ISBA Ag Law Seminar Pipeline Outline_Draft v3
Transcription
ISBA Ag Law Seminar Pipeline Outline_Draft v3
REPRESENTING LANDOWNERS IN PIPELINE CASES AND EASEMENT NEGOTIATIONS Part 1: Introduction I. Overview Many similarities to electric transmission lines in terms of regulatory approval and easement terms and conditions. This outline will not repeat the information applicable to transmission lines (which was provided separately) that also applies to pipelines. II. Recent Pipeline projects before the Illinois Commerce Commission A. Cases pending before the ICC i. Explorer Pipeline Company – ICC 13-0433 From the Petition (¶15) – Explorer will consult with landowners along the route and seek to acquire all necessary easements through good-faith negotiations. Explorer has engaged experienced land valuation and R-O-W consultants/land agents, is undertaking land valuation analyses, will conduct all requisite surveys, and has established an Illinois field office. Explorer intends to offer full fee value for the necessary acreage for easements even though the land will actually be impressed only with an easement interest. Explorer will fully compensate landowners for crop damage and will restore all R-O-W areas as closely as possible to their preconstruction state. Explorer is working with IDOA to develop and AIMA modeled on those reached by IDOA and other pipelines. Explorer has developed a standard easement document template to use in negotiation. Requisite informational filings have been or are being made as required by 83 IL Admin. Code Part 300. Explorer’s request for eminent domain authority is “purely contingent.” Recourse to condemnation would only be as a last resort, and efforts to reach agreement will continue even if the condemnation process has to be invoked. Witnesses – Engineering/Routing, Finance, Energy consultant (need for project) ii. Enbridge Eminent Domain Petition – ICC 13-0446 Follow up to grant of authority issued (certificate in good standing authorizing Enbridge to operate as a common carrier by pipeline) in ICC 07-0446 for the Southern Access Extension Pipeline, 165 miles of a 36-inch liquid petroleum pipeline from Pontiac to Patoka. ICC had deemed it premature in the prior proceeding to grant eminent domain authority under PUA Section 8-509, instead directing Enbridge to engage in further negotiations with affected landowners. Enbridge described the progress it had made in acquiring easements since the 2007 docket order and asserted it now needed an 8-509 order due to its inability to negotiate easements with remaining landowners. Enbridge introduced the testimony of an expert who introduced land market studies to show that the payments being offered to landowners are 1 supported by market data. Enbridge also offered the testimony of its Manager of Land Services pertaining to Enbridge’s efforts to acquire the rights-of-way necessary for the pipeline project. The reasons for the considerable gap in time between the original ICC proceeding and the new Petition are the appeals of the ICC’s prior order (concluded in March 2011) and two federal district court challenges to certain of Enbridge’s easement rights, along with an appeal to the 7th Circuit. Delays in increases in demand for petroleum transport also contributed to the delays. Enbridge described in detail its more recent activities and efforts to negotiate rights-ofway. Petition to Intervene filed by Attorney Thomas Pliura ostensibly on behalf of the landowners named in the Petition. Enbridge filed Motion to Strike and Dismiss on several grounds. ALJ Jones issued a ruling that is included with the materials as it covers several aspects and issues of the case. ICC Staff gas engineering witness filed testimony in support of Enbridge’s request for eminent domain authority. The basis for the Staff witness’ support was his understanding that Enbridge has made “reasonable attempts to acquire the outstanding land rights through the negotiation process, but that further attempts to acquire the necessary land rights are not expected to be successful.” Relevant factors, as set forth in the Order in ICC 13-0456 (Ameren): 1. The number and extent of contacts with landowners 2. Whether the utility (pipeline) has explained its offer of compensation 3. Whether the offers of compensation are comparable to offers made to similarly situated landowners 4. Whether the utility (pipeline) has made an effort to address landowner concerns 5. Whether further negotiations will likely prove fruitful in reaching negotiated settlements A copy of the Enbridge Petition for Eminent Domain Authority is included for reference. Also included is a copy of ALJ Larry Jones’ ruling on a Motion filed by Enbridge to deny intervention filed by Thomas Pliura; as the ruling touches on several issues pertaining to the proceeding, the right to intervene, and the scope of the proceeding. B. Another Recent ICC Proceeding ICC 09-0054 Application of CenterPoint Energy – Illinois Gas Transmission Company for Certificate Authorizing and Directing Construction, Abandonment, and Operation of a Natural Gas Pipeline and Granting Authority to Exercise Eminent Domain Pipeline’s application to abandon a 55-mile segment of its natural gas pipeline system in southern Illinois and to construct a 2.2 mile pipeline, and to exercise eminent domain; filed under Sections 15-401, 8-503 and 8-509 of the PUA. The ICC granted the application except for 2 the request under Section 8-509. The Order, at p. 12, stated: “Because the Commission is concerned about the accuracy of representations made to landowners along the existing pipeline, it is hesitant to assume that the negotiations with landowners along the route of the proposed 2.2-mile pipeline will be free of any miscommunications, whether intentional or not.” Part 2: Proceedings Under 220 ILCS § 5/15-401 I. Sources of Law A. Public Utilities Act [220 ILCS 5/1-101 et seq.] Certificate in Good Standing under Section 15-401 of the Common Carrier by Pipeline Law, a part of the Public Utilities Act: (220 ILCS 5/15-401) Sec. 15-401. Licensing. (a) No person shall operate as a common carrier by pipeline unless the person possesses a certificate in good standing authorizing it to operate as a common carrier by pipeline. No person shall begin or continue construction of a pipeline or other facility, other than the repair or replacement of an existing pipeline or facility, for use in operations as a common carrier by pipeline unless the person possesses a certificate in good standing. (b) Requirements for issuance. The Commission, after a hearing, shall grant an application for a certificate authorizing operations as a common carrier by pipeline, in whole or in part, to the extent that it finds that the application was properly filed; a public need for the service exists; the applicant is fit, willing, and able to provide the service in compliance with this Act, Commission regulations, and orders; and the public convenience and necessity requires issuance of the certificate. Evidence encompassing any of the factors described in items (1) through (9) of this subsection (b) that is submitted by the applicant, any other party, or the Commission's staff shall also be considered by the Commission in determining whether a public need for the service exists under either current or expected conditions. The changes in this subsection (b) are intended to be confirmatory of existing law. For crude oil pipelines, are nine enumerated factors the ICC is to consider in deciding whether a proposed pipeline is required under the public convenience and necessity. The pipeline, in seeking approval under this section, has the option to apply for approval of a specific route or, instead, a route of a specific width, up to 500 feet, within identified areas. The pipeline may request any other approvals (including eminent domain authority) needed to complete the pipeline as part of the same application. All landowners along a proposed project route, or all potentially affected landowners within a proposed project route width, are to be notified within 30 days after the filing. 3 Section 15-401(d) provides: If the Commission grants approval of a project route width as opposed to a specific project route, then the common carrier by pipeline must, as it finalizes the actual pipeline alignment within the project route width, file its final list of affected landowners with the Commission at least 14 days in advance of beginning construction on any tract within the project route width and also provide the Commission with at least 14 days notice before filing a complaint for eminent domain in the circuit court with regard to any tract within the project route width. The ICC must issue its decision within one (1) year after the application is filed; extendable up to six more months if the ICC finds, after the initial testimony, that the extension is needed due to the number of landowners affected and complexity of issues. An expedited schedule may be set if the ICC determines the public interest requires it. Within six (6) months after the ICC order approving a route or a route width, the pipeline may apply for “minor route deviations outside the approved project route width, allowing for additions or changes to the approved route to address environmental concerns encountered during construction or to accommodate landowner requests.” Section 15-401(f). The ICC must approve the route deviations within 45 days unless a written objection is filed within 20 days. Hearings are limited to the reasonableness of the specific variation proposed. ICC rules may include additional expedited proceeding options. Part 3: Eminent Domain I. Sources of Law A. PUA a. Section 8-509 provides that when necessary for construction of facilities authorized under Sections 15-401 and 8-503, the ICC may authorize the pipeline to exercise eminent domain. B. Eminent Domain a. Eminent Domain Act [735 ILCS 30/1-1-1, et seq.] 4 Part 4: Negotiating Pipeline Easements for Landowners A. Considerations in Assisting Clients in Negotiating Pipeline Easements: 1. Who has the bargaining power? Does the pipeline have ICC condemnation authority? If the Pipeline does not, Landowner has much greater leverage. 2. If they do have condemnation authority, keep records of all communications (or lack thereof) in order to have possible foundation to claim lack of good faith negotiations. (Later consideration if the matter goes to condemnation). 3. Compensation for easement is important but is not everything. a. Get an appraisal the property. b. Understand how the pipeline will affect the remainder value of c. Talk to your client and discuss any future use or exploitation of the property. Is there any mineral deposit, frac sand, natural gas, coal, etc on the property? 4. Recite character and uses of Grantor’s property on which the easement is to be granted. Ensure you limit the easement to what your client was paid (no other grants). 5. Confine the pipeline’s installation activities to the specific construction easement area negotiated. When drafting the construction easement make sure the access areas are explicitly described; avoid generalities. area shown. a. Include property diagram/ survey of the construction easement b. The Construction process can create serious soil issues: 1) Compaction (heavy equipment, trucks, etc.) 2) Soil Mixing (failure to maintain clay/ loam segregation has long-term impact on productivity) 3) Drainage/ Field tile (must be repaired - issue may not present itself for some time). 5 c. Demand that the farmer/ landlord be paid (hourly) to assist/ supervise the installation of the pipeline. (Farmers want to know what is happening to their property). d. Demand additional compensation if the pipeline plans to use other land of grantor for construction or staging (control valves/ access pointstypically fee price for land). 6. The Permanent easement is typically much smaller a. How will the easement restrict current use? b. How does it impact future farming or future development? 7. Grantor. Ensure that the Notice Provision is adequate for Landowner/ a. Describe any periodic maintenance. b. Provide for any other time when Grantee will be performing work, and specifying type of equipment that will be on-site. 8. Limit Grantee pipeline’s right to relocate pipeline after initial installation, or adding a second parallel pipeline or other facilities within easement area (there must be a separate negotiation for each pipeline). 9. Understand and specify depth of pipeline, and provide for protection of drainage/ field tile. 10. Crop damage during installation as well as anytime thereafter during easement period; compaction remediation and damages, and damages to fences and other grantor property, should be included. Specify method of determining damages if parties cannot agree, such as independent persons who can arbitrate the damages. 11. Pipeline may want right to clear certain amount of land adjoining the easement area, but this should be limited to easement area only. Specify that grantor may utilize land for any purpose except as it will interfere with the pipeline installation or operations; any limitations on grantor should be specifically described, e.g., grantor will not excavate within easement area without notice to and approval from grantee. 12. Include clause by which grantee indemnifies grantor for damages and injuries resulting from grantee’s activities or presence on grantor’s property (including any and all environmental related cleanup). Provide for grantor 6 protection from mechanics liens and other claims against grantee that could affect grantor or grantor’s property. 13. Provide for removal of pipeline and restoration of land if abandoned (and define “abandon”). 14. Incorporate AIMA into easement agreement. 15. If old pipeline easement already exists and pipeline wants to use it for new project, be sure to determine whether pipeline needs any further rights (such as extra width of easement area) that can be used to trigger a renegotiation and re-drafting of easement agreement. 16. Get tax advice as to proper treatment of compensation, including whether portion of compensation is considered a sale (subject to capital gain treatment) and what portion is rental income or damage compensation (ordinary income). 17. See draft easements attached. 7 STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION ENBRIDGE PIPELINES (ILLINOIS) L.L.C. Petition pursuant to Section 8-509 ofthe Public Utilities Act to Take Private Property as Provided by the Law of Eminent Domain. ) ) ) Dkt. No. _ __ ) ) PETITION FOR EMINENT DOMAIN AUTHORITY Joel W. Kanvik Amy Graham Back Enbridge Energy Company, Inc. 1409 Hammond A venue Superior, Wisconsin 54880 (715) 398-4500 Gerald A. Ambrose Dale E. Thomas G. Darryl Reed Sidley Austin LLP One South Dearborn Chicago, Illinois 60603 (312) 853-7000 Attorneys for Petitioner July 22, 2013 TABLE OF CONTENTS Page INTRODUCTION ....................................................................................................................... .... 1 EN BRIDGE BACKGROUND ........................................................................................................ 4 STATUTORY PROVISION ........................................................................................................... 5 ENBRIDGE EXPANSION PROGRAMS ....................................................................................... 5 PROJECT STATUS ......................................................................................................................... 8 EASEMENT NEGOTIA TIONS .................................................................................................... l 0 LUXOR EASEMENTS ..................................................................................................... 11 NON -LUXOR EASEMENTS ...................................................................... ..................... 14 NEGOTIATIONS AT IMPASSE .................................................................................................. l6 CONCLUSION .............................................................................................................................. 21 STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION ENBRIDGE PIPELINES (ILLINOIS) L.L.C. Petition pursuant to Section 8~509 of the Public Utilities Act to Take Private Property as Provided by the Law of Eminent Domain. ) ) ) ) ) Dkt. No. _ __ PETITION FOR EMINENT DOMAIN AUTHORITY INTRODUCTION Enbridge Pipelines (Illinois) L.L.C. ("Enbridge lllinois"), through this Petition, hereby renews its request, originally made in Docket No. 07-0446, for an order pursuant to Section 8509 of the Public Utilities Act ("PUA''), 220 ILCS 5/8-509, authorizing it to acquire private property in the manner provided for by the law of eminent domain. Such grant of authority is necessary for Enbridge to construct its new liquid petroleum pipeline - the Southern Access Extension (''SAX") Pipeline- of approximately 165 miles in length from near Pontiac, Illinois to Patoka, Illinois, for which the Commission previously issued a "Certificate In Good Standing" in Docket No. 07~0446. This Petition is also supported, in part, by the Affidavit of John McKay, filed concurrently herewith. In its Order in Docket No. 07-0446, dated July 8, 2009 (''Order"), the Commission found that ''a certificate in good standing authorizing Petitioner to operate as a common carrier by pipeline should be granted" to Enbridge Illinois for the SAX pipeline. Order at 69. The Commission also found that "the proposed pipeline is necessary and should be constructed, to promote the security or convenience of the public, pursuant to Section 8~503 of the Public Utilities Act." !d. at 70. The Commission therefore ordered that a Certificate In Good Standing be granted as follows: "IT IS HEREBY CERTIFIED, subject to the conditions imposed in this order, that Enbridge Pipelines (Illinois) L.L.C. is authorized, pursuant to Section 15-401 of the Common Carrier By Pipeline Law, to construct, operate and maintain the proposed 36-inch pipeline as described in this order and to operate as a common carrier by pipeline within an area sixty feet wide and extending approximately 170 miles along the route identified in Attachments A and B to the petition in Docket No. 07-0446." Although the Commission granted to Enbridge Illinois the requested Certificate in Good Standing and authority to construct the SAX pipeline, the Commission did not at the time grant Enbridge Illinois' further request under Section 8-509 of the PUA for eminent domain authority. The Commission concluded that .. [h]aving reviewed the record in this case and the Commission's findings in recent orders in transmission line proceedings, the Commission believes that it would be premature to grant eminent domain authority under Section 8-509 at this time." Order at 67. The Commission based its conclusion in part on a determination that "the record does not support a finding that further negotiations would be pointless" and its stated belief"that additional negotiations would be appropriate." /d. Indeed, the Commission stated its view that the very entry of its Order "in which a certificate is granted and a line's route approved," along with "decisions in federal court involving the status of the easements on the CIPC pipeline and other factors," "should ... facilitate the negotiation process" by removing or at least mitigating a number of uncertainties and impediments to fruitful negotiations. /d. at 68. The Commission made equally clear, however, that "[i]n the event Enbridge Illinois is still unable to obtain the necessary easement rights through the negotiation process," it could "renew its request for authority to exercise eminent domain authority by filing a petition for such relief under Section 8-509 of the PUA and demonstrating that it has made reasonable attempts to 2 obtain easements, through good-faith negotiations, with respect to properties for which it is seeking eminent domain." 1 !d. Accordingly, Enbridge Illinois, by this Petition and pursuant to Section 8-509 of the PUA, is hereby renewing its request for eminent domain authority for the SAX pipeline as to the properties, along with the owners thereof, described herein and specifically identified in Attachment A hereto. As explained in detail below, experience with property owners along the approved route since the Commission's Order shows that such authority is necessary for the efficient completion of the pipeline. To date, Enbridge Illinois has obtained 405 agreements with landowners. As a result, when considering the 405 obtained agreements along with the 114 tracts where existing Luxor rights will be exercised, Enbridge lllinois presently has easement rights on approximately 76 percent of the 679 tracts comprising the SAX pipeline route. Enbridge Illinois still lacks easement rights, however, in the 148 tracts listed in Attachment A. For those tracts, "further negotiations" have become "pointless" because the parties are at impasse. Thus, through this Petition, Enbridge Illinois now seeks eminent domain authority solely for these tracts. It remains the policy, practice, and intention of Enbridge Illinois to acquire necessary interests in real estate through negotiated agreements with property owners to the maximum extent possible. Indeed, even with the filing of this Petition and the grant by the Commission of the requested eminent domain authority, En bridge is continuing and will continue to seek the necessary easements and temporary work space ("TWS") agreements through negotiation with 1 In the Docket No. 07-0446 proceeding, Enbridge 1llinois represented to the Commission that its good-faith offers would be based upon "paying full fee value for both fee interests and permanent easements used for the right-of-way as well as above-market rentaHype values, generally thirty percent (30%) of fee value, for temporary workspace easements which last only during construction." Application For Certificate In Good Standing And Other Relief, Dkt. 07-0446, Aug. 16, 2007, at 24. See also Testimony of Douglas B. Aller, Dkt 07-0446, Enbridge Ex. 2, at II. As explained in more detail infra, in an effort to increase agreement to easements, Enbridge has now increased its good faith offers to 125 percent of fee value for permanent easements and SO percent of that amount for temporary work space grants. 3 the landowners listed in Attachment A. But where, as is now the case, certain property owners refuse to negotiate, indicate they will negotiate only on unreasonable terms, fail to respond to attempts at contact, or seek unreasonable amounts, a grant of eminent domain authority is needed to remove the incentive to hold out and engage in uneconomic rent-seeking. ENB~DGEBACKGROUND 1. Enbridge Illinois is a Delaware limited liability company with its principal office located at 1100 Louisiana, Suite 3300, Houston, Texas 77002 (ph. 713-821-2000). En bridge Illinois is an indirect, wholly-owned subsidiary of Enbridge Inc. ("Enbridge") and as such is an affiliate of Enbridge Energy Partners, L.P. ("Enbridge Partners"), Enbridge Energy, Limited Partnership ("Enbridge Energy"), and Enbridge Pipelines (FSP) L.L.C. (""Enbridge FSP"). Enbridge is a leading company in the transportation and distribution of energy in North America. Through its subsidiary Enbridge Pipelines Inc., Enbridge operates pipelines that, inter alia, traverse western Canada to transport crude oil east and south to the United States and eastern Canada. En bridge Partners, through subsidiaries such as Enbridge Energy, owns and operates a series of liquid petroleum pipeline systems in the United States, including the "Lakehead System," the U.S. portion of Enbridge's operationally integrated pipeline system which operates in seven Great Lakes states, including Illinois, and the Enbridge Pipeline (North Dakota) L.L.C. system, which operates in the Williston Basin!Bakken Formation area of North Dakota and eastern Montana and ultimately interconnects directly or via affiliates with the Enbridge Mainline System in Clearbrook, Minnesota and Cromer, Manitoba. Enbridge's Spearhead Pipeline, which is owned by CCPS Transportation, L.L.C., operates from Enbridge Energy's Flanagan Terminal near Pontiac, Illinois and transports crude oil to the major national crude oil pipeline hub in Cushing, Oklahoma. Together with the Canadian pipeline systems of Enbridge Pipeline Inc., these systems comprise over 15,000 miles of liquid petroleum pipelines and 4 constitute the world's longest crude petroleum and petroleum liquids pipeline network. They are the primary means of transporting crude oil from Canada to the United States as well as the only pipeline transit system that transports crude oil from western Canada to eastern Canada. Overall, Enbridge's pipelines transport over one-half of western Canada's crude oil production and deliver approximately 15% of U.S. imports of crude oil. 2. Enbridge and its affiliates employ approximately 10,000 people, primarily in Canada and the United States. The common stock of Enbridge is widely held and is publicly traded on both the Toronto Stock Exchange ("TSX:ENB") and the New York Stock Exchange ("NYSE:ENB"). In 2012, Enbridge had total capitalization of Cdn $36 billion and earnings applicable to common shareholders of Cdn $610 million. En bridge maintains its corporate headquarters in Calgary at 425- 1st Street S.W., Calgary, Alberta T2P 3L8 Canada. STATUTORY PROVISION 3. Enbridge Illinois is petitioning for eminent domain authority pursuant to Section 8-509 of the PUA. (220 ILCS 5/8-509). Section 8-509 states, in pertinent part: "When necessary for the construction of any alterations, additions, extensions or improvements ordered or authorized under Section 8406.1, 8-503, or 12-218 of this Act, any public utility may enter upon, take or damage private property in the manner provided for by the law of eminent domain." (220 ILCS 5/8-509). ENBRIDGE EXPANSION PROGRAMS 4. As found by the Commission in its Orders in Docket Nos. 06-0470, 07-0446, and 12-0347, public demand for refined petroleum products in Illinois, the Midwest generally, and across the country requires the importation into Illinois and other areas of immense amounts of crude oil that can be refined into gasoline, diesel fuel, heating fuels, jet fuel, asphalts, 5 petrochemicals, and other items needed by the consuming public. Although conservation efforts and economic cycles have slowed the rate of growth in demand for petroleum products as an energy source, such demand is nevertheless expected to remain strong and will continue to grow in Illinois and throughout the United States as population grows and economic activity expands. Petroleum products will continue to meet the great majority of America's transportation energy needs for the foreseeable future, despite growth in alternative energy sources. 5. Both the heavy and light crude oil produced in western Canada and in the Williston Basin, an area encompassing much of North Dakota, eastern Montana, and southern Saskatchewan within which the hydrocarbon rich area known as the Bakken Formation is located, are economically attractive to American refiners, exist in ample supply, and constitute a reliable and secure resource for Illinois-area and other U.S. refiners. As non-Canadian supplies of crude oil have become less attractive or more unsecure or unreliable, and as Canadian and Bakken supply has increased, Enbridge and its affiliates have acted to expand and extend their pipeline systems through strategic construction programs to increase access to secure and growing Canadian and Williston Basin resources. In the Docket No. 07-0446 proceeding, Enbridge Illinois provided evidence that the SAX pipeline, along with other system facilities and improvements, will afford Enbridge the ability to provide an initial 400,000 barrels-per-day ("bpd") of additional capacity into the Midwestern market area. The SAX pipeline will extend from the Flanagan Terminal to a crude oil hub near Patoka, Illinois in Marion County, where Enbridge owns storage facilities. At the Patoka Terminal, Enbridge and other companies have some 13 million barrels of crude petroleum storage and breakout tankage to facilitate further delivery via connecting pipelines to numerous refineries. By connecting at Flanagan, the SAX pipeline will afford U.S. refiners the capacity they need for movements of crude petroleum to 6 Patoka, where connections exist for movements further south as well as east and west to various market areas. 6. As Enbridge Illinois previously explained, the SAX pipeline is to run underground for approximately 165 miles2 within a 60-foot wide permanent easement right-ofway running from the Flanagan terminal through parts of Livingston, McLean, DeWitt, Macon, Shelby, Christian, Fayette, and Marion Counties to the Enbridge facilities near Patoka. Much of the right~of-way will be either adjacent to or collocated with existing rights-of-way and/or will be partially in an existing right-of-way of the former Central Illinois Pipeline Company ("CIPC"), with which Enbridge Illinois merged in 2006. The CIPC right-of-way is generally referred to as the "Luxor" right-of-way. During construction, an additional 60-foot temporary workspace easement generally will be needed alongside the permanent easement area (extra temporary workspace will be required in some locations, such as road, wetland, and water-body crossings). Order at 6. In its Order, the Commission found that "the proposed pipeline is necessary and should be constructed, to promote the security or convenience of the public, pursuant to Section 8-503 of the Public Utilities Act." Order at 70. The Commission agreed with Staff that '"bringing Canadian petroleum to this [Patoka] hub would provide not only our state, but our nation, with additional crude oil supplies from a friendly and reliable country.'" /d. at 46. The Commission stated that it "also agrees with Staff that 'Illinoisans are also citizens of the United States, and a project that provides access to a secure and reliable energy supply and helps to meet our country's energy needs is a project that benefits Illinois citizens, whether directly or indirectly"' and that "[t]he changing landscape requires us as a nation to re-evaluate our energy supply and transmission network and make sure that it is as reliable and redundant as 2 The SAX pipeline route is now estimated to be 165 miles in length, rather than the 170 miles in length initially estimated. 7 ------------------------- - possible."' !d. at 46.4 7. The Commission then concluded that "[b]ased on the record in the case, including the location of the pipeline which would carry Canadian crude to the major pipeline hub at Patoka, the capacity of the pipeline, the current environment as described by Staff, and other evidence presented, the Commission agrees with Staff that there is a public need for the proposed pipeline.'' !d. at 47. The Commission further held that ••[b]ased on the record of this proceeding and the other findings in this order, and subject to the conditions related to routing imposed herein, the Commission finds that Enbridge Illinois' proposed route for the pipeline is reasonable and it is hereby approved." Order at 57. PROJECT STATUS 7. The SAX pipeline project has progressed slower than anticipated at the time of the Commission's Order for several reasons. Most significantly, the Order was appealed to the Illinois Appellate Court by other parties to the case, and that appeal process was not concluded until the appellate order was issued on October 25, 2010, and the appeal mandate was issued on March 9, 2011. See Pliura Intervenors v. Illinois Commerce Commission, 405 Ill. App. 3d 199 (20 10); Enbridge Pipelines (Illinois) L. L. C., ICC Dkt. 07-0446, Mandate of the Court (Appellate Court, Fourth Dist., March 8, 2011 ). Further, at virtually the same time, and as noted in the Order itself, litigation was underway in two federal district courts in Illinois concerning the validity of En bridge Illinois' easement rights in the fonner CIPC or Luxor pipeline right-of-way. Enbridge Pipelines (IIlinoi!;~ LLC v. Burris, 08-CV-697-DRH, 2010 WL 1416019 (S.D. Ill. Mar. 31, 2010); Enbridge Pipelines (Illinois) L.L.C. v. Burris, 08-CV-697-DRH-CJP, 2010 WL 3038716 (S.D. Ill. Aug. 3, 2010); Enbridge Pipelines (Illinois) LLC v. Burris, 08-CV-697-DRH, 2010 WL 3038501 (S.D. lll. Aug. 3, 2010); and Enbridge Pipelines CV-697-DRH, 2010 WL 3038529 (S.D. Ill. Aug. 3, 2010). 8 (lllinoi~) LLC v. Burris, 08~ Enbridge Illinois ultimately ----- - - - - - - - prevailed on summary judgment motions in all of the cases challenging its right to use the Luxor route for the SAX pipeline. !d. Many of the landowner-plaintiffs in these cases appealed to the federal court of appeals - the United States Court of Appeals for the Seventh Circuit - and Once again, Enbridge Illinois ultimately all the appeals were consolidated for decision. prevailed in the litigation: All the appeals were denied and the judgments in favor of Enbridge Illinois were affirmed in Enbridge Pipelines (Illinois) L.L.C. v. Moore, 633 F.3d 602 (ih Cir. 2011 ). That appeal process, however, did not completely culminate until February of 2011. All of this litigation created uncertainty that the project could successfully go forward, the appeal from the Order by threatening Enbridge Illinois' status as a common-carrier-by-pipeline, and the federal cases by threatening its ability to utilize significant parts of the approximately 165-mile pipeline route, and such uncertainty impeded progress on the project. Moreover, while the appellate litigation was pending, significant economic and petroleum-supply developments occurred that caused delays in the realization of the anticipated transport demand. Such factors as the economic downturn of 2008-2011 -- the so-called "Great Recession" --and the emergence of substantially increased light-crude supplies from the Bakken Formation and elsewhere, as well as industry restructurings such as the disaggregation of integrated entities like Marathon and ConocoPhillips into independent "upstream" and "downstream" entities, caused petroleum shippers and refineries to refrain from commitment to transport obligations. Despite these influences, as the federal government has recognized and declared "[t]he need for [pipeline] infrastructure is particularly acute right now. . .. [and] we must make pipeline infrastructure a • • pnonty ... 11 Presidential Memorandum of March (www.whitehouse.gov/the-press-office/ 20 12/03/22presidentialmemorandum). 22, 2012 According to a Presidential Executive Order of the same date, "the need for pipeline infrastructure is urgent" and 9 "[e]xpanding and modernizing our nation's crude oil and refined products pipeline infrastructure is a vital part of a sustained strategy to continue to reduce our reliance on foreign oil and enhance our nation's energy security," to which ends "it is critical that we make pipeline infrastructure a top priority" (Fact Sheet: www. whitehouse .gov/the-press-office/20 12/03/21 fact~sheet ). Particularly notable in this regard is the dramatic surge in Bakken Formation supply, which had grown from slightly over200,000 bpd in January 2010 to almost 800,000 bpd by July 2012. The demand for such supply, particularly for light crude, has caused refiners such as Marathon, which has three refineries served from the Patoka hub (Canton, Catlettsburg, and Robinson ) to seek transport via the SAX pipeline for several hundred thousand barrels per day of mostly light crude oil. To meet such demand, the SAX pipeline must be in-service by mid-2015. EASEMENT NEGOTIATIONS 8. Despite the fact that the project was delayed by litigation and by economic conditions as just described, even before easement negotiation efforts were expanded in July 2012, Enbridge Illinois had obtained easements on approximately 45 percent of the 679 tracts needed for the project. Of particular relevance to this Petition, Enbridge lllinois has been pursuing a land-acquisition program as described and approved in the certification Order and as is necessary for construction of the pipeline. 9. Enbridge Illinois' efforts to establish the right-of-way necessary for the SAX project both before and since July 20 I 2 generally have taken one of two forms. First, for properties on the Luxor right-of-way, as to which Enbridge Illinois already has easement rights, Enbridge Illinois has negotiated upgraded easement rights and payments, determined that certain re-routes were necessary and therefore some Luxor tracts could not be used at all, or concluded that condemnation will be necessary for a limited number of Luxor tracts because although the 10 tracts must be used, the particular Luxor easements in question have restrictions that make them inadequate as they stand for use in construction and negotiations to upgrade these easements have failed. 10. Second, as to the non-Luxor or "greenfield" properties, Enbridge Illinois' land- acquisition program has followed the procedures and processes approved by the Commission in the certification Order. Enbridge Illinois has made numerous attempts to contact all such landowners through phone, mail, and in-person inquiries. Based on landowner willingness to meet, Enbridge Illinois agents have followed up with onsite visits with the landowners to discuss the project and answer any questions regarding the project Agents have been working with landowners since July 2012, and continue to attempt to acquire easements through negotiations. Such efforts will continue even if condemnation actions have to be filed. 11. Details about each of these paths to obtaining the necessary easements through negotiations, and the reasons why condemnation authority is needed to complete the process, are set forth below. LUXOR EASEMENTS 12. In the proceedings in Docket No. 07-0446, the record showed that the Luxor right-of-way, owned by Enbridge, was expected to be used for approximately 120 miles of the SAX pipeline, and that that use would provide significant benefits. These benefits included a reduction in the potential need to condemn easements and a route that would be predominantly located in rural areas used for agricultural purposes, thereby generally avoiding residential, commercial, and industrial areas. Order at 54-55. 13. The expected benefits from use of the Luxor right-of-way have been realized. There are 371 Luxor tracts along the route ofthe SAX pipeline. Most ofthese are in rural areas 11 used for agricultural purposes; indeed, in those few instances where Enbridge Illinois has had to vary from the Luxor route, as described below, the reason most often was that the area in question has become more developed and/or constrained. On 239 of the Luxor tracts, Enbridge Illinois has negotiated upgraded easements or options with the landowners. These upgrades provided benefits such as bringing the Luxor easement payments up to the same level as Enbridge Illinois is paying for non-Luxor or '"greenfield" easements (fair market value and higher), provisions for adhering to modern pipeline safety and operational maintenance standards, and added language that makes each easement a defined, rather than a blanket, easement (a defined easement applies to a specified location on the property, whereas a blanket easement simply applies to the entire property). Enbridge Illinois also intends to exercise its existing Luxor rights on 114 tracts if the landowners thereof continue to refuse to negotiate. These rights are a matter of contract and have been upheld as such by several federal courts. See pp. 8-9, supra. See also Knight v. Enbridge, No. 12-CV-01244, U.S. Dist. Ct., C.D. Ill., Order (June 19, 20 13). Nonetheless, Enbridge Illinois' offers of upgraded easements and payments on these Luxor tracts remain and will remain open. 14. All together, approximately 78% of the Luxor properties are being used to construct the SAX pipeline. However, for approximately I 02 of the Luxor properties, it has become necessary to divert from the precise 1939 path in which the original CIPC pipe was laid by moving the route to certain non-Luxor tracts. The reasons for these relocations vary, but in each instance the need for deviating from the CIPC route is compelling. Those reasons are briefly summarized in the chart in Attachment B. However, a few examples are useful to illustrate the situations found. Some 27 Luxor tracts are not being used because the existing Luxor pipeline path traverses portions of the Lake Pana reservoir, crosses a weir forming the 12 reservoir, and runs through what are now residential neighborhoods. Another 22 Luxor tracts are not being used in order to reduce impacts to post-1939 residences, principally in Harristown, and to provide better alignment for crossing what is now 1-72. Similarly, nine other Luxor tracts are not being used to avert a new residential area near the City of Vandalia as well as a concrete plant and to permit a more perpendicular crossing by the pipeline of a railroad and interstate highway I-70. Further, seven Luxor tracts are not being used in order to avoid the Fayette Water Company's wells. 3 Finally, another eight Luxor tracts are not being used near the Patoka Terminal to avoid making two crossovers of two Marathon petroleum products pipelines, crossovers which pose inherently greater safety, operational, and maintenance issues. These five examples alone account for 73 of the I 02 deviations from the Luxor route. The remaining deviations, each limited, occurred for similar reasons. See Attachment B. 15. Furthermore, and of particular importance to this request for eminent domain authority, these deviations from the Luxor route do not significantly increase the number of tracts for which En bridge Illinois is seeking eminent domain authority. Indeed, the 102 Luxor tracts not used for the reasons described above were replaced by 82 new tracts, but only 18 of the new tracts potentially require the use of eminent domain authority since Enbridge Illinois successfully negotiated easements for all the others. Equally important, the owners of all 18 of these tracts had notice that the pipeline might traverse their properties in the Docket No. 07-0446 proceeding. 3 At the time of certification, state regulations required setbacks of the pipeline from these wells of 400 feet, a standard that the Luxor pipeline met. Since the certification, however, the applicable state regulations have now been changed to require a I 000 foot setback, which the Luxor pipeline does not meet. See Setback Zone For Fayette Warer Company Community Water Supply: Amendments To 35111. Adm. Code 618, Opinion and Order of the Board (by T.A. Holbrooke), RII-25, Illinois Pollution Control Board (June 21, 2012). Thus, a new route and corresponding new tracts were required to meet the 1,000-foot setback requirement for the Fayette wells. The certification Order urged that En bridge avoid the wells if possible. Order at 56. 13 NON-LUXOR EASEMENTS 16. Completion of the SAX pipeline has always required acquisition of easements in properties not impressed with the CIPC/Luxor right-of-way, so called "greenfield" properties. Enbridge Illinois has worked doggedly to acquire such interests. In 2012, Enbridge Illinois launched an expanded effort to complete the acquisition of required land rights for the SAX project. Thus, a new land and right-of-way office was established in Decatur in late June 2012, and currently 13 full time right-of-way personnel, based in Decatur, are working on the acquisition of land rights. 17. On July 9, 2012, Enbridge Illinois sent a letter to all landowners (or their attorneys) of tracts on which easements were needed, communicating that Enbridge Illinois was "' ... resuming work on the Southern Access Extension Project." See Attachment C. New acquisition offers were first made in the enhanced right-of-way effort by mid-July 2012, and agents were authorized to make "option" offers (i.e., contingent deals) to non-Luxor tract owners who did not have attorney representation. These efforts continued through January 2013. In February 2013, right-of-way agents were directed to make offers to acquire easements instead of options and to contact all owners (or their attorneys) of tracts on which such easements were needed. The attorneys were sent copies of any letters and were separately contacted by Enbridge 18. In addition to the in-person and by-mail-and-telephone contacts outlined above, Enbridge Illinois held informational "Open Houses" and invited all landowners and stakeholders to attend and ask questions. See Attachment D. Announcements about these events were also placed in local newspapers inviting anyone with an interest to attend and learn more about the 4 Concurrently, owners of Luxor tracts were contacted about upgrading or modernizing their easements and payments. 14 SAX project. These Open Houses were held on February 25-28, 2013, at four locations along the pipeline route. 19. As in all current Enbridge projects, Enbridge Illinois' initial acquisition offers to greenfield landowners were based on 100% of fee value of the property even though only easement interests were sought. Temporary work space offers were made at 30% of fee value, well above normal land-rent values. These are the "good-faith" offers that Enbridge Illinois told the Commission in the Docket No. 07-0446 proceeding it would make to landowners. Application For Certificate In Good Standing And Other Relief, Dkt. No. 07-0446, Aug. 16, 2007, at 24. Subsequently, in an effort to increase agreement to easements or options by landowners on this project, on April 1, 2013, En bridge Illinois increased its offer to landowners to 125% of fee value for permanent easements and 50% of that amount for temporary work space grants, additional temporary work space, and access roads. Enbridge Illinois also provides the difference of this increased payment to landowners who signed previous offer tenders. To ensure that its offers were fair, Enbridge Illinois commissioned a new market study of land values along the route by professional appraisers, which determined that Enbridge Illinois' offers are in line with current market values. 20. Between April 1, 2013 and May 22, 2013, all greenfield tract landowners willing to communicate with Enbridge Illinois were contacted either by phone, mail or personal visits to present Enbridge Illinois' most recent offers. Overall, in 2012 and 2013, right-of-way agents made numerous offers to landowners for either an option or easement and in many instances made additional offers to the same landowner when the offer amount increased. 21. On May 22, 2013, Enbridge Illinois sent written offer letters to 165 landowners by Certified Mail, Return Receipt Requested, and a second copy was sent to the same 15 landowners by First Class Mail. See Attachment E. A copy was also sent to the lando\Vller's attorney by Certified Mail, Return Receipt Requested, if the lando\Vller was kno\Vll to have attorney representation. 22. Enbridge Illinois received very little positive response to its May 22 letters, but did receive three written letters rejecting the offer. Most replies, which ranged from acknowledgement of receiving the letter to specific statements by landowners that they did not want to be contacted in person or by mail, made clear that Enbridge Illinois and these landowners are at an impasse in the negotiations. NEGOTIATIONS AT IMPASSE 23. Since the inception of the project, Enbridge Illinois has made nearly 4,600 contacts with the lando\Vllers of the 679 tracts located along the SAX route, for an average of over six contacts per landowner. These numbers do not include offers made to owners of tracts on the first fourteen miles of the SAX pipeline, which runs adjacent to the Flanagan South Pipeline ("FSP") on those tracts. 5 As a result of all efforts, Enbridge 11linois has obtained 405 agreements with landowners including the first fourteen miles. 24. No agreement has been reached, however, as to 148 properties that are critical to the approved route for the SAX pipeline and that are listed in Attachment A. It is these 148 properties for which eminent domain authority is sought. Enbridge Illinois has made a concerted effort to contact and make an offer to each lando\Vller, including the written offers sent on May 22, 2013. Since July 2012, Enbridge land agents have made approximately 921 contacts (excluding survey permission contacts) with the 148 lando\Vllers for the purpose of presenting 5 Because the first fourteen ( 14) miles of the SAX pipeline route in Livingston County parallel the FSP route therein, acquisition negotiations for properties thereon have been conducted by the FSP right-of-way group for both pipelines. Numerous contacts, meetings, offers, and discussions have also occurred in connection with this 14-mile segment. 16 - -- --- - - - - - - - and negotiating easement or easement option offers. This also represents an average of over six contacts per landowner, with actual contacts ranging from a minimum of two to as many as 32 contacts per landowner. Generally speaking, most landowners have been contacted approximately five to eight times for easement acquisition purposes. 25. Negotiations with the 148 remaining properties have reached an impasse, and further efforts to attempt to negotiate would be "pointless." The owners of the 148 tracts received notice in the Docket No. 07-0446 proceeding that the SAX pipeline would be traversing their properties, and as described above have been contacted by Enbridge lllinois numerous times since then by phone, mail, or personal visits to present Enbridge Illinois' most recent offers. The basis on which the landowners in question have rejected or not even considered Enbridge Illinois' offers vary, but can be grouped as described below. The common feature is that the reasons for rejecting or not even considering Enbridge Illinois' offers are unreasonable or represent an effort to block the construction of the pipeline and extract non-economic, extortionate payments by "holding out." The construction of the SAX pipeline, and the proposed route of that pipeline, were found by the Commission to be reasonable and in the public interest. Impasse situations such as these threaten to thwart those findings and Enbridge Illinois' ability to complete the pipeline economically and efficiently and within the timeframe necessary to meet contractual obligations. 26. A principal reason for the impasse in obtaining easements for the tracts for which eminent domain authority is sought is stalled legal negotiations. Indeed, approximately 48 unsecured tracts belong to landowners represented by two lawyers who previously contested the certification decision in Docket No. 07-0446 before the Commission and, unsuccessfully, on appeal. Some 41 tracts, primarily in Livingston County, are represented by attorney Mercer 17 ------------ Turner, who also represents landowners along the FSP route (Docket No. 12-0347). Despite numerous proposals and meetings, agreement on valuations has not been reached with these landowners as their counsel contends that a pipeline inherently causes substantial remainder damages, a position Enbridge Illinois disputes. 6 Based on the FSP situation, it appears that although condemnations will be necessary, both sides will seek expeditious resolutions via cooperative procedures. 7 At least another seven tracts are represented by attorney Thomas Pliura. Enbridge Illinois' various fee-value proposals to the landowners of these tracts, transmitted to them as well as counsel, have generally been ignored and/or rejected. No specific counter-offers have been received other than demands to discuss extraneous matters. 27. Another reason for the impasse in obtaining easements is opposition by certain landowners to pipeline projects in general. That is, some landowners simply oppose the pipeline project, regardless of any amount that might be paid for the easements or any other terms and conditions associated with the easements, and regardless that their lands will not be burdened without compensation. 28. Impasse has also arisen because of a refusal by some landowners even to respond to Enbridge Illinois' offers or to enter into any negotiations with Enbridge Illinois for easements. Sometimes such refusals take the form of an express refusal to discuss any easement until Enbridge Illinois obtains eminent domain authority. In other instances, the landowners simply 6 Enbridge Illinois expert witness Joseph Batis pointed out in his Reply Testimony in Docket No. 07-0446 that "[i]t is not acceptable to conclude remainder damages exist without studying factual market data," and testified that based on his study of such market data, "[i]t is my opinion there is no systematic and measureable negative impact to remainder properties based upon the proposed permanent easements for the En bridge project." Reply Testimony of Joseph E. Batis, MAl, Dkt. No. 07-0446, Enbridge Ex. 6R, February 4, 2008, at 5. 7 Because the FSP route traverses the same "Turner tracts" as the SAX pipeline and because FSP construction is scheduled to start in August 2013, several FSP condemnation actions against these tracts have been filed and others are under preparation. Negotiations to settle these cases have continued but so far have not reached agreement. 18 will not communicate with Enbridge Illinois in any way, whether by responding to direct and certified mailings, telephone calls, or even on-site visits by Enbridge Illinois right-of-way agents. 29. Finally, eminent domain authority may be required for 5 Luxor tracts because the original easement rights on these tracts are insufficient to construct the new pipeline (e.g., insufficient workspace), and despite various negotiation efforts the tract owners have refused to enter into upgraded easement with higher payments. 8 30. As ICC Staff witness Mark Maple testified in the Docket No. 07-0446 proceeding, "the mere fact that the landowners and Enbridge cannot agree to the terms or prices of the offers does not lead to the conclusion that Enbridge has not made reasonable attempts to acquire the property." Maple Rebuttal Test., Dkt. No. 07-0446, ICC Staff Exh. 3.0, at 23. The actions taken by Enbridge Illinois to obtain the agreement with landowners for the necessary easements, including holding public forums, sending out informational literature, contacting landowners or their attorneys by mail, using qualified and trained land agents to make face-toface contacts, basing offers on current market values as confirmed by updated market studies, increasing the level of the offers to enhance the chances of obtaining easements by negotiations, updating easement offers so that all landowners with easement agreements are paid on the same basis, are reasonable and reflect good-faith negotiation. 31. As shown, despite such good faith negotiations, Enbridge Illinois still faces a sizeable number of "holdouts." As Peter F. Colwell, Emeritus Professor at the University of Illinois at Urbana-Champaign and a recognized expert in the fields of real estate valuation/appraisal and eminent domain, testified in the Docket No. 07-0446 proceeding, "[a] holdout is a seller of property who tries to extract the gain of the buyer through an extreme 8 For example, one of the Luxor easements specifies that only a 10-inch pipeline is permitted. In other instances, the pipeline, as noted, will need to traverse the tract in a different location than utlized by the CIPC!Luxor line. 19 asking price." Colwell Test., Dkt. No. 07-0446, Enbridge Ex. 4.0R, at 5. Professor Colwell explained that holdouts present a particular problem for networks, such as an oil pipeline, that "must connect to have value." !d. For reasons of efficiency, in terms of the use of land and other resources, Professor Colwell testified that "these connections should be as straight as possible." !d. at 6. The problem, according to Professor Colwell, is that as the assembly of a network such as the SAX pipeline proceeds, "market power naturally gravitates to the ovmers of segments of the network that are not yet assembled." !d. at 5. This is the situation in which Enbridge finds itself today. In these circumstances, Professor Colwell testified, "[e]minent domain is a device that provides the assembler of the network some countervailing power to the monopoly power that accrues to holdouts as a result of the nature of these network assembly problems." !d. at 5-6. 32. Construction of the SAX pipeline is scheduled to begin in August/September of 2014. The pipeline is scheduled to be in service in the second quarter of 2015. En bridge Illinois also plans to perform some right-of-way clearing in March 2014. Accordingly, for those properties for which eminent domain authority has become necessary (all with landovmers who had notice in the Docket No. 07-0446 proceeding that their property would be traversed by the pipeline), it is essential that En bridge Illinois receive that authority by September A grant of eminent domain authority by September 1st 1st of this year. would enable Enbridge to begin condemnation proceedings, which once filed can take between 9- to 12-months in Illinois to complete, as early as September. Moreover, it is disruptive and not cost effective during construction to skip over tracts on the route where easement rights have not yet been settled. Accordingly, Enbridge Illinois must now seek condemnation authority to meet its schedules. 20 33. Even as this Petition is filed, and even if condemnation authority is granted, Enbridge Illinois will continue its efforts to reach agreement with landowners by negotiation. Indeed, such efforts will continue even if condemnation actions have to be filed. However, landowners should not be permitted to blockade construction of the pipeline, found by this Commission to be necessary and promote the security or convenience of the public, to extract non-economic, extortionate payments by holding-out, or refusing to negotiate. CONCLUSION For the reasons stated above, the Petition of Enbridge Pipelines (Illinois) L.L.C. should be granted and Enbridge Illinois should be authorized to condemn private property when necessary to construct the Southern Access Extension Pipeline. Specifically, authority to condemn should now be granted as to the 148 tracts set forth in Attachment A to this Petition. 21 Respectfully submitted, ENBRIDGE PIPELINES (ILLINOIS) L.L.C. OF COUNSEL: Joel W. Kanvik Amy Graham Back Enbridge Energy Company, Inc. 1409 Hammond A venue Superior, Wisconsin 54880 (715) 398-4500 Gerald A. Ambrose Dale E. Thomas G. Darryl Reed Sidley Austin LLP One South Dearborn Chicago, Illinois 60603 (312) 853-7000 Attorneys for Petitioner By: /s/ G. Darryl Reed G. Darryl Reed One of Petitioner's Attorneys Dated: July 22, 2013 CHI 7840101 v.l 22 -- - - - - - - - - - - - - - - - - - - VERJt'JCATION CITY OF SUPERIOR DOUGLAS COUNTY STATE OF WISCONSIN ) ) ) SS: John McKay~ first being duly sworn upon oath, deposes and says that he is the Manager, Land Services (U.S. Projects), of Enbridgc Energy. Limited Partnership. an affiliate of Petitioner Enbridgc Pipelines (Illinois) l ,,L.C .; that he manages and directs the right~of-way acquisition program for the Southern Access Extension pipeline project; [hat he is authorized to muke this verification on behalf of Petitioner; and that he has read the above and foregoing Petition, including the attachments appended thereto. and knows the contents thereof, and that said contents arc true and correct to the best of his knowledge, intonnation, and beliet: Sl JRSCRlRED AND SWORN to before this_) ,q day of July, 2013 ..... ..-.......__ - CORISSA SElLV Notal)' PuNc Stitt of wttconstn 1 or 5 Enbrldge Pipelines (Illinois) LL.C Landowner List A· A TractNo Tract County Owner LIVinoston Joan T. Bolen ~003 06-005 Livinoston James W. Mackinson Trustee 00-007 Livinoston James W. Mackinson Trustee KJ€;-010 LIVingston M & R Duffy Farms LL.C. 06-014 Livinoston Michael W Francis 06-016-3 Livingston Paul A. Russow 06-017 t ivinoston Phillip J Duffy, Trustee 06-018 LIVingston Ruth K. McCabe 00-019 Livinoston Ruth McCabe Livingston P6-020 Joan M. Duffy 06-020-2 Steven G. Duffy LivrnQston 06-025 Livinoston Ted A Bauknecht Livingston Ted A. Bauknecht 06-027 06-028 Livinoston Justin J. Stoller as Trustee 06-029 Livingston M & R Duffy Farms L LC LIVIngston M & R Duffy Farms LLC 06-030 06-031 Uvinoston Robert E. Carroll Livingston 06-037-1 Jayme Wilburn 06-038 LivU"lQston Farada}' J. Strock Trustee 100:_040 Lrvinaston Paul D. Duffy 06-041 Livinoston MIChael M. Duffy Q§-042 Livingston Michael M. Duffy 06-044 Livinqston Julie A. Gleeson as Trustee Livingston 06-045 Jeff E Barth Michelle E KniQht 06-04$ Livinoston Jean E. Cremeens 06-047 Uvinqston Jeff E. Barth 06-048-2 Livingston EliZabeth Anne Laughlrn Ellen Lou1se D1naledrne p6-049 Livingston Elizabeth Anne Laughlin Ellen Louise Dinoledine 06-050 Livinoston Tracv L. Barth 06-051 LIVIngston Sancken AQri-Resources Inc. Address 6 Laure! Court 6 Laure! Court 6484 E 1600 North Rd. 230 Westwood Oaks Court 6 Laure! Court 6 Laure! Court 5413 Rolhng R1dge 5413 ROIIInQ RldQe 313 Apple Dnve 6484 E 1600 North Rd. 300 West Washmgton Street 1200 N Ma1n St Apt 5A 20681 N. 1500 Ea& Rd. 20681 N. 1500 East Rd. 19014 N. 1275 East Rd. 20200 N. 1300 East Rd 12076 East 1975 North Road 19014 N. 1275 East Rd. 215 E Washington St 215 E. Wash1nQton St 11368 Wa shw.gton Street 11368 Easl1900 North Road 11753 E. 1800 North Rd 11753 East 1800 North Road 15 west Front Street 19014 N. 1275 East Rd 19014 N. 1275 East Rd. 17583 N 1090 East Rd 1807 West Diehl Road 223 North Mrll Street PO Box 680 758 N. First Rd. 535 South Bluff 535 south Bluff Citv Pontiac Pontiac Pont1ac Pontiac Pontiac Pont1ac Pontiac Pontiac Pontiac Pont1ac Pont1ac Pontiac Pont1ac El Paso Pont1ac Pontiac Pont1ac Naperville Pontiac Dana South Beloit South Beloit Pontiac lomahawk Tomahawk Metamora Flanag_an Washington WashinQton washington Washington Flanag_an Kankakee IL IL IL ll State IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL WI WI IL IL IL IL A ITACIIMENT A 61764 61764 61764 61764 61764 61764 61764 61764 61764 61764 61764 61764 61764 61738 61764 61764 61764 60563 61764 61321 61080-2238 61080-2238 61764 54487 54487 61548 61740 61571 61571 61571 61571 61740 60901 Zip 2of 5 Enbrldge Pipelines (Illinois> l.L.C Landowner List A TractNo Tract Countv owner L ivt[lg_&On The Bank of Pontiac as Trustee 96-051-4 Jay E Barth LiVII"tQston 06-054 Livingston 06-055 Jay E Barth 06-056 LivinQston Maurine KalkWart 06-057 Livingston Jeffrey E. Barth Jay E Barth Living&on 06-059 LiVIQQ_ston Allee M Raber as Trustee 96-061 L1V1ngston Margaret Rose Kampfner 06-065 06-072 Uvtrgston DEL-MAR-BVA Trust Agreement C&C Trust No. 1 dated 1-6-1989 Soy captlaiBank Livtngston 06-073 Ltvtng&on Louis Bachman 06-078 06-079 Livingston Louis R Bachman Kenneth L Kuerth P6-083-1 LivtOQston b6-084 Livtngston Debra S. Kuerth Trust Joan K Widmer Life Estate 07-003 McLean Mark Widmer Robert Vv'idmer Mclean Larry D. Kiefer P7-006 07-007 Mclean Barbara J. Kiefer 107-012 Mclean James M Ondeck McLean Residuary Trust under the Last WHI and Testament ~7-015 McLean Monarch Farms LLC an Illinois Limited Liability ~7-016 Sarah H Butler Trust, Soy capit_al Bank and Trust 07-019 Mercer Turner as Trustee McLean 07-021 McLean Franklin J. Grusv Duane E Guth McLean m-o22 P7-022-2 McLean C&C Webber Pro~rties Inc. an Iowa Corporation William A Freed Declaration ofT rust ~7-022-6 McLean McLean Wilham A Freed Declaration of Trust P7-022-7 K)7-027 McLean Freed Agricultural Service Inc. steve A. Freed Freed Agricultural Service Inc steve A. Freed Mclean 107-028 07-028-1 Bryan K. HoQgtns McLean McLean Wendell Learned 107-031 07-035 Oswego Community Bank. as Trustee Trust #187 McLean 07-037 Mclean Catherine Jordan Keller Killian Farms, Inc Mclean 107-038 Address 230 Westwood Oaks Court 230 Westwood Oaks Court 230 Westwood Oaks Court 15691 North 600 East Road 6484 E 1600 North Rd 401 Webster Street 6355 E 1400 North Road 14569 North 500 East Road 2415 East 28 Road PO Box 1607 30 Crosswinds Court 30 Crosswinds Court 22777 E 31 00 North Rd 31594 N 2180 East Road 2025 East Lincoln Apt 2210 4 Ebach 4 Ebach Drive 707 Market St RR#2 Box118 707 Market St 25358 N 1475 East Rd 1960 N 2200 East Rd PO Box 1607 PO Box 1607 116 Boulder 2669 E 1000 North Rd 305 E. 6th Street 804 Meadowlark Ave 21389 N 2875 East Road 21389 N 2875 East Road 1108 S Falmore Drive 1108 S Falmore Drive 25754 N 2150 East Road 26 Baypomt 1812 Cherry Road 302 W Main st. RR 1 Box 349 Citv 46506 IN 61702 61704 61704 61744 61744 67101 61701 61701 61744 61744 61748 61752 61702 61702 61744 61744 61744 50583-1818 61753 61753 60067-7024 60067-7024 61753 61704 60543 61753 61776 60901 61740 61740 61740 61740 61740 61740 61740 ZIP State IL IL IL IL IL IL IL IL ll IL IL IL IL IL IL IL ll IL IL IL IL IL IL Grid~ Gridley IL Gridley IL Sac City lA Lexiogton IL Lexington IL Palatine IL Palatine IL Lexington IL Bloomington IL Oswego IL Lexington IL IL Towanda Kankakee Flanagan Flanagan Flanagan Flanagan Flanagan Flanagan Flanagan Bremen Bloomington Bloommgton Bloomington Gridley Gridley Bloomington Bloomington Bloomington Gndley Gridley Hudson LeRoy Bloominaton Bloomtngton 3of5 En bridge Pipelines (Illinois) L..LC Landowner List A rractNo ITract Countv owner Killian Farms Inc 07-040 Mclean AI Killian Al Killran Mclean Tom Killian and Jean Killian Family Farm Trust 07-041 Tom Krllian and Jean Killian Famrty Farm Trust 07-043 Mclean Tom Killran and Jean Killran Famrty Farm Trust Timothy Krllian 07-044 Mclean AI Killran as Trustee 07-045 McLean AI Killian as Trustee 07-046 McLean Doris J Grunloh as Trustee Doris J. Grunloh 07-047 McLean Leslie Dean Troyer Mclean 07-048 AMB Holdrngs, LLC. 07-049 McLean Kraft Farms LLC kJ7-050 Mclean Kraft Farms llC 07-051 Timothy C Kraft Mclean 07-052 Mclean William H. Hams Trustee 07-053 Mclean William H. Hams Trustee 07-054 Mclean Maurice E Jones Trustee 07-055 McLean M and 0 Jones Farm rnc '07-056 Mclean M and 0 Jones Farm. Inc. 07-057 McLean Carol K. Holstine 07-058 Mclean Nina S. Armstrong, as Trustee 07-059 Mclean Nma S. Armstrong, as Trustee 07-060 McLean Nina S Armstrong as Trustee 07-060-5 McLean Carla S. Temple Trustee Carol K. Holstine 07-061 McLean The Hinthorn Fam1tv Limrted Partnership "8" 07-062 McLean The Robert J. Kmg Declaration of Trust dated 29th 07-063 McLean Rosemary KlnQ, Trustee 07-064 McLean JPR Family Partnership, L. P. and Patnc1a Kelley 07-066 Mclean Korte Farm Partnership Trust 07-067 Mclean Korte Farm Partnership Trust 07-068 Mclean Kraft Farms LLC 07-069 McLean Kraft Farms LlC 07-070 McLean KraftFarms, lLC s Address RR 1 Box 349 2138 E 2200 North Road 2138 E 2200 Nortn Road 28525 N. 2380 East Rd. 28525 N. 2380 East Rd 28525 N. 2380 East Rd 28525 N. 2380 East Road RR 1 Box 349 RR 1 Box 349 20514 N 2150 East Rd 2514 N 2150 East Road 17792 E. 2200 North Rd 7357 Covington Home Place 426 South Frfth Street 426 South Fifth Street 21148 E 1900 N Rd P.O Box412 P. 0. Box 412 18264 N. 2150 East Road 16264 N 2150 East Rd 16264 N 2150 East Rd 415 South 11th Street· PO Box 500 920 Johnson Road 920 Johnson Road 920 Johnson Road 415 11th St 415 South 11th Street PO Box 500 22720 E 1900 North Rd 17473 N. 2100 East Road 21024 E 1600 North Rd. 23545 E 1600 North Road 400 Oouq!as Street 400 Douglas Street 426 South Fifth Street 426 South Fifth Street 426 §outh Fifth Street :itv Towanda Towanda Towanda Gridley Gridley Gndley Gridley Towanda Towanda Towanda Towanda Hudson Culpeper Springfield Springfield Towanda Fairfreld Fairfteld Towanda Towanda Towanda Nevada Wadsworth Wadsworth Wadsworth Nevada Nevada Towanda Towanda Normal Normal Park Forest Park Forest Sorinafield SprinQfield Springfield IL IL IL !l !l !L !L ll ll lA !A OH OH OH lA ll IL !l VA ll !L IL VA VA IL !L State ll IL ll IL JL ll ll ll IL IL Zio 62701 62701 61776 61776 61776 61744 61744 61744 61744 61776 61776 61776 61776 61748 22701 62701 62701 61776 24435 24435 61776 61776 61776 50201-0500 44281-9091 44281-9091 44281-9091 50201-3004 50201-0500 61776 61776 61761 61761 60466 60466 62701 Mclean Mclean Mclean Mclean Mclean Mclean Mclean Mclean Mclean Dewitt Dewitt Dewitt Dewitt Dewitt 07-106 07-107 07-109 07-112 07-113 Q7-116 07-130 07-131 07-134 pa-015 00::025 PB-026 pa-.027 08-029 4of5 Mclean Mclean Mclean McLean Mclean Mclean Mclean Mclean Mclean Mclean McLean Mclean Mclean Woolley I LLC. a WvomlnQ l.LC Woolley I LLC. a W.,.ominQ l.LC Daniel F Lay V1ctor W Bittner Weldon Trov Muli1ken & Barre B. Mulliken-Briaos Darrell L Miller Charles E Murptry Marv Sue Murphy Martin Midnight Sun Inc. VI Midnight Sun Inc. VI REH Family Farms Inc. REH Family Farms Inc. REH Family Farms Inc Barbara J Washburn Trustee of Trust Number H-295 Maroot Y. Rudesill Trustee UTA dated 11/10/87 John L. BenJamin Dorothv F. Beniamin Trustee VTAdated 11-27-1995 Mark Hines Mark Hines Monarch Farms LLC an Illinois Limited Liability Mona1ch Farms LLC an Illinois Limited Liability Mark Irving Andrews Ronald l. Stark Ronald L Stark Kent Murphy Founders Bank Trustee Daniel Friant Raymond Dean Prosser as Trustee Jean Snvder Trustee Betty Jean livingston Frank E. Roop Grworv B Roop Heidi CRoop Lisa M. Jones William J. Jr. Roop Tract County 0\Nfler 07-071 07-072 07-073 07-074 07-076 07-077 07-081 07-082 07-083 07-097 07-098 07-103 07-104 A TractNo ....... Enbridge Pipelines (Illinois) L.L.C Landowner List Address 5445 Half Round Rd 5445 Half Round Rd 7583 N 1300 East Road 19754 E 1300 North Rd PO Box67 1264 N 1800 East Rd 7524 Carte Springs Road 5023 Nicklaus DriveN W 14550 Excelsior Blvd. Ste 202 14550 Excelsior Blvd Ste 202 24207 Ron Smith Hwy 15515 Dan Patch Dr 24207 Ron Smrth Hwy POBox 405 20353 E 650 North Road 1 Brickvard Drive Su1te 101 216 Fleetwood Drive 216 Fleetwood Dr. 5446 North 2000 East Road 319 Robin Hood Drive 608 Spring Brook Lane 4430 Mercer 302 W Main St. 15214 Strollwavs 2375 lntertackm C1rcle t'NV 2025 E. Lincoln Street Act. 1213 23236 E. 1100 N. Rd. 23236 E 11 00 N. Rd. 810 Karin Drive 21237 E 950 North Rd 302 W Main St. 3268 Blue Ridqe Road 3268 Blue Ridge Road 23287 E 800 North Rd 14497 John Humphrey Dr Cltv Lexington Chesterfield Cleveland Bloominqton Downs Downs Normal Bloominqlon Lexington Briohton Brighton Downs Orland Park Minooka Downs Bloominaton Bloomington Bloomington Downs Rale1gh Leander Grand Prairie Oswego Oswego Shirley Bloomington Bloominqton Heyworth Wapella Rochester Minnetonka Minnetonka Hudson Plainfield Hudson IL IL IL IL IL IL IL MN MN MN IL ll ll IL MO TN IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL NC TX TX State 60543 60543 61772 61704 61702-{)067 61745 61777 55901 55345 55345 61748 60544 61748 ZiD 61753 63017 37312-2235 61701 61736 61736 61761-3144 61704 99999 62012 62012 61736 60462 60447 61736 61701 61701-2027 61701 61736 27605 78641 75052 Macon Macon Macon Macon Christian Shelby Shelt:Jy Shelby Shelby Shelby Shelby Shelby Shelby Shelby Shelby Fayette Fayette Fayette Fayette Fayette Fayette Marion Marion 12-060-2 12-064-1 13-011 13-020 5of5 09-050 09-052 09-059 09-078-3 10-033 11-040 11-041 11-042 11-044 11-045 11-047 11-050 11-051 11-059-1 11-067 12-008-1 12-030 12-051 12-052 REH Family Farms Inc. Edward Hoke James D Roby Beverly A. Gul1ck R1chard D. Gulick Brian S. Schwalbe Revocable Inter Vivos Trust Jon B. Kraft Luclile Bernice Hanks Deborah F. Evans Jason R Farmer The Baker Family Umrted Partnership M1chael R Evrley Robert J. Beyers Trustee of the Regina E. ~yers Robert J. Beyers Trustee of the Regina E Beyers Robert J Beyers Trustee of the Regina E Beyers Sharon Jean Morell Daniel C. Beyers Jeffrey J Witt Kathleen A. KJein William Patrick Schmitz Donald Lynch Wlliam R. Pearson Rocky L. Kramer The Charles E. Rhoads Family LIVing Trust Allen Joe Radcliff Clyde Austin Trustee and Carol Austin, Trustee Clyde Austin Clyde Austin Clyde Austin Randy A. Meyer Mark Murfin Jr Tract County O'Mler Dewitt Macon Macon Macon Macon A 08-039-5 09-037 09-040 09-041 09-047 TractNo .Ill Enbridge Pipelines (Illinois) L.L.C Landowner List Address 15515 Dan Patch Dr 5686 state Highway 10 1665 Quail Run 4303 W Center St 4660 McKinley Road 130 Southbrooke Ct 130 South Brooke Ct 5640 W Cantrell St 1190 S Joynt Rd 5456 W Rock Springs Rd 19 ShaW Court 15 N 2700 EAST RD 2217 Georgetown Drive 221 7 Georgetown Drive 2217 Georgetown Drive 252 North 2600 East Road 31 N 1600 East Rd 107 V1ne Street 387 N. 1600 East Rd RR3 Box294A RR 3 Box 141C 1772 N 2525 E Rd RR 1 Box 415 6965 Oleatha Ave RR 1 Box 79 RR 1 Box 156 RR 1 Box 156 R R #i Box 156 R R #1 Box 156 18241 Irving Rd. 2168 Tank Farm Rd Citv Pla1nfield Clinton Prescott Decatur Decatur Decatur Decatur Decatur Decatur Decatur Macon Pana Chamooion Champaign Champaign Pana Rosamond Pana Pana Pana Pan a Moweaoua Herrick StLouis Brownstown Brownstown Brownstown Brownstown Brownstown Witt Vernon ll ll IL IL IL IL IL MO IL ll IL IL IL IL IL IL IL IL IL IL IL IL IL IL IL !L IL IL AZ State IL IL ZiD 60544 61727 86303 62522 62526 62521 62521 62522 62522 62522 62544 62557 61821 61821 61821 62557 62083 62557 62557 62557 62557 62550 62431 63139 62418 62418 62418 62418 62418 62094 62892-1808 ATTACHMENT B ENBRIDGE PIPELINES (ILLINOIS) L.L.C. SOUTHERN ACCESS EXTENSION PROJECT ICC DOCKET NO. 07-0446 MAJOR DEVIATIONS FROM LUXOR ROUTE Deviation # Deviation Name Tabor Road Re1 Route Approx. Milepost 63.55 Approx. Length 0.1 Deviation Rational Avoid having to put the new line below Luxor as there is not sufficient room to put it next to Luxor under original easements, avoid bore pit in ditch and lower elevation of pipeline under road Luxor Tracts Deviated From l 2 1-72 Re-Route 87.55 3.1 3 Decatur Landfill ReRoute 89.35 0.7 Better alignment for 1-72 crossing, reducing residence impacts, mostly Harristown. Avoid developed area of landfill, better alignment crossing river, reduced tree removal, avoid ponds 92.05 0.1 Avoid home. 3 l 94.8 0.8 Better alignment to cross Panhandle and REX pipelines l 98.25 1 Shorter route, adjacent to road fewer bends 3 3.9 Avoid Reservoir. avoid disturbance to weir, avoid residential areas 27 4 Crackel Re-Route 5 Panhandle Re-Route 6 Suqoia Re-Route 7 Lake Pana Re-Route 8 Rudow Re-Route 9 Medley Re-route Allen & Rouch 10 Reoute 120.95 123.4 Avoid residence, pond, 1 minimize tree removal 125.65 0.5 Avoid pond, avoid substantial tree removal, avoid proximity to residence 133.35 0.5 Avoid 3 residences 22 1 l 2 ------------------ ATTACHMENT B ENBRIDGE PIPELINES (ILLINOIS) L.L.C. SOUTHERN ACCESS EXTENSION PROJECT ICC DOCKET NO. 07~0446 MAJOR DEVIATIONS FROM LUXOR ROUTE 11 Kramer Re-route 12 County Road 24 Reroute 13 Potter Re-route 14 Fayette Wells 15 Linn Creek Reroute 16 1-70 Reroute 17 Hickory Creek Reroute 18 Kruenegel farms 19 Marathon Triangle 135.625 Re-route around garage, farther away from house, 0.25 try to get into farm field With most tracts closed opportunity to shorten up 1.3 the route. Move line to not be under water when Potter floods. Keep line closer to 1.5 upland 138 140.75 142.5 7 0 Avoid Fayette wells, need 1000ft setback under current regulations, was 400ft at time of ICC Certification. 7 Avoid 2 residents, avoid pond, shorter route, 6 of 1.25 8 closed 6 2 145.475 0 150.6 Avoiding new residential area, more perpendicular crossing of railroad and I 1 70, avoids concrete plant 9 155.3 Creek crossing more perpendicular, shorter, fewer trees removed 0 161 0.4 1 Avoid farm property Avoid two crossovers (which pose inherently greater safety, operational, and maintenance issues) of the two marathon pipelines, shorten up route. We had previously 1.7 acquired most tracts. 163.15 2 3 8 - -- - ~---------------------------- ATTACHMENT C 00u9ta• e. Aller Enllridv• tU.S 1 Inc. t ~c~ H~l'l'f">>nd Av•n..o Sus:-er~cr. \I'll ~aeo T~II-FtN Bf6·331•3-li3 L~rd• & R-91>1· of· UotRe;•·· us -~~-1 ..,_ •nb•oc.q•~:>et$ .:01"' Re: Sourbcro Accw Extension Projecc ..-conl:~d by Enhc1d¥e rep~nt:.)ti"" De:u landoJwncr: cnbritlge PIJWlines (Illinois) L.I•.C. ("'EnbriJI!!e··l is retumins work an the SoJutl\em Access Ex1ensiun Proj~:~t. a pipeline prt.>j«t located in your an:a th:u Enbridse tempot:wily suspended. Wo are sending you thi$ l•tt.,r in :1d'~~·• of ;sn i::nbd.Jg~ repr~en1:uiv~ cont:lc:tin!J you by tcl~one cr in ~rsen. As ""<: resum.: tl:\' Proj~t. w~ will N :~cquiring ca$emCOI$ from sl)me l:llldo\'\oncts ond. in some c:aus. updating en\·ironmclll:&l and civil sur\·ey information in ordc.tr IQconfirm the proposed ruutt orrh~ pipeline 40d iu s~itic o.lignmc:nt oo individualprupenies. Th..: S<)uthem A.:ceS$ E:\lension Project i~ an ~~opproltim&loly 166-mile I\Jnl piptli~ that will C."<tcnd Enbridge's c:T\Ide oil pipeline system from lu Flanog:m renninal n~r Pootiac, llliMis south to the m~jor petroleum hub at Patoka. lllinuis Th~ pip.:lioe will b4 co~aed in the corridor appto~·cd by lhe llllnoi~ Com~JK"~"~;C Cummission in pi"OI;~edin" 07--446 And will iencrally parnUcl cxiSling pipeline and electric transmission rights-of-wa~·. includini Enbridge·s existing right-of-w:~y. Subj~ to other pending regulaiOl) oppro~111s . Enbrid§r:: antKipat~:s bc&inning co~tNction U. mid-201-J, wid1 dw pipeline' in $ervicc in 20 IS. lo mo~t c:1~cs, Enbridge reproscruali,.es will ~umc discussions with lanJuwael"$ w:~d upd~Us: info~tion ~:nhc:rcd pre"·iously. For prop•my QW~onr;rs whiJ arc new or who v.erc oot pan cf those oriJinal diS(uS5ions. EnbriJge represent:uives will prOI.'icH tllem witb PJ')~Ct inf~Xma,iun ~ ~swer their question~. A..:quiring the rcmnining e~$<:rncnu needed the Project and updacing intbrmution is an impon;mt pan or che procl!ss r.,r of rc...:ontinnins rhe pipelin~ Ntlh!. B:ued on the updated inf\lrm~tion, """ cnn icHntjfy 3ny new community, tnviroomenul or lundo .... ner-sp.:citic: ~ue• to:~ oni11t Project pbnnen in minimiziDJ Oldvcrse im~u IQ landowner~ nt~d lhc c:nvirQIJmc:nt. Information about the '""'w ..:nbriJgc.ctlm. In ~<lmmcnf~. Svuth~m A~:c~sl htc:nsiun Projo:ct will ~ availabl.! on the: Enbridje websire .-c 1hc me:~ntim~. ple-:lse feel free to ..:onucr us at {866) JJ1-J.,9J with any q~H5tWtt:i or ATTACHMENT D February 8, 2013 (Prefix] (First Name) [Address 1) [Address2) (City}, (State} IZipl RE: Southern Ac:cess 'Extension Pipeline ProJect Open Houses Dear Sal. last Name: As you are aware, Enbridge Enersv Company, Inc., thrcuah Its affiliate Enbrtdse Pipelines (Illinois) L.L.C., !together with Enbrldge Enersv Company, Inc., "Enbrid&e") Is proposlns to expand Its pipeline system by building the Southern Access Extension Pipeline Project ("ProJect")- a 165-m lie crude oil pipeline that wiU orisinate at Enbrldge's Flanagan Terminal near Pontiac, Ill. and terminate at a majOr refinery hub near Patoka, Ill. This Project Is Enbr1dge's response to market demands for Increased access to growing volumes of oil from North Dakota and western Cilnada. The Project 1$ approved 11;1c up to 361.-.;tie~ In diameter; /'lowever, the final c~paclty and diameter won't be finalized untU the transporutlon needs of shippers have been determined throurh commercial open seuons. As part of Enbrldge's initial outreach for the ProJect, the company 1$ hostJns tflree open houses alons the route. The times ;wnd rocatlons are as follows: funo'pv. E«btyqrv26 • S;OO- Z;31J PM Yandaii-.IL. WdniJdm kbrvqryll • I:DD-l.;JO.PM Decatur, IL. Vandalia Oays Inn Hotel 1920 Kennedy Bou~vacd, Hwy St;~~nd 1-70, Vandalia, IL 62471 Decatur Conference Center and Hotel 4191 US .36 West (Wyckles Rd.) Decatur, IL625l2 Thursdgv. FDM!ry ZB • 5:00- 7:30PM Sloomintton, IL Bloomington Chateau Hotel & Conference center 1601 Jumer Drive 8/oomlfllton, IL 61704 landowners and the public may attend these wme·and-eo open houses ilt any time betweeo 5:00p.m. aod 7:30 p.m. Attendees will be able to view maps and displays, meet ltroject team members, ask question~ and comment on the rollte. If you have any questions about the open houses, or anythll18 about the pro}ect, ple11se contilet me. Slncerely, Richard Xem Right of Way Enbrldge Enersy Company, Inc. Phone: 1·855-714-8373 E-mail; r1ch 1 11tm!!tn~rldgtu;om ATTACHMENT E En bridge Pipelines (Illinois) L.L.C. 2535 Millikin Parkway Decatur, Illinois 62526 May22,2013 VIA CERTIFIED MAIL AND FIRST CLASS MAIL RE: OFFER TO PURCHASE PERMANENT AND TEMPORARY EASEMENT rNTERESTS FOR A PIPELINE RIGHT-OF-WAY·· PROPERTY TRACf NO. FP·' Dear As you are aware from previous communications nnd negotiations, Enbridge Pipelines (Illinois) L.L.C. -· "Enbridge" --wishes to purchase pennanent and temporary easement interests in your property located in County, rllinois, (Enbridge Tract No. FP-· .). These interests are sought for tbe construction of a new pipeline known as the ftSouthem Access Extension Pipeline." Our records indicnte that in the period of 2008-2010 Enbridge right-of-way agents communicated Enbridge's interest to you and offered to purchase the necessary property interests. As background, in July 2009 Enbridge received authorization from the Illinois Commerce Commission (ICC) by its Order in Docket No. 07~0446 to construct, operate, and maintain the Southern Access Extension Pipeline. The route approved and authorized for the pipeline will travel from Enbridge facilities near Pontiac to a petroleum storage and pipeline interconnection facility in Patoka (the "Patoka Hub"). The route for this pipeline crosses your property. The pipeline will transport crude petroleum from western Canada and North Dakota to American refineries. Implementation ofthe authority granted by the ICC was deferred due to various fac.:tors, including legal and economic challenges. The legal appeals and challenges to both the Commission's authorization decision and other Enbridge rights were finally resolved in Enbridge's favor only io 2011. The national adverse economic conditions lasting from 2009 to 2011, as well as petroleum industry reorganizations and uncertainties, also worked to defer the proj~t. As these adverse economic influences have waned. increased North American crude production and refinery demund have mnde completion of the Southern Access Extension Pipeline essential to meeting public nel:!d tor refined petroleum products nnd enhancing national energy security and independt:nce. AC(:Otdingly, Enhridge is proceeding with construction of the pipeline, as approved by the ICC, with the intention of placing it in servi~e by mid-2015. To achieve that goal, Enbridge needs to ncquirc eosement interests in tracts along the pipeline route in which it does not have e;oo;.isting right-of-way rights. To that end, Enbridge makes this offer to you in the total amount of$ ·to purch11se the requisite permanent and tempor.1ry casements. As with Enbridge's previous offer(s), Enbridge has based this offer on a professional market analysis of current property values in Macon County tor properties such as yours. This offer is May 22,2013 Pag(> 2 based on the highest value shown by this analysis for a fee interest even though Enbridge seeks only easement interests. Easement interests by definition are ofless value than the fee of a propt:rty. Please note that while the pt!rmanent easement areas are valued at fee; tt:mporary workspace areas are vall1ed essentially as land rentals. Although the temporary workspace i~ similar to a land rental, it is valu<d at 50% of the fcl."! value of the nec\!ssary acreage (land rentals generally are I O~·o-15% of ft-e). In addition to the compensation produced by calculating pcnnanent und temporary easement figures as just di!Scribed. Enbridgc's ubovc·stated offer includes an additional bonus payment of 25% of the fee value tor the easement. This bonus is included as an inducement to your acceptance of this offer. For your convenience, a Calculation Sheet is included with this letter; it shows the determination of the components of the total offer of S . Please be advised that the total ot1er is a unitary otTer tor the full compensation of all persons having an inti.!rest in the property addressed hcrein. If more than one person has an interest in this propeny, 8Uch persons may agree among themselves on any division of the total amount offered.' A..:companying thi:> letter for your attention and evaluation an: the following documents: ll) An Alignment Drawing showing the pennancnt casement area and any temporary workspace beyond the permanent easement area itself required in your property; (2) A "Right-of- Way and Easement Grant" that sets forth the respective rights and duties of you as the landowner, referred to as the "Grantor," and Enbridge as the casement owner, referred to us the "Grantee," the attached drawing describes the strip ofland that will be the pipeline "Right-of-Way'' (the permanent easement area) and "T ~mpornry Work Space (TWS)" granting En bridge the temporary use of the designated an~a needed tor constl-uction of the new pipelim: (TWS rights expire upon construction of the pipeline and restoration of the easement areas substantially to their pre-construction condition; this process requires uppro:dmatdy one year); nnd (3) A copy of the "A!,'l'icultural Impact Mitigation Agreement'' entered into by Enbrldge with the Ulinols Department of Agriculture to specify applicable constntction, impact mitigation, and restoration requirements for the proj~ct. It is Enbridge's earnest hope that you will find this offer acceptable and will agree to execute the agreements enclosed herewith. Enbridge believes that this otTer is the best and most reasonable il can m<tke for the interests being sought in your property and, absent persuasive data contradicting irs anulyse:;, does not intend to make higher ofters. Of course, Enbridge is willing to discuss any and all aspects of this propo~al with you and to address ruty questions and concerns you mny have. Accordingly. this offer will rem<:~ in open for the next fourteen ( 14) days until the close of business on Juni.! 5, 2013. tfyou WOllld lik\! lO disrJI!;S this otl'r.r r~mlior any of the included materials, please ~on tact our Right-of- Way agent : al ( ) Any reasonable counter-proposal will be brought to my immediate attention and given the most serious consideration. However, given the schedule r~ferenced above, Enbridge needs to moo:c expeditiously ns time is critical tn us. Absent your accc...-pllmce of the proposal made herein or agreement with you on some variation · Please no1~ thai in addhion 10 tho:: Iota! (.'Ompen:mHOII dc~rib.:d above. Enbrid!IC: will pny for MY damages lo the propc:n)' incurred during 1h~ pipclin..:·s. co•~1rucLion, induding fhr rr:pair replacement of drain tiks if netessar:--. as wo:ll as during sub~uent opemri,,n.·rnainr.:nanl~:jnsjX•c!ion·elc. proc~dures. In Bddilion. Enbridt'e ~ill compeu~te you t\1r crop los~~j. upon presema1ion of uc1u:.J yidu and u1luc Jatn. ~r the fol!owing fonnula: Ye01r of CUIJ:ilrtK:Ilon '· !1)() ~; ftrst ~ubs.:quent y.:ur ·' ~s~.; :te\:Qnu ~ub~<:qucm y.:ur ··- 50u·o: lhir\1 sutos~:queo\ :rrt:ur ~ 2:;•;.,; dt~rc-4fl~r ~r J,,,·um~m~"'..los> Yuu may .-l.:ct lv r~ehe the ro1~1 c~rima1e with the acccptMce of !his l)fT~'I' or dd..:r .:rop-los$ Cl'nlf>"!ll';Hinn to the tblur,. 6 May 22,2013 Page3 by the date stated above, Enbridge will assume that our good-faith and reasonable negotiations with you have not succeeded. We will then assess other options, which may include petitioning the ICC for eminent domain authority as discussed in the 2009 Order. Thank you for your attention to this. We look forward to the favor of a prompt response. Sincerely yours, /LJW7 John McKay Manager, Land Services (US Projects) cc: October 11, 2013 Enbridge Illinois Pipelines (Illinois) L.L.C. Petition Pursuant to Section 8-509 of the Public Utilities Act to Take Private Property as Provided by the Law of Eminent Domain. : : : : : : 13-0446 ADMINISTRATIVE LAW JUDGE’S RULING This ruling by the Administrative Law Judge is issued with respect to the “Motion to Deny and Strike Pliura Petition for Intervention” (“Motion”), filed on behalf of Enbridge Pipelines (Illinois) L.L.C. (“Enbridge Illinois”) on August 30, 2013. A response (“Response”) opposing the Motion was filed by “Pliura Intervenors” on September 30, 2013. A reply to the Response was filed by Enbridge Illinois on October 7, 2013. In the Commission’s Order in Docket No. 07-0446, Enbridge Illinois was issued a Certificate of Good Standing, pursuant to Section 15-401 of the Common Carrier by Pipeline Law, which is part of the Public Utilities Act (“PUA”), authorizing it to construct a pipeline and to operate as a common carrier by pipeline over a route described therein. The Order also found that the proposed pipeline was necessary, and should be constructed, to promote the security or convenience of the public, pursuant to Section 8-503 of the Public Utilities Act. In its petition in the In the current proceeding in Docket No. 13-0446 (“Enbridge Petition”), Enbridge Illinois states that easement rights for most tracts on the route have been obtained, but that it still lacks easement rights for the 141 tracts owned by persons identified in Attachment A to the Enbridge Petition. Enbridge Illinois is seeking, with respect to those 141 tracts, an order under Section 8-509 of the PUA enabling Enbridge Illinois to proceed with a condemnation action before the courts “in the manner provided for by the law of eminent domain.” A single Petition to Intervene was filed on behalf of persons sometimes referred to “Pliura Intervenors” or “Pliura Petitioners.” The 63 Pliura Petitioners are listed in Schedule A to the Intervening Petition. The list includes, but is not limited to, some of the owners of the 141 tracts listed in Attachment A to the Enbridge Petition. In its Motion, Enbridge Illinois objects to intervention by those Pliura Petitioners who are not owners of any of the 141 tracts that are the subject of the Enbridge Petition filed pursuant to Section 8-509. Enbridge Illinois argues that those petitioners have not shown a sufficient interest to entitle them to intervene in this proceeding or identified issues that are relevant to a Section 8-509 proceeding, and that their apparent efforts to treat the current Enbridge Petition as also being subject to Sections 8-503 and 15-401 reveals an intent to go beyond the proper issues in a Section 8-509 case. Pliura Petitioners respond, in part, that they each have an enforceable or recognizable right to their individual properties that are in or near the route and will be adversely affected by the pipeline. In its Motion, Enbridge Illinois asserts, among other things, that its pre-existing easement rights have already been affirmed in the federal courts with respect to 37 tracts owned by 28 landowners who now seek to intervene in the current proceeding. Enbridge is not seeking Section 8-509 relief for those tracts. Enbridge Illinois argues that Pliura Petitioners should not 13-0446 be permitted to avoid or relitigate the validity of Enbridge Illinois' rights in those tracts in the current proceeding. In their Response, Pliura Petitioners do not directly respond to Enbridge Illinois’ arguments with respect to those parcels, other than with general comments. It is observed in this ruling that it is not the purpose of the current proceeding to provide an opportunity to relitigate issues already decided in the federal courts, or an opportunity to avoid those decisions, and that a desire to do so is not a sufficient basis for intervention. In its Motion, Enbridge Illinois also states that at least 12 of the landowners who own 18 tracts listed in Schedule A to the Pliura Petition have in fact reached easement agreements with Enbridge Illinois. In their Response, Pliura Petitioners do not directly respond to this contention. Upon a review of the arguments of the parties, it is hereby ruled that the Motion to Deny Intervention is granted with respect to those Pliura Petitioners who are not subject to the request for authorization to utilize eminent domain pursuant to Section 8-509 of the PUA. That is, the Motion is granted with respect to those Pliura Petitioners who are not on the list attached to the Enbridge Petition as Attachment A. As noted above, Enbridge has already been issued a Certificate for the project in Docket No. 07-0446. There were numerous issues addressed by landowners and others in that contested proceeding. The Commission’s decision was upheld in the Appellate Court. The scope of a proceeding under Section 8-509 is more narrow, as reflected in Section 8-509, prior Section 8-509 proceedings and Orders, and the Order in Docket No. 07-0446. Those Pliura Petitioners who are not listed in Attachment A to the Enbridge Petition are not subject to the Enbridge Petition. The Enbridge Petition does not seek any relief with respect to them or their parcels, most of which involve easement rights which have been resolved by the federal courts or by agreements with the owners as observed above. With regard to those landowners who are not listed in Attachment A to the Enbridge Petition, the blanket assertions by Pliura Petitioners in their Intervening Petition and their Response to the Enbridge Motion do not support a conclusion that the issues discussed therein fall within the scope of this Section 8509 proceeding. Signature and Verification The Intervening Petition filed on behalf of Pliura Petitioners is not signed by the persons seeking to intervene. It is signed and verified by attorney Thomas Pliura. In its Motion, Enbridge Illinois argues that the Intervening Petition filed on behalf of Pliura Petitioners is defective because it is not verified by each party named in the petition. Enbridge states that while the petition is verified by attorney Thomas Pliura, Section 200.130 of the Commission’s Rules of Practice requires that the contents be verified by each party. In their Response, Pliura Petitioners argue that one reasonable interpretation of Section 200.130 is that the Petition must be signed and verified by either the party or the party’s attorney. Pliura Petitioners state that in Docket No. 07-0446, petitions to intervene filed by the Pliura Intervenors contained the verification of Counsel, not the individual petitioner, and Enbridge Illinois did not object. It is noted in this ruling that the individual petitioners in Docket No. 07-0446 did sign the petitions to intervene. Section 200.130, “Signature and Verification,” provides in part, “The original of every pleading filed with the Commission shall be signed by the party filing the same or by an officer, agent or attorney therefor … . The contents of all formal complaints, petitions, applications, petitions to intervene, supplemental formal complaints and supplemental petitions shall be verified by the filing party before a notary public”. 2 13-0446 Enbridge also asserts that the Intervening Petition fails to establish that any of the persons listed in the attached Schedule A are in fact represented by attorney Thomas Pliura for purposes of this proceeding. Enbridge Illinois provides examples of “Pliura Intervenors” who may, according to Enbridge Illinois, be represented by a different attorney. With respect to those Pliura Petitioners who are listed in Attachment A to the Enbridge Petition, it appears that a concern of Enbridge Illinois is uncertainty over whether Dr. Pliura does in fact represent the persons named in the Intervening Petition. Given these concerns, to which there was no direct response, those Pliura Petitioners who are on the list in Attachment A of the Enbridge Petition are given until November 1, 2013 to file amended petitions to intervene that are signed by each filing party seeking to intervene. The filings shall be verified by each petitioner, or their attorney. In the meantime, they will continue to be permitted to participate in the proceeding. This procedure does not apply to those filers whose requests to intervene are denied in this ruling above. Whether or to what extent verification by the filing party is expressly required by Section 200.130, as opposed to the filing party’s attorney, is a question that is not reached in this ruling, and no presumptions are created with respect thereto. 3