Design and Construction Planning Process Strongsville City Schools

Transcription

Design and Construction Planning Process Strongsville City Schools
Design and
Construction
Planning Process
Strongsville City Schools
THANK YOU.
OUR TEAM
•  50+ years experience
•  Headquartered in Akron, Ohio
•  Full-service A&E firm
•  Over 400 professionals
•  Employee owned
OUR TEAM
MARK SALOPEK
RODWELL KING
GPD GROUP
PRINCIPAL-IN-CHARGE
GPD GROUP
PROJECT MANAGER
Monitors progress, quality
and client satisfaction
Develop program and design,
Monitor schedule and budget
Follow construction
OUR TEAM
OFCC
Ohio Facilities
Construction Commission
STRONGSVILLE
City School District
CONSTRUCTION
MANAGER
GPD GROUP
Architectural
Planning
OVERSIGHT COMMITTEE
•  Mayor Tom Perciak
•  Mike Catan
•  Mike Kalinich
PROGRAM SUMMARY
Project
Cost
New 6-8 Middle School
$46,009,242
Includes 800 seat auditorium
Middle School Football Field and Track
High School Renovations
Includes electrical, HVAC, lights, windows, parking lots, roofs, technology and more
Transportation Renovations
Includes replacing the driveway, parking lot and the roof over buildings #2 and #3
Renovations to Preschool
Includes completing the activity area and technology upgrades
$656,742
$26,047,476
$2,483,647
$250,000
Renovations to Elementary Schools
$3,500,000
Abate and Demolish
Allen Elementary School
Albion Middle School
Center Middle School
$382,046
$596,896
$1,073,951
Includes technology and critical repairs
Grand Total
$81,000,000
PROGRAM
IMPLEMENTATION PROCESS
Enrollment
Projections
Validate
Educational
Standards/
Adequacy
Facility
Programming/
Future Needs
Facility
Condition
Assessment
Develop
Concept Plans
Identify Costs
Final
Implementation
Plan
PROGRAMMING
DEVELOPMENT PROCESS
CPT Meetings
(Community Planning Team)
Strongsville
POR
Final POR
•  Strongsville City Schools
and City
•  Principal
•  Key Building Leadership
•  Teachers
•  Parents
•  Community Representatives
•  Community Partners
•  Students
Program of
Requirements
Site
Specific
Block Planning
PROGRAMMING
DEVELOPMENT PROCESS
Community
Meeting #1
Orientation
Education
Outline
Typical POR
Recruit CPT
Members
CPT/SCS
Meetings
Meet with
Staff and
Community
Planning Team
to discuss
Programming
Options
Community
Meeting #2
Presentation
of Planning
Option(s),
Budget and
Schedule
Consensus on
Community
Programming
SCS
SCS
GPD Group
GPD
GPD
Communities
Community Planning Teams
CPT
Strongsville City Schools
COMM
PROGRAM OF
REQUIREMENTS
OHIO SCHOOL DESIGN
MANUAL
MIDDLE SCHOOL CLASSROOM FEATURES
•  Student Desks / Tables
and Chairs
•  Computer Workstation
•  Teacher Desk and Chair
•  Casework
•  Wireless Connectivity
OHIO SCHOOL DESIGN
MANUAL
TECHNOLOGY
•  Telephone and Intercom
•  Interactive Projectors
•  Full Wireless Coverage
for One-to-one Computing
•  Individual Classroom
Sound Reinforcement
Note: OFCC does not fund computers
SITE STANDARDS
•  Maximized Green Play Space and Sports Facilities
•  Safe Bus Loading
•  Separate Parent
Drop-off
•  Staff Parking
On-site Where
Possible
•  Convenient Visitor
Entrance, Parking
•  Recognizable
Front Door
MUSIC AND ART ROOMS
MEDIA CENTER
ASSEMBLY SPACES
PE and Athletics
Auditeria / Cafetorium
FLEXIBLE CORE OF
SUPPORT FOR:
•  Parent Services
•  After School
Programs
•  Athletics
ALIGNING SPECIAL NEEDS WITH
THE STANDARDS-BASED MODEL
•  Flexibility Provided by the Standards
Based Model
•  Needs of Community
•  Inclusion of Special Programs
•  Inclusion for Students With
Special Needs
®
LEED
•  Sustainable site planning
•  Safeguarding water and water
efficiency
•  Energy efficiency and renewable
energy
•  Conservation of materials and
resources
•  Daylighting
•  Indoor environmental quality
BUILDING EXTERIORS
?
STRONGSVILLE
BUILDING INTERIORS
Classroom
Media Center
BUILDING INTERIORS
Gymnasium
Cafeteria
BUILDING INTERIOR
FEATURES
Lighting
Acoustics
Furniture
Wayfinding
Color
EXISTING SITE
MIDDLE SCHOOL
SITE PLAN OPTIONS
MIDDLE SCHOOL
SITE PLAN OPTIONS
MIDDLE SCHOOL
DISTRICT RENOVATIONS
East Community Learning Center
Lakewood High School
Brunswick High School
PROJECT PLANNING
MILESTONES
•  Program of Requirements (2-3 months)
•  Schematic Design (3-4 months)
•  Design Development (4-5 months)
•  Construction Documents (4-5 months)
•  Bid Packages (2 months)
•  Ground Breaking
•  Construction (18-24 months)
•  Dedication
NEXT STEPS
•  We Need Volunteers!
– Community Planning Team Members
– Roll-Up-the-Sleeves Meetings
•  Site Visits
•  Next Meeting: TBD
QUESTIONS