Project-Mining-Endako-Expansion-Escape-Tunnel-Fraser
Transcription
Project-Mining-Endako-Expansion-Escape-Tunnel-Fraser
CASE STUDY ENDAKO EXPANSION ESCAPE TUNNEL The Endako Mine is a Molybdenum mine located near Fraser Lake, approximately 160km west of Prince George, British Columbia. Thompson Creek Mining needed to lower the cost of ore production as well as modernize its 45-year-old mill. In 2008, the mine announced its plans for expansion. The processing capacity at the Endako Mine would be increased from 31,000 tons of ore per day to 55,000 tons. 1-877-5-ARMTEC | ARMTEC.COM Owner Thompson Creek Mining Ltd. Installer Sharp Construction Ltd. Design Consultant Hatch Location Fraser Lake, BC ENDAKO EXPANSION ESCAPE TUNNEL The expanded facility was designed to have a lower production cost and the easiest way to accomplish this was by increasing the capacity of the new mill. The increased capacity at the mill resulted in a need for larger ore supplies, higher capacity transportation methods at a lower cost, and an ore stockpile that would be much deeper than typically encountered by Armtec. The challenge that Hatch designers faced was to install a 2,280mm diameter emergency escape tunnel, below the ore stockpile, from the terminating end of a cast-in-place concrete reclaim tunnel to a safe exit point. After a geotechnical investigation was completed, Hatch discovered that the tunnel would be situated well into bedrock and that a large amount of additional drilling and blasting would be required to make the original alignment work. Having reviewed several options, it was decided that the final layout would have the tunnel running alongside the conveyor gallery for 50m, allowing it to daylight outside of the bedrock zone, and then the alignment would deflect 45° and travel another 71m The final alignment provided a major challenge to Armtec with regards to the actual design and supply of the 2,280mm diameter Multi-Plate escape tunnel—the tunnel needed to be designed for an overburden of 48m since it traveled almost directly below the center of the ore stockpile. This depth of overburden exceeded the normal maximum allowed for a structure of this size and resulted in a safety factor that was less than the industry standard. Armtec and Hatch worked together to determine an acceptable factor of OUTSIDE VIEW OF TUNNEL DURING BACKFILLING AND COMPACTION safety for this application. Some of the criteria considered in determining an appropriate safety factor included: • Stockpiles are conical and soil pressures will decrease moving away from the peak. • Average pressure over an area under the stockpile cone is not representative of standard design assumption which is fully flat overburden. • 6m of permanent fill would be carefully placed and compacted to 100% Standard Proctor Density, allowing the use of a soil pressure reduction factor (k) for the permanent cover. • The stockpile material was wellgraded angular and could develop some shear strength even in an uncompacted state. • Extra attention to quality control in assembly and backfilling to reduce risk. ENDAKO EXPANSION ESCAPE TUNNEL Given that Armtec and Hatch were going to deviate from normal design procedures, it was decided that utmost attention to quality control would be required and Hatch requested that Armtec provide on-site support during construction and a final structure certification upon completion. This is normal procedure for large span structures (spans > 6m) and Armtec had a quality management plan in place and ready to go. This started with a preconstruction meeting to define roles and responsibilities, included an experienced Armtec site representative to monitor the contractor throughout the assembly and backfilling process, and was completed with a structure walkthrough by the Armtec Region Engineer for final sign-off. The actual Multi-Plate structure included several unique features. The shell design required that the number of bolts be doubled along the seams of the Multi-Plate underneath the deepest overburden sections. In order to economize the design, the steel thickness was decreased as the tunnel progressed further away from the center of the stockpile. Lastly, Armtec also supplied three prefabricated Multi-Plate elbows in order to match the alignment provided by Hatch. Armtec has a history of striving for excellence and was proud to have partnered with Hatch in providing a solution that was cost effective and required ingenuity. MATERIAL DELIVERED IN COMPACT BUNDLES LABOURER ASSEMBLES MULTI-PLATE CONCRETE COLLAR CAST ESCAPE TUNNEL TO GALLERY CONNECTION, INSIDE VIEW ASSEMBLY COMPLETED PLACING AND COMPACTION OF CRITICAL BACKFILL ZONE READY FOR A DOOR TO BE INSTALLED ESCAPE TUNNEL EXIT RECLAIM PILE ABOVE ESCAPE TUNNEL Armtec is a leading Canadian infrastructure and construction materials company combining creative engineered solutions, relevant advice, dedicated people, proven products and a national presence with a local focus on exceptional customer service. 1-877-5-ARMTEC | ARMTEC.COM Armtec / Case Study / Endako Expansion Escape Tunnel | 2012–03