mas errázuriz ltda. – aveng grinaker lta. consortium

Transcription

mas errázuriz ltda. – aveng grinaker lta. consortium
MAS ERRÁZURIZ LTDA. – AVENG GRINAKER LTA.
CONSORTIUM
SINKING VENTILATION SHAFTS CONSTRUCTION
CHUQUICAMATA SUBTERRÁNEA PROJECT
Expositors
Sr. Iván Pérez P.
Business Manager
Mas Errázuriz Ltda.
Sr. Louis Germishuys
International Business Manager
Aveng Grinaker LTA
Isometric View of the Project
Consortium Organization
MAS ERRAZURIZ LTDA. – AVENG GRINAKER LTA.
TECHNICAL ADMINISTRATIVE COMMITTE
MAS ERRAZURIZ LTDA. – AVENG GRINAKER LTA.
SITE MANAGER
ADMINISTRATIVE LEADERSHIP
MAS ERRÁZURIZ
TECHNICAL LEADERSHIP
AVENG GRINAKER LTA
Risk Control, Environmental and Occupational Health Program
DOCUMENTATION
Analysis and legal adjustment and Grinaker experience
Communication, participation and consultation
 Dissemination
 Incident Indicator Report
 Behavior Improvement Program
 Risk Assessment
o Documentation and control (Quality Manual)
o Preparation and response in emergency cases
 Preparation of procedures
 Formation of Committees
o
o
VERIFICATION AND CONTROL
Measurement and monitoring of the SSOMA program performance.
 Monthly review through the Administrative Technical Committees on site
 Monthly reports to the senior management (Directory)
o Evaluation of legal compliance
o Accident Investigation
o Non compliances and corrective actions
 Findings Management System
o Internal Audit Program
o Leadership Review: evaluate program SSOMA effectiveness
o
Human Resource Management Plan
The Human Resource Management Model is
based on a mixed organization of Chilean and
southafrican personnel. Aveng Grinaker’s
Technical Leadership involves training and
transferring knowledge to Mas Errázuriz staff, by
training carried out in current Aveng Grinaker
works in South Africa or Zambia and on-site
instruction for six months periods in previously
defined positions. The organization follows similar
criteria.
CHILEAN/SOUTHAFRICAN MIXED ORGANIZATION
• RECRUITING AND SELECTION
• TRAINING IN CHILE AND SOUTHAFRICA
• TRAINING AND DEVELOPMENT PLAN WITH COMPETENCE
CERTIFICATION
• PERFORMANCE MANAGEMENT
• QUALITY OF LIFE AND SOCIAL RESPONSIBILITY
• INTERNAL AND EXTERNAL COMMUNICATIONS
Direct Personnel
DIRECT PERSONNEL AND STRUCTURAL
MECHANICAL ASSEMBLIES
Capataz de Montajes
Maestro Primera de Montajes
Maestro Segunda de Montajes
Soldadores Plancha
Ayudantes de Montajes
Maestro Primera Mecánico
Maestro Primera Eléctrico
Ayudante Mecánico
Ayudante Eléctrico
DIRECT PERSONNEL AT THE FACE
Jefe de Turno Pique
Operadores de Perforadoras
Ayudantes Mineros
DIRECT PERSONNEL AT THE PLATFORM
Jefe de Turno Plataforma
Campanero de Plataforma
Ayudantes de Minería (Plataforma)
DIRECT PERSONNEL ON BENCH OR SURFACE
Minería: Ayudante Minería (Banco)
Operador de Grúa Torre
SUPPORT SERVICES
Jefe de Turno Minería
Mecánicos
Ayudantes
Eléctrico Servicios
Mecánico Servicios
Soldadores
PERSONAL TRAINING FOR 6 MONTHS
Jefe de Turno Minería General
Jefe de Turno Plataforma
Jefe de Turno Pique
Operador Compuerta de Superficie
Operador de Clam Shell
Operador de guinche
Mecánico de Jumbo
Critical Shaft Sinking Safety Rules
1.
Avoid Falling Objects at all Cost
2.
Follow procedures for Working at Heights
3.
Safety Slings on All Tools
4.
Follow Proper Barring Technique & Procedure
5.
Support Installed to Standard
6.
Follow Correct Explosive Handling & Blasting Procedures
7.
Ensure Right Equipment for the Job
8.
Follow procedures – No Short Cuts
9.
Personal Protective Clothing
10. Behavioural Based Safety (BBS) – Your and your colleague’s safety
Shaft Sinking Phases
1.
Mobilisation
2.
Design & Planning
3.
Site Establishment
4.
Collar Construction
5.
Pre-Sink
6.
Change over to Main Sink
7.
Main Sink
8.
Remove Sinking Services & Clear Site
1. Mobilisation
1.
Mobilisation of Equipment
2.
Forwarding & Clearing of Equipment
3.
Recruitment of Workforce
4.
Sinking Training
5.
Approvals and Permits (legal requirements)
2. Design & Planning
Type of Drawing
Number of Drawings
Hours Required
General Arrangement
5
110
Infrastructure & Reticulations
30
1150
Collar & Pre-Sink
20
720
Main Sink
35
1100
Sinking Headgear
25
1100
Sinking Equipment
15
600
Winders
15
550
Management & Administration
400
3. Site Establishment
1.
Winder Foundations
2.
Batch Plant
3.
Workshops
4.
Stores
5.
Offices
6.
Services Reticulations
7.
Manufacture in Chile
4. Collar Construction
1.
Survey – setting out
2.
Back Actor
3.
Support
4.
Shutter
5.
Concrete
5. Pre-Sink
1.
Drilling
2.
Support
3.
Mucking
4.
Hoisting
5.
Pre-Sink Stage
6. Change Over to Main Sink
1.
Remove pre-sink stage
2.
Lower main sink stage
3.
Collar Steel
4.
Headgear
5.
Winders
6.
Fans
7. Main Sink
1.
Drilling
2.
Mucking
3.
Support
4.
Concrete Lining
5.
Services
8. Remove Sinking Services & Clear Site
1.
Remove all sinking infrastructure
2.
Hand over of site to client
3.
Permanent Fan Construction to commence
Resumen
Duración
m3
Excavados
Consumo
Explosivos
m3 Totales de
Hormigón**
Consumo Eléctrico
Estimado
Dotación Total
Promedio
Mes
m3
Kg
m3
KWh
Trabajadores/Mes
Alt 1 Concurrent
24.0
117,078
316,112
27,478
71,215,200
219
Alt 1 in line
30.0
idem
idem
idem
89,019,000
213
Alt 2 Concurrent
41.0
234,022
631,859
55,041
121,659,300
230
Alt 2 in line
52.0
idem
idem
idem
154,299,600
225
Alt 3 Concurrent
24.0
123,891
334,505
31,064
71,215,200
230
Alt 3 in line
30.0
idem
idem
idem
89,019,000
223
Alternativa
Pique 1
Pique 1 + Pique 2
Pique 1 + Collar 2
Site Preparation and Civil Works
Site Preparation and Civil Works
Site Preparation and Civil Works
Pre-Sinking
Pre-Sinking
Main Excavation
Main Excavation
Blast Diagram
Phase : Jumbo Perforation
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Blast
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Ventilation
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Dump
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Fortification
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : removal of perforation equipment
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Box Lining
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo