Fiscal Year 2004/05 - Hyperion Treatment Plant
Transcription
Fiscal Year 2004/05 - Hyperion Treatment Plant
COLLECTION SYSTEM SETTLEMENT AGREEMENT ANNUAL REPORT Fiscal Year 2004/05 September 30, 2005 City of Los Angeles DEPARTMENT OF PUBLIC WORKS BUREAUS OF CONTRACT ADMINISTRATION ENGINEERING SANITATION … … ttoo pprrootteecctt ppuubblliicc hheeaalltthh aanndd tthhee eennvviirroonnm meenntt (This page was intentionally left blank.) C ITY OF L OS A NGELES BOARD OF CALIFORNIA PUBLIC WORKS DEPARTMENT OF PUBLIC WORKS –– –– COMMISSIONERS BUREAU OF SANITATION –– –– RITA L. ROBINSON DIRECTOR CYNTHIA M. RUIZ PRESIDENT JOSEPH E. MUNDINE EX EC UT IV E O FF IC E R DAVID SICKLER VICE PRESIDENT ANTONIO R. VILLARAIGOSA PAULA A. DANIELS MAYOR PRESIDENT PRO TEMPORE VAROUJ S. ABKIAN TRACI J. MINAMIDE ENRIQUE C. ZALDIVAR ASSISTANT DIRECTORS YOLANDA FUENTES 433 S OUT H S PR ING S T RE ET L O S A NG E L E S , CA 90013 TEL: (213) 473-7999 FAX: (213) 473-8100 VALERIE LYNNE SHAW September 30, 2005 Kathi Moore, Chief Clean Water Act Compliance (WTR-7) Water Division U.S. Environmental Protection Agency, Region 9 75 Hawthorne Street San Francisco, CA 94105 Attention: Mr. Ken Greenberg Jonathan S. Bishop, Executive Officer Los Angeles Regional Water Quality Control Board 320 W. 4th Street, Suite 200 Los Angeles, Ca. 90013 Attention: Mr. Sam Unger Greetings: ANNUAL PROGRESS REPORT NO. 1 FOR PERIOD ENDING JUNE 30, 2005 COLLECTION SYSTEM SETTLEMENT AGREEMENT AND FINAL ORDER (CIVIL ACTION NO. 01-191-RSWL AND NO. 98-9039-RSWL CONSOLIDATED) The City of Los Angeles is pleased to present the first annual report on the status of compliance with the Collection System Settlement Agreement and Final Order (CSSA). The report was prepared and submitted for the period ending June 30, 2005 pursuant to Section VI-G (Paragraph 70 to 72) of the CSSA. The provisions of the CSSA are designed to protect neighborhoods and improve water quality throughout Los Angeles through a comprehensive program of sewer cleaning, upgrades and repairs. In partnership with the City’s Department of Public Works’ Bureaus of Contract Administration, Engineering and Sanitation, the City Attorney’s Office and other City offices, consultant and contractors, this report demonstrates the City’s diligent efforts in improving its performance. Our commitment has not only resulted in compliance but, in fact, surpassed the requirements of the CSSA and has resulted in excellent results. The City has embraced this opportunity and has, in deed, assigned the CSSA compliance program the highest priority and provided the necessary resources to meet or exceed the requirements of the CSSA. Following an aggressive public outreach campaign that included over 1.5 million notices and 60 community meetings to inform the public about the importance of the CSSA and the need for additional funding, the City Council authorized sewer rate increases AN EQUAL EMPLOYMENT OPPORTUNITY — AFFIRMATIVE ACTION EMPLOYER Recyclable and made from recycled waste September 30, 2005 USEPA/RWQCB CSSA 1st Annual Progress Report – Period ending June 30, 2005 Page 2 of 3 over the next five years to provide the needed resources on February 2, 2005. In addressing the necessary staff resources, the City Council also authorized the addition of 21 staff to the Bureaus of Engineering and Sanitation on June 7, 2005. Because of the complexity and time sensitive nature of the CSSA and the City’s commitment to the CSSA, a committee called the Settlement Agreement Committee (SAC) was created in September 2004. With representation from the various bureaus of the Department of Public Works and the City Attorney’s Office, SAC oversees the progress of the CSSA compliance efforts. The SAC meets monthly to review and coordinate compliance activities and reports quarterly to the Board of Public Works. The City is in full compliance with the CSSA and, in most cases, has exceeded the requirements. The great majority of projects have been completed ahead of the scheduled dates. Sanitary sewer overflows (SSOs) are steadily declining. For fiscal year 2004-05, SSOs were approximately 45 percent less than those in the baseline year of 2000-01. It is noteworthy to mention that spills continued to decline even with the City’s recent second wettest season on record. Over the last two years, as a result of a focused chemical root control and sewer cleaning activities, root-caused SSOs have been reduced by 53 percent. SSOs caused by fats, oils and grease (FOG) were reduced by 80 percent since the inception of the FOG control program and as compared to those in the baseline year of 2000-01. More sewers are being repaired. New sewers are being built. More sewers are being cleaned and inspected. New and state-of-the-art odor control facilities are being built. SSOs and odors continue to be on a steady decline. As a result of these efforts, our neighborhoods and the environment are getting healthier and safer. A progress review meeting is being tentatively schedule for October 27, 2005 at 10:00 AM at our office at 2714 Media Center Drive. Formal notification will be made as soon as the date is confirmed. In keeping up with our mission “to protect public health and the environment”, I am grateful for the contributions of our dedicated staff to the success stories of this report. We all realize there is much more to do but I believe we have a good foundation and beginning. If you have any questions or comments regarding this report or the CSSA, please contact Mr. Adel Hagekhalil at (323) 342-6225. RLR/AHH:tn/cr I:\SA\1Annual Reports\2004-05\Actual Report\Annual Progress Report No 1 Final cover letter 093005.doc CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION BUREAU OF ENGINEERING BUREAU OF CONTRACT ADMINISTRATION COLLECTION SYSTEM SETTLEMENT AGREEMENT ANNUAL PROGRESS REPORT NO. 1 FOR PERIOD ENDING ON JUNE 30, 2005 September 30, 2005 (This page was intentionally left blank.) CERTIFICATION DECLARATION I certify under penalty of law that this Annual Progress Report No. 1 for the Period Ending June 30, 2005 was prepared either by me personally or under my direction or supervision in a manner designed to ensure that qualified and knowledgeable personnel properly gathered and presented the information contained herein. I further certify, based on my personal knowledge or on my inquiry of those individuals immediately responsible for obtaining the information, that to the best of my knowledge and belief the information is true, accurate, and complete. I am aware that there are significant penalties for submitting false information and willful submission of a material false statement. __________________________________ Adel H. Hagekhalil Division Manager Wastewater Engineering Services Division Bureau of Sanitation ________9/30/2005____________ Date (This page was intentionally left blank.) Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending on June 30, 2005 TABLE OF CONTENTS EXECUTIVE SUMMARY ..............................................................................................................v INTRODUCTION...........................................................................................................................1 Purpose .....................................................................................................................................1 Background ...............................................................................................................................1 An Overview of the Annual Report ............................................................................................2 ANNUAL REPORT .......................................................................................................................5 a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. p. q. r. Designated Rehabilitation and Replacement Projects ......................................................5 Rehabilitation and Replacement – Mileage Requirements .............................................10 Sewer Relief Projects ......................................................................................................10 Capacity Exceptions List .................................................................................................13 Wastewater Capital Improvements .................................................................................23 Sewer Cleaning ...............................................................................................................23 Sewer Line Television Assessment - Mileage.................................................................25 Sewer Line Television Assessment – Condition Ratings ................................................26 Fats, Oils, and Grease (FOG) Control Program..............................................................27 Primary and Secondary Basin Plans:..............................................................................30 MOUSE Model ................................................................................................................39 Chemical Root Control ....................................................................................................39 Significant Program Implementation ...............................................................................40 Failure to Comply Projects ..............................................................................................41 Odor Outreach Plan ........................................................................................................41 Odor Control Facilities Construction Progress ................................................................42 Independent Review of the Sewer Odor Control Program ..............................................45 Annual Supplemental Environmental Projects (SEPs) Status Report.............................47 i Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending on June 30, 2005 TABLE OF CONTENTS FIGURES Figure ES-1: Overall SSOs by Fiscal Year .................................................................................. vi Figure 1: Sewer Cleaning Progress ............................................................................................24 Figure 2: Sewer Line Television Assessment Progress..............................................................26 Figure 3: Condition Assessment Results ....................................................................................27 Figure 4: FOG-Related SSOs by Fiscal Year .............................................................................30 Figure 5: Primary Basin Plans in Progress .................................................................................33 Figure 6: Secondary Sewershed Plans Completed ....................................................................37 Figure 7: Root Control Progress .................................................................................................39 Figure 8: Root-Caused SSOs .....................................................................................................40 TABLES Table 1: Status of Designated Rehabilitation and Replacement Projects.....................................6 Table 2: Status of Sewer Relief Projects.....................................................................................11 Table 3: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 75%.....................14 Table 4: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 50% But Less Than or Equal to 75%.................................................................................................18 Table 5: Fiscal Year 2004-05 Sewer Cleaning Data ...................................................................24 Table 6: Television Assessment Overview .................................................................................25 Table 7: Condition Assessment Results .....................................................................................26 Table 8: Summary of FOG Program Results ..............................................................................27 Table 9: Referral Investigation Summary....................................................................................29 Table 10: Status of Primary Sewer Plans ...................................................................................30 Table 11: Completed Secondary Basin Plans.............................................................................35 Table 12: Construction Status of Odor Control Facilities ............................................................43 Table 13: Summary and Status of Independent Review Recommendations..............................45 Table 14: Summary of Progress on SEPs ..................................................................................48 ATTACHMENTS A: Wastewater Capital Improvement Program Summary B: Summary Status of CSSA Deliverables C: Summary Status of the North Atwater Creek Restoration & Water Quality Enhancement Project ii Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending on June 30, 2005 ACRONYMS AND ABBREVIATIONS Acronym or Abbreviation ATF Baykeeper CCTV CDO City COS CSSA d/D ECA ECIS ERIS ERP/ERG FOG FSE FY GBIS In. IRP LARWQCB MH MOUSE NCOS NEIS No. NORS NOS NOV NPDES PDWF SAC SEP SMARTS SOPs SSOs SSRP USEPA VSLFRS WCCD WCIP WCSD WLAIS Definition Air Treatment Facility Santa Monica Baykeeper Closed-Circuit Television Cease and Desist Order City of Los Angeles Coastal Interceptor Sewer Collection System Settlement Agreement Flow depth (inches)/Pipe Diameter (inches) Engineering Contractors Association East Central Interceptor Sewer Eagle Rock Interceptor Sewer Enforcement Response Plan and Enforcement Response Guide Fats, Oil and Grease Food Service Establishment City of Los Angeles’ Fiscal Year (July 1 through June 30) Glendale-Burbank Interceptor Sewer Inches Integrated Resource Plan Los Angeles Regional Water Quality Control Board Maintenance Hole Model of Urban Sewer Evaluation North Central Outfall Sewer Northeast Interceptor Sewer Number North Outfall Replacement Sewer North Outfall Sewer Notice of Violation National Pollutants Discharge Elimination System Peak Dry Weather Flow Settlement Agreement Committee Supplementary Environmental Project Sewer Management Automated Repair Tracking System Standard Operating Procedures Sanitary Sewer Overflows Secondary Sewer Renewal Program United States Environmental Protection Agency Valley Spring Lane & Forman Relief Sewer Wastewater Conveyance Construction Division Wastewater Capital Improvement Program Wastewater Collection System Division West Los Angeles Interceptor Sewer iii Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending on June 30, 2005 (This page was intentionally left blank.) iv Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 EXECUTIVE SUMMARY The City of Los Angeles is pleased to present the first annual report on the status of compliance with the Collection System Settlement Agreement and Final Order (CSSA). The report was prepared and submitted for the period ending June 30, 2005 pursuant to Section VI-G (Paragraphs 70 through 72) and Paragraphs 36, 53, 57, and 94 of the CSSA. This report is also available on the Bureau of Sanitation’s website at http://www.lasewers.org/CSSA/arno1.pdf. The provisions of the CSSA are designed to protect neighborhoods and improve water quality throughout Los Angeles through a comprehensive management program including sewer cleaning, upgrades, and repairs. In partnership with the City’s Department of Public Works’ Bureaus of Contract Administration, Engineering, and Sanitation, the City Attorney’s Office and other City offices, consultants, and contractors, this report demonstrates the City’s diligent efforts which have not only resulted in compliance but, in fact, have surpassed the requirements of the CSSA with excellent results. The City has embraced this opportunity and has, indeed, assigned the CSSA compliance program the highest priority and provided the necessary resources to meet or exceed the requirements of the CSSA. On February 2, 2005, the City Council authorized sewer rate increases for the next five years following an aggressive public outreach campaign that included over 1.5 million notices and 60 community meetings to inform the public about the importance of the CSSA and the need for additional funding. On June 7, 2005, the City Council authorized the addition of 21 staff to the Bureaus of Engineering and Sanitation to address the need for adequate staffing. Because of the complexity and time sensitive nature of the CSSA, a committee called the Settlement Agreement Committee (SAC) was created in September 2004. With representation from the various Bureaus of the Department of Public Works and the City Attorney’s Office, the SAC oversees the progress of the CSSA compliance efforts. The SAC meets monthly to review and coordinate compliance activities and reports progress quarterly to the Board of Public Works. The City is in full compliance with the CSSA and, in most cases, has exceeded the requirements. The great majority of required projects have been completed ahead of the scheduled dates. Sanitary sewer overflows (SSOs) are steadily declining. As shown in Figure ES-1, the overall SSOs in Fiscal Year (FY) 2004-05 were approximately 45 percent less than those of the baseline FY of 2000-01. It is noteworthy that spills continued to decline even with the City’s recent second wettest season on record. Over the last two years, as a result of a focused chemical root control and sewer cleaning activities, root-caused SSOs have been reduced by 53 percent. SSOs caused by fats, oils, and grease (FOG) were reduced by 79 percent since the inception of the FOG control program in Fiscal Year 2000-01. The City is fully committed to meeting all of the requirements of the CSSA as evidenced by its solid start during Year One of the CSSA. The accomplishments listed in this report show, in most cases, that the City moved beyond the requirements of the CSSA. Each future annual report will show additional enhancements to the wastewater collection system operation, v Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 maintenance, and management. The City looks forward to continuing to support the ultimate objective of the CSSA, which is to protect our neighborhoods and improve water quality. Figure ES-1: Overall SSOs by Fiscal Year 1,000 900 800 700 687 647 # of SSOs 613 600 Baseline Year 500 400 6% Reduction From Baseline Year 300 11% Reduction From Baseline Year 200 444 369 35% Reduction From Baseline Year 100 46% Reduction From Baseline Year 0 2000-01 2001-02 2002-03 2003-04 2004-05 Fiscal Year The following is a brief summary of the City’s compliance efforts during FY 2004-05: • • • • • Forty-five of the 127 deliverables that are due during the 10-year term of the CSSA have been completed in Year One of the CSSA or ahead of schedule with the remaining deliverables being on target. Twenty-six of the 55 projects designated by the CSSA for the first three years have been completed, most of them ahead of schedule. The two largest sewer relief projects, the East Central Interceptor Sewer and the Northeast Interceptor Sewer, have been completed. The City continues to implement its sewer-cleaning program, including hot spot cleaning. In FY 2004-05 the City cleaned 82,000 pipe reaches, which is 36 percent more than the 60,000 reaches required in the CSSA. In addition, the City’s quality assurance and follow-up inspection programs ensure that cleaning operations are effective. Using Closed Circuit Television (CCTV) technology and utilizing both City crews and contractors, the City assessed the structural and maintenance conditions of 821 miles of sewer lines, 36 percent beyond the 600 miles required by the CSSA. vi Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 • • • • • • • • • • • • • • The sewer line condition assessment in this report for the 821 miles inspected by CCTV indicates that 87 percent of the sewers assessed are in good to excellent condition. All 7,832 permitted food service establishments (FSEs) have been inspected at least once as part of the City’s FOG Control Program. A total of 15,000 inspections were conducted with a total of 944 notices of violation issued with 462 cases forwarded for further enforcement. Since the inception of the FOG Program in 2001, FOG-related SSOs have been reduced by 79 percent. The City has made excellent progress on the development of its primary and secondary sewer master plans. The City has completed the development of the “R” modeling factors for the basins within the MOUSE predictive model. 474 miles of root-infested sewers were chemically treated, far in excess of the CSSA requirement of 150 miles. This has resulted in significant reduction in root-caused SSOs. The City issued four quarterly reports summarizing the sewer overflows. Total SSOs for FY 2004-05 were approximately 45 percent less than those experienced in the baseline year of 2000-01. The City amended its sewer design manual as required in Section V-D (Paragraph 20) of the CSSA to accommodate excessive wet weather flow. The City has paid all negotiated civil penalties and attorney fees on schedule as set forth in the CSSA. The City has implemented all of the required odor control and response modifications. The City’s sewer odor hotline is in place and odor response measures, including chemical addition, are being employed. Odor control activities are routinely reported to the community Odor Advisory Board. During this reporting period, four interim odor scrubbers were placed in operation. Two additional scrubbers under construction are 70 percent complete. Permanent air treatment facilities are in design. Recommendations from the independent consultant for sewer odor control are being implemented. The City has initiated the development of work plans for the Supplemental Environmental Projects (SEPs). The work plan for the North Atwater Creek Restoration and Water Quality Enhancement Project is currently being reviewed by the Los Angeles Regional Water Quality Control Board (LARWQCB) staff. The next scheduled work plan is for the Hazard Creek and Wetlands Restoration Project which will be completed by March 2006. The City Council authorization of a sewer rate increase and 21 additional staff positions are significant program modifications that will contribute to the sustained success of this program. The Settlement Agreement Committee will continue to provide oversight and support to the City’s CSSA compliance program. vii Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) viii Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 INTRODUCTION Purpose This first annual progress report (Annual Report) has been prepared by the City of Los Angeles (City) to comply with Section VI-G (Paragraphs 70 through 72) and Paragraphs 36, 53, 57, and 94 of the Collection System Settlement Agreement and Final Order (CSSA). This Annual Report summarizes the City’s compliance efforts during the year ending on June 30, 2005. This report is also available on the Bureau of Sanitation’s website at http://www.lasewers.org/CSSA/arno1.pdf. Background During February 1998, the wettest February in Los Angeles’ history, sanitary sewer overflows (SSOs) occurred in a number of communities with the majority occurring in the Eagle Rock and South Los Angeles areas. In response to these SSOs, the Los Angeles Regional Water Quality Control Board (LARWQCB) issued a Cease and Desist Order (CDO) requiring construction of several new sewer lines to prevent additional wet weather overflows. These projects were to be completed within seven years and approached a cost of $600 million. During the same time period, the Santa Monica Baykeeper (BayKeeper) filed a Federal lawsuit against the City asking for injunctive relief due to the SSOs. In January 2001, the U.S. Environmental Protection Agency (USEPA), the LARWQCB and a number of community groups representing residents in South Los Angeles joined the BayKeeper in its lawsuit against the City. The plaintiffs alleged that the City’s SSOs and odor problems violated the Clean Water Act and the terms and conditions of the National Pollutants Discharge Elimination System (NPDES) Permits for the Hyperion and the Terminal Island Treatment Plants for the operation and maintenance of the City’s sewer system. With the City’s enhancements to its sewer system and renewed commitment by all parties to reach a manageable settlement that would protect neighborhoods and improve water quality throughout Los Angeles, the parties were able to reach this landmark settlement in August 2004. The objectives of the CSSA were: to resolve the pending consolidated litigation; to set out a program that the City would implement to reduce SSOs through a comprehensive program of sewer cleaning, upgrades, and repairs; and to investigate, resolve, and mitigate sewer odors to the maximum extent practicable. The CSSA was signed by all parties and filed with the court on August 5, 2004. On October 29, 2004, the United States Central District Court officially approved and entered the CSSA. The following is a brief summary of the terms of the CSSA, which requires the City to: 1) Enhance the City’s sewer condition assessment program. Assess a minimum of 600 miles of sewers annually with focus on older sewers and those susceptible to blockages. 1 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 2) Increase the City’s sewer repair, rehabilitation, and replacement efforts. Commit to the current program for the first three years and evaluate future needs with a minimum commitment of renewal of 60 miles per year after the third year. 3) Continue with the City’s Fats, Oils, and Grease (FOG) Control Program and enhance the inspection and enforcement of the Program. 4) Upgrade the sewer cleaning efforts with focus on those sewers that are prone to blockages. Commit to a minimum annual sewer cleaning of 60,000 pipe reaches or approximately 2,600 miles. 5) Continue with current chemical root control efforts in sewers prone to blockages and expand the program to meet needs. 6) Increase the City’s collection system capacity evaluation and assurance efforts. Implement identified relief sewer projects for the first three years and evaluate needs for the future. Revise the City's sewer design criteria to account for wet weather flow. Perform the necessary master planning for both large and small sewers and upgrade computer modeling capabilities to be used as enhanced planning tools. 7) Operate the sewer odor hotline and the necessary odor control efforts while expanding it Citywide. Construct the planned odor control facilities and continue the odor assessment and mitigation measures including the preparation of a Citywide odor control master plan. 8) Implement $8.5 million in supplemental environmental enhancement projects in lieu of penalties. 9) Continue with the sewer spill reporting on a quarterly basis. 10) Abide by the term of the CSSA (10 years) with possible early termination. An Overview of the Annual Report This Annual Report presents the City’s progress in its efforts to comply with the terms of the CSSA for the year ending on June 30, 2005. The content and structure of this Report are based on the requirements set forth in Section VI-G (Paragraphs 70 through 72) and Paragraphs 36, 53, 57, and 94 of the CSSA. The Annual Report's sections appear in the same alphabetical order (“a” through “n”) used in Section VI-G of the CSSA and continue with additional sections (“o” through “r”) in response to Paragraphs 36, 53, 57, and 94 of the CSSA. The following lists the Report sections and provides a brief summary of compliance with the CSSA requirements: a. Designated Rehabilitation and Replacement Projects: Twenty-six of the 55 projects designated by the CSSA for the first three years have been completed, most of them ahead of schedule. b. Rehabilitation and Replacement – Mileage Requirements: This provision applies to Years Four through Ten of the CSSA. 2 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 c. Sewer Relief Projects: The CSSA designated construction of ten sewer relief projects during the first three years. The two largest of these projects have been completed (East Central Interceptor Sewer and the Northeast Interceptor Sewer). d. Capacity Exceptions List: As required, this report includes the current capacity exceptions list. Listed are the sewers flowing at depth greater than 75 percent of the pipe diameter during peak dry weather flow (PDWF), along with the City’s planned action for these locations. Also listed are the sewers with PDWF depth exceeding 50 percent but less than or equal to 75 percent of the pipe diameter. Many of these locations are already part of our ongoing planning and capacity assurance efforts. e. Wastewater Capital Improvements: The City expended $225 million in wastewater capital improvement in FY 2004-05, of which $130 million (58 percent) was spent for collection system improvements. For FY 2005-06, the projected total wastewater capital improvement expenditure is $280 million with $160 million (57 percent) designated for the collection system. Attachment “A” is a summary of the City’s current 10-year capital improvement expenditure plan. A complete copy of the current 10-year Wastewater Capital Improvement Program (FYs 2005-06 through 2014-15) is available at http://www.lacitysan.org/fmd/WCIPBook05-06.pdf. A summary of the program is provided as Attachment A. The Wastewater Capital Improvement Program is currently undergoing its annual review and update. f. Sewer Cleaning: The City continues to implement its sewer-cleaning program, including hot spot cleaning. The City cleaned 82,000 pipes in FY 2004-05, 36 percent more than the 60,000 pipes required in the CSSA. In addition, quality assurance and follow-up inspection programs continue to ensure the effectiveness of cleaning operations. g. Sewer Line Television Assessment – Mileage: Using Closed Circuit Television (CCTV) technology and utilizing both City crews and contractors, the City assessed the structural and maintenance conditions of 821 miles of sewer lines, 36 percent beyond the 600 miles required by the CSSA. h. Sewer Line Television Assessment - Condition Ratings: The sewer line condition assessment in this report for the 821 miles inspected by CCTV indicates that 87 percent of the sewers assessed are in good to excellent condition. i. Fats, Oils and Grease (FOG) Control Program: All permitted food service establishments (FSEs) have been inspected at least once as part of the City’s FOG Control Program. This report contains detailed information on the program implementation. j. Primary and Secondary Basin Plans: The City has made excellent progress on the development of its primary and secondary sewer master plans. Eight Primary Basin Plans are scheduled for completion by July 2006, and all 25 are scheduled for completion by March 2009. A total of nine Secondary Basin Plans have been completed to date, and twelve more are scheduled for completion by July 2006. k. MOUSE Model: The City has completed the development of the “R” modeling factors for the basins within the MOUSE predictive model. l. Chemical Root Control: During FY 2004-05, 474 miles of root-infested sewers were chemically treated, far in excess of the CSSA requirement of 150 miles. This has resulted in significant reduction in root-caused SSOs, as indicated by the 53 percent reduction in root-related SSOs since program inception in FY 2002-03. 3 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 m. Settlement Agreement Implementation: The City Council authorization of a sewer rate increase and 21 additional staff positions are significant program modifications that will contribute to the sustained success of this program. The formation of the Settlement Agreement Committee; organizational changes; and improved planning, design, and operation and maintenance processes will provide further support to and focus on the CSSA compliance program. n. Failure to Comply Projects: The City has complied with all requirements of the CSSA to date. The following is additional information on topics outside of those required by Section VI-G of the CSSA: o. Odor Outreach in accordance with Paragraph 36 of CSSA: The City has implemented all of the required odor control and response modifications. The City’s sewer odor hotline is in place and odor response measures, including chemical addition, are being employed. Odor control activities are routinely reported to the community Odor Advisory Board. p. Odor Control Facilities per Paragraph 53: During this reporting period, four interim odor scrubbers were placed in operation. Two additional scrubbers under construction are 70 percent complete. Permanent air treatment facilities are in design. q. Independent Review of the Sewer Odor Control Program per Paragraph 57: Recommendations from the independent odor control consultant are being implemented. r. Supplemental Environmental Projects per Paragraph 94: Status reports for SEPs are included in this report. Detailed progress on the North Atwater Creek Restoration SEP is also attached. 4 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 ANNUAL REPORT a. Designated Rehabilitation and Replacement Projects Appendix “B” of the CSSA includes a list of designated sewer rehabilitation and replacement projects to be completed during the first three years of the CSSA. Table 1 summarizes completed projects and the current status of each ongoing project. The City has been aggressively pursuing the implementation of all projects required by the CSSA and assigned them the highest priority and the necessary resources. As shown, 26 of the 55 projects listed in Appendix “B” have been completed to date, all of them well ahead of schedule. Of the remaining projects, only one, the Wilshire Area Northeast Sewer Rehabilitation Project, was not completed by its original scheduled completion date of August 30, 2005 due to unforeseen construction conditions. An extension to the schedule was granted by USEPA and the LARWQCB based on unforeseen conditions. The new completion date is November 30, 2005. However, the project was actually completed on September 9, 2005. 5 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 1: Status of Designated Rehabilitation and Replacement Projects Shaded items indicate completed projects. CSSA Construction End Date Completed? (Yes or No) Project Status EQ RPR SWRS U298 12/14/2004 Yes Completed 6/9/04. Completed 188 days ahead of schedule. EQ RPR SWRS U277 01/13/2005 Yes Completed 7/20/04. Completed 177 days ahead of schedule. EQ RPR SWRS U269 01/13/2005 Yes Completed 7/20/04. Completed 177 days ahead of schedule. EQ RPR SWRS U290 02/11/2005 Yes Completed 6/10/04. Completed 246 days ahead of schedule. EQ RPR SWRS U289 02/11/2005 Yes Completed 6/10/04. Completed 246 days ahead of schedule. SAN PEDRO AREA SWR REHAB 02/28/2005 Yes Completed 9/7/04. Completed 174 days ahead of schedule. EQ RPR SWRS U346 03/16/2005 Yes Completed 5/4/04. Completed 316 days ahead of schedule. EQ RPR SWRS U344 03/16/2005 Yes Completed 5/4/04. Completed 316 days ahead of schedule. EQ RPR SWRS U373 04/15/2005 Yes Completed 5/12/04. Completed 338 days ahead of schedule. EQ RPR SWRS U369 04/15/2005 Yes Completed 5/12/04. Completed 338 days ahead of schedule. EQ RPR SWRS U327 05/16/2005 Yes Completed 6/23/04. Completed 327 days ahead of schedule. EQ RPR SWRS U317 05/16/2005 Yes Completed 6/23/04. Completed 327 days ahead of schedule. SOUTH LA CSRP U - 6 07/30/2005 Yes Completed 8/4/04. Completed 360 days ahead of schedule. SOUTH LA CSRP U - 5 07/30/2005 Yes Completed 8/4/04. Completed 360 days ahead of schedule. SOUTH LA CSRP U – 3 07/30/2005 Yes Completed 12/22/04. Completed 220 days ahead of schedule. Project Title Comments 6 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 1: Status of Designated Rehabilitation and Replacement Projects Shaded items indicate completed projects. Project Title CSSA Construction End Date Completed? (Yes or No) Project Status Comments WILSHIRE AREA NE SWR REHAB Original 08/30/05 Revised 11/30/05 No On Schedule Working closely with the contractor to complete construction by November 30, 2005. MT WASHINGTON AREA SWR REHAB 09/30/2005 Yes Completed 11/2/04. Completed 332 days ahead of schedule. S BOYLE AREA SWR REHAB 12/8/2005 Yes Completed 8/10/05.* Completed 120 days ahead of schedule. HOLLYWOOD AREA PRIM SWR REHAB 12/30/2005 Yes Completed 3/2/05. Completed 303 days ahead of schedule. 4TH SHATTO VERMONT SWR REHAB 12/30/2005 No On Schedule EQ RPR SWRS U274 03/16/2006 Yes Completed 10/6/04. Completed 526 days ahead of schedule. EQ RPR SWRS U340 04/15/2006 Yes Completed 3/25/05. Completed 386 days ahead of schedule. EQ RPR SWRS U283 04/15/2006 Yes Completed 3/25/05. Completed 396 days ahead of schedule. HARBOR AREA CSRP U- 6 05/30/2006 Yes Completed 8/2/05.* Completed 301 days ahead of schedule. NICHOLS CYN ESMT SWR REPLC 05/31/2006 No On Schedule EQ RPR SWRS U300 07/15/2006 Yes Completed 11/15/04. Completed 607 days ahead of schedule. EQ RPR SWRS U299 07/15/2006 Yes Completed 11/15/04. Completed 607 days ahead of schedule. LAS PULGAS CANYON SWR REPLC 07/30/2006 No On Schedule Construction is 15% complete. Bid & Award is 95% complete. Construction is 85% complete. 7 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 1: Status of Designated Rehabilitation and Replacement Projects Shaded items indicate completed projects. CSSA Construction End Date Completed? (Yes or No) Project Status HOLLYWOOD AREA CSRP U2 07/30/2006 No On Schedule Construction is 98% complete. EQ RPR SWRS U295 09/15/2006 No On Schedule Construction is 99% complete. EQ RPR SWRS U292 09/15/2006 No On Schedule Construction is 99% complete. EQ RPR SWRS U291 09/15/2006 No On Schedule Construction is 99% complete. EQ RPR SWRS U354 10/14/2006 No On Schedule Construction is 99% complete. EQ RPR SWRS U339 11/15/2006 No On Schedule Construction is 85% complete. EQ RPR SWRS U338 11/15/2006 No On Schedule Construction is 85% complete. EQ RPR SWRS U320 12/15/2006 No On Schedule Construction is 99% complete. EQ RPR SWRS U316 12/15/2006 No On Schedule Construction is 99% complete. WASHINGTON FLOWER GRAND SWR REPLC 12/30/2006 No On Schedule Bid & Award is 90% complete. CENTRAL AREA CSRP U-5 12/30/2006 No On Schedule Bid & Award is 90% complete. CENTRAL AREA CSRP U-3 & U-4 12/30/2006 No On Schedule Bids were opened on June 22, 2005. Bid & Award is 90% complete. 12TH HILL SWR REHAB 12/30/2006 No On Schedule Bid & Award is 92% complete. SAN FERNANDO PSDNA SWR REHAB 12/31/2006 No On Schedule Design was completed on August 10, 2005. Project Title Comments 8 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 1: Status of Designated Rehabilitation and Replacement Projects Shaded items indicate completed projects. CSSA Construction End Date Completed? (Yes or No) Project Status EQ RPR SWRS U294 01/13/2007 Yes Completed 6/15/05. Completed 587 days ahead of schedule. EQ RPR SWRS U293 01/16/2007 Yes Completed 6/15/05. Completed 590 days ahead of schedule. EQ RPR SWRS U319 02/15/2007 No On Schedule Construction is 50% complete. EQ RPR SWRS U318 02/15/2007 No On Schedule Construction is 50% complete. HARBOR AREA CSRP U-3 03/03/2007 No On Schedule Construction is 35% complete. EQ RPR SWRS U342 03/15/2007 No On Schedule Construction is 25% complete. EQ RPR SWRS U341 03/15/2007 No On Schedule Construction is 25% complete. FLINT AVE G ST SWR REPLC 03/24/2007 No On Schedule Construction is 90% complete. EQ RPR SWRS U304 04/14/2007 No On Schedule Construction is 16% complete. EQ RPR SWRS U296 04/14/2007 No On Schedule Construction is 16% complete. HOOVER ST SWR REHAB 05/02/2007 No On Schedule Design is 93% complete. LINCOLN 83RD SWR REPLC 06/30/2007 No On Schedule Bid & Award is 50% complete. HARBOR AREA CSRP U- 5 & WILM U-20 06/30/2007 No On Schedule Bid & Award is 50% complete. Project Title Comments 9 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 b. Rehabilitation and Replacement – Mileage Requirements For Years four through Ten of the CSSA, the City is required to report the number of miles of sewer pipes that have been rehabilitated and replaced in the previous Fiscal Year, and, for Years Six through Ten, to report the three-year average of sewer pipes rehabilitated and replaced in the previous three Fiscal Years. There is no reporting requirement in this reporting period. c. Sewer Relief Projects Appendix A of the CSSA includes a list of designated sewer relief projects to be completed during the first three years of the CSSA. Table 2 summarizes completed projects and the current status of each on-going project. The City has been diligently pursuing the implementation of all projects required by the CSSA and assigned them the highest priority and the necessary resources. As shown, two of the ten projects have been completed to date. Of the remaining projects, five are in the bid and award process and two are under construction. Only one, the Avenue 45 Arroyo Drive Relief Sewer Project, is behind schedule. The Avenue 45 Arroyo Drive Relief Sewer Project was to be completed by October 6, 2006. The project will construct 12,500 linear feet of new sewer to relieve an overloaded primary sewer system in the Eagle Rock and Highland Park Areas. The delay was due to unforeseen construction difficulties related to groundwater levels, access, easements and soil conditions. These unforeseen conditions also resulted in major complications in the bid and award of the construction contract, including limited and abnormally and excessively high bids. The City requested extension of the construction completion date to October 30, 2009 in a letter to USEPA and LARWQCB and dated August 25, 2005. 10 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 2: Status of Sewer Relief Projects Shaded items indicate completed projects. CSSA Construction End Date Completed? (Yes or No) Project Status EAST CENTRAL INTERCEPTOR SEWER 08/27/2004 Yes Completed 8/9/04. Completed 18 days ahead of schedule. NORTH EAST INTERCEPTOR SEWER, PHASE 1 10/30/2005 Yes Completed 5/27/05. Completed 156 days ahead of schedule. AVE 45 ARROYO DR RELIEF SEWER 10/06/2006 No Behind Schedule EAGLE ROCK INTERCEPTOR SEWER 10/30/2006 No On Schedule Construction is 62% complete. BAYWOOD BENEDICT EASEMENT SEWER 10/31/2006 No On Schedule Bid & Award is 70% complete. FLOWER WASHINGTON PICO SEWER 10/31/2006 No On Schedule Bid & Award is 30% complete. BUCKINGHAM ROAD DIVERSION SEWER 11/11/2006 No On Schedule Construction is 30% complete. SEPULVEDA SHERMAN OAKS /VALLEY MEADOW RELIEF SEWER 12/30/2006 No On Schedule Bid & Award is 35% complete. Project Title Comments Revising Construction Plans with a new project schedule. Request was made to Government Plaintiffs on August 25, 2005 for extension of Construction End Date to 10/30/2009. 11 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 2: Status of Sewer Relief Projects Shaded items indicate completed projects. CSSA Construction End Date Completed? (Yes or No) Project Status NOS DIVERSION AT HUMBOLDT STREET BTW AVE 18 & SAN FERNANDO ROAD 12/31/2006 No On Schedule Bid & Award is 90% complete. SLAUSON / VAN NESS / COS EXTERNAL BYPASS 12/31/2006 No On Schedule Design was completed on June 28, 2005. Currentlyin Bid & Award. Project Title Comments 12 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 d. Capacity Exceptions List The Capacity Exceptions List is provided below in Tables 3 and 4. Table 3 lists sewer gauging locations that exhibit peak dry weather flow (PDWF) levels exceeding 75 percent of the pipe diameter. Table 4 lists locations that exhibit PDWF levels exceeding 50 percent of the pipe diameter but less than or equal to 75 percent of the pipe diameter. The CSSA requires the City to report planned actions on the locations that exceed the City trigger flow level of 75 percent of the pipe diameter. Many of these locations are either being addressed through an existing capital improvement project or being evaluated throughout master planning efforts. Some of the locations were reported to exhibit PDWF levels exceeding 50 percent of the pipe diameter based on the latest gauging data although the historical trend does not support this result. As such, these locations are being reviewed with the City’s maintenance and engineering staff for necessary action. 13 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 3: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 75% No. MH No. Location Size (in.) 1 46715026 R/W 800' S/O ECHO ST AT AVE 50 18 2 53401077 GRANVILLE @ BROOKHAVEN 30 3 55807059 60TH PL 330'W/O NORMANDIE AV 34 4 55807066 WESTERN AV CL 300' S/O 60TH PL 18 5 55807126 NORMANDIE AV AT 64TH ST 30 6 55812097 FLORENCE AV 350' E/O VERMONT AV 20 d/D Planned/Proposed Action Flowing Full The Avenue 45 Arroyo Dr Relief Sewer, which is currently in design, will provide relief to this location. The completion of the Eagle Rock Interceptor Sewer (ERIS) in spring 2006 will also help relieve this sewer. Flowing Full Maintenance issue. The West Los Angeles Interceptor Sewer (WLAIS) Maintenance Hole (MH) Addition project will provide new MHs and will clean the WLAIS System. Projected future flow does not indicate any need for future relief. After the WLAIS System is cleaned, the City will continue to reevaluate future capacity needs. Flowing Full Debris in the sewer contributes to high d/D. The Florence Avenue Sewer Rehabilitation/Replacement project will be built to replace the sewer. The Vermont Relief Sewer ECIS-Slauson and the Vermont Relief Sewer Florence-Slauson will address ultimate relief for this system. Flowing Full Debris in the Florence Avenue Sewer and resulting high flow contributes to the high d/D at this location. The Florence Avenue Sewer Rehabilitation/Replacement project will be built to replace the Florence Avenue Sewer. The Vermont Relief Sewer ECISSlauson and the Vermont Relief Sewer Florence-Slauson will address ultimate relief for this system. Flowing Full Debris in the sewer contributes to high d/D. The Florence Avenue Sewer Rehabilitation/Replacement project will be built to replace the sewer. The Vermont Relief Sewer ECIS-Slauson and the Vermont Relief Sewer Florence-Slauson will address ultimate relief for this system. Flowing Full Debris downstream of this sewer contributes to the high d/D. The Florence Avenue Sewer Rehabilitation/Replacement project will be built to replace the downstream sewer. The Vermont Relief Sewer 14 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 3: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 75% No. MH No. Location Size (in.) 7 61309059 KING AV 50' S/O ALTON ST 18 8 62009134 HARBOR BL E/S AT 2ND ST S/PL 21 9 53806111 SOTO ST 260 S/O LUGO ST 27 10 55812086 FLORENCE AV 300' E/O NORMANDIE AV 30 11 55812093 FLORENCE AV 300' W/O VERMONT AV 30 12 62013031 HARBOR BL R/W 33 13 55807086 62ND ST N/S 33' E/O HARVARD BL. 54 d/D Planned/Proposed Action ECIS-Slauson and Vermont Relief Sewer Florence-Slauson will address ultimate relief for this system. Flowing Full Past Gauging data does not suggest a capacity problem. Further investigation underway. 96% Maintenance Issue. Placed on a Regular Maintenance Program. Sewers will be monitored through the regular gauging program. There is no capacity issue. 95% MH 53806129 is an existing Venturi Flume measuring flow between the City of LA and City of Vernon downstream of this location. The flume restricts flow and creates upstream backwater conditions. The Soto St Gauging Chamber Modification project will modify the chamber. 90% Debris in the sewer contributes to high d/D. The Florence Avenue Sewer Rehabilitation/Replacement project will be built to replace the sewer. The Vermont Relief Sewer ECIS-Slauson and Vermont Relief Sewer Flor-Slauson Projects will address ultimate relief for this system. 89% Debris in the sewer contributes to the high d/D. The Florence Avenue Sewer Rehabilitation/Replacement project will be built to replace the sewer. The Vermont Relief Sewer ECIS-Slauson and Vermont Relief Sewer Flor-Slauson Projects will address ultimate relief for this system. 89% The high d/D reading was due to construction activities for the Siphon Harbor Crossing Relocation, which was recently completed. Additional gauging will be requested to verify post-construction sewer conditions. 88% The construction of the Slauson/Florence Diversion to the Central Outfall Sewer (COS) will provide relief for this sewer. Currently in 15 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 3: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 75% No. MH No. Location Size (in.) d/D 14 55807040 60TH ST N/S 1ST MH W/O ST. ANDREWS PLACE 39 86% 15 55806217 62ND ST E/O HAAS AV 54 86% 16 55806220 VAN NESS AV AT 59TH ST 54 85% 17 53504136 M.L.KING BL AT RODEO RD (35' S/O N/CURB) 44306177 ACAMA ST AT FAIR AV 54 85% 57 84% 51806192 CRESCENT HEIGHTS BL AT AIRDROME ST 49208174 MARTEL AV. 400' N/O OAKWOOD 39 83% 72 82% 18 19 20 Planned/Proposed Action Bid & Award process. High d/D is caused by the hydraulic restriction downstream. Debris in the sewer contributes to high d/D. The Florence Avenue Sewer Rehabilitation project will be built to replace the sewer. Ultimate relief will be addressed by the Vermont Relief Sewer ECIS-Slauson and Vermont Relief Sewer Flor-Slauson. The construction of the Slauson/Florence Diversion to the COS will provide relief for this sewer. Currently in Bid & Award process. The construction of the Slauson/Florence Diversion to COS will provide relief for this sewer. Currently in Bid & Award process. The construction of the Slauson/Florence Diversion to COS will provide relief for this sewer. Currently in Bid & Award process. High flow is due to reduction of flow at the Donald C. Tillman Water Reclamation Plant (DCTWRP) due to construction activities for the nitrogen removal projects. Long-term relief is being addressed in the Integrated Resource Plan (IRP). The Valley Spring Lane & Forman Relief Sewer (VSLFRS), Glendale-Burbank Relief Interceptor Sewer (GBIS) and Northeast Interceptor Sewer (NEIS) Phase II will provide relief to this sewer. The draft Environmental Impact Report (EIR) for the IRP, which will address GBIS and NEIS Phase II, will be out for public review by the end of the year. Past gauging events did not show any indication of high flow. Review and validation of the recent gauging results is underway. High flow is due to reduction of flow at DCTWRP due to construction activities for the nitrogen removal projects and due to diversion of flow away from sewers prone to wet weather overflow. The Diversion will cease with the completion of the Eagle Rock Interceptor Sewer. Long-term relief is being addressed in the IRP. The GBIS and NEIS Phase II will provide relief to this sewer. The 16 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 3: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 75% No. 21 22 23 MH No. Location 55802143 4TH AV W/S 75' N/O SLAUSON AV 51815096 ADAMS BL AT BURNSIDE AV (NORTH) 46713275 S.F. RD E/S 2ND MH S/O ELM ST. Size (in.) d/D 75 82% 21 81% 18 78% 24 55806046 ALLEY E/O VAN NESS AV 30' S/O 59TH ST 39 77% 25 46816021 NEWELL ST. 250' NE/O BLAKE AV 53410035 VICTORIA AV @ BUTLER AV 24 76% 36 75% 26 Planned/Proposed Action draft EIR for the IRP, which will address GBIS and NEIS Phase II, will be out for public review by the end of the year. The construction of the Slauson/Florence Diversion to COS will provide relief for this sewer. Currently in Bid & Award process. The Adams Blvd Relief Sewer project will provide relief for this sewer. Currently in Design. The Eagle Rock Interceptor Sewer (ERIS) will provide relief to this sewer. ERIS is currently in construction and scheduled for completion in spring 2006. Debris in the sewer contributes to high d/D. The Florence Avenue Sewer Rehabilitation/Replacement project will be built to replace the sewer. Ultimate relief will be addressed by the Vermont Relief Sewer ECIS-Slauson and Vermont Relief Sewer Flor-Slauson. The ERIS will provide relief to this sewer. ERIS is currently in construction and scheduled for completion in spring 2006. Maintenance issue. The WLAIS MH Addition will provide new MH and will clean the WLAIS System. Projected future flow does not indicate any need for future relief. After the WLAIS System is cleaned future capacity needs will be evaluated. Notes: in. = inches d/D = measured depth of flow (in.)/pipe Diameter (in.) MH No. = Maintenance Hole Number PDWF = Peak Dry Weather Flow 17 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 4: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 50% But Less Than or Equal to 75% No. MH No. 1 2 3 53410035 35809050 53602139 4 5 55807098 53603048 6 53401147 7 39515015 8 9 55812135 49401178 10 53503180 11 51816109 12 38809101 13 14 55706031 39212013 15 39913010 16 17 18 55803144 49307156 49204111 19 51716017 20 51807118 21 53604056 22 46812095 23 51810122 Location VICTORIA AV @ BUTLER AV FOX ST AT OMELVEN AV ARLINGTON AV E/S 175'S/O 36TH ST WESTERN AV AT GAGE AV JEFFERSON BL S/S E/O GRAMERCY PL NATIONAL BLVD., 200' E/O BARRINGTON SHERMAN WAY N/S 300' W/O ASMAN AV VERMONT AV E/S AT 75TH ST LOCKWOOD AV 350' E/O VIRGIL AV LA BREA AV W/O W/PL 729' N/O RODEO RD ADAMS BL S/S AT PALM GROVE AV WOODMAN AV E/S (IN PKWY) 600' S/O TERRA BELLA ST AVALON BL AT 59TH ST NE/MH PLUMMER ST. S/S 25' S/O CL 50' E/O HANNA AV SHERMAN WY 650' W/O HAZELTINE AV NORMANDIE AV AT 58TH ST MAPLEWOOD AV AT HOBART BL VISTA ST W/S 235' S/O ROMAIN ST (E & W MHS) 22ND ST N/S 50' E/O RAYMOND AV GENESEE AV. 144' S/O PICO BLVD JEFFERSON BL 12' S/O CL 1ST MH E/O CATALINA ST EAGLE ROCK BL. E/S 110' S/O AVE 30 CL PROJECTED STEARNS DR AT GUTHERIE AV Size (in.) d/D 36 18 30 75% 73% 73% 18 20 73% 73% 24 73% 24 72% 27 15 72% 71% 54 70% 15 70% 21 69% 18 18 69% 68% 27 68% 16 16 42 68% 67% 67% 18 67% 78 67% 14 67% 24 66% 39 66% 18 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 4: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 50% But Less Than or Equal to 75% No. MH No. 24 25 26 27 55802170 55709117 61311104 42701116 28 29 30 61314067 56104084 49513076 31 51713017 32 53401133 33 34 49216010 49208011 35 51814202 36 39510064 37 49413010 38 53407095 39 51712108 40 41 42 43 53803144 56107230 51814134 51805019 44 39808045 45 46 53603058 51805082 47 55701114 Location SLAUSON AV AT CIMARRON ST 74TH ST 1ST MH E/O HOOVER ST D ST 210' E/O MCFARLAND ST LANKERSHIM BL. W/S AT HAMLIN ST W/INT. A ST AT MARINE AV ZANJA ST 50' W/O WALNUT AVE GIBBONS ST 475' S/O NORTH MAIN ST. VIRGINIA RD 1ST MH N/O 23RD ST NATIONAL BL 200' E/O BARRINGTON AV MARTEL AV E/S 50' S/O 3RD ST ORANGE DR E/S 320' S/O WILLOUGHBY AV VENICE BL S/S 260' E/O DAUPHIN AV WOODLAKE AV E/S 417' S/O SATICOY ST NORTH CORONDOLET ST AT COUNCIL ST VENICE BL S/S 100' E/O WESTWOOD BL BUDLONG AV W/S AT 20TH ST S/S CONCORD ST AT OPAL ST WASHINGTON ST FAIRFAX AV. 495' S/O SMILEY DR SHENANDOAH ST E/S 3RD MH S/O PICO BL. VAN NUYS BL 330' N/O BLYTHE ST JEFFERSON BL AT BRIGHTON AV SHENANDOAH ST E/S 90' S/O PICKFORD ST BROADWAY AT 58TH ST Size (in.) d/D 42 36 16 15 66% 66% 66% 65% 18 18 24 65% 64% 64% 15 63% 30 63% 72 18 63% 63% 24 63% 15 63% 15 63% 60 62% 15 62% 14 42 98.5 33 62% 62% 62% 62% 15 62% 18 33 62% 61% 16 61% 19 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 4: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 50% But Less Than or Equal to 75% No. MH No. 48 49 50 55710098 53614020 49513015 51 51812090 52 56007001 53 54 49316080 49510098 55 56 57 53203036 55702109 52115200 58 46812105 59 51814020 60 61 44202135 56108008 62 63 49509071 51810137 64 49311066 65 49204019 66 67 68 51703076 51509057 51814132 69 70 71 56007106 51803032 49210068 Location Size (in.) d/D AVALON BL E/S N/O 71ST ST 4TH AV 50' S/O VERNON AV AVE 17 CL N/O ALBION ST. E/S 21 75 54 61% 61% 61% ORANGE DR 5' W/O CL ALLEY S/O WASHINGTON BL HAVELOCK AV 200' W/O MARSHALL DR VERMONT AV S/O 4TH ST NORTH BROADWAY AT SICHEL ST. PCH @ 200" W/O ENTRADA DR MAIN ST AT 58TH ST PCH W/S 336' N/O OLD PUMP PLANT EAGLE ROCK BL. W/S 350' S/O AVE 30 WASHINGTON BL N/S 30' SW/O FWY OFFRAMP CL MILBANK ST AT MAMMOTH AV ALLEY N/O HAYWRD ST AT MARR ST AVE 18 220' S/O PASADENA AV. GENESEE AVE W/S 2ND MH S/O VENICE BL WESTERN AV 1ST MH S/O BEVERLY BL ORANGE DR E/S AT 320' S/O FOUNTAIN AV IROLO ST 225' S/O 7TH ST MISSION BL. AT 4TH ST. SMILEY DR 1ST MH E/O CLYDE AV RANDALL ST AT BEATRICE ST. 8TH ST W/O SIERRA BONITA AV LA CIENEGA BL W/S 2ND MH S/O BEVERLY BL 45 60% 24 60% 20 15 60% 60% 42 16 30 59% 59% 59% 18 59% 15 59% 18 24 59% 59% 24 84 59% 58% 14 58% 15 58% 20 48 15 58% 58% 58% 27 78 18 58% 57% 57% 20 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 4: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 50% But Less Than or Equal to 75% No. MH No. 72 73 49505104 39611031 74 53602042 75 76 43008001 49308082 77 39713166 78 79 80 42710069 49503014 52016161 81 82 83 53604022 42815021 49505067 84 85 86 87 88 49214055 42715053 38805133 39913052 42813007 89 55702119 90 51608130 91 52016164 92 93 94 95 53613008 53609063 56102019 56003108 Location Size (in.) d/D S.F. RD E/S 300' N/O HURON ST SATICOY ST N/S 270' W/O OSO AV ARLINGTON AV E/S 175'S/O 30TH ST 24 15 57% 57% 24 57% LOUISE AV 195' S/O VICTORY BL NEW HAMPSHIRE AV W/S 400' W/O MELROSE AV CREBS AND VANOWEN 450' UPSTREAM OF 397-13-169. TUJUNGA AV E/S AT COLLINS AV AVE 43 500' SE/O FIGUEROA ST. AMHERST AV AT ALLEY N/O PICO BL VERMONT AV E/S AT 30TH ST CHANDLER BL AT ETHEL AV S.F. RD W/S AT 400' N/O HURON ST. SAN VINCENTE BL AT 6TH ST BILOXI AV PIERCE ST 330' SW/O VARNA AV HAZELTINE AV E/S AT GAULT ST CHANDLER BL 10' S/O N/RDWY AT CALHOUN AV AVALON BL E/S 250' N/O SLAUSON AV LOS ANGELES ST E/S 100' S/O 3RD ST GRANVILLE AV E/S 2ND MH S/O CLAYRES AV VERNON AV 75' E/O 11TH AV BRONSON AV 150' S/O 41ST ST MAIN ST 244' N/O SUNSET AV HAVELOCK AV 218' E/O LINDBLADE DR 18 24 57% 56% 36 56% 15 21 24 56% 56% 56% 14 48 14 56% 55% 55% 21 27 21 24 42 54% 54% 54% 54% 54% 18 54% 36 54% 30 53% 66 66 48 15 53% 53% 53% 53% 21 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 4: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 50% But Less Than or Equal to 75% No. MH No. 96 46707081 97 39513114 98 51814001 99 51704174 100 101 51613046 44307150 102 103 104 105 106 49316104 61306052 51704146 53703007 51805165 107 38805021 108 51705024 109 44305264 110 42813015 111 44305072 112 53602148 113 56504042 114 51813160 115 116 117 118 51601061 49514040 49506084 51806094 Location AVE 50 W/S 230' S/O MENDOTA AV. VANOWEN ST 16' N/O CL 390' E/O SHELTONDALE AV LA CIENEGA BL W/S 400' N/O VENICE BL NORMANDIE AV W/S 30' N/O SAN MARINO ST UNION AV W/S AT 23RD ST LANKERSHIM BL 320' N/O VALLEY SPRING LANE BERENDO ST S/O 5TH ST GULF AV 300' S/O M ST 9TH ST AND BERENDO GRIFFITH AV AT 15TH ST SHENANDOAH ST E/S 460' N/O 18TH ST PIERCE ST BTWN STANWIN AV AND ARLETA AV 11TH ST 8' S/O CL 1ST MH E/O LUCERNE BL VALLEY SPRING LN N/S 25' E/O BECK AV CHANDLER BL 10' S/O N/RDWY 430' W/O RANCHITO AV WOODBRIDGE ST 150 FT W/O RADFORD AVE ARLINGTON AV W/S 75' S/O 36TH PL VERMONT AV E/S 1ST MH N/O MANCHESTER AV SHENANDOAH ST W/S 130' N/O OLIN ST HOOVER ST AT LEEWARD AV AVE 17 AT MOZART ST AVE 33 AT POST ST CRESCENT HEIGHTS BL E/S @ SATURN ST Size (in.) d/D 12 53% 18 53% 18 53% 27 53% 20 24 53% 53% 20 18 18 40 42 52% 52% 52% 52% 52% 18 52% 45 51% 48 51% 54 51% 48 51% 42 51% 27 51% 48 51% 20 20 16 21 51% 51% 51% 51% 22 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 4: Gauging Locations with Peak Dry Weather Flow d/D Greater Than 50% But Less Than or Equal to 75% No. MH No. 119 120 56102092 44307151 Location BROOKS AV 150' W/O PACIFIC AV CAHUENGA BL 260' N/O VALLEY SPRING LN Size (in.) d/D 15 18 51% 51% Notes: in. = inches d/D = measured depth of flow (in.)/pipe Diameter (in.) MH No. = Maintenance Hole Number PDWF = Peak Dry Weather Flow e. Wastewater Capital Improvements The City expended $225 million in wastewater capital improvement in FY 2004-05, of which $130 million (58 percent) was for collection system improvements. For FY 2005-06, the projected total wastewater capital improvement expenditure is $280.5 million with $160 million (57 percent) designated for the collection system. For the next ten years (FYs 2005-06 through 2014-15), the projected total expenditure is $3.5 billion with $2.7 billion (77 percent) designated for the collection system. A complete copy of the latest 10-Year Wastewater Capital Improvements Program is available at http://www.lacitysan.org/fmd/WCIPBook05-06.pdf. A summary of the Program is provided as Attachment “A” to this Annual Report. f. Sewer Cleaning A summary of the sewer cleaning program progress is provided in Table 5 and Figure 1 below. As shown, the City complied with all requirements for Year One and exceeded the mandated cleaning of 60,000 pipe reaches by more than 22,000 reaches. Per the provisions of the CSSA, the City is allowed to “bank” the excess pipe reaches cleaned over the required 60,000 pipe reaches. The banked reaches can be used in the future to augment the quantity of sewer cleaning performed if it falls below the required 60,000 pipe reaches. The City is proposing to “bank” 22,030 pipe reaches. 23 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 5: Fiscal Year 2004-05 Sewer Cleaning Data 60,000 2,600 Miles (approx.) Number or Length of Pipe Reaches Completed 82,030 3,699 Miles Not Applicable 22,030 35,000 60,873 Not Applicable 2,745 Miles CSSA Requirement for Year One Compliance Item Number of Pipe Reaches Length of Pipe Reaches Proposed Number of Pipe Reaches Banked Number of Hot Spot Pipe Reaches Cleaned Length of Hot Spot Pipe Reaches Figure 1: Sewer Cleaning Progress 90,000 82,030 80,000 30,000 20,000 10,000 35,000 Completed by City 40,000 Required by CSSA 50,000 60,873 Completed by City 60,000 60,000 Required by CSSA No. of Pipes Cleaned 70,000 0 Total No. of Pipe Reaches Cleaned No. of Hot Spot Pipes Cleaned The City continues to review its sewer maintenance efforts and to adjust the sewer cleaning schedule and cleaning frequencies accordingly. As a result, cleaning goals are established on 24 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 an annual basis to meet revised cleaning needs. The following is an estimated breakdown of the sewer cleaning for FY 2005-06: • Total Pipe Reaches to be Cleaned as required in the CSSA: 60,000 pipes. However, the City has established an internal goal for cleaning of 90,000 pipe reaches. • Total Hot Spot Pipe Reaches to be Cleaned as required in the CSSA: 35,000 pipes. However, the City has established an internal goal for hot spot cleaning of 60,000 pipe reaches. g. Sewer Line Television Assessment – Mileage A summary of the sewer line television assessment is provided in Table 6 below. As shown in Figure 2, the City complied with the requirement of the CSSA, exceeding the mandated inspection goal of 600 miles of pipe by 221 miles. Per the CSSA, the City is allowed to “bank” a percentage of the excess amount over 600 miles to be used in the future to augment the quantity of sewer line television assessment performed if it falls below the 600-mile requirement. The percentage of excess that can be banked is equal to the miles of pipe assessed for the first time divided by the total miles of pipe assessed. The City is proposing to “bank” 196 miles. Table 6: Television Assessment Overview Compliance Item Sewer Pipes Inspected Sewer Pipes Inspected for the First Time Sewer Pipe Inspected for the First Time As Percentage of Total Inspected Inspected Sewer Pipes Proposed to Be Banked CSSA Requirement for Year One 600 Miles Completed in Year One 821 Miles Not Applicable 728 Miles Not Applicable 87% Not Applicable 196* Miles Note: * {196 miles = (821miles – 600 miles)*(87%)} 25 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Figure 2: Sewer Line Television Assessment Progress 900 821 800 700 Completed by City 500 Required by CSSA Miles of Pipe 600 600 400 300 200 100 0 Miles of Sewer Pipe Assessed h. Sewer Line Television Assessment – Condition Ratings A summary of the sewer line television assessment findings is provided in Table 6 and Figure 3 below. As shown, 87% of the pipe assessed was found to be condition rating “C” or better. Table 7: Condition Assessment Results Condition Rating Condition Description A B C D E Total Very Good Good Fair Poor Emergency Pipe Assessed for the First-Time (Miles) Total Pipe Assessed (Miles) Percent of Total 100 323 213 79 13 728 110 363 246 86 16 821 13% 44% 30% 11% 2% 100% 26 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Figure 3: Condition Assessment Results 400 363 350 No. of Miles 300 246 250 200 150 110 86 100 50 16 0 A B C D E Condition Ratings Condition “E” sewers are referred to the Bureau of Engineering for immediate emergency repair. In FY 2004-05, 514 emergency sewer work requests were authorized and completed, requiring more than $20 million. This is equivalent to approximately 12 miles of sewers repaired during FY 2004-05. Projects to repair, rehabilitate, and/or replace Condition “D” sewers are scoped and then placed in the City’s Wastewater Capital Improvements Program. i. Fats, Oils, and Grease (FOG) Control Program. As summarized in Table 8 below, the City continues to implement its FOG Standard Operating Procedures (SOPs) and Enforcement Response Plan and Enforcement Response Guide (ERP/ERG). These procedures include permitting of FSEs, investigating referrals from Wastewater Collection System Division (WCSD), and taking enforcement actions against noncompliance. The ERP/ERG includes activities such as issuing Notices of Violation (NOVs), taking enforcement actions, and requiring grease interceptor installations. Table 8: Summary of FOG Program Results Summary of Weekly FOG Reports CSSA Summary FY 04-05 Permitted Food Service Establishment (FSE) as of 7/1/2004 FSEs Inspected - Annual Inspections Conducted Total for FY 04-05 7,832 7,832 27 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 8: Summary of FOG Program Results Summary of Weekly FOG Reports % Completed Total for FY 04-05 100 Inspection Activity Summary Total Inspections of FSEs 15,002 Notice of Violation (NOV) Activity Summary Total NOVs Issued NOVs Forwarded for Enforcement 944 462 Enforcement Case Summary Active Cases as of 6/30/2005 Completed Cases Total Enforcement Cases Processed 106 462 568 Wastewater Collections System Division (WCSD) Referrals Summary Received 142 Investigated 142 FSEs Identified as Source of FOG Blockage – See Table I.2 0 FSEs Issued NOV during Investigation – See Table I.2 11 FSEs with an Enforcement Case – See Table I.2 4 FSEs Ordered to Install Grease Interceptor – See Table I.2 1 Conditional Waivers Processed Granted Revoked Denied 0 0 0 Modifications to the SOPs, ERP/ERG, and implementation of Conditional Waivers were pending Government Plaintiffs’ approval of implementation plans presented in "The FOG Report," as required by Paragraph 59 of the CSSA, and submitted to the Plaintiffs on April 22, 2005. The approval was granted on September 29, 2005. One of the SOPs that the City implements as part of the FOG Control Program is that of conducting a field investigation of each referral from WCSD. When an investigation reveals noncompliance with the FOG Ordinance, the City activates its ERP/ERG. Table 9 identifies the City’s ERP/ERG activities resulting from field investigations of WCSD referrals and names the FSEs affected. 28 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 9: Referral Investigation Summary FSEs Identified as Source of FOG Blockage None FSEs Issued Notice of Violation (NOV) During Investigation 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Acapulco Restaurant #53, 750 Sampson Way, San Pedro BBQ Unlimited, 12980 Sherman Way, North Hollywood Fay’s Foods, 10650 Burbank Blvd., North Hollywood Flores Meat Market, 1200 W. Anaheim St., Wilmington Hop Li Sea Food, 10974 W. Pico, Los Angeles Jack in the Box #292, 4210 Crenshaw Blvd., Los Angeles KFC #x610126, 8515 S. Central Ave., Los Angeles La Perla Blanca Seafood, 5400 S. Avalon Blvd., Los Angeles M & M Soul Foods, 3552 W. Martin Luther King Jr. Blvd., Los Angeles Mount Carmel Treatment Center, 801 W. 70th St. Los Angeles Tommy’s Burgers #1, 137 E. Anaheim St., Wilmington FSEs with an Enforcement Case 1. 2. 3. 4. Hop Li Sea Food, 10974 W. Pico, Los Angeles BBQ Unlimited, 12980 Sherman Way, North Hollywood M & M Soul Foods, 3552 W. Martin Luther King Jr. Blvd., Los Angeles KFC #x610126, 8515 S. Central Ave., Los Angeles FSEs Ordered to Install Grease Interceptor 1. KFC #x610126, 8515 S. Central Ave., Los Angeles Since the inception of the FOG Control Program in 2001 and the enhanced sewer cleaning and public outreach, FOG-caused SSOs were reduced by over 80 percent, as shown in Figure 4. 29 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Figure 4: FOG-Related SSOs by Fiscal Year 300 290 # of FOG-Related Spills 250 200 197 Baseline Year 174 150 32% Reduction from Baseline Year 100 117 40% Reduction from Baseline Year 50 60% Reduction from Baseline Year 79% Reduction from Baseline Year 62 0 2000-01 2001-02 2002-03 2003-04 2004-05 Fiscal Year j. Primary and Secondary Basin Plans The CSSA requires completion of all 25 Primary Sewer Plans by the end of Year Five. Eight plans are currently in progress, including the Lincoln Heights Primary Sewer Plan, which is 95 percent complete. The remaining seven plans are all more than 50 percent complete. The City has prepared a completion plan and schedule for the Primary Sewer Basin Plans. A summary of the current status of each is provided in Table 10. A map showing the locations of the 25 basins is provided as Figure 5. Table 10: Status of Primary Sewer Plans Primary Sewer Plan Projected Completion Date November 2005 95% Complete January 2006 80% Complete March 2006 80% Complete 4. Tarzana Primary Sewer Plan April 2006 75% Complete 5. Baldwin Hills Primary Sewer Plan June 2006 75% Complete 1. Lincoln Heights Primary Sewer Plan 2. Venice Primary Sewer Plan 3. Northridge Primary Sewer Plan Current Status 30 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 10: Status of Primary Sewer Plans Primary Sewer Plan Projected Completion Date June 2006 75% Complete 7. Central City Primary Sewer Plan July 2006 50% Complete 8. NOHO Primary Sewer Plan July 2006 50% Complete 6. Granada Hills Primary Sewer Plan Current Status 9. Highland Park Primary Sewer Plan September 2006 Scheduled for future years. 10. Wilshire Primary Sewer Plan December 2006 Scheduled for future years. 11. CBD Primary Sewer Plan March 2007 Scheduled for future years. 12. Boyle Heights Primary Sewer Plan March 2007 Scheduled for future years. 13. West LA Primary Sewer Plan March 2007 Scheduled for future years. 14. Hollywood Primary Sewer Plan March 2007 Scheduled for future years. 15. N.E. Wilshire Primary Sewer Plan March 2007 Scheduled for future years. May 2007 Scheduled for future years. 17. Encino Primary Sewer Plan December 2007 Scheduled for future years. 18. Pacoima Primary Sewer Plan February 2008 Scheduled for future years. 19. Westchester Primary Sewer Plan 16. South LA Primary Sewer Plan February 2008 Scheduled for future years. 20. Brentwood Primary Sewer Plan March 2008 Scheduled for future years. 21. Wilmington Primary Sewer Plan March 2008 Scheduled for future years. 22. San Pedro Primary Sewer Plan March 2008 Scheduled for future years. May 2008 Scheduled for future years. December 2008 Scheduled for future years. March 2009 Scheduled for future years. 23. Woodland Hills Primary Sewer Plan 24. Van Nuys Primary Sewer Plan 25. Chatsworth Primary Sewer Plan 31 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) 32 Granada Hills/ Van Nuys/ Mission Hills Sylmar 75% 118 Chatsworth Pacoima Northridge North Hollywood/Sunland 405 80% 50% 210 Woodland Hills/ Canoga Park Tarzana 80% 5 170 Northeast Los Angeles/ Burbank/Glendale 101 134 Encino/Studio City 101 210 134 Griffith Park 2 110 Hollywood Brentwood/ Pacific Palisades 101 Northeast Wilshire 405 West Los Angeles Baldwin Hills 75% 1 Wilshire 5 Lincoln Heights 95% Silverlake/ Central City North 10 110 10 Central Business Boyle Heights 5 Venice Primary Basin Plans in Progress 80% South Los Angeles 90 710 Westchester 105 Baldwin Hills (78%) Granada Hills/Mission Hills (75%) North Hollywood/Sunland (50%) Northridge (80%) 91 Tarzana (80%) Venice (80%) Lincoln Heights (95%) 110 Figure 5 405 GIS Group Wastewater Engineering Services Divsion Bureau of Sanitation City of Los Angeles Created September 14, 2005 0 1 2 4 6 Wilmington San Pedro 8 Miles S:\gisunit\bprojects\sewershedmaps\status\PrimaryPlanningStatus.mxd Thomas Bros Data reproduced with permission granted by THOMAS BROS MAP Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) 34 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 The CSSA requires Secondary Basin Plans for the 100 highest priority basins to be completed by the end of Year Ten of the CSSA. To date, a total of nine Secondary Basin Plans have been completed, as shown in Table 11. Current projections are to complete an additional 12 Plans by the end of FY 2005-06. Figure 6 shows the locations of the secondary basins with completed Plans. Table 11: Completed Secondary Basin Plans Plan Name Secondary Sewer Basin Plan for Basin S02 Secondary Sewer Basin Plan for Basin H27 Secondary Sewer Basin Plan for Basin C04 Secondary Sewer Basin Plan for Basin U04 Secondary Sewer Basin Plan for Basin P03 Secondary Sewer Basin Plan for Basin H30 Secondary Sewer Basin Plan for Basin H32 Secondary Sewer Basin Plan for Basin H28 Secondary Sewer Basin Plan for Basin A02 Completion Date Sewer Miles in Basin Sewer Miles Identified for Renewal 5/11/05 40.3 5.2 5/24/05 27.7 6.8 5/25/05 9.1 3.4 5/27/05 20.6 5.5 7/6/05 14.5 4.4 8/3/05 45.1 10.7 8/10/05 24.3 9.5 9/21/05 39.0 17.0 9/28/05 44.1 9.8 35 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) 36 ANTELOPE VALLEY FRWY FO O TH L IL W FR Y 118 O G LD EN E AT ST 405 W FR Y 210 N VE TU F RA RW Y GL EN DA LE FRW Y 5 170 101 134 210 134 101 2 H28 H27 N AD E PA S H32 H30 HO L 405 LY W 5 N SA OO DF 101 RW Y S PA AD EN A W FR DI O EG W FR Y U04 A02 1 N SA TA MO N IC AF Y P03 O PO M RW Y RW Y NA F 60 N SA TA O EG A Y 710 W FR Y HARBOR FRWY AN W FR 90 POM ONA FRW Y 5 S02 DI C04 SA N 10 110 10 110 FRW Y SAN TA MON ICA WY A FR N SA TA AN A W FR 105 HF RW BE A C 91 ARTESIA FRWY LO N G HARBOR FRWY ARTESIA FRWY 110 LONG BEACH FRWY A02 C04 H27 H28 H30 H32 Figure 6 P03 S02 U04 605 Y Secondary Sewershed Plans Completed SAN GABRIEL RIVER FRWY Y GLENN M ANDERSON FWY & TRANSIT GIS Group Wastewater Engineering Services Division Bureau of Sanitation City of Los Angeles Created September 14, 2005 0 1 2 4 6 8 Miles S:\gisunit\bprojects\sewershedmaps\SecondaryPlanngStatusAsize.mxd Thomas Bros Data reproduced with permission granted by THOMAS BROS MAP 405 605 FRWY Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) 38 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 k. MOUSE Model As requested, “R” factors for all MOUSE model basins were developed based on historical rainfall and sewer flow data. A report on the “R” factors was submitted on April 29, 2005. The City will continue its wet-weather calibration and validation of the “R” factors as additional data is collected. l. Chemical Root Control The City continues its proactive root control program. A total of 11,608 pipes or 474 miles of root-infested sewers were chemically treated with root inhibitors. As shown in Figure 7, this corresponds to more than 3 times the CSSA requirement of 150 miles per year. Over the last two years alone, sewer overflows caused by roots were reduced by 53 percent (Figure 8). Figure 7: Root Control Progress 474 500 450 400 Miles of Pipe 350 300 250 200 150 Completed by City 150 100 50 Required by CSSA 0 Miles of Pipe Treated with Root-Control Chemicals 39 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Figure 8: Root-Caused SSOs 350 # of Root-Related SSOs 300 290 234 250 200 First Year of Root Control Program 19% Reduction from First Year of Program 150 100 137 53% Reduction from First Year of Program 50 0 2002-03 2003-04 2004-05 Fiscal Year m. Significant Program Implementation A summary of other significant program modifications and achievements made during the FY 2004-05 that affect compliance with the CSSA requirements is provided herein. - On February 2, 2005, following an extensive public outreach campaign that included more than 1.5 million notices and 60 community meetings to inform the public about the CSSA and the necessary rate increase, the City Council authorized the necessary sewer rate increase over the next five years to provide the necessary resources. - On June 7, 2005, the City Council authorized an additional 21 staff to support the implementation of the CSSA in the Bureaus of Engineering and Sanitation. - Representatives from the Department of Public Works and other City offices continue to meet monthly as part of the Settlement Agreement Committee (SAC) to review and track progress and coordinate activities. Quarterly updates are given to the Board of Public Works. - The City is currently launching a root control outreach and education program for private properties. The focus will be on areas where private laterals are prone to root intrusion and as evidenced by sewer television inspection. - The City has implemented state-of-the-art field automation of our sewer maintenance trucks (FAST). All maintenance equipment is now equipped with an on-board computer with sewer information, work orders, etc. This has facilitated and streamlined work, as 40 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 evidenced by a reduction in response time and increased productivity demonstrated by the sewer maintenance crews. - In an effort to improve communications and facilitate the timely completion of the CSSA deliverables, the City’s Bureau of Contract Administration is reorganizing its sewer construction inspection staff. The plan will move sewer projects currently managed by three divisions and combine them under one division – the Wastewater Construction Division. The Emergency Sewer Repair Group was transferred to the Wastewater Construction Division. - In an effort to ensure the availability of adequate resources in the construction community, the City is working closely with the Engineering Contractors Association (ECA), which represents many of the sewer contractors in the area. The ECA contractors felt confident that they could deliver the anticipated sewer repair and rehabilitation workload. The City and ECA agreed to meet on a semi-annual basis to review progress and coordinate activities. - The City is currently evaluating various options to streamline the contracting process to expedite the bid and award of projects, including pre-qualification of contractors that will be bidding on sewer projects. - The City’s Bureau of Engineering has undergone necessary reorganization to accommodate the construction of the CSSA-required projects. A new construction division named the Wastewater Conveyance Construction Division (WCCD) was created and staffed for the construction management of sewer projects. - The City’s Bureau of Engineering has implemented a design tool called the Sewer Management Automated Repair Tracking System (SMARTS). SMARTS functions as a one-stop shop of information for Secondary Sewer Renewal Program (SSRP) engineers, using mapping resources and GIS technology to help engineers deliver design projects faster, more accurately, and more efficiently. SMARTS allows sewer information to be rendered on top of City base map components like parcels, streets, and freeways to better represent the location of damaged pipe. In addition, SMARTS renders data relating to condition assessment, sewer wyes, storm drains, substructures, aerial photographs, and existing projects to help engineers identify other factors critical to the sewer repair. n. Failure to Comply Projects The City has complied with all requirements of the CSSA for Year One. o. Odor Outreach Plan As required by Section V-G (Paragraphs 34 and 36) of the CSSA, the City is required to update the Odor Outreach Plan for advertising the Sewer Odor Hotline and report progress on the implementation of the updated Odor Outreach Plan. A summary of the progress to date is provided herein. The Draft Odor Hotline Publicity Outreach Plan, hereafter referred to as the Draft Outreach Plan, was developed and copies were provided to the Odor Advisory Board. The Odor Advisory Board input and comments as stated in the Board’s meeting minutes over the last 41 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 two years were reviewed and incorporated into the Draft Outreach Plan. The Draft Outreach Plan was presented to the Odor Advisory Board at its meeting of March 14, 2005. The issue of effective outreach was discussed at length and the Board’s comments were incorporated. The Final Odor Hotline Publicity Outreach Plan was submitted on April 27, 2005. The City designed magnets and flyers that include updated contact and reporting procedures for both 3-1-1 and the Odor Hotline in both English and Spanish. The City ordered and received 1,500 magnets and is printing 5,000 flyers for distribution starting in October 2005. Meanwhile, the City is using various outreach materials that contain Odor Hotline information to inform the residents at many public events or meetings, including the following: - Boyle Heights 3rd Annual Resource Fair Southeast LA Awareness Walk Community Outreach Event Film Arts Community Outreach Event 2004 Coastal Bay Clean-up Event Solid Resources Collection North Central Yard Open House Event Solid Resources Collection South LA Yard Open House Event Solid Resources Collection West LA Yard Open House Event Neighborhood Clean Up event at Green Meadow Recreation Center Studio City Residents Association Presentation on the City of Los Angeles’ Odor Control Effort Winnetka Neighborhood Council-Public Works Committee Tarzana Neighborhood Council Meeting Coastal San Pedro Neighborhood Council Meeting p. Odor Control Facilities Construction Progress A summary of the construction status of the odor control facilities is provided in Table 12. 42 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 12: Construction Status of Odor Control Facilities Shaded items indicate completed projects. CSSA Construction End Date Completed? (Yes or No) Project Status 5/23/08 No On Schedule Mission & Jesse No On Schedule Design is 75% complete. 23rd & San Pedro No On Schedule Design is 100% complete. Currently In bid and award. Jefferson Siphon No On Schedule Design is 90% complete. NORS Connection No On Schedule Design is 90% complete. No On Schedule No On Schedule No On Schedule Humboldt No On Schedule Design is 60% complete. Richmond No On Schedule Design is 60% complete. Yes Completed Yes Completed Yes Completed 8/26/04 Completed 1 day ahead of schedule. 23 & San Pedro Yes Completed 8/26/04 Completed 1 day ahead of schedule. Jefferson Siphon Yes Completed 8/26/04 Completed 1 day ahead of schedule. Project Title Air Treatment Facility (ATF) – ECIS/NORS ATF – NCOS 5/23/08 Jefferson & Rodeo ATF – NEIS 3/26/09 Interim Carbon Scrubber – NCOS Interim Carbon Scrubber – ECIS/NORS Mission & Jesse rd 8/27/04 Comments Design is 100% complete. Currently In bid and award. 43 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 12: Construction Status of Odor Control Facilities Shaded items indicate completed projects. CSSA Construction End Date Completed? (Yes or No) Project Status Yes Completed 8/27/04 No On Schedule An additional carbon scrubber was installed at the Division Street site and placed in service on May 27, 2005. Humboldt No On Schedule Construction is 70% complete. Richmond No On Schedule Construction is 70% complete. Project Title NORS Connection Interim Carbon Scrubber – NEIS 10/30/06 Comments Completed 1 day ahead of schedule. 44 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 q. Independent Review of the Sewer Odor Control Program The Final Report prepared by the designated independent review consultant issued in March 2004 included 16 recommendations in section 9.2 of the report. The City prepared the Draft “Responses to the Recommendations from Independent Review of the City of Los Angeles’s Sewer Odor Control Program.” The responses were presented to the Odor Advisory Board at its meeting of March 14, 2005. These recommendations were discussed at length at the meeting and the Board’s comments were incorporated into the Final Report issued on April 27, 2005. Table 13 provides the status of the 16 recommendations from the independent consultant report. Table 13: Summary and Status of Independent Review Recommendations Number 1 2 3 4 5 6 7 Recommendation Status Conduct “before and after” monitoring of headspace pressures in both the north and south branches of the NOS. If headspace pressures in the “Maze” NOS are not sufficiently reduced to prevent widespread odor releases, proceed with the siting and design of air extraction/treatment systems. COMPLETED - “Before and after” ECIS on line pressure tests were conducted between April and October 2004. NEEDS FURTHER EVALUATION - After the construction of “Slauson/VanNess/COS External Bypass” project, the City will conduct another pressure test in the S. Maze. Based on results of the testing, the City will decide whether the odor releases have been controlled or if further action is required. NOT APPLICABLE - The City proceeds with the application of magnesium hydroxide; therefore, testing is not needed. Proceed with the full scale testing of continuous magnesium hydroxide addition to reduce the intensity of odors emitted from the south branch of the NOS. Increase the design air flows for ATFs Monitor wastewater characteristics and headspace H2S and pressure levels in major interceptors outside the “Maze.” Expand the odor hotline and complaint database to all areas of the City. Evaluate the feasibility of routing all odor complaints through the odor hotline. COMPLETED. COMPLETED. COMPLETED. COMPLETED. 45 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 13: Summary and Status of Independent Review Recommendations Number Recommendation Status 8 Maintain a sewer odor advisory board with representatives from various sectors of the City affected by sewer odors. 9 The Odor Advisory Board should prepare a report that summarizes its accomplishments, conclusions, and recommendations. Strive to become a center of excellence in the field of sulfide odor and corrosion research, working with local universities, experts in the field, and such organizations as the Water Environment Research Foundation. ONGOING - During FY 2004-05, the Odor Advisory Board conducted five meetings on Nov. 8 and Dec. 12, 2004; and Jan. 10, Mar. 14, and May 9, 2005. NOT APPLICABLE TO THE CITY. 10 11 Meet regularly with County Sanitation Districts of Los Angeles County and the Orange County Sanitation District. 12 Change the design criteria of the Sewer Design Manual to flow 50 percent full. Research the adequacy of current design guidelines for air jumpers. 13 The City continues to work with experts in the odor field. In April 2004, the City presented the topic “Los Angeles Selects Bio-Trickling/ Activated Carbon for Collection System” at the Water Environment Federation/Air & Wastewater Management Association (WEF/WMA). The presentation was subsequently selected as one of the best at this conference and the City was invited to be on the panel for the American Water Works Association Conference in June 2004. The City is also joining CH2MHill in proposing to support the Water Environment Research Foundation research project, “Prevention and Minimization of Odors and Related Corrosion in Collections Systems”. This project will examine the effectiveness of odor mitigation strategies that have been used to minimize odors and reduce corrosion within collection system. The City prefers to share/exchange information on odor/corrosion control strategies with other agencies, but in the forum of ad hoc meetings and discussions. COMPLETED. The work plan for the siphon air jumpers research will be recommended in the Odor Master Plan. 46 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 13: Summary and Status of Independent Review Recommendations Number 14 15 & 16 Recommendation Status Re-evaluate the design of gas trap maintenance holes. Inventory of the trap maintenance hole structures was conducted. Crew interviews will be conducted to see if there is an existing structure type that the City owns and operates that is more reliable and requires less maintenance than the currently standard design in use. COMPLETED. Create an Odor Control Section with adequate staff. r. Annual Supplemental Environmental Projects (SEPs) Status Report As required in Section VIII, Paragraph 94 of the CSSA, the following is a status report on each Supplemental Environmental Project (SEP) for which a SEP Completion Report has not been submitted. The project status and a list of eligible SEP costs for each Tier 1 SEP are provided below in Table 14. In addition, a detailed update on the North Atwater Creek Restoration is provided as Attachment C. 47 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Table 14: Summary of Progress on SEPs Name Project Description Status North Atwater Creek Restoration & Water Quality Enhancement Project Construct water quality improvements to an area along the Los Angeles (LA) River in the vicinity of North Atwater Park. South Los Angeles Storm Water Treatment Project at 54th and Avalon St. Construct an advanced system for capture and treatment of urban runoff. Hazard Creek and Wetlands Restoration Project Restore and enhance a one-half-mile reach of the Hazard Creek corridor and 2.5 acres of wetlands habitat in the Lincoln Heights area of Los Angeles. Address high bacteria levels at Inner Cabrillo Beach. The draft work plan was submitted to the Regional Water Quality Control Board on August 30, 2005 for review prior to proceeding with design. Additional information on this project is provided in Attachment C. The work plan is scheduled for completion in August 2007. The work plan may be expedited based on the availability of additional funding. Seeking community and LARWQCB input to develop project work plan. The work plan is scheduled for completion in March 2006. Awaiting test results of a wave generator machine at Dana Point Harbor to reduce bacteria count in the water. The work plan is scheduled for completion in August 2008. The site has been selected. The work plan is scheduled for completion in August 2009. Inner Cabrillo Beach Pollution Control and Water Circulation Enhancement Project Downtown Los Angeles Storm Drain Low-Flow Diversion Project Construct a storm drain low-flow diversion structure to divert low flow from a storm drain in the Downtown Los Angeles area that discharges to the LA River. Eligible Costs $70,300 None None None None 48 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 ATTACHMENT A WASTEWATER CAPITAL IMPROVEMENT PROGRAM SUMMARY* * The City’s Wastewater Capital Improvement Program (WCIP) is currently undergoing its annual review and update. A complete copy of the City’s current 10-year (FYs 2005-06 through 2014-15) WCIP is available at http://www.lacitysan.org/fmd/WCIPBook05-06.pdf. Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ COLLECTION SYSTEM DONALD C. TILLMAN WATER RECLAMATION PLANT EARTHQUAKE RECOVERY HYPERION TREATMENT PLANT LA-GLENDALE WATER RECLAMATION PLANT PUMPING PLANTS SYSTEMWIDE TERMINAL ISLAND TREATMENT PLANT CATEGORIES: (FISCAL YEARS 2005/06 – 2014/15) PROJECT DESCRIPTIONS AND 10-YEAR EXPENDITURE PLAN CAPITAL IMPROVEMENT PROGRAM WASTEWATER 5TH DISTRICT JACK WEISS 6TH DISTRICT TONY CARDENAS 2ND DISTRICT WENDY GREUEL 3RD DISTRICT DENNIS P. ZINE BOARD OF PUBLIC WORKS 9TH DISTRICT JAN PERRY 8TH DISTRICT BERNARD PARKS 7TH DISTRICT ALEX PADILLA 12TH DISTRICT GREIG SMITH 11TH DISTRICT BILL ROSENDAHL 10TH DISTRICT VACANT ENVIRONMENTAL ENGINEERING DIVISION WASTEWATER CONVEYANCE ENGINEERING DIVISION D.C.TILLMAN WATER RECLAMATION PLANT ENVIRONMENTAL MONITORING DIVISION FINANCIAL MANAGEMENT DIVISION HYPERION TREATMENT PLANT INFORMATION & CONTROL SYSTEMS DIVISION LOS ANGELES-GLENDALE WATER RECLAMATION PLANT TERMINAL ISLAND TREATMENT PLANT WASTEWATER COLLECTION SYSTEMS DIVISION WASTEWATER ENGINEERING SERVICES DIVISION WASTEWATER CONSTRUCTION DIVISION BUREAU OF CONTRACT ADMINISTRATION JOHN L. REAMER, JR. – INSPECTOR OF PUBLIC WORKS BUREAU OF ENGINEERING GARY LEE MOORE, P.E. – CITY ENGINEER 15TH DISTRICT JANICE HAHN 14TH DISTRICT VACANT 13TH DISTRICT ERIC GARCETTI BUREAU OF SANITATION RITA L. ROBINSON – DIRECTOR CYNTHIA M. RUIZ, PRESIDENT DAVID SICKLER, VICE PRESIDENT PAULA A. DANIELS, PRESIDENT PRO-TEM VALERIE LYNNE SHAW, COMMISSIONER YOLANDA FUENTES, COMMISSIONER 4TH DISTRICT TOM LABONGE 1ST DISTRICT ED REYES COUNCIL MEMBERS ANTONIO VILLARAIGOSA MAYOR Page 1 5,618,212 5,737,970 2,898,709 5,477,963 28,366,220 31,805,663 27,853,500 31,805,663 0 18,301,080 31,755,663 0 16,667 9,998,840 0 33,333 12,600,000 31,607,663 0 0 48,520 0 0 0 27,611,663 0 0 0 0 0 July 1, 2005 TOTAL WCIP 280,595,989 346,454,173 377,132,850 375,685,074 430,330,132 420,383,418 425,358,643 346,589,945 265,638,398 252,381,874 13,719,947 5,844,663 0 50,000 10,431,140 0 99,999 16,660,052 13,945,863 13,751,820 513,853 18,372,700 0 666,667 TERMINAL ISLAND TREATMENT PLANT 12,075,532 20,094,180 3,502,707 34,232,129 0 3,539,873 23,102,256 6,816,460 3,371,667 54,349,256 0 3,555,893 SYSTEM WIDE 828,740 4,454,560 92,829,258 4,000,000 10,982,060 5,817,425 2,871,898 69,811,933 10,900,000 42,468,436 PUMPING PLANTS th 10 Year 2014/15 6,337,342 th 9 Year 2013/14 LA-GLENDALE WATER RECLAMATION PLANT th 8 Year 2012/13 38,716,901 th 7 Year 2011/12 HYPERION TREATMENT PLANT th 6 Year 20010/11 18,000,000 th 5 Year 2009/10 EARTHQUAKE (ASRP) th 4 Year 2008/09 37,429,010 rd 3 Year 2007/08 D. C. TILLMAN WATER RECLAMATION PLANT nd 2 Year 2006/07 134,533,003 193,777,687 238,486,437 282,731,445 366,926,931 340,658,315 355,118,341 286,484,362 221,382,215 224,770,211 ST 1 Year 2005/06 COLLECTION SYSTEMS CATEGORY PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION ST 939,860 AVE 45 ARROYO DR RLF SWR Page 3 BEACHWOOD CANYON MH ADDITION BAYWOOD BNDCT ESMT SWR 161,260 1,439,720 97,260 464,000 ASSESSMENT ACT SWRS BALDWIN HILLS AREA SWR REHAB 306,906 0 ARLINGTON RELIEF SEWER APPLE ST RLF SWR 320,000 2,183,000 AIR TREATMENT FAC NORS ALVARADO CRANDALL RLF SWR 400,320 AIR TREATMENT FAC NEIS 4,935,680 787,190 AIR TREATMENT EQUIP BIOTRICK AIR TREATMENT FAC NCOS SIPHON 543,600 ADAMS BL RELIEF SEWER 12,437,720 0 71ST AVALON SWR REHAB AIR TREATMENT FAC ECIS 0 1,016,480 0 29TH CONGRESS RLF SWR 12TH HILL SWR REHAB 9TH BERENDO NORMANDIE SWR RLF 24,100 461,320 4TH SHATTO VERMONT SWR REHAB 6TH ST ABANDN DIV TO NOS 0 1 Year 2005/06 4TH AVENUE SLAUSON SWR REHAB PROJECT TITLE CS PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 369,480 1,120 140,240 12,821,870 464,000 5,680 0 4,918,000 3,741,120 8,093,500 3,713,680 8,842,410 338,620 525,960 0 0 2,053,840 0 124,200 0 331,060 nd 2 Year 2006/07 163,640 0 0 138,120 0 0 495,000 th 4 Year 2008/09 1,292,570 0 1,849,900 17,352,385 464,000 0 0 0 0 0 0 0 0 4,583,215 CS 128,520 0 1,017,620 17,399,890 464,000 0 0 1,814,000 1,918,680 6,637,940 855,400 2,137,830 222,480 14,952,725 157,080 0 0 0 0 0 456,940 rd 3 Year 2007/08 1,847,735 0 10,400 4,949,195 464,000 0 73,360 0 0 0 0 0 0 0 1,368,238 124,920 0 149,720 0 0 8,470,850 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 1,847,735 0 0 0 464,000 0 76,460 0 0 0 0 0 0 0 2,289,042 179,000 0 697,370 0 0 7,702,010 6 Year 20010/11 602,800 0 0 0 464,000 0 867,660 0 0 0 0 0 0 0 9,760 2,290,420 0 1,322,330 0 0 54,880 th 7 Year 2011/12 0 0 0 0 0 0 0 464,000 0 0 0 0 0 0 0 0 0 0 1,388,740 0 45,540 th 8 Year 2012/13 0 0 0 0 0 0 0 0 0 0 960 0 0 0 0 0 0 0 0 0 464,000 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 0 0 0 0 464,000 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY COLLECTION SYSTEM (CS) ST 0 0 CENTRAL AREA CSRP U-6 CENTRAL BUS DST RLF SWR PH-5 6,309,719 EAGLE ROCK INTER SWR 393,440 51,160 FLOW MON REAL TIME & SCADA INT FLOW MON REAL TIME-PILOT STUDY 586,260 HARBOR AREA CSRP U-1 Page 4 302,400 GLENDALE-BURBANK IN SWR (GBIS) 3,150,000 386,340 FLORENCE AV SWR REHAB FLOWER WASHINGTON PICO SWR 407,005 0 103,000 0 165,800 9,060,000 FLINT AVE G ST SWR REPLC FIGUEROA ST SWR REPLC FIGUEROA MERIDIAN YORK RLF SWR EXPOSITION BL SWR REHAB ENTERPRISE ST SIPHON MOD EMERGENCY SEWER REPLACEMENT 88,740 2,150,000 COS REHAB NORS DIV 4 TO MARKET EAST LA AREA PRIM SWR REHAB 0 COS REHAB MARKET ST TO RODEO 2,500,000 649,440 CENTRAL AREA CSRP U-5 COLL SYS ADV PLANNING (BOS) 945,600 3,293,300 136,720 1 Year 2005/06 CENTRAL AREA CSRP U-3 & U-4 BUCKINGHAM DIVR SWR BUCHANAN RELIEF SEWER PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 803,020 2,121,320 398,760 48,600 499,280 6,328,500 960 0 107,000 0 331,590 6,060,000 88,920 104,080 1,080,000 454,360 2,500,000 0 16,080 2,240 169,140 20,450 134,880 nd 2 Year 2006/07 368,900 0 0 0 0 715,566 th 4 Year 2008/09 0 7,660,500 0 0 0 3,372,720 0 197,900 1,078,486 192,800 0 6,060,000 1,525,030 0 18,963,600 1,666,600 1,450,000 CS 0 3,660,500 0 0 0 10,222,020 0 18,900 688,814 130,520 1,175,750 6,060,000 413,218 0 400,000 1,824,480 1,600,000 105,560 1,378,636 0 0 0 1,162,414 rd 3 Year 2007/08 0 0 0 0 0 0 5,830,080 0 0 0 0 0 237,440 0 834,520 0 6,060,000 1,172,172 0 14,445,760 1,620,720 300,000 368,900 th 5 Year 2009/10 CITY OF LOS ANGELES, DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 0 0 13,217,937 0 0 0 0 0 1,596,660 0 1,740,120 0 6,060,000 10,320 0 1,220,720 18,070,995 150,000 2,372,200 6 Year 20010/11 0 0 0 0 0 0 43,894,382 0 0 0 0 0 2,979,970 0 9,120 0 6,060,000 0 0 0 18,120,562 0 7,965,180 th 7 Year 2011/12 0 0 0 0 0 0 43,790,415 0 0 0 0 0 725,170 0 0 0 6,060,000 0 0 0 17,697,323 0 3,880,840 th 8 Year 2012/13 0 0 0 0 0 0 43,790,415 0 0 0 0 0 0 0 0 0 6,060,000 0 0 0 211,120 0 21,920 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 0 31,626,111 0 0 0 0 0 0 0 0 0 6,060,000 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY COLLECTION SYSTEM (CS) ST 295,986 HARBOR AREA CSRP U-6 Page 5 0 268,800 NEIS PH 2 NE WILSHIRE AREA CSRP U-3 2,900,000 0 220,000 NEIS PH 1 NHIS CAHUENGA TO LCSFVRS N BROADWAY SWR REHAB 5,750,000 990,000 NICHOLS CYN ESMT SWR REPLC NORMANDIE FLORENCE SEWER REPL 0 MID NOS REHAB (U2) SANTEE ST 110,360 MANCHESTER CENTRAL & AVALON 0 770,000 MAINTENANCE HOLE RESETTING MANHATTAN 4TH SWR REHAB 459,236 LINCOLN 83RD SWR REPLC 0 796,876 LCIS REHAB & RELOC RODEO BLKWR LCIS REHAB BLACKWELDER MELROSE 558,906 1,055,000 576,171 1,891,467 0 LAS PULGAS CANYON SWR REPLC HOOVER ST SWR REHAB HOLLYWOOD AREA PRIM SWR REHAB HOLLYWOOD AREA CSRP U-2 HIGHLAND PK EAGLE ROCK SWR RHB 1,544,546 49,280 HARBOR AREA CSRP U-4 HARBOR CSRP U-5 & WILM U-20 1,358,280 1 Year 2005/06 HARBOR AREA CSRP U-3 PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 1,280 15,440 6,641,440 0 0 2,590,000 8,625,000 0 89,420 6,880 171,760 810,000 248,744 650,900 5,476,860 240 665,000 0 0 0 814,934 0 1,705,060 nd 2 Year 2006/07 0 0 0 0 0 0 0 5,840 0 th 4 Year 2008/09 0 0 0 0 0 0 0 0 0 150,000 1,938,140 0 98,980 0 0 0 1,259,960 68,168 2,358,190 890,000 0 1,219,800 1,525,920 CS 1,259,600 7,122,040 0 0 851,000 2,185,000 0 808,860 56,380 1,366,150 860,000 0 1,316,280 5,491,724 rd 3 Year 2007/08 0 0 0 0 0 0 0 0 0 0 0 55,622,695 0 345,420 0 0 0 1,063,620 299,112 9,520 950,000 0 13,641,840 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 0 52,144,775 0 345,420 0 0 0 20,387,195 1,120 0 990,000 0 19,908,780 0 0 0 0 0 156,460 6 Year 20010/11 0 0 0 0 0 55,746,658 0 2,646,340 0 0 0 14,991,725 0 0 1,030,000 0 16,578,700 0 0 0 0 0 134,960 th 7 Year 2011/12 0 0 0 0 0 45,583,272 0 8,771,600 0 0 0 0 0 0 1,070,000 0 55,520 0 0 0 0 0 1,855,600 th 8 Year 2012/13 0 0 0 0 0 0 0 1,933,200 0 0 0 0 0 0 1,110,000 0 0 0 0 0 0 0 1,752,100 th 9 Year 2013/14 0 0 0 0 0 0 0 5,600 0 0 0 0 July 1, 2005 0 0 0 0 0 0 0 0 0 0 1,150,000 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY COLLECTION SYSTEM (CS) ST 1,284,600 NOS REHAB VAN NESS TO TRINITY Page 6 SLAUSON/FLORENCE DIVR TO COS 1,276,362 0 447,960 SEWER FLOW MONIT UPGR PH 2 SLAUSON COMPTON SWR REHAB 50,000 1,811,874 SEWER FLOW MONIT UPGR PH 1 SEPULVEDA VAL MEADOW RLF SWR 0 22,560 SAN PEDRO CSRP U-8 SECONDARY SWR RENEWAL PROG (SSRP) 164,808 0 1,084,724 300,000 0 815,000 SAN PEDRO CSRP U-4 SAN PEDRO 92ND SWR REPLC SAN FERNANDO PASADNA SWR REHAB RODEO/ARLINGTON SWR MAINT FAC PLANNED UPGR REPLC PROG ODOR CTRL SIERRA BONITA 0 303,520 NOS REHAB TRINITY 6TH MISSION ODOR CTRL - FUTURE 6,484,340 184,500 1,152,250 0 NOS REHAB SIPHON TO LCIS JCT NOS REHAB MISSION TO HUMBOLDT NOS REHAB MAZE PHASE 5 NOS REHAB HUMBOLDT TO LAG 29,909,805 NOS REHAB HTP TO SIPHON 0 3,191,024 1 Year 2005/06 NOS DIV HUMBOLDT AV 18 & SFR NE WILSHIRE AREA CSRP U-5 PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 725,658 0 4,060 0 1,757,756 0 1,113,240 702,272 16,480 274,516 0 0 397,000 2,000,000 1,711,920 1,059,160 20,223,448 642,500 7,383,250 0 21,911,730 5,368,167 41,840 nd 2 Year 2006/07 0 0 360,000 th 4 Year 2008/09 0 328,320 0 0 0 1,550,000 0 0 320 0 0 0 0 4,000,000 17,426,335 532,480 0 349,200 1,763,000 1,295,400 CS 2,160 244,580 0 0 0 1,550,000 3,360 0 503,420 0 0 0 0 4,000,000 13,590,430 1,062,000 19,415,267 642,600 7,383,250 556,600 238,880 19,600 2,314,160 rd 3 Year 2007/08 0 0 0 0 307,800 0 0 0 1,550,000 0 0 0 0 0 0 0 4,000,000 12,670,415 13,512,850 0 3,918,600 0 1,295,400 th 5 Year 2009/10 CITY OF LOS ANGELES, DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 1,916,560 0 0 0 52,720,000 0 0 0 0 0 36,710,000 0 4,000,000 135,520 16,062,900 0 12,561,300 0 1,295,400 6 Year 20010/11 0 0 0 0 6,981,800 0 0 0 55,220,000 0 0 0 0 0 81,490,000 0 0 0 11,708,090 0 12,561,400 0 1,003,580 th 7 Year 2011/12 0 0 0 0 1,540,320 0 0 0 57,720,000 0 0 0 0 0 81,490,000 0 0 0 124,560 0 2,973,500 0 7,595,520 th 8 Year 2012/13 0 0 0 0 0 0 0 0 60,220,000 0 0 0 0 0 81,490,000 0 0 0 0 0 0 0 24,328,500 th 9 Year 2013/14 0 0 0 July 1, 2005 0 0 0 0 0 62,720,000 0 0 0 0 0 81,490,000 0 0 0 0 0 0 0 41,254,500 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY COLLECTION SYSTEM (CS) ST Page 7 94,840 292,500 SSRP S02B LA BREA & CRENSHAW SSRP SC05 LINCOLN & SUNSET 349,172 SSRP S02A RODEO RD & 52ND ST 57,420 0 SSRP H35 HOLLYWOOD SSRP P03B SOTO ST & 10 FWY 0 SSRP H32 HOLLYWOOD 29,900 0 SSRP H30 HOLLYWOOD SSRP P03A GOLDEN STATE & 10 FWY 0 SSRP H28 HOLLYWOOD 338,100 SSRP H27C CAHUENGA & HOLLYWOOD 0 SSRP H26 HOLLYWOOD 332,900 0 SSRP H04 HOLLYWOOD SSRP H27B CAHUENGA & MELROSE 0 SSRP H01 HOLLYWOOD 228,300 0 SSRP E02 NO HOLLYWOOD SUNLAND SSRP H27A BARHAM & CAHUENGA 0 190,000 0 67,460 SSRP C08 BRENTWOOD P PALISADES SSRP C04 ROSE & WASHINGTON SSRP A02 BALDWIN HILLS SOUTH LA CSRP U - 1 171,792 SOUTH BOYLE AREA SWR REHAB 0 102,900 1 Year 2005/06 SOTO ST GAUGING CHAMBER MOD SOTO PICO SWR REPLC PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 0 1,807,120 775,935 670,539 533,860 278,300 0 0 0 0 68,080 5,760 1,448,320 0 0 0 0 0 544,000 0 1,402,920 0 740,460 nd 2 Year 2006/07 0 0 0 6,480 0 0 167,580 th 4 Year 2008/09 0 808,255 698,887 4,425,882 2,307,602 0 20,113,500 2,569,590 31,594,400 1,939,960 1,226,260 532,300 22,434,000 1,928,700 0 1,794,000 4,112,460 4,290,000 12,192,600 CS 0 2,553,710 2,207,254 2,452,638 1,278,638 0 252,450 0 3,952,800 3,400,000 3,400,000 2,040,880 2,694,600 0 0 0 0 3,693,000 2,176,200 742,920 rd 3 Year 2007/08 0 0 0 21,200 10,960 2,240,640 0 23,258,570 0 0 0 0 0 16,770,100 250,560 40,735,400 54,258,580 9,000 0 0 0 0 579,720 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 0 32,392,720 0 0 0 0 0 0 0 0 23,074,880 0 0 0 0 0 0 0 852,300 6 Year 20010/11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7,584,460 th 7 Year 2011/12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2,934,160 th 8 Year 2012/13 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY COLLECTION SYSTEM (CS) ST 165,380 VOS WASHINGTON SWR REHAB 400,252 412,092 WEST LA INT SWR MH ADDITION WEST LA INT SWR REHAB OVERLAND - BARRY 0 0 WILSHIRE AREA SYS SWR REHAB WILSHIRE WSTMORELAND SWR REHAB Page 8 5,571,336 0 0 113,100 1,809,660 828,366 4,151,080 474,340 412,092 2,387,528 62,120 45,520 774,660 1,723,596 1,147,600 2,834,240 987,140 0 0 0 287,900 292,200 nd 2 Year 2006/07 9,047,508 45,000 104,800 119,020 2,262,400 1,145,114 5,826,800 849,380 6,341,832 0 69,380 46,240 0 564,904 1,125,600 24,830,851 1,221,960 162,780 77,180 0 1,959,100 1,988,400 rd 3 Year 2007/08 2,112,336 16,000 27,840 91,560 0 0 60,640 7,496,890 9,665,320 0 1,178,580 785,720 0 0 7,960,633 26,628,215 8,000 198,560 62,240 2,006,010 2,275,100 2,310,200 th 4 Year 2008/09 5,000 5,000 0 250,000 2,303,580 3,415,120 0 0 0 15,404,990 84,000 0 0 0 0 0 10,201,845 19,592,134 0 178,400 526,620 19,310,230 th 5 Year 2009/10 th 0 0 0 0 0 0 0 0 0 0 0 34,400 0 0 0 0 0 0 4,942,322 222,880 0 2,108,814 6 Year 20010/11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 35,200 0 0 2,764,364 th 7 Year 2011/12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 718,282 th 8 Year 2012/13 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 th 10 Year 2014/15 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 PROJECT PLANNED EXPENDITURE SUMMARY COLLECTION SYSTEM (CS) CS July 1, 2005 TOTAL CS 134,533,003 193,777,687 238,486,437 282,731,445 366,926,931 340,658,315 355,118,341 286,484,362 221,382,215 224,770,211 449,400 0 WILSHIRE AREA OLYM SWR REHAB WORKMAN MOZART INTER SWR 247,760 0 397,240 WILSHIRE AREA JEFF SWR REHAB WILMINGTON CSRP U-7 WESTERN 35TH RLF SWR 0 63,480 WASH OXFRD BEACH RLF SWR WEST LA RLF SWR 22,720 WASH GRIFFITH LB SWR REPLC 2,074,820 626,800 VERMONT RLF SWR FLOR-SLAUSON WASH FLOWER GRAND SWR REPLC 1,789,920 VERMONT RLF SWR ECIS-SLAUSON 0 VERMONT AV SWR REPLC 149,680 0 VAN NUYS SYLMAR SWR REHAB VERMONT MANCHSTER SWR REHAB 0 100,200 SSRP U04B VENICE BLVD & 10 FWY SSRP U18 WEST LOS ANGELES 102,400 1 Year 2005/06 SSRP U04A BEVERLYWOOD & 10 FWY PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 CITY OF LOS ANGELES, DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION ST 124,000 1,618,559 436,280 14,968,005 DCT NDN - CHEMICAL ADD SYSTEM DCT NDN - EQUIP PROCUREMENT DCT NDN - SEC CLAR SKIM AUTO DCT NITROGEN REM CONVERSION Page 145 DCT PHASE II BARCREENS REPLC DCT ODOR CONTROL SYSTEM 800,000 1,000,000 219,785 1,097,997 DCT NDN - BLOWER PROCUREMENT DCT NITROGEN REMOV CONV SC MODS 5,672,070 290,600 DCT LAB FACILITY DCT NDN - BLOWER FACILITY 600,000 61,355 386,070 0 97,159 DCT IRRIGATION CONV POT WATER DCT FILTER UPGRADE DCT EMERGENCY BACKUP POWER DCT ELECTRICAL POWER SYS MODS DCT DCS STANDARDIZATION 0 669,000 DCT CHANNEL 2 CONC REHAB @ PH2 DCT DCS REPLACEMENT 1,129,400 165,000 DCT CAPITAL STR REPLC PROG DCT CHANNEL 2 CONC REHAB @ PH1 105,000 7,863,480 1 Year 2005/06 DCT CAPITAL EQP REPLC DCT ADDL TERT FILTRATION PROJECT TITLE DCT PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 0 3,000,000 194,125 6,930,820 3,176,900 877,878 0 5,899,999 5,992,930 3,135,905 1,800,000 166,145 3,177,200 0 55,779 0 1,255,000 0 50,500 210,000 5,735,610 nd 2 Year 2006/07 0 0 0 0 0 0 0 0 0 0 0 0 0 760 0 0 0 3,499,540 22,260 0 0 33,333 th 4 Year 2008/09 DCT 0 1,000,000 0 0 42,310 0 0 2,439,030 0 975,580 600,000 188,380 1,056,640 4,000,000 0 0 0 0 0 90,000 rd 3 Year 2007/08 th 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2,706,540 0 0 0 833,333 5 Year 2009/10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 666,667 th 6 Year 20010/11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 99,999 th 7 Year 2011/12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 33,333 th 8 Year 2012/13 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY DONALD C. TILLMAN WATER RECLAMATION PLANT (DCT) CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION Page 146 37,429,010 30,000 DCT UPGRADE LANDSCAPING 0 80,000 15,250 TOTAL DCT ST 1 Year 2005/06 DCT PREFILTER MIXING IMPR DCT POWER/ENERGY MGMT DCT PLC REPLACEMENT PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 42,468,436 0 43,645 52,000 714,000 nd 2 Year 2006/07 0 0 0 0 3,555,893 th 4 Year 2008/09 DCT 10,982,060 0 52,120 255,000 283,000 rd 3 Year 2007/08 th 0 0 0 0 3,539,873 5 Year 2009/10 th 0 0 0 0 666,667 6 Year 20010/11 th 0 0 0 0 99,999 7 Year 2011/12 th 0 0 0 0 33,333 8 Year 2012/13 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY DONALD C. TILLMAN WATER RECLAMATION PLANT (DCT) CITY OF LOS ANGELES, DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION Page 173 CS EARTHQUAKE REPAIR WORK PROJECT TITLE 10,900,000 10,900,000 TOTAL EQ 18,000,000 nd 2 Year 2006/07 18,000,000 1 Year 2005/06 ST EQ PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 EQ 4,000,000 4,000,000 rd 3 Year 2007/08 th 4 Year 2008/09 0 0 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION 0 0 th 6 Year 20010/11 0 0 th 7 Year 2011/12 0 0 th 8 Year 2012/13 0 0 th 9 Year 2013/14 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY EARTHQUAKE RECOVERY (EQ) ST 0 614,000 300,000 0 HTP CAPITAL STR REPLC PROG HTP CAPITAL UTILITY REPLC PROG HTP CENTRAL SOLIDS HNDLNG FAC 826,886 252,590 HTP DIG GAS COMP FAC HTP DIG GAS DESULF FAC IMPR 482,672 280,000 265,840 214,000 432,000 264,904 HTP DIG SCREENING FAC SCRUBBER MOD HTP DISMANTLING UNUSED FAC HTP FIRE ALARM SYSTEMS HTP GRIT HANDLING IMPROVEMENT HTP INFLUENT CHANNEL REHAB HTP IPS ODOR CNTRL IMPR Page 177 585,390 HTP DIG GAS SILOXANE REMOV 0 144,200 HTP DIG EXPANSION IMPR HTP DIG GAS FLARE REPLC 346,553 1,454,220 HTP DIG CEN WET CAKE PUMP IMPR HTP DCS REPLACEMENT 818,280 2,071,000 HTP CAPITAL EQP REPLC PROG HTP CLASS A BATCH PROCESS EX 405,500 51,060 1 Year 2005/06 HTP BOILER NO 3 OPTIMIZATION HTP BIOFILTER TESTING HTP 1 & 5 MILE OUTFALL REHAB PROJECT TITLE HTP PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 1,308,640 0 4,400,000 0 4,250,000 0 0 248,690 317,035 4,843,293 0 6,552,464 1,639,966 1,637,420 500,000 355,000 603,650 2,365,000 238,500 0 370,575 nd 2 Year 2006/07 0 0 0 0 0 0 0 3,504,680 2,660,160 95,948 0 0 9,165,460 0 6,729,000 365,000 150,250 1,650,000 0 0 7,276,240 th 4 Year 2008/09 HTP 1,210,700 0 1,100,000 0 0 0 0 399,200 3,824,750 19,542,215 0 1,901,000 27,025,152 0 700,000 360,000 353,650 1,215,000 0 0 576,325 rd 3 Year 2007/08 0 0 0 0 0 0 0 1,243,020 0 0 0 0 0 0 23,631,500 370,000 150,250 1,400,000 0 0 5,700,700 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 17,739,500 6 Year 20010/11 th 7 Year 2011/12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 th 8 Year 2012/13 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY HYPERION TREATMENT PLANT (HTP) 987,502 1,141,394 HTP PRIM SOLIDS CENTRIFUGE HTP REACT NITRGN PURGE SYS 199,000 455,615 HTP STANDBY BOILER #4 HTP SUBSTATION SEPARATION Page 178 552,040 HTP SERVICE WATER FAC EXP 38,716,901 977,220 0 HTP SEC CLARF FLOW MEASUR HTP SEC CLARF EXPANSION 186,965 236,660 HTP PRIM SLUDGE PREHTR INST HTP REACT SELEC MIXER REMOTE 229,558 1,122,974 HTP PRIM BATT C MOD HTP PRIM POLYMER FACILITY 13,797,775 HTP PRIM BATT B MOD 114,704 HTP PRIM AND SEC SCUM HANDLING 2,365,506 HTP ODOR CTRL PRIM SCRUB PROC 308,000 4,860,853 HTP ODOR CTRL PRIM SCRUB EXP HTP PARKING STRUCTURE REHAB 144,640 HTP ODOR CTRL HDWRKS SYS RPL 289,000 206,000 HTP LPGH FLAME ARRESTER HTP OUTFALLS ASSESSMENT 643,000 60,000 HTP LANDSCAPING HTP LIQUID SLUDGE STORAGE FAC 29,400 TOTAL HTP ST 1 Year 2005/06 HTP LAG & DCT MONITORING PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 0 69,811,933 2,447,600 1,160,000 3,401,140 0 0 0 0 7,376,541 0 932,530 773,225 19,084,465 564,200 597,000 1,424,000 538,360 572,085 289,554 228,000 733,000 60,000 nd 2 Year 2006/07 0 0 0 0 0 54,349,256 0 0 0 0 284,428 0 0 0 0 0 17,810,771 0 0 0 0 0 0 4,657,319 th 4 Year 2008/09 HTP 92,829,258 2,212,698 48,000 1,180,050 0 0 0 0 12,519,558 0 582,750 15,376,645 1,211,730 0 0 0 0 0 1,429,835 0 0 60,000 rd 3 Year 2007/08 0 0 0 0 34,232,129 0 0 0 0 610,944 0 0 0 0 0 2,607 0 0 0 0 0 0 1,123,108 th 5 Year 2009/10 CITY OF LOS ANGELES, DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18,372,700 0 0 0 0 633,200 6 Year 20010/11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 10,431,140 0 0 0 0 10,431,140 th 7 Year 2011/12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 9,998,840 0 0 0 0 9,998,840 th 8 Year 2012/13 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 48,520 0 0 0 0 48,520 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY HYPERION TREATMENT PLANT (HTP) ST Page 223 LAG TERTIARY FILTER REPL LAG SURGE TANKS REPLACEMENT TOTAL LAG LAG PROG LOGIC/DISTRIB CNTRL SYS UPGRADE 6,337,342 0 200,000 2,511,200 0 2,493,388 LAG NITROGEN REMOVAL CONV LAG PROCESS PIPING REPLACEMENT 120,954 LAG NDN - EQUIP PROCUREMENT 0 298,000 LAG NDN - CHEM ADDITION SYS LAG POWER/ENERGY MGMT IMPL 645,800 0 LAG ELECTRICAL POWER SYST MODS LAG NDN - BLOWERS MAN SYS 0 68,000 1 Year 2005/06 LAG DCS REPLACEMENT LAG CAPITAL EQUIP REPL PROG PROJECT TITLE LAG PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 2,871,898 96,380 0 0 250,000 0 2,214,418 59,720 0 208,380 0 0 43,000 nd 2 Year 2006/07 0 0 0 3,371,667 3,355,000 0 0 0 0 0 0 0 0 0 16,667 th 4 Year 2008/09 LAG 4,454,560 247,880 0 0 0 206,600 0 80 0 0 4,000,000 rd 3 Year 2007/08 0 3,502,707 3,086,040 0 0 0 0 0 0 0 0 0 416,667 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION 0 513,853 180,520 0 0 0 0 0 0 0 0 0 333,333 th 6 Year 20010/11 0 50,000 0 0 0 0 0 0 0 0 0 0 50,000 th 7 Year 2011/12 0 16,667 0 0 0 0 0 0 0 0 0 0 16,667 th 8 Year 2012/13 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY LA-GLENDALE WATER RECLAMATION PLANT (LAG) 192,344 175,676 ODOR CONTROL BALLONA CREEK PP ODOR CONTROL DACOTAH PP SCRUBB Page 237 448,000 VENICE PP SLUICE GATE REPLC 5,817,425 26,085 4,470,720 VENICE PP HIGH RES GROUNDING VENICE PP DUAL FORCE MAIN 15,600 125,000 NORTH PULGA PP639 UPGRADE TEMESCAL CANYON PP634 REHAB 364,000 TOTAL PP ST 1 Year 2005/06 DACOTAH PP VFD REPL PROJECT TITLE PP PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 0 0 0 0 0 828,740 0 106,700 722,040 nd 2 Year 2006/07 0 0 0 0 0 th 4 Year 2008/09 0 0 0 0 0 20,094,180 0 0 20,094,180 PP 6,816,460 0 0 6,816,460 rd 3 Year 2007/08 0 0 0 0 0 13,751,820 0 0 13,751,820 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 6 Year 20010/11 0 0 0 0 0 0 0 0 0 th 7 Year 2011/12 0 0 0 0 0 0 0 0 0 th 8 Year 2012/13 0 0 0 0 0 0 0 0 0 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY PUMPING PLANTS (PP) ST 196,000 J G CODE IMPROV 386,000 644,800 161,663 OPEN SYSTEMS WAN SCADA REPLACEMENT FOR WCSD SMURRF Page 247 5,000,000 351,000 LAG S.A.F.E. COLLECTION CENTER TA-PUBLIC WORKS BUILDING 636,000 97,900 687,500 75,000 LABORATORY EQUIPMENT PROCUREMENT J G SHOIN BLD IMPR J G KAWANA PAVILION J G IRRIGATION 0 161,377 J G & ADMIN BLD CCTV REPL J G CSRP 422,000 60,000 HTP S.A.F.E. COLLECTION CENTER GREEN ACRES CERP 0 360,000 EMD LIMS REPLACEMENT EQP UPGR/REPLC TREATMENT PLANT 661,585 4,850,000 500,000 0 20,000 1 Year 2005/06 DOCUMENT MANAGEMENT SYSTEM CONSTRUCTION SERVICES CONTRACT COMM INVLVMNT & PROJ MITIGAT COLL SYS SETTLEMENT AGREEMENT SEPs BALBOA LAKE IMPRV PH 2 PROJECT TITLE SW PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 0 0 161,663 344,800 46,000 0 350,000 150,500 229,500 0 200,000 0 0 0 455,000 0 910,000 0 4,850,000 500,000 500,000 nd 2 Year 2006/07 0 0 0 161,663 0 0 0 440,000 0 0 0 200,000 0 0 0 10,000 0 0 0 3,000,000 500,000 1,150,000 th 4 Year 2008/09 SW 0 161,663 0 0 0 71,000 0 6,732,000 0 200,000 0 0 0 330,000 0 230,000 0 3,000,000 500,000 1,050,000 rd 3 Year 2007/08 0 0 161,663 0 0 0 314,300 0 0 0 0 0 0 0 10,000 0 0 0 3,000,000 500,000 1,250,000 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 161,663 0 0 0 0 0 0 0 0 0 0 0 0 26,700,000 0 0 3,000,000 500,000 1,200,000 6 Year 20010/11 0 0 161,663 0 0 0 0 0 0 0 0 0 0 0 0 26,700,000 0 0 3,000,000 500,000 1,200,000 th 7 Year 2011/12 0 0 161,663 0 0 0 0 0 0 0 0 0 0 0 0 26,700,000 0 0 3,000,000 500,000 1,150,000 th 8 Year 2012/13 0 0 161,663 0 0 0 0 0 0 0 0 0 0 0 0 26,700,000 0 0 3,000,000 500,000 1,000,000 th 9 Year 2013/14 0 0 July 1, 2005 0 161,663 0 0 0 0 0 0 0 0 0 0 0 0 26,700,000 0 0 0 500,000 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY SYSTEMWIDE (SW) 250,000 WW SYS FINANCIAL CNSLT (BONDS) Page 248 ZOO DRAINAGE FACILITY 23,102,256 2,000,000 40,000 501,500 WW NETWORK SERVERS CERP WW SYSTEM AUDITOR 989,000 WW FACILITIES PLAN 2,450,000 WW COLLECTION YARD IMPR 402,800 WCSD YARD CLARIFIER INSTALLS 1,100,000 58,200 WCSD CCTV STORAGE CABINETS WISARD REPLACEMENT 39,931 TOTAL SW ST 1 Year 2005/06 VIDEO CONFERENCING IMPLEMENTAT PROJECT TITLE WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 12,075,532 1,000,000 40,000 200,000 218,000 682,000 500,000 600,000 0 0 138,069 nd 2 Year 2006/07 0 0 0 0 0 0 0 0 0 5,844,663 0 42,000 200,000 141,000 th 4 Year 2008/09 SW 13,945,863 1,000,000 42,000 200,000 129,200 0 0 300,000 rd 3 Year 2007/08 0 0 0 0 0 0 0 5,477,963 0 42,000 200,000 th 5 Year 2009/10 CITY OF LOS ANGELES, DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 0 0 0 31,805,663 0 44,000 200,000 6 Year 20010/11 0 0 0 0 0 0 0 31,805,663 0 44,000 200,000 th 7 Year 2011/12 0 0 0 0 0 0 0 31,755,663 0 44,000 200,000 th 8 Year 2012/13 0 0 0 0 0 0 0 31,607,663 0 46,000 200,000 th 9 Year 2013/14 0 0 0 0 0 0 0 July 1, 2005 27,611,663 0 50,000 200,000 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY SYSTEMWIDE (SW) ST 74,400 TITP DIG MODERNIZATION 38,000 TITP POWER/ENERGY MGMT Page 281 TITP RENEWABLE ENERGY SLUDGE PIPING 206,400 2,382,454 37,000 TITP OUTFALL ASSESSMENT TITP RENEWABLE ENERGY 81,900 TITP KNIFE GATE HP GASKET REPL 3,410,000 134,420 TITP HEADWORKS IMPROVEMENTS TITP INTERIM CENTRIFUGE IMP 900,000 TITP FUTURE UTIL CONCEPT RPT 2,334,000 137,340 TITP DIG GAS CONDIT FAC TITP FINAL TANK STRUCTRL REHAB 122,780 TITP CONTROL SYSTEM UPGRADE 403,000 650,000 TITP CENTRATE WET WELL REHAB TITP EFF PUMP SUCTN VALV REPL 850,000 TITP CAPITAL STR REPLC 0 TITP AWTF PH2 216,000 0 TITP AWTF MEMB FILT PROC PH2 TITP CAPITAL EQP REPLC 3,119,940 151,018 TITP AWTF INTERIM LIME SATUR SYS TITP AWTF LIME SATURATOR SYS 257,980 1 Year 2005/06 TITP AWTF BRINE LINE MODS PROJECT TITLE TITP PLANNED EXPENDITURE SUMMARY WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 0 7,280 0 0 368,000 163,000 0 6,480,000 246,275 0 2,170,800 0 402,400 382,650 165,562 0 710,000 43,000 0 0 1,319,260 nd 2 Year 2006/07 0 0 0 0 0 0 0 0 0 0 0 663,920 0 0 0 1,519,857 902,350 363,338 0 372,000 0 1,808,915 107,590 th 4 Year 2008/09 TITP 0 0 0 0 0 40,000 1,121,730 0 0 0 914,811 2,312,610 820,751 0 372,000 0 0 0 36,310 rd 3 Year 2007/08 0 0 0 0 0 0 0 0 0 0 0 0 0 31,739 0 0 0 372,000 0 1,942,670 552,300 th 5 Year 2009/10 CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 372,000 0 21,967,440 2,926,780 6 Year 20010/11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 372,000 0 21,700,140 2,681,360 th 7 Year 2011/12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 372,000 0 5,329,080 th 8 Year 2012/13 th 9 Year 2013/14 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY TERMINAL ISLAND TREATMENT PLANT (TITP) Page 282 TITP SOLIDS HANDLING MODS TITP SEC AIR MOD / SCUM REMOV PROJECT TITLE TOTAL TITP 16,660,052 0 1,153,420 1 Year 2005/06 ST WASTEWATER CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR 2005/06 - 2014/15 13,719,947 0 1,261,720 nd 2 Year 2006/07 0 0 0 0 5,737,970 th 4 Year 2008/09 TITP 5,618,212 rd 3 Year 2007/08 0 0 2,898,709 th 5 Year 2009/10 CITY OF LOS ANGELES, DEPARTMENT OF PUBLIC WORKS BUREAU OF SANITATION th 0 28,366,220 3,100,000 6 Year 20010/11 0 27,853,500 3,100,000 th 7 Year 2011/12 0 18,301,080 12,600,000 th 8 Year 2012/13 0 12,600,000 12,600,000 th 9 Year 2013/14 0 0 0 July 1, 2005 th 10 Year 2014/15 PROJECT PLANNED EXPENDITURE SUMMARY TERMINAL ISLAND TREATMENT PLANT (TITP) Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 ATTACHMENT B SUMMARY STATUS OF CSSA DELIVERABLES Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) Attachment B - Collection System Settlement Agreement - Requirements Summary Shaded Items indicate completed projects. No. Requirement Frequency SA Due Date SA 1 Interim Scrubber at ECIS (Mission & Jesse) One time 8/27/2004 SA 2 Interim Scrubber at ECIS (23rd & San Pedro) One time 8/27/2004 SA 3 Interim Scrubber at ECIS (Jefferson Siphon) One time 8/27/2004 SA 4 Interim Scrubber at ECIS (NORS) One time 8/27/2004 SA 5 EAST CENTRAL INTERCEPTOR SEWER One time 8/27/2004 Ongoing Ongoing Ongoing One time 10/29/2004 Completed on 07/01/04. Ongoing 10/29/2004 Completed on 07/01/04. Ongoing 10/29/2004 Completed on 07/01/04. One time 11/28/2004 Completed. One time 10/9/2004 Completed on 11/08/04. One time 12/13/2004 Completed. Quarterly 1st Q 10/30/2004 2nd Q 01/30/2005 3rd Q 04/30/2005 4th Q 07/30/2005 1st Q Completed 10/26/2004. 2nd Q Completed 01/26/2005. 3rd Q Completed 04/29/2005. 4th Q Completed 07/29/2005. Quarterly 1st Q 10/30/2004 2nd Q 01/30/2005 3rd Q 04/30/2005 4th Q 07/30/2005 1st Q Completed 10/26/2004. 2nd Q Completed 01/26/2005. 3rd Q Completed 04/29/2005. 4th Q Completed 07/29/2005. Quarterly 1st Q 10/30/2004 2nd Q 01/30/2005 3rd Q 04/30/2005 4th Q 07/30/2005 1st Q Completed 10/26/2004. 2nd Q Completed 01/26/2005. 3rd Q Completed 04/29/2005. 4th Q Completed 07/29/2005. SA 6 SA 7 SA 8 SA 9 SA 10 SA 11 SA 12 SA 13 SA 14 SA 15 The City will monitor all the odor control facilities as necessary to comply with all regulatory and permit requirements. The City will modify its Odor Complaint Response Form to include a qualitative description of the wind condition (By entry 10/29/04) The City will make an initial return call to the community member filing the sewer odor complaint through the Sewer Odor Hotline (complainant) within 1 week from the receipt of the hotline complaint if requested by the complainant and the complainant has provided call back information (By entry 10/29/04) The City will investigate the sewer odor complaint received by the Sewer Odor Hotline and shall call the complainant to attempt to report findings and actions within 30 days from the receipt of the Sewer Odor Hotline complaint if requested by the complainant and the complainant has provided call back information (By entry 10/29/04) Within 30 days after the Effective Date of this Settlement Agreement (By entry 10/29/04), the City shall pay the United States the sum of $800,000 as a civil penalty. Within two months after ECIS becomes operational, the City will conduct monitoring of hydrogen sulfide gas levels, air pressure, and other necessary parameters. Within 3 months after ECIS, share the result with the Odor Advisory Board. Within 45 days after the Effective Date of this Settlement Agreement, the City shall pay Baykeeper $1,600,000; the Intervenors $ 425,000; and the Regional Board $71,745 (By entry 10/29/04). For the first year after the entry into this Settlement Agreement, the City will prepare quarterly reports reviewing the Sewer Odor Hotline program. The final report, including any findings and recommendations for improvement, shall be posted on the sewer hotline web page. The City will report quarterly to the Odor Advisory Board, or more frequently if requested by the Odor Advisory Board, on the removal levels for hydrogen sulfide at each of the odor control facilities (interim scrubbers and permanent ATFs) showing inlet concentration and outlet concentration. The information will also be posted on the odor hotline web site. On the thirtieth day of January, April, July, and October (30 days after the end of the fiscal quarter) of each year until this Settlement Agreement is terminated, the City shall submit to Plaintiffs a summary of all SSOs occurring during the previous fiscal quarter. Status Completed on 08/26/04. Completed on 08/26/04. Completed on 08/26/04. Completed on 08/26/04. Completed on 08/09/04. B-1 Attachment B - Collection System Settlement Agreement - Requirements Summary Shaded Items indicate completed projects. No. Requirement Frequency SA Due Date SA 16 EQ RPR SWRS U298 One time 12/14/2004 SA 17 EQ RPR SWRS U277 One time 1/13/2005 SA 18 EQ RPR SWRS U269 One time 1/13/2005 SA 19 EQ RPR SWRS U290 One time 2/11/2005 SA 20 EQ RPR SWRS U289 One time 2/11/2005 SA 21 No later than six months after entry of this Agreement (estimated at 4/29/05), the City shall submit a report that evaluates the need for modifications to its current FOG Control Program Standard Operating Procedures (“SOPs”) and Enforcement Response Plan and Enforcement Response Guide (“ERG”), and applicable sections of its existing rules and regulations implementing its Grease Control Ordinance. One time 4/29/2005 Completed on 04/22/05. SA 22 SAN PEDRO AREA SWR REHAB One time 2/28/2005 Completed on 09/07/04. One time 4/29/2005 Completed on 11/17/04. One time 4/29/2005 Completed on 06/01/04. One time 4/29/2005 Completed on 04/29/05. SA 23 SA 24 SA 25 Within six months after the entry of this Agreement, the City shall submit a report on the City’s progress on the wet weather Calibration and Validation of the City’s MOUSE model Within six months from the entry of this Settlement Agreement, the City shall, if practicable, arrange for calls to the Sewer Odor Hotline to be answered and documented by a live person rather than a recording. Within six months from the entry into this Settlement Agreement, the City will develop an updated Odor Outreach Plan for advertising the Sewer Odor Hotline. As part of the City's Odor Outreach Plan, the City will develop a community feedback system. Status Completed on 06/09/04. Completed on 07/20/04. Completed on 07/20/04. Completed on 06/10/04. Completed on 06/10/04. SA 26 Within six months of the entry into this Settlement Agreement, the City will prepare written procedures for the odor control measures the City currently employs including the addition of chemicals for sewer odor control. One time 4/29/2005 Completed on 04/27/05. SA 27 Within six months from entry into this Settlement Agreement, the City will prepare an implementation plan for implementing the recommendations made as part of the Independent Review of the Sewer Odor Control Program for the City of Los Angeles. One time 4/29/2005 Completed on 04/27/05. SA 28 EQ RPR SWRS U346 One time 3/16/2005 SA 29 EQ RPR SWRS U344 One time 3/16/2005 SA 30 EQ RPR SWRS U373 One time 4/15/2005 SA 31 EQ RPR SWRS U369 One time 4/15/2005 SA 32 EQ RPR SWRS U327 One time 5/16/2005 SA 33 EQ RPR SWRS U317 One time 5/16/2005 Annual 6/30/2005 Annual 6/30/2007 Annual 6/30/2005 One time 6/30/2005 SA 34 SA 35 SA 36 SA 37 Starting with FY 04/05, the City shall clean a minimum of 60,000 sewer Pipe Reaches annually. Starting with FY 06/07, maintain a Three-Year Rolling Average of 65,000 sewer Pipe Reaches cleaned. Starting with FY 04/05, at a minimum, the City shall use CCTV to inspect 600 miles of pipes annually. No later than 6/30/05, the City shall add the agreed to language to its design manual Completed on 05/04/04. Completed on 05/04/04. Completed on 05/12/04. Completed on 05/12/04. Completed on 06/23/04. Completed on 06/23/04. 82,030 reaches were cleaned. N/A 821 miles were inspected. Completed on 12/13/04. B-2 Attachment B - Collection System Settlement Agreement - Requirements Summary Shaded Items indicate completed projects. No. Requirement Frequency SA Due Date Status SA 38 No later than 6/30/05, the City shall utilize all current and past valid flow data to complete the development of all “R” Factors for all model basins within the City’s MOUSE model. One time 6/30/2005 Completed on 11/17/04. SA 39 Starting FY 04/05, the City shall inspect all permitted FSEs annually. Annual 6/30/2005 100 % of the FSEs were inspected. SA 40 On an annual basis, or as requested by the Odor Advisory Board, the City will share summary data with the Odor Advisory Board regarding the odor control measures utilized by the City and any relevant information Annual 10/1/2005 Completed on 07/30/05. SA 41 SOUTH LA CSRP U - 6 One time 7/30/2005 SA 42 SOUTH LA CSRP U - 5 One time 7/30/2005 SA 43 SOUTH LA CSRP U - 3 One time 7/30/2005 SA 44 WILSHIRE AREA NE SWR REHAB One time Original 8/30/2005 Revised 11/30/2005 SA 45 MT WASHINGTON AREA SWR REHAB One time 9/30/2005 Annual 10/1/2005 Annual 10/1/2005 SA 46 SA 47 The City will report on the construction progress of the odor control facilities as part of the annual report By October 1, 2005 and on September 1 of each following year this Settlement Agreement remains in effect, the City shall submit an Annual Progress Report Completed on 08/04/04. Completed on 08/04/04. Completed on 12/22/04. On schedule. Working closely with contractor to complete contstruction by 11/30/2005. Completed on 11/02/04. Completed on 09/30/05. Completed on 09/30/05. Completed on 05/27/05. Completed on 08/10/05. Completed on 03/02/05. On schedule. Construction is 15% complete. Completed on 10/06/04. Completed on 03/25/05. Completed on 03/15/05. Completed on 08/02/05. SA 48 NORTH EAST INTERCEPTOR SEWER, PHASE 1 One time 10/30/2005 SA 49 S BOYLE AREA SWR REHAB One time 12/8/2005 SA 50 HOLLYWOOD AREA PRIM SWR REHAB One time 12/30/2005 SA 51 4TH SHATTO VERMONT SWR REHAB One time 12/30/2005 SA 52 EQ RPR SWRS U274 One time 3/16/2006 SA 53 EQ RPR SWRS U340 One time 4/15/2006 SA 54 EQ RPR SWRS U283 One time 4/15/2006 SA 55 Harbor Area CSRP U- 6 One time 5/30/2006 SA 56 NICHOLS CYN ESMT SWR REPLC One time 5/31/2006 On schedule. Bid & Award is 95% complete. SA 57 No later than 6/30/06, the City shall submit a Capacity Report and Plan One time 6/30/2006 On schedule. One time 6/30/2006 On schedule. Annual 7/1/2005 SA 58 SA 59 No later than 6/30/06, the City shall submit a Rehabilitation and Replacement Report and Plan. In FY 04/05 and FY 05/06, the City shall apply chemicals to a minimum of 150 miles of sewers annually to control the growth of roots. SA 60 EQ SWR RPR U300 One time 7/15/2006 SA 61 EQ RPR SWRS U299 One time 7/15/2006 474 miles were treated in FY 04-05. Completed on 11/15/04. Completed on 11/15/04. B-3 Attachment B - Collection System Settlement Agreement - Requirements Summary Shaded Items indicate completed projects. No. Requirement Frequency SA Due Date Status SA 62 LAS PULGAS CANYON SWR REPLC One time 7/30/2006 SA 63 HOLLYWOOD AREA CSRP U- 2 One time 7/30/2006 SA 64 The City will complete the preparation of its Odor Master Plan within 2 years from the entry into this Settlement Agreement. One time 10/29/2006 SA 65 EQ RPR SWRS U295 One time 9/15/2006 SA 66 EQ RPR SWRS U292 One time 9/15/2006 SA 67 EQ RPR SWRS U291 One time 9/15/2006 SA 68 No later than 9/30/06, the City shall submit an evaluation of the effectiveness and applicability of its use of root control chemicals. One time 9/30/2006 On schedule. Revising Construction Plans with a new project schedule. On August 25, 2005, a request was made to Government Plaintiffs for extension of the Construction End Date to 10/30/2009. On schedule. Construction is 85% complete. On schedule. Construction is 98% complete. On schedule. On schedule. Construction is 99% complete. On schedule. Construction is 99% complete. On schedule. Construction is 99% complete. SA 69 AVE 45 ARROYO DR RLF SWR One time 10/6/2006 SA 70 EQ RPR SWRS U354 One time 10/14/2006 SA 71 Interim Scrubber at NEIS (Humboldt) One time 10/30/2006 SA 72 Interim Scrubber at NEIS (Richmond) One time 10/30/2006 SA 73 EAGLE ROCK INTER SWR One time 10/30/2006 SA 74 BAYWOOD BNDCT ESMT SWR One time 10/31/2006 On schedule. Bid & Award is 70% complete. SA 75 FLOWER WASHINGTON PICO SWR One time 10/31/2006 On schedule. Bid & Award is 30% complete. SA 76 BUCKINGHAM DIVR SWR One time 11/11/2006 SA 77 EQ RPR SWRS U339 One time 11/15/2006 SA 78 EQ RPR SWRS U338 One time 11/15/2006 SA 79 EQ RPR SWRS U320 One time 12/15/2006 SA 80 EQ RPR SWRS U316 One time 12/15/2006 On schedule. Construction is 99% complete. On schedule. Construction is 70% complete. On schedule. Construction is 70% complete. On schedule. Construction is 62% complete. On schedule. Construction is 30% complete. On schedule. Construction is 85% complete. On schedule. Construction is 85% complete. On schedule. Construction is 99% complete. On schedule. Construction is 99% complete. B-4 Attachment B - Collection System Settlement Agreement - Requirements Summary Shaded Items indicate completed projects. No. Requirement Frequency SA Due Date Status SA 81 SEPULVEDA VAL MEADOW RLF SWR One time 12/30/2006 On schedule. Bid & Award is 35% complete. SA 82 WASHINGTON FLOWER GRAND SWR REPLC One time 12/30/2006 On schedule. Bid & Award is 90% complete. SA 83 CENTRAL AREA CSRP U-5 One time 12/30/2006 On schedule. Bid & Award is 90% complete. SA 84 CENTRAL AREA CSRP U-3 & U-4 One time 12/30/2006 On schedule. Bid & Award is 90% complete. SA 85 12TH HILL SWR REHAB One time 12/30/2006 On schedule. Bid & Award is 92% complete. SA 86 NOS DIV HUMBOLDT AV 18 & SFR One time 12/31/2006 On schedule. Bid & Award is 90% complete. SA 87 SLAUSON/VAN NESS/COS EXTERNAL BYPASS One time 12/31/2006 On schedule. In Bid & Award. SA 88 SAN FERNANDO PSDNA SWR REHAB One time 12/31/2006 On schedule. Design completed 08/10/2005. SA 89 EQ RPR SWRS U294 One time 1/13/2007 SA 90 EQ RPR SWRS U293 One time 1/16/2007 SA 91 EQ RPR SWRS U319 One time 2/15/2007 SA 92 EQ RPR SWRS U318 One time 2/15/2007 SA 93 Harbor Area CSRP U- 3 One time 3/3/2007 SA 94 EQ RPR SWRS U342 One time 3/15/2007 SA 95 EQ RPR SWRS U341 One time 3/15/2007 SA 96 FLINT AVE G ST SWR REPLC One time 3/24/2007 SA 97 EQ RPR SWRS U304 One time 4/14/2007 SA 98 EQ RPR SWRS U296 One time 4/14/2007 SA 99 HOOVER ST SWR REHAB One time 5/2/2007 SA 100 LINCOLN 83RD SWR REPLC One time 6/30/2007 On schedule. Bid & Award is 50% complete. SA 101 Harbor Area CSRP U- 5 & WILM U-20 One time 6/30/2007 On schedule. Bid & Award is 50% complete. SA 102 ATF at ECIS (Mission & Jesse) One time 5/23/2008 On schedule. Design is 75% complete. Completed on 06/05/05 Completed on 06/05/05 On schedule. Construction is 50% complete. On schedule. Construction is 50% complete. On schedule. Construction is 35% complete. On schedule. Construction is 25% complete. On schedule. Construction is 25% complete. On schedule. Construction is 90% complete. On schedule. Construction is 16% complete. On schedule. Construction is 16% complete. On schedule. Design is 93% complete. B-5 Attachment B - Collection System Settlement Agreement - Requirements Summary Shaded Items indicate completed projects. No. Requirement Frequency SA Due Date SA 103 ATF at ECIS (23rd & San Pedro) One time 5/23/2008 SA 104 ATF at ECIS (Jefferson Siphon) One time 5/23/2008 SA 105 ATF at ECIS (NORS) One time 5/23/2008 SA 106 ATF at NCOS (Jefferson and Rodeo) One time 5/23/2008 One time 5/23/2008 On schedule. One time 5/23/2008 On schedule. One time 5/23/2008 On schedule. Annual 6/30/2008 On schedule. The City will develop written maintenance and operations manual for each of the ATFs. SA 108 The City will install an indicator light on the outside wall of each ATF With the completion of each of the ATFs, the City will extend an invitation to SA 109 the Odor Advisory Board to tour the facility. In FY 07/08 through FY 13/14, the City shall rehabilitate or replace 50 miles SA 110 minimum. SA 107 Status On schedule. Project is in Bid & Award. On schedule. Design is 90% complete. On schedule. Design is 90% complete. On schedule. Project is in Bid & Award. On schedule. Design is 60% complete. On schedule. Design is 60% complete. SA 111 ATF at NEIS (Humboldt) One time 3/26/2009 SA 112 ATF at NEIS (Richmond) One time 3/26/2009 One time 6/30/2009 On schedule. One time 6/30/2009 On schedule. One time 6/30/2009 On schedule. Annual 9/1/2010 N/A One time 6/30/2014 On schedule. One time N/A On schedule. One time N/A On schedule. One time N/A On schedule. One time N/A On schedule. One time N/A On schedule. One time 6/30/2014 On schedule. One time 6/30/2014 On schedule. One time 6/30/2014 On schedule. One time 6/30/2014 On schedule. One time 6/30/2014 On schedule. SA 113 SA 114 SA 115 SA 116 SA 117 SA 118 SA 119 SA 120 SA 121 SA 122 SA 123 SA 124 SA 125 SA 126 SA 127 No later than 6/30/09, the City shall have expanded its MOUSE model to include all Primary Sewers. No later than 6/30/09, the City shall complete and submit its Integrated Resources Plan (IRP) No later than 6/30/09, the City shall complete all Primary Basin Plans. If, in any three-Year period starting with the three-Year period comprising FY 7/08 through FY 09/10, the City rehabilitates or replaces, on a Three-Year Average, more miles of pipe than is required pursuant to the approved Rehabilitation and Replacement Report and Plan submitted pursuant to Subsection VI.D. of this Settlement Agreement, the City may "bank" the excess miles of pipe. No later than 6/30/14, the City shall complete Secondary Basin Plans for the 100 highest priority secondary basins. The City shall submit Work Plan for the following SEP: North Atwater Creek Restoration Project The City shall submit Work Plan for the following SEP: South Los Angeles Storm Water Treatment Project at 54th and Avalon St. The City shall submit Work Plan for the following SEP: Hazard Creek and Wetlands Restoration Project The City shall submit Work Plan for the following SEP: Inner Cabrillo Beach Pollution Control and Water Circulation Enhancements The City shall submit Work Plan for the following SEP: Downtown Los Angeles Storm Drain Low-Flow Diversion Project The City shall complete the following SEP: North Atwater Creek Restoration Project The City shall complete the following SEP: South Los Angeles Storm Water Treatment Project at 54th and Avalon St. The City shall complete the following SEP: Hazard Creek and Wetlands Restoration Project The City shall complete the following SEP: Inner Cabrillo Beach Pollution Control and Water Circulation Enhancements The City shall complete the following SEP: Downtown Los Angeles Storm Drain Low-Flow Diversion Project B-6 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 ATTACHMENT C SUMMARY STATUS OF THE NORTH ATWATER CREEK RESTORATION & WATER QUALITY ENHANCEMENT PROJECT Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 (This page was intentionally left blank.) Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 NORTH ATWATER CREEK RESTORATION & WATER QUALITY ENHANCEMENT PROJECT PROJECT LOCATION Area in Atwater Village located adjacent to the L.A. River in the Upper Los Angeles River Watershed. DESCRIPTION (Refer to Figure C1) The North Atwater Creek Restoration and Water Quality Enhancement Project will construct water quality physical and structural improvements to an area along the Los Angeles (LA) River. The project will restore wetlands for stormwater runoff capture and treatment and provide habitat linkage to the LA River. This will begin a restoration and revitalization of the LA River and its vicinity where wetlands existed along the riverbanks. The project will reconstruct an area along the LA River in the North Atwater community and restore wetlands to treat runoff from the North Atwater Creek storm drain. Water for irrigation of the site could potentially be pumped from the LA River, treated and applied to the landscape. In addition, runoff Best Management Practices will be implemented to minimize waste from horses using the LA riverbank from entering the LA River. This will directly benefit the East and Northeast LA communities, which are predominantly low income and minority. The Los Angeles River through an area known as the Glendale-Narrows still contains a naturalized streambed and supports a rich diversity of bird life, as well as aquatic species. This project will create wetlands, a seasonal creek, trails and footbridges for the public to enjoy, as well as educational information so that the public can understand the fuller riparian ecosystem that once existed here. Water for the wetlands will be provided through stormwater runoff; irrigation water by pumping from LA River, treating it, and applying it to the landscape. The surrounding residential neighborhood is predominantly low income and minority. On the other side of the site are active recreation fields and equestrian amenities. The benefits this project provides are numerous: demonstrating that Los Angeles can revive its ecosystems with water that is currently discarded and thus at the same time show that the City can augment water supply by utilizing this water for landscaping; improving water quality through on-site treatment; restoring habitat; increasing open space, places for passive recreation and education; implementing non-point source Best Management Practices; as well as flood hazard mitigated through the use of the storm water capture and treatment. A significant planning effort is underway to revitalize the Los Angeles River from an economic, ecologic, and social perspective. This park and wetlands will provide early proof of many of the concepts that have been discussed for river revitalization and have a significant impact on the pace of the revitalization effort. Currently the site is used primarily for storage of tree cuttings. Implementing this project will provide a great opportunity to demonstrate how the City can turn the liability of runoff into an asset and start the process of becoming more sustainable in the use of regional water resources. It will also provide an opportunity for visitors to see a working wetland and enjoy nature as it once existed. Given its close proximity to active recreation, the project takes advantage of visitor use already, and provides ready opportunities for education. C-1 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 PROJECT OBJECTIVES The objectives of the project are: - Wetlands creation and utilization of runoff; - Restoration of riparian and upland habitat; - Demonstration of sustainable use of local water resources; - Implementation of non-point source Best Management Practices; - Increased open space and passive recreation; - Safe and pleasurable access to the Los Angeles River and bikeway; - Ecosystem education; - Improved water quality; and - Post-project monitoring to understand the effectiveness and maintenance of the systems installed. WATER MANAGEMENT STRATEGIES - Ecosystem restoration* Environmental and habitat protection and improvement* Water supply reliability* Flood management* Groundwater management* Recreation and public access* Storm water capture and management* Water conservation* Water quality protection and improvement* Water recycling* Wetlands enhancement and creation* Conjunctive use Desalination Imported water Land use planning NPS pollution control Surface storage Watershed planning Water and wastewater treatment Water transfer * Pursuant to CWC §§ 79562.5 and 79564, these water management strategies must be considered to meet the minimum IRWM Plan Standards. Ecosystem Restoration: Much of the ecosystem of the Los Angeles River has been lost or degraded. This project will put back ecosystem function by creating a wetland and seasonal creek that typically would have existed along the river. Old maps of the Los Angeles River show a braided river with vast areas of wetlands and creeks, some ephemeral. This will mimic that function and structure. C-2 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Environmental Protection and Habitat Improvement: The wetlands and surrounding area planted in California natives will provide high quality habitat adjacent to a naturalized portion of the LA River. The project will provide a habitat linkage to the river from an upland area. Educational materials can foster an appreciation of nature and expand the constituency to care and protect these special places. Water Supply Reliability: Although minor in its immediate impact on water supply, this project can demonstrate how the region can better utilize its existing water resources without necessarily treating storm water to drinking water standards. It is estimated that 40-60% of all water use in Southern California is for landscaping. By using this resource for landscaping and habitat creation, the City can reduce its dependence on imported water. Flood Management: The utilization of runoff from the surrounding area will keep some of the water out of the Los Angeles River and mitigate flood potential. Recreation and Public Access: The site is already adjacent to a park with active recreation; this will enhance recreational opportunities and provide access to one of the naturalized streambed portions of the river. When the bike path along the river is eventually completed, this could provide an opportunity to create an entry point to the bike path, with the ability to bike all the way to Long Beach. Storm Water Capture and Management: The primary objectives of the project are to use a wetland to capture and treat stormwater; install non-point source Best Management Practices in the parking lot; and treat the water pumped from the river for irrigation purposes. Water Conservation: By eliminating the use of potable, imported water, the project conserves water for drinking purposes. The use of native plants will further conserve irrigation water. Water Quality Protection and Improvement: All the water utilized on the project will be treated and improved. The project will remove typical constituents found in urban runoff such as oils, grease, and trash. It will also remove constituents such as nutrients from high quality effluent from upstream sewage treatment plants that discharge to the river. Water Recycling: Much of the dry weather flows in the Los Angeles River are from the Donald C. Tillman and Los Angeles/Glendale sewage treatment plants. This project will recycle the water from those plants for irrigation purposes. Wetlands Enhancement and Creation: This creates wetlands where none currently exists. NPS Pollution Control: Urban runoff is ubiquitous; yet this project will capture the runoff from the surrounding neighborhood and treat it through a wetland. Best Management Practices installed on the parking lot on site will also treat NPS pollution. Both of these will prevent pollutants from entering the Los Angeles River. Surface Storage: The wetland will provide surface storage of water. Watershed Planning: This project has been identified as a key project in the Integrated Regional Water Management Plan, and with its multiple benefits and elements, is a good example of watershed planning and implementation. C-3 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Water and Wastewater Treatment: The urban runoff will be directly treated through Best Management Practices and the wetland system. Additional wastewater treatment will be somewhat indirect, yet real, in that the primary source of dry weather flows in the river that will be pumped to the site are high quality effluent from the sewage treatment plants, which will be further treated through nutrient removal. PARTNERSHIPS The City of Los Angeles is the only agency needed to implement the project. However, the Los Angeles County Department of Public Works is also supportive of the project. There is consensus within the City of Los Angeles - Bureau of Engineering, Bureau of Sanitation, Recreation and Parks Department, Department of Water and Power, Los Angeles River Ad Hoc Committee, and local City Council District are all in support of the project. POLLUTION CONTROL The project collects urban runoff and will reduce pollutant loads associated with the captured urban stormwater runoff, thereby incrementally reducing current and any future TMDL requirements (trash, bacteria, metals, etc) for the Los Angeles River. The project may also utilize various treatment techniques to improve water quality. Construction of the proposed wetlands will undoubtedly reduce the amount of nutrients downstream and will likely result in reduction of other pollutants. WATER QUALITY MONITORING WPD will monitor water quality before and after construction of the wetlands. The success of plant establishment and percentage of the native vegetation will be documented. Wildlife utilization of the wildlife corridor will be documented before and after project implementation. Water quality monitoring will be coordinated with Los Angeles County Department of Public Works to assist in data collection. Project success will be quantifiably measured through the improvement of water quality. The project will be monitored prior to construction to establish baseline water quality conditions. This will be accomplished by utilizing strategically located flow measuring devices, surface water and water quality monitoring devices. A final list of specific constituents to be monitored by the water quality monitoring program will be developed in collaboration with the stakeholders. For the first five years of project implementation, stormwater sampling will occur at least quarterly. Thereafter, a yearly sampling will be done unless otherwise determined through the analysis of the previously collected data. Currently, the City leads an established stormwater sampling program that can accomplish pre-project water quality monitoring. ADAPTIVE MANAGEMENT One of the key objectives of this project is to be a demonstration site for numerous technologies from created wetlands to installation of Best Management Practices. Monitoring will provide key information on the operation of the project and adjustments will be made throughout the life of the project, especially as Total Maximum Daily Loads (TMDLs) are implemented on the river and watershed management is implemented in the region. Through the monitoring results, the C-4 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 project flow rates and treatment systems can be adjusted if necessary, along with maintenance operations. DATA MANAGEMENT The data will be gathered and tracked by the existing staff of the City of Los Angeles Bureau of Sanitation Watershed Protection Division. Results will be made available to the public primarily through the use of the City's website: http://www.lastormwater.org. The data will also be incorporated with the Friends of the Los Angeles River (FoLAR) Riverwatch program that has been conducting water quality sampling along the river. The Los Angeles and San Gabriel Rivers Watershed Council has an extensive website and there will be a link from their website to the City's website. Finally, results of monitoring from this project, as well as others in the region will be presented at Watershed Council Stakeholder meetings. CONNECTION TO LOCAL PLANNING This project has been identified in the Integrated Regional Water Management Plan for the Upper Los Angeles River, as part of the early planning for the Los Angeles River Revitalization Master Plan, and as a Supplemental Environmental Project as part of a settlement for sewage overflows. STAKEHOLDER INVOLVEMENT Leading the effort are the City of Los Angeles agencies, including the Recreation and Parks Department, the Council District, and the Bureaus of Engineering and Sanitation. Additional stakeholders include park users, the local Audubon Society, homeowner associations, Neighborhood Councils, and local businesses. Regulatory stakeholders include the California Department of Fish and Game, the Regional Water Quality Control Board, the US Army Corps of Engineers, the US Fish and Wildlife Service, and the Los Angeles County Vector Control District. Planning efforts have been ongoing for several years. These efforts have resulted in discussion among many of the stakeholders listed above, as well as public meetings intended to gather community input. Feedback has been very positive and supportive, and contacts have been excited about the implementation of a sustainable project that brings multiple benefits to the community and the watershed as a whole. BENEFIT TO A DISADVANTAGED COMMUNITY The project is located in and provides a direct benefit to many disadvantaged communities. Matching funds will not be provided directly by the community and, therefore, the funding requirements will not pose a hardship to the community. C-5 Collection System Settlement Agreement (CSSA) Annual Progress Report No. 1 For the Reporting Period Ending June 30, 2005 Figure C-1: LAYOUT AND SCHEMATIC OF PROPOSED PROJECT C-6 (This page was intentionally left blank.) … … ttoo pprrootteecctt ppuubblliicc hheeaalltthh aanndd tthhee eennvviirroonnm meenntt