to view - Paragon Diamonds Limited
Transcription
to view - Paragon Diamonds Limited
Lemphane Kimberlite Project NI 43-101 Independent Technical Report on the Lemphane Kimberlite Project, Lesotho Prepared by MSA Geoservices (Pty) Ltd on behalf of: Meso Diamonds Authors: Frieder Reichhardt Principal Consultant Mike Lynn Senior Project Manager MSc, PhD, Pri.Sci.Nat. BSc (Hons), MSc, GSSA th Date: 28 October 2010 Project: J1952 Primary Author Dr Frieder Reichhardt Lemphane Project th NI 43-101 Report – 28 October 2010 Supervising Principal Dr Ian Haddon Page: i Table of Contents 1 SUMMARY........................................................................................................................ 1 1.1 Property, Location and Ownership ........................................................................... 1 1.2 Exploration Concept ................................................................................................. 1 1.3 Status of Exploration ................................................................................................ 2 1.4 Conclusions and Recommendations ........................................................................ 2 2 INTRODUCTION AND TERMS OF REFERENCE............................................................. 4 2.1 Scope of Work ......................................................................................................... 4 2.2 Currency................................................................................................................... 4 2.3 Principal Sources of Information............................................................................... 4 2.4 Current Personal Inspection ..................................................................................... 5 2.5 Qualifications, Experience and Independence.......................................................... 5 3 RELIANCE ON OTHER EXPERTS ................................................................................... 7 4 PROPERTY DESCRIPTION AND LOCATION.................................................................. 8 4.1 Area and Demarcation of Licence ............................................................................ 8 4.2 Surface Rights.......................................................................................................... 9 4.3 Issuer’s Interest........................................................................................................ 9 4.4 Mining Rights and Royalties in Lesotho.................................................................. 10 4.5 Environmental Liabilities......................................................................................... 10 4.6 Permits................................................................................................................... 11 5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY............................................................................................................ 12 5.1 The Kingdom of Lesotho ........................................................................................ 12 5.2 Access ................................................................................................................... 12 5.3 Ecology and Climate .............................................................................................. 13 5.4 Local Resources and Infrastructure........................................................................ 14 6 HISTORY ........................................................................................................................ 16 7 GEOLOGICAL SETTING ................................................................................................ 18 7.1 Regional Geology................................................................................................... 18 7.2 Local Geology ........................................................................................................ 21 7.3 Kimberlite Geology ................................................................................................. 22 8 DEPOSIT TYPE .............................................................................................................. 26 9 MINERALISATION.......................................................................................................... 28 10 EXPLORATION............................................................................................................... 31 10.1 Exploration approach and methodology ................................................................. 31 10.2 Grab Sampling ....................................................................................................... 31 Lemphane Project th NI 43-101 Report – 28 October 2010 Page: ii 10.2.1 Grab Sampling Results ............................................................................... 33 10.3 Geophysical Surveys.............................................................................................. 34 11 DRILLING ....................................................................................................................... 38 12 SAMPLING METHOD AND APPROACH........................................................................ 39 13 SAMPLE PREPARATION, ANALYSES AND SECURITY............................................... 40 13.1 Kimberlitic Indicator Mineral Sample Analysis ........................................................ 40 13.2 Caustic Fusion Total Liberation Diamond Content Sample Analysis....................... 40 14 DATA VERIFICATION..................................................................................................... 43 14.1 Kimberlitic Indicator Mineral Samples..................................................................... 43 14.2 Caustic Fusion Total Liberation Diamond Content Samples ................................... 43 15 ADJACENT PROPERTIES ............................................................................................. 44 15.1 Letseng Diamonds ................................................................................................. 45 15.2 Mothae Diamond Project ........................................................................................ 47 15.3 Kao Project............................................................................................................. 48 15.4 Liqhobong Project .................................................................................................. 51 16 MINERAL PROCESSING AND METALLURGICAL TESTING........................................ 52 17 MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES................................... 53 18 OTHER RELEVANT INFORMATION .............................................................................. 54 18.1 Diamond Market ..................................................................................................... 54 19 INTERPRETATION AND CONCLUSIONS...................................................................... 57 19.1 Project Risks and Opportunities ............................................................................. 58 20 RECOMMENDATIONS ................................................................................................... 59 20.1 Phase I Evaluation Programme .............................................................................. 59 20.1.1 Phase I Evaluation Sampling Plant ............................................................. 60 20.2 Phase II Evaluation Programme ............................................................................. 62 20.3 Work Programme Budgets..................................................................................... 62 21 REFERENCES ................................................................................................................ 63 22 DATE AND SIGNATURE PAGE...................................................................................... 65 23 CERTIFICATES............................................................................................................... 66 24 GLOSSARY OF TECHNICAL TERMS............................................................................ 68 Lemphane Project th NI 43-101 Report – 28 October 2010 Page: iii List of Tables Table 4-1 Coordinates of PL 005 8 Table 6-1 Available historical artisanal production records from Lemphane 17 Table 7-1 Heavy Mineral Concentrates from the Lemphane Main and Satellite Pipes 24 Table 10-1 List of samples collected over the Lemphane Kimberlite 32 Table 10-2 Total Liberation by Caustic Fusion Sampling Results 33 Table 10-3 Heavy Mineral Stream Sampling Visual Sorting Results 33 Table 12-1 Sampling methodology 39 Table 15-1 Letseng Mine (source Gem Diamonds Annual Report 2009) 45 Table 15-2 Mothae Project 47 Table 15-3 Kao Project 49 Table 15-4 Liqhobong Project (± 6 km E of Lemphane) 51 Table 19-1 Summary of Project Risks 58 Table 20-1 Exploration Budget (Phases I and II) 62 List of Figures Figure 4-1 Locality map of the Lemphane Kimberlite Project 9 Figure 5-1 Access route to the Lemphane Project 13 Figure 5-2 Infrastructure Map of Lesotho 14 Figure 7-1 Tectonic Setting of the Lemphane Kimberlite Project 18 Figure 7-2 Stratigraphy of the Lemphane Project Area (units shown as per Figure 7-3) 19 Figure 7-3 Geological Map of Lesotho and the Northern Lesotho kimberlite Field 20 Figure 7-4 Section through the Karoo Basin from Lesotho to the coast in South Africa 21 Figure 7-5 Remote view of the Lemphane kimberlite pipe looking southeast and showing the approximate pipe outline. 22 Figure 7-6 Top left: Macrocrystic garnet and ilmenite-bearing volcaniclastic(?) kimberlite. Bottom left: Eastern contact looking north with near vertical basalt wall rocks. Top right: Lemphane Project th NI 43-101 Report – 28 October 2010 Page: iv Bedded crater facies (?) kimberlite draped over a basalt xenolith (ZAR 5 coin for scale). Bottom right: Xenolith-rich volcaniclastic(?) kimberlite. 23 Figure 7-7 Geology of the Main Lemphane Kimberlite Pipe 25 Figure 9-1 Artisanal miners at Lemphane 28 Figure 9-2 Top left: Pit sunk by artisanals through slumped (non-kimberlite) material and soil cover to access the eluvial lag on the upper surface of the kimberlite. Depth approximately 6m. Bottom left: Screening and hand concentrating of excavated material. Top right: Screened and hand concentrated material. Bottom right: Hand sorting the concentrate. 29 Figure 10-1 Samples localities, superimposed on the geophysical interpretation of the pipe 32 Figure 10-2 Ground magnetic survey results. Total magnetic field with survey lines (top) and interpretation overlain on an image of the 1st vertical derivative (bottom) 35 Figure 10-3 Comparison of the geophysical interpretation with the geological map of Kresten (1973) 37 Figure 15-1 Northern Lesotho Kimberlite cluster 44 Figure 15-2 Panoramic View of Letseng Mine 46 Figure 15-3 Geological Model of the Mothae Kimberlite. The pipe is approximately 700m long 48 Figure 15-4 Geological Model of the Kao kimberlite main pipe. The pipe is approximately 750m across (NE-SE) 50 Figure 18-1 Rough diamond supply vs demand forecast pre-global financial crisis 54 Figure 18-2 Rough and polished diamond prices 2002 to September 2010 56 Figure 20-1 Evaluation Programme 59 Figure 20-2 Phase I Sampling plant and mass balance 61 Lemphane Project th NI 43-101 Report – 28 October 2010 Page: v 1 SUMMARY 1.1 Property, Location and Ownership Meso Diamonds (Pty) Ltd (‘Meso’) has commissioned The MSA group (‘MSA’) to prepare an Independent Technical Report on the company’s Lemphane Kimberlite Project in the Kingdom of Lesotho (Lesotho). This report on the Lemphane Kimberlite Project is to comply with disclosure and reporting requirements set forth in the TSX - Venture Exchange (TSX – V) Corporate Finance Manual, National Instrument 43-101, Companion Policy 43-101CP, and Form 43-101F1. Meso holds a Prospecting Licence totalling some 6.33 km2 in the Maluti Mountains of Lesotho in southern Africa. The geology of Lesotho is dominated by the basaltic Drakensberg Group lavas (187 Ma to 155 Ma) of the Karoo Supergroup. These rocks comprise an impressive range of high plateau mountains. Underlying the basalts in the western lowlands is a thick sequence of clastic sediments. These rocks do not outcrop in the mountains but may appear as country rock inclusions in the numerous Cretaceousage kimberlite pipes that have been discovered in northern Lesotho. The current erosion level in the Lesotho highlands places the original emplacement surface of these kimberlites a few hundreds of metres above the present surface at Lemphane, the kimberlite that is the subject of this report. Observation of the kimberlite suggests that the current erosion level is near the boundary between the original volcanic crater and the kimberlite diatreme below. The Lemphane kimberlite was discovered in the 1950s and received cursory early economic evaluation by Jack Scott. A grade of between 1-2 cpht was achieved from limited sampling. In the context of the economics of the time these grades militated against further development. No systematic evaluation work has been conducted on the pipe since this time. The kimberlite is approximately oval in shape. It has a surface area of 6.4 ha and occupies a bowl-shaped depression on the flanks of a high ridge at an elevation of approximately 2 600 m. The occurrence of diamonds is demonstrated by the presence of artisanal diggers on surface and has been confirmed by recent total liberation diamond content sampling of the kimberlite by Meso. However, the grade, revenue and diamond character has not yet been determined. 1.2 Exploration Concept The Lemphane exploration model favours a Letseng- or Mothae-like diamond value and grade for the kimberlite. This requires that a high value, low grade diamond deposit will be demonstrated, and the exploration work programme that has been planned reflects this model. The Letseng Diamond Mine is an adjacent property currently in production at a rate of 7.5 Mt per year (2009). Letseng diamond grade is a very low 1.2 ct/100t, but the extraordinary value of USD1 534/ct (2009) complements this to provide an ore value of Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 1 USD28/t. with a reported operating cost of USD12/t. Mothae has a higher grade of 4.7cpht (based on bulk sampling data) and modelled stone values of $549/ct. It is currently undergoing trial mining to determine economic viability. A 53.5 ct white gem quality diamond (Type II) was reported very early during the trial mining programme. The aggressive two year programme at Lemphane has been designed to test this model. 1.3 Status of Exploration The exploration and evaluation programme envisages the establishment of a geological model through the acquisition of new geological and geophysical data. A high-resolution ground magnetic survey has been completed, which delineated the kimberlite pipe boundary and identified possible internal kimberlite facies variations. Total liberation diamond content sampling of surface outcrops and a stream sediment sample has recovered diamonds that will be tested to determine the presence of Type IIa stones and which have potential revenue implications. The positive results from this work have prompted the decision to move on to a Phase I evaluation programme. Surface pitting will provide material to characterise kimberlite facies and determine diamond potential by assessing kimberlitic indicator minerals from mineral chemical analyses. Further total liberation diamond content sampling will be undertaken to investigate diamond content and size frequency per phase. A recovery plant has been commissioned to recover +1.8 to -40 mm diamonds from the excavated material to provide additional size and potential revenue information. If the results of Phase I are favourable, the project will continue with Phase II evaluation work. This would involve ongoing processing of material to obtain a sufficiently large parcel of diamonds to provide a preliminary estimate of diamond content per kimberlite phase. Upon favourable completion of the bulk sampling programme, a 3 000 to 5 000 m core drilling programme would be completed to determine a geological model with volumes, densities and modelled grades of the kimberlite facies so that a mineral resource can be defined. 1.4 Conclusions and Recommendations An aggressive programme to evaluate the diamond potential of the Lemphane kimberlite pipe has commenced. Geophysical and geological field surveys have delineated the surface extent of the kimberlite body (6.4 ha). A conceptual 30 Mt to 200 m depth may be visualised. Geophysical and surface geological mapping has identified lithological variations within the pipe and the first qualitative indication of diamond potential has been interpreted from total liberation diamond content analyses. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 2 The current erosion level exposes possible diatreme and volcaniclastic kimberlite as a major lithologies which would imply that limited erosion of the pipe has occurred. There may be important lithological variations that could have significant economic implications. Certain risks and opportunities have been identified for the project. These include environmental, technical and community risks which Meso are being proactive in managing. The proximity of other projects in the exploration, development, and mining stage may also provide opportunities for certain synergies. The evaluation strategy is based on a Letseng-, and Mothae-like model and a pitting programme is being designed to test this model. Meso is committed to a specific work programme in terms of its Prospecting Licence. The outcome of the full programme will be the mapping of the surface geology of the pipe, and the recovery of sufficient diamonds to be valued. The breakdown of this programme and the costs are shown in Table 20-1 and the total planned cost is GBP 1.27 million over the 24 month period to June 2012. MSA considers that the proposed exploration strategy is consistent with the potential of the project and that the proposed schedules are achievable. Similarly, MSA considers that the committed tenure expenditure is consistent with the proposed programme and will prove adequate to meet these minimum expenditure requirements. The following points suggest that Lemphane must be regarded as a target of some potential: • Availability of grid power • The occurrence of high value diamonds based on historical artisanal mining data • The occurrence of high value Type IIa diamonds on adjacent properties, suggesting that there is potential at Lemphane for similar high value diamonds • So far a total of 19 diamonds have been recovered by Meso, all but one of which are reported as white in colour. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 3 2 INTRODUCTION AND TERMS OF REFERENCE 2.1 Scope of Work The MSA Group (“MSA”) has been commissioned by Meso Diamonds (Pty) Ltd (“Meso”) to provide an independent technical report (“ITR”) on the Lemphane Project focused on the Lemphane kimberlite pipe in Lesotho, in which Meso holds a 100% interest. This ITR has been prepared to comply with disclosure and reporting requirements set forth in the TSX Venture Exchange (TSX-V) Corporate Finance Manual, Canadian National Instrument 43-101 (Standards of Disclosure for Mineral Projects) and related Companion Policy 43-101CP and Form 43-101F1, of January 2005 (the Instrument) and the Mineral Resource and Reserve classifications adopted by CIM Council in August 2000. This report may be included in future equity financing plans by Meso to fund exploration work for the Lemphane Project. 2.2 Currency All monetary figures expressed in this report are in British Pounds (GBP) unless otherwise stated. The Lesotho currency is the Maluti (M) which is on par with, and tied to the South African Rand (ZAR). On the effective date of this report, the exchange rates are GBP 1 = ZAR 10.89 = M 10.89 and USD 1 = ZAR 6.77 = M 6.77. 2.3 Principal Sources of Information MSA has based its review of the Lemphane Project on information provided by Meso, along with technical reports by Government of the Kingdom of Lesotho (“GKL”) agencies and other relevant published data. A listing of the principal sources of information is included in the References section at the end of this ITR. Previous drafts of the report were provided to Meso, along with a written request to identify any material errors or omissions prior to lodgement. The Lemphane Project is considered to represent a “Mineral Project”. Economic viability has not been demonstrated by a Feasibility Study. However, an exploration programme is proposed which will involve pitting, and consequently the Lemphane property is considered to have passed beyond the definition of “Early Stage Exploration property” as that term is defined in the rules and policies governing disclosure. This ITR has been prepared on information available up to and including 28th October 2010. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 4 2.4 Current Personal Inspection A site visit was made on 9th October 2010 to the Lemphane Project in Lesotho by Dr. Frieder Reichhardt MSc, PhD, a ‘qualified person’ as that term is defined in NI43-101, and Mr. Mike Lynn MSc, a geologist with 24 years experience in diamond exploration, accompanied by Mr. Roy Spencer, a representative of Meso. A visit was made to the surface outcrop of the kimberlite and the presence of kimberlite and active artisanal workings was verified. 2.5 Qualifications, Experience and Independence MSA is an exploration and resource consulting and contracting firm which has been providing services and advice to the international mineral industry and financial institutions since 1983. This ITR has been compiled by Dr Frieder Reichhardt and Mr Mike Lynn. Dr Frieder Reichhardt is a professional geologist with 21 years experience, including diamond exploration management for Rio Tinto leading to the discovery and evaluation of the Murowa kimberlite diamond mine in Zimbabwe. He is Principal Consultant diamonds, nickel, PGE, vanadium and chrome with MSA, a member of the Geological Societies of South Africa and Germany and a registered Professional Natural Scientist with the South African Council for Natural Scientific Professions. Dr Reichhardt has the appropriate relevant qualifications, experience, competence and independence to act as a ‘qualified person’ as that term is defined in NI43-101. Dr. Reichhardt’s certificate as a ‘qualified person’ is attached in Section 23 of this ITR. Mike Lynn is a professional geologist with 25 years experience, primarily in the exploration for and evaluation of diamond deposits in Southern, Central, West and East Africa and India. He is a member of the Geological Societies of South Africa and India, and of the Society of Economic Geologists. He is not yet registered as a Professional Natural Scientist with the South African Council for Natural Scientific Professions, and as such is not authorised to act as a “qualified person’ as that term is defined in NI43-101. His contributions to this ITR have been signed off by Dr Frieder Reichhardt. Peer review has been undertaken by Dr Ian Haddon, who is a professional geologist with over 15 years experience, initially with the Council for Geoscience in South Africa and more recently with MSA. Dr Haddon is Manager, Group Operations for MSA, with overall responsibility for exploration, evaluation and environmental contracting and consulting service offerings of the Group. He is a registered professional natural scientist with the South African Council for Natural Scientific Professions. Neither MSA, nor the authors of this ITR, have or have had previously, any material interest in Meso or the mineral properties in which Meso has an interest. Our relationship Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 5 with Meso is solely one of professional association between client and independent consultant. This ITR is prepared in return for professional fees based upon agreed commercial rates and the payment of these fees is in no way contingent on the results of this ITR. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 6 3 RELIANCE ON OTHER EXPERTS MSA assumed that all of the information and technical documents reviewed and listed in the “References” are accurate and complete in all material aspects. While MSA carefully reviewed all of this information, MSA has not concluded any extensive independent investigation to verify their accuracy and completeness. MSA has obtained a copy of Prospecting License No 005, in the name of Meso Diamonds (Pty) Ltd, and signed by Mr Monyane Moleleki the Honourable Minister of Natural Resources in the Kingdom of Lesotho, as evidence that the licence is valid and in good standing. The information and conclusions contained herein are based on information available to MSA at the time of preparation of this report. Meso has warranted that a full disclosure of all material information in its possession or control has been made to MSA. Meso has agreed that neither it nor its associates will make any claim against MSA to recover any loss or damage suffered as a result of MSA’s reliance upon the information provided by Meso for use in preparation of this report. Meso has also indemnified MSA against any claim arising out of the assignment to prepare this report, except where the claim arises as a result of proved wilful misconduct or negligence on the part of MSA. This indemnity is also applied to any consequential extension of work through queries, questions, public hearings or additional work required arising from MSA’s performance of the engagement. Meso has reviewed draft copies of this report for factual errors. Any changes made as a result of these reviews did not involve any alteration to the conclusions made. Hence the statements and opinions expressed in this document are given in good faith and in the belief that such statements and opinions are not false and misleading at the date of this report. MSA reserves the right to, but will not be obligated to, revise this report and conclusions thereto if additional information becomes known to MSA subsequent to the date of this report. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 7 4 PROPERTY DESCRIPTION AND LOCATION The property is PL 005 issued in terms of Section 22 of the Mines and Minerals Act No 4 of 2005, and covering 6.33 km2 in the Butha-Buthe District of Lesotho. The licence is in northern Lesotho, 29 km west of the Letseng diamond mine, centred on approximately 28° 35' 00" E / 28° 56' 35" S. PL 005 is held by Meso, a company incorporated in Lesotho. It was issued on 1st June 2010. It is valid for 2 years and gives the right to undertake diamond exploration activities in terms of the act. 4.1 Area and Demarcation of Licence The corner points of PL 005 are given in Table 4-1. Table 4-1 Coordinates of PL 005 Datum WGS84, Area = 6.33 km2 Point Latitude (S) A B C D E F 28° 55' 54.8" 28° 55' 54.8" 28° 57' 24.5" 28° 57' 24.1" 28° 56' 53.9" 28° 56' 53.9" Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Longitude (E) 28° 33' 57.6" 28° 35' 32.6" 28° 35' 32.6" 28° 34' 27.5" 28° 34' 27.5" 28° 33' 57.6" Page: 8 Figure 4-1 Locality map of the Lemphane Kimberlite Project Background imagery from Google Earth 4.2 Surface Rights The surface area of PL 005 is communal agricultural land. A ‘kraal’ on the kimberlite is used by the local community for summer grazing and is required to be removed by the community on demand by Meso. 4.3 Issuer’s Interest Meso is a Private Limited Company incorporated in Lesotho in terms of the Companies Act (Act No. 25 of 1967). The Lemphane Project is 100% owned and funded by Meso. Should the project develop to the mining stage, the Government has the right to take a share of the project. The Government’s share, and proportion of any free carry is negotiable. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 9 4.4 Mining Rights and Royalties in Lesotho According to the Mines and Minerals Act No 4 of 2005, all rights to minerals are vested in the Basotho Nation. Mineral rights may only be granted to a Lesotho-registered company (or Lesotho nationals). Exploration work is performed under a Prospecting Licence (PL) with a maximum area of 2 25 km , and which is valid for two years and renewable for one year. The renewal may be extended at the discretion of the Minister if proper evaluation work is being undertaken. There is no automatic right to convert a PL to a Mining Lease (ML), although the record indicates that the Ministry of Mines has not unreasonably withheld this transfer in the past. A ML is issued for a maximum of 10 years, and is renewable for a further 10 years. The GKL retains the right to negotiate with a company regarding its shareholding, and all technical, commercial and financial aspects of a diamond mining operation, before issuing a ML. A royalty is payable to the government of 10% for precious stones and 3% for other minerals. This percentage is based upon the gross sale value receivable at the mine gate, and in the case of diamond projects, is negotiable. 4.5 Environmental Liabilities MSA is not aware of any current environmental liabilities on the Lemphane Project. The holders of mineral rights are required to compensate surface owners for the use and/or damage to their properties as a result of the mining activities. With respect to environmental issues, the Act stipulates that the holder of a mineral right shall: 1. Preserve the natural environment; 2. Minimise and control waste or undue loss of or damage to natural and biological resources; 3. Prevent and where unavoidable, promptly treat pollution and contamination of the environment; 4. Restore the land substantially to the condition in which it was prior to the commencement of operations; and, 5. Make ongoing financial provision for compliance with his (environmental) obligations. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 10 The Mining Department requires that an Environmental Impact Assessment (‘EIA’) and an Environmental Management Programme Report (‘EMPR’) be submitted prior to commencement of mining operations. Since artisanal mining activity has occurred on the Lemphane kimberlite pipe, there is a risk that Meso could inherit liability for the environmental damage caused. Meso has mitigated this risk by recording the pre-existing activity prior to commencing its own exploration activities. A thorough record of pre-existing infrastructure and mining activities has been prepared by Amathemba Environmental Management Consulting cc, a Cape Town-based company. The Khoabeng stream which drains the kimberlite, flows into the Malibomatsu River, which in turn flows into the Khatse Dam some 17 km to the south. This dam provides water for hydro-electric power and export to South Africa, and a management plan will be required to mitigate the risk of slimes from the project entering the dam. 4.6 Permits Other than the PL and work permits for foreign nationals, limited permitting is required to undertake exploration activities. Removal of samples for analysis requires written permission from the local Commissioner of Mine and Geology. A water use permit is required from the Department of Water Affairs to use surface water for domestic and process requirements if a camp is erected. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 11 5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY 5.1 The Kingdom of Lesotho Previously known as Basutoland, the Kingdom of Lesotho is a small, mountainous landlocked country entirely surrounded by the Republic of South Africa. It has an area of 30 355km2, and a population of 1.9 million (July 2010 estimate by Central Intelligence Agency World Fact Book) with a life expectancy estimate of 50 years and a median age of 22 years. The literacy rate is the second highest in Africa, with 85% of the population over 15 years able to read and write. Lesotho gained independence from Britain in 1966. Lesotho is a parliamentary constitutional monarchy. King Letsie III has no executive or legislative power but is considered to be a "living symbol of national unity". According to the constitution, the Head of Government is the leader of the majority party in the assembly. Following a period of political unrest between 1990 and 1998, the political and social environment is stable. In May 2002, the ruling Lesotho Congress for Democracy (''LCOD'') won parliamentary elections which were endorsed by international observers, and Rt. Hon. Prime Minister Pakalitha Mosisili was sworn-in for a second term. Lesotho is a low-income country with an economy linked to South Africa. In the recent past, Basotho men worked in the South African mining industry, but this source of employment has dwindled, and the consequent loss of remittances has impacted the economy. Lesotho’s main natural resource is water. Completion of a major hydropower facility, the Lesotho Highlands Water Project (LHWP) in January 1998 now permits the sale of water to South Africa, generating significant revenue for the country. Lesotho is self-sufficient in electrical power for two-thirds of the year, but the country imports electricity from South Africa during the winter. 5.2 Access The property is accessed from Maseru via a tarred road to Leribe (+/- 93 km) and another tarred road to Ha Lejone (+/- 59 km), and then a gravel road to the village of Lemphane (+/- 30 km). From the village, there is a track to the pipe (2.1 km). The track is driveable part of the way, and there is a plan to upgrade the track to provide access for pit sampling. The international airport at Maseru is linked to the major hub of Oliver Tambo Airport in Johannebsurg. The drive from Johannesburg to Maseru takes approximately 6 hours. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 12 Figure 5-1 Access route to the Lemphane Project Elevation data from ASTER (30m resolution) 5.3 Ecology and Climate The landscape of Lesotho is divided into two major regions; the lowlands, which make up less than 20% of the country, and occupy a narrow strip along the western edge of the country at an elevation below approximately 1 800 m, and the highlands, which rise to their highest point at Thabana Ntlenyana (3 476 m). The Lemphane Property is located at an elevation of approximately 2,600 m in the northern highlands of Lesotho (Figure 4-1). The terrain is mountainous with deeply incised valleys. The vegetation is classified as Lesotho Highland Basalt Grassland, consisting of grasses with minor shrubs (especially Passerina Montana and Chrysocoma ciliate) and localised marshes known as Lesotho Mires, which act as water reservoirs. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 13 These vegetation types are classified as ‘Least Threatened’ but are ‘Poorly Protected’ (Mucina and Rutherford, 2006). There is no crop farming at this altitude. The climate is temperate, moderated by the altitude. There is a cool, dry, winter from March to October, and a milder and wetter summer during the remaining months. Temperatures as low as minus 15°C may be experience d in the winter nights and daytime temperatures in the summer are as high as 30°C. The climate would not normally impede mining operations, which can continue year round. 5.4 Local Resources and Infrastructure The road infrastructure in the area is limited. Good tar roads traverse the highlands to the north and south of the project area, but access between these is by moderately maintained gravel roads. Figure 5-2 Infrastructure Map of Lesotho Elevation data from ASTER (30m resolution) Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 14 The electricity power grid is connected to the Eskom (the South African national electricity supply company) power grid in South Africa. Major power lines pass approximately 20 km to the north and southwest of Lemphane (Figure 5-2). The area has a history of diamond mining dating to the late 1950s when a number of kimberlite discoveries were declared government diggings. Currently one diamond mine is operational (Letseng), another two are under development with trial mining in progress (Mothae and Kao), and a fourth is the subject of an ongoing feasibility study (Liqhobong). The Letseng Mine lies 29 km from Lemphane and obtains process water from an existing dam located on the mine’s property. All rain water run-off generated on site, is diverted into this dam, in addition to return water from the slimes dam and from open pit dewatering. The dam also supplies the potable water treatment plant with raw water. Electricity is supplied from the Lesotho national grid. A high voltage line was constructed specifically to supply the mine. Back-up electricity is ensured through a series of diesel generators. The majority of mine employees at Letseng are resident on site during their shift cycle in a series of accommodation units. Site services (cleaning, catering, etc.) are outsourced. Due to the relative remoteness of the operation, an onsite sewage treatment plant, domestic and industrial waste separation facility and incinerator are utilized to manage waste. At the Liqhobong Project, some 6 km east of Lemphane, power is provided on site by large diesel generators. MSA understands that preliminary approval and funding has recently been reported to build a 28 km-long connection to the national grid along the valley of the Malibomatso River to provide power to the Liqhobong and Lemphane Projects. The connection would be built as a development project and would take two years to complete. Construction has not yet started. Water for domestic and process use is currently obtained from surface streams. No study has yet been undertaken on supply of power or water for the Lemphane Project. However, it is likely that the project would utilize diesel generators and surface stream water during the exploration phase. The PL permits the erection of a camp on site. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 15 6 HISTORY Kimberlites were first recorded in the area by Stockley (1947). Geological mapping by Leeds University researchers and a Lesotho-wide exploration programme by Basutoland Diamonds Limited (BDL) added to the number of known kimberlites between 1957 and 1963. These programmes brought the number of known kimberlite pipes and dykes in the country to 135, the most important of which were the Letseng-la-Terai (“Letseng”) kimberlites (the Main and Satellite pipes), Kao, Liqhobong, and Lemphane. These pipes were declared government diggings, and by 1967 there were up to 6 000 local diggers on site at Letseng and the Letseng pipes are estimated to have produced 63 000 carats between 1959 and 1967, including the 601-carat Lesotho Brown diamond. Rio Tinto Exploration (Pty) Ltd was awarded the exploration license for the Letseng pipes in 1968 and was tasked with undertaking a feasibility study to mine. Although grades of the Letseng pipes were found to be low (less than 4 ct/100t), many large high-quality stones were recovered. Rio Tinto abandoned the deposit in 1972, because of the low grade and associated economics at the time which militated against further development. Lesotho's government then asked De Beers to re-evaluate the Letseng kimberlites, which lead to the opening of the Letseng Mine in November 1977. The mine was closed after 5 years in 1982 having produced 272 840 carats, from 9.4 Mt of kimberlite (mostly from the Main pipe) at an average grade of 2.9 ct/100t. Lesotho's government investigated ways to reopen the Letseng Mine in the 1990s. Letseng Diamonds (Pty) Ltd (a Lesotho-registered company) was formed in 1995 as a partnership between industry investors (76 percent) and the Lesotho Government (24 percent). The mining rights for the Letseng Mine were acquired by Letseng Diamonds (Pty) Ltd in 1999. The reconstruction of the mine's infrastructure commenced in 2003, and production at two alluvial deposits associated with the Main and Satellite Pipes started in November 2003. Production at the Satellite Pipe resumed in March 2004. The Lemphane kimberlite was discovered as part of the BDL exploration programme and was evaluated in the late 1950s and early 1960s. Details of this work are unavailable, but the pipe was abandoned because the economics of the time militated against further development. Nevertheless, artisanal workings have continued intermittently on the kimberlite. Records for artisanal production are incomplete, but some figures from 1978 to 1980 have been obtained from the Lesotho Department of Mines and are reported in Table 6-1. This work was supported by the Canadian International Development Agency (CIDA). Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 16 Table 6-1 Available historical artisanal production records from Lemphane (Source: GKL Ministry of Mines artisanal production records) Period Tonnes Carats Processed Produced Average Grade Total Stones Cts/stone Revenue (Maluti/ct) 1978 (3 months) 719 22 3.1 cpht 85 0.26 M 201/ct 1979 (12 months) 7 590 166 2.2 cpht 581 0.29 M 188/ct June 1980 13 425 256 1.9 cpht 863 0.30 M 260/ct Totals 21 734 444 2.0 1 529 0.29 M 230/ct Available artisanal production figures from Lemphane between 1978 and 1980 show production of 444 carats at an average grade of 2.0 cpht, an average revenue of M 230/ct (USD 277/ct* in dollars of the day), and an average stone size of 0.29 ct per stone. During the same period, production from Liqhobong (combined figures from the satellite and main pipes) totaled 8 216 carats with an average revenue of M 147/ct (USD 177/ct* in dollars of the day) and approximately the same average stone size of 0.29 ct per stone. Details of the recovery methods are unknown. Nevertheless, the implication is that the diamond revenue from Lemphane may be significantly higher than at Liqhobong. This data, along with anecdotal information, is the basis for the hypothesis that Lemphane may be a low grade, high revenue deposit. *The Rand Monetary Area (RMA) existed at this time and the Maluti was tied at parity to the South African Rand. The average Maluti/Rand to the USD exchange rate for the years 1978 to 1980 (inclusive) was 0.8303 and this figure is the basis for the calculation of the revenue per carat in dollars of the day. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 17 7 GEOLOGICAL SETTING 7.1 Regional Geology Lesotho is situated on the southern edge of the Kaapvaal Craton, which extends through central, eastern and north-eastern South Africa, into southern Zimbabwe and southeastern Botswana, and incorporates most of Swaziland (Figure 7-1). The Kaapvaal Craton is host to numerous important diamondiferous kimberlites of various ages, including the Mesoproterozoic Premier kimberlite (Cullinan Mine), the Cambrian Venetia kimberlites, the Middle Triassic Jwaneng kimberlites, and the Cretaceous Kimberley, and Finsch kimberlites. Figure 7-1 Tectonic Setting of the Lemphane Kimberlite Project (Domain nomenclature after Eglington et al. 2009) The geological history and structure of the Kaapvaal Craton have been discussed by various authors (see for example de Wit et al., 1992, James et al., 2001, Begg et al., Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 18 2009, Eglington et al., 2009, Jones et al, 2009). The Northern Lesotho Kimberlite Cluster lies on the Swaziland Terrane of Eglington et al. (op. cit.). The basement rocks are not exposed in Lesotho, but further to the southeast in the Kwazulu Natal Province of South Africa, the basement sequence includes the Archaean Natal granite greenstone terrane (3.4 to 3.2 Ga). De Wit et al. (1992) suggest that the Swaziland Terrane and Witwatersrand Terrane to the north had combined and stabilised by about 3.2 Ga during the formation of the Kaapvaal Craton. The diamondiferous Northern Lesotho Kimberlite Field therefore conforms to ‘Clifford’s Rule’ which states that diamondiferous kimberlites tend to occur in geologic regions that have been tectonically stable since the Archaean (Clifford, 1966). Figure 7-2 Stratigraphy of the Lemphane Project Area (units shown as per Figure 7-3) Supergroup Cretaceous Period / Eon Intrusives Group Subgroup Formation Lesotho Kimberlites Lithology Kimberlite Permian Karoo Dolerite Suite Karoo Supergroup Triassic Jurassic ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Unconformity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Drakensberg Gp Flood basalts and intrusive dolerite dykes and sills Clarens Fm Elliot Fm Molteno Fm Stormberg Gp Beaufort Gp Ecca Gp Fine grained aeolian sandstone Limestone, mudstone and sandstone Sandstone Tarkastad Sbgp Sandstone, red mudstone Adelaide Sbgp Mudstone, shale, sandstone Madzaringwe Fm Pietermaritzburg Fm Sandstone, siltsone, shale Shale, siltsone Dwyka Diamictite, shale Gp ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Unconformity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Archaean Gneiss, amphibolite The Archaean basement in Lesotho is entirely covered by the flat-lying Palaeozoic to Mesozoic Karoo Supergroup which reaches a thickness of approximately 4 km in Lesotho (Figures 7-2, 7-3 and 7-4). Its strata, mostly shales and sandstones, record an almost continuous sequence of marine glacial to terrestrial deposition from the Late Carboniferous to the Early Jurassic, a period of about 100 Ma. These accumulated in the main Karoo Basin, which has been interpreted as a retroarc foreland basin formed by the subduction and orogenesis along the southern boundary of Gondwana (Catuneanu et al, 2005). Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 19 Figure 7-3 Geological Map of Lesotho and the Northern Lesotho kimberlite Field The basalts of the Drakensberg Group were erupted within a very short period at about 180 Ma (Jurassic Period) and consist of a monotonous pile of compound basalt lava flows Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 20 which lacks significant palaeosols or persistent sedimentary intercalations. Geochemical analysis by Marsh et al. (1997) demonstrates that the stratigraphic sequence in Lesotho closely resembles that in a thinner sequence of basalts some 400 km to the north. This in turn indicates the widespread nature of the Karoo continental flood basalt event. Figure 7-4 Section through the Karoo Basin from Lesotho to the coast in South Africa (modified after Brown et al. 2002) Kimberlite emplacement during the Cretaceous Period was widespread throughout southern Africa, and was probably associated with tectonic triggers during the break-up of Gondwana (Bailey, 1992). 7.2 Local Geology Although the entire Karoo sequence has been intersected in boreholes, no stratigraphy beneath the Beaufort Group outcrops in Lesotho. The geology of northern Lesotho comprises sediments of the upper Karoo Supergroup, (Molteno, Elliot and Clarens Formations) in the western lowlands, overlain by the basaltic lavas of the Drakensberg Group which form the Lesotho Highlands. The sediments and, to a lesser extent, the lavas are extensively intruded by dykes and sills of dolerite which decrease in frequency upwards in the succession. Minor normal faulting is present in these sediments and lavas. The base of the lava sequence lies at an elevation of approximately 1,600 m. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 21 The youngest structural trend in Lesotho is dominantly WNW and is manifested by regional faults, zones of fracturing and brecciation, and jointing. Kimberlite dykes and pipes are localized in portions of these regional structures (Figure 7-3). 7.3 Kimberlite Geology The geology of the Lemphane kimberlites is described by Kresten (1973; Figure 7-5). The main Lemphane pipe is oval in shape and covers an area of approximately 6 ha. The contacts between the kimberlite and basalt country rocks appear sharp and nearly vertical. A number of different kimberlite phases are observed in outcrop, and at least five separate intrusions are inferred from a recent ground magnetic survey (Section 10.2). The outcropping kimberlite is dominantly greenish or light grey, with abundant olivine macrocrysts in a fine serpentinized matrix. The different phases observed vary primarily in the abundance and size of xenoliths and olivine macrocrysts, as well as the abundance of ilmenite and garnet. Some poorly defined bedding is apparent in some areas, which dips towards the centre of the pipe. This implies that some crater facies material is preserved at Lemphane, and is consistent with a model of limited erosion of the pipe having occurred. Figure 7-5 Remote view of the Lemphane kimberlite pipe looking southeast and showing the approximate pipe outline. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 22 Xenoliths of basalt are common and range up to over one metre across in outcrop. Xenoliths of basement rock (predominantly biotite gneiss) also occur. Kresten (op. cit.) reports two mantle-derived xenoliths; one lherzolite and one harzburgite. Kresten describes a small ‘satellite’ pipe which occurs on the western margin of the main pipe, measuring just 12m x 17 m in outcrop. This is connected to the main pipe and is better described as an apophysis that comprises a different kimberlite phase. The contact is not exposed, but the kimberlite is greyish green and contains a greater abundance of ilmenite and garnet xenocrysts than the main pipe. Figure 7-6 Top left: Macrocrystic garnet and ilmenite-bearing volcaniclastic(?) kimberlite. Bottom left: Eastern contact looking north with near vertical basalt wall rocks. Top right: Bedded crater facies (?) kimberlite draped over a basalt xenolith (ZAR 5 coin for scale). Bottom right: Xenolith-rich volcaniclastic(?) kimberlite. At least one kimberlite dyke occurs which trends WNW. It appears to pre-date the main pipe, and may be connected to the apophysis. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 23 Heavy mineral abundances were estimated from the main pipe and apophysis (‘satellite’) and are reported by Kresten (op. cit.; Table 7-1). Table 7-1 Heavy Mineral Concentrates from the Lemphane Main and Satellite Pipes (source: Kresten, 1973) LOCATION Main Pipe, northern contact Main Pipe, southern contact Main Pipe, central part Apophysis (‘Satellite’) Pipe, centre % ilmenite % garnet %olivine/pyroxene 11.6 14.5 7.4 74.6 3.8 2.9 0.3 13.1 84.6 82.6 92.3 12.3 Overburden varies from zero to 10m thick and is thickest at the centre of the main pipe. The following superficial sequence is observed: - Organic layer - Grey gravel - Grey soil - Brown oxidised gravel - Eluvial kimberlite lag enriched in ilmenite - Yellow oxidised kimberlite The kimberlite lag is enriched in ilmenite and is likely to carry an elevated diamond grade. It is being targeted by artisanal diggers. The steep slope across the surface of the kimberlite has enabled slumping of kimberlite to occur from southeast to northwest through secondary weathering and erosion processes. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Page: 24 Figure 7-7 Geology of the Main Lemphane Kimberlite Pipe (after Kresten, 1973) Lemphane Project th NI 43-101 Technical Report – 28 October 2010 25 8 DEPOSIT TYPE The Lemphane kimberlite intrusion is a kimberlite diatreme, or pipe, which was the feeder to a now eroded kimberlite volcano. Kimberlite is by far the most important primary source of diamond. Diamonds are a high pressure (~50 Kbar) and temperature (~1,200°C) variety of carbon, which form at depths of at least 150 km below the earth’s surface. Kimberlite is a volcanic rock, which originates at great depth, between 150 km and 300 km, in the asthenosphere. Rapidly ascending kimberlite magma entrains diamonds, together with other rocks and minerals present at those depths. Kimberlite is named after the diamond-mining centre of Kimberley, South Africa, where the diamond bearing rock type was first discovered. Prior to the Kimberley discoveries, all world diamond production had been from alluvial deposits and the primary source was unknown. Only a small minority of kimberlite bodies contain diamonds in sufficient concentrations to be considered as diamond ore. The great majority of kimberlites have zero or very low diamond contents. It has been found that those which do have elevated diamond tenors usually occur in areas of old and stable crust, which are typically found in the cratonic cores of continental blocks. Kimberlites within younger orogenic belts usually contain few or no diamonds. Cratonic areas are characterised by thick crust and low geothermal gradients. The transportation of entrained diamonds to the surface must be rapid in order to prevent their resorption or retrogression to graphite as pressure is released. Kimberlite magma is very rich in volatiles, notably CO2, which makes this rapid ascent possible, and explosive breakthrough to the surface may start at depths of 2 to 3 km, giving rise to the characteristic carrot shaped pipe, or diatreme. A number of challenges are inherent in diamond sampling and evaluation, and any exploration programme should be designed to mitigate these challenges: • Even in economically viable deposits, diamonds are present in extremely small quantities, and their distribution within the host tends to be erratic (e.g. a grade of 10 carats per hundred tonnes (cpht) is equivalent to 0.02 parts per million) • The size and value of stones is erratic and it is possible that the bulk of the value of a parcel of diamonds is attributable to small number of individual stones or even a single stone Lemphane Project th NI 43-101 Technical Report – 28 October 2010 26 • Drill sampling of hard kimberlite tends to break larger diamonds, and underrecover smaller diamonds due to a reduction in liberation. It is not uncommon for there to be multiple intrusions within a single kimberlite pipe, so that the later intrude the earlier ones. The tenor and quality of diamonds may vary between different facies and lithologies, therefore a good geological model and lithologically controlled sampling are important in evaluation. To eliminate the evaluation challenges caused by these factors, very large samples are required. Grade may be determined by relatively small samples and analysis for diamonds using caustic fusion total liberation diamond content samples. This is because the diamond population in a kimberlite follows a log normal size distribution. The size frequency of the commercial sized diamond population can therefore be accurately estimated from the size frequency of the ‘microdiamond’ population. However, the microdiamond population does not provide adequate revenue information. In order to determine the typical revenues to be expected for a diamond deposit, the following is required: • Grade (cpht) • Diamond size frequency distribution • Diamond revenue (USD/ct), measured by the valuation or sale of a complete parcel of diamonds at current prices. In order to measure a mineral resource with respect to diamonds, the following parameters must be defined: • Tonnage, which is the calculated volume of the ore deposit multiplied by its density (specific gravity) • Grade • Average diamond value Lemphane Project th NI 43-101 Technical Report – 28 October 2010 27 9 MINERALISATION The property includes the Lemphane kimberlite pipe and associated dykes and blows. Diamonds may occur as rare xenocrysts which have been entrained by a kimberlite magma during its ascent to surface from depths ranging between approximately 150 and 180 km. Factors influencing the grade of mineralization include the quantity of diamonds originally entrained by rising magma, the rate of ascent to surface and possible resorption of some diamond into graphite, and dilution of the primary kimberlite magma by barren country rock material. The presence of diamond at Lemphane has been empirically determined by Meaton (1966), although this work was not NI 43-101 compliant. The presence of artisanal diggings and historical artisanal production figures confirm that diamonds do occur in the kimberlite. Sampling work undertaken by Meso, and reported in Section 10.2.1 further confirms the presence of diamonds. However, the grade of the Lemphane kimberlite has not yet been determined by a NI 43-101 compliant sampling programme. Kresten (1973) reported that approximately 250 artisanal diggers were active on the pipe in the early 1970s. Figure 9-1 Artisanal miners at Lemphane Today, artisanal miners are digging holes up to 9 m deep through the slumped material and primary soil profile to reach the top surface of the kimberlite. The eluvial lag deposit present above the primary weathered kimberlite is brought to surface, screened, and then concentrated and sorted by hand. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 28 Kresten (1973) describes diamonds from Lemphane as, “…. pale yellow with subordinate colourless, grey and brown colours. About 80% are broken and formless. The most common crystal form is dodecahedron with subordinate trisoctahedron and octahedron; combinations as well as twinned crystals also occur.” She further reports that stones of over 4 carats occur. Unconfirmed reports from the diggers themselves indicate that the majority of stones recovered are white, but MSA has not verified this claim. No diamonds were observed during the site visit made on 9th October 2010. Mr A. Sekhele, a Lesotho Government diamond valuer, present at Lemphane during the early 80’s suggests anecdotally that the largest stone to be recovered at Lemphane at that time was 32 carats. He has also commented that he has seen a 3.7 ct blue stone at Lemphane and other fancy colours including pink, yellow and black. Again, MSA cannot verify this claim. Figure 9-2 Top left: Pit sunk by artisanals through slumped (non-kimberlite) material and soil cover to access the eluvial lag on the upper surface of the kimberlite. Depth approximately 6m. Bottom left: Screening and hand concentrating of excavated material. Top right: Screened and hand concentrated material. Bottom right: Hand sorting the concentrate. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 29 Determination of the presence or absence of Type II diamonds at Lemphane may be important in determining the deposit’s economic potential. Moore (2009) has reported the characteristics of Type II diamonds. They were originally distinguished on the basis of their infra red (IR) spectra, with Type IIa stones characterised by their very low (<20 ppm) nitrogen contents. The Type IIa stones often have top quality white colours (D-G), a consequence of their low nitrogen contents. They include the largest gem diamond ever found, the 3 106 ct Cullinan, recovered from the Premier Mine, South Africa, as well as gems like the legendary Koh-i-noor and Hope, from India. The presence of an unusually high proportion of Type II stones at Letseng results in this locality having the world’s highest average diamond value (USD 1 753/ct in 2009) for a kimberlite, and being the lowest grade (< 2ct/100t) pipe ever mined economically. Type IIa diamonds from Letseng have the following general characteristics: • Morphology is typically irregular and stones are often elongated and distorted. They are described as being highly resorbed. Very rarely, primary crystal faces are preserved. • They can be almost any colour except yellow (reflecting the absence of nitrogen). Many are of top white colour (D,E,F or G), but they also occur in shades of brown. At Letseng, most pink and brownish-pink stones are Type IIa varieties. • Silicate, oxide and sulphide inclusions are either very rare or absent in Letseng Type IIa stones, and where “flaws” are observed, these are invariably graphite. • Unlike Type I diamonds, which cleave in steps, the Type II stones often show excellent planar cleavage – a characteristic linked to their low nitrogen contents. • With very rare exceptions, the Letseng Type IIa stones do not fluoresce. • The proportion of Type IIa stones at Letseng increases with diamond size, constituting 13% of the population in the 0.05 to 0.15ct range, but 38% (in carat terms) of the +10.8 ct stones in the Main Pipe and 69% of the stones of this size category in the Satellite Pipe. They thus show a bias towards large stone size. The paragenesis of Type IIa diamonds does not appear to be linked to either the peridotitic or eclogitic suites. The presence or absence of peridotitic pyrope or eclogitic garnets does not therefore provide a direct indication of the presence or absence of Type II diamonds. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 30 10 EXPLORATION Kresten (1973) reported that the evaluation work undertaken by Meaton in the 1960s indicated primary grades of 1 to 2 cpht for the Lemphane kimberlite, with some local eluvial and alluvial enrichment also reported. However, this work was not NI 43-101 compliant. The reports of Meaton have not yet been obtained, and will be reported in the future if they can be found. The current exploration work being undertaken by Meso, represents the first systematic exploration of the Lemphane kimberlite pipe since the work of Meaton. 10.1 Exploration approach and methodology The exploration approach followed by Meso is to first demonstrate the potential of the kimberlite by collecting samples in the vicinity of the pipe and processing for indicator minerals and diamonds, and undertaking a geophysical survey. Favourable results from this work will lead to a phased evaluation programme. Results from some initial grab samples are reported below. The objective of the sampling work is to prove the presence of diamonds, and to obtain indicator mineral chemistry, to demonstrate that the kimberlite has entrained material from diamondiferous mantle and estimate the proportion of this material. The objective of the geophysical survey is to measure the areal extent of the pipe and determine the presence of separate internal geological phases, which are likely to carry different diamond tenor. The identification of different kimberlite phases will inform future sampling work, such that separate geological phases will be sampled separately. 10.2 Grab Sampling To date, Meso have collected a total of 14 samples from PL005. These samples are summarised in Table 10-1 and shown in Figure 10-1. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 31 Table 10-1 List of samples collected over the Lemphane Kimberlite Sample ID Lat (Y) Date Sample Type LEM 1A&B -28.942444 Long (X) 28.583556 12-Aug-10 Stream sediment LEM 1 -28.942528 28.583778 06-Jul-10 Weathered kimberlite LEM 2 -28.943278 28.583389 06-Jul-10 Weathered kimberlite LEM 3 -28.943528 28.583694 06-Jul-10 Weathered kimberlite LEM 4 -28.943333 28.583333 06-Jul-10 Weathered kimberlite LEM 8 -28.942917 28.584528 12-Aug-10 Weathered kimberlite LEM 9 -28.943278 28.585111 12-Aug-10 Weathered kimberlite LEM 10 -28.943694 28.585139 12-Aug-10 Weathered kimberlite LEM 11 -28.944111 28.584056 12-Aug-10 Weathered kimberlite LEM 12 -28.944417 28.584194 12-Aug-10 Weathered kimberlite LEM 13 -28.944389 28.584556 12-Aug-10 Weathered kimberlite LEM 14 -28.944111 28.585694 12-Aug-10 Weathered kimberlite LEM 15 -28.944111 28.585694 12-Aug-10 Weathered kimberlite LEM A-L -28.941028 28.582222 06-Jul-10 Stream sediment Figure 10-1 Samples localities, superimposed on the geophysical interpretation of the pipe Lemphane Project th NI 43-101 Technical Report – 28 October 2010 32 10.2.1 Grab Sampling Results Results from all samples have been received and are reported below: +1.18 mm +0.850 mm +0. 600 mm +0.425 mm +0.300 mm +0.212 mm Sample Type LEM 1-4 Kimberlite 60.10 1 LEM 8 Kimberlite 6.92 0 LEM 9 Kimberlite 9.61 3 LEM 10 Kimberlite 8.08 0 LEM 11 Kimberlite 12.56 0 LEM 12 Kimberlite 11.86 1 LEM 13 Kimberlite 8.68 0 LEM 14 Kimberlite 14.72 1 LEM 15 Kimberlite 4.80 0 137.33 6 4 0 1 0 0 1 0 0 230.3 13 3 2 2 2 1 1 1 1 230.3 13 3 2 2 2 1 1 1 1 LEM A-L Stream TOTAL No Stones +0.150 mm Sample number TOTAL Mass (kg) +0.106 mm Table 10-2 Total Liberation by Caustic Fusion Sampling Results 1 2 1 1 1 Too few stones were recovered for statistical size frequency analysis. However, a total of 19 stones have been recovered for IR spectral analysis. All but one of the stones is reported as white in colour. Table 10-3 Heavy Mineral Stream Sampling Visual Sorting Results Sample number LEM 1A + 1B Size Fraction Diamond Garnet Ilmenite Chrome Diopside Chrome Spinel 0 331+ 120+ ~208 120+ +0.5 mm Lemphane Project th NI 43-101 Technical Report – 28 October 2010 33 Abundant garnet, ilmenite, chrome diopside and chrome spinel were recovered, all of which are probably derived from the Lemphane kimberlite. Garnet, ilmenite and spinel was not stripped from the samples, but a representative number of grains was recovered. The total number of chrome diopside was estimated from stripping all of the grains from 50% of the sample concentrate. It is recommended that all of these grains are microprobed to determine their major element geochemistry and confirm their paragenesis. 10.3 Geophysical Surveys In August 2010, a detailed ground magnetic survey was undertaken by The MSA Group over the Lemphane kimberlite pipe in Lesotho, on behalf of Meso. The objectives were to map the pipe contacts, basalt float, and potential different facies within the pipe, as well as to locate cross-cutting dykes and structures. A line spacing of 20 m and station spacing of 2 m were used. A total of 10.51 line km was surveyed. The survey results showed a substantial magnetic low associated with the pipe, indicating strong remnant magnetism. The western edge of the pipe is very sharp and linear, suggesting that the contact is near vertical and that the pipe may be intruded along a structural feature such as a fault. The south-eastern and eastern edges are less sharp, implying that the pipe contacts may be dipping. The edges of the pipe can be effectively mapped using the derivatives of the total field. The areal extent of the pipe is interpreted as 6.4ha. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 34 Figure 10-2 Ground magnetic survey results. Total magnetic field with survey lines (top) and interpretation overlain on an image of the 1st vertical derivative (bottom) 654600 6797500 654500 6797500 6797400 654400 6797400 6797300 654300 6797300 6797200 654200 6797200 , 29023 28807 28660 28531 28442 28364 28295 28230 28171 28115 28062 28001 27952 27905 27858 27813 27769 27725 27680 27627 27583 27539 27494 27449 27403 27356 27307 27246 27193 27137 27077 27013 26944 26865 26777 26648 26501 26285 Total Field (nT) Scale 1:2500 25 0 25 50 75 100 125 150 (meters) 6797100 6797100 Lemphane Kimberlite Pipe Detailed Ground Magnetics 20m Line Spacing 2m Station Spacing 654400 654500 654600 654200 654300 654400 654500 654600 GRS Consulting for the MSA Group 6797500 6797400 6797200 6797200 6797300 6797300 6797500 654300 6797400 654200 , 84.83 52.53 38.42 30.05 23.97 19.88 16.31 13.29 10.86 8.57 6.70 5.06 3.60 2.17 0.90 -0.35 -1.51 -2.74 -3.97 -5.15 -6.38 -7.58 -8.77 -10.03 -11.27 -12.63 -13.90 -15.45 -17.09 -18.79 -20.77 -23.03 -26.02 -29.48 -34.00 -41.02 -52.13 -75.32 Interpretation Main Pipe Mag positive dyke Mag negative dyke/pipe Basalt blocks First Vertical Derivative Scale 1:2500 25 0 25 50 75 100 125 150 679710 0 6797100 (meters) Lemphane Kimberlite Pipe Detailed Ground Magnetics 20m Line Spacing 2m Station Spacing 654200 654300 654400 Lemphane Project th NI 43-101 Technical Report – 28 October 2010 654500 654600 GRS Consulting for the MSA Group 35 Figure 10-3 shows a comparison between the map of Kresten (1973) and the geophysical interpretation. There is a strong correlation. Similarities include the approximate size and shape of the pipe, the small blow on a dyke identified on the western edge of the pipe, and some internal geological features However there are some differences. The geophysical survey has identified some additional dykes and possible blows with a very similar geophysical signature to that mapped by Kresten, as well as some additional internal geology. The north-east trending shear zone mapped by Kresten does not appear to have a magnetic signature. Interpretations of the internal geology identify magnetically quiet and magnetically busier portion in the core part of the pipe, and a magnetic low partially surrounding the core. These may represent distinct intrusive phases. A number of new NW-SE and E-W trending linear features have been mapped which are interpreted as dykes (possibly kimberlite or dolerite). In addition to the inferred dykes, a number of small sub-circular features were identified which may correspond to blows or small satellite pipes. Discrete magnetic anomalies within the pipe indicate probable basalt blocks, which may have been incorporated into the main pipe. In summary, five possible kimberlite phases are interpreted and are listed below in the possible order of emplacement which is inferred from their geometry: • Kimberlite dykes; • Kimberlite blows; • A ‘collar’ phase; • A northern core phase containing a relatively low proportion of country rock xenoliths. • A southern core phase containing a greater proportion of country rock xenoliths; If the interpretation of the pipe contacts as very steep are correct, then the upper 200 m of the Lemphane pipe could contain over 30 Mt of kimberlite. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 36 Figure 10-3 Comparison of the geophysical interpretation with the geological map of Kresten (1973) Lemphane Project th NI 43-101 Technical Report – 28 October 2010 37 11 DRILLING No drilling has been undertaken on the kimberlite. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 38 12 SAMPLING METHOD AND APPROACH Meso has adopted a phased approach to sampling to mitigate risk. Continuation from one phase of work to the next implies that the results from the previous phase were encouraging. The sampling methodology is summarised in Table 12-1. Table 12-1 Sampling methodology Phase Initial Phase Initial Phase Evaluation Phase I Method Total Liberation by Caustic Fusion Sampling (“Microdiamonds”) Kimberlitic Indicator Minerals Objectives • • • • Pitting and mapping • Evaluation Phase I Total Liberation by Caustic Fusion Sampling Evaluation Phase I Kimberlitic Indicator Minerals • • • • Evaluation Phase I Evaluation Phase II Evaluation Phase II Evaluation Phase II Bulk sampling • Bulk sampling • Core drilling • Core drilling Total Liberation by Caustic Fusion Sampling Lemphane Project th NI 43-101 Technical Report – 28 October 2010 • • Demonstrate presence of diamonds Obtain diamonds for analysis to determine presence of Type IIa diamonds Investigate and quantify degree of mantle ‘sampling’ by the kimberlite Investigate geological kimberlite phases to control ongoing sampling work Total diamond content and size frequency estimation of individual kimberlite phases Obtain diamonds for analysis to determine presence of Type IIa diamonds ‘Fingerprint’ individual kimberlite phases from pit samples Investigate mantle ‘sampling’ by each phase Obtain diamonds for analysis to determine presence of Type IIa diamonds Determine grease recovery of diamonds Obtain large parcel of diamonds for grade and revenue determination Sub-surface density and geometry for geological model 3D total content grade and size frequency model Determine mineral resource 39 13 SAMPLE PREPARATION, ANALYSES AND SECURITY To date, only kimberlitic indicator mineral and total diamond content caustic fusion sampling has been undertaken at Lemphane. 13.1 Kimberlitic Indicator Mineral Sample Analysis The kimberlitic indicator mineral sample was exported from Lesotho with a valid permit and received at MSA in Johannesburg. The sample was wet-screened into three size fractions: +2.0mm; -2.0, +0.3mm and -0.3mm. The oversize (+2.0mm) and undersize (0.3mm) material was discarded. The -2.0mm, +0.3mm material was concentrated using tetrabromoethane (TBE) which has a density of 2.96 g/cm3. The TBE concentrate was cleaned using oxalic acid to remove oxide coatings on mineral grains and produce a clean mineral concentrate for visual microscopic examination. The concentrate was screened into three size fractions for visual examination: -2.0, +1.0mm; -1.0, +0.5mm; and -0.5, +0.3mm. Each fraction was visually sorted for kimberlitic indicator minerals and diamonds. Indicator minerals were placed on cards for later microprobe analysis. None of the indicator minerals have been microprobed as of the effective date of this report. 13.2 Caustic Fusion Total Liberation Diamond Content Sample Analysis Caustic fusion total liberation diamond content (“microdiamond”) samples were exported from Lesotho with a valid permit and received at MSA in Johannesburg. The caustic fusion laboratory is a secure environment with restricted access. The samples were subjected to caustic fusion at the MSA/SGS laboratory in Johannesburg. Caustic fusion provides a concentrate from which liberated diamonds can be readily extracted by microscopic examination. Sample weight reductions after caustic fusion are typically greater than 99.8%. The standard operating procedure is briefly described below. • For each sample the optimum aliquot was determined by loading a variety of weights to individual pots and assessing the maximum weight that can be successfully dissolved per pour. • The carbonate content was assessed by testing with hydrochloric acid prior to aliquot preparation and caustic fusion. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 40 • Other than simple breakage of the kimberlite into +/- 20 mm sized pieces, no other sample preparation was performed prior to dissolution by caustic fusion. • Caustic soda was added to the kimberlite sample in each pot and the kiln was heated to 550 ºC. This temperature was maintained for fourteen hours. • After the digestion in molten caustic soda, the sample residue was screened using a bottom screen of 75 microns (µm). • The residue, greater than 75 µm, was liberated from the NaOH by washing in hydrochloric acid leach and hot water baths. The bottom screen for the acid leach was 75 µm. The washed residue of each sample, enclosed in the 75 µm screen used during the leaching and washing process, was then dried. • The dry residue of each sample, wrapped in the 75 µm screen used during the acid leach, was received for sorting. • If the residue was large (> 30 g) a secondary fusion, in smaller crucibles, was done. This involved treating the acid cleaned caustic residue in a mixed chemical 0 flux at 550 C to remove ilmenite and garnet. This produced a significantly smaller sample residue more suitable for diamond recovery. • Quality control throughout the process was monitored by spiking with sized synthetic diamonds that are easily identifiable. The synthetic diamond spikes were added to the sample at the start of the caustic fusion process. • The synthetic diamonds used to monitor the process efficiency for each sample were selected from the following 3 size fractions: -425 µm to +300 µm, -300 µm to +212 µm and -212 µm to +150 µm. • Natural and synthetic diamonds were recovered from the +75 µm residue using 60 x magnification with a binocular microscope. The residue was examined a minimum of two times to ensure the total recovery of diamond. • Recovery rate of the spikes was reported (see Section 14.2) and the recovered spikes were stored on sample cards. • The recovered diamonds were separated into 13 sieve classes by screening. • Recovery rate of the spikes was reported and the recovered spikes were stored on sample cards. • Colour, clarity, and morphology of each diamond was determined and reported. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 41 • X, Y and Z dimensions of each diamond were measured in mm. • All diamonds greater than 300 µm were weighed individually and placed on sample cards. Diamonds smaller than 300 µm were weighed in groups. • The gram weight was converted to carats. • Diamond data was tabulated in Excel spreadsheets. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 42 14 DATA VERIFICATION Historical data and information on adjacent properties recorded in this report has been obtained from published reports as referenced, and has not been independently verified. Samples from the current exploration programme have been subject to quality control measures as described below. 14.1 Kimberlitic Indicator Mineral Samples Quality control for the recovery of kimberlitic indicator mineral was established by adherence to standard operating procedures and 100% check sorting. The MSA laboratory operates a quality management system and has applied for ISO 17025 accreditation. 14.2 Caustic Fusion Total Liberation Diamond Content Samples Quality control for the recovery of diamonds using the caustic fusion total liberation process was established by adherence to standard operating procedures and spiking of samples with diamonds in different size fractions. 25 diamonds were introduced to each sample prior to dissolution with caustic soda. 100% of all spikes were recovered during the sorting process, indicating that the process is very efficient. The MSA/SGS caustic fusion laboratory operates a quality control system and has applied for ISO 17025 accreditation. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 43 15 ADJACENT PROPERTIES The Lemphane Project lies within the northern Lesotho kimberlite cluster. This area of kimberlite occurrences was first recognised in the late 1950s and includes over 100 known kimberlite intrusions, varying in size from the Kao pipe (19.8 ha) and the main Letseng pipe (15.9 ha) to several small dykes and blows. Historically, only the Letseng and Liqhobong pipes have been mined. The Letseng pipes were originally mined by De Beers, and more recently by Letseng Diamonds (Pty) Ltd. Two other pipes in the cluster have been subject to investigation and project development in recent years, namely Mothae and Kao. Figure 15-1 Northern Lesotho Kimberlite cluster A characteristic of kimberlites in the adjacent properties is the occurrence of large, high quality stones which have very high value. The occurrence of such stones at Lemphane is Lemphane Project th NI 43-101 Technical Report – 28 October 2010 44 anecdotal and has not been confirmed. Testing for such stones will be an important objective in the sampling programmes. The adjacent properties are summarized below. 15.1 Letseng Diamonds Table 15-1 Letseng Mine (source Gem Diamonds Annual Report 2009) Owner: Gem Diamonds (70%), GoL (30%) Mining Licence: Letseng ML Area of Licence: 68 km Production periods; 1977-1982, 2004 - present Mining method: Open pit Grade: 1.2 ct/100t (2009) Production 90 878 carats (2009) Approx. value USD 1 534/ct (2009); USD 28 per tonne Geology Letseng kimberlite Main Pipe (15.9 ha) and Satellite Pipe (4.7 ha). Some minor eluvial and alluvial deposits also included in the Mining Licence have been mined out. Life of Mine 2029 and beyond. Resource / Reserve Probable reserve of 68.7 Mt grading at 1.59 ct/100t with an average value of USD 1 753 per ct. 2 Total resource* of 239 Mt grading at 1.74 ct/100t with an average value of USD 1 592 per ct. *Includes reserves The Letseng Mine was acquired by Gem Diamonds from JCI Ltd in 2006 for USD 118.5 million. The mine is characterised by very low grade ore but is well known for producing large diamonds. It produces the highest percentage of ‘special’ diamonds (gems greater than 10.8 carats) of any kimberlite diamond mine. Letseng is renowned for its production of historic diamonds, many of which have been identified as Type IIa stones. The recently recovered 478 carat Leseli la Letšeng white diamond (sold for USD 18.4 million) is the world’s 20th largest rough gem diamond and Lemphane Project th NI 43-101 Technical Report – 28 October 2010 45 third significant recovery from the Letseng Mine in as many years, following the 603 carat Lesotho Promise (14th largest; sold for USD 12.4 million) and the 493 carat Letšeng Legacy (18th largest; sold for 10.4 million) recovered in 2006 and 2007 respectively. Including the 601 carat Lesotho Brown, recovered in 1960 (15th largest), the Letseng Mine has now produced four of the world’s 20 largest rough gem diamonds and the three largest gem diamonds recovered this century. In September 2010, the mine reported a 196 ct white stone which has yet to be sold. Figure 15-2 Panoramic View of Letseng Mine (photo by Tessa Joughin on panoramio.com) Lemphane Project th NI 43-101 Technical Report – 28 October 2010 46 15.2 Mothae Diamond Project Table 15-2 Mothae Project Owner Lucara Diamond Corporation (75%), GKL (25%). GKL has a 12.5% free carry and will fund the balance from its share of profits. Mining Licence Valid until September 2019. Area of Licence 20 km2 Mining start date Test mining underway since mid-2010. Plan to commence new mine production in 2013. Mining method open pit Grade 4.7 ct/100t (dry sample grade from a total of 82 380 t of bulk samples) Production Trial mining 30 000t per month. Full production (2014) estimated 2.5 Mt and 70 000 ct per annum. Approx. value USD 549 per ct (modelled); USD 25.8 per dry tonne (modelled) Geology An elongate pipe (8.8 ha) comprising multiple kimberlite types intruding Karoo basalts. Life of Mine 12 years Royalty 8% of gross revenue Resource Reserve / Not yet reported. Lucara Diamond Corp has acquired a 75% share in the Mothae Project through funding of exploration (USD 10 million) and purchase of outstanding shares in Motapa Diamonds Inc in 2009. Sampling work in 2009 recovered a 23.4 ct Type IIa diamond. In June 2010, the company commenced a 720 000 t trial mining programme and reported the recovery of a 53.5 ct Type IIa diamond within the first 2 000 t of material processed. The first sale of diamonds from the trial mining is scheduled for the first quarter of 2011. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 47 Figure 15-3 Geological Model of the Mothae Kimberlite. The pipe is approximately 700m long (source: Lucara Diamond Corp website) 15.3 Kao Project The Kao kimberlite pipe was discovered in the 1950s and artisanal production of 17,567 carats was recorded when the pipe was declared a government digging during the 1960s. Stones produced included a 46 carat “blue white”, a 387 carat “pure white” and a 33 carat “blue”. The pipe was explored and assessed by the Newmont joint venture company known as Maluti Diamond Corporation, in the early 1970s. The Newmont assessment included both drilling (some 2 600 m) as well as bulk sampling of 11 large pits (6 x 20 m deep). Individual bulk samples of 1500 t each were crushed to pass through a 12 mm screen and a concentrate was obtained using a DMS plant. Diamonds were thereafter recovered with an X–ray fluorescence “Gunner Sortex” machine. The Newmont sampling results were deemed sufficiently reliable and thorough for the upper 60 metres of the Kao Pipe to be classified as an indicated resource of 27 million tons at 7 cpht (SRK reported by Venmyn, 2010). Subsequent drilling and total liberation diamond work led to a revision of the resource. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 48 Table 15-3 Kao Project (Source: Venmyn Rand (Pty) Ltd Independent Competent Person’s Report dated 28th February 2010) Owner Namakwa (75%), GKL (25%) Mining Licence Kao ML valid until 2019 and renewable for three periods of 10 years each subject to production targets. Area of Licence 6.53 km2 Mining started Trial mining started in May 2010 Mining method Open pit. Grade Not yet reported Production Not yet reported Approx. value Not yet reported. USD 10.9 per tonne based on the reported resource model. Geology Two kimberlite pipes (Main Pipe, 19.8 ha and Satellite pipe 3.2 ha) Life of Mine Not yet reported Royalty 8% of gross revenue Resource Reserve / Indicated resource of 20.9 Mt at 7.06 cpht and USD 154/ct Venmyn have valued the Kao Project at approximately USD 22.4 million (Venmyn, 2010; Net Present Value calculated from a discounted cash flow at 10% discounted rate). The project is currently undergoing trial mining. A parcel of diamonds recovered from the trial mining and totalling in excess of 6 000 ct was scheduled to be sold by tender in October 2010. The results of the tender were not published prior to the effective date of this report. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 49 Figure 15-4 Geological Model of the Kao kimberlite main pipe. The pipe is approximately 750m across (NE-SE) (source: Venmyn Rand, 2010) Lemphane Project th NI 43-101 Technical Report – 28 October 2010 50 15.4 Liqhobong Project Table 15-4 Liqhobong Project (± 6 km E of Lemphane) (source Firestone Diamonds AIM admission document, 2010) Owner Firestone Diamonds plc (75%), GKL (25%) Mining Licence Liqhobong Mining Lease valid to 2017 and renewable for a further period of 10 years Area of Licence 3.9 km2 Production period 2005 - 2008 Mining method Open pit Grade 43.5 cpht Production 352,780 ct Approx. value USD 48/ct Geology Two kimberlite pipes Life of Mine Not yet determined Royalty 10% Resource / Reserve Indicated resource (Main pipe) of 38.54 Mt with an average grade of 32.8 cpht and an average revenue of USD 86/ct. An inferred resource of 52.12 Mt with an average grade of 35.5 cpht and the same revenue (+1.0mm). No reserve has been defined. On 29th September 2010, Firestone Diamonds plc acquired Kopane Diamond Development plc in an all-share deal valued at USD 70.7 million. The Liqhobong Project is an exploration property (as that term is defined in NI 43-101) and was the only significant asset in the Kopane portfolio. A definitive feasibility study is underway and is scheduled to be completed at the end of 2010. It is reported that the largest Type IIa diamond recovered at Liqhobong was a 144 ct D-colour white stone which was broken in the recovery process in 2006. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 51 16 MINERAL PROCESSING AND METALLURGICAL TESTING No metallurgical testing has been conducted on samples from the Lemphane Project. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 52 17 MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES No NI 43-101 compliant mineral resource has been defined on the Lemphane Project. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 53 18 OTHER RELEVANT INFORMATION 18.1 Diamond Market All diamond projects are sensitive to diamond revenue and diamond price fluctuations. Forward looking diamond demand and supply models in recent years have all indicated a steady rise in demand (driven largely by growth in the number of Chinese and Indian consumers) with a steady decrease in supply as major diamond resources are depleted, and few new mines come into production (see for example Figure 18-1). Figure 18-1 Rough diamond supply vs demand forecast pre-global financial crisis (source: WWW International Diamond Consultants Ltd) This scenario was driving diamond prices higher until the third quarter of 2008, when the global financial crisis (GFC) caused a rapid decline in diamond prices. As signs of global economic recovery appear, both rough and polished diamond prices have resumed their upward trend. Several sources suggest evidence of a strong recovery in rough diamond prices having occurred through 2010: Lemphane Project th NI 43-101 Technical Report – 28 October 2010 54 • De Beers reported strong demand following Quarter 3 auction sales from Diamdel (source: Diamdel auctions update, October 20, 2010). • In September 2010, Rio Tinto announced a USD 803 million investment in underground development at the Argyle diamond mine in Australia. Spokesmen indicated, “This investment …. underlines our commitment to and confidence in the world diamond industry. The project was slowed in 2009 due to the global financial crisis but the diamond market continues to recover and long-term industry fundamentals remain healthy. A significant supply gap is expected to emerge in the medium to long term and the outlook for demand is strong, driven by the growth of emerging markets." (source: Rio Tinto Diamonds news release, September 14, 2010). • According to IDEX online, Indian imports of rough diamonds in May 2010 were comparable to pre-crash levels. The same was reported for Belgium. (source: IDEX online news report dated June 16, 2010). • Petra Diamonds reported strong recovery in rough diamond prices in their results for the year ended June 30, 2010. • Quarter 2 2010 diamond sales reported by Harry Winston Diamond Corporation st (press release dated 1 Sept 2010) indicate an average 62% increase in rough diamond prices relative to the same period in 2009. Figure 18-2 shows the growth of rough and polished diamond prices since 2002. The effect of the global financial crisis on diamond prices was profound. There has been a subsequent recovery in both the price of rough and polished diamonds. However, it is remarkable to note that according to WWW Interational Diamond Consultants, the price of rough has already surpassed the pre-GFC peak. This recovery is expected to continue. In a presentation given to the colloquium entitled “Diamonds - Source To Use” held in Gaborone from 1 – 3 March 2010, Allan - Hochreiter (an independent corporate finance company) forecast real growth in diamond prices of 7% per annum from March 2010 until 2020. Royal Bank of Canada Europe Limited, an investment bank, published an equity research report on the diamond industry on 3rd March 2010. This report forecast a short term price increase of 7% between March 2010 and January 2011. From this short review of a number of separate and independent sources, it appears that the diamond market, and in particular the rough diamond market, has already recovered from the GFC, this recovery is robust, and prices will continue to rise. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 55 Figure 18-2 Rough and polished diamond prices 2002 to September 2010 (sources: WWW International Diamond Conultants and PolishedPrices.com) In the medium- to long-term, demand for rough diamonds is expected to continue to outstrip supply as mineral reserves continue to dwindle and the market continues to expand. Recent capital investments at major mines around the world (e.g. Jwaneng in Botswana and Argyle in Australia) will not boost production. They will only extend the life of those mines. The consequence of this is likely to be that prices of rough diamonds will continue to rise, and marginal diamond projects will become economic. If this is the case, it is unlikely that the additional supply from new producers would be sufficient to change the overall trend. Demand will continue to outstrip supply in a growing market. However, as a luxury item, diamonds remain very vulnerable to global economic downturns, and the positive outlook for diamonds remains heavily dependent on continued short term economic recovery, and longer term economic stability. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 56 19 INTERPRETATION AND CONCLUSIONS Meso is embarking on an aggressive evaluation of the Lemphane kimberlite based on a review of available information on the kimberlite itself and adjacent properties. The initial geophysical and sampling programme has slightly increased the interpreted areal extent of the main pipe, and confirmed the presence of diamonds. The results of this initial work have prompted a decision to move ahead with a phased bulk sampling programme. In historical context, Lemphane was one of the kimberlite discoveries identified as a ‘Government digging’ during the 1960s, along with adjacent kimberlites such as Letseng, Kao and Liqhobong. As such, it must be regarded as a target with some potential. However, it has subsequently received less attention than these other properties and this may be due to a variety of reasons. For example, it was relatively more remote compared to the other kimberlites, the overburden had a greater thickness or it may be due to lower grade or value of stones. This can only be established by a proper evaluation programme. The recent upgrade of access to nearby Liqhobong means that the previous remoteness of Lemphane is no longer an issue. The ground magnetic survey on the kimberlite identified some inferred internal geological contacts. The presence of different kimberlite phases have been confirmed from outcrop, and this may be significant in terms of variations in grade and revenue. The pipe is approximately 6.4 ha near surface with steep wall contacts. Two alternative interpretations of internal geology have been made, but essentially five possible kimberlite phases are recognised and are listed below in their possible order of emplacement, which is inferred from their geometry: • Kimberlite dykes; • Kimberlite blows; • A ‘collar’ phase; • A northern core phase containing a relatively low proportion of country rock xenoliths; • A southern core phase containing a greater proportion of country rock xenoliths. These inferred phases will be investigated during the planned sampling programmes (see Section 20). No measurement of the volume or tonnage of kimberlite has been undertaken. However, based on the geophysical survey, and the inference that the pipe contacts are steep, the upper 200m of the pipe could conceptually contain approximately 30 Mt of kimberlite. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 57 No recent grade or revenue determination has been undertaken. These will be the subject of the Phase I and Phase II evaluation programmes described in Section 20. 19.1 Project Risks and Opportunities Meso are aware of project risks as listed in Table 19-1. Table 19-1 Summary of Project Risks Risk Category Description of Risk Rating Environmental Artisanal workings Moderate Environmental Drainage into the Khatse Dam Moderate Financial Exchange rates Moderate Technical Grade and revenue High Technical Evaluation sampling methodology Low Technical Mining method Moderate Technical Evaluation and mining footprint Moderate Community Local farmers and artisanal miners present on site Moderate Mitigation/Comment The historical and recent activity on the property has been recorded and reported in a preliminary Environmental study. Drainage from the mine is into the Malibomatsu River and slimes from evaluation and possible future mining need to be carefully managed. Project development and any future production costs will essentially be in M/ZAR, whilst project funding is in GBP and diamond sales would be in USD. The ZAR/USD and ZAR/GBP exchange rates are fairly volatile. The grade and revenue of the project have not yet been established and the potential of the project remains conceptual. There is a risk that the Phase I sampling methodology will be ineffective due to nonrecovery of diamonds with grease. This has been mitigated by planned extended residence in a scrubber, and X-ray analysis of grease tailings. The topography would make conventional open pit mining challenging. The topography would make any future mine layout challenging. Good relations have been created and maintained with the local residents. Employment will be offered during the evaluation and possible future mining of the kimberlite. Opportunities for the project include the proximity of the Liqhobong and Kao projects which are in the exploration or development stage and which share infrastructural requirements. This may provide the opportunity for certain synergies including grid power and other infrastructure, security, skills development, resource sharing, and development of secondary support services. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 58 20 RECOMMENDATIONS The limited sampling that has been done to date has demonstrated the presence of diamonds. The occurrence of high value stones in adjacent projects suggests that there is the potential to find similar high value stones at Lemphane. The exploration model is therefore to test a low grade, high revenue deposit. In order to evaluate the Lemphane kimberlite effectively, a phased approach is proposed. Phase I is aimed at establishing the geology of the pipe and providing some information on total content grade and size frequency of the diamond population, as well as providing some information on the types of diamonds present, and their recoverability. Phase II would establish the grade and develop diamond revenue information and a three dimensional geological, density and grade model to determine a mineral resource. The time frame for the evaluation programme is indicated on a Gantt chart (Figure 20-1). Figure 20-1 Evaluation Programme Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Phase I Evaluation Access Pitting Mapping Total content sampling and results HM Sampling and results Plant I establishment and commissioning Process Pit samples (100 t) Process Eluvial sample (100 t) Process Alluvial sample (100 t) X-ray analysis of grease tailings Phase II Evaluation Bulk sample of >1,000 t Core drilling (~5,000 m) (Plant design depends on results from Phase I) 20.1 Phase I Evaluation Programme The results from the Phase I evaluation programme will assist in developing a geological map of the kimberlite sub-crop. The results should also provide a number of diamonds and information regarding their recoverability using grease. The Phase I work programme will comprise the following. • Access - Repair the track from the village to the pipe to allow access for pitting equipment. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 59 27 28 • Excavation of pits on a 50m grid over the pipe (25 - 30 pits) • Mapping of kimberlite (visual and petrographic analysis) to identify different kimberlite phases within the main pipe. • Total liberation diamond and heavy mineral sampling of pits to establish kimberlite phases and establish total content grade. Samples can be combined per kimberlite phase once this is established. • Establishment of a plant on site to recover diamonds. • Up to 5 tonnes of kimberlite material from each pit will be processed through the plant to recover diamonds (approximately 100 to 150 tonnes). • Up to 100 tonnes of the eluvial lag material will be collected and processed through the plant. • Up to 100 tonnes of alluvial material will be collected and processed through the plant. 20.1.1 Phase I Evaluation Sampling Plant A low-cost sampling plant (+1.8, -40 mm) has been designed for the Phase I evaluation programme. The plant essentially comprises a scrubber, atritioner and grease table arrangement. The flow-sheet is shown in Figure 20-2. Samples will be stored in a secure environment whilst awaiting treatment. The fresh feed will be loaded onto a feed bin with a front end loader. The feed bin will be fitted with a static grizzly. The oversize will be deposited onto a stockpile and will be introduced into a cement mixer loaded with abrasive balls. The residence time in the cement mixer will be decided on site. The cement mixer feed will be re- introduced into the feedbin. The feed from the feed bin will be conveyed to a primary scrubber and the feed rate will be measured with a weightometer. The material from the scrubber will be fed through a trommel fitted to the scrubber with 40 mm apertures. The material passing the apertures will be deposited onto the scrubber screen. The material not passing the trommel apertures will be deposited onto an oversize stockpile and will be processed through the cement mixer with abrasive balls as described above. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 60 Figure 20-2 Phase I Sampling plant and mass balance Grizzly 10 tph Feed Bin Feed belt 9 tph 9 tph Tailings belt Greasetables 5 tph Oversize 1 tph Primary scrubber 9 tph Secondary scrubber 5 tph 5 tph Scrubber screen 9 tph Slimes pump 4 tph Greasefeed belt 5 tph Storage 5 tph The scrubber screen will be fitted with 1.8mm slotted panels. The material passing through the screen apertures will be pumped to the slimes dam. It is estimated that approximately 40% of material will be undersize. The material not passing the screen apertures will be conveyed to the secondary scrubber. The material from the secondary scrubber will be dewatered and fed onto a classifying screen. The classifying screen will size the material into three size fractions, one size fraction per grease table. The material that sticks to the grease will be removed manually and put into a degreasing canister. The canister will be put into a hot water tank where the grease is removed and the degreased material will be dried. The canister with the dry material is closed and sealed and stored inside a secure area inside the grease recovery area. The grease concentrate will be hand sorted. It is intended that the grease table tailings will be combined and sent through an x-ray or optical sorter to determine the proportion of diamonds which were not grease recoverable. It is further intended that the diamonds recovered will be analysed by the Diamond High Council (HRD) in Antwerp to determine the presence of Type II diamonds, and to determine their X-ray recoverability. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 61 20.2 Phase II Evaluation Programme The objective of the Phase II programme will be to establish a mineral resource. This will be achieved by sampling the geological phases identified from Phase I, and processing them through a plant designed according to the parameters established during Phase I, in terms of diamond recoverability. It is likely that 3 000 to 5 000 t of kimberlite will need to be processed to establish the grade, size frequency and value of the diamond population present at Lemphane. In addition, a core drilling programme will be required to determine three dimensional geological, grade and density models for estimation of a mineral resource. 20.3 Work Programme Budgets Table 20-1 Exploration Budget (Phases I and II) Phase Item Budget (GBP) Initial Phase Infrastructure: camp construction and road upgrade 180 000 Initial Phase Total liberation diamond content analysis and kimberlitic indicator mineral sampling 30 000 Evaluation Phase I Pitting, mapping, total liberation diamond content sampling, plant, sample processing 200 000 Evaluation Phase II Bulk Sampling (3 000 to 5 000 t) 200 000 Evaluation Phase II Core drilling (3 000 to 5 000 m), logging and geological modelling 550 000 Evaluation Phase II Total liberation diamond content sampling of drill core 110 000 TOTAL Lemphane Project th NI 43-101 Technical Report – 28 October 2010 1 270 000 62 21 REFERENCES Bailey, D.K., (1992) Episodic alkaline igneous activity across Africa: implications for the causes of continental break-up. In: Storey, B.C., Alabaster, T. and Pankhurst, R.J. (Eds.), Magmatism and the causes of continental break-up, Geol. Soc. Spec. Publ., 68, 91-98. Brown, R. W., M. A. Summerfield, and A. J. W. Gleadow, (2002) Denudational history along a transect across the eastern margin (Drakensberg Escarpment) of southern Africa derived from apatite fission-track thermochronology, J. Geophys. Res., 107, 10.1029/2001JB000745 Catuneanu, O., Wopfner, H., Eriksson, P.G., Cairncross, B., Rubidge, B.S., Smith, R.M.H., and Hancox, P.J. The Karoo basins of south-central Africa Journal of African Earth Sciences, Volume 43, Issues 1-3, October 2005, Pages 211-253 De Wit, M.J., Roering, C., Hart, R. J., Armstrong, R. A., De Ronde, C. E. J., Green, R .W. E., Tredoux, M., Peberdy, E and Hart, R. A. (1992). Formation of an Archean continent. Nature 357, 553-562. Eglington, B., Reddy, S. and Evans, D. (2008) IGCP 509 Example Space-Time Plot: Palaeoproterozoic of Southern Africa. Geological Society, London, Special Publications; 2009; v. 323; p. 27-47 Firestone Diamonds (2010) Proposed Acquisition of Kopane Diamond Developments plc and Application for Admission of Enlarged Issued Share Capital to trading on th AIM.13 August 2010. Gem Diamonds Annual Report (2009) James, D.E., Fouch, M.J., Van Decar, J.C., van der Lee, S., and the Kaapvaal Seismic Group (2001) Tectospheric structure beneath southern Africa. Geophysical Research Letters, Vol. 28, No. 13, Pages 2485-2488, Jul 1, 2001 Kresten, P. (1973) The Geology of the Lemphane Pipes and Neighbouring Intrusions. In: Lesotho Kimberlites. Edited by P.H. Nixon. Lesotho National Development Corporation Marsh, J.S., Hooper, P.R., Rehacek, J., Duncan, R.A., and Duncan, A.R. (1997) Stratigraphy and age of Karoo basalts of Lesotho and implications for correlations within the Karoo Igneous Province. Geophysical Monograph, vol 100, pp 247-272 Meaton, E. St. P. (1966) Basutoland Diamonds: Evaluation of selected kimberlites and alluvials. London, Report of the Ministry of Overseas Development, 1966 Lemphane Project th NI 43-101 Technical Report – 28 October 2010 63 Moore, A.E. (2009) Type II diamonds: Flamboyant Megacrysts? South African Journal of Geology. Vol. 112, pp 23-38. The MSA Group (2007) Independent Technical Report on the Mothae Diamond Project for Motapa Diamonds Inc. 12th February 2007. Mucina, L. and Rutherford, M.C. (eds) (2006) The vegetation of South Africa, Lesotho and Swaziland. Strelizia 19. South African National Biodiversity Institute, Pretoria. Nixon, P.H. (1973). Lesotho Kimberlites. Lesotho National Development Corporation 351pp. Stockley, G.M, (1947) Report on the geology of Basutoland. Maseru. Basutoland Government, 1947. Thabex Ltd Annual Report (2009) Venmyn Rand (2010) Independent Competent Persons' Report on the Mineral Assets of Namakwa Diamonds Limited, 28th February 2010. www.firestonediamonds.com www.gemdiamonds.com www.letsengdiamonds.co.ls www.lucaradiamond.com Lemphane Project th NI 43-101 Technical Report – 28 October 2010 64 22 DATE AND SIGNATURE PAGE The undersigned, Dr Frieder Reichardt, contributed to all sections of this technical report, titled “NI 43-101 Technical Report on the Lemphane Kimberlite Project, th Lesotho.” with an effective date of 28 October 2010, in support of the public disclosure of technical aspects of the Lemphane Property. The format and content of this report are intended to conform to Form 43-101F1 of National Instrument 43-101 of the Canadian Securities Administrators. Signed, ………………………………………. Dr Frieder Reichhardt 28th October 2010 ------------------------------------------------------------------------------------------------------------------ Lemphane Project th NI 43-101 Technical Report – 28 October 2010 65 23 CERTIFICATES CERTIFICATE OF QUALIFIED PERSON I, Frieder Reichhardt, Pr.Sci.Nat., do hereby certify that: 1. I am a Principal Consulting Geologist with The MSA Group, 22b Rothesay Avenue, Craighall Park, Johannesburg. 2. I graduated with a M.Sc. degree in geology from the University of Munich in 1984. I obtained a Ph.D. degree in geology from Pretoria University, South Africa, in 1989. 3. I am a registered Professional Natural Scientist (Geology, Registration Number 400048/04) with the South African Council for Natural Scientific Professions and a member of the Geological Societies of South Africa and Germany. 4. I have worked as a geologist for 26 years since my graduation. My relevant experience for the purposes of this Technical Report is: a. Five years (1989-1994) as senior geologist in Botswana, for Gold Fields Botswana, engaged in exploration for PGE-Ni-Cu, kimberlite and diamonds. b. Six years (1994-2000) as project geologist for Rio Tinto Zimbabwe, exploring for kimberlite and diamonds in Zimbabwe resulting in the discovery of the Sese and Murowa diamondiferous kimberlites. c. Four years (2000-2004) as project geologist for Rio Tinto M&E Botswana, exploring for kimberlite and diamonds in Botswana d. One year (2005 – 2006) as Vice President of exploration for Sierra Leone Diamond Company managing diamond exploration programmes in Sierra Leone. e. Five years (2006 – Current) as consulting geologist for the MSA Group consulting and/or reporting on diamond properties in Botswana, Namibia, Zimbabwe, South Africa, Brazil and Angola. 5. I have read the definition of “qualified person” set out in National Instrument 43-101 (“NI43-101”) and certify that by reason of my education, affiliation with a professional association (as defined in NI43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101. 6. I am responsible for sections 1 – 21 inclusive of this Technical Report entitled “NI 43-101 Independent Technical Report on the Lemphane Kimberlite Project, Lesotho.” and dated October th 28 2010 relating to the Lemphane property. I visited the Lemphane property on 9th October 2010. 7. I have had no prior involvement with the property which is the subject of the Technical Report. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 66 8. I am not aware of any material fact or material change with respect to the subject matter of the Technical Report that is not reflected in the Technical Report, the omission to disclose which makes the Technical Report misleading. 9. I am independent of the issuer applying all of the tests in section 1.4 of National Instrument 43101. 10. I have read National Instrument 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form. 11. I consent to the filing of this Technical Report with any stock exchange and other regulatory authority and any publication by them, including electronic publication in the public company files on their websites accessible by the public, of this Technical Report. th Dated this 28 day of October 2010. ………………………………………………. Dr Frieder Reichhardt, Pr.Sci.Nat., GSSA Lemphane Project th NI 43-101 Technical Report – 28 October 2010 67 24 GLOSSARY OF TECHNICAL TERMS aeolian an adjective to describe a sediment transported and deposited by wind aeromagnetic survey Surveys flown by helicopter or fixed wing aircraft to measure the magnetic susceptibility of rocks at or near the earth’s surface. Kimberlite may be detected by these surveys. alkaline rock an igneous rock containing an excess of sodium and or potassium alluvial Transported and deposited in a river system, e.g. diamonds eroded from kimberlites and deposited in river gravel. Archaean The oldest rocks of the Precambrian era, older than about 2 500 Ma. artisanal Adjective to describe mining by workers operating without substantial capital, technical skills or training. ASTER Advanced Spaceborne Thermal Emission and Reflection Radiometer) is an imaging instrument flying on Terra, a satellite launched in December 1999 as part of NASA's Earth Observing System. basalt A common volcanic rock, dark and fine grained, relatively low in silica. May form very extensive lava flows. basement The igneous and metamorphic crust of the earth, underlying sedimentary deposits. bedrock the first hard and solid rock underlying soil or unconsolidated overburden breccia A coarse grained rock made up of large angular fragments, sometimes of various rock types. In kimberlite geology, often the filling of a kimberlite pipe made up of country rock fragments enveloped in kimberlite. The fragments may be transported within the pipe (an intrusive breccia) or essentially in-situ (an intrusion breccia). Lemphane Project th NI 43-101 Technical Report – 28 October 2010 68 brecciated Adjective applied to an intensely fractured body of rock. bulk sample a large sample, at least a hundred tonnes, usually excavated mechanically carat Standard unit of diamond weight, 1 carat = 0.2 grams carbonate A rock, usually of sedimentary origin, composed primarily of calcium, magnesium or iron and CO3. Essential component of limestones and marbles. caustic fusion A laboratory method for achieving total liberation and recovery of the diamonds (and other resistant minerals) from kimberlite down to microscopic sieve sizes by means of fusing the rock with sodium hydroxide, which destroys the silicate phases and leaves a small residue of resistate, in which will be found any diamonds present. CIM Canadian Institute of Mining, Metallurgy and Petroleum core drilling Method of obtaining cylindrical core of rock by drilling with a diamond set or diamond impregnated bit. For drilling of diamond deposits bits with synthetic rather than natural diamonds are used, to avoid possible contamination. chrome diopside A calcium, magnesium silicate, Ca(Mg,Fe,Cr)(Si,Al)2O6, with a high proportion of chromium substitution in the lattice, which is a common indicator mineral for diamond. chromite An oxide of chromium, (Mg,Fe)Cr2O4, some varieties of which can occur in kimberlite. colluvium Sediment transported downslope by gravity; usually proximal to its source. conglomerate A rock type composed predominantly of rounded pebbles, cobbles or boulders deposited by the action of water. craton Large, and usually ancient, stable mass of the earth’s crust comprised of various crustal blocks amalgamated by tectonic processes. A cratonic nucleus is an older, core region embedded within a larger craton. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 69 Cretaceous Applied to the third and final period of the Mesozoic era, 141 Ma to 65 Ma ago. ct/100 t Carats per hundred tonnes. A common way of expressing the grade of diamonds in a deposit. ct/m 3 carats per cubic meter. A common way of expressing the grade of diamonds in a deposit, sometimes favoured because it does not require an estimation of rock density. dense media separation DMS a process where a suspension of dense powder (ferrosilicon in diamond plants) in water is used to form a type of ‘heavier liquid’ to separate mineral particles in a sink-float process. diamond drilling synonymous with core drilling diamond size frequency distribution A cumulative plot of the percentage of stones found in each size fraction of a parcel. Confidence in the sampling results is obtained when multiple samples of the same deposit display similar curves. The curve also provides information regarding the overall value of the parcel. For example, a higher percentage of large stones will provide a higher value to the overall parcel. diatreme A volcanic vent created by gaseous magma sourced from the mantle. A common mode of occurrence of kimberlite and often referred to as a pipe. DMS Dense Media Separation. A technique to produce a diamond bearing concentrate. DMS yield The proportion of material reporting to the concentrate from a DMS process. Expressed as a percentage. dyke A vertical or near vertical sheet of igneous rock, the widths of which may range from centimeters to hundreds of meters. One of the typical modes of occurrence of kimberlite, in the case of which widths are usually narrow, less than 2 m. Ecart probable (Ep) Measure of the efficiency of a density separation device. Defined as half the differential in density between the 75% and 25% coefficient. The lower the Ep, the better the separation. EIA Environmental Impact Assessment. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 70 eluvium Sediment derived from the physical and/or chemical decomposition of the underlying bedrock. EMP Environmental Management Plan. Equator Principles A set of voluntary governance rules for managing social and environmental risk in project finance (see www.equator-principles.com). facies The sum of the lithological (and palaeontological) characters of a particular rock. In the case of kimberlite there are usually four facies recognized – hypabyssal, diatreme, crater and transitional. Specific facies may also be identified with particular caharcteristics. fault A fracture or fracture zone, along which displacement of opposing sides has occurred. G9 A type of red to purple pyrope garnet often found in both diamond bearing and non diamond bearing kimberlite. G10 A type of lilac-coloured pyrope garnet often associated with diamond bearing kimberlite. Ga Giga years (1 Ga = 1,000 million years) garnet A silicate mineral with many varieties. Specific compositions can be related to depths and pressures of formation, eg pyrope garnets are chrome rich and are common in kimberlite, and are a kimberlite indicator mineral. geophysical surveys Instrumental surveys measuring small variations in the earth’s magnetic field, gravity field electrical conductivity or other proprties related to local variations in rock type. Widely used to discover kimberlite pipes. Magnetic and some electrical methods can be carried out from an aircraft, whereas gravity surveys are most commonly conducted using ground based surveys. Gondwana The southernmost of two supercontinents that existed during the Mesozoic comprising what are today Africa, Australia, South America, India and Antarctica gneiss A coarse grained, banded, high grade metamorphic rock. GPS Global Positioning System. A satellite based navigation system able to give real time positions to approx ±5 m. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 71 grease table A device for recovering diamonds in a treatment plant using grease, to which the diamonds preferentially adhere due to their hydrophobic properties. ha Hectare = 10,000 m . A common unit for expressing the surface area of a kimberlite pipe. harzburgite An ultramafic igneous rock comprising the minerals olivine and orthopyroxene. Harzburgite is an important component of the Earth’s mantle. hypabyssal An adjective for an igneous rock, e.g. kimberlite, which has crystallized from a melt within the earth’s crust, but at relatively shallow depth. ilmenite An iron, magnesium and titanium oxide ((Fe,Mg)TiO3). The magnesium-rich ilmenite in kimberlite is called picroilmenite. Indicated Resource An Indicated Mineral Resource is that part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics, can be estimated with a level of confidence sufficient to allow the appropriate application of technical and economic parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed. (CIM definition). (Indicated Mineral Resource) 2 indicator minerals A suite of resistant minerals with an origin and mode of occurrence similar to diamond, that can be indicative of the presence of primary diamond deposits. Inferred Resource An Inferred Mineral Resource is that part of a mineral resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. (CIM definition). (Inferred Mineral Resource) Lemphane Project th NI 43-101 Technical Report – 28 October 2010 72 isotope dating A method of dating rocks by quantifying the relative ratio of isotopes. joints Regular planar fractures or fracture sets in massive rocks, usually created by unloading, along which no relative displacement has occurred. Jurassic Second period of the Mesozoic Era, 190 to 141 Ma ago Kalahari An extensive tract of flat, featureless sand savanna, mainly devoid of perennial surface water, which takes up all of central and western Botswana, in addition to areas of South Africa, Namibia, Angola, Zimbabwe and Zambia. kelyphyte An alteration rim on the surface of (pyrope) garnets in kimberlite resulting from reaction with kimberlite magma at depth or phase transformation reactions in peridotitederived pyrope garnets. kimberlite An alkaline ultramafic igneous rock that is generated at great depths in the earth and emplaced at the surface in pipes (diatremes), dykes or sills. The principal source of primary diamonds. KIM Kimberlite Indicator Mineral: pyrope garnet, eclogitic garnet, picro-ilmenite, chromite and chrome diopside. These are distinctive resistive minerals which occur in kimberlite in much higher concentrations than diamond, and which can be found in streams and soils and traced back to their kimberlite source, thus acting as pathfinders for diamond. The chemical compositions of garnet, ilmenite and chromite are related to the diamond potential of their source kimberlites, thus their mineral chemistry can provide an initial, non quantitative, grade prognosis. kriging A mathematical technique which uses spatial statistics to calculate estimations of mineral resources. LDD Large diameter drilling. diameter >15" lamproite A peralkaline volcanic or subvolcanic rock of mafic to ultramafic composition. Rarely, lamproite contains diamonds in economic quantities. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 Drilling of non-cored holes of 73 lherzolite An ultramafic igneous rock containing the mineral olivine, clinopyroxene and orthopyroxene. Lherzolite is though to be a major constituent of the Earth’s upper mantle. limestone A sedimentary rock containing at least 50% calcium or calcium-magnesium carbonates. lineament A significant linear feature of the earth’s crust. lithosphere Mass of the mantle attached to the base of the crust that has a geological history related to that of the overlying crust, and that is cold and rigid relative to the deeper parts of the mantle. loam sampling Sampling the soil profile to recover resistant minerals. In the case of diamond exploration, loam sampling is intended to recover kimberlite indicator minerals. luminescence intensity(li) Measure of the fluorescence of diamond when bombarded with X-rays. The fluorescence is caused by impurities or crystallographic dislocations in the diamond. Ma Million years. mafic Descriptive of rocks composed dominantly of magnesium and iron rock-forming silicates. magmatic Rock formed from crystallization of molten magma; an igneous rock. A descriptive of some kimberlite types which have crystallized without exploding. magnetic survey A geophysical survey which measures variations in the earth’s magnetic field caused by differences in the magnetic susceptibilities of underlying rock. Kimberlite may be detected by this method, as its susceptibility may be higher or lower than surrounding rock types. mantle The layer of the earth between the crust and the core. The upper mantle, which lies between depths of 50 and 650km beneath continents, is the principal region where diamonds are created and stored in the earth. Measured Resource A Measured Mineral Resource is that part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics are so well established that they can be estimated with confidence sufficient to allow appropriate application of technical and (Measured Mineral Resource) Lemphane Project th NI 43-101 Technical Report – 28 October 2010 74 economic parameters, to support production planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough to confirm both geological and grade continuity. (CIM definition). metamorphism Alteration of rock and changes in mineral composition, most generally due to increase in pressure and/or temperature. macrodiamond Definitions vary, but a diamond which would be recovered in a full scale mine plant. Now generally taken as >0.85 mm in size. “microdiamond” A diamond <0.5 mm in size, although definitions vary. Usually considered to be of no commercial value and too small to be recovered in a full scale mining operation. mobile belt An elongate belt in the earth’s crust, usually occurring at the collision zone between two crustal blocks, within which major deformation, igneous activity and metamorphism has occurred. ore dressing Another term for mineral processing. The process of recovering the valuable minerals from an ore. orogeny A deformation and/or magmatic event in the earth’s crust, usually caused by collision between tectonic plates. Palaeozoic An era of geologic time between the Late Precambrian and the Mesozoic era, 545 Ma to 251 Ma ago. paragenesis The origin of a mineral in the context of associated minerals and their common history. petrography The description and classification of rocks. Percussion drilling Drilling by means of an air hammer which breaks the rock into chips which are brought to surface by air circulation. Precambrian Pertaining to all rocks formed before Cambrian time (older than 545 Ma). Lemphane Project th NI 43-101 Technical Report – 28 October 2010 75 Probable Reserve (Probable Mineral Reserve) Proven Reserve (Proven Mineral Reserve) A Probable Mineral Reserve is the economically mineable part of an Indicated, and in some circumstances a Measured Mineral Resource, demonstrated by at least a Preliminary Feasibility Study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified. (CIM Definition) A Proven Mineral Reserve is the economically mineable part of a Measured Mineral Resource demonstrated by at least a Preliminary Feasibility Study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction is justified. (CIM Definition). Proterozoic An era of geological time spanning the period from 2 500 Ma to 545 Ma before present. pipe When referring to kimberlite, a synonym of diatreme. PL Prospecting Licence pyrope garnet A ruby-coloured garnet, Mg3Al2(SiO4)3, common in deepseated ultramafic intrusive rocks and common as a xenocryst in kimberlite. RC drilling Reverse circulation drilling. A percussion drilling technique in which the sample is brought to surface by air and/or water through the centre of the drill pipe. Used when accurate sampling is required as the method minimizes cross contamination of samples. retroarc foreland basin An orogenic basin that forms on the overriding plate of a subduction plate boundary. schist A crystalline metamorphic rock having a foliated or parallel structure due to the recrystallisation of constituent minerals. SAMREC The South African code for the reporting of exploration results committee Lemphane Project th NI 43-101 Technical Report – 28 October 2010 76 slimes The term for a mixture of undersize material and water which is removed from crushed ore during processing. spinel A group of oxide minerals of various compositions, (Mg,Fe,Mn)(Al,Fe,Cr)2O4, commonly occurring as an accessory in basic igneous rocks. stream sediment sampling The collection of samples of stream sediment with, in diamond exploration, the intention of looking for kimberlite indicator minerals or diamonds. strike Horizontal direction or trend of a geological structure. Tertiary (System) The rocks formed between the end of the Cretaceous at 65 Ma and the start of the Quarternary at 1.7 Ma. tonne A metric tonne, 1,000 kg tectonic Pertaining to the forces involved in, or the resulting structures of, movement in the earth’s crust. type IIa diamond Very pure type of diamond containing very little nitrogen. Type IIa diamonds may have higher values than other stones, but have much lower luminescence under Xrays, which makes them more difficult to recover using X-ray technology. volcaniclastic Rock formed by exploding magma in a volcano. Volcaniclastic kimberlite is common in kimberlite pipes. ultramafic Igneous rocks consisting essentially of ferromagnesian minerals with trace quartz and feldspar. variogram In spatial statistics, a graph which relates the variance of the difference in value between pairs of samples to the distance between them. Allows the weighting of a sample value in terms of its distance from the point where an estimate of sample value is required. xenocryst Applies to mineral crystals in igneous rocks that are foreign to the body of rock in which they occur. Very common in kimberlite, with diamond being an example. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 77 X-ray machine Diamond recovery technology utilizing the fact that diamonds fluoresce and to some degree phosphoresce when exposed to X-Ray radiation. Light emitted from diamonds which have been excited by X-rays is detected and converted into electrical signals. Such signals (after suitable amplification and processing) trigger an ejection device which physically separates the diamond from the rest of material fed through such a sorting machine. xenolith A piece of another pre-existing rock within an igneous intrusion. Very common in kimberites. Lemphane Project th NI 43-101 Technical Report – 28 October 2010 78