the Five in One Dedication Ceremony Brochure
Transcription
the Five in One Dedication Ceremony Brochure
Virgin Islands Water and Power Authority “Five in One“ WAPA…Working for You! Dedication Ceremony Estate Richmond Power Plant Facility Northeastern Section August 29, 2012 10 a.m. Master of Ceremonies Vernon Alexander, Director of Special Projects Virgin Islands Water and Power Authority (WAPA) Music Ambassador Sound System National Anthem and Virgin Islands March Chlorine GeneraƟon System MIOX Invocation Reverend Gloria Williams V. I. Christian Ministries ChrisƟansted Underground Project Phase I Introduction of Special Guests Vernon Alexander Director of Special Projects Richmond Standpipe Building Upgrade Remarks Hugo V. Hodge, Jr., CPQ, Executive Director (CEO) Virgin Islands Water and Power Authority Gerald T. Groner, Esquire, Chairman Governing Board Virgin Islands Water and Power Authority RehabilitaƟon of the Richmond Storage Tank Please join us for refreshments immediately after the program Richmond 69/25kV SubstaƟon Upgrade Richmond 69/25kV Substation Upgrade The Virgin Islands Water & Power Authority is a public power utility with its core purpose to enhance the economic development and the quality of life for people living in the U. S. Virgin Islands and surrounding area. The Authority is an autonomous governmental instrumentality of the Virgin Islands Government tasked with the generation/ production and distribution of electrical power and potable water to the territory’s residents. WAPA operates electric generation and water desalination units to supply utility services to St. Croix, St. John and St. Thomas. Electric service is provided to St. John, and Water and Hassel Islands, by submarine cables. Rates for electric, potable water and street light services are regulated by the Public Services Commission. Belgrave D. Stedman, Electrical Engineer II, Project Coordinator System Planning Division In early 2010, the Authority developed an ambitious 25-year plan to fully develop the distribution system on St Croix. This plan entailed an upgrade to the Richmond Substation which would serve as the starting point of a new 69kV transmission line. From Richmond, this transmission line would travel to Estate Spanish Town and connect into a second proposed substation to be known as Midland Substation. The Richmond Substation Project completed on January 7, 2012, includes a redundant air conditioned concrete switchgear building with underground cable vaults connecting concrete encased duct banks and manholes; an ABB four breaker(s) ring-bus 69kV GIS switchgear expandable to eight breakers; an Areva split-bus with nine breaker(s) 25kV arc-resistant switchgear; two non PCB oil filled 50/40/30 MVA, 69/24.9/13.2 kV three winding Siemens power transformers (T4 and T5); three-way generator manually operated transfer switches; SCADA (supervisory control and data acquisition) ready protective relays and meters; an automation system in switchgear building control room; redundant battery/rectifier systems in the battery room; redundant station service system (120/208 voltage) with pad-mount transformers; an auto transfer switch with metering; high voltage cables; two existing transformers (T1 and T3) connected to the new 25 kV switchgear and to an existing 15kV breaker and a half switchgear; connection of two existing generators (Unit 16 and Unit 20) to the newly upgraded substation; grid system with lighting protection; fire protection system; security camera system; and relay protection system with coordination This project was funded from the 2010 Electric Bonds in the amount of $12,200,000. Richmond 69/25kV Substation Upgrade continued... The benefits of moving to a transmission and distribution system from just a distribution system include: ♦ ♦ ♦ ♦ ♦ ♦ ♦ Decreased line loss on the distribution system Improved system reliability Enhanced system protection and automation Enhanced ability for future load expansion Reduction of fault current at the Richmond Power Plant Facilitating ease of interconnection by an independent power producer Establishing a foundation for a transmission system on St. Croix With the completion of the Richmond Substation, the Authority has begun the design planning stage for the proposed new 69/25kV Midland Substation Contractor Dashiell Corporation Sub-Contractors PAR Electric ● Taller Lardes ● LLC (Architect & Design) Aireko (Electrical Contractor) ● Geotechnical Survey Zenon Construction (Civil Works) ● Quality Electric ● Fortress Electric Vivot Equipment Corporation WAPA - Consultants FX Bonnes Associates, Inc. & Power System International Christiansted Electrical Underground Phase I Raymond A. Burton , Electrical Engineer II, Project Coordinator Acknowledgements WAPA Engineering Team Clinton T. Hedrington, Jr. Director Melton Smith Allyson Gregory Raymond A. Burton Belgrave Stedman Xavier Acevedo Stephen Samuel & Gregory Willocks (deceased) (technical and managerial support during the design and execution of this project) Extended WAPA Team Bliss Bully & Gina Cintron FEMA/VITEMA Team Jacqueline Heyliger Robert Moorhead Ethelbert Benjamin Leonard Gumbs Mike Foley MG Renaldo Rivera, Adjutant General Elton Lewis -Director Chlorine Generation System (MIOX) Richmond Standpipe Building Upgrade Elva Polimis, Mechanical Engineer I/Project Coordinator Acknowledgements Water Engineering Team (WET) Rupert Pelle, Director Kerwyn Augustin Clement Hewlett Hector Mercado Cara Pascal Elva Polimis Elisa St. Rose & Idealfonso Encarnacion (technical and managerial support during the design and execution of this project) Entire Water Distribution Operations and Maintenance Staff (for their patience and understanding while construction was in progress) Elisa St. Rose, Civil Engineer II, Project Coordinator Water Division The Authority was awarded $300,000 through the Drinking Water Capital Improvement Grant Program for the installation of a state-of-the-art mixed-oxidant (MIOX) chlorination generation system. The Chlorine Generation System was installed in February, 2011 to eliminate the use of calcium hypochlorite, which is potentially harmful to water plant operators, neighboring homes, schools, and businesses. Using a patented innovative technology, the chemistry is safely and cost-effectively generated on site and on demand, using just salt, water, and power. Generating fresh disinfectant on site eliminates transportation and storage of hazardous chemicals, reducing freight and ground traffic, carbon emissions, and fuel consumption The MIOX Corporation designed, installed, and commissioned the new system. The revolutionary self-cleaning VAULT™ on-site generator is the first of its kind. The mobile unit is designed for high efficiency, low lifecycle cost, durability, reliability and requires minimum maintenance. During the manufacturing phase, a site was prepared for delivery of the unit. Z and I Builders was contracted to construct the concrete pad on which the unit sits. WAPA technicians installed communication conduits, waterlines, and electrical ducts (under the direction of the System Planning Department). Technicians from Hudson Construction Company and MIOX Corporation prepared the preliminary tie-in from the unit to WAPA’s water supply system while Fortress Electric pulled the electrical cables and prepared the tie-in to the transformer. William R. Nash assisted with the installation of the air condition units and with securing the trailer to the concrete pad. Within the 18 months that the unit has been installed, the Authority has saved close to $15,000. Instead of purchasing calcium hypochlorite, WAPA now purchases bags of salt granules in order to make chlorine. The system is safer to work with, user friendly, and is mostly automated. It is also important to note that the system is portable. Everything except the oxidant tank is located inside a 40’ trailer. Therefore, the unit can be easily moved to another location, if necessary. Rehabilitation of the Richmond Storage Tank Rehabilitation of the Richmond Storage Tank Cara Pascal, Civil Engineer I, Project Coordinator Cara Pascal, Civil Engineer I/Project Coordinator Water Division Acknowledgements The Virgin Islands Water and Power Authority (WAPA) was awarded $1,690,149 through the Drinking Water Capital Improvement Grant Program for the Rehabilitation of the Richmond Tank. The 10 million gallon (MG) storage tank, the largest tank on island, was built by Chicago Bridge and Iron Company in 1967. Ownership and management of this tank along with all other components of the water distribution system were transferred from the Department of Public Works to WAPA in 1988. In 2007, Howle Engineering performed an out-of-service inspection of the Richmond Tank. It was determined that the tank had experienced extensive corrosion and was in need of structural repairs. The tank perimeter bottom plates, tank roof, tank shell plates, and all roof nozzles and man ways were in need of repair. The storage tank was upgraded by installation of a stairway, wind girder, valves, labeling, and recoating of the exterior, interior and other attachments to improve the tank. Tampa Tank, Inc. was contracted to complete the rehabilitation in 180 calendar days, however, the work was completed a month ahead of schedule and the newly rehabilitated tank was immediately placed back into service. This project also included the installation of a Variable Frequency Drive (VFD) control system in the Estate Richmond pump station and civil work to improve the storm water drainage around the base of the tank. ICS was contracted to complete the installation of the controls which was necessary for operating the Richmond pump station without the use of the 10MG storage tank, a task that has never been done before. Through the cooperative efforts of the WAPA staff and ICS, water service was provided for five months without the use of this main storage tank which accounts for nearly half of the utility’s storage capacity. Contractors Instrument & Controls System, Inc. (ICS) • Tampa Tank, Inc. Water Engineering Team (WET) Rupert Pelle, Director Kerwyn Augustin, Clement Hewlett, Hector Mercado, Cara Pascal, Elva Polimis & Elisa St. Rose (technical and managerial support) Entire Water Distribution Operations and Maintenance Staff especially Cecil Daniel and Keith Greenaway (their dedication and hard work during the draining of the Richmond Tank and throughout the course of the project) Fred Chinea- ICS, Christopher Ferreras, and Clement Hewlett (going above and beyond during the completion of the VFD Installation at the Richmond Pump Station) Kevin Smalls, Ira Bowry, Damian Marius and Sylvester Blake (management support during the coordination between water production, storage, and distribution while the tank was out of service) Special Thanks to Virgin Islands Department of Planning and Natural Resources Chlorine Generation System (MIOX) Richmond Standpipe Building Upgrade Elisa St. Rose, Civil Engineer II, Project Coordinator Elva Polimis, Mechanical Engineer I, Project Coordinator Acknowledgements Water Division Contractors Fortress Electric ● Z & I Builders ● William R. Nash VI, Inc. Parkson/Miox Corporation ● Hudson Construction Company Tony Edwards, Kevin Hoeschen and Doug Davis (cooperation throughout the entire project, sharing knowledge, and providing training to the operation staff) Water Engineering Team (WET) Rupert Pelle, Water Director Kerwyn Augustin, Clement Hewlett, Hector Mercado, Cara Pascal, Elva Polimis & Elisa St. Rose (technical and managerial support during the design and execution of this project) VIWAPA STT Staff Michael Quetel, Shawn Scotland, Roy Vanterpool (assistance with the preparation of scope of work ) Information Technology Department Dalma Simon, Julius Aubain, Vaughn Audain (For providing the necessary materials and expertise to get the communications in place from the units to the standpipe) System Planning Department Melton Smith, Belgrave Stedman, Xavier Acevedo (providing the necessary materials and expertise to get all the electrical components in place for commissioning of the units) Entire Water Distribution Maintenance and Operations Staff Keith Greenaway &Cecil Daniel (For all the preparation work that was done prior to and during the installation of the MIOX System) The Richmond Standpipe Building was built in 1968 under the proprietorship of the Department of Public Works. In 1988, ownership and management of the Richmond Standpipe Building along with all the components of the water distribution system were transferred from the Department of Public Works to the Virgin Islands Water and Power Authority. The building houses the controls for the Richmond Standpipe, Richmond Pump Station (which is an integral part of the distribution system), and office space for operations and maintenance staffs. The Richmond Standpipe Building Upgrade was developed to create additional office space and to house the newly installed control system of the Richmond Pump Station. The scope included construction of a 15’ x 15’ room, retiling of the existing interior floor, painting the interior and exterior of the building, installing new doors, new windows, energy efficient lighting, and bathroom fixtures. The scope also included installing two concrete staircases, constructing kitchen cabinets and plastering the chlorine room. Z and I Builders was contracted to complete the Richmond Standpipe Building Upgrade. This project was completed on December 1, 2011 and was funded by WAPA’s internal funds at a cost of $174,345. Contractor Z & I Builders Christiansted Electrical Underground Phase I Richmond 69/25kV Substation Upgrade Raymond A. Burton, Electrical Engineer II, Project Coordinator Belgrave D. Stedman, Electrical Engineer II/Project Coordinator System Planning The Christiansted Phase I project is part of the Water and Power Authority’s larger mitigation concept for its electrical underground system. This project has created the backbone for future projects in the Christiansted area to remove the aerial electrical system in town. This project built an electrical duct bank system from the Richmond Substation to the intersection of Prince and Fisher Streets. This project was financed through monies awarded by a Hazard Mitigation Grant in 2006 to begin the process of removing the aerial electrical system and transferring it to underground. The project is funded by several grants from the Pre-Disaster Mitigation Competitive Grant (PDM-C) Program which require a 75/25 percent cost share between the Federal Emergency Management Agency (FEMA) and the WAPA at a total cost of $3.74 million. After a lengthy permitting process, two Ground Penetrating Radar Surveys and an archeological study, construction began on September 1, 2009. General Engineering Corporation (GEC) was the contractor for the project. During construction of the project there was an archeologist on site at all times to ensure that work would stop if any artifacts were uncovered during construction until investigative historical research could be conducted. No meaningful artifacts were discovered. With the installation of underground power lines, WAPA anticipates an improvement in service reliability, quicker restoration from storms and other natural disasters and improvement in the aesthetic of Christiansted town. Construction of Phase I was completed in June of 2010 and the system has been functioning commendably. Phase II of the Christiansted Underground project is expected to begin in 2012. Contractors General Engineering Corporation (GEC) ● Fortress Electric Acknowledgements Hugo V. Hodge, Jr. Clinton T. Hedrington Jr. Huston Harrigan Executive Director and Chief Executive Officer Director of Transmission & Distribution Manager of Substation Dept. (STX/STT/STJ) Melton Smith Manager of Design & Construction (STX) Belgrave D. Stedman Project Coordinator/Electrical Engineer II Raymond A. Burton Electrical Engineer II Allyson Gregory Manager of System Planning (STT/STX/STJ) Dexter Hypolite Electrical Engineer I Xavier Acevedo Draftsman Niel Vanterpool Electrical Engineer III LeCheea Smith Electrical Engineer I Cordell Jacobs Electrical Engineer II Kevin Smalls Ira Bowry Damian Marius Sylvester Blake STX Line Department STX Water Department STX Customer Service STX Revenue Assurance Department STT Substation department STX Plant Superintendent STX Plant Operations Manager STX Plant Maintenance Manager Operations Supervisor STX