Mining Operation Plan (MOP) - NMC | Nevada Mining Company
Transcription
Mining Operation Plan (MOP) - NMC | Nevada Mining Company
MINE OPERATING PLAN (MOP) Lease Number: 11-86475 Mineral Lease Section 11, TI3N, R4W Yavapai County, Arizona NMC, INC. (Nevada Mining Company) 909 Sunset Ridge Drive Franklin, TN 37069 (615) 400-1099 http://www.nmcinc.com PREPARED BY: NMC, INC. FOR: Minerals Section Natural Resource Division Arizona State Land Department DATED: December 31, 2009 NMC NEVADA MINING COMPANY TABLE OF CONTENTS SECTION I: ENVIRONMENTAL ASSESSMENT (EA) 1.0 ADMINISTRATIVE SUMMARY 1 2 1.01 INTRODUCTION 1.1.1 Purpose and Scope of Assessment 1.1.2 Location and Legal Description 1.1.3 Access 1.1.4 Operator Contact Information 2 2 3 3 3 1.02 LAND OWNERSHIP AND CURRENT/PROPOSED LAND USE 1.2.1 Project Site 1.2.2 Adjoining Lands 1.2.3 Existing/Past State Trust Leases 1.2.4 Background /Land Use History 1.2.5 Land Use Compatibility 3 3 3 4 4 4 1.03 SETTING 1.3.1 Site and Vicinity Characteristic 1.3.2 Climate 1.3.3 Geology and Soils 4 4 4 4 1.04 AFFECTED ENVIRONMENT 1.4.1 Water 1.4.2 Hazardous Materials and Waste 1.4.2.1 Chemical 1.4.4.2 Explosives 1.4.3 Solid Waste 1.4.4 Air Quality 1.4.5 Noise 1.4.6 Visual Impacts 1.4.7 Parks, Recreation Areas, Wildlife Refuges 4 4 5 5 5 5 5 5 5 5 1.05 RECLAMATION 1.5.1 Description of Desired Results 1.5.2 References to Mine Operating Plan and Reclamation Details 5 5 5 1.06 PERMITS AND APPROVAL 1.6.1 Corps of Engineers Section 404 Permit 1.6.2 National Pollutant Discharge Elimination System Permit 1.6.3 Air Quality Permit 1.6.4 Aquifer Protection Permit 1.6.5 Notice of Intent to Drill 1.6.6 Septic Tank 1.6.7 Flood Plain Use Permit 1.6.8 Use Exemption 6 6 6 6 6 6 6 6 6 1.07 UTILITIES 1.7.1 Water 1.7.2 Gas 1.7.3 Electric 1.7.4 Sewer 6 6 7 7 7 Page i 1.08 TRANSPORTATION 7 1.09 PLANNING AND ZONING 1.9.1 Current Planning and Zoning 7 7 1.10 SOCIO-ECONONMICS IMPACTS 1.10.1 Mine Operations economics 1.10.2 State Trust revenue Projections 1.10.3 County and Surrounding Community Impacts 7 7 7 7 1.11 SUMMARY 8 1.12 AGENCIES CONTACTED 8 SECTION II: MINE OPERATIONS PLAN (MOP) 9 2.01 INTRODUCTION 2.1.1 Purpose and Scope 2.1.2 Operations Summary 2.02 DEPOSIT DESCRIPTION 10 10 10 10 2.03 ORE/MATERIAL RESERVES 10 2.04 DEVELOPMENT/PRODUCTION SCHEDULE 10 2.05 OPERATIONS 2.5.1 Site Development 2.5.2 Construction 2.5.3 Mining 2.5.3.1 Mine Design 2.5.3.1.1 Mine design Parameters 2.5.3.2 Topsoil Removal and stockpiling 2.5.3.3 Slope/Bench Preparation 2.5.3.4.1 Drilling 2.5.3.5 Blasting 2.5.3.6 Loading/Hauling 2.5.3.7 Mining Equipment 2.5.4 Processing 2.5.4.1 Plant Operating Parameters 2.5.4.2 Product Mix 2.5.4.3 Ore/Material Handling 2.5.4.4 Crushing Conveying 2.5.4.5 Screening 2.5.4.6 Sorting/Classifying 2.5.4.7 Production Monitoring and Verification 2.5.4.8 Product Handling, Stockpiling, Storage 2.5.4.9 Product Hauling 2.5.4.10 Processing Equipment and Buildings 2.5.5 Labor Force 2.5.5.1 Company 2.5.5.2 Construction Contractors/Subcontractors 2.5.5.3 Mining Contractors/Subcontractors 2.5.6 Emissions and Pollution Controls 2.5.6.1 Particulates 2.5.6.1.1 Drilling and Blasting 10 10 10 11 11 11 11 11 12 12 12 12 12 12 12 12 12 12 13 13 13 13 13 13 13 13 13 13 13 13 Page ii 2.5.6.1.2 Crushing, Screening, Sorting 2.5.6.1.3 Loading, Hauling and Conveying 2.5.6.1.4 Stockpiles 2.5.6.2 Noise 2.5.6.2.1 Mining Equipment 2.5.6.2.2 Blasting 2.5.6.2.3 Crushing, Screening, Sorting 2.5.6.2.4 Power Generation 2.5.6.3 Solid Waste Handling and disposal 2.5.6.4 Hazardous Waste Water Pollutants/Spills 2.5.6.4.1 Surface water 2.5.6.4.2 Ground Water 2.5.6.5 Emergency Response 2.5.6.6 Monitoring and Reporting 2.5.7 Wildlife/Endangered Species Protection 2.5.8 Protected Plant Species Handling 2.5.9 Visual Impacts 2.5.10 Cultural Resources 14 14 14 14 14 14 14 14 14 14 14 14 14 14 15 15 15 15 2.6 FACILITIES 2.6.1 Ancillary Equipment and Facilities 2.6.1.1 Access and Haul Roads 2.6.1.2 Power Generation and Distribution 2.6.1.3 Water Supply and Storage 2.6.1.4 Explosives Storage 2.6.1.5 Fuel Storage 2.6.1.6 Maintenance Areas 2.6.1.7 Mine Office 2.6.1.8 Sanitary and Solid Waste Disposal 2.6.1.9 Site Security 2.6.1.10 Fire Protection 15 15 15 15 15 15 15 16 16 16 16 16 2.7 ECONOMIC FEASIBILITY 2.7.1 Economic Summary 2.7.2 Commodity/Products 2.7.3 Market Analysis Discussion 2.7.4 Cost 16 16 16 16 18 SECTION III: RECLAMATION AND CLOSURE PLAN (RCP) 3.01 INTRODUCTION 3.1.1 Purpose and Scope 3.1.2 Reclamation Summary 3.02 RECLAMATION APPROACH 3.03 EQUIPMENT AND STRUCTURE 3.04 WASTE DUMPS 3.05 ROADS, POWERLINES, WATERLINES, FENCES 3.06 AREA PREPARATION 3.07 RE-VEGETATION/SEEDING 3.08 SLOPE STABILIZATION 3.09 EROSION AND DRAINAGE CONTROL 19 20 20 20 20 20 20 21 21 21 21 Page iii APPENDIX A 1. Geosyntec Analysis (Appendix: Skull Valley Seismic Survey, Hasbrouck Geophysics, Inc.) APPENDIX B 1. Advanced Analytical Assay 2. Additional Assays APPENDIX C 1. Skull Valley Pit Map APPENDIX D 1. Arizona Mill Site Flow Sheet APPENDIX E 1. Equipment List Page iv SECTION I : ENVIRONMENTAL ASSESSMENT (EA) ADMINISTRATIVE SUMMARY Proposed Operating Summary NMC, Inc. was incorporated on April 3, 1984. On February 4, 1997, Peeples Mining Company ("PMC"), a Nevada corporation was formed as a wholly owned subsidiary. The assets of Peeples Mining LLC and F&H Mining, Inc. were consolidated into PMC. In addition, the first stage concentrated precious metals acquired from Zarzion, Ltd in 1995 were transferred to PMC. On September 9, 2003, NMC, Inc. merged with PMC, with NMC, Inc., continuing as the surviving corporation. In 2007, we created California Precious Metals, LLC, a California limited liability company, in order to hold our California mineral claims. The Company currently has two subsidiaries, Peeples, Inc., a Delaware corporation and California Precious Metals, LLC Peeples Inc. (A Delaware Corporation qualified to do business in Arizona) submits the following information in support of a proposed Plan of Operation (POO) in order to perform the rights granted under Lease No. 11- 86475. The POO would end on the expiration date of the Lease: May 1, 2003, or upon the expiration of any extended term of the lease. Peeples Inc. proposes to reclaim and recover valuable precious metals from certain inventoried concentrates placed in two pits by previous operators on the site. Peeples Inc. will reclaim the pit areas as they process same. A $15,000 Reclamation Bond was placed with the State of Arizona in 1995 even though the lease requires only a $5,000 bond. Because this proposed POO is part of a previous Plan and does not involve disturbing any new land, a new formal Environmental Assessment (EA) is not required. The Plan will address any environmental issues pertinent to the current proposed operation. The mineral lease was first entered into on May 2, 1983. The original Lessees acted as the operator until May 11, 1992. At this date, a "subcontract" was made between the Lessees and Peeples Inc. ( a Delaware Corp.). Peeples Inc. submitted a POO on Nov. 3, 1992. In 1996, Peeples Inc. submitted an Amended POO. NMC Inc. has received no formal written action on the 1992 or 1996 POOs. Peeples Inc. has relied on statements and documents from the previous operators and the former Lessees as to the belief and understanding that NMC Inc was in full compliance of all necessary permits, filings and POOs. 1.1.01 INTRODUCTION 1.1.1 Purpose and Scope of Assessment A formal EA will not be a part of this Plan. An EA was performed by previous operators. No new disturbance will be made and the proposed POO is in essence the same as the initial plan using State of the Art mechanical separation and gravity concentrating techniques. PAGE | 2 OF 21 1.1.2 Location and Legal Description The site is located on Arizona State Land Mineral lease No. 11 - 86475, Yavapai County, Tl3N, R4W, Sec. 11, Kirkland Quad. The site and adjacent arroyos have been mined since 1983. 1.1.3 Access The site is approximately three miles east of Skull Valley via Copper Basin Road to a dirt road following a ridge approximately 3/4 of a mile to site of operation. (see Appendix C, Skull Valley Pit Map). 1.1.4 Operator Contact Information Operator: NMC, Inc. Michael Sheppard, CEO 909 Sunset Ridge Drive Franklin, TN 37069 Phone: 615-400-1099 Project Manager Onsite: Pete Rushbrook Phone: 928-899-1251 1.02 LAND OWNERSHIP AND CURRENT / PROPOSED LAND USE 1.2.1 Project Site The project site is owned by the State of Arizona as Trust Land. The site is currently used for cattle grazing. The proposed use is to process stockpiled concentrates left in pits by previous operators and reclaim the disturbed areas. 1.2.2 Adjoining Lands The lands adjoining the site are undeveloped lands used for grazing and owned by the State of Arizona and The Bureau of Land Management (BLM). PAGE | 3 OF 21 1.2.3 Existing/Past State Trust Leases There is an existing Lease on the subject site: Mineral Lease No. 11-86475 Date entered: May 2, 1983 Date ending: May 1, 2003 Names in which issued: Eugene Bender and Arnold Spielman 1.2.4 Background/Land Use History The site has been used for precious metal mining since 1983. An estimated 8,000 ounces of gold have been recovered in the area over the years. The size of the gold found ranges from extremely small particles to nuggets weighing several ounces. Past operators recovered only the coarse gold. The fine gold and other precious metals were placed in pits for recovery at a latter date. 1.2.5 Land Use Compatibility The proposed POO is compatible with the adjoining land use of cattle grazing. The past mining history also demonstrates that compatibility. 1.03 SETTING 1.3.1 Site and Vicinity Characteristic The site is located in an undeveloped high desert environment. The community of Skull Valley lies 3 miles to the west. There is no other development in the area. 1.3.2 Climate The climate is typical of high (4800') desert elevations. It is generally dry with moderate temperatures. The area is subject to high daytime temperatures in the summer (100 degrees F) and freezing temperatures at night in the winter. Rainfall averages approximately 20 - 25 inches per year. 1.3.3 Geology and Soils The site is located on the western flanks of the Sierra Prieta. This small mountain range is the northern extension of the Bradshaw Mountains. These mountains consist of older schists and granites, which have been intruded by younger granites and volcanic rocks. Precious metal bearing gravels derived from the higher eastern elevations occur on a granite pediment and in the arroyos. Soils range from 0 to 25 ft. in thickness. Little or no soils are found on the pediment. 1.04 AFFECTED ENVIRONMENT 1.4.1 Water Peeples Inc. has applied for a determination of jurisdiction with the Army Corps of Engineers and has applied to state of Arizona Department of Environmental Quality for determination of Applicability. PAGE | 4 OF 21 1.4.2 Hazardous Materials and Waste 1.4.2.1 Chemical There will be no hazardous chemicals used for mining operations at the site. Common petroleum products will be used to operate vehicles on the site. They will be stored in such a way as to not contaminate the environment from a leak or spill 1.4.4.2 Explosives There will be no explosives stored on site. 1.4.3 Solid Waste Any solid waste generated by the Plan will be collected and placed in appropriate containers and disposed of in an approved landfill. 1.4.4 Air Quality Air quality standards will be met as set forth by Yavapai County Air Quality Control and Arizona Department of Environmental Quality. There will be no hazardous air pollutant emissions as a result of this Plan. Dust emissions will be controlled by wetting roads with water. The Plant is a wet process and will not generate any dust. 1.4.5 Noise Noise from loaders, crushing, screening and power generation will occur. The equipment will be maintained according to manufacture's specifications. 1.4.6 Visual Impacts The closest community is Skull Valley located 3 miles to the west of the site. The site is not visible from Copper Basin Road. 1.4.7 Parks, Recreation Acres, Wildlife Refuges There are no known Parks, Recreation Areas or Wildlife Refuges on the site or in the general area. 1.05 Reclamation 1.5.1 Description of Desired Results The desired result of reclamation is to reestablish the site so the topography and vegetation of the disturbed area blends into the undisturbed landscape. This will be accomplished by backfilling dug out areas and recontouring those areas to match the natural slopes. These graded areas will then be re-vegetated with plants to match type and density. 1.5.2 References to Mine Operating Plan and Reclamation Details The MOP incorporates final reclamation detail and part of the scope of the POO is to accomplish reclamation. PAGE | 5 OF 21 1.06 Permits and Approval 1.6.1 Corps of Engineers Section 404 Permit There are no known Section 404 jurisdictional waterways involved in this project. Peeples, Inc. has applied for a determination of Jurisdiction with the Army Corps of Engineers. 1.6.2 National Pollutant Discharge Elimination System Permit Not applicable as our water usage is a closed loop recirculation and does not have discharge. 1.6.3 Air Quality Permit Not applicable. We use water for separation; therefore, dust will be minimal with no chemical use. 1.6.4 Aquifer Protection Permit No Aquifer Protection Permit will be required at this site. The water recirculation pond is lined with an impervious material. An application for Determination of Applicability of the state APP program has been filed with ADEQ. 1.6.5 Notice of Intent to Drill No drilling is involved with this Plan except when prospective buyers or JV partners require ore samples deeper than 15 feet. 1.6.6 Septic Tank Portable toilet systems will be used during this project. 1.6.7 Flood plain Use Permit Does not apply 1.6.8 Use Exemption Mining/Metallurgical Use Does not apply. 1.07 Utilities 1.7.1 Water Water is supplied from four wells developed on the site by the former Lessees. Diesel operated well pumps are in place along with necessary ancillary water lines and access roads. Water from the wells are metered with State approved meters. Water for processing use will come from the recirculation pond at an estimated rate of 300 to 500 GPM. The well water will be used as make-up water only. 1.7.2 Gas We will be using a propane dryer for drying concentrates. PAGE | 6 OF 21 1.7.3 Electric Portable power generators will be used for the project. 1.7.4 Sewer Portable toilets will be used for the project. 1.08 Transportation Transportation to and from the site will occur on existing roads 1.09 Planning and Zoning 1.9.1 Current Planning and Zoning (County/City General Plan) Does not apply to mining or mineral processing operations. 1.10 Socio-Economies Impacts 1.10.1 Mine Operations Economics Evaluation of the impounded material has been an ongoing process since 1994. Assays show the presence of Gold. (see Appendix B Advanced Analytical Assays). Beginning in 1997, extraction methods were initiated and have been improved to a current acceptable level. There are approximately 279,000 tons of material (see Appendix A, Geosyntec Analysis) available in the storage pits. There are 2.22 ounces of Gold per ton averaged over 7 sample assays. (see Appendix B). At an 80% recovery rate, that equals 1.78 ounces per ton, times 279,000 tons, times the current spot price of $1090 per ounce, equals $541,315,800. 1.10.2 State Trust Revenue Projections The Mineral Lease requires a 5% royalty of the value to be made to the State of Arizona. Based on the projections of 1.10.1, the total royalty represents approximately $27,065,790 1.10.3 County and Surrounding Community Impacts The Project will employ 9-12 people when in full production. Local businesses will be impacted from the purchase of diesel and maintenance supplies. PAGE | 7 OF 21 1.11 Summary The site has been active for 26 years and Peeples Inc. will process the table concentrates of the original operation which took place during the 1980's and early 90’s. The proposed project will provide final reclamation. 1.12 Agencies Contacted 1). US Army Corps of Engineers 2). Arizona Department of Environmental Quality 3). Air Quality Division of the Arizona Department of Environmental Quality 4). State Land Department 5). Bureau of Land Management 6). Arizona State Mine Inspector PAGE | 8 OF 21 SECTION II: MINE OPERATIONS PLAN (MOP) PAGE | 9 OF 21 2.01 INTRODUCTION 2.1.1 Purpose and Scope The purpose of this Mining Operations Plan (MOP) is to provide updated information relative to the extraction of storage pit concentrates, the processing of those concentrates and the final reclamation measures necessary to close the site. 2.1.2 Operations Summary Peeples Inc., and assigns, proposes to initially reclaim, process, and recover precious metals from stockpiled inventory. After the stockpiled inventory is processed and the affected areas reclaimed, Peeples proposes to process virgin material on the site for precious metal recovery as profitability is determined by proper assay method. A map of proposed areas for exploration and mining will be provided prior to such work commencing. 2.02 DEPOSIT DESCRIPTION The "deposit" consists of an upper pit and a lower pit (see Appendix C, Skull Valley Pit Map). Each pit has sections separated by earthen walls. The upper pit's sections are labeled Upper Pit East, Upper Pit West, and Upper Pit South. The lower pit's sections are labeled Lower Pit East, Lower Pit Middle, Lower Pit West-2 and Lower Pit West-1. The concentrates to be recovered from these pits represent the "fines" (1/8" X 0) developed from previous processing for “free Gold” on the site. Depths of these concentrates are documented in the Geosyntec analysis. (see Appendix A) 2.03 Ore/Material Reserves Based on storage pit dimensions and material density the following reserves 279,000 tons of ore concentrate (see Appendix A, Geosyntec analysis) 2.04 Development/Production Schedules Development of the site is ready. Much of the ground preparation has been prepared from past operations. Processing methods have been known from past production and new testing during the past few years. Production can occur within 4-6 months of a target date. Production rates will be approximately 10 tons per hour. The projected time to process the stockpiled inventory is 5 to 7 years. 2.05 Operations 2.5.1 Site Development The site is already developed (Approximately 1500 x 700 ft). Access roads exist and the entire infrastructure is in place left over from the past operations. Construction of the processing plant will be at the same location as the previous processing plant. Water wells, water lines, haul roads already exist. 2.5.2 Construction Construction will commence upon Permit approval. The equipment to be installed is portable or will be placed on skids. Construction should take from 4-6 months. The equipment is shown in the attached flow PAGE | 10 OF 21 chart.(see Appendix D ). Cargo containers placed on a gravel bed will be used for maintenance, Q.C. and shop requirements. 2.5.3 Mining 2.5.3.1 Mine Design (Pit, Quarry, Underground) All concentrates will be removed from the storage pits located on the south side of the site. Pit construction is shown in (Appendix C, Skull Valley Pit Map) 2.5.3.1.1 Mining Design Parameters The mining will follow three steps: 1. Identify the "concentrates" during excavation by location and visual examination. The concentrates are a "fine" (1/8" X 0) and are of a greenish brown color, and are only found in the storage pits and wash basin. 2. Scarify the top 1 to 1 ½ ft. of the pit surface by ripping with a D4 Dozer to aid in drying the material. 3. Push the dried scarified material to the side of the pit to load-out point for transport to the processing plant stockpile feed area. Haul the stockpiled material with a front-end loader from the pit to the plant stockpile feed area. Steps 1 to 3 will be continuously repeated until the pits are emptied. The mining of the pits will occur during the summer and fall months when the weather is dry and evaporation rates are the highest. The retaining berms will be left in place so the pit can be reused as part of the final reclamation plan. There is no topsoil or waste in this recovery process. All of the material contained in the storage pits will be hauled to the plant stockpile area. The depth of excavating will stop when native ground is encountered in the scarifying process. Hours: 10hrs/day Mining Days: 250 days/year Haul Road Width: 12 ft. Wide, 1 ft. Safety Berm Haul Road Grade: Less than 10% 2.5.3.2 Topsoil Removal and Stockpiling No topsoil is involved in this mining project. 2.5.3.3 Slope/Bench Preparation The development of benches is not planned for this project. Upon completion of the project, the ponds will be filled with natural material left from past mining and contoured to match undisturbed areas. PAGE | 11 OF 21 2.5.3.4.1 Drilling Core drilling will be done only as required for custodial assays. 2.5.3.5 Blasting No blasting is planned 2.5.3.6 Loading/Hauling Loading/Hauling of mined material will be accomplished with a Cat 950 Front-end loader. Haul trucks are not planned to be used. 2.5.3.7 Mining Equipment A complete list of equipment is shown in attached flow chart. (See Appendix D). 2.5.4 Processing 2.5.4.1 Plant Operating Parameters It is anticipated that the plant will operate 10 hours a day, six days a week. Onsite generators will provide electricity for the equipment. At least one generator may need to be run 24 hours per day because some of the equipment should not be shut off, except on weekends. 2.5.4.2 Product Mix The final product will consist of a black sand final concentrate or ore containing precious metals with our primary focus on Gold. 2.5.4.3 Ore/Materials Handling Front-end loaders and belt conveyors will be used to handle materials on the site. 2.5.4.4 Crushing Conveying After primary screening, the +20 Mesh fraction will be conveyed to a vibrating ball mill for size reduction. The crushed material will be returned to the primary screen. 2.5.4.5 Screening Two stages of screening will be used. The first stage will size the material at ±20 Mesh prior to the first stage gravity concentration step. The second stage screening will occur between the primary and secondary gravity concentration steps. The secondary screening will separate the material into three different sizes for improved liberation of precious metals during the second stage gravity concentration step. PAGE | 12 OF 21 2.5.4.6 Sorting/Classifying The precious metal bearing material will be gravity classified in two stages The first stage consists of a primary gravity concentrating step. The feed will be sized to minus 200 mesh. The second stage gravity concentrating step will be made on closely sized feed in order to improve precious metal liberation. (see Appendix D Arizona Mill Site Flow Sheet) 2.5.4.7 Production Monitoring and Verification Independent assays will be performed for referee purposes 2.5.4.8 Product Handling, Stockpiling, Bagging, Storage The final product will be stored in one ton capacity containers for shipment to the refinery. Shipments will be in one to six ton lots 2.5.4.9 Product Hauling Hauling the final product to the refinery will be made via contract haulers 2.5.4.10Processing Equipment and Buildings See attached equipment list. ( Appendix E.) 2.5.5 Labor Force 2.5.5.1 Company Operator: NMC, Inc. Michael Sheppard, CEO 909 Sunset Ridge Drive Franklin, TN 37069 Phone: 615-400-1099 Project Manager Onsite: Pete Rushbrook Phone: 928-899-1251 2.5.5.2 Construction Contractors/Subcontractors Plant construction will be made directly under the supervision of Peeples Inc. 2.5.5.3 Mining Contractors/Subcontractors Mining will be performed directly under the supervision of Peeples Inc. 2.5.6 Emissions and Pollution Controls 2.5.6.1 Particulates 2.5.6.1.1 Drilling and Blasting No drilling or blasting will take place except for core drilled samples required for assays. PAGE | 13 OF 21 2.5.6.1.2 Crushing, Screening, Sorting Material passing through the crushing Screening and sorting steps will be in slurry form. 2.5.6.1.3 Loading, Hauling and Conveying Dust on the site resulting from loading hauling and conveying will be controlled with spraying from water trucks. 2.5.6.1.4 Stockpiles Dust on the site resulting from stockpiles will be controlled with spraying from water trucks. 2.5.6.2 Noise All equipment will be maintained to emit noise levels within manufacturer’s specifications. 2.5.6.2.1 Mining Equipment See attached equipment list. (Appendix E) 2.5.6.2.2 Blasting There will be no blasting on site 2.5.6.2.3 Crushing, Screening, Sorting Noise from crushing, screening, and sorting will be minimal because of the small feed rates and because the process is wet 2.5.6.2.4 Power Generation Power for the processing plant will be generated using portable generators 2.5.6.3 Solid Waste Handling and disposal Solid discard material will be stored in approved containers and disposed of in approved landfills. 2.5.6.4 Hazardous Waste/Water Pollutants/Spills No hazardous waste will be generated on the site. No water will leave the property. Process water will be recycled into a lined pond. 2.5.6.4.1 Surface Water 2.5.6.4.2 Ground Water No ground water monitoring will occur 2.5.6.5 Emergency Response An emergency response plan will be developed 2.5.6.6 Monitoring and Reporting Monitoring and reporting will be included in the emergency response plan. PAGE | 14 OF 21 2.5.7 Wildlife/Endangered Species Protection It is not anticipated that any federally listed species will be impacted by the operations or reclamation steps taken in this proposal. 2.5.8 Protected Plant Species Handling There will be no new disturbance involved in processing the stockpiled inventory, therefore there will be no impact on any plant species. After the stockpiled inventory is completely processed, an impact study of proposed areas for exploration and mining will be provided prior to such work commencing. 2.5.9 Visual Impacts The closest community is Skull Valley located 3 miles to the west of the site. The site is not visible from Copper Basin Road 2.5.10 Cultural Resources There will be no new disturbances involved in processing the stockpiled inventory, therefore there will be no impact on any cultural sites. After the stockpiled inventory is completely processed, an impact study of proposed areas for exploration and mining will be provided prior to such work commencing. 2.6 FACILITIES 2.6.1 Ancillary Equipment and Facilities 2.6.1.1 Access and Haul Roads All access and haul roads already exist. 2.6.1.2 Power Generation and Distribution Portable power generation will be used for the entire site. Generally, the main power will run only during operating hours. One generator will operate 24 hours per day because of specific equipment requirements 2.6.1.3 Water Supply and Storage Water will be supplied from four wells on the site. Process water will be stored in a lined pond. The plant water is recycled through this pond. Make-up water will come from the wells. Water used for ancillary purposes will come from a 2000 gallon tank on site. 2.6.1.4 Explosives Storage There will be no explosives stored on site. 2.6.1.5 Fuel Storage Diesel fuel will be stored on site in a double wall above ground 500 gallon tank. PAGE | 15 OF 21 2.6.1.6 Maintenance Areas An 8' x 40' cargo container located at the processing plant will function as a maintenance shop. 2.6.1.7 Mine Office An 8' x 40' container located east of the processing plant. 2.6.1.8 Sanitary and Solid Waste Disposal Portable toilets will be used at the site. All solid waste will be hauled to an approved landfill. 2.6.1.9 Site Security A cable gate provides access security to the site. A 24-hour security guard may also be necessary to protect against vandalism and watch over any equipment that may be operating, such as power generators. 2.6.1.10 Fire Protection The site is located within the Central Yavapai Fire District, which provides fire protection to the area. In addition, Peeples Inc. will provide fire extinguishers on site and in vehicles. 2.7 ECONOMIC FEASIBILITY 2.7.1 Economic Summary NMC plans to produce about 619,380 oz of gold over a period of approximately 5 years. Assuming a royalty rate of 5% and average price of $1090 for gold less 20% for selling and refining, the state's annual revenue would be about $5,400,000 at the planned mining rate. Based on the most recent appraisal in 2006, the land is valued at $3600 per acre. The state's annual rental fee at $2.00 per acre for all 377 acres, including the disturbed area of approximately 3.5 acres where the previously mined ore is stored, would be $754. The state's cash flow is expected to be $5,400,000 + $754 = $5,400,754 per year for at least five years. The state's NPV at a discount rate of 10% over the approximate 5 year stored ore processing period would be $22,159,424. NMC plans to lease or joint venture the equipment, so the capital cost will be very low. NMC’s break-even cost is expected to be $340 per ounce of gold, plus state royalty and rental costs. NMC's estimated cash flow is estimated at $74,325,600 per year for at least 5 years, less state royalty and rental costs. 2.7.2 Commodity/Products. NMC plans to produce placer gold in the form of nuggets and gold dust. 2.7.3 Market Analysis Discussion. Gold is regarded as a store of value, meaning that its purchasing power is relatively constant over time. Gold is sold on the international market. The usual benchmark for the price of gold is known as the London Gold Fixing, a twice-daily (telephone) meeting of representatives from five bullion trading firms. There is also active gold trading based on the intra-day spot price, derived from gold-trading markets around the world. Like other investments and commodities, the price of gold is driven by supply and demand, including hoarding and disposal. Unlike most other commodities, hoarding and disposal play a much PAGE | 16 OF 21 bigger role in affecting the price Most of the gold ever mined still exists and is potentially able to come on to the market for the right price. Given the quantity of hoarded gold compared to the annual production, the price of gold is more subject to changes in sentiment rather than changes in annual production. According to the World Gold Council, annual mine production of gold over the last few years has been close to 2,500 metric tons. About 3,000 tons goes into jewelry or industrial/dental production, and around 500 tons goes to retail investors and exchange traded gold funds. This translates to an annual demand for gold to be 1000 tons in excess of mine production, which has come from central bank sales and other sources. Central banks and the International Monetary Fund play an important role in the gold price. At the end of 2004, central banks and official organizations held 19 percent of all above-ground gold as official gold reserves. The Washington Agreement on Gold, September 1999, limits gold sales by its members (Europe, United States, Japan, Australia, Bank for International Settlements and the International Monetary Fund) to less than 400 tonnes a year. European central banks, such as the Bank of England and Swiss National Bank, have been key sellers of gold. The Russian central bank and others have expressed interest in growing their gold reserves again. In early 2006, China, which holds 1.3% of its reserves in gold, announced that it was looking for ways to reposition more of its holdings into gold in line with other central banks. In general, gold becomes more desirable in times of: 1) Bank and investment firm failures. When investors fear failure their bank or investment firm, many move their savings or investments into durable commodities such as gold. 2) Low or negative real interest rates. If the return on bonds, equities and real estate does not adequately compensate for risk and inflation, the demand for gold and other alternative investments increases. An example of this is the period of "stagflation" that occurred during the 1970s and which led to an economic "bubble" in the price of precious metals. 3) War and other crisis. In times of crisis, people in some countries fear that their assets may be seized and that the currency may decline in value. Gold is viewed as a transportable, solid asset which will always buy the necessities. In times of great uncertainty the demand for gold rises. These factors, which are all active in different countries today, indicate that gold prices will likely stay high for the foreseeable future. From 1975 to the present, the price of Gold increased from $170 to $1200 per ounce recently. While there have been peaks and valleys, the trend of gold price is up. We are using a gold price of $1090 per ounce for all calculations. PAGE | 17 OF 21 2.7.4 COST 2.7.4.1 Pre-mine Development. Pre-mine development consists only of access roads and leveling of the concentration plant site, both of which have been done during the exploration and milling phase. Roads require minor improvement. Pre-mine development costs will be less than $5000 for about one week of dozer rental, fuel and operator. Weekly Operating Cost Equipment Rental ($/h r) Op. Cost ($/hr) Cat 330 Excavator 25 Ton Dump truck Alaskan 25 Plant Cat 938 Loader 20 KW Generator Conveyer Water Truck Total Weekly Cost $66.00 $34.00 $47.00 $44.00 $10.00 $18.00 $86.00 $35.00 $31.00 $28.00 $21.00 $6.00 $6.00 $29 Operator ($/hr) Rental (hr/wk) $20.00 $20.00 $20.00 $20.00 $0.00 $0.00 $20.00 40 40 40 40 40 40 8 Op time (hr/wk) 8 40 40 40 40 0 0 Total ($/wk) Remarks $4840 $3400 $3800 $3400 $640 $960 $1080 $18120 Monthly rental Monthly rental Monthly rental Monthly rental Monthly rental Monthly rental Daily rental 2.7.5 Break Even Price. NMC’s approximate break even price is $340 per ounce, plus state royalty and rental. PAGE | 18 OF 21 SECTION III : RECLAMATION AND CLOSURE PLAN (RCP 3.01 INTRODUCTION 3.1.1 Purpose and Scope The purpose of this Reclamation and Closure Plan (RCP) is to present the details of rehabilitation. The "Mining Operations" have ceased on this site. No new disturbance is planned. All of the Mining areas have been reclaimed. The ±5 Ac. Processing site, consisting of storage pits, access and haul roads, and the Plant site itself remain to be reclaimed. Upon completion of final reclamation, the site will appear as a gentle inclined sloping ridge. The end use will be open space and wildlife habit suitable for grazing. 3.1.2 Reclamation Summary Most of the reclamation required under the original Lease is complete. A $5,000 Reclamation Bond was posted when the Lease began. The Bond amount was increased to $15,000 in 1996. The completion of the Reclamation for the site will only take about 12 months since reclamation will continue to be concomitant with our mining processes. Reclaiming the storage pits by processing the fines and recovering the Precious Metals contained will provide revenue for Peeples Inc. and royalties for the State of Arizona. Finally, all improvements will be removed and the area treated in accordance with the Lease and Commissioner requirements. 3.02 RECLAMATION APPROACH The following four steps will be taken to accomplish the final reclamation of the site: 1. 2. Process the Pit concentrates that contain the valuable Precious Metals. There are approximately 279,000 tons of concentrates impounded that contain values. Process and concentrate the Precious Metals to a condition that they can be sold or removed to a smelter, Back fill pits with stockpiled overburden and Plant tailings. Grade the area to match the natural contours as mush possible. Remove access and haul roads. Reseed the area in accordance with the Lease and Commissioner 3.03 EQUIPMENT AND STRUCTURE All equipment located on the site will be removed upon completion of precious metals processing. It is estimated that dismantling and removal would take approximately 120 days. 3.04 WASTE DUMPS Any earth that may have been contaminated during operations, such as the maintenance shop, will be removed and disposed of at an approved location. 3.05 ROADS POWERLINES, WATERLINES, FENCES Any roads that were constructed as a part of the mining operations at this site will be removed and reseeded. Water bars will be placed in predetermined areas to stabilize growth and prevent water erosion. PAGE | 20 OF 21 There are no above ground power lines on the site. Any Underground lines will be removed when the portable generators are removed. The water wells will be capped and the lines running to the plant will be removed. There are no fences at the site, except the fence around fresh water re-circulating pond which will be removed during reclamation. 3.06 AREA PREPARATION The pond area will be backfilled and then graded to match the surrounding natural contours as much as possible. Fine growth media will be placed on top of the graded fill to aid the re-vegetation, Rock lined drainage trenches will be made on the hillside and along the bottom of the hill as a storm waterway. Water bars will be placed in predetermined areas to stabilize growth and prevent water erosion. 3.07 RE-VEGETATION/SEEDING The hillside, plant site and roads will be re-vegetated and seeded per the requirements of the Lease and the Commissioner. 3.08 SLOPE STABILIZATION Reclaimed slopes will be made to match the natural slopes as much as possible. Vegetation can provide sufficient stabilization for this type of slope. Seeding the slopes with a seed mix that will germinate quickly will assist in protection against soil erosion and aids in stabilization. Water bars will be placed in predetermined areas to stabilize growth and prevent water erosion. 3.09 EROSION AND DRAINAGE CONTROL Vegetation will provide most of the erosion control. Where needed, rock lined trenches will be placed for storm water run-off. Water bars will be placed in predetermined areas to stabilize growth and prevent water erosion. PAGE | 21 OF 21 Appendix A Geosyntec Analysis Evaluation of the Peeples Mine Arizona Concentrates Quantity, Skull Valley, Arizona September 10, 2007 200 East Del Mar Boulevard, Suite 250 Pasadena, CA 91105 PH 626.449.0664 FAX 626.449.0411 www.geosyntec.com 10 September 2007 Michael Sheppard Chief Executive Officer Nevada Mining Company, Inc. 4229 Warren Road Franklin, Tennessee 37067 Subject: Evaluation of the Peeples Mine Arizona Concentrates Quantity, Skull Valley, Arizona Dear Mr. Sheppard: Pursuant to your request of 13 July 2007, Geosyntec Consultants, Inc. (Geosyntec), is pleased to provide this report evaluating the quantity of Arizona Concentrates within pits located at the Peeples Mine in Skull Valley, Arizona (Figure 1), owned by the Nevada Mining Company (NMC). The Arizona Concentrates are mineral concentrates that contain various precious metals. The concentrates are stockpiled within two pits at the Skull Valley lease, comprising an Upper Pit and a Lower Pit that is divided into three smaller sub-pits. This work was performed in accordance with our proposed scope of work, dated 10 August 2007, with the exceptions noted below. Field work was performed by Mr. Walt Grinyer, P.G. of Geosyntec and Mr. Jim Hasbrouck, G.P. of Hasbrouck Geophysics, Inc. This report was prepared by Dr. Jim Finegan, P.G., C.Hg. and has been reviewed by Mr. Sam Williams, P.G., C.Hg. of Geosyntec Consultants (Geosyntec), in accordance with the review policies of the firm. SCOPE OF WORK Geosyntec’s scope of work included review of existing aerial photographs and site assay reports and discussions with NMC personnel regarding the approximate locations and dimensions of the pits. This was followed by two-dimensional (2D) surface seismic tomography surveys to aid in identifying the bottom and sidewalls of the pits. These data were used to calculate estimated volumes of Arizona Concentrates within each pit. Based on this scope of work, recommendations for further subsurface investigation are made below. HA1086/SV07-001.VolRpt.doc Mr. Michael Sheppard 10 September 2007 Page 2 BACKGROUND The NMC Skull Valley site consists of two pits that have been backfilled with ore concentrates composed of minerals containing precious metals. These ore concentrates, stockpiled on site during previous mining activities, are referred to as Arizona Concentrates within documents provided by NMC. The Arizona Concentrates comprise a major asset of NMC, and the volume of these materials may affect the sale price. However, the dimensions of the pits at the Skull Valley site were not clearly defined prior to the backfilling with the ore concentrate, although several estimates of the volumes of the pits have been produced. It is our understanding that the pits were excavated into the native material at the site and the sidewalls are generally near vertical with berms between separate areas of the pits. In addition, portions of the pits may be benched where excavations achieved greater depths. EVALUATION OF ARIZONA CONCENTRATES Site History Review Pursuant to the scope of work defined above, Geosyntec reviewed available documents and aerial photographs of the site in preparation for 2D surface seismic surveys of the Upper and Lower Pits. In addition, site conditions were discussed with NMC management. Accompanying Geosyntec and the geophysicist to the site for the seismic surveys were Mr. Michael Sheppard of NMC, Mr. Bill Berridge (geologist), and Mr. Pete Rushbrook. 2D Seismic Tomography As described in detail in the attached report by Hasbrouck Geophysics, Inc. (Appendix A), a high resolution two-dimensional (2D) surface tomographic seismic survey across each of the pits was performed on 17 to 18 August 2007, to allow resolution of the contact between the processed ore concentrate and the native surrounding material. Figure 2 shows the locations of the lines along which seismic data were acquired. Due to inaccessible terrain and relatively narrow pit widths, lateral seismic lines could not be run, so the volume estimates provided below are limited by the estimated pit widths and information provided by NMC management. In addition, physical access limitation at the west end of the Upper Pit seismic line prevented extension of the line in this direction and a pit just south of the Upper Pit could not be surveyed due to lack of access. The seismic line along the Lower Pit was run relatively close to the southern edge of the west and middle sub-pits because of the presence of large debris piles in the center of the west sub-pit. However, the drilling program proposed below to confirm seismic data will also provide additional data on pit dimensions, thus refining the pit volume estimates. HA1086/SV07-001.VolRpt.doc Mr. Michael Sheppard 10 September 2007 Page 3 The primary principal of the seismic data collection is that the partially processed ore concentrate will have a significantly different velocity from the surrounding native material. This interface between the assumed lower velocity ore concentrate and the higher velocity native material provides the contact for reflecting the seismic signal. The results of field work performed at the site indicate a strong velocity contrast between bedrock and unconsolidated materials. Seismic data were acquired by detecting seismic waves generated by an artificial energy source, in this case a 20-pound sledge hammer striking a square aluminum plate on the ground at specific intervals (40 feet) along each seismic line. Seismic waves were detected by geophones placed at regular intervals (20-foot spacing) along the test line and digitized data were recorded on a seismograph (hard disc) and subsequently downloaded to a computer for processing and interpretation. The first arrivals used in seismic tomography may be refractions, reflections, or diffractions, which is important for this project because of the possible vertical pit walls. A 20foot spacing interval for geophones was used for both the Upper and Lower Pits. A 10-foot interval was initially used along a portion of the Lower Pit seismic line to evaluate bedrock resolution. The 10-foot interval did not indicate the high velocity layer expected at the base of the pits and therefore the 20-foot geophone interval was used. The response observed in the geophones from the sledge hammer using 20-foot spacing alleviated this concern. As shown in the attached report (Appendix A), processed seismic data are displayed on depthversus-velocity cross sections. Elevation-velocity cross sections that show relative groundsurface elevations are also provided. The attached seismic data and the pit limits provided by NMC personnel were used to calculate pit volumes. Volumes were calculated using AutoCAD Land Development software, based on the pit boundaries shown on Figure 2 and estimated pit depths derived from the seismic data. Seismic velocities ranging from 4,000 to 4,500 feet per second (ft/sec) were used to delineate the base of ore concentrates on seismic cross-sections. This value was selected as a conservative assumption, but it also generally corresponds to where seismic velocity contours tended to condense together, particularly on the Upper Pit seismic section. The compressing of velocity contours is assumed to generally represent the base of the ore-filled pits. A delay-time analysis was also performed using a regression method, in which a straight line is fit by least squares to the arrival times representing the velocity layer and average velocities are computed by taking the reciprocals of the weighted average of the slopes of the regression lines. The average regression value calculated was approximately 4,500 ft/sec, further supporting the use of 4,500 ft/sec as the base of the ore concentrate. HA1086/SV07-001.VolRpt.doc Mr. Michael Sheppard 10 September 2007 Page 4 Note that additional non-ore deposits may have washed or been pushed into the pits on top of the ore concentrate. Seismic data suggest that this overburden may be several feet thick in places, indicating that calculated volumes may be over-estimated if this material is not subtracted from the calculations. However, it is not expected to represent a significant portion of the material filling the pits. A reported distinctive dark coloring of the ore concentrate may allow for evaluation of the overburden thickness during confirmatory drilling. UPPER PIT The boundaries of the Upper Pit shown on Figure 2 are irregular, with a possible berm, indicated by seismic data, across the western half of the pit. Seismic data also suggest that the Upper Pit extends further west than indicated by NMC management, as shown on Figure 2 where two possible pit boundaries are shown. This extra area has been included in the volume calculations, and should be confirmed by drilling. Based on the seismic data, an average depth of 40 feet is assumed for the western portion the Upper Pit and a depth ranging from 40 feet to 20 feet is assumed for the eastern portion where the base appears to slope upward. Rather than use a range of values for the pit bottom where it appears to slope, an average depth of 30 feet was used. Because of inaccessibility due to steep walls and abundant vegetation, another pit south of the Upper Pit (Figure 2; Upper - south pit) could not be seismically surveyed. However, available data suggest that this pit contains ore concentrate. Volume calculations for this pit are based on a depth estimated during recent excavation (approximately 25 to 30 feet) and dimensions determined by visual observation of the aerial photograph and historical documents provided by NMC. The table below summarizes estimated pit depths, surface areas, and volumes/tonnage for the eastern and western sub-pits, which are divided by the inferred berm, and the Upper southern pit. The eastern sub-pit calculations are provided as a range of values, one set of values for the NMC-indicated boundary and one set for the area east of the berm. LOWER PIT The Lower Pit has been divided into three separate sub-pits, the west, middle, and east (Figure 2). The boundaries of these pits were estimated using historical documents with modifications as follows: the middle sub-pit was extended to occupy the depressed area indicated on the aerial photograph, and the east sub-pit was extended at least 200 feet further to the east. The west subpit was reported in historical documents to be the deepest at up to 90 feet. However, use of the 4,500 ft/sec base limit would restrict the average depth of this pit to no more than 35 feet. There is also a low-velocity anomaly at depth at this location, suggesting that there may be a deeper section of the pit down to approximately 90 feet. The seismic data also suggest that there may be HA1086/SV07-001.VolRpt.doc Mr. Michael Sheppard 10 September 2007 Page 5 buried benches within this pit that may have been used to excavate the pit to the reported depth of 90 feet. Volume calculations for this pit have been performed assuming that about 75 feet of its west end are 90 feet deep (1) and the remainder is 35 feet deep (2). This assumption is based on the approximate width of the apparent seismic anomaly. There is no clear separation in the seismic data between the west and middle pits, although a berm between them may be indicated, as described in the seismic survey report between source points 99.5 and 101.5 (Lower Pit – Elevation Section). Volume calculations were performed separately for these pits (west and middle), because if a berm is located between them, it may have similar velocity to the ore concentrate while still separating the two sources. Using the 4,500 ft/sec seismic contour provides an average depth of about 27.5 feet for the middle pit. On the seismic cross sections, this pit approximately extends from source point 103 to 111.5 where the 2,000 ft/sec contour is close to the ground surface. Seismic data suggests an average depth of about 35 feet for the east pit, based on the 4,500 ft/sec contour. The recommended drilling program should be used to verify actual pit depth. The table below includes estimated depths, surface areas, volumes, and tonnage for the west, middle, and east sub-pits of the Lower Pit. PIT VOLUMES AND ARIZONA CONCENTRATES TONNAGE Upper and Lower Pit Estimated Depths and Volumes AVERAGE DEPTH (feet) SURFACE AREA (square feet) VOLUME (cubic yards) TONS* UPPER PIT – WEST 40 10,239 15,169 21,236 UPPER PIT – EAST 30 22,872 25,414 35,580 UPPER PIT – SOUTH** 27.5 29,576 30,124 42,174 LOWER PIT – WEST 1 90 7,754 25,847 36,186 LOWER PIT – WEST 2 35 13,907 18,027 25,238 LOWER PIT – MIDDLE 27.5 35,396 36,051 50,471 35 37,525 48,643 68,100 LOWER PIT - EAST * Tonnage was calculated assuming 1.4 tons per cubic yard, based on historical documents. ** This pit was not seismically surveyed; the indicated depth is based on recent excavation and the outline was estimated by visual assessment of the aerial photograph; both should be field confirmed. HA1086/SV07-001.VolRpt.doc Mr. Michael Sheppard 10 September 2007 Page 6 The total estimated volume of Arizona Concentrates is 199,275 cubic yards (278,985 tons), based on both the seismic data and historical site data for surface areas and estimated pit depths from seismic data as indicated above. These calculations also assume that the pits have vertical sides and flat bottoms. The tonnage conversion value of 1.4 is derived from historical assay documents and should be confirmed by testing. The recommended drilling program below will help to verify the pit depths and confirm the seismic data as well as refine the indicated pit boundaries, particularly the Upper Pit, which may be larger than is shown on Figure 2, and the un-surveyed Upper south pit. RECOMMENDATIONS Based on the seismic data acquired on 17 to 18 August 2007, and the physical limitations of data acquisition, several boreholes should be drilled in both the Upper and Lower Pits to refine the volume calculations presented herein. All drilling should proceed to refusal (e.g., bedrock) and samples should be collected either continuously or at a regular interval (i.e., 5 feet) using a drivesampling method to confirm the lithology indicated by cuttings returned to ground surface during drilling. These include four drilling locations in the Upper Pit to refine the depth estimates and pit boundaries, which may extend further than previously believed both to the east and west. Drilling should also be performed in the depression south of the Upper Pit. We understand that access to this pit may be difficult, so excavation may be required to provide an access ramp. Two drilling locations are recommended for the Lower west sub-pit: one to evaluate ore-concentrate depth in the western portion of this sub-pit and one to help define the northern pit boundary. One drilling location is recommended in the Lower middle sub-pit to evaluate ore concentrate depth. Two locations are recommended for the Lower east sub-pit to define both ore-concentrate depth at either end of this sub-pit and to verify its eastern extent. Additional shallow boreholes may also be drilled at the expected edges of the pits to verify their widths. Potholing using a backhoe may also be used for this purpose. Geosyntec can provide a cost estimate upon request to perform the recommended drilling program. LIMITATIONS Subsurface investigations and geophysical surveys are inherently limited to data derived from samples taken or tests performed at selected locations, and the number of locations, samples and tests are commonly based on cost-benefit judgments and the client’s budgetary concerns. Due to these inherent limitations, it must be recognized that actual conditions may vary from those predicted on the basis of such limited data, despite the use of professional care. HA1086/SV07-001.VolRpt.doc Mr. Michael Sheppard 10 September 2007 Page 7 CLOSURE Geosyntec appreciates this opportunity to be of service to NMC. questions, please contact Jim Finegan at (626) 449-0664 ext. 202. Should you have any Sincerely, Jim Finegan, PhD, CHg Senior Hydrogeologist Walt Grinyer, PG Senior Hydrogeologist Attachments: Figure 1 – Site Location Map Figure 2 – Site Plan Appendix A – “Skull Valley Seismic Survey,” Hasbrouck Geophysics, Inc., 23 August 2007 HA1086/SV07-001.VolRpt.doc Hasbrouck Geophysics, Inc., Skull Valley Seismic Survey August 23, 2007 TABLE OF CONTENTS INTRODUCTION .......................................................................................................................... 1 METHODOLOGY ......................................................................................................................... 1 DATA ACQUISITION................................................................................................................... 1 DATA PROCESSING .................................................................................................................... 2 RESULTS ....................................................................................................................................... 2 Upper Pit ..................................................................................................................................... 3 Lower Pit..................................................................................................................................... 4 RECOMMENDATIONS ................................................................................................................ 5 LIMITATIONS OF INVESTIGATION......................................................................................... 5 Figures Upper Pit Station Locations Map Lower Pit Station Locations Map Caterpillar D8 Ripping Chart Upper Pit Elevation Section Upper Pit Depth Section Lower Pit 20 Feet Geophone Interval Elevation Section Lower Pit 20 Feet Geophone Interval Depth Section Lower Pit 10 Feet Geophone Interval Elevation Section Lower Pit 10 Feet Geophone Interval Depth Section Nevada Mining Company, Inc. August 23, 2007 Skull Valley Seismic Survey Page i INTRODUCTION Two-dimensional (2D) surface seismic tomography surveys were conducted on 17 and 18 August 2007 at Nevada Mining Company, Inc.’s Skull Valley mine near Skull Valley, Arizona. The purpose of the seismic survey was to aid in the determination of the volume of ore concentrate within waste pits from previous mining operations. METHODOLOGY Surface seismic tomography surveys essentially consist of recording seismic waves that have been generated by artificial sources, observing the arrival times of these waves, and producing cross-sections of variations in subsurface seismic wave velocities that can then be related to geology. The source of seismic energy for relatively shallow surface surveys is generally either a sledgehammer or weight-drop system, primarily dependent upon target depths and logistics. In surface surveys the seismic waves are detected by geophones that consist of a coil suspended by a spring with magnets build into the case. A seismic wave moves the case and the magnets while the coil remains relatively stationary because of its inertia. The relative movement of the magnetic field with respect to the coil generates a voltage across the coil with the voltage proportional to the relative velocity of the coil to the magnets. The electrical voltages produced by the geophones are transmitted back to a seismograph via cables. DATA ACQUISITION Surface seismic data were acquired along two lines (one each in the Upper and Lower Pits as shown in the Station Locations Maps) in a manner suitable for 2D tomographic analyses using a leased 24-channel Geometrics SmartSeis seismograph in 32-bit floating-point format, 1024 samples per channel, 0.25 ms sample interval and 256 ms record length. Within the Upper Pit Geospace 14-Hz geophones were placed at intervals of twenty feet with distances measured by the takeout (connection point for the geophones) interval along the geophone spread cable. Within the Lower Pit the data were acquired along the entire line at geophone intervals of twenty feet and also along a portion of the line at intervals of ten feet (with the ten feet intervals measured using a tape). The seismic source was a twenty-pound sledgehammer struck vertically upon an approximately two feet square aluminum plate. A PEG-40 (Propelled Energy Generator) accelerated weight-drop system with an 88-pound ram weight that could be mounted on the trailer receiver hitch of a pickup truck was available but was not used because the quality of the sledgehammer data was considered excellent and access to portions of the lines was not possible with a vehicle. For proper 2D tomographic analyses, seismic data must be acquired with several source points along each geophone spread and for longer profiles subsequent spreads must be overlapped by 50%. A total of 14 source points were used for each spread of 24 geophones with the Upper Plate line consisting of one spread of geophones while the 20 feet geophone interval data along the Lower Plate line consisted of two spreads overlapped by 12 geophones. The Lower Pit ten feet geophone interval line consisted of one geophone spread. The seismic data were stacked nominally three to four times (depending upon offset and noise) at each source point to increase the signal-to-noise ratio. Stacking, or signal enhancement, involved repeated source impacts at the same point into the same set of geophones. For each source point, the stacked data were recorded into the same seismic data file and theoretically the seismic signal arrived at the same Nevada Mining Company, Inc. August 23, 2007 Skull Valley Seismic Survey Page 1 time from each impact and thus was enhanced, while noise was random and tended to be reduced or canceled. The data were recorded on the hard disk of the seismograph and downloaded to a personal computer for subsequent data processing and interpretation. A total of 70 24-channel seismic records (or 1680 traces) were acquired for this project. The overall quality of the seismic data was excellent with clearly identifiable first breaks (first arrival of seismic energy) present along all the spreads. DATA PROCESSING Seismic tomography is defined as a method for finding the seismic velocity distribution within the subsurface from a multitude of observations using combinations of source and receiver locations. The subsurface is divided into cells and the seismic data are expressed as line integrals along raypaths through the cells. A velocity is assigned to each cell and traveltimes are calculated by tracing rays through the model. The results are compared with observed times, the model is modified, and then the process is repeated iteratively to minimize errors. The seismic tomography data for this project were processed using the Rayfract (version 2.74) computer software program developed by Intelligent Resources Inc. of Vancouver, BC, Canada. The models produced by the Rayfract tomography program use multiple signal propagation paths (e.g., refraction, reflection, transmission and diffusion) that comprise a first break. The first arrival of seismic energy at each geophone is chosen as the first significant variation from a somewhat straight line. The selection of first arrival times is a tedious procedure, particularly since there are almost 1700 individual traces involved in this project, but it is very important. These arrival or traveltimes are then modeled and iteratively compared with the original times. The modeling for this project consists of delta-t-v and WET (wavepath eikonal traveltime) methods. The delta-t-v turning ray inversion method delivers continuous depth versus velocity profiles for all geophones, while the WET method automatically adjusts the subsurface velocity model until the synthetic times optimally match the first arrival times. The modeled traveltimes are used in the tomographic calculations to determine the subsurface seismic velocity distribution and only the results from the WET method are presented. Location, elevation or depth, and velocity values for each profile are converted into a format compatible with the Golden Software Surfer (version 8.00) computer program and presented as individual elevation and depth sections. All the figures within this report are not referenced by number because each map or section is clearly identified. RESULTS With surface seismic tomography a full representation of the subsurface velocities is obtained and different geological units can often be identified based upon their velocities even if those velocities are relatively close together in value. Additionally, first breaks used in seismic tomography can be from refractions, reflections, transmissions or diffusions and thus, to a certain extent, velocity inversions can be mapped. Surface seismic tomography results are generally Nevada Mining Company, Inc. August 23, 2007 Skull Valley Seismic Survey Page 2 considered to present a more geologically representative view of the subsurface than other shallow refraction seismic methods (e.g., delay-time). Previous work to aid in the determination of the volume of ore concentrate within both the Upper and Lower Pits consisted of the use of an excavator. According to the operator of the machine it was possible to excavate to a depth of 35 feet from benches within portions of the pits or to a depth where suspected bedrock was encountered (i.e., no further excavation could be made because the material was too hard). Caterpillar Inc. has prepared charts that estimate the rippability of material relative to geology and seismic velocities for their models D8 through D11 tractors. As seen in the ripping chart figure, igneous rocks can be ripped up to a seismic velocity of around 6000 feet per second using a D8. It is improbable that that the excavator used in the pits could penetrate material as well as a D8 ripper so the excavator’s maximum depth probably ended within material with velocities of no more than about 4000 to 5000 feet per second. From seismic investigations in similar geologic environments, it is assumed that velocities less than about 1500 feet per second are primarily representative of unconsolidated and dry overburden, weathered bedrock velocities range from around 6000 or 7000 to perhaps about 9000 or 10000 feet per second, and competent bedrock has velocities greater than about 9000 or 10000 feet per second. Without confirming data from drill holes it is only possible to assign rough velocity values to the ore concentrate. A possible conservative range of seismic velocities for the ore concentrate is from about 1500 to 4000 feet per second, while a less conservative range may be from about 1500 to 5000 feet per second. However, it must be kept in mind that sedimentary material may also have velocities similar to those preliminarily assigned to what might be ore concentrate. It is considered unlikely that the ore concentrate will have seismic velocities less than about 1500 feet per second because that is generally more applicable to highly unconsolidated material. The 4000 to 5000 feet per second upper end velocity for ore concentrate material is estimated by what an excavator could possibly penetrate and interpretation of the seismic data. The elevation and depth sections shown in this report have highlighted velocity contours of 1500, 4000 and 5000 feet per second to facilitate calculation of the amount of possible ore concentrate. However, it must be stressed and stated again that it is not possible to accurately assign velocity values to the ore concentrate material without drill hole data. Upper Pit The results of the seismic modeling using Rayfract are originally output as elevation sections that are then converted to depth sections. Consequently, there are sometimes minor variations (or what appears as noise) within the depth sections because of the arithmetic conversion operation. Within the Upper Pit some historical documents state that the depth of ore concentrate is 90 feet deep which may be approached near the southwest end of the seismic line using the 5000 feet per second upper end velocity limit although there appears to be some higher velocity material from depths of about 40 to 60 feet that separate shallower and deeper lower target velocities. To around 240 feet, or so, along the line the estimated upper end target velocities of 4000 to 5000 feet per second are relatively constant at about 40 feet depth and the target lower end velocity material of 1500 feet per second is generally shallow at depths less than about ten feet. Nevada Mining Company, Inc. August 23, 2007 Skull Valley Seismic Survey Page 3 Beyond about 240 feet along the line in the Upper Pit (wherein the pit becomes progressively more narrow) material with velocities less than 1500 feet per second becomes absent (at about source point 219.5 or 370 feet along the line) and there is a definite upward dip in the subsurface material. The source point at 225.5 is along the side of the hill within natural sediments thus the material downdip from that point with velocities greater than about 2500 feet per second may actually be natural sediments versus ore concentrates. A knob of relatively higher velocity material from about 120 to 175 feet along the Upper Pit line beginning at a depth of around 50 feet and extending beyond 100 feet depth in addition to another shallower knob with the same horizontal range that is present from around 20 to 35 feet depth may be indications of a possible berm between sub-pits. Lower Pit In historical documents the Lower Pit is identified as having a depth of 60 feet. Along portions of the line (from approximately 0 to 240 and 380 to 540 feet) if the arbitrary upper end velocity limit for the possible ore concentrate is increased to about 5500 feet per second then the depth of 60 feet is met or exceeded. In particular, from around 90 to 180 feet along the line there appears to be material present with velocities up to around 5500 feet per second to depths approaching 120 feet. Along other portions of the line the arbitrary upper end velocity of 5000 feet per second is shallower and generally around 35 feet depth. Within the geophysical data the indication of the berm between about source points 99.5 and 101.5 is not present within the shallow section (i.e., to a depth of about 40 feet), but may be manifested within the deeper data (if an increased upper end velocity of 5500 feet per second is used) as benches with relatively vertical boundaries extending from around 40 to 70 feet and 70 to 120 feet depth from about 180 to 240 feet along the line. These possible benches may indicate the northeastern side of what is termed the west lower sub-pit. The southwestern side of the west lower sub-pit may be indicated at the velocity limit of 5000 feet per second as a variation in depth (between approximately 26 and 37 feet) from about 80 to 100 feet along the line and as moderate angle contour level variations of the increased upper limit value of 5500 feet per second to a maximum depth of about 120 feet at approximately 160 feet along the line. The southwestern side of the central lower sub-pit (around source point 103.5) is not seen within either the shallow or deeper geophysical data, however material with velocities equal to or less than about 4500 feet per second shallow consistently to within 40 or 50 feet the berm at the northeastern edge of this pit (approximately source point 111.5). Also, from about 400 to 450 feet along the line there is an anomalous increase in material with velocities approaching the upper end velocity of 5000 feet per second. Note that the ten feet geophone interval line shows similar results with maybe a slight indication of the berm to the southwest and a shallowing of materials with velocities less than about 4500 feet per second to the northeast. The southwestern edge of what is termed the east lower sub-pit is evident within the geophysical data as an increase in thickness of material up to at least a velocity of around 5000 feet per second just before source point 115.5 (approximately 520 feet along the line). The thickness of this range of material remains relatively constant at about 35 or 40 feet to about source point 135.5 after which it shallow considerably. Therefore, from the geophysical data it appears that Nevada Mining Company, Inc. August 23, 2007 Skull Valley Seismic Survey Page 4 the east lower sub-pit may extend from about source point 115.5 to 135.5 (approximately 520 to 930 feet along the line). RECOMMENDATIONS As stated previously, it must be stressed that it is not possible to accurately assign seismic velocity values to the ore concentrate material without drill hole data. Therefore, the only way to determine the actual composition of the subsurface material within either the Upper or Lower Pits is through drilling. Within the Upper Pit the following drill locations are recommended: 1. Halfway between the flags at 221.5 and 223.5 to an approximate depth of 80 feet to investigate whether material with velocities from about 2500 to 5000 feet per second are natural sediments or ore concentrate. 2. At station 211.5 to an approximate depth of 45 feet to determine the actual limits of suspected ore concentrates. 3. Halfway between the flags at 201.5 and 203.5 to an approximate depth of 90 feet to determine the actual limits of suspected ore concentrates, to determine the composition of material at depths from about 40 to 65 feet depth and to determine if ore concentrates are present at depths approaching 90 feet. The Lower Pit recommended drill locations are as follows: 1. Within the west sub-pit, halfway between the flags at 95.5 and 97.5, if access is possible, to an approximate depth of at least 100 feet to investigate if material beyond a depth of about 35 feet and with velocities up to about 5500 feet per second are natural sediments or ore concentrate. 2. Within the central sub-pit, halfway between the flags at 109.5 and 111.5 to an approximate depth of 50 feet to determine the actual limits of suspected ore concentrates and if material with velocities between 4000 and 5000 feet per second are natural sediments or ore concentrate. 3. Within the east sub-pit, halfway between the flags at 117.5 and 119.5 to an approximate depth of 40 feet to determine the actual limits of suspected ore concentrates. 4. Within the east sub-pit at station 133.5 to an approximate depth of 35 feet to determine the actual limits of suspected ore concentrates and the horizontal extent of the pit. LIMITATIONS OF INVESTIGATION This survey was conducted with state-of-the-art instrumentation operated by an experienced and licensed geophysicist, the data were processed with commercial software packages utilized on projects with similar objectives, and the results were interpreted by an experienced and licensed geophysicist. However, no warranty, expressed or implied, is made as to the results and professional advice included within this report. The findings of this report are valid as of the present date. However, changes in the conditions of a property can and do occur with the passage of time, whether they be due to natural processes or the work of people on this or adjacent properties. Accordingly, the findings of this report may Nevada Mining Company, Inc. August 23, 2007 Skull Valley Seismic Survey Page 5 be invalidated wholly or partially by changes outside of our control. Therefore, this report is subject to review and revision as changed conditions are identified. Nevada Mining Company, Inc. August 23, 2007 Skull Valley Seismic Survey Page 6 Nevada Mining Company, Inc. Upper Pit -- Station Locations Map 2D Surface Seismic Tomography Survey 400 226 224 300 222 Relative Northing (feet) 220 218 200 216 214 212 100 210 208 206 204 0 202 200 -100 -100 0 100 200 Relative Easting (feet) 300 400 Station Hasbrouck Geophysics, Inc. Line2GeophoneLocations.grf Relative Elevation (feet) Nevada Mining Company, Inc. Upper Pit -- Elevation Section 2D Surface Seismic Tomography Survey 20 Feet Geophone Interval 225.5 20 10 200 201.5 207.5 205.5 209.5 223.5 203.5 221.5 211.5 213.5 215.5 217.5 219.5 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100 -110 -120 -130 -140 -150 -40 0 40 80 120 160 200 240 280 320 360 400 440 480 520 Southwest Northeast Distance along line (feet) Velocity (ft/sec) 12000 11000 10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 Vertical Exaggeration = 2 Source Point Hasbrouck Geophysics, Inc. Line2Elevation.srf Nevada Mining Company, Inc. Upper Pit -- Depth Section 2D Surface Seismic Tomography Survey 20 Feet Geophone Interval Velocity (ft/sec) 12000 Depth (feet) 200 201.5 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100 -110 -120 -130 -140 -150 -40 0 Southwest 203.5 205.5 207.5 209.5 211.5 213.5 215.5 217.5 219.5 221.5 223.5 225.5 11000 10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 40 80 120 160 200 240 280 320 Distance along line (feet) 360 400 440 480 520 Northeast Vertical Exaggeration = 2 Source Point Hasbrouck Geophysics, Inc. Line2Depth.srf Nevada Mining Company, Inc. Lower Pit -- Station Location Map 2D Surface Seismic Tomography Survey 1000 900 800 Relative Northing (feet) 700 600 500 400 300 200 100 96 98 88 90 92 94 0 100 102 104 106 108 110 112 114 116 118 120 122 136 134 132 130 128 126 124 10 ft geophone interval -100 -100 0 100 200 300 400 500 600 Relative Easting (feet) 700 800 900 1000 Station (20 ft geophone interval) Hasbrouck Geophysics, Inc. Line1GeophoneLocations.grf Nevada Mining Company, Inc. Lower Pit -- Elevation Section 2D Surface Seismic Tomography Survey 20 Feet Geophone Interval Relative Elevation (feet) 10 ft geophone interval line Velocity (ft/sec) 20 115.5 117.5 119.5 121.5 123.5 125.5 127.5 129.5 131.5 133.5 135.5 137 97.5 99.5 101.5 91.5 95.5 10 88 89.5 93.5 103.5 105.5 107.5 109.5 111.5 113.5 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100 -110 -120 -130 -140 -150 -40 0 40 80 120 160 200 240 280 320 360 400 440 480 520 560 600 640 680 720 760 800 840 880 920 960 Southwest Northeast Distance along line (feet) 12000 11000 10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 Vertical Exaggeration = 2 Source Point Hasbrouck Geophysics, Inc. Line1-20Elevation.srf Nevada Mining Company, Inc. Lower Pit -- Depth Section 2D Surface Seismic Tomography Survey 20 Feet Geophone Interval Velocity (ft/sec) 10 ft geophone interval line Depth (feet) 88 89.5 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100 -110 -120 -130 -140 -150 -40 0 Southwest 91.5 40 93.5 95.5 97.5 99.5 101.5 103.5 105.5 107.5 109.5 111.5 113.5 115.5 117.5 119.5 121.5 123.5 125.5 127.5 129.5 131.5 133.5 135.5 137 80 120 160 200 240 280 320 360 400 440 480 520 560 600 640 680 720 760 800 840 880 920 960 Northeast Distance along line (feet) 12000 11000 10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 Vertical Exaggeration = 2 Source Point Hasbrouck Geophysics, Inc. Line1-20Depth.srf Nevada Mining Company, Inc. Lower Pit -- Elevation Section 2D Surface Seismic Tomography Survey 10 Feet Geophone Interval Velocity (ft/sec) 12000 11000 100 101.5 10000 Relative Elevation (feet) 10 103.5 105.5 107.5 109.5 111.5 113.5 115.5 117.5 119.5 121.5 123.5 125 0 9000 8000 -10 7000 -20 6000 5000 -30 4000 -40 -20 0 Southwest 20 40 60 80 100 120 140 160 180 Distance along line (feet) Vertical Exaggeration = 2 200 220 240 Northeast 3000 2000 1000 Source Point Note: Source Point locations are not the same as along 20 feet geophone interval line and do not correlate to flags in the field Hasbrouck Geophysics, Inc. Line1-10Elevation.srf Nevada Mining Company, Inc. Lower Pit -- Depth Section 2D Surface Seismic Tomography Survey 10 Feet Geophone Interval Velocity (ft/sec) 12000 11000 10000 Depth (feet) 0 100 101.5 103.5 105.5 107.5 109.5 111.5 113.5 115.5 117.5 119.5 121.5 123.5 125 9000 8000 -10 7000 -20 6000 5000 -30 4000 -40 -20 0 Southwest 20 40 60 80 100 120 140 160 180 Distance along line (feet) 200 220 240 Northeast 3000 2000 Vertical Exaggeration = 2 1000 Source Point Note: Source Point locations are not the same as along 20 feet geophone interval line and do not correlate to flags in the field Hasbrouck Geophysics, Inc. Line1-10Depth.srf Caterpillar D8 Ripping Chart Hasbrouck Geophysics, Inc. Station 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 X -20 -0.07556 19.84889 39.77333 59.69778 79.62222 99.54667 119.4711 139.3956 159.32 178.1139 196.9079 215.7018 234.4957 253.2896 272.0836 290.8775 309.6714 328.4654 347.2593 366.0532 384.8471 403.6411 422.435 441.2289 460.0229 478.8168 497.6107 516.4046 535.1986 553.9925 572.7864 591.5804 610.3743 629.1682 647.9621 666.7561 685.55 703.6758 721.8017 739.9275 758.0533 776.1792 794.305 812.4308 830.5567 848.6825 866.8083 884.9342 903.06 Y -20 -18.2567 -16.5133 -14.77 -13.0267 -11.2833 -9.54 -7.79667 -6.05333 -4.31 2.530357 9.370714 16.21107 23.05143 29.89179 36.73214 43.5725 50.41286 57.25321 64.09357 70.93393 77.77429 84.61464 91.455 98.29536 105.1357 111.9761 118.8164 125.6568 132.4971 139.3375 146.1779 153.0182 159.8586 166.6989 173.5393 180.3796 187.22 195.6725 204.125 212.5775 221.03 229.4825 237.935 246.3875 254.84 263.2925 271.745 280.1975 288.65 Elev 0 0 1 6 6 3 3 3 6 9 8 6 11 11 5 2 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2 11 12 11 11 11 11 11 11 11 11 11 11.08333 11.16667 11.25 11.33333 11.41667 11.5 11.58333 11.66667 11.75 11.83333 11.91667 12 StaEvery2 88 90 92 94 96 98 100 102 104 106 108 110 112 114 116 118 120 122 124 126 128 130 132 134 136 Sta X 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 -20 -1.874 16.252 34.378 52.504 70.63 84.77143 98.91286 113.0543 127.1957 141.3371 155.4786 169.62 179.62 189.62 199.62 209.62 221.092 232.564 244.036 255.508 266.98 278.452 289.924 301.396 312.868 324.34 Y -20 -11.548 -3.096 5.356 13.808 22.26 36.40143 50.54286 64.68429 78.82571 92.96714 107.1086 121.25 138.57 155.89 173.21 190.53 206.913 223.296 239.679 256.062 272.445 288.828 305.211 321.594 337.977 354.36 Elev 2 2 1.666667 1.333333 1 1.75 2.5 3.25 4 4 0 0 0 0 0 0 0 0 0 0 0 0 0.666667 1.333333 2 16 20 StaEvery2 200 202 204 206 208 210 212 214 216 218 220 222 224 226 Appendix B Skull Valley Advanced Analytical Assay Assay No. 81117 Dated: October 3, 2008 Appendix B Skull Valley Additional Advanced Analytical Assays Dated: December 3, 2007 Appendix C Skull Valley Site Features and Pit Map N EVADA M INING C OMPANY (NMC, Inc.) NORTH SKULL VALLEY, ARIZONA S ETTLING PONDS SITE FEATURES MAP (RECLAIMED) www.nmcinc.com L OWER P IT E AST L OWER P IT M IDDLE L OWER P IT W EST 2 L OWER P IT W EST 1 (RECLAIMED) TAILINGS PILE U PPER P IT W EST U PPER P IT S OUTH R ETENTION P OND P ROCESSING F ACILITIES (DISASSEMBLED & SOLD) PROCESSED ORE STORAGE AREA (FIRST STAGE) NOTE: ALL IDENTIFIED AREAS ARE APPROXIMATE AND SUBJECT TO FIELD VERIFICATION. Copyright 2009©NMC,Inc 0’ 50’ 100’ 200’ SCALE: 1”-100’ ‘300 U PPER P IT E AST TAILINGS PILE A CCESS R OAD (via Copper Basin Road) WGS-84 (GPS) COORDINATES N 34˚29’ 07” W 112˚38’ 53” ELEVATION = ± 4,750 MSL Appendix D Skull Valley Arizona Mill Site Flow Sheet P1 - Feed Hopper The bagged ore is dumped into the feed hopper and is not handled again until the final concentrate is collected and put into the dryer. P2 - Conveyer This conveyer feeds a constant ore into the trammel. P3 - Trammel The ore is vigorously washed to float off the clays after separating the heavy ore from them. P4 - Double Deck Power Screen This classification step removes all particles larger than 1/8",sending it to PF to be discarded. The +20 mesh to 1/8" is stockpiled to be pulverized and processed at a later date. The ore that washes thru the 20 mesh screen is dumped into a sump pump (P6) and pumped thru pipe (P7) to the sweco screen group (P8). P5 - Conveyer The conveyer carries ore larger than 1/8" to waste pile. P6 - Sump Pump Pumps slurred ore (with plain water) to the sweco screens. P7 - Steel Pipe Carries ore slurry to the sweco screens. P8 - 4 Multi Deck, 48" Sweco Screens Primary ore size classification. Beginning with -20 mesh ore, the sweco classifies to 5 size groups of ore for transfer to the U. H. F. concentrated tables. P9 - Diaphragm Pumps These pumps transfer the classified ore groups to their designated U. H. F. concentrated tables. P10 - 7' X 12' U. H. F. Concentrating Table P11 -7' x 12' U. H. F. Concentrating Table P12 - Vibrating Ball Mill Pulverizes table concentrates from P11 back to P8 for reclassification P13 - Vibrating Ball Mill Pulverizes table concentrates from P11 back to P8 for reclassification. P14 - Sweco Dewatering Screen Removes most of the water from the table tails and collects the -400 mesh ore pumping it to the settling tanks, and sends the +400 mesh table tails thru the dewatering screw (P21 to P22). P15 - 4' x 8' U. H. F. Concentrating Table Receives classified ore from the sweco's (P8), separating the concentrates from the tails. P16 - 4' x 8' U. H. F. Concentrating Table Receives classified ore from the sweco's (P8), separating the concentrates from the tails. P17 - 4' x 8' U. H. F. Concentrating Table Receives classified ore from the sweco's (P8), separating the concentrates from the tails. P18 - 3' x 5' U. H. F. Concentrating Table Receives classified ore from the sweco's (P8), separating the concentrates from the tails. P19 - (2) 2' x 4' U-Tech Concentrating Table Receives classified ore from the sweco's (P8), separating the concentrates from the tails. P20 - Table Concentrate Dewatering System This removes most of the water from all of the (final) table concentrates and delivers them to the dryer. P21 - Conveyer P22 - 24" Dewatering Screw Dewaters table tails and discards them. P23 - Water Collection Tank Collects all excess water and sends it thru to the fines settling tanks (P24, P25 and P26) . P24 - 4" Steel Pipe Carries water to settling tanks (P25). P25 - First Of Two Settling Tanks The ultra fine ore (-400 mesh) settles out of the water and then flows to the other settling tank (P26) where the settling process continues, before the water flows into our vinyl lined third acre pond for recycling the water for reuse in our processing. P26 - Second Settling Tank P27 - Propane Fueled Dryer Dries concentrates before the induction furnace. P28 - Screw Feeder Loads dried concentrates into 55 gallon barrels. P29 - Water Cooling System For The Induction Furnaces P30 - Double Induction Furnaces Used to make Dore bars from the table concentrates. P31 - 100 KW Silent Run Diesel Generator Set P32 - 1000 KW 16 Cylinder Diesel Generator Set With House and 22 Hundred Gallon Fuel Tank P33 - Screw Type Air Compressor 350 CFM P34 -1400 Gallon Air Storage Tank P1A - Full Laboratory Facility The lab includes a direct current plasma machine (OCP) with all supportive accessories, two fume hoods, acid resistant work tables, two water sinks, scales, glass ware, safety equipment, first aid equipment, air conditioners and all other necessary items. P1 B - Lunch Room Including clothing lockers, safety equipment, first aid equipment and a restroom with a biodegradable toilet. P1C - Parts and Maintenance Facility P10 - Tool and Electrical Supply Facility P1 E - Sample Preparation Facility Rock crushing and pulverization of samples. Appendix E Equipment List Quantity Year Model Description Identification / Serial No. 1 1973 CASE 580B Loader Backhoe 5230332 1 1981 CHEVY Dually 1 Ton Pickup (white) 1GBHC34W1BV118109 516-HKF (NV) 1 1986 CHEVY Dually 1 Ton Pickup (grey) CA·77878 1 2000 CHILDERS 20 ft Flatbed Trailer 5DRCH2022YLOOOO2 K-44591 1 1999 TEXAS BRAG 20 ft Flatbed Trailer 17XFP182XX1999067 k-51492 1 1980 100 KW Generator Trailer Mount 317-A-63 1 1991 CAT 205 KW Generator Skid Mount 5JC01459 3306 1 1999 OLYMPIAN 100KW Generator D2875A1001 D100P1\4100 SERIES 1 1987 CHEVY 3/4 Ton Pickup (Brown) 1 1975 GALION Road Grader T-500 A GC 06026 T-500 1 N/A WIGGINS Lo-pro Forklift HWIGGINSWLC851044 1 N/A N/A 6' X 15' Steel Hopper N/A 1 N/A N/A 6' X 10' Steel Hopper N/A 1 N/A N/A 6' X 8' Steal Hopper N/A 1 N/A N/A 5' X 5' Steel Hopper N/A 1 N/A N/A 2'6" X 7'6" Steel Hopper N/A 1 N/A N/A 4' X 4' Steel Hopper N/A 1 N/A N/A 5' X 5' Aluminum Hopper N/A 1 N/A N/A 6' X 10' Steel Cone N/A 1 N/A N/A 6' X 10' Steel Platform N/A 1 N/A N/A 2'6" X 12' X 5' High Steel Catwalk N/A 1 N/A N/A 2'6" X 12' X 2'6" High Steel Catwalk N/A 1 N/A N/A 2'6" X 12' X 5'9" High Steel Catwalk N/A 2 N/A N/A 2'6" Wide Steel Catwalk Stairs N/A 1 N/A N/A 4' X 4’ Wide Stainless Steel Tank N/A 1 N/A N/A 400 Gallon Tank N/A 1 N/A N/A 550 Gallon Fuel Tank N/A 1 N/A N/A Propane Tank 500 Gallon B19259 2 N/A N/A 8' X40' Steel Containers N/A 2 N/A N/A 8' X 40' Aluminum Storage Containers N/A 1 N/A N/A 4' X 3' Marble Table N/A 1 N/A N/A 4'X8' Graphic Eng. Aluminum Top Vibrating Table 2471 1 N/A N/A 4'X8' Graphic Eng. Plastic Top Vibrating Table 2523 1 N/A N/A 2'X4' Graphic Eng. Aluminum Top Vibrating Table 2367 1 N/A N/A 7' X 12' Graphic Eng. Aluminum Top Vibrating Table 2536 4 N/A N/A 1'6" X 4' UTECHTIC Vibration Finish Tables N/A 1 N/A N/A 3' x 3' Stainless Steel Table N/A 1 N/A N/A 3' x 4' Stainless Steel Table N/A 1 N/A N/A 1' Belt X 9' Steel Conveyer N/A 1 N/A N/A 1'2" Belt X 13' Stainless Steel Conveyer N/A 1 N/A N/A 1'2" Belt X 40' Stainless Steel Conveyer N/A 1 N/A N/A 10" Belt X 13' Steel Conveyer Shelf Style Belt N/A 1 N/A N/A 1' Belt X 14' Alumium ELPCO Conveyer C-O-U156K2·3020 1 N/A N/A 1' Belt x 13' Steel Conveyer 87962 N/A 1 N/A N/A 1'6" Belt X 2'6" Steel Conveyer N/A 1 N/A N/A 2' X 5' Rolling Screen Unit-Silver Spr. Equip N/A 1 N/A N/A 12" screw X 12' screw feeders N/A 1 N/A N/A 9" screw X 12' screw feeders open top N/A 1 N/A N/A 6" screw X 21' screw conveyer enclosed N/A 1 N/A N/A 6" screw X 5' dewatering screw unit open top N/A 2 N/A N/A 4" screw X4' screw feeders open top N/A 1 N/A N/A BICO Pulverizer 802189F-1 1 N/A N/A DENVER Jaw Crusher 5" x 6" 002113-001-1 ,10317/P15 1 N/A N/A DENVER Jaw Crusher 4" x 8" 01-145194-001-1 1 N/A N/A BICO Puck and ring N/A 1 N/A N/A 1996 ROSKAMP roll crusher 6" 135447 1 N/A N/A 15 HP DURCO pump 7731 PUMP/5542 MOTOR 1 N/A N/A Gen. American trans. Corp- Dryer 2672 1 N/A N/A 18" SWECO Vibrating Stack Screen LS18-579-88 LS18533 1 N/A N/A 30" SWECO Vibrating Stack Screen LS30-686-6 LS39C66 1 N/A N/A 48" SWECO Vibrating Stack Screen 750393-A200 X548C888 1 N/A N/A 48" SWECO Vibrating Stack Screen 750393-8200 X548C888 1 N/A N/A 48" SWECO Vibrating Stack Screen 750393-C200 X548C888 1 N/A N/A 48" SWECO Vibrating Stack Screen C-865-3 948C88 1 N/A N/A Direct Current Plasma Machine N/A 2 N/A N/A 1'x1' Kilns N/A 2 N/A N/A Stainless Steel Sinks N/A misc. N/A N/A Steel Shelving N/A ORIGINAL INVENTORY LIST Quantity Year Model Description Identification / Serial No. 1 N/A N/A CAT 950 Loader (rubber tire) 3 yd. N/A 1 N/A N/A CAT D4D Bulldozer 10 ton N/A 1 N/A N/A CAT Generator Trailer mounted 50 KW N/A 1 N/A N/A ISUZU diesel w/4" trash pump & 5 KW Gen. N/A 1 N/A N/A Welding Truck w/400 Amp. Welder & Torches N/A 1 N/A N/A 3" Red Jacket Deep Well pumps/440 Volt Controls N/A 2 N/A N/A Approx. 1300 ft. of 3" Steel Pipe and Misc. Fittings N/A 1 N/A N/A 3" Valves and Couplers, etc. N/A 1 N/A N/A Approx. 12,000' of 2"-8" Aluminum & Plastic Pipe N/A 1 N/A N/A 8x6 Rubber Lined Pump 60 HP. N/A 1 N/A N/A Electrical Control Trailer N/A 1 N/A N/A DUETZ Generator Trailer Mounted 100 KW. N/A 1 N/A N/A 6x5 Rubber Lined Pump w/I Tank 30 HP. N/A 1 N/A N/A 4x3 Rubber Lined Pump w/ Tank 10 HP. N/A 1 N/A N/A 4" High Pressure Pump 10 HP. N/A 1 N/A N/A 4" Submersible Pump 10 HP. N/A 1 N/A N/A 6" Volume Fresh Water Pump 30 HP. N/A 1 N/A N/A 56"x 40' Trailer Mounted Trommel 5 to 40 Ton per hr. N/A 1 N/A N/A 56"x40' Skid Mount Trommel 5 to 40 Ton per hr. N/A 1 N/A N/A 48" Belt Feeder-Under 6'x10' Hopper 5 to 60 ton per hr. N/A 1 N/A N/A 30' Feed Belt N/A 1 N/A N/A 60' Discharge Conveyor N/A 1 N/A N/A 40' Discharge Conveyor N/A 1 N/A N/A Double Deck Vibrating Screen- Portable N/A 1 N/A N/A Riechart Spiral System Portable w/ Pumps & Sumps N/A 1 N/A N/A 36" Eagle Sand Dewatering Screw N/A 1 N/A N/A Knudson Concentrating Bowl N/A 1 N/A N/A 4'x8' Steel Drying Table N/A 1 N/A N/A 2,500 Gallon Water Storage Tank N/A 1 N/A N/A 7,500 Gallon Water Storage Tank N/A 1 N/A N/A Honda Three Wheeler w/ 2 Wheel Cart N/A 1 N/A N/A 40' Skid Mount Steel Storage Container N/A 1 N/A N/A Misc. Spare Parts, Supplies and Work Tools N/A PROPOSED ADDITIONAL EQUIPMENT SUBJECT TO CHANGE ONCE BUYER/JV PARTNER DETERMINED Quantity Year Model Description Identification / Serial No. 1 N/A N/A Front End Loader 5/7 vds. 1 N/A N/A Crawler Backhoe 2/4 vds. 2 N/A N/A Concentrating Tables N/A 1 N/A N/A CAT D8 Bulldozer N/A 1 N/A N/A Fuel Truck N/A 1 N/A N/A Water Meter N/A Misc. N/A N/A Additional Conveyors and Mechanical Grizzly N/A