Snow and Ice Control Plan 2015-2016
Transcription
Snow and Ice Control Plan 2015-2016
CITY OF DIEPPE SNOW AND ICE CONTROL PLAN TABLE OF CONTENTS FORWARD AND DISCLAIMER 1.0 INTRODUCTION ....................................................................................................................3 1.1 General .............................................................................................................. 3 1.2 Aim .................................................................................................................. 3 1.3 Mission ………………………………………………………………………..3 1.4 Policy ................................................................................................................ 3 2.0 RESPONSIBILITIES ..............................................................................................................4 3.0 PROCEDURES.........................................................................................................................4 4.0 SNOW PLOWING ...................................................................................................................5 4.1 Objective .......................................................................................................... 5 4.2 Initial operation ................................................................................................. 5 4.3 Road Hazards .................................................................................................... 6 4.4 Exchanged Routes ............................................................................................. 6 4.5 Sidewalks .......................................................................................................... 6 4.6 Walking Trails ................................................................................................. 7 4.7 Parking Lots ...................................................................................................... 8 4.8 Widening on Dieppe Boulevard........................................................................ 8 4.9 Damage Due to Snow Plowing ......................................................................... 9 4.10 Special Provisions for Mobility-Impaired Persons ......................................... 9 5.0 SNOW REMOVAL ................................................................................................................10 5.1 Snow Blowers ................................................................................................ 10 5.2 Fire Hydrants .................................................................................................. 10 5.3 Snow Dumps ................................................................................................... 10 6.0 SALTING / SANDING OPERATIONS ...............................................................................11 6.1 Storage ........................................................................................................... 11 6.2 Initial Operation .............................................................................................. 11 6.3 Brine ................................................................................................................ 11 6.4 Sand................................................................................................................. 11 6.5 Accidental Salt Spills ...................................................................................... 12 6.6 Critical Areas .................................................................................................. 12 6.7 General Operations ......................................................................................... 12 APPENDIX A – Level of Service for Roadway Types…………………………………………………….13 APPENDIX B – Variable Application Rates for Road Salt………………………………………………...14 APPENDIX C – Street Classification Map…………………………………………………………………15 APPENDIX D – Snow Plowing Map……………………………………………………………………….16 APPENDIX E – Parking Lots……………………………………………………………………………….17 APPENDIX F – Place 1604 Winter Maintenance Map and Fire Station (500 Gauvin Rd.)………………..18 APPENDIX G – Dieppe Aquatic and Sports Centre and Operations Centre Maps………………………...19 APPENDIX H – Sidewalk Snow Clearing Map…………………………………………………………….20 APPENDIX I – Walking Trails Snow Cleaning Map………………………………………………………21 APPENDIX J – Snow Dump………………………………………………………………………………..22 APPENDIX K – Snow and Ice Control Equipment List……………………………………………………23 APPENDIX L – Snow Tips…………………………………………………………………………………24 Version no. 8 Last revision: November 2015 Page 1 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Disclaimer This plan is based on normal winter weather conditions, reliability and availability of resources both human and physical. The City does not guarantee a level of service under abnormal or extreme winter conditions nor in the event of a work stoppage. Version no. 8 Last revision: November 2015 Page 2 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN 1.0 INTRODUCTION 1.1 General The City of Dieppe currently plows and salts all public streets within its City limits. All of these streets are asphalted, with the exception of new gravelled subdivision streets not yet asphalted, and a few kilometres of streets that are chip sealed. The City also clears the snow off sidewalks, parking lots as well as all fire hydrants and some walking trails. The municipality has experienced rapid growth in recent years, and the maintenance of streets and sidewalks is adjusted each year to take into account the new areas added. The population of the City of Dieppe is currently estimated at over 26 000. 1.2 Aim To provide an effective and efficient level of service for snow and ice control in the City of Dieppe and to insure that this level of service is well understood by operators, supervisors, senior staff, City Council and the public. 1.3 Mission To provide a consistent level of snow and ice control in the City of Dieppe. 1.4 Policy The City of Dieppe provides snow removal and ice control on city streets and sidewalks according to pre-established priorities. Streets are prioritized based on their importance in the overall transportation network. Priority 1 streets are arterial and heavily travelled collector streets. Priority 2 streets are collectors and some heavily travelled local streets. Priority 3 streets are typically local streets. Higher priority streets are serviced earlier in the storm response, and are given higher level of service. Version no. 8 Last revision: November 2015 Page 3 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN 2.0 RESPONSIBILITIES 2.1 The superintendent of the transportation division is responsible to the manager of the public works department, within the services to the Community for snow and ice control in the City of Dieppe. 2.2 The superintendent or his designate is responsible for ensuring the winter storm response is in accordance with this Snow and Ice Control Plan. The superintendent, along with his foremen, will be familiar with this plan and will conduct winter maintenance tasks to achieve and maintain safe driving and ease of traffic flow. 2.3 The general procedures followed will be in accordance with established procedures. a) Priority 1 - Arterials and heavily travelled Collectors b) Priority 2 - Collectors and heavily travelled Locals c) Priority 3 - Local Streets Please remember, you may not live on a priority one street but you probably drive on one. It is to everyone's benefit that these high volume streets are serviced first. 2.4 Evening, night and weekend crews play a critical role in storm response. While they ensure the Snow and Ice Control Plan is followed, they are expected to exercise judgment and respond to changing conditions. 2.5 The operators of all snow control and winter maintenance vehicles and equipment will operate in a safe and efficient manner at all times. They are responsible for ensuring their vehicles and equipment are in a safe and mechanically ready state. Operators will also be responsible to ensure that their route is completed in accordance with the Snow and Ice Control Plan. The operators will report to their immediate supervisors if there are any problems or difficulties with their equipment, both at the start of or during the storm response. 3.0 PROCEDURES Specific policies and procedures have been developed over a number of years and are based on experience, available resources and the expectations of Council and the community. Procedure for Snow and Ice Control During Snowfall Conditions 1. A decision by the appropriate foreman or crew chief will be made concerning what type of vehicle and how many will be used to clear snow and ice from the streets during snowfall events. For example, a light snowfall may require salt Version no. 8 Last revision: November 2015 Page 4 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN trucks only. Whereas if snowfall increases, additional vehicles may be necessary – this could include loader plows or truck plows. Heavy snowfall may require all available vehicles and equipment. 2. Ice conditions by themselves or combined with snow, may require special operations. This may include extra salting/sanding of intersections, heavily traveled routes and/or hills. 3. Foremen will exercise judgment on what types of vehicles and equipment will be used with each situation. Factors that contribute to these decisions includes light snow, heavy wet snow, ice, ice pellets, time of day, day of week, etc. Other factors include experience of personnel, available equipment, safety concerns, etc. 4.0 SNOW PLOWING 4.1 Objective The snow plowing objective is to plow all streets to the travelled surface width within eight (8) hours of storm ending for snowfalls up to 30 centimetres. For snowfalls above 30 centimetres, the objective is to clear the snow as soon as available equipment and personnel will allow. The amount of snow received during each event and the type often varies (wet/heavy, dry/powder, combinations of each) and this can either positively or negatively effect the times stated above. Levels of service for specific types of roadways are provided in Appendix A. The street classification map is provided in Appendix C. 4.2 Initial Operation Initially, salt is spread on all arterial and some collector streets as storm begins. Brine will also be spread on local streets; this procedure will be done during the 24 hours before the expected snow fall. This step eliminates the freezing of the first snowfall and makes the “bare pavement” goal more achievable. In many cases of light snowfall, this is all that is required. Upon the accumulation of four to eight centimeters of snow, the salt truck operators commence plowing and the other plow operators are called in. Version no. 8 Last revision: November 2015 Page 5 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN For snow plowing operations, the City is divided into eleven (11) zones with the equipment assigned to each zone being the best suited for the anticipated road conditions (see Appendix D for drawings showing the plowing routes of each zone). Appendix K provides a list of the equipment available for snow and ice control. Plowing continues on these routes until the snow has stopped falling and all the streets are plowed. As well, the crews normally make a pass over the streets after the snowfall ends to widen the streets and clear the intersections. However, depending on the length of the storm or the build-up of snow on the edge of the street, it is sometimes necessary that this widening take place after the crews have rested. 4.3 Road Hazards Plowing on municipal streets is not the same as plowing on the open road. Municipal plowing is usually at slower speeds. The streets are shorter between intersections and there are many hazardous structures such as manhole covers, valve boxes, railway tracks, etc., which often project above the street surface. In the fall the work crews make adjustments to eliminate these hazards but they often reappear through frost action. Mountable curb is also difficult to locate during the snowstorms; wood markers are therefore placed in the fall at strategic locations to assist the operators to avoid lawn damage. In order to familiarize the equipment operators with their routes and these hazards, the operators in the various zones will travel their districts with their supervisor prior to snowfall. This process also increases their productivity and minimizes equipment damage. 4.4 Exchanged Routes Each year, the City exchanges plowing with the New Brunswick Department of Transportation. A section of Champlain Street, a section of LeBlanc Road, a section of Melanson Road and Arsenault Road, located outside the City, are maintained through the winter by the City. This arrangement has been in practice for several years and works to the benefit of the City and the Province, and gives very good service to the residents of these areas. 4.5 Sidewalks Sidewalks are plowed and sanded according to the following priorities: Priority 1 1. sidewalks on heavily traveled arterial streets 2. sidewalks near school zones 3. Place 1604 (see Appendix F for sidewalks in Place 1604 that will be cleared) Priority 2 1. sidewalks in Uptown Dieppe area and Dieppe Aquatic and Sports Centre 2. sidewalks on less travelled arterial streets and collector streets 3. remaining sidewalks Version no. 8 Last revision: November 2015 Page 6 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Note that 2.4 km of sidewalks will not be cleared from snow. That section is a Priority 2 located on Dieppe Blvd west side, between Melanson Road and Chartersville Road. See Appendix H for the Sidewalk Snow Clearing Map. The objective is that all Priority 1 sidewalks will be cleaned of snow within 24 hours from the end of the snowfall for snow storms up to 30 centimetres. When we receive larger snow accumulations, it may take as long as 72 hours depending on the type of snow (wet and heavy, powder, etc), the previous accumulations, equipment and staff availability. All sidewalk in Priority 2 will be cleaned from snow in regular hours after P-1 sidewalks. The objectif is to clean P-2 sidewalks 3 days after the P-1 sidewalks are cleaned. The sidewalks around Place 1604 which are covered with compressed concrete pavers as well as the granite staircase next to City Hall will be maintained with salt. Other sidewalks will receive sand to improve traction. Note: It is not the City’s intention to have bare sidewalks during the winter season. Snow will be removed and sand provided to improve traction. 4.6 Walking Trails The Culture, Leisure and Community Life department removes fallen snow along 23.6 km of trails following a snowstorm. Trails are cleared according to their use and on the basis of priority: Priority 1 - Trails near schools - Trails connecting school bus stops Priority 2 - Trail along the marsh, extending up to Pointe-aux-Renards - Trail along Dieppe Boulevard - Other trails located in various subdivisions Please note that there are 11.4 km of trails that are not cleared, the most important ones being Bonaventure Park, Pointe-aux-Renards in Dover, Dover Community Park and other minor connections to neighborhood parks. See Appendix I for walking trails snow clearing maps. The objective is to have the P-1 cleared of snow in the 24 hours that follow a snowfall of 30 cm or less. When the snow accumulation is greater, snow clearing can take up to 72 Version no. 8 Last revision: November 2015 Page 7 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN hours depending on the type of snow (wet and heavy, fluffy, etc.), previous snowfall, available resources and equipment. The P-2 trails will be cleared after P-1 trails are cleared and during regular work hours. The objective is to clean the P-2 trails 5 days after the P-1 trails are cleaned. Snow removal and upkeeping of trails at the Rotary St-Anselme Park will be done in the same timeframe as in the P-1, 24 hours following a snowstorm of 30 cm or less. Note: It is not the City’s intention to have all the trails cleared during the winter season. Snow will be removed and sand provided to improve traction. 4.7 Parking Lots The objective for City-owned parking lots of Place 1604 is to clear the snow within four (4) hours from the end of the snowfall for snow storms up to 30 centimetres. Snow will be stockpiled at strategic locations in the parking lots to minimize lost parking spaces. Snow removal operations from the parking lots in Place 1604 during the day and evening are expected to be extremely inefficient, not only because of parked cars and traffic conflicts in the work areas, but also because of delays experienced traveling to and from the snow dumps. Therefore, snow removal operations will be performed at night. In general the goal is to have the snow hauled from Place 1604 parking lots and the sidewalks next to the parallel parking areas along Champlain and Marché Streets within 96 hours of the storm end. As a general rule, other parking lots are cleared after streets have been plowed. The objective is that other parking lots will be cleared within eight (8) hours of the storm end. Snow will be stockpiled at strategic locations in the parking lots to minimize lost parking spaces. (see Appendix E for the list of parking lots). 4.8 Widening on Dieppe Boulevard and Amirault Street Due to stopping sight distance requirements, the accumulation of snow must not exceed 0.38m in height on each side of certain intersections. This requirement applies for a width of 2.0m back from the face of the curb and a distance of 50 metres on each side of the intersection along Dieppe Boulevard. The intersections with these requirements are: Englehart Street/Dieppe Boulevard Samuel Court/Dieppe Boulevard Murray Street/Dieppe Boulevard Aucoin Street/Dieppe Boulevard Version no. 8 Last revision: November 2015 Page 8 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN These areas will be checked after each snowfall by the foreman. If snow accumulation has exceeded the 0.38m requirement, the objective is to clear or remove the snow within 48 hours from the end of the snowfall. These areas are shown on the maps in Appendix D. 4.9 Damage Due to Snow Plowing Public works and engineering staff are alerted to damages due to snow removal by other City employees, by a member of the public, or through routine checks. 1. Lawn Damage Information regarding lawn damage due to snow removal is relayed by public works and engineering dispatch to the foreman for investigation and scheduling of repairs. The department will maintain a list of properties with lawn damage, and the repairs will be scheduled to begin in May (when growing medium is available). The foreman ensure that employees who perform this work are trained for, or experienced in, the proper procedure for repairing lawn damage, and appropriate precautions are taken to ensure the safety of City employees and the public. Every effort is made to minimize disruption in the work area. 2. Mail Box Damage The City of Dieppe accepts no liability for any damage to mailboxes or associated structures. 4.10 Special Provisions for Mobility-Impaired Persons The operators of snow clearing equipment will take special care when working on or around sidewalk to ensure that all snow is cleared between the street and sidewalk at crosswalks. Operators will also ensure that no snow is left on the sidewalk when clearing snow around fire hydrants. For bus shelters, the objective is to clear the snow inside, between the street and the sidewalk at all bus shelters within 24 hours from the end of snowfall for snow storms up to 30 centimetres. The objective is that snow will be cleared around all traffic light poles to give access to pedestrian push buttons to wheelchairs within 24 hours from the end of snowfall for snow storms up to 30 centimetres. Version no. 8 Last revision: November 2015 Page 9 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN 5.0 SNOW REMOVAL After the initial snow plowing operations are completed, snow could be removed, depending on conditions, from the sides of selected streets but primarily in the downtown core and the Uptown area. This is accomplished by loading the snow into trucks and hauling it to specifically identified locations for disposal (snow dumps), or blowing the snow off the street and sidewalk to the adjoining area. City staff and equipment as well as hired equipment and trucks are utilized for this operation. Also, if accumulations warrant, snow could be hauled from major intersections to improve sight distances. There are not enough resources available to remove snow from the sides of all city streets, however if deemed necessary for public safety reasons, streets can be widened by blowing the snow in back of the sidewalks, curbs or ditches. 5.1 Snow Blowers During removal operations, in the downtown core and elsewhere, the City windrows the snow along the curb lane of the street and the snow blowers immediately load and dispose of this snow in order to minimize the snow banks the pedestrians must navigate to cross these busy streets. 5.2 Fire Hydrants The clearing of snow around the City’s fire hydrants begins after the plowing of streets is completed and the clearing of sidewalks is under way. Fire hydrants will not necessarily be cleaned of snow after each snow storm. The superintendent, in cooperation with his foremen, will decide if the accumulation of snow around the fire hydrants and/or the snow bank along the street in front of the fire hydrant warrants the clearing operation to be activated. The objective is to clear the snow from fire hydrants according to priorities established by the Fire Department and as soon as available equipment and personnel will allow. For snow clearing around fire hydrants, the City uses City equipment (depending on availability) and hired equipment. In low density housing areas, the City will encourage residents to “Adopt a Hydrant”. Citizens will be asked to voluntarily clear snow from fire hydrants serving their neighborhood. Such efforts by the citizens are in their own best interest as it affords better fire protection to their own property as well as their neighbours. 5.3 Snow Dumps The City will maintain three (3) snow dumps for snow disposal, namely the Copp Street field (next to the soccer field), at the end of Benjamin Street and east of Rufin Street, near the Operations Centre. In extreme winter conditions, other auxiliary dumps will be used as needed; as identified on the map illustrated in Appendix J. Version no. 8 Last revision: November 2015 Page 10 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Each of the snow dump sites used through the winter will be cleaned of any garbage and debris once the snow has melted in the Spring. 6.0 SALT, BRINE, AND SAND OPERATIONS Sodium chloride remains the chemical of choice for snowstorm situations. The City of Dieppe has a Salt Management Plan that was adopted by Council. 6.1 Storage All salt is stored indoors in a weather resistant salt storage building at the Operations Centre, specifically designed for salt storage. The site of the salt dome is constructed in such a way that water flows away from the building. The salt dome has an impermeable floor that protects migration of salt into the ground. It has the capacity to store approximately 3,000 tonnes of salt. After each salt spreading operation, any unused salt is returned to the salt storage building for storage. All sand is blended with salt to prevent it from freezing, and is stored in the same building as the salt, in a separate area. 6.2 Initial Operation As previously mentioned, City streets are salted at the commencement of a snowstorm or freezing rain. Salt trucks are also dispatched for salt spreading at the end of the storm to assist in achieving bare pavement. 6.3 Brine Brine will be spread on local streets in the 24 hours period preceding an expected snowfall. Composed of salt and water, brine helps prevent ice formation on the roadway 6.4 Sand In Dieppe, sand is used on the paved streets as the temperatures drop below the levels of effectiveness for salt. However, when the temperatures do drop below these levels, the streets are sanded in the same manner, as they would have been salted. Sanding rates tend to be higher than salt because it is used as an abrasive rather than a de-icer. Sanding impacts negatively on street cleanliness, sewer cleaning requirements and air quality. 6.5 Accidental Salt Spills If a significant amount of road salt is spilt, such as from an overturned truck, Environment N.B. shall be advised by calling one of the following numbers: daytime 856-2374, or nighttime 1-800-565-1633, where an inspector is on call 24 hours/day, 7 days/week. Public Works’ staff will cleanup the site as soon as possible and reuse as much of the salt as possible. Version no. 8 Last revision: November 2015 Page 11 CITY OF DIEPPE 6.6 Critical Areas SNOW AND ICE CONTROL PLAN During freezing rainstorms and when temperatures drop after a period of thawing, there are critical areas where vehicle movements can become treacherous and sometimes impossible. These occur at major intersections, main routes, hills, bridges and runoff areas. These critical areas are the first to be salted or sanded in the various districts. In many instances these are the only areas, which require salting and sanding. The order of priority is as follows: Arterials and collectors – salted within 3 hours. Local streets – salted or sanded within 4 to 6 hours. 6.7 General operations Levels of service for specific types of roadways are provided in Appendix A. The street classification map is provided in Appendix C. Unless otherwise specified by the superintendent, no salt is applied on chip sealed streets (example: sections of Melanson Road and LeBlanc Road, Bourque Road and Parc Drive) and on gravelled streets. Only sand is to be applied on these streets. For safety reasons, the superintendant may change this procedure. Salting rates are based on road surface temperature not ambient temperature. The brine application rate will be 100 liters per lane kilometer. Maximum operating speed for salt/sand applications is 40 km/h. Version no. 8 Last revision: November 2015 Page 12 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix A Level of service for roadways Arterial and heavily travelled collector streets receive the highest priority. These streets are plowed continuously during the snowstorm, where possible (see guidelines below). The ice control service utilizes controlled salting to maintain clear driving lanes during and following a storm, and a bare centre strip. Collectors and heavily travelled local streets are plowed after 5 cm of snow accumulation. Salting / sanding is carried out following the storm so as to maintain bare pavement full width. Local streets are plowed after 5 to 8 cm accumulation of snow; salting is carried out for ice control. The level of service accepts a snow packed street with hills, curves, intersections and hazardous areas treated with salt. Arterials and heavily travelled collectors (Priority 1) Collectors and heavily travelled local streets (Priority 2) Local Streets (Priority 3) 1. Start immediately plowing and salting at the beginning of the snowstorm. Plowing should start as soon as slush begins to form. 2. Plow continuously during storm, visibility permitting. 3. Normally plowed to bare pavement, shoulder to shoulder, within 3 to 4 hours after storm ends. 1. Plow after 5 cm of snow. 2. Salt as required during the storm. 3. Salting of the entire streets takes place after the storm. 4. Normally plowed to bare pavement, curb to curb, within 5 to 6 hours after storm ends. 1. Start plowing after 5 to 8 cm of snow. 2. Salt at intersections during the storm. 3. Salting of hills, curves, intersections and icy spots takes place after the storm. 4. Normally plowed, curb to curb, within 6 to 8 hours after storm ends. Note: The completion times in the above table are based on a snowstorm of magnitude up to 30 cm. The public works superintendent ensures that employees who perform this work are trained for, or experienced in, the proper procedure for winter maintenance (snow and ice removal), and appropriate precautions are taken to ensure the safety of City employees and the public. Version no. 8 Last revision: November 2015 Page 13 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix B Variable application rates for road salt Pave.Temp. (C) Over O Dilution potential Low Medium High -1 to O Low Medium High -4 to 1 Low Medium High -7 to -4 Low Medium High -9 to -7 Low Medium High -12 to -9 Below -12 Version no. 8 Ice/Pavement Bond No Yes No Yes No Yes Application Rate (Kg/lane Km) 25 57 28 64 31 71 Our #'s 30 60 30 60 30 70 No Yes No Yes No Yes 31 78 43 85 45 92 30 80 40 90 50 90 No Yes No Yes No Yes 48 100 51 107 54 114 50 100 50 110 50 110 No Yes No Yes No Yes 57 120 60 128 62 135 60 120 60 130 60 140 No Yes No Yes No Yes 65 142 68 150 71 156 60 140 70 150 70 160 74 163 77 170 80 178 70 160 80 170 80 180 Low No Yes Medium No Yes High No Yes A. If unbonded, try mechanical removal without chemical B. If bonded, apply material at 200kg/lKm. Plow when slushy C. Apply abrasives as necessary Last revision: November 2015 Page 14 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix C Street Classification Map Version no. 8 Last revision: November 2015 Page 15 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix D Snow Plowing Map Version no. 8 Last revision: November 2015 Page 16 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix E Parking Lots Location Place 1604 (parking lots A, B, C, D, E, F and G) Farmers’ Market (parking lots H and I) 2 fire halls (Gauvin Rd and Dieppe Blvd) Operations Centre (6 parking lots) Arthur-J.-LeBlanc Centre Centennial Arena Dieppe Aquatic and Sports Centre Airport pumping station Champlain water treatment plant Pumping station and Industrial Park reservoir Chartersville pumping station Saint-Anselme elevated reservoir Fox Creek pumping station Golf Street water treatment plant Youth House Dieppe Boys and Girls Club Dover Park (building) Dover Park (parking lot) Future Museum (building) - Amirault Version no. 8 Last revision: November 2015 Page 17 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix F Place 1604 and Fire Station (500 Gauvin Road) Winter Maintenance Maps Version no. 8 Last revision: November 2015 Page 18 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix G Dieppe Aquatic and Sports Centre and Operations Centre Winter Maintenance Maps Version no. 8 Last revision: November 2015 Page 19 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix H Sidewalk Snow Clearing Map Version no. 8 Last revision: November 2015 Page 20 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix I Walking Trails Snow Clearing Maps Version no. 8 Last revision: November 2015 Page 21 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix J Snow Dumps Map Version no. 8 Last revision: November 2015 Page 22 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix K Snow and Ice Control Equipment List Unless otherwise indicated, all equipment belongs to the City Public Works Department 4 tandem trucks with front blade and wing; also used for road salting and sanding; 6 loaders with front blade and wing (five municipal and one contractor); 1 grader with front blade and wing; 2 Vohl snow blowers to hook up to a loader – Capacity: 2,700 tons per hour; 4 sidewalk tractors with blades, blowers and sand spreaders; 1 backhoe; 1 ton truck with reversible front blade or double blade; 1 Versatile tractor with blade (or bucket) and blower and V-shape blade. Culture, Leisure and Community Life Version no. 8 1 sidewalk tractor with blade, blower and sand spreader; 1 F250 4X4 truck with reversible front blade; 1 3500 4X4 with reversible front blade 1 F150 2X4 with salt/sand spreader only; 1 skid steer; 1 versatile tractor with blade (or bucket) and blower and 1 tractor with blade (or bucket) and blower. Last revision: November 2015 Page 23 CITY OF DIEPPE SNOW AND ICE CONTROL PLAN Appendix L Snow Tips There are a few things you can do: -Sometimes it takes several passes with the maintenance equipment to completely clear the street. Wait until plowing operations are completed and you will only have to shovel your driveway once. -When you shovel your driveway, place the snow on the "downstream" side so your driveway won't be filled in the next time the plow comes by. -Gear up for winter. Keep your car well tuned, and keep adequate supplies of salt and sand on hand for your driveway. There are things you can do to help the City crews: o o o o o o o o Observe snow by-laws. Don't park overnight on any City street from December 1st to March 31st. Don't push snow from a driveway or parking lot onto a City street or sidewalk. Don't park your vehicle at the end of your driveway in a way that would impede the City equipment. To help prevent localized flooding, try to keep the catch basin adjacent to your property free from ice and snow. Please don't place garbage or garbage containers where they can be buried, damaged or interfere with snow removal operations. Avoid unnecessary spinning of tires at intersections. This practice is dangerous and is hazardous to other motorists. It also tends to "ice up" the intersections. Adopt a fire hydrant - If there is a fire hydrant in front of or near your property, you may remove the snow from around it and make it accessible for emergencies. Help us to help you. DRIVE CAREFULLY The Culture, Leisure and Community Life Department attempts to minimize the impact of snow and ice for our citizens. However, it is each motorist's responsibility to drive according to the road conditions. If it is slippery, please slow down. Version no. 8 Last revision: November 2015 Page 24