INSTALLED CAPACITY EVOLUTION SERVICE QUALITY

Transcription

INSTALLED CAPACITY EVOLUTION SERVICE QUALITY
Installed Capacity at End of Year
MW
INSTALLED CAPACITY
HYDRO POWER PLANTS
THERMAL POWER PLANTS
Coal
Fuel-oil
Fuel-oil / Natural Gas
Gas-oil
Natural Gas
INSTALLED CAPACITY SPECIAL
STATUS PRODUCERS P. R. E. (1)
Thermal
Hydro
Wind
Photovoltaic Generators
Wave Energy Producers
NATIONAL TRANSMISSION GRID
Length of Lines and Transformer Capacity
2009
2008 Variation
16 738
4 578
6 690
1 776
1 476
236
165
3 036
14 924
4 578
5 820
1 776
1 476
236
165
2 166
1 814
0
870
0
0
0
0
870
LENGTH OF LINES (km)
400 kV
220 kV
150 kV
TRANSFORMER CAPACITY (MVA)
Autotransformers (VHV/VHV)
Transformers (VHV/HV)
2009
2008
Var.
[%]
7 569
1 609
3 289
2 671
28 235
10 701
17 534
7 513
1 589
3 257
2 667
26 194
9 921
16 273
0,7
1,3
1,0
0,1
7,8
7,9
7,7
A. Lindoso
4 526
1 424
385
2 662
53
2
944
208
21
695
21
0
30 000
km
MVA
V.Nova A.Rabagão
V.Furnas
Vila Fria
Salamonde
Oleiros
Pedralva
Caniçada
Ruivães
1
2
Guimarães
PORTO
4
7
2 - Vermoim
3
5
8 - Canelas
Paraimo
Mogofores
Tábua
20 000
2 000
Lavos
Pombal
Cabril
Penela
8804
Corgas
10 000
1 000
0
(Cedillo)
C.Bode
Zêzere
0
2005
Transf.
Transf.
Fratel
2006
AAutotransf.
uto transf.
2007
2008
150
150kV
kV
2009
220
220kV
kV
5852
6 000
A.Mira
5470
4578
4578
4 000
Hydro
Thermal
Peak Load
F.Ferro
2 - Carriche
5
RNTNTG
- Dezembro
2009
– Decemberde
2009
400 kV
400kV
220 kV
kV
220
150kV
kV
150
Palmela
8
Évora
9
Lines
Linhas
C.Setúbal
Setúbal
M.Pedra
3 - Sete Rios
(Brovales)
4 - Zambujal (60kV)
Equivalent Interruption Time - EIT
Alqueva
5 - Trafaria
6 - Fogueteiro
7 - Seixal
minutes
8 - Lusosider
3
9 - Q. Anjo
Tensões
Voltages
Porto Alto
3
67
LEGEND
C.Carregado
Estremoz
1
2
4
LEGENDA
C.Ribatejo
Carregado
Fanhões
1 - Sacavém
SERVICE QUALITY
PRE
Santarém
Carvoeira
400
400kV
kV
Falagueira
Pego
Rio Maior
Trajouce
9217
6690
C.Branco
Bouçã
Batalha
LISBOA
8528
Penamacor
Gardunha
MW
8 000
Ferro
P.Serra
C.Lares
INSTALLED CAPACITY EVOLUTION
8973
Vila Chã
Aguieira
Pereiros
Connected Power Supply to the Public Grid or Installed Thermal Power in
accordance to M. Order 399/2002
9110
(Saucelle)
Chafariz
Mourisca
(1)
10 000
Pocinho
Tabuaço
Bodiosa
Estarreja
5 - Ermesinde
3 000
(Aldeadávila)
Valdigem
4 - Custóias
Bemposta
Lagoaça
Valeira
Régua
Carrapatelo
C.T.Outeiro
C.Petrogal
F.Alentejo
E.Sado
Sines
2 000
Wind
Eólicafarm
2
Substation
Subestação
0,49
0,57
0,74
Costumer
Instalaçãoinstallation
de cliente
2005
2006
2007
0,42
0
0
2005
2006
2007
2008
2009
PowerCentrais
Plants
Thermal
Térmica
Ourique
Sabóia
1
Simples
Single
Double
Dupla
Doble
with 1
Dupla com 1
Equiped
circuit
terno equipado
Hydro
Hídrica
C.Sines
1,29
2388
Miranda
Picote
Mogadouro
Torrão
3 - Urrô
7 - Prelada (60kV)
M. Cavaleiros
V. P. Aguiar
Riba d'Ave
8
1 - Maia
Chaves
Frades
T.A. Fafe
6
6 - Recarei
5 470
1 631
405
3 357
75
2
(Cartelle)
Mendoiro
Espanha
Spain
NATIONAL TRANSMISSION GRID
GENERATION EQUIPMENT
EIT
2008
Average 04-08
2009
Portimão
Tunes
Estoi
FARO
Edição: REN, Rede Eléctrica Nacional, S.A. - Design: LPM Comunicação S.A.
Feb. 2010 - Print run 1 500 - Printing: Textype, Artes Gráficas Ltda.
YEAR CHARACTERIZATION
Electricity consumption in 2009 was 49.9
TWh, which is 1.4% lower, or 1.8% corrected
for the effect of temperature and the
number of working days, than the preceding
year (the first fall since 1981). Consumption
at the regulated tariff fell to 82% of the
total.
Peak power demand on the public grid
occurred on 12 January and amounted to
9,217 MW, which is 100 MW above the
previous all-time record set in December
2007.
Hydroelectric energy capability was 23%
below ordinary levels, but hydroelectric
generation was 23% up on the preceding year
and supplied 14% of consumption. Thermoelectric generation was similar to the preceding year, accounting for 48% of consumption.
Special status generation (PRE) grew 25% and
accounted for 29% of consumption, 15% of
which originated from wind power, where
capacity was boosted by 700 MW.
The import balance was the lowest since
2003, accounting for 9% of consumption.
The highlights in the development of the
national transmission grid were: the con-
struction of the Falagueira-Estremoz line and
the opening of Estremoz substation - significant enhancements to improve service
quality in inland areas of the Alto Alentejo
region, the opening of Tábua substation - to
handle PRE generation, and also the operational start-up of Lagoaça substation (Freixo
de Espada à Cinta) - the first step in significantly increasing exchange capacity with the
Spanish national grid, which is to be
achieved with the completion of the new 400
kV interconnection in this zone. The autotransformation capacities of the Falagueira
and Ferreira do Alentejo substations were
also strengthened with a new unit installed
in each. At Falagueira, this new unit played
a role in increasing the renewable energy
handling capacity of the Beira Interior axis,
and at the Ferreira do Alentejo substation it
helped to raise the interconnection capacity
with Spain. The operational start-up of Lares
combined cycle power station (2x435 MW),
which is connected to the grid through
a double 400 kV line between the power
station and Lavos substation, was also
relevant.
In terms of quality of service the national
grid continued to perform well. The Equivalent Interruption Time was 0.42 minutes (the
best value ever).
Net Demand
GWh
TOTAL GENERATION
HYDRO GENERATION
THERMAL GENERATION
Coal
Fuel-oil / Gas-oil
Natural Gas
SPECIAL STATUS GENERATION
Hydro
Thermal
Wind
Photovoltaic
Waves
IMPORT BALANCE
Import (trade values)
Export (trade values)
HYDRO PUMPING
TOTAL DEMAND
2009
31 600
7 892
23 708
11 942
303
11 463
14 417
823
5 963
7 492
139
4 777
5 616
827
929
49 865
ANNUAL PEAK DEMAND AND MAXIMUM DAILY CONSUMPTION
SUPPLY
POWER GENERATION
2008
30 238
6 441
23 797
10 423
801
12 573
11 565
660
5 177
5 695
33
0
9 431
9 479
40
639
50 595
Var. [%]
5
23
0
15
-62
-9
25
25
15
32
316
-49
-41
>
45
-1,4
-1,8
(corrected by temperature and working days)
50
TWh
Power (MW)
40
Import Balance
Hydro
Fuel-oil
Natural Gas
Coal
Wind
PRE Others
Demand
30
20
10
0
1,3
1,0
1,08
Hidroelectric
Capacity
Factor
1,19
0,98
0,7
0,75
0,83
0,56
0,4
Import
Balance
9%
Natural Gas
23%
6
PRE
Others
14%
Fuel-oil
1%
Fuel-oil
1%
2009
Coal
24%
PRE
Wind
15%
Hydro
14%
2008
Coal
21%
Hydro
11%
IMPORTS AND EXPORTS
3 000
PRE
Others
12%
PRE
Wind
11%
4
2 000
2
1 000
0
0
-1000
-2
2000
2001
GWh
2002
2003
2004
%
2005
2006
2007
2008
2009
% Corrected by t&wd
09-Jan
178
8 973
02-Dec (19.30h)
2008
03-Dec
175
9 110
18-Dec (18.45h)
2007
18-Dec
30-Jan (19.30h)
2006
31-Jan
27-Jan (19.30h)
2005
20-Dec
8 804
8 528
9 000
6 000
3 000
0
0
30
179
169
164
60
90 120 150 180
MW
January 12th 2009
December 2sd 2008
6 000
4 000
GWh
Import
Balance
19%
Natural Gas
25%
GWh
%
2009
8 000
0,41
ELECTRICITY CONSUMPTION DEVELOPMENT– Annual Variation
SUPPLY
12-Jan (19.45h)
10 000
0,77
0,77
9 217
LOAD DIAGRAM ON THE DAYS OF ANNUAL PEAK DEMAND
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
1,33
Energy (GWh)
9 000
2 000
6 000
0
0
0
4
8 12 16 20 24
Imports
3 000
Exports
Balance
0
-3 000
4 8 12 16 20 24
IMPORT
HYDRO
THERMAL
PRE
DEMAND
2005
2006
2007
2008
2009
Maximum load MW
Minimum load MW
Load factor
Min. Load / Max. load
2009-01-12
9 217
4 771
0,78
0,52
2008-12-02
8 973
4 609
0,78
0,51
(%)
2,7
3,5
Variation

Similar documents