case study - Hynds Pipe Systems
Transcription
case study - Hynds Pipe Systems
CASE STUDY SH20 Manukau Extension Stormwater Ponds Lusit Angle Support Retaining System Infrastructure Retaining System 0800 WE PIPE (93 7473) • www.hynds.co.nz As a result of Lusit’s success in solving a stormwater pond retaining issue at the Highbrook Industrial Park, Leighton Works approached Lusit to determine whether they could provide a cost effective solution to retain the Plunket Avenue Stormwater ponds. These ponds were part of the stormwater management plan for the $260 million SH20 Manukau Extension project in Auckland. The Plunket Ave stormwater ponds had to be located in a relatively narrow section of the SH20 extension, with occupied industrial land on one side, and the SH20 motorway on the other side. Site constraints meant It was not possible to construct the ponds in the conventional manner using battered earth and contoured slopes. The design engineers had originally planned to use a system of sheet-piles to form retaining to the long sides of the ponds, with a 500mm clay base liner and earth sloped ends. However the client, surrounding land owners and Leighton Works were after a more cost effective and aesthetically pleasing solution. Leighton Works were initially interested in using the Lusit Angle Support System because of the attractive design and vertical retaining solution that the system offers. LAS Elements can also be designed to handle specific load surcharges. In addition, the LAS Elements would enable the stormwater ponds to be located directly on the boundary between the SH20 corridor and the surrounding industrial land. The Lusit Angle Support system normally works with approximately 75% of the typical soil types encountered within New Zealand. However the geotechnical soil analysis in the proposed stormwater ponds location indicated some of the “weakest” soils Lusit had yet encountered, with modulus of elasticity as low as 2 MPa. In conjunction with Leighton Works, and the geotecnical engineers (Tonkin & Taylor), an initial re-design was proposed, involving a series of 8m deep colmix columns. This would provide enhanced bearing capacity and improve the global stability along with installing 3m+ high Reverse LAS Elements along both sides of the stormwater ponds. HIGHBROOK POND DURING CONSTRUCTION: LAS Elements sitting at top awaiting installation. Following further design iterations and input from the German knowledge base behind the 32 year old Lusit Angle Support System, the retaining solution eventually evolved into a “concrete beam and bath” methodology. This involved using 2.9m tall 20er Reverse LAS Elements (i.e. LAS Elements with the foot towards the airside) together with a series of HIGHBROOK POND COMPLETED LAS INSTALLATION: Made easy with the special Lusit Quick Hitch. 0800 WE PIPE (93 7473) • www.hynds.co.nz 600 x 200mm reinforced concrete beams linking these LAS Elements across the pond. Lastly a 100mm thick concrete topping was poured to provide the pond base. This did away with the need to enhance the weak soils and removed the need for the clay base liner. To further reduce installation time and costs, Lusit manufatured the Reverse LAS Elements in 1.5m widths, together with a shortened 1000mm long precast foot, with rebar extenders (to enable an insitu stitch beam to be poured). During the installation, it became apparent that any water in the area behind the retaining wall could not be drained by normal means. Lusit and its consultants then devised an alternative solution of pressure relief holes allowing hydrostatic pressure to equalise between the pond and the surrounding areas. Installation of LAS Elements was done by Waiau Earthmovers who simply used a 20 tonne digger. To speed up the installation, Lusit developed a special lifting Quick Hitch which attached onto the digger’s tilt hitch and then onto each of the LAS Elements. This provided safe, quick and full installation movement (in, out, side to side with 360 degree rotation). REVERSE LAS ELEMENTS AFTER GROUTING PREPARING TO INSTALL THE CONCRETE “BEAMS AND BATH” The Reverse LAS Elements were lifted onto the foundation pad and installed on precast shims. They were then aligned and levelled with the use of panel bars and grouted into place once sufficient runs of 30m or more had been placed. All installation work was undertaken by a small team comprising of a digger operator and 3 dogmen. EASTERN STORMWATER POND COMPLETED Project Summary: LAS Elements: 164no. 1.5metre wide, 20er Reverse LAS Design Loads: 12kN/m2 LAS heights: 2.9m LAS weights: 2780kg Wall foundation: 50mm Cemix non-shrink grout, on 100mm thick 17.5MPa lean concrete pad, on 200mm compacted hardcore Main Contractor: Leighton Works (JV between Leighton Contractors PTY Ltd and Works Infrastructure Ltd) Installation Contractor: Waiau Earthmovers 0800 WE PIPE (93 7473) • www.hynds.co.nz 0800 WE PIPE (93 7473) • www.hynds.co.nz