Applicant. - Energy Regulatory Commission
Transcription
Applicant. - Energy Regulatory Commission
Republic of the Philippines ENERGY REGULATORY COMMISSION San Miguel Avenue, Pasig City IN THE MATTER OF THE APPLICATION FOR APPROVAL OF THE PROPOSED CAPITAL EXPENDITURE PROJECTS FOR THE YEARS 2011 TO 2014 ERC CASE NO. 2012-043 RC NUEVA VISCAYA COOPERATIVE, (NUVELCO), ELECTRIC INC. Applicant. )(- ------- -------------- -)( DECISION Before the Commission for resolution is the application filed on March 21, 2012 by Nueva Viscaya Electric Cooperative, Inc. (NUVELCO) for approval of its capital expenditure (CAPEX) projects for the years 2011 to 2014. Having found said application sufficient in form and in substance with the required fees having been paid, an Order and a Notice of Public Hearing, both dated April 10, 2012, were issued setting the case for initial hearing on May 16, 2012. In the same Order, NUVELCO was directed to cause the publication of the Notice of Public Hearing, at its own expense, twice (2x) for two (2) successive weeks in two (2) newspapers of general circulation in the Philippines, with the date of the last publication to be made not later than ten (10) days before the date of the scheduled initial hearing. It was also directed to inform the consumers within its franchise area, by any other means available and appropriate, of the filing of the instant application, its reasons therefor and of the scheduled hearing thereon. The Office of the Solicitor General (OSG), the Commission on Audit (COA) and the Committees on Energy of both Houses of Congress were furnished with copies of the Order and the Notice of Public Hearing and were requested to have their respective duly authorized representatives present at the initial hearing. ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 2 of 24 Likewise, the Offices of the Provincial Governor of Nueva Viscaya and the Mayors of the City and Municipalities within NUVELCO's franchise area were furnished with copies of the Order and Notice of Public Hearing for the appropriate posting thereof on their respective bulletin boards. On May 7,2012, NUVELCO filed its "Pre-Trial Brief'. During the May 16, 2012 initial hearing, only NUVELCO appeared. No intervenor/oppositor appeared nor was there any intervention/opposition reg istered. At the said hearing, NUVELCO presented proofs of its compliance with the Commission's posting and publication of notice requirements which were duly marked as Exhibits "A" to "0", inclusive. Thereafter, it conducted an expository presentation of its application. At the termination of the expository presentation, the Commission conducted the pre-trial conference where NUVELCO presented its proposed facts and issues relative to the instant application. NUVELCO presented the following witnesses in support of its application: 1) Engr. Epifanio P. Mendoza, its Engineering Manager, who testified, among others, on the following: a) his participation in the preparation of the instant application; b) his participation in the preparation and development of the feasibility study for the proposed CAPEX; and c) the total estimated cost of the projects; and 2) Mr.Wilfredo N. Acasio, its Financial Consultant, who testified, among others, on the following: a) his participation in the financing plan for the proposed CAPEX; b) the funding requirement of the proposed projects; c) the financial resources of NUVELCO; and d) the projects' rate impact. In the course of their direct examinations, additional documents were presented and duly marked as exhibits. The direct examinations having been terminated, the Commission propounded c1arificatory questions on the said witnesses. NUVELCO was, then, directed to file its formal offer of evidence. On May 29, 2012, NUVELCO filed its "Formal Offer of Evidence" which is hereby admitted for being relevant and material in the final resolution of this case. On March 20 to 22, 2013, the Commission conducted an ocular inspection on NUVELCO's assets subject of the instant application. ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 3 of 24 On January 22, 2014 a~d February 17, 2014, the Commission issued the Orders directing NUVELCO to submit various documents. On March 28, 2014, NUVELCO filed its "Additional CAPEX Requirements" in compliance with the aforesaid directives. DISCUSSION NUVELCO sought the Commission's approval of the following capital projects for the years 2011 to 2014: Proposed Project Primary 1 Distribution Name 2011 - Installation of Three-phase 3 Installation of Fuse Cut-out and Auto-link Resettable Electronic Sectionalizer along lateral distribution lines 4 Installation of Substation and Solano Substations 5 Installation of Revenue Meter to Alfonso Castaneda Acquisition Auto-recloser Feeder Metering at Bambang of Distribution Upgrading Replacement Secondary Distribution Replacement of Overloaded 9 Replacement Clustering of Kilowatt-hour Distribution Transformers meter and Meter due to Add-on Projects Acquisition of Lineman's Tools Set Acquisition of Vehicles Acquisition of Meter Reading/Billing Acquisition of Office Furnitures and Equipment 16 Acquisition Hardware of Engineering Analysis Software and 17 Acquisition of Accounting, Payroll, Warehousing and Member-Consumer Information System Software Acquisition Construction Acquisition 2,770,307.98 1,872,640.00 4,771,402.08 8,308,389.06 1,762,676.00 - - 268,800.00 - 268,800.00 - 499,520.00 4,905,309.89 4,717,929.15 5,264,232.36 5,190,715.29 12,287,546.52 12,766,226.60 18,298,683.53 15,075,322.64 499,520.00 20,078,186.69 58,427,779.28 8,956,631.42 10,706,928.02 12,015,039.22 14,307,633.16 45,986,231.82 9,424,052.18 9,958,079.80 10,450,169.45 11,066,385.93 40,898,687.35 4,610,320.11 4,985,262.74 5,385,941.99 5,814,908.94 20,796,433.78 - of Test Instruments 18 19 20 2,558,439.68 - Projects Acquisition 11 12 13 14 15 949,760.00 2,419,945.56 Projects Connection of New Customers (KWh meters & accessories) Non-network 1,216,965.40 922,880.00 2,351,456.52 Total (PhP) 2014 2013 Projects 8 10 Materials of Rotten Poles Other Network Cost (PhP) Projects Installation of Air Break Switches 2 6 7 Project 2012 4,488,000.16 - Gadgets of Street Lighting Equipment of NUVELCO Office Buildings & Facilities 268,800.00 50,215,945.68 Total (PhP) Performance System Assessment - 3,296,160.00 8,369,760.00 - 213,640.00 890,400.00 571,032.00 807,520.00 22,094,960.16 2,907,072.00 2,180,360.00 - 6,968,925.98 - - 6,968,925.98 - 7,500,000.00 - - 7,500,000.00 593,600.00 7,447,721.36 - 576,800.00 12,643,226.20 1,120,000.00 - 2,340,800.00 24,622,104.44 1,120,000.00 88,810,338.69 74,855,561.45 560,000.00 2,730,000.00 of Office Stand-by Power Generator 571,032.00 807,520.00 5,941,040.00 2,907,072.00 807,520.00 of NUVELCQ's 610,400.00 1,801,156.88 59,138,998.84 Existing Distribution NUVELCO serves the Province of Nueva Viscaya which comprises of fifteen (15) Municipalities, namely: Ambaguio, Aritao, Bagabag, Bayombong, Bambang, Diadi, Dupax del Sur, Dupax del 273,020,844.65 ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 4 of 24 Norte, Kasibu, Kayapa, Quezon, Santa Fe, Solano, Villaverde and Alfonso Castaneda. At present, there are three (3) substations that cater the energy requirements of NUVELCO with a combined rated capacity of 35 MVA. Two (2) of the three (3) substations, the Solano and Bambang Substations, are owned by NUVELCO while the other substation, the Bayombong Substation, is owned by the National Grid Corporation of the Philippines (NGCP). NUVELCO owns about 14.36 kilometers of 69 kV subtransmission lines. As of year-ending 2010, there are eleven (11) feeders being supplied by the substations consisting of a total of 1,450.40 circuit kilometers of primary distribution lines and 1,290.76 circuit kilometers of secondary distribution lines. As illustrated below, the single phase lines dominate the medium voltage segment with a total length of 913.16 km. or more than one half of the entire segment. These are elongated and over extended lines intended to supply the power requirements of the consumers all throughout the far flung barangays: SYSTEM LINE CONFIGURATION (km) The figures below show the type of consumers being served by NUVELCO as of year 2010. Its residential consumers reflect the large area being served as a rural countryside. 62,794 out of 67,939 total consumers of the cooperative or 92% of the market are residential consumers followed by commercial customers with a market share of 3%. The remaining 5% of the market is composed of public industrial, buildings, street lights, sale for resale, and temporary customers. ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 5 of 24 CUSTOMER CLASS Public8uildin~lree~ l~~hIS 1,~5;.'00 1~ Commercial 2,314.00 3% In terms of energy sales, the residential consumers contribute to about 48,840 MWh or 630/0 of the entire sales of the NUVELCO, while industrial customers' share is 22%, as shown in the figure below. The remaining 150/0 share in the energy sales comprise of commercial, street lights, public buildings, sale for resale, and temporary customers. ENERGY SALES • Residential 48,840.00 63% • Temporary Customer 1,232.00 2% a Public Building 3,209.00 4% Bulk of the power requirements of NUVELCO are being sourced from the National Power Corporation (NPC) and San Miguel Energy Corporation (SMEC) through the 69 KV sub-transmission lines of the National Grid Corporation (NGCP). This constitutes 97.84% of its total energy requirements. The remaining portions are being supplied by FRENDCO mini-hydro at 1.44% and Aurora Electric Cooperative, Inc. (AURELCO) and Nueva Ecija II Electric Cooperative, Inc. - Area 2 (NEECO II Area 2) at 0.72%. AURELCO is supplying three (3) barangays in the Municipality of Alfonso Castaneda while NEECO II Area 2 is supplying two (2) barangays in the Municipality of Dupax del Sur and three (3) barangays of Alfonso Castaneda. ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 6 of 24 NUVELCO's energy purchases and sales for the past seven (7) years are directly proportional as illustrated in the figure below. An increase on both the energy purchases and sales were significant annually for the last seven (7) years with an average annual growth rate of 6.1 % and 6.80/0, respectively. The increase in energy sales was brought about by the annual rural electrification program implemented by NUVELCO. Notably, NUVELCO did not meet the percent loss cap from the period presented below. There is an increase in system loss starting 2005 to 2007 with an average of 170/0 within the said period. A decrease in system loss, however, was experienced during the years 2008 to 2010 but still beyond the cap. Energy Profile (MWh) 100,000.00 --; .. l--~....._.... ! ~,~~ ~!.•• ~ ! 50,00000 40,000.00 30.000,00 20,000.00 t J.. ' : . . '-"i •- =~~' ! SALES (MWh) I l ,-. 1... 1 j III 10,000.00 .~ .... ~~ _-_.'--_.~:-. ---_ ..._,_ .. _- ~---_ .._"._._ _ ~~_,f._ .. ~8' :f .__ J Forecasting It is imperative to have an accurate energy, demand and customers of an electric determine the optimal project for a particular the appropriate solution which will redound consumers. forecast of the future cooperative in order to scenario and prescribe to the benefit of the There are two (2) methods of forecasting that may be utilized to calculate or estimate the future requirement of an electric utility. These are the Econometric Analysis which uses economic and demographic information to forecast the load as an input and Trend Analysis which requires only historical data as an input. The Econometric Analysis presents the most accurate for medium and long-term forecasting while the Trend Analysis is the widely used method of forecasting among the electric cooperatives which requires only the historical data as an input. This method of forecasting is best suited for short-term (5 years) planning, which ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 70f24 coherently meets the criteria for the planning period under ERC Resolution 26, Series of 2009. Under the Electric Cooperative's Distribution Utility Planning Manual (ECDUPM), all forecasting models formulated must be tested for validity and accuracy. Valid models should meet the following criteria for each statistical value: 1) Adjusted R2 should be at least 800/0for econometric analysis or 990/0for trend analysis; 2) 3) 4) P-value should be lower than 0.1; T-statistic should be greater than 2 or less than -2; and Mean Absolute Percentage Error (MAPE) should be less than 5%. NUVELCO simulated several forecasting models using trend analysis in order to produce accurate forecast of its future energy purchases, sales and customers. The table below shows the summary of the forecast that passed all the criteria mentioned above and was used by NUVELCO in its distribution development planning: Forecasting Energy Purchase (Distribution System) Energy Sales (Distribution System) c: 0 Distribution System :;::; tl a + bt + ce + dr' (double horizon) ce a + bt + (with horizon) 0.9960 0.9954 0.9939 a + be (double horizon) 0.9952 Bambang a + Ine+ Ine (with horizon) 0.9923 ~ c a + loge + loge (double horizon) Validity Adj. R2 (>0.99 or >0.8) Solano .c ::l 'tl Model Cll E Ql C Bayombong ce a + bt + (with horizon) 0.9937 l!! ~~ ~oi ~~ Distribution System a + logt + logt2 + loge 0.9985 0 Residential Commercial a + Int + Ine + Ine a + bt + logt (double horizon) 0.9986 0.9940 Tests t-stat (It I > 2) Accuracy p-value «0.1) a 41.4774 1.3136E-08 b -3.8346 0.00861289 c a 10.9931 3.36753E-05 6.6583 0.001153087 b 3.6243 0.015151358 c 2.0326 0.097787765 d 2.7446 0.040569866 a 37.0585 2.69454E-07 b 4.3427 0.007410199 c a 7.8745 0.000530813 37.9924 2.27698E-09 b 40.8751 1.36746E-09 a 43.0258 1.27982E-07 b -4.7086 0.005296242 c a 10.4168 0.0001405 33.7520 b 4.0724 0.009611044 c a 7.9105 0.000519575 146.5364 7.00747E-07 b 14.7063 0.000681991 c -9.5395 0.002443318 d a 10.4460 0.001872754 141.6215 7.76256E-07 b 14.0685 0.000777832 c -8.7556 0.003137498 d 9.6495 0.002362718 a 42.1917 1.18605E-08 b 21.1087 7.36684E-07 c -7.3455 0.000325701 Test MAPE «5%) 1.78% 2.95% 1.88% 3.07% 2.19% 4.29271 E-07 2.06% 0.24% 0.27% 1.93% ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 8 of 24 Public Building Street Lights a + be + logt (double horizon) a + Int + Ine + Ine (double horizon) a 0.9929 0.9949 b 8.4982 18.6008 c a 3.9468 26.1358 b 3.5753 -5.6177 c d a Temporary Customer a+bt+ce+de (with horizon) 0.9942 b c d Industrial a + be (with horizon) 0.9923 Sale for Resale a + be + logt 0.9928 a b a b c 8.9110 5.5927 4.3054 -4.5637 5.6091 42.5328 29.9906 4.9937 9.9184 3.6853 0.000145299 1.55779E-06 0.007565771 1.53227E-06 0.015954324 0.002473521 0.000296336 0.005015828 0.012591464 0.010309681 0.004962878 1.13027E-08 9.11615E-08 0.007523808 0.000580104 0.02110598 4.79% 1.92% 3.48% 3.73% 2.51% The energy purchase and sale of its entire distribution system, as well as the peak demand requirement of each substation and the entire distribution system was forecasted directly using the abovementioned trend methods. On the other hand, the number of customers in each class as well as the number of customer for the entire system was directly forecasted using the polynomial trend method. Subsequently, the forecasted data of each class were allocated to the forecasted number of customers of the entire system to produce a conservative and accurate forecast of the said parameter. I. PERFORMANCE ASSESSMENT NUVELCO identified and quantified the problems and categorized these requirements to address the safety, capacity (including customer requirements), reliability improvements and system loss reduction. It is worthy to note that the last CAPEX application of NUVELCO was filed in year 2007 under ERC Case No. 2007-123 MC. A. Safety The existing substations of NUVELCO are equipped with complete voltage and current protection systems. The 13.2/7.62 kV main feeder's protective devices are Automatic Circuit Breakers which main function is to interrupt power supply during abnormal circuit condition or faults. ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 9 of 24 B. Capacity NUVELCO's maximum rated capacity of its entire distribution system is 35 MVA. This comprises the merged capacities of the existing three (3) substations of NUVELCO. Based on the forecasted demand, as shown in the table below, the loading percentage of the entire distribution system within the CAPEX period is within the 700/0 criteria for capacity augmentation planning margin. All substations are also within the said margin except for the Solano Substation which will exceed the said margin starting the year 2011. No. 1 2 3 Substation Solano Bambang Bayombong Entire System c. Rated MVA Capacity Max. MVA Capacity Power Factor' Max. MW Capacity 10.00 12.50 89% 11.18 10.00 12.50 98% 12.28 15.00 35.00 18.75 43.75 97% 18.10 95% 41.45 Capacity Parameters MWDemand % Loading MW Demand % Loading MWDemand % Loading MWDemand % Loading Historical Forecasted 2010 2011 2012 2013 8.15 8.59 9.05 9.57 67.61% 72.89% 76.79% 80.94% 85.57% 5.79 7.20 7.59 8.00 8.46 47.10% 58.65% 61.78% 65.12% 68.85% 5.19 6.51 6.86 7.23 7.64 28.68% 35.97% 37.89% 39.93% 42.22% 17.16 17.57 18.47 19.49 20.65 41.40% 42.39% 44.55% 47.02% 49.83% Power Quality The Philippine Distribution Code (PDC) provides that the voltage levels at the customer's connection point must be within :f:100/0 of the nominal voltage level of 230 volts. In the instant application, the existing power quality of NUVELCO's distribution system complies with the said provision of the PDC, as shown in the table below. There were no low-voltage or over-voltage and unbalance voltage problem encountered within the system during peak and off-peak hours. No. Substation 1 80lano 2 Bambang 3 Bayombong Feeder Name 21804 22804 23804 24804 21BM4 22BM4 23BM4 24BM4 22B04 23B04 24B04 2014 7.56 Voltage Profile (p.u.) Year 2010 0.9790 0.9370 0.9170 0.9420 0.9290 0.9080 0.9370 0.9250 0.9120 0.9620 0.9420 ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 10 of 24 D. System Efficiency For the past seven (7) years, the average system loss of NUVELCO is 15.64%, to wit: 20,00% 18.86% 18.00% 16.00% 14.00% 12,00% 10.00% 8.00% 6.00% 4.00% 2.00% 0.00% 2004 2005 - 2006 2007 2008 System Loss - - - -- System Loss cap 2009 2010 In the table above, the most efficient is during the year 2004 and the worst was in year 2007 wherein NUVELCO reached a system loss of 18.860/0which is beyond the system loss cap of 130/0. These enormous losses were due to the inappropriate distribution transformer capacities installed at that time. NUVELCO gradually replaced these units with appropriate sizes which improved the entire distribution system's efficiency as reflected in the years 2008 up to 2010. However, the existing system loss of NUVELCO is still beyond the allowable limit and thus, there is a need to reduce these losses through an exerted effort to determine the probable cause of the distribution system's inefficiency. E. Reliability The reliability performance of NUVELCO was measured using the following indices: a) the System Average Interruption Frequency Index (SAIFI); and b) the System Average Interruption Duration Index (SAIDI). These indices are the prescribed reliability indicators in the ECDUPM, the value of which shall not exceed the interim criteria for SAIFI at 20 customer-interruptions per customer-year and for SAIDI at 45 hours per customer-year. For the last seven (7) years, NUVELCO' average reliability performance indices for SAIFI and SAIDE are 2.54 and 3.67, respectively, both within the abovementioned criteria, to wit: ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 11 of 24 12.00 10.00 tJ> q) 0 8.00 '5 of: ~ ~ 6.00 i~ :a ~::.;.; .!!! ~ . -I ~~~t )i~ 4.00 II 2.00 ~It::~ .SAIFI !'!ISAlOl &MAIFI 2004 3.59 6.93 3.32 F. Rural Electrification There are still several barangays within the franchise area of NUVELCO that needs to be energized. Since its mandate is to provide rural electrification, NUVELCO included in its program the detailed plan for the electrification of the remaining barangays and sitios. II. PROJECT OVERVIEW A. Capital Projects Resolution No. 26, Series of 2009 (Guidelines for the Approval of Regulated Entities' Capital Expenditure Projects) requires that the capital projects should be necessary to serve, among others, the forecasted future loads of the distribution utility and to maintain efficient electric service to its existing and future consumers. It should comply with the utility's technical criteria for capacity, reliability', quality and safety of its entire distribution system. Regulated Entities' capital assets are divided into two (2) categories, namely: (1) regulated distribution assets; and (2) distribution connection assets. The regulated distribution assets are further divided into two (2) sub-categories, namely: (a) distribution plant assets or network assets; and (b) general plant assets or nonnetwork assets. B. Project Formulation The preparation of capital expenditure projects requires diligent formulation of project ideas in coming up with a particular solution to assess deficiencies/problems of a distribution network. Several alternatives were considered by NUVELCO in addressing the deficiencies of its distribution system in order to provide a technically ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 12 of 24 feasible and economically viable project for the benefits of its member consumers. c. Proposed Projects and Objectives NUVELCO identified and proposed twenty (20) capital projects intended to address the distribution system's technical deficiencies, as discussed in the performance assessment. These projects are essential to provide continuous supply, efficient, reliable and best possible quality of service to its customers. Shown below is the summary of the proposed projects which is presented according to the distribution system's categories, corresponding project type, system deficiencies to be resolved and project cost: Project Primary Distribution Name Proposed Cost (PhP) Rationale Projects 1 Installation of Air Break Switches Improve system reliability performance while maintaining a safe distribution system. The proposed equipment shall be used as load shifter during interruptions. 2 Installation of Three-phase Auto-Recloser The installation of Automatic Circuit Recloser will provide back-up protection within the main feeders in the event fault occurs in the system. Safety 4,771,402.08 3 Installation of Fuse Cut-out and Auto-link Resettable Electronic Sectionalizer along lateral distribution lines Improve system reliability performance while maintaining a safe distribution system since the proposed equipment shall protect the installed distribution transformers. Safety 8,308,389.06 4 Installation of Substation Feeder Metering at Bambang and Solano Substations Improve distribution system's efficiency by installing revenue meters to the feeders of Bambang and Solano substations. Efficiency 268,800.00 5 Installation of Revenue Meter to Alfonso Castaneda The procurement of metering equipment is necessary to determine the consumption of the sale for resale customer class (served by AURELCO) in Alfonso Castaneda Efficiency 499,520.00 6 Acquisition of Distribution Upgrading Materials Replacement of the existing distribution facilities such as conductors and other distribution facilities that are beyond its asset life is necessary for public safety and to improve system's reliability and efficiency. 7 Replacement of Rotten Poles Some rotten poles must be replaced for distribution system to operate safely and reliably. Secondary Distribution Replacement of Overloaded Transformers 9 Replacement of Kilowatt-hour Meter Clustering 10 1,872,640.00 Safety the Safety 20,078,186.69 58,427,779.28 Projects 8 Other Network Reliability Distribution meter and Upgrading and augmenting the existing distribution transformers are necessary to accommodate the predicted additional demand and customers. Capacity 45,986,231.82 Improve the EC's existing system's efficiency by replacing defective and old KWh meters with new meters and the same shall be clustered in several strategic locations. Efficiency 40,898,687.35 Address the impending load and customer growth by providing them necessary service drop wires, and metering facilities and equipment. Capacity 20,796,433.78 Projects Connection of New Customers due to Addon Projects (KWh meters & accessories) ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 13 of 24 Non-network Projects Acquisition of Test Instruments The acquisition of several test equipment is necessary to continuously monitor the condition of DUs network assets such as meters, conductors, protection equipment and transformers, thereby, improving the EC's reliability performance. Customer Efficiency 571,032.00 Acquisition of Lineman's Tools Set Replacement of the existing worn out tools and safety apparels of the cooperative personnel in order for the EC to continuously maintain a safe distribution system. Customer Efficiency 807,520.00 13 Acquisition of Vehicles Enhance the services rendered in the operation and maintenance of the cooperative. Reliable maintenance vehicles provide efficient way to ensure the consumers' needs. Customer Efficiency 22,094,960.16 14 Acquisition of Meter Reading/Billing Gadgets Enhance the existing reliability performance of the DU by introducing this new technology of "Read & Bill" System. Customer Efficiency 2,907,072.00 15 Acquisition of Office Furnitures and Equipment The acquisition of office equipment such as furnitures and office supplies which is necessary for a conducive-work station and providing better service to its customers. Customer Efficiency 2,180,360.00 16 Acquisition of Engineering Analysis Software and Hardware Enhance the existing database of the DU in order to maximize the use of SynerGee Program. The said database is not compatible to the SynerGee program which aids engineers in effective performance analysis and planning. Customer Efficiency 6,968,925.98 17 Acquisition of Accounting, Payroll, Warehousing and Member-Consumer Information System Software Adopt an automated financing and accounting system or program in order to enhance financial processes of the cooperative, thereby, improving the ECs customer service performance. Customer Efficiency 7,500,000.00 18 Acquisition of Street Lighting Equipment The cooperative is responsible lighting equipment. Customer Efficiency 2,340,800.00 19 Construction of NUVELCO & Facilities The project shall provide conduciveness to the cooperatives personnel and to paying customers as well as eliminating rentals for its sub-offices. Customer Efficiency 24,622,104.44 20 Acquisition of Office Stand-by Power Generator The project aims to provide the main office a continuous power in case of power failure within the distribution system. Customer Efficiency 1,120,000.00 TOTAL I 273,020,844.65 11 12 Office Buildings to provide street I III. PROJECT EVALUATION As prescribed in the ECDUPM, the power system model or electric circuits used to assess distribution system's performance should be modified to reflect the proposed projects or solutions. Likewise, the conduct of appropriate technical analysis is necessary in order to predict the performance of the distribution system. NUVELCO provided several alternative projects for each quantified problems and ranked the technically feasible projects in terms of technical effectiveness. The projects that were considered technically feasible were subject to economic evaluation such as the least cost or economic viability. I ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 14 of 24 Upon evaluation of the twenty (20) proposed capital projects, the Commission hereby approves seventeen (17) projects proposed by NUVELCO with an approved amount of One Hundred NinetyEight Million One Hundred Sixty-One Thousand Five Hundred Thirty and 21/100 Pesos (PhP198,161,530.21). The remaining three (3) projects shall be deferred for failure of NUVELCO to provide technical justifications. Shown below is the summary of the projects with modification and the corresponding costs: Project Primary Distribution Project Name Proposed Installation of Air Break Switches 1,872,640.00 3 Installation of Fuse Cut-out and Auto-link Resettable Electronic Sectionalizer along lateral distribution lines 8,308,389.06 5 Installation of Revenue Meter to Alfonso Castaneda 6 Acquisition of Distribution Upgrading 7 Replacement Materials of Rotten Poles Distribution Replacement of Overloaded 9 Replacement Clustering 10 Connection of New Customers (KWh meters & accessories) 12 Acquisition 13 Acquisition of Vehicles 14 Acquisition of Meter Reading/Billing 15 Acquisition of Office Furnitures and Equipment 16 Acquisition Hardware Software and 17 Acquisition of Accounting, Payroll, Warehousing Member-Consumer Information System Software and 18 Acquisition 19 Construction 20 Acquisition of Office Stand-by Power Generator Other Network Non-network Taken Assessment/Reason - Deferment Lack of technical justification 5,920,773.06 Cost Reduction Technical amendments 499,520.00 382,320.00 Cost Reduction Cost amendments 20,078,186.69 15,795,055.66 Cost Reduction Cost amendments and OPEX re-alignment of some materials 58,427,779.28 43,679,477.89 Cost Reduction Cost amendments 45,986,231.82 40,290,401.35 Cost Reduction Cost amendments 40,898,687.35 26,299,449.79 Cost Reduction Technical 20,796,433.78 20,618,797.19 Cost Reduction Cost amendments Projects 8 of Action Approved Projects 1 Secondary Cost (PhP) Distribution Kilowatt-hour meter Transformers and Meter amendments Projects due to Add-on Projects Projects of Lineman's Tools Set of Engineering - Deferment Re-aligned to OPEX 22,094,960.16 17,672,080.16. Cost Reduction Technical 2,907,072.00 790,171.20 Cost Reduction Cost amendments 2,180,360.00 1,626,632.00 Cost Reduction OPEX re-alignment materials of some 6,968,925.98 2,458,600.00 Cost Reduction OPEX re-alignment materials of some Deferment Unavailable 807,520.00 Gadgets Analysis of Street Lighting Equipment of NUVELCO Office Buildings & Facilities 7,500,000.00 - amendments cost breakdown 2,340,800.00 130,872.00 Cost Reduction Technical Amendments 24,622,104.44 16,432,029.93 Cost Reduction Cost amendments & OPEX re-alignment of some materials 1,120,000.00 453,635.90 Cost Reduction Cost amendments IV. COSTANALYSIS NUVELCO's estimated the cost of its projects based on the prevailing market price through public, transparent and competitive bidding process. ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 15 of 24 The Commission made an assessment of the proposed project cost in accordance with the Valuation Handbook prescribed in Resolution No. 17, series of 2010 (A Resolution Adopting the Valuation Handbook for the Cost Valuation of System Distribution Utilities Operating [PBR))" and the latest NEA Optimized Depreciated Replacement Fixed Assets of Privately Owned Under Performance-Based Regulation Price Index for the year 2012. The Commission reduced the project costs that exceeded the benchmark provided in the said Valuation Handbook or the NEA price index and retained the estimated project costs that are closed to the said benchmarks. Shown below is the comparison of the proposed estimated cost, the Commission's Price Benchmark and the 2012 NEA Price Index: Equipment Specification Unit Cost (PhP/Unit) Unit Proposed' ERC'" NEA'" - Air-break Switch Outdoor Type, 69kV No. 230,720.00 No. 587,864.13 805,400.00 No. 5,369.81 4,800.00 4,674.00 21,320.00 440,904.39 - Recloser Automatic, Cut-out and Arrester 15kV, Distribution Overhead Conductor Bare, ACSR #2 km 32,116.01 33,700.00 Overhead Conductor Bare, ACSR #1/0 km 47,985.50 52,200.00 30,140.00 Overhead Conductor Duplex, ACSR #6 km 21,193.60 27,400.00 20,770.00 Overhead Conductor Duplex, ACSR #2 km 56,200.17 58,500.00 41,580.00 Distribution Transformer 15 KVA No. 68,137.13 75,000.00 59,638.33 Distribution Transformer 25 KVA No. 88,407.58 95,000.00 77,380.00 Distribution Transformer 37.5 KVA No. 107,929.68 107,000.00 94,467.00 Distribution Transformer 50 KVA No. 126,173.31 124,000.00 110,435.00 Pole 30 ft., steel No. 12,710.16 16,100.00 10,204.05 Pole 35 ft., steel No. 18,499.55 19,300.00 12,716.92 Pole 40 ft., steel No. 22,156.74 27,800.00 17,395.25 Pole 45 ft., steel No. 26,085.11 34,200.00 20,420.75 35,500.00 3-phase, 15kV, 630A Class KWh Meter Programmable No. 33,600.00 KWh Meter 30A, bottom connected No. 796.95 KWh Meter Class 200, 15A, 2W No. 1,747.70 Electronic, Polyphase 2,200.00 818.57 1,768.69 The proposed costs and the NEA price benchmark were based only on the material costs while the Commission's valuation includes all the necessary cost in establishing and installing such equipment or materials. It can be observed from the aforesaid table that most of the unit costs are comparable and lesser than the abovementioned price benchmarks. Meanwhile, the Commission allowed an inflation rate factor of 3% to cover the future increase in cost of the proposed materials/equipment. 1 The proposed unit cost does not include contingency 2 The ERC and NEA price benchmarks rate factors and VAT already includes contingency rate factors and VAT ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 16 of 24 V. PROJECT DESIGN The. acquisition of several major equipment such as the distribution transformers and conductors, and protection equipment (circuit breakers, disconnect switches, fuse cut-outs and surge arresters) are necessary to ensure the safety of the entire distribution system. Moreover, the acquisition of revenue and monitoring meters, engineering hardware and software programs are vital tools necessary for monitoring the power quality and reliability of the system, and other parameters needed to provide an efficient and reliable power service to the consumers. These parameters are also in compliance with the provisions of the Philippine Distribution Code (PDC). The design of the proposed electrical projects complies with the standards of NEA Engineering Bulletin and the Philippine Electrical Code (PEC). VI. PROJECT STATUS During the ocular inspection, it was disclosed that some projects were already implemented by NUVELCO, as follows: Project No. Project Title Project Type Actual Cost (PhP) Remarks 3 Installation of Fuse Cut-out and Auto-link Resettable Electronic Sectionalizer along lateral distribution lines Safety 999,830.00 Partially implemented 6 Acquisition Materials Safety 8,973,222.47 Partially implemented Safety 7,076,355.84 Partially implemented Capacity 9,443,115.82 Partially implemented System Efficiency 3,836,789.64 Partially implemented 1,025,375.00 Partially implemented 625,772.81 Partially implemented of Distribution Upgrading 7 Replacement of Rotten Poles 8 Replacement Transformers of Overloaded 9 Replacement of Kilowatt-hour Meter Clustering 10 Connection of New Customers due to Add-on Projects (KWh meters & accessories) Capacity 18 Acquisition Customer Efficiency Distribution meter and of Street Lighting Equipment Total 31,980,461.58 I NUVELCO decided to implement the abovementioned projects in order to maintain a safe and secure operation of its power system. It is incumbent upon any distribution utility to ensure the safety of its consuming public and to address the increasing power requirement of its customers. ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 17 of 24 VII. FINANCING PLAN/RATE IMPACT ANALYSIS NUVELCO intends to finance the proposed projects through loan from any available private banking institution. Although NUVELCO has not yet identified the bank, it used the NEA loan package to simulate the rate impact of its expenses on Reinvestment Fund for Sustainable CAPEX (RFSC) rate. The loan shall have an annual interest rate of g% and quarterly repayment within ten (10) years. NUVELCO shall use its previous collection and the projected revenues from the RFSC to settle the annual amortization. NUVELCO proposed a staggered scheme on the private banks loan releases. The release of the loan proceeds shall be on an annual basis as projected in the annual implementation of the projects. Considering the modification as to the cost requirements of some of the projects, the projected annual loan amount shall be as follows: Projected Financier I 2011 Private banks I 26,624,719.41 Loan Amount I 2012 4,860,841.36 I (PhP) I 2014 85,495,714.81 Total (PhP) 2015 I 81,180,254.63 198,161,530.21 The Commission simulated the impact on NUVELCO's existing RFSC rate if it opted not to avail of any loan and will just utilize its expected revenues from the RFSC to finance the entire CAPEX projects. Shown below is the Commission's simulation: 2011 Energy Sales Forecast, KWh Approved RFSC Rate, PhP/KWh Cash balance beginning, PhP, excess/(shortfall) 2012 2013 83,150,000 88,305,000 93,825,000 0.3722 0.3722 0.3722 2014 2015 99,763,000 Entire 5 years 106,115,000 0.3722 471,158,000 0.3722 0.3722 267,172.00 (3,448,999.23) 16,680,627.59 43,762,095.77 (13,083,245.26) 267,172.00 30,948,430.00 32,867,121.00 34,921,665.00 37,131,788.60 39,496,003.00 175,365,007.60 313,173.13 313,173.13 313,173.13 313,173.13 313,173.13 1,565,865.63 31,261,603.13 33,180,294.13 35,234,838.13 37,444,961.73 39,809,176.13 176,930,873.23 31,528,775.13 29,731,294.89 51,915,465.71 81,207,057.49 26,725,930.86 177,198,045.23 26,624,719.41 4,860,841.36 85,495,714.81 81,180,254.63 198,161,530.21 8,153,369.95 8,153,369.95 8,153,369.95 8,153,369.95 40,766,849.73 199,685.00 36,456.00 641,218.00 608,852.00 1,486,211.00 34,977,774.36 13,050,667.31 8,153,369.95 94,290,302.76 89,942,476.57 240,414,590.93 (3,448,999.23) 16,680,627.59 43,762,095.77 (13,083,245.26) (63,216,545.71) (63,216,545.71) CASH INFLOWS Current year RFSC Collection, PhP 50% income on leased properties, PhP Total Cash Inflows, PhP Available cash for disbursement, PhP ..- CASH OUTFLOWS CAPEX Requirement, - - PhP Previous Loan Amortization, PhP ERC Permit Fees, PhP Total Cash Outflows, PhP Cash balance ending, I Rate Impact PhP, excess/(shortfall) on RFSC, PhP/KWh, excess/(shortfall) I (0.0415) I 0.1889 8,153,369.95 I 0.4664 I (0.1311) I (0.5957) Based on the above simulation, the revenues derived from NUVELCO's existing RFSC rate is not sufficient to finance the entire I (0.1342) I ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 18 of 24 CAPEX projects. There is a need to increase its RFSC rate by PhPO.1342/kWh and thus, the need to avail a loan is necessary. The Commission also made several simulations on the indicative effect of NUVELCO's existing RFSC rate using the following conditions prescribed under the proposed financing scheme of the capital expense: 1. The proposed loan terms and conditions: 2011 _Energy Sales Forecast, KWh 2012 83,150,000 Approved RFSC Rate, PhP/KWh 0.3722 Cash balance beginning, PhP, excess/(shortfall) 2013 2014 88,305,000 93,825,000 99,763,000 0.3722 0.3722 0.3722 2015 Entire 5 years 106,115,000 471,158,000 0.3722 0.3722 267,172.00 23,175,720.18 44,100,340.44 66,373,664.00 90,215,893.15 267,172.00 30,948,430.00 32,867,121.00 34,921,665.00 37,131,788.60 39,496,003.00 175,365,007.60 313,173.13 313,173.13 313,173.13 313,173.13 313,173.13 26,624,719.41 4,860,841.36 85,495,714.81 81,180,254.63 198,161,530.21 CASH INFLOWS Current year RFSC Collection, PhP 50% income on leased properties, PhP Loan proceeds from financial institutions, PhP Total Cash Inflows, PhP Available cash for disbursement, PhP - 1,565,865.63 .. 57,886,322.54 38,041,135.49 35,234,838.13 122,940,676.54 120,989,430.75 375,092,403.43 58,153,494.54 61,216,855.66 79,335,178.57 189,314,340.53 211,205,323.90 375,359,575.43 198,161,530.21 CASH OUTFLOWS -- CAPEX Requirement, PhP CAPEX Amortization, PhP 26,624,719.41 Previous Loan Amortization, PhP 8,153,369.95 ERC Permit Fees, PhP Total Cash Outflows, PhP Cash balance I ending, PhP, excess/(shortfall) Rate Impact on RFSC, PhP/KWh, excess/(shortfall) 2. I - 4,860,841.36 - 85,495,714.81 81,180,254.63 4,065,847.91 4,808,144.63 4,808,144.63 17,864,153.54 31,546,290.71 8,153,369.95 8,153,369.95 8,153,369.95 8,153,369.95 40,766,849.73 - 199,685.00 36,456.00 641,218.00 608,852.00 1,486,211.00 34,977,774.36 17,116,515.22 12,961,514.57 99,098,447.38 107,806,630.11 271,960,881.64 23,175,720.18 44,100,340.44 66,373,664.00 90,215,893.15 103,398,693.79 103,398,693.79 I 0.2787 0.4994 I I 0.7074 0.9043 I 0.9744 I 0.2195 I NEA loan portfolio with 8% annual interest rate at 15 years repayment: 2011 Energy Sales Forecast, KWh Approved RFSC Rate, PhP/KWh Cash balance beginning, PhP, excess/(shortfall) 2012 2013 83,150,000 88,305,000 93,825,000 0.3722 0.3722 0.3722 267,172.00 23,175,720.18 45,102,432.29 30,948,430.00 32,867,121.00 34,921,665.00 313,173.13 313,173.13 26,624,719.41 4,860,841.36 2014 2015 99,763,000 Entire 5 years 106,115,000 0.3722 471,158,000 0.3722 0.3722 68,247,625.20 93,274,896.83 267,172.00 37,131,788.60 39,496,003.00 175,365,007.60 313,173.13 313,173.13 1,252,692.50 85,495,714.81 81,180,254.63 198,161,530.21 CASH INFLOWS Current year RFSC Collection, PhP 50% income on leased properties, PhP Loan proceeds from financial institutions, PhP Total Cash Inflows, PhP Available cash for disbursement, PhP - 57,886,322.54 38,041,135.49 34,921,665.00 122,940,676.54 120,989,430.75 374,779,230.31 58,153,494.54 61,216,855.66 80,024,097.29 191,188,301.73 214,264,327.58 375,046,402.31 -,-._----- CASH OUTFLOWS -.. CAPEX Requirement, PhP CAPEX Amortization, PhP Previous Loan Amortization, 26,624,719.41 PhP ERC Permit Fees, PhP Total Cash Outflows, PhP Cash balance ending, I 4,860,841.36 - PhP, excess/(shortfall) Rate Impact on RFSC, PhP/KWh, excess/(shortfall) 3,063,756.07 85,495,714.81 81,180,254.63 198,161,530.21 3,623,102.14 3,623,102.14 13,461,253.35 23,771,213.71 --"---_._. - 8,153,369.95 8,153,369.95 8,153,369.95 40,766,849.73 641,218.00 608,852.00 1,486,211.00 8,153,369.95 8,153,369.95 199,685.00 36,456.00 34,977,774.36 16,114,423.38 11,776,472.09 97,913,404.90 103,403,729.93 264,185,804.65 23,175,720.18 45,102,432.29 68,247,625.20 93,274,896.83 110,860,597.66 110,860,597.66 0.2787 I 0.5108 I 0.72741 0.9350 I 1.0447 I 0.2353 I ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 19 of 24 3. RFSC utilization shall be maximized and the deficit to fully implement the projects shall be sourced through a loan from NEA with 8% annual interest rate at 15 years repayment period: 2011 Energy Sales Forecast, KWh 2012 83,150,000 Approved RFSC Rate, PhP/KWh 0.3722 Cash balance beginning, PhP, excess/(shortfall) 2013 2014 2015 88,305,000 93,825,000 99,763,000 106,115,000 0.3722 0.3722 0.3722 0.3722 - 267,172.00 19,732,744.05 Entire 5 years 471,158,000 0.3722 - 46,104,156.34 267,172.00 CASH INFLOWS Current year RFSC Collection, PhP 50% income on leased properties, PhP Loan proceeds from financial institutions, PhP cash for disbursement, 32,867,121.00 313,173.13 313,173.13 PhP 34,921,665.00 - - 3,448,999.23 Total Cash Inflows, PhP Available 30,948,430.00 - 37,131,788.60 39,496,003.00 313,173.13 313,173.13 175,365,007.60 1,252,692.50 11,138,067.46 51,811,861.39 66,398,928.08 34,710,602.36 33,180,294.13 34,921,665.00 48,583,029.19 91,621,037.52 243,016,628.18 34,977,774.36 33,180,294.13 54,654,409.05 94,687,185.52 91,621,037.52 243,283,800.18 85,495,714.81 81,180,254.63 198,161,530.21 396,882.77 1,678,560.94 2,869,209.25 8,153,369.95 8,153,369.95 40,766,849.73 641,218.00 608,852.00 1,486,211.00 - CASH OUTFLOWS CAPEX Requirement, PhP CAPEX Amortization, PhP Previous Loan Amortization, 26,624,719.41 PhP ERC Permit Fees, PhP Total Cash Outflows, PhP Cash balance ending, I Rate Impact on RFSC, PhP/KWh, excess/(shortfall) 396,882.77 396,882.77 8,153,369.95 8,153,369.95 8,153,369.95 199,685.00 36,456.00 34,977,774.36 - PhP, excess/(shortfall) I - 4,860,841.36 - -I - 13,447,550.07 8,550,252.71 19,732,744.05 46,104,156.34 0.22351 0.4914 94,687,185.52 I 91,621,037.52 - 243,283,800.18 - - - -I -I -I Based on the above simulations, NUVELCO's existing RFSC rate will not be sufficient to fund its capital expense. It is therefore strategically optimal if NUVELCO will avail of the loans to finance CAPEX projects. To mitigate the rate impact on its rate, NUVELCO should negotiate for longer terms, lower interest rate and reasonable loan amount. However, the above simulations do not reflect the fact that there will still be a reduction in NUVELCO's overall rate due to the efficiency, reliability (less ENS) and system loss reduction in the implementation of the proposed projects. The detailed discussion of the Commission's resolution of the proposed capital expenditures is embodied in a separate document hereto attached as Annex "A" and made integral part of this Decision. A perusal of the evidence presented herein showed that the approval of NUVELCO's capital projects for the years 2011 to 2014 is in accordance with the provisions of R.A. 9136 and the Commission's "Resolution Amending the Rules for Approval of Regulated Entities' Capital Expenditure Projects" and will redound to the benefit of the electricity consumers in terms of continuous, reliable and efficient power supply as mandated by R.A. 9136, or the Electric Power ERC Case No. 2012'-043 RC DECISION/December 18,2014 Page 20 of 24 Industry Reform Act of 2001 (Section 2. Declaration of Policy - (b) "to ensure the quality, reliability, security and affordability supply of electric power'? the foregoing premises application filed by the Nueva Viscaya Electric (NUVELCO) for approval of its capital projects for 2014 is hereby APPROVED with MODIFICATION following conditions: considered, the Cooperative, Inc. the years 2011 to and subject to the WHEREFORE, a. The following are the confirmed projects with the corresponding costs: Confirmed Project Primary Distribution Name 2011 of Distribution Upgrading Distribution of Overloaded Replacement of Kilowatt-hour Materials Distribution Transformers meter and Meter Clustering due to Add-on Projects 2,351,456.52 712,816.67 287,013.33 2,063,512.71 3,063,342.71 8,267,978.38 5,494,917.46 705,244.09 1,581,438.38 2,731,553.92 17,456,116.89 11,704,776.39 24,532,472.73 8,046,925.98 3,375,628.92 1,396,189.84 461,160.72 18,292,983.75 9,585,343.94 27,736,099.57 13,422,133.58 595,580.00 429,795.00 9,313,255.66 10,338,630.66 10,429,040.16 807,520.00 12,464,931.27 10,429,040.16 807,520.00 130,872.00 12,464,931.27 85,495,714.81 116,981,275.59 Projects Acquisition of Vehicles Acquisition of Office Furnitures and Equipment Acquisition of Street Lighting Equipment Construction 2,351,456.52 Projects Connection of New Customers (kWh Meters and Accessories) Non-Network - Projects Replacement Other Network Total (PhP) 2014 - of Rotten Poles Secondary Cost (PhP) 2012 Auto-Recloser Installation of Fuse Cut-out and Auto-link Resettable Electronic Sectionalizer along lateral distribution lines Replacement Project Projects Installation of Three-phase Acquisition of the - 130,872.00 - of NUVELCO Office Buildings & Facilities Total (PhP) 26,624,719.41 b. The following are the corresponding costs: 4,860,841.36 approved Approved Project Primary Distribution Installation Name Auto-recloser Installation of Fuse Cut-out and Auto-link Resettable Electronic Sectionalizer along lateral distribution lines Installation of Substation Solano Substations Feeder Metering at Bambang and Installation of Revenue Meter to Alfonso Castafleda Acquisition of Distribution Secondary Replacement Upgrading Materials of Rotten Poles Distribution projects Project with Cost (PhP) 2015 Projects of Three-phase Replacement - 2,419,945.56 2,857,430.35 268,800.00 382,320.00 4,090,279.27 19,147,005.17 Projects of Overloaded Distribution Transformers 12,554,301.79 the ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 21 of 24 I Replacement of Kilowatt-hour meter and Meter Clustering 12,877,316.21 I 10,280,166.53 I Other Network Projects Connection of New Customers due to Add-on Projects (KWh meters & accessories) Non-Network Projects Acquisition of Test Instruments Acquisition of Vehicles Acquisition of Meter Reading/Billing Gadgets Acquisition of Office Furnitures and Equipment Acquisition of Engineering Analysis Software and Hardware Acquisition of Street Lighting Equipment Construction of NUVELCO Office Buildings & Facilities Acquisition of Office Stand-by Power Generator Total (PhP) a. 571,032.00 7,243,040.00 790,171.20 819,112.00 2,458,600.00 3,967,098.66 453,635.90 81,180,254.63 I The following projects are deferred and may be included in the next CAPEX application of NUVELCO with sufficient justifications: 1. Installation of Air Break Switches; 2. Acquisition of Lineman's Tools Set; and 3. Acquisition of Accounting, Payroll, Warehousing and Member-Consumer Information System Software; b. NUVELCO should secure the appropriate Certificate of Compliance (COC) prior to the operation of its proposed generation facility pursuant to Resolution No. 09, Series of 2010; c. It should conduct competitive biddings for the acquisition of the materials and equipment in accordance with the existing rules and regulations; d. It should file an application for authority to secure loan to finance its capital expenditures; and e. NUVELCO is directed to remit to the Commission a total permit fee in the amount of One Million Four Hundred Eighty-Six Thousand Two Hundred Eleven Pesos (PhP1,486,211.00) within fifteen (15) days from receipt hereof, computed as follows: ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 22 of 24 PhP198, 161,530.21 ---------------------------- x Ph PO.75 = PhP1,486,211.00 PhP100.00 SO ORDERED. Pasig City, December 18,2014. AIDA G. c~z~~ Chairperson ALFREDOJ~ r G.. /~~~t GL~~leTORIA . YAP-TARue Commissioner JOSEFINA PATR C Commissio er . MAGPALE-ASIRIT issioner ERC Case No. 2012-043 RC DECISION/December 18,2014 Page 23 of 24 Copy Furnished: 1. ATTY.RANULFOM. OCAMPO Counsel for Applicant 8/F STRATA 100, F. Ortigas Jr. Road Ortigas Center, 1605 Pasig City 2. The General Manager NuevaViscaya Electric Cooperative,Inc. (NUVELCO) 3. The Office of the Solicitor General 134 Amorsolo Street, Legaspi Village Makati City, Metro Manila 4. The Commission on Audit Commonwealth Avenue Quezon City, Metro Manila 5. The SenateCommitteeon Energy GSIS Bldg., Roxas Blvd., Pasay City Metro Manila 6. The House Committeeon Energy Batasan Hills, ,Quezon City, Metro Manila 7. Office of the Provincial Governor Province of NuevaVizcaya 8. Office of the Municipal Mayor Municipality of Villaverde Province of Nueva Vizcaya 9. Office of the Municipal Mayor Municipality of Bagabag Province of Nueva Vizcaya 10. Office of the Municipal Mayor Municipality of Diadi Province of Nueva Vizcaya 11. Office of the Municipal Mayor Municipality of Ambaguio Province of Nueva Vizcaya 12. Office of the Municipal Mayor Municipality of Solano Province of Nueva Vizcaya 13. Office of the Municipal Mayor Municipality of Bayombong Province of Nueva Vizcaya 14. Office of the Municipal Mayor Municipality of Quezon Province of Nueva Vizcaya ERC Case No. 2012-043 RC DECISION/December 18, 2014 Page 24 of 24 15. Office of the Municipal Mayor Municipality of Kayapa Province of Nueva Vizcaya 16. Office of the Municipal Mayor Municipality of Bambang Province of Nueva Vizcaya 17. Office of the Municipal Mayor Municipality of Kasibu Province of Nueva Vizcaya 18. Office of the Municipal Mayor Municipality of Aritao Province of Nueva Vizcaya 19. Office of the Municipal Mayor Municipality of Dupax del Norte Province of Nueva Vizcaya 20. Office of the Municipal Mayor Municipality Dupax del Sur Province of Nueva Vizcaya 21. Office of the Municipal Mayor Municipality of Santa Fe Province of Nueva Vizcaya 22. Office of the Municipal Mayor Municipality of Alfonso Castaneda Province of Nueva Vizcaya ANNEXA DETAILED PROJECT DISCUSSION I. NETWORK PROJECTS 1 Installation of Air Break Switches Project Description I Duration • Acquisition and installation of eight (8) disconnect switches within the primary lines and laterals of the 2012 to 2013 distribution s stem. Proposed CAPEX Cost (PhP) 2012 2011 922,880.00 - 2013 949,760.00 2014 - Total I 1,872,640.00 I Project Justification • The proposed project shall provide system's reliability improvement within the distribution system since load transfer can be implemented in case fault occurs within the ortion of the line. Technical Analysis • NUVELCO did not submit any technical documents to substantiate its claim of achieving such goal. During the inspection, it was disclosed that there is no available data to determine the possible improvement that should be reflected in the reliability indices such as System Average Interruption Duration Index (SAlOl) or Expected Energy Not Served (EENS). • The Commission deferred the proposed project considering the insufficient technical analysis to support the claim of the project's benefit. Approval Project to continue as proposed Project to continue with REVISED Capital Expenditure Project to continue with Technical Amendments Project to be deferred which may be included in its next application with additional justification I Remarks ./ 2 Installation of Three-phase Auto-recloser Distribution Line Pro'ect Project Description I Duration • Acquisition of eight (8) units of 3-phase Auto-recloser which will be installed in the main feeders of 2012 to 2013 NUVELCO's substations replacing the existing protection devices therein. Proposed CAPEX Cost (PhP) 2013 2012 2011 - 2,351,456.52 2,419,945.56 2014 Total I - 4,771,402.08 I Project Justification • The project intends to improve the existing distribution operation and maintenance and to rovide safet . system's Technical Analysis • An auto-recloser is a circuit breaker equipped with a mechanism that can automatically close the breaker after it has been opened due to a fault. In order to prevent damage to the distribution network, reclosers are used on the overhead distribution systems which will detect and interrupt momentary the faults. Since several faults on overhead lines clear themselves, a recloser improves service continuity by automatically restoring power to the line after a momentary fault without the need of any human intervention. These advantages are highly desired by the business enterprises which are intolerant to outage and interruptions being inimical to its operations. • The table below shows the feeders to be installed with Auto-reclosers: No. 1 2 3 4 5 6 7 8 • Substation Bambang Bayombong Solano Feeder Name F21BM4 F22BM4 F23BM4 F24BM4 F22B04 F24B04 F23S04 F24S04 Based on the technical analysis conducted by NUVELCO, there is no other alternative solution to protect the distribution system but to install protective devices. The EC selected auto-recloser as against fuse as its protective device considering that it has the capability to sense minimum fault in its rotected feeders and isolate the same leavin the 2 un-faulted portion to remain unaffected thus, limiting the magnitude of curtailed power. The said device has the capability to clear the fault and reclose the circuit and resume the power without the need of any human intervention. These advantages are highly desired by the business enterprises which are intolerant to outage and interruptions which are inimical to its operations. • Fuses, on the other hand, should not be used in a three phase system since this can only isolate faulted phase and will bring problem to three-phase customers. Moreover, the incapability of fuse to sense zero-sequence component is one of the reasons why auto-recloser is the optimal device to correct the problem. • The proposed project shall also comply with the prOVIsions of the Philippine Distribution Code (PDC) for safety and protection of the distribution system. Economic and Cost Analysis • Shown below is the approved project cost breakdown, to wit: Materials Auto-Recloser Specifications 3-phase, 15kV, 560A No. of Units Unit Cost (PhP/unit) Year 4 4 587,864.13 604,986.39 2012 2013 Grand Total Project Cost (PhP) 2,351,456.52 2,419,945.56 I 4,171,402.08 I • The proposed unit cost has an annual increase of 3% due to annual inflation rate. • The cost of the device is not available with Commission and NEA price benchmarks. However, the proposed cost is comparable with the existing market price and available price reference found on the internet. Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a Iication with additional 'ustification Approved CAPEX Cost (PhP) 2013 2012 2011 - 2,351,456.52 2,419,945.56 I 2014 - Remarks ./ Total I 4,771,402.08 I 3 3 Installation of Fuse Cut-out and Auto-link Resettable Electronic Sectionalizer alon lateral distribution lines Distribution Line Pro'ect Project Description I Duration • Acquisition of fuse cut-outs and surge arrester combination device, and auto-link resettable 2011 to 2014 sectionalizer which shall be installed within the entire distribution network. Proposed CAPEX Cost (PhP) 2013 2012 2011 1,216,965.40 2,558,439.68 2,770,307.98 2014 1,762,676.00 I I Total 8,308,389.06\ Project Justification • The proposed project is intended to protect the cooperative's distribution network assets to ensure safe distribution s stem. entire Technical Analysis • The operation of the system should satisfy all the prevailing safety standards considering that safety is a criterion that does not settle for compromise. The distribution utility should always ensure the satter of the consumers from the hazards intrinsic in the business of electricity. • The proposed number of protection equipment to be acquired is based on the actual number of protection equipment that is lacking within the distribution system. • The sectionalizer, which is one of the components of the proposed project, is already above the minimum standard for protection equipment considering that the combination of the fuse cut-outs and surge arresters are the minimum standard protection equipment being used by several distribution utilities. • The acquisition of fuse cut-outs and surge arrester combination device is necessary to address the identified problem. • The project should be supported by technical and economic analysis which will justify its advantage compared with the minimum standard requirement. • The Commission deferred consideration for the proposed acquisition of sectionalizer considerin that NUVELCO did not submit an 4 I technical or economic analysis to justify its benefits. Economic and Cost Analysis • The table below shows the proposed project cost breakdown, to WIt: 1 2 No. of Units Materials No. Cutout & Arrester Cutout & arrester w/load break 3 Cutout & Arrester 4 Cutout & arrester w/load break Unit Cost (PhP/unit) 5,369.81 25 5,720.16 143,004.12 220 5,530.90 1,216,798.13 28 5,891.77 12 242 5,691.99 Cutout & arrester w/load break 30 6,063.37 8 Autolink-resettable 12 100,912.00 9 Cutout & Arrester Autolink-resettable 6 Cutout & Arrester 7 10 Electronic Electronic Auto Sectionalizer Auto Sectionalizer Cutout & arrester w/load break 1,073,961.28 200 98,056.00 5 Project Cost (PhP) Year 266 5,853.09 33 6,234.98 2011 164,969.55 2012 1,176,672.00 1,377,462.74 181,901.24 2013 1,210,944.00 1,556,921.67 2014 205,754.33 I Grand Total 8,308,389.06 I • The proposed unit cost has an annual increase of 3% due to annual inflation rate consideration. • With the deferment of acquiring sectionalizer, the approved project costs are as follows: No. Materials 1 Cutout & Arrester 2 Cutout & arrester w/load break 3 Cutout & Arrester 4 Cutout & arrester w/load break 5 Cutout & Arrester 6 Cutout & arrester w/load break 7 Cutout & Arrester 8 Cutout & arrester w/load break No. of Units Unit Cost (PhP/unit) Project Cost (PhP) Year 1,073,961.28 200 5,369.81 25 5,720.16 143,004.12 220 5,530.90 1,216,798.13 28 5,891.77 164,969.55 242 5,691.99 1,377,462.74 30 6,063.37 266 5,853.09 33 6,234.98 2011 2012 2013 181,901.24 1,556,921.67 2014 Grand Total 205,754.33 I 5,920,773.06 • The required equipment unit costs of the proposed roximate with the NEA rice benchmark. project I Remarks 2014 1,762,676.00 Total Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification Approved CAPEX Cost (PhP) 2013 2012 2011 1,216,965.40 1,381,767.68 1,559,363.98 I are I 5,920,773.06 5 I 4 Installation of Substation Feeder Metering at Bamban and Solano Substations Project Description • Acquisition of eight (8) units of kilowatt-hour (KWh) meters which shall be installed at Bambang and Solano Substations. Proposed CAPEX Cost (PhP) 2012 2011 268,800.00 I Duration 2011 2014 2013 - - Total 268,800.00 Project Justification • The proposed project is necessary in order for the cooperative to monitor the system efficiency performance of the entire distribution network. • It will also aid the EC's technical staff in monitoring and planning for the development of the distribution s stem. Technical Analysis • Bambang and Solano Substations are presently being metered and billed by power suppliers at the primary side of the line (69kV). However, the feeders of each existing substations do not have meters installed in it. • Kilowatt-hour (KWh) meters installed in the secondary side or in each feeder are crucial in order to determine the actual demand (active and reactive power), actual energy consumption, and other important data relative to electrical parameters, which is a crucial factor in power distribution system analysis. The data retrieved from these meters will then be used to determine the specific improvements needed in the distribution s stem such as efficienc and ower ualit. Economic and Cost Analysis • Shown below is the proposed project cost breakdown, to wit: Materials KWhMeter Specifications GE, KV2C,Fitzall No. of Units 8 Unit Cost (PhP/unit) Project Cost (PhP) 33,600.00 • The required equipment unit costs of the proposed roximate with the NEA rice benchmark. 268,800.00 project are 6 I I Approval Pro.ect to continue as ro osed Pro.ect to continue with REVISED Ca ital Ex enditure Pro.ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional .ustification I Remarks ./ Approved CAPEX Cost (PhP) 2011 268,800.00 2014 2013 2012 - - - Total I 268,800.00 I 7 5 Installation of Revenue Meter to Alfonso Castaneda Distribution Line Pro'ect Project Description I • Acquisition of primary distribution line metering facilities to be installed at Alfonso Castaneda, Nueva Vizca a. Proposed CAPEX Cost (PhP) 2012 2011 499,520.00 2014 2013 - - Duration 2011 Total 499,520.00 Project Justification • The installation of meters is necessary to determine the accurate energy consumption of the entire customers in the Municipality of Alfonso, Castaneda, Nueva Vizca a. Technical Analysis • The customers in the Municipality of Alfonso Castaneda, one of the franchise areas of NUVELCO, are being served by Aurora Electric Cooperative, Inc. (AURELCO) through a sale for resale agreement with NUVELCO. One of the conditions in the said agreement requires that NUVELCO shall be responsible for installing necessary primary metering equipment at the delivery point located at the boundary of San Juan, Aurora and Lublub, Alfonso Castaneda, Nueva Vizcaya. • In order to comply with the said agreement, NUVELCO shall purchase the necessary metering facilities which shall then be installed at the agreed connection point. Economic and Cost Analysis • Shown below is the proposed project cost breakdown, to wit: No. Specifications Materials No. of Units Unit Cost (PhP/unit) Year Project Cost (PhP) 1 KWh meter Electronic, 3-phase 1 33,600.00 33,600.00 2 Current Transformer 13.8kV, 10:5 3 72,800.00 218,400.00 3 Potential Transformer 13.8kV, 70:1 3 72,800.00 4 Meter Box - 1 7,840.00 5 PT Box 1 7,840.00 7,840.00 1 7,840.00 7,840.00 1 5,600.00 5,600.00 6 CT Box 7 Accessories . - 218,400.00 2011 Grand Total 7,840.00 499,520.00 I • The Commission calculated the proposed project cost which resulted to the reduction. The reduction of the ro'ect was based rimaril on 8 the cost alignment of the current and potential transformers with the price benchmark provided in the ERC Valuation handbook. The said price index already includes installation, plant and overhead costs for the meter and transformers, and the accessories required for installation of the same. • Shown below is the approved project cost breakdown, to wit: No. 1 2 3 4 5 6 KWh meter Current Transformer Potential Transformer Unit Cost (PhP/unit) No. of Units Specifications Materials GE, KV2C, Fitzall 13.8kV, 10:5 13.8kV, 70:1 Meter Box PT Box CTBox 33,600.00 54,300.00 54,100.00 7,840.00 1 3 3 1 1 1 Project Cost (PhP) Year 33,600.00 162,900.00 162,300.00 7,840.00 7,840.00 7,840.00 2011 7,840.00 7,840.00 382,320.00 Grand Total Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification I Remarks Approved CAPEX Cost (PhP) 2011 382,320.00 2014 2013 2012 - - - Total 382,320.00 9 uisition of Distribution U & Secondar Distribution Line Pro'ect Project Description I • Replacement of several aged and damaged distribution network facilities within the entire franchise area. Said facilities shall be replaced with the same specifications accordingly. Duration • The following are the distribution assets to be acquired, to wit: a) Conductor with sizes ACSR #2, ACSR #1/0, ACSR #6 duplex and ACSR #2 duplex; and b) Electronic 3-phase KWh meters and its correspondin accessories. 2011 to 2014 Proposed CAPEX Cost (PhP) 2013 2012 2011 4,905,309.89 4,717,929.15 5,264,232.36 2014 5,190,715.29 Total 20,078,186.69 Project Justification • The proposed project is necessary in order to maintain a safe, efficient and reliable distribution s stem. Technical Analysis • Based on the applicant's site survey, it was determined that some of the existing distribution line assets are already old and dilapidated. These assets are threat to public safety and a contributing factor to the inefficiency and unreliability of the distribution system. • The proposed project will ensure the safety and eliminate the hazardous conditions caused by these assets, It shall also contribute in maintainin an efficient and reliable distribution s stem. Economic and Cost Analysis • The determination of the assets to be replaced was based on the actual inventory done by the cooperative. The proposed cost estimates includes an annual inflation rate factor of 3%. • Shown below is the project cost breakdown, to wit: 10 No. Specifications Materials Conductor 1 30.00 Bare, ACSR #1/0 30.00 Duplex, ACSR #6 25.00 Duplex, ACSR #2 10.00 GE, KV2C Meter Seal - Conductor 2 Bare, ACSR #2 35.00 Bare, ACSR #1/0 20.00 Duplex, ACSR #6 25.00 Duplex, ACSR #2 10.00 Meter GE, KV2C Meter Seal - - - - Accessories Conductor Bare, ACSR #2 30.00 Bare, ACSR #1/0 30.00 Duplex, ACSR #6 25.00 Duplex, ACSR #2 3 - - Accessories - Bare, ACSR #2 Meter Meter GE, KV2C Meter Seal - - Conductor 4 40.00 Bare, ACSR #1/0 20.00 Duplex, ACSR #6 25.00 Duplex, ACSR #2 10.00 Meter GE, KV2C Meter Seal - Accessories 5 33,600.00 168,000.00 49,835.02 15.10 1,192,587.79 1,192,587.79 - 33,079.49 1,157,782.24 49,425.07 988,501.38 545,735.14 21,829.41 - 57,886.17 5 34,608.00 578,861.70 2012 173,040.00 58,329.62 15.55 3,750 1 1,215,679.07 1,215,679.07 - 34,042.97 1,021,289.19 50,864.63 1,525,939.03 - 22,465.21 5 35,616.00 59,572.18 595,721.75 178,080.00 65,567.18 1 1,316,004.87 1,316,004.87 - 35,006.45 1,400,258.14 - 52,304.20 1,046,083.99 5 36,624.00 577,525.53 23,101.02 61,258.18 612,581.80 2014 183,120.00 76,772.50 16.46 4,664 - 561,630.34 2013 16.01 4,096 1,294,373.33 1,294,373.33 1 I • 529,839.94 562,001.65 2011 1 - 963,480.37 1,439,565.12 56,200.17 3,300 - Bare, ACSR #2 32,116.01 21,193.60 - - Project Cost (PhP) Year 47,985.50 - 10.00 - Accessories Unit Cost (PhP/unit) No. of Units Length I Grand Total 20,078,186.69 I The Commission reduced the proposed project cost based on its assessment. The reduction was based on the elimination of meter seals from the cost component and the cost alignment of the conductors with the price benchmark provided in the 2012 NEA Price Index wherein the said pnce benchmark already includes 50/0 contingency and 12% Value Added Tax (VAT). Moreover, an annual inflation rate of 3% was retained in the said costs. • Based on the proposed quantity of meter seals, it is possible that NUVELCO intends to replace the existing seals of all installed KWh meters. However, NUVELCO did not provide any justification in its application or any reports in accordance with the rules and procedures for the test and maintenance of electric meters of distribution utilities. The Commission believes that the said materials should form part of the applicant's operations and maintenance (O&M) expenditures. As such, the proposed materials should be re-aligned to form part of the applicant's O&M budget. • Shown below is the approved project cost breakdown, to wit: No. Specifications Materials Conductor 1 Bare, ACSR #2 30.00 Bare, ACSR #1/0 30.00 Duplex, ACSR #6 25.00 Duplex, ACSR #2 10.00 GE, KV2C Meter Accessories . No. of Units Length - - Unit Cost (PhP/unitl - Year Project Cost (PhP) 21,320.00 639,600.00 30,140.00 904,200.00 20,770.00 41,580.00 2011 519,250.00 415,800.00 5 33,600.00 168,000.00 1 1,192,587.79 1,192,587.79 11 Conductor 2 Bare, ACSR #2 35.00 Bare, ACSR #1/0 20.00 - Duplex, ACSR #6 25.00 - Duplex, ACSR #2 10.00 Meter GE,KV2C Accessories - Conductor 3 Bare, ACSR #2 30.00 Bare, ACSR #1/0 30.00 Duplex, ACSR #6 25.00 Duplex, ACSR #2 10.00 Meter GE, KV2C Accessories Bare, ACSR #2 Bare, ACSR #1/0 Conductor 4 - Duplex, ACSR #6 Duplex, ACSR #2 Meter GE, KV2C Accessories - 40.00 25.00 10.00 - - 620,884.00 21,393.10 534,827.50 2012 42,827.40 5 34,608.00 173,040.00 1 1,215,679.07 1,215,679.07 22,618.39 678,551.64 31,975.53 959,265.78 - 22,034.89 428,274.00 550,872.33 2013 - 44,112.22 5 35,646.24 178,231.20 1 1,316,004.87 1,316,004.87 - 23,296.94 931,877.59 32,934.79 658,695.84 - 20.00 768,586.00 31,044.20 - - - 21,959.60 22,695.94 441,122.22 567,398.49 2014 - 45,435.59 5 36,715.63 183,578.14 1 1,294,373.33 1,294,373.33 454,355.89 15,795,055.66 Grand Total Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a Iication with additional 'ustification Approved CAPEX Cost (PhP) 2013 2012 2011 3,839,437.79 3,741,290.57 4,124,048.04 2014 4,090,279.27 I Remarks Total 15,795,055.66 12 lacement of Rotten Poles & Seconda Distribution Line Pro'ect Project Description • Acquisition of steel poles, with length varying from 30 up to 50 feet, which shall replace all rotten wood poles installed within the entire distribution network. Proposed CAPEX Cost (PhP) 2011 2012 I I 112,287,546.52112,766,226.60 2013 18,298,683.53 I Duration 2011 to 2014 2014 15,075,322,64 Total 58,427,779.28 Project Justification • NUVELCO intends to replace its existing old and damaged poles in order to maintain a safe, efficient and reliable distribution s stem. Technical Analysis • Based on NUVELCO's site survey, it was determined that some of the existing poles within the distribution system are already old and dilapidated. These distribution network assets post threat to public safety and contributing factor to the inefficiency and unreliability of the distribution system. It also contributes to the distribution system's continuous and unaccounted losses or non-technical losses. • The proposed projects will provide an assurance of eliminating hazard and reducing nuisance interruptions caused by these assets. It will also provide efficiency and reliability improvement in the distribution s stem. Economic and Cost Analysis • The determination of the number of poles for replacement was based on the actual inventory done by the cooperative. The proposed project cost includes labor cost which was based on 150/0, 16%, 170/0, and 18% of the material cost for the years 2011,2012,2013, and 2014, respectively, and an annual inflation rate factor of 3%. • Shown below is the recommended project cost breakdown, to wit: No. 1 2 Materials Poles Poles Specifications No. of Units Unit Cost (PhP/unit) Year Material Cost (PhP) Labor Cost (PhP) 30' Steel 170 12,710.16 2,160,727.26 324,109.09 35' Steel 200 18,499.55 3,699,910.86 554,986.63 40' Steel 100 22,156.74 2,215,673.52 332,351.03 45' Steel 100 26,085.11 2,608,511.42 391,276.71 30' Steel 170 13,091.47 2,225,549.08 356,087.85 35' Steel 200 19,054.54 3,810,908.19 609,745.31 2011 2012 Project Cost (PhP) 12,287,546.52 12,766,226.60 13 3 4 Poles Poles 40' Steel 100 22,821.44 2,282,143.73 365,143.00 45' Steel 100 26,867.67 2,686,766.76 429,882.68 30' Steel 165 13,482.77 2,224,657.05 378,191.70 35' Steel 231 19,609.53 4,529,800.87 770,066.15 40' Steel 167 23,486.14 3,922,185.27 666,771.50 45' Steel 166 27,650.22 4,589,936.69 780,289.24 2013 50' Steel 11 33,938.23 373,320.57 63,464.50 30' Steel 164 13,854.06 2,272,065.84 408,971.85 35' Steel 196 20,164.52 3,952,245.92 711,404.27 24,150.84 2,753,195.92 495,575.27 614,147.93 69,526.18 40' Steel 114 2014 45' Steel 120 28,432.77 3,411,932.94 50' Steel 11 35,114.23 386,256.53 I Grand Total I 50,105,788.42 I 8,321,990.86 18,298,683.53 15,075,322.64 I 58,427,779.28 I • The Commission reduced the proposed project cost based on its assessment. The reduction was based on the cost alignment of poles with the price benchmark provided in the 2012 NEA Price Index wherein the said price benchmark already includes 5°1o contingency and 12°/0 Value Added Tax (VAT). • The approved project cost includes labor cost but was computed based on 15°/0 of the material cost for the entire CAPEX plan. Moreover, an annual inflation rate of 3°1o was retained in the said cost. • Shown below is the recommended project cost breakdown, to wit: No. 1 2 3 4 Materials Poles Poles Poles Poles Material Cost (PhP) Labor Cost (PhP) 10,204.05 1,734,688.50 260,203.28 12,716.92 2,543,384.00 381,507.60 1,739,525.00 260,928.75 No. of Units Unit Cost (PhP/unit) 30' Steel 170 35' Steel 200 Specifications Year 2011 40' Steel 100 17,395.25 45' Steel 100 20,420.75 2,042,075.00 306,311.25 30' Steel 170 10,510.17 1,786,729.16 268,009.37 35' Steel 200 13,098.43 2,619,685.52 392,952.83 40' Steel 100 17,917.11 1,791,710.75 268,756.61 45' Steel 100 21,033.37 2,103,337.25 315,500.59 30' Steel 165 10,825.48 1,786,203.65 267,930.55 35' Steel 231 13,491.38 3,116,508.88 467,476.33 40' Steel 167 18,454.62 3,081,921.66 462,288.25 45' Steel 166 21,664.37 3,596,286.03 539,442.90 2012 2013 50' Steel 11 28,802.59 316,828.45 47,524.27 30' Steel 164 11,150.24 1,828,639.51 274,295.93 2,723,639.88 408,545.98 35' Steel 196 13,896.12 40' Steel 114 19,008.26 45' Steel 120 50' Steel 11 2,166,941.57 325,041.23 22,314.30 2,677,716.59 401,657.49 29,666.66 326,333.30 48,950.00 37,982,154.69 5,697,323.20 2014 Grand Total Approval Pro'ect to continue as pro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification I Project Cost (PhP) 9,268,623.38 9,546,682.08 13,682,410.97 11,181,761.48 43,679,477.89 Remarks 14 11112]!)~ 11112~0~ __ 9,268,623.38 9,546,682.08 ~3~ 13,682,410.97 15 lacement of Overloaded Distribution Transformers Distribution Line Pro'ect Project Description • Acquisition of distribution transformers (DT) to replace all overloaded and old DTs installed within the entire distribution network. Proposed CAPEX Cost (PhP) 2011 2012 2013 8,956,631.42 10,706,928.02 12,015,039.22 I Duration 2011 to 2014 2014 14,307,633.16 Total 45,986,231.82 Project Justification • The replacement of the existing overloaded and old DTs installed within the network is necessary to address the impending capacity problem and to maintain a safe, efficient and reliable distribution s stem. Technical Analysis • Based on NUVELCO's site survey, there are several areas within the distribution system that contain overloaded and aged/decaying distribution transformers. The condition of such assets is a threat to public safety as well as a contributing factor to the inefficiency and unreliability of a distribution system. • Since the electric cooperative is obliged to provide safe, efficient and reliable distribution system, NUVELCO proposed to replace its distribution transformers in order to eliminate hazard and reduce nuisance interruptions caused by these equipment and provide reliable ower su I to its customers. Economic and Cost Analysis • The determination of the assets to be replaced was based on the actual inventory done by the cooperative. The proposed cost estimates includes an annual inflation rate factor of 3%. • Shown below is the proposed project cost breakdown, to wit: No. 1 2 Materials Distribution Transformer Distribution Transformer Specifications No. of Units Unit Cost (PhP/unit) Year Project Cost (PhP) 15kVA 20 68,137.13 1,362,742.61 25kVA 35 88,407.58 3,094,265.25 37.5kVA 30 107,929.68 50kVA 10 126,173.31 15kVA 23 70,181.24 25kVA 40 91,059.81 2011 3,237,890.43 1,261,733.13 2012 1,614,168.63 3,642,392.24 16 3 4 Distribution Transformer Distribution Transformer 37.5kVA 35 111,167.57 3,890,865.00 50kVA 12 129,958.51 1,559,502.15 15kVA 25 72,225.36 1,805,633.96 25kVA 44 93,712.03 4,123,329.46 37.5kVA 38 114,405.46 50kVA 13 133,743.71 1,738,668.25 15kVA 29 74,269.47 2,153,814.70 25kVA 51 96,364.26 37.5kVA 44 117,643.35 50kVA 15 137,528.91 I • 2013 4,347,407.55 4,914,577.29 2014 5,176,307.51 2,062,933.66 Grand Total I I 45,986,231.82 The Commission reduced the proposed project cost based on its assessment. The reduction was based on the cost alignment of DTs with the price benchmark provided in the 2012 NEA Price Index wherein the said price benchmark already includes 5°1o contingency and 12°/0 Value Added Tax (VAT). Moreover, an annual inflation rate of 3°1o was also retained in the said cost. • Shown below is the approved project cost breakdown, to wit: No. 1 2 3 4 Materials Distribution Transformer Distribution Transformer Distribution Transformer Distribution Transformer Specifications No. of Units Unit Cost (PhP/unit) Year Project Cost (PhP) 15kVA 20 59,638.33 1,192,766.60 25kVA 35 77,380.00 2,708,300.00 37.5kVA 30 94,467.00 50kVA 10 110,435.00 1,104,350.00 1,412,832.04 2011 2,834,010.00 15kVA 23 61,427.48 25kVA 40 79,701.40 37.5kVA 35 97,301.01 50kVA 12 113,748.05 15kVA 25 63,270.30 1,581,757.61 3,612,067.45 2012 3,188,056.00 3,405,535.35 1,364,976.60 25kVA 44 82,092.44 37.5kVA 38 100,220.04 50kVA 13 117,160.49 15kVA 29 65,168.41 1,889,883.99 25kVA 51 84,555.22 4,312,315.98 37.5kVA 44 103,226.64 50kVA 15 120,675.31 2013 1,523,086.39 2014 Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification 2013 10,525,272.98 ' . 4,541 ,972.23 1,810,129.59 Grand Total Approved CAPEX Cost (PhP) 2012 2011 9,371,399.99 7,839,426.60 3,808,361.53 40,290,401.35 I 2014 12,554,301.79 I Remarks Total 40,290,401.35 17 Project No. 9 Project Title Replacement of Kilowatt-hour meter and Meter Clusterin Project Project Priority Project Code Type Rank Category System Efficienc 1 Secondar Distribution Line Pro'ect Project Description I • Acquisition of KWh meters to replace the existing dilapidated and deteriorated meters within the entire franchise with electronic meters. Duration 2011 to 2014 • The newly acquired kWh meters shall then be relocated and clustered to the DUs electric poles from the consumer's remises. Proposed CAPEX Cost (PhP) 2013 2012 2011 9,424,052.18 9,958,079.80 10,450,169.45 2014 11,066,385.93 Total 40,898,687.35 Project Justification • The proposed project is intended to improve the efficiency of the entire distribution s stem. Technical Analysis • Some of the DU's installed kWh meters have exceeded their operational life which leads to the ineffectiveness and unreliability of the meters. The presence of these meters contributes to the continuous and unaccounted losses or high non-technical losses of the distribution utility. • In order to reduce these losses, NUVELCO intends to replace and relocate said kWh meters from the customer's premises and cluster these meters to the DUs electric poles. • Article 11 of the Magna Carta for Residential Electricity Consumers states that; ... The customer has the right to a meter installed in a clean place free of vibration and where it will be easily accessible and visible for reading and testing by both the distribution utility and the consumer ... ... Meters shall be located on the outside wall of the building or private pole and shall not be more than 3 meters nor less than 1.52 meters mounting height. .. ... Clustering of meters may be allowed under any of the following circumstances: 18 1. Upon the request of a customer; 2. When there is no right of way; or 3. In areas with high incidence of electricity pilferages ... 1J • It is clearly stated in the guidelines that all electric kilowatt-hour meters that are put into service should be installed within the premises of the customer. Any deviation from the intended location of the meters should only be based on the circumstances provided in the abovementioned provision and that the DU should present documented proof of such claims. • NUVELCO did not present any proof or documents to substantiate the need of the proposed project. • It further admitted that it has no means of providing technical analysis in determining the root cause of the system loss, and yet it still proposes to cluster the meters. This approach has no technical basis and not acceptable because NUVELCO might end up implementing a wrong solution in addressing a specific problem. It is therefore necessary for NUVELCO to identify precisely the real cause of the problem for them to arrive at the right solution. • NUVELCO provided the benefits derived in replacing the existing KWh meters with electronic meters, as shown in the table below. NUVELCO preferred such type of meter since it has lower internal meter loss compared to the electromechanical meters and that the existing meters performance can no longer be adjusted to its required level. Condition Existing Proposed Meter Type Mechanical Electronic Years Installed 25-30 NA Ave. Internal Meter Loss Ave. Error 0.001343 KW 0.000285 KW 5.1538% 0.3000% 0.001058 KW 248,267 1,679,153 4.8538%1 1,430,886 No. of proposed meters for replacement Ave. Annual Energy/Customer (KWh) Ave. System Loss Saved Energy Saved (KWh) Total Energy Saved (KWh) I • The replacement of KWh meters is justifiable. On the other hand, the relocation and clustering of meters lacks technical 'ustification. Economic and Cost Analysis • The determination of the number of KWh meters for replacement was based on the actual inventory done by the cooperative. The proposed project cost includes labor cost which was based on 15%, 16%, 17%, and 18% of the material cost for the years 2011, 2012, 2013, and 2014, respectively, and an annual inflation rate factor of 30/0. • Shown below is the proposed project cost breakdown, to wit: 19 No. Materials KWh meter Meter seal 1 Material Cost (PhP) Labor Cost (PhP) 30A, electronic 5,500 773.74 4,255,574.40 638,336.16 CI 200, 15A, 2W 1,200 1,696.80 2,036,160.00 305,424.00 - 6,700 15.10 101,180.18 15,177.03 560,000.00 84,000.00 560.00 Conductor Duplex, #2, AWG 4,000 56.20 224,800.66 33,720.10 Conductor Duplex, #6 ACSR 30,000 21.19 635,807.93 95,371.19 Pole Steel, 30' 30 12,710.16 381,304.81 57,195.72 30A, electronic 5,500 796.95 4,383,241.63 701,318.66 CI 200, 15A, 2W 1,200 1,747.70 2,097,244.80 335,559.17 6,700 15.55 104,215.59 16,674.49 576,800.00 92,288.00 2011 Meter seal . Cluster Box - 1,000 576.80 57.89 266,276.38 42,604.22 122,244.67 Conductor Duplex, #2, AWG 4,600 Conductor Duplex, #6 ACSR 35,000 Pole Steel,30' 2012 21.83 764,029.19 30 13,091.47 392,743.96 62,839.03 5,500 820.17 4,510,908.86 766,854.51 CI 200, 15A, 2W 1,200 1,798.61 2,158,329.60 366,916.03 - 6,700 16.01 107,251.00 18,232.67 593,600.00 100,912.00 30A, electronic Cluster Box - 1,000 593.60 Conductor Duplex, #2, AWG 5,100 59.57 303,818.09 51,649.08 Conductor Duplex, #6 ACSR 38,000 22.47 853,678.11 145,125.28 Pole Steel, 30' 30 13,472.77 404,183.10 68,711.13 30A, electronic 5,500 843.38 4,638,576.10 834,943.70 C1200, 15A, 2W 1,200 1,849.51 2,219,414.40 399,494.59 16.46 110,286.40 19,851.55 610,400.00 109,872.00 KWh meter - Meter seal 6,700 2013 - 1,000 610.40 Conductor Duplex, #2, AWG 6,000 61.26 367,549.08 66,158.83 Conductor Duplex, #6 ACSR 44,000 23.10 1,016,444.94 182,960.09 Pole Steel,30' 13,854.07 415,622.24 74,812.00 Cluster Box 30 I • Year 1,000 Meter seal 4 Unit Cost (PhP/unit) - KWh meter 3 No. of Units Cluster Box KWh meter 2 Specifications 2014 Grand Total Project Cost (PhP) 9,424,052.18 9,958,079.80 10,450,169.45 11,066,385.93 I 35,089,441.45 I 5,809,245.90 I 40,898,687.35 I The Commission verified that the proposed project IS viable considering that the project's Net Present Value (NPV) is positive and the Benefit-Cost Ratio is greater than one (1), as manifested in the using the determined was assessment The below. table some incorporating while benefits technical abovementioned significant variables such as its asset life and discount rate of 10 years and BO/o, respectively. The discount rate shall be the NEA interest rate considering that the projects will be funded through NEA loan. 1.53 BIC 8% Interest Rate PV of Benefits PhP43,886,959.40 PVof Cost PhP28,623,009.31 Total Benefits (NPV) PhP15,263,950.09 • The Commission reduced the proposed project cost based on its assessment. The reduction was based on the exclusion of the material cost involving meter clustering which includes meter seals, and the associated manpower or labor cost. However, the annual inflation rate of 30/0 was retained in the said cost. • Shown below is the approved project cost breakdown, to wit: No. Materials 1 KWh meter 2 KWh meter Specifications No. of Units Unit Cost (PhP/unit) 30A, electronic 5,500 773.74 CI 200, 15A, 2W 1,200 1,696.80 30A, electronic 5,500 796.95 Year 2011 2012 Project Cost (PhP) 4,255,574.40 2,036,160.00 4,383,241.63 20 1,200 1,747.70 2,097,244.80 5,500 820.17 4,510,908.86 1,200 1,798.61 30A, electronic 5,500 843.38 CI 200, 15A, 2W 1,200 1,849.51 CI 200, 15A, 2W . 30A, electronic 3 4 KWh meter KWh meter CI200, 15A, 2W 2013 4,638,576.10 2014 Grand Total Approval Pro.ect to continue as ro osed Pro.ect to continue with REVISED Ca ital Ex enditure Pro.ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional .ustification Approved CAPEX Cost (PhP) 2011 2012 2013 6,291,734.40 6,480,486.43 6,669,238.46 2,158,329.60 2,219,414.40 26,299,449.79 I 2014 6,857,990.50 Remarks Total 26,299,449.79 21 II. OTHER NETWORK PROJECTS 10 Connection of New Customers due to Add-on Pro.ects - KWh meters & accessories Distribution Line Pro.ect Project Description • The following are the required specifications of the projects, to wit: a) The service drop wire is a twisted bare and insulated duplex AWG #6 ACSR conductor. Consumers at low voltage have the same service drop wire size; and b) The single phase KWH meters are electronic rated 60A at 240V. Proposed CAPEX Cost (PhP) 2013 2012 2011 4,610,320.11 4,985,262.74 5,385,941.99 I 2014 5,814,908.94 Duration 2011 to 2014 Total 20,796,433.78 Project Justification • The DU is mandated to provide sufficient distribution services and connections to its consumers consistent with the PDC. It is necessary to forecast the number of new connections to determine the quantity of metering equipment and other materials necessary to address load growth. Technical Analysis • The forecasting of the new customers was based on the 7-year historical customer data of NUVELCO. The customer types are forecasted separately to capture the best model fitted to each customer type.' NUVELCO mainly focused on residential customers for this particular project. The models passed and met all the criteria necessary to validate the accuracy of the forecasted model. • The table below shows the forecasted additional residential customer requirement of NUVELCO. Customer Class Residential 2011 Forecasted No. of Customers I 2012 2013 3,271 I 3,434 I I 3,605 I I 2014 3,785 22 Cost Analysis • Shown below is the proposed project cost breakdown, to wit: No. 1 2 3 4 Materials Specifications KWh meter Electronic single phase Service Drop Duplex #(j AWG KWh meter Electronic single phase Service Drop Duplex #(j AWG KWh meter Electronic single phase Service Drop Duplex #(j AWG KWh meter Electronic single phase Service Drop Duplex #(j AWG Length No. of Units Unit Cost (PhP/unit) 773.74 21,190.40 796.95 21,826.11 820.17 22,461.82 843.38 23,097.54 - 3,271 98.13 - - 3,434 103.02 - - 3,605 108.15 - - 3,785 113.55 - Project Cost (PhP) Year 2011 4,610,320.11 2012 4,985,262.74 2013 5,385,941.99 2014 5,814,908.94 I Grand Total 20,796,433.78 I • The above proposed cost estimates includes an annual inflation rate factor of 3%. • The Commission reduced the proposed project cost. The reduction was based on the cost alignment of the conductor for service drop with the price benchmark provided in the 2012 NEA Price Index wherein the said price benchmark already includes 5010 contingency and 120/0 Value Added Tax (VAT). Moreover, the annual inflation rate of 3% was retained considerably in the said cost. • Shown below is the approved project cost breakdown, to wit: No. 1 2 3 4 Materials Specifications KWh meter Electronic single phase Service Drop Duplex #(j AWG KWh meter Electronic single phase Service Drop Duplex #(j AWG KWh meter Electronic single phase Service Drop Duplex #6 AWG KWh meter Electronic single phase Service Drop Duplex #(j AWG Length - No. of Units Unit Cost (PhP/unit) 3,271 773.74 20,770.00 796.95 21,393.10 820.17 22,034.89 843.38 22,695.94 - 98.13 - 3,434 103.02 - - 3,605 108.15 - - 3,785 113.55 - Project Cost (PhP) Year 2011 4,569,066.2'6 2012 4,940,653.84 2013 5,339,769.40 2014 2014 5,769,307.69 Grand Total Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification Approved CAPEX Cost (PhP) 2011 2012 2013 I I 4,569,066.26 4,940,653.84 5,339,769.40 2014 5,769,307.69 20,618,797.19 I Remarks Total 20,618,797.19 23 III. NON-NETWORK PROJECTS Project Project Project Project No. Title Code Type .l • uisition of Test Instruments Customer Efficienc 5 ~ Project Category Non-Network Re uirements Project Description • Acquisition of one (1) unit of each measuring and testing equipment such as Meter Standard, Load Logger, Clamp Ammeter and Megger Tester. Proposed CAPEX Cost (PhP) 2012 2011 - 571,032.00 I Duration 2012 2014 2013 - - Total 571,032.00 Project Justification • The abovementioned equipment are intended to monitor the power quality of the distribution system, the condition of the installed kilowatthour meters, and the condition of the electrical wirings within the customer's premises. equipment shall improve the distribution has the Cost Analysis • The proposed cost components are comparable with the existing market price and available price reference found on the internet. • Shown below is the approved project cost breakdown, to wit: No. Materials No. of Units Unit Cost (PhP/unit) 1 Meter Standard 1 288,400.00 2 Load Logger 1 213,416.00 3 Clamp Ammeter 1 23,072.00 4 Megger Tester 1 46,144.00 Year Project Cost (PhP) 288,400.00 213,416.00 2012 Grand Total 23,072.00 46,144.00 571,032.00 Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro"ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification I Remarks ./ 24 f'" , ...-(!)~~~(!)~-~.3__...-(!)~..-n.atal" Approved CAPEX Cost (PhP) - 571,032.00 - - 571,032.00 25 ~&. Project No. uisition of Lineman's Tools Set ~ Project Type Priority Rank Project Category Customer Efficienc 5 Non-Network Re uirements Project Description I • Acquisition of several safety apparels, such as safety shoes, hardhats and working gloves, to be used by the technical staff of the EC. Proposed CAPEX Cost (PhP) 2012 2011 807,520.00 - Duration 2012 : total 2014 2013 - - 807,520.00 Project Justification / Cost Analysis • As part of the human resource management program, the safety and welfare of its human resources are the priority program. At present, technical personnel, particularly the linemen are equipped with tools and safety personal protective devices which are already old and worn-out due to its everyday use. Furthermore, some field technical men are presently deficient in the necessary safety apparels such as safety shoes, hardhats and working gloves • The Commission finds that the acquisition of linemen's tools set should form part of NUVELCO's operations and maintenance (O&M) ex enditures. Approval Pro.ect to continue as ro osed Pro.ect to continue with REVISED Ca ital Ex enditure Pro.ect to continue with Technical Amendments Project to be re-aligned to applicant's Operations and Maintenance Ex enditure Accounts I Remarks 26 Project Project Project Project Priority Project No. Title Code Type Rank Category .l • uisition of Vehicles Customer Efficienc 5 Non-Network Re uirements Project Description I Duration • Acquisition of utility vehicles intended for operation and maintenance and service vehicles intended for 2011 to 2014 emplo ees and customer services. Proposed CAPEX Cost (PhP) 2013 2012 2011 4,488,000.16 5,941,040.00 8,369,760.00 Project Justification • NUVELCO intends to augment the vehicles that exceeded the be replaced considering that it frequent breakdown and some 2014 3,296,160.00 Total 22,094,960.16 its existing fleet of vehicles and replace standard asset life. Old vehicles should produces high maintenance cost due to of its spare parts are already obsolete. • NUVELCO finds the project necessary in order to meet the growing demand of its consumers. The continuous increase in the distribution lines, the power demand and the number of customers should require an expansion of utility and service vehicles in order to maintain these assets appropriately and respond to customer demands more efficiently. • The following table shows the proposed and the approved number of vehicles for the entire CAPEX years, to wit: No. of Units No. Materials 1 Double Cab Specifications Proposed Recommended 4x4 pick-up 2 1 3 3 2 Double Cab 4x2 pick-up 3 Double Cab 4x4 pick-up (drop-side) 1 1 4 Van 4x4 Passenger 3 2 5 6 Motorcycle - 2 2 Motor cab 1 1 7 Truck Tadano 4 4 8 9 10 Man-lift Standard 4 4 Man-lift 3-fold extended boom 1 Shuttle Bus - 1 1 22 19 Grand Total • The Commission excluded assessment, to wit: some vehicles - based on the following the required number of vehicles, cab and van. The Commission 27 allocated only one (1) unit per area/office for a specific type of vehicle; and 2. The shuttle bus should be deferred since it does not address the project's intention of providing service to its customers. The said vehicle would only serve the employees of NUVELCO and not its customers. Cost Analysis • NUVELCO considered an annual inflation rate factor of 3% In its proposed project cost. Shown below is the proposed project cost breakdown, to wit: No. 1 Materials Unit Cost (PhP/unit) Double Cab 4x4 pick-up ESD 1 1,568,000.00 4x4 Passenger Metering 1 1,008,000.00 Motorcycle - Metering 2 70,000.00 Metering 1 92,000.16 Truck Tadano Aritao & Solano Area 2 840,000.00 Double Cab 4x2 pick-up North & South Area 2 1,095,920.00 Double Cab 4x4 pick-up (drop-side) Apprehension 1 980,560.00 Tadano Bambang & Dupax Area 2 865,200.00 Man-lift Standard Solano 1 1,038,240.00 Double Cab 4x4 pick-up ISO 1 1,662,080.00 Double Cab 4x2 pick-up FSD 1 1,127,840.00 Van 4x4 Passenger Audit 1 1,068,480.00 Shuttle Bus - Main office 1 1,662,080.00 1 1,068,480.00 1 1,780,800.00 1 1,098,720.00 2 1,098,720.00 2 Truck 4 No. of Units Van Motor cab 3 Department Designation Specifications Man-lift Standard Bagabag Area Man-lift 3-fold extended boom Subtransmission Van 4x4 Passenger ISO Standard Bayombong Area Man-lift O&M & Dupax I Year Project Cost (PhP) 2011 4,488,000.16 2012 5,941,040.00 2013 8,369,760.00 2014 3,296,160.00 Grand Total I 22,094,960.16 I • The Commission reduced the proposed project cost based on its review. The reduction was based on the exclusion of some vehicles in the project, as discussed previously. The annual inflation rate of 3% was retained considerably in the said cost. • Shown below is the approved project cost breakdown, to wit: No. 1 2 3 Materials Department Designation Specifications No. of Units Unit Cost (PhP/unit) Double Cab 4x4 pick-up ESD 1 1,568,000.00 Van 4x4 Passenger Metering 1 1,008,000.00 Motorcycle Metering 2 70,000.00 Motor cab - Metering 1 92,000.16 Truck Tadano Aritao & Solano Area 2 840,000.00 Double Cab 4x2 pick-up North & South Area 2 1,095,920.00 Double Cab 4x4 pick-up (drop-side) Apprehension 1 980,560.00 Tadano Bambang & Dupax Area 2 865,200.00 Manlift Standard Solano 1 1,038,240.00 Double Cab 4x2 pick-up FSD 1 1,127,840.00 Van 4x4 Passenger ISO/Audit 1 1,068,480.00 Manlift Standard Bagabag Area 1 1,068,480.00 3-fold extended boom Subtransmission O&M 1 1,780,800.00 Truck Manlift Year Project Cost (PhP) 2011 4,488,000.16 2012 5,941,040.00 2013 5,045,600.00 28 Standard Bayombong Area & Dupax 2,197,440.00 17,672,080.16 Approval Pro'ect to continue as roposed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification I Approved CAPEX Cost (PhP) 2011 2012 2013 2014 4,488,000.16 5,941,040.00 5,045,600.00 2,197,440.00 Remarks Total 17,672,080.16 29 Project Project Project Project Priority Project No. Title Code Type Rank Category A • uisition of Meter Readin Customer Efficienc 5 Non-Network Re uirements Project Description I • Acquisition of several new portable devices intended for the application of meter reading, billing and collection s stem. Proposed CAPEX Cost (PhP) 2012 2011 - 2012 Total 2014 2013 - 2,907,072.00 Duration - 2,907,072.00 Project Justification • NUVELCO presently relies on "centralized" processing with respect to its customers' energy consumption. The said process requires manual reading of each customer's consumption which will then recorded in the EC's main computer. • The proposed project of "read & bill" system or a system of collecting energy bills from the customers using the meter-reading/billing equipment would enhance its customer service more efficiently. NUVELCO intends to use such system and replace the said existing billing process. • The proposed project requires hand-held computerized metering and billing devices with memo card for file storage. Cost Analysis • Shown below is the proposed project cost breakdown, to wit: Materials Portable Meter Reading Gadgets No. of Units Unit Cost (PhP/unit) Year Project Cost (PhP) 18 161,504.00 2012 2,907,072.00 • The Commission reduced the proposed project cost based on its assessment. The proposed cost of equipment is expensive compared to the approved cost of advance meter reading/billing equipment. The Commission adopted the cost of the metering/billing equipment approved to ISECO. • Shown below is the approved project cost breakdown, to wit: 30 I No. 1 2 3 4 Materials' "';~'. .. PSION Neo Wall Charger Adaptor Docking Connector Lithium Ion Battery No. of Units UnitCost (PhP/uriit) 18 18 18 18 35,400.00 2,073.60 1,324.80 5,100.00 Year Project Cost (PhP) 2012 637,200.00 37,324.80 23,846.40 91,800.00 Grand Total 790,171.20 Recommendation Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification I Remarks Approved CAPEX Cost (PhP) 2011 - 2012 790,171.20 2014 2013 . - - Total 790,171.20 31 ~&. ~ uisition of Office Furniture and E ui ment ~ ~ ~ Project Category Customer Efficienc 5 Non-Network Re uirements 1- uisition of office furniture and e Proposed CAPEX Cost (PhP) 2011 2012 268,800.00 807,520.00 2013 2014 890,400.00 Total 213,640.00 2,180,360.00 Project Justification • NUVELCO intends to acquire office furniture and equipment in order to improve its customer service program. The objectives of the program are as follows: 1. To provide customers the quality of institutional services; and 2. To render fast and effective way of processing electric service application, inquiries pertaining to billing, membership and service concerns through automation. • The Commission approves the proposed project excluding the office furniture which are not included in the list of assets to be capitalized in the CAPEX guidelines. These assets should form part of the a licant's 0 erations and maintenance O&M ex enditures. Cost Analysis • NUVELCO considered an annual inflation rate factor of 30/0 in its proposed project cost. Shown below is the proposed project cost breakdown, to wit: No. Materials 1 Office Furnitures 2 Data server & workstations 4 Unit Cost (PhP/unit) 1 lot 268,800.00 2011 268,800.00 807,520.00 2012 807,520.00 1 lot 284,928.00 6 41,552.00 2013 249,312.00 Computer for ID processing 1 356,160.00 Finger Scanner 5 42,728.00 2014 213,640.00 Finger Scanner I • Project Cost (PhP) Year 1 set Office Furnitures 3 No. of Units 284,928.00 356,160.00 Grand Total I 2,180,360.00 With the previously discussed technical amendments, project cost breakdown are as follows: No. Materials No. of Units Unit Cost (PhP/unit) Year I the approved Project Cost (PhP) 1 Data server & workstations 1 807,520.00 2012 807,520.00 2 Finger Scanner 6 41,552.00 2013 249,312.00 32 Computer for 10 processing 356,160.00 Finger Scanner 213,640.00 . Grand Total 1,626,632.00 I • The devices are comparable with the existing market price and available price reference found in the internet. Meanwhile, the annual inflation rate factor of 30/0 was retained in the recommended project cost. Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next ap lication with additional 'ustification Approved CAPEX Cost (PhP) 2012 2011 807,520.00 . 2013 605,472.00 I 2014 213,640.00 Remarks ..Total" 1,626,632.00 .. 33 Project No. 16 Project Title Acquisition of Engineering Analysis Software and Hardware Project Project Priority Project Code Type Rank Category Customer Efficienc 5 Non-Network Re uirements Project Description I • Acquisition of engineering analysis software and hardware capable to interface with the existing SYNERGEE Engineering Anal sis software. Proposed CAPEX Cost (PhP) 2012 2011 - 6,968,925.98 2014 2013 - Duration 2012 Total - 6,968,925.98 Project Justification • NUVELCO has existing SYNERGEE Engineering Analysis software which plays a vital tool in assisting the engineers in the performance of their duties such as analysis of the distribution system to develop plans and procedures and to improve the same efficiently. However, its usage is minimized due to the absence of technical database and software that can interface with the data inputs required by the said software. • The proposed project shall support its preparation for distribution network planning to improve, if not maintain, an efficient, reliable and safe distribution s stem. Cost Analysis • Some of the materials and components in the proposed project cost include 12% VAT. Moreover, some of the cost components are material cost incurred in the surveys such as logistics and office supplies. • Shown below i~ the proposed project cost breakdown, to wit: No. No. of Units Activity Unit Cost (PhP/unit) Year Material Cost (PhP) Cost wI VAT (PhP) Project Cost (PhP) 1 Manpower for Pole Numbering 16,500 50.05 825,825.00 99,099.00 924,924.00 2 Manpower for Distribution Mapping 20,000 41.88 837,571.43 100,508.57 938,080.00 3 Manpower for Transformer Numbering 3,030 85.80 259,974.00 31,196.88 291,170.88 1,365,525.39 163,863.05 1,529,388.43 4 Manpower for Consumer 5 Manpower for Distribution Encoding 6 Manpower for Consumer Encoding Line Data Survey Line Data 2012 70,362 19.41 20,000 7.15 143,000.00 17,160.00 160,160.00 70,362 2.15 150,926.49 18,111.18 169,037.67 34 . 7 Integrated Facility Data Management System (IFDMS) installation, trainings and consultancy 1 set 8 Engineering Hardware and Logistic 1 set 371,000.00 371,000.00 9 Engineering Hardware Accessories 1 set 799,600.00 799,600.00 10 Outsourcing Surveyors Management Team 1 set 462,000.00 11 Office Supplies used in surveys 1 set 35,565.00 and Project 1,150,000.00 1,150,000.00 I I Grand Total 138,000.00 1,288,000.00 462,000.00 - 462,000.00 35,565.00 - 35,565.00 6,400,987.31 I 567,938.68 371,000.00 799,600.00 I 6,968,925.98 I • The proposed cost components are comparable with the existing market price and available price reference found in the internet. • The Commission reduced the proposed project cost based on its assessment. It excluded the labor and material costs involving surveying activities, particularly activity nos. 1-6 and 10-11, in the cost component. These costs should form part of the applicant's operations and maintenance (O&M) expenditures. • Shown below is the approved project cost breakdown, to wit: No. of Units Unit Cost (PhP/unit) Year Material Cost (PhP) Cost wI VAT (PhP) Project Cost (PhP) 1,150,000.00 138,000.00 1,288,000.00 No. Activity 7 Integrated Facility Data Management System (IFDMS) installation, trainings and consultancy 1 set 8 Engineering Hardware and Logistic 1 set 371,000.00 371,000.00 . 371,000.00 9 Engineering Hardware Accessories 1 set 799,600.00 799,600.00 - 799,600.00 1,288,000.00 2012 Grand Total 2,320,600.00 Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification Approved CAPEX Cost (PhP) 2012 2011 2,458,600.00 - 2014 2013 - 138,000.00 I 2,458,600.00 Remarks Total - 2,458,600.00 35 Project No. 17 Project Title Acquisition of Accounting, Payroll, Warehousing and Member-Consumer Information S stem Software Project Project Priority Project Code Type Rank Category Customer Efficienc 5 Non-Network Re uirements Project Description I • Acquisition of computer software and hardware intended for accounting, payroll, warehousing, and member-consumer information s stem. Proposed CAPEX Cost (PhP) 2012 2011 - 7,500,000.00 2014 2013 - Duration 2012 Total - 7,500,000.00 Project Justification • NUVELCO intends to acquire Management Information System software in order enhance the accounting practices. The proposed project shall adopt automated financing and accounting system which will aid its management in the decision making with respect to accounting matters. • The overall design of the proposed system will also provide the necessary document that will comply with the current demands of the electric industry, the existing government and regulatory agencies, and the actual work flow of the EC. Cost Analysis • NUVELCO failed to submit the necessary project cost breakdown or any quotation to justify the proposed project cost amounting to PhP7.5 Million. Thus, the Commission deferred consideration of this project which should be included in the next CAPEX application of NUVELCO. Approval Project to continue as proposed Pro.ect to continue with REVISED Capital Ex enditure Pro.ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional .ustification I Remarks 36 . - Project No. Project Title • - A • uisition of Street Li ment ~ ~ Customer Efficienc ~ 5 Project Category Non-Network Re uirements Project Description • AcquIsItion of street lightIng equipment to be installed within road/ri ht of wa areas with insufficient Ii htin . Proposed CAPEX Cost (PhP) 2011 2012 560,000.00 576,800.00 2013 593,600.00 I Duration 2011 2014 610,400.00 to 2014 Total 2,340,800.00 Project Justification • Part of the social responsibility program of NUVELCO is to provide street lighting equipment within its franchise area. The proposed project intends to install several sets of street lighting equipment that shall be im lemented within the a lied CAPEX ears. Cost Analysis • NUVELCO considered an annual inflation rate factor of 3% in its proposed project cost. Shown below is the proposed project cost breakdown, to wit: No. Materials No. of Units Unit Cost (PhP/unit) Year Project Cost (PhP) 1 Street Light 700 800.00 2011 560,000.00 2 Street Light 700 824.00 2012 576,800.00 3 Street Lig ht 700 848.00 2013 593,600.00 4 Street Light 700 872.00 2014 610,400.00 Grand Total • I 2,340,800.00 I Upon verification, the proposed quantity of street lighting equipment does not coincide with its forecast for the entire applied CAPEX years. Thus, the Commission reduced the project cost consistent with forecasted number of equipment. Shown below is the approved project cost breakdown, to wit: No. Materials No. of Units Unit Cost (PhP/unit) Year Project Cost (PhP) 1 Street Light 130 800.00 2011 104,000.00 2 Street Light 18 824.00 2012 14,832.00 3 Street Light 7 848.00 2013 5,936.00 4 Street Lig ht 7 872.00 2014 6,104.00 Grand Total 130,872.00 I • The required materials are comparable with the existing market price and available price reference found in the internet. The annual inflation rate factor of 3% was retained considerabl in the a roved ro'ect 37 cost. Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Capital Expenditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next ap lication with additional 'ustification Recommended CAPEX Cost (PhP) 2013 2012 2011 14,832.00 5,936.00 104,000.00 I 2014 6,104.00 Remarks Total 130,872.00 38 " Project No. 19 Project Title Construction of NUVELCO Office Buildings & Facilities Project Code Project Type Customer Efficienc 5 ~ Project Category Non-Network Re uirements Project Description I Duration • The proposed projects involve the following activities: 1. Construction of Engineering Services Department (ESD) and Warehouse Building; 2. Rehabilitation of Solano Substation Office, Administrative Building and Gymnasium; 3. Construction of Information Technology (IT) 2011 to 2014 office at the northern part of the franchise; 4. Construction of headquarters perimeter fencing and lighting; 5. Installation of water system; and 6. Construction of General Mana er's uarter. Proposed CAPEX Cost (PhP) 2013 2012 2011 2,730,000.00 12,643,226.20 7,447,721.36 2014 1,801,156.88 Total 24,622,104.44 Project Justification • The proposed project shall ensure the convenience of the memberconsumers as well as the employees during the official transactions. • The following are detailed discussions of each activity of the projects: 1. The ESD, Administrative and Warehouse Sections are presently located within the main building causing area congestion. The construction of ESD and warehouse building shall provide better working conditions to the employees; 2. The rehabilitation of Solano Substation office, Administrative Building and Gymnasium, which is located at NUVELCO's main office, is intended to enhance its existing physical condition; 3. The construction of IT building at Bonfal, Bayombong, Nueva Vizcaya is necessary considering that the said area has reliable internet network services; 4. The construction of fencing and lightings at NUVELCO's main office is necessary to ensure its security and protection; 5. Upgrading of existing water facilities is necessary to ensure continuous supply of water to be used by the employees; and 6. The construction of GM's quarter is intended to accommodate the EC's eneral mana er and his/her visitors. 39 Cost Analysis • The proposed project cost includes other financial factors such as labor cost (35% of material cost), administrative and supervision cost (5% of material and labor cost), and contingencies (10% of material, labor cost, and administrative and supervision cost). • Shown below is the proposed project cost breakdown, to wit: 1 2 Year Activity No. Construction of ESD & Warehouse Rehabilitation of Solano Substation Building Bldg. 3 Construction of IT Office at North Area Office 4 Construction of HQ Perimeter Fencing & Lighting 5 Installation 6 Construction 2012 of Water System of HQ Perimeter Fencing & Lighting 2013 7 Repair of Admin Bldg. 8 Construction of GM's Quarter 9 Gymnasium Improvement '-- 2011 2014 G_ra_n_d_To_ta_I Material Cost (PhP) Other Costs (PhP) Project Cost (PhP) 1,430,174.77 799,825.23 2,230,000.00 320,666.99 179,333.01 500,000.00 5,515,472.19 3,084,527.81 8,600,000.00 2,272,391.34 1,270,834.86 3,543,226.20 370,370.37 129,629.63 500,000.00 2,066,651.90 1,155,775.07 3,222,426.97 1,724,862.40 964,629.30 2,689,491.70 984,962.45 550,840.24 1,535,802.69 1,155,143.10 646,013.78 1,801,156.88 115,840,695.51 I 8,781,408.93124,622,104.441 • The Commission reduced the proposed project cost based on its assessment. The reduction was based on the following factors: a) The exclusion of all rehabilitation activities and gymnasium improvement; b) The exclusion of administrative and supervision cost; and c) The reduction of labor cost and contingencies to 250/0and 5% of the required material cost, respectively. • The rehabilitation activities and its corresponding costs should form part of NUVELCO's operations and maintenance (O&M) expenditures considering that said activities are expenditures on repairs or maintenance of an asset. Pursuant to the amended CAPEX Rules, these type of expenditures should be excluded from the capitalization cost of the electric cooperative. As such, said activities should be realigned and form part of NUVELCO's O&M budget. • The required materials of the approved projects are comparable with the existing market price and available price reference found in the internet. Shown below is the approved project cost breakdown, to wit: Year Activity No. 1 Construction of ESD & Warehouse 2 Construction of IT Office at North Area Office Building 3 Construction 4 Installation of HQ Perimeter Fencing & Lighting 2011 2012 of Water System 5 Construction of HQ Perimeter 6 Construction of GM's Quarter Fencing & Lighting Grand Total 2013 Material Cost (PhP) Cost of Labor & Contingency (PhP) Project Cost (PhP) 1,430,174.77 429,052.43 1,859,227.20 5,515,472.19 1,654,641.66 7,170,113.85 2,272,391.34 681,717.40 2,954,108.74 370,370.37 111,111.11 481,481.48 2,066,651.90 619,995.57 2,686,647.47 984,962.45 295,488.74 1,280,451.19 12,640,023.02 3,792,006.91 16,432,029.93 40 Approval Pro.ect to continue as pro osed Pro.ect to continue with REVISED Ca ital Ex enditure Pro.ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional .ustification Recommended CAPEX Cost (PhP) 2012 2013 2011 1,859,227.20 10,605,704.07 3,967,098.66 I Remarks ./ ./ 2014 - Total 16,432,029.93 41 Project Project Project Project Priority Project No. Title Code Type Rank Category • & • uisition of Office Stand-b Power Generator Customer Efficienc 5 Non-Network Re uirements Project Description Acquisition of one (1) set of 100 kVA, Cummins, power enerator. Duration ill Proposed CAPEX Cost (PhP) 2011 2012 - 1,120,000.00 2013 2014 - 2012 Total - 1,120,000.00 Project Justification • The proposed generator set would provide back-up electricity to its main office in case of power failure within the area. It shall enhance customer service reliability considering the office work flow will not be interru ted even durin such event. Cost Analysis • The total cost of the equipment is PhP1.12 Million. However, NUVELCO failed to submit the necessary project cost breakdown or any quotation to justify the proposed amount. • The Commission determined that a 100 kVA Cummins brand generator with similar proposed specifications amounted to US$9,145.00, equivalent to PhP453,635.90 (inclusive of 12% VAT and 3% inflation rate). Thus, the approved proposed project cost amounted to PhP453,635.90. • NUVELCO should secure the appropriate Certificate of Compliance (COC) from the Commission prior to the operation of the generation facilities ursuant to Resolution No. 09, series of 2010. Approval Pro'ect to continue as ro osed Pro'ect to continue with REVISED Ca ital Ex enditure Pro'ect to continue with Technical Amendments Project to be deferred which may be included in its next a lication with additional 'ustification Approved CAPEX Cost (PhP) 2011 2012 453,635.90 - 2013 I ./ 2014 - Remarks - Total 453,635.90 42