Kearny High School Gymnasium Retrofit

Transcription

Kearny High School Gymnasium Retrofit
Aztec Energy
Request for Proposal (RFP)
Kearny High School Gymnasium
Retrofit
2014 Green Energy Challenge
Submitted: May 5, 2014
*
*
*Support Members
Aztec Energy
DESIGN- BUILD
2014 Green Energy Challenge
Table of Contents
Project Summary
Team Resumes
Energy Use Analysis
Lighting
Renewable Energy
Sub Metering
Construction Estimate
Construction Schedule
Site Logistics
Financial Analysis
Outreach
Testing and Feedback
Letter from the client
Article
NECA Interaction
List of Tables
Table 2.1-Baseline calculations
Table 2.2-Energy Bill
Table 2.3-Projected energy savings
based on analysis
Table 3.1-Existing and Proposed
Lighting
Table 4.1-Solar Panel Spec and
Costs
Table 4.2-Solar Cost Estimate
List of Figures
Figure 1.1-Campus Layout
Figure 1.2-3D Model of Gymnasium
Figure 2.1-Hot water tank
Figure 2.2-Locker room heater
Figure 2.3-Fan
Figure 2.4-Proposed fan locations
Figure 2.5-Mounting height
Figure 2.6- Locker room radiation
Figure 2.7- Wrestling room radiation
Figure 2.8- Locker room windows
1
4
10
17
21
26
29
30
32
33
34
38
39
40
42
10
11
16
17
23
Figure 2.9-Wrestling room windows
Figure 2.10- Gymnasium radiation
Figure 3.1-Existing Gymnasium Lighting
Figure 3.2-Photometrics for I-Beam LED Luminairs
Figure 3.3-Sensors and Exit Signage
Figure 4.1-Geothermal heat pump diagram
Figure 4.2-Solar calculations
Figure 4.3-Proposed location of PV System
Figure 4.4-PV Layout
Figure 4.5-Sun Power X-21 Panels
Figure 4.6-Power and product warranty diagrams
Figure 4.7-Micro inverter
Figure 4.8-Central Inverter
Figure 4.9-Estimated Monthly Solar Production
Figure 5.1-Leviton System Components
Figure 5.2-Leviton BMO Display Software
Figure 5.3-Construction Schedule
Figure 5.4-Site Logistics Plan
Figure C1.1-SDGE Innovation Center
Figure C1.2-Open house brochures
Figure C1.3-Volunteering at SDSU open house
Figure C1.4-Kearny High School presentation
Figure C1.5-Kearny High School presentation
Figure C4.1-SDGE Innovation Center
Figure C4.2-Kearny High School walk
15
16
18
19
20
21
22
22
23
23
23
24
24
25
27
28
31
32
34
35
36
37
37
42
42
Apendices
Appendix A-Lighting Luminaire
Appendix B-Proposed Lighting/Sensor Layout
Appendix C-Estimate-Preconstruction Services
Appendix D-Estimate-General Conditions
Appendix E-Estimate-Construction Costs
Appendix F-Financial-Solar ROI
Appendix G-Financial-Lighting ROI
Appendix H-References
43
44
45
46
47
48
49
50
24
2
3
11
12
12
14
14
15
15
15
Aztec Energy
DESIGN- BUILD
2014 Green Energy Challenge
Project Summary
Executive Summary
Aztec Energy Design-Build is a premier company serving all of San Diego. Our
team
is
We are
comprised
comprised
with
the
most
passionate
and
qualified
individuals
that
create
a
high
performance
of a passionate and qualified team members which specialized in energy efficiency and
team
thatoptimization.
is collaborative,
adaptable,
andmade
well-rounded.
why ourbyteam
building
This innovative,
is why Aztec
Energy has
its mark inThis
theisindustry
has
made
its
mark
in
the
industry
by
providing
a
high
quality
product
that
exceeds
owner to
exceeding owner expectations. Aztec Energy is a leader in providing sustainable solutions
expectations.
Energy
is a
leaderhigh
in providing
sustainable
to our clients
and
our clients andAztec
we are
always
setting
standards
for quality,solutions
green construction,
safety,
we
are
always
setting
high
standards
for
quality,
green
construction,
safety,
and
in
ethics.
and in ethics.We will work with the client to achieve their goals of sustainable clean energy.
We
work with
the clientistowhat
achieve
their goals
of sustainable
clean We
energy.
extensive
Our will
extensive
experience
separates
us from
the competition.
also Our
serve
as
experience
what
separates
usways
from to
thefinance
competition.
only do
we cater
the client’s that
consultants is
and
help
determine
energyNot
efficient
projects.
Wetounderstand
needs
makeso
improvements
that iswould
best for
theirbest
situation,
buttowe
also serve
cost is and
an issue
we prioritize what
be the
solution
reduce
energythem as a
consulting
company
and help
determine
ways to
the project. We understand
consumption
and improve
the them
comfort
and wellness
of finance
the occupants.
that cost is an issue so we will prioritize what we believe would be the best solution to
Adjustedenergy
Technical
Analysisand
Score
(Estimate
Schedule
and Financial
* 1.4
reducing
consumption
improve
the comfort
and wellness
of theAnalysis)
occupants.
(Lighting Retrofit) * 0.6
Local Company
We pride ourselves on having our headquarters located in the nation’s first LEED Platinum
Student Union at San Diego State University. We are a local business only 15 miles away
from the Kearny Mesa High School. Our close proximity to the parking structure makes it
easy for us to coordinate the project, materials, deliveries and labor. Local business
interactions is better for the environment and better for the community.
Mission Statement
Aztec Energy’s goal as leader in the green energy community is to help the community to
reduce their cost of operations, help the environment, and serve the community. Our team
has exercises creative, and alternative ways to solve problems. We exemplify this by
overcoming the unique circumstance in which all of San Diego County’s student union
building have been renovated by the end of the first quarter of 2014. Our team of experts
thought it would be most beneficial to serve the community by reaching out to Kearny Mesa
High and providing the School District with a plan to update their Gym, which serves as a
place of congregation for their students. The community as a whole benefits as we are not
only changing out the lights, but we also opened up the door to educating the students
about sustainability and changing the habits of the future generation. It starts not with the
technology, but with the people. This is our mission.
Proposal Outcome
By using our contractor and utilizing our proposed renewable sources, lighting retrofits, and
monitoring equipment, we will continue to save the client energy for decades and continue
to educate the community about their energy consumption habits. We will be updating the
lighting through the use of new Title 24 compliant dimming LED ballasts along with solar
tubes for daylighting capabilities and all it will be wired to the nLight system in the gym for
improved lighting controls. The will reduce total energy consumption by 40%. . In addition,
we would like to implement a PV system that will be able to put the gym into an energy
producer to serve the rest of the high school campus. In keeping up with Title 24
requirements, we are also proposing to install a monitoring system with a display panel to
show and educate the community on their energy consumption behaviors.
Aztec Energy
DESIGN- BUILD
1
2014 Green Energy Challenge
Project Summary
Proposed Budget
Our total proposal cost is $307,737 and will have a total payback of 8.9 years.
The Client
The official client is the San Diego Unified School District because Kearny High is a K-12
school under the control of the District, but our interactions with the client and feedback is
received directly from the school staff. Kearny Mesa High is directed by Principal of
Construction Tech Academy, Cheryl Hibbeln, and Principal of Kearny High, Ana Diaz.
Jerry Butkiewicz is on the advisory board and helped to introduce sustainability into the
curriculum at Construction Tech Academy.
When Kearny Mesa was established, it was named after its military base, Camp Kearny.
Camp Kearny was operational from 1917 to 1946. This public high school opened its doors
in 1941, and only undergone slight renovations since. During the 2004-2005 school year,
Kearny High was transformed from a traditional high school into a campus with four
independent and specialized schools, each with an emphasis on fields of study such as
Digital Media and Design, International Business, Construction, and Science and
Technology. This system resembles the different colleges on a typical campus, because
each separate “high school” is completely autonomous and independent of the others and
each has a specialized curriculum specific to their own area of study. The new school
system was founded by Bill and Melinda Gates and the program is funded by the Bill and
Melinda Gates Foundation.
Role of Facility
We propose to retrofit the existing Kearny Mesa
High School gymnasium located at 7651 Wellington
Way in San Diego, California. The gym and its
adjacent spaces within the structure spans 20,130
square feet, and is located in an inner-city setting
within the Kearny Mesa neighborhood. The structure
was built to accommodate student body meetings,
assemblies, and athletic competitions year round. It
is also an emergency shelter for the community in
the case of a disaster. Geographically, it is
surrounded by the Pacific Ocean on the west and
mountains to the east. The location between ocean
and mountain provides a slow, but fairly consistent
stream of cool air.
Figure 1.1-Campus Layout
Aztec Energy
DESIGN- BUILD
2
2014 Green Energy Challenge
Project Summary
The gymnasium includes other spaces such as restrooms, a wrestling room, coach offices
and a boy’s locker room. The high school’s alumni has strong sentimental feelings towards
the original gym design. Some of the alumni have kids who now attend the school.
Therefore, all proposed design modifications will maintain a low profile in order to keep the
original image of the building. Aztec Energy plans to implement new systems to improve
functionality of the building while simultaneously enhancing the community’s awareness to
the energy saving benefits through sub-metering. After the retrofit, the structure will have
improved energy efficiency and the original look will be maintained to satisfy the wishes of
the community.
A 3D scanner was used to model the interior spaces of the gymnasium. This allowed Aztec
Energy to provide accurate take offs for the estimate. The model is shown below in figure
1.2.
Figure 1.2-3D Model of Gymnasium
Aztec Energy
DESIGN- BUILD
3
Aaron Nickovich
5333 Baltimore Drive Apt. 11, La Mesa, CA 91942
(925) 858-5321 | [email protected]
Objective
Obtain experience in machine designing or energy auditing.
Education
San Diego State University, B.S. Mechanical Engineering, San Diego, CA 92182
Anticipated Graduation: December 2015
Cumulative GPA: 3.46
Dean’s List
California High School, High School Diploma, San Ramon, CA 94583
Graduated: May 2006
Skills
Microsoft Office (Word, Excel, Access, Outlook and PowerPoint), AutoCAD, Revit, SolidWorks,
Pro Engineer (Creo Elements 5.0), MultiSim 12.0, geometric tolerancing (GTOL), programming in C++ and JavaScript
for Adobe Pro.
Experience
BioSero, San Diego, CA (September 10, 2013 - Present)
Intern
 Teamed up with a contract engineer and other interns to redesign machines, then manufacture and test prototypes.
 Maintained consistent communication with other team members.
 Maintained SolidWorks models of machine redesigns.
Chula Vista Electric, Chula Vista, CA (May 20, 2013 – September 9, 2013)
Summer Intern
 Completed basic tasks such as printing and binding blueprints, taking inventory and organizing project binders.
 Created customized PDF forms with JavaScript programming for customized data entry and calculations.
 Other tasks involved solving a sizing problem with in-row cooling racks for a hot aisle containment system,
creating project schedules, and helping project managers on job walks.
SDSU Research Foundation, San Diego, CA (September 1, 2012 – May 30, 2013)
Undergraduate Research Assistant
Project: Research on Energy Efficient Projects. ELECTRI Foundation | Advisor: Dr. Thais Alves
 Conduct research on the energy efficiency of electrical and mechanical systems in buildings at SDSU.
 Report findings in academic papers and presentations.
Nickovich Insurance, San Ramon, CA (May 2010 - August 27, 2012)
IT Technician
 Trained employees how to use Excel, Outlook, ACT! and Access.
 Rearranged the office to improve employee task productivity.
 Provided maintenance services on the computers, printers, and server.
Best Buy, Dublin, CA (October 2006 - March 2007)
Floor Sales
 Provided quality advice on product selection based on customer needs.
Membership/ Extra-curricular
NECA SDSU Student Chapter
Officer (2012-2013), President (2013-2014)
 Green Energy Challenge (GEC) team member – a national competition which NECA student chapters conduct an
energy analysis of a structure, then propose ways to retrofit the structure to increase energy efficiency.
Tau Beta Pi, California Xi (engineering honors society)
Member (since 2013)
4
Maryia Volhina
13543 Zinnia Hills Pl. #86, San Diego, CA 92130
[email protected]
(619) 302-7759
Objective
To obtain a Project Engineer position where I expand on my current work experience of assisting
the project team with daily planning, execution, and coordination of construction project.
Education
B.S. Construction Engineering and Management
San Diego State University
Expected graduation: May 2014
Employment History
McCarthy Building Companies
September 2012-Present
Cardiovascular Institute &
Central Energy Plant for Scripps Memorial Hospital in La Jolla
Intern
• Responsibilities include review and coordination of shop drawings and submittals, processing RFI’s and
submittals, participation in documentation of MEP and Project Status meetings
• Conduct weekly Safety Committee Observation Report and Evaluation walks
• Process inspection requests to OSHPD inspection agency and supervise subcontractors’ field installation through
inspection requests
Southland Industries Internship
June 2012-August 2012
Intern
• Responsibilities included developing RFI’s and coordination drawings for submission to the General
Contractor
• Assisted in the development of bid packages and negotiated prices with vendors for Ventura County Medical
Center Hospital Replacement Wing
• Collected necessary information to create the required submittal packages for 3 individual projects
ISEC Inc.Internship
November 2011-January 2012
Intern
• Recorded RFI’s, invoices and cost information into ProLog
• Assisted Project Manager with creation of invoices and document control
• Conducted 2 cost estimates for projects located in the San Diego area
Community Service
• “Habitat for Humanity” – Assisted with cleaning the store and rolling up left-over linoleum
• Participated in the AGC Chapter community service that included beach clean ups, golf tournaments,
various AGC & CMAA events
Education Activities
• CMIT, Construction Manager In Training
• Vice President for NECA student chapter
• AGC & CMAA chapter member
• Green Energy Challenge Student Competition – Nationally recognized Universities compete in preparing a
written proposal and a poster for NECA convention
• Associated Schools of Construction Student Competition: Multi-family team, alternate – Students obtain
contract documents and construct a bid package and a written proposal within a time constraint
• Design-Build Institute of America Student Competition – Nationally recognized Universities compete in
preparing a written proposal
• 10 hour OSHA certificate
Scholarships
CMAA (2013); AGC (2013); NECA(2014); CMAA (2014)
5
Gustavo Maldonado
[email protected]
377 Shady Ln Apt 41• El Cajon, Ca. 92021 • (619) 937-1630
EDUCATION
B.S Construction Engineering and Management
San Diego State University
Study abroad in Panama
Expected graduation Spring 2014
Summer 2013
Relevant Course: Construction concepts and building codes, ethics and law, estimating,
planning and scheduling, analysis of construction operations, mechanical and electrical
systems, design of temporary structures, virtual design and civil engineering classes.
EXPERIENCE
Estimator
2/10/14- Present
Whillock Contracting, Inc.
6/25/12-5/24/13
 Bidding projects
 Helping in the managing process of a project
 Communicating and working together as a team inside and outside the office
Estimator
Dynalectric- San Diego
 Helping estimators with takeoffs quantities
Cashier
Albert’s Mexican Food Restaurant



4/19/09- 1/16/13
Providing excellent customer service
Multitasking in a fast paced environment
Collaborating as a team to get the job done
Project Management
A & G Construction





5/28/13-12/20/13
2006- Present (Part-time)
Assisting with preparing proposals
Purchasing/ gathering construction materials
Supporting needs of workers and job site necessities
Communicating and following up with clients
Handling workers payroll
PROFESSIONAL INVOLVEMENT
Treasurer of NECA student chapter
Member of AGC & CMAA student chapter
CMIT, Construction Manager in Training
OSHA 10 hour certification
2013-2014
2011-2014
EXTRA- CURRICULAR ACTIVITIES
Green Energy Challenge Student Competition
2013-2014
Associated School of Construction Student Competition: Heavy Civil 2014
6
Charles Plank
5445 55th Street #4H
San Diego, CA 92115
530-383-8600
[email protected]
Employment History
Electrical Intern for the City of Woodland
July 2013- present supervised by Joey Gines,
Woodland, CA
Maintenance on traffic lights
Operated cherry picker
 Badging and signage upkeep
Sales Associate at Golfsmith
January 2013- April 2013 Golfsmith of San Diego, CA
Selling merchandise
 Customer service
Operating cash register
 Maintaining store appearance
 Golf club repair and assembly
Associate at Panera Bread
October 2012- January 2013 Panera Bread of La Mesa, CA
Operating cash register
Delivering orders to customers
 Maintaining store appearance
 Customer service
 Barista: making coffee drinks for customers
 Dishwashing experience
 Baking experience
Education

August. 2012 - present San Diego State University, San
Diego, CA
Electrical Engineering objective, focus on power
distribution

High School Diploma from Pioneer High School, Woodland,
CA
References
References are available on request.
7
Timothy J. McElwee
1152 Hanover Place Alpine, CA 91901
619-929-7389 • [email protected]
EDUCATION
Bachelor of Science, Construction Engineering,
San Diego State University, San Diego, CA
Graduating May 2014
Current GPA 3.4
EXTRACURRICULAR ACTIVITIES
•
•
•
•
VP of Internal Affairs, AGC CMAA
Student Chapter
2013/2014 ASC Competition
Preconstruction Team
AGC Beach Cleanups
ASCE Student Chapter Member
•
•
•
•
•
NECA Student Chapter Member
2014 Green Energy Challenge
Chi Epsilon Engineering Honors
Society Member
Habitat for Humanity
2013 CMAA Rising CM Conference
PROFESSIONAL EXPERIENCE
Intern Swinerton Builders, Rancho Bernardo, CA
January – May 2014
• Project Engineer, BMW of El Cajon, El Cajon, CA
• Project Engineer, Sunroad Centrum 2 Parking Structure, San Diego, CA
• Managed change orders, submittals, RFIs and material procurement
• Prepared scope packages for subcontractor buyout
Researcher and TA San Diego State University, San Diego, CA
• Assisted professor with multiple research projects
• Graded assignments and recorded grades for professor
August – December 2013
Intern Southland Industries, Garden Grove, CA
June 2012 – August 2013
• Project Engineer, San Diego FBI headquarters, San Diego, CA
• Project Engineer, AAA Data Center, Costa Mesa, CA
• Tracked field productivities to verify projects were on schedule and budget
• Assisted with budget management and managing change orders
Cashier Albertsons Grocery, Alpine, CA
Feb 2008 – June 2012
• Checked out groceries, balanced register, unloaded trucks and stocked shelves
• Exhibited outstanding customer service, awarded employee of the month
SKILLS
•
•
•
•
OSHA 10 certified
Accredited Construction Manager in Training
Proficient with Bluebeam, On Screen Takeoff, Auto CAD, Navisworks Viewer, and Primavera
Experienced with JD Edwards, CMIC and COINS Project Management Software
8
Norberto Ruvalcaba
6159 Montezuma Rd. #3, San Diego, CA 92115
(760) 791-4151
[email protected]
Objective
To obtain an intern position in the energy engineering field that involves finding efficient, clean and innovative
ways to supply energy.
Education
SAN DIEGO STATE UNIVERSITY
Bachelor of Science in Civil Engineering
Expected Spring 2015
Related Coursework
ASHRAE Level 1 Energy Auditing, Structural Analysis, Mechanics of Materials, Surveying for Civil Engineers,
AutoCAD, ArcGIS, Transportation Engineering and Environmental Engineering
Experience
PROJECT STUDENT LEAD - ACKERSTEIN SUSTAINABILITY, LLC
2013-CURRENT
•
Perform technical analysis and calculations relating to energy, water, landscaping, transportation, and other
sustainability issues
•
Document compliance with LEED requirements via LEED Online
•
Maintain project schedules and work independently without constant supervision
•
Collaborate with others to implement policies relating to sustainable practices
PROJECT COORDINATOR - SDSU POWER SAVE CAMPUS
2012-CURRENT
•
Identify energy/ water savings through research into and implementation of energy/ water efficiency best
practices and facilitation of retrofits
•
Promote energy and water efficiency through educational outreach campaigns
•
Collaborate with student groups, organizations, campus stuff and administrators to educate the campus
community on energy and water efficiency
BARTENDER - SHERATON SAN DIEGO HOTEL & MARINA
2011-CURRENT
•
Excelled the highest levels of cleanliness, safety, compliance with licensing law and cash handing procedures
•
Prepare and serve alcoholic and non-alcoholic drinks quickly and efficiently while meeting highest standards of
presentations and attention to detail
•
Able to quickly and confidently communicate with guests to establish their needs
Affiliates
National Association of Electrical Contractors (NECA), American Society of Civil Engineers (ASCE), Engineers Without
Borders (EWB), and U.S. Green Building Council (USGBC)
9
2014 Green Energy Challenge
Energy Use Analysis
Aztec Energy investigated and analyzed the client’s total energy consumption for the
gymnasium to identify ways to conserve energy and save the client money. Energy bills
were made available to Aztec Energy upon special request to the District. Unfortunately,
the metering data received monitored the entire campus aside from a few select buildings.
The main campus meter also monitored the power fed by the current PV panels under a
purchasing agreement located in the parking lot. It was clear that the energy bills were not
going to provide enough detailed information on the building to create a solid baseline,
therefore, it was decided by the team to analyze the lighting system based on
observations and guidance from Nordstrom Christer, he works for the District in the
Auxiliary Services department and he is a LEED AP involved with the most recent lighting
retrofit. With the help of Nordstrom, we were able to figure out how the current controls
were designed in order to make a close approximation of the amount of energy that is
consumed by the Gym. The baseline calculations can be seen in Table 2.1. The campus
metering data is shown on the next page as well.
Table 2.1- Baseline calculations
Aztec Energy
DESIGN- BUILD
10
2014 Green Energy Challenge
Energy Use Analysis
Table 2.2- Energy Bill
The electricity consumption for the entire Kearny High campus uses an
average of 62,615 kWhr per month which is 3 times as much power as the
Gym consumes in a year! This is the justification for ignoring the metering
data for our baseline.
Heating
The team was advised during the first site walk that the building contains a
heater room, but the boiler inside is used to heat the offices in the adjacent
buildings, not the gym (Figure 2.1). The hot water tank has been insulated
fairly well, but certain sections of the pipes are missing insulation.
Nordstrom mentioned that the pumps for this tank uses a VFD at 5%
speed which suggests that the hot water is used as radiant heat for the
offices. There are some possible upgrades to this system, but none will be
implemented as this campus serves as an emergency shelter so reliability Figure 2.1-Hot water tank
as well as maintainability takes a higher priority over energy efficiency.
Aztec Energy
DESIGN- BUILD
11
2014 Green Energy Challenge
Energy Use Analysis
There are separate gas line heaters located
in the building as seen in figure 2.2. The
school’s staff stated that, “those heaters
haven’t been used in a long time”. This is a
reasonable statement since Kearny Mesa’s
semi-arid climate and close proximity to the
ocean provides sufficient temperature
throughout the year.
Figure 2.2-Locker room heater
Ventillation
Ventillation in the building is almost
non-existent. There are ceiling vents
in place as well as some active
ventilation, but the school has been
relying on 4 large fans to push air
through the building when it gets too
hot.
Figure 2.3-Fan
ENERGY STAR Benchmarking
The following reports were generated by the EPA Benchmarking tool. The first report is
based on the entire campus in order to obtain a performance score to compare against
other schools. This was to done due to the fact that the Gym’s facility type is not available
for comparison against other facilities from EnergyStar. The second report includes the
specific building in question in order to provide an EUI score. We have no specific
metering data available so the report is only based on the accuracy of our assessment on
the Gym.
Aztec Energy
DESIGN- BUILD
12
2014 Green Energy Challenge
Energy Use Analysis
®
ENERGY STAR
Performance
99
ENERGY STAR®
Statement of Energy
Kearny High School
Primary Property Function: K-12 School
Gross Floor Area (ft²): 195,000
Built: 1955
For Year Ending: February 28, 2014
Date Generated: May 04, 2014
1
Score
1. The ENERGY STAR score is a 1-100 assessment of a building’s energy efficiency as compared with similar buildings nationwide, adjusting for
climate and business activity.
Property & Contact Information
Property Address
Kearny High School
7651 Wellington Way
San Diego, California 92111
Property Owner
__________________
,
(____)____-______
Primary Contact
____ ________
,
(____)____-______
__________________
Property ID: 4046010
Energy Consumption and Energy Use Intensity (EUI)
Site EUI
26.5 kBtu/ft²
Annual Energy by Fuel
Electric - Grid (kBtu)
2,303,599 (45%)
Natural Gas (kBtu)
2,864,677 (55%)
National Median Comparison
National Median Site EUI (kBtu/ft²)
National Median Source EUI (kBtu/ft²)
% Diff from National Median Source EUI
Annual Emissions
Greenhouse Gas Emissions (Metric Tons
CO2e/year)
Source EUI
52.5 kBtu/ft²
®
ENERGY STAR
Performance
N/A
ENERGY STAR®
61.2
121.2
-57%
354
Statement of Energy
Kearny High Gym
Primary Property Function: Social/Meeting Hall
Gross Floor Area (ft²): 20,130
Built: 1955
For Year Ending: January 31, 2014
Date Generated: May 05, 2014
1
Score
1. The ENERGY STAR score is a 1-100 assessment of a building’s energy efficiency as compared with similar buildings nationwide, adjusting for
climate and business activity.
Property & Contact Information
Property Address
Kearny High Gym
7651 Wellington Way
San Diego, California 92111
Property Owner
__________________
,
(____)____-______
Primary Contact
____ ________
,
(____)____-______
__________________
Property ID: 4047266
Energy Consumption and Energy Use Intensity (EUI)
Site EUI
32.7 kBtu/ft²
Source EUI
102.6 kBtu/ft²
Annual Energy by Fuel
Electric - Grid (kBtu)
657,875 (100%)
National Median Comparison
National Median Site EUI (kBtu/ft²)
National Median Source EUI (kBtu/ft²)
% Diff from National Median Source EUI
Annual Emissions
Greenhouse Gas Emissions (Metric Tons
CO2e/year)
22.2
69.8
47%
58
Aztec Energy
DESIGN- BUILD
13
2014 Green Energy Challenge
Energy Use Analysis
Observation and Recommendations
Ventilation
This building provides a unique challenge to save money. There is already some passive
ventilation currently being used in the structure through the roof and vents on the walls. Any
fresh air will usually come from a natural breeze or from the portable fans that are temporarily
plugged in. What is missing from the gym is comfort. Students complained about the
consistently high ambient temperature. When measured from a thermometer, the temperature
was consistently above 75 degrees Fahrenheit. Without moving air, this is not a suitable
temperature to be in during strenuous activity. Aztec Energy proposes to install two X2.0
Powerfoil fans from Big Ass Fans. Our team contacted Big Ass Fans to determine the best
location and sizes to provide adequate cooling. We recommend 2 of them to mounted at 20
feet above the floor. See the cost estimations for included costs for time and material. See
figure 2.5 below for location details:
16' dia Big Ass Fans
Figure 2.4- Proposed fan locations
Figure 2.5- Mounting height
Aztec Energy
DESIGN- BUILD
14
2014 Green Energy Challenge
Energy Use Analysis
Day Lighting
The current lighting system requires a key to turn on a number of fluorescent lights
without any way to zone the lights individually. There is also no advantages taken to
consider the use of daylight from the windows. There were some luminaires that
appeared to be attached to the motion sensors, but since the whole gym is one zone,
the individual rooms light up regardless of its occupancy. So they remained on behind
locked doors and closets. To improve daylight capability in the gym, Aztec Energy
proposes to install solartubes that mount into the ceiling. This is a crucial component for
the retrofit as there is currently not enough ambient light to take advantage of inside the
gym. Skylights are not an option as they would require a large hole in the ceiling which
would introduce issues with structural integrity. Our team made an in-depth analysis on
the lighting power provided by the current windows in the locker room and the wrestling
room, and also made a study of the potential daylight available if the solartubes were
installed. The tool used was an excel lighting calculator provided by PG&E. Only the
formula was changed from BTU/(hr * SF) to kW based on the area of the windows or
solartubes, percentage of transmission through the material, and a conversion factor for
energy units. The results are shown below:
Figure 2.6- Locker room radiation
Figure 2.8- Locker room windows
Figure 2.7- Wrestling room radiation
Figure 2.9-Wrestling room windows
Aztec Energy
DESIGN- BUILD
15
2014 Green Energy Challenge
Energy Use Analysis
The result if this analysis is that we have sufficient light that is available during the day. The
Wrestling room is usually used in the morning or afternoon and it sees the most directly
sunlight during these times so it can take advantage of that light. The locker rooms are
used throughout the day as PE class goes on and as the locker rooms get used for the
sports teams. The light intensity doesn’t pick up until the afternoon when the light is able to
reflect off the white roof. A lot of the light available in the locker rooms is ambient lighting
which is good since there is less need for window treatments. The daylight sensors will still
be able to be used in this room. Certain areas are blocked off from the daylight, but there is
still some light during the peak hours. Lastly, the gym’s solar tubes are mounted on the roof
in a vertical orientation so the gains from daylighting is most prominent during the
afternoon, but also provides plenty of light as early as 9:30AM and as late as 4:00PM. With
a new controls system, daylighting sensors, and high efficient dimmable lights, we can take
advantage of the daylight and be able to turn off the lights completely during peak hours of
the day, and slowly add more power to the lights as the daylight starts to drop off. Based
on this analysis energy savings Aztec Energy proposes will be reduced under baseline by
42% as shown in table 2.3.
Figure 2.10- Gymnasium radiation
Table 2.3-Projected energy savings based on analysis
Aztec Energy
DESIGN- BUILD
16
2014 Green Energy Challenge
Lighting
~40% SAVINGS!!
Table 3.1-Existing and Proposed Lighting
Brief Summary
Aztec Energy is proposing to retrofit the lighting for the gymnasium and adjacent spaces at
Kearny High School. Given existing conditions, changing the lighting from fluorescent to
LED, adding occupancy sensors in all of the spaces along with daylight controls and
dimming, will make the gymnasium more energy efficient. With this retrofit Aztec Energy is
expecting over 40% in savings! A breakdown of the existing fixtures and and proposed
lighting is included in table 3.1.
Aztec Energy
DESIGN- BUILD
17
2014 Green Energy Challenge
Lighting
Existing Conditions
The gymnasium lights are mounted at inconsistent heights, which makes lighting
distribution uneven. The average foot-candles differ at various locations around the gym,
ranging from 25 to a maximum of 28 foot-candles.
There are (36) 8-lamp fluorescent high bay light fixtures, which use a lot of power but do
not provide sufficient lighting or at least 50 foot candles for the gymnasium area. The gym
area also has (4) 2-lamp fluorescent high bay safety fixtures that are always on. There are
(6) 2-lamp fluorescent emergency fixtures that are never on, however they are battery
controlled fixtures in case of a power outage. The rest of the areas in the gymnasium,
along with the bathrooms, lockers, and offices, have 2-lamp fluorescent fixtures that are
switched and do not allow dimming. Many rooms have windows which permit natural
lighting and the lights should be off during the day. Also, Aztec Energy found about 6
fixtures that do not serve any purpose in the building.
Figure 3.1-Existing Lighting in Gymnasium
Proposed Lighting
The most energy efficient light fixture is the one that doesn’t require energy. That is why
Aztec Energy is proposing SkyVault M74 solar tubes which will deliver natural light into the
gym and help to reduce energy consumption by dimming the high bay lighting. Aztec
Energy is proposing a total of 16 solar tubes to achieve an average of approximately 23
foot candles, which is perfect for regular school classes. Research performed at this
location indicated the following lumens data: average – 16,732 (March 21st, 9am); Max. –
35,140 (June 21st, noon); Min. – 4,483 (Dec. 21st, 3pm). The photometrics for the solar
tubes is included in appendix A.
Aztec Energy
DESIGN- BUILD
18
2014 Green Energy Challenge
Lighting
The (36) 8-lamp fluorescent high bay light fixtures will be replaced with just 12 I-beam LED
high bay luminaries equivalent to about approximately 48,000 nominal lumens per fixture.
Instead of replacing one-for-one, Aztec Energy did research and is proposing to upsize the
lights to get greater output and eliminate 24 fixtures. To evenly distribute the lighting, Aztec
Energy is proposing to mount all 12 fixtures at a 22’ elevation. Figure 3.2 below shows the
photometrics for the 12 I-beam LED luminaries.
Luminaire Schedule
Quantity
Note
12
1. 22' Mounting Height
Lumens Per
Catalog Number
Description
IBL 48L WD LP740 DLC
I-BEAM LED, 31"X45", WITH 48,000
Wattage
Lamp
49918
489
NOMINAL LUMENS, WIDE
DISTRIBUTION, AND 4000K 70 CRI
2. 28' ceiling height
LEDS, DLC CERTIFIED
3. designed for 50fc
7.3
15.1
26.8
30.9
19.1
10.3
7.5
12.6
22.8
32.5
22.8
12.6
7.5
10.3
19.1
30.9
26.6
14.7
7.1
10.2
33.0
103.4
134.9
51.0
15.7
8.9
22.7
74.2
147.5
74.2
22.7
8.9
15.7
51.0
134.9
103.4
33.0
10.1
12.0
48.4
220.5
320.8
85.0
19.6
9.7
30.4
140.0
362.7
140.0
30.4
9.7
19.6
84.9
320.8
220.5
48.4
12.0
10.5
33.3
101.8
132.0
51.0
16.0
9.2
23.1
73.5
144.2
73.5
23.1
9.1
16.0
51.0
132.0
101.8
33.3
10.4
8.1
16.7
29.3
33.7
21.0
11.2
8.0
13.9
25.2
35.5
25.2
13.9
8.0
11.2
21.0
33.7
29.3
16.7
8.1
7.9
14.6
23.4
26.2
17.9
10.7
8.1
12.7
20.7
27.4
20.7
12.7
8.1
10.7
17.8
26.2
23.4
14.6
7.9
9.7
26.5
66.1
81.9
37.9
14.5
8.8
19.6
51.1
88.2
51.1
19.6
8.8
14.5
37.9
81.9
66.1
26.5
9.7
12.2
47.2
202.1
289.1
80.9
19.7
10.2
30.1
130.8
324.9
130.8
30.1
10.2
19.7
80.9
289.1
202.1
47.2
12.2
11.6
41.6
153.9
210.6
67.8
18.3
10.0
27.5
104.4
233.4
104.4
27.5
10.0
18.3
67.8
210.6
153.9
41.6
11.6
8.8
20.8
42.8
50.9
27.7
12.7
8.4
16.4
35.1
54.1
35.1
16.4
8.4
12.7
27.7
50.8
42.8
20.8
8.8
7.9
14.0
21.7
24.1
16.9
10.6
8.3
12.4
19.4
25.1
19.4
12.4
8.3
10.6
16.9
24.1
21.7
14.0
7.9
8.8
20.8
42.8
50.9
27.7
12.7
8.4
16.4
35.1
54.1
35.1
16.4
8.4
12.7
27.7
50.8
42.8
20.8
8.8
11.6
41.6
153.9
210.6
67.8
18.3
10.0
27.5
104.4
233.4
104.4
27.5
10.0
18.3
67.8
210.6
153.9
41.6
11.6
12.2
47.2
202.1
289.1
80.9
19.7
10.2
30.1
130.8
324.9
130.8
30.1
10.2
19.7
80.9
289.1
202.1
47.2
12.2
9.7
26.5
66.1
81.9
37.9
14.5
8.8
19.6
51.1
88.2
51.1
19.6
8.8
14.5
37.9
81.9
66.1
26.5
9.7
7.9
14.6
23.4
26.2
17.9
10.7
8.1
12.7
20.7
27.4
20.7
12.7
8.1
10.7
17.9
26.2
23.4
14.6
7.9
8.1
16.7
29.3
33.7
21.0
11.2
8.0
13.9
25.2
35.5
25.2
13.9
8.0
11.2
21.0
33.7
29.3
16.7
8.1
10.4
33.3
101.8
132.0
51.0
16.0
9.1
23.1
73.5
144.2
73.5
23.1
9.1
16.0
51.0
132.0
101.8
33.3
10.4
12.0
48.4
220.5
320.8
84.9
19.6
9.7
30.4
140.0
362.7
140.0
30.4
9.7
19.6
84.9
320.8
220.5
48.4
12.0
10.1
33.0
103.4
134.9
51.0
15.7
8.9
22.7
74.2
147.5
74.2
22.7
8.9
15.7
51.0
134.9
103.4
33.0
10.2
7.2
14.7
26.6
30.9
19.0
10.3
7.5
12.6
22.8
32.5
22.8
12.6
7.5
10.3
19.1
30.9
26.7
15.1
7.3
Statistics
Avg
50.7 fc
Max
362.7
fc
Min
7.1 fc
Max/Mi
n
51.1:1
Avg/Mi
n
7.1:1
Avg/Ma
x
0.1:1
IBL_24L_WD_LP740_DLC
Figure 3.2: Photometrics for I-Beam LED Luminaries
The (36) 8-lamp fluorescent high bay light fixtures will be replaced with only 12 I-beam
LED high bay luminaries equivalent to about approximately 48,000 nominal lumens per
fixture. Instead of replacing one-for-one, Aztec Energy did a research and is proposing to
upsize the lights to get greater output and eliminate 24 fixtures. To get even distribution of
lighting, Aztec Energy is proposing to mount all 12 fixtures at a 22’ elevation. Below is a
photometric for the 12 I-beam LED luminaries.
Aztec Energy
DESIGN- BUILD
19
2014 Green Energy Challenge
Lighting
The (4) 2-lamp fluorescent safety fixtures will be replaced one-for-one with I-beam LED
high bay luminaries equivalent to approximately 9,000 nominal lumens per fixture. This
LED fixture will give out better light and provide more lumens than the one currently
installed. Since these are safety fixtures, and are always kept on, Aztec Energy will ensure
that the replacement safety fixtures will continue to be kept on. Please refer to the
proposed lighting/sensors layout for fixture type.
The (6) 2-lamp fluorescent emergency fixtures are battery-controlled and are never on.
The only instance these fixtures would be on, is during a power outage. These emergency
fixtures do not consume any energy, therefore Aztec Energy will not replace these fixtures.
The current (89) 2-lamp fluorescent fixtures in adjacent rooms will be replaced with only
(61) STL LED luminaires. There are several reasons Aztec Energy chose these fixtures.
One reason is they have longer life, which reduces maintenance. The next reason is they
are highly energy efficient and sustainable. Another reason these fixtures combine digital
LED lighting and controls technologies with high-performance. The proposed lighting
layout and fixture types are included in appendix B.
Dimming Controls, Occupancy Sensors, and Photocell Sensors
The gymnasium will have specialized sensors that include combination dimming and
switching photocell with high/low occupancy operation. These fixture mount sensors are
LSXR family SensorSwitch that can be found on Figure 3.3. Aztec Energy will provide one
sensor per fixture, which will total 12. The adjacent rooms will have occupancy sensors
and all lights will be dimmable. The wrestling room, boys locker room, and several
bathrooms will have daylight controls to offset the natural lighting. Please refer to the
proposed lighting/sensors layout for locations of these sensors.
LSXR
The gymnasium will use natural lighting through solar
tubes and provide more lighting to occupied space,
meeting the foot candle requirement. The adjacent rooms
will also have sufficient lighting and daylight/occupancy
sensors with dimming controls that will reduce energy
consumption. Aztec Energy will also switch out all 4 exit
signs with LED exit sign combo with emergency lights
shown on Figure 3.3. And we will add a missing exit sign
in the boys locker room. This retrofit will save the client
over 40% energy use.
FAMILY
FIXTURE MOUNT SENSOR w/
INTERCHANGEABLE LENSES,
PIR, LINE VOLTAGE
Figure 3.3-Sensors and Exit Signage
Aztec Energy
DESIGN- BUILD
20
2014 Green Energy Challenge
Renewable Energy
Background
A majority of the world's current electricity supply is generated from fossil fuels such as
coal, oil and natural gas, these traditional energy sources face a number of challenges
including rising prices. As a leader in renewable energy, Aztec Energy will be working
with the client to pursue energy performance targets that will increase the production of
renewable energy. Aztec Energy will be analyzing and recommending the best
renewable energy system fit for the site and will accomplish the client’s goal.
Renewable Energy Analysis
One renewable energy option that was analyzed was a wind energy system. It was
determined that a wind energy system would not be feasible for the high school due to
the low wind speeds in the area.
Geothermal
Second renewable option that was analyzed
was installing a geothermal heat pump. Due to
the cost to of the equipment, it made geothermal
cost-prohibitive to the client. The other two
forms of geothermal, direct use or electricity
generation are also cost-prohibitive due to them
being used for larger scale grid system. Aztec
Energy did reference NREL map for best sites
for geothermal. Figure 4.1 shows a simple
geothermal heat pump diagram. Geothermal is
not an ideal source of energy and will not be
recommended to the client.
Figure 4.1-Geothermal heat pump diagram
Aztec Energy
DESIGN- BUILD
21
2014 Green Energy Challenge
Renewable Energy
Solar
The last type of renewable energy that was analyze is solar. Aztec Energy recommends
that the best form of renewable energy is solar energy. Data gather from SunCalc.com
shows that Kearny High School stands in a great location. Figure 4.2 shows the sun
position and the sunlight phases that the school is getting on a regular day.The gymnasium
is facing the south side meaning that this has a great potential to produce a lot of electricity
throughout the day. For the most part San Diego is always sunny. From the figure below
Kearny High is getting approximate 8-10 hours of sunshine per day. A photovoltaic system
will be recommended to take advantage of all the sun that the school is getting.
Figure 4.2-Solar calculations
Placement of Photovoltaic System
The gymnasium has a very unique architectural look to
it and has been around since 1941. Due to this the
dome like roof cannot be modified, by request of the
school district. This means that no cutting or additions
to the existing roof. Accepting the school’s request
Aztec Energy is proposing to install a photovoltaic
system adjacent to it. The photovoltaic system will be
directly above the locker rooms/office such as shown in
figure 4.3 indicated in red.The total square footage of
that area is approximate 2800 SF. Aztec Energy will
be installing 80 solar panels to the roof, a layout of the Figure 4.3-Proposed location of PV System
solar panels array can be shown in figure 4.4. The
electrical room is almost directly below, making this a
great location to connect all of our electrical
components. Aztec Energy found this to be the best
location for a photovoltaic system that will reduce the
initial cost and satisfy the client’s request.
Aztec Energy
DESIGN- BUILD
22
2014 Green Energy Challenge
Renewable Energy
Mounting System
The proposed location of the solar panels will be on top of
the adjacent building of the gymnasium. The roof is flat
and has a few exhaust fans and a HVAC line that runs
through to other roofs. The few exhaust that are in the roof
and the HVAC line will not be in the way of the solar
arrays. The layout on figure 4.4 shows the location of the
solar panels and how the fans and the HVAC line will not
be affected. The solar panel arrays will be mounted on top
of the roof; they will be place at a 17 degree angle.
Although 31 degrees is the standard placement for solar
panels Aztec Energy will be placing the solar panels at a
17 degree angle. This will be done in order to received the
right amount of power for the space. There is no major tilt
that has to be accounted for due to the fact that they are
located facing south.
Figure 4.4-PV Layout
Solar Panel Selection
Solar technology has evolved over time and has progressively got more efficient and
affordable; pricing is included in table 4.1. The solar panels that Aztec Energy is proposing
to install are top of the line SunPower X-21 Series 345 Watt monocrystalline solar panels
(figure 4.5). The panels produce 21% more energy per rated watt than other conventional
solar panels. As one can see from figure 4.7 the X-21 Series will be a better investment
over the years compared to other conventional panels. A variety of solar panels such as
Sharp,Solar World, Astronergy or Suniva were considered, but the best option is SunPower
which maintains the most efficient output over its lifetime. SunPower also offers the best
combined power and product warranty compared to other conventional solar panels on the
market such as shown figure 4.6.
Figure 4.5-Sun Power X-21 Panels
Figure 4.6-Power and product warranty diagrams
Table 4.1-Solar Panel Spec and Costs
Aztec Energy
DESIGN- BUILD
23
2014 Green Energy Challenge
Renewable Energy
Inverters
Aztec Energy will be installing just one central inverter for the entire solar panel system.
Aztec Energy first thought about including individual AC microinverters for each solar
panel, but it would result higher initial cost. Microinverters are best fit for areas that have
an ease of access under the panels because it is expensive to access them safely if they
need future service. Although there can be benefits to microinverters, Aztec Energy is
proposing high producing panels that can have the same amount of benefits as installing
a microinverter for each panel.
Figure 4.7-Micro inverter
Figure 4.8-Central Inverter
Estimate
Once all the components have been accounted for Aztec Energy will be installing the
photovoltaic. A cost down breakdown of all the components can be seen in table 4.2.
*Pricing from Dynalectric-San Diego
Table 4.2-Solar Cost Estimate
Aztec Energy
DESIGN- BUILD
24
2014 Green Energy Challenge
Renewable Energy
Return on Investment
Figure 4.9 shows the electricity the solar panels will produce per month. The total annual
system production is 42,683 kWh per year. This is approximately 4.5 times the energy that the
gymnasium requires to operate. Therefore, our combined proposed lighting and solar retrofits
will put the Gym into an energy producer. This retrofit will not only pay for itself, but it will help
to offset the enrgy consumption of the rest of the campus. Aztec Energy educating the
students and teachers at the school the importance of conserving electricity.
Figure 4.9-Estimated Monthly Solar Production
Image of The Client
As mentioned before, Kearny High is departmentalized into separate schools with their
specific area of study. The Construction Technology Academy preaches energy conservation
awareness. For example, students go on field trips to places like the San Diego Gas & Electric
innovation center to get educated on sustainability. Aztec Energy will be helping the student
body be aware of the school's energy consumption by installing a monitoring system with a
graphical a display of the energy savings provided by the building. Students will also be able
to monitor how much energy the solar panels are producing. This will coincide with the
sustainability concepts the students are being taught in class, thus reinforcing the impact that
building improvements provide with tangible data.
Aztec Energy
DESIGN- BUILD
25
2014 Green Energy Challenge
Sub Metering - Overview
Benefits of Sub Metering
Sub metering is beneficial for multiple reasons, first it allows a benchmark to be set so
facilities managers understand energy draws on their building. Second, it allows for real
time accurate data to be collected thus making reduction in peak demand charge a viable
option. Third, the actual return on investment can be easily realized and this more detailed
data will help to spur other energy efficient projects across the campus and reduce energy
bills for the school. Forth, it will allow the client to portray their energy usage to student
which will be a great educational tool for the school.
Installation of sub meters can easily be integrated to the retrofit for the facility. The meters
will tie in to the feed in to the gymnasium lighting and plug loads and will be located on the
electrical room. A meter will also be installed on the solar array to monitor the energy output
of the system. All sub meters will be located in the electrical room.
Monitoring Areas
The gym building will be divided into several different monitoring areas; by doing this it allow
facilities staff to understand the diverse space within the gym.
The proposed system for sub metering the separate systems in the gymnasium includes:
1. Gymnasium, wrestling room, bathrooms and kitchen
2. Boys/girls locker rooms and coaches offices
3. Photo voltaic array
Student Awareness
Sub metering allows an opportunity to educated students about their energy consumption.
By installing an energy dashboard at the entrance of the gym it will allow students to see the
actual cost of energy and give them a better understanding of what it costs to use electricity.
This dashboard can also be used in the Green Tech class in Construction Tech Academy
located at Kearny High. This class is covers green construction and energy use. The class
is currently in a competition with other schools to reduce the energy consumption and useful
sub meters can give them a much better understanding of where they can conserve energy.
Aztec Energy
DESIGN- BUILD
26
2014 Green Energy Challenge
Sub Metering - System Architecture
VerifEye Sub Metering Solutions
Components
(3) Series 2000 three phase meter kits
(1) Flex I/O module
(1) Energy Monitoring Hub (EMH)
(1) BMO 2.0 On-line Web Energy Management Software
Figure 5.1-Leviton System Components
The System
The series 2000 metering kits will be connected to the electrical feed from the main panels for the
gymnasium and locker rooms (panels 12LA and 12LB). Meter pulse output is connected to HUB
via low voltage cabling. This hub compiles the data and transfers it into a readable script for the
Energy Manager software. This information will be displayed in the gym and will portray the
energy production of the solar array and consumption of the gym.
27
2014 Green Energy Challenge
Sub Metering - Display
Figure 5.2-Leviton BMO Display Software
Features
Displays information in real time
Collects information in 1 to 60 minute intervals for detailed tracking
Users log into Energy Manager website to view and customize display
Benefits
Helps to identify cost saving solutions for reduced energy bills
Discovers energy inefficiencies
Establishes baselines in order to reduce future energy consumption
Helps to mange facilities carbon footprint
Awareness
The display will be posted at the north entrance of the gym. This will allow students to view
the energy consumption of the gym and understand how leaving lights on wastes energy.
A sample display is shown in figure 5.2. This monitor will be in a weather tight impact
resistant case in order to prevent damage during sporting events.
Aztec Energy
DESIGN- BUILD
28
PROJECT:
OWNER:
CONTRACTOR:
MANAGER:
Kearny High School Gym Retrofit
San Diego Unified School District
Aztec Energy
Aaron Nickovich
Building SF:
20,130
ESTIMATOR:
Tim McElwee
GENERAL CONDITIONS BUDGET
DESCRIPTION
PRECONSTRUCTION/DESIGN PHASE
GENERAL CONDITIONS
GENERAL CONDITIONS BUDGET
BUILDING BUDGET
DESCRIPTION
GYMNASIUM
TOTAL BUILDING SF:
Duration MO:
Site SF:
20,130
2
20,130
LOCATION:
San Diego, CA
DATE:
May 5, 2014
100% DESIGN DEVELOPMENT
BUDGET
QTY
UNIT
UNIT
COST
AMOUNT
1
2
20,130
QTY
MO
MO
SF
UNIT
11,112
29,234
40,346 13.11% of total
AMOUNT
COMMENTS
20,130
GSF
11,112
14,617
2.00
UNIT
COST
10.87
218,766
SUMMARY
Budget
COMMENTS
71.09% of total
$ per SF
$
$
$
$
$
$
$
$
$
$
259,112
5,182
264,294
3,304
267,598
40,140
307,737
307,737
-
$
$
$
$
$
$
$
$
$
$
12.87
0.26
13.13
0.16
13.29
1.99
15.29
15.29
-
TOTAL BUDGET $
307,737
$
15.29
SUBTOTAL: SOFT SIDE, GENERAL CONDITIONS, SITEWORK, BUILDING:
CONTINGENCY @
2.00%
SUBTOTAL
INSURANCES @
1.25%
SUBTOTAL
CONTRACTOR'S FEE @
15.00%
SUBTOTAL
SUBCONTRACTOR BONDS @
N/A
SUBTOTAL
MATERIAL ESCALATION @
N/A
*Detailed Breakdown of construction costs is included in appendix C-E.
Aztec Energy
DESIGN- BUILD
29
2014 Green Energy Challenge
Construction Schedule
Duration
The duration of this project is from June 16, 2014 - August 14,
2014. The two month duration is possible due to phasing, which
also allows construction activities to be completed during the
summer months when traffic on campus is reduced.
Phasing
The retrofit of the gym will be broken into 3 general work areas.
The gymnasium, locker rooms and photo voltaic array will be
stacked in order to reduce the duration.
Critical Path
The critical path for this project runs through construction of the
gymnasium. There are several days of float available in the
locker room and PV array which will allow Aztec Energy to shift
crews if needed in order to remain on schedule and turn over the
gymnasium prior to the 2014/2015 school year.
Student Safety
The construction duration will be completed during summer
months when traffic is reduced on campus. This will allow us to
ensure student safety by not exposing them to construction
traffic. The site will be fully fenced preventing unauthorized
personnel from entering the site. Flaggers will also be used to
prevent traffic delays, and assist students in crossing the street
to the adjacent parking lot. This is a vital tool used to keeping
students and staff safe during construction. A preliminary site
logistics plan is shown in figure 5.4.
Reduced Cost
By working during the summer it will allow Aztec Energy to avoid
overtime and premium pay, reducing cost to Kearny High.
Workers will also be able to drive equipment on campus without
being uninterrupted by classes, which will allow for higher
productivities making the short construction duration possible.
Direct access to the gym via the adjacent parking lot will provide
the site with lay-down and space for construction trailers. Close
proximity to the project reduces material handling time. Material
handling is the largest source of non productive time in
construction.
A detailed schedule is included in figure 5.3.
Aztec Energy
DESIGN- BUILD
30
Kearny High Lighting Retrofit
Activity ID
Classic WBS Layout
Activity Name
Original Start
Duration
Finish
04-May-14 13:30
June 2014
July 2014
Kearny High Lighting Retrofit
14-Aug-14
17
24
14-Aug-14, Kearny High Lighting Retrofit
Kearny High Lighting Retrofit
43 16-Jun-14
14-Aug-14
14-Aug-14, Kearny High Lighting Retrofit
43 16-Jun-14
14-Aug-14
14-Aug-14, Site Overview
2 16-Jun-14
17-Jun-14
43 16-Jun-14
14-Aug-14
A1000
Site Safety and Fencing
A1310
Construction Duration
A1300
Startup and Commissioning
Phase 1 (Gymnasium)
5 08-Aug-14
14-Aug-14
36 18-Jun-14
07-Aug-14
22
29
06
August 2014
43 16-Jun-14
Site Overview
15
13
20
27
03
10
Site Safety and Fencing
Construction Duration
Startup and Commissioning
07-Aug-14, Phase 1 (Gymnasium)
A1010
Safe off
1 18-Jun-14
18-Jun-14
A1040
Demo lighting (wrestling room, bath, kitchen)
3 19-Jun-14
23-Jun-14
A1050
Remove Light Fixtures (Gym)
6 24-Jun-14
01-Jul-14
A1110
Run new conduit (wrestling room)
2 24-Jun-14
25-Jun-14
A1100
Install conduit for Big Ass Fans
2 26-Jun-14
27-Jun-14
A1290
Run new wire (wrestling, bath, kitchen)
3 26-Jun-14
30-Jun-14
A1090
Install new ballasts and lights (wrestling room, bath, kitchen) 3 01-Jul-14
03-Jul-14
A1080
Install solar tubes
12 07-Jul-14
22-Jul-14
A1130
Install new ballasts and lights (gym)
15 10-Jul-14
30-Jul-14
A1070
Spray foam roofing
4 23-Jul-14
28-Jul-14
A1140
Install Big Ass Fans
7 23-Jul-14
31-Jul-14
Install Big Ass Fans
A1200
Install new sub meters
1 31-Jul-14
31-Jul-14
Install new sub meters
A1210
Install energy dashboard
5 01-Aug-14
07-Aug-14
Phase 2 (Locker Rooms)
19 02-Jul-14
29-Jul-14
A1280
Demo existing lighting
4 02-Jul-14
08-Jul-14
A1020
Replace Windows
3 09-Jul-14
11-Jul-14
A1160
Install new conduit
4 09-Jul-14
14-Jul-14
A1190
Run new wire
3 15-Jul-14
17-Jul-14
A1170
Install daylight and occupancy sensors
2 18-Jul-14
21-Jul-14
A1150
Install new sub meter
1 22-Jul-14
22-Jul-14
A1180
Install new lighting
5 23-Jul-14
29-Jul-14
21 19-Jun-14
18-Jul-14
Phase 3 (Solar)
A1320
Set Estanchions
8 19-Jun-14
30-Jun-14
A1330
Wire to Inverter
5 01-Jul-14
08-Jul-14
A1340
Modules
5 09-Jul-14
15-Jul-14
A1350
Install Sub Meter
1 16-Jul-14
16-Jul-14
A1360
Check System for Ground Faults and Continuity
2 17-Jul-14
18-Jul-14
Safe off
Demo lighting (wrestling room, bath, kitchen)
Remove Light Fixtures (Gym)
Run new conduit (wrestling room)
Install conduit for Big Ass Fans
Run new wire (wrestling, bath, kitchen)
Install new ballasts and lights (wrestling room, bath, kitchen)
Install solar tubes
Install new ballasts and lights (gym)
Spray foam roofing
Install energy dashboard
29-Jul-14, Phase 2 (Locker Rooms)
Demo existing lighting
Replace Windows
Install new conduit
Run new wire
Install daylight and occupancy sensors
Install new sub meter
Install new lighting
18-Jul-14, Phase 3 (Solar)
Set Estanchions
Wire to Inverter
Modules
Install Sub Meter
Check System for Ground Faults and Continuity
Aztec Energy
DESIGN- BUILD
Remaining Level of Effort
Actual Work
Critical Remaining Work
Primary Baseline
Remaining Work
Milestone
Summary
Page 1 of 1
© Primavera Systems, Inc.
Figure 5.3-Construction Schedule
31
2014 Green Energy Challenge
Site Logistics
Construction
Trailers
Dumpsters
Truck Route
Temp Toilets
Flagger
Pick Points
Student Safe
Walkway
Construction
Fencing
Figure 5.4-Site Logistics Plan
Site Logistics
The proposed site logistics plan will ensure students and staff remain safe during
construction. A dedicated flagger will be used for deliveries and help students cross the street
safely. Pick points will be located to the south of the project and will not cross any pedestrian
walkways. All constuction activities will be contained within the construction fence and the
dotted yellow path is a safe access routes for students and faculty. This will ensure they
remain safe during construction.
Aztec Energy
DESIGN- BUILD
32
2014 Green Energy Challenge
Financial Analysis
Project Funding
The total cost of this project was an estimated $307,737. Aztec Energy identified several
options for funding the renovations to the gymnasium. NECA Works was utilized to
analyze the costs, ROI, incentives and rebates for solar and lighting for the gymnasium.
The city of Kearny Mesa receives electricity from SDG&E utility company, which qualifies
them for SDG&E related rebates and financing. For the lighting retrofit, Funding will be
received from the use rebates from SDG&E “Energy Efficiency Business Rebates
Lighting Catalog”. The catalog lists fixtures and controls along with $/unit. After
calculations, the total we will receive in rebates is $1360. This will bring our project total
down to $306,377.
Proposition 39
Proposition 39 indicates that multi-state companies have to pay taxes based on sales in
California (Single Sales Tax). By doing so, California will generate $1 billion in new tax
revenue each year, part of which will be used towards clean energy and energy
efficiency projects. The majority of funding is based off of average daily attendance
(ADA). Although funding is granted per School District, the maximum amount of money
allowed to be allocated to one individual school is $130,000. Aztec energy is confident
the maximum amount will be received to fund this project, due to Kearny High's ADA of
1,735. This will bring our project total down to $176,377.
Solar
The solar array will output 72,540
42,684 kW or $18,135 per year as shown in Appendix F. This
will provide a payback of approximately 1.2 years with incentives. The California Solar
Initiative Standard PV program will provide $4,865.80 per year after installment for 10
years. Benefits from the California Solar Initiative will bring the project total to $127,719.
Solatubes, has decided to donate 5 of the 16 solar tubes in order to market their product.
This will save the project roughly $5000. Additionally, this reduces the total project cost to
$122,719.
Financing
Aztec Energy will apply for SDG&E On-Bill Financing program to cover the additional
project cost; this program offers 0% financing and is open to all non-residential customers
who had an active account with SDG&E for the past two years. The maximum amount of
incentive is $1,000,000 with ten year max payback, and we will be apply just for the
remaining $122,719.
Lighting Costs
As shown in Appendix the lighting retrofit will save approximately 65,871 kW or $16,468
per year with a payback of 4.4 years with incentives and rebates. With this savings the
total project remaining cost of $122,719 will be paid back in roughly 7.5 years. This 7.5
years includes miscellaneous costs for the project not covered by incentives. After the
payback period is complete the additional yearly savings will be realized by the district.
The ROI for lighting is included in appendix E.
Aztec Energy
DESIGN- BUILD
33
2014 Green Energy Challenge
Outreach
As part of our mission to reach out to other students at all levels, we create a positive pathway for
the future in both renewable energy and furthering careers in electrical contracting. This year we
decided to blaze a new path by including a 9th grade class from our local Kearny High School and
Construction Tech Academy. Our goal was to enhance their studies of renewable energy and
develop a partnership by including the class input. In addition, we were able to act as mentors
representing the college path. We were surprised to understand that many students had not
considered college nor understood the vast possibilities in the study of construction management
and engineering. We were also pleased to see young women now considering this career. By
engaging the class in our site walk and providing a forum for a discussion of our project and all
available renewable technologies, we were able to enlighten an already bright group of students to
new energy solutions and expand their vision of the future. In turn, Aztec Energy was rewarded
with a long term partnership with a local high school, mentoring students towards a college path
and into the electrical contracting industry. This will now be included in our mission. San Diego
State University is also a proud supporter of many groups and clubs that inform students of the
importance of the environment and how to be environmentally conscious. The following are a few
groups that contribute to the amazing family of clubs at SDSU:
NECA Student Chapter
This chapter is comprised of mainly Construction, Electrical, and
Mechanical Engineering but all other majors are welcome. It
provides students with a greater familiarization with the electrical
construction industry, promotes professionalism and prepares the
students land an internship with an electrical contractor.
Associated Student Green Love
Figure C1.1-SDGE Innovation Center
This organization works very hard to embrace sustainable practices in all facilities at San Diego
State. Their mission is to pave the way for a full-scale sustainable movement by and for SDSU
and the community. They assist in measuring and improving operations and encourage student
organizations and residents to adopt sustainable habits. Assist SDSU in becoming a model
University in sustainability by measurably improving operations to meet the highest standard of
sustainability that is feasible.
http://as.sdsu.edu/greenlove/
Enviro-Business Society
This is a non-profit environmental advocacy organization at SDSU that offers all students of all
majors of a unique and beneficial way to make a positive and environmental impact on campus,
in the community, and in business. This society promotes modern business practices that
maximize profit and a sustainable future.
http://meldi.snre.umich.edu/node/24797
USGBC Student Chapter
This chapter’s mission is to create an entire Green University by making all existing buildings on
campus to be LEED certified and bring awareness to all students on campus. This year the NECA
student chapter and Green Energy Challenge team members conducted joint meetings with this
organization to improve the effectiveness of meetings and combine the memberships of two
organization that have similar goals.
Aztec Energy
DESIGN- BUILD
34
2014 Green Energy Challenge
Outreach
Power Save Campus
Green Campus promotes their ideas and projects by holding
various events, audits and awareness campaigns to educate
students, faculty, and staff on how they can save energy. They
aim to reduce the amount of energy used on campus and to
promote the green workforce.
http://www.sdsupowersave.org/
Greenfest
GreenFest is sponsored by the SDSU’s associated
students and their objective is to engage the campus
community through social and interactive programs in
an effort to educate them on the important of living a
sustainable lifestyle and to promote sustainable
practices. Every year they have activities for an entire
week which consist of bike brunch, herb garden
expo, and a variety of student organization
competitions to educate the community.
http://www.as.sdsu.edu/greenfest/
Method 1: Bring Awareness to Campus
Aztec Energy plans to improve energy conservation awareness on campus by creating brochures and
passing them to students on campus. We inform our community of the importance of our chapter and of
ways in which they can help out their communities. Our goal is to show that a little act by each individual
can greatly impact the community. We want to show students easy but not so obvious ways to conserve
energy.
Figure C1.2-Open house brochures
Aztec Energy
DESIGN- BUILD
35
2014 Green Energy Challenge
Outreach
Method 2: Green Orientation
Every year San Diego State University
holds the Explore SDSU Open House in
which incoming students are invited to
come and meet all the clubs on campus.
This is to get a feeling on what they might
want to join in their future career in college.
Our chapter attends every year and
informs students of what the NECA student
chapter consists of. We also recruit people
to join our chapter in order to get involved
at school and with their future. We want to
implement a mandatory orientation in
which all incoming freshmen would go
through a Green Practice Orientation. This
can be a joint effort by all organizations on
campus in order to teach students how
they can adopt sustainable habits. This is
a great opportunity for all organizations of
different majors to work together with a
common goal to create an orientation that
will capture and inspire incoming students.
Our team can help be the spark to the
movement and will plant the seed that
Associated Students will follow through
with.
Figure C1.3-Volunteering at SDSU open
house
Aztec Energy
DESIGN- BUILD
36
2014 Green Energy Challenge
Outreach
Method 3:Lecture to Students and Other Groups
When it comes to spreading the word and
awareness our team is determined to reach out to
as many people that will hear it. As a student
organization we like to inform other students and
organizations of our efforts. Aztec Energy spreads
the importance of the electrical construction
industry, local NECA chapter events, and
sustainable habits in general. This year we have
decided to help out Construction Tech Academy
at Kearny High School and raise energy
awareness among the students. Our goal was to
educate the students on the importance of energy
and what they can do in order to save energy at
school and in their households. The students
were also educated on what the efforts of Aztec
Energy are in helping their school retrofit their
gymnasium. An open
questionnaire was given to the student in order for
them to ask any questions that they had about
energy conservation, or even just their future with
college. Aztec Energy's goal is to help the
students understand the importance of energy
and to help guide them into the correct path when
it is time for college.
Figure C1.4-Kearny High School
presentation
Figure C1.5-Kearny High School
presentation
Method 4: Social Media
As social networking is becoming increasingly important in
our society, our team has been taking note. We have been
informing communities in San Diego through these social
networks. For example, we like to take advantage of the most
popular social media; Facebook. We keep our followers
informed on upcoming events and news via our Facebook
page. Through daily posts, we spread awareness across
campus and encourage students to be sustainable by
showing them examples of how to reduce energy. In addition
it is a great way to recruit new members. QR Code has been
a great contributor to our awareness because of the
popularity of smart phones. Anyone is able to download an
application and they are able to scan the barcode right away.
This takes them to our website. It is a very easy and effective
way to reach out to new members. Please try it for yourself!
Aztec Energy
DESIGN- BUILD
37
2014 Green Energy Challenge
Testing and Feedback
Testing, feedback, and Implementation of plan completed
Currently, NECA SDSU’s proposal to the client has not yet been implemented. In dealing
with a K-12 school, there are many steps to be taken before the School District will give the
approval to use the whole plan or parts of the plan. Our team has already taken some of the
initial steps by gaining recognition and support from members of the school. Specifically,
our team has been in direct contact with the principal of the school, members of SDGE who
are involved with the school’s operations, and members of the School District’s
sustainability efforts who have been involved with the school’s sustainability upgrades for
the last 16 years. The people who can help us make a difference on this high school
campus already gave us their support and have joined the discussion about our proposal.
Nordstrom Christer, who helped to design the current lighting control system, commented
that one day when the funding is available that the School District would like to upgrade to
LED fixtures, but it is preferred to do so when the funding is made available from either prop
39 or when the price of LEDs has dropped down low enough. We’ve been praised for
creating a plan that is compliant with the new 2014 Title 24 energy codes that is planned to
be effective in July. Furthermore, our team has created a new partnership with the school in
which our team is expected to come back in the following years to help mentor the high
school students. By staying connected to the school’s sustainability curriculum, we are
guaranteed to keep the discussion open about future retrofits.
Aztec Energy
DESIGN- BUILD
38
39
40
41
2014 Green Energy Challenge
Local NECA Chapter Interaction
Aztec Energy would like to thank the following individuals and organizations that have been
our mentors for this competition. We could not have been as successful without the
guidance and patience of the following:
The NECA Student Chapter would not exist if it were not for the local NECA chapter. We
have worked very closely with the local chapter in many ways from attending training
sessions to presenting at the monthly chapter meetings. In addition we were able to interact
with local large contractors such as Dynalectric, Chula Vista Electric, and HMT Electric. This
was a great opportunity in where we got to learn from the experts. Aztec Energy was able to
attend "Understanding Rates, Bills and Benchmarking" learning session which was done by
David M. Wylie from ASWB Engineering. Scot Hemingway of Dynalectric came with us to the
Kearny High School gymnasium and consulted us on lighting, helped identify controls
system, and answered all of our questions. Aztec Energy also got to tour SDG&E Innovation
Center, where we got many great ideas such as solar tubes and Big Ass Fans for the
gymnasium. Possibly the most beneficial to our members was the opportunity for internships
thanks to our local NECA chapter. Because of the quality of work that our members
showed, students were offered internships.This is the most rewarding benefit that the local
NECA chapter provided for us, aside from the experience and knowledge that enabled us to
secure these positions. Our experiences with the local chapter only strengthen our views of
this great organization. We all plan to continue our involvement and help give back just like
the chapter has done for us.
Figure C4.1- SDGE Innovation Center
Figure C4.2- Kearny High School walk
Aztec Energy
DESIGN- BUILD
42
Appendix A-Lighting Luminaire Schedule
STATISTICS
Description
Symbol
Workplane
Avg
Max
Min
Max/Min
Avg/Min
22.8 fc
34.7 fc
10.5 fc
3.3:1
2.2:1
Label
Qty
LM-1
16
Catalog Number
Description
Lamp
File
Solatube SkyVault
Clear Sky, Sun at 40 deg.,
SM74DSO-DPSM74DS-O-DP-B-L2 Sun at 40 deg.
B-L2Daylighting System with
CLR40.ies
Single-Glazed Dome (Type
DP) and Base Unit (Type
B) with Prismatic (Type
L2) Diffuser.
15.4 15.3 21.1 25.5 22.3 18.5 22.7 26.4 22.7 18.5 22.3 25.5 21.1 15.3 15.4
16.1 18.1 22.7 26.6 23.9 21.5 24.4 27.6 24.4 21.5 23.9 26.6 22.7 18.1 16.1
20.6 23.1 26.6 29.9 28.0 26.7 28.5 30.9 28.5 26.7 28.0 29.9 26.6 23.1 20.6
Lumens
LLF
Watts
16732
0.92
0
gym
Sun West
Symbol
Kearny H.S.
LUMINAIRE SCHEDULE
19.9 20.8 26.0 33.6 27.4 24.5 28.0 34.7 28.0 24.5 27.4 33.6 26.0 20.8 19.9
17.2 17.4 23.8 28.9 25.3 21.2 25.8 30.0 25.8 21.2 25.3 28.9 23.8 17.4 17.2
16.8 18.9 23.7 27.8 25.2 22.7 25.7 29.0 25.7 22.7 25.2 27.8 23.7 18.9 16.8
20.9 23.3 27.0 30.3 28.4 27.1 29.0 31.4 29.0 27.1 28.4 30.3 27.0 23.3 20.9
19.9 20.8 26.0 33.6 27.4 24.6 28.0 34.7 28.0 24.6 27.4 33.6 26.0 20.8 19.9
17.0 17.0 23.5 28.5 24.9 20.8 25.4 29.7 25.4 20.8 24.9 28.5 23.5 17.0 17.0
16.3 18.2 23.0 27.0 24.3 21.8 24.9 28.2 24.9 21.8 24.3 27.0 23.0 18.2 16.3
20.0 22.2 25.8 29.0 27.0 25.7 27.6 30.0 27.6 25.7 27.0 29.0 25.8 22.2 20.0
18.4 19.1 24.1 31.6 25.3 22.4 25.8 32.6 25.8 22.4 25.3 31.6 24.1 19.1 18.4
14.5 14.2 20.4 25.2 21.4 17.3 21.9 26.1 21.9 17.3 21.4 25.2 20.4 14.2 14.5
11.3 12.3 16.9 20.9 17.8 14.9 18.2 21.7 18.2 14.9 17.8 20.9 16.9 12.3 11.3
Designer
HS
Date
May 1 2014
Scale
Drawing No.
10.5 10.8 14.3 17.2 15.0 12.8 15.3 17.9 15.3 12.8 15.0 17.2 14.3 10.8 10.5
Plan View
1 of 1
Scale 1" = 25'
43
Proposed
Appendix
B-Proposed
Lighting/Sensors
Lighting/Sensor Layout
Layout
Office
Coaches
Offices
Elec.
Mechanical
Room
Room
Wrestling
Room
Boys Locker Room
Gymnasium
Coaches
Offices
Varsity
Locker
Rooms
Storage
Snack
Bar
Emergency
Battery Panel
Showers
Janitor's
Closet
Bathroom
Bathroom
Boys
Bath
(16)
(4)
Girls
Bath
Unlensed (standard)
9-24L pictured
I-beam LED
Skyvault M74 A Solatube
S
(61)
(12)
I-beam LED
(6)
Photocell sensors
(20)
Occupancy sensors
STL LED
44
44
Appendix C-Estimate-Preconstruction Services
Kearny High School Gym Retrofit
Aztec Energy
Start:
Complete:
6/16/14
8/14/14
1 Months
900 - PRECONSTRUCTION SERVICES
20.00% Tax Rate: 8.000%
LA Burd:
COST
CODE
100-090
100-100
DESCRIPTION
Senior Engineer
Project Manager
LABOR
UNIT
MATERIAL
UNIT
SUB-
LINE ITEM
PRICE
COST
PRICE
COST
PRICE
CONTRACT
TOTALS
UNITS
% Time on
Project
1.00
MO
85%
5,500
5,610
1.00
MO
15%
5,100
918
QTY.
Subtotal Staff
100-108
100-109
100-115
100-116
100-125
100-133
San Diego, CA
UNIT
5,610
918
$
6,528
Office Supplies
Telephone/Fax/Computer Lines
Computers
Fax / Copy Machines
Printing & Blueprinting
Building Permits & Fees
6,528
1.00
MO
50
60
100
108
168
1.00
MO
50
60
100
108
168
1.00
MO
150
180
1.00
MO
100
120
100
108
228
1.00
LS
300
360
1000
1,080
1,440
1.00
LS
2,000
2,400
Subtotal Temporary Requirements
TOTAL PRECONSTRUCTION
COMMENTS
$
180
2,400
3,180
1,404
9,708
$ 1,404
$
$
-
$
4,584
11,112
List of Inclusions:
1 Bi-Weekly meeting assistance
2 Estimates as follow:
a. Design Phase. This estimate includes design, quantity take-off, major subcontrator budget numbers, site
requirements. This activity is expected to take 4 weeks.
Aztec Energy
DESIGN- BUILD
45
Appendix D-Estimate-General Conditions
Kearny High School Gym Retrofit
Aztec Energy
Start:
6/16/2014
Complete:
8/14/2014
1000 - GENERAL CONDITIONS
2 month overall duration
PHASE CODE
DESCRIPTION
900-101
900-102
900-103
Project Manager
General Foreman/Gas/Truck
Laborer
1000-102
Sales & Use Tax Rate:
8.000%
Cost Type 1
UNIT
LABOR
PRICE
COST
% Time
Quantity UOM On Proj.
$
$
$
5,100
4,300
1,600
$ 10,200
$ 8,600
$ 1,600
2
UNIT
PRICE
3
MATERIAL
COST
UNIT
PRICE
4
SUBCONTRACT
UNIT
PRICE
LINE ITEM
TOTALS
EQUIPMENT
2.0
2.0
2.0
MO
MO
MO
100%
100%
50%
Office Trailers
2.0
MO
N/A
1000-103
Office Supplies
2.0
MO
N/A
$
200
$
432
$
432
1000-104
Storage Sheds & Bins
1.0
LS
N/A
$
1,000
$
1,080
$
1,080
1000-105
Temp Bathrooms
2.0
MO
N/A
$
350
1000-107
Telephone/Fax/Computer Lines
2.0
MO
N/A
$
200
$
432
$
432
1000-108
Install Phone and computer Lines
1.0
LS
N/A
$
500
$
500
$
500
$
540
$
1,040
$
300
$
600
$
300
$ 18,800
Subtotal of Staff Costs
$
648
$
648
$
$
300
175
$
$
600
$
$
$
10,200
9,248
1,600
$
19,448
$
350
600 1 Trailer
1000-109
Temp. Power - Consumption/Meter
2.0
MO
N/A
$
300
$
648
$
1,248
1000-110
1000-111
Drinking Water For Trailer
Temp Fencing
2.0
2.0
MO
MO
N/A
N/A
$
50
$
108
$
$
108
2,000
1000-112
Onsite Fax/Copy Machines
2.0
MO
N/A
$
$
540
1000-113
Trash Containers & Dump Fees
2.0
MO
N/A
1000-114
Mobilization
1.0
LS
N/A
1000-115
1000-116
1000-117
Printing & Blueprinting
As-Built Record Drawings
Construction Signs
Subtotal Temporary Facilities
1.0
1.0
1.0
LS
LS
LS
N/A
N/A
N/A
TOTAL GENERAL CONDITIONS
$
250
$
1,000
$
2,000
540
$
$
500
$
350
$
700
500
$
$
$
$
700
$
500
270
270
216
9,786
1,600
$
$
$
$
270
270
216
4,536
$
2,950
$
700
$
$
$
$
$ 20,400
$
5,184
$
2,950
$
700
$
$
250
250
200
COMMENTS
29,234
Aztec Energy
DESIGN- BUILD
46
Appendix E-Estimate-Construction Costs
Kearny High School Gym Retrofit
Aztec Energy
Start
6/16/14
Complete
8/14/14
1100 - Construction
2 month overall duration
PHASE CODE
DESCRIPTION
Quantity
UOM
Sales & Use Tax Rate:
8.000%
2
UNIT
MATERIAL
PRICE
COST
Cost Type 1
UNIT
LABOR
PRICE
COST
3
UNIT
PRICE
SUBCONTRACT
LINE ITEM
TOTALS
COMMENTS
Gymnasium
1100-100
Demolition
64.0
HRS
$
58.15
$
3,722
1100-101
New Lighting Drops - Gym
12.0
EA
$
58.15
$
349
$
125
N/A
$
3,722
$
1,620
N/A
$
1,969
16,773
1100-102
New Lighting - High Bay LEDs
12.0
EA
$
58.15
$
1,221
$
1,200
$
15,552
N/A
$
1100-103
New Lighting - Ceiling Mount
18.0
EA
$
58.15
$
848
$
286
$
5,560
N/A
$
6,408
1100-104
Low Voltage Wiring
1.6
LF*
$
58.15
$
3,442
$
200
$
346
N/A
$
3,788 Plenum Rated
3,212
1100-105
100 Watt High bay Safety Lights
4.0
EA
$
58.15
$
188
$
700
$
3,024
N/A
$
1100-106
Exit Lights
3.0
EA
$
58.15
$
262
$
35
$
113
N/A
$
375
1100-107
New Power Wire
1.8
LF*
$
58.15
$
5,443
$
220
$
428
N/A
$
5,871
1100-108
New Sensors
23.0
EA
$
58.15
$
1,003
$
85
$
2,111
N/A
$
3,114
1100-109
Energy Dashboard
1.0
EA
$
58.15
$
291
$
1,000
$
1,080
N/A
$
1,371
1100-110
Energy Dashboard - Software
1.0
EA
$
58.15
$
116
$
3,000
$
3,240
N/A
$
3,356
1100-111
New Sub Meter
Subtotal Gymnasium
1.0
EA
$
58.15
$
$
174
17,059
$
3,652
$
$
3,944
37,018
N/A
$
$
4,119
54,078
3,722
$
-
Locker Rooms
1100-112
Demolition
64.0
HRS
$
58.15
$
3,722
N/A
$
1000-113
1100-113
1000-114
1100-114
1000-115
Low Voltage Wiring
New Sensors
New Lighting
Exit Lights
New Sub Meter
0.3
16.0
43.0
2.0
1.0
LF*
EA
EA
EA
EA
$
$
$
$
$
58.15
58.15
58.15
58.15
58.15
$
$
$
$
$
645
465
2,025
174
174
$
$
$
$
$
300
50
286
35
3,652
$
$
$
$
$
97
864
13,282
76
3,944
N/A
N/A
N/A
N/A
N/A
$
$
$
$
$
743 Plenum Rated
1,329
15,307
250
4,119
1100-115
Computer in Coaches Office
Subtotal Locker Rooms
1.0
EA
$
58.15
$
$
58
7,265
$
1,000
$
$
1,080
19,343
N/A
$
$
1,138
26,607
Solar
1100-116
Set Estanchions
80.0
EA
$
58.15
$
15,119
$
150
$
12,960
N/A
$
27,957
1100-117
1100-118
1100-119
1100-120
1100-121
Wire to Inverter
Modules
Wire Modules
Sub Meter
Inverter
Subtotal Solar
1.8
80.0
1.4
1.0
1.0
LF*
EA
LF*
EA
EA
$
$
$
$
$
58.15
58.15
58.15
58.15
58.15
$
$
$
$
$
$
9,537
12,502
12,502
872
2,733
53,265
$
$
$
$
$
350
345
230
3,652
6,000
$
$
$
$
$
$
680
29,808
348
3,944
6,480
54,220
N/A
N/A
N/A
N/A
N/A
10,217
42,310
12,850
4,816
9,213
107,364
$
-
$
$
$
$
$
$
Subcontracts
1100-122
1100-123
Solar Tube Subcontract
Mechanical Subcontract
1.0
1.0
LS
LS
N/A
N/A
N/A
N/A
1100-124
Roofing Subcontract
1.0
LS
N/A
N/A
1100-125
Glass and Glazing Subcontract
Subtotal Sbcontracts
1.0
LS
N/A
N/A
$
$
11,000
15,895
$
$
11,000
15,895
$
$
$
3,700
$
3,700
$
$
$
$
TOTAL BUILDING BUDGET
11,000 Includes Flashings at ceiling
15,895 Big Ass Fans
-
Excluded
3,700 Windows in Locker Rooms
30,595
218,644
NOTES
LF* - per 1000 linear feet
Ave Labor Rate $
58.15
Foreman
$
66.12
Journeyman
$
62.18
Apprentice
$
29.54
Standard Productivities were used from the NECA Manual of Labot Units 2013-2014
Aztec Energy
DESIGN- BUILD
47
Appendix F-Financial-Solar ROI
48
2014 Green Energy Challenge
Appendix G-Financial-Lighting ROI
Title
Aztec Energy
DESIGN- BUILD
49
2014 Green Energy Challenge
Appendix H-References
Title
"Sub Metering Solutions." Leviton. Leviton, n.d. Web.
PG&E online solar tool:
"Architecture Resources at the PEC." Architecture Resources at the PEC.
N.p., n.d. Web. 05 May 2014.
"Portfolio Manager." ENERGY STAR : Portfolio Manager. N.p., n.d. Web. 05
May 2014.
"California Solar Initiative (CSI) - Go Solar California." California Solar
Initiative (CSI) - Go Solar California. N.p., n.d. Web. 05 May 2014.
"Welcome." Sdge Home. N.p., n.d. Web. 05 May 2014
"The California Clean Energy Jobs Act (Proposition 39)." The California
Clean Energy Jobs Act (Proposition 39). N.p., n.d. Web. 05 May 2014.
"Proposition 39 - California Clean Energy Jobs Act." Past Funding Profile (ID
3435): (CA Dept of Education). N.p., n.d. Web. 05 May 2014.
"Sdge Rebates." Sdg&e Rebates. N.p., n.d. Web.
<http://www.sandi.net/cms/lib/CA01001235/Centricity/Domain/43/AE%209-2
7-13%20revised%20on%2010-8-13.pdf>.
Aztec Energy
DESIGN- BUILD
50