moisture curve: Untreated G5 vs. BSM-foam G5 Material – Mod AASHTO The same comparison, as to what was done for the BSMemulsion, of the treated material to the untreated material was done for the BSM-foam. The OMC of the BSM-foam for the Mod AASHTO moisture curve was found to be 0.25% higher than for the OMC of the untreated G5 Mod AASHTO moisture curve (Figure L.94). The Maximum Dry Density of the BSM-foam was however 78.5kg/m3 less than the untreated material, and when looking at the gradients, the BSM-foam material has a slightly flatter incline compared to the untreated material, but the decline of the moisture curve is steeper in the case of the BSM-foam. This gradient indicates that the BSM-foam is less sensitive to moisture while moving up to the OMC point than the untreated material, but after reaching OMC the decrease in the Dry Density is more rapid and therefore more sensitive to the moisture in the case of the BSM-foam. 128 4.10.2 Vibratory Hammer Compaction of G5 Material 4.10.2.1 Untreated G5 Material Moisture Curve: Untreated G5 Bosch GSH 11E® 10kg Surcharge 2250.00 Dry Density (kg/m3) 2240.00 2236.00 2230.00 2220.00 2210.00 2200.00 2190.00 2180.00 2170.00 2160.00 2150.00 3.0 4.0 6.0 6.0 5.0 7.0 8.0 9.0 10.0 Moisture Content (%) Figure L.95: Moisture curve: Untreated G5 Vibratory Hammer – Bosch GSH 11E® Moisture Curve Mod AASHTO vs. Vibratory Hammer Bosch GSH 11E® 10kg Surcharge: Untreated G5 Material 2260.00 Dry Density (kg/m3) 2240.00 2236.00 2228.00 2220.00 2200.00 2180.00 2160.00 2140.00 2120.00 2100.00 OMC Mod AASHTO OMC Vibratory Hammer 2080.00 2060.00 2.0 4.0 6.0 6.0 6.7 8.0 10.0 12.0 Moisture Content (%) Figure L.96: Moisture Curve: Mod AASHTO Compaction vs. Vibratory Hammer Compaction – Untreated G5 Material 129 Table L.16: %Mod AASHTO Compaction Achieved: Mod AASHTO vs. Vibratory Hammer – Untreated G5 Material Sample M.C %OMC Achieved Dry Density 3 % Mod (kg/m ) AASHTO 1 5.30 79.06 2161.00 100.05 2 5.91 88.26 2238.45 102.12 3 6.69 99.87 2234.07 100.27 4 8.09 120.69 2228.15 100.64 The average achieved Dry Density = 100.77% Mod AASHTO The vibratory hammer compaction of the untreated G5 material was done using the same procedure developed for the BSM-emulsion. This was decided based on the fact that the emulsion is believed to act as a lubricant during the compaction of BSM-emulsion, and in the case of untreated material there is only lubrication being added to the material in the form of water. Therefore layer one was compacted for 10 seconds and the remaining 4 layer were each compacted for 15 seconds. The results of the experiment are presented graphically in Figures L.94 and L.95. It is seen from these results that the vibratory hammer compaction is more sensitive to moisture on the incline as apposed to the Mod AASHTO compaction. The decline shows a drop in moisture sensitivity for the vibratory hammer, the Mod AASHTO compaction however shows a higher level of sensitivity to the moisture content after OMC than does the vibratory hammer. Across the various moisture contents the Dry Densities achieved were consistently around 100% Mod AASHTO (averaging 100.77%). On site the accepted level of compaction of a G5 material is 95 percent Mod AASHTO, considering that across the various moisture contents an average Mod AASHTO Dry Density of 100.77% is being achieved with the vibratory hammer, it shows that the densities achieved with the procedure are acceptable with respect to accepted levels of site compaction for the G5 material. In the case of the G2 material the Dry Densities were on average around 103% Mod AASHTO. The peak moisture content of the untreated 130 G5 material using the procedure was found to be 6% which indicates that the OMC of the vibratory hammer may in fact be lower than that of the Mod AASHTO compaction (which in this case is 6.7%). The OMC results indicate that at a lower OMC for a given material (in this case a G5 material) the vibratory hammer compaction can produce Dry Densities similar to or higher that the Mod AASHTO Dry Densities. The result of the achieved Dry Densities of the G5 material indicates that the procedure is useable on lesser quality granular materials such as G5 material. 131 4.10.2.2 BSM-emulsion G5 Material Moisture Curve: BSM-emulsion G5 Material, Bosch GSH 11E® 10kg Surcharge 2220.00 OMC Vibratory Hammer Dry Density (kg/m3) 2202.00 2200.00 2180.00 2160.00 2140.00 2120.00 2100.00 4.0 5.0 7.0 7.0 6.0 8.0 9.0 10.0 11.0 12.0 Moisture Content (%) Figure L.97: Moisture curve: BSM-emulsion G5 Material, Vibratory Hammer – Bosch GSH 11E® Moisture Curve Mod AASHTO vs. Vibratory Hammer Bosch GSH 11E® 10kg Surcharge: BSM-emulsion G5 Material 2240.00 OMC Vibratory Hammer OMC Mod AASHTO Dry Density (kg/m3) 2220.00 2217.00 2202.00 2200.00 2180.00 2160.00 2140.00 2120.00 2100.00 2080.00 2060.00 4.0 5.0 6.0 6.8 6.95 7.0 8.0 9.0 10.0 11.0 12.0 Moisture Content (%) Figure L.98: Moisture curve: BSM-emulsion G5 Material, Mod AASHTO vs. Vibratory Hammer – Bosch GSH 11E® 132 Table L.17: %Mod AASHTO Compaction Achieved Using the Vibratory Hammer – BSM-emulsion G5 Material Sample M.C %OMC Achieved Dry Density (kg/m3) % Mod AASHTO 1 4.91 75.56 2106.52 101.47 2 5.53 85.06 2167.29 102.13 3 6.42 98.77 2186.11 99.82 4 7.01 107.83 2201.12 99.69 5 7.41 114.04 2197.18 101.07 Average Achieved Dry Density = 100.84% Mod AASHTO G5 material was treated using Bitumen Emulsion and the Dry Density vs. Moisture content curve was developed for this mix using the vibratory hammer. For this compaction the same procedure developed for the BSM-emulsion for the G2 material was applied; figures L.96 and L.97 show the results of the experiment. The experiment shows that at the peak moisture content the Dry Density achieved with the vibratory hammer is less than the Mod AASHTO Dry Density. The peak moisture content i.e. the OMC of both the vibratory hammer and of the Mod AASHTO is very similar, only differing by 0.15%. The criterion for the accepted level of compaction on site is however still met, site compaction being accepted at 95% Mod AASHTO and the vibratory hammer achieved a compaction level of 99.82% Mod AASHTO at its OMC. It should be noted that from Figure L.99 it is seen that there is a moisture content bracket where the Dry Density achieved using the vibratory hammer does not reach 100% Mod AASHTO (it reached between 99.5% and 100%) but outside of the bracket Dry Densities exceeding 100% Mod AASHTO are achieved. The BSM-emulsion experiment also showed that the G5 material was less sensitive to moisture overall when compacting using the vibratory hammer as apposed to the 133 Mod AASHTO; this is shown by virtue that the vibratory hammer curve is quite flat when compared to the Mod AASHTO cure (figure L.97). Comparing the result of the G5 BSM-emulsion to the G2 BSM-emulsion (sub section 4.5.1) a potential trend may be noted, i.e. that as the material quality decreases (e.g. from a G2 to a G5 material) so to does the extent with which 100% Mod AASHTO compaction is exceeded using the vibratory hammer. This indicates that the material quality influences the level of compaction. The repeatability experiment for the BSM-emulsion shows that the procedure is applicable to and can produce acceptable result across material quality which varies as far as from G2 to G5. 134 4.10.2.3 BSM-foam, G5 Material Moisture Curve: BSM-foam G5 Material, Bosch GSH 11E® 10kg Surcharge 2170.00 OMC Vibratory Hammer Dry Density (kg/m3) 2160.00 2160.00 2150.00 2140.00 2130.00 2120.00 2110.00 2100.00 3.0 4.0 5.0 6.0 6.85 7.0 8.0 9.0 10.0 Moisture Content (%) Figure L.99: Moisture curve: BSM-foam Vibratory Hammer – Bosch GSH 11E® Moisture Curve Mod AASHTO vs. Vibratory Hammer Bosch GSH 11E® 10kg Surcharge: BSM-foam G5 Material 2170.00 OMC Vibratory Hammer OMC Mod AASHTO Dry Density (kg/m3) 2160.00 2150.00 2149.50 2140.00 2130.00 2120.00 2110.00 2100.00 3.0 4.0 5.0 6.0 6.85 6.95 7.0 8.0 9.0 10.0 11.0 Moisture Content (%) Figure L.100: Moisture curve: BSM-foam G5 Material, Mod AASHTO vs. Vibratory Hammer – Bosch GSH 11E® 135 Table L.18: %Mod AASHTO Compaction Achieved Using the Vibratory Hammer – BSM-foam Treated G5 Material Sample M.C %OMC Achieved Dry Density (kg/m3) % Mod AASHTO 1 4.93 73.59 2133.19 102.66 2 6.26 93.40 2151.56 101.15 3 7.07 105.52 2158.96 100.46 4 7.94 118.54 2151.34 101.62 Average Achieved Dry Density = 101.47% Mod AASHTO The final repeatability experiment was setting up the moisture content vs. Dry Density curve for G5 material that had been treated using Foamed bitumen. The results of the experiment are presented in figures L.98 and L.99 as well as in table L.15. The experiment procedure used was similar to the procedure developed for the G2 BSM-foam. Compaction was done using the compaction times assigned to perform the moisture content vs. Dry Density curve of the G2 BSMfoam, these times are as follows: Layer 1 = 10 seconds Layer 2 = 25 seconds Layer 3 = 25 seconds Layer 4 = 34 seconds Layer 5 = 25 seconds The results of the BSM-foam showed, similar to the BSMemulsion results, that the compaction density achieved using the vibratory hammer is less sensitive to moisture than what the Mod AASHTO compaction is; this is evident by the lower incline and decline in the moisture content vs. Dry Density curve of the vibratory hammer compaction. The Dry Densities achieved averaged out at 101.47% Mod AASHTO with all moisture contents exceeding the 100% Mod AASHTO mark. This result is good in that it indicates that the compaction procedure is capable of producing Dry Densities well above the accepted level of site compaction; 136 95% Mod AASHTO for G5 material. The procedure may therefore be used for lesser quality granular materials, which have been treated using Foamed mix bitumen, to produce samples so as to give an indication of the level of compaction achievable on site. In the Moisture vs. Dry Density curve of the BSM-foam G5 material, the sample treated for 80% OMC was ignored when setting up the graph. When this ample was compacted the point at which it fell on the graph was outside of the other four (4) points. The grading curve in Figure L.101 was constructed (dry grading) and the possible explanation for this outlier is show in the en-circled area. The 80% OMC sample and the 100% OMC sample were both broken up after compaction and allowed to dry out completely prior to doing the grading curve. The 100% OMC was chosen as it lay on the plotted curve. Because the remaining four samples all fell on the plotted curve it may be assumed (considering that they are reconstituted samples) that their grading is virtually the same. The encircled section of figure L.101 shows a discrepancy in the grading. When this was evaluated and the results converted to mass of material it was found that the 80% OMC sample had ±1100gm of material for the sieve fractions 13.2mm to 2mm more than the 100% OMC sample. Looking at the fines, it was found that the 100% OMC sample had ±500gm for the sieve fractions 0.0425mm to 0.075mm more than the 80% OMC sample. 137 Grading Curve: Foamed Mix G5 Material - 80% OMC vs. 100% OMC 120.0 80% OMC 100% OMC 100.0 % Passing 80.0 60.0 40.0 20.0 0.0 0.01 0.1 1 10 100 Sieve Size (mm) Figure L.101: Grading curve: BSM-foam G5 Material – 80% OMC vs. 100% OMC The difference in the material grading of the two samples may be attributed to the segregation of the 80% OMC sample during the weighing off of the various layers. For the 100% OMC sample the moisture content and weighing off of the various layers made use of almost all of the material, after which there was in the order of 600gm material left over where with the 80% OMC there was well in excess of 1000gm of material left over after weighing off of separate layers and moisture content samples being taken, this large excess indicates that there is larger room for segregation of the sample than for the 80% OMC sample. 138 4.10.3 Grading of G5 material Before and After Compaction Grading Curve of G5 Material: Grading Prior to Compaction vs. Grading After Compaction 90.0 80.0 Grading Prior to Compaction Grading After Compaction 70.0 % Passing 60.0 50.0 40.0 30.0 20.0 10.0 0.0 0.01 0.1 1 Sieve Size (mm) 10 100 Figure L.102: G5 Material Grading Curve – Before and After Compaction The grading curve provided in figure L.102 was developed using the dry grading method on untreated G5 material. The grading curves of the material indicate that after compaction the overall grading of the sample is different. The result does not appear to be as a result of crushing, this is because there is not a distinctive increase in the finer material. The reason may rather be due the segregation that occurs during the weighing off process, or it could be due to the loss of fine material through the seepage of material between the walls of the mould and the foot piece of the vibratory hammer when samples are compacted at higher moisture levels. 139 4.11 Zero Air Voids of the Curves The Zero air voids curve was plotted against the moisture sensitivity curve of the various mixes. This was done so as to establish were the compaction curves lie with respect to the absolute maximum Dry Density, indicated by the zero air voids curve. To set up these curves the specific gravity (Gs) of both the G2 and G5 material was determined in both the untreated and BSM states; the Gs of the bitumen was taken as 1.00 and for both the BSM-emulsion and BSM-foam the binder content was taken as 1.98%. The Gs values of the fine material were determined using the TMH 1 method in the case of the G5 material. In the case of the coarse material i.e. the large stones, the same method was used as was used for the G2 material. A few of the largest stones (± 19mm) were taken and the individual density of each one was determined, these were averaged out and used as the representative density of the parent rock from which the Gs value may be obtained; dividing this density with the density of water in the case of the G2 material; for the G5 material the relative density (RD) of the fine material was summed with the representative density of the parent rock and divided by two, this gave the density from which the Gs value was determined. The Gs values determined were as follows: • Gs of the Untreated G2 = 2.873 • Gs of BSM G2 = 2.836 • Gs of the Untreated G5 = 2.788 • Gs of BSM G5 = 2.733 Figures L.103 to L.108 show the relationship of the moisture curve to the zero air voids line. 140 4.11.1 Zero air voids vs. Moisture curve of the G2 material Dry Density (kg/m3) Zero Air Voids Line vs. Moisture Curve of Mod AASHTO and Bosch GSH 11E®: Untreated G2 Material 2400.00 2350.00 2300.00 2250.00 2200.00 2150.00 2100.00 2050.00 Vibratory hammer Mod AASHTO Zero Air Voids 0.0 2.0 4.0 6.0 8.0 10.0 12.0 Moisture Content (%) Figure L.103: Zero air voids line vs. Moisture curve – Untreated G2 Material Dry Density (kg/m3) Zero Air Voids Line vs. Moisture Curve of Mod AASHTO and Bosch GSH 11E®: BSM-emulsion G2 Material 2350.00 2300.00 2250.00 2200.00 2150.00 2100.00 2050.00 2000.00 Vibratory hammer Mod AASHTO Zero Air Voids 0.0 2.0 4.0 6.0 8.0 10.0 12.0 Moisture Content (%) Figure L.104: Zero air voids line vs. Moisture curve – BSM-emulsion G2 Material 141 Dry Density (kg/m3) Zero Air Voids Line vs. Moisture Curve of Mod AASHTO and Bosch GSH 11E®: BSM-foam G2 Material 2350.00 2300.00 2250.00 2200.00 2150.00 2100.00 2050.00 2000.00 Vibratory hammer Mod AASHTO Zero Air Voids 0.0 2.0 4.0 6.0 8.0 Moisture Content (%) 10.0 12.0 Figure L.105: Zero air voids line vs. Moisture curve - BSM-foam G2 Material The zero air voids curve plotted for the G2 material show that the untreated material finishes closer to the zero air voids line than dos the BSMs. The expected result of higher compaction energy is seen in the curves as the vibratory hammer curve shifts upward slightly to the left, moving closer to the zero air voids line, with the exception of the BSM-emulsion plot (figure L.104) which shifts to the right however the movement is closer to the zero air voids line. In view of these results, the vibratory hammer produces samples with lower air voids than does the Mod AASHTO compaction method. 142 4.11.2 Zero air voids vs. Moisture curve of the G5 material Dry Density (kg/m 3) Zero Air Voids Line vs. Moisture Curve of Mod AASHTO and Bosch GSH 11E®: Untreated G5 Material 2400.00 Vibratory hammer Mod AASHTO Zero Air Voids 2350.00 2300.00 2250.00 2200.00 2150.00 2100.00 2050.00 2000.00 1950.00 0.0 2.0 4.0 6.0 8.0 10.0 12.0 Moisture Content (%) Figure L.106: Zero air voids line vs. Moisture curve – Untreated G5 Material Zero Air Voids Line vs. Moisture Curve of Mod AASHTO and Bosch GSH 11E®: BSM-emulsion G5 Material 2350.00 Vibratory hammer Mod AASHTO Zero Air Voids Dry Density (kg/m3) 2300.00 2250.00 2200.00 2150.00 2100.00 2050.00 0.0 2.0 4.0 6.0 8.0 10.0 12.0 Moisture Content (%) Figure L.107: Zero air voids line vs. Moisture curve – BSM-emulsion G5 Material 143 Zero Air Voids Line vs. Moisture Curve of Mod AASHTO and Bosch GSH 11E®: BSM-foam G5 Material 2350.00 Vibratory hammer Mod AASHTO Zero Air Voids Dry Density (kg/m3) 2300.00 2250.00 2200.00 2150.00 2100.00 2050.00 0.0 2.0 4.0 6.0 8.0 Moisture Content (%) 10.0 12.0 Figure L.108: Zero air voids line vs. Moisture curve – BSM-foam G5 Material The results seen in the G2 material are evident in the G5 material results. The G5 material showed more consistent results in terms of how close to the zero air voids line the compacted samples finished. The moisture curve of the untreated material did not finish excessively closer to the zero air voids line than did the BSMs; on the contrary when the position of the MDD of the vibratory hammer of the G5 is viewed relative to the zero air voids line then it is seen that the BSM-emulsion curve (figure L.107) is closer to the zero air voids line. As with the G5 material the expected trend of the moisture curve moving upward slightly to the left for higher compaction energy is seen; however for the G5 material the BSMemulsion conforms to this trend. In view of these curves the vibratory again shows that it produces samples with lower air voids than does the Mod AASHTO compaction method. 144 4.11.3 Zero air voids curve compared to CT scanning results The comparison of the CT scanning results could only be done for the BSM-emulsion of the G2 material as there was both a Mod AASHTO compacted sample and a vibratory hammer compacted sample of the material. The voids of Figure L.79 were used for the vibratory hammer and an area on the sample where the voids were at a minimum was chosen, therefore the voids from slice 20 to slice 54 were average out and used as this gave a comparable result, (the scarification of the layer surface had not been identified prior to the CT scanning, therefore the voids of Figure L.81 were not used for this comparison). The voids of figure L.83 were used for the Mod AASHTO compaction and the section of the sample where the voids were at a minimum was chosen and the voids across that section were averaged out; slice 8 to slice 62. The voids results are as follows: • CT scanning = 0.68% voids • Mod AASHTO = 0.77% voids These results show that the vibratory hammer produced lower air voids content than did the Mod AASHTO, this confirms the results of the zero air voids line, which showed that the vibratory hammer produced samples with a lower air voids content. 145 4.12 Compaction Energy of the Compaction Methods 4.12.1 Bosch GSH 11E® The compaction energy exerted by the Bosch® vibratory hammer over the BSM-emulsion and BSM-foam samples as well as the untreated granular material was determined after completion of the compaction experiments. This energy was then compared to the compaction energy of the New Zealand vibrating hammer compaction method and to the energy of the ASTM vibrating hammer compaction method (see table L.Lit 3 and L.Lit 4 of the literature study section of this appendix). The New Zealand and ASTM compaction methods compact in two and three layers respectively to produce samples of a height similar to the Mod AASHTO compaction method. Therefore to compare the energies the new Zealand and ASTM methods were evaluated over five layers; this allowed both methods to be compared to the procedure developed by the University of Stellenbosch (US). The calculation of the energy of each hammer was done as follows. n=5 • Total Energy = Σ x=1 ( Point Energy × (beats/min) × compaction time of Layer x ÷ 60seconds) • Average energy per Layer = Total Energy ÷ No. of Layers The energy of the Bosch® hammer for the BSM-emulsion was determined for two time scenarios: 1. Times assigned to the layers based on the experiment results. 2. Doubling the compaction times assigned to the layers based on the experiment results. The energies are assigned a lower limit and an upper limit. This is the range in which the energies fall based on the minimum and maximum beats per minutes of the specific vibratory hammer. The point energy of the respective compaction methods are provided below and the comparative results then follow. • New Zealand = 7 Joules: 1500-3600 beats/min 146 • ASTM = 10 Joules (Bosch 11248 EVS ®): 1700-3300 beats/min • US = 25 Joules (Bosch GSH 11E ®): 900-1890 beats/min Compaction Energy over the BSM-emulsion samples: Times initially assigned to each layer Table L.19: Comparison of Total Energy of Vibratory Hammers BSMemulsion Vibratory Hammer New Zealand ASTM: Bosch 11248EVS® US: Bosch GSH 11E® Lower Limit (kJ) 157.5 Upper Limit (kJ) 378 85 165 26.25 55.13 Table L.20: Comparison of Average Energy/Layer of Vibratory Hammers BSM-emulsion Vibratory Hammer New Zealand ASTM: Bosch 11248EVS® US: Bosch GSH 11E® Lower Limit (kJ) 31.5 Upper Limit (kJ) 75.6 17 33 5.25 11.025 The New Zealand and ASTM compaction methods make use of fixed times per layer of 180 seconds and 60 seconds respectively. The comparisons presented above assume that there compaction methods are used as is to compact BSM samples. The untreated material at Stellenbosch University was compacted using the procedure developed for the BSM-emulsion samples. The compaction times for the US procedure are as follows • Layer 1 = 10seconds • Layer 2 through to Layer 5 = 15 seconds each Based on the given point energies the trend that is seen is that a higher point energy yields a less total energy required to compact a sample. This trend was noted in the literature study of this appendix and the compaction procedure developed by the University of Stellenbosch confirms this point as the Bosch GSH 11E® has the highest point energy (25 Joules) but uses the least total energy and least average energy per layer to compact the untreated and BSM-emulsion samples. 147 Compaction Energy over the BSM-emulsion samples: Times initially assigned to each layer Doubled Table L.21: Comparison of Total Energy – Compaction time per layer doubled BSM-emulsion Vibratory Hammer New Zealand ASTM: Bosch 11248EVS® US: Bosch GSH 11E® Lower Limit (kJ) 157.5 Upper Limit (kJ) 378 85 165 52.5 110.25 Table L.22: Comparison of Average Energy/Layer – Compaction time per layer doubled BSM-emulsion Vibratory Hammer New Zealand ASTM: Bosch 11248EVS® US: Bosch GSH 11E® Lower Limit (kJ) 31.5 Upper Limit (kJ) 75.6 17 10.5 33 22.05 The trend seen in the energies prior to doubling the compaction times for the US procedure are still seen after doubling the compaction times. It is expected that doubling the compaction times of the US procedure will produce samples with a much higher final Dry Density which will also be further above the upper limit of the accepted level of compaction specified for site. 148 Compaction Energy over the BSM-foam samples: Times initially assigned to each layer Table L.23: Comparison of Total Energy of Vibratory Hammers BSMfoam Vibratory Hammer New Zealand ASTM: Bosch 11248EVS® US: Bosch GSH 11E® Lower Limit (kJ) 157.5 Upper Limit (kJ) 378 85 165 44.63 93.71 Table L.24: Comparison of Average Energy/Layer of Vibratory Hammers BSM-foam Vibratory Hammer New Zealand ASTM: Bosch 11248EVS® US: Bosch GSH 11E® Lower Limit (kJ) 31.5 Upper Limit (kJ) 75.6 17 8.93 33 18.74 The BSM-foam samples show the same trend as the BSM-emulsion samples in both the total energy required to compact a sample and the average compaction energy per layer. There was no need to double the compaction energies for the BSM-foam samples as the samples produced from this procedure have final Dry Densities that are well exceed the accepted level of compaction on site. 149 4.12.2 Mod AASHTO Compaction The compaction energy of the Mod AASHTO compaction method was determined from the formula: • Compaction Energy (CE) = (No. of blows/layer) x (No. of layers) x (weight of hammer) x (drop height of hammer) In order to compare the overall energy of the Mod AASHTO method to the vibratory hammer method the number of layer was taken as 5, the number of blows per layer was taken as 55, the drop height was taken as 0.4572m and the weight of the hammer was 4.536kg x g (gravitational acceleration = 9.81m.s-2). The compaction energy is provided below: • CE/Layer = 1.865 kJ • CE Total = 5.595 kJ This results, when compare to the Bosch GSH 11E® compaction energy, is much lower than the vibratory hammer compaction energy. The Bosch® hammer at the University of Stellenbosch exerted a CE/Layer of 11.025kJ for the BSM-emulsion and 18.74kJ for the BSM-foam. The vibratory hammer exerted energy per layer greater than the total energy of the Mod AASHTO compaction method. The total energy of the vibratory hammer of 55.13KJ and 93.71KJ for BSM-emulsion and BSM-foam respectively are vastly greater that the total energy of 5.595KJ for the Mod AASHTO compaction method. 150 4.13 Development of Material Tools During the experiment process spot measurements were made of the layer thickness just prior to compaction, i.e. directly after the material for the respective layer had been added and the hammer had be lowered into position, measurements were taken as to determine the starting thickness of the layer. These measurements were taken by measuring the distance from the lower end of the sleeve to either the zero line, in the case of layer one, or to the final position of the previously compacted layer; the measurements showed a starting height of around 92mm in the case of the G5 material. These measurements were used to design a scoop. This was done by determining the volume of the material prior to compaction and then developing a scoop with either the same volume as the starting volume of an individual layer or with a fraction of the starting layer of ½ or 1/3 of the volume. This was done so that as apposed to weighing of the mass of material per layer a scoop could be used to place material into the mould that would provide a similar mass as to what would have been weighed off. The result was a scoop with a volume of 1/3 the starting volume of a layer. The dimensions are a diameter of 90mm and a height of 85mm. This design allows for three scoops of aggregate to be added into the mould that will provide a starting height of ±92mm. 151 4.14 Development of Specifications for Site Compaction The vibratory hammer compaction method is to be used to provide specifications for compaction levels on site. In order to develop the specifications the vibratory hammer results were equated to the current specifications. This was done as follows: Current specification (%Mod AASHTO) Material Type G2 100-102% G5 95% The average level of compaction achieved during the sensitivity analysis of the vibratory hammer was determined for each of the individual BSMs. The standard deviation for each BSM was also calculated. The Design Value i.e. the level of compaction from which the specifications will be developed was calculated using the following formula: DesignValue = X − zS Previously Ф was taken as 15% (Subsection 4.7.1) therefore z = 1.033 X is the average level of compaction of the vibratory hammer as a % of Mod AASHTO z is the dimensionless factor S is the standard deviation The results of this calculation were as follows: Table L25: Design values for site compaction specifications of G2 material BSM Average compaction level Standard Design Value (% Mod AASHTO)* Deviation (85% reliability) Untreated 102.70 0.72 101.96 Emulsion 102.86 1.42 101.40 Foam 105.47 1.36 104.06 *After vibratory hammer compaction 152 Table L26: Design values for site compaction specifications of G5 material BSM Average compaction level (% Standard Design Value Mod AASHTO)* Deviation (85% reliability) Untreated 100.77 0.91 99.58 Emulsion 100.84 1.06 99.74 Foam 101.48 0.92 100.52 *After vibratory hammer compaction The current accepted level of compaction is then divided by the Design Value to obtain the level of compaction for the vibratory hammer. This level of compaction for the vibratory hammer is equivalent to the current specifications. The specifications determined in this report do need to be revisited as site compaction data becomes available. The final specifications are as follows: Table L27: Site compaction specifications for G2 material BSM Site Specification (% vibratory hammer compaction) Untreated 98.6 - 100 Emulsion 98.6 - 100 Foam 96.1 - 98 The G5 material produced Design Values all in the order of 100% Mod AASHTO for vibratory hammer compaction. Therefore the fraction of Mod AASHTO compaction specified for the level of site compaction is to be used. An example of this is as follows: for a G5 material the current specification for site compaction is 95% of Mod AASHTO compaction. Therefore according to the previous statement the accepted level of site compaction is as specified below. Table L28: Site compaction specifications for G5 material BSM Site Specification (% vibratory hammer compaction) Untreated 95 Emulsion 95 Foam 95 153 4.15 Outline of Proposed Protocol From the results a potential compaction protocol may be identified. The protocol is for the production of samples that will give an indication of what Dry Densities may be obtained in the field i.e. using the vibratory hammer compaction as a means to indicate what densities are possible on site by means of a sensitivity analysis. A full, detailed description of the compaction protocol is provided in the recommendations section of this appendix. A brief outline is described below. Protocol: Sample production as an indication of achievable compaction levels For the compaction protocol the following information is needed: 1. Mod AASHTO moisture content curve 2. OMC (Mod-U) 3. Target Binder content if material is to be stabilized 4. Type of cold mix treatment i.e. bitumen emulsion mix or foamed bitumen mix The following tools and temperature information is also needed 5. Bosch GSH 11E® with a surcharge of 10kg 6. Compaction is done at room temperature 7. Drill with a drill bit longer than or equal to 300mm with a point marked off 10mm from the tip of the drill bit. 8. Extension piece for the mould so as to compact layer 5 9. Material scoop. A Moisture curve for the untreated material ifs first developed, from this moisture curve the OMC of the untreated material is known and this OMC is used to develop a moisture curve for either the BSM-emulsion or the BSM-foam; which ever stabilizing method is to be used. These graphs are the reference graphs for the target Dry Densities. Compaction using the vibratory hammer is done at various moisture contents ranging from 2% moisture to 10 or 12% moisture; this depends on the type of aggregate used. 154 The amount of moisture added to the material will depend on the type of cold mix treatment. For the BSM-foam moisture is added to the samples till the sample is reached which has a ratio of the water added to OMC of the untreated material of 0.8 (80%). At this point the remaining samples receive the same amount of water as the sample with a ratio of water added to OMC of the untreated material of 0.8. The material is then treated using the foamed bitumen and the remaining moisture required to achieve the targeted moisture content of each of the samples is added. The BSM-emulsion samples must first have the moisture in the emulsion calculated out of the targeted moisture content, the moisture is then added followed by the bitumen emulsion. The material is prepared; either BSM-emulsion or BSM-foam. The sample is then compacted in 5 layers in a mould 300mm high with a diameter of 150mm. Material is placed In the mould using a material scoop. Each individual layer receives three scoops of material for the respective mix, this is placed in the mould using a scoop with dimensions of 90mm diameter and height of 85mm and the sample is compacted. Each layer is compacted for a set period of time until all five layers have been compacted. Times for the respective layers are provided in the recommendations section of the appendix. After a layer has been compacted, that layer surface is then scarified using the drill. Three scoops of material are then added using the material scoop and the layer is compacted, this process continues until all five layers have been compacted. The sample is removed and the final height and final mass of the sample are taken. A moisture content of the remaining material is also taken using the standard oven drying method and the Dry Density is then determined. The Dry Density for each of the samples is at their respective moisture contents is determined. These are then used to plot the moisture curve of moisture Content vs. Dry Density of the vibratory hammer. This curve is then compared to the Mod AASHTO moisture curve set up for the respective BSM. The comparison is expressed as a percentage of the Mod AASHTO Dry Density. The results show that the Dry Densities achieved are above the recommended levels of compaction for G2 and G5 materials. This shows that the vibratory hammer may be used to specify the level of site compaction. Based on the results of this research the level of compaction should be taken as 100% of the Maximum Dry Density achieved using the vibratory hammer for the G2 material. In the case of the G5 material the Maximum Dry Densities of the vibratory hammer 155 compaction was found to be extremely near to the Maximum Dry Densities of the Mod AASHTO compaction, therefore the specification of 95% Mod AASHTO compaction currently used to specify the level of compaction on site should be applied to the vibratory hammer to specify the level of site compaction; i.e. site compaction should be equal to or larger than 95% vibratory hammer compaction. 156 5 CONCLUSIONS Based on the results of the experiments the following conclusions were drawn. 5.1 Influence of Time on Compaction with Varying Moisture Content of G2 Material The experiments showed that as the moisture content increased the compaction time to 100% Mod AASHTO compaction decreased. What was also seen is that once the moisture content was at 90% OMC for the BSM-emulsion the compaction time reduced so far that it may be assumed that sufficient time is not provided for the particles to become properly orientated within the specimen during compaction at this moisture content and hence the representation of the prepared sample to the compaction of the material on site may not be adequate. At 80% OMC in both the BSM-foam and BSM-emulsion mixes the compaction time to reach 100% Mod AASHTO was sufficient to allow for proper orientation of the material particles, but also short enough that the preparation of the sample does not necessarily become a very time consuming procedure. The influence of the surcharge weight is also evident in the results of the experiments. The 20kg load at 80% OMC showed a compaction time effect similar to that of the 10kg load at 90% OMC. The Kango 637® however suffered damages to the gear box at a 20kg surcharge load and this damage is believed to be as a result of this load. Based on the short time the 20kg load gives and the fact that the Kango 637® suffered damages at this load the 10kg load became the safest and best option. The 15kg surcharge showed compaction times in between the 10kg and 20kg surcharge mass, it could therefore be considered as an option for the surcharge weight used during compaction, however these results are all based on the Kango 637® results and when the correlation experiment between the Kango and Bosch hammer is taken into account, the 10kg surcharge proves to be the best option. In terms of the refusal density, it was generally seen that throughout the compaction of the emulsion mixes the time required to achieve refusal density was between 2 and 5 minutes of compaction time depending on the layer being compacted. The effect of moisture on this seems minimal, as there are cases where at 80% OMC it took roughly 3.5 minutes to reach refusal density and then at 90% OMC the layers all fall into a bracket of between 3.5 and 4 minutes. The surcharges also had little effect, with the layers across the various samples, again taking 3.5, 4 minutes to reach refusal density. What is clear is that the achieved refusal densities are influenced by the moisture content and surcharge load. The higher the moisture content, the higher the bracket of the refusal density and the higher the surcharge load in combination with the moisture content the higher the bracket in which the refusal density falls. 157 The foam mixes exhibited a similar trait to that of the emulsion mixes with regard to the refusal density compaction. Once again as the moisture content increased so to does the bracket in which the refusal density falls, and with the surcharge mass, the same trend was seen. A difference was seen in the compaction of the foamed mix to refusal density, the density of this mix continued to climb after 5 minutes of compaction. This results shows that the foamed mix requires longer compaction time to reach refusal density than does the emulsion mix. 5.2 Comparison of Vibratory Hammer to Vibratory Table The conclusion from this correlation experiment is that the vibratory hammer is a faster procedure with less physical labour required (if no pulley system is available for the vibratory table). Also the vibratory hammer gives more control and accuracy over both the target densities and the final level of the surface of the sample (a more perpendicular surface face is achieved with the vibratory hammer). 5.3 Correlation of N7 Material to G2 Material Parameters used for the compaction of the clean G2 material i.e. time per layer etc. were not applicable to the N7 G2 material. This is because, although the N7 material is a G2 quality, the milling process of the recycling process changes the grading and quality of the material from its original state when initially used in construction. The presence of RAP in the N7 material is believed to have had an influence on the compaction of the material. More time is required to reach the targeted site densities for the N7 material than for the clean bitumen treated G2 material to reach its 100% Mod AASHTO dry density. Simply because it takes 30 seconds to compact the G2 material to its 100% Mod AASHTO does not mean it will take the same time to compact the N7 material to its 100% Mod AASHTO density or the targeted site density. The material properties, i.e. grading and the presence of other elements such as RAP or cement from the initial construction influence the compaction time. The correlation experiment shows an important conclusion. Time cannot be taken as a fixed unit. Material properties influence the compaction time, therefore compaction using the vibratory hammer to produce site related samples should be performed as a function of the layer thickness and not as a function of time. 158 5.4 CT Scanning From the CT scanning results the first conclusion that can be drawn is that the vibratory hammer produces samples with very low voids contents. The extent to which the surface of various layers is scarified has an influence on the level of voids at the intersection of two layers. This indicates that when compacting, care must be taken that the surface of a compacted layer is not scarified to extensively as this allows for higher voids contents in those areas, this is because the compaction time assigned to compact a single layer (specifically for emulsion mixes) is relatively short, this does not allow the loose material to necessarily arrange itself properly even though the target Dry Densities are achieved. These points will inevitably be week spots in the prepared sample. The CT Scanning showed a consistency in the air voids across the two samples per mix that were sent to the Netherlands. There is no sudden drop in the voids content in the lower layer of the sample, this indicates that no subsequent compaction of the underlying layers takes place nor does crushing of the material occur. 5.5 Repeatability Experimentation: G5 Material The repeatability experiments showed that the compaction procedure developed using G2 material proved to be adequate for the compaction of lesser quality granular materials such as G5 material. The G2 emulsion mix showed Dry Densities of around 103% Mod AASHTO and using the same procedure on the emulsion treated G5 material Dry Densities of around 100% Mod AASHTO were achieved; both these Dry Densities exceed the accepted level of site compaction. Looking at the Untreated material the same results were seen as with the emulsion mixes, the G2 material achieved Dry Densities of 103% Mod AASHTO and the G5 material achieved Dry Densities of 101% Mod AASHTO. 5.6 Conclusions regarding variability The variability results of Subsection 4.7 show that the vibratory hammer does have a low variability in terms of specimen production. Therefore the vibratory hammer is capable of consistently producing laboratory specimens. The results also show in Subsection 4.7.6 that the Mod AASHTO compaction (at room temperature) is slightly less variable than the vibratory hammer compaction. The difference is only slight. The largest difference came from the BSM-foam which showed a difference of 0.67 from the Mod AASHTO COV at room temperature. The conclusion drawn from such a small difference is that the variability of vibratory hammer is very similar to the Mod AASHTO compaction. 159 5.7 Conclusions drawn from the Mod AASHTO curves An interesting conclusion may be drawn when viewing the Mod AASHTO curves of the untreated material against the BSMs. The maximum Dry Densities produced for the BSMs were lower than the untreated material. This shows that the bitumen emulsion and foamed bitumen influence the level of compaction that may be achieved. 5.8 Conclusions drawn from the Vibratory Hammer Moisture curves The moisture curves of the vibratory hammer showed in general (with the exception of the BSM-emulsion) that the graph moved slightly to the left of the Mod AASHTO moisture curve. This shows that the OMC of the vibratory hammer is slightly lower than that of the Mod AASHTO OMC; vibratory hammer OMC was typically around 90% of the Mod AASHTO OMC of a specific mix. The curves also showed that in general higher Dry Densities are achieved using the vibratory hammer at lower moisture contents. The vibratory hammer moisture curves showed that in general the accepted level of compaction, according to current standards, may be obtained at various moisture contents. The bitumen emulsion and untreated materials produced compaction levels that are very close to what would typically be accepted on site. The fact that the results are so close to accepted compaction levels leaves room for variability (specifically in the case of the high quality G2 material which has an accepted level of compaction of 100 -102% Mod AASHTO (TRH 4) and with the vibratory hammer levels of 102-103% Mod AASHTO were achieved). Therefore in order to reduce this variability the compaction times may be increased by a factor of 2, this may produce samples that are well in excess of the accepted levels of compaction, but the variability may be reduced. 5.9 Overall Conclusions and Observations Drawn from the Experiments A procedure using time to produce samples may be developed. This procedure should not be used to compact a sample after a pavement has been constructed with the intention to produced site representative samples. When the procedure using time to compact is compared to the procedure followed by the USA (ASTM D 7382 – 07) and New Zealand it is evident that the compaction time allocated from the experiment results is far less than what these two countries have specified in their compaction procedures. The reason for this is the compaction energy of the hammer. The compaction energy assigned by the USA is around 10 Joule, The Bosch GSH 11E® used by Stellenbosch University has a point energy during compaction of 27 Joule, this is 2.7 times higher than specified by the USA, and will influence the compaction time of the various layers. 160 The refusal densities of the various layers are variable. As was stated in the results, this is believed to be as a result of the variability of the grading of the individual layers. Although the final grading of a sample may be correct in relation to the grading curve of the material, the material of the individual layers may in fact have variability in relation to the grading curve. Much time is lost during the preparation of samples once compaction is completed. This is due to having to unscrew the bolts of the split mould and then having to dismantle the entire mould so as to remove the specimen and once removed the mould may at times be wiped clean, depending on how dirty it has become during compaction, and then re-assembled for the compaction of the next sample. This dismantling is necessary because the sample does have a tendency to stick to the walls of the mould, therefore it cannot merely be slid out of the mould. A not stick spray, this may be purchased at any supermarket, is used to treat the walls of the mould prior to the compaction of a sample; this reduces the sticking of the sample to the mould walls. An important point that was also noted was that at high moisture contents, particularly 90% and 100% OMC (Mod-U) the material in the mould began to stick to the bottom of the foot piece. The effect of this was that upon raising the vibratory hammer, large amounts of material from the compacted layer were removed from the mould. The compaction of the emulsion mix for prolonged periods of time had the effect that emulsified bitumen began to ‘squeeze out’ between the walls of the mould and the foot piece. This ‘squeezing effect’ in the end results in lower binder content of the compacted sample. Also small amounts of water were seen seeping out at the base of the mould when compacting at high moisture contents (80%, 90% and 100% OMC (Mod-U)) for prolonged periods of time. It was also noted that a times the interlocking between layers was not always adequate and the sample tended to break in this case when being picked up. Therefore adequate scouring of the surface of the compacted layer should be done, typically look to 10mm of scour. Also samples should be picked up from the bottom end, this is because, as was seen in samples that were too moist, the bottom end seemed at times as if it would fall off, and this is due to the size and mass of the sample. The typical mass of a sample of 150mm × 300mm was in the order of 11kg and should the sample be picked up at the top end, the weight of the layers below each interlocking face will exert a tensile force on the section and if the interlocking is not strong enough the sample will break at those points. During the compaction of the G5 material at higher moisture contents (90%OMC to 110%OMC) it was noted that there was no seepage of water out from the bottom of the mould. Where in the case of the G2 material there was clearly water seeping out. The G5 material when wet had a very clayey appearance where the G2 did not. This clayey appearance may account for the 161 water retention of the G5 material, as clay materials do have a high level of water retention, which may be the reason for the lack of seepage of water through the bottom of the mould. 162 6 RECOMMENDATIONS Based on the results obtained from the experiments and the conclusions drawn, the following recommendations may be made. 6.1 Reducing the loss of time The dismantling and re-assembling of the mould takes up a significant part of the sample preparation time. The removing and replacing of the bolts in particular consumes time. Therefore the mechanism of loosening and fastening the split mould and fastening the mould onto its steel base should be reviewed. As apposed to using nuts and bolts to fasten the mould, a type of clasp should rather be used. i.e. instead of having to unfasten the bolts, the clasps may merely be opened and the mould disassembled. 4 3 Closed Clasp 1 2 Opened Clasp Figure L.109: Split mould set up with clasps Figure L.109 shows the Mould (4) set up taken from the British Standards. A similar clasp system to this is proposed to mount the mould to the base; these clasps are shown by number 2 on the figure and the base by number 1. The bolts used in the British Standards (number 3) should be replaced by clasps similar to those shown on the right of the mould set up; a total of four clasps would be need, two clasps on either side of the mould. It is also recommended that as apposed to two clasps being mounted to the base, that two more clasps be mounted; a clasp at the point marked 1 on the mould set up and a clasp directly across from it. This would bring the total number of clasps used to fasten the mould to the base to four which would provide enough support for the mould during compaction. It is believed that a clasp system similar to the one proposed would greatly speed up the process of producing samples. 163 6.2 Reducing the loss of material The extension piece used to extend the split mould height so as to accommodate the final Layer of material just prior to compaction was taken from the moulds used for Mod AASHTO compaction. This piece does not fit tightly around the split mould used for the vibratory hammer compaction; instead there is a small surface space between the mould and the extension’s inner circumference; this is where material gathers while compacting Layer 5. An extension piece that fits exactly on the circumference of the split mould’s opening should be made; this will therefore reduce the amount of material lost in Layer 5. 6.3 Vibratory Hammer Specifications From the research done the following Vibratory Hammer Specifications are proposed: Power rating: 1500 Watt consumption Frequency: 900 – 1890 beats/min (15 – 31.5Hz) Point Energy: 25 Joule The vibratory Hammer should be mounted on two guide rods; one on either side of the hammer. The total mass of vibratory hammer, surcharge and mounting head should be 30kg ± 1.5kg. The Bosch GSH 11E® vibratory hammer meets these specifications 164 6.4 Procedure to be followed for compaction using vibratory hammer Based on the findings of this report the following compaction procedure is recommended when using the vibratory hammer. The compaction of a 150mm X 300mm sample of bitumen stabilized granular material will be performed using a vibratory hammer, e.g. the Bosch GSH 11E®, with a surcharge of 10kg mounted in a frame. Compaction of the material will take place with the aggregate at room temperature i.e. 25ºC. The layout of the procedure is similar to the layouts provided in the TG 2 manual. 1 APPARATUS 1.1 A steel split mould 152mm in diameter and 300mm in height with an extension piece and clasps to fix the mould to the base of the frame. 1.2 3 Circular papers with diameter of 152mm. 1.3 Non-stick spray e.g. non stick cooking spray purchased at any supermarket. 1.4 A Vibratory Hammer with the following Specifications (see note 4.3): Power rating: 1500 Watt consumption Frequency: 900 – 1890 beats/min (15 – 31.5Hz) Point Energy: 25 Joule The vibratory Hammer should be mounted on two guide rods; one on either side of the hammer. A mounting head should be fitted to the vibratory hammer to allow a surcharge of 10kg to be mounted to the vibratory hammer. There should be a pulley system connecting the frame and mounting head. This allows for easy lifting and lowering of the vibratory hammer. The total mass of vibratory hammer, surcharge and mounting head should be 30kg ± 1.5kg. 1.5 A 150mm tamping foot 1.6 Material Scoop (90mm Ф x 85mm h) 1.7 Samples are compacted in 5 Layers. 1.8 Suitable marker e.g. permanent marker 1.9 Adjustable spanner to fasten and loosen surcharge load to the vibratory hammer. 1.10 Steel ruler of length >300mm 1.11 Chisel for tamping layers 1.12 Drill with drill bit of 300mm with a point marked off 10mm from the tip of the bit. 165 2 PROCEDURE 2.1 Preparation of the material Preparing the sample of material for initial Moisture Curve Determine the grading curve of the aggregate (TMH 1) and reconstitute the material to produce samples that will be used to obtain the OMC of the natural (untreated) material using the Mod AASHTO compaction method (TMH1: Method A7). Develop a Mod AASHTO curve (dry density versus moisture content) for the appropriate BSM using the OMC of the untreated material. This is done for various moisture contents over a range of 60% of OMC (Mod-Untreated Material) to 110% of OMC (Mod-Untreated Material) or till the appropriate moisture curve is obtained. Preparing the sample of material for vibratory hammer compaction From the grading curve reconstitute the material to the produce a sample of 14kg (see note 4.1) of aggregate with a maximum particle size of 19mm. A total of 5 or 6 samples of 14kg each are needed for a moisture curve. The aggregate is prepared as follows: 1. For a moisture curve samples are to be compacted over a range of moisture contents. Ranging from 2% moisture to 10 or 12% moisture; increasing in increments of 2%. 2. Should cement or lime need to be added to a specific mix, add these first to the sample: 3. For Untreated material i.e. no bitumen stabilization, add the fractions of water to each of the individual sample masses. 4. For BSM-emulsion, the moisture content of the bitumen emulsion needs to be calculated out of the physical mass of water that is added by hand. An example of this calculation is as follows: 166 Assumptions made for the example: A mix is to have a target moisture content of 6% moisture. The bitumen emulsion content of the mix is 3%. The bitumen emulsion is a 60/40 emulsion. For a 60/40 emulsion, 40% of the emulsion is water. Therefore of the 3% bitumen emulsion to be added to the mix, 40% of it is water. Therefore the fraction of water being added to the mix from the emulsion is 40% x 3%÷100 = 1.2% The fraction of water that is to be added to the mix in order to obtain a moisture content of 6% is now 6%-1.2% = 4.8%. The physical mass of water to be added to the mix in order to give a target moisture content of 6% when the bitumen emulsion is added is now 4.8% of the mass of the sample. First add the physical mass of water to the material and allow to stand for 40 – 60 minutes. After this time add the bitumen emulsion to the mix and also allow to stand for 40-60 minutes to allow breaking of the bitumen emulsion. 5. For the BSM-foam add the fractions of moisture to the material checking the ratio of the water relative to the OMC of the moisture curve developed for the untreated material from the TMH 1. When the moisture to be added reaches around 70-80% of the OMC of the untreated material, add this same moisture to the remaining samples and calculate the amount of moisture to be added to the sample to achieve the targeted moisture content. Prepare the BSM-foam in accordance with the procedure outlined in the TG (2) manual. After the foaming procedure add the remaining moisture to the samples mixed with moistures of 70-80% of OMC of the untreated material. 167 2.2 Compaction Procedure 2.2.1 Prepare the mould and vibratory hammer Preparing the vibratory hammer Fix the Mounting Head to the vibratory hammer and fit hammer onto the guide rods. Place the 10kg surcharge load onto the mounting head and fasten tightly – see separate drawing for Mounting Head, Subsection 5 (Kelfkens, 2008). Using the pulley system raise the vibratory hammer to the maximum height it can be raised or to an adequate height that will allow the operator to work beneath the vibratory hammer. Preparing the Mould Make sure the mould is clean and then spray the interior of the mould with the non-stick spray. After a sample has been compacted and removed from the mould, the mould should be cleaned by wiping of excess material from the mould walls. This should be done prior to the compaction of the next sample. Fix the mould to the base of the frame directly below the foot piece of the vibratory hammer using the clasps. Place two of the circular paper sheets at the base of the mould. Lower the vibratory hammer into the mould, checking that the vibratory hammer is perpendicular to the base of the mould i.e. the tamping foot is flat on the base with no point of the foot slightly raised. Allow the vibratory hammer to rest in the mould with no material present. Where the lower end of sleeve of the mounting head rests on the guide rod mark that position clearly on the vertical guide using the suitable marker. Raise the vibratory hammer and measure up from the initial mark 300mm and mark this clearly (non-erasable). 2.2.2 Compaction of the sample Addition of material to mould Material is placed in the mould 1 using the material scoop. Fill the scoop with the prepared material and level off the scoop and place it in the mould. Add three scoops of material to provide a starting layer thickness of 92mm. 168 Using the chisel, work the material around in order to evenly distribute it in the mould; try to distribute the particles evenly as well i.e. not too much fine material on top or to much coarse material on top, but rather a fair distribution of each i.e. unsegregated. Make sure the material is as level as possible before lowering the vibratory hammer till the foot piece comes to rest on the material. Compaction of individual layers Samples are compacted according to set times for each layer. The compaction times for the individual layers of a sample according to the type of Bitumen Stabilized Material is provided in Table L.29: Table L.29: Compaction times of individual layers for various BSMs Compaction Time of Individual layers Number in Seconds Mix type Layer 1 Layer 2 Layer 3 Layer 4 Layer 5* Untreated 10 15 15 15 15 BSM-emulsion 10 15 15 15 15 BSM-foam 10 25 25 35 25 After the material of a layer has been compacted for the allocated time, raise the vibratory hammer. Using the drill, scarify the entire surface area of the top of the compacted layer to a depth of ± 10mm (see Note 4.2). After the surface of a respective layer has been scarified, add the material for the next layer and compact accordingly. *After Layer four has been compacted and scarified, the extension piece (collar) must first be fitted to the mould before adding the material for layer 5. After adding the material for layer 5 place a circular sheet of paper on top of the material and then lower the vibratory hammer into position; the paper helps prevent material of the final layer from sticking to the tamping foot. Before raising the vibratory hammer the final height of the sample must be measured, once this is done the vibratory hammer may be raised and the sample removed. Measuring the final height of the specimen After Layer 5 has been compacted and prior to raising the vibratory hammer take the steel rule and measure the distance from the zero line to the 169 bottom end of the sleeve. This distance is taken as the final height of the specimen. Removing and handling the compacted sample Raise the vibratory hammer and remove the extension piece (collar). Disassemble the mould entirely. Place a plastic bag over the sample and remove it taking care to pick the sample up from the bottom end. Weigh the sample after compaction to check the final mass of the sample. Checking the moisture content of the sample Take a small amount (750-950 gm) of BSM either just prior to during or after compaction and using the standard oven drying method determine the moisture content. Determining the final Dry Density From the moisture content determined, the final mass of the compacted sample and the final height measured the final Dry Density of the sample may be determined. 2.3 Moisture sensitivity curve For the moisture sensitivity curve a total of 5 or 6 samples needs to be compacted at various moisture contents. This is described in Subsection 2.1. The curve is developed by plotting the final Dry Density of each of the samples against their respective final moisture contents. The peak, point at which the curve turns, is the OMC of the vibratory hammer and the Maximum Dry Density. Compaction specifications for site compaction The MDD of the vibratory hammer may be used to specify site compaction levels. The table below provides the levels of compaction: Table L30: Specifications for the level of site compaction Material Type/Quality Level of Site Compaction (% Vibratory Hammer) Untreated G1 and G2/G3 (High Quality) 98.6 - 100 BSM-emulsion 98.6 - 100 BSM-foam 96.1 – 98 170 For G4 to G6 materials the fraction of Mod AASHTO compaction specified for the level of site compaction is to be used. An example of this is as follows: for a G5 material the current specification for site compaction is 95% of Mod AASHTO compaction. Therefore according to the previous statement the accepted level of site compaction is 95% of vibratory hammer compaction. See Note 4.8 The Moisture curve of the vibratory hammer may be compared to the moisture curve of the specific mix which was developed from the TMH 1: Method A7. The OMC values are then compared and the lower OMC of the two curves is used to specify the compaction moisture on site. 171 3 CALCULATIONS 3.1 Addition of lime or cement Cement or lime content (C/L) C/L (gm) = C/L (%) × 14000 ÷ 100 3.2 Addition of water for untreated material Water (gm) = (target moisture content (%))/100× mass of sample (gm) 3.3 Addition of stabilizer and water to Bitumen Stabilized Material (BSM) BSM-emulsion Mass of bitumen emulsion Emulsion mass (gm) = Emulsion content (%)/100 × dry mass of aggregate (gm) Moisture contents MC in BSM from emulsion (%) = (MC of emulsion (%))/100 × emulsion content (%) Mass of water added to BSM = (∆MC) × mass of sample (gm)) 100 ∆MC = X (%) - MC in BSM from emulsion (%) X = target moisture content of the mix BSM-foam The bitumen stabilizer is added according to the method provided in the TG 2 manual for preparing BSM-foam. Ratio of Moisture contents MCmix : OMC = X/ (OMC (untreated material)) MCmix : OMC = Ratio of the targeted moisture content of the mix to the OMC (untreated material) X = target moisture content of the mix 172 For MCmix : OMC > 0.8 (80%) Mf = X – (MCmix : OMC)previous mix × (OMC (untreated material)) MF = Moisture added after foaming X = target moisture content of the mix (MCmix : OMC)previous mix= Final sample with a ratio ≤ 0.8 3.4 Dry Density Volume of the sample = π × 0.005625 × Fh Fh = Final height of the sample Dry Density = (Fm(kg)/(1+(MC(%)/100)) ÷ Volume of the sample Fm = Final Mass of the sample MC = Moisture Content 4 NOTES 4.1 For a final sample of 300mm high a sample mass of 14kg is recommended when preparing the BSM. 4.2 Layers should not be scarified deeper than 10mm. The result of scarifying deeper than10mm is that the layer being compacted does not bond adequately well to the previous layer and hence there is an increase in voids at this interface. 4.3 Should the vibratory hammer not meet the specifications provided and where no suitable alternative compaction hammers can be sourced, then a vibratory hammer with a point energy of 25 Joule ± 2 Joule should be used. If the weight of the hammer deviates from the specifications by more than 5%, then calibration tests need to be made. 4.4 After a sample has been compacted and removed from the mould, the mould should be cleaned by wiping off excess material from the mould walls. This should be done prior to the compaction of the next sample. 173 4.5 When preparing the moisture curve, the material should be looked at carefully. It must be noted at which moisture content the material becomes muddy. This is due to when samples are prepared that are to be tested in the laboratory; material that is muddy may not produce samples that are representative of the site compaction (in terms of particle orientation). The samples should then be compacted at the moisture content immediately below the moisture content at which the material became muddy. Should samples be prepared in the laboratory for testing without first preparing a moisture curve, then low levels of moisture should be added to the sample and slowly increased until the operator is satisfied that the material is not muddy but adequately wet. 4.6 When the sample prepared is to be used in the laboratory and the first four layers have been compacted, add sufficient material to layer five so that that the final height of the sample is 300mm or slightly higher. This is checked by viewing the final position of the sleeve relative to the 300mm marked of point on the guide rod, a tolerance of 2mm either side of 300mm is allowed. The sleeve may finish either on the mark, slightly above the mark or blow the mark. For each of the finishing positions a description of the procedure to be followed is given in a), b) and c). a) If the sleeve finishes on the 300mm mark after compacting layer 5, the sample is removed as previously described. b) If the sleeve finishes above the 300mm mark after compacting layer 5 a steel straight edge is used to cut of the piece of the sample extending out of the mould. Material is then sieved through a 4.75mm sieve on top of the sample. The vibratory hammer is the lowered and the sieved material is compacted till the sleeve reached the 300mm mark. The sample is then removed as previously described. c) If the sleeve finishes below the 300mm mark after compacting layer 5, the surface is scarified and three scoops of material are added. The added material is then compacted for the same duration as layer five and checked using a) and b) of note 4.6. 4.7 Should 7 ply shutter board not be obtainable then a wooden base with material properties as close to those of the 7 ply shutter board should be used. 4.8 The compaction specifications for site compaction need to be revisited as compaction data from sites become available. 174 5 DRAWINGS AND PHOTOGRAPHS Positioning of dead weight Sleeve Rubber fitting 113 127 112 870 Sleeve 64 50 Figure L.110: Schematic drawing of the Mounting head for the Bosch GSH 11E® 10kg Surcharge Vertical Mounting Rubber Fitting Sleeve guide rod head Figure L.111: Left view of Mounting head Figure L.112: Front view of Mounting head 175 6 Summary of vibratory hammer compaction procedure Outlined in this summary is the sequential procedure of the vibratory hammer. Step 1 When material is obtained that is to be compacted in the laboratory, the first step is to perform a grading on the material. Following the grading, samples for individual specimens are reconstituted from the grading results. Step 2 The first set of samples reconstituted is samples with a mass of 7kg that are used to perform a moisture sensitivity analysis using Mod AASHTO compaction (TMH 1: Method A7). Two moisture sensitivity analyses are performed. The first is an analysis on the untreated material, i.e. material only having moisture added to it and not having under gone bitumen stabilization. The OMC of the untreated material (OMC-U) is obtained from this the first analysis (Figure L.113). Moisture Sensitivity curve Untreated Material: Mod AASHTO Dry Density (kg/m3) MDD OMC-U Moisture Content (%) Figure L.113: Moisture Cure: Mod AASHTO- Untreated The second analysis is a moisture sensitivity analysis on the BSM i.e. the material after it has under gone bitumen stabilization. This analysis is performed using the OMC-U to determine the moisture content of each sample. A fraction of the OMC-U is added to the material prior to bitumen stabilization that will provide the target moisture content once the material has under gone bitumen stabilization. The fractions of OMC-U start at 60% increasing in increments of 10 until 110%. From this analysis the OMC of the BSM material is obtained (Figure L.114). 176 Moisture Sensitivity curve - BSM: Mod AASHTO Dry Desnity (kg/m3) MDD OMC-BSM Moisture Content (%) Figure L.114: Moisture Cure: Mod AASHTO- BSM Step 3 The second set of samples reconstituted is samples with a mass of 14kg. These are used for to perform the moisture sensitivity analysis for the vibratory hammer. At least 5 samples should be reconstituted. Cement or lime is first added to the material; should the mix being prepared require these stabilizers. Moisture is then added to the material in varying amounts across the samples. The moisture added starts at 2% moisture for sample 1 increasing in increments of 2% until a content of 10 or 12% for the final sample. The material is then allowed to stand for ± 60 minutes. The bitumen stabilizer (Emulsion or Foamed) is then added after the 60 minute time period. The material is once again allowed to stand for ± 60 minutes to allow for the breaking of the bitumen. Step 4 The mould and vibratory hammer are prepared as outlined in 2.2.1 of the procedure. Step 5 Each sample is compacted individually to produce a specimen for a specific sample. Specimens are compacted in five layers. Material from the specific sample is placed into the mould using a material scoop. Three scoops of material per layer are placed into the mould and each layer is compacted for a set period of time (Table L.29). Step 6 177 Prior to removing each specimen from the mould the final height of the specimen is measured. The specimen is then removed and the final mass is measured. The remaining material from the sample is used to perform a moisture content test for that specimen. The Dry Density of each sample is then calculated. Step 7 The moisture curve for the vibratory hammer is plotted. This is done by plotting the Dry Density of each specimen against its own moisture content. All specimens are plotted on the same set of axis. The Maximum Dry Density and OMC of the vibratory hammer are then read off the curve (Figure L.115). Moisture Sensitivity curve - BSM: vibratory hammer Dry Density (kg/m3) MDD OMC-vib Moisture Content (%) Figure L.115: Moisture Cure: vibratory hammer- BSM Step 8 The Maximum Dry Density for the vibratory hammer is then used to specify the target level of compaction for site (Subsection 2.3 of this procedure). Step 9 The OMC of the vibratory hammer (OMC-vib) is then compared to the OMC of the Mod AASHTO compaction for the specific mix. The lower OMC of the two is then selected for site compaction. See the figures below. Figures L.113 to L.115 show that the OMC of the vibratory hammer is typically lower than the Mod AASHTO OMC. The BSM-emulsion however may provide a curve which has an OMC-vib higher than the Mod AASHTO OMC. Therefore it becomes necessary to compare the moisture curves of the vibratory hammer and Mod AASHTO compaction methods as the lower OMC is used for site specification. 178 Step 10 Should specimens be prepared in the laboratory for testing purposes then specimens are compacted at 100% of OMC-vib. 179 REFERENCES Muthen, KM, 1998, Contract Report CR-98/077, CSIR Hanekom, R, 2007, University of Stellenbosch, Thesis V08, Compaction of Cold Mixes using the Kango Hammer Method Prochaska, A.B., and Drnevich, V.P., (2005), “One-Point Vibrating Hammer Compaction Test for Granular Soils,” Proceedings, GeoFrontiers Conference, ASCE, Austin, TX, January, 25 p. BS EN 12697-32:2003, 2004, Bituminous mixtures-Test methods for hot mix asphalt Part 32: Laboratory compaction of bituminous mixtures by vibratory compactor, University of Nottingham, Uncontrolled Copy, © British Standards Thenoux, G, Jamet, A, Encina, C, 2004, A Study and Recommendations of a Mix Design Procedure Using Gyratory Compactor for Foamed Asphalt Recycled Material, School of Engineering Universidad Católica de Chile Jönsson, M, Partl, MN, Flisch, A, 2002, Comparison of Different Compaction Methods Using X-ray Computer Tomography, EMPA Van de Ven, M, et al, , Gautrans, 1997, ITT Report 18.1-1997 Investigation into the Feasibility of Scaling Granular Materials for use with the MMLS Trial Tests on G1, Waterbound and ETB, Institute for Transport Technology Theyse, HL, 2003, Confidential CSIR Contract Report CR-2003/23 First Level Analysis Report: HVS Testing of the Foamed-treated crushed stone base on the N7/1 near Cape Town, Theyse, HL, 2004, Restricted CSIR Contract Report CR-2004/38 The Compaction Potential of Foamed- and Emulsified Bitumen Treated Material, Pretoria ASTM Standard D7382, 2007, “Standard Test Methods for Determination of Maximum Dry Unit Weight and Water Content Range for Effective Compaction of Granular Soils Using a Vibrating Hammer,” ASTM International, West Conshohocken, PA, www.astm.org. TNZ B/02, 2005, “Specifications for Construction of Unbound Granular Pavement Layers”, Transit New Zealand NZS 4402, 1986,”Test 4.3.1 New Zealand vibrating hammer compaction test”, New Zealand Standards, Wellington, 180 Draft TRH 4, 1996, “Structural Design of Flexible Pavements for Interurban and Rural Roads”, Pretoria, South Africa, CSRA, 1987, Standard Specifications for Road and Bridge Works 1987, Committee of State Road Authorities, Pretoria Sabita, 1993, GEMS-The design and use of granular emulsion mixes, Sabita, Roggebaai, South Africa MH 1, 1986, “STANDARD METHODS OF TESTING ROAD CONSTRUCTION MATERIAL”, National Institute for Transport and Road Research, Pretoria, South Africa Web Sites Miller group & Associate authors, 2004, http://www.millergroup.ca/pavement/emulsion_mixes.html, July 22, 2008 (11:28 AM) Patent Storm, http://www.patentstorm.us/patents/6451885-description.html, July 22, 2008 (11:29 AM) 181