Colorado Government Officials Briefing

Transcription

Colorado Government Officials Briefing
Agenda
Kiewit-Turner a Joint Venture
Project Progress
Small Business Goals/Performance
K-T Job Fair
Project Website
Who is Kiewit-Turner a Joint Venture?
Joint venture between Kiewit Building Group
and Turner Construction Company.
We joined forces as Kiewit-Turner a Joint
Venture for the Replacement Medical Center
Facility, Eastern Colorado Health Care
System.
Project progress
Awarded Preconstruction
August 2010
Awarded Renovation
April 2011
Award of Construction
Nov. 11, 2011
Construction Documents
Q2 2012
Construction Completion
Q2 2015
VA Activation / Move In
2015
Project progress
Mass excavation
January 2012
CBS 4th floor
complete
Wheeling St
In-progress
Tower cranes 1&2
Q2 2012
Subsequent floors in CBS
Q2 2012
Tower crane 3
Q3 2012
Project Progress
80 drilled piers out of 1,226 total
= ~6.5% complete
264,431 cubic yards of soil excavated
= ~18,888 truck loads!
CBS Project Progress
CBS Project Progress
CBS Project Progress
CBS Project Progress
Project Progress - CBS
A view from above
Project Progress – Demo
Project Progress – Demo
Project Progress - DAT
Project Progress - DAT
Project Progress - DAT
Project Progress - DAT
Project Progress - PVS
Project Progress - PVS
Project Progress - IBS
Project Progress - IBS
Project Progress - IBS
Project Progress - IBS
Project Progress - IBN
Project Progress - ENC
Project Progress - ENC
Project Subcontracting Goals
Subcontracting Plan:
Planned / Goal
To Date
Pending
Totals
Small Business
Subcontract
Value
$395m
$80m
$290m
$370m
SBA
%
28.7%
83.2%
59.2%
64.4%
SBA
$’s
$133m
$66m
$171m
$238m
Project Subcontracting Goals
Subcontracting Plan:
Planned / Goal
To Date
Pending
Totals
SDVOSB
Subcontract
Value
$395m
$80m
$290m
$370m
SDVOSB
%
15%
41.6%
20.7%
25.2%
SDVOSB
$’s
$59m
$33m
$60m
$93m
Project Subcontracting Goals
Subcontracting Plan:
Planned / Goal
To Date
Pending
Totals
VOSB
Subcontract
Value
$395m
$80m
$290m
$370m
VOSB
%
20%
41.9%
33.1%
35%
VOSB
$’s
$79m
$33m
$96m
$129m
Project Subcontracting Goals
Subcontracting Plan:
Planned / Goal
To Date
Pending
Totals
SDB
Subcontract
Value
$395m
$80m
$290m
$370m
SDB
%
5%
9.2%
11%
10.6%
SDB
$’s
$20m
$7m
$32m
$39m
Project Subcontracting Goals
Subcontracting Plan:
Planned / Goal
To Date
Pending
Totals
WOSB
Subcontract
Value
$395m
$80m
$290m
$370m
WOSB
%
5%
2.3%
16.4%
13.3%
WOSB
$’s
$20m
$2m
$47m
$49m
Project Subcontracting Goals
Subcontracting Plan:
Planned / Goal
To Date
Pending
Totals
HUBZone
Subcontract
Value
$395m
$80m
$290m
$370m
HUBZone
%
3%
0%
0%
0%
HUBZone
$’s
$12m
$0m
$0m
$0m
K-T VA Job Fair
March 23, 2012
– 9a – noon
– APS, Professional Learning Convention Center
• 15701 East 1st Ave, Aurora, CO
The purpose of this job fair was to provide veterans and Coloradans
an opportunity to work on the new Replacement Medical Center
Facility (aka new VA Hospital). We had representatives from
subcontractors and non-profits ready to assist interested attendees
in finding employment.
Participants
Autocon Incorporated
Axxess Connect
Bergelectric Corp.
C & B Plumbing
Cole Construction
Colorado Window Systems
Empowercon
Faith Enterprises
GCH Construction
Horizon Glass
JE Hurley Construction
Oldcastle Precast Inc
Permasteelisa
RK Mechanical
Rocky Mountain Excavating, Inc.
Rocky Mountain Prestress
Siemens
Terracon Consulting Engineers
Tusca Inc.
Veterans Green Jobs
Over 150 attendees
Participants
www.denvervahospital.com
Thank you
W. Celeste Davis, CPSM
Public Information Officer
Replacement Medical Center Facility
Eastern Healthcare System
720-202-6153 mobile
[email protected]