Offshore Windfarms in Germany –
Challenges and Technical Solutions
Example „BARD Offshore 1“
The Offshore Wind Power
Conference
Den Helder, Netherlands
12. February 2009
BARD Engineering GmbH
Presentation Structure:
1. BARD-Group
2. Offshore Sites in the North Sea
3. Wind Turbine Manufacturing in Emden
4. Rotor Blade Production in Emden
5. Foundation Solution BARD-Tripile
6. Grid Connection and Transformer Platform
7. Wind Lift I the Installation- and Service Vessel
8. Construction Concept Offshore
9. Harbor Logistics
10.BARD Building, BARD Service & Training Center
11.Nearshore Project Hooksiel
Guido Kumbartzky
2009-02-12
2
BARD Engineering GmbH
BARD-Group:
Business Development, Locations and Jobs
Company locations
Activities of the BARD-Group
with currently over 10 affiliates:
2003
2004
2005
2006
2007
2008
2009
Establishment of BARD Engineering GmbH in Bremen
Design of Offshore Foundation
Development of 5 MW wind turbine generator
Set-up of WTG and rotor blade production in Emden
Permit for BARD Offshore 1
Installation of 2 prototypes Onshore
Set-up of foundation production in Cuxhaven
Installation of Nearshore Turbine Hooksiel
Installation of BARD Offshore 1
Employment growth:
2004
2005
2006
2007
2008
Jan 2009
until end 2009 expected
Guido Kumbartzky
2009-02-12
3
20
30
61
205
450
642
1000
BARD Offshore Projects
BARD Engineering GmbH
BARD-Group:
The Structure / Organisation for Turn key supply
The aim of the BARD Building is the smooth installation of the offshore wind farms.
A professional team is coordinating the erection of the foundation system, tower segments, nacelle,
hub and blades. After the grid connection the wind turbines are handed over to BARD Service company
who is responsible for operation and service of the offshore wind farms.
BARD
Holding GmbH
BARD
Engineering
GmbH
Construction / Projects
BARD
Building GmbH
& Co. KG
BARD
Service GmbH
Cuxhaven
Steel
Construction
GmbH
Installation
Service / Maintenance
Tripile Fondation
BARD
Emden Energy
GmbH & Co. KG
BARD
Schiffsbetriebs.
Natalie GmbH
& Co. KG
BARD 5.0 / blades
Vessel coordination
Guido Kumbartzky
2009-02-12
4
BARD Engineering GmbH
BARD-Group:
Offshore Sites in the North Sea
The German North Sea
More than 1.400 WTGs permitted
More than 7.000 MW of power.
BARD-Group
Applied for 10 further projects
Water depths ca. 30-40m
Distance to coast ca. 80-110 km
Average wind speeds 10 m/s
ca. 4250 full load hours
BARD Offshore 1
1,7 TWh for more than 400.000
households
Guido Kumbartzky
2009-02-12
5
BARD Engineering GmbH
BARD-Group: A4
Wind Turbine Manufacturing in Emden
BARD 5.0 (designed by Aerodyne)
•
Capacity:
5MW, Rotor Ø: 122m
•
Hub:
electrical pitch, ca. 86 t
•
Generator type:
double-fed, asynchronous
•
Nacelle weight:
260 t
•
Rotor weight:
150 t (28 t / rotor blade)
Series production in Emden 100 units/year starting 2011
Guido Kumbartzky
2009-02-12
6
BARD Engineering GmbH
Slide 6
A4
Wenn mit Artikel Die BARD-Gruppe, dann konsekvent
ABoguna; 24-10-2008
BARD-Group:
Rotor Blade Manufacturing in Emden
Rotor blade „BARD 61“
Blade length:
59.4 m
Max. blade depth:
5.9
m
Connection diameter:
4.0
m
Total weight:
approx. 28.5 t
Energy research Centre of the Netherlands
Series production
300 units /year
starting 2011
Guido Kumbartzky
2009-02-12
7
BARD Engineering GmbH
BARD-Group:
Foundation solution BARD-Tripile
Series production at the CSC in Cuxhaven 100 units/
year starting 2011 in two production areas with in total
600 jobs
Tripile made up of steel piles
connected by a transition triangle
for water depths:
pile length:
Ø pile
:
Ø total construction
pile weight:
weight of transition triangle:
Height tower flange
service platform
Guido Kumbartzky
2009-02-12
8
approx.
approx.
up to
approx.
approx.
approx.
25 - 40 m
80 - 115 m
3,35 m
26 m
420 t
470 t
25 m LAT
18,5 m LAT
Assembly and coating hall
BARD Engineering GmbH
BARD-Group:
Wind Lift I : Installation
Jack-up Barge
•
Developed with Gusto, NL
•
•
•
•
•
•
•
•
•
Construction: Western Shipyard in Klaipeda/Lithuania (Delivery 05/2009)
approx. 100 m length and 36 m width
Hydraulic legs approx. 70 m length
Deployment up to 45 m water depth
Payload 2.600 t
Heavy lift crane for 500 t with 125 m hook height & secondary crane
Attachable guiding frame and own pile driver ram
Max. crew of 50
Ship operation by Otto Wulf, Cuxhaven
Guido Kumbartzky
2009-02-12
9
BARD Engineering GmbH
BARD Offshore 1:
Grid Connection and Transformer Plattform
Transformer platform:
--
swimming & self-installing platform
--
lattice like substructure
--
5 decks with service station, bunker and
spare part storage area
--
residential units for up to 40 persons
--
BARD communication station and VTA
--
helicopter deck
In Germany the TSO is responsible
for the offshore grid connection since
December 2006:
For BARD Offshore 1 this is
E.ON Netz GmbH Deutschland
Guido Kumbartzky
2009-02-12
10
BARD Engineering GmbH
BARD Offshore 1:
Construction Concept
Deployment of vehicles:
Installation vessel Wind Lift I – Installation and transport of major components
Pontoons with towboats and assistence vessels (AV stationary) – transport of major components
Service vessel – Transport of service personnel & transport of small parts (2,5- 3 m wave)
Supply vessel – Supply, transportation of service- and maintenance containers
Traffic safety vessel – Safe guarding of construction site
Helicopters – Transfer of personnel
Construction times:
Foundation
ca. 48 h
WTG with Tower
ca. 48 h
Cabling
ca. 24 h
Transformer station ca. 2 weeks
Guido Kumbartzky
2009-02-12
11
BARD Engineering GmbH
BARD-Group:
Harbor Logistics
Loading port Emden: Nacelle and rotor blades
Own heavy lifting platform and own portal
crane
Loading port Cuxhaven: Foundations,
Towers by Co. Anbau und Smulders
Own heavy lifting platform and own portal
crane
Wiking Helikopter:
Wilhelmshaven/Norddeich
Home port of the Wind Lift 1:
Cuxhaven Reederei Wulf
Roermond/Vlissingen (NL): Foundation piles
Guido Kumbartzky
2009-02-12
12
Additional storage area in Brake
BARD Engineering GmbH
BARD Building GmbH, BARD Service GmbH
and Training Center
BARD Building GmbH: Installation
BARD Offshore
Training Center in Emden 2009
BARD Service GmbH:
Service & Maintenance, A3
Offshore-Training
Guido Kumbartzky
2009-02-12
13
BARD Engineering GmbH
Slide 13
A3
BARD Service GmbH, nicht Services
ABoguna; 24-10-2008
BARD-Group:
Nearshore Project Hooksiel
Transport of the Offshore Foundation BARD
Tripile in Hooksiel in Cuxhaven on a self
propelled modular transporters (SPMTs
from Goldhofer)
•
•
•
•
•
•
Guido Kumbartzky
2009-02-12
14
2-10 m water depth
Test location for „BARD Tripile“
Test of the offshore logistics
Training location for personnel
Hub height: 90 m
Total height : 151 m
BARD Engineering GmbH
Thank you for your
attention!
Your Contact:
BARD Engineering GmbH
Office Bremen
Otto-Lilienthal-Str. 21
D-28199 Bremen
Tel: 0049(0)421-59660-0
Fax: 0049(0)421-59660-420
web: www.bard-offshore.de
Guido Kumbartzky
2009-02-12
15