Giant foundations for the Venice floodgates
Transcription
Giant foundations for the Venice floodgates
Spring 2011 Seabed titans Giant foundations for the Venice floodgates Plus: Tottenham Court Road diaphragms Wind farming powers up Emap Inform, Emap Limited First Floor, Greater London House, Hampstead Road, London NW1 7EJ Tel: Direct dial extensions on (020) 7728 exchange: EDITORIAL Fax: 020 7728 4666 Consulting editor Adrian Greeman 4550 [email protected] Production Andy Bolton Lucien Howlett Graphics Anthea Carter 4548 DISPLAY ADVERTISING Fax: 020 7728 4666 DISPLAY ACCOUNT EXECUTIVE Olivia Horne 4529 [email protected] DISPLAY PRODUCTION MANAGER Paddy Orchard 4111 MEDIA REPRESENTATIVES Italy/Switzerland: Fabio Potesta, Mediapoint & Communications, Corte Lambruschini, Corso Buenos Aires, 8 v Piano, Interno 7, 16129 Genova. Tel: 0039 010 570 4948. Fax: 0039 010 553 0088. Email: [email protected] www.mediapointsrl.it Germany/Austria: Randolf Krings, EuroMediaConnect, Dambachtal 10, D-65193 Wiesbaden, Germany. Tel: 00 49 611 532 4416 Fax: 00 49 611 532 4519 Email: [email protected] www.euromediaconnect.com USA and Canada: Olivia Horne, as above. EUROPEAN FOUNDATIONS is published four times a year by Part of Emap Limited Printed by William Gibbons, Sussex. ISSN Number: 0017-4653 www.foundationworld.org.uk The European Federation of Foundation Contractors aims to promote the common interests of members of the federation, to improve standards of workmanship and to maintain high standards of technical competence, safety and innovation. It is also a primary objective of the EFFC to express the point of view of members to the European Commission, national governments, consulting and civil engineers, architects, contractors, professional institutions, public authorities and other interested parties in member countries or abroad. For more information contact the EFFC secretariat at: Forum Court, 83 Copers Cope Road Beckenham, Kent BR3 1NR, UK tel: +44 20 8663 0948 fax: +44 20 8663 0949 european foundations spring 2011 No 49 Spring 2011 Tunnel is preferred Fehmarnbelt option Danish politicians are supporting a e5.1bn immersed tube tunnel option for the Fehmarnbelt crossing, as proposed by Femern, the stateowned company in charge of planning the link. One of Europe’s largest-ever construction projects, the future Fehmarnbelt link is set to comprise a combined motorway and rail tunnel immersed under the Fehmarnbelt between Rødbyhavn in Denmark and Puttgarden in Germany. The 18km tunnel, which is scheduled to open in 2020, will cut travelling times between the European continent and Scandinavia by allowing high-speed train services to operate between northern Germany and Scandinavia’s main cities. It should create a new and important northern European growth area. After comparison between a subsea tunnel designed by consultants Ramboll, Tec and Arup against Cowi and Obermeyer cable-stayed bridge solutions, it was concluded that the tunnel option will not only have advantages during the construction phase, but also during the operational phase. As well as technical, environmental and safety advantages, the impact on the environment and marine traffic are considered to be lower for the tunnel solution. Construction costs for the tunnel are also lower. When complete, the Fehmarnbelt link will be the third huge infrastructure project to have taken place in southern Scandinavia over the past three decades. In 1997 and 1998, the Storebælt Bridge opened to rail and road traffic respectively, linking the Danish islands of Funen and Zealand. In 2000, the Øresund Bridge between Denmark’s capital, Copenhagen, and Malmö, Sweden’s third largest city, opened to traffic. Since their commissioning, the two bridges have contributed significantly to economic growth in their respective areas. “We welcome the political support for our recommendation that the future link be designed as an immersed tunnel,” said Femern CEO Leo Larsen. “The decision means that Femern A/S has reached an important milestone in the planning of the fixed link. “As our conceptual design projects are based on an extremely thorough, technical foundation, we can now focus on ensuring that the authorities approve the project, including from an environmental perspective.” Over the coming year, Femern will prepare an environmental impact statement to be considered by the authorities in Denmark and Germany in accordance with national regulations. Femern expects to submit an application to the German authorities during the first six months of 2012. A construction bill will then be submitted to the Danish parliament, Folketinget, in 2013. This more or less coincides with the timetable for the German authorities’ approval of the project. “The aim is to build and operate one of Europe’s safest and most modern tunnels for both trains and cars, which will bring northern Europe and Scandinavia even closer together,” said Larsen. “As a result we’ll create opportunities for increased growth and prosperity for more than 10M residents in the Fehmarnbelt region.” The construction of one of Europe’s biggest infrastructure projects is expected to commence in 2014. The link is scheduled to open to traffic in 2020. 4 Worldwatch Crossrail’s Woolwich station box funding deal imminent 6 Worldwatch Trapped TBM halts work on s135M UK storm water tunnel 8 Thinking inside the box Work continues in tight conditions for the new Tottenham Court Road station 10 Housing the Venice gates Flood gates will protect the Italian city, but huge foundations must be built first 20 Pass the port A proposal for a new offshore shipping terminal near Venice is under consideration 22 In at the deep end A 576MW wind farm to be built off the Welsh coast highlights the size of the challenge facing the UK’s wind farm foundation Cover photograph: Rolls Royce winches at the Venice flood barrier 3 Crossrail’s Woolwich station box funding deal is imminent By Alexandra Wynne Final sign-off on the funding of the Woolwich station box for London’s Crossrail project was still pending as EF went to press, despite hopes agreement had finally been reached. The future of the station has been uncertain for over a year, since developer Berkeley Homes was hit by the economic downturn. Berkeley had promised to put €218M towards station box construction and planned to develop the space around it. Berkeley is understood to have spent €6M on the station design but its finances suffered badly in the recession and it has since been attempting to renegotiate the extent of its funding commitments with Crossrail. Crossrail chief executive Rob Holden told the London Assembly’s Transport Committee in early February that Crossrail sponsors had been working “very hard” to agree the financial details of Berkeley Homes’ commitment. He had expected that papers would be signed over the deal on 8 February. He had declared himself “as confident as anybody can be that we can bring it to a successful conclusion (shortly)”. The plan involves building a 291m long by 23.5m wide and 17m deep box to give capability for a station at Woolwich on the route as well as creating 2,500 homes. Agreement about who will finance the fit-out of the box and build the station at ground level must also be reached. Long-time backer of the station, MP for Greenwich & Woolwich Nick Raynsford said he was anxious for news and has challenged transport secretary Philip Hammond for an update. Delays to the funding deal had caused Crossrail to accommodate changes in the schedule, said Holden. But he said that the government review of the scheme and subsequent plan to postpone the opening of the route meant that the opening schedule of the “limbs” surrounding the central Crossrail section had still to be confirmed. The central section is scheduled to open in the third quarter of 2018 – a year later than originally planned. This means it is likely that the remainder of the route will be opened in 2019. Crossrail chairman Terry Morgan added that investigations into the potential for a station at Kensal Green in west London were still ongoing and that a decision would be made in the next few months. The Royal Borough of Kensington & Chelsea is lobbying for the station to be built. Network Rail is leading this work and is looking at the implications of building the station against criteria set by London mayor Boris Johnson, said Morgan. These are that the station must be delivered at no additional cost, that it has no effect on the timetable and that work causes no construction delays. Outgoing Crossrail boss wants engineer replacement By Alexandra Wynne The new Crossrail boss should have an engineering background rather than one in project management, says outgoing chief executive Rob Holden. Holden told the London Assembly Transport Committee in February that “skillsets [of the chief executive] will change and evolve” 4 as the e17bn mega-rail scheme shifts through different phases. He said the job would be different as it moved into the heavy construction stage. “The skillset needs to be less managerial and more engineering,” he said before singling out Crossrail finance director David Allen and programme director Andy Mitchell – last week picked as the engineers’ favourite to take over from Holden – as potential beneficiaries from such a boss. “People like Andy Mitchell and David Allen, the two executive directors I’m leaving behind, will benefit from somebody different – somebody who has those skillsets to help them in their career ambitions and to help them in delivering Crossrail. “My engineering colleagues will benefit from a person who can talk more engineering talk,” he added. Mitchell was clear favourite after EF sister magazine New Civil Engineer canvassed engineers following Holden’s surprise decision to quit last month. europeanfoundationsspring2011 Unique machine to take apart Hong Kong tunnel By Andrew Bolton A French machinery manufacturer is building a revolutionary tunnel dismantling machine, which will help contractors in Hong Kong splice an existing metro to a new extension. Bessac, part of Bachy Soletanche, is making the machine, which will be trialled in a purpose-built test tunnel in France. A joint venture between contractors Dragages, Maeda and Bachy Soletanche has the contract to connect the new tunnels with existing ones on Hong Kong’s Island Line. The machine will remove bored tunnel lining segments along a 120m section of overrun tunnel ,which serves as siding at the western end of the existing Island Line, beyond its terminus station. It will work in compressed air, which will support the mixed ground around the tunnel while a sprayed concrete lining is applied, replacing the segments. The machine will work a few metres at a time, backfilling the tunnel with low-strength concrete to give added support. Dismantling the lining will allow a tunnel boring machine working at the eastern end of the new exten- sion, known as the West Island Line, to punch through into the existing tunnel. The joint venture is boring a first 770m section of the new tunnel through soft ground with the TBM, which will finish in the dismantled joint section. This TBM section will connect to the rest of the €1.53bn West Island Line being built with drill and blast bores in hills to the west. The project is due for completion in 2014. The one-off machine is under assembly now and will go through proving trials near Toulouse before delivery to Hong Kong. Machines Czech in for micropiles A e3M slope stabilisation project begun in February last year is continuing at the giant Bilina opencast brown-coal mine in the rainswept and hilly Bohemia region of the Czech Republic, near the German border. Micropiles and 400 anchors are being installed by Soletanche Czech europeanfoundationsspring2011 Republica to prevent slips in old waste material which has been deposited over the years on the edge of the deep pit. The mainly sandy clays and claystones rest on harder schists beneath and tend to slide, threatening the huge excavators which continue working below, says project manger Jan Libus. Soletanche is using two Comacchio MC1200 machines to drill 160mm diameter holes between 15m and 40m deep, half in the waste and half into the bedrock. Concrete blocks made by another contractor are held by the anchors. Mine owner SD – rekultivace is the client. Austrians pass cash for tunnel The Austrian government has committed funds for the next phase of the 55km long Brenner Base Tunnel (BBT). It will be the second of the great Alpine deep high-speed rail connections to be built. A tranche of e1.3bn from the Ministry of Transport in Vienna will match a similar sum by the country’s Italian partners in the project. “Along with subvention funds from Brussels, that will bring funding to just over e3bn,” said a spokesman for BBT, the Austrian company set up by the Austrian state railway company to manage and commission the project. The project is part of the Berlin to Palermo high-speed corridor, which is top of the list of Trans European Network (TEN) projects designated by the European Union. Work can now continue until 2015 to complete all the preparations for main bores, including a 6m diameter exploratory and service tunnel, side adit access for the main drives, and spoil disposal facilities. “We will also be able start the main drives at the north and south portals,” said the spokesman. The funding also makes it almost certain that the tunnel will eventually be built, after almost a decade of ground investigation, design, and exploratory tunnels. The BBT spokesman said the biggest contracts would be carried out from three intermediate points along the 55km length of the tunnel. Funds for the main drives will be needed after 2015. Like the Gotthard, the Brenner will be a low base tunnel with gradients held as flat as possible by passing deep under the high peaks of the Alps. Maximum cover for the bores will be more than 1,700m, less than on the Gotthard but still posing major problems. Unlike Gotthard the tunnel will have three bores, two main rail tunnels of around 8m diameter and a central service tunnel of 6m diameter. The additional bore serves for drainage and as an exploratory tunnel to investigate the rock. A 3km long section of a 6km initial bore through potentially difficult rock has been driven from Innsbruck, and a 10.5km section from Aica on the Italian side was completed in November. 5 Trapped TBM halts work on £114M UK storm water tunnel PRESTON TUNNELS Storm water tunnel (unaffected by stuck TBM) Storm water main A5085 oa d Blackpool R A583 Preston New Rd Preston waste water treatment le Ribb works River Pumping Station Direction of drive Location of stuck tunnel boring machine then filling them with a coolant such as brine. The JV is also considering dewatering the area. “We could reduce the water pressure on the tunnel, but we would need to use something else to make [the tunnel] safe, such as a compres- Li v Contractors grappling with a trapped tunnel boring machine (TBM) in Lancashire say that jetgrouting, ground freezing or dewatering are the three most likely methods to be used to free it. The KMI Water joint venture (JV) of Kier, J Murphy and Interserve had halted work on part of a £114M United Utilities tunnelling project in Preston after silt breached the tunnel lining of the 3.5km long, 2.85m diameter storm water tunnel underneath Preston and Penwortham in Lancashire. The TBM is stuck 25m below ground in alluvial clay deposits. As a result, work was stopped on 24 November and the Lovatt earth pressure balance shield machine has not progressed since. KMI Water said it was looking at several methods to stabilise the ground and allow the TBM to be recovered. “We’re working up different options to get back into the tunnel and repair [the tunnel lining],” said KMI Water contracts manager Andy Parker. “We could drill a hole from the surface down to the tunnel and inject grout around the TBM and the tunnel lining [to alleviate pressure around the TBM]”. KMI Water is also looking at freezing the ground around the TBM. This would be done by inserting pipes around the TBM and Ro ool e rp ad 9 A5 sive air lock,” added Parker. KMI is still unsure what caused the silt breach. The lining of the 2.85m internal diameter tunnel is made up of 1m long precast concrete rings. Each ring consists of six sections which are bolted together and then sealed with a rubber gasket. Tunnelling for the project was going to plan until engineers noticed silt below the ferryplate – a sledge pulled along behind the tunnel boring machine containing the electrical panels, grouting equipment and a conveyor belt to take away the spoil. “We couldn’t get to it, or see where it was coming from,” said Parker, adding that the ingress was a fine silt that could “get through any gap”. A stack wall made of timber and sandbags was built to contain the ingress whilst the extent of the problem was assessed. When it was evident that silt was still entering the tunnel, engineers decided to flood the tunnel to make it stable. A decision on the recovery method will have to be sanctioned by the Environment Agency due to the tunnel’s close proximity to the River Ribble. The Agency will seek assurances that jet grouting or ground freezing would not lead to pollutants entering the river. Health & Safety Executive approval will also be needed. Parker said he could not put a timescale on the recovery attempt but insisted the project team was “working flat out”. The remainder of the project in Preston city centre remains unaffected. Foundations reconstruction for Kent dockyard building A listed pumphouse in the historic dockyard in Chatham, Kent is to have its foundations rebuilt. The South East Development Agency has commissioned Campbell Reith as consultant for the delicate work . Campbell Reith will design and replace two of the pile foundations, which have worn away over time. The historic Pump House Five is a Grade II listed building dating from 1879. It has planning permission for use as restaurant and leisure facilities. Original design of the brick build6 The listed building is being converted into a leisure development ing and its foundations still exist from 1871 drawings signed by a member of the Institution of Civil Engineers, supervising engineer EA Bernays, MICE. Investigations reveal them to be “remarkably” accurate. They showed that some of the structure was supported with timber piles, which were drilled into deep fill and alluvium into the underlying gravel. Land raising around the building early and dewatering of the dockyards in the 1990s for the Medway tunnel are blamed for significant differential settlement of foundation elements. An initial assessment shows two damaged piers need support with new underpinning, said the consultant. Monitoring indicates that the remainder of the building is stable. The pump house was originally built to expand the dockyard in preparation for the construction of then new iron clad warships. This development will go alongside the Dockyard Museum. EuropEanFoundationsspring2011 GE Awards attracts record number of entries A largescale cofferdam for a Crossrail station construction in a water filled dock at London’s Canary Wharf, dramatic plunge columns for top down construction on the London Bridge Shard skyscraper and use of large scale, deep, steel pile techniques to remove a huge buried granite block seawall in very soft ground in Singapore are among a record number of entries in this year’s Ground Engineering awards. The entries from respectively Canary Wharf Contractors, with consultant Arup and specialist contractor Expanded Piling, Balfour Beatty Ground Engineering and Gammon Construction have each been shortlisted for the technical excellence category. They join grouting work on the new Shanghai Yangtse river tunnel in China by the Shanghai Tunnel Engineering Company together with the Shanghai Yangtse River Tunnel & Bridge Construction & Development Company; data man- agement and software integration for bored tunnel design on Crossrail by a joint Arup-Atkins consultancy team; bi-directional pile testing using the Osteberg method for large piles on the Farringdon station redevelopment on London’s Thameslink by Atkins; and development of a large scale asset management and recording system for earth embankment structures on London Underground, also by Atkins. Seven other categories make up the awards, including a new one of product innovation in the geotechnical sector. Shortlisted entries for all of them were published on 10 February and the winners will be selected over the next six weeks by the panel of five judges drawn from the geotechnical community. The eight categories are for international project of the year, UK geotechnical or geo-environmental project over £1M, and separately under £1M, sustainability, health and safety, innovation, technical excellence, and finally young geotechnical or geo-environmental engineer of the year. The winners of the eight prizes for this fourth year of the event, which is sponsored by Bam Ritchies and Bachy Soletanche, will be announced on 11 May at a presentation lunch Park Lane’s Grosvenor Hotel in London UK. n Full details of the shortlisted entries are at www.geawards.com St Helena gets rockfall protection Major rockfall protection works will wind up in March on the remote southern Atlantic island of St Helena after construction began last August. Appropriately for the famous last internment of Napoleon Bonaparte, the project has been carried out by French contractor CAN France. The project extends emergency protection carried out in 2009 by the same contractor, after a 300t rockfall damaged parts of the island capital Jamestown and forced evacuation of a primary school. Local workers trained at that time have largely been used for the work. The volcanic island remains vulnerable to falls because of its geology of heavy basalt lava flows interbedded with easily eroded ash and pyroclastic deposits, which make the island’s steep valley sides unstable. Much of its 4,000 resident population plus water and power infrastructure is at risk in the narrow EuropEanFoundationsspring2011 valley of the capital. The latest works involve installation of proprietary GBE rockfall barriers from Swiss manufacturer Geobrugg along the steep slopes above the town. Just over 2.5km of 500kJ capacity has gone in, 1.3km of 1,000kJ and 210m of 2,000kJ and 900m of extra strong 3,000kJ. As with all supplies to the island this was delivered via a 10 day journey from Capetown in South Afria aboard the poster ship St Helena, the only means of access. The barriers are formed with minipile anchored plates supporting a steel post tied back at the top with cables to rock anchors further up the slope. Design of the works for the client, the UK’s Department for International Development acting for the St Helena Government, is by consultant WA Fairhurst of Glasgow, which also supervised. 7 transport The small site is hemmed in by offices and residential buildings thinking insidE thE box Minimising ground movements while building a 44m deep diaphragm wall box at London’s Tottenham Court Road station is challenging enough. But joint venture Bauer Keller must also install 48.5m deep piles with plunge columns to millimetre accuracy. Ruby Kitching reports. E ngineers can reel off the problems of working in congested city centre construction sites with relative ease: very little storage and loading area for supplies; noise restrictions due to nearby residents and businesses; and limitations on ground movements to protect existing underground structures and infrastructure. So for subcontractor Bauer Keller joint venture, these constraints came as no surprise when it arrived on site at central London’s Tottenham Court Road station last year. But the degree of accuracy required to build some elements of 8 the £12M Goslett Yard basement still came as quite a shock. Tottenham Court Road station is situated at the junction of the famous Oxford Street and Charing Cross Road and under the towering gaze of the 34-storey Centre Point building. Here, the road above and the Tube tunnels below experience some of the heaviest traffic in central London. Since the station currently serves two Underground lines A new line foR london Crossrail is a new cross-London rail line that will run 118km from Maidenhead and Heathrow in the west, through new 21km twin-bore tunnels under central London to Shenfield and Abbey Wood in the east. With a total budget of £15.9bn, the new line will have 37 stations, with eight brand new central London stations and 28 upgrades of others, 11 of these major reconstructions. When Crossrail opens in 2018 it will increase London’s rail-based transport network capacity by 10%. – the Central and the Northern – it is a popular interchange as well as one of the main stations serving the West End office, shopping and entertainment areas. Built in 1900, the station is now used by 150,000 passengers a day and by 2018, this will rise to more than 200,000 with the new Crossrail station opening (see box). Anyone who has elbowed their way through the crowds down the greasy steps of Tottenham Court Road station will be able to testify that the century old station is well past its use-by date. It’s not surprising, then, that a £1bn station upgrade is currently europeanfoundationsspring2011 PLAN 2.32m diameter piles with plunge columns 1m thick, 44m deep reinforced concrete diaphragm wall A A Precast concrete stop ends with water bar 0 m 10 SECTION A-A Level (+0) Ground level (0m) Made ground Level (-1) Level (-2) River Terrace Deposits 44m 48.5m Level (-3) Level (-4) London Clay Lambeth Group 1 Lambeth Group 2 Plunge columns Thanet Sand Chalk Plunge columns will support buildings on top of the station The diaphragm wall grab takes 3.2m long, 1m wide bites as it digs under way to improve the situation. This overall scheme involves creating a new station six times bigger than the existing one and with twice the original capacity. The project also involves reducing congestion above ground for pedestrians, cyclists, bus passengers and other road users. It will also have much improved passenger access by escalator and lift. Client London Underground is undertaking the project on behalf of Crossrail. Main contractor is Vinci Bam Nuttall. Bauer Keller’s contract is part of this upgrade project and involves building a 44m deep diaphragm wall box to create a four-storey basement which will eventually house four escalators and one lift. These will take passengers from the new, larger street level ticket hall to the Northern and Central Underground lines and the new Crossrail line. A third of the perimeter diaphragm wall has been completed and work is about to begin (after Easter) on 11 large diameter piles, each with plunge columns. “We’ve got a substantial excava- Cartwright. But in central London where there are Tube tunnels and shallow foundations nearby, it was decided that it would be prudent to build the walls using the minimum, single bite length. Each panel is excavated to its final depth 44m below ground level, requiring six to seven hours of straight digging. The steel reinforcement cages are nearly at their limit for bar size and spacing with 50mm diameter bars used for the main reinforcement. They are detailed to accommodate slab connections and utilities ducts. Each cage is fabricated in one complete length on the factory floor in south Wales by supplier Express europeanfoundationsspring2011 tion – a perimeter of 150m – and to make sure we’re as good to our neighbours as can be, we’ve had to look very closely about how to build it,” says Bauer Keller JV project director Alex Cartwright. The diaphragm wall is being built in shorter lengths, or panels, than would usually be expected. This is because shorter panels disturb the ground less than longer ones and hence induce much smaller ground movements. A crane-mounted grab excavates the ground in single bites 3.2m long and 1m wide. Walls of the excavation are supported by bentonite. “In an open field, you could build panels about 7m long by taking bites next to each other,” says “We’ve got a substantial excavation and to make sure we’re as good to our neighbours as can be, we’ve had to look very closely about how to build it” Alex Cartwright, Bauer Keller Reinforcements. The cage is then dismantled and brought to site only the night before it is needed since there is no space to store them on site. After one panel has been excavated 44m below ground level and the reinforcement lowered, it is then filled with concrete and the bentonite displaced. The site operates 24 hours a day, Monday to Saturday. Not only does night-time work have to be carried out quietly and with careful co-ordination with the local council, noise restrictions also apply by day. The basement will be constructed using top-down techniques to ensure noise levels are kept to a minimum. Top down construction involves creating a perimeter wall in the ground, and installing piles with columns on top (“plunge columns”) to create the basement structure. With the basement columns in place, a ground floor slab and further superstructure can be erected and basement soil dug out in tandem. At Goslett Yard, when the diaphragm wall is complete, 11 piles of 2.32m diameter and 48.5m deep will be built inside. A plunge 9 transport column will be carefully embedded into each pile just before the concrete hardens. The plunge column steels are bespoke sections with web and flange depths of 700mm. Thicknesses vary. “The plunge columns are 33m long – so are really quite big – and serve two roles: as the box is excavated, they work in tension and reduce the buoyancy of the box and secondly, they serve as the supports for the future development above ground level,” explains Cartwright, who most recently oversaw plunge column installation on London’s Shard of Glass skyscraper. On the Shard, top-down construction was adopted so that the above ground structure could progress swiftly, unhindered by complicated basement construction. But at Tottenham Court Road, the scheme is solely concerned with underground construction and purpose of the top down technique is to keep noise levels low and, more crucially, to keep ground movements to a minimum, reducing the effect on nearby Tube tunnels or foundations. The site is currently gearing up for the start of piling and installation of the colossal plunge columns. “They are the challenge for this project,” says Cartwright rather gleefully. “They are some of the heaviest you’ll ever see.” The columns have been fabricated by steel contractor William Hare. “They [William Hare] stood out as one of the few who could get these columns built really straight,” Cartwright explains. The columns are 32m long and have to be placed to a 1 in 400 accuracy to ensure they work efficiently. “One of the difficulties was that the 1 in 400 tolerance could be used up during fabrication.” The column arrives on site in three pieces: a 12m and 20m length which make up the permanent column and a 6m length “follower” piece which is recovered. Simply connecting the lengths of column on site within these tolerances will be a challenge, considers Cartwright, “so we will be doing a lot of practicing before we do our first column”, he admits. Pile construction begins with the “This is certainly a raising of the bar in our industry. We’ve got just 2.5mm in a metre to play with.” Alex cartwright, Bauer keller 10 Fixing steel for one of the plunge columns installation of 10m of 2.4m diameter temporary steel casing to seal the loose and wet soils in the upper formations. A BG40 excavator then works to 48.5m below ground level under bentonite. The pile cage is then lowered in and concrete is tremmied from the bottom of the pile to the required cut-off level, displacing the bentonite. The bentonite is then drawn out from the remaining top section of excavation, (where the plunge column will sit) while the concrete cures below. “The challenge then will be to pick up the plunge column and place it to fairly tight tolerances into the pile before it hardens,” says Cartwright. The column will be embedded into the top 11m of the pile which is made up of 32/40 strength concrete, supplied by Hanson. The concrete has been designed to take longer to cure so that there is more time to position the column. A bespoke plunging frame has been designed and loaded up with laser guides and instrumentation to help position the column correctly. This frame has spider-like legs at the bottom which spread out onto, and push against, the inner face of the excavation, clamping the frame in place. A square opening runs along the length of the frame to guide the plunge column. Lasers are fired up from the bottom of the frame to the top to check that the square openings are all in line. The frame is then effectively steered until it is plumb. Positional tolerances require the top of the column to be within 10mm of its intended plan position and 10mm of its correct level. Cartwright adds: “This is certainly a raising of the bar in our industry. We’ve got just 2.5mm in a metre to play with.” The data collected by instrumentation on the frame will give Bauer Keller the confidence that the column is plumb. Designer Atkins assumed that this verticality could be achieved on site, and has designed the column to work in compression to an even greater degree than normal. This means that the column section size is as slim as possible. The basement is to be excavated and ready for fit out and connection with other London Underground and Crossrail infrastructure in 2013. The wider Tottenham Court Road upgrade project will be complete in 2016. concrete keeps the noise down Diaphragm wall panels are usually separated during construction by a thin steel stop-end which runs the full depth of the wall. The main job of this stop-end is to incorporate a water bar which allows water to pass out of the wall. The stop-end is usually a piece of sheetpile which is broken out using a crane-mounted chiselling tool after a panel section has cured. The water bar remains embedded on one side of the panel to sit hard up against the adjacent panel about to be built. Breaking out the steel was considered too noisy for the Tottenham Court Road site. Instead, a much thicker, unreinforced precast concrete stopend is being used which will be cast permanently into the wall. Since the permanent precast steel stop-end is much thicker than the removable steel one, there is a greater length of wall which will be unreinforced. “While this is less efficient than the steel stopend option, it is the quieter solution,” Cartwright says. Night-time site activity is kept to a minimum because there are residents nearby. However, London Underground stakeholder manager Adam Healy says that currently, the average nighttime site noise levels are currently below the ambient levels from nightclubs in the area. europeanfoundationsspring2011 POrts HOusinG tHe venice Gates A large reclaim work site has been formed at Malamocco channel. It will be removed later Few foundations are as gigantic as the base units for the Venice flood gates. Adrian Greeman visits the site. G reat fleas have lesser fleas upon their back to bite ’em”, so the poem says. And great foundations have lesser foundations also, to support them. For the great Venice flood prevention scheme, the foundations even have further temporary foundations during their construction. The main founding blocks of the project are huge concrete caissons that will be inserted flush with the seabed in the three channels connecting Venice Lagoon with the sea outside. The three channels are the Lido channel to the north, the central Malamocco channel and the Chioggia channel to the south. Sitting within cavities in these giant cellular concrete blocks will be the steel flap gates that will rise from the bottom during storms and tidal surges to protect the canal city and its unique architecture, history and irreplaceable artistic heritage. The gate housing blocks are enormous, the largest rising to a height of 11.5m with a 60m length and 48m width – the size of eight tennis courts. Even the smallest are 36m wide and the same length and height. The differing widths will accommodate different gate sizes, according to the depth of the various channels. Four lines of gates are needed in total, one each for the two southern inlets and two in the northern Lido inlet, the closest entrance to the cluster of islands making up the old city. “The Lido is the widest entrance and was too big for the gates to work effectively,” explains Monica Ambrosini, an information officer at Consorzio Venezia Nuova, the client for the €4.6bn project. Tests showed the gates would only be effective in a channel up to 400m wide. The designer, consultant Technital from Verona, early on decided to divide the Lido channel in two by 12 the formation of an artificial island, now fully dredged and with building construction already under way. Conveniently, the island could also be used as the location for all the control and monitoring equipment and for the air compressors and other machinery needed for the gates once they are in operation. Lido’s Treporti channel, passing north of the new island, is the shallowest with a 6m depth of water. Small private vessels, light craft and yachts will use it. It will have 21 gates in a row. Each caisson will seat three of the 20m-wide gates, which means seven will be needed. At either end there will be two higher and narrower caissons to form the abutments and give access to the underwater units. The other Lido channel, San Nicolò, has another seven caissons plus two abutments. It is slightly narrower and only 20 gates are required, so one of the caissons will be smaller, holding just two gates. But the water is deeper here at 11.5m, to allow the big tourist cruise ships through to the city, and so the gates are longer and the units must be longer too. In the far south the lagoon’s Chioggia channel will need a 12m depth to allow fishing vessels through to their nearby port of Chioggia. Here, 18 gates are needed, housed in six caissons with again two additional abutment units. Largest of all the works are for the central Malamocco entrance. This is the most important for shipping with a deep water channel continuing right across the lagoon to the modern industrial port of Marghera. It will have 19 gates in seven caissons with another two abutment units. All these huge units are now in construction. For the smaller Treporto channel in the Lido inlet, contractor Mantovani is taking advantage of a small 500m long harbour space built as part of the new channel. The harbour is a storm refuge and also a waiting space for a small side lock which will allow boats to pass through even during gate closures. A second harbour is on the inside. “By strengthening the walls and sealing the entrance with a cofferdam the harbour makes a useful workspace for caisson construction,” says Ambrosini. “At Malamocco, there was no land suitable for a giant work yard. It had to be large, because the caissons need a year of construction work” Enrico Pellegrini, GLF The 9m deep dock will be flooded eventually and the units floated out. A similar temporary drydock arrangement prevails at Chioggia where a larger lock and harbour refuge will allow the fishing crews to pass. Contractor Condotte d’Acqua is working on these. By the big channel which runs through the Malamocco inlet, and for Lido’s cruise ship channel, there is no harbour space. The cruise ships do not get a lock either as they can easily reschedule their routes. The big oil tankers need no refuge, though they do require a lock, the largest, as they cannot reschedule during storm closures. For contractor Grandi Lavori Fincosit (GLF), which is carrying out the work in the Malamocco and southern Lido channels “another solution was required”, says GLF site manager Enrico Pellegrini. That was to build the caissons on land and move them, on completion, to the sea, where they will be lowered into the water using a giant Synchrolift ship lift. “The equipment for that is europeanfoundationsspring2011 Lagoon Venice Marghera Port Lido lagoon inlet 1. Refuge haven and navigation lock 2. Abutment 3. Treporto Gates 4. New island and abutments 5. St Nicolo Gates 6. Abutment 7. New breakwater Sea Lido lagoon inlet 1. Abutment 2. Row of gates 3. Abutment 4. Navigation lock 5. New breakwater 6. Temporary worksite Lagoon Malamocco lagoon inlet Sea 6 Malamocco lagoon inlet 1. Refuge haven with craft harbours 2. Abutment 3. Row of gates 4. Abutment 5. New breakwater Chioggia Chioggia lagoon inlet Sea Lagoon Chioggia fishing port Chioggia lagoon inlet The Venice lagoon with three existing entrances and the new configurations with gates literally Rolls-Royce standard,” says Pellegrini. It has been designed and assembled by the US Syncrolift company, a part of Rolls-Royce’s marine equipment division since the 1980s. “But at Malamocco, there was no land suitable for a giant work yard,” says Pellegrini. “It had to be large, because the caissons need a year of construction work. With some 18 to build and install by 2013 they all needed to run concurrently in a single space.” GLF’s existing facilities in southern Italy, where it makes marine structures for delivery all around Europe, were too small. Land had to be made. Conveniently there was a space close to the channel. Just here a new breakwater has been built out to sea as part of the scheme to slow the fastest tides. It could be joined to land with a sheetpile quay wall extension to protect a shoreside space which could be filled. “Sand had to be dredged anyway for the shiplock approaches,” says Pellegrini. Work began in 2005 for three years to make a 13,000m2 europeanfoundationsspring2011 Venice is threatened by flooding several times a year 13 POrts Breakwaters, which define the existing channel, have been extended and a ship lock added temporary platform “with great care and tight organisation”, jetting sand onto the beach and close shore. The problem was to avoid settlement as much as possible under the maximum 24,000t weight of each unit “and particularly any differential settlement” says Pellegrini. A key issue was the sloping shoreline profile to a maximum filled depth of 7m. Juggling the fill sequences was critical. “We also drilled 21 large diameter dewatering wells,” adds Pellegrini. These tapped into two water tables in the mostly clay layers underneath, which are separated by a 2m thick band of very hard clay at around 10m depth. “We dropped one of these by 2.5m and one by nearly 9m and this forced some 150mm of settlement.” On top of the dredged sand, 1.5m of gravel was laid in 300mm layers, each compacted to highway standards, he says “around 98% or 99%”. On that went a further 500mm layer of leanmix concrete. Pellegrini would have preferred more robust asphalt but environmental restrictions prevailed. On top of that each caisson gets its own temporary concrete slab during construction, and the whole area is being constantly monitored for settlement, just in case, as the caissons are built. But before that could begin last year there was plenty more to do, says Pellegrini. Each of the four channels has to be prepared and shaped, partly to receive the caissons and partly for tailoring the overall hydraulic regime. “First work actually was strengthening and defending the lagoon islands,” he says. The sea edge of the lagoon is little more 14 Foundation mattresses are laid by unwinding from huge floating rollers than sand spits stretching its 50km length and only a few hundred metres wide, narrowing at one point to around just 50m. It was here the sea broke through in 1966’s devastating floods. New groynes and other sea defences have been made. New additional breakwaters and reinforcements to the existing ones, shelter the sea entrances. Then each channel had to be dredged to a square profile, from the natural V-shape. At Malamocco dredging will fill in the 16m deep centre, while cutting back the edges to 14m. Grab barges fitted with sonar did this work. “And it is amazing how precise you can be with the 3D images you get from modern multi-beam underwater survey equipment,” says Pellegrini. To protect the new sea floor, giant mattresses were made from aggregate sandwiched in geofabric and steel mesh tied across with steel bar. These are like the seafloor protection used on the Osterschelde barrier on the North Sea coast in the Netherlands. The 200m long blankets, each 10m across, were made up on land and then rolled Site manager Enrico Pellegrini europeanfoundationsspring2011 ports Flood gate operation Lagoon Sea Air pumped in Expulsion of water A piling barge was built for the 1,800 trench bed piles onto large floating rollers. A specially designed and built vessel could hold the rollers in Y-shaped arms and then gradually unroll the mattresses across the channel width. A heavy weighted section formed the start point. But this was easier said than done says Pellegrini. Accuracy in placing the rolls was vital, particularly as they had to overlap by about a metre. “That can be achieved with modern GPS positioning equipment controlling the balance between six anchor cables” he says. But a major problem for all the channel works is the tides. The water from the lagoon wants to pour through the three narrow entrances and back twice a day, explains Pellegrini, “which can mean currents up to five knots, which is almost impossible”. For the mattresses, only dead calm would suffice, which limited the work window to just over half an hour on the turn of the tide, just long enough for one mattress. “But you only get one chance,” says Pellegrini. Above the mattresses a 2m thick layer of rockfill has been placed by grab barges, the material coming from limestone quarries in Croatia across the Adriatic. This shaped layer extends 200m either side of the gates which have to sit flush in a trench in the middle. Forming and excavating this is the most crucial work. The first step was to make a heavy sheet pile wall either side of the 16 future trench. This is being driven by a pontoon-mounted hydraulic pile hammer, driving 30m into the dense clays. Accuracy is vital to form the trench wall and positioning crucial – even using GPS and four anchor cables it can sometimes take half a day to set up, says Pellegrini. The tide race means the pontoons have been fitted with extendible legs to fix their position once it is done. Work is complicated by the need to keep the channel open for the big ships. Closure of one side is possible with constant liaison with the port authority, but switching from side to side has been needed. The inside of the sheet pile walls was next dredged 15m down with grab barges and then comes a second stage of piling. This time concrete piles have to go in, to form a grid pattern across the bed of the trench, some 1,800 in all. Another purpose-made and fairly large barge has been used for this work which just completed before Christmas. It carries two trackmounted pile masts with hydraulic hammers, one each side. They could move up and down to cover the grid each time the barge was repositioned. Driving the piles 30m down requires pile extenders. The 500m diameter circular precast piles arrived from a local supplier and were delivered by a small barge and lifted out by crane to slide into the pile rig. Another 2m thick layer of stone goes on to the trench floor and Lagoon Sea 2m thick rubble mattress Hinge Water filled cells Gate housing Gate Plant tunnels Access tunnels Concrete filled cells Seabed consolidation piles Aggregate mattress Aggregate layer 1.5m rubble Grouted gravel infill Cross section of the caisson trench. Profiled flat seabed, prepared by laying huge mattresses (below), extends 200m either side europeanfoundationsspring2011 ports The huge caissons require a carefully programmed sequence of concreting (right) Special mobile jacks will lift the caissons when complete The reinforcement required for the caissons is exceptionally dense 18 1 4 2 5 3 6 this time must be compacted carefully to form a flat base. The contractor has made a giant plate compactor for this, 3m square with vibrator units and kentledge on top. It will be suspended by barge cables. Some of the trench piling continues at the edges, but attention is now on the casting yard where the huge caissons began construction last year. Each is built on a concrete slab above which is a grid of 2.3m high pillars, keeping a cavity underneath to be used later to move the 24,000t units. Casting is complicated as each unit a highly complex structure in itself with multiple cells and walls to form, all linked together with piping and ducts. These will allow water to be pumped to and fro in the float out stage, explains Pellegrini, to help balance the buoyancy of the irregularly shaped elements. Once immersed the units will also be filled with water to weight them down, and with concrete in the cells around air-filled tunnels, which are needed for inspection and maintenance. Reinforcement for the big box-like units is extensive, with a density of up to 350kg/m3 and bars of 22mm to 26mm thickness everywhere. For air/water boundary walls, highly expensive stainless steel bar is used. So congested is the steel in the cell walls, which are often only 250mm thick and a maximum of 500mm, that ordinary vibrator compaction is ruled out. Instead, a self-compacting concrete mix has been designed. “It is a difficult mix with tight tolerances,” says Pellegrini, and mainly for that reason the contractor has set up his own batching plant on site even though there is a local ready mix firm nearby. “That also makes delivery very quick,” he adds. An extensive programme of pretesting and pour trials was carried out, as well as trying out the packed-in reinforcement assembly. Trials included pressure testing a variety of waterstop options for joints. In the end a stainless steel strip with bitumen was selected. “The sequencing of pours and timing to compensate for shrinkage is critical,” says Pellegrini. The yard has to follow a stringent routine. “One unit would be difficult, but doing all of them on a production line basis makes programming especially complicated,” he adds. About one third of the units have been completed so far. Once finished rails will be laid underneath each unit on which will run small hydraulic jack trolleys each capable of lifting 350t. The trolleys are specially designed versions of Norwegian TTS mobile jacks used in shipbuilding and oilrig work. About 80 units will be linked by computer to lift the caisson and move it to the Syncrolift. This too is based on shipyard design with a 24-strong rank of 500t winch units each side and a platform of beams between them. These are twice as wide as a normal ship lift and 5m deep to resist the deflections. Load testing was under way when EF was on site, but it will be a while before the lift is used for a complete caisson. That has to happen before 2013 when the gates will be ready for installation. But that is a way off yet and Pellegrini says even the precise method for the immersion stage has not yet been worked out. He has enough on his plate for the moment. groundengineeringspring2011 Marine The total 1.5km of quays will be for container ships Oil will be offloaded and piped to shore pass the port A new offshore shipping terminal is being planned outside Venice to increase the city’s port capacity. Richard Johnstone looks at the plans. A plan to build a port in the north of the Adriatic about 14km east of the port of Venice is being examined by the Italian government and the Venice Port Authority. The proposed facility is a deep-sea container terminal with a maximum capacity for 3M container units a year. Plans for the €1.3bn project also include a crude oil terminal with annual throughput of 7Mt. The 80ha site was originally planned as an oil terminal in 1984, according to Halcrow’s maritime project director Payam Foroudi, who has undertaken concept design work for the project on behalf of the Venice Port Authority. Foroudi says the idea was rejected to due to difficulties in extending the existing inland port in Venice without increasing the risk of flooding in the historic city. The proposals that Halcrow has developed are now with the port authority which, according to Foroudi, is now examining the logistics of the scheme, including how to transport cargoes between 20 the new port and Venice. Halcrow suggests a fleet of barges could transfer containers, but Foroudi says that even if this is agreed, “five or six years of design and assessment” will be needed before work can begin. This work will include detailed design of the 3.5km protective breakwater planned for the site, and the 1.5 km of quays for deep-sea containerships. Foroudi says with the available information the structure would undergo a large amount of settlement due to the fine sediments on the seabed 20m underwater. These will be compacted by the breakwater and engineering solutions will have to be proposed to deal with this. Two options, which were outlined in Halcrow’s report for the breakwater – a rubble mound or caisson design – and one of four types of design for the quay wall, will address this. More information on conditions will become available through the Venice Tide Barrier project that is constructing 78 oscillating inflat- able flood gates that will guard the city against rising tides by 2014 (see pages 12-18). Marco Redaelli, a geotechnical engineer with Halcrow who has also worked on the project, confirms that “the information we had in terms of ground conditions was quite limited”. However, he adds: “We are aware that the main geotechnical issues will be settlement and consolidation of the ground where we are constructing.” The final solution would be based on a “number of factors”. Regarding the breakwater, Redaelli says: “From a geotechnical point of view, the more flexibility in the structure, the better.” Quay construction could involve building concrete caissons, a sheet piled “combi-wall”, a piled concrete deck or blockwork concrete solution. Blockwork concrete has advantages as “this technique is quite simple, it’s not complicated, and it is quite robust”. However, he argues that they are “not great” at being adapt- ed, and this would have an impact as one of the criteria of the design was future expansion of the port. The caisson design had advantages because it could be constructed off site and then transported and sunk into place. The project’s logistical issues include the necessary engineering to pump crude oil directly from the offshore terminal to inland refineries by a pipeline. Halcrow proposes that electrical power to the port be supplied by submarine cables, with water and fuel for the terminal provided by barges. The port itself is to form part of the new Northern Adriatic multiport system, which aims to play a greater role in handling more Europe-Asia and Europe-Mediterranean cargo flows over the next 10 years. The North Adriatic Ports Association envisages that development projects worth €3.43bn in the region are needed to provide Europe with a consolidated port base in the Mediterranean, to attract shipping coming from the Suez Canal. european foundations spring 2011 Renewable eneRgy in at the deep end A 576MW wind farm to be built off the Welsh coast highlights the size of the challenge facing the UK’s wind farm foundation designers. John McKenna reports. l ike a swan, an offshore wind turbine glides gracefully above the water, offering little clue as to the strenuous activity taking place beneath the surface. Foundation design for offshore wind farms is the great unseen element of the UK’s green energy revolution and in many ways it is the most challenging part of each project’s construction. The UK’s offshore wind plans are the most ambitious in Europe, if not the world, and consequently pose the greatest challenge to foundation designers. The UK is already the world sector leader with 1.34GW of offshore generating capacity installed, according to figures published by the European Wind Energy Association (EWEA) in January. Most of the existing operational capacity comes from the Crown Estate’s first round of leasing for offshore wind sites, which restricted projects to 30 turbines, with wind farm generating capacities ranging from 60-90MW. Its second round of leasing will 22 total 7.2GW, with project generating capacities ranging from 300MW to 1.2GW. The vast majority of round two schemes are either under construction or in the advanced stages of design. On top of this will come a 32GW round three, comprising mega offshore development zones ranging between 600MW and 9GW in generating capacity. Allowing for the big turbines in round three a rough average is 4MW capacity for each turbine. This means the UK stands to have more than 10,000 wind turbines installed off its shores over the next 15-20 years. With variable ground conditions and sea levels requiring each turbine’s foundation to be designed individually, this represents a sizeable challenge for geotechnical engineers. “The sheer size of the piles that need to be installed on most of the offshore foundations is mind blowing,” says Ramboll director of geotechnical engineering Mohsen Vaziri. “They can be up to 6m in diameter, with wall thicknesses up to 100mm and each one around 500m apart.” The 576MW Gwynt y Môr wind farm off the north Wales coast is the project for which the team is designing foundations, and it offers a fascinating insight into the “We are designing a cantilever, which is really a simple design. But because you have so many variations, what is very simple soon becomes very complicated” Mike Hallett, Ramboll challenge facing the UK’s offshore wind ambitions. At a cost of e2bn, Gwynt y Môr (Welsh for “wind in the sea”) is being delivered by a project company in which Germany’s RWE Innogy is the main shareholder with a 60% stake. The other shareholders are Germany’s Stadtwerke Munich (Munich Municipal Utility – 30%) and Siemens (10%). The total development area is 124km2, although the area within which the turbines will be built will be no more than 79km2. It sits 13km off the north Wales coast at the nearest point to shore, 16km from Llandudno, and 18km from the Wirral. The project comprises 160, 3.6MW wind turbines, and is being built in two stages. Driving of the monopile foundations for the first 92 turbines will begin in November, in water depths of between 13.3m and 21.3m with respect to lowest astronomical tide and a tidal range of 10m. The construction of the monopiles europeanfoundationsspring2011 Renewable eneRgy “The sheer size of the piles that need to be installed is mind blowing” Mohsen Vaziri, Ramboll is expected to continue through to late 2013, with the second stage comprising foundations for the remaining 68 turbines in deeper waters. These are in the region of 30m with respect to lowest astronomical tide and, again, a 10m tidal range. Each of the 160 foundations consists of two parts: a steel monopile of between 50m and 70m in length and between 4.7m and 6m in diameter plus a 25m steel transition piece that is fixed on top of the monopiles, connecting them with the turbine tower. The pile might extend between 13m and 30m through water, and then a further 5.5m above the water. The whole above-water height, including the transition piece and turbine tower, is 85m. A e240M (£200M) contract for the manufacturer of the foundations and transition points was awarded in January to a consortium of Danish fabricator Bladt Industries and German manufacturer Erndtebruker Eisenwerk (EEW) Special Pipe Construction. However, before they can begin manufacturing the monopiles and transition pieces, Ramboll must conclude its design work, which requires designing each foundation individually. “What we are doing essentially is designing a cantilever, which is really a simple design. But because you have so many variations, what is very simple soon becomes very complicated,” says Ramboll offshore wind associate Mike Hallett. “Each of the 160 foundations will be different.” As a rule of thumb, wind turbines need to be spaced apart by seven times the diameter of the turbines’ rotor blade. On Gwynt y Môr, the rotor blades have a diameter of 107m, so with turbines spaced so far apart it is understandable that the ground conditions can change for each foundation. “The ground is glacial, but no point in the ocean is the same,” says Ramboll geotechnical design engineer Laurence Cross. “There’s about 15-20m of sand and clay, laterally and vertically variable, underlain by mudstone. We 24 Britain is becoming the largest offshore wind energy user in Europe generally embed the monopiles in the mudstone by 20m, although the mudstone level itself might range 5m to 35m below mudline,” adds Cross. The varying ground conditions and the various loads the monopile has to deal with mean that on each monopile there is a different result each time when calculating the pile carrying capacity. The loads can be grouped broadly into three categories: axial loads from the mass of the foundation, tower, nacelle, and rotor nacelle assembly; lateral loads from the wind and waves; and torsion as the wind turbine tries to twist the foundation. In the harsh and variable marine environment, it is not surprising that the design of each monopile is a job in itself. “There’s a ridiculous number of load cases, somewhere between 2,000-3,000,” says Hallett. “You are looking at issues like different wind directions, wave lengths, is the turbine operating, scour or no scour? Each one produces a different load case.” But if the ground conditions are so variable, then why not simply design each monopile to the greatest load case. Surely this replication would be more efficient in terms of both time and cost? Not so, says Hallett: “You have to be location specific to optimise the amount of steel required. It does cost the client more money in Gwynt y Môr Consented December 2008 Rhyl Flats Generating since 2009 Liverpool North Hoyle Generating since 2003 Rhyl Conwy 0 km 10 Bangor WALES Chester Above: the location of various schemes now under way off Wales. Below: the monopile supports needed for the turbines are huge europeanfoundationsspring2011 Renewable eneRgy 26 Turbine tower 20m mudstone Pile foundation 15-20m sand and clay Transition piece (25m) Wind generators must be carefully spaced. Right: monopile cross section 50-70m design time, but the returns are vastly exponential.” More important, as the projects become larger all the design parameters, such as water depths, soil conditions and waves, become more varied, making it simply impossible to design a single foundation. “If we design for the worse case the deeper positions would probably be okay,” says Hallett. “However, as the water depth reduced the foundations would likely be too stiff and so would be outside of the frequency limits the wind turbine generator can operate in.” Cross adds that optimising the design of the monopiles so that each one is as small as it can be helps in the installation process. “The smaller your piles, the easier they are to drive,” he says. He also says that one of the biggest challenges in designing these monopiles is the lack of case history to inform his work. “A lot of the standards and industry papers are generally for much smaller diameter piles and this job becomes all about relating those principles to larger piles,” he says. “Also, thinking about this project in particular, there aren’t many 6m diameter monopiles that have been installed to that depth in mudstone. Other offshore wind farms are typically embedded in London Clay, chalks etc, so there really isn’t the case history there to back up what you are doing.” This point is proven by last year’s revelation that many of Europe’s windfarms with monopile foundations were at risk of fatigue cracking due to the settlement of the transition piece caused by the failure of its grouting. A group of major European energy firms commissioned Norwegian standards body Det Norske Veritas (DNV) to investigate the problem, and in January it concluded that the grouting failures were due to the axial capacity of cylindrical grouted transition pieces being lower than that previously assumed. The effect of large diameters, the lack of control of tolerances that contribute to the axial capacity, and the abrasive wear of the grout due to the sliding of contact surfaces when subjected to large bending moments from wind and waves, all reduced the axial capacity to a far greater extent than the limited case history of offshore wind was able to predict. “The original guidance didn’t allow for the scale,” says Hallett. “The tolerances aren’t there. This is a very harsh environment with lots of loading and unloading.” The DNV report recommends that conical-shaped transition pieces be used on new projects. According 4.7-6m (100mm thick) to this design, the monopile and transition piece are fabricated with a small cone angle in the grouted section. If the bonds between the steel and grout are broken during in-service life, some slight settlement of the transition piece will occur. This settlement will introduce compressive contact stresses between the steel and grout which, together with some friction, will provide sufficient resistance against further settlement. At the same time as making its recommendation on conicalshaped transition pieces, DNV also announced a further investigation into the viability of cylindrical grouted connection with shear keys as an alternative solution. Shear keys are circumferential weld beads on the outside of the monopile and the inside of the transition piece in the grouted section. The shear keys’ purpose is to increase the sliding resistance between the grout and steel so that no settlement occurs. According to DNV, the existing design standards for such connections are based on limited test data for alternating dynamic loading. The consultancy says that before this solution can be recommended, design practices for shear keys should be developed and properly incorporated in design standards. As a result, Hallett says the transition piece design for Gwynt Y Môr is yet to be agreed. But he denied that the problems with the grouting connections meant that monopile foundations should be abandoned altogether. On a number of projects, “Other offshore wind farms are typically embedded in London Clay, chalks etc, so there really isn’t the case history there to back up what you are doing.” Laurence Cross, Ramboll including another RWE scheme in Germany, steel jacket foundations – reminiscent of North Sea oil rig structures – are being used instead of monopiles. These four-legged structures rest on smaller piles and act as a base for the turbine towers to sit in. “Jacket structures are certainly a valid solution,” says Hallett. “However, they currently tend to be more expensive than steel monopiles for the depths we are looking at.” He adds that they may become more viable in round three in deeper water, and that projects are very near the depths where monopiles fare less favourably against jacket structures. Cross agrees: “With deeper water comes bigger piles, and monopiles may become too big for barges at the depths some of the round three projects are at. Jackets may become more appropriate.” With wind turbine installation due to start in 2013 and the project due be fully operational in 2014, it may well be that Gwynt y Môr is one of the last great monopiled offshore wind farms. Regardless of whether it is or not, there is still a fantastic foundations challenge ahead as Britain seeks to once again rule the waves. europeanfoundationsspring2011