Montoursville Area Montoursville Area School District

Transcription

Montoursville Area Montoursville Area School District
Montoursville Area
School District
High School Project Update
September 9, 2014
Crabtree, Rohrbaugh & Associates,
Architects
Additions and Renovations
Montoursville Area High School
Renovation ‐ Demolition
Option 5: Additions and Renovations
Montoursville Area High School
3
Option 5: Additions and Renovations
Montoursville Area High School
1993 CONSTRUCTION
Existing and New
Option 5: Additions and Renovations
Montoursville Area High School
1st Floor Plan
Option 5: Additions and Renovations
Montoursville Area High School
2nd Floor Plan
3rd Floor Plan
Option 5: Additions and Renovations
Montoursville Area High School
1st Floor Plan ‐ Update
Option 5: Additions and Renovations
Montoursville Area High School
2nd & 3rd Floor Plan ‐ Update
Option 5: Additions and Renovations
Montoursville Area High School
9
Schedule
2014
2015
2016
2017
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S
I
PRE-DESIGN
II
SCHEMATIC DESIGN
III DESIGN DEVELOPMENT
IV CONSTRUCTION DOC'S
V
BIDDING
VI CONST. ADMIN.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PHASE I : 3 Story Wing
PHASE II: Reno Gym
y
PHASE III: Aud. Wing
PHASE IV: DAO, A. Gym
PHASE V: Sitework
Additions and Renovations
Montoursville Area High School
Construction Phasing
Additions and Renovations
Montoursville Area High School
Construction Phasing
Option Characteristics
Option Characteristics
High School Option 5
1. Uses existing site
2. Retains the 1993 portion of the existing building
3. Parking for 300 Vehicles
4. Parking adjacent to stadium and new main entrance to High School
5. Retains DAO and district maintenance building on site
6. Retains stadium in it’s current location w/ new synthetic turf field
7. Minimal disruption to students during construction
8. Variance for 3 story building height will be required
9. Variance for Lot Coverage will be required
13
Pre-Design Tasks - Completed
‰ Finalize Educational Program
‰ Obtain Civil Engineering Proposals
‰ Preliminary Discussions with Borough P li i
Di
i
ith B
h
(zoning, impervious surface approval requirements, etc.) ‰ Addressed various Project Goals (Tech Ed Phasing, Future Expansion)
Pre-Design
Pre
Design Tasks - Ongoing
‰ Educational Specifications
‰ Site Requirements (Parking, Circulation, Athletics, etc.)
‰ Document District Building Standards (Materials, Systems, Technology, etc.)
g
(
y
gy
)
‰ Building & Site Design
Building & Site Design
‰ Scope and Budget
Scope and Budget
Pre-Design Tasks - Upcoming
‰ Zoning Variance Process: (Building Height, Parking, Impervious Lot Coverage)
‰ Obtain Additional RFP’s (Mechanical/Electrical Engineering, Structural Engineering, Food Service, Geotechnical, etc.)
/
‰ Develop Aesthetic Preferences
‰ Finalize Scope and Budget
‰ Existing Site & Building Surveys
‰ Initiate PDE PlanCON Process