YUSUFELI DAM AND HEPP
Transcription
YUSUFELI DAM AND HEPP
REPUBLIC OF TURKEY MINISTRY OF ENERGY AND NATURAL RESOURCES GENERAL DIRECTORATE OF STATE HYDRAULIC WORKS REAL ESTATE AND EXPROPRIATION DEPARTMENT YUSUFELI DAM AND HEPP RESETTLEMENT ACTION PLAN DRAFT FINAL CHAPTER 3 MINIMIZING RESETTLEMENT Environmental Consultancy Co. July 2006 (Rev B), Ankara 3. MINIMIZING RESETTLEMENT Yusufeli Project is a significant energy production project for Turkey. As such, it is of public interest, but will result in an involuntary resettlement of the people living in the project area. Any project planning should aim at minimization of displacement of the people to the extent possible. Minimization of displacement is given high priority throughout the resettlement action planning and will be of prior importance during implementation as well. At this stage of Yusufeli Project development, involuntary resettlement is acknowledged as unavoidable by all stakeholders. Basic aim for further action is full and fair compensation of the affected people. In this chapter, the efforts towards minimization of resettlement during project planning and the issues to be considered for this purpose during project implementation are presented. 3.1. Minimization of Resettlement during Project Planning and Design 3.1.1. Coruh Basin Hydropower Development Context Yusufeli Dam and HEPP were decided to be built as a part of the Development of Coruh River Basin, in accordance with the energy policies of Turkey. The master plan for the project was completed in 1982. In these and continuing studies various options were considered for the Coruh River Development Plan and as a result 10 hydro projects were planned on the main course of Coruh River to be developed in series in a cascade style. These projects are considered in three groups as; lower Coruh (Muratli, Borcka and Deriner), middle Coruh (Yusufeli and Artvin) and upper Coruh (Laleli, Ispir, Gullubag, Aksu and Arkun) projects. Muratli Project was taken into operation in June 2005 and Borcka and Deriner projects are under construction with more than 90% and 75% physical completion, respectively. The constructions of Muratli and Borcka Projects started in September 1999 and have been undertaken by Turkish and Austrian companies on a full-financing basis (with international finance). Construction of Deriner Project was started in April 1998, which is being undertaken by a consortium of Turkish, Swiss, and Russian companies with fullfinancing as well. Three large reservoirs were planned to be constructed at Laleli, Yusufeli and Deriner sites, located at the uppermost, middle and lower parts, respectively, to regulate the Coruh River flow. The drainage area of the Coruh River increases by 1.9 times after the Oltu River joins the main stream. Therefore Yusufeli Dam, the second largest of the Coruh development plan after Deriner Dam, was planned to be constructed about 800 m downstream from the confluence with Oltu River. Artvin Dam, located 19 km downstream of Yusufeli dam site, was planned to make use of the residual head between Yusufeli and Deriner projects. In the feasibility studies of all these projects, each project was not only evaluated to be feasible in itself, but also their feasibility was assessed in integration with all the projects proposed in the Coruh Basin. These projects are not only interrelated with respect to their operation to produce energy, but also with regard to the infrastructure that they need and which they would affect. Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 1 / 14 Based on the feasibility report of Japan International Cooperation Agency (JICA, 1986) the proposed Yusufeli Project site was determined to be the best economically and technically feasible option. Then, Japan Electric Power Development Company (EPDC), Su-Is Project Engineering Company, and Terzibasoglu Consultancy and Engineering Company completed the design documents in October 1990, which were approved by the Electrical Power Resources Survey and Development Administration (EIE). The project was first put into 1997 Investment Program by the Turkish Government. Studies on two types of alternatives, project site and project size, which was presented in the Feasibility Report on Coruh River Hydroelectric Power Development Project prepared by JICA (1986), would have an effect on the extent of expropriation and resettlement. 3.1.2. Alternative Dam Site Locations Alternative dam site locations for the Yusufeli Project were considered during the feasibility studies done by Japan International Cooperation Agency (JICA) in 1986, before selecting the proposed site. An alternative set-up for the middle Coruh was investigated in order to avoid the inundation of the Yusufeli Town. This set-up is referred to as the “3-dam plan.” As a result of the evaluations at that time, it was concluded that the set-up of the 2-dam plan is more favorable. Evaluation of these alternatives with respect to the issues such as energy production, inundation area and characteristics, impact on land use and resettlement needs, required secondary structures (transmission lines and relocation roads) are presented in detail in the EIA report (ENCON, 2005). Here a summary of the results of this evaluation and the rationale of the decision is provided. The evaluation studies for these alternatives showed that the 3-dam alternative would avoid the inundation and relocation of the Yusufeli district center and would overall cause considerably less people to resettle (about 414 HH), when compared with 2-dam alternative (about 1,954 HH). The difference between the total inundated agricultural lands is 1.11 km2, which means that the loss is 12% less, when compared with the 2-dam alternative. The areas to be inundated in both schemes are shown in Figure 3.1 and Figure 3.2. The cost of compensation and resettlement, including the establishment of a new district center, in the 2-dam alternative is 151 million USD more expensive when compared with the 3-dam alternative. The comparison of resettlement costs shows that losses and resettlement requirements of the 2-dam set-up are more than 100 % higher than the 3-dam alternative. However, in order to make use of the investment cost saving and long-term energy revenues, about 11% of the total investment cost in this comparison is calculated for mitigating and compensating the resettlement consequences of the 2-dam set-up as planned today. Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 2 / 14 Source: Compiled From Satellite Image and Consortium, 2005 Figure 3.1. Area to be Inundated by 2-Dam Alternative Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 3 / 14 Source: Compiled From Satellite Image and Consortium, 2005 Figure 3.2. Area to be Inundated by 3-Dam Alternative Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 4 / 13 The technical investment costs, when all dams are considered to be concrete as assumed in JICA feasibility report of 1986 (Scenario 1), including the cost of dam and appurtenant structures, E&M equipment, relocation roads and transmission lines, but excluding the above resettlement costs for the 2-dam set-up is about 427 million USD less than the 3-dam alternative. When all dams are assumed to be rockfill dams, except Artvin (Scenario 2), the investment costs including the cost of dam and appurtenant structures, E&M equipment, relocation roads and transmission lines, but excluding the above resettlement costs for the 2-dam set-up is about 398 million USD less than the 3-dam alternative. Overall, the costs of dam construction constitute the main difference between the 2dam and 3-dam alternatives 1: • The total investment cost (i.e. inclusive of the resettlement costs) in Scenario 1 (all concrete dams) for the 2-dam alternative is 2,230million USD versus 2,506 million USD for the 3-dam alternative. Thus, the total investment cost of the 2-dam set-up is by 276 million USD less compared to the 3-dam alternative. • The total investment cost in Scenario 2 (rockfill dams) for the 2-dam alternative is 1,976 million USD versus 2,223 million USD for the 3-dam alternative. The total investment cost of the 2-dam alternative is about 247 million USD less than the 3-dam alternative. The annual energy productions of the two schemes (2 and 3 dam alternatives) show a difference of 380 GWh/year in favor of the 2-dam alternative before optimization of the Yusufeli and Artvin Projects, and 511 GWh/yr after optimization. Annual revenue at the rate of 0.06 USD/kWh 2 for the energy production for 2-dam and 3-dam alternatives is estimated as 203.28 and 180.48 million USD, respectively. In other words, the yearly revenue benefit of the 2-dam alternative over the 3-dam alternative is 22.8 million USD or 1,140 million USD accumulated over 50 years. Calculated at a discount rate of 4.5% per annum, the net present value (NPV) of the revenue difference of 1,140 million USD for the un-optimized case is 450.57 million USD. 3 1 Cost figures are relating to comparison un-optimized 2 dam set-up vs. 3-dam set –up. 2 The tariff rate of 6 cents/kWh is used by DSI in their feasibility studies, which is also adopted here. It should also be noted that the tariff rate which has been used in the JICA Feasibility Report was 27 TL/kWh, which when converted into USD is 0.058 USD/kWh, with the exchange rate prevailing in April 1985 (462.5 TL/$). DSI also informed that the present tariff rate would most likely be increased in the following years as per country’s economic situation, particularly by the end of the decade when Turkey is expected to be faced with energy shortages. Notionally, the applicable calculation tariff might be 8 or 9 cents, more close to the customer rate. 3 After optimization of the Yusufeli and Artvin projects (Yusufeli HWL at 710 m.a.s.l) the annual energy production of the 2-dam alternative is 511 GWh/year higher compared to the 3-dam alternative. The energy production benefit of the optimized 2-dam alternative over the 3-dam alternative is 30.66 million USD/year, or 1,533 million USD for 50 years. The net present value (NPV) of the revenue difference of 1,533 million USD is 605.90 million USD. Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 5 / 14 A summary of the cost benefit ratios for all cases considered in the comparison of 2 and 3 dam set-up alternatives is provided in Table 3.1. This table also includes figures for un-optimized and optimized 2 dam-setup, but no optimization is available for the 3 dam-alternative. Table 3.1. Economic Comparison 2 dam vs. 3 dam setup for the Middle Coruh Development Cost - Benefit Ratio 2 dam setup Yusufeli optimized HWL at 710m Scenario: 3 dam setup Yusufeli un-optimized HWL at 700m (no optimization available) All dams concrete 1 : 1.82 1 : 1.80 1 : 1.42 All dams rockfill, except Artvin concrete 1 : 2.11 1 : 2.08 1 : 1.60 Based on the above cost benefit comparison it can be concluded that the decision for the 2-dam alternative taken as a result of the feasibility study of JICA in 1986, which at that time was based mainly on construction costs and storage parameters, also from today’s perspective is economically viable. It can be seen from Table 3.1 that the 2 dam setup as planned today (with Yusufeli as rockfill dam and HWL at 710 meters) significantly creates the highest benefit per cost unit (2.11). It also can be seen that any 2 dam configuration is economically superior to a 3 dam-setup. This is due to the difference in investment costs and more important, also the expected energy benefits in the long run are clearly in favor of implementing the 2-dam set-up, regardless of the tariff rate used. Finally, from present day perspective the 3-dam alternative would not be compatible with the planned development of the upper Coruh Cascade, which has reached substantial progress in preparation for implementation. 3.1.3. Alternative Project Sizes In order to adjust the seasonal and yearly fluctuations in inflow and develop the water resources in the most effective manner, it is necessary to secure a storage capacity making it possible to effectively utilize the inflow to the reservoir, supplementing water not only in dry seasons, but also in dry years, aiming for long term stabilization of generating output. Reservoir high water level and effective storage capacity must further be optimized with regard to the outcomes in the economics of power generation. In contemplating the high water level, comparison studies were made for four cases; 690 m, 700 m, 710 m, 720 m, taking into account such factors as compensation costs, sedimentation, dam height and effective storage capacity. Regarding the effective storage capacity of the Yusufeli Reservoir, the cases were selected in a Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 6 / 14 range of 670×106 m3 to 1,620×106 m3, which correspond to the various high water levels stated above. Details of the evaluations can be found in the EIA report. Comparisons were made for energy costs per one kilowatt-hour, internal rate of return (IRR) and benefit-cost ratios (B/C). Results of the economic evaluation of these alternatives showed that the selection of 710 m for high water level of the reservoir and effective storage capacity of 1,080×106m3 was the most economic, and, thus, considered to be the optimal level. Accordingly, the decision was based on economic grounds (e.g. comparison of benefit-cost ratios) and technical viability, and high water level of 710 m was proposed for the project. When some of the affects of the alternative high water levels are compared, the area to be inundated is 36 km2 at high water level of 720 m, while it decreases to 32.4 km2 at 710 m, 29 km2 at 700 m, and 25.7 km2 at 690 m high water levels (see Table 3.2, Table 3.3 and Figure 3.3). Table 3.2. Land Use in the Inundation Area for Alternative High Water Levels Land Use Type 720 m ASL Agriculture Irrigated Vegetable (ha) Maize (ha) Rice (ha) Clover (ha) Orchard (ha) Rain-fed Wheat (ha) Fallow (ha) Pasture lands (rain-fed) (ha) Settlements Private Property (ha) Public Areas (ha) Roads (ha) Forest areas (ha) Riverine Habitat (ha) River (ha) Other Doc. Name: (Xerophyte shrubs, steppe, rocky areas, bare rock, etc.) (ha) TOTAL YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN High Water Level 710 m ASL 700 m ASL 690 m ASL 116 68 88 63 311 110 65 75 59 285 103 61 61 54 265 95 57 49 52 243 67 85 60 81 54 73 48 67 135 129 122 116 22 12 60 20 12 57 19 12 54 18 12 50 14 80 296 10 76 285 7 68 268 4 59 251 2,174 1,917 1,680 1,452 3,591 3,241 Doc. Code: Revision: Date: 2,901 ENC - YSF - YYP - 01 B July 2006 2,572 Chapter 3 Pg. 7 / 14 Source : Compiled From Topographic Map, ENCON, 2005 Figure 3.3. Area to be Inundated at Water Levels of 720 m, 710 m, 700 m, and 690 m Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 8 / 14 Table 3.3. Comparison of the High Water Levels Studied in the Feasibility Report with respect to Some Associated Impacts 720 m ASL Total area to be inundated (ha) Agricultural lands to be inundated (ha) Total number of buildings to be affected Historical assets to be inundated Number of settlements to be affected Population to be directly affected according to RAP 2005 survey results Settlements to be affected High Water Level 710 m ASL 700 m ASL 690 m ASL 3,591 3,241 2,901 2,572 798 735 671 610 2,704 2,499 2,342 2,108 Tekkale Citadel Tekkale Citadel Tekkale Citadel Tekkale Citadel 19 villages and district center 19 villages and district center 18 villages and district center 15 villages and district center 12,124 12,124 11,711 9,702 Alanbasi, Arpacik, Bahceli, Bostanci, Celtikduzu, Cevreli, Cirali, Darica, Dereici, Irmakyani, Ishan, Kilickaya, Kinalicam, Kupluce, Morkaya, Pamukcular, Sebzeciler, Tekkale, Yenikoy, Yusufeli Town Alanbasi, Arpacik, Bahceli, Bostanci, Celtikduzu, Cevreli, Cirali, Darica, Dereici, Irmakyani, Ishan, Kilickaya, Kinalicam, Kupluce, Morkaya, Pamukcular, Sebzeciler, Tekkale, Yenikoy, Yusufeli Town Arpacik, Bahceli, Bostanci Celtikduzu, Cevreli, Cirali, Darica, Dereici, Irmakyani, Ishan, Kilickaya, Kinalicam, Kupluce, Morkaya, Pamukcular, Sebzeciler, Tekkale, Yenikoy, Yusufeli Town Arpacik, Bahceli, Celtikduzu, Cevreli, Cirali, Darica, Dereici, Irmakyani, Ishan, Kinalicam, Morkaya, Pamukcular, Sebzeciler, Tekkale, Yenikoy, Yusufeli Town As shown in Table 3.3, in all of the alternatives inundation of Yusufeli Town is inevitable. With the high water levels (HWL) of 720 and 710 m the number of affected villages (19 villages) does not change, while at 700 m only one village can be avoided. At HWL of 690 m three villages can be saved from inundation. When HWL are compared with the proposed HWL of 710 m based on the area of private property to be lost in the settlements (e.g. occupied by structures), it can be seen that at 720 m HWL this area is 10% more and for 700 m and 690 m HWL 5% and 10% less, respectively. The number of buildings to be inundated at 700 m and 690 m HWL is 94% and 84% of the ones to be lost at 710 m HWL respectively. On the other hand, this loss is 1.08 times higher at 720 m HWL than the case with HWL of 710 m. Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 9 / 14 Tekkale Citadel, Hamzat 1 and Hamzat 2 chapels are the historical assets to be inundated in all of the studied high water levels. Tekkale Citadel is located between elevations of 670 m and 697 m ASL (Figure 3.4 and Figure 3.5). DSI has already ensured funding for the relocation of this citadel and the two chapels by allocation of a budget of about 240,000 US$ in the 2005 Fiscal Year Expenditures Program on line 5 of the Yusufeli Dam and HEPP Project Allocations Section. It will be relocated before impoundment. The total agricultural lands to be inundated also show similar differences. At 720 m HWL agricultural area to be lost is 9% (63 ha) higher, while at 700 m 9% (64 ha) lower and at 690 m and 17% (125 ha) lower than the loss at 710 m HWL. Forest areas increases with elevation in the area. Thus, forest areas to be lost are 40% (4 ha) higher than the proposed HWL alternative, when HWL is 720m. On the other hand this loss is 30% (3 ha) and 60% (6 ha) less in case of 700m and 690 m high water levels. The loss of riverine habitat, which will be all lost due to the formation of reservoir, changes with the HWL as well. At 720 m HWL this habitat to be inundated is 5% (4 ha) higher than the proposed HWL. At 700 m and 690 m levels this habitat is 11% (8 ha) and 22% (17 ha) lower than the case at 710 m HWL. The estimated area to be flooded at HWL 720 m is 11% (350 ha) higher than the loss at 710 m HWL. At 700 m HWL the total area lost is 11% (340 ha) less than the case at 710 m HWL. Similar comparison shows that the difference between 710 m and 690 m HWL is 21% (669 ha). During the feasibility studies the high water levels of 700 m and 690 m are found to be not economically and technically viable as will have less energy benefits than 710 m HWL due to decrease of the effective storage capacities by about 12 % and 22%, respectively. It can be said that the 700 m HWL will cause comparatively less loss of land and structures than 710 m HWL, but the difference of this loss is not very big for 700 m HWL and 710 m HWL. Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 10 / 14 Source: Compiled From Satellite Image and Field Studies, ENCON, 2005 Figure 3.4. Status of Tekkale Citadel After Impoundment Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 11 / 14 Source: Compiled From Satellite Image and Field Studies, ENCON, 2005 Figure 3.5. Status of Hamzat I and Hamzat II Chapels After Impoundment Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 12 / 14 3.2. Minimization of Resettlement during Project Implementation The Yusufeli Project will be constructed by the Consortium and all means shall be considered to avoid or minimize further needs for resettlement. With this regard the project facilities (construction camp facilities, material sites, borrow and disposal areas, etc.), which would not be required for use in the operation phase, are located such that they would be in the future reservoir area, except some portion of the material borrow sites. Basically one impervious material borrow site extends to outside of the inundation area. A significant part of this material site is in the boundaries of Kinalicam Village, which will be completely relocated (see Chapter 6), and is basically a rocky area. Thus, this material borrow area will not cause any increase in resettlement. Any further needs or changes during construction will be considered with the same approach to avoid further need for expropriation or resettlement. In addition, resettlement activities for the downstream Artvin Project will be coordinated with the resettlement implementation for the Yusufeli Project so to eliminate and minimize any further need for expropriation or resettlement. During project implementation another mean to avoid or reduce the need for resettlement will be proper selection and preparation of the resettlement sites. The resettlement site selection process for Yusufeli District Center is described in Chapter 6. In this process certain criteria had been used to analyze the alternative sites. These criteria included: • • • • • • • • • • • • • • • • Available land. Present population. Distance to main transportation routes and centers. Distance to villages. Existence of productive agriculture lands. Existence of forest areas. Existence of tourism potential. Distance to the future reservoir. Ownership status (treasury lands preferred). Existence of groundwater. Flood risk. Earthquake risk. Geological structure. Altitude from sea level. Existence of social and public facilities. Status of present infrastructure. In the identification of the alternative relocation sites ownership status in the area were given special importance so to minimize (avoid to the extent possible) of any expropriation or resettlement risk for the host population. However, the urban relocation site (new Yusufeli district center) was selected at Yansiticalar and Sakut Creek location (hereafter Yansiticilar) by the Turkish Government in July 2005. At this site most of the land is owned by the State and no one lives in this area. There are only 1.2 ha (0.7 % of the total area of 174.5 ha) agricultural land (clover) in the Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 13 / 14 area. (Appendix B.3). Table 3.4. The dominant land use types at this site are given in Table 3.4. The Land Use in Resettlement Site (Yansiticilar) Land Use Bareland Forest River Bed Agricultural Area (Clover) Shrub Total Area (ha) 124.2 1.6 1.4 1.2 46.1 174.5 Percentage 71.2% 0.9% 0.8% 0.7% 26.4% 100.0 % For minimizing the need for resettlement during implementation, the relocation site for Yusufeli Town, the sites for project facilities and the alignment of relocation roads (mainly Artvin-Bayburt road, which only has a conceptual design) are determined and will be designed to avoid any further need for resettlement. In conclusion not to increase the socio-economic impacts of the project and keeping the project economics in mind, every effort will be put to avoid any further resettlement during implementation. Doc. Name: YUSUFELI DAM AND HEPP PROJECT RESETTLEMENT ACTION PLAN Doc. Code: Revision: Date: ENC - YSF - YYP - 01 B July 2006 Chapter 3 Pg. 14 / 14