The road to automation – a user perspective

Transcription

The road to automation – a user perspective
The road to automation – a user perspective
Update presentation of CTB terminal development (TOC Hamburg 2006)
C. Blauert , Managing Director HHLA Container Terminal Burchardkai GmbH
17.06.2009
© HHLA Container Terminal Burchardkai GmbH
AGENDA
CTB and Project Backround
Terminal Development and Current Status
Next Steps and Main Challenges
© HHLA Container Terminal Burchardkai GmbH
2
HHLA GROUP
Central Divisions
CONTAINER
INTERMODAL
© HHLA Container Terminal Burchardkai GmbH
Policy Units
LOGISTICS
REAL
ESTATE
3
HHLA CONTAINER TERMINALS
BILD WIRD NOCH FARBLICH ÜBERARBEITET
© HHLA Container Terminal Burchardkai GmbH
4
Brief Project History
Pilot Study (2002):
Planning Parameters, Applicable Technologies,
Layout Variants
Study Phase 1 (2003):
Reduction of Variants,
Dimensioning & Layout Planning
Study Phase 2 (2003):
Phasing Concepts & Sensitivity Analysis
Study Phase 3 (2004):
Safeguard Planning Results,
Decision-Making Document
End of 2004:
Concept´s Approval by CTB´s Supervisory Board
© HHLA Container Terminal Burchardkai GmbH
5
Existing Facility / Starting Position
Functional Layout (End of 2004)
e
e
lb
E
r
Empty Container
Storage Area
(Shed No. 5)
Truck
Dispatch
ua
Q
y
e
Ar
Railhead
a
ot
ep
D
y
y
ua
Q
CFS Area
(Shed No. 6)
ea
Ar
Mo
tor
Sh
wa
un
yA
tin
7
g
Ya
rd
Container
M
Repair
üh
le
nw
Workshop
er
de
r
Offices
y
e
Ar
a
Gate Area
Full Container Storage Area
r ea
in g A
Park
ua
Q
Truck
Dispatch
Quay Area
an
d
pt
Em
iv
R
Kö
hlb
r
Quay Area
Waltershof Basin
© HHLA Container Terminal Burchardkai GmbH
6
Terminal Extension Measures
Measures Excluding Changes of the Full Container Storage Concept
Re-positioning of InGate
Partial Demolition of CFS Shed 6
Re-positioning of Empty
Yard
Demolition of CFS Shed 5
Re-positioning of
Container Repair Shop
Inte r
cha n
ge
In-Gate
Re-positioning and Enlargement of
Railhead
Shed
6
Pu
b
li c
Sh
un
New Railhead
Empty Yard
tin
g
Ya
r
d
Shed 5
HO2
Old Railhead
HO1
Yard
Purchase of new and Repositioning of existing Quay Cranes
© HHLA Container Terminal Burchardkai GmbH
SC
Parkg.
Car
Park
OutGate
Consolidation of
Quay Wall
7
Terminal Development Concept
© HHLA Container Terminal Burchardkai GmbH
8
New CTB Yard Design
© HHLA Container Terminal Burchardkai GmbH
9
AGENDA
CTB and Project Backround
Terminal Development and Current Status
Next Steps and Main Challenges
© HHLA Container Terminal Burchardkai GmbH
10
CTB November 2005
© HHLA Container Terminal Burchardkai GmbH
11
CTB March 2007
© HHLA Container Terminal Burchardkai GmbH
12
CTB November 2007
© HHLA Container Terminal Burchardkai GmbH
13
CTB Mai 2008
© HHLA Container Terminal Burchardkai GmbH
14
CTB 2009
Quayside: commissioning of new Twin 40 Quaycranes
Yard: finishing of construction work is started (roll out of blocks)
© HHLA Container Terminal Burchardkai GmbH
15
CTB 2009
TOS: first operation of feeder vessel since June 2009
© HHLA Container Terminal Burchardkai GmbH
16
AGENDA
CTB and Project Backround
Terminal Development and Current Status
Next Steps and Main Challenges
© HHLA Container Terminal Burchardkai GmbH
17
Next Steps
ƒ Setting-up operation with TWIN 40 Cranes
ƒ Finishing and Go Live of Automated Yard System
-> First 5 Yard Blocks
-> Next 3 Yard Blocks
ƒ Further commissioning and Go Live of new TOS
ƒ Integration of new TOS and Automated Yard System
ƒ Implementation of new Control Tower
(operational procedures and work flow)
© HHLA Container Terminal Burchardkai GmbH
18
Main Challenges
ƒ Capacity Expansion under Full Operation
ƒ Ongoing existing operation has priority
ƒ Fall Back Options
ƒ Risk Management
ƒ Human Factor
ƒ Changes within the existing terminal organization
ƒ Implementing new operational procedures
ƒ Qualification of the terminal crew
© HHLA Container Terminal Burchardkai GmbH
19
END