Hancock County Marsh Living Shoreline Section 404 Joint
Transcription
Hancock County Marsh Living Shoreline Section 404 Joint
Hancock County Marsh Living Shoreline Section 404 Joint Application and Notification Form SAM-2013-00088-MJF Hancock County, Mississippi December 2014 Submitted to: Mississippi Department of Marine Resources U.S. Army Corps of Engineers Mississippi Department of Environmental Quality HANCOCK COUNTY MARSH LIVING SHORELINE JOINT APPLICATION AND NOTIFICATION DECEMBER 2014 1.0 Cover Letter 2.0 Joint Application and Notification 3.0 Supplement Attachments Attachment A: Maps/Drawings Attachment B: Agent Authorization Attachment C: Environmental Assessment Attachment D: Variance or Revisions to Mississippi Coastal Program Attachment E: Adjacent Landowners Attachment F: Summary of Agency Coordination Attachment G: Cultural Resource Feasibility Study for the Hancock County Marsh Living Shoreline Project and Section 106 Compliance Recommendations Attachment H: Heron Bay SAV and Oyster Survey Attachment I: USFWS Concurrence Letter Attachment J: MDMR Mississippi Coastal Program Consistency Determination Attachment K: NOAA (PRD) Concurrence Letter Attachment L: NOAA (HCD) Essential Fish Habitat Concurrence Letter Attachment M: NOAA Design Memorandum for Living Shorelines and Marsh Restoration Project in Hancock County Hancock County Marsh Living Shoreline Section 404 Joint Application and Notification Form Supplement December 2014 Hancock County, Mississippi Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement Table of Contents Page 1.0 INTRODUCTION ............................................................................................................ 1 2.0 PURPOSE AND NEED .................................................................................................... 2 3.0 ALTERNATIVES ANALYSIS.............................................................................................. 2 3.1 Site Alternatives ........................................................................................................... 2 3.1.1 Buccaneer State Park ................................................................................................... 3 3.1.2 Bayou Caddy ................................................................................................................ 3 3.1.3 Hancock County marsh (Preferred alternative) ............................................................. 4 3.2 Construction Alternatives Analysis ............................................................................... 7 3.2.1 No Construction Alternative ........................................................................................ 7 3.2.2 Construct Living Shoreline Structure in Heron Bay and Provide 70 acres of Sub-Tidal Oyster Reef ........................................................................................................................... 7 3.2.3 Heron Bay to Pearl River Construction Alternatives ...................................................... 7 3.2.4 St. Joseph’s Point Construction Alternatives ................................................................. 8 3.2.5 Final Construction Alternative Selection ....................................................................... 8 4.0 PROJECT LOCATION ...................................................................................................... 9 5.0 PROJECT DESCRIPTION ............................................................................................... 10 5.1 Anticipated Construction Process ............................................................................... 13 5.2 Aids to Navigation ..................................................................................................... 17 5.3 Geotechnical Pilot Study ............................................................................................ 17 5.4 Water Quality Certification ........................................................................................ 17 5.5 Project Adverse and Beneficial Impacts ...................................................................... 21 6.0 REFERENCES ............................................................................................................... 27 i Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 1.0 INTRODUCTION This report supports the Joint Application and Notification Form for the Hancock County Marsh Living Shoreline project in coastal Mississippi. The report details the project location, purpose and need, alternatives analysis, preferred alternatives, and project impacts. The attachments to the Joint Application and Notification Form include: • • • • • • • • • • • • • Attachment A: Maps/Drawings Attachment B: Agent Authorization Attachment C: Environmental Assessment Attachment D: Variance or Revisions to Mississippi Coastal Program Attachment E: Adjacent Landowners Attachment F: Summary of Agency Coordination Attachment G: Cultural Resource Feasibility Study for the Hancock County Marsh Living Shoreline Project and Section 106 Compliance Recommendations Attachment H: Heron Bay SAV and Oyster Survey Attachment I: USFWS Concurrence Letter Attachment J: MDMR Mississippi Coastal Program Consistency Determination Attachment K: NOAA (PRD) Concurrence Letter Attachment L: NOAA (HCD) Essential Fish Habitat Concurrence Letter Attachment M: NOAA Design Memorandum for Living Shorelines and Marsh Restoration Project in Hancock County The Mississippi Department of Environmental Quality (MDEQ), is the Mississippi Trustee for the Deepwater Horizon Oil Spill and related response actions (the Spill) and is partnering with the National Oceanic and Atmospheric Administration (NOAA) to propose an early restoration project that would protect a shoreline and marsh area by employing living shoreline techniques in Hancock County, Mississippi (see Figure 4). The proposed Hancock County Marsh Living Shoreline Project is included in the Final Programmatic and Phase III Early Restoration Plan and Final Early Restoration Programmatic Environmental Impact Statement (Phase III ERP/PEIS); which was released for public review and comment on December 6, 2013. On June 26, 2014 after considering all public comments received on the draft plan, the Trustees adopted and released a final Phase III Early Restoration Plan that included the Early Restoration Project. Thereafter, the Trustees approved the final Phase III Early Restoration Plan (“Phase III Plan”) and selected the Early Restoration Project in a Record of Decision dated October 2, 2014. The Trustees’ Record of Decision and the final Phase III Plan are available publicly (http://www.gulfspillrestoration.noaa.gov/restoration/early-restoration/phase-iii/). 1 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement The Final Phase III ERP/PEIS addresses programmatic early restoration project types as well as specific Phase III early restoration projects (including this project – See Chapter 10) that may be selected for implementation in accordance with the Oil Pollution Act, Natural Resource Damage Assessment (NRDA) regulations, the National Environmental Policy Act and the “Framework for Early Restoration Addressing Injuries Resulting from the Deepwater Horizon Oil Spill” (Framework Agreement). 2.0 PURPOSE AND NEED For the purpose of accelerating meaningful restoration of injured natural resources and their services resulting from the Spill, the Mississippi Trustee along with other state and federal Trustees propose to continue implementation of Early Restoration in accordance with the Framework Agreement and other applicable statutes and regulations. In April 2011, the Trustees entered into the Framework Agreement under which BP, a responsible party, agreed to provide up to $1 billion toward Early Restoration projects in the Gulf to address injuries to natural resources caused by the Spill. This Framework Agreement is intended to facilitate and expedite restoration in the Gulf in advance of the completion of the NRDA process. The Framework Agreement provides a mechanism through which the Trustees and BP can work together “to commence implementation of Early Restoration projects that will provide meaningful benefits to accelerate restoration in the Gulf as quickly as practicable” prior to completion of the NRDA process or full resolution of the Trustees’ natural resource damage claims. In order to accelerate meaningful restoration, the Trustees have identified restoration projects that will contribute to making the environment and the public whole for injury to or loss of natural resources and services resulting from the Spill. 3.0 ALTERNATIVES ANALYSIS 3.1 SITE ALTERNATIVES Throughout the Early Restoration process, the Trustees have used preliminary results from the NRDA to inform and guide the selection of Early Restoration projects. To date, the NRDA work clearly demonstrates extensive oiling of marsh and beach shorelines from Texas to the Florida Panhandle. Preliminary results also make clear that the oiling had significant adverse impacts on coastal and nearshore habitats and their biological communities. Early Restoration reflects the Trustees’ proposal to focus on those injury categories for which the nature of the adverse impacts is reasonably well understood and is limited to those areas at this time. Once the Trustees’ Assessment is complete, a final damage assessment and restoration plan will be developed to address injuries not fully addressed by the Early Restoration program. Three sites were considered for the creation of a living shoreline project, all of which are located in southwestern Hancock County, in close proximity to the selected Hancock County Marsh Living Shoreline site. The Hancock County Marsh is uniquely important because it is one of the largest remaining, intact marsh habitats in Mississippi, but it is experiencing high rates of shoreline erosion and marsh loss, and was directly impacted by oiling from the Spill. The three potential sites that were 2 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement considered included 1) a site near Buccaneer State Park, 2) a site near Bayou Caddy, 3) and the preferred alternative, the Hancock County Marsh Living Shoreline Project. The three sites are discussed below. 3.1.1 BUCCANEER STATE PARK Buccaneer State Park is located southwest of Waveland, Mississippi. Buccaneer State Park includes numerous camping sites, a water park, pavilions, an activity building, nature trails, and other recreational amenities. The Mississippi Sound shoreline associated with Buccaneer State Park was considered for the project; however, the site was not considered feasible due to the following factors: 1. Submerged Aquatic Vegetation (SAV) Cover - The shallow water in the Mississippi Sound adjacent to Buccaneer State Park has historically contained colonies of SAV (ground-truthed as recently as 2010) in the vicinity of the park. Siting the project in this vicinity would likely result in impacts to existing SAVs especially for marsh creation project components. 2. Shoreline Erosion and Marsh Loss - This site is not identified as a priority area in the Beneficial Use (BU) Master Plan (CH2M HILL for the Gulf of Mexico Alliance/Habitat Conservation and Restoration Team. May 2011. Final Master Plan for the Beneficial Use of Dredged Material for Coastal Mississippi). 3. Previous Mitigation Measures - None 3.1.2 BAYOU CADDY Bayou Caddy is located southwest of Waveland, in southwestern Mississippi. The shoreline associated with Bayou Caddy was considered for the project. 1. SAV Cover - The project area adjacent to Bayou Caddy has shallow water and has historically contained colonies of SAV. Siting the project in this vicinity would likely result in impacts to existing SAVs especially for marsh creation project components. 2. Shoreline Erosion and Marsh Loss - The Bayou Caddy site was identified as a priority area within the Hancock County Coastal Preserves in the BU Master Plan due to shoreline loss related to erosion. 3. Previous Mitigation Measures - The Bayou Caddy site was listed as a high priority site in the Final Project Management Plan for Selected Beneficial Use Projects along Coastal Mississippi (CH2M HILL for the Gulf of Mexico Alliance/Habitat Conservation and Restoration Team, September 2011) and the project was implemented by the USACE under the Mississippi Coastal Improvements Plan as an Interim Project to protect the shoreline and create marsh. A significant portion of this project has now been completed, so the scale of project required to achieve the NRDA offsets is not tenable at this location. 3 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 3.1.3 HANCOCK COUNTY MARSH (PREFERRED ALTERNATIVE) The Hancock County Marsh Preserve is located in southwestern Hancock County. The preserve includes adjoining marshlands bordering the Mississippi Sound from the Pearl River to Point Clear. The project area includes the shoreline of the Hancock County marsh from the mouth of the Pearl River on the west to approximately 1.86 miles past the heel of St. Joseph’s Point, including Heron Bay. 1. SAV Cover – A SAV and Oyster Survey was conducted in June 2013 in Heron Bay, located in the center of the Preferred Alternative Location site (provided in Attachment H). SAV presence was limited to very shallow waters along the fringe of the marsh edge, which would not be impacted by the marsh creation or breakwater construction portions of the proposed project, but could result in short-term, minor, adverse impacts to SAV during deployment of the oyster cultch. Widgeon grass exists in scarce amounts in very shallow waters along the fringe of the marsh edge in Heron Bay and grows on eroded marsh platforms. Any disturbance would be re-vegetated naturally. 2. Shoreline and Marsh Erosion - The northern portion of the Preferred Alternative Location site was identified in the BU Master Plan as the Saint Joseph Point Project, and was considered to be a priority project site. The same project was listed as a high priority in the Final Project Management Plan for Selected Beneficial Use Projects along Coastal Mississippi. Saint Joseph Point has experienced extreme marsh loss in the past 60 years, with over 260 acres of land loss since the 1950s (National Oceanographic and Atmospheric Administration [NOAA] Office of Coastal Survey, 2011). There has been over 1,600 linear feet of shoreline loss with over 1,000 feet of this loss occurring within the last 20 years (NOAA 2011) in this area. Shoreline regression since 1850 was studied and is depicted in Figures 1 through 3 below (Schmid 2002). These figures represent the change in shorelines over the course of three different periods: from 1850 to 2001, from 1969 to 2001, and from 1986 to 2001. Analysis of this data reveals that 45 to 60 percent of the shoreline was receding at a rate of one meter per year (Schmid 2002). That rate is the anticipated shoreline loss rate going forward. The loss of shoreline along the Hancock County Marsh is not uniform. The area from Three Oaks Bayou to Heron Bay Point has shown shoreline loss at a rate higher than one meter per year. This area is important because once it is breached, shoreline erosion will start taking place within Heron Bay. Presently the shoreline along Heron Bay is stable. Furthermore, Schmid indicates that approximately 6.2 acres of shoreline in Hancock County Marsh are being lost per year, and there is no evidence of any new marsh area being created, meaning that wave action is the main mechanism for loss of shoreline. 4 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement Figure 1: Shoreline Change Levels from 1850 to 2001 (Schmid 2002) Figure 2: Shoreline Change Levels from 1969 to 2001 (Schmid 2002) 5 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement Figure 3: Shoreline Change Levels from 1986 to 2001 (Schmid 2002) 3. Previous Mitigation Measures – None Based on the criteria evaluated during the site alternatives analysis, the Hancock County Marsh Site was selected as the Preferred Alternative. The other identified sites would either have more impacts to SAV, were not identified as a restoration priority, did not have comparable amounts of shoreline erosion, and / or were already implemented under other funding mechanisms. Selection of the Hancock County Marsh Living Shoreline project site also ensures that the Trustees meet our responsibilities under the Framework Agreement and OPA, including: • • • • The project would restore within Mississippi the injured salt marsh and lost benthic secondary productivity resulting from the Spill in an effort to make the environment whole by restoring, rehabilitating, replacing or acquiring the equivalent of these natural resources injured by the Spill. The nexus to resources injured by the Spill is clear; The project is technically feasible and utilizes proven techniques with established methods and documented results. Government agencies have successfully implemented similar projects in the region. For these reasons, the project has a high likelihood of success, and; The cost estimates are based on similar past projects, and the project can be conducted at a reasonable cost. 6 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 3.2 CONSTRUCTION ALTERNATIVES ANALYSIS Once the project site was selected through the Site Selection Process described above (Section 3.1), project and construction alternatives were developed, including a “no construction” alternative. These alternatives were evaluated to determine whether the following project goals were capable of being achieved with each alternative: • • • • Reduce shoreline erosion, particularly around St. Joseph Point and Lighthouse Point; Create and protect marsh habitat and provide for future marsh creation areas; Construct a sub-tidal oyster reef in Heron Bay in areas that historically contained oyster reefs and Achieve environmental, habitat and secondary production goals established for the project. 3.2.1 “NO CONSTRUCTION” ALTERNATIVE This alternative was evaluated and rejected because it would not achieve the project goals. 3.2.2 CONSTRUCT LIVING SHORELINE STRUCTURE IN HERON BAY AND PROVIDE 70 ACRES OF SUB-TIDAL OYSTER REEF An approximately 18,600’ living shoreline structure was proposed around the shoreline of Heron Bay. A 70 - acre sub-tidal oyster reef was proposed at the mouth of Heron Bay in water deeper than -3’ MSL. The living shoreline structure was to be constructed of rip rap with a 9” veneer of oyster shell. The crest width was to be 10’ with an overall structure height of 2.5’. The sub-tidal oyster reef was to be 6” of oyster shell. The total cost of project was estimated to be approximately $20.7M. This alternative was rejected since it did not address reducing erosion along major erosion areas (St. Joseph Point, Lighthouse Point and between Heron Bay and Pearl River). Additionally, this alternative did not provide areas for marsh creation. 3.2.3 HERON BAY TO PEARL RIVER CONSTRUCTION ALTERNATIVES Two types of structures (1) a low-crested rip rap breakwater structure and (2) a low-crested living breakwater structure (a breakwater structure topped with oyster shell), both approximately 1.9 miles in length, were evaluated. The proposed low-crested rip rap breakwater structure had a crest width of 15’ and a total structure height of 2.5’. The living breakwater structure would be identical in structure but with a 9” veneer of oyster shell. Although the living breakwater structure was slightly more expensive to construct, this alternative was selected because it achieved the habitat and secondary production goals established for the project. Two locations for the breakwater structures were evaluated – close to the existing shoreline (lowcrested rip rap breakwater structure) and along the -3.5’ MSL contour (low-crested living breakwater structure). The location along the -3.5’ MSL contour was preferred because it provided more opportunity to construct marsh shoreward of the structure, provided a structure on which secondary 7 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement productivity could occur and allowed wave dissipation along the shoreline, thus, providing greater shoreline erosion reduction, while providing a structure suitable for secondary production. 3.2.4 ST. JOSEPH’S POINT CONSTRUCTION ALTERNATIVES The living breakwater structure was the only construction alternative evaluated along this reach of the project given its proximity to existing submerged oyster reefs and the secondary production benefit that could be derived from this type of substrate (oyster shell as opposed to only riprap). The living breakwater structure had a 15’ crest width and varied in overall structure height from 2.5’ to 4’, depending on the location of the structure. The location of the living breakwater structure varied from close to shore to varying locations generally along the -3.5 msl contour to allow designated areas for construction of marsh on the landward side. The location that was closest to the existing shoreline was rejected because this location would have required an exposed breakwater structure in order to reduce erosion and would not allow for marsh creation opportunities. Additionally, the breakwater structure would not provide adequate habitat for secondary benthic production due to the exposed nature of the structure. By placing the living breakwaters generally along the -3.5 msl contour, there were opportunities to create from 66 to 257 acres of marsh, in addition to reducing the erosion along the existing shoreline. 3.2.5 FINAL CONSTRUCTION ALTERNATIVE SELECTION After looking at several alternative locations and construction alternatives, as described above, it was decided that a living breakwater constructed of a rip rap core with a 9” oyster shell veneer would be constructed along the -3.5 msl contour from Heron Bay to Pearl River (approximately 1.9 miles in length) and from Heron Bay eastward along St. Joseph’s Point (approximately 4.0 miles in length). There would be approximately 297 acres available for marsh creation, of which, 46 acres of marsh would be created under this project. A location in Heron Bay was selected to construct 46 acres of sub-tidal oyster reef due to the historical presence of submerged oyster reefs in this location and an oyster survey conducted in June 2013 (Attachment H). The oyster reef would consist of 6” of cultch material (oyster shell or limestone). After further consideration of the construction techniques and sub-surface soil conditions, the construction of the living shoreline structure was modified to utilize marine mattresses filled with rip rap and a 9” oyster veneer on the seaward side of structure and the crest. The structure would still have a 15’ crest width and be approximately 3.75’ in total height. To minimize settlement, the lowest layer of marine mattresses would have a geotextile fabric on the underside of the mattress. The marine mattresses would be constructed on shore, loaded on material barges, and transported to the site where they will be deployed from barges to construct the living breakwaters. Further the oyster reef height in Heron Bay was increased to 9” in order to provide the necessary secondary production goals. The advantages to this alternative are: • better quality control of the construction of the structure; 8 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement • • • • 4.0 less time on site to construct the structure; less turbidity generated during the construction process; reduction of the depth of temporary flotation channels to meet the construction needs; and minimization of settlement of the structure. PROJECT LOCATION The proposed project is located (Figure 4) in Hancock County, Mississippi (Bounding Coordinates: West 89.530339 W, 30.184 N; South: -89.462 W, 30.169 N; East: -89.415 W, 30.233 N; North: -89.53 W, 30.184 W. Centroid = -89.457 W, 30.19 N). Figure 4: Hancock County Marsh Living Shoreline Site Vicinity. The Hancock County Marsh Preserve is managed by the MDMR and is the second largest continuous marsh area in the state. The preserve includes adjoining marshlands bordering the Mississippi Sound from the Pearl River to Point Clear. The project area includes the shoreline of the Hancock County marsh from the mouth of the Pearl River on the west to approximately 1.86 miles past the heel of St. Joseph’s Point, including Heron Bay. On the seaward side, the project area extends approximately to the -8 ft. contour from the proposed breakwater to incorporate potential impacts from temporary flotation 9 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement channels that would be utilized by work barges during construction. Table 1 lists the Sections, Townships, and Ranges and the USGS topographic maps are located in Attachment A. TABLE 1 – Sections, Township, and Range of Project Section Township Range 1 10 South 15 West 5 10 South 15 West 6 10 South 15 West 9 10 South 15 West 10 10 South 15 West 11 10 South 15 West 12 10 South 15 West 13 10 South 15 West 14 10 South 15 West 5.0 PROJECT DESCRIPTION The Hancock County Marsh Living Shoreline project would include shoreline/marsh protection, marsh creation, subtidal reef restoration, and increased benthic secondary productivity. Specifically, the proposed project consists of three restoration components: • • • Use of living shoreline techniques that utilize natural and artificial breakwater material to reduce shoreline erosion by dampening wave energy while encouraging reestablishment of habitat that was once present in the region As part of the living shoreline approach, approximately 46 acres of salt marsh habitat will be created in areas that have experienced high rates of shoreline and marsh habitat erosion Placement of approximately 46 acres of oyster cultch in areas that have historically supported oyster habitat The following description is intended to be a conservative description of the project components in order to evaluate a maximum environmental impact for environmental permitting purposes. Project refinement(s) are anticipated as part of the design and construction process; however, any project revisions will be restricted to the current project footprint presented in this plan and on the project exhibits (Attachment A). Notification to the appropriate agencies will occur if revisions are made. The proposed Hancock County Marsh Living Shoreline project is intended to employ living shoreline techniques including natural and artificial breakwater material and marsh creation to reduce shoreline erosion by dampening wave energy while encouraging reestablishment of habitat that was once present in the region. Utilizing living shoreline techniques, the project would provide for construction of up to 5.9 miles of breakwater, approximately 46 acres of marsh creation, and approximately 46 acres of 10 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement subtidal oyster reef would be created in Heron Bay to increase secondary productivity in the area. The project would provide shoreline erosion reduction, creation of habitat for secondary benthic productivity, and protection and creation of salt marsh habitat. Figure 5: Project Features (Preferred Alternative) For this project, the living shoreline approach includes constructing a breakwater made of limestone with oyster shell veneer that provide erosion control benefits and enhances natural shoreline habitat and creation of 46 acres of salt marsh shoreward of the breakwaters. A breakwater can be defined as linear structures that may utilize artificial and/or shell‐based materials placed parallel to the shore in medium to high-energy open-water environments for the purpose of dissipating wave energy to reduce shoreline erosion. Living Breakwaters The breakwaters would be constructed at two locations: along St. Joseph’s Point (eastern reach) and Pearl River to Heron Bay (western reach). 11 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement • St. Joseph’s Point Breakwater (eastern reach): The conceptual design for the breakwater would be approximately four miles long, extending from Heron Bay to approximately four miles to the northeast, which includes openings throughout, with a crest width of approximately 15.0 ft. and total height of approximately 4.0 ft. (to +0.87 ft., North American Vertical Datum [NAVD]). The breakwater would have a footprint of approximately 14.4 acres and would be placed on a substrate of fine-grained sediment. It would be composed of a core of riprap and some or all could be covered by a 9-inch-thick layer of bagged oyster shell. • Pearl River to Heron Bay Breakwater (western reach): This conceptual breakwater would be approximately 1.9 miles long, with openings throughout, with a crest width of 15.0 ft. and a total height of approximately 4.0 ft. (to +0.87 ft., NAVD). Its design and sediment substrate are to be similar to the St. Joseph’s Point breakwater. The Pearl River to Heron Bay breakwater project area footprint would be approximately 5.5 acres, consisting of fine-grained sediment. The conceptual design is subject to refinement. Creation of Marsh in the Vicinity of St. Joseph’s Point In addition to the breakwaters, the living shoreline approach would include creating a total of approximately 46 acres of salt marsh in one to several locations. Salt marshes are defined as transitional marsh areas between land and water that occur in coastal areas at salinities at or approaching that of ocean water. Typical vegetation in salt marsh habitat includes species such as smooth cordgrass (Spartina alterniflora), black needlerush (Juncus romerianus), and saltgrass (Distichlis spicata). The area behind the constructed breakwater at St. Joseph’s Point would be backfilled with dredged material and allowed to re-vegetate by natural colonization of estuarine marsh species. Dredged fill material would be obtained through the Mississippi Beneficial Sediment Use Program as available or excavated from a suitable borrow source. Dredged material would be hydraulically placed to obtain the target elevation. Placement of Oyster Reef Cultch in Heron Bay In addition to the living shoreline components, oyster cultch would be deployed over approximately 46 acres in Heron Bay in areas that currently support or previously supported oyster production. Oyster reefs are typically colonial aggregations of living oysters and other bi-valves that can have subtidal as well as intertidal portions and that provide habitat for a community of other species. Oyster cultch deployment would occur generally in water depths of approximately -3 to -5 ft. MLLW. The reef(s) would be sited based on data gathered from an oyster presence survey and would consist of an approximately 6- to 9-inch-thick layer of oyster shell or limestone. The project exhibits (Attachment A) show a larger cultch footprint within which the cultch will be deployed. 12 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 5.1 ANTICIPATED CONSTRUCTION PROCESS This Section describes the anticipated construction process. The design drawings are included in the application packet as Attachment A. NOAA performed preliminary design calculations for the project based on tidal datum information from the Bay-Waveland Yacht Club NOAA tidal station, bathymetry based on nautical chart of the area, wind data from West Pier, Gulfport and design parameters and transmission coefficients for various wave heights and for the proposed breakwater cross-section. NOAA’s design summary is provided as Attachment M. Breakwaters The specific breakwater construction elevation was selected to maximize shoreline protection. Preliminary specifications are shown on Table 2. Construction would include placement of linear structures that would utilize artificial and/or shell‐based materials. The alignment and limits of the breakwaters would be surveyed; the outer limits of the breakwaters would be marked with poles driven into the bottom and extended approximately 3 feet above the water surface. The height of the breakwaters along the alignment would be constructed based on bottom elevations and the anticipated crest elevation (0.87 foot NAVD88 – Mean Tide Level). Barriers, navigation warning signs (up to approximately 185, lighted), and other safety devices would be installed along the work area to protect boaters as required. Table 2. Preliminary living shoreline (breakwater) specifications. Living Shoreline (Breakwater) Design Data Total project length Total project acreage Crest width Base width Assumed bottom elevation Total structure height Bagged shell veneer thickness Riprap Core volume Bagged shell volume Depth of material (riprap/marine mattress) Estimate initial settlement Design side slopes Breakwater distance from shoreline St. Joseph’s Point Breakwater (eastern reach) Approx. 4 miles 14.4 acres 15.0 feet 30 feet -3.5 MLLW 3.75 feet 9 inches Pearl River to Heron Bay Breakwater (western reach): Approx. 1.9 miles 5.5 acres 15.0 feet 30 feet -3.5 MLLW 3.75 feet 9 inches 51,600 cubic yards 16,400 cubic yards 16,900 cubic yards 6,300 cubic yards 3 feet 1 foot 2v:1h 30’-90’ 3 feet 1 foot 2v:1h 30’-90’ 13 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement Reach of each breakwater Length of each gap between breakwater 75 feet 25 feet 75 feet 25 feet The dimensions for the breakwaters would be approximately 30 feet wide at the base and approximately 15 feet wide at the crest. (Table 2). The breakwaters would be installed in segments with each segment being approximately 75 feet with 25-foot gaps between the segments. The riprap core of the breakwaters would either be constructed using marine mattresses, which would consist of 2- to 6-inch-diameter rocks assembled on land, or loose boulders. The marine mattresses or loose boulders would be transported to the work area on barges and installed by a crane located on a separate barge to construct the living breakwaters. The loose boulders or marine mattresses would be underlain by geotextile fabric, and placement of the material would be monitored to ensure the breakwater dimensions, slopes, and crest elevations are achieved. After installation of the loose boulders or marine mattresses, some or all of the breakwater segments would be covered with bags of shell. Construction details are provided on Sheet C13.0, Appendix A. The deployment of the breakwaters may extend over a period of ten to twelve months. Through consultations with appropriate federal agencies (Attachments I, K and L), construction activities would be conducted in accordance with Construction Conditions and best management practices (BMPs) established by federal agencies. These Construction Conditions and BMPs are presented in paragraph 5.5, below. Total installed volumes would be as follows: • St. Joseph’s Point Breakwater (eastern reach): The target depth for deployment is approximately -3.5 ft. MLLW, but could be between -3.0 and -5.0 ft. MLLW. The volume of placed material would be approximately 51,600 cubic yards of riprap and 16,400 cubic yards of shell. The breakwater would cover a footprint of approximately 14.4 acres of fine-grained sediment. • Pearl River to Heron Bay Breakwater (western reach): The target depth for deployment is approximately -3.5 MLLW-; but could be between -2.0 ft and -5.0 ft. MLLW. The volume of placed material would be approximately 16,900 cubic yards of riprap and 6,300 cubic yards of shell. The breakwater would cover a footprint of approximately 5.5 acres of fine-grained sediment. The project is designed to use temporary flotation channels (Table 3) to facilitate access for work barges into the work area. Channels will be excavated parallel to the alignments of the two breakwaters with additional channels excavated perpendicular to these channels to provide access from the Mississippi Sound. These channels will allow work barges entry and exit to the project area (See Attachment A) and will allow work to proceed much more quickly. All excavated dredged material not used for marsh creation would be cast on the seaward side of the channels so they naturally fill back in after construction. The channels are anticipated to fill in naturally in five years (based on project engineer 14 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement and contractor experience). A sediment transport study will be conducted using current and readily available data during the final design process. The study will seek, among other things, to address the redeposition of the proposed flotation channels. The depth of the channels would be 8 feet below MLLW to accommodate barge draft. The bottom width of the channels would be approximately 80 feet with 3H:1V side slopes (see Project Exhibits - Attachment A, Sheet Numbers C14.0 and C15.0). The entry locations for the channels would be determined by analyzing the shortest distance from the breakwaters to the appropriate depth of -8 feet and excavated using BMPs to minimize environmental impacts. For the purposes of project planning, the preliminary temporary flotation channel footprint was calculated based on an estimate of a heavy, fully- loaded barge. Proposed temporary flotation channel dimensions are summarized in Table 3. Table 3. Preliminary temporary flotation channel specifications. COMPONENT Channel length Existing depth Barge draft (proposed Depth) Channel width Area temporarily impacted Cubic yards of material to be moved Location of spoil disposal area Material type Dimensions of spoil area Method of excavation How will spoil area be contained? DIMENSION 55,008 feet 3-7 feet 8 feet 80 feet 101 acres 650,000 Adjacent to the new channel on the seaward side or potential beneficial use for marsh creation. Silty substrate 22.9 acres seaward side of channel Barge mounted excavator Uncontained, Intended to naturally refill channel over time After completion of construction, the breakwater structure would be surveyed and permanent navigation signs would be installed in accordance with safety requirements. Creation of Marsh in the Vicinity of St. Joseph’s Point After the breakwater along St. Joseph’s Point has been installed, selected areas totaling 46 acres landward of the breakwater within a 297-acre area (Attachment A, Sheet C13.0) would be filled with dredged material obtained from the MDMR Beneficial Use of Sediment Program, if material is available, or a suitable borrow source. If dredged materials are utilized for marsh creation, a Beneficial Use Permit would be required with MDMR as the permit holder, because the volume of material required will exceed 2,500 cubic yards. It is anticipated that a dike (containment structure) would be constructed at the seaward extent of the marsh. Sheet C14.0, Appendix A, provides details. Upon location of suitable fill material, the dike would be constructed by excavating existing material from the landward side of the proposed dike location, but not borrowing from the existing marsh (no existing marsh impact). Once an area of the marsh is diked, the area landward of the dike would be filled with dredged material until 15 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement final marsh grades are achieved. Sediment would be pumped through a floating pipeline from a hydraulic dredge located where suitable fill material is available. Pumps and sediment controls would remain in place throughout the dredging and filling process and after initial settling has occurred. Once the entire marsh area(s) is constructed, the area would be monitored for natural re-vegetation. The following table details the specification of this project component. Table 4. Preliminary marsh creation specifications. COMPONENT Dimensions of fill area Cubic yards of fill DIMENSION 46 acres minimum 375,000 MDMR Beneficial Use of Sediment Program as available Type of fill OR material from a suitable borrow source Other regulated activities None Placement of Oyster Cultch Reefs in Heron Bay Oyster cultch would be deployed in Heron Bay in water depths of -3 to -5 ft. MLLW in areas that currently support or previously supported oyster production. An oyster presence survey has been completed that identified suitable areas (Attachment G). The cultch would be deployed as a 6- to 9-inchthick layer of oyster shell or limestone. Prior to deployment, the limits of the oyster cultch deployment area(s) would be marked with buoys or poles. Oyster shells or other cultch material would be deployed by a barge-mounted crane with a clam shell bucket. A material barge loaded with cultch material would be moored to the crane barge. As a construction alternative, water jetting of cultch material off of a material barge may be used in case of water-depth constraints. Similar to the breakwater construction described above, temporary flotation channels will be used to access the oyster cultch area (Attachment A, Sheets C12.0 and C15.0). The flotation channels will be excavated from the Mississippi Sound into Heron Bay to facilitate barges carrying oyster cultch. Depending on the method of deployment, smaller deployment vessels will be used to spread the 46 acres of cultch material while the material barge anchors in the channel. If cultch material is deployed directly from the material barge, it will be necessary to dredge additional flotation channels perpendicular to the main flotation channel. It is expected that these channels will fill in naturally within five years of excavation, but will also be marked with lighted navigational signs to warn boaters of the presence of the spoil pile. Upon completion, the deployment area would be surveyed and no impacts are anticipated to result from the survey work. The following table details the specification of this project component. Table 5. Preliminary oyster cultch specifications. COMPONENT Dimensions of fill area Cubic yards of fill Type of fill Other regulated activities Flotation Channel DIMENSION 46 acres 37,150 Oyster shells or limestone None Included in the Table 6.0 estimate 16 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 5.2 AIDS TO NAVIGATION Aids to Navigation signage would be coordinated with the U.S. Coast Guard to determine the type of signage required and the locations of the signage. This is normally coordinated after the Section 404 Permit is issued. The signage and placement would be in accordance with the Coast Guard’s “U.S. Aids to Navigation System” guidelines. Preliminary discussions with the U.S. Coast Guard, New Orleans District indicates that all signage would need to be lighted. The signs would need to be approximately 300’ apart and located either seaward of the excavated material from the flotation channels along the proposed living breakwater structures, if the excavated material is not backfilled into the flotation channel during the project, or seaward of the living breakwater structure, if the excavated material is backfilled into the flotation channel during the project. If the excavated material from the temporary flotation channel to the oyster reef in Heron Bay remains, lighted signs would be required every 300’ along both sides of the excavated material. If the excavated material is backfilled into the flotation channel, temporary signage would be required during construction operations only. The permit drawings reflect these requirements and the anticipated lighted sign that would be required (Appendix A, Sheets C14.0 and C15.0). 5.3 GEOTECHNICAL PILOT STUDY In order to determine the potential settling rate (both short-term and long-term) and constructability of the proposed living shoreline breakwater structure, a geotechnical pilot study was proposed, permitted and implemented. A permit application was submitted to the Mississippi Department of Marine Resources (MDMR), the Mississippi Department of Environmental Quality (MDEQ) and the Mobile District, Corps of Engineers (USACE). The permit was approved by all regulatory agencies with the last approval being obtained from the USACE on July 15, 2014 (SAM-2014-00063-MJF). The geotechnical pilot study consisted of two 25’ X 25’ living breakwater marine mattress structures in a portion of the project area where the anticipated softest soils were identified. The two (2) living segments were installed on September 11, 2014. Two (2) settlement plates were installed with each structure and monitored for both initial and longer term settlement. Elevations of the existing footprint of each structure were taken prior to installation in order to determine the initial bottom elevation. As each structure was being installed, elevations of each settlement plate were taken. The initial settlement on September 11, 2014 was 0.07’ (0.84”) to 0.11’ (1.32”). Through October 27, 2014 (47 total days), the settlement was 0.18’ (2.16”) to 0.27’ (3.24”). 5.4 WATER QUALITY CERTIFICATION In accordance with Section 401 of the Federal Act, 33 U.S.C. Section 1341, a Water Quality Certification from the Mississippi Department of Environmental Quality (MDEQ) is required for this project. According to Rule 1.3.4 (Scope of Review for Application Decisions) of the MDEQ Wastewater Pollution Control Regulations, the following 11 factors related to the construction and operations of the activity must be addressed by the applicant and will be considered in determining certification action. 17 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 1. FEASIBLE ALTERNATIVES TO THE ACTIVITY An alternatives analysis is presented in Section 3.0 of this Joint Application and Notification Form Supplement. The site location alternatives analysis and the construction alternatives analysis are presented in Section 3.1 and 3.2, respectively. 2. MITIGATION Placement of the breakwater, created marsh, and deployment of oyster cultch would result in short-term, minor impacts to water quality as a result of resuspension of sediment by vessels (barges, tugs, skiffs, etc.) moving in and out of the project area, excavation of the temporary flotation channels, and filling of the marsh. The suspended sediment may be transported into surrounding wetlands, waterways, and the Mississippi Sound. However, the area is currently exposed to elevated turbidity levels as a result of resuspension of sediment from river transport, erosion of existing shoreline and during frequent storms, tides, and other typical weather events. Best management practices, along with other avoidance and mitigation measures required by state and federal regulatory agencies, would be employed to minimize potential water quality and sedimentation impacts. Impacts from turbidity would be minor, short term and limited in spatial extent. In addition to turbidity, the water quality could be impacted by leaks or spills of fuel and lubricants used by vessels and other equipment during the construction of the breakwater, marsh, and oyster cultch deployment. Appropriate best management practices, such as routine maintenance, inspection, and proper refueling of construction equipment, would be used to prevent, control, and mitigate impacts. Suitable maintenance dredge sediments that have been examined for levels of contamination, consistent with applicable requirements, would be used as fill material in the project area. 3. INITIAL AND SECONDARY IMPACTS ON ALL EXISTING AND ALL CLASSISIFED USES OF THE WATERS OF THE STATE The project area classified as “Recreation” from Heron Bay eastward, and as “Fish and Wildlife” from the western boundary of Heron Bay west to the mouth of the Pearl River (State of Mississippi Water Quality Criteria for Intrastate, Interstate, and Coastal Waters, 2007). Dissolved solids (turbidity) may increase temporarily during construction as described above but will dissipate and are not expected to result in conditions other than those which naturally occur in this area. Turbidity curtains will not be required. In a response to request for amendments memorandum dated September 26, 2014 (included in Attachment K of this application package), Dr. Roy E. Crabtree of NOAA 18 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement NMFS discussed turbidity issues associated with the proposed project and indicated that Ms. Florance Watson of the MDEQ had indicated by email to the applicant that “Turbidity screens are required for activities that will be ongoing for a significant period of time. [The Hancock County project] is temporary in nature, has minimal construction activities in water, and the construction timeframe is very short. Also, the water quality standard establishes that turbidity shall not exceed 50 NTUs of the ambient turbidity outside a 750-foot mixing zone. This activity will likely occur well within the mixing zone and is not expected to disturb the water bottoms to an extent that exceeds this standard”. This project is not anticipated to result in an increase in total fecal coliform bacteria. This project is not expected to have any secondary impact on existing and classified uses of the waters of the state. The waters of the State affected by the proposed project area not currently listed as impaired. 4. DEGREE OF COMPLIANCE OF THE PROPOSED ACTIVITY AND WITH THE STATE OF MISSISSIPPI WATER QUALITY CRITERIA FOR INTRASTATE, INTERSTATE, AND COASTAL WATERS The project is in compliance with water quality criteria outlined in the 2007 State of Mississippi Water Quality Criteria for Intrastate, Interstate, and Coastal Waters. It is not anticipated that this project will result in an increase in total fecal coliform bacteria. Dissolved solids (turbidity) may increase temporarily during construction but will dissipate and are not expected to result in permanent exceedances beyond those which currently exist. 5. DEGREE OF PHYSICAL, CHEMICAL, AND BIOLOGICAL IMPACTS ON WATERS OF THE STATE Physical impacts would be limited to temporary increased turbidity, as described above. No chemical impacts on waters of the state are anticipated due to the proposed project. During marsh creation and excavation of the flotation channels there could be shortterm, minor, impacts to the benthic infauna and epifauna and flora in the immediate area of construction. Biological impacts would be beneficial in the long term, due to increased secondary productivity benefits created by the living shoreline breakwater structure and the placement of oyster cultch in approximately 46 acres in Heron Bay. 6. THE EFFECT ON CIRCULATION PATTERNS AND WATER MOVEMENT ON WATERS OF THE STATE No long-term impacts from the breakwater and the created marsh to the tidal hydrology of Hancock County marsh and surrounding areas are anticipated. Gaps would be present between breakwater segments and created marsh areas that would allow tidal exchange flows and waterway access. Access to all of the tributaries within the Hancock 19 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement County Marsh will be maintained (see Figure 5 and Attachment A). The general shape of the shoreline would remain the same; therefore, there would be no anticipated impacts to tides and currents as a result of the project activities. Using final engineering design criteria, best available regional current, wind and sediments dynamics data will be utilized to determine the effects of the structure on hydrology and sediment dynamics in the project area. Additionally, the long-term monitoring would identify any erosion/sediment accumulation issues associated with the project that would be addressed through the maintenance budget included in the overall project budget. 7. DEGREE OF ALTERATION OF THE AQUATIC ECOSYSTEM The project will result in long term benefits to the aquatic ecosystem. This project is intended to enhance the aquatic ecosystem through the creation of oyster and benthic habitat thus increasing secondary benthic productivity, the creation of new marsh habitat and protection of existing marsh habitat, and reduction of shoreline erosion. Although temporary impacts to benthic communities could occur during dredging of temporary flotation channels and marsh creation, these communities are anticipated to recover quickly. The project has been coordinated with the US Fish and Wildlife Service and they concurred that the project is Not Likely to Adversely Affect any species regulated under the Endangered Species Act, Migratory Bird Treaty Act, and Bald and Golden Eagle Protection Act (Attachment I). Additionally, the NMFS Habitat Conservation Division concurred that the project will not adversely affect any Essential Fish Habitat (EFH) components regulated under the Magnuson-Stevenson Act (Attachment K). The project has also been coordinated with the National Marine Fisheries Service (NMFS) Protected Resources Division and they concurred that the project is Not Likely to Adversely Affect any species protected under the ESA or the Marine Mammal Protection Act (Attachment L). 8. DEGREE OF CONSISTENCY WITH APPROVED WATER QUALITY MANAGEMENT PLANS ADOPTED BY THE COMMISSION The water bodies located within the project area (Heron Bay and Mississippi Sound) are not listed as impaired water bodies in the “Mississippi 2014 Section 303(d) List of Impaired Water Bodies” dated July 24, 2014. There are no TMDLs assigned to these waters. Compliance of proposed activity with the water quality criteria is discussed in Factor 4, above. 9. STORM WATER MANAGEMENT Construction activities will occur in water; therefore no storm water management issues are anticipated. 20 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 10. COMPLIANCE HISTORY OF THE APPLICANT The Applicant obtained a Joint Application permit (SAM-2014-00063-MJF) for conducting a Geotechnical Pilot Study within the project area. The Geotechnical Pilot Study consisted of installing small lengths of the proposed breakwater structure utilizing proposed construction techniques. The Applicant has complied with all terms and conditions of this permit. 5.5 PROJECT ADVERSE AND BENEFICIAL IMPACTS Adverse and beneficial impacts of the Hancock County Marsh Living Shoreline project were evaluated in detail in the project specific Environmental Assessment included in Chapter 10 of the Final Phase 3 Early Restoration Plan and Programmatic Environmental Impact Statement (http://www.gulfspillrestoration.noaa.gov/restoration/early-restoration/phase-iii/). There will be no direct impacts to the existing shoreline or marsh habitat. Access to all of the tributaries within the Hancock County Marsh Preserve will be maintained (see Figure 5). The project is expected to result in minor, short-term adverse impacts in several resource categories, but overall the project is expected to result in a net long-term benefit due to shoreline protection, marsh creation, and restoration of submerged reef habitat that was once prevalent in this area. The following table identifies each resource category that was evaluated and whether the project will result in no effect, an adverse effect, or a beneficial effect. Public Health and Safety and Shoreline Protection Infrastructure Tourism and Recreational Use Aesthetics and Visual Resources Land and Marine Management Socioeconomics and Environmental Justice Habitats Protected Species Living Coastal and Marine Resources Noise Air Quality and GHGs Hydrology and Water Resources Geology and Substrates Table 6. NEPA effects summary table for Hancock County Marsh Living Shoreline Project Hancock County N -/+ -/+ S S + + -/+ + + S + + Marsh Living E Shoreline - Represents an adverse impact; + represents a beneficial impact; s represents a short-term adverse impact; NE represents no effect ( - ) Represents an adverse impact; ( + ) represents a beneficial impact; ( S) represents a short-term adverse impact; ( NE ) represents no effect In addition to NEPA review, several other federal consultations have been completed. The project has been coordinated with the US Fish and Wildlife Service and they concurred that the project is Not Likely 21 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement to Adversely Affect any species regulated under the Endangered Species Act, Migratory Bird Treaty Act, and Bald and Golden Eagle Protection Act (Attachment I). Additionally, the NMFS Habitat Conservation Division concurred that the project is will not adversely affect any Essential Fish Habitat (EFH) components regulated under the Magnuson-Stevenson Act (Attachment K). The project has also been coordinated with the National Marine Fisheries Service (NMFS) Protected Resources Division and they concurred that the project is Not Likely to Adversely Affect any species protected under the ESA or the Marine Mammal Protection Act (Attachment L). Best Management Practices and conservation measures associated with these consultations are described below. The impacts to aquatic resources and benefits are discussed below and listed in Table 6. St. Joseph’s Point Area Living Breakwater Construction Activity Area The St. Joseph’s Point Area Living Breakwater Structure is anticipated to be 4 miles long with a footprint of approximately 14.4 acres. Fine-grained sediment will be filled with riprap to form a breakwater, and then partially to completely covered with a bagged shell veneer. If the temporary flotation channels are backfilled during construction, approximately seventy 6-inch diameter treated posts will be driven adjacent to the submerged reef and will be used to mount warning signs. A total of 14.4 acres of open water with fine-grained sediment bottom habitat will be permanently converted to reef habitat. The project footprint has little to no vegetative cover and consists of only shallow open water as described in the Environmental Assessment (Attachment C). Pearl River to Heron Bay Living Breakwater Construction Activity Area The Pearl River to Heron Bay Living Breakwater Structure is anticipated to be 1.9 miles long with a footprint of approximately 5.5 acres. Fine-grained sediment will be filled with riprap to form a breakwater, and then partially to completely covered with a bagged shell veneer. If the temporary flotation channels are backfilled during construction, approximately 35 6-inch diameter treated posts will be driven adjacent to the submerged reef and will be used to mount warning signs. A total of 5.5 acres of open water with fine-grained sediment bottom habitat will be permanently converted to reef habitat. The project footprint has no vegetative cover and consists of only shallow open water as described in the Environmental Assessment (Attachment C). Temporary Flotation Channels Construction Activity Area Temporary flotation channels would be excavated for the construction of the breakwaters and deployment of oyster cultch in Heron Bay. The temporary flotation channels are anticipated to be 55,008 feet long with a footprint of 101 acres. The construction activities would include disturbing finegrained sediment bottom habitat due to the excavation of approximately 101 acres of channel. Material from channels would be sidecast adjacent to the temporary flotation channels to facilitate natural filling due to ocean currents, if not utilized for beneficial use in marsh creation. A short-term impact would be caused by sidecasting material on 22.93 acres. These impacts would be temporary as the channel will fill back in with the sediment to the seaward side in five years (based on project engineer and contractor experience). If the temporary flotation channels are not backfilled during construction, approximately 185 6-inch diameter treated posts will be driven adjacent to and seaward of the sidecast material and 22 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement will be used to mount warning signs. A sediment transport study will be conducted using current and readily available data during the final design process. The study will seek, among other things, to address the redeposition of the proposed flotation channels. Oyster Reefs in Heron Bay Loose oyster shell or suitable cultch material would be used to create approximately 6-9 inch thick subtidal reefs in Heron Bay. A total of 46 acres of cultch material would be placed on remnant oyster beds/hard bottom habitat that would be permanently converted to submerged reefs that would recolonize with benthic organisms. The project footprint has little to no vegetative cover and consists of only shallow open water as described in the Environmental Assessment (Attachment C). Marsh Creation at St. Joseph’s Point A total of 46 acres of open water with fine-grained sediment bottom habitat would be filled with suitable material and permanently converted to salt marsh habitat. The majority of this open water area was historically marsh that eroded over time. The project footprint has no vegetative cover and consists of only shallow open water as described in the Environmental Assessment (Attachment C). Table 6. Summary of Impacts Project Component St. Joseph’s Point Area Submerged Reef Construction Activity Area Pearl River to Heron Bay Submerged Reef Construction Activity Area Temporary Flotation Channels Temporary Flotation Channel Sidecast material Oyster Reefs in Heron Bay Marsh Creation at St. Joseph’s Point Impact Type Duration of Impact Long-Term Habitat Type Impacted Shallow water/finegrained sediment bottom Acreage of Impact 14.4 Permanent Shallow water/finegrained sediment bottom 5.5 Excavation of sea bottom Short-Term 101.0 Placement of excavated sea bottom of seaward side of flotation channels or for use in marsh creation Filling with Oyster Cultch (shells, limestone) Filling with suitable material Short-Term Water depths of 2 to 8 feet with finegrained sediment bottom Water depths of 2 to 8 feet with finegrained sediment bottom Long-Term Shallow water/hard bottom 46.0 Long-Term Shallow water with fine-grained 46.0 Filling fine-grained sediment with riprap, covered with bagged shell veneer Filling fine-grained sediment with riprap, covered with bagged shell veneer 22.9 23 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement sediment bottom Total Temporary Impacts Total Permanent Impacts Total Impacts 123.9 111.9 242.2 Construction of the Hancock County Marsh Living Shoreline project would result in long-term impacts to benthic soft and hard bottom habitat (approximately 111.9 acres) over the life of the project. The area would be covered with hard structure and sediment for the creation of breakwaters, marsh, and oyster reefs. There would be temporary impacts to approximately 123.9 acres of fine-grained sediment for the creation of temporary flotation channels including sidecast of spoil on the seaward side of the channel. The net benefits of the habitat protection and restoration would include increased benthic habitat diversity, structural complexity, greater diversity and abundance of marine aquatic species. In addition, the entire Hancock County marsh would experience reduced shoreline erosion. The project would provide long-term benefits by creation of approximately 46 acres of salt marsh, approximately 46 acres of oyster habitat, and create approximately 5.9 miles (19.9 acres) of high-profile reef. Approximately 5.9 miles of shoreline would be protected (Table 7). Overall, there would be a long-term benefit to geology and substrates in the Hancock County marsh. There would be no long-term adverse impact as a result of excavation of temporary flotation channels. Table 7. Habitat Created or Protected Habitat Type Shoreline Oyster Reef Marsh Means of Protection/Creation Creation of living breakwaters Restoration Measures 5.9 miles; 19.9 acres of high profile reef Placement of loose oyster shells or other 46 acres cultch material Placement of dredged material behind living 46 acres breakwaters Best Management Practices Throughout the design and construction process, every practical attempt would be made to avoid and minimize potentially adverse environmental, social, and cultural impacts. The following conservation measures and BMPs (sorted by resource type) would be implemented to minimize impacts to resources: • Green House Gas Emissions o Shut down idling construction equipment, if feasible. o Locate staging areas as close to construction sites as practicable to minimize driving distances between staging areas and construction sites. o Encourage the use of the proper size of equipment for the job to maximize energy efficiency. o Encourage the use of alternative fuels or power sources for generators at construction sites, such as propane or solar power, or use electrical power where practicable. 24 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement • • • • • Marine Mammals o If manatee(s) are found to be present in the immediate project area during restoration activities, construction would be halted until the species moves away from the project area. Protected Species o Awareness of potential turtle presence. If any sea turtles are found to be present in the immediate project area during restoration activities, construction will be halted until species moves away from project area. o Awareness of manatee presence. If manatee(s) are found to be present in the immediate project area during restoration activities, construction will be halted until species moves away from project area. For in-water work in Mississippi where manatees could be present, the Trustee will follow conditions a, b, c, and d of the Standard Manatee Conditions for In-water Work (USFWS 2011). The Trustee would report any collisions to the U.S. Fish and Wildlife Service or State trust resource agency. Temporary signs, if necessary, would be modified from the standard template to reflect local conditions. o Measures to protect Gulf Sturgeon. Project restoration features will be built close to the shoreline in shallow water (1-4 feet) and will not impede any migratory paths. Project construction activities will be subject to a stop work order if the species is observed in the project footprint. Work will continue once the species leaves the area. o Construction activities will adhere to special conditions specified in the Sea Turtle and Smalltooth Sawfish Construction Conditions, dated March 23, 2006 (NMFS 2006). The project will follow Measures for Reducing Entrapment Risk to Protected Species, revised May 22, 2012 (NMFS 2006). Migratory Birds o Pre-construction nesting surveys for migratory birds and raptors would be conducted and if evidence of nesting is found, coordination with the USFWS would be initiated to develop and implement appropriate conservation measures. Essential Fish Habitat o Work barges would be moored for overnight and weekends/holidays in areas where previous impacts have occurred (flotation channels, deployment areas). o Spoil from flotation channels will be placed on the seaward side of the channel to facilitate current-driven backfilling of channels. o Pilings would be driven instead of jetting to reduce the disturbance of bottom sediments and bottom dwelling organisms. o Where practicable, shell obtained from commercial vendors that did not or will not impact the aquatic environments will be utilized for reef construction. o Monitoring will be conducted before, during, and after project implementation to ensure compliance with project design and completion. If immediate post-construction monitoring reveals that unavoidable impacts to EFH have occurred, appropriate coordination with regional EFH personnel will take place to determine appropriate 25 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement • • response measures, possibly including mitigation. If additional adaptive management of the breakwater structure is necessary after monitoring evens, all minimization measures discussed above will be followed. o Any temporary access channels will be filled in naturally following construction to reestablish baseline elevations. Monitoring will assess whether unexpected impacts to EFH have occurred. Invasive Species o All equipment to be used during the project, including personal gear, will be inspected and cleaned such that there is no observable presence of mud, seeds, vegetation, insects and other species. o Oyster cultch and vegetation will be treated or inspected to remove “non-target” species. General Construction BMPs o Spoil from temporary flotation channels would be placed on the seaward side of the channel to facilitate current-driven backfilling of channels. o Placement of all signage pilings would be achieved by “driving” in lieu of “jetting” to reduce the disturbance of bottom sediments and bottom-dwelling organisms. Attachment C is a complete environmental analysis of the preferred alternative including the Mississippi Coastal Program decision factors. 26 Hancock County Marsh Living Shoreline Joint Application and Notification Form Supplement 6.0 REFERENCES CH2M HILL for the Gulf of Mexico Alliance/Habitat Conservation and Restoration Team. May 2011. Final Master Plan for the Beneficial Use of Dredged Material for Coastal Mississippi. CH2M HILL for the Gulf of Mexico Alliance/Habitat Conservation and Restoration Team. September 2011. Project Management Plan for Selected Beneficial Use Projects Along Coastal Mississippi. Final Programmatic and Phase III Early Restoration Plan and Final Early Restoration Programmatic Environmental Impact Statement http://www.gulfspillrestoration.noaa.gov/restoration/earlyrestoration/phase-iii/ Mississippi Department of Marine Resources (MDMR). 2013. Coastal Zone Management, Coastal Preserves Missions Values and Goals. Accessed online on July 9 at http://www.dmr.state.ms.us/coastal-ecology/coastal-preserves/60-coastal-preserves-missionvision-and-goals. 2013. NMFS. 2006. Sea Turtle and Smalltooth Sawfish Construction Conditions. Southeast Regional Office. St. Petersburg, Florida. Revised March 23. Schmid, Keil. 2002. Shoreline Change: Hancock County Marsh 1850 to Present. RPG # 0664, Mississippi Department of Environmental Quality, Office of Geology. Accessed online on June 10 at http://geology.deq.state.ms.us/coastal/NOAA_DATA/Publications/Publications/Hancock/Shoreline %20and%20Area%20Change%20of%20Hancock%20Marsh-1850%20to%20Present.pdf. 2013. State of Mississippi 2014 Section 303(d) List of Impaired Water Bodies, July 24, 2014. State of Mississippi Water Quality Criteria for Intrastate, Interstate, and Coastal Waters, 2007 USFWS. 2011. Standard Manatee Conditions for In-water Work. Available at: http://www.dep.state.fl.us/water/wetlands/forms/spgp/SPGP_IV_Attachment_3ManateeConstructionConditions.pdf. 27