Fall 2013
Transcription
Fall 2013
Fall 2013 Columbia University Page 7 In This Issue: Cover Story 7 Columbia University Phase 2 work is moving into the final stages 3 NYU Medical Center Comeback work was completed at the end of June 4 Bronx River Parkway ! Overall completion of the project is slated for Spring 2015 5 7th/8th Ave Vent Plant 7th Avenue excavation is complete and prep work for the main excavation continues 9 2nd Avenue Subway Completion of Contract 2A expected by the end of September 10 Bronx Whitestone Bridge The replacement of the ! ! Queens approach to be finished October 2014 11 Through the Pipeline E.E. Cruz & Company, Inc. 32 Avenue of the Americas New York, NY 10013 www.eecruz.com Tel: 212-431-3993 Cruz News is a quarterly publication by E.E.Cruz and Company, Inc. Please direct comments and suggestions to Michelle Reiser at 212-431-3993 or [email protected] Letter from the President Dear Friends and Fellow Employees of E.E. Cruz: I am writing this message to you just a few days before Labor Day and I am sure many of us are sharing the typical feelings that come with the end of summer. In a matter of days our families will be out of vacation mode, kids will return to school, we’ll close up our swimming pools and beach houses, and the days will get shorter and cooler. As fall sets in, we’ll have time to remember beach weather and summer vacations and look ahead to crisp autumn air and football season. For construction people, this time of year means looking at the near term to get as much productive work accomplished as we can while the weather cooperates. I know you are all working hard in the field, in our shop, and in our offices to make that happen. We can look back at a season of exciting progress at all of our project sites: the Whitestone Bridge, 7th and 8th Avenue Vent Plant, Bronx River Parkway, Columbia Manhattanville, and the Second Avenue Subway 2A/ 2B. Work is proceeding on or ahead of schedule and we can all be proud of what we Joe Malandro have accomplished to date this year. Revenues in 2013 have exceeded any previous year. Our backlog of work remains strong. The season ahead looks encouraging as well. Estimating is tracking a number of substantial projects due for bidding in the next several months and we will pursue all opportunities aggressively. We have started a new Business Development department that is exploring possibilities for work outside our traditional New York/New Jersey markets. Our Marketing Department is completing work on a revamped E.E. Cruz website. And you may have noticed that we have revived our old logo that emphasizes our capabilities as a company of both contractors and engineers. Difficult economic conditions continue to hound the construction industry, and we expect competition to remain very tough for new business. It is especially difficult to compete against numbers that are at or below our estimate of the cost of the work. Be assured that our estimators are up to the challenge. In 2013, we have bid over $800 million worth of work and have consistently been in the upper third of bidders. The quality of our estimates has been and will remain high, and I am confident that will serve us well in our pursuit of new work. As always, I will close by thanking all of you for your hard work and dedication to E.E. Cruz. In recent weeks I have made some time to visit the projects and plan to make a habit of doing that more often. (Those of you who know me a long time know I’d rather be in work boots than dress shoes). Work safe, be well and enjoy the rest of your summer. Joe Malandro August 2013 Page 2 NYU Medical Center At the end of January, E.E. Cruz de-mobilized from the NYU Medical Center site upon completion of the concrete and waterproofing work at the MSB shell space. In June, E.E. Cruz remobilized to the site in order to perform comeback work that was required after the construction hoist was removed. The hoist had been used to build the elevator tower superstructure. This work involved completing the foundation walls, finish slab, and drainage layer in the shell space adjacent to the new elevator tower. In order to cut back the schedule and avoid bringing in formwork, we employed our shotcrete subcontractor to return and finish the remaining foundation walls. We also installed the formwork and concrete for the new Con-Edison duct banks along the north wall of the MSB shell space and subsequently completed backfilling per the contract requirements. The comeback work concluded on June 21st, and E.E. Cruz again demobilized all tools and equipment from the site on June 24th. Currently, we are working towards closing out the job. Thank you to the crew and management team for their hard work and diligence in the culmination of challenging job. by Dan Wortley, Field Engineer Rebar and scaffolding in place for shotcrete operation Mesh, drainage stone and pipe installed prior to pouring finish slab Page 3 Bronx River Parkway Work at the Bronx River Parkway has continued throughout the spring and summer. At the time of our last update, E.E. Cruz had prepared and submitted a value engineering package to the owner revising the MPT traffic pattern from Stage 1 to Stage 3. The owner has since accepted the proposed revision and traffic has now been reconfigured making additional work available and eliminating the requirement of temporary shoring at Piers 1, 2, and 3. The footing for Pier 6 has been completed, and concrete for the pier and anchor bolts for the core steel have been cast. Stage 1 of the Pier 4 footing has also been completed. The cofferdam for Pier 4, Stage 2 is installed, excavation complete, and mud mat placed. Currently we are installing rebar and formwork for the second half of the Pier 4 footing. Pier 4 is Pier 6 formwork by Frank Spinozza, Assistant Project Manager Pier 4 Stage 1 footing/reconfiguring cofferdam for Stage 2 construction scheduled to be completed in early September. The cofferdam for Pier 5 has been installed and concrete for the footing has been placed. Formwork and rebar for the pier and installation of the anchor bolt template is underway. Piers 4, 5, and 6 will be ready for core steel by the middle of September. EEC’s in-house engineering team has completed the design of cofferdams for Piers 1 and 2. Construction of the cofferdam for Pier 2 is underway. Pier 1 cofferdam is anticipated to begin in early September. Several subcontractors have recently mobilized to the site including Moretrench, currently installing 62 micropiles required for the south abutment. Underpinning mobilized in June and has completed the installation of the secant piles required for the west abutment and wall 3 of Pier 2. American Bridge is continuing with their efforts to complete the fabrication of Pier 4, 5, and 6 core steel and arches. First delivery of core steel is anticipated for the end of September. Additionally, Granite Works began removing stone from the existing bridge, cleaning, and reinstalling stone on the face of the middle abutment. Currently, Verde Electric and Mohegan Associates are procuring material to complete the pedestrian bridge. Following completion of the secant piles installed by Underpinning, EEC began excavation to install the west abutment pile cap. The footings and piers for the pedestrian bridge have also been completed and the precast planks have been set. Construction of the south abutment footing and walls will begin in the fall. The overall completion of the project is slated for the spring of 2015. Page 4 7th / 8th Avenue Vent Plant by Paul Connolly, Project Manager Since our last update, E.E. Cruz has made significant progress, transitioning from preparatory activities into the more substantial aspects of the project. The permeation grouting program adjacent to the 59 Greenwich building was completed, and was followed immediately by the mobilization of our secant pile sub, Underpinning & Foundation Skanska (UFS.) Despite the extremely limited working area and difficult access conditions, UFS’s crews worked efficiently and were typically able to complete over two piles per shift, enabling them to finish all of the piles in less than two months. Unloading 52’ core beams to be placed in secondary secant piles Secant pile operations taking place on Vent Plant site and relocation of steam line taking place on 7th Avenue Another milestone achieved was the relocation of the 24” steam main on 7th Avenue. As this work progressed, E.E. Cruz forces worked inside the same trench used by our utility sub, enabling us to start work on the support of excavation and decking system for the 7th Avenue flue structure. Performing this work concurrently with the steam line relocation allowed us to recover a significant portion of the scheduling delays that were experienced during the pipe re-location work itself. These delays were caused by the discovery of asbestos in and around the pipe, as well as Con Edison’s directive to replace an additional 30’ of the existing pipe due to its age and condition. Page 5 Immediately upon backfilling of the new steam line housing, E.E. Cruz began the installation of the decking beams and precast panels working from the middle of 7th Avenue toward the vent plant. The first two sections advanced quickly but, as expected, the pace slowed when we reached the last section adjacent to the curb line. In this location, a maze of utilities is present, not to mention the existing vent structure atop the subway tunnel roof, which must be demolished and slabbed over to allow the decking system to be installed. This work is ongoing and when completed, we will mobilize Moretrench to the site to begin the installation of the jet grout columns located alongside the tunnel walls at Installation of deck beams and roadway panels for 7th Avenue SOE system Installation of lateral braces between deck beams for 7th Avenue SOE system both 7th and Greenwich Avenues. In the meantime, work progressed well on the reconstruction of the Greenwich Avenue sidewalk vents, which is now approximately 80% complete. Some of the vents on 7th Avenue were finished during this period as well. In the tunnels, we worked several weekend G.O.s to accomplish a variety of tasks including the installation of demo shields as well as steel column strengthening work. Our electrical sub, Kleinberg Electric made use of the G.O.s as well, using work trains to run conduit to the future damper locations in the vent bays along 7th Greenwich Avenues. Page 6 Columbia University by Matthew Prpich, Project Engineer MBB-SC2 Slab Much progress has been made at the Columbia University project since our Spring Cruz News update. Under the watchful eye and constant motivation of Patrick Roach, General Superintendent, work on Phase 1 is proceeding at a fevered pace. The available work at grade has been completed, leaving limited quantities of grade beam waterproofing and backfill/restoration remaining. Access to these areas is provided by the General Contractor. Site dewatering, in support of the top down excavation, has ramped up to three shifts running seven days a week. Ground water elevations have been successfully drawn down below the total depth of excavation with requisite monitoring and reporting ongoing. Excavation of the topdown SC2 level (Stages 5 & 6) has been completed throughout the MBB (Mind Brain Building) and CEP (Central Energy Plant) areas. Mud mat and slab placement for the MBB side of the excavation is finished while 75% of the mud mat and slab has been placed for the CEP side. The remaining section of SC2 slab for the CEP has been put on hold to facilitate construction of an access ramp down to the final SC4 level where excavation is ongoing. ECN JV has assumed responsibility for concrete slab placement from Artisan as well as the balance of their work scope. Pressure washing, grinding, chipping and patching of the exposed slurry panels is nearing completion for the SC2 level, opening the door for Restor to mobilize on August 18th and begin waterproofing. The extensive air monitoring and ventilation plan, discussed in the Spring issue of Cruz News, has continued with great success. The real-time detection of elevated VOC (Volatile Organic Compounds) levels within the SC4 excavation allowed for immediate steps to insure worker safety. In addition, the increased application of Rusmar foam has been successful in suppressing odor from the impacted soil. Page 7 Looking forward, Phase 1 will complete excavation of the MBB-SC4 level utilizing the access ramp. Once the MBB excavation is complete, the SC2 closure slab will be placed and excavation will continue utilizing a “Glory Hole” and tunneling under the CEP-SC2 slab. Not to be outdone by Phase 1, the Phase 2 team lead by Al Bonura, Superintendent, is moving into the final stages. Slurry wall panels are 87% complete with over 178,000SF excavated and only 12 panel pours remaining. The Hydrofraise has demobilized from the site and two clamshell buckets will be utilized for the balance of the excavation. Work on Phase 2 slurry walls is on schedule to conclude September 16th. The upcoming restoration and re-opening of 131st Street is an important milestone in Phase 2. Once achieved, it will allow for the closure of 130th Street and provide access to several of the final panels located within the roadway. Restoration of the sidewalks and roadway is ongoing with an anticipated end date of August 21st. Pressure grouting is currently 90% complete with a mere 13 of 126 holes remaining. Finalization of the grouting activity will occur after access is attained with closure of 130th Street. Excavation Access Ramp Restoration of 131st Street Page 8 2nd Avenue Subway by Tiago Rodrigues and Tien Tran, Field Engineers At Gridline 37 looking north at the tie-in of the station to the existing 99-105th Street tunnel (ca.1970’s). Once abated, the sheeting was pulled and bulkhead demolished. An invert slab was then poured followed by shotcrete and waterproofing on the secant pile wall. Below 2nd Avenue, the E.E. Cruz/Tully JV is focusing its operations on concrete in building the station from the invert up to street level. This consists of a platform level, mezzanine slab, and roof slab. It is now possible to walk underneath 2nd Avenue from 105th to 87th Street…. that’s almost a MILE! At the existing north tunnel, over 2000 cubic yards of concrete has been poured and 63,000 linear feet of FRE conduit has been installed within the 1800 LF of high and low benches. Since the last update, the lead abatement and demolition have been completed and the CTJV is preparing the area for the turnover to the follow-up contractor. This area will be used as a storage area for track rail and cable. The columns in the existing tunnels have been primed and fireproofed thus allowing our masonry subcontractor to install the 6” CMU wall along the center of the tunnel. A northbound and southbound track has been established. Upon completion of the asbestos abatement at the 99th Street bulkhead, the CTJV was able to pour the northern most invert slab as well as a section of the roof. Moving south, scaffolding has been erected so that carpenters, lathers, and subcontractors can prepare the mezzanine slab. Currently, 4 of the 22 mezzanine slabs in the main tunnel have been placed and the team is aiming to continue with two mezzanine slabs poured each week. Once the concrete has reached design capacity, our crews can begin removing the Tier 3 temporary struts and wales in anticipation of pouring the roof slabs scheduled for the end of the year. Since the last update, all the invert slabs at Ancillary 1 have been poured and the secant pile dividing wall has been demolished. Waterproofing for the outside walls can begin and will be followed by rebar installation. At Entrances 1 and 2, crews are preparing for invert slabs that will tie into the mezzanine slab in the mainline. At Entrance 3, the CTJV has hired a subcontractor to drill and wire saw the slurry wall into knockout panels measuring 4’ by 10’. Cutting the wall into blocks makes it easier to manage although some blocks will weigh nearly 34,000 lbs. At the south tubes, work has been nonstop in efforts to meet our September 15th deadline to turn the area over to the Track, Power, and Communication contractor. All plumbing, electrical, and concrete work in the west tube is complete. In the east tube, crews have placed 1/3 of the high benches and installed all FRE conduits. Our plumbing subcontractor will follow with hanging the pump car manifold and dry fire stand pipe. As of this update, the only remaining work on Contract 2A will be at Rainbow Hardware. The CTJV expects to finish this by the end of September. Crews, in the meantime, will continue to focus on all remaining punch list items. The project team has shifted focus to the second contract without losing sight of reaching substantial completion for 2A. We look forward to building a roof above our heads as the winter arrives. Page 9 The Bronx-Whitestone Bridge Since our last update, the E.E. Cruz/Tully JV has made great advances at the BronxWhitestone Bridge. In April, the concrete deck for stage 1B was finished followed by the temporary shoring system for the existing bridge, completed in early June. Once the shoring system was in place, demolition of the existing bridge began and new girders and cross frames were erected for stage 2A/3. The CTJV then prepared for the new concrete deck which was placed in August. Upon completion of the concrete deck and parapet in stage 2A/3, the CTJV will reconfigure the existing traffic pattern and resume demolition of the existing bridge in stage 2B. This demo work is scheduled to be finished in October. The new girders will be erected Bolt up cross frames Stage 2A by Dave Busick, Project Engineer Erecting new girders immediately after demolition, followed by construction of the new concrete deck in stage 2B. Work on stage 2B is scheduled to conclude in November. Staged construction of the BronxWhitestone Bridge will continue into 2014 with the removal and replacement of the entire Queens approach slated to culminate in October 2014. In addition to the demolition and construction of the Queens approach, installation of the new methyl methacrylate protective polymer slurry overlay was finished in June. Substantial completion of the project is anticipated for January 2015. Page 10 Through the Pipeline Employee Profile Profile of Amir Mousa by Valerie Rodriguez Tell us a little bit about your background. I am a graduate of Bagdad University’s School of Engineering with a Bachelor’s of Science degree in Engineering and I obtained my Masters from the City University of New York in Structural Engineering. Prior to E.E. Cruz, I worked for Weidlinger Associates for 17 years in their Bridge Department where I was responsible for the rehabilitation design of all of the eight suspension bridges in New York City (George Washington, Brooklyn, Manhattan, Williamsburg, Whitestone, Throgs Neck and Verrazano bridges). I also handled the rehabilitation design of suspension bridges around Philadelphia and Pittsburg including the Ben Franklin, Walt Whitman and South 10th Street bridges. After years of working on bridge design, I accepted the offer from Joe Malandro to join E.E. Cruz as Chief Engineer and establish a design group. As Chief Engineer for E.E. Cruz, what exactly does your work entail? As Chief Engineer and member of the design group, I am responsible for resolving the design issues that arise during our current projects. For example, calculations were prepared and submitted to the structural design department at the NYC Transit Authority/MTA to eliminate the need to reinforce some of the subway tunnel columns along 8th Avenue as was shown in the Emergency Vent Plant contract drawings. Additionally, design calculations and drawings were also prepared to build and install a temporary platform/ramp for equipment access into the existing subway tunnel at 102nd Street for the 2nd Avenue project. The design group also reviews design calculations and drawings prepared by our design subcontractors including the SOE design work on the Emergency Vent, the demolition and erection staging at the Bronx Whitestone project and Shaft 95 remediation at Columbia University. Most of the time, these reviews result in design revisions that are effective, safe and economical. Additionally, we prepare design calculations and drawings for temporary support work, support of excavation, rigging, demolition staging and safety measures. Furthermore, I am proud to announce that the design group has created a thermal and cooling system for mass concrete on all our current jobs. If you’re not at work, where are you? During the summer months, I enjoy time with my wife and two sons, ages 20 and 11. During the Fall and Spring I am an adjunct professor at the City College of New York where I teach structural and design courses at the undergraduate and graduate levels. Last fall, I began teaching PE review classes in structural subjects at the School of PE on several weekends in New York, New Jersey and Georgia. Any additional thoughts? I am very impressed by the challenging nature of our heavy construction jobs as well as the hard-working and collaborative nature of E.E. Cruz. I am equally impressed with the progress we have made with establishing a Design group at E.E. Cruz. We have substantially increased our capabilities and have purchased software to make our work more efficient. These programs include Mathcad for preparing processional design calculations, SAP 2000 computer code for structural modeling and analysis and DeepXcav for support of excavation design. Page 11 Through the Pipeline John Benas New Employees Brian Sacks Chuck Stewart is a Field Engineer on the 2nd Avenue Subway Project. He graduated from The College of New Jersey in May with a degree in Civil Engineering. While in school, Chuck played football and enjoyed playing golf in his spare time. He also enjoys snowboarding and going to the beach with friends. John Benas is an Estimator in the New York Office. He graduated from Roger Williams University in Rhode Island with a B.S. in Civil Engineering this May. John currently resides in Harrison, NY. Matthew Prpich Matt Prpich is a Project Engineer on the Columbia University Project. Matt recently relocated from Florida and is excited to join the E.E. Cruz team. His hobbies include hunting, fishing, camping, and hiking. Chuck Stewart Brian Sacks is a CPM Scheduler at the 2nd Avenue Subway Contract 2B. He is a native New Yorker and grew up in Huntington, Long Island. Brian graduated from the University of Maryland College Park in 2004 with a B.A. in Economics. Prior to joining E.E. Cruz, Brian worked as a Project Engineer for Slattery Skanska, a Cost Engineer for Turner Construction, and a CPM Scheduler at a scheduling firm in Irvine, California and his father’s company Sacks and Son Construction Co. Brian enjoys snowboarding out west, where he travels each year with his father and sister. He also enjoys concerts, camping, and anything outdoors. Brian currently resides in Astoria, NY and has two cats, Smokey and Squirt. E.E. Cruz & Company, Inc. welcomes you to our team! Page 12 Through the Pipeline Awards, Honors, and Certifications The Moles organization has elected Officers and Committee Members for 2013-2014 including four individuals from EE Cruz! • Joe Malandro: President • Charlie Montalbano: Member of the Membership Committee • Jack Tobin: Vice Chair of the Education Committee • Jeffrey R. Cruz: Member of the Program Committee • • • Thank you for your continued support to the construction industry. The Boys & Girls Club of Metro Queens will be honoring Joe Malandro at their Annual Dinner on Wednesday, October 23rd. Congratulations to Joe for being recognized for his dedication to the community. OSHA Region II held a voluntary 2013 Safety Stand Down throughout New York and New Jersey. The E.E. Cruz / Tully JV in Queens participated with a review of Falls in Construction. In 2010, there were 264 fall fatalities in construction out of 774 total fatalities. These deaths are preventable. During the Stand Down, an array of fall protection, proper construction, inspections, and limitations were reviewed to empower employees to protect themselves in any situation. Employees took time to evaluate their individual operations and identify potential fall exposures. The Safety Stand Down proved not only beneficial to this team but also a great review for all E.E. Cruz employees. This awareness is a crucial step in preventing workplace injuries. The United States Department of Labor Occupational Safety and Health Administration recognizes the employees and managers of E.E. Cruz / Tully Construction, JV, Queens, NY for participating in the OSHA Region II 2013 Stand-Down for Preventing Falls in Construction July 1, 2013 __________________ Robert D. Kulick Regional Administrator Congratulations to Safety Manager Clayton Heitz for receiving the accreditation of Certified Safety Professional (CSP) on June 10, 2013. Thank you for your commitment to safety on the job. New additions Bill Tyson and his wife Ginny welcomed their first grandchild on July 29th in Tokyo, Japan! Their grandson Liam Ayuzawa was born two weeks early to daughter Kristine and her husband Hisashi. Liam weighed 6lbs, 1oz and was 19.5” long. Best wishes to the entire family! Page 13 Through the Pipeline E.E. Cruz vs. Columbia / Lend Lease Softball Game This summer, E.E. Cruz participated in its 2nd E.E. Cruz vs. Columbia/Lend Lease softball game at Columbia University’s Baker Field Complex. This year, John Benas, Dan Cocco, Rui DaSilva, Nick Dukleski, Lenin Gonell, Jimmy Hilas, Dan Mallen, and Ed White represented E.E. Cruz. E.E. Cruz beat Columbia/Lend Lease 12 to 10. Highlights included Rui’s 8 for 8 at the plate, Jimmy’s RBI triple, Dan Mallen’s outfield defense, John’s cannon arm, and Nick’s slick fielding at shortstop. The play of the game was Rui’s barehanded grab of a ball up the middle and jumping throw to first base a la Derek Jeter. Ed White Jimmy Hilas and Rui DaSilva Nick Dukleski Page 14 E.E. Cruz & Company, Inc. 32 Avenue of the Americas 13th Floor New York, NY 10013 www.eecruz.com Bronx-Whitestone Bridge Page 10
Similar documents
Spring 2014
roadway elevation. Backfilling will continue throughout the next few weeks along with the installation of the drainage. ! E.E. Cruz has continued with the installation of the
More information