Columbia University Medical Center Strategic

Transcription

Columbia University Medical Center Strategic
Columbia University Medical Center
School of Nursing Project Update
March 21, 2014
Agenda
I.
Project Overview
II. Plan Overview
III. Russ Berrie
IV. Noise and Vibration Management Plan
V. Parking
VI. Communications
Page 2
PROJECT
OVERVIEW
Project Overview
Site Plan
Page 4
Project Overview
Proposed Building Design
Page 5
PLAN
OVERVIEW
Plan Overview
Russ
Berrie
Ground Floor
School of
Nursing
Page 7
Plan Overview
Russ
Berrie
Typical Floor Plan
School of
Nursing
Page 8
Plan Overview
Russ
Berrie
ICM/7th Floor
School of
Nursing
Page 9
RUSS BERRIE
Russ Berrie Medical Science Pavilion
•
Naomi Berrie Diabetes Center
•
Research Activity
•
Animal Facility
Berrie was the second building in the Audubon
Biomedical Science and Technology Park
Primary Construction Goal: To maintain ongoing daily research
and clinical activities with minimal disruption
Page 11
Vibration Sensitive Equipment Locations
Room 5-520C:
F. Mancia
Crystallography Equipment
3rd Floor
4th Floor
5th Floor
Room 4-408A
S. Kousteni
DEXA scanner
Room 5-515
A. Marks
Crystal Plate Storage
Room 5-510
C. Karan
Automation Suite
Room 3-306
A. Christiano
Microscopy Room
Confocal Microscope
Room 6-612
L. Sussel
Confocal Microscope
Room 4-404
S. Kousteni
Histology Sectioning & Real
Time PCR Machine
6th Floor
Room 3-301
E. Lumpkin
Electrophysiology
RIG Room #1
Room 5-511
A. Marks
Confocal Microscope
Room 3-302A
E. Lumpkin
Electrophysiology
RIG Room #2
Room 6-606
L. Sussel
Epifluorescence Microscope
Room 4-402
L. Shapiro
Crystal Plate Incubator
Page 12
Animal Holding Locations
Room 738
Room 746
New Acoustical
Barrier
Room 730
New Acoustical
Barrier
Administration
Building Services
New Acoustical
Barrier
Cage and Rack Washing
Colony
Procedure Lab
Page 13
NOISE AND VIBRATION
MANAGEMENT
Rock Excavation
Building Section
Building Section
Russ Berrie
Building
Basement and Foundation Plan
*Rock removal scheduled to range 3-4 months
Page 15
Building Section
School of Nursing
Russ Berrie
Page 16
Site Logistics Plan
Page 17
Vibration Management Plan
• Baseline tests/Cerami Associates
• Employ best practices
•
Monitoring equipment
•
Hammer with baffle
•
Channel drilling
•
Hydraulic splitting
• 3-4 month duration of rock removal
Page 18
Noise and Dust Management Plan
• Clean construction best practices
•
Manhattanville
•
Medical and Graduate
Education Building
•
School of Nursing Building
• Clean Construction
•
Dust
•
Noise
•
Vibration
•
Emissions
•
Pest Control
•
Site Management
• Noise mitigation
•
Acoustical partitions at windows
•
Acoustical baffles at construction site fence
Page 19
Construction Phase
Harlem Hospital Building
Kings County Hospital Building
Irving Cancer Research Building
Medical and Graduate
Education Building
Page 20
PARKING
Faculty and Researchers
Needs and Concerns
• Availability and Cost of Parking
• Proximity to Russ Berrie
• Parking Lot Access
Page 22
The Naomi Berrie Diabetes Center Patients
Needs and Concerns
• Cost of parking and proximity to Russ Berrie
• Parking Lot Access
Page 23
COMMUNICATIONS
Project Timeline
• Design Development: Complete
• Construction Drawings: May 2014
• Bidding & Negotiations: September 2014
• Contracts & Permitting: October 2014
• Anticipated Construction Start: Q4 2014
• Duration of Noise Activity: 3-4 months
Page 25
Ongoing Communications Outreach
• Project Contacts:
•
Anthony Donatich, Project Manager
•
•
Patrick Burke, Assistant Vice President of
Capital Project Management
•
•
[email protected] or 917-453-7687
[email protected] or 212-305-1006
General Construction-related Inquiries
•
[email protected] or
212-304-RUSS (7877)
• Ongoing communications includes:
• Electronic Signage
• Email Updates
• Project Website
Page 26
Page 27
Page 28