President’s Message
Ye a r i n Re v i e w
2015 was an impressive year for the company on many fronts. Most importantly, our company continued its sterling safety
performance with industry leading safety metrics for EMR and recordable/incident rates all while self performing some of
the industry’s most challenging heavy civil projects. Our continuing ability to compete and successfully execute projects in
all types of market segments sets us apart. This year was especially exciting to see the resounding success of the Ameren
Illinois River’s project work and the successful completion (3 months ahead of schedule) of Terre Haute Wastewater
Treatment Plant Additions & Improvements, the largest project in company history.
I am exceedingly thankful for the exceptional group of individuals that make up the Plocher team. Thank you to the clients
and stakeholders that allow us the opportunities to display our talents and our outstanding family of employees for safely
executing the challenging work. Wishing everyone a safe and happy holiday season.
Scott Plocher
Additional Completed & Ongoing Projects:
 Stone Falls Center Building 5 —$1.4MM
Terre Haute Wastewater Treatment Plant Additions & Improvements—$116MM

PSGC CCR Material Handling Upgrades—$9.5MM

First Baptist Maryville School Expansion—$4.1MM

Altitude Trampoline Park—$2.6MM

Staunton Chrysler Dodge Dealership—$ 2.3MM

Timberlake Office Building #1—$650K

Taylorville CSO Improvements—$2MM

Edwardsville Town Center—$32MM

Christ Our Rock Lutheran High School Addition—$600K

Dynegy Newton Oil Boom Project—$400K

Health Central Remodels—$1.9MM
Waterloo Memory Care Facility
Altitude Trampoline Park
Taylorville CSO Improvements
Staunton Chrysler Dodge Jeep Ram
Dealership
National Bank—Hillsboro
PSGC Stamler Coal Feeder Retaining Wall
FBCM School Expansion
P LOCHER C ONSTRUCTION
D EDICATION DE LIVERS A SU CCE SSFUL 2015
INSIDE THIS ISSUE:
Green Mount
Professional Building
2
MSD Lemay WWTP /
Coldwater Creek
2
Fayette Co. Bridge
Replacement
3
Park Street Plaza
3
Jackie Joyner Kersee
Foundation
3
Ongoing Projects
4
CWLP Clarifier No. 3
CORLHS Addition
Fayette Avenue Bridge
Ameren Illinois Rivers Project
December 2015
2015 was a safe and prosperous year for the Plocher organization. Our work
volumes matched the high amounts from recent years with revenues approaching
$100MM. Although Plocher has never been focused on being a “large company”,
our modestly sized staff’s continuing successful execution of this large backlog is a
true illustration of what makes our company special.
The year was highlighted by our ongoing work on the exciting Ameren Illinois River’s
transmission line projects. Our crews tackled complicated worksites and constantly
changing conditions throughout central Illinois all while working in a safe and
efficient manner. The company started two five story signature office/retail building
projects, completed the westbound bridge replacement on I70 at Vandalia, and
successfully finished the $116MM Terre Haute WWTP.
Through it all, the Plocher team continued to reinforce our reputation as the
contractor of choice for the most challenging projects our industry has to offer.
AMEREN ILLINOIS RIVERS TRANSMISSION LINE
F O U N DAT I O N S , S U B S TAT I O N S A N D R I V E R C RO S S I N G
To ensure long-term reliability and efficiency of the
Midwest electric power grid, Ameren Transmission Co.
is building a nearly 400-mile, approximately $1.4 billion
dollar transmission line. The project consists of a new
345-kilovolt transmission line crossing the Mississippi
River near Quincy, Illinois and continuing east across
central Illinois to the Indiana border.
Various Plocher Illinois Rivers Projects Include:
 Meredosia-Ipava Line—48 mile stretch with 291
piers
 Meredosia-Herleman River Crossing Pile
Foundations at Illinois River
 Mt. Zion Substation Foundations & Sitework—57
piers
 Faraday Substation Foundations & Sitework —
312 piers
 Herleman to Maywood Line — 14.3 mile line with
93 piers
 Pana to Faraday Line —208 piers on a 31.7 mile
line
 Meredosia to Herleman Line — 291 piers on a 48
mile line
 Pana Substation — 622 piers
V o l um e 1 , I s s ue 5
P age 2
GREEN MOUNT PROFESSIONAL BUILDING
Construction is well under way for the
Green Mount Professional Building. The
five-story, approximately 60,000-squarefoot professional office/light retail
building is expected to be complete
summer of 2016. Plocher Construction
and Hurford Architects are working
collectively together on this design/build
project to provide a one-of-a-kind
structure that will be unique to the area
with its incorporation of expansive glass
for its exterior. Design includes a rooftop patio that will be available for use by
the building’s tenants and community
groups. The first floor will feature a mix
of retail with other professional offices
to be located throughout the remaining
floors.
P l o c he r C o ns tr uc ti o n
P age 3
F AY E T T E C O U N T Y B R I D G E R E M O VA L &
R E P L AC E M E N T
Vandalia, IL — Removal and replacement
of the bridges carrying I-70 over the
Kaskaskia River. The replacement bridges
contain two six-span steel structures.
PARK STREET PLAZA
M S D L E M AY W W T P S E C O N D A RY I M P R OV E M E N T S &
C O L D WA T E R C R E E K W W T F I M P R OV E M E N T S
Lemay WWTP Secondary Improvements:
Construction improvements at Lemay Wastewater
Treatment Plant are near completion. The project
included two fine screen/washer compactor
facilities at both the Headworks of the plant and
the Wet Weather process area.
Coldwater Creek WWTF Screenings &
Washer/Compactor Improvements:
The Headworks building consists of demolition
of the existing sluice trough and compactor
equipment, a new building addition,
replacement of the compactor equipment and
new sluice troughs.
Digester Gallery/Tank work includes
demolition of existing equipment,
improvements to existing areas, new sludge
pumps and associated piping and equipment.
Plocher is the designbuilder for this
impressive $12MM, 5story—45,000 SF retail/
professional building in
downtown Edwardsville.
Completion is slated for
late 2016.
J AC K I E J OY N E R K E RS E E C E N T E R A D D I TI ON
Plocher is proud to be a part of the
$2.4MM Addition to Jackie Joyner
Kersee Center . The Center improves
the quality of life for many individuals
and families as well as surrounding
communities. Improvements include
a new 20,700 SF addition featuring a
10,850 SF classroom for SIUe Head
Start program and 9,850 SF for a
wrestling center. The JJK Foundation
is a non-profit organization that offers
support services for educational and
community building programs to
adolescents, adults, and senior
citizens. The foundation in turn
manages the JJK Center. JJK Center
offers dance classes and conducts
arts and crafts activities. The Dr. Ben
Carson Reading Program and
Keystone Club are both operated at
the Center as well.