Magnum® Steel Push PierTM Technical
Transcription
Magnum® Steel Push PierTM Technical
Magnum Piering, Inc. Magnum® Steel Push PierTM Technical Reference Guide May 10, 2004 © Copyright 2002-04 Magnum Piering, Inc. All Rights Reserved. No portion of this document may be copied or reproduced in any manner whatsoever without written approval from Magnum Piering, Inc. Magnum® Steel Push PieringTM Technical Reference Guide TABLE OF CONTENTS Introduction Introduction Letter Magnum Products Applications Foundation Repair Guide Specifications Geotechnical Report Inspection Case Study Engineering Axial Capacity Bracket Eccentricity Anchor Bolts Specifications Pier Capacity Bracket Spacing Product Drawings Testing Bracket Strength Pier Shaft Strength MAGNUM® STEEL PUSH PIER™ TECHNICAL REFERENCE GUIDE Introduction by Howard A. Perko, Ph.D., P.E. Consulting Engineer for Magnum Piering, Inc. Push pier is the trade name used in conjunction with the hydraulically-jacked, steel pipe micropile. Although Magnum steel push piers and other similar systems have been used to underpin and repair existing structures throughout the United States for over 50 years, very few engineers and architects are familiar with their capabilities and applications. This is due in part to the general lack of technical information available on the subject of push piering. The Magnum Steel Push Pier Technical Reference Guide was developed specifically for architects, geotechnical engineers, structural engineers, and building officials. It contains considerable details regarding the axial and lateral capacity, connection to structures, installation procedures, design, and specification of hydraulically-jacked steel push piers. Sample details, plans, reports, inspections, and specifications are included. The purpose of this guide is to provide the background knowledge necessary to not only ascertain when steel push piers are an appropriate foundation repair alternative but also to enable the composition of a detailed performance specification. As will be discussed in more detail herein, one of the advantages of steel push piering is that by virtue of the method of installation a full-scale load test is performed at every pier location, and capacity can be verified to a high degree of accuracy. Almost all push piers are installed using the weight of the structure to provide the necessary force to drive the pier. A significant advantage of Magnum steel push piers is that they are installed using the foundation bracket to transfer the weight of the structure to the pier, and hence the integrity of the structure, the connection of the bracket to the structure, and the mechanical strength of the bracket are all tested during proof loading of Magnum steel push piers. Thank you for your interest in Magnum steel push piering. Howard A. Perko, Ph.D., P.E. ABBREVIATED CURRICULUM VITAE OF HOWARD A. PERKO, Ph.D., P.E. EDUCATION Ph.D. Geotechnical Engineering, May 2002, Colorado State University M.S. Geotechnical Engineering, May 1996, Colorado State University B.S. Civil/Mining Engineering, May 1993, Michigan Technological University PROFESSIONAL ENGINEERING REGISTRATION Colorado (No. 33340) Ohio (No. E-66008) Wisconsin (No. 35955) West Virginia (No. 15378) Minnesota (No. 43042) Kentucky (No. 22128) New York (No. 081365) Florida (No. 61051) Georgia (Pending) SELECT WORK EXPERIENCE 2000 to Present Engineering Consultant, Magnum Piering, Inc., Cincinnati, OH 1998 to Present Principal Engineer, Secure Foundations, Inc., Fort Collins, CO 1994-1998 Project Engineer, CTL/Thompson, Inc., Denver, CO Exclusive helix pier and steel push pier foundation consultant for Magnum Piering, Inc. Manage telephone technical support center for foundation installation contractors. Coordinate on-going product development and product testing activities. Developed plans and specifications for manufactured foundation components. Authored product technical support documents. Founder and majority owner of a consulting structural engineering firm that specializes in design of new foundations and foundation repair plans. The firm currently employs 11 engineers, technicians, and support staff, and has completed over 500 projects ranging from light residential to low-rise commercial buildings. (www.secureengineer.com) Planned and supervised geotechnical field investigations and materials testing programs and wrote soil and foundation reports. Project experience includes several structures supported by helix foundations, small to large zoned earth dams, ski areas, underground garages and tanks, pavements, utilities, and commercial and residential structures. Performed one of the first helix foundation inspections in Colorado. SELECT PUBLICATIONS Perko, H.A. (2003). “Lateral Capacity and Buckling Resistance of Helix Pier Foundations”, Foundations Technology Seminar – Helical Foundations and Tie-Backs, Deep Foundations Institute, Helical Pile Committee, University of Cincinnati, Cincinnati, OH Perko, H.A. (2000). “Energy Method for Predicting the Installation Torque of Helical Foundations and Anchors”, New Technologies and Design Developments in Deep Foundations, N.D. Dennis, Jr., R. Casteli, and M.W. O’Neill, Eds., ASCE Press, Reston, VA, pp. 342-352. PATENTS Earth Anchors and Methods for their Use, U.S. Patent No. 6,058,662. Helice Pier Post and Method of Installation, U.S. Patent No. 6,722,821 SELECT AWARDS NASA Graduate Student Research Fellowship, Jet Propulsion Laboratory, 1999-2002 First Place Technical Paper, Graduate Division, AIAA Regional Conf., Albuquerque, NM, 1996 Initiation to Chi Epsilon, Civil Engineering Honor Society, Houghton, MI, 1992 SELECT MEMBERSHIPS Associate Member, American Society of Civil Engineers Member, Deep Foundation Institute Helical Pile Committee Inductee, Order of the Engineer Magnum Steel Push Piering Products About Magnum Piering Magnum Piering, Inc. was founded in 1985 by Mr. Donald Rippe, Sr. in St. Louis, MO. Mr. Rippe invented the Magnum® Plate Bracket for which he received a U.S. Patent in 1989. The Magnum® Plate Bracket is a key component of a steel push piering system known as the Magnum® Steel Push Piering System. Also, Mr. Rippe invented and received a patent for the Magnum® Slab Jack System, which is used to lift sunken concrete slabs. These two product lines, along with other piering products, are all manufactured at Magnum’s manufacturing plant and are distributed nationwide through a network of Authorized Magnum Piering Dealer/Installers. Mr. Brian Dwyer, owner of Dwyer Companies, purchased Magnum Piering, Inc. in April of 2000 and relocated all Magnum operations to the company’s corporate headquarters in West Chester, OH. Dwyer Concrete Lifting, another subsidiary of Dwyer Companies, is the Authorized Magnum Piering Dealer/Installer for Ohio, Indiana and Kentucky. The Magnum® Steel Push Piering system is recognized in the industry as one of the most efficient and cost effective underpinning systems for use in stabilizing and lifting residential and light commercial structures. Also, each of Magnum’s Authorized Dealer/Installers are required to complete the Magnum Piering Authorized Dealer Certification Program. The combination of this comprehensive training program and Magnum’s engineering and field support, provides an unequalled level of technical proficiency within the steel push piering industry. Magnum® Steel Push Piering products are manufactured at Magnum’s headquarters in West Chester, Ohio using only the finest high-grade steel and welding materials. Magnum’s commitment to superior product quality is unparalleled in the industry. When you specify Magnum® Steel Push Piering products, you will have confidence knowing you have specified the very best. Magnum Piering, Inc. Magnum Steel Push Piering Products Unless You Tell Them . . . Clients & General Contractors are Going to Think All Steel Push Pier Systems are the Same • Time Tested - Installations Since 1987 • Guaranteed Load Testing for Each Pier Installed • Engineering Reference Manual & Support • Most Efficient System on the Market • Calibrated Hydraulic Ram Program • Patented Plate Bracket or Angle Brackets • Dealer Certification & Training • Highest Capacity for Lowest Cost Per Pier • Dealer/Installers Coast-to-Coast • Case Study Library At Magnum Piering, we take great pride in our push piering products, and our commitment to engineering and technical support is unequalled in the industry. When You Specify Magnum Steel Push Piers, . . . You’re Specifying the Very Best! Magnum Steel Push Piering Products Pier Sections • 36 Inch Length • 3 Inch O.D. • Mechanical steel tube with minimal tensile & yield strength of 50,000 PSI • Steel Specification ASTM A-513 Available In • 1/8” Wall Thickness • 1/4” Wall Thickness • Optional Hot-Dip Galvanize Magnum Steel Push Piering Products Foundation Brackets Magnum Plate Bracket U.S. Patent #5,234,287 Bracket Specifications • Bracket Tube Wall 3.875 in. O.D. • Bracket Tube ASTM A-519 Grade 1026 • 70,000 # Minimum Tensile Strength • 60,000 # Minimum Yield Strength • Bracket Plate ASTM A-36 Hot Rolled Steel • 3600 # Minimum Yield Magnum Angle Bracket Magnum Steel Push Piering Products The Company & Support Behind the Products By having registered geotechnical engineers and structural engineers on staff, Magnum Piering takes its commitment to engineering and technical support very seriously. The company periodically hosts engineering seminars including load tests and field demonstrations with the company’s steel piering systems. In addition to distributing technical reference manuals, the company also makes project case history information available to engineers, architects and general contractors. Magnum Piering - where engineering and technical support are part of our everyday life. EXAMPLE SPECIFICATIONS FOR STEEL PUSH PIER INSTALLATION EXAMPLE SPECIFICATIONS FOR STEEL PUSH PIER INSTALLATION 1. SCOPE This item pertains to the installation of steel push piers at the locations shown on the Plans or staked by the Owner or General Contractor. These specifications and the Plans shall be used in conjunction with a standard contract to procure the work. 2. ACCESS Owner will provide for right of entry of Push Pier Foundation Contractor, all necessary personnel, and equipment for conducting the steel push pier installation work. Push Pier Foundation Contractor will remove and replace any structures, utilities, pavements, landscaping and other improvements in the work area to facilitate steel push pier installation. Reasonable care shall be exercised by Push Pier Foundation Contractor to avoid damage to existing structures, utilities, pavements, landscaping and other improvements during the course of the steel push pier installation work. 3. UTILITIES Owner or General Contractor will locate all underground structures and utilities. Any such underground structures and utilities in and nearby areas of the steel push pier installations will be clearly marked prior to steel push pier installation work. No steel push pier shall be installed at a horizontal distance from a utility or underground structure if the horizontal distance is equal to or less than half the depth of the utility. 4. SAFETY In accordance with generally accepted construction practices, the Push Pier Foundation Contractor shall conduct construction operations in such a manner as to assure maximum safety of persons and property in the immediate vicinity of steel push pier installation work. Push Pier Foundation Contractor shall provide and utilize safety clothing and equipment in accordance with General Contractor’s safety plan and OSHA Standards. 5. INSURANCE The Push Pier Foundation Contractor shall obtain and maintain general liability insurance to the limits described in the Owner’s contract and adequate Worker Compensation Insurance as prescribed by the Worker’s Compensation Act. This insurance shall cover all of the Push Pier Foundation Contractor’s personnel on site at anytime. © Copyright 2002 Magnum Piering, Inc. All Rights Reserved (may be copied for use in construction specifications) 6. CAPACITY Loads shown on the Plans are design allowable loads. These loads shall include dead loads and live loads of an existing structure as determined by a licensed professional engineer. Live loads shall include snow, wind, and earthquake forces as well as other applicable forces. Push pier spacing shall be such that the design capacity of the push piers are capable of supporting the total load of the structure. In areas of soft soils or fill, downdrag of soils against push piers should be added to the total load on the piers. A Minimum Factor of Safety of 1.5 should be used to determine the required ultimate capacity of the steel push piers with regard to their interaction with soil and bedrock. The Push Pier Installation Contractor shall install all piers to the required ultimate capacity at each pier location. The capacity of a push pier and bracket used to underpin an existing structure is as much a function of the strength of the concrete in the existing structure as it is a function of the pier and bracket capacity. Application of lateral load and overturning moment to an existing structure through the process of underpinning is an unavoidable consequence of any underpinning system. The Push Piering Contractor and the Structural Engineer must evaluate the condition of an existing structure in the field to estimate the load that can be applied safely to an existing structure without causing additional distress. The Push Piering Contractor’s method of steel push pier installation must include a means for directly testing the connection of the bracket to the structure for field verification. If push piers are installed in areas of expansive soils or where other tensile loads are applied, the grouting, placement of reinforcing bar within the pier, and/or welding should be considered as per the Plans. 7. MATERIALS All steel push pier materials including the bracket, installation rams, and pier shaft shall be manufactured by Magnum Piering, Inc. or an equivalent. Steel push piers shall be 3" O.D. round shaft and shall have the required pipe wall thickness so as to prevent buckling during installation. The potential for buckling is often evidenced by spring-back of the pier shaft after removing the applied installation load. Spring-back is the slight upward movement of the pier in a direction opposite the direction of installation. Push piers shall be installed with a minimum of observable spring-back. If buckling or spring-back is observed, steel push piers shall be filled with concrete grout. In severe corrosive soils, steel push piers shall be protected from corrosion by hot-dip galvanizing per ASTM A153 or shall be filled with concrete grout. The steel push pier shaft may be required to resist lateral loads in addition to buckling loads as shown on the Plans. The pier shaft and connection between the pier foundation and the structure shall resist lateral loads as specified by the Structural Engineer. The push pier shaft and connections shall have a minimum structural section modulus and the steel shall have a minimum tensile strength as specified on the Plans. The maximum section modulus for typical steel push piers is 1.37 in3 and common tensile strength is 70 ksi. Push pier connections shall consist of in-line, rigid inner sleeves. © Copyright 2002 Magnum Piering, Inc. All Rights Reserved (may be copied for use in construction specifications) 8. INSTALLATION Each steel push pier shall be advanced into the ground by application of axial force using a single calibrated installation ram pressing directly against the top of the pier. When forward advancement of a push pier is halted by soil resistance, the force exerted by the ram indicates the ultimate capacity of the push pier. Forward advancement of a push pier shall be considered halted when the movement rate is less than 1/16 inch per hour. The Push Pier Foundation Contractor shall install push piers and demonstrate that movement is halted at a load equal to or greater than the required ultimate capacity at each pier location as predetermined by the engineer and as shown on the Plans. The Push Pier Foundation Contractor shall annually calibrate each hydraulic ram used to determine design capacity of push piers. Current ram calibration information shall be supplied to the Foundation Inspector upon request. 9. MODIFICATIONS Field welding, if required, shall be in accordance with the “Code for Welding in Building Construction” of the American Welding Society. Welding of galvanized steel can produce toxic gases and should be done in adequate ventilation and with adequate gas detection, breathing gear, and other safety equipment. Modification of manufactured push pier pipe, brackets, and connectors is prohibited and shall not be performed without first consulting Magnum Piering, other manufacturer, or the Structural Engineer. 10. INSPECTION Installation of steel push piers shall be observed by a representative Inspector of a professional Soils or Structural Engineering firm to verify final depth and installation loads. The Push Pier Foundation Contractor shall notify Inspector at least 24 hours prior to installation work. The Inspector shall observe the installations and document the Push Pier Foundation Contractor’s method and materials used. The Inspector shall maintain a record of depth and ram pressure readings. The Push Pier Foundation Contractor shall provide the Inspector with recent calibration information for the rams used to measure capacity. 11. DRAINAGE The General Contractor shall provide proper site drainage in the area of all installed steel push piers at all times during and after construction. Proper site drainage shall conduct surface water runoff away from the structure and steel push piers. If expansive soils are a concern, irrigation systems shall not discharge within five (5) feet of an installed steel push pier. © Copyright 2002 Magnum Piering, Inc. All Rights Reserved (may be copied for use in construction specifications) 12. CLEANLINESS Immediately upon completion of the work, the Push Pier Foundation Contractor shall remove any and all equipment, tools, building materials, rubbish, unused materials, concrete forms, and other like materials belonging to him or used under his direction. Also during the work, the site occupied by the Push Pier Foundation Contractor and his material stockpiles shall be kept in a reasonable state of order and cleanliness. © Copyright 2002 Magnum Piering, Inc. All Rights Reserved (may be copied for use in construction specifications) STATE DEPARTMENT OF TRANSPORTATION EXAMPLE SPECIFICATIONS SECTION 551 STEEL PUSH PIERS DESCRIPTION 551.01 This work pertains to furnishing and installing steel push piers (a.k.a. hydraulically driven pipe micro-piles or resistance pier foundations) shown in the Contract in accordance with the Drawings and these specifications. Each steel push pier shall be installed and load tested at the location and to the elevation, minimum length, and design allowable load shown on the Plans or as established. These specifications are to be used in conjunction with State Department of Transportation Standard Specifications for Road and Bridge Construction. MATERIALS 551.02 Guarantees and Insurance Steel push pier and bracket manufacturer shall furnish a guarantee for a period of ten (10) years from date of delivery against defects due to manufacturing of steel push pier and bracket. Steel push pier and bracket manufacturer must carry product liability insurance. Refer to General Conditions for additional insurance requirements. 551.03 Prequalification Requirements Due to the special requirements for design and manufacture of steel push piers, and the requirements for proper performance of the structural system, as a whole, steel push piers and brackets shall be obtained from an organization specializing in the design and manufacture of steel push piers. The following manufacturers’ products are prequalified for use on this project: Magnum Piering, Inc. A request for using any other manufactured steel push pier products desired for use on this project must be submitted to the Project Manager and Foundation Engineer for review not less that seven (7) calendar days prior to the bid date. The request must include: 1. 2. 3. 4. A catalog or recent brochure describing the manufacturer. Evidence showing manufacturer has at least five (5) years experience in this area of work. Detailed descriptions, schematic details, and material properties for all products to be used on this project. Current ICCES/BOCA/ICBO product acceptance report or complete description of product testing and manufacturing quality assurance programs used to assess and maintain product quality. Prior to bidding by any installer using a manufactured steel push pier system that is not prequalified, written approval to bid must be received from the Project Manager upon consultation with the Foundation Engineer. Project Manager shall grant approval based on compliance with specific criteria herein. The Project Manager’s decision is final. 551.04 Minimum Material Requirements Steel push piers shall have a minimum 3" O.D. round shaft and shall have the required shaft wall thickness so as to prevent buckling during installation. The potential for buckling is often evidenced by spring-back of the pier shaft after removing the applied installation load. Steel push piers shall have sufficient diameter and thickness to minimize observable spring-back. Steel push piers and brackets shall be protected from corrosion by hot-dip galvanizing per ASTM A123. Steel push pier connections shall consist of in-line, straight and rigid inner sleeves. The steel push pier bracket shall have a maximum eccentricity (distance between the face of the bracket and the center of the steel push pier) of 2” or that acceptable to the Foundation Engineer. The connection between the steel push pier shaft and the bracket and between the bracket and the structure shall have sufficient strength to support design allowable loads shown on the Plans times a minimum factor of safety of 1.5. 551-1 MATERIAL SELECTION 552.05 Design and Application A list of all steel push pier and bracket materials to be used on this project shall be submitted with the bid package. The list shall clearly state the allowable mechanical capacity of all materials. The list shall be certified by the manufacturer’s engineer. It is the steel push pier installation contractor’s responsibility to select the appropriate size and type of steel push pier and bracket and design the connection of the bracket to the structure. These specifications and the Plans provide minimum requirements to aid the contractor in making appropriate materials selections. The size and type of steel push pier must be such that the steel push piers achieve the appropriate capacity in the soils at this site within the minimum and maximum length requirements. Failure to achieve proper capacity shall result in contractor replacing steel push piers as appropriate to support the required loads. All installation procedures, materials, and replacements shall be acceptable to Foundation Engineer. CONSTRUCTION REQUIREMENTS 551.06 Warranty and Insurance Steel push pier installation contractor shall furnish a warranty for a period of ten (10) years from date of installation against defects due to workmanship on installation of steel push pier and bracket. Steel push pier installer must carry general liability insurance. Refer to General Conditions for additional insurance requirements. 551.07 Prequalification Requirements Due to the special requirements for installation of steel push piers, and the requirements for proper performance of the structural system, as a whole, steel push piers and brackets shall be installed by an organization specializing in the installation of steel push piers. The following installation contractors are prequalified for work on this project: Dwyer Concrete Lifting, Inc. - Cincinnati, OH Earth Tech, Inc. - Land O' Lakes, FL Extreme Technology's, Inc. - Atlanta, GA Camden Construction Co. - Pierceton, IN Concrete Slabjacking - Jessup, MD Lipe Brothers Construction - Duluth, MN Pelton Concrete Services - Lake Oswego, OR Terratec, Inc. - West Columbia, SC Agate Foundations - Knoxville, TN Advanced Builders, Inc. - Chesapeake, VA Marco Concrete Lifting - St. Albans, WV Pier Tech, Inc. - Maspeth, NY VSI Geotec, LLC - Lancaster, NY Any other contractor desiring to bid as the steel push pier installer for this project shall submit a request to the Project Manager and Foundation Engineer for review not less than seven (7) calendar days prior to the bid date. The request must include: 1. 2. 3. A recent company brochure indicating experience in this type of work. Evidence of having installed steel push piers on at least ten (10) projects, including project name, location, and client contact information. Proposed method of installation/ load testing pier and bracket. Prior to bidding by any installer that is not prequalified, written approval to bid must be received from the Project Manager upon consultation with the Foundation Engineer. Project Manager shall grant approval based on compliance with specific criteria herein. The Project Manager’s decision is final. 551.08 Installation Equipment Each steel steel push pier shall be advanced into the ground by application of axial force using a hydraulic ram(s) pressing directly against the pier. Installation equipment shall include a direct means of determining the installation load being applied to the steel push pier and a means for testing both the capacity of the bracket and connection of 551-2 the bracket to the structure. Acceptable methods of load measurement include calibration of hydraulic ram pressure with axial force, a calibrated mechanical or electronic load cell, or other means acceptable to the Foundation Engineer. Current evidence of load calibration for Contractor’s equipment shall be provided upon request of Engineer. If installation equipment does not include a direct means of testing the capacity of the bracket and connection of the bracket to the structure, then Contractor shall submit to Foundation Engineer for acceptance detailed drawings of the proposed bracket and connection of bracket to structurestamped by a professional engineer registered in the State where the project is located. Drawings shall clearly indicate allowable load capacity. 551.09 Equipment and Material Acceptance All steel push pier installation equipment and materials shall be acceptable to the Foundation Engineer prior to delivery to the site. Acceptance will be based upon submission of records and data requested by the Foundation Engineer, as discussed in Sections 551.02 through 551.08. Once accepted, changes in installation equipment and materials will not be permitted without additional acceptance, and will be considered only after Contractor has submitted any and all information requested by Foundation Engineer. 551.10 Installing Steel push Piers Loads shown on the Plans are design allowable loads. A minimum factor of safety of 1.5 shall be used to determine the required minimum final installation force for the steel push piers. Contractor shall install and test all piers to the required final installation force at each pier location. Steel push piers shall be installed vertically. Steel push piers may be out-of-plumb a maximum of 5% of the final installation length as measured by observation of the inside of the steel push pier upon completion. Steel push pier brackets shall be installed at the locations shown on the Plans. Tolerances for bracket placement shall be 2” in both directions parallel with the face of the bracket and ½” in a direction perpendicular with the face of the bracket unless otherwise specified. Steel push piers shall be installed to a final length appropriate to achieve the required final installation force. The minimum length of the steel push piers shall be such that the pier tip is at approximately the same or lower elevation as the surface of bedrock shown on the graphic logs of exploratory borings contained in the soil report. Installation of steel push piers and brackets used to underpin an existing structure is typically performed utilizing the dead weight of the existing structure as the reaction force necessary to insert the piers into the ground. As such, steel push pier installation relies upon the strength of the concrete and reinforcing steel in the existing structure. Application of axial load, lateral load, and overturning moment to an existing structure through the process of underpinning is an unavoidable consequence of any underpinning system. The Contractor must evaluate the condition of an existing structure in the field and estimate the maximum installation load that can be applied safely to an existing structure without causing additional distress. The maximum installation load shall also not exceed that acceptable by the Foundation Engineer. 551.11 Axial Load Capacity Testing An axial load capacity test shall be performed at each pier location. The load capacity test shall consist of application of an axial force to each pier equal to or exceeding the required final installation force and monitoring pier advancement rate for a minimum of 30 minutes. The test shall be deemed successful provided steel push pier advancement under the applied load is less than 1/16 inch per hour. Forward advancement of steel push piers shall be continued until a successful load capacity test has been completed at each steel push pier location. In addition to the axial capacity of each steel push pier, each bracket and the connection of each bracket to the existing structure shall be tested during or after steel push pier installation. These capacity tests shall consist of applying an upward force equal to or exceeding the required final installation force on the steel push pier to the pier bracket in its final configuration and connection with the existing structure. If the Contractor’s installation equipment is incapable of performing these capacity tests, then Contractor shall submit a detailed drawing of the 551-3 pier bracket and connection of the bracket to the existing structure that clearly indicates the allowable capacity of the system in accordance with 551.08. 551.12 Field Modifications Field welding, if required, shall be in accordance with the “Code for Welding in Building Construction” of the American Welding Society. Welding of galvanized steel can produce toxic gases and should be done in adequate ventilation and with appropriate gas detection, breathing gear, and other safety equipment per OSHA regulations. Modification of manufactured steel push pier shaft, brackets, and connectors is prohibited and shall not be performed without approval of product manufacturing company and acceptance of Foundation Engineer. 551.13 Quality Assurance Observation Installation of steel push piers shall be observed by Foundation Engineer or Foundation Engineer’s representative/agent to verify the length and required final installation loads. Contractor shall notify Foundation Engineer or Foundation Engineer’s representative/agent at least 24 hours prior to installation work. METHOD OF MEASUREMENT 551.14 Steel push piers will be measured on a per unit basis with one unit equal to the equipment, materials, including bracket and pier shaft, and labor required for proper installation and testing of one single steel push pier at the required final installation capacity, location, elevation, and minimum length specified. BASIS OF PAYMENT 551.15 The accepted quantities will be paid for at the unit price per unit of measurement for each of the pay items listed below that appear in the bid schedule. Payment will be made under: Pay Item Pay Unit Steel push Pier & Bracket, Installed Each Compensation will not be made for any additional length required to achieve the final installation force that is beyond the specified minimum length. It is the Contractor’s responsibility to anticipate the required length of the steel push piers and include these costs in the bid price per unit. 551-4 EXAMPLE GEOTECHNICAL ENGINEERING REPORT PREPARED FOR: British Cablevision Subsurface Investigation 1414 Ash Drive Columbus, Ohio ABC Project 51-5121 ABC ENGINEERING, INC CONSULTING ENGINEERS Thomas K. Showblock 612 Cherokee Road Chillicothe, Ohio 45601 ATTENTION: Mr. Thomas K. Showblock, P.E. REFERENCE: Subsurface Investigation British Cablevision 1414 Ash Drive Columbus, Ohio August 20, 1991 ABC Project 51-5121 Dear Mr. Showblock: Pursuant to your request, ABC Engineering, Inc. has performed a subsurface investigation at the above referenced project. Two (2) engineering test borings, designated as B-1 and B-2, were drilled at the locations shown on the enclosed plan sheet. The test borings were drilled to a depth of 29.5 feet in B-1 and 30.0 feet in B-2. Drilling, sampling, field and laboratory testing have been performed in accordance with standard geotechnical engineering practices and current ASTM D-1452 and D-1586 procedures. Results from all field and laboratory tests are shown on the enclosed boring logs. Surface elevations of the test borings were obtained and referenced to elevation 762.50 feet, being finish floor elevation of existing building. A. PROJECT DESCRIPTION The site is located to the east of Frebis Avenue and Ash Drive intersection, in the City of Columbus, Ohio. This investigation is meant for evaluating the subsurface condition beneath the existing office and studio building. British Cablevision Subsurface Investigation 1414 Ash Drive Columbus, Ohio August 20, 1991 ABC Project 51-5121 Page 2 B. FINDINGS Visual inspection revealed that the site is relatively flat with grass ground cover. The existing building walls, paved areas and sidewalks exhibit some cracking and construction joints separation. The test borings exhibited 1.0 to 2.0 inches of topsoil over approximately 23 feet of random fill. The fill contains slag, wood, plastic glass, metal and brick fragments in clayey silt or sandy silt matrices. Boring B-1 encountered large wood blocks between 8.0 and 23.5 feet. Strong organic odor was noted in both borings. Loss on Ignition testing indicated that the fill contains high organic matters. The native soil was encountered at an average depth of 23.3 feet below ground surface elevation. The native soil is described as dark gray changing to brown clayey silt to sandy silt containing varying amounts of roots and organic matter. A layer of cohesionless soil consisting of sand and gravel was encountered at an average depth of 27.5 feet in both borings. Standard penetration blowcounts varied widely throughout the test borings. Blowcounts were generally affected by stiffness and type of the encountered materials (metal, rotten wood, soil, etc). Blowcounts, however, ranged from 9 to 96 blows per foot (bpf). Blowcounts in excess of 50 bpf are due to striking on brick fragments, stiff wood or coarse gravel. Groundwater was encountered at a depth of 22.5 feet in both borings. At completion of drilling program, test boring B-1 was caved-in at 19.0 feet, and B-2 was caved-in at 27.4 feet with water level reading at 20.4 feet. C. CONCLUSION Based upon fill/soil data obtained from the drilling and testing program, the following conclusions have been made: 1. The existing structure is built over random fill (landfill). British Cablevision Subsurface Investigation 1414 Ash Drive Columbus, Ohio August 20, 1991 ABC Project 51-5121 Page 3 D. 2. The cracks and separation showing over the existing structure are due to progressive settlement of existing fill. 3. Total and differential settlements cannot be estimated due to the variability of fill composition. 4. Settlements of subsoil/fill may be due to or a combination of organic matter decaying, building loading, and/or re-orientation of fill/soil particles with passage of time. RECOMMENDATIONS Due to the considerable depth of the landfill material encountered by the borings and the high probability of continued movement, we recommend complete underpinning of the existing structure with a deep foundation system. Based on our experience in the central and southern Ohio areas, hydraulically jacked steel pipe micropiles (a.k.a. steel push piers) are typically the most economical deep underpinning method. Listed below are our standard recommendations for these systems: Push Piering Systems 1. Push piers should extend through the existing fill and, hence, must have a minimum depth of at least 30 feet. Push piers shall have a center-to-center spacing of not less than 2 feet. 2. The required design load capacity for the existing perimeter spread footing should be determined by a licensed professional engineer. He/she should work with the piering contractor to determine required pier spacing and design loads. 3. The hydraulic ram used to load the pier shall be fitted with a pressure gauge, shall be capable of delivering the prescribed loads with a sensitivity of at least 2% of the required ultimate capacity of the pier, and shall be calibrated at least annually. The bracket and ram assembly shall be such that loads are applied vertically and directly to the central longitudinal axis of the push pier with a minimum of eccentric loading. British Cablevision Subsurface Investigation 1414 Ash Drive Columbus, Ohio August 20, 1991 ABC Project 51-5121 Page 4 4. After each pier is installed, a proof load shall be applied to the pier using the calibrated hydraulic ram and pressure gauge. The proof load shall be at least 150% of the required design load and shall be maintained for a minimum of 1 hr and until the rate of pier advancement in the soil is not greater than 1/16 in/h. 5. Push pier advancement relative to a fixed frame of reference shall be measured optically or through the use of a dial gage. 6. Push piers shall be supplied by Magnum Piering, Inc. or equivalent. Push pier installation should be observed by a representative of ABC Engineering to verify proof loading procedures. Field records shall be prepared that at least contain pier location, applied loads, load duration, and final pier depth. 7. After all piers have been installed and proof loaded, the structure shall be lifted and restored to its original grade or to the extent possible without compromising the structural integrity of the building. ABC Engineering’s assignment does not include, nor does this geotechnical report address the environmental aspects of this particular site. We appreciate the opportunity to be of service to you on this project. If you require any additional information, please do not hesitate to contact our office. Respectfully submitted, ABC ENGINEERING, INC. Tom Jones, P.E. Project Engineer J. S. Edwards, M. S., P. E Project Engineer TJ/JSE/bab Enclosures APPENDIX A BORING LOGS BORING LOG # B-1 CLIENT: Thomas Showblock PROJECT: British Cablevision ABC Project No.: 51-5121 Page 1 of 2 Date: 7-20-91 STATION: Type of Boring: SFA OFFSET: Elevation: 762.3' Drilled By: IC & BC GROUND WATER: Encountered at 22.5' at Completion Caved in @ 19.0' VOLUME: Heavy U.C. - Unconfined Compression, psf * Hand Penetrometer E le v . Ft SAM PLE No T o p s o il x B lo w C o u n ts S o il D e s c rip tio n D e p th 1 6 in M .C . % D e n s ity PCF U .C @ % s tra in s in - in . 2" B ro w n , D ry, H a rd , S a n d y S ilt x a n d F in e to C o a rs e G ra v e l, x N 2 2 1 -2 1 - S o m e B ric k F ra g m e n ts , S o m e 7 5 9 .8 25 46 4 5 -7 -7 14 11 1 1 2 .2 16 31 13 1 1 8 .7 8 ,5 0 0 * 4 -6 -3 9 27 4 -4 -7 11 34 R o o ts (F IL L ) 3 x B ro w n , D a m p , S tiff, C L A Y E Y 2 x 4 S A N D Y S IL T , w ith F in e to x C o a rs e G ra ve l (F IL L ) 7 5 6 .9 5 .4 ' 5 x 6 1 4 -1 5 - 3 x B ro w n to D a rk B ro w n , D a m p , x 7 C o m p a c t, S IL T Y S A N D Y w ith M e ta l F ra g m e n ts , S la g (F IL L ) 7 5 4 .3 8 .0 ' 8 x 9 4 x x 10 11 1 2 D a rk G ra y , D a m p , W o o d w ith P la s tic B ric k , w ith T ra c e s 1 3 o f C L A Y E Y S IL T (F IL L ) x 14 5 x x 15 16 17 18 x 19 6 x 4 -5 0 /1 " x 20 C o n tin u e d o n n e xt p a g e 19 BORING LOG #B-1 CLIENT: Thomas Showblock PROJECT: British Cablevision ABC Project No.: 51-5121 Continue Page 2 of 2 U.C - Unconfined Compression * Hand Penetrometer Elev. Ft SAMPLE No Blow Counts Soil Description Depth 6 in N M.C. % Density U.C @ % PCF strains in - in. 21 Same as above ------------(FILL) 22 23 738.8 23.5' 8,650 @ x 24 7 x Dark Gray, Damp, Stiff x 25 4-4-8 CLAYEY SILT with Some 26 27 27.0' 28 Gray, Wet, Very Compact, SILTY SANDY and Fine to x 29 732.8 8 x Coarse Gravel with Some Organics 29.5' BOTTOM OF BORING 73 11.50% 91.7 9,150 @ 6% Organics 735.3 12 93.7 32-50/ 5" BORING LOG # B-2 CLIENT: Thomas Showblock PROJECT: British Cablevision ABC Project No.: 51-5121 Page 1 of 2 Date: 7-20-91 STATION: Type of Boring: HSA OFFSET: Elevation: 762.5' Drilled By: IC & BC GROUND WATER: Encountered at 22.5' at Completion Caved in @ 27.4' VOLUME: Heavy U.C. - Unconfined Compression, psf * Hand Penetrometer E lev. Ft SAMPLE No B low C ounts S oil D escriptio n D e pth 6 in T opsoil x 1 M .C . % D e nsity PCF 1" B rown, D ry to D am p, V e ry H a rd x S A N D Y S ILT, with S om e F in e x N 2 16-32- C o arse G ravel, S and stone 760 F ragm ents (F ILL) 34 66 8 122 .3 9-14-16 30 16 109 .6 9-18-11 29 16 124 .1 2-3-6 9 22 122 .3 5-5-5 10 46 5-6-1 3 19 28 2.5' 3 x B rown, D am p, V ery S tiff, C LA Y E Y 2 x 4 S A N D Y S ILT w ith Little F ine x to C oarse G ravel (F ILL) 5 756 .3 x 6 6.2' 3 x B rown G ray, D a m p, V ery S tiff, x 7 C L A Y E Y S A N D Y S ILT with Little F ine to C oarse G ra vel 8.4' 8 with R oot Fiber (F ill) 754 .1 x 9 4 x x 10 11 12 13 D a rk G ra y, D am p M ed iu m x 14 D e nse to D ense, C LA Y E Y 5 x x S A N D Y S ILT w ith B rick, W ood 15 F ragm ents (F ILL) 16 O dor from A u ger C utting s 17 18 x 19 6 x x 20 C o ntinued on next p age U .C @ % stra in s in - in. BORING LOG #B-2 CLIENT: Thomas Showblock PROJECT: British Cablevision ABC Project No.: 51-5121 Continue Page 2 of 2 U.C - Unconfined Compression * Hand Penetrometer Elev. Ft SAMPLE No Blow Counts Soil Description Depth 6 in N M.C. % Density PCF U.C @ % strains in - in. 21 Same as above ------------22 (FILL) 739.5 23 23.0' Dark Gray, Moist, Stiff x 24 738 SILTY CLAY with Roots 7 x 24.5' 5-6-9 15 36 25 13 x 25 Brown, CLAYEY SANDY SILT 26 27 734.5 28 28.0' Gray, Wet, Dense, SILTY SAND x 29 8 x and Fine to Coarse Gravel with Wood x 30 8-12-13 30.0' BOTTOM OF BORING 115.6 3,000* APPENDIX B TEST RESULTS ABC ENGINEERING, INC. SOILS DIVISION LOSS ON IGNITION TEST DATA PROJECT NO. : 51-5121 DATE: LAB CODE: British Cablevision TECHNICIAN: T.B # SAMPLE 08-15-91 ME PERCENT LOSS BY IGNITION B-1 1 2 4 5 6 7 8 11 14 17 15 17 18 14 B-2 1 2 16 9 Unconfined Compression Test #1 10 9 8 Load (Thousands) 7 6 5 4 3 2 1 0 0 2 4 6 8 Strain 10 12 14 Stress-Strain Curve Boring No.1 Sample No.7 Depth 23.5'-25' Unit Weight - 93.7 pcf 16 Unconfined Compression Test #2 10 9 8 Load (Thousands) 7 6 5 4 3 2 1 0 0 1 2 3 4 5 Strain 6 7 8 9 Stress-Strain Curve Boring No.1 Sample No.7 Depth 23.5'-25' Unit Weight - 93.7 pcf 10 APPENDIX C SITE PLAN GENERAL PROCEDURES FOR OBSERVATION OF STEEL PUSH PIER INSTALLATION As a general rule, all Magnum Piering installation contractors keep a log of installation pressures as a function of steel push pier depths. In addition, Magnum Piering encourages the observation of steel push pier installation by the engineer of record or engineer’s representative for additional quality assurance. This document contains general guidelines for use by the engineering inspector during steel push pier installation observation. Capacity Determination Each Magnum steel push pier is advanced into the ground by application of axial force using a single Magnum installation ram pressing directly against the top of the pier. When forward advancement of a steel push pier is halted by soil resistance, the force exerted by the ram indicates the ultimate capacity of the steel push pier. It is the policy of Magnum Piering that forward advancement of a steel push pier shall be considered halted when the movement rate is less than 1/16th inch per hour. Allowable or design capacity of a Magnum steel push pier shall be determined by application of a factor of safety. A factor of safety of 3.0 is commonly used in bearing capacity calculations for footing and drilled caisson foundations. However, when the foundation installation process includes a direct or indirect measurement of soil strength at the foundation depth, lower factors of safety are permissible. A traditional example of this is pile driving. The American Society of Civil Engineers Publication 20_96, “Standard Guidelines for Design and Installation of Pile Foundations”, explains that a factor of safety of 1.5 is acceptable for pile foundations. Since the force of a ram on a steel push pier provides a direct test of the capacity of the steel push pier, a lower factor of safety is permissible for determining design capacity. Magnum Piering recommends determination of steel push pier design capacity by dividing the ultimate capacity by a factor of safety of 1.5. Input Hydraulic Pressure The hydraulic pressure measured at the input to Magnum installation rams is an indication of the force exerted on steel push piers and consequently their design capacity. This force can be approximated by multiplying the hydraulic pressure by the surface area of the ram piston. Since this calculation does not account for friction of the piston within the ram housing, wear on the ram surface, and pressure losses through hoses and fittings, a better indication of applied force may be obtained by physically calibrating each hydraulic ram. It shall be the policy of Magnum dealer/installers to annually calibrate each hydraulic ram used to determine design capacity of -1- steel push piers. In this manner, Magnum dealer/installers will be able to provide clients with current calibration information regarding their equipment. This information will enable accurate determination of steel push pier ultimate and design capacity. Magnum steel push pier installation rams are calibrated by quality assurance technicians at Magnum headquarters in West Chester, OH. A tag containing an identification number, date of calibration, calibration constant, and technician initials is typically affixed to each ram. Connection to Structures The capacity of a steel push pier and bracket used to underpin an existing structure is as much a function of the strength of the concrete in the existing structure as it is a function of the pier and bracket capacity. Application of lateral load and overturning moment to an existing structure through the process of underpinning is an unavoidable consequence of any underpinning system. Magnum dealer/installers evaluate the condition of an existing structure in the field to estimate the load that can be applied safely to an existing structure without causing distress. Installation of Magnum steel push piers by directly pushing against a structure provides a field verification that the bracket and connection to the structure can resist the ultimate load applied to the pier. Application of a factor of safety of 1.5, as described previously, also safeguards against failure of the bracket and connection to the structure. The engineering representative or inspector should be aware that other steel push pier systems do not necessarily test the connection of the pier to the structure during installation because the rams used by others often incorporate additional fasteners to the structure that are removed with the ram. Pier Spacing It is recommended by Magnum Piering that the dead loads and live loads of an existing structure be determined by a licensed professional engineer whenever possible. Live loads shall include snow, wind, and earthquake forces as well as other applicable forces. Push pier spacing shall be such that the design capacity of the steel push piers are capable of supporting the total load of the structure. In areas of soft soils or fill, down-drag of soils against steel push piers should be added to the total load on the piers. Plumbness Magnum Piering advocates that the orientation of each steel push pier be checked for plumb by the engineering inspector. This can generally be accomplished visually by the use of re-directed sunlight from a mirror, an artificial light source, or a laser pointer. The final depth should also be checked using a plumb bob or steel tape extended down the center of the pier pipe to ensure that the it was not damaged and that the length was not altered during installation. -2- Safety As with all other hydraulic systems, there exists the constant danger of failure of hydraulic hoses and fittings. The engineering inspector shall wear safety glasses and other appropriate safety equipment when observing steel push pier installation. He/she should keep clear of hydraulic equipment during the inspection to the extent possible. Record Keeping For each job, the engineering inspector shall record steel push pier locations and center-to-center spacing clearly on a plan view of the structure. The date of each installation, weather conditions, contractor’s representative, steel push pier manufacturing company, steel push pier section dimensions and other pertinent information shall be recorded at the start of each project. Installation time, hydraulic pressure, and the corresponding load on the pier should be recorded at a minimum of 3-foot depth intervals. The final depth of each pier, final installation pressure and load, total installation time, and rate of pier advancement shall be recorded at the end of each pier installation. An example steel push pier installation log is attached and may be copied for use by the steel push pier engineering inspector on Magnum Piering projects. -3- STEEL PUSH PIER INSTALLATION OBSERVATION RECORD Inspector: ____________________________ Date: ______________________________ Project: ______________________________ Location: ___________________________ Contractor: ___________________________ Manufacturer: _______________________ Weather Conditions: ____________________________________________________________ Pier O.D.: ________ Pier Wall Thickness: ____________ Steel Type: ___________________ Bracket Dimensions: ________________ No. & Type of Anchors: _______________________ Plan View of the Structure & Pier Locations N Comments: ___________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ STEEL PUSH PIER INSTALLATION OBSERVATION RECORD Page _____ of _____ Installation Logs: Pier No. Depth Pier No. Load Time Depth Pier No. Load Time Depth Pier No. Load Time Depth Load Final Installation Values: Depth Depth Depth Depth Applied Load Applied Load Applied Load Applied Load Design Load Design Load Design Load Design Load Install Rate Install Rate Install Rate Install Rate Time Shopping Mall Store Construction Project: A Steel Push Pier Underpinning Case Study by Howard Perko, Bill Bonekemper, Dave Jacob and Brian Dwyer Magnum Piering, Inc., West Chester, Ohio March 18, 2003 Abstract Hydraulically driven steel push piers were used for the lifting and stabilization of two walls of a partially constructed department store located in a shopping mall in West Chester, OH. Both the north and south walls experienced similar settlement and outward rotation problems, and significant failures occurred in the concrete floor slabs near the base of each wall. The soil conditions on the site predominantly consist of glacial till overlying shale with very shallow ground water. Due to limitations of lot lines, the original foundation design for the new structure consisted of eccentrically loaded spread footings. Hydraulically driven steel push piers were installed at the outside edge of the spread footings along the masonry walls. The piers were driven to refusal at an average depth of 13.5 feet. Once all piers were in place, the installation contractor systematically manipulated the hydraulic driving rams to achieve the necessary degree of lift at specific locations along each wall. As a result of vertical lifting, the tops of both walls were successfully rotated to near plumb while, at the same time, the vertical deflections were significantly reduced and brought to well within tolerances defined for the project. Contained herein is a chronology of events, push pier installation data, a detailed description of the repair, and information pertaining to building loads and soil conditions. Introduction the two men explained to Dave that there was a serious foundation failure on the north and south walls of this 120,000 sq. foot store. The problem was described to Dave as critical because all steel roofing and steel structural work had been shut down. After this brief introductory meeting, the three men went to view the problems with the walls. Photographs of the site before repair are shown in Figs. 1 and 2. As can be seen in the figures, the store was in the early stages of construction. Concrete masonry unit (CMU) block walls had been constructed and were temporarily braced for wind loads. The Dave Jacob, Dwyer Concrete Lifting’s Ohio Regional Manager, received a phone call from the GC’s Construction Project Manager on the afternoon of October 14th. The manager asked Dave if he would come to the construction site at the mall to look at settlement problems with two masonry block walls that were part of a new department store currently under construction. Dave met with both the GC and the construction manager for the department store’s regional construction manager for the mid-eastern district, and -1- line, the design was changed and instead the first approximately 250 feet of the wall’s footing was shifted inward and constructed flush with the exterior alignment of the CMU block wall. This change in the foundation design, in conjunction with heavy amounts of rain at the site for several days, were deemed, by GC’s structural engineers and the contracted geotechnical firm for the project, to be the sources of the failure. roof trusses were not completely in place at the time of the failure. The first wall that the owner, the construction manager, and Dwyer’s Dave Jacob visited was the north wall – the wall with the most severe problem. A considerable crack in the interior concrete slab was immediately apparent, and it measured approximately 1/2" to 5/8" wide at its worst point. The crack ran adjacent to the wall for approximately 200 feet and ranged in distance from 3 to 4 feet from the wall’s base. The two men quickly pointed to some hand written measurements marked at eye level on the wall about every 20 feet. As they explained to Dave, these markings represented the distance the north wall had rolled outward (to the north) at the top of its 27 foot height as measured by the steel contractor on October 10th. The measurements ranged from a minimum of 1/8", close to both the west and east corners of the wall, to a maximum of 23/4”, near the center of the wall’s 310foot total length. The extreme amount of lateral wall movement had created two serious situations for the contractor and owner. Fig. 1 North Wall of Store Under Construction 1. The roof truss supports could not be welded to the wall, and 2. The wall had actually “moved” across the property line into the adjacent tenant’s property Dave Jacob immediately queried both men about the foundation design that was selected to support the wall. The GC explained that there was intended to be an 18” to 36” wide spread footing under the entire wall. Due to the close proximity of the adjacent property Fig. 2 North Wall of Store Showing Lateral Bracing When the three men finished discussing the conditions at the north -2- wall, they quickly went to examine the similar conditions at the structure’s south wall. Although the settlement and subsequent outward roll of the south wall was not as severe as with the north wall, the top of the south wall had rolled outward (south) 1-7/8” inches near the center of the wall’s 260 foot total length, as recorded by the steel contractor. The concrete slab also had a crack similar to the crack at the base of the north wall. The slab crack is shown in Figs. 3 and 4. A similar foundation design change had been made on this side of the building due to the close proximity of the property boundary. The foundation failure of the south wall was again attributed to the eccentric loading on the spread footing for the first approximately 200 feet of the wall measuring west to east. A photograph of one of the cracks in the CMU block wall is shown in Fig. 5. Fig. 5 Example Vertical Crack in South Wall of Store Fig. 4 Close-up View of Example Floor Slab Crack Fig. 3 Example Floor Slab Crack Adjacent to South Wall -3- After making the decision to proceed, Dave Jacob called the GC and provided him with a verbal price estimate and a brief description of the proposed solution. He also informed the GC that Dwyer would commit to starting the project on the following Monday, October 21st. The proposed piering method, the price and the start date were all deemed to be tentatively acceptable, and Jacob formalized the quotation, terms and conditions in writing in preparation for a meeting the next morning - Wednesday. Dave Jacob presented the proposal as planned on Wednesday, and the project was formally approved to start on the following Monday. Once the south wall examination was complete, the three men returned to the construction office to discuss a potential remedy. The ensuing discussions focused on the amount each wall would have to be rotated inward in order to achieve a near plumb condition and satisfy both the roof construction requirements and the adjacent property line restrictions. Dave Jacob was informed that each wall could not be more than ¾ of an inch out of plumb in order to complete the welding of the steel roofing trusses, and this amount would more than satisfy the property line requirements. Additionally, Jacob was informed the remediation project had to be started immediately – preferably on Monday, October 21 at the latest (only 6 days after the initial telephone call). Dave was provided with a set of prints for the project as well as the geotechnical engineer’s soils report for the site. He informed the two men that he would be in touch later that day with a proposal to return both walls to within the required specifications. Upon reviewing the job with Dwyer engineers and piering specialists, it was determined that piers would need to be installed every five feet along the walls. This meant that a total of 50 piers would be required for the south wall and 60 piers for the north wall. It was also decided that all piers for each wall would have to have hydraulic rams mounted on them simultaneously for lifting, which would require Dwyer to mobilize 60 hydraulic rams to the site to complete the lift. It also necessitated careful review and some rescheduling of the piering projects already planned in Dwyer branch offices located in Cincinnati, Columbus, Lexington and Louisville. Building and Site Description The mall project site is located in West Chester, OH – a northern suburb of Cincinnati. The ground surface is comparatively flat across the site. Subsequently, minimal site grading was performed in preparation of store’s construction. A view of the store from a distance is shown in Fig. 6. A view of the inside of the store at the time of repair is shown in Fig. 7. This figure reveals that the store consists of a combination of masonry and steel construction. The rectangular store footprint encompassed approximately 120,000 sq. feet, and measured roughly 310 ft x 400 ft. Adjacent property lines to the south and north walls were extremely close. In fact, the store width was only 8 inches smaller than the lot width. This condition necessitated that the foundation had to be virtually flush with the block wall as shown in Fig. 8. -4- The north and south exterior walls were to consist of 8” CMU block with a brick veneer and foam insulation. Both walls were grouted on 32” spacing. The final height of the walls was 27 feet from interior slab finished floor to the top of the parapet. The foundation extended approximately 30 inches below the top of the slab. The original foundation design for these walls can be summarized as follows: Fig. 6 Distant View of Store Site North Wall The foundation for the north wall was designed as follows: 0 to 250 feet – 26” wide, 12” thick spread footing eccentrically offset and vertically flush with exterior wall 250 to 310 feet – 18” wide, 12” thick spread footing centrally located under exterior wall South Wall Fig. 7 View from Inside Store The foundation for the south wall was designed as follows: 0 to 200 feet – 26” wide, 12” thick spread footing eccentrically offset and vertically flush with exterior wall 200 to 260 feet – 18” wide, 12” thick spread footing centrally located under exterior wall Subsurface Conditions The soil conditions on the site predominantly consist of soft, wet silty clays to lean clays with sand partings, gravel, and rock fragments (glacial till) that gradually stiffened with depth Fig. 8 As-Built Spread Footing Shown Nearly Flush with Exterior Wall -5- unsupported distance of eight feet. Hence, the available load for pier installation without risk of damage is the weight of 16 feet of wall or about 40 kips. Pier installation to 35 kips could be accomplished by installing the piers individually thereby utilizing slightly less than the available weight of the wall at each pier location. Lifting and rotation of the wall is performed using all Magnum Piering hydraulic rams simultaneously. It follows that the dead load on each pier due to the partially constructed wall, which was 12.5 kips per pier, should correspond roughly to the lifting forces that would be necessary. The true force required for lifting may be higher than this due to soil mobilization along the interior of the foundation wall and cohesion under the footing. underlain by stiff layered shale and interbedded hard limestone at a depth of 7.5 to greater than 15.4 feet. Ground water was typically encountered at depths of 1 to 3 feet below the ground surface at the time of drilling. Foundation Loads The building was designed with an internal steel frame and external masonry walls. The structure’s roof system consisted of steel bar joists with corrugated metal deck and standard built-up roof materials. The masonry walls were load bearing and spaced approximately 22 feet from the closest set of interior steel columns. Thus, the walls supported approximately 11 ft of tributary roof loads and their own weight. The estimated dead load of the walls and foundation prior to attachment of the roof joists and installation of the brick veneer is 2.5 kips/lf. After construction is completed, the total live and dead load on the walls is on the order of 4.5 kips/lf. This assumes a 20 psf snow load for the Ohio area. The required total dead and live design load capacity of the piers spaced 5 feet on-center is 23 kips. Applying a factor of safety of 1.5, indicates that each pier must be installed and load tested to a minimum of 35 kips. Since the weight of the structure itself is used as resistance for the installation of this type of hydraulically driven steel push pier, pier spacing is typically governed by the weight of the structure that can be utilized safely without risk of overstressing and cracking the foundation and wall. It could be assumed that the store wall was, at a minimum, designed to span an Alternative Repair Solutions The store owner and the general contractor considered tearing down and replacing both walls and their respective foundations, but the added construction costs and lost time made this extremely expensive option a last resort. Using the Magnum Piering remedial steel push pier underpinning system was considered to be the most economical solution with the least amount of impact on the overall construction schedule. Other systems that may have been considered are helix remedial piers or concrete piers. Each of these systems has drawbacks. Helix piers generally introduce more disruptive loads to the structure due to the larger eccentricity of helix pier brackets. It is also more difficult to use helix piers to achieve the precise, uniform, and controlled lift that was required by project tolerances. -6- rotational eccentricities. This step could be skipped, since the footing was already flush with the wall above. Bracket installation is shown in Fig. 10. Next, the ram assembly is attached to the bracket and the installation of 30 inch sections of 3 inch O.D. high strength steel pier shaft is conducted, as shown in Fig. 11. Concrete underpinning piers are generally cost prohibitive and could not be installed within the property line restrictions. Concrete piers would require much more time to install, and they would not transfer loads below the soft soils with the building loads available due to increased installation pressures of the larger diameter concrete cylinders. Considering time, cost, practicality, and sound engineering, hydraulically driven steel push piers were found to be the best solution for this project. Dwyer Concrete Lifting has been using the Magnum Piering Steel Push Piering System for over 10 years, and the firm has successfully stabilized thousands of commercial and residential foundations in the region. Installation Data Fig. 9 Marking Bracket Positions Along Foundation Walls The process of pier installation began by excavating along the exterior of the foundation as shown in Fig. 8. A site safety meeting was held whereby crews were briefed on construction hazards, and a wall monitoring program was set in place. Next, bracket positions were marked along the wall, as shown in Fig. 9. Each Magnum Piering bracket was secured using ½ inch diameter by 5½ inch long, expansion bolts extending into the side of the footing. Normally, the footing is chipped flush with the foundation wall prior to bracket installation in order to minimize Fig. 10 Bracket Installation -7- At the store, the design ultimate capacity of each pier was 35 kips. In order to add to the factor of safety and ensure proper pier installation, Dwyer personnel installed each pier to the maximum load that could safely be applied to the structure (40 kips), which corresponds to a hydraulic ram pressure of approximately 5,000 psi. The final depth of the piers along the North and South walls of the building are shown in Figs. 14 and 15. As can be seen in the figures, the final depth of the piers along the North wall varied from 10 to 20 feet below the top of slab and along the South wall from 15 to 19 feet. In either case, a discernable profile is evident. The reason for larger variation in pier depth on the North side of the site is unknown. However, the depth of the piers was generally consistent with the depth and variability of bedrock described in the geotechnical engineer’s report for the project site. It was concluded that all piers are likely supported on or within the bedrock. Fig. 11 Pier Installation Hydraulic pressure during pier installation is recorded at various depths, as shown in Fig. 12. A log of these readings is prepared for each pier location. Pier installation is halted once the hydraulic pressure corresponding to the design ultimate capacity of the pier is reached. At that point, the load is maintained on the pier and movement is monitored over a period of time until the pier movement decreases to less than 1/16th inch per ½ hour. This process constitutes a full-scale load test at each pier location. Fig. 13 Monitoring Wall Movement During Lifting Phase Fig. 12 Logging Pier Depth and Hydraulic Pressure -8- Survey stations were established inside and outside the building in order to monitor movement, as shown in Fig. 13. After all piers were individually installed, it was time to lift and rotate the building walls back to within tolerances for plumbness. All rams were utilized simultaneously in the lifting process. Pier # - West to East Depth of Piers from Top of Floor Slab (Feet) 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 2 4 6 8 10 12 14 16 18 20 22 Fig. 14 Final Pier Depths Along North Wall Pier # - West to East 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 Depth of Piers from Top of Floor Slab (Feet) 0 2 4 6 8 10 12 14 16 18 20 Fig. 15 Final Pier Depths Along South Wall -9- 61 4 Deflection (Inches) 3 2 1 0 -1 Before Lift After Lift -2 -3 c1 b c d e f g h j.2 Deflection Benchmarks - 10 Points Fig. 16 Initial and Final North Wall Top Location 4 Deflection (Inches) 3 2 1 0 -1 Before Lift After Lift -2 -3 c1 b c d e f g h Deflection Benchmarks - 10 Points Fig. 17 Initial and Final South Wall Top Location -10- j.2 the inside of the wall and cohesion below the footing. After lifting, each bracket was rigidly fixed to the piers using two ¾ inch diameter grade 8 bolts. The hydraulic ram assemblies were removed, and the tops of the piers were cut flush with the tops of the brackets. Backfilling of the trench commenced and the piers were concealed. Both walls were successfully relocated. Initial and final top of wall locations with respect to plumb are shown in Figs. 16 and 17. The North and South walls were restored to within ½ inch of plumb, except for the Eastern portion of the South wall. The reason for this discrepancy is that the wall was not constructed perfectly straight. It was identified during this phase that the South wall had started to settle during masonry construction, and the block mason had to adjust the course of the wall. Afterward, the wall continued to move and eventually ended in the position where Dwyer was called to the site. The wall could not be improved beyond that shown unless it was reconstructed. It was deemed that the lift was acceptable and the underpinning project was completed. Lifting was achieved at ram pressures of approximately 2,000 psi, which corresponds to a load of 16 kips. As expected, lifting forces were slightly higher than the dead load of the wall, 12.5 kips, due to soil mobilization along Conclusions The store walls were successfully repaired using hydraulically driven steel push piers. The piers caused no discernable damage to the structure during installation. Each pier was installed and load tested to a factor of safety of 1.7 times the design total live and dead load of the completed structure. The entire 110 pier underpinning project was completed within 8 working days from the start date and at a cost significantly less than the cost to reconstruct both walls. -11- Axial Capacity of Hydraulically-Jacked, Steel-Pipe Micropiles Used for Underpinning by Howard A. Perko, Ph.D., P.E. Consulting Engineer for Magnum Piering, Inc. June 14, 2002 Abstract A review of the axial capacity of hydraulically-jacked, steel-pipe micropiles used for underpinning is presented. A procedure is suggested for field verification of underpinning pile capacity. Theoretical calculations of pile capacity are compared with measured values for a case study involving a foundation repair performed on a telecommunications building. Introduction Push pier, push pile, and resistance pier are some of the trade names often applied to hydraulically-jacked, steel-pipe micropiles used for underpinning. For convenience the term steel push pier will be used herein. There are several different manufacturers of steel push piers including Magnum Piering, RamJack, and Atlas Systems. Although steel push piers can be installed using heavy machinery for construction of new structures, this paper is focused on piers used exclusively for underpinning and repair of existing structures. Steel push piers essentially consist of short sections of pipe or structural steel tube that are often coupled together by an internal sleeve. Each section of a steel push pier is forced into the ground using a hydraulic ram fastened to the footing, stem wall, or grade beam of an existing structure. In this way, the weight of the structure provides the resistance necessary to force the pier into the ground. A factor of safety is obtained by installing the piers individually and by using more piers than the number required to carry the weight of the structure. An example steel push pier connected to a footing foundation is shown in Fig. 1. A photograph that depicts steel push pier installation is shown in Fig. 2. Fig. 1 Example Steel Push Pier -1- 1. 2. 3. 4. 5. Integrity of the structure at pier location Connection between bracket and structure Mechanical strength of the bracket Buckling strength of the pier Soil friction and bearing pressure Although each of these factors is equally important, the topic of this paper is the capacity provided by soil friction and bearing pressure. It is assumed for the remainder of this discussion that the first four factors are adequate to support the required load on the pier. Fig. 2 Example Push Pier Installation Capacity Requirements The required capacity of a steel push pier used for underpinning is computed by the same techniques as those used for other deep foundations with a few special precautions. As with other foundation types, a push pier must have sufficient capacity to support the dead and live loads of the structure. If a structure is to be lifted and re-leveled, it is essential to add the weight of the soil above the footing to the total dead loads computed by conventional means. The cohesion of the soil on the bottom of the footing and/or slab and the friction of the soil along the foundation wall or grade beam also need to be considered. Demonstrating the ability to lift and relevel the structure is an insufficient verification of push pier capacity. Foundation underpinning must also be capable of supporting live loads such as snow, wind, people, and furnishings that may be added to the structure at a later time. It is imperative that live loads are taken into account in the layout and spacing of push piers. Total dead and live loads represent the required design capacity of push pier underpinning. In general practice, an appropriate factor of safety must then be Steel push piers are used to underpin an existing spread footing or slab-on-grade foundation that has undergone excessive total or differential settlement. Once all of the piers are in place, the structure can be lifted to its original grade. This often results in crack closure and provides relief to over-stressed structural members. The rate of installation of a single steel push pier varies among installers and depends on the subsurface conditions. The typical time required to install a 20 ft long push pier is generally in the range of 4 to 8 hrs. A shear ring with a diameter slightly larger than the pier shaft is usually placed at the bottom of the pier. The purpose of this ring is to reduce friction along the shaft during installation, which permits greater depths to be achieved. Although some of the capacity of a push pier is due to friction of the soil along the sides of the pier, the use of a shear ring effectively produces an end bearing pile. Steel push piers are fastened to an existing structure by the application of a foundation bracket. The capacity of a steel push pier depends on five factors, given as follows: -2- applied to derive the required ultimate capacity. Factors of safety used in foundation engineering vary depending on the reliability of soil and subsurface information, the heritage of particular foundation capacity determination methods, and the sensitivity of the structure to movement. A factor of safety of 3 is generally used in conjunction with spread footing foundations. The American Society of Civil Engineers Publication 20 96, “Standard Guidelines for Design and Installation of Pile Foundations”, explains that a factor of safety of 1.5 is permissible for driven pile foundations since the method of installation provides a means of capacity determination in the field. Installation of a steel push pier provides an even more direct means of capacity determination as compared to pile driving. The engineer of record should select a factor of safety suitable for each project and site conditions. A factor of safety between 1.5 and 2.0 is often used in practice for steel push pier installation. 7. 8. 9. 10. 11. 12. location is measured and a building monitoring program is established Hydraulic rams are temporarily attached to the brackets on the existing structure Steel push piers are jacked into the ground individually until the load used for driving the pier equals or exceeds the required ultimate capacity Ram pressure is measured and recorded at 3 feet intervals of push pier depth Local building official or building owner’s representative observes pier loading and verifies required capacity has been achieved After all piers are installed and inspected, the building is lifted and releveled to the extent possible without compromising integrity of the structure The piers are permanently secured to the brackets and the hydraulic rams are removed Final building elevation is recorded Access holes are backfilled and landscaping materials are restored Field Verification of Capacity The installation of steel push piers generally involves the following procedures: 13. 14. 1. To date, no standard method exists for completion of installation steps 7 and 8 which involve field verification of push pier capacity. The American Society for Testing and Materials specification D1143 - 81, “Standard Test Method for Piles Under Static Axial Compressive Load” explains routine methods to determine if a pile has adequate bearing capacity. Based in large part on this standard, the following procedure for verifying the capacity of a steel push pier is suggested. 2. 3. 4. 5. 6. An engineer or contractor’s technical representative observes the condition of the structure, computes building loads, and plans push pier locations All underground structures and utilities in the vicinity of the piers are located and moved or avoided Foundation access holes are excavated at each pier location Existing foundation is modified to allow connection of brackets as close to foundation wall face as possible Piering brackets are mounted to the existing foundation Elevation of the structure at each pier 1. -3- The bracket and ram assembly shall be such that loads are applied vertically 2. 3. 4. 5. 6. 7. 8. 9. and directly to the central longitudinal axis of the push pier with a minimum of eccentric loading The structure to which the bracket and ram assembly is attached shall have sufficient integrity and weight to allow for application of loads to the push pier without excessive lifting and without causing damage to the structure If the structure is of insufficient weight to permit the required push pier loading, then an earth anchor, ballast weight, or battered pile must be used to provide the necessary reaction The hydraulic ram used to load the pier shall be fitted with a pressure gauge, shall be capable of delivering the prescribed loads with a sensitivity of at least 2% of the required ultimate capacity of the pier, and shall be calibrated at least annually Push piers shall have a minimum spacing of 2 feet or at least 10% of their average depth After the pier is installed and is ready to be proof loaded, the loading procedure shall consist of applying the design ultimate load to the pier, which shall be at least 150% of the design allowable load Push pier movement relative to a fixed frame of reference shall be measured optically or through the use of a dial gauge The proof load shall be maintained until the rate of settlement is not greater than 1/16 in/h but not less than 1h A field report shall be prepared that at least shall contain pier location, applied loads, load duration, and final pier depth Theoretical Capacity In practice, the theoretical capacity of a steel push pier is seldom computed due to the measurement and verification of capacity in the field. However, on certain occasions it may be desirable to determine theoretical capacity in order to evaluate the suitability of a particular bearing stratum or to approximate push pier depth. A case history is presented for a twostory, 12,000 sf, telecommunications office structure in Cincinnati, OH. The south sides of the building had experienced excessive settlement. A plan view of the structure is shown in Fig. 3. Exploratory borings were drilled at the three locations shown. Graphic logs of these borings are provided in Fig. 4. As can be seen from the boring logs, the subsurface conditions consisted of 0 to 3 feet of fill over sandy clays and highly weathered shale underlain by hard shale and limestone bedrock at depths between 14 and 19 feet. In most cases, underpinning the entire structure with steel push piers is the recommended course of action. In this particular case study, the north ends of the building were underlain directly by the hard shale and limestone bedrock. It was decided that the north sides of the building were adequately supported and did not require underpinning. A total of 24 steel push piers were located and installed along the south sides of the building, as shown in Fig. 3. The depth of pier installations varied from 3 to 21 feet. All of the piers were installed individually and proof loaded to at least 45 kips. Hydraulic ram pressure was measured and recorded at installation depth intervals of 3 ft. Ram pressure and corresponding load is shown in Table 1 for the three piers located closest to the exploratory soil borings. -4- Table 1. Records of Push Pier Installation Pier Location 3 14 20 Hydraulic Ram Pressure (psi) - Applied Load (lbs) Depth 3 500 4,125 200 1,650 100 6 500 4,125 500 4,125 100 825 9 1,000 8,250 1,500 12,375 1,000 8,250 12 5,500 45,375 5,500 45,375 3,000 24,750 15 5,500 45,375 18 Fig. 3 Case History Site Plan LOGS OF EXPLORATORY BORINGS B-1 B-2 B-3 0 0 32/12 38/12 11/12 31/12 15/12 5 13/12 23/12 26/12 31/12 13/12 30/12 19/12 17/12 80/3 59/12 72/12 139/12 100/5 Depth (ft) 60/6 77/6 Legend: Asphalt Concrete Weathered Shale Gravel Basecourse Shale and Limestone Fill, Clay, Sandy 25 15 67/12 Clay Glacial Till 80/3 Standard Penetration Resistance Test Blow Count (blows/inches) Fig. 4 Logs of Exploratory Borings -5- 20 25 Depth (ft) 10 15 20 5 11/12 10 97/12 825 Due to the use of a shear ring, a steel push pier should be treated essentially as an end bearing pile. According to Meyerhof (1956, 1976), ultimate static pile point capacity can be related directly to Standard Penetration Resistance test blow count by P p tu = 8 40 A N the penetration length, L, is not associated with friction along the pile shaft; rather, it is an indication of the effective vertical pressures that govern the Nq term in the traditional bearing capacity equation. As such, it is reasonable to use a fraction of the push pile depth. In applying Meyerhof’s equation to the data available for the case history, it was assumed that the penetration length, L, is equal to 25% of the depth of the pier minus 1.5 ft to account for disturbed soil at the ground surface. In terms of mathematical symbols, L is given by L D where A = pile tip area (ft2); N = SPT blow count (blows/ft); L = penetration length (ft), and D = pile diameter (ft). L = 2 5 % × ( L T − 1.5 ) Meyerhof also specified the criterion that where LT = total depth of the pier (ft). A comparison between theoretical and measured pier capacity for the three piers given in Table 1 is shown in Fig. 5. These data are for all depth intervals. As can be seen in the figure, Meyerhof’s equation and the definition of penetration length given above match the field measurements very well. L ≤ 10 D It has been shown (Miller and Lutenegger, 1997) that open-ended piles exhibiting a plugged condition develop end bearing similar to that of a closed-ended pile. It has also been calculated that plugged conditions are achieved at depths between 10 and 20 pile diameters (Paikowsky and Whitman, 1990). This is consistent with the authors observation that push piers typically develop a plugged condition within the completion of the first 3' section of pier pipe installed. Hence, in almost all practical cases, the pile tip area, A, should include the area of the plugged end. Pile tip area should also include the additional diameter provided by the shear ring (if used). The steel push pier diameter, D, used for the case history presented above was 3". The shear ring diameter was 4". The standard penetration resistance blow count used in the above equation should be taken as the average value from 3 D below the pile tip to about 8 D above the pile tip. Since Meyerhof’s equation is for tip capacity, it should be recognized that Discussion In saturated low permeable soils, the installation of steel push piers causes high pore water pressures. Subsequently, soil effective stress is reduced substantially. It is standard practice to proof load steel push piers immediately after installation. This procedure is conservative since the capacity of the pier should increase substantially after pore pressures dissipate and effective stresses return to steady state. It is common knowledge amongst installers that push piers must be completely installed in the same day. Even an overnight delay is sufficient to make the obtainment of additional installation depth difficult. In most cases, push pier capacity should increase with time. Groundwater fluctuations and corrosion are exceptions that may adversely affect capacity. -6- 60000 Theoretical Capacity (lbs) 50000 40000 30000 20000 10000 0 0 5000 10000 15000 20000 25000 30000 35000 40000 45000 50000 Push Pier Field Capacity (lbs) Fig. 5 Theoretical and Measure Push Pier Capacity References American Society for Testing and Materials (1994) “Standard Test Method for Piles Under Static Axial Compressive Load” Test Designation D1143 Meyerhof, G.G. (1956) “Penetration Tests and Bearing Capacity of Cohesionless Soils”, J. of Soil Mechanics and Foundation Design, ASCE, Vol. 82, SM 1, pp. 1-19 American Society of Civil Engineers (1996) “Standard Guidelines for Design and Installation of Pile Foundations” Publication 20-96 Miller, G.A. and Lutenegger, A.J. (1997) “Influence of Pile Plugging on Skin Friction in Overconsolidated Clay”, J. of Geotechnical and Geoenvironmental Eng., ASCE, Vol. 123, No. 6, p. 525 Meyerhof, G.G. (1976) “Bearing Capacity and Settlement of Pile Foundations”, J. of Geotechnical Eng., ASCE, Vol. 102, GT 3, pp. 195-228 Paikowsky, S.G. and Whitman, R.V. (1990) “The Effects of Plugging on Pile Performance and Design” Can. Geotech. J., Ottawa, Canada, No. 27, pp. 429-440 -7- Lateral Loads and Bending Moments Associated with Steel Pier Foundation Brackets Used for Underpinning Existing Structures by Howard A. Perko, Ph.D., P.E. Consulting Engineer for Magnum Piering, Inc. July 7, 2002 Abstract The fundamental mechanics of a bracket and foundation connection are demonstrated. A static analysis was performed on an example steel pier foundation bracket used for underpinning an existing foundation. Strain compatibility between the connection to the structure and the bending resistance of the pier was investigated using a computer program for the analysis of pile foundations under eccentric loads. The lateral load and overturning moment exerted on an existing foundation due to eccentricity of steel pier foundation brackets were quantified for various soil types. The results of these analyses were used to examine the viability of steel pier underpinning given the strength of an existing foundation. Introduction There exist a number of possible methods for repair of a footing or mat foundation that has undergone excessive total or differential movement. One common method of repair is the use of hydraulicallyjacked steel pipe micropiles (steel push piers) for underpinning. This method consists of installing a steel pier adjacent to an existing foundation and then attaching the pier to the foundation by application of a bracket. Steel pier foundation brackets must be placed as close to the center of the existing foundation as possible. Often, the process of attaching a bracket involves chipping away a section of the footing so the bracket can be aligned with the outside face of the foundation wall. A typical steel pier underpinning foundation bracket is shown in Fig. 1. Despite considerable care in placing the bracket, some eccentricity is inevitably introduced, since the pier cannot be placed directly under the centerline of the foundation wall for practical reasons. Fig. 1 Example Steel Pier Foundation Bracket One of the common concerns regarding the application of steel pier underpinning is the susceptibility of the existing foundation to damage caused by forces and moments in the connection between the bracket and existing concrete foundation elements. In order to evaluate the viability of using steel pier underpinning, it is necessary to compute the applied lateral loads and overturning moments resulting from -1- eccentricity of the bracket and pier assembly. With this information, it is possible to compute the factor of safety between applied loads and the available strength of the foundation. A static analysis was conducted to evaluate the stability of an example foundation bracket for steel pier underpinning. Strain compatibility between the connection to structure and the bending resistance of the pier were investigated using a computer program, LPILE Plus for Windows by Ensoft, Inc. The lateral load and overturning moment exerted on an existing foundation due to eccentricity of an example steel pier foundation bracket were quantified for various soil types. The results of these analyses were applied to examine the viability of steel pier underpinning. Static Analysis There are several manufacturers of steel pier underpinning foundation brackets. In general, foundation brackets can be categorized as either plate brackets or angle brackets. A cross-sectional view of an example plate bracket is shown in Fig. 2. This assembly is manufactured by Magnum Piering, Inc. of Cincinnati, OH and is protected under U.S. Patent No. 5,234,287 (Magnum Piering, Inc., 2002). Atlas Systems, Inc. also manufactures a plate bracket, however it differs from the Magnum bracket in the way that the pier is connected to the bracket (Atlas Systems, Inc. 2000). An example of an angle bracket is shown in Fig. 3. This example is not modeled after any particular manufacturer, however it is similar to several that are currently available. Two characteristics that are shared by all brackets are a face plate that mounts vertically on the existing foundation (A) and a sleeve or pair of clamps that prevent the pier Fig. 2 Plate Bracket Free Body Diagram Fig. 3 Angle Bracket Free Body Diagram -2- from moving laterally (B). Angle brackets also have an angle plate that extends below the foundation (C). Provided the sleeve or clamps (B) are sufficient to prevent rotation of the pier with respect to the bracket, the total vertical load supported by the pier can be represented as a single resultant force, P2, located at the central axis of the pier shaft. If the existing foundation upon which the bracket is mounted is sufficiently rigid, then the total force applied by the existing foundation can be represented as a single resultant force, P1, located close to the face plate (A). The exact location of the applied force, P1, on the bracket depends on the connection of the bracket to the structure. For plate brackets, such as the one shown in Fig. 2, the applied force, P1, is transferred by concrete anchors and acts immediately adjacent to the face plate (A). For most angle brackets, such as the one shown in Fig. 3, the majority of the applied force, P1, is transferred through the bottom of the foundation concrete to the angle plate (C). The distance from the face plate of an angle bracket to the resultant applied force, P1, depends on the roughness of the existing concrete, occurrence of exposed aggregate, and mechanical rigidity of the bracket itself. The total overturning moment, M0, resulting from eccentricity of steel piering brackets is given by M0= Resistance to overturning is provided by the moment resistance of the connection between the bracket and the structure, M1, and the moment resistance of the pier in the soil, M2. The magnitude of each of these moment reactions depends on the strain compatibility between them. If the connection to the structure is very rigid compared to the strain necessary to mobilize the moment resistance of the pier in the soil, then M1 will be much greater than M2. A strain compatibility analysis was performed and the results are given in the next section. The lateral force, L1, is the horizontal component of force exerted by the connection between the existing structure and the bracket. It is a combination of horizontal loads in the anchor bolts, compression behind the face plate (A), and friction along the angle plate (C). In order for the condition of static equilibrium in the x-direction, perpendicular to the face of the bracket (A), this force must be equal and opposite to the horizontal component of force at the top of the pier, L2. The horizontal component of force at the top of the pier may be due to a departure of the pier from plumbness. Lateral force in the connection between the existing structure and the bracket may be due to horizontal loads on the structure such as wind or active earth pressures. These causes of lateral force are ubiquitous to all foundations, can be addressed using conventional techniques, and will not be discussed further herein. Another cause of lateral loads is inherent to the application of eccentric loads and their resulting moments to the tops of steel piers. If a moment is applied to the free end of a steel pier embedded in the ground, the pier will move laterally as the soil becomes mobilizes to resist the applied moment. If the pier head is prevented from moving laterally, then a horizontal component ( P 1 + P 2) e 2 where e = total eccentricity. In order for static equilibrium in the z-direction, parallel with the face of the bracket (A), the total vertical load supported by the pier, P2, must be equal to the total force applied to the existing foundation, P1, and hence M 0 = P1 e -3- of force must be applied to maintain the position of the pier head. The magnitude of this reaction was determined for steel piers in different soils. A description of the analysis and the results are given in a later section. AC01-0402-R1), the allowable displacement of ½" diameter anchor bolts under design tensile loads is 0.0500 inches. If the anchor bolts are have a design tensile capacity of 3.5 kips, which is typical for anchors spaced 3" O.C. and embedded 4" in 4,000 psi concrete (Illinois Toolworks, Inc., 2001), then the moment generated in the connection is on the order of 150 kip-in and the rotation of the bracket, 1, is approximately 0.4 deg (arcsin 0.0500"/7"). Stain Compatibility It is well known in the field of mechanics of materials that stress and strain are intimately related. Loads and moments must be accompanied by displacements and rotations. In order to generate a resisting moment, M1, in the connection between the existing foundation and the bracket, a small amount of rotation must occur. Likewise, in order to generate a resisting moment in the pier, M2, some rotation of the pier in the soil must occur. The angles of rotation are shown in Fig. 4. Assuming that the connection between the bracket and pier is very rigid and the structure itself is very rigid, the rotation of the pier in the soil and the rotation of the bracket connection with respect to the structure must be equal. θ1 = θ 2 The first step in determining rotational compatibility is to establish the relationship between bracket rotation and applied moment. The amount of rotation in the connection between the existing structure and the bracket, 1, as a function of applied moment, M1, is different for the many types of foundation brackets available. An example calculation is provided here using a Magnum Piering bracket with 6 anchor bolts located 7" from the top of the bracket (Magnum Piering, Inc., 2002). The rotation of a bracket that incorporates the use of concrete anchors can be roughly estimated by examination of the displacement of the anchor bolts under tensile loads. According to the acceptance criteria for expansion anchors in concrete (ICBO Report Fig. 4 Rotation Compatibility The second step in determining rotational compatibility is to determine the relationship between rotation of the top of the pier, 2, and the moment generated in the soil, M2. This relationship is a function of the rigidity of the pier and the stiffness of the soil. An example set of relationships was generated using 3" O.D., 1/4" thick wall and 1/8" thick wall Magnum Push Piers (Magnum Piering, Inc., 2002). -4- 200 180 Bracket Connection to Structure Resisting Moment (kip-in) 160 140 120 1/4 Wall Pier 100 80 1/8 Wall Pier Soft Clay 60 Soft Clay Stiff Clay Stiff Clay 40 20 0 0 0.1 0.2 0.3 0.4 0.5 0.6 Rotation Angle (deg) Fig. 5 Rotational Compatibility The rotation of the example pier was determined using LPILE Plus for Windows software. Typical properties for various soils were assumed (Reese, L.C., et al., 2000). The top of the pier was fixed with respect to lateral displacement. A small range of rotation angles was input as boundary conditions and the resulting moments at the top of the pier were computed. Results are shown in Fig. 5. rotational compatibility, the rotation angle of the pier and the bracket connection must be equal (1=2). For the example case presented here, the bracket connection to the structure has approximately 3 to 7 times as much moment resistance as the pier in different soils. In order for static equilibrium, the summation of the reaction moment in the connection of the pier to the structure and the reaction moment of the pier in the soil must be equal to the applied moment due to eccentricity of the vertical loads, as given by As can be seen in Fig. 5, the rotation required to generate resisting moments of the pier in the soil are much greater than the rotation necessary to generate the same moment for the bracket connection to the structure. According to the condition of M1+ M 2 = M 0 If a single new parameter, , is defined to account for rotational compatibility, where -5- loads were determined for 3" O.D., 1/4" and 1/8" thick tubular shafts which are indicative of Magnum Push Piers (Magnum Piering, Inc., 2002) and other manufactured steel piers. Results are provided in Figs. 6 though 9. The results of the lateral force analysis indicate that pier stiffness differences between the 0.125" thick and 0.250" thick wall pipe piers produce negligible differences in the magnitude of lateral force as a function of the applied moment to the top of the pier. The results also indicate that larger lateral forces are produced in more dense or more stiff soils. The graphs shown in Figs. 6 through 9 can be used to estimate the lateral force exerted on an existing foundation due to steel pier underpinning if the brackets and piers are the same as or similar to those manufactured by Magnum Piering, Inc. In the next section, the results of the static, strain compatibility, and lateral load analyses are used to predict the lateral and overturning moments exerted on an existing foundation due to steel pier underpinning. is the ratio of M2 to M1, then the equation for moment equilibrium can be rewritten, as given by M 1 (1 + λ) = M 0 = P 1 e The rotational compatibility factor, , is a function of soil conditions, pier shaft rigidity, and bracket connection to the existing structure. For the Magnum Push Pier used in the example herein, the rotational compatibility factor has the following values. Table 1. Rotational Compatibility Factor for Magnum Push Piers and Brackets factor Shaft Thickness Soil Type .23 0.250 soft clay .35 0.250 stiff clay .22 0.250 loose sand .27 0.250 med. sand .15 0.125 soft clay .22 0.125 stiff clay .14 0.125 loose sand .17 0.125 med. sand Bracket Reactions An example calculation of the lateral forces and overturning moments caused by steel pier underpinning is presented using the Magnum Piering brackets and push pier products used in prior sections of this report. Similar calculations can be performed using the steel piering products of other manufacturers if the specifications of those products are known. The goal of this exercise is to provide a working example that demonstrates the fundamental mechanics of a steel pier and bracket connection to an existing structure. Although the specifications for Magnum Piering products are used in the example, it is recognized that other manufacturers systems may be analyzed in a similar manner. Lateral Forces As stated previously, the generation of moments in the pier without lateral movement can only be accomplished if the existing structure is capable of providing a lateral restraining force. The magnitude of lateral load required to restrain the pier head can be determined by again incorporating LPILE Plus for Windows software. Required lateral restraint is a function of the pier shaft rigidity and the stiffness of the soil. Example lateral -6- 3" O.D., 0.125 Thick Wall Pipe Pier 3" O.D., 0.250 Thick Wall Pipe Pier Fig. 6 Lateral Loads for Fixed-Head Steel Piers in Loose Sand Fig. 7 Lateral Loads for Fixed-Head Steel Piers in Medium Dense Sand Fig. 8 Lateral Loads for Fixed-Head Steel Piers in Soft Clay -7- 3" O.D., 0.125 Thick Wall Pipe Pier 3" O.D., 0.250 Thick Wall Pipe Pier Fig. 9 Lateral Loads for Fixed-Head Steel Piers in Stiff Clay For the example calculation, it will be assumed that 3" O.D., 0.250" thick wall push piers are used to underpin an existing foundation, the piers penetrate a stiff layer of clay soils, and that the design load on each pier is 30 kips. Magnum Piering plate and angle brackets have an eccentricity, e, between the center axis of the pier and the face of the bracket of about 2". Hence, the applied moment, M0, is given by According to the right-hand chart in Fig. 9, the lateral load on the existing foundation caused by a bending moment of 16 kip-in for a 3" O.D., 0.250 thick steel pipe pier in stiff clays is approximately -1 kip. The negative sign indicates that the bracket is being pulled away from the foundation due to the bending of the pier under the applied eccentric loads. M 0 = ( 3 0 kip s ) (2 in ch es ) = 6 0 kip in Discussion In summary, the example underpinning application examined in the previous section would exert on the existing foundation an overturning moment equal to 44 kip-in and a lateral load of -1 kip where the negative sign indicates tension. These loads are in addition to the more obvious design vertical load of 30 kips. In order for steel pier underpinning to be a viable alternative for repair of an existing foundation under these example conditions, the existing concrete foundation elements must be capable of withstanding these loads. In the preparation of this work, push piers were assumed to be rigidly fixed to their brackets so that rotation between the bracket According to Table 1, the rotational compatibility factor, , for a 3" O.D., 0.250 thick steel pipe pier in stiff clays with a Magnum Piering or similar bracket is 0.35. Hence, the overturning moment exerted on the existing foundation due to the underpinning is given by M1= 1 ( 6 0 kip in ) = 4 4 kip in 1 + 0 .3 5 and the moment resisted by the pier in the soil is simply given by M 2 = 6 0 kip in − 4 4 kip in = 1 6 kip in -8- and pier is negligible. During steel push pier installation, the pier is typically not integrally attached to the bracket. However, the ram assembly used to install the pier often is attached in a manner that limits pier rotation relative to the bracket. It is possible and perhaps probable that some small amount of rotation of the pier with respect to the bracket may occur during installation and prior to bolting the pier to the bracket. This rotation would increase the reaction moment carried by the pier in the soil and, consequently would result in a larger rotational compatibility factor, . Hence, the foregoing analysis is conservative with regard to moments in that it tends to overestimate the moment transferred to the existing foundation, whereas, it is unconservative with regard to lateral loads, because it tends to underestimate the lateral loads exerted on the existing foundation. A literature search was performed in the preparation of this study. Specific references regarding the analysis and determination of lateral loads and bending moments associated with underpinning brackets were not found. Yet, steel pier underpinning has been used to repair structures in the United States for at least 50 years. There are more than 6 manufacturers of steel pier underpinning systems and hundreds of installation contractors. Due to their widespread use, academic study of steel pier underpinning and bracket connections to structures is an important area of research that should be encouraged. Magnum Piering, Inc. (2002) “Magnum Push Pier Technical Reference Manual” Corporate Literature, Cincinnati, OH Atlas Systems, Inc. (2002) “Piering Products Manual”, Corporate Literature Reese, L.C., et al. (2000) “Computer Program LPILE Plus Version 4.0 User’s Guide” Ensoft, Inc., Austin, TX 78718 Illinois Toolworks, Inc. (2001) “ITW Ramset/Redhead Product & Resource Book” Form No. FLC-6/01, Wood Dale, IL References ICBO Evaluation Service, Inc. (2002) “Acceptance Criteria for Expansion Anchors in Concrete and Masonry Elements” ICBO Report #AC01-0402-R1 -9- August 26, 2002 ATTENTION: Mr. Bill Bonekemper SUBJECT: Concrete Wedge Anchor Capacity For Magnum Piering Bracket Per your request, concrete anchor bolt shear capacities were analyzed assuming eight different bolt groups for use with Magnum Piering Plate Brackets. The analysis generally followed recommendations provided by the anchor bolt manufacturing company and those contained in the 1997 Uniform Building Code. The following are assumptions used in that analysis: 1. Bottom of lifting bracket and concrete member are at the same elevation. 2. The concrete member is assumed to extend well beyond the sides and top of the lifting bracket. 3. Reductions to applied load are based on recommended spacing and edge distance requirements for shear and tension loads as taken from the ITW Ramset/Red Head Product Resource Book, 2001. 4. Allowable loads for combined shear and tension forces are determined by the following equation: (Ps/Pt)5/3 + (Vs/Vt)5/3 1 Where: Ps =Applied tension load Vs = Applied shear load Pt =Allowable tension load Vt = Allowable shear load 4. Red Head Concrete Anchoring Systems ½” diameter Trubolt Wedge Anchors with 4-1/8” embedment were assumed in analysis. 5. Trubolt Wedge Anchors ultimate tension and shear values for 2000, 4000 and 6000 psi concrete were taken from Ramset/ Red Head Product Resource Book, 2001. 6. Applied load “P” on the lifting bracket was assumed to be distributed 1.33 inches from the edge of the bolted plate in accordance with the paper on eccentric loads on piering brackets by Howard A. Perko (2002). Normal weight concrete was assumed for this analysis. 7. Normal weight concrete was assumed for this analysis. It is important to note that the attached calculations are based on ultimate capacity of the concrete wedge anchor bolt pattern. The bolt manufacturer and the Uniform Building Code recommend using a factor of safety of 4.0 in order to determine design capacity. This large factor of safety is typically assigned to wedge anchors, because their capacity depends significantly on the method and care used in anchor bolt installation and the quality of the concrete. We understand that the bolted connection between a Magnum plate bracket and an existing foundation is tested to 150% of the design capacity during push pier installation. The purpose of this test is to verify the strength of the pier, bracket, and connection to the structure. Provided this type of field capacity verification is used for every installation, then, in our opinion, a lower factor of safety may be acceptable. In no case should a factor of safety of less than 1.5 be used in the design with field verification or less than 4.0 without field verification. Thank you for the opportunity to work with you on this project. If you have any questions regarding this analysis, please do not hesitate to contact the undersigned. Sincerely, SECURE FOUNDATIONS & STRUCTURES, INC. William R. Rebillet Structural Engineer ICBO Evaluation Service, Inc. 5360 WORKMAN MILL ROAD • WHITTIER, CALIFORNIA 90601-2299 A subsidiary corporation of the International Conference of Building Officials EVALUATION REPORT Copyright 2000 ICBO Evaluation Service, Inc. ER-1372 Reissued March 1, 2000 Filing Category: FASTENERS—Concrete and Masonry Anchors (066) ITW RAMSET/RED HEAD SELF-DRILLING, TRUBOLT WEDGE, AND MULTI-SET II CONCRETE ANCHORS ITW RAMSET/RED HEAD 1300 NORTH MICHAEL DRIVE WOOD DALE, ILLINOIS 60191 1.0 SUBJECT ITW Ramset/Red Head Self-Drilling, Trubolt Wedge, and Multi-Set II Concrete Anchors. 2.0 DESCRIPTION 2.1 ITW Ramset/Red Head Self-Drilling Anchor: 2.1.1 General: The ITW Ramset/Red Head anchor is a selfdrilling concrete expansion shell anchor with a single cone expander. Both elements are made from heat-treated steel. The steel for the body conforms to AISI C-12Ll 4, and the steel for the plug conforms to AISI C-1010. The anchor has eight sharp teeth at one end and is threaded internally at the other end. The outer surface of the tubular shell at the toothed end has annular broaching grooves and four milled slits. At its threaded end, the anchor is provided with an unthreaded chucking cone that has an annular break-off groove at its base for flush mounting. Anchor shell and expander cone are electrodeposit zinc and chromate-plated. 2.1.2 Installation: Embedment, spacing, edge distance, and concrete requirements are shown in Tables 1 and 2. The anchors are installed by a Model 747 Roto-Stop Hammer, by air or electric impact hammer, or by hand. The anchor is used as a drill in forming the hole in normal-weight concrete. After the hole is formed, the anchor must be removed and the hole thoroughly cleaned. The hole depth is regulated by the drill chuck. A Red Head plug must be set into the bottom of the anchor prior to insertion in the hole. The concrete anchor must be driven over the plug, to cause expansion of the anchor in the hole. The chucking end of the anchor is broken off with a hammer blow. Verification that the anchor has been installed properly is evidenced by the fact that the anchor does not project above the surface of the concrete and the red plug is visible at the bottom of the hole. 2.2 ITW Ramset/Red Head Trubolt Wedge Anchor: 2.2.1 General: The Trubolt Wedge anchor is a stud bolt type of drop-in anchor. The anchors are cold-formed or machined from zinc-plated and chromate-dipped carbon steel, hotdipped galvanized carbon steel or stainless steel. Steel used to produce the anchors complies with AISI C-1015 to AISI C-1022 and AISI C-1213 carbon steels, Type 304 or Type 316 stainless steels. Hot-dipped galvanizing complies with ASTM 153 Class C requirements. The expander sleeves are fabricated from stainless steel or carbon steel meeting the require- ments of Type 302 or AISI C-1010, respectively. Cold-formed anchor studs are available only for the 1/4-inch-, 3/8-inch-, 1/ -inch-, 5/ -inch- and 3/ -inch-diameter (6.4, 9.5, 12.7, 15.9 2 8 4 and 19.1 mm) wedge anchors. The anchor stud is threaded at its upper end and has a straight cylindrical section reduced in diameter, around which the expander sleeve is formed. A straight-tapered section enlarging to a cylindrical base acts to increase the diameter of the expander ring as the stud is tightened in the concrete hold. The expander ring, which is formed around the stud bolt, consists of a split-ring element with a “coined” groove at each end. The expander ring is designed to engage the walls of the concrete hold as the tapered portion of the stud is forced upward against its interior. 2.2.2 Installation: Embedment, spacing, edge distance, and concrete requirements are shown in Tables 3, 4, 5 and 10. Holes must be predrilled in normal-weight or lightweight concrete with carbide-tipped masonry drill bits manufactured within the range of the maximum and minimum drill tip dimensions of ANSI B212.15-1994. The anchors must be installed in holes the same nominal size as the anchor size, with a greater depth than the length of embedment desired, but no less than the minimum embedment. The hole must be cleaned out prior to installation of the anchor. The anchor must be tapped into the hole to the embedment depth desired, but no less than the minimum embedment. A standard hexagonal nut and washer must be used over the material being fastened and the nut tightened until the minimum installation torque, as indicated in Tables 3 and 10, is reached. 2.3 ITW Ramset/Red Head Multi-Set II Anchor: 2.3.1 General: The Multi-Set anchors are designed to be installed in a predrilled hole equal to the anchor diameter. The anchor consists of a shell formed from carbon steel meeting the minimum requirements of AISI C-1213 and an expansion plug formed from carbon steel meeting the minimum requirements of AISI C-1010. The expansion end is divided into four equal segments by radial slots. The expansion plug is preassembled and is cylindrical in cross section. 2.3.2 Installation: Embedment, spacing, edge distance, and concrete requirements are shown in Tables 6, 7 and 9. Holes must be predrilled in normal-weight or lightweight concrete with carbide-tipped masonry drill bits manufactured within the range of the maximum and minimum drill tip dimensions of ANSI B212.15-1994. The anchors must be installed in predrilled holes, the hole depth and diameter for each anchor size being listed in Tables 6, 7 and 9. After the hole is drilled, it is cleared of all cuttings. The anchor is set by installing the expansion shell and then driving the cone expander with a setting tool provided with each anchor size. When the Evaluation reports of ICBO Evaluation Service, Inc., are issued solely to provide information to Class A members of ICBO, utilizing the code upon which the report is based. Evaluation reports are not to be construed as representing aesthetics or any other attributes not specifically addressed nor as an endorsement or recommendation for use of the subject report. This report is based upon independent tests or other technical data submitted by the applicant. The ICBO Evaluation Service, Inc., technical staff has reviewed the test results and/or other data, but does not possess test facilities to make an independent verification. There is no warranty by ICBO Evaluation Service, Inc., express or implied, as to any “Finding” or other matter in the report or as to any product covered by the report. This disclaimer includes, but is not limited to, merchantability. Page 1 of 7 Page 2 of 7 ER-1372 cone expander is driven down into the anchor, the legs of the shell expand. 2.4 Design: Allowable static loads are as set forth in Tables 1, 3, 6, 9 and 10. Allowable loads for anchors subjected to combined shear and tension forces are determined by the following equation: 4.0 FINDINGS That the ITW Ramset/Red Head fasteners described in this report comply with the 1997 Uniform Building Code, subject to the following conditions: 4.1 Anchor sizes, dimensions and installation are as set forth in this report. 4.2 Allowable shear and tension loads are as set forth in Section 2.4. 4.3 Calculations justifying that the applied loads comply with this report are submitted to the building official for approval. 4.4 Special inspection is provided as set forth in Section 2.5. 4.5 Anchors are limited to installation in uncracked concrete, which is concrete subjected to tensile stresses not exceeding 170 psi (1.2 MPa) as induced by external loads, deformations and interior exposures. 2.5 Special Inspection: 4.6 When special inspection is required, compliance with Section 1701.5.2 of the code is necessary. The special inspector must be on the jobsite continuously during anchor installation to verify anchor type, anchor dimensions, concrete type, concrete compressive strength, hole dimensions, anchor spacings, edge distances, slab thickness, anchor embedment and tightening torque. Anchors are limited to nonfire-resistive construction unless appropriate data is submitted to demonstrate anchor performance is maintained in fireresistive situations. 4.7 Anchors are manufactured at Highway 12, Michigan City, Indiana, with inspections by PFS Corporation (NER-QA251). 4.8 Use of electroplated or mechanically plated carbon steel anchors is limited to dry, interior locations. Use of hot-dipped galvanized carbon steel is permitted in exterior-exposure or damp environments. 4.9 Except for ITW Ramset/Red Head Carbon Steel and Stainless Steel Trubolt Wedge anchors embedded in normal-weight concrete, as noted in Table 3, use of anchors in resisting earthquake or wind loads is beyond the scope of this report. (P sńP t) 5ń3 ) (V sńV t) 5ń3 v 1 where: Ps = Applied service tension load. Pt = Allowable service tension load. Vs = Applied service shear load. Vt = Allowable service shear load. The anchors cannot be subjected to vibratory loads. Sources of such loads include, for example, reciprocating engines, crane loads and moving loads due to vehicles. 2.6 Identification: The concrete anchors are identified by their dimensional characteristics, the anchor size, and by the length code stamped on the anchor. The conical-shaped expander plugs are colored red. See Figure 1 for additional details. Length codes are in Table 8. Packages are identified with the anchor type and size, the manufacturer’s name and address, and the name of the quality control agency, PFS Corporation. 3.0 EVIDENCE SUBMITTED Data complying with the ICBO ES Acceptance Criteria for Expansion Anchors in Concrete and Masonry Elements (AC01), dated January 1999. 4.10 The anchors are not subjected to vibratory loads, such as those encountered by supports for reciprocating engines, crane loads and moving loads due to vehicles. This report is subject to re-examination in two years. TABLE 1—ITW RAMSET/RED HEAD SELF-DRILLING ANCHOR ALLOWABLE SHEAR AND TENSION VALUES (pounds)1,3,4 f ′c = 2,000 psi BOLT DIAMETER (inch) 1/ ANCHOR DIAMETER (inch) 4 7/ 3/ 8 9/ 1/ 2 5/ 8 16 11/ 16 27/ 32 3/ 4 1 16 f ′c = 4,000 psi Tension Tension MINIMUM EMBEDMENT DEPTH (inches) With Special Inspection 2 Without Special Inspection Shear With Special Inspection 2 Without Special Inspection Shear 13/32 17/32 21/32 215/32 31/4 415 785 1,150 1,510 1,985 210 395 575 755 995 295 770 920 1,605 2,495 650 1,035 1,555 2,485 3,165 325 520 775 1,240 1,585 365 650 930 1,755 2,575 For SI: 1 inch = 25.4 mm, 1 lbf = 4.45 N, 1 psi = 6.89 kPa. 1The tabulated shear and tensile values are for anchors installed in normal-weight concrete having the designated ultimate compressive strength at the time of installation. Values have been tabulated for both ASTM A 307 and A 449 bolts installed with the device. 2These tension values are applicable only when the anchors are installed with special inspection as set forth in Section 2.5. 3The minimum concrete thickness is 11/ times the embedment depth, or the embedment depth plus three times the anchor diameter, whichever is greater. 2 4The anchors are illustrated as follows: Page 3 of 7 ER-1372 TABLE 2—RECOMMENDED SPACING AND EDGE DISTANCE REQUIREMENTS FOR ITW RAMSET/RED HEAD SELF-DRILLING ANCHOR1 DESCRIPTION BOLT DIAMETER (inch) 1/ ANCHOR DIAMETER (inch) 4 7/ 3/ 8 9/ 1/ 2 5/ 8 16 11/ 16 27/ 32 3/ 4 1 16 MIN. EMBEDMENT DEPTH (inches) Edge Distance Required to Obtain Max. Working Load (inches) 13/32 17/32 21/32 215/32 31/4 115/16 211/16 39/16 43/8 511/16 Min. Allowable Edge Distance (inches) Load Factor Applied = 0.85 for Tension = 0.75 for Shear Spacing Required to Obtain Max. Working Load (inches) Min. Allowable Spacing Between Anchors (inches) Load Factor Applied = 0.95 for Tension = 0.70 for Shear 37/8 53/8 71/8 811/16 113/8 115/16 211/16 39/16 43/8 511/16 1 13/ 8 113/16 23/16 27/8 For SI: 1 inch = 25.4 mm. 1Linear interpolation may be used for intermediate spacing and edge distances. TABLE 3—ITW RAMSET/RED HEAD TRUBOLT WEDGE ANCHOR ALLOWABLE SHEAR AND TENSION VALUES (pounds)1,2,4,5,6 f ′c = 2,000 psi f ′c = 4,000 psi Tension ANCHOR DIAMETER (inches) INSTALLATION TORQUE (lbf · ft) EMBEDMENT DEPTH (inches) With Special Insption 3 Without Special Inspection 1/ 4 8 3/ 8 25 1/ 2 55 5/ 8 90 3/ 4 175 7/ 8 250 11/8 115/16 21/8 11/2 3 4 21/4 41/8 6 23/4 51/8 71/2 31/4 65/8 10 33/4 61/4 8 41/2 73/8 91/2 51/2 8 10 295 525 565 420 870 1,200 1,165 1,165 1,335 1,645 1,645 1,765 1,780 2,745 2,745 2,380 3,665 3,665 3,485 3,650 4,675 4,535 6,835 9,035 150 265 280 210 435 600 580 580 665 820 820 880 890 1,375 1,375 1,190 1,835 1,835 1,745 1,825 2,340 2,270 3,413 4,515 1 300 11/4 500 f ′c = 6,000 psi Tension Shear 350 420 580 1,000 1,190 1,810 1,780 2,400 2,530 5,080 3,290 5,220 4,020 7,170 5,820 8,770 With Special Inspection 445 825 825 560 1,485 1,485 1,275 2,410 2,410 1,795 3,730 3,755 2,710 4,425 4,470 3,685 5,235 5,580 5,045 5,995 6,635 6,595 10,825 11,385 Tension Without Special Inspection 225 410 410 280 740 740 640 1,205 1,205 900 1,865 1,880 1,355 2,210 2,235 1,840 2,620 2,790 2,520 3,000 3,315 3,300 5,410 5,695 Shear 350 420 655 1,035 1,190 1,810 1,780 2,975 3,430 5,935 4,145 7,200 5,705 9,485 7,365 11,065 With Special Inspection 475 825 825 710 1,530 1,530 1,760 2,705 2,705 2,430 4,095 4,095 3,325 5,065 5,895 4,355 6,090 6,090 5,295 8,315 8,315 8,410 11,385 14,075 Without Special Inspection 240 410 410 355 765 765 880 1,355 1,355 1,215 2,045 2,045 1,665 2,530 2,950 2,180 3,045 3,045 2,650 4,160 4,160 4,205 5,695 7,040 Shear 350 420 790 1,125 1,760 2,040 2,405 3,130 3,995 5,935 4,790 7,200 6,120 9,520 8,445 12,640 For SI: 1 inch = 25.4 mm, 1 psi = 6.89 kPa, 1 lbf · ft = 1.355 818 N · m, 1 lbf = 4.45 N. 1The tabulated shear and tensile values are for anchors installed in stone-aggregate concrete having the designated ultimate compressive strength at the time of installation. 2The holes are drilled with bits complying with ANSI B212.15-1994. The bit diameter equals the anchor diameter. 3These tension values are applicable only when the anchors are installed with special inspection as set forth in Section 2.5. 4The minimum concrete thickness is 11/ times the embedment depth, or the embedment depth plus three times the anchor diameter, whichever is greater. 2 5Allowable static loads may be increased one-third for earthquake or wind resistance in accordance with Section 1612.3.3 of the code. No further increase is allowed. 6The anchors are illustrated as follows: Page 4 of 7 ER-1372 TABLE 4—RECOMMENDED SPACING AND EDGE DISTANCE REQUIREMENTS FOR TENSION LOADS FOR ITW RAMSET/RED HEAD TRUBOLT WEDGE ANCHORS1 DESCRIPTION ANCHOR DIAMETER (inches) EMBEDMENT DEPTH (inches) Edge Distance Required to Obtain Max. Working Load (inches) 1/ 4 3/ 8 11/8 115/16 21/8 11/2 3 4 21/4 41/8 6 23/4 51/8 71/2 31/4 65/8 10 33/4 61/4 8 41/2 73/8 91/2 51/2 8 10 2 115/16 5 1 /8 25/8 3 3 315/16 31/8 41/2 413/16 37/8 55/8 511/16 5 71/2 69/16 61/4 6 77/8 73/8 71/8 95/8 8 71/2 1/ 2 5/ 8 3/ 4 7/ 8 1 11/4 Min. Allowable Edge Distance (inches) Load Factor Applied = 0.65 Spacing Required to Obtain Max. Working Load (inches) Min. Allowable Spacing Between Anchors (inches) Load Factor Applied = 0.70 1 1 13/16 15/16 11/2 11/2 2 19/16 1 2 /4 27/16 115/16 213/16 27/8 21/2 33/4 35/16 31/8 3 315/16 311/16 39/16 413/16 4 33/4 315/16 37/8 33/16 51/4 6 6 77/8 63/16 9 95/8 711/16 111/4 113/8 915/16 15 131/8 121/2 12 153/4 143/4 141/4 191/4 16 15 2 115/16 5 1 /8 25/8 3 3 315/16 31/8 41/2 413/16 37/8 55/8 511/16 5 71/2 69/16 61/4 6 77/8 73/8 71/8 95/8 8 71/2 For SI: 1 inch = 25.4 mm. 1Linear interpolation may be used for intermediate spacing and edge distances. 2Spacings and edge distances shall be divided by 0.75 when anchors are placed in structural lightweight concrete in accordance with Table 10. TABLE 5—RECOMMENDED SPACING AND EDGE DISTANCE REQUIREMENTS FOR SHEAR LOADS FOR ITW RAMSET/RED HEAD TRUBOLT WEDGE ANCHORS1 DESCRIPTION (E) Edge Distance Required to Obtain Max. Working Load (inches) (E1) Min. Edge Distance at Which the Load Factor Applied = 0.60 (inches) (E2) Min. Edge Distance at Which the Load Factor Applied = 0.20 (inches) Min. Allowable Spacing Between Anchors (inches) Load Factor Applied = 0.40 ANCHOR DIAMETER (inches) EMBEDMENT DEPTH (inches) (See Figure 2) (See Figure 2) (See Figure 2) Spacing Required to Obtain Max. Working Load (inches) 1/ 4 11/8 115/16 2 115/16 15/16 1 N/A N/A 315/16 37/8 2 115/16 3/ 8 11/2 3 25/8 33/4 13/4 3 N/A 11/2 51/4 6 25/8 3 1/ 2 21/4 41/8 315/16 53/16 29/16 31/8 N/A 19/16 77/8 63/16 315/16 31/8 5/ 8 23/4 51/8 413/16 67/16 31/8 37/8 N/A 115/16 95/8 711/16 413/16 37/8 3/ 4 31/4 65/8 511/16 85/16 33/4 5 N/A 21/2 113/8 915/16 511/16 5 7/ 8 33/4 61/4 69/16 81/2 45/16 61/4 N/A 31/8 131/8 121/2 69/16 61/4 1 41/2 73/8 77/8 101/16 51/8 73/8 N/A 311/16 153/4 143/4 77/8 73/8 11/4 51/2 8 95/8 117/16 61/4 8 N/A 4 191/4 16 95/8 8 For SI: 1 inch = 25.4 mm. N/A = Not applicable. 1Linear interpolation may be used for intermediate spacing and edge distances. 2Spacings and edge distances shall be divided by 0.75 when anchors are placed in structural lightweight concrete in accordance with Table 10. Page 5 of 7 ER-1372 TABLE 6—ITW RAMSET/RED HEAD MULTI-SET II ANCHOR ALLOWABLE SHEAR AND TENSION VALUES (pounds)1,2,4,5 f ′c = 2,000 psi BOLT DIAMETER (inch) ANCHOR DIAMETER (inch) 1/ 4 3/ 8 3/ 8 1/ 2 1/ 2 5/ 8 5/ 8 7/ 8 3/ 4 1 f ′c = 4,000 psi Tension f ′c = 6,000 psi Tension Tension MINIMUM EMBEDMENT DEPTH (inches) With Special Inspection 3 Without Special Inspection Shear With Special Inspection 3 Without Special Inspection Shear With Special Inspection 3 Without Special Inspection Shear 1 15/8 2 21/2 33/16 420 745 825 1,375 2,070 210 375 415 685 1,035 270 790 1,145 1,860 2,620 590 950 1,460 2,160 2,370 295 475 730 1,080 1,185 300 625 875 1,385 1,920 745 1,560 2,075 2,755 3,065 375 780 1,035 1,375 1,530 325 465 600 910 1,215 For SI: 1 inch = 25.4 mm, 1 lbf = 4.45 N, 1 psi = 6.89 kPa. 1The tabulated shear and tensile values are for anchors installed in stone-aggregate concrete having the designated ultimate compressive strength at the time of installation. Values have been tabulated for both ASTM A 307 and A 449 bolts installed with the device. 2The holes are drilled with bits complying with ANSI B212.15-1994. The bit diameter equals the anchor diameter. 3These tension values are applicable only when the anchors are installed with special inspection as set forth in Section 2.5. 4The minimum concrete thickness is 11/ times the embedment depth, or the embedment depth plus three times the anchor diameter, whichever is greater. 2 5The anchors are illustrated as follows: TABLE 7—RECOMMENDED SPACING AND EDGE DISTANCE REQUIREMENTS FOR ITW RAMSET/RED HEAD MULTI-SET II ANCHOR1 DESCRIPTION BOLT DIAMETER (inch) ANCHOR DIAMETER (inch) 1/ MIN. EMBEDMENT DEPTH (inches) 4 3/ 8 1 3/ 8 1/ 2 15/ 1/ 2 5/ 8 5/ 8 7/ 8 3/ 4 1 8 2 21/2 33/16 Edge Distance Required to Obtain Max. Working Load (inches) Min. Allowable Edge Distance (inches) Load Factor Applied = 0.80 for Tension = 0.70 for Shear Spacing Required to Obtain Max. Working Load (inches) Min. Allowable Spacing Between Anchors (inches) Load Factor Applied = 0.80 for Tension = 0.55 for Shear 13/4 27/8 31/2 43/8 55/8 7/8 17/16 13/4 23/16 213/16 31/2 511/16 7 83/4 113/16 13/4 27/8 31/2 43/8 55/8 For SI: 1 inch = 25.4 mm. 1Linear interpolation may be used for intermediate spacing and edge distances. 2Spacings and edge distances shall be divided by 0.75 when anchors are placed in structural lightweight concrete in accordance with Table 9. TABLE 8—LENGTH IDENTIFICATION CODES LENGTH OF ANCHOR CODE A B C D E F G H I J K L M Black White Red Green Yellow Blue Purple Brown Orange N/A N/A N/A N/A LENGTH OF ANCHOR (inches) (mm) CODE (inches) (mm) 11/2 < 2 2 < 21/2 21/2 < 3 3 < 31/2 31/2 < 4 4 < 41/2 41/2 < 5 5 < 51/2 51/2 < 6 6 < 61/2 61/2 < 7 7 < 71/2 71/2 < 8 38 < 51 51 < 63 63 < 76 76 < 89 89 < 102 102 < 114 114 < 127 127 < 140 140 < 152 152 < 165 165 < 178 178 < 191 191 < 203 N O P Q R S T U V W X Y Z 8 < 81/2 81/2 < 9 9 < 91/2 91/2 < 10 10 < 11 11 < 12 12 < 13 13 < 14 14 < 15 15 < 16 16 < 17 17 < 18 18 < 19 203 < 216 216 < 229 229 < 241 241 < 254 254 < 267 267 < 305 305 < 330 330 < 366 366 < 381 381 < 406 406 < 432 432 < 457 457 < 483 Page 6 of 7 ER-1372 TABLE 9—ITW RAMSET/RED HEAD MULTI-SET II ANCHOR ALLOWABLE SHEAR AND TENSION VALUES (pounds)1,2,4 LOWER FLUTE OF STEEL DECK WITH LIGHTWEIGHT CONCRETE FILL f ′c = 3,000 psi LIGHTWEIGHT CONCRETE f ′c = 3,000 psi BOLT DIAMETER (inch) ANCHOR DIAMETER (inch) 3/ 8 1/ 2 1/ 2 5/ 8 5/ 8 7/ 8 3/ 4 1 MINIMUM EMBEDMENT DEPTHS (inches) 3 With Special Inspection 3 Without Special Inspection 19/16 2 21/2 33/16 965 1,020 1,570 2,750 482 510 785 1,375 Tension Tension Shear With Special Inspection Without Special Inspection Shear 1,105 1,410 2,610 3,945 835 800 1,490 2,045 417 400 745 1,022 1,105 1,235 1,460 2,280 For SI: 1 inch = 25.4 mm, 1 lbf = 4.45 N, 1 psi = 6.89 kPa. 1The tabulated shear and tensile values are for anchors installed in structural lightweight concrete having the designated ultimate compressive strength at the time of installation. Values have been tabulated for both ASTM A 307 and A 449 bolts installed with the device. 2The holes are drilled with bits complying with ANSI B212.15-1994. The bit diameter equals the anchor diameter. 3These tension values are applicable only when the anchors are installed with special inspection as set forth in Section 2.5. 4Installation details are in Figure 3. Spacing and edge distances are in Table 7 as modified by Footnote 2. TABLE 10—ITW RAMSET/RED HEAD TRUBOLT WEDGE ANCHOR ALLOWABLE SHEAR AND TENSION VALUES (pounds)1,2,4 LOWER FLUTE OF STEEL DECK WITH LIGHTWEIGHT CONCRETE FILL f ′c = 3,000 psi LIGHTWEIGHT CONCRETE f ′c = 3,000 psi INSTALL TORQUE (ft.-lb.) MINIMUM EMBEDMENT DEPTHS (inches) 3 8 25 11/ 1/ 2 55 5/ 8 90 3/ 4 175 ANCHOR DIAMETER (inch) 3/ Tension With Special3 Inspection Tension Without Special Inspection Shear With Special Inspection Without Special Inspection Shear 2 530 735 265 367 930 1,060 475 710 237 355 790 1,000 21/4 3 4 3 5 900 1,180 N/A 1,500 1,490 450 590 N/A 750 745 1,760 1,655 1,730 2,310 2,320 850 1,120 1,200 1,180 1,645 425 560 600 590 822 1,345 1,655 1,610 1,375 2,285 31/4 51/4 1,790 2,225 895 1,112 3,150 3,980 1,460 1,760 730 880 2,220 N/A 3 For SI: 1 inch = 25.4 mm, 1 psi = 6.89 kPa, 1 lbf = 4.45 N. N/A = Not applicable. 1The tabulated shear and tensile values are for anchors installed in structural lightweight concrete having the designated compressive strength at the time of installation. 2The holes are drilled with bits complying with ANSI B212.15-1994. The bit diameter equals the anchor diameter. 3These tension values are applicable only when the anchors are installed with special inspection as set forth in Section 2.5. 4Installation details are in Figure 3. Spacing and edge distances are in Tables 4 and 5 as modified by Footnote 2. Self-Drills Trubolt Wedge Anchors Multi-Set II S (bolt size) WS-Carbon Steel (anchor size RM-Carbon Steel (bolt size) length) FIGURE 1—IDENTIFICATION SYMBOLS FOR THE VARIOUS ANCHORS Page 7 of 7 ER-1372 1.00 S 0.60 S 0.20 E2 E1 E FIGURE 2—LOAD FACTORS FOR TRUBOLT WEDGE ANCHOR SHEAR LOADS AT REDUCED EDGE DISTANCES (See also Table 5) For SI: 1 inch = 25.4 mm. FIGURE 3—TRUBOLT AND MULTI-SET II ANCHORS IN LIGHTWEIGHT CONCRETE (f ′c = 3,000 psi) AND STEEL DECK WITH LIGHTWEIGHT CONCRETE FILL (f ′c = 3,000 psi) Standard Plate Bracket Single Bolted Connection Double Bolted Connection Triple Bolted Connection Magnum Steel Push Pier Foundation Specifications Connection Type Allowable Capacity * Standard Duty Steel Pier ( 1/8" Wall Tube ) Single Bolted Double Bolted Triple Bolted 9 kips 19 kips 28 kips Heavy Duty Steel Pier ( 1/4" Wall Tube ) Single Bolted Double Bolted Triple Bolted * 15 kips 30 kips 43 kips Values shown indicate the working capacities of different connections between the push pier shaft and bracket. These capacities include a factor of safety of 1.5. The strength of the connection between the bracket and a structure and the bearing capacity of the push pier after installation shall be field verified through load testing. Standard Angle Bracket Single Bolted Connection Double Bolted Connection Triple Bolted Connection Magnum Steel Push Pier Foundation Specifications Connection Type Allowable Capacity * Standard Duty Steel Pier ( 1/8" Wall Tube ) Single Bolted Double Bolted Triple Bolted 9 kips 19 kips 28 kips Heavy Duty Steel Pier ( 1/4" Wall Tube ) Single Bolted Double Bolted Triple Bolted * 15 kips 30 kips 43 kips Values shown indicate the working capacities of different connections between the push pier shaft and bracket. These capacities include a factor of safety of 1.5. The strength of the connection between the bracket and a structure and the bearing capacity of the push pier after installation shall be field verified through load testing. Magnum Piering, Inc. Steel Push Pier Maximum Spacing Guide 16 This chart is applicable to Magnum Plate and Angle Brackets. It assumes that two bolts are used to secure the bracket to the pier, at least 6-inches of 2,000 psi concrete cover is present over the top row of concrete anchors, the angle bracket is attached to the structure using grout, and that the structure is capable of providing some moment resistance. A factor of safety of 1.5 is incorporated. Actual Total Dead+Live Wall Load (kip/ft) 14 12 10 Magnum Heavy Duty Push Pier (1/4 Wall, Double Bolted) 8 Magnum Standard Duty Push Pier (1/8 Wall, Double Bolted) 6 4 2 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 Center-to-Center Spacing (ft) 9.0 10.0 11.0 12.0 Magnum Steel Push Piering Products Magnum Hydraulic Ram, Channels & Bracket Mounting Boot Magnum Steel Push Piering Products Magnum Hydraulic Ram, Channels and Bracket Mounting Boot Mounted on Magnum Angle Bracket Magnum Steel Push Piering Products Magnum Angle Bracket Magnum Steel Push Piering Products Magnum Patented Plate Bracket Magnum Steel Push Piering Products Tube for Angle and Plate Brackets Magnum Steel Push Piering Products Pier Pipe and Friction Ring Magnum Steel Push Piering Products Pipe to Bracket Grade 8 Bolt MAGNUM PUSH PIER FOUNDATION TECHNICAL REFERENCE GUIDE MECHANICAL BENDING STRENGTH OF PUSH PIER PIPE SHAFT PRODUCT TESTING REPORT July 15, 2002 by Howard A. Perko, Ph.D., P.E. Consulting Engineer for Magnum Piering, Inc. TABLE OF CONTENTS Introduction .................................................................................................................................... 3 Test Method ................................................................................................................................... 3 Pipe Shaft Bending Results ............................................................................................................ 5 Effect of Galvanization .................................................................................................................. 6 Effect of Grouting .......................................................................................................................... 8 Bending Strength of Shaft Connectors ......................................................................................... 10 -2- INTRODUCTION Determination of the lateral and buckling resistance of a steel push pier requires knowledge of the mechanical bending strength of the pier shaft. Bending resistance of an empty steel pipe can be estimated by traditional and well known engineering calculations. The bending resistance of a grout filled pipe shaft and the effect of galvanization on bending strength is more difficult to compute theoretically. An investigation was conducted to measure the mechanical bending resistance of the pipe shaft used for Magnum steel push piers. The investigation included a series of load tests on steel pipe, grout-filled pipe, and galvanized pipe shafts. The bending strength of Magnum steel push pier connectors were also measured. This document represents a sample of the types of testing used by Magnum Piering to determine capacities of its steel push pier foundation products. Other tests that have been conducted include bracket mechanical capacity, bracket concrete anchor capacity, and full-scale field capacity. As part of a manufacturing quality assurance program, Magnum Piering periodically tests various components of its product line. For Magnum Piering, product testing and quality assurance is an ongoing effort. Contact Magnum Piering headquarters for additional information and test results on any product or component. TEST METHOD Shaft bending tests were conducted on 5'-0" long specimens. The specimens were mounted in a load frame with reaction supports spaced 44" apart. Deflection was measured using a dial gage mounted at the center of the pipe specimen. A photograph of the test set-up is shown in Fig. 1. Some of the load tests were performed with 3 point loading wherein load was applied to a single point at the center of the reaction supports. During these tests, it was noted that the pipe shaft exhibited fairly significant compression at the load point. In order to evaluate the effect of this distortion of the pipe cross-section on the bending strength, later tests were performed using a 4 point loading technique wherein load was applied to two points between the reaction supports. Each of the load application points was located at a distance from respective reaction supports equal to one-third the total distance between the reaction supports. As expected, much higher loads could be applied with considerably less pipe distortion using the 4 point load method. However, the calculated maximum moment and measured deflection for both types of load tests were nearly equivalent, as shown in Fig. 2. The dark or filled points on the graph represent data obtained for the 1/8" thick wall pipe shaft, while the white or open points on the graph represent data obtained for the 1/4" thick wall pipe shaft. As can be seen in the figure, results for 3 point and 4 point loading for the 1/8" thick tube are identical. The load displacement curves obtained for load tests on the 1/4" thick tube display a slight variation, however the maximum moment and total displacement at maximum moment were nearly the same. -3- Fig. 1 Pipe Shaft Bending Test Apparatus 3" O.D. Steel Tube 140,000 Applied Moment (in-lbs) 120,000 100,000 80,000 1/8 wall tube, 3 Pt. Loading 60,000 1/8 wall tube, 4 Pt. Loading 40,000 1/4 wall tube, 3 Pt. Loading 20,000 1/4 wall tube, 4 Pt. Loading 0 0 0.2 0.4 0.6 0.8 1 1.2 Displacement (in) Fig. 2 Effect of Load Application Method -4- 1.4 1.6 PIPE SHAFT BENDING RESULTS Magnum steel push pier pipe shafts are manufactured from high-strength steel, seamless, structural tubing with a 3" O.D. Two different shafts are available with 1/8" and 1/4" thick walls. The steel comprising the structural tube has a minimum yield strength of 40 ksi and ultimate strength of 55 ksi. Section modulus, area moment of inertia, and other properties of Magnum steel push pier pipe shafts are given in Table 1. Area moment of inertia was computed using the well known formula given by π (d 4 − d 14 ) I = 64 where I d d1 = = = area moment of inertia, outside diameter, and inside diameter. Section modulus was computed by dividing the area moment of inertia, I, by half the outside diameter, d/2. The mechanical bending strengths of the shafts were computed by multiplying the yield and ultimate strength of the pipe steel by the section modulus. Mechanical bending strength is subject to variations in steel strength and tolerances in structural tube thicknesses. Minimum theoretical mechanical bending strength is shown in Table 2. Table 1. Magnum Push Pier Shaft Specifications 1/8" Wall Pipe 1/4" Wall Pipe Outside Diameter (in) 3.000 3.000 Inside Diameter (in) 2.750 2.500 Area Moment of Inertia (in4) 1.17 2.06 Section Modulus (in3) 0.78 1.37 Cross-Section Area (in2) 1.13 2.16 Table 2. Magnum Push Pier Shaft Theoretical Bending Strength 1/8" Wall Pipe 1/4" Wall Pipe Mechanical Bending Yield Strength (kip-in) 31 55 Mechanical Bending Ultimate Strength (kip-in) 43 75 Results of bending tests on non-galvanized, non-grouted pier shafts are shown in Fig. 3. As can be seen in this figure, the measured yield and ultimate bending strength of the 1/8" thick wall pier shaft was similar to the calculated values shown in Table 2, whereas, the measured yield and ultimate bending strength of the 1/4" thick wall pier shaft was considerably greater -5- than the calculated values shown in Table 2. This suggests that the mechanical strength of the steel used by Magnum Piering in the construction of their 1/4" thick wall steel push pier shafts was on the order of 73 ksi yield strength and 93 ksi ultimate strength. The values given previously were minimum values. It is suggested that design engineers continue to use minimum values with the understanding that the strength may often be considerably greater. Magnum Piering uses periodic hardness testing and measurement of tube wall thickness for quality assurance. 140,000 Bending Moment (in-lbs) 120,000 1/8" Wall 1/4" Wall 100,000 Yield Point 100 kip-in 80,000 60,000 40,000 20,000 Yield Point 30 kip-in 0 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 Deflection (in) Fig. 3 Bending Resistance of Non-Galvanized, Non-Grouted Steel Pipe Shaft EFFECT OF GALVANIZATION For use in highly corrosive soils or when requested by their clients, Magnum Piering utilizes hot-dip galvanization to increase the life expectancy of steel push pier shafts. The process of hot-dip galvanization increases the thickness of the tubular shaft and may increase steel strength due to heat treatment. In order to evaluate the effect of galvanization on the bending resistance of Magnum Push Pier shafts, several specimens were tested that were identical to the specimens described in the previous section except they were galvanized. -6- Results of these tests are shown in Figs. 4 and 5. As can be seen in the figures, the galvanization process had a considerable effect on the bending strength of the 1/8" thick wall shaft and a negligible effect on the 1/4" thick wall shaft. 140,000 Applied Moment (in-lbs) 120,000 100,000 80,000 60,000 40,000 Non-Galvanized 20,000 Galvanized 0 0 0.2 0.4 0.6 0.8 1 Displacement (in) Fig. 4 Effect of Galvanization on Bending Strength of 1/8" Thick Wall Shafts 140,000 Applied Moment (in-lbs) 120,000 100,000 80,000 60,000 Non-Galvanized 40,000 Galvanized 20,000 0 0 0.2 0.4 0.6 0.8 1 Displacement (in) Fig. 5 Effect of Galvanization on Bending -7- Strength of 1/4" Thick Wall Shafts 1.2 The galvanization process increased the bending resistance of 1/8" thick wall pier shaft by a factor of approximately 100% (i.e. 2x greater). It is left to the discretion of the design engineer whether to utilize this strength gain in foundation design. Application of galvanization strength gain should be weighed against the life expectancy and corrosion requirements of the project. These strength gains likely will be reduced over time as the zinc coating is sacrificially degraded over time. EFFECT OF GROUTING One method of increasing the bending resistance of steel pier shafts that can be performed after installation is complete is filling the shaft with a high-slump cement grout. A set of tests were performed on non-galvanized pier shaft specimens filled with a minimum 2,000 psi, 28-day compressive strength cement grout. The specimens were allowed to cure in air for 28 days prior to testing. Results of these tests are shown in Figs. 6 and 7. The results indicate that the process of grouting increases the bending yield strength of 1/8" thick wall shafts by approximately 75% (i.e. 1.75x greater) and the bending ultimate strength by approximately 40% (i.e. 1.40x greater). The effect of grouting on the bending strength of 1/4" thick wall tube was considerably less significant with negligible measured increases in the bending yield strength and only 1% increase (i.e. 1.01x greater) in the bending ultimate strength. 140,000 Non-Grouted 120,000 Applied Moment (in-lbs) Grouted 100,000 80,000 60,000 40,000 20,000 0 0 0.2 0.4 0.6 0.8 Displacement (in) Fig. 6 Effect of Grouting on Bending Strength of 1/8" Thick Wall Shafts -8- 1 140,000 Applied Moment (in-lbs) 120,000 100,000 80,000 60,000 Non-Grouted 40,000 Grouted 20,000 0 0 0.2 0.4 0.6 0.8 1 Displacement (in) Fig. 7 Effect of Grouting on Bending Strength of 1/4" Thick Wall Shafts With respect to the ultimate bending strength, the different effect exhibited by the grout in 1/8" and 1/4" thick wall tubular shafts cannot be due to differences in the rigidity of the two pipe sections. Although the 1/4" thick wall pipe shaft has a larger area moment of inertia, as shown in Table 1, and a more steeply sloped moment-displacement curve, as shown in Fig. 2, the displacements at the point of ultimate failure were approximately the same, as shown in Fig. 3. A potential reason for the difference in the effect of the grout is a variation in the diameter of the grouted column. The grout column for the 1/4" thick wall tube is 2.5", whereas the grout column for the 1/8" thick wall tube is 2.75". Since bending strength is a function of the diameter of the column to the 3rd power, the smaller diameter grout column should have a bending resistance that is approximately 2/3 that of the larger diameter grout column. When this modification is taken into account, the bending strength of the 1/4" thick wall tube should have been 15% greater than the non-grouted tube with the same wall thickness. However, this value is still greater than the measured result indicating that the interplay of the cement grout and the pipe shaft is more complex and depends on additional factors. From the foregoing set of tests, it is recommended that the bending yield strength of 1/8" thick wall pier shafts can be increased by a factor of 75% if the shaft is grouted after installation. Similar strength gains were not observed for the 1/4" thick wall shaft. -9- BENDING STRENGTH OF SHAFT CONNECTORS Magnum Push Pier shaft sections are manufactured in 36" lengths. Sections are coupled together by means of an internal sleeve that is fixed to one end of the section by two plug welds. Unless otherwise specified, the sleeve is not fixed to the opposing end of the adjoining section, as shown in Fig. 8. At the discretion of the design engineer, the sections can be welded together in the field during installation at additional cost to the project. Welding of galvanized steel push pier sections produces toxic gasses and should only be performed in well ventilated areas using appropriate safety equipment. Most steel push pier installations do not require welding. Hence, it is imperative to determine the bending resistance of the connections between the steel push pier sections. Fig. 8 Magnum Push Pier Connector The bending strength of the steel push pier connector shown in Fig. 8 is expected to depend in-part on the axial load on the pier. A conservative estimate of the bending strength of the connector supported from buckling by the surrounding soils can be determined by examining the bending strength of the inner sleeve. Magnum steel push pier pipe shaft connectors are manufactured from high-strength steel, seamless, structural tubing. The outside diameter and thickness of the sleeve depends on the inside diameter of the main pier shaft. The steel comprising the structural tube sleeves has the same minimum yield strength and ultimate strength of the main shaft sections. Dimensional specifications, section modulus, area moment of inertia, and other properties of Magnum steel push pier pipe shaft inner sleeve connectors are given in Table 3. Area moment of inertia was again computed using the well known formula given by π (d 4 − d 14 ) I = 64 -10- where I d d1 = = = area moment of inertia, outside diameter, and inside diameter. Section modulus and mechanical bending strength were computed as explained previously. Mechanical bending strength of the inner sleeve connectors is shown in Table 4. Table 3. Magnum Push Pier Shaft Inner Sleeve Specifications 1/8" Wall Pipe 1/4" Wall Pipe Outside Diameter (in) 2.750 2.500 Inside Diameter (in) 2.500 2.000 Area Moment of Inertia (in4) 0.89 1.13 Section Modulus (in3) 0.65 0.90 Cross-Section Area (in2) 1.03 1.77 Table 4. Magnum Push Pier Shaft Inner Sleeve Theoretical Bending Strength 1/8" Wall Pipe 1/4" Wall Pipe Mechanical Bending Yield Strength (kip-in) 26 36 Mechanical Bending Ultimate Strength (kip-in) 36 50 Mechanical bending tests were performed on both non-grouted and grouted steel push pier shaft sections. The specimen dimensions, test apparatus, and procedures were as described previously. Results of the tests are shown in Figs. 9 and 10. The measured yield and ultimate bending strength of the 1/8" thick wall shaft connector is similar to the theoretical bending strength of the inner sleeve as given in Table 4, whereas the measured yield and ultimate bending strength of the 1/4" thick wall shaft connector was considerably greater than the theoretical value given in Table 4. These results are again indicative of the typically higher strength steel typically used by Magnum Piering for the construction of its heavy duty 1/4" thick wall piers. Another conclusion shown by the test data is that grouting of the 1/8" thick wall pier section connectors significantly increased the bending strength (approx. 100% greater), whereas grouting of the 1/4" thick wall pier section connectors produced a smaller effect (approx. 10% greater bending strength). -11- 140,000 Non-Grouted Applied Moment (in-lbs) 120,000 Grouted 100,000 80,000 60,000 40,000 20,000 0 0 0.2 0.4 0.6 0.8 1 Displacement (in) Fig. 9 Bending Strength of 1/8" Thick Wall Shaft Connectors 140,000 Non-Grouted Grouted Applied Moment (in-lbs) 120,000 100,000 80,000 60,000 40,000 20,000 0 0 0.2 0.4 0.6 0.8 1 Displacement (in) Fig. 10 Bending Strength of 1/4" Thick Wall Shaft Connectors -12- 1.2