regional flood control, drainage and stormwater
Transcription
regional flood control, drainage and stormwater
REGIONAL FLOOD CONTROL, DRAINAGE AND STORMWATER MANAGEMENT PROGRAM FIRST QUARTER REPORT FOR JANUARY FEBRUARY MARCH CALENDAR YEAR 2006 SUBMITTED BY BEXAR REGIONAL WATERSHED MANAGEMENT PROGRAM MANAGEMENT COMMITTEE BEXAR COUNTY CITY OF SAN ANTONIO SAN ANTONIO RIVER AUTHORITY EXECUTIVE SUMMARY INTRODUCTION The Inter Local Agreement for Regional Flood Control Management was approved in December 2002 between Bexar County, the City of San Antonio, and the San Antonio River Authority. This agreement represents an evolution of coordination in flood control management efforts between three major entities who have a history of successfully partnering to provide the community flood control initiatives. The goal of the process outlined in the agreement is to build on the strengths and resources each of the entities has to offer in a collaborative and coordinated manner for the benefit of the community. This combined effort will also provide a strong local position in attracting additional nonlocal resources that may be available. The agreement outlines all of the participants and processes critical to implementing a strong and successful program. The success of the program will be measured through the development and implementation of efficient and economic flood control. In approving the document, the governing bodies identified a model that tracks the success to date of the San Antonio River Improvement Project. The oversight and implementation process for this program includes elected officials, entity staff at all levels, and most importantly, a citizens’ advisory process. Each of these levels of representation in the process is explicitly tasked with holding regular meetings to provide public involvement and community input. These groups, which include representatives from each of the partner entities, as identified in the agreement include: • Committee of Seven (Elected officials) • Management Committee (Executive level staff) • Watershed Improvement Advisory Committee (Citizens Advisory) • Technical Committee (Staff and consultants) In order to manage the process and be able to measure the progress of the effort, a series of reporting documents and milestones are identified in the agreement. These include quarterly, annual, and five year reporting requirements which will outline meetings, process, and achievements of the regional flood control management program. The Management Committee has taken the initial step in this process by developing a “Deliverables” tracking sheet to include task, due date, and status of items required by the Inter Local Agreement. 1 FIRST QUARTER REPORT This document represents the First Quarter Report for the Bexar Regional Watershed Management Program (BRWM). The first quarter is comprised of January, February, and March 2006. The report contains the activities of each program group identified in the BRWM Program. The report sections and respective subgroups are as follows: • Section 1: Deliverables List of Management Committee • Section 2: Committee of Seven • Section 3: Management Committee • Section 4: Watershed Improvement Advisory Committee • Section 5: Technical Committee o Geographic Information System Focus Group o Hydrologic & Hydraulic Focus Group o Water Quality Modeling Focus Group To promote understanding of the information provided the respective Inter Local Agreement excerpt, which identifies the responsibilities of each program group, is located behind the section divider for sections 2 through 5. Each section also contains a meeting summary of every meeting that occurred during the third quarter. The meeting summaries include the meeting date, discussions and the resulting actions taken. Meeting agendas, minutes and handouts are not included; however they can be provided by calling 210-335-0263. 2 Acronyms and Abbreviations AACOG ADT BC BMA BRWM C6 C7 CIP COE COSA CPS CRS dFIRM FEMA GIS H&H ILA MOU MC NFIP NRCS RFQ’s SACIP SARA SAWS SC TAMU TCEQ TFMA TPWA TWDB TxDOT UDC USGS WIAC WTC Alamo Area Council of Governments Average Daily Traffic Bexar County Bexar-Medina-Atascosa Water District Bexar Regional Watershed Management Committee of Six Committee of Seven Capital Improvement Projects U.S. Army Corps of Engineers City of San Antonio City Public Service Community Rating System Digital Flood Insurance Rate Maps Federal Emergency Management Agency Geographic Information System Hydrologic/Hydraulic Interlocal Agreement Memorandum of Understanding Management Committee National Flood Insurance Program Natural Resource Conservation Service Request for Qualifications San Antonio Channel Improvement Project San Antonio River Authority San Antonio Water System Suburban Cities Texas A&M University Texas Commission on Environmental Quality Texas Floodplain Management Association Texas Public Works Association Texas Water Development Board Texas Department of Transportation Unified Development Code U.S. Geological Survey Watershed Improvement Advisory Committee Watershed Technical Committee 3 FIRST QUARTER 2006 ACOMPLISHMENTS SARA contracted KGB Texas a public relations firm to assist and develop a BRWM Public Information Program. Bexar County has pushed back the November 2006 bond election for a possible May 2007 Bexar County Flood Tax Bond Election. Bexar County contracted with HNTB, Corporation for scoping and estimating CIPs regarding Bexar County Flood Control Bond Election. Charlie Conner selected as the new WIAC Chairman approved by the Committee of Seven. BRWM staff identified CIPs in the San Antonio River watershed for a Bexar County Flood Control Bond Election. COSA Bond Program is scheduled for May 2007. 4 SECTION 1 MANAGEMENT COMMITTEE DELIVERABLES Bexar Regional Watershed Management Program Deliverables Deliverable: 1. Financial Model Assigned To: SARA 2. Transfer of data to support the Regional Models ALL 3. Watershed Improvement Advisory Committee (WIAC) ALL/COUNTY 4. Suburban City and Federal Installation Program SARA/COSA 5. Management Guidance Document 6. Performance Appraisal and Report Card COSA 7. Watershed Master Plan 8. Regional Watershed Modeling System SARA SARA 9. Quarterly Reporting COUNTY 10. Annual Capital Improvement Plan SARA February 2006 COSA 1 Status: Model has been completed and was approved by C6 on April 5, 2004 Initial data transfer completed in January 2003. Continued sharing of data in progress. Last meeting was held on October 17, 2005. Next meetings are scheduled for February 15th and March 22nd, 2006. 19 Suburban Cities have signed ILAs. The most recent approval was by the city of Helotes on Jan. 12, 2006. The city of Grey Forest considering joining. Complete. Will become part of the Watershed Master Plan. Presented to the WIAC on November 10, 2004 to the C7 on December 6, 2004 and at the public meeting on December 7, 2004 Approximately 95% complete. Regional Watershed Modeling System version 1.0 is complete and ready to be loaded with models as the dFIRM effort finishes. Staff and consultant training and use will start in the Summer 2006. Third Quarter 2005 Report was delivered in Dec. 2005. The Fourth Quarter 2005 report is being prepared. The 2006 update to the CIP list is being prepared using the recently developed H & H models. The list will support the selection of projects for a potential Bexar County bond election in Nov. 2006. Bexar Regional Watershed Management Program Deliverables Deliverable: 11. Five Year Capital Improvement Plan 12. Bexar County/SARA Annual Work Plan Assigned To: SARA COUNTY/SARA 13. Annual approvals of ALL Watershed Master Plan, Five Year and Annual Capital Improvement Plans 14. Coordinate funding and ALL grant opportunities Status: The Five Year CIP is being updated using new H & H models. The FY 2007 work plan is being prepared and discussions with the County are planned for April. Completed as detailed above for 2004. SARA has been awarded $1.2 million in FEMA funds to accelerate dFIRMs for Bexar County. COSA provided $1.88 million; the County provided $350,000 and TxDOT provided additional in-kind services in conjunction with SARA’s $8 million to support the dFIRM project. USACE is funding 50% ongoing flood studies in the Leon, Salado and Cibolo watersheds and in the Woodlawn Lake and Broadway/Alamo Heights areas. SARA is local sponsor. 15. Committee of Seven records and administration Bexar County applied for $4.8 million to support five projects. County match would be 25% or $1.2 million. Ongoing. Next meeting is Feb. 21, 2006. Meeting schedule for 2006 is set. Ongoing. SARA 16. Watershed Improvement COUNTY Advisory Committee records and administration 17. Management Committee COSA records and administration 18. Retain and maintain all SARA statistical and other documents February 2006 Ongoing. Ongoing. SARA complete with the installation of fiber optics, which will allow for 2 Bexar Regional Watershed Management Program Deliverables Deliverable: Assigned To: 19. 311 response and coordination of calls from citizens COSA 20. Watershed Technical Committee (WTC) records and administration SARA February 2006 3 Status: connection to COSA and COUNTY servers. Underway. The Joint Citizens Commission on City-County Service Integration has recommended coordination of 311. Meets no less than two times per month. Meeting minutes and agendas on file at SARA. SECTION 2 COMMITTEE OF SEVEN Committee of Seven Agenda Dates and Topics Fourth Quarter 2005 October 26, 2005 Report from Bexar County on WIAC activities. o Reported last meeting held on October 17, 2005. o Discussed Bexar County Bond Program process and schedule. o Discussed the current modeling (dFIRM) and database program to be held at SARA. o BC, COSA, and SARA reported its FY 2006 budget and programs. Presentation regarding the resignation of Howard Peak as Chairman of the WIAC. o Mr. Peak resigned as Chairman of the WIAC so that he can focus on issues pertaining to the Linear Creekways Advisory Committee. o Additionally, Vice Chairman, Cheryl Focht, has exceeded her attendance and requested the vacancy to be filled. o C7 formed a subcommittee comprised of Tom Weaver-SARA, Commissioner Sergio “Chico” Rodriguez-BC, and Councilwoman Sheila McNeil-COSA for the selection of a new chair and vice chair. Presentation and discussion by SARA regarding the final report of the Upper San Antonio River flood mitigation joint study with the Texas Water Development Board. o The study was part of a grant from the Texas Water Development Board applied by the BRWM partners to conduct a study to identify projects that could mitigate the increases in the flood plain on the Upper San Antonio River. Presentation and discussion by SARA regarding a BRWM program standard for the development of Flood Insurance Rate Maps for Bexar County. o SARA addressed flood mapping options to address the delineation of flood ways and ultimate 100 year flood plain boundaries. o BC and Suburban Cities have a delineated floodway where regulations are more stringent for development. o COSA’s 100 year flood plain is the floodway and applies development restrictions. Presentation by BC, COSA, and SARA regarding the BRWM program’s fiscal year 2006 CIP and plan for technical studies. o BC explained each entity presented the current approved programs. o SARA explained funding was coordinated as part of the program between the three entities. Committee of Seven 1 Presentation by SARA regarding the public accessibility to information created through the RWMS. o The options presented to offer the information for free or for a fee. o The committee requested that SARA develop a detailed cost analysis. Status report by COSA on the BRWM Program deliverables as of October 2005. BC distributed the BRWM Program Quarterly Reports, Second Quarter for Calendar Year 2005. Status report by SARA on the integration of information technology between BC, SARA and COSA. Status report from the Management Committee on the summary of activities and meetings held since May 2005. Status report by BC on the proposed timeline for a potential Bexar County Flood Tax Bond Election with a proposed bond list resulting from the BRWM CIP List. o BC is considering issuing a $250-$300 million bond package supported by the Flood Tax, to the voters in November 2006. o The projects being evaluated and selected meet the criteria of a regional project (a drainage area of at least 1.5 square miles). o A draft list of priority projects have been further refined by the Management Committee. Recommendation from the Management Committee regarding rainfall values for the San Antonio River Basin. o The committee recommended that BRWM use the best and most current data available. December 13, 2005 Report from Bexar County on WIAC activities. o Reported last meeting held on October 17, 2005. o Discussed Bexar County Bond Program process and schedule. o Discussed the current modeling (dFIRM) and database program to be held at SARA. o BC, COSA, and SARA reported its FY 2006 budget and Capital Improvement Programs. Discussion and appropriate action regarding the appointment of a chairman and co-chairman for the WIAC. o The Committee of Seven appointed Charlie Conner as the Chairman of the WIAC. Committee of Seven 2 Status report and time line for completion of the hydraulic and hydrologic models, release of dFIRM for Bexar County; and identification of capital projects for a potential Bexar County flood control bond election presented by SARA and Bexar County. o dFIRM for BC is to be completed by September 2006. o Identification of CIPs by the end of June 2006. Discussion regarding the development of a public information and education campaign for the BRWM Program and potential Bexar County flood control bond issue presented by SARA. o Increase public understanding and awareness regarding the nature, science and terminology of flooding and flood plains in Bexar County including increased of the existence, location, and function of watersheds. Presentation and status report on the Upper San Antonio River Watershed Protection Plan including a report on a public meeting held on November 29, 2005 presented by SARA. Reports by the Management Committee: o Status report on the BRWM Program deliverables. o Report on the integration of information technology between COSA, BC, and SARA. All three entities are connected and training on the new system will be in 2006. o Distribution of the BRWM Program Quarterly Report for the Third Quarter 2005. Committee of Seven 3 SECTION 3 MANAGEMENT COMMITTEE Management Committee Agenda Dates and Topics First Quarter of 2006 January 9, 2006 Status on Communication Consultant Selection: o SARA explained the selection process. o The list of consultants was narrowed down to tow firms: KGB Texas and Guerra, DeBerry and Goode o SARA will contract with the consultant selected. Management Committee Public Meeting. o COSA tentatively requested a meeting for February 13th o Agenda items will be taken from the Committee of Seven meeting. WIAC Appointments prior to February 15th meeting: Charlie Conner has been appointed as Chairman of the WIAC. SARA has one vacancy and working on it being filled. COSA has two vacancies BC has no vacancies. Need to determine WIAC’s role in the selection of projects for the Bexar County Bond Election. o KGB Texas will focus on how WIAC is involved, who they are, and where they come from? o o o o o Bexar County Bond Projects Update: o BC and SARA reported on the status of the potential CIP’s for the upcoming bond. o BC contracted HNTB, Corporation. HNTB performed data collection November thru December. o Staff has provided HNTB with 8 projects “no brainers” which have level 1 cost estimates. o Sent out letters to stakeholders in efforts to seek out leverage opportunities. o COSA Parks and Recreation Dept. has two projects for possible consideration. o Internal coordination with BC officials needs to be moved up in order to be able to lay out the bond process by late May or early June. Balcones Heights Drainage Project: o BC and COSA staff met with Balcones Heights consultant and there is a problem with the study results. o The project appears to have an adverse impact down stream into COSA city limits. o COSA prepared comment sheet on the proposed project. Management Committee 1 Status of dFIRM Mapping effort and discussion of draft flood plain maps and process: o SARA met with consultant and starting to develop maps. o San Antonio River watershed took some time to develop but it is moving forward. o In general SARA staff is not seeing a dramatic change on the flood plains. Rio Perla Development Agreement: o SARA was concerned with the project limits within the agreement. o SARA has an existing project plan to be forwarded to the developer. o COSA is working with Rio Perla to incorporate their vision into the project. o COSA will negotiate an agreement with Rio Perla and present to MC. o Staff needs to report to the SAROC regarding the Rio Perla project. January 23, 2006 Review of February 15th WIAC Agenda: o Item #5 – Status on Bexar County Bond Election to be presented by Bexar County, SARA, and HNTB Corporation regarding CIP’s as “no-brainers”. o Item #6 – Presentation on the BRWM Public Information Program to include schedule for future public meetings presented by SARA and KGB Texas. o Item #7 – Status report on dFIRM mapping effort to be presented by SARA. o Item #8 – Status report on BRWM deliverables to be presented by COSA. o Item#9 – Discussion on WIAC Appointments and Re-appointments to be presented by Bexar County. o Item#10 – Summary Report Bexar County Bond Election status update: o HNTB to move forward on level two cost estimates for the eight “nobrainer” projects. These projects will be designed for a 100 year design. o San Antonio River watershed projects are being analyzed by BC, COSA, and SARA. o Meetings are being scheduled with COSA and BC regarding CIP’s starting in early February thru late March. o Projects being requested which do not meet the regional definition (1.5 square mile) drainage area, can request for a variance by the Management Committee. Management Committee Public Meeting: o Schedule next meeting and prepare a draft agenda. Management Committee 2 Committee of Seven February 21st meeting agenda: o SARA discussed agenda and made minor changes. Other Business: o Grey Forest is considering joining the BRWM and approving the ILA. o Water Quality focus group is meeting to discuss the Watershed Protection Plan. o City of Balcones Heights is pending COSA approval to complete the project. o Future meetings to be scheduled with Suburban Cities January30, 2006 Review final agenda for WIAC meeting on February 15, 2006. Discussed and reviewed Management Committee Public Meeting for March 7th o Watershed Protection Plan for the San Antonio River watershed o dFIRM mapping status o Status on CIPs for the County Bond Election o Education Campaign and upcoming public meetings for County Bond Election o Updated status of ILA Deliverables Modeling information provided to FEMA o Modeling information requested by COSA Bexar County Bond Program Public Meeting Schedule o SARA presented the public meetings scheduled for the CIP Bond projects Other Business: o Enhancement Program: Bexar County in submitting on project within the San Antonio River. o Railroad along I-10 corridor: Railroad will be converted into a trail and drainage issues along this corridor need to be addressed. o Public Information Program schedule and survey questions: SARA distributed schedule and survey questions and requested comments. February 13, 2006 Bexar County Bond Program Update: o HNTB presentation on the project status update. o KGB Texas presentation (public information program) o Proposed CIPs in the San Antonio River Watershed. WIAC meeting agenda packets for the February 15th Management Committee 3 o Packets were handed out to the Management Committee. February 21, 2006 Bexar County Bond Program update. o San Antonio River Watershed CIPs were presented and to move forward with analysis to HNTB. o SA23, SA19, SA6, SA22 required additional evaluation and analysis in order to move forward. o SA21, SA5, and SA25 delete from the list as not moving forward. o Management Committee requested staff to look upstream in the Balcones Heights and bridge crossings in the SARIP as a regional project. February 27, 2006 Bexar County Bond Program update. o Review pending CIP projects in the San Antonio River Watershed. o SA6, SA3, SA22, SA25, and SA26 to be include in the list of CIPs to move forward with analysis. o Review of initial CIPs for the Medina Watershed. o MR1 is currently being reviewed. o Review of initial CIPs for the Leon Creek Watershed. o LC1 and LC2 delete from the list. o LC8 is being reviewed and need to identify detention facilities in the upper watershed. Management Committee Public Meeting scheduled for March 28th. o The meeting has been rescheduled for April 11th. Debriefing on action items from the Committee of Seven meeting. o City of Balcones Heights Project- need to set up coordination meetings with COSA, BC and City of Balcones Heights. o Public Relations – need to coordinate meetings with BC, COSA and SARA. o It will supplement the Linear Creekways Maintenance document. Debriefing on action items from the WIAC meeting. o No action items requested. March 6, 2006 Communication Committee briefing on the Public Information Program. Management Committee 4 o Bexar County is considering pushing back the Bond Program from November 2006 to May 2007 o COSA Bond Program is still on schedule for a May 2007. Management Committee Public Meeting for April 11th. o Discussed the agenda and report to be completed by all the partners. Bexar County Bond Program update o San Antonio River Watershed: Delete SA19 and SA23; add SA27. March 20, 2006 Management Committee Public Meeting for April 11th o Agenda will be revised. o Report Card needs to be updated by COSA, BC and SARA. o Publicity for the meeting will be in the media, and notices to be mailed out from SARA’s database. Review CIP Schedule: o Needs to be revise schedule to reflect elected official briefings o Revise public and organization meetings. Review public outreach material and potential schedule change impacts. o Management Committee recommended staff to continue the branding of BRWM. Review elected official and WIAC CIP packets for the San Antonio River watershed projects. o Need to include Average Daily Count (ADT), projects benefits, project description, preliminary and existing floodplains, aerial photography, and map location. Discuss the viability of pre-development detention facilities for the Cibolo and Medina watersheds. o SARA to research various options for detention facilities. o Management Committee requested staff look at MPO Major Thoroghare Plan. o SARA stressed that a watershed master plan needs to occur in order to make a strong recommendation in the rural areas of the county. Management Committee 5 SECTION 4 WATERSHED IMPROVEMENT ADVISORY COMMITTEE WIAC Agenda Dates and Topics First Quarter 2006 February 15, 2006 Presentation regarding the status and time line for completion of the hydraulic and hydrologic models; release of digital Flood Insurance Rate Maps for Bexar County; and identification of capital projects for a potential Bexar County flood control bond election to include a discussion on the WIACs role on the CIP/Bond Program. o Bexar County presented the Bexar County Bond program update and the CIP selection for the proposed 2006 Bexar County Bond election. o SARA presented on the dFIRM status. o HNTB presented their role in the cost estimating for Bexar County Bond Program. Presentation and discussion regarding the public information and education campaign for the Bexar Watershed Management Program and potential Bexar County flood control bond issue. o SARA and KGB Texas made the presentation. o The public information program will focus on public relations and marketing and advertising. o Public relations: Brought on for education and not advocacy. o Marketing and advertising: Develop a program that will elevate people’s interest. Communication: The upcoming meetings will be to discuss the CIPs being proposed by watershed. The committee decided to create subcommittees by watershed but all committee members are invited to attend all the subcommittee meetings in order to be familiar with the CIPs being presented. Agenda items # 6, 7, 8, & 9 were deferred to the next WIAC meeting. March 22, 2006 (Upper San Antonio River Watershed Subcommittee) WIAC Presentation regarding the identification of Capital Improvement Projects (CIP’s) on the Upper San Antonio River Watershed for a potential Bexar County flood control bond election. o SARA made the presentation on the Upper San Antonio River CIPs. o The committee agreed with the 14 CIPs presented and to move forward. o The committee requested staff to coordinate with military installations involving CIPs such as SA25 Mulberry Low Water Crossing. 1 SECTION 5 TECHNICAL COMMITTEE REGIONAL WATERSHED MODELING AND PLANNING Report by: WATERSHED TECHNICAL COORDINATION Management Team Goals List Activity/Actions Tech & Financial Models Eliminate Duplication/ Increase Efficiency X CIP Priority List Design & O&M standards Other COE Coordination Reporting Period: January 2006 Status Date: Feb. 28, 2006 Accomplishments Estimated Completion Date % Complete Broadway / Woodlawn Study X On-going Activity • No progress on Broadway Study On-hold waiting on. • COE initiating data gathering; minimal progress by COE Cibolo Creek Study y Jan. 25th meeting with COE to discuss scope of Phase III with sponsors & BRWM. COE needs firm direction on Phase III by early March. Lower San Antonio Basin Study • COE working on H&H and Flood Mapping System • Developing Karnes County planimetrics • Discussing calibration issues between Bx. Co. dFIRM Q’s & Historic Q’s • H&H deliverable scheduled for March 2006 Salado Creek Study • No significant progress Leon Creek Study – (dFIRM effort) - Hydrologic Analysis – (COE work) • Storage routings incorporated in HEC-HMS model • Calibration of HEC-HMS model started. - Hydraulic Analysis - (COE work) • GEO-RAS models imported to HEC-RAS • Continue development of HEC-RAS storage models • HEC-RAS storage models submitted on Jan. 31, 2006 - Hydraulic (original scoped streams, routing models only) (Halff & Assoc) • Created TIN’s and generated contours for all the study stream corridors • Verified stream centerlines for all the study stream corridors including Corps streams Management Team Goals List Activity/Actions Status Accomplishments Estimated Completion Date • Tech & Financial Models X Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other WTC (general) %Complete X On-going Activity On-hold waiting on. X Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other Year 2 activities by UT/A&M/PBS&J %Complete X On-going Activity On-hold waiting on. Created “N” value shapefiles for all study stream corridors in scope • Completed cross section layouts for all study streams in scope • The input of all structure surveys have been processed and imputed into the HEC-RAS models • Balancing of all HEC-RAS routing models are complete. - Hydraulics (Importing Bridge Data for COE Streams) • Created “N” value shapefile study streams. (100% complete) • Received and processed all survey data All of the Corp’s base HEC-RAS models with structures input have been completed General • 12/3 ILA presentation to the City of Helotes & Grey Forrest • 1/4 Details meeting w/HNTB about CIP information collected. • 1/13 meeting w/EAA about potential dam CIP • 1/17 RWMS presentation to CEC • 1/27 WQ Focus group meeting y 1/27 FEMA quarterly meeting w/BRWM • 1/26 COE project update to BRWM Develop Regional Watershed Modeling System (RWMS) • Phase III work started • Developing a business plan with PBS&J for RWMS (PBS&J draft reviewed; comments due back by SARA) Management Team Goals X Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other List Activity/Actions dFIRM Work Status % Complete X On-going Activity On-hold waiting on. Accomplishments Estimated Completion Date PBS&J A. Support Task a. Participated in the 3rd FEMA Quarterly Review Meeting. b. Conducted and completed the mapping workshop B. Task 1 – Field Surveys and Reconnaissance a. Finalizing survey TSDN – to be delivered next month C. Task 2 – Topographic Data Development a. Received all of the riverine topographic data. D. Task 3 - Independent QA/QC Review of topographic Data - Not Applicable E. Task 4 - Hydrologic Analysis a. Submitted interim hydrologic model on Dec. 15, 2005 b. Submitted interim hydrology TSDN on Dec. 28, 2005 c. Responding to all review comments from SARA, COSA and Bx. Co. d. Finalizing hydrology TSDN F. Task 5 – Independent QA/QC Review of Hydrologic Analysis – Not applicable at this stage of the project. G. Task 6 – Hydraulic Analysis a. Delivered partial submittal of interim hydraulic models on Dec. 15, 2005 b. Delivered additional submittal of interim hydraulic models along with the full set of survey data and preliminary floodplains (directly from GeoRAS) on Dec. 28, 2005 c. Received review comments from COSa, Bx. Co. and SARA. Finalixzing revisions to hydraulic models based on review comments provided. d. Finalizing hydraulic TSDN H. Task 7 – Floodplain Mapping a. Continuing to develop floodplain boundaries for detailed (including conversion reaches) Management Team Goals List Activity/Actions Status Accomplishments Estimated Completion Date and limited detail stream segments. b. Prepared base map template for work maps. c. Delivered sample of draft base map template on December 15, 2005 d. Delivered preliminary floodplain information generated from GeoRAS with the hydraulic submittal on December 28, 2005 Pape Dawson A. MAS Task #3 - Field Surveys and Reconnaissance • Completed field survey TSDN and uploaded all survey data to MIP B. MAS Task #4 – Topographic Data Development • Continuing development of additional topography to supplement riparian corridor.. C. MAS Task #6 - Hydrologic Analysis. • Completed all hydrologic models. Submitted final hydrologic TSDN for San Antonio River Watershed D. MAS Task #8 – Hydraulic Analysis • Completed all hydraulic models on all study streams E. MAS Task #10 – Floodplain Mapping • Began mapping for Cibolo Creek tributaries and Calaveras Creek • Began redelineation and digital conversion rectification on all watersheds F. MAS Task #13 • Continuing final centerline delineation and creation of DCS/dFIRM Turner Collie & Braden A. Task 3 – Field Surveys and Reconnaissance: a. Uploaded data to the FEMA MIP b. Compiled TSDN submittal. B. Task 4 – Topographic Data Development: a. Phase II production underway (70% complete) b. Corridor DTM production complete. C. Task 6 – Hydrologic Analysis: a. Responded to interim review comments Management Team Goals List Activity/Actions Status Accomplishments b. Medina Ultimate developed model in production c. Leon Ultimate developed model awaiting approved existing model Estimated Completion Date D. Task 8 – Hydraulic Analysis: a. Medina River (detailed): 90% complete b. Other 5 detailed models fully underway: 95% complete c.26 limited detail models fully underway: 90%complete d. Remaining 8 limited detail models schematically complete. e. All 72 approximate models schematically complete E. Task 10 –Floodplain Mapping a. Began mapping setup processes F. Task 13 - DFIRM – Digital Conversion a. Received data for conversion of Atascosa, Medina and Leon streams awaiting tie-ins with modeled streams G. Task 14 – dFIRM – Merge: a. Began mapping setup processes. Halff & Associates • Created TIN’s and generated contours for all the study stream corridors • Verified stream centerlines for all the study stream corridors including Corps streams • Created “N” value shapefiles for all study stream corridors in scope • Completed cross section layouts for all study streams in scope • The input of all structure surveys have been processed and imputed into the HEC-RAS models • Balancing HEC-RAS routing models complete Management Team Goals X Tech & Financial Models X Eliminate Duplication/ Increase Efficiency CIP Priority List X Design & O&M standards Other Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other List Activity/Actions Status Accomplishments Estimated Completion Date H&H focus group % Complete X On-going Activity On-hold waiting on − No specific activity; focus was on dFIRM GIS/IT/Monumentation Focus Group % Complete X On-going Activity On-hold waiting on. − No activity WQ focus group % Complete X On-going Activity On-hold waiting on. − 12/30 Meeting to discuss : • WPP Status • BMP to be applied in the Bx. Co. Bond Projects • Real Time WQ monitoring w/TCEQ • Cibolo Study (Phase III) • HSPF training • Mayor’s AD-HOC WQ report REGIONAL WATERSHED MODELING AND PLANNING Report by: WATERSHED TECHNICAL COORDINATION Management Team Goals List Activity/Actions Tech & Financial Models Eliminate Duplication/ Increase Efficiency X CIP Priority List Design & O&M standards Other Reporting Period: February 2006 Status COE Coordination % complete Date: March 23, 2006 Accomplishments Estimated Completion Date Broadway / Woodlawn Study • No progress on Broadway Study X On-going Activity Cibolo Creek Study th On-hold waiting y Jan. 25 meeting with COE to discuss scope of Phase III with sponsors & BRWM. COE needs firm on . direction on Phase III by early March. • Difficulties in calibrating Q’s between Upper & Lower Cibolo Lower San Antonio Basin Study • COE working on H&H and Flood Mapping System • Hydrologic analysis- completed hydrology for Goliad tributaries, Cabeza Creek, Escondido Creek, and Nichols Creek • Hydraulic analysis- completed hydraulic models for Goliad tributaries, Cabeza Creek, Escondido Creek and Nichols Creek • Developing Goliad County planimetrics • Discussing calibration issues between Bx. Co. dFIRM Q’s & Historic Q’s • COE starting windshield survey of structures • Flood warning software development on schedule Salado Creek Study • No significant progress Leon Creek Study – (dFIRM effort) - Hydrologic Analysis – (COE work) • Revisions requested to model by Halff have been incorporated and depth area analysis is being rerun for all frequencies - Hydraulic Analysis - (Final hydraulic models for Management Team Goals List Activity/Actions Status Accomplishments • • Tech & Financial Models X Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other WTC (general) % Complete X On-going Activity On-hold waiting on . Estimated Completion Date original scoped streams) Waiting for hydrology to be completed. It is expected that discharges will be provided by the COE by March 1, 2006. BRWM staff should complete their review by March 6, 2006 All topo required has been provided as of February 20, 2006. • The TIN was supplemented with the additional topo and submitted to the Corps on Feb. 17, 2006. • Final funding has been approved and allocated for this work order as of Feb. 15, 2006 • Due to the delays in receiving final discharges, the delivery schedule will need to be revised. The schedule will be revised after the hydrology is complete and considered final. It is expected that the final delivery date of 5/1/06 (final hydraulic only) will be maintained, but the first few stream deliveries will be delayed. • The compressed schedule submitted will also need to be revised after the hydrology is complete and considered final. It is expected that final hydraulic models for all scoped streams can be completed by the 5/1/06 deadline, but final mapping and TSDN for these streams may not be fully complete. It is expected that the revised compressed schedule will need to include a prioritization of streams needing to be mapped by the 5/1/06 deadline. General • 12/3 ILA presentation to the City of Helotes & Grey Forrest • 1/4 Details meeting w/HNTB about CIP information collected. • 1/13 meeting w/EAA about potential dam CIP • 1/17 RWMS presentation to CEC • 1/27 WQ Focus group meeting y 1/27 FEMA quarterly meeting w/BRWM • 1/26 COE project update to BRWM Management Team Goals X Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other X Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other List Activity/Actions Year 2 activities by UT/A&M/PBS&J Status Accomplishments Estimated Completion Date Develop Regional Watershed Modeling System Complete (RWMS) X On-going Activity • Phase III work started On-hold waiting • Developing a business plan with PBS&J for RWMS (PBS&J draft reviewed; comments due back by on . SARA) % dFIRM Work % Complete X On-going Activity On-hold waiting o PBS&J A. Task 1 – Field Surveys and Reconnaissance a. Completed survey of detailed bridge/culvert crossing. Finalizing detailed survey with last submittal of survey corrections. b. Completed QA/QC of field data prior to uploading into WISE. Almost complete with all detailed survey migration into WISE. c. Completed upload of all limited detail ed survey data into WISE d. Completed all survey of limited detailed sections. e. Finalized survey TSDN and delivered to SARA B. Task 4 - Hydrologic Analysis a. Finalized model calibration b. Finalized locations for flow changes in the HECRAS models (HEC-HMS) computational point corresponding to a HEC-RAS river/reach/ station c. Developed modified Puls Routing information based on finalized HEC-RAS models d. Finalized design flows e. Submitted interim hydrologic model on Dec 15, 2005 f. Submitted interim hydrology TSDN on Dec. 28, 2005 g. Responding to all review comments from SARA, City of San Antonio and Bexar County h. Finalized hydrology TSDN- delivered to client. C. Task 6 – Hydraulic Analysis a. Completed modifications to Conversion reaches. This work included vertical datum Management Team Goals List Activity/Actions Status Accomplishments Estimated Completion Date adjustment, verification /modification of structures based limited detail survey, incorporation of LOMR information, extension of modeling into additional detailed areas and extension of cross sections where necessary. b. Completed WISE Open System Inventory Processing. We need to upload final datasets onto the MIP, but have been encountering technical difficulties with the Citrix connection. c. Completed detailed reach stream modeling based on topographic data and detailed field survey data. d. Completed limited detail reach stream modeling based on topographic data and limited detail survey data. e. Delivered partial submittal of interim hydraulic models on Dec. 15,2005 f. Delivered additional submittal of interim hydraulic models along with the full set of survey data and preliminary floodplains (directly from GeoRAS) on Dec. 28, 2005 g. Received review comments from City, County and SARA. Finalizing revisions to hydraulic models based on review comments provided h. Finalizing hydraulic TSDN – will submit to SARA early March. D. Task 7 – Floodplain Mapping a. Continuing to develop floodplain boundaries for detailed (including conversion reaches)and limited detail stream segments. b. Prepared base map template for work maps. c. Delivered sample of draft base map template on December 15, 2005 d. Delivered preliminary floodplain information generated from GeoRAS with the hydraulic submittal on December 28, 2005 e. Finalizing work map information and generating watershed work maps f. Preparing mapping TSDN Management Team Goals List Activity/Actions Status Accomplishments Estimated Completion Date Pape Dawson A. MAS Task #3 - Field Surveys and Reconnaissance • Assembled all data on MIP B. MAS Task #4 – Topographic Data Development • Continuing development of additional topography to supplement riparian corridor.. C. MAS Task #6 - Hydrologic Analysis. • Beginning development of Ultimate Development Hydrology D. MAS Task #8 – Hydraulic Analysis • Addressing comments from local review partners E. MAS Task #10 – Floodplain Mapping • Submitted Preliminary Mapping TSDN for Calaveras Creek and San Antonio River watersheds • Submitted Draft Final Mapping TSDN for tributaries of Cibolo Creek. F. MAS Task #13 • Continuing final centerline delineation and creation of DCS/dFIRM databases G. MAS Task #14 • Merged all delineations in Calaveras and San Antonio River Watersheds H. MAS Task #15 • Began creation of FIS report for Calaveras Creek Turner Collie & Braden A. Task 3 – Field Surveys and Reconnaissance: a. Compiled TSDN submittal. B. Task 4 – Topographic Data Development: a. Phase II production underway (TIN’s 100%, final tiled datasets 30%) b. Corridor DTM production complete. C. Task 6 – Hydrologic Analysis: a. Revised model to reflect interim review comments and additional improvements b. Medina Ultimate developed model in Management Team Goals List Activity/Actions Status Accomplishments Estimated Completion Date production (parameter generation) c. Leon Ultimate developed model awaiting approved existing model D. Task 8 – Hydraulic Analysis: a. 5 detailed models in client review. 1 in production b. 15 limited detail models in client review, 5 ready for submittal, 13 in production c. 32 approximate models in production E. Task 10 –Floodplain Mapping a. Awaiting model data F. Task 13 - DFIRM – Digital Conversion a. Re-assessed conversion process, per Baker comments in mapping workshop. New process entails greater effort than prior estimates G. Task 14 – dFIRM – Merge: a. Awaiting mapping data. H. Task 15 – TSDN & text write-up a. In production Halff & Associates (parts of Upper Cibolo & Upper SAR) • Created TIN’s and generated contours for Upper Apache Creek, Bandera Branch, Upper reach of Martinez A, and Commercial tributary to Six Mile Creek • All streams are in HEC-RAS and cleanup of models are being performed. • Hydrology from the LMMP COE model is being adjusted to provide additional discharge points. • Received missing topo for Cibolo Creek and Six Mile Creek on Sept. 26, 2006 • Received new discharges from Pape-Dawson from revised LMMP model on Jan. 30, 2006 • HEC-RAS models for Zarzamora Creek, Apache Creek, and Bandera Branch were submitted to the Corps on Jan. 20, 2006. The Corps forwarded Management Team Goals List Activity/Actions Status Accomplishments • these models and files to SARA for review. HEC-RAS models for Alazan, Alazan UNT, Eastr Woodlawn, Martinez A, Martinez A trib, Six Mile Creek, Commercial Trib, and South Flores Trib were submitted to the Corps on Feb. 6, 2006. The Corps forwarded these models and files to SARA for review. Waiting for review comments from the Corps, SARA, City of SA, and BxCo prior to proceeding with final hydraulic models and final mapping. It is expected that review comments will be received by March 6, 2006 Due to the delays regarding the Cibolo Creek hydrology produced by the Corps, the Cibolo Creek schedule was delayed. The preliminary discharges for Cibolo Creek were received by the Corps. on Feb. 13, 2006. In addition, there is significant overbank topo needed on the Guadalupe County side that needs to be supplemented. Therefore, the preliminary HECRAS model for Cibolo Creek is expected to be submitted by March 10, 2006. Floodplain Mapping- preliminary delineations and work maps have been developed for the hydraulic submittals DFIRM Production- No progress at this time − No specific activity; focus was on dFIRM • • • • X Tech & Financial Models X Eliminate Duplication/ Increase Efficiency CIP Priority List X Design & O&M standards Other H&H focus group % complete X On-going Activity On-hold waiting on Estimated Completion Date Management Team Goals Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other List Activity/Actions GIS/IT/Monumentation Focus Group Status Accomplishments Estimated Completion Date % Complete X On-going Activity On-hold waiting on. − No activity % Complete X On-going Activity On-hold waiting on − 2/24 Meeting to discuss : • WPP Status • Discuss the States request for comments on the State Stream Standards • Review stream standards for Upper SAR • Stream Bank Restoration by CSA on Salado Creek WQ focus group . REGIONAL WATERSHED MODELING AND PLANNING Report by: WATERSHED TECHNICAL COORDINATION Management Team Goals List Activity/Actions Tech & Financial Models Eliminate Duplication/ Increase Efficiency X CIP Priority List Design & O&M standards Other COE Coordination Reporting Period: March 2006 Status Date: April 28, 2006 Accomplishments Estimated Completion Date % Complete Broadway / Woodlawn Study X On-going Activity • No progress on Broadway Study On-hold waiting Cibolo Creek Study on . • Difficulties in calibrating Q’s between Upper & Lower Cibolo • H&H 100% Lower San Antonio Basin Study • COE working on H&H and Flood Mapping System • Flood warning software development schedule of delivery moved to August 2006 for WES to support relief efforts in New Orleans • 100% of planimetrics in all 3 counties completed by SARA & delivered to COE • H&H by COE at 100% federal • FY’06 funds almost depleted Salado Creek Study • No significant progress Leon Creek Study – (dFIRM effort) - Hydrologic Analysis – (COE work) • Final HMS model submitted March 8, 2006: this model included the depth-area analysis for all frequencies - Hydraulic Analysis – • Final hydraulic modeling with final Q’s started. • Final hydraulic models for 10 streams were submitted on March 30, 2006 - Hydraulic Analysis – (by Halff & Assoc.)(Final hydraulic models for original scoped streams) • Final hydrology was provided on March 9, 2006 • Halff provided comments on the hydrology for several stream between March 9th and March 21st. The Corps provided final resolutions to these comments on April 1, 2006. Management Team Goals List Activity/Actions Status Accomplishments • • Tech & Financial Models X Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other WTC (general) X Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other Year 2 activities by UT/A&M/PBS&J % Complete X On-going Activity On-hold waiting on . Estimated Completion Date Due to delays in receiving final discharges, the delivery schedule will need to be revised. It is expected that the final hydraulic models with preliminary 100 and 500 delineations, as per the scope of the COE contract, will be completed by 5/1/06 For the follow up FEMA contract to perform final mapping and TSDN, the delivery schedule will be delayed in a proposed SPR to be submitted to FEMA this week. The schedule for this work will depend on the final hydraulic and preliminary mapping reviews by all agencies, which is in need prior to the final mapping being performed. General • 3/8 meeting w/ Branton Ross (CSA Linear Creekways) to coordinate Bx. Co. CIP projects • 3/9 RWMS presentation to City of Austin • 3/14 & 3/28 meetings of BRWM Communications Comm. • 3/16 Work session w/Commissioner’s Court regarding dFIRM & CIP bond election y 3/15 Discussed w/Joe Chapa (CSA) fiture aerial flight plans & opportunities. • 3/22 WIAC meeting Discussed SAR CIP’s Develop Regional Watershed Modeling System % Complete (RWMS) X On-going Activity • Web Portal updates started (Phase III) On-hold waiting • Business plan complete; started public/private agreement for RWMS rights & development on . Management Team Goals X Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other List Activity/Actions Status dFIRM Work % Complete X On-going Activity On-hold waiting on. Accomplishments PBS&J A. Task 1 – Field Surveys and Reconnaissance a. Completed survey of detailed bridge/culvert crossing. Finalizing detailed survey with last submittal of survey corrections. b. Completed QA/QC of field data prior to uploading into WISE. Almost complete with all detailed survey migration into WISE. c. Completed upload of all limited detailed survey data into WISE d. Completed all survey of limited detailed sections. e. Finalized survey TSDN and delivered to SARA B. Task 2 – Topographic Data Development a. Received all of the riverine topographic data. C. Task 3 – Independent QA/QC Review of Topographic Data _ Not Applicable D. Task 4 - Hydrologic Analysis a. Finalized model calibration b. Finalized locations for flow changes in the HEC-RAS models (HEC-HMS) computational point corresponding to a HEC-RAS river/reach/ station c. Developed modified Puls Routing information based on finalized HEC-RAS models d. Finalized design flows e. Submitted interim hydrologic model on Dec 15, 2005 f. Submitted interim hydrology TSDN on Dec. 28, 2005 g. Responding to all review comments from SARA, City of San Antonio and Bexar County h. Finalized hydrology TSDN- delivered to client. i. Received and addressed hydrology TSDN comments E. Task 6 – Hydraulic Analysis a. Completed modifications to Conversion reaches. This work included vertical datum adjustment, verification /modification of Estimated Completion Date Management Team Goals List Activity/Actions Status Accomplishments structures based limited detail survey, incorporation of LOMR information, extension of modeling into additional detailed areas and extension of cross sections where necessary. b. Completed WISE Open System Inventory Processing. We need to upload final datasets onto the MIP, but have been encountering technical difficulties with the Citrix connection. c. Completed detailed reach stream modeling based on topographic data and detailed field survey data. d. Completed limited detail reach stream modeling based on topographic data and limited detail survey data. e. Delivered partial submittal of interim hydraulic models on Dec. 15,2005 f. Delivered additional submittal of interim hydraulic models along with the full set of survey data and preliminary floodplains (directly from GeoRAS) on Dec. 28, 2005 g. Received review comments from City, County and SARA. Finalizing revisions to hydraulic models based on review comments provided h. Finalizing hydraulic TSDN – will submit to SARA early March. F. Task 7 – Floodplain Mapping a. Continuing to develop floodplain boundaries for detailed (including conversion reaches)and limited detail stream segments. b. Prepared base map template for work maps. c. Delivered sample of draft base map template on December 15, 2005 d. Delivered preliminary floodplain information generated from GeoRAS with the hydraulic submittal on December 28, 2005. Estimated Completion Date Management Team Goals List Activity/Actions Status Accomplishments e. Finalizing work map information and generating watershed work maps f. Preparing mapping TSDN g. Submitted work maps for SARA review Pape Dawson A. MAS Task #3 - Field Surveys and Reconnaissance • Assembled all data on MIP B. MAS Task #4 – Topographic Data Development • Continuing development of additional topography to supplement riparian corridor.. C. MAS Task #6 - Hydrologic Analysis. • Continuing development of Ultimate Development Hydrology D. MAS Task #8 – Hydraulic Analysis • Completed addressing final comments from local review partners • Uploaded final hydraulic TSDN for Cibolo Tributaries to MIP E. MAS Task #10 – Floodplain Mapping • Preparing Final Mapping TSDN for Calaveras Creek & SAR watersheds • Preparing Final Mapping TSDN for tributaries of Cibolo Creek. F. MAS Task #13 • Finalizing DCS/dFIRM databases G. MAS Task #14 • Merged all delineations in Calaveras and San Antonio River Watersheds H. MAS Task #15 • Preparing FIS report for all tributaries Turner Collie & Braden A. Task 3 – Field Surveys and Reconnaissance: a. Submitted draft TSDN B. Task 4 – Topographic Data Development: a. Final tiled datasets 50% complete b. TSDN production underway C. Task 6 – Hydrologic Analysis: Estimated Completion Date Management Team Goals List Activity/Actions Status Accomplishments a. Medina existing conditions final report submitted. b. Medina Ultimate conditions draft report submitted c. Medina TSDN production underway d. Leon awaiting approved existing conditions model from USACE D. Task 8 – Hydraulic Analysis: a. Medina existing conditions draft models submitted b. Leon awaiting approved existing conditions model from USACE E. Task 10 –Floodplain Mapping a. Medina awaiting approved model data b. Leon awaiting approved model data F. Task 13 - DFIRM – Digital Conversion a. Atascosa production 90% complete b. Medina production underway, awaiting adjacent mapping c. Leon awaiting adjacent mapping G. Task 14 – dFIRM – Merge: a. Awaiting final mapping data. H. Task 15 – TSDN & text write-up a. In production as discussed above X Tech & Financial Models X Eliminate Duplication/ Increase Efficiency CIP Priority List X Design & O&M standards Other − H&H focus group % Complete X On-going Activity On-hold waiting on. 3/29 H&H meeting to explain in depth the use of aerial reduction in the dFIRM project Estimated Completion Date Management Team Goals Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other Tech & Financial Models Eliminate Duplication/ Increase Efficiency CIP Priority List Design & O&M standards Other List Activity/Actions GIS/IT/Monumentation Focus Group Status % Complete X On-going Activity On-hold waiting on. Accomplishments − No activity WQ focus group % Complete X On-going Activity On-hold waiting on. • • 3/31 WQ focus group meeting 3/29 WPP public meeting #2 conducted at SARA Estimated Completion Date