CAPM Certification

Transcription

CAPM Certification
Certified Associate in Project Management
Sample Questions
Herbert G. Gonder, PMP
Oliver F. Lehmann, PMP
CAPM® Test Questions
th
Test Version based on PMBOK® Guide 4 Edition
Questions in the real exam:
Scoring questions:
Non-scoring questions (pre-test):
150
135
15
Questions in this prep test:
162
______________
Your result:
correct answers
______________
…
…
Prep test passed:
Prep test not passed:
Prep test questions provided by:
Contact:
CAPM® Credential
Handbook:
(121 or more)
(120 or less)
Oliver F. Lehmann, PMP
www.oliverlehmann.com
www.pmi.org/PDF/pdc_capmhandbook.pdf
Contents:
Questions: ........................................ Q - 1 to Q - 88
Answers: ............................................. A - 1 to A – 5
© Oliver F. Lehmann, PMP
Munich, Bavaria, Germany
www.oliverlehmann.com
This document may be freely distributed and the questions may be used in other materials as long as
this copyright attribution remains unchanged.
CAPM® Preparation
Certified Associate in Project Management
Sample Questions
CAPM Certification
Herbert G. Gonder, PMP
Oliver F. Lehmann, PMP
Chapter 1 – Introduction
4%, PMBOK Guide pages 3 - 14
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-1
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Introduction
A Project is…
a) …an ongoing endeavor to create repetitive products, services, or
results.
b) …a unique service undertaken to create a temporary product or
result.
c) …a unique endeavor undertaken to create a temporary product,
service, or result.
d) …a temporary endeavor undertaken to create a unique product,
service, or result
CAPM Certification
Introduction
What is true for the types of work in an organization?
a) The purpose of a project is to achieve its objective and then to
end.
b) The purpose of a project is to attain its objective and then to
obtain another one.
c) The purpose of a project is to constantly sustain the business.
d) The purpose of ongoing work is to conclude when its specific
objectives have been attained.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-2
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Introduction
The Project manager is the person…
a) …assigned by the performing organization to achieve the project
objectives.
b) …responsible for meeting the organization’s strategic goals.
c) …responsible for an organization’s level of profitability.
d) …responsible for an organization’s overall productivity.
CAPM Certification
Introduction
A Program is…
a) …a group of related projects managed in a coordinated way.
b) …a project for which earned value management is used.
c) …projects grouped together to facilitate effective management of
their work to meet business objectives.
d) …a way of effectively handling change control in a group of related
projects.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-3
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Introduction
The areas of expertise that a project manager should at least
master does not include
a) General management knowledge and skills
b) Attitudes and leadership
c) Knowledge about project management
d) Tools for operational optimization
CAPM Certification
Introduction
Enterprise environmental factors includes all of the following
except
a) Organizational culture
b) Political climate
c) Physical environment
d) Work authorization system
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-4
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Introduction
A PMO (Project management office) is an organizational unit
to…
a) …centralize and coordinate management of projects under its
domain.
b) …ensure proper payment of acquired project human resources.
c) …ensure customer satisfaction during the handover of
deliverables.
d) …manage sub-project work under the domain of the project
manager.
CAPM Certification
Introduction
The Project manager is the person
a) Assigned by the Performing organization to ensure that the
project meets the strategic plan goals.
b) Assigned by the Performing organization as the project’s quality
expert.
c) Assigned by the Performing organization as the project’s technical
expert.
d) Assigned by the Performing organization to achieve the project
objectives.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-5
www.oliverlehmann.com
CAPM
CA
CAPM
P Certification
Cer
e ti
t ffiica
c tion
CAPM® Preparation
Chapter 2 – Project Lifecycle and Organization
4%, PMBOK Guide pages 15 - 33
CAPM Certification
Lifecycle and Organization
Projects and operations share the following characteristics
EXCEPT:
a) Both are performed by people.
b) Both are ongoing and repetitive.
c) Both are constrained by limited resources.
d) Both are performed to achieve organizational objectives.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-6
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Lifecycle and Organization
The Project life cycle…
a) …documents the costs caused by the project at certain point in
time.
b) …is presales, project execution, product handover and
documentation.
c) …is a technique especially for extreme programming and agile
project management.
d) …is a collection of sequential or overlapping Project phases.
CAPM Certification
Lifecycle and Organization
At the start of the project the level of uncertainty…
a) …is highest and decreases over the life of the project.
b) …cannot be predicted unless the Project charter has been signed.
c) …is lower than at the end of the project.
d) …similar to the level of uncertainty at the end of the project.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-7
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Lifecycle and Organization
The ability of the stakeholders to influence the project…
a) …is always due to the soft skills of the project manager.
b) …is highest at the start and gets progressively lower as the project
continues.
c) …does not change over time unless a change request has been
initiated.
d) …remains constant over the entire running time of the project.
CAPM Certification
Lifecycle and Organization
A Project phase is characterized by…
a) …a ringing bell at the moment of final completion.
b) …the instruction email of the managing director.
c) …the completion and approval of one or more deliverables.
d) …reaching the predicted milestone in your project plan.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-8
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Lifecycle and Organization
The sequence of phases in a project life cycles is…
a) …often a basis for project governance.
b) …necessarily sequential.
c) …necessarily overlapping.
d) …necessarily iterative.
CAPM Certification
Lifecycle and Organization
What is true for Stakeholders of a project?
a) All stakeholders belong to the performing organization.
b) The project team is not regarded as a key stakeholder.
c) Identifying stakeholders can be difficult but critical.
d) The sponsor of the project is not regarded as a key stakeholder.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q-9
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Lifecycle and Organization
Projectized organizations…
a) …are those whose most resources are involved in project work.
b) …usually lack skills and competence in project management.
c) …usually have a strong hierarchically built functional organization.
d) …give usually weak authority to their project managers.
CAPM Certification
Lifecycle and Organization
Which of the following is NOT typical for Weak matrix
organizations?
a) The project managers role is part-time.
b) The project managers authority is high.
c) Resource availability is limited.
d) The project managers authority is limited.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 10
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Lifecycle and Organization
What is true on organizational cultures and styles?
a) They should be influenced by software that helps draw GANTTCharts and PERT Networks and calculate Earned value.
b) They are mainly reflected in the schedule, which the project
manager explains to team members in weekly review meetings.
c) They are emanating from the range of incentives and bonuses,
which project team members will receive at the end of the project.
CAPM Certification
d) Cultures and styles may have a strong influence on a project’s
ability to meet its objectives.
Chapter 3 – Project Management Processes for a
Project
11%, PMBOK Guide pages 35 - 65
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 11
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
In order for a project to be successful, it is usually NOT
necessary for a project team to…
a) …use a defined approach required to meet the project objectives.
b) …buy highly sophisticated project management software and train
project team members in its application.
c) …comply with the requirements to meet the stakeholder needs
and expectations.
d) …balance the competing demands of scope, time, cost, quality,
resources, and risk to produce the specified product.
CAPM Certification
Processes for a Project
Project management is the application of…
a) …specific project management software in an enterprise
environment.
b) …motivational and developmental techniques to team-members
and other stakeholders.
c) …the chain of command in order to ensure timely completion of
all project activities.
d) …knowledge, skills, tools, and techniques to project activities to
meet project requirements.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 12
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
The five Project management process groups are:
a) Planning, auditing, directing, monitoring, and closing.
b) Selling, planning, staffing, executing, and documenting.
c) Initiating, planning, executing, monitoring and controlling, and
closing.
d) Initiating, executing, controlling, reviewing, and closing.
CAPM Certification
Processes for a Project
A process is …
a) …a legal act where project managers are blamed in court for
material or repudiatory breach of contract.
b) …a set of interrelated actions and activities performed to achieve a
pre-specified product, result, or service.
c) …something mystical which is comprehensible only to well-trained
experts from the project management disciple.
d) …something that cannot be explained without a sound
understanding of standardized project phase models.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 13
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
What is true for Project management processes?
a) They are limited to the processes of design, development,
deployment and maintenance.
b) All processes described must always be applied uniformly in all
projects without tailoring.
c) The project manager is responsible for determining which
processes are appropriate for the project.
d) They are fully independent of the Product-oriented processes that
may also be part of the project.
CAPM Certification
Processes for a Project
The purpose of the Project management processes is to…
a) …initiate, plan, execute, monitor and control, and close a project.
b) …safe as much money of the customer as possible.
c) …please the stakeholders and sponsors.
d) …show the project manager that he is in charge.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 14
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
The PMBOK Guide presents the project management processes
as...
a) ...discrete elements with well defined interfaces.
b) …stochastic elements with well defined interfaces.
c) ...unique black elements of process control graphs.
d) ...scatter diagrams and process flow charts.
CAPM Certification
Processes for a Project
The application of Project management processes is...
a) ...only done at the beginning of a project when not much
knowledge is available.
b) …only done by project managers without experience and standing
in the organization.
c) ...recommended but not necessary unless the management
requires it.
d) ...iterative and many processes are repeated during the project.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 15
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
Project Management processes and product-oriented
processes...
a) ...are both fully described in the PMBOK Guide, 4th edition.
b) …overlap and interact throughout the life of a project.
c) ...do not show any differences.
d) ...are not described up to now.
CAPM Certification
Processes for a Project
On each project the Project management process groups are...
a) ...usually performed in a random sequence or not at all.
b) …are guides for applying appropriate project management
knowledge and skills during the project.
c) ...performed in a very specific sequence decided in alignment with
the progress of the current project phase.
d) ...performed in a sequence determined by the key stakeholder.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 16
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
What is true for Project management process groups and
Knowledge areas?
a) The Project quality management Knowledge area includes most
processes.
b) The Monitoring and controlling Process group includes most
processes.
c) Each process is an element of exactly one Process group and one
Knowledge area.
d) Process groups are another term for Project phases and should
thus be done in sequence.
CAPM Certification
Processes for a Project
The Process group that provides feedback to implement
corrective or preventive action is:
a) Testing
b) Planning
c) Executing
d) Monitoring and Controlling
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 17
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
In multi-phase projects, the processes defined in the process
group would be...
a) ...done only once during the whole project.
b) ...normally repeated for each phase.
c) ...done only in the early phases.
d) ...done only in fixed price contracts.
CAPM Certification
Processes for a Project
The Closing Process group consists of those processes...
a) ...performed to finalize all activities across all Project management
process groups to formally complete the project, phase, or
contractual obligations.
b) ...that signal to the team may come together again and have a
night together at a post mortem project barbeque.
c) ...that support advertising of the product in order to let everyone
know how successful and efficient the team worked.
d) ...that reward the customers for their investment, the patience
with the team and the preparation to support change control.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 18
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
The processes of which Process group are often done external
to the project‘s scope of control?
a) Planning
b) Testing
c) Initiating
d) Executing
CAPM Certification
Processes for a Project
Which document formally authorizes the project?
a) Project scope statement
b) Project charter
c) Work breakdown structure
d) Cost management plan
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 19
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Processes for a Project
The Project scope statement is the primary output of which
process:
a) Define Scope
b) Verify Scope
c) Create WBS
CAPM Certification
d) Define Activities
Chapter 4 – Project Integration Management
11%, PMBOK Guide pages 71 - 102
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 20
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
The Knowledge area of Project Integration Management
includes the project management processes:
a) Define Activities, Create WBS.
b) Develop Project Charter, Define Scope.
c) Collect Requirements, Define Activities.
d) Develop Project Charter, Close Project or Phase.
CAPM Certification
Project Integration Management
Which process uses Expert judgment?
a) Verify Scope
b) Develop Project Charter
c) Conduct Procurements
d) Report Performance
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 21
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
Approved change requests may require:
a) Stakeholder expectations
b) Expert judgment
c) Implementation of preventive or corrective actions
d) Cost estimating
CAPM Certification
Project Integration Management
The stimuli for chartering and authorizing a project include
usually all of the following EXCEPT:
a) Customer needs
b) Business needs
c) Need for a new product, service or result
d) Project selection
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 22
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
Application of additional padding material, due to a legally
enacted emission protection regulation, which requires
increased wall insulation for a building, is an example for a...
a) ...market demand.
b) ...business need.
c) ...social need.
d) ...legal requirement.
CAPM Certification
Project Integration Management
Which document indicates that a project manager has been
assigned and formally authorized to apply organizational
resource to project activities?
a) Stakeholder register
b) Project management plan
c) Work breakdown structure
d) Project charter
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 23
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
Which of the following is NOT an input for the process Develop
Project Charter?
a) Project statement of work
b) Enterprise environmental factors
c) Organizational process assets
d) Requirements documentation
CAPM Certification
Project Integration Management
A contract signed by an external customer …
a) ...is developed concurrently to the Project charter.
b) ...is input to the Develop Project Charter process .
c) ...describes only the consideration on the contractor side.
d) ...lays down the organizational standard processes applied.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 24
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
The Business case is created as a result of one or more of the
following EXCEPT:
a) Market demand
b) Enterprise environmental factors
c) Customer request
d) Organizational need
CAPM Certification
Project Integration Management
In developing the Project charter, expert judgment may come
from all of the following EXCEPT:
a) Industry groups
b) Other units within the organization
c) Project team and Project management team
d) Stakeholders, including customers or sponsors
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 25
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
The Project statement of work…
a) ...is a graphical description of products or services to be delivered
by the project.
b) ...is commonly developed by the project team to document
common understanding.
c) ...can be provided by a project initiator, sponsor, or the project
customer.
d) ...can generally never be provided as a part of a bid document.
CAPM Certification
Project Integration Management
Which process is used to implement approved change requests?
a) Perform Integrated Change Control
b) Verify Scope
c) Close Project or Phase
d) Direct and Manage Project Execution
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 26
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
The Direct and Manage Project Execution process requires the
project manager and the project team to perform multiple
actions to perform work defined in the Project management
plan EXCEPT...
a) Developing of a Project charter.
b) Performing activities to accomplish project requirements.
c) Implementing the planned methods and standards.
d) Managing sellers and suppliers.
CAPM Certification
Project Integration Management
Deliverables are an outcome of which process?
a) Direct and Manage Project Execution
b) Develop Project Charter
c) Create WBS
d) Control Scope
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 27
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Integration Management
Approved change requests are...
a) ...the documented, authorized changes to expand or reduce
project scope.
b) ...changes to enhance the profit of the performing organization.
c) ...activities delegated by the project manager to the project
coordinator.
d) ...requested changes before a final decision on their rejection has
been made.
CAPM Certification
Project Integration Management
Concerning deliverables, which of the following statements is
true?
a) Deliverables must be produced and provided to complete a
process, phase or project .
b) Clearly defined deliverables are nice to have, but not necessary.
c) Responsible team-members perform without stated deliverables.
d) A deliverable is any item, which pleases the customer.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 28
www.oliverlehmann.com
CAPM® Preparation
A Configuration management plan documents...
a) ...how change management will be performed.
b) ...how changes will be monitored and controlled.
c) ...how configuration management will be performed.
d) ...none of the above.
CAPM Certification
CAPM Certification
Project Integration Management
Chapter 5 – Project Scope Management
11%, PMBOK Guide pages 103 - 128
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 29
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
Define Scope is the process of...
a) ...developing the Work breakdown structure.
b) ...developing a detailed description of the project and product.
c) ...creating the Project management plan.
d) ...creating the Project scope management plan.
CAPM Certification
Project Scope Management
Create WBS is the process of...
a) ...subdividing the project deliverables and project work into
smaller, more manageable components.
b) ...preparing and performing the product acceptance and verifying
the correct administrative closure of a project.
c) ...assigning work levels, resources, durations, budgets, and begin
and end data to identified activities.
d) ...delegating schedule activities to project management team
members, to departments or to contractors.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 30
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
In the project context, the term scope can refer to...
a) ...managing and controlling activities.
b) ...customer scope as well as to stakeholder scope.
c) ...product scope as well as to project scope.
d) ...none of the above.
CAPM Certification
Project Scope Management
The Scope baseline of the project contains...
a) ...the approved detailed Project scope statement, WBS and its
associated WBS dictionary.
b) ...a Preliminary scope statement and its associated WBS and WBS
dictionary.
c) ...the customers wishes for additional scope during the time of
project execution.
d) ...legal regulations and public standards on necessary scope
elements.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 31
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
The Project scope statement includes, either directly, or by
reference to other documents all of the following EXCEPT:
a) Product scope description
b) Product acceptance criteria
c) Project deliverables
d) The Project charter
CAPM Certification
Project Scope Management
What is true for the Scope management plan?
a) The Scope management plan and the Project management plan
are independent from each other.
b) The Scope management plan and the Scope baseline are virtually
the same.
c) The Scope management plan and the Scope statement are always
not related.
d) The Scope management plan describes how the project scope will
be managed and controlled.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 32
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
Product breakdown, systems analysis, requirements analysis
and value engineering are included in what technique?
a) Forced identification
b) Project deliverables
c) Product analysis
d) Project constraints
CAPM Certification
Project Scope Management
Constraints are analyzed for all of the following EXCEPT:
a) Completeness
b) Additional risks
c)
Assumptions
d) Approved changes
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 33
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
Which is a commonly used method for alternatives
identification?
a) Factor analysis
b) Rule of seven
c) Brainstorming
d) Root-cause analysis
CAPM Certification
Project Scope Management
All of the following are usually part of the Project scope
statement EXCEPT:
a) Project deliverables
b) Project exclusions
c) Project documentation
d) Project constraints
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 34
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
Which is an explicit statement that describes what is excluded
from the project, in case of the assumption of a stakeholder that
a particular product, service, or result might be a component of
the project?
a) A project constraint
b) A project exclusion
c) A project deliverable
d) A project requirement
CAPM Certification
Project Scope Management
The WBS is ...
a) ...deliverable oriented.
b) ...activity oriented.
c) ...result oriented.
d) ...none of the above.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 35
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
What is Decomposition?
a) The process of breaking down schedule activities into work
packages.
b) The subdivision of project deliverables into smaller, more
manageable components.
c) The aggregation of activities to more manageable units.
d) The process of fragmentation of activities to allow parallel
processing.
CAPM Certification
Project Scope Management
The lowest level of the WBS is called...
a) ...authorization level
b) ...cost account
c) ...deliverables
d) ...work packages
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 36
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
What technique is usually applied if a deliverable in a WBS can
only be decomposed in the future?
a) Prototyping
b) Quality function deployment
c) Cost accounting
d) Rolling wave planning
CAPM Certification
Project Scope Management
All of the following are Group creativity techniques EXCEPT:
a) Brainstorming
b) Nominal group technique
c) Delphi technique
d) Estimation technique
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 37
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Scope Management
Approved changes can result from which of the following
processes?
a) Control Scope
b) Define Scope
c) Create WBS
d) Collect Requirements
CAPM Certification
Project Scope Management
Requirements documentation is input for which Project scope
management processes?
a) Define Scope, Collect Requirements, Control Scope
b) Verify Scope, Define Scope , Collect Requirements
c) Define Scope, Create WBS, Verify Scope, Control Scope
d) Report Performance, Define Scope, Collect Requirements
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 38
www.oliverlehmann.com
CAPM Certification
CA
CAPM
C
Cer
erti
er
ttiifiica
cati
ttiion
n
CAPM® Preparation
Chapter 6 – Project Time Management
11%, PMBOK Guide pages 129 - 164
CAPM Certification
Project Time Management
All of the following are outputs of the Define Activities process
EXCEPT:
a) Activity attributes
b) Activity list
c) Milestone list
d) Work breakdown structure
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 39
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
What statement is true?
a) A Milestone may be mandatory or optional.
b) A Milestone is always a phase finish event.
c) Milestones are inputs to define activities.
d) Milestone is a term synonymous to Deadline.
CAPM Certification
Project Time Management
What is Rolling wave planning?
a) It is a way to earn additional revenues.
b) It is a signal for poor initial planning.
c) It is a form of progressive elaboration planning.
d) It is a method no longer in use today.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 40
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
Work and effort performed within a work package...
a) ...is not reported to the senior management.
b) ...is gathered in high level items called activities.
c) ...is further decomposed into single activities.
d) ...should be always contracted out to external vendors.
CAPM Certification
Project Time Management
The Activity list...
a) ...includes all Schedule activities that are required on the project.
b) ...does not include the Schedule activities that are required on the
project.
c) ...does only include activities which are unrelated to the WBS work
packages.
d) ...is always a personal list for the project manager‘s eyes only.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 41
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
The Milestone list...
a) ...identifies all Work packages of the WBS.
b) ...is the list of Activity attributes.
c) ...identifies all Milestones.
d) ...is part of the project selection process.
CAPM Certification
Project Time Management
Which of the following is not among the Tools and techniques of
the Sequence Activities process?
a) Precedence Diagramming Method (PDM)
b) Dependency determination
c) Applying leads and lags
d) Critical chain method
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 42
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
All of the following are inputs of the Sequence Activities process
EXCEPT:
a) Project scope statement
b) Project charter
c) Activity list
d) Milestone list
CAPM Certification
Project Time Management
Which of the following is NOT an output of the Estimate Activity
Resources process?
a) Activity resource requirements
b) Resource breakdown structure
c) Project document updates
d) Schedule network diagrams
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 43
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
The Resource breakdown structure (RBS) is ...
a) ... a hierarchical structure of the identified resources.
b) ... a database showing human resources‘ skills.
c) ... a breakdown of scope by assigned resources.
d) ... an output of the process Activity Sequencing.
CAPM Certification
Project Time Management
PDM stands for:
a) Power distance management
b) Precedence diagramming method
c) Project data management
d) Performance distribution method
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 44
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
AON stands for:
a) Advanced online network
b) Annual order negotiation
c) Activity on node
d) Assessment of nonconformance
CAPM Certification
Project Time Management
PDM uses all of the following EXCEPT:
a) Finish-to-start relationships
b) Leads and lags
c) Dummy activities
d) Finish-to-finish relationships
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 45
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
Dependency determination uses all of the following types of
dependencies EXCEPT:
a) External dependencies
b) Mandatory dependencies
c) Discretionary dependencies
d) Relational dependencies
CAPM Certification
Project Time Management
All of the following are true EXCEPT: Precedence diagramming
method (PDM)...
a) ... uses nodes to represent the dependencies.
b) ...may require application of leads and lags.
c) ...is a method used in Critical Path Method (CPM).
d) ...uses boxes or rectangles to represent activities.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 46
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Time Management
Common estimating methods in the process Estimate Activity
Durations are all of the following EXCEPT:
a) Analogous estimating
b) Parametric estimating
c) Three-point estimates
d) Six-point estimates
CAPM Certification
Project Time Management
Analogous estimating...
a) ...means estimating by comparing with well designed experiments.
b) ...uses the activity dates taken from a previous project.
c) ...uses historical information and expert judgment.
d) ...does not need information from previous, similar projects.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 47
www.oliverlehmann.com
CAPM® Preparation
CPM stands for:
a) Change project manager
b) Critical path methodology
c) Cost performance measurement
d) Critical power maintenance
CA
CAPM
APM
M Certi
Certification
t fication
CAPM Certification
Project Time Management
Chapter 7 – Project Cost Management
9%, PMBOK Guide pages 165 - 188
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 48
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Cost Management
Project Cost Management includes all of the following processes
EXCEPT:
a) Acquire project team
b) Estimate costs
c) Determine budget
d) Control costs
CAPM Certification
Project Cost Management
Inputs for the Estimate Costs process are all of the following
EXCEPT:
a) Scope baseline
b) Project schedule
c) Human resource plan
d) Resource calendars
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 49
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Cost Management
Vendor bid analysis is among the tools and techniques of which
process?
a) Determine budget
b) Plan Costs
c) Control Costs
d) Estimate costs
CAPM Certification
Project Cost Management
The Cost performance baseline is an output of which process?
a) Estimate costs
b) Determine budget
c) Control costs
d) Estimate activity durations
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 50
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Cost Management
The accuracy of Parametric estimating depends on the following
EXCEPT:
a) Sophistication of the technique
b) Underlying data
c) Statistical relationship with historical data
d) Creation without inputs from external stakeholders
CAPM Certification
Project Cost Management
Which process has Cost performance baseline (updates) as an
output?
a) Estimate Costs
b) Determine Budget
c) Control Costs
d) Perform Integrated Change Control
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 51
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Cost Management
Company A is working on a project. The project‘s budget is
$10,000. The Planned value as of Data date is $4,000. The
project is 30% completed. 60% of the budget has been spent to
Data date.
The Earned value (EV) of the project is:
a) $600
b) $3,000
c) $5,000
d) $6,000
CAPM Certification
Project Cost Management
Company A is working on a project. The project‘s budget is
$10,000. The Planned value as of Data date is $4,000. The
project is 30% completed. 60% of the budget has been spent to
data date.
The Actual cost (AC) to date for the project is:
a) $6,000
b) $2,400
c) $3,000
d) $5,000
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 52
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Cost Management
Company A is working on a project. The project‘s budget is
$10,000. The Planned value as of Data date is $4,000. The
project has an Earned value of $3,500 and Actual costs of
$4,500.
Which statement is correct?
a) The project is behind schedule.
b) The project is ahead of schedule.
c) The project is finished.
d) The project is on schedule.
CAPM Certification
Project Cost Management
Company A is working on a project. The project‘s budget is
$10,000. The Planned value as of Data date is $4,000. The
project has an Earned value of $3,500 and Actual costs of
$4,500.
What is the Cost variance of the project?
a) - $1,000
b) $500
c) -500
d) $1,000
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 53
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Cost Management
Company A is working on a project. The project‘s budget is
$10,000. The Planned value as of Data date is $4,000. The
project is 30% completed. 60% of the budget has been spent.
If the company continues to spend money at the same rate,
what will the project cost (EAC)?
a) $10,000
b) $20,000
c) $6,000
d) $4,000
CAPM Certification
Project Cost Management
Company A is working on a project. The project‘s budget is
$10,000. The Planned value as of Data date is $4,000. The
project is 30% completed. 60% of the budget has been spent.
If cost variances of the future are expected at the same rate as
they have occurred in the past, what is the Estimate to
complete (ETC)?
a) $10,600
b) $14,000
c) $7,000
d) $2,400
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 54
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Cost Management
Examining project performance over time to determine if
performance is improving or deteriorating is called:
a) Variance analysis
b) Trend analysis
c) Earned value technique
d) Cost benefit analysis
CAPM Certification
Project Cost Management
All of the following are outputs of the Control Costs process
EXCEPT:
a) Project management plan updates
b) Organizational process assets updates
c) Work performance measurements
d) Work performance information
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 55
www.oliverlehmann.com
CAPM
CAPM
PM Certification
Certi
rt fiica
cation
CAPM® Preparation
Chapter 8 – Project Quality Management
7%, PMBOK Guide pages 189 - 214
CAPM Certification
Project Quality Management
Project Quality Management processes include all of the
following processes EXCEPT:
a) Plan Quality
b) Perform Quality Assurance
c) Perform Qualitative Risk Analysis
d) Perform Quality Control
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 56
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Quality Management
Each process of Project Quality Management occurs ______ in
every project and occurs ______ of the project phases, if the
project is divided into phases.
a) At least once / in one or more.
b) At least twice / in one or more.
c) Sometimes / in all
d) At least once / in all
CAPM Certification
Project Quality Management
Which of the following is true?
a) Quality is “the degree of customer satisfaction achieved by
meeting stated and implicit wishes”.
b) Quality is “the degree of stakeholder satisfaction achieved by
meeting explicit requirements”.
c) Quality is “the degree to which a set of inherent requirements
meets client needs”.
d) Quality is “the degree to which a set of inherent characteristics
fulfill requirements”.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 57
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Quality Management
Which of the following statements about quality and grade is
true?
a) Low quality may not always be a problem.
b) Projects should always deliver high grade.
c) Quality and grade are basically the same thing.
d) Low grade may not always be a problem.
CAPM Certification
Project Quality Management
All of the following statements about precision and accuracy are
true EXCEPT:
a) Precision means that the values of repeated measurements are
clustered and have little scatter.
b) Accuracy means that the measured values are close to the true
value.
c) Precision and accuracy are equivalent in that they are gained using
the same methods.
d) The project management team must determine appropriate levels
of precision and accuracy.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 58
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Quality Management
Quality management recognizes the importance of each of the
following EXCEPT:
a) Customer satisfaction
b) Inspection over prevention
c) Management responsibility
d) Continuous improvement
CAPM Certification
Project Quality Management
Which of the following is a direct Input to the Perform Quality
Assurance process?
a) Project scope baseline
b) Quality audits
c) Quality metrics
d) Process analysis
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 59
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Quality Management
One of the fundamental tenets of modern quality management
states that:
a) Quality is planned, desired, and built in – not inspected in.
b) Quality is not planned, designed, and built in – only inspected in.
c) Quality is planned, designed, and built in – not inspected in.
d) Quality has to be planned, designed, built in, and inspected in.
CAPM Certification
Project Quality Management
Which of the following is a direct input to Plan Quality?
a) Quality metrics
b) Quality management plan
c) Design of experiments
d) Cost performance baseline
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 60
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Quality Management
Which of the following is not among the tools and techniques of
the Plan Quality process:
a) Cost-benefit analysis
b) Benchmarking
c) Brainstorming
d) Design of experiments
CAPM Certification
Project Quality Management
The upper (UCL) and lower (LCL) control limits for repetitive
processes are usually set at:
a) +/- 6 sigma
b) +/- 3 sigma
c) +/- 2 sigma
d) +/- 1 sigma
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 61
www.oliverlehmann.com
CAPM Certification
CAPM® Preparation
Chapter 9 – Project Human Resources Management
7%, PMBOK Guide pages 215 - 242
CAPM Certification
Project Human Resources Management
The project management team is...
a) …a supervising or controlling team.
b) …a subset of the project team.
c) …the project team contingency.
d) …none of the above.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 62
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Human Resources Management
All of the following are processes of Project Human Resource
management EXCEPT:
a) Develop Human Resource Plan
b) Select Sellers
c) Develop Project Team
d) Manage Project Team
CAPM Certification
Project Human Resources Management
All of the following are direct inputs to the Develop Human
Resource Plan process EXCEPT:
a) Enterprise environmental factors
b) Organizational process assets
c) Project scope statement
d) Activity resource requirements
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 63
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Human Resources Management
Which of the following is not a subset of the Human resource
plan:
a) Roles and responsibilities
b) Project organization charts
c) Pre-assignment
d) Staffing management plan
CAPM Certification
Project Human Resources Management
Examples of Enterprise environmental factors that can influence
the Develop Human Resource Plan process are all of the
following EXCEPT:
a) Estimating techniques
b) Organizational structure
c) Personnel administration policies
d) Existing human resources
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 64
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Human Resources Management
OBS stands for:
a) Organizational breakdown structure
b) Organizational billing system
c) Open bargaining subject
d) Operational break-even status
CAPM Certification
Project Human Resources Management
RACI is an acronym for:
a) Resource, accountability, consult, inform
b) Responsible, accountable, consult, inform
c) Resource, acquirable, consult, instruct
d) Responsible, accountable, confirm, inform
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 65
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Human Resources Management
All of the following are inputs to the Develop Project Team
process EXCEPT:
a) Performance reports
b) Project staff assignments
c) Project management plan
d) Resource calendars
CAPM Certification
Project Human Resources Management
Co-location strategies can include all of the following EXCEPT:
a) Conveniences that enhance communication
b) A team meeting room
c) Building virtual teams
d) Places to post schedules
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 66
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Human Resources Management
The evaluation of a team‘s effectiveness can include indicators
such as the following EXCEPT:
a) Improvements in skills that allow individuals to perform
assignments more effectively.
b) Improvements in competencies that help the team perform better
as a team.
c) Reduced staff turnover rate.
CA
CAPM
A
C
Certification
ertifi
er
f cati
tion
ti
o
d) Participation in regular after work parties and other socializing
events.
Chapter 10 – Project Communications Management
7%, PMBOK Guide pages 243 - 271
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 67
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Communications Management
Which of the following is NOT a process of Project
Communications Management?
a) Manage Stakeholder Expectations
b) Plan Communications
c) Distribute Information
d) Manage Project Team
CAPM Certification
Project Communications Management
Acknowledgement means that...
a) ...the receiver signals receipt of the message, but not necessarily
agreement with the message.
b) ...the receiver signals receipt of the message, and necessarily
agreement with the message.
c) ...the receiver chooses writing-style to document the reception of
the message, and the agreement with the message.
d) ...the receiver nods to the message, and agrees with the message.
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 68
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Communications Management
In the communication model, who is responsible for encoding
the initial message?
a) The receiver
b) The receiver and the sender
c) The sender
d) The receiver or the sender
CAPM Certification
Project Communications Management
The process Plan Communications uses the following inputs
EXCEPT:
a) Enterprise environmental factors
b) Organizational process assets
c) Stakeholder management strategy
d) Human resource calendar
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 69
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Communications Management
Stakeholder communication requirements are provided in the
output of which process?
a) Report Performance
b) Develop Human resource plan
c) Distribute Information
d) Plan Communications
CAPM Certification
Project Communications Management
You have to coordinate 10 team members. How many
Communication channels are there on your project during that
time?
a) 10
b) 45
c) 50
d) 100
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 70
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Communications Management
Expert judgment is among tools and techniques of which
process?
a) Performance Reporting
b) Communications Planning
c) Identify Stakeholders
d) Manage Stakeholders
CAPM Certification
Project Communications Management
Communication activity includes all of the following potential
dimensions EXCEPT:
a) internal
b) formal
c) messy
d) written
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 71
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Communications Management
All of the following are outputs of the Report Performance
process EXCEPT:
a) Performance reports
b) Organizational process assets updates
c) Change requests
d) Implemented corrective actions
CAPM Certification
Project Communications Management
Which is not an example of Writing styles?
a) Active versus passive voice
b) Sentence structure
c) Face-to-face meetings
d) Word choice
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 72
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Communications Management
Communication technology is a tool and technique of which
process?
a) Report Performance
b) Plan Communications
c) Distribute Information
C PM Certifica
CA
CAPM
C
Certification
c ti
ca
t on
d) Manage stakeholder expectations
Chapter 11 – Project Risk Management
11%, PMBOK Guide pages 273 - 312
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 73
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
A project risk is a(n) _______ event or condition that, if it occurs,
has a __________________ effect on at least one project
objective.
a) Certain / negative or positive
b) Uncertain / negative and positive
c) Uncertain / negative or positive
d) Unkown / neither negative nor positive
CAPM Certification
Project Risk Management
Which is used as tool and technique for the process Plan Risk
Management?
a) Tornado diagramming
b) Decision tree analysis
c) Monte-Carlo simulation
d) Planning meetings and analysis
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 74
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
Against risks for which it may not be cost-effective or possible to
develop a proactive response a prudent response can be...
a) To allocate a contingency reserve
b) To build reserves
c) To do nothing
d) To ask your sponsor
CAPM Certification
Project Risk Management
Which document is established and updated along the Project
Risk Management processes from Identify Risks through Plan
Risk Responses and Monitoring and Control Risks ?
a) List of risk triggers
b) Risk register
c) Risk mitigation
d) Decision tree
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 75
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
The Output of the process Plan Risk Management will be
summarized in?
a) The quality baseline
b) The project scope management plan
c) The risk management plan
d) In none of the above
CAPM Certification
Project Risk Management
An item typically included in the Risk management plan is:
a) Potential responses
b) Identified risks
c) Risk management methodology
d) Root causes
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 76
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
In relation to the process Risk Management Planning, RBS
stands for:
a) Reserve budget settlement
b) Risk brain storming
c) Risk baseline support
d) Risk breakdown structure
CAPM Certification
Project Risk Management
Information gathering techniques used during the process
Identify Risks include all of the following EXCEPT:
a) Brainstorming
b) Delphi technique
c) Interviewing
d) Assumptions analysis
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 77
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
Typical Diagramming techniques used for the process Identify
Risks include all of the following EXCEPT:
a) System or process flow charts
b) Cause-and-effect diagrams
c) Influence diagrams
d) Delphi technique
CAPM Certification
Project Risk Management
The process Perform Qualitative Risk Analysis includes:
a) Risk urgency assessment
b) Sensitivity analysis
c) Checklist analysis
d) Probability distribution
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 78
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
Data developed during the process Perform Quantitative Risk
Analysis often leads to what type of probability distributions?
a) S-curves
b) 4-peak distributions
c) Continuous distributions
d) Tornado distributions
CAPM Certification
Project Risk Management
Commonly used Quantitative risk analysis and modeling
techniques include all of the following EXCEPT:
a) Sensitivity analysis
b) Expected monetary value analysis
c) Decision tree analysis
d) Assumptions analysis
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 79
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
Strategies for negative risks or threats include all of the
following EXCEPT:
a) Convince
b) Avoid
c) Transfer
d) Mitigate
CAPM Certification
Project Risk Management
Examples of risk mitigation include:
a) Building a prototype
b) Contingencies
c) Insurance
d) Warranties
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 80
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
All of the following strategies are strategies for positive risks or
opportunities EXCEPT:
a) Exploit
b) Share
c) Transfer
d) Enhance
CAPM Certification
Project Risk Management
The process Monitor and Control Risks includes all of the
following EXCEPT:
a) Risk reassessments
b) Risk audits
c) Technical performance measurements
d) Modeling and simulation
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 81
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Risk Management
All of the following are updated during the process Monitor and
Control Risks EXCEPT:
a) Risk register
b) Risk audit
c) Organizational process assets
CAPM Certification
d) Project management plan
Chapter 12 – Project Procurement Management
7%, PMBOK Guide pages 313 - 344
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 82
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Procurement Management
All of the following are tools and techniques of the process Plan
Procurements EXCEPT:
a) Make-or-buy analysis
b) Expert judgment
c) Advertising
d) Contract types
CAPM Certification
Project Procurement Management
All of the following are arrangements under which the buyer
must precisely specify the product or services being procured
EXCEPT:
a) Firm fixed price contracts
b) Fixed price incentive fee contracts
c) Fixed price with economic price adjustment contracts
d) Cost plus award fee contracts
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 83
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Procurement Management
Your company is in the process of selling consulting services to a
new buyer. The contract type with lowest risk for your company
in this situation is:
a) Firm fixed price
b) Time and material
c) Cost plus fixed fee
d) Cost plus incentive fee
CAPM Certification
Project Procurement Management
Source selection criteria are input to which process?
a) Plan procurements
b) Conduct procurements
c) Administer procurements
d) Close procurements
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 84
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Procurement Management
A Bidder conference is typically held during what process?
a) Close Procurements
b) Plan Procurements
c) Administer Procurements
d) Conduct Procurements
CAPM Certification
Project Procurement Management
All of the following are tools and techniques to select a seller
EXCEPT:
a) Proposal evaluation techniques
b) Contract change control system
c) Independent estimates
d) Bidder conference
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 85
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Procurement Management
The Contract change control system...
a) ...is an input to the Plan Procurements process.
b) ...requests changes to the project management plan.
c) ...lists the types of contract to be used.
d) ...defines the processes by which the procurement can be
modified.
CAPM Certification
Project Procurement Management
A Contract change control system is often among the tools and
techniques in what process?
a) Plan procurements
b) Conduct procurements
c) Administer procurements
d) Select sellers
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 86
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Procurement Management
Updates in Organizational process assets in the Administer
Procurements process contain all of the following EXCEPT:
a) Correspondence
b) Payment schedules and requests
c) Seller performance evaluation documentation
d) Requested changes
CAPM Certification
Project Procurement Management
Depending on contract terms and conditions, early termination
of a contract may occur for all of the following reasons EXCEPT:
a) Default of either party
b) Completion of the project
c) Mutual agreement
d) Convenience
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 87
www.oliverlehmann.com
CAPM® Preparation
CAPM Certification
Project Procurement Management
A Procurement audit is often held during what process?
a) Verify Scope
b) Verify Product
c) Close Contract
d) Close Procurements
© 2009, Herbert G. Gonder, Oliver F. Lehmann, Germany
PMI, CAPM, PMBOK and PMP are marks of the Project Management Institute,
Newtown Square, PA, USA, which are registered in the USA and in other nations.
Q - 88
www.oliverlehmann.com
CAPM Prep Questions
Answers
Chapter
PMBOK
Guide,
page
5
5
13
9
13
14
11
13
Slide
12
13
14
15
16
17
18
19
20
21
Right
answer
b
d
a
b
c
a
c
a
b
d
PMBOK
Guide,
page
22
15
17
17
19
20
24
30
28
27
Slide
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
Right
answer
b
d
c
b
c
a
a
d
b
b
c
d
b
a
c
b
a
PMBOK
Guide,
page
37
37
39
37
38
39
39
39
38
39
43
59
41
64
45
45
49
Slide
1
1
1
1
1
1
1
1
Chapter
2
2
2
2
2
2
2
2
2
2
Chapter
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
© 2009
3
4
5
6
7
8
9
10
Right
answer
d
a
a
a
d
c
a
d
A- 1
Herbert G. Gonder, PMP
Oliver F. Lehmann, PMP
Germany
CAPM Prep Questions
Answers
Chapter
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
Chapter
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
© 2009
Slide
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
Right
answer
d
b
c
d
d
d
d
b
b
c
c
d
a
a
a
a
c
PMBOK
Guide,
page
71
74
85
77
75
73
74
14
75
77
75
99
83
84
85
87
82
Slide
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
Right
answer
b
a
c
a
d
d
c
d
c
c
b
a
b
d
d
d
a
c
PMBOK
Guide,
page
112
116
456
456
115
126
114
112
114
115
115
116
118
118
120
108
128
104
A- 2
Herbert G. Gonder, PMP
Oliver F. Lehmann, PMP
Germany
CAPM Prep Questions
Answers
Chapter
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
Chapter
7
7
7
7
7
7
7
7
7
7
7
7
7
7
© 2009
Right
answer
d
a
c
c
a
c
d
b
d
a
b
c
c
d
a
d
c
b
PMBOK
Guide,
page
133
136
135
133
135
136
136
136
142
145
138
138
138, 140
139, 140
138
149, 150
149
138
Right
Slide
answer
97
a
98
d
99
d
100
b
101
d
102
c
103
b
104
a
105
a
106
a
107
b
108
b
109
b
110
d
PMBOK
Guide,
page
165
169
169
175
172
188
182
182
182
182
184
184
186
180
Slide
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
A- 3
Herbert G. Gonder, PMP
Oliver F. Lehmann, PMP
Germany
CAPM Prep Questions
Answers
Chapter
8
8
8
8
8
8
8
8
8
8
8
Chapter
9
9
9
9
9
9
9
9
9
9
Chapter
10
10
10
10
10
10
10
10
10
10
10
© 2009
Slide
112
113
114
115
116
117
118
119
120
121
122
Right
answer
c
a
d
d
c
b
c
c
d
c
b
PMBOK
Guide,
page
189
189
190
190
190
190, 191
202
190
191
191
196
Slide
124
125
126
127
128
129
130
131
132
133
Right
answer
b
b
c
c
a
a
b
a
c
d
PMBOK
Guide,
page
215
215
217
222, 223
219
220
221
230
234
235
Slide
135
136
137
138
139
140
141
142
143
144
145
Right
answer
d
a
c
d
d
b
c
c
d
c
b
PMBOK
Guide,
page
243
255
255
253
257
253
250
245
266
258
244
A- 4
Herbert G. Gonder, PMP
Oliver F. Lehmann, PMP
Germany
CAPM Prep Questions
Answers
Chapter
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
Chapter
12
12
12
12
12
12
12
12
12
12
12
© 2009
Slide
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
Right
answer
c
d
a
b
c
c
d
d
d
a
c
d
a
a
c
d
b
PMBOK
Guide,
page
275
279
304
274
277
279
287
286, 287
287
289
297
298, 299
303, 304
304
304, 305
308
308
Slide
165
166
167
168
169
170
171
172
173
174
175
Right
answer
c
d
c
b
d
b
d
c
d
b
d
PMBOK
Guide,
page
317
322-324
323
329
329
331, 332
338
335
340
342
342
A- 5
Herbert G. Gonder, PMP
Oliver F. Lehmann, PMP
Germany