Shell Albian Sands - Jackpine Mine - Tailings Plans
Transcription
Shell Albian Sands - Jackpine Mine - Tailings Plans
Shell Albian Sands Jackpine Mine ERCB Directive 074 Submission September 2009 TABLE OF CONTENTS TABLE OF CONTENTS Directive 074 Appendix C – Dedicated Disposal Area Plan for Cell 1… Directive 074 Appendix E – Annual Tailings Management……….…….. Tailings Measurement Plan Response ii Section 1 Section 2 Section 3 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 ERCB Directive 074 Appendix C Content of the DDA Plan 1) engineering designs and operating procedures for the containment structure and the deposit, including details and timelines for construction, operation, closure, capping, formation of a trafficable deposit, and final landform design; 2) the planned rate and amount of fines captured within the deposit each year, and 3) a comprehensive plan on removal or remediation of segregated fluid tailings each year. 1 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan 1.1 Section 1 INTRODUCTION This document has been prepared to address the requirements for a dedicated disposal area (DDA) plan, as required under Energy Resources Conservation Board (ERCB) Directive 074, Appendix C. In accordance with Clause 4.2 of Directive 074, DDA plans must be provided two years prior to construction of the DDA, although this timing may vary for existing operators. The first DDA for Jackpine Mine Phase 1 is the Thickened Tailings (TT) cell of the External Tailings Facility (ETF), referred to in this document as JPM DDA 1. The construction of the ETF starter dyke began in 2008 prior to the issuance of Directive 074. The content of this DDA plan makes reference to details provided in the Jackpine Mine Phase 1 Tailings Management Plan, required in Appendix E of Directive 074 and submitted in conjunction with this DDA plan. 1.2 DESCRIPTION OF EXTERNAL TAILINGS FACILITY (ETF) The Jackpine Mine Phase 1 ETF is located in the south east of Lease 13, covers 1,551 ha and has a capacity of 621 Mm3 of tailings. The ETF is comprised of a TT cell and two mature fine tailings (MFT) cells (Figure 1-1), of which only the TT cell is proposed as JPM DDA 1. The ETF is constructed with an overburden starter dyke, followed by coarse sand tailings (CST) beached to the interior. CST will be discharged into settling cells on top of the dyke to raise elevations as shown in Figure 1-2. 2 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-1: Layout of Dedicated Disposal Area within Surrounding Area 3 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-2: External Tailings Disposal Area Construction Concept 4 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan 1.3 Section 1 ENGINEERING DESIGN FOR THE JPM DDA 1 CONTAINMENT STRUCTURE The JPM DDA 1 is contained by a 6500 m long centreline dyke along the north, west, and south sides and a 2100 m long upstream dyke along the east side (Figure 1-3). It is constructed to an ultimate elevation of 381 metres above sea level (masl) and a maximum height of 67 m. The footprint of the structure occupies approximately 4.5 km2 from the centreline toe to the upstream crest. The centreline starter dykes are constructed entirely of overburden to an elevation of 324.9 masl. This portion of the structure is built in two phases: • A ring-dyke with a 50 m top-width will be constructed along the upstream side of the centreline section of the structure to provide initial containment of the tailings. The volume of this preliminary dyke is 3.3 Mm3. • The remainder of the starter dyke will be constructed following completion of the first phase, and requires 13.1 Mm3 of overburden. External dyke slopes along the centreline portion of JPM DDA 1 vary from 6H:1V to 4H:1V. The external slope angle is controlled by foundation conditions; specifically, the shear strength of the material and pore pressure response to loading. At this location, tidal flat mud (TFM) and Clearwater materials (Kc) govern the overall slope. Shallow plasticity index (Pl) clays are stripped to a width equal to three times the height of the starter dyke along much of the starter dyke footprint. The upstream portion of the starter dyke is constructed entirely of overburden to the adjacent MFT cell design elevation of 335.75 masl. Approximately 4.5 Mm3 of material is required to construct the dyke. Shallow Pl clays are stripped to a width equal to three times the height of the starter dyke along some sections of the structure. A buttress of tailings will be deposited on the downstream side of the upstream dyke, as the maximum unsupported height of this dyke is 20 m. As a cell is built above the starter dyke, the upstream dyke crest moves away from JPM DDA 1, towards the adjacent MFT cell. The external dyke slope is 4H:1V, governed by shallow Kc deposits and the potential for liquefaction failure. Internal dyke slopes for both centreline and upstream dykes are assumed to be 2H:1V. 5 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-3: Dyke Design 1.4 OPERATING PROCEDURES FOR THE CONTAINMENT STRUCTURE AND DEPOSIT Full details of the tailings engineering scheme for Jackpine Mine Phase 1 can be found in the Tailings Management Plan submission that addresses ERCB Directive 074 Appendix E requirements. Operating procedures for the containment structure and tailings deposition process, and details of removal of segregated fluid tailings (MFT) are provided in Section 3, the Tailings Management Plan. Plan On Removal or Remediation of Segregated Fluid Tailings Any material not meeting the strength criteria required by Directive 074 and not removed as segregated fluid tailings will be remediated in place. Any MFT disaggregating from TT placed in JPM DDA 1 will be pumped to the adjacent MFT cell in the ETF, and recycled back into non-segregating tailings (NST) production once in-pit disposal is available. 1.5 TIMELINES FOR CONSTRUCTION, OPERATION, CLOSURE, CAPPING, FORMATION OF A TRAFFICABLE DEPOSIT AND FINAL LANDFORM DESIGN Table 1-1 provides a summary of the timelines established for the construction, operation and closure of JPM DDA 1. Specific details concerning 1.3 construction of JPM DDA 1 containment are provided in Section 1.3, for 6 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 operational use of the DDA in Section 1.4, and for closure and reclamation in Sections 1.6 and 1.7. Table 1-1: Timeline Summary Start Date End Date Construction Preparation of starter dyke 2008 Preparation of External Dyke Walls (centerline) 2015 Preparation of Upstream Dyke 2010 Operation TT deposition – initial filling period 2010 TT deposition – in-pit tailings cell sand capping 2035 TT deposition – in-pit tailings cell sand capping 2049 TT deposition – in-pit tailings cell sand capping 2054 MFT transfer 2010 Closure, Capping and Final Landform Design Completion of TT deposition n/a Trafficable tailings surface 2055 Overburden capping and drainage contouring 2057 Reclamation coversoil placement 2060 Nurse crop coverage and cap settlement 2060 Revegetation 2062 Monitoring 2063 1.6 2010 2029 2011 2027 2036 2050 2055 2055 2055 2057 2059 2061 2062 2063 TBD Formation And Capping of Trafficable Deposit Completion of TT deposition and pumping of MFT to the adjacent ETF MFT cell or to NST production is anticipated in 2055. As shown in Table 1-1 and the Tailings Management Plan, TT is deposited over four periods: initial deposition and three subsequent depositions during CST capping activities in each of the in-pit tailings cells. Between each of these periods, a thin layer of CST will be placed over the TT within the DDA to facilitate water expression from the deposit. Deposit strength required to allow a trafficable surface is anticipated to be achieved by 2057. At completion of the Jackpine Mine Phase 1 TT deposition events, the TT elevation is expected to reach 365 masl within JPM DDA 1. As described in the Tailings Management Plan, the latent capacity within the TT cell structure (to the approved 381 masl) is intended to act as contingency in the event of changes to plan parameters that may generate increased volumes of TT, or to be filled by TT produced in proposed Jackpine Mine Expansion activities. To maintain the integrity of fines sequestration within the DDA, alternative tailings storage has not been planned for this TT cell capacity. In the event that proposed expansion activities do not go ahead, the TT cell will be capped with an overburden plug to bring the final elevation to the 381 masl elevation required for closure drainage activities, as described below. 7 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Overburden sourced from overburden storage areas will be placed onto the trafficable TT surface, to an average depth of 16 m (or a minimum of 3 m if Jackpine Mine Expansion TT deposition fills the TT cell). The overburden cap will be contoured to grade to the adjacent dyke walls, to provide channels for drainage and to provide mesotopographical features for reclamation activities. Cross sections showing typical overburden and reclamation material depths along drainage channels and at high and low elevations on the JPM DDA 1 surface are provided in Section 1.7. Overburden capping activities are scheduled to occur between 2057 and 2059 (see Table 1-1) to cover the 4.5 km2 surface area of the DDA. 1.7 FINAL LANDFORM DESIGN As JPM DDA 1 is part of the larger ETF landform, reclamation activities and drainage features have been adapted to provide an operational reclamation plan until such time as the ETF is closed and the closure drainage plan for the entire structure is completed. The location of the JPM DDA 1 requires activities related to vegetation of the dyke wall to be controlled by Dam Safety Board regulations relating to active tailings dam treatment, until such time as the MFT cells are closed and the ETF is decommissioned. Some reclamation activities will be carried out at the closure of the DDA to prepare the area for further revegetation at closure. Closure Drainage Design The closure drainage plan for the ETF involves a drainage network directed to the east side of the ETF where it is ramped down to a closed-loop network leading to a future pit lake located on the west side of the Jackpine Mine Phase 1 development area. Until closure of the ETF, the drainage plan has been modified for the JPM DDA 1 area to drain surface water eastwards towards the adjacent MFT cell, and to provide vegetated waterways draining dyke wall areas towards the toe interception ditch present around the entire ETF (Figure 2-4). In this way, drainage from the JPM DDA 1 will be designed to expand to the drainage network across the remainder of the ETF at closure, but will be maintained within a closed-loop area while the ETF remains in operation. Overburden capping materials will be contoured to provide the appropriate channel morphologies, as described in detail in the Jackpine Mine Phase 1 Application (2002). It is anticipated that overburden capping material will settle over time and provide microtopographical variation on the surface. Reclamation Material Placement On completion of overburden capping, reclamation materials will be placed according to prescribed replacement depths within EPEA Approval No. 153125-00-00. Closure and reclamation plans for Jackpine Mine Phase 1 will be designed to meet the conditions within the Muskeg River Mine Expansion 8 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 EPEA Approval No. 20809-01-00, and the reclamation designs shown in Figures 1-4 to 1-9 anticipate these requirements. Reclamation material will be direct placed from salvage activities in northern pit areas, or from Reclamation Material Stockpiles (RMS – see Figure 1-1) located close to the ETF. Dyke wall slopes and the top of the dyke wall will have an average of 30 cm of peat-mineral mix placed over the overburden capping materials. The dyke walls were originally planned to have upland soils replaced on their surface as per the approved closure, conservation and reclamation plan for Jackpine Mine Phase 1, however AENV Dam Safety has advised that the use of upland soils and subsequent woody species growth is contraindicated for dam safety inspections. Peat-mineral mix has therefore been substituted in these areas, with an Alberta Sustainable Resource Development-approved grass mix planted until such time as the ETF is decommissioned and the planting of woody species is allowed. JPM DDA 1 top surface areas adjacent to drainage channels and in flat areas will have 20 cm of coarse-textured upland surface soil and 30 cm of mediumtextured subsoil placed in areas designed for g1 ecosites. These upland soils will be either medium or coarse-textured depending on the ecosite planned for the location (see Revegetation Design below). Peat-mineral mix to a depth of 30 cm will be placed on the banks of drainage channels. Revegetation Design Creation of the channel areas also provides adjacent raised “hummock” areas that will be used for upland ecosite development in the reclamation plans (Figure 1-5). It is anticipated that given the shallow gradient on the surface of the JPM DDA 1 area, most of the areas around the drainage channels have the potential to remain moist and have been designed as g1 ecosites with areas of c1 in hummock areas and h1 adjacent to drainage channels (Figures 1-5 to 18). Areas around the periphery of the top surface, top of the dyke wall and on the slopes of the dyke walls have been designed as d ecosites with an area of c ecosite on the potentially drier south-facing top slope (Figures 1-4 and 1-9). The closure plan presented in Figures 1-4 to 1-9 indicates boreal mixedwood ecosites on the dyke walls, as per EPEA Approval No. 153125-00-00 for Jackpine Mine Phase 1, however it should be noted that reclamation plans may see these areas grassed for a period designated by the Dam Safety Board. 9 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-4: JPM DDA 1 Closure Landform Design and Drainage Features 10 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-5: Cross Sections A-A1 of JPM DDA 1 Drainage Channels 11 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-6: Cross Sections B-B1 of JPM DDA 1 Drainage Channels 12 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-7: Cross Section C-C1 of JPM DDA 1 Drainage System at Outlet to Adjacent MFT Cell 13 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-8: Cross Sections D-D1 of JPM DDA 1 Top Surface to Dyke Wall Junction 14 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 1 Figure 1-9: Cross Sections E-E1 of JPM DDA 1 Top Surface to Dyke Wall Junction 15 of 15 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan 1) a description of the tailings management plan and any deviations from the approved tailings plan for the entire mine scheme; 2) a process flow diagram for the scheme’s tailings operations; 3) a mineable oil sands reserves table for the life of the mine scheme that includes • mine total waste, overburden, and interburden, and • ore quantity, bitumen grade, fines, sand, and water (as a weight per cent of the ore), and recovered barrels of bitumen; 4) a production forecast table for the life of the mine scheme by time period, including • mined total waste, • mined ore, bitumen grade, and recovered barrels of bitumen, and • total tailings production by type; 5) a table of waste material (overburden and interburden) classified by • geologic formation (Holocene, Pleistocene, Clearwater, McMurray, etc.) with associated volume and weight, • type and per cent of material suitable for tailings impoundment construction, and • the amount projected for use in tailings impoundment construction; 6) a table that schedules the source and destination of waste material by • mass and volume, classifying material type by structure, • the material types—overburden, interburden, crusher rejects (or oversize), and tailings—used for structures, • destination area, including DDAs, external and in-pit waste disposal areas, external and in-pit tailings impoundment structures, and external and in-pit tailings areas; 7) a starting baseline for all structures, including the present elevation of each waste material type within each structure; 8) a construction schedule, volume, and projected life span for each tailings impoundment structure; 9) an illustration of fluid tailings impoundment and DDA capacity versus the associated storage requirements; 1 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 10) destination and description of each tailings type by structure, including mass, volume, and components (water, fines, sand, and bitumen, as a per cent of the ore); 11) a site-wide tabulation and illustration of fluid tailings inventory; 12) site-wide sand, fines, and water balance; 13) mine scheme development maps by reporting period, and a text description of the major development activities as illustrated on each map; 14) a summary of tailings water chemistry, seepage water chemistry, and seepage water rates into the groundwater from reports of groundwater and tailings monitoring programs provided to AENV; 15) a description of the process for remediation or rehandling of segregated fines within the DDAs within one year of segregation; 16) planning assumptions and criteria used to support the tailings management plan, such as fines distribution in the ore body, tailings stream-specific gravities, tailings consolidation curves, tailings deposition angles, and tailings impoundment design and construction criteria; and 17) any other information that the ERCB requires. 2 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 DIRECTIVE 074 TAILINGS MANAGEMENT PLAN Overview The information contained in this document is provided in response to the requirements of ERCB Directive 074 – “Tailings Performance Criteria and Requirements for Oil Sands Mining Schemes”. The tailings management plan and associated information provided are based on the mining scheme described in ERCB Approval No. 9756 and consider an annual average bitumen production of 100,000 Bbls/day bitumen for the Jackpine Mine. The plans also recognise that bitumen froth produced at the Jackpine Mine will be transferred for processing through expanded Muskeg River Mine froth treatment facilities. Fine tailings produced as a result will be managed at the Muskeg River Mine tailings facilities. The information is provided in a format that follows the requirements as described in Section 4.5 and Appendix E of the directive. Tailings Strategy and Background In developing its tailings management strategy Shell has considered all aspects of Directive 074 and was done so based on the understanding that; “The ERCB recognizes that fluid tailings management is developing and that operators may need flexibility to apply technologies and techniques that best suit the circumstances of particular projects” and that “The ERCB will consider submissions of operators and will determine project-specific requirements related to the directive”. Whereas this Tailings Management Plan is designed to meet the requirements of Directive 074, the development and implementation of new technologies at commercial scale provides a degree of uncertainty that may impact the timing and performance of the proposed fine tailings management schemes. The initial tailings management scheme that will be implemented at the Jackpine Mine is based on the ability to separate tailings streams for deposition in the external tailings facility currently under construction. The construction of this facility provides for a dedicated disposal area (DDA) that will be utilised for the storage and management of thickened tailings (TT) that will ultimately provide a trafficable deposit. The facility design and construction is currently underway with first deposition of TT in the external DDA anticipated in the latter half of 2010. To compliment the start up and initial operation of the thickened tailings DDA Shell will continue its evaluation and development of other fine tailings management technologies using its dedicated tailings pilot plant and test facility located at the Muskeg River Mine. Shell is also considering the larger scale 3 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 field-testing in 2010 of atmospheric fines drying techniques. These techniques have only been evaluated to date through small-scale test facilities. Shell has included in its planning and response to the requirements of Directive 074 the implementation of “Non-Segregating tailings” (NST) at commercial scale. This process is currently under development utilising the tailings pilot plant facility. The timing of implementation of this technology to commercial scale recognises the needs for; • thorough testing, compilation and analysis of test data • detailed design of a commercial facility • project start-up to commercial scale capacity and performance It is expected that the use of NST will be initiated at the Jackpine Mine once inpit deposition of tailings is available; this is forecasted to be in the year 2027 In its planning, Shell has recognised that during early development of a thickened tailings deposit, there may be shortfalls in capacity to meet the requirements of the directive with respect to the required percentage of fine tailings sequestration. Technologies to supplement the primary depositional techniques, such as atmospheric fines drying, are being considered for implementation during these periods and additional production capability of such technology has been included. 4 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 1 A description of the tailings management plan and deviations from approved plans for the entire mine scheme 5 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 EXTERNAL TAILINGS DISPOSAL OPERATIONS Separate Stream Tailings technology is utilized during deposition in the Jackpine Mine Phase 1 ETDA. Separate Stream Tailings production at Jackpine Mine produces the following tailings streams: • Coarse Sand Tails from Cyclone underflow • Thickened Tails from Thickener underflow • Whole Tailings (WT) produced when production upsets occur in the tailings circuit • Thin Fine Tails (TFT generated when fines segregate during the deposition of all tailings streams. TFT consolidate, to form Mature Fine Tails after 12 to 18 months. The Jackpine Mine ETDA is a segmented structure that separates the Thickened Tails deposit from the beached Coarse Sand Tails and the Fluid Tailings contained within the beach (MFT Pond). Segmenting of the structure allows the MFT Pond to be contained with dykes constructed with upstream cell technique. The TT Pond is contained with centreline constructed containment dykes. The Jackpine Mine - Phase 1 Application ETDA plan showed the TT containment dykes at an ultimate elevation of 373 masl, and the Main Tailings Area (MFT Pond) reached a final elevation of 371 masl. Subsequent ETDA designs and tailings staging studies have modified the design of the Jackpine Mine ETDA. The ETDA design submitted for Dam Safety approval in July 2007 segmented the Main Tailings Area into two MFT Ponds and raised the final elevation of the entire ETDA to 381 masl. The Main Tailings Area was segmented in order to defer diversion of Khahago Creek. MFT Pond 1 (MFT1) is developed west of Khahago Creek, and MFT Pond 2 (MFT2) borders the east limit of OSL T13 and the Khahago Surge Facility. The Jackpine Mine Expansion Application proposes the elimination of the Khahago surge facility and provides a redesign of the east limit of the ETDA to use the additional space up to the east limit of OSL T13. However, this design change has not been integrated into the plans described in this submission. The Jackpine Mine 2009 Tailings Management Plan external tailings plan uses: • Separate Stream tailings production • The 2007 Dam Safety Approved ETDA 6 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 The tailings management plan as presented shows the ETF MFT Pond will rise to the final design elevation of 381 masl by 2027. The MFT Pond 2 will be filled at a rate where containment dykes reach the same elevation as MFT Pond 1 to provide the opportunity to merge the two ponds and eliminate the need for a cross dyke between the ponds. The TT Pond is the nominated DDA to provide fines sequestration over the short term. The TT deposit will not achieve the full long term fines sequestration requirements of the directive, however initiatives are underway to optimize fines capture in the TT deposit, and investigate supplemental fines capture methods such as atmospheric fines drying. When the MFT Pond reaches design elevation in 2027 the TT Pond will be approximately 20 m below design elevation. The lagging TT Pond elevation is a result of reduced TT production in this plan versus previous plans due to the reduction in predicted orebody fines. The intermittent deposition of TT during in-pit CST capping will not raise the pond to final design elevation. The dormant TT Cell will have a thin layer of coarse sand placed on top during dormant periods to facilitate water expression from the deposit. The resulting increase in elevation at the end of operations is addressed in the closure plan and is not considered for alternative tailings storage in this plan in order to: • preserve the integrity of the DDA • maintain contingency TT space for increased TT quantities due to potential changes to plan parameters or from future expansions. In-Pit Tailings Disposal Operations Non-segregating tailings (NST) has been selected as the tailings technology for in-pit tailings operations, which will start in 2027. NST will be produced and deposited in cells contained by a combination of engineered dyke structures and the final pit walls. Upon implementation of NST, JPM will be compliant with D-074 fine sequestration targets. NST is produced by the mixture of TT, coarse dewatered sand, and MFT from a fluid tailings cell, with gypsum added to prevent segregation of the mixture. The NST product is pumped at a high solids density and deposited sub-aerially to prevent segregation during deposition. 7 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 In-pit NST operations will require two active cells: • The NST Cell for deposition of NST product and the CST cap • A Clarification (Fluid Tails) cell to receive Thin Fine Tails runoff pumped continuously from the location of active NST deposition; the Fluid Cell also provides a fines reservoir to harvest fines for recombination back into the NST stream The top five metres of NST cells are capped with Coarse Sand tails to facilitate water expression from the NST deposit and accelerate establishment of a trafficable surface. During CST capping, NST production is suspended and Separate Stream tailings production is temporarily resumed. The CST will be hydraulically placed (beached) over the NST. During this process the TT will be placed in the ETDA TT Cell. All TFT is pumped to the in-pit clarification cell. The design properties of NST has a Sand to Fines Ratio (SFR) between 4:1 and 5:1 in order to establish a non-segregating product and maintain pumpability. However, for the purposes of ensuring that there is no deficit in fines availability to produce a viable NST product, an SFR of 7.5:1 has been applied for planning purposes. NST capped with CST will be deposited in three in-pit Cells. • Cell 1 receives NST from 2027 to 2035 and is CST capped in 2035 and 2036 • Cell 2 is segmented with an intermediate (overtopping) dyke to allow final clearing of the cell. Cell 2i filled with NST from 2036 to 2042. The remainder of Cell 2 is filled with NST from 2042 to 2049, and CST caped in 2049 and 2050. • Cell 3 receives NST from 2050 to 2054 and is CST capped in 2054 and 2055. All Fluid Tails generated during in-pit operations will be pumped to the sole clarification cell, Fluid Cell 1. The Jackpine Mine - Phase 1 Application had selected Consolidated Tails as the in-pit tailings technology. Since 2002, Shell has determined that NST is a better composite product with more consistent fines capture in the deposit, superior non-segregating properties, and has accelerated timing to a trafficable surface. 8 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 2 A process flow diagram for the schemes tailings operations 9 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Figure 2-1 – NST Process Flow Diagram Warm Water To Process Fine Sand Wate r To Process Coagulant Cyclones Thickener Extraction Tailings Fluid Cell Wate r and Thin Fine Tailings (TFT) Coarse Sand Non Segregating Tailings In-Pit DDA Tailings Pump Box Infrastructure Tailings Stream Beginning of Tailings Process 10 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Figure 2-2 – ETDA Process Flow Diagram Warm Water to Process Cyclones Thickener Extraction Tailings Whole Tailings and Bypass Tailings Thickened Tailings (TT) Coarse Sand Tailing Pump Box Thin Fine Tailings Wate r to Process ETDA MFT Pond MFT West Dyke Infrastructure Tailings Stream Beginning of Tailings Process 11 of 70 External DDA – Thickened Tailings (TT) Cell Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Figure 2-3 – In-Pit Process Flow Diagram Fine Sand Thickener Cyclones Warm Wate r To Process Extraction Tailings Whole Tailings and Bypass Tailings Coarse Sand Tailings Pump Box Wate r To Process Thickened Tailings (TT) Wate r and Thin Fine Tailings (TFT) In-pit Fluid Cell Thickened Tailings (TT) Cell (DDA) DDA (In-pit Cell Coarse Sand Tailings Cap ) Infrastructure Tailings Stream Beginning of Tailings Process 12 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 3 A mineable oil sands reserve table for the mine scheme that includes • • mine total waste, overburden and interburden ore quality, bitumen grade, fines, sand, and water (as weight percent of the ore) and recovered barrels 13 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-1 Waste Material Balance Year Total 1 Waste 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020-2024 2025-2029 2030-2034 2035-2039 2040-2044 2045-2049 2050-2054 2055 (Mt) 54.8 44.8 40.2 39.6 40.9 48.2 40.6 43.9 46.2 51.6 254.8 252.6 254.6 248.0 247.0 268.5 218.8 41.5 Total Dump Locations Reclamation Cell Inpit Inpit Inpit Inpit WODA WODA WODA Dump 2 Capping Phase Phase Phase EODA Dump Dump Dump Dump Material 4 3 2 3 1 2 1 (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) 26.4 16.4 9.9 0.0 0.0 9.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 21.6 12.6 9.0 0.0 0.0 9.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 19.3 10.9 8.3 0.1 0.0 2.9 5.5 0.0 0.0 0.0 0.0 0.0 0.0 19.1 10.8 8.1 0.2 0.0 0.0 8.1 0.0 0.0 0.0 0.0 0.0 0.0 19.6 10.8 8.4 0.5 0.0 0.0 8.4 0.0 0.0 0.0 0.0 0.0 0.0 23.2 10.5 9.9 2.7 0.0 0.0 9.9 0.0 0.0 0.0 0.0 0.0 0.0 19.5 9.8 8.4 1.3 0.0 0.0 8.4 0.0 0.0 0.0 0.0 0.0 0.0 21.1 11.8 8.7 0.6 0.0 0.0 8.7 0.0 0.0 0.0 0.0 0.0 0.0 22.2 12.8 9.1 0.3 0.0 0.0 9.1 0.0 0.0 0.0 0.0 0.0 0.0 24.8 10.0 9.3 5.5 0.0 0.0 9.3 0.0 0.0 0.0 0.0 0.0 0.0 122.5 51.5 61.3 9.7 0.0 0.0 6.0 55.3 0.0 0.0 0.0 0.0 0.0 121.5 50.1 66.2 5.1 0.0 0.0 0.0 16.7 49.5 0.0 0.0 0.0 0.0 122.4 66.1 52.6 3.7 0.0 0.0 0.0 0.0 16.9 35.7 0.0 0.0 0.0 119.3 67.1 48.9 3.3 0.0 0.0 0.0 0.0 0.0 0.0 48.9 0.0 0.0 118.8 65.9 33.4 3.8 15.7 0.0 0.0 0.0 0.0 0.0 33.4 0.0 0.0 129.1 70.2 52.1 6.7 0.0 0.0 0.0 0.0 0.0 0.0 36.4 15.7 0.0 105.2 19.9 84.4 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 84.4 19.9 0.0 19.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 19.9 Total Waste 2,236.8 1,075.4 Placed Dyke 507.3 507.9 44.4 15.7 21.8 73.4 72.0 66.3 35.7 118.7 15.7 104.4 1: Total waste includes interburden and overburden, these material are not diffirentiated in the scheduling software and cannot be presented individually 2: Reclamation material either stockpiled or direct placed WODA EODA West Overburden Dump Area East Overburden Dump Area 14 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-2 Mineable Oilsands Reserves and Production Year Total Ore Mined (Mt) Total Ore Rejects (Mt) Total Ore Extraction (Mt) 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020-2024 2025-2029 2030-2034 2035-2039 2040-2044 2045-2049 2050-2054 2055 38.3 56.8 60.7 60.6 65.9 64.5 59.1 56.5 59.1 61.6 313.5 312.0 302.5 308.2 306.3 317.1 300.7 21.2 1.4 2.1 2.2 2.2 2.4 2.3 2.1 2.0 2.1 2.2 11.4 11.3 11.0 11.2 11.1 11.5 10.9 0.8 36.9 54.8 58.5 58.4 63.6 62.2 57.0 54.4 56.9 59.4 302.1 300.7 291.5 297.0 295.2 305.6 289.8 20.4 Bitumen (wt %) 12.3% 12.1% 11.4% 11.2% 11.1% 11.2% 12.0% 12.1% 12.7% 12.3% 11.5% 11.6% 11.9% 11.7% 11.7% 11.4% 11.6% 11.6% Extraction Ore Quality Water Course (wt %) (wt %) 4.7% 76.7% 4.7% 76.7% 4.7% 73.3% 4.7% 72.5% 4.7% 75.1% 4.7% 75.2% 4.7% 77.3% 4.7% 76.0% 4.7% 76.1% 4.7% 76.3% 4.7% 76.3% 4.7% 75.3% 4.7% 76.5% 4.7% 75.9% 4.7% 74.5% 4.7% 75.0% 4.7% 74.3% 4.7% 75.3% Totals 2,764.5 100.2 2,664.3 11.7% 4.7% 1: Fines measured in Laser then converted to Sieve Hydrometer 15 of 70 75.4% Fines1 (wt %) 6.3% 6.6% 10.7% 11.7% 9.2% 8.9% 6.0% 7.3% 6.5% 6.8% 7.6% 8.5% 7.0% 7.8% 9.1% 9.0% 9.4% 8.5% 8.3% Recovered Barrels (Mbbls) 17.3 32.6 35.2 32.9 34.7 35.0 37.1 34.6 38.4 38.9 182.5 182.5 182.4 182.6 182.4 182.5 182.5 16.5 1,630.7 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 4 a production forecast for the life of the mine scheme by time period including • mined total waste • mined ore, bitumen grade and recovered barrels of bitumen • total tailings production by type 16 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-3 Tailings Production by Product Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020-2024 2025-2029 2030-2034 2035-2039 2040-2044 2045-2049 2050-2054 2055 Totals CST WT TT NST TSRU CST (Mt) 21.2 30.9 32.1 32.1 35.8 35.2 32.7 30.9 32.4 33.8 172.2 59.8 0.0 32.8 0.0 29.4 34.3 11.5 WT (Mt) 7.5 11.2 12.0 12.0 13.1 12.8 11.7 11.1 11.6 12.1 62.1 21.8 0.0 11.9 0.0 10.8 12.6 4.2 Plant Tailings TT (Mt) 1.3 2.7 3.9 3.9 3.5 3.1 2.2 2.4 2.3 2.6 14.1 5.5 0.0 2.8 0.0 2.9 3.5 1.1 NST (Mt) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 165.7 252.8 205.0 247.8 214.0 191.0 0.0 TSRU (Mt) 0.4 0.8 1.1 1.1 1.1 1.1 0.9 0.8 0.8 0.9 4.8 5.0 4.5 4.8 5.0 5.2 5.2 0.5 657.1 238.4 58.0 1,276.3 44.0 Coarse Sand Tailings Whole Tailings Thickened Tailings Non-Segregating Tailings - Combined CST with TT Tailings Solvent Recovery Unit 17 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 5 A table of waste material (overburden and interburden) classified by; • geological formation (Holocene, Pleistocene, Clearwater, McMurray, etc) with associated volume and weight • type and percent of material suitable for tailings impoundment construction • the amount projected for use in tailings impoundment construction 18 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-4 Dyke Construction Schedule Year Total Mine Waste Total Mine Waste Available Construction Material Construction Material Used Projected Percentage TT Pond Used for Starter Tailings Dyke Impoundment MFT1 Starter Dyke TT Pond Centreline Dyke MFT1 Upstream Dyke MFT2 Shear Key MFT2 Starter Dyke (Mt) (Mbcm) (Mbcm) (Mbcm) (%) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) Initial 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020-2024 2025-2029 2030-2034 2035-2039 2040-2044 2045-2049 2050-5054 2055 54.8 44.8 40.2 39.6 40.9 48.2 40.6 43.9 46.2 51.6 254.8 252.6 254.6 248.0 247.0 268.5 218.8 41.5 26.4 21.6 19.3 19.1 19.6 23.2 19.5 21.1 22.2 24.8 122.5 121.5 122.4 119.3 118.8 129.1 105.2 19.9 20.5 15.7 13.7 13.5 13.4 13.8 12.3 14.7 16.0 12.5 77.2 82.4 87.1 83.9 82.4 87.8 72.9 13.8 16.4 12.6 10.9 10.8 10.8 10.5 9.8 11.8 12.8 10.0 51.5 50.1 66.1 67.1 65.9 70.2 19.9 0.0 80% 80% 80% 80% 80% 77% 80% 80% 80% 80% 67% 61% 76% 80% 80% 80% 27% 0% 11.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.3 10.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.8 10.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 10.8 10.8 2.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Totals 2,236.8 1,075.4 733.6 507.3 69% 11.1 3.1 12.9 1.2 11.3 24.1 19 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-4 Dyke Construction Schedule continued Dyke 1 Dyke 2 Dyke 3 Dyke 4 Crusher Slot Dyke Dyke 5 Dyke 6 Perimeter Dykes (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) (Mbcm) Initial 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020-2024 2025-2029 2030-2034 2035-2039 2040-2044 2045-2049 2050-5054 2055 0.0 0.0 0.0 0.0 0.0 6.8 7.3 8.8 12.8 10.0 47.4 28.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.7 2.6 3.0 0.0 0.0 4.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 7.3 15.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 21.0 32.5 26.7 28.5 4.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 23.3 24.9 32.4 5.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.0 59.3 18.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.6 0.0 0.0 1.0 1.4 0.0 Totals 121.2 11.3 22.7 113.3 2.5 85.9 82.8 4.0 Year 20 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 6 A table that schedules the source and destination of waste material by; • mass and volumes, classifying material by structure • material types- overburden, interburden, crusher rejects (or oversize), and tailings- used for structures • destination area, including DDA’s , external and in-pit waste disposal areas, external and in-pit tailings impoundment structures, and external and in-pit tailings areas INFORMATION REQUESTED HAS BEEN INCLUDED IN TABLE 2-4 AS PROVIDED WITH THE RESPONSE TO ITEM # 5 21 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 7 A starting baseline for all structures, including the present elevations of each waste material type within each structure 22 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2- 5 2010 Baseline for Tailings Structures MINE Structure Designed Volume (Mm3) Placed Volume (Mm3) Current Elevation (masl) Remaining Volume (Mm3) WODA Ph 1 WODA Ph 2 WODA Ph 3 EODA TT Pond Starter Dyke MFT1 Starter Dyke MFT2 Starter Dyke MFT2 Shear Key 23.1 73.4 72.0 66.3 15.8 17.6 24.1 11.3 5.9 0.0 0.0 0.0 4.7 14.5 0.0 0.0 318m N/A N/A N/A 324m 332m N/A N/A 17.2 73.4 72.0 66.3 11.1 3.1 24.1 11.3 Pond Designed Volume (Mm3) Placed Volume (Mm3) Current Elevation (masl) Remaining Volume (Mm3) TT Pond MFT Ponds 150.8 466.0 0.0 0.0 324m 332m 150.8 466.0 TAILINGS 23 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 8 A construction schedule, volume, and projected life span for each tailings impoundment structure 24 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-6 Tailings Activities Schedule Tailings Impoundment ETF - TT Pond ETF - MFT1 Pond ETF - MFT2 Pond Cell 1 Fluid Cell 1 Cell 2i Cell 2b Cell 3 C/L Dykes U/S Dykes MFT D# TT Dykes Contain Dyke TT C/L Dykes*, MFT1 West U/S Dyke* MFT1 U/S Dykes MFT2 U/S Dykes, MFT1 East U/S Dyke D1, D2, Pit Wall D2, Pitwall D1, D3, D4a, D5a D1, D4a, D4b, D5a, D5b, Pit Wall D5a, D5b, D6, Pit Wall Centre line Dykes Upstream Dykes Mature Fine Tailings Dyke Thickened Tailings 25 of 70 Start Cell Cell Cell 2015 2015 2015 2015 2030 Finish Cell Cell Cell 2029 2022 2039 2046 2051 Capacity 150.8 364.6 101.4 266.7 47.4 177.0 211.2 134.9 Pond Start 2010 2010 2014 2027 2026 2037 2043 2051 Finish 2055 2027 2019 2037 2055 2043 2052 2055 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 9 An illustration of fluid tailings impoundment and DDA capacity versus the associated storage requirements 26 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Figure 2- 4 Fluid Inventory and ETDA DDA Capacity by Elevation 370 360 Elevation (masl) 350 340 330 320 310 300 2010 2015 2020 2025 2030 2035 2040 2045 2050 2055 Year DDA Elevation 27 of 70 Tailings Elevation TT) Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Figure 2- 5 Fluid Inventory and ETDA (TT) DDA Capacity by Volume 60 50 Volume (Mm 3) 40 30 20 10 0 2,005 2,010 2,015 2,020 2,025 2,030 2,035 2,040 Year DDA Capacity Tailings Storage Requirements 28 of 70 2,045 2,050 2,055 2,060 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 10 Destination and description of each tailings type by structure, including mass, volume, and components (water, fines, sand and bitumen as a percent of ore) 29 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-7 Tailings Material Balance 30 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-7 Tailings Material Balance continued 31 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-7 Tailings Material Balance continued 32 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 11 A site wide tabulation and illustration of fluid inventory 33 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Table 2-8 Site-wide tabulation of fluid tailings inventory POND 2010 2011 3 3 2012 2013 2014 2015 2016 2017 2018 2019 2020- 2025- 2030- 2035- 2040- 2045- 2050- 20552024 2029 2034 2039 2044 2049 2054 2059 Mm 3.1 3.5 - 3 Mm 3.8 9.1 - 3 Mm 3.9 15.4 - 3 Mm 2.4 22.6 - 3 Mm 2.7 27.4 - 3 Mm 1.4 32.3 - 3 Mm 1.7 35.9 - 3 Mm 1.5 39.8 - 3 Mm 1.8 43.7 - 3 Mm 1.9 66.5 - 3 Mm 66.9 8.9 4.0 - 3 Mm 46.3 13.5 3.9 - 3 Mm 47.9 8.4 3.9 - 3 Mm 47.9 9.5 3.9 - 3 Mm 2.0 47.9 13.0 3.3 - 3 TT MFT FC 1 Cell 1 Cell 2i cell 2b Cell 3 Mm 0.5 1.7 - Mm 0.0 52.1 25.1 3.3 Mm 0.6 52.1 26.6 0.6 Total 2.2 6.6 12.9 19.3 25.0 30.1 33.7 37.6 41.3 45.4 68.4 79.8 63.7 60.2 61.3 66.1 80.6 79.9 34 of 70 3 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 Figure 2- 6 Site-wide tabulation illustration of fluid tailings inventory 90 80 70 50 40 30 20 10 Year 35 of 70 2054 2052 2050 2048 2046 2044 2042 2040 2038 2036 2034 2032 2030 2028 2026 2024 2022 2020 2018 2016 2014 2012 0 2010 Volume (Mm3) 60 Shell Canada Limited Jackpine Mine – Tailings Management Plan ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 12 A site wide fines and water balance Section 2 SITE WIDE FINES BALANCE HAS BEEN INCLUDED WITH TABLE 2-8 IN THE RESPONSE TO ITEM # 11 SITE WIDE WATER BALANCE WILL BE AVAILABLE IN Q2 2010 36 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 13 Mine scheme development maps by reporting period, and a text description of the major development activities as illustrated on each map 37 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 MINING AND TAILINGS SEQUENCES 2010 Period Pre-production activities will continue at Jackpine Mine in the first half of 2010, focusing on construction of the TT Pond Starter Dyke and MFT1 Starter dyke. Suitable fill material for the two starter dyke structures will be sourced from borrow areas within the mine footprint. All sourced borrow material will come from overburden stripping, primarily consisting of quaternary sediments. Commissioning and start-up of Jackpine Mine will occur in 2010. Lean oil sands (ore less that 7 wt% bitumen) will be delivered to the plant for early commissioning. Ore deliveries begin mid-year from the upper and mid-ore benches immediately south and west of the crusher pocket, which have been stripped of overburden as a borrow source. Starter dykes will be raised to a design height to achieve containment for startup. The TT Pond will provide initial containment for: • CST and WT produced during the first three months of operation. These tails will be bitumen and fines rich during commissioning and considered unsuitable for upstream dyke construction in the containment dykes for MFT1. These tails will be deposited off the east side of the MFT1 West Dyke, producing a beach that will buttress the MFT1 Dyke. • TT deposited in above water beaches when the Thickener becomes fully operational • A minimal water pond required to locate the sump and pumping equipment The MFT1 Pond starter dykes will provide initial containment for: • Commissioning water and Basal Pond containment • Lost cell sand from early cell construction • Beaching of CST and WT during the first winter. • Pond for clarification and consolidation of TFT and a clear water cap for plant reclaim • Freeboard to the pond level In the second half of 2010, it is expected that the tailings circuit will reach steady state production and separate stream tailings properties will normalize. Cell construction will be focused on the upstream dykes for MFT1 Pond during 38 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 the remaining cell construction season. Beaching of CST and WT will commence in MFT1 during the winter months. All TFT runoff will accumulate within the beached deposits with a clear water cap maintained on top of the pond for plant reclaim water. TT deposition to will commence after approximately three months of plant operation. Placement of suitable overburden borrow material will continue to the downstream side of the TT starter dyke during early production. The TT Pond and MFT1 Dykes will continue to receive suitable material throughout the year in order to establish the containment requirements without the benefit of a full cell construction season. Mine waste will be placed in the West Overburden Dump Area (WODA) Phase 1. WODA Phase 1 is the area offset from Canterra Road to the west and limited to a maximum elevation of 335 masl. 39 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-7 - Mining Status 2010 40 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2011 to 2013 Period Ore and waste mining will continue south of the crusher pocket, advancing west along the footprint of in-pit Dyke 1 and Dyke 2. Dyke footprint clearing with an additional minimum clearance will establish an approximate 1,800 m wide advance at the Base of Mineable Oil Sands (BMOS). The Fluid Cell 1 area south of the Ore Prep area and east of WODA will be completely cleared to BMOS during this period. Suitable material will continue to be placed in the TT Pond and MFT1 Pond dykes to supplement a cell sand deficiency throughout 2011. By the end of this period the majority of MFT2 starter dyke construction will be completed. The preliminary design of this structure includes excavation of a shear key in target sections along the starter dyke. The MFT2 starter dyke is designed to contain: • Lost cell sand from early cell construction • Beaching of CST and WT during the first winter • Sufficient Pond capacity to float the transfer barge • Freeboard to the pond level CST and WT will be used to construct containment dykes during cell construction season throughout this period. CST and WT will be discharged into beach deposits in MFT1 during winter operations. All TFT, MFT and free water will continue to pond within the beached deposits of both MFT Ponds. TT will be discharged into beaches throughout the year with a minimal pond established to continuously pump TFT and free water into MFT1 Pond. WODA Phase 1 will be filled to capacity during this period, and dumping will commence in WODA Phase 2. WODA Phase 2 design crosses Canterra Road to the west to a temporary boundary. The WODA Phase 2 boundary is established to allow completion of the resource delineation along the west side of the ultimate WODA footprint. 41 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-8 - Mining Status 2011 42 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-9 - Mining Status 2012 43 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-10 - Mining Status 2013 44 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2014 to 2019 Period Ore and waste mining will continue to advance west, targeting exposure of the Dyke 1 footprint at BMOS to the east mining limit. Prestripping will reach the southeast limit of the Cell 1 area in 2016. Prestripping will then turn to strip to the south limit of Cell 1 and north to establish prestrip benches in the Cell 2 area. MFT2 starter dyke construction will be complete in 2014. Upon completion of the starter dyke, all suitable material will be utilized in-pit to construct Dyke 1 and Dyke 2, which will ultimately contain Cell 1 and Fluid Cell 1. Construction of Dykes 1 and 2 will continue throughout this period. MFT2 Pond will begin operation in 2014, operating in tandem with MFT1 Pond, with an objective of raising MFT2 containment to the same elevation as MFT1, resulting into a single pond and thereby eliminating the cross dyke separating the two ponds. Alternating seasons of summer cell construction and winter beach deposition will continue, with priority deposition focused in MFT2. All TFT, MFT and free water will continue to pond within the beached deposits of both MFT Ponds. TT discharge will continue to the TT Pond Mine waste placement will continue in WODA Phase 2 throughout the period. 45 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-11 - Mining Status 2014 46 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-12 - Mining Status 2015 47 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-13 - Mining Status 2016 48 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-14 - Mining Status 2017 49 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-15 - Mining Status 2018 50 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-16 - Mining Status 2019 51 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2020 to 2024 Period Ore and waste mining will complete clearing of the entire Cell 1 area. The mine advance will turn north, with focus on clearing Dyke 3 and Dyke 4 footprints to BMOS, which will provide containment for Cell 2. All suitable material available will be placed in Dykes 1 and 2. Dyke 2 will be completed to design elevation, providing full containment for Fluid Cell 1. Dyke 1 will be tied into the east mine highwall to provide initial containment in Cell 1. Some material placement will be required in the upper lifts at the east end of Dyke 1 to complete construction to final design elevation. MFT1 and MFT2 Ponds will be merged into a single MFT Pond. Alternating seasons of summer cell construction and winter beach deposition will continue to the MFT Pond. All TFT, MFT and free water will continue to pond within the beached deposits of both MFT Ponds. TT discharge will continue to the TT Pond WODA Phase 2 will be filled to capacity during this period, and dumping will commence in WODA Phase 3. WODA Phase 3 design extends to the ultimate WODA limit and final design elevation. 52 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-17 - Mining Status 2020 to 2024 53 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2025 to 2029 Period Mine advance will continue north, with focus on clearing Dyke 3 and Dyke 4 footprints to BMOS. All suitable material available will be placed in Dykes 1 and 4. Dyke 1 will be completed to design elevation to provide full containment for Cell 1. Construction of Dyke 4 will be commenced at the south end along the tie-in with the mine highwall, adjacent to the Ore Preparation area. Alternating seasons of summer cell construction and winter beach deposition will continue in the ETDA until 2026, when the MFT Pond will reach final design capacity. At this time, tailings production will be switched to NST technology, with in-pit deposition into Cell 1. The NST will be deposited in Cell 1, with continuous removal of TFT and free water from the cell, which will be pumped to Fluid Cell 1 for clarification. TT discharge to the TT Pond will be suspended when NST production starts. NST deposition to Cell 1 will continue through the end of the period. Mine waste placement will continue in WODA Phase 3 until it is filled to design capacity. When WODA reaches final design capacity, dumping will commence in the East Overburden Disposal Area (EODA). EODA design limit is offset from the Cell 1 east-mining limit, overlaying the Pleistocene Channel Aquifer between Jackpine Mine and Syncrude’s proposed Aurora South Mine. 54 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-18 - Mining Status 2025 to 2029 55 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2030 to 2034 Period The mine advance will continue north, with focus on clearing Dyke 3 and Dyke 4 footprints to BMOS. The footprint will also be cleared for Dyke 3, which is an intermediate (overtopping) dyke established to generate an intermediate tailings containment within Cell 2, prior to the entire cell becoming available. All suitable material available will be placed in four in-pit dykes. Dykes 4 and 5 will be constructed for Cell 2 containment. Dyke 3 is designed to adequate height to provide initial containment for Cell 2-intermediate (Cell 2i), in conjunction with the south sections of Dykes 4 and 5 (Dykes 4a and 5a). A plug of construction material will be placed in the crusher pocket to seal off the Ore Preparation area from the west side of Cell 2, necessitating a relocation of the dump pocket. Construction of all four dykes will continue throughout the period. NST production will continue throughout the period with deposition in Cell 1. All TFT and free water will be pumped to Fluid Cell 1 for clarification. Mine waste placement will continue in EODA until it is filled to design capacity. When EODA reaches capacity, dumping will commence in the in-pit dump located in the southeast corner of Cell 2. 56 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-19 - Mining Status 2030 to 2034 57 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2035 to 2039 Period The mine advance will continue north, clearing out the remainder of Cell 2 to the BMOS. The mine advance will then split to progress west and east from Cell 2. The west advance will clear footprint to establish additional in-pit dump space, and the east advance will clear footprint to establish Cell 3. Suitable material placement will continue in Dykes 3, 4, 5 and the Crusher Pocket Dyke. Dykes 3, 4a, 5a and the Crusher Pocket Dyke will be constructed to final design elevation, providing full containment in Cell 2i. Construction of the north section of Dykes 4 and 5 (Dykes 4b and 5b) will continue to the end of the period. NST production will continue with deposition in Cell 1 until 2035. At this time NST production will switch to separate stream technology, with CST placed over the NST to form the final (upper) 5 m of the Cell 1 deposit. CST capping of Cell 1 will occur in 2035 and 2036, and all TT produced will be deposited in the ETDA TT Pond. Upon completion of Cell 1 CST capping, tailings production will switch back to NST technology with deposition in Cell 2i. All TFT and free water will be pumped to Fluid Cell 1 for clarification. All mine waste will be placed in an in-pit dump located in the northwest corner of Dyke 4. 58 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-20 - Mining Status 2035 to 2039 59 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2040 to 2044 Period The west mine advance will progress to establish a footprint for expansion of the in-pit dump in that location. The mine fleet will be reallocated to join the remaining fleet on the east mine advance focused on clearing Dyke 6 footprint at BMOS. Suitable material placement will continue in Dykes 4b, and 5b. Both dykes will be tied-in to the north mine highwall to establish containment in Cell 2. Some material placement will be required in the upper lifts at the north end of both dykes to complete construction to design elevation. NST production will continue with deposition in Cell 2i until 2042. At this time NST deposition will commence in the remainder of Cell 2 and continue through the end of the period. All TFT and free water will be pumped to Fluid Cell 1 for clarification. All mine waste placement will continue in an in-pit dump located in the northwest corner of Dyke 4 60 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-21 - Mining Status 2040 to 2044 61 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 2045 to 2055 Period The mine fleet will be split to advance east and west, clearing all of the remaining mine footprint. Suitable material will be placed in three in-pit dykes. Dykes 4b, and 5b will be completed to final design elevation. Dyke 6 will be constructed to provide containment for Cell 3, which is the final in-pit cell. NST production will continue, with deposition in Cell 2 until 2049. The CST cap will be placed over the NST 2049 and 2050. Upon completion of Cell 2 CST capping, tailings production will switch back to NST technology with deposition in Cell 3 from 2050 to 2054. The CST cap will be placed over the Cell 3 NST in 2054 and 2055. All TT produced will be deposited in the ETDA TT Pond. All TFT and free water will be pumped to Fluid Cell 1 for clarification. Mine waste will be placed in three in-pit dumps. The dump located in the northwest corner of Dyke 4 will be filled to capacity. A dump will be established along the east side of Dyke 6, and a berm fill dump will be constructed along the ultimate west mine highwall adjacent to the Muskeg River. 62 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-22 - Mining Status 2045 to 2049 63 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Figure 2-23 - Mining Status 2050 to 2055 64 of 70 Section 2 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 14 A summary of tailings water chemistry, seepage water chemistry, and seepage water rates into the groundwater from reports of groundwater and tailings monitoring programs provided to AENV, 65 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 SUMMARY OF TAILINGS WATER AND SEEPAGE WTER CHEMISTRY Jackpine Mine Phase 1 is still in construction and therefore this tailings management plan is being submitted in advance of any tailings deposition. Once tailings deposition activities are underway details of water chemistry, seepage water chemistry, and seepage water rates into the groundwater will be provided in annual monitoring reports submitted to Alberta Environment. 66 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 15 A description of the process for remediation or rehandling of segregated fines within the DDAs within one year of segregation 67 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 REMEDIATION OR REHANDLING OF SECREGATED FINES Any material not meeting the sand to fines ratio (SFR) of TT within JPM DDA 1 will be remediated in place such that it meets the strength criteria required by Directive 074. Any fluids disaggregating from TT placed in JPM DDA 1 will be pumped to the adjacent MFT cell, and recycled back into the NST production process. 68 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 2 ERCB Directive 074 Appendix E Annual Tailings Management Plan Item # 16 Planning assumptions and criteria used to support the tailings management plan, such as fines distribution in the ore body, tailings stream-specific gravities, tailings consolidation curves, tailings deposition angles, and tailings impoundment design and construction criteria 69 of 70 Shell Canada Limited Jackpine Mine – Tailings Management Plan Stream CST (cell/berm) CST (beach) TT TSRU WT (beached) MFT NST (on-spec) NST (off-spec) Beach Above Water slope (%) Beach Below Water slope (%) Dry Density N/A 2.5% 0.8% 0.1% 1.5% N/A 1.0% 1.5% N/A 6.6% 3.0% 10.0% 6.6% N/A 4.0% 5.0% 1.69 1.51 0.85 0.93 1.51 0.37 1.62 1.55 (t/m³) Section 2 % Fines to TFT1 1: Planning was performed based on Sieve Hydrometer fines TFT Thin Fine Tailings CST Coarse Sand Tailings TT Thickened Tailings TSRU Tailings Solvent Recovery Unit WT Whole Tailings MFT Mature Fine Tailings NST Non Segregating Tailings 70 of 70 50% 50% 30% 40% 50% N/A 20% 50% Slurry Density Void ratio (% solids) 55% 55% 51% 12% 47% N/A 67% 57% 0.57 0.75 2.12 1.85 0.75 5.63 0.64 0.71 Shell Canada Limited Jackpine Mine – Tailings Management Plan Page 1 of 11 Section 3 Shell Canada Limited Jackpine Mine – Tailings Management Plan Page 2 of 11 Section 3 Shell Canada Limited Jackpine Mine – Tailings Management Plan 3.0 Section 3 TAILINGS MEASUREMENT PLAN SUBMISSION Introduction The information contained in this section of the Tailings Management Plan is in response to the letter dated May 29, 2009 from the ERCB requesting Shell’s plans for monitoring, measurement, and sampling that will be implemented to enable reporting on the fines in oil sands feed and tailings as required in ERCB Directive 074. The Measurement Plan described here will be applied similarly for both the Muskeg River Mine (MRM) and the Jackpine Mine (JPM). Routine sampling and measurement of the fines in the oil sands feed is well established as described below and was provided to the ERCB in a letter dated January 16, 2009 on Shell’s measurement practices. In contrast, the extensive sampling and measurement of fluid and solid tailings deposits as required in Directive 074, have not been conducted routinely. Therefore the specific plans and methodologies for monitoring, sampling and measurement are still under development. The plans and progress of this development are described below. Oil Sands Feed Measurement The determination of volumes and characterization of ore and waste for planning purposes are based on the results from a comprehensive sampling and measurement plan within the orebody. These results are used to create a computer-based geologic model that is referenced on a daily basis to determine the volumes and characteristics of the mined ore and waste materials. Ore Measurement Plan Geologic characterization of the orebody will follow a similar convention of previous core drilling, core sampling and testing. Field Execution: The annual ore characterization drilling program begins with a review of existing geologic information, followed by the execution of a winter field drilling program consisting of several hundred coreholes for both the Muskeg River Mine (MRM) and Jackpine Mine (JPM). The drill hole spacing begins at approximately 400 m and decreases to a spacing of approximately 100 m in advance of mining. The 100 m drilling grid density is required for detailed mine planning and to further characterize the ore for processability. In areas of increased geologic complexity, drill hole spacing may be reduced to 50 m to improve data resolution. Page 3 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Holes to characterize the Quaternary are drilled over each corehole from the same pad and intersect the top of the McMurray Formation. This process is illustrated in Figure 3.1: Overview of Quaternary and Oil Sand Sampling. Ore Characterization: All coreholes are completed with a full suite of downhole wireline geophysical logs consisting of gamma, resistivity and density logs. These logs are used for depth corrections during the core logging phase as well as for ore characterization. All holes are cored from top of the McMurray Formation to the base of the last significant occurrence of bitumen. In the 400 m drilling grid areas, holes are cored to Devonian, while in the 100 m area, holes may be terminated in the water bearing Lower McMurray Member. Core Logging & Photography The cores are transported to a core facility where they are frozen and subsequently cut into 0.75 m lengths, and then slabbed or cut longitudinally into two parallel pieces. One side of the cores are depth corrected with resistivity logs. The cores are assigned facies according to the Shell oil sands facies scheme and described for any anomalies within the facies. Facies intervals can be 0.3 m or larger, though interval maximum is commonly 1.5 m. This interval is a function of the complexity of the geology for a given area. After logging, cores are photographed digitally with sample intervals noted. Sampling The second side of the slabbed cores are sampled from the top of McMurray Formation to the last significant occurrence of bitumen. Samples are selected by facies interval at the minimum 0.3 m interval, or can be composited to between 0.5 m and 1.5 m for Dean Stark analysis of bitumen samples and up to 3.0 m for particle size distribution. Sampling always remains within unique consecutive facies intervals (i.e. non-unique facies boundaries are not crossed). Occasionally samples are also tested for soluble ions (connate water chemistry) and/or clays (methylene blue index, MBI). Testing Samples are tested for per cent weight bitumen using the Dean Stark analytical method by difference. A quality assurance program is run in parallel with the lab program. Every 20th sample is run in duplicate, with the second sample Page 4 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 tested for per cent weight bitumen using the Dean Stark method by closure. The purpose of this duplicate test is to ensure internal lab repeatability. In addition, for each core tested a reference sample is analyzed and results are compared to known values for accuracy assessment of both Dean Stark methods. The sample retains from the Dean Stark test are either tested individually or composited for particle size distribution (PSD) analysis up to 3 m intervals. As with bitumen, each sample only consists of unique facies intervals. PSD is currently determined using the laser diffraction methodology utilizing Malvern Mastersizer 2000 (M2000) equipment. A correlation between the M2000 laser diffraction and the ASTM sieve hydrometer methodologies has been developed. This correlation is used to compile and report the fines data on a consistent basis. As noted in ERCB D-074, Appendix A, “Fines” is defined as: “Fines: Mineral solids with particle sizes equal to or less than 44 µm based on sieve-hydrometer analysis or a method approved by the ERCB.” Therefore, Shell will review with the ERCB the M2000 laser diffraction methodology and share the results of the sieve-hydrometer correlation study to confirm the use of the laser diffraction method. Continual Analytical Improvement Consistent characterization of particle size distribution of bitumen saturated granular material is challenging. Shell is continually looking for opportunities to improve this process and will monitor industry development for improvements to laboratory methods using alternate analyses. Plant Feed The ore feed from the mine faces into the plant is measured by weight or volumes by field survey of the area mined, which are then correlated back to the geologic model to determine ore characteristics including the fines content. Feed from the ore stockpile is determined from truck counts assuming a standard mass per load with characteristics including fines determined from field sampling and testing. The ore conditioning plant reject material is measured from truck count assuming a standard mass per load and the characteristics including fines determined from field sampling and testing. Page 5 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Tailings Measurement Plan Measurement of Tailings Deposits in DDA’s and Fluid Tailings Ponds Since start up in 2002 Shell has focussed on monitoring the mudline as a means of managing the volume of clear water above the mudline for plant recycle at the External Tailings Facility (ETF). Therefore, methodologies for monitoring, sampling and measurement in Dedicated Disposal Areas (DDAs) and fluid ponds as required in ERCB Directive 074 are under development. Fluid and solid deposits, as defined by ERCB criteria, are expected to be present in both fluid ponds and DDAs. Shell has undertaken an extensive trial measurement program at the MRM External Tailings Facility (ETF) to test and compare several field procedures for drilling, sampling and measurement of tailings materials and properties. Experience and results from this program will form the basis for ERCB reporting requirements, beginning in 2010. Investigation of Methodologies for Field Sampling and Testing: Figure 3.2 shows the scope of the 2009 MRM ETF trial program, with fieldtesting and sampling locations to be used for tailings monitoring, planning, management and reporting to the ERCB. The methodology has two basic components: Fluid surfaces will be investigated using a grid approach; initial grids will be 200 m by 200 m and will be adjusted as required to suit the surface area to be investigated. Sand dykes and beaches will be investigated using a cross section approach starting from the dyke crest extending down the beach into the pond. Where possible, cross sections will align with cross sections required for geotechnical assessment of dyke structures as shown in Figure 3.2 for the MRM ETF. The field component of this program was completed in September 2009. Laboratory work will begin in October 2009. Programs for surveying fluid ponds are described in general in the following text and will be adjusted for each pond’s specific use, information need, and container geometry. The fluid clear water to mudline contact will be probed from a boat on a grid pattern of 200 m by 200 m, however this pattern has not been indicated in Figure 3.2. The grid will overlap cross sections in some locations. Fluid tailings samples will be collected at grid locations at regular intervals to pond bottom. Sampling intervals will be determined for each fluid and solid tailings pond. Page 6 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Samples were collected at 0.5 m intervals from the MRM ETF in the 2009 trial program to provide a large sample baseline for investigation, however the intervals would be increased when modelling indicates a higher degree of deposit homogeneity. Several locations in the 2009 trial program are sampled to assess field strength testing and sampling methods. Field strength tests include Cone Penetration Test (CPT), Sonic Penetration Test (SPT), vane shear and ball penetration tests. The sonic core and SPT sampler collect solids samples. Grab samples are also taken from the surface of the beach or cell where surface density testing is performed. Sonic core, piston sampler, wireline sampler and suction sampler collect fluid and soft tailings samples. Figure 3.3 shows the layout of MRM in-pit Cell 1, the first DDA for MRM. Insert Figures 3A and 3B show a schematic of the locations for sampling fluids and beaches in the DDA, respectively. The methodology follows the same used for the MRM ETF, which is described at the beginning of this section. Figure 3.4 shows the layout of JPM’s DDA, the thickened tailings pond. Insert Figures 4A and 4B show the overall ETF layout and a schematic of the locations for sampling fluids and beaches in the DDA, respectively. The methodology follows the same used for the MRM ETF, which is described at the beginning of this section. Field Equipment Safety of field personnel is paramount in completing tailings field investigations using conventional and specialized investigation vehicles. Site conditions range from solid and trafficable to fluid, potentially liquefiable surfaces with the possible presence of volatile hydrocarbons. Therefore, investigations will not be performed when suitable preventive safeguards are not in place or are not feasible. Aerial tailings deposits (cell sand, beach above water) will be investigated along longitudinal cross sections from the cell or beach crest out to the fluid pond as far as it is safe to use track mounted equipment. The soft above water beaches close to the pond edge and the below water beaches will be investigated by extending the cross section into the pond using amphibious and or barge mounted equipment. Page 7 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Sample and Data Collection Common data is required from above water and below water deposits including: Particle size distribution Density Strength data (drained and/or undrained) Pore pressure response Changes with time Sample frequency and density will be adjusted according to the results from annual campaigns, complexity, and behaviour of the tailings deposit in question. Shell’s initial approach will be to gather a robust initial data set and scale up or down in future campaigns. Changes to the campaigns will be based on technical assessment and justification. Data will be presented in formats consistent with ERCB reporting requirements. These will be determined in consultation with the ERCB. Statistical methods will be applied to support broader deposit interpretations from the trial program cross-sections and grid sample points. Field and Laboratory Testing Methods and Procedures Shell needs to evaluate and detail several test methods and laboratory procedures. A program on the tailings test methods and laboratory procedures is being initiated and will be completed to support submissions to the ERCB in September 2010. Page 8 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Figure 3.1 Overview of Quaternary and Oil Sand Core Auger Rig or Sonic S S Unit B S Unit C S Unit D 1.5 m S 1.5 m McMURRAY (oil sand: ore or waste) S 1.5 m Set casing above Cretaceous Quaternary Minimum Sampling Requirements Send to Lab A for: • Particle Size Distribution (sieve) ASTM D 6913-04 • Hydrometer if fines>10% ASTM D 422-63 • Moisture Content ASTM D 2216-05 • Atterberg limits if fines>10% S 1.5 m QUATERNARY 1.5 m Unit A Unit E S1 S13 Min. 1.5 m into Km S End of auger or sonic Unit G 1.5 m Unit H 1.5 m DEVONIAN McMurray Minimum Sampling Requirements Send to Lab B for: • PSD (laser) • Assay (Dean Stark Method) 1.5 m S12 Unit F 1.5 m S1 S Note that the geological unit sampled governs the tests required and hence the lab, not the drilling method. S1 – S4 sent to Lab A S5 – S13 sent to Lab B Min. 3 m into Dw Clearwater will be tested at Lab A unless noted otherwise End of core Page 8 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Figure 3.2 Page 9 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Figure 3.3 Page 10 of 11 Shell Canada Limited Jackpine Mine – Tailings Management Plan Section 3 Figure 3.4 Page 11 of 11