AVOIDING THE DISPUTE RESOLUTION DISCONNECT
Transcription
AVOIDING THE DISPUTE RESOLUTION DISCONNECT
R E S U L T S CO-EDITORS F I R S T | S M N E W S L E T T E R VOLUME XXII | WINTER 2014 CHARLES F. KENNY, PARTNER AND MICHAEL S. ZICHERMAN, PARTNER AVOIDING THE DISPUTE RESOLUTION DISCONNECT RECENT RULINGS HIGHLIGHT CLASS ACTION RISK FOR UNPAID INTERNSHIP PROGRAMS The wave of class actions in the United States now includes a frontal assault on unpaid internship programs, Jeffrey M. with plaintiffs’ Daitz, Esq. attorneys securi ng some successful preliminary results in the Ne w Yor k federal court. These victories come at a time when it is being Kevin J. O’Connor, Esq. widely predicted that the improving economy will fuel an increased focus on class action lawsuits in 2014 by the plaintiffs’ bar. The most recent victory came in Glatt v. Fox Searchlight Pictures1 (June 11, 2013). The plaintiffs in Glatt were hired to work as unpaid interns on the sets of films for the defendants’ production companies. After their internships, they sued under federal and state law, claiming they were deprived of minimum wage and overtime compensation. The central continued on page 5 David A. Fultz Every major construction project involves a variety of players with differing contractual obligations, including owners, architects, engineers, prime contractors, David A. Fultz subcontractors, and material suppliers, among others. A simple dispute – for example a defective work claim – can easily implicate multiple parties, and the contractual ability to join those parties into a single forum for the resolution of that dispute is crucial. This goal can be accomplished by a carefully drafted provision for alternative dispute resolution (“ADR”) (i.e., other than by litigation), but only if proper care is taken to ensure that the ADR provision is effectively incorporated into, and consistent with, the agreements of the other project participants. Joining all necessary parties in one forum is generally not an issue in litigation because it is typically authorized by the civil practice statutes,1 encouraged by the courts, and, in many forums, expressly required. However, since ADR is purely a creature of contract, a recalcitrant party cannot be compelled to participate with other parties in ADR unless it is expressly required under that party’s agreement. Frequently, an ADR provision will require non-binding mediation as a condition precedent to the commencement of binding dispute resolution proceedings, continued from page 1 AVOIDING THE DISPUTE RESOLUTION DISCONNECT 2 such as in-court litigation or arbitration.2 Mediation is essentially a negotiated settlement process facilitated by the presence of a neutral party (i.e., the “mediator”). The mediator cannot force a party to make, or accept, a settlement offer, and unless all parties can reach agreement, there is no settlement. Arbitration, in contrast, represents a more formal – and binding – ADR procedure. In arbitration, an arbitrator, or panel of arbitrators, sit as the finder of fact (like a judge or jury), and although some discovery may be permitted, it is typically limited, thus providing a less costly and expedited resolution process. Arbitration is generally favored in the construction industry because of the ability to select an arbitrator who has some expertise in the construction field. However, other parties cannot be joined in the arbitration proceedings unless that issue is specifically addressed in the underlying agreements.3 The Consequences of Failing to Properly Harmonize ADR Provisions Can Be Drastic Unwary contractors may fall into the trap of requiring their subcontractors to enter into the contractor’s standard form subcontract, without giving much consideration to the ADR requirements in the prime contract, or whether those ADR provisions are sufficiently incorporated into the subcontract in a way that is logical, harmonized, and legally-enforceable. This can result in a rude awakening for the prime contractor if it finds itself unable to compel its subcontractor to resolve its disputed claims by participating in ADR with the project owner, pursuant to the terms of the prime contract. Such an outcome leaves the contractor without a single, convenient forum within which to resolve the subcontractor’s or owner’s intertwined claims. It also exposes the contractor to the costs of litigating in two or more separate proceedings and potential double liability resulting from inconsistent determinations in the different forums. By way of example, if an owner claims that the work of a subcontractor is defective, it will generally assert a backcharge against the prime contractor for any costs associated with correcting the defective work or any resulting project delays, among other potential damages. To challenge the owner’s backcharge, the prime contractor would be required to follow the ADR procedures set forth in the prime contract, which, for this example, requires arbitration. In the event the prime contract’s ADR provisions are not properly incorporated into the subcontract, the prime contractor will have no mechanism to compel its subcontractor to participate in the arbitration, leaving the prime contractor to defend the work of its subcontractor in the arbitration between the contractor and owner. Assume the owner prevails in the arbitration and secures a $500,000 award and judgment against the prime contractor for the defective work of its subcontractor. The prime contractor would, of course, wish to recoup these losses from its subcontractor, and here is the bad news: the determination in the owner’s arbitration award that the subcontractor’s work was defective is not binding on the subcontractor because it was not a party to the arbitration proceedings.4 As a result, the prime contractor would have no alternative but to pursue its claims against the subcontractor in an entirely new legal proceeding, incurring additional legal fees, and now taking a position inconsistent with its prior testimony in the arbitration hearings, by instead trying to prove that the subcontractor’s work was defective, rather than defending that work. The arbitration award itself would likely be deemed inadmissible as evidence against the subcontractor as well. More troubling, however, is the possibility that, because the arbitration award is not binding on the subcontractor, the subcontractor could prevail in the litigation by convincing the judge or jury that its work was not defective, leaving the prime contractor without the ability to recover its losses. The same issue of inconsistent results can arise when dealing with subcontractor claims that have been passed through and submitted to arbitration between the prime contractor and owner. By contrast, if properly harmonized ADR provisions are in place, the owner, prime contractor and subcontractor will all be in one proceeding and bound by a single outcome. Careful Drafting Is Critical Properly harmonizing an ADR provision requires more than just a general clause that incorporates by reference the terms of the prime contract into the subcontract (sometimes referred to as “flow down” provisions). Because a party contractually agreeing to submit disputes to ADR is effectively waiving many of the legal and procedural remedies it would ordinarily have, the courts of New York and other jurisdictions require that the intent to submit contractual disputes to ADR be “… clear, explicit, unequivocal, and not depend upon implication or subtlety.”5 As such, commonly-used contract provisions by which the subcontractor agrees to be bound by the terms of the prime contract and to “assume toward the Contractor all obligations and responsibilities which the Contractor, under [the prime contract], assumes toward the Owner” 6 may not survive a challenge by a subcontractor unwilling to participate in the ADR procedures called for under the prime contract.7 In order to effectively bind a subcontractor to the ADR provisions of the prime contract, it is incumbent upon the drafter to specifically call out those provisions in the subcontract, either by a direct reference, pursuant to which the “Subcontractor agrees to be bound by and to participate in the dispute resolution procedures set forth in the Prime Contract,” or, preferably, by identifying the specific provisions of the prime contract to be deemed continued on page 16 Adam P. Handfinger and Monique S. Cardenas Adam P. Handfinger FLORIDA SUPREME COURT LIMITS THE APPLICATION OF THE ECONOMIC LOSS RULE In the Florida Supreme Court’s recently issued opinion, Tiara Condominium Ass’n, Inc. v. Marsh Monique S. Cardenas & McLennan, Cos., Inc., Florida’s highest court limited the application of the Economic Loss Rule (ELR)1 to product liability cases, presumably limiting the protections traditionally thought to be provided for construction defect claims, generally. As discussed below, we have already seen an increase in tort claims that would have otherwise been subject to the ELR and perhaps barred. The facts of the case are instructive. Tiara Condominium Association (Tiara) retained Marsh & McLennan (Marsh) as its insurance broker to secure condominium insurance coverage, including windstorm coverage, for Tiara, which Marsh did through Citizens Property Insurance Corporation (Citizens). Citizens issued a policy that contained a loss limit of nearly $50 million. Subsequently, Tiara’s condominium sustained significant damages from two hurricanes: Frances and Jeanne. During Tiara’s loss remediation, Tiara received assurance from Marsh that the loss limits coverage for windstorm coverage was per occurrence, not aggregate, which would entitle Tiara to approximately $100 million in insurance proceeds for damage caused by the hurricanes. In reliance upon Marsh’s assurances, Tiara proceeded with a more expensive remediation and sought payment from Citizens. Contrary to Marsh’s assurances, Citizens claimed that the loss limit was $50 million in the aggregate not per occurrence, capping Tiara’s insurance coverage at $50 million rather than $100 million. As a result of the foregoing, Tiara filed suit against Marsh alleging: (1) breach of contract; (2) negligent misrepresentation; (3) breach of implied covenant of good faith and fair dealing; (4) negligence; and (5) breach of fiduciary duty. The trial court granted summary judgment in favor of Marsh on all claims resulting in Tiara’s appeal to the Eleventh Circuit. The Eleventh Circuit concluded that summary judgment was proper as to Tiara’s breach of contract, negligent misrepresentation and breach of implied covenant of good faith and fair dealing claims, but with respect to claims for negligence and breach of fiduciary duty, the federal court certified the following 3 expense of contract principles.” 5 Justice Pariente further expounded: 4 question to Florida’s Supreme Court: Does the economic loss rule bar an insured’s suit against an insurance broker where the parties are in contractual privity with one another and the damages sought are solely for economic losses? In addressing the certified question, the Florida Supreme Court first reviewed the history of the ELR and its expansion from products liability cases to contractual privity cases, noting that the ELR was adopted by the courts to “prevent parties to a contract from circumventing the allocation of losses set forth in the contract by bringing an action for economic loss in tort.”2 Specifically, the Court set forth the circumstances in which the ELR has historically been applied: (1) where the parties are in contractual privity and one party seeks to recover damages in tort for matters arising out of the contract (contractual privity ELR); and/or (2) where the defendant is a manufacturer or distributor of a defective product which damages itself but does not cause personal injury or damage to any other property (products liability ELR). With respect to contractual privity ELR, the doctrine dictates that one party cannot sue the other party under tort theories for damages that arise out of the contract. The rationale being that when the parties are in contractual privity, the parties define the “limitation of liability through bargaining, risk acceptance, and compensation.” 3 In limiting its expansion and applying its historical purpose, the Court concluded that the ELR applies only in the products liability context: Having reviewed the origin and original purpose of the economic loss rule, and what has been described as the unprincipled extension of the rule, we now take this final step and hold that the economic loss rule applies only in the products liability context. We thus recede from our prior rulings to the extent they have applied the economic loss rule to cases other than products liability.4 Concurring with the majority, Justice Pariente stated that the Court’s limitation of the ELR “is neither a monumental upsetting of Florida law nor an expansion of tort law at the The majority’s conclusion that the economic loss rule is limited to the products liability context does not undermine Florida’s contract law or provide for an expansion in viable tort claims. Basic common law principles already restrict the remedies available to parties who have specifically negotiated for those remedies, and, contrary to the assertions raised in dissent, our clarification of the economic loss rule’s applicability does nothing to alter these common law concepts. For example, in order to bring a valid tort claim, a party still must demonstrate that all of the required elements for the cause of action are satisfied, including that the tort is independent of any breach of contract claim.6 The practical application of the Tiara decision does not deviate from the common law principles preventing tort causes of action in contractual privity cases where the claimed damages are solely economic, but rather fortifies these common law principles while limiting the application of the ELR to products liability cases. A party must still demonstrate an independent tort claim separate and distinct from a breach of contract claim in order to maintain both tort and breach of contract claims. However, parties must now be cognizant that despite Pariente’s contention that the limited application of the ELR will not undermine contract law or expand tort claims arising from purely economic damages, the holding in Tiara does suggest that parties in contractual privity can now maintain concomitant tort claims to potentially recover damages in excess of the recoverable breach of contract damages and/or to circumvent the parties’ contractual rights and remedies. As Chief Justice continued on page 15 continued from page 1 RECENT RULINGS HIGHLIGHT CLASS ACTION RISK FOR UNPAID INTERNSHIP PROGRAMS defense raised by the defendants in Glatt was that the interns fell within the “trainee” exception established by the United States Supreme Court in a 1947 case2. As such, they argued, the interns were properly denied any hourly compensation. In Glatt, the plaintiffs were successful in challenging the exemption by arguing for a strict application of the exemption. Class certification was permitted, opening up the employers to potential liability to a class of persons similarly situated to the named plaintiffs. These arguments by creative plaintiff’s lawyers that unpaid interns are really employees in disguise are not new, but, in the last sixteen months, they have been renewed with vigor. Plaintiff’s lawyers have sought a strict application of a U.S. Department of Labor Wage and Hour Adminstrator’s six-part test for determining when a trainee is not an employee of a for-profit business. Under this test, an intern is not an employee if all six tests are met: 1.The internship, even though it includes actual operation of the facilities of the employer, is similar to training which would be given in an educational environment; 2.The internship experience is for the benefit of the intern; 3.The intern does not displace regular employees, but works under close supervision of existing staff; 4.T he employer that provides the training derives no immediate advantage from the activities of the intern; and on occasion its operations may actually be impeded; 5.The intern is not necessarily entitled to a job at the conclusion of the internship; and 6.The employer and the intern understand that the intern is not entitled to wages for the time spent in the internship. According to the Department of Labor, “[i]f all of the factors listed above are met, an employment relationship does not exist under the Fair Labor Standards Act (FSLA), and the Act’s minimum wage and overtime provisions do not apply to the intern. This exclusion from the definition of employment is necessarily quite narrow because the FLSA’s definition of “employ” is very broad.” 3 Obviously, the fourth element of the test could prove problematic if strictly enforced, as it could be interpreted as meaning that if an employer derives any advantage from an intern’s work, the test is not satisfied and the intern is considered an employee. The application of this test is very fact specific and, up until recently, has been interpreted by and large to protect employers with legitimate internship or vocational programs. In a sixth circuit court of appeals case, Solis v. Laurelbrook Sanitarium & School, Inc. (2011), the Secretary of the U.S. Department of Labor brought suit against a private religious institution that provided voca tion al training in the nursing context to young people looking to enter that profession. The Department of Labor brought suit to enjoin the contin uation of the program as being violative of child labor laws. The District Court disagreed and dismissed the complaint, which was affirmed on appeal. Notably, the Sixth Circuit held the Department of Labor’s six-part test to be “a poor method for determining employee status in a training or educational setting,” and refused to give it any deference. The court settled on a “primary benefit” test, which examined who received the primary benefit of the training/internship program – the intern or the program sponsor. Id. It 5 5 continued from page 5 RECENT RULINGS HIGHLIGHT CLASS ACTION RISK FOR UNPAID INTERNSHIP PROGRAMS • The courts will look to the “value added” and overall educational value of an internship program. Intern programs where the intern receives little or no educational value will be subject to attack. The employer should arrange workshops and organized training programs for the intern, and consider assigning mentors. Consideration should also be given to rotating the intern through different departments at the employer’s business to broaden the internship experience; 6 affirmed the dismissal of the claims under this lesser standard. In a 2013 court of appeals case, Kaplan v. Code Blue Billing & Coding, Inc., the court affirmed dismissal of claims by three former students of a medical billing and coding program who were placed in externships with Florida medical practices to satisfy externship requirements of the program. They later sued alleging that they were improperly exempted under state and federal laws and should have been paid minimum and overtime wages. The Court applied the six-part test and determined that, on balance, the externs received the primary benefit from the relationship and were properly exempt. On August 8, 2013, the plaintiffs in Kaplan filed a petition with the United States Supreme Court, and it remains to be seen whether that issue will be heard by the high court in the near future. Even within a single Circuit Judges have disagreed over how to apply this sixpart test, as shown in two cases pending in New York. The two judges handling these two matters reached two different conclusions. In Glatt, District Judge William Pauley, III rejected the defendants’ argument that the six-part test should yield to the more broad “primary benefit test” followed in Solis and other matters. Judge Pauley found that interns (class representatives) working in the media industry were employees rather than interns because, among other things, the employers benefitted from their services and because they displaced workers. Judge Pauley’s decision came just one month after Judge Harold Baear issued a May 8, 2013 ruling in Wang v. Hearst Corp. reaching the opposite result and concluding that the court must apply a “totality of the circumstances test,” which was similar to the primary benefit test found controlling in the earlier cases. Using that test, the court denied summary judgment and left the issue for trial. The decisions in Glatt and Wang are expected to be ultimately reviewed by the Second Circuit if not resolved earlier. Given these preliminary successes by plaintiff’s counsel and the uncertainty that exists in this area of the law, employers would be well advised to undertake a review of their internship programs to ensure compliance with the six-part Department of Labor test – the more rigid of the two standards. Some of the practical business considerations that can be gleaned from these recent decisions and from the test are: • The overall intent of the program should be educational in nature. Programs that are created in partnership with educational institutions for which the intern receives college or vocational credit will tend to survive scrutiny; • Interns should not be taken on to displace employees who were being paid for those duties. Using interns to complete productive tasks that otherwise would be performed by paid employees increases the risk that the intern will be deemed an employee; and • The overall length of internships should be restricted to a limited and defined period of time and not left open ended. The new case developments highlight the importance of closely examining any internship program to ensure compliance with applicable law and guidelines to reduce or eliminate risk of suit and to avoid prolonged and expensive litigation in the event there are claims for unpaid wages. Our Labor Relations and Employment Law Department is available to meet with you and counsel your business in these areas. n Glatt v. Fox Searchlight Pictures, 2013 WL 2495140 (June 11, 2013). 1. 2. Walling v. Portland Terminal Co., 330 U.S. 148 (1947). 3 S DOL Factsheet, available at http://www.dol.gov/whd/regs/ U compliance/whdfs71.pdf. MISCONCEPTIONS ABOUT ATTORNEY – CLIENT PRIVILEGE Eric M. Gruzen Eric M. Gruzen 7 A construction manager faces an issue on a project and seeks direction on how to proceed. He drafts an email and considers who to send it to at his company. The issue is contentious and he wants to ensure that if it ever evolves into a lawsuit, the email chain will not be subject to discovery. Hoping to trigger the attorney-client privilege, he addresses the email to a company Vice President, who happens also to be the company’s in-house counsel. As an additional safeguard, he also copies the company’s outside counsel. However, despite the construction manager’s best intentions, the email chain is not necessarily shielded from discovery. 3.I n-house counsel may conduct non-legal tasks without jeopardizing the attorney-client privilege. The attorney-client privilege is a commonly misunderstood legal concept, especially in the context of email communication. Some misconceptions we often hear include: In truth, the existence of privilege turns largely on the role of the attorney and the nature of the correspondence. 1.Copying counsel on an email renders the email privileged; 2.Any email sent exclusively to counsel is always privileged; and The purpose of the attorney-client privilege is to “safeguard the confidential relationship between clients and their attorneys so as to promote full and open discussion of the facts and tactics surrounding individual legal matters.” Once a communication is deemed “privileged,” it is undiscoverable even if it contains unprivileged information. However, for a communication to be privileged, there must first exist an attorney-client relationship, and the communication must take place in the course of that relationship. Additionally, the transmission must occur “by a means which, so far as the client is aware, discloses the information to no third persons other than [(a)] those who are present to further the interest of the client in the consultation or [(b)] those to whom disclosure is reasonably necessary for the transmission of the information or the accomplishment of the purpose for which the lawyer is consulted ....” Establishing the Existence of an Attorney-Client Relationship 8 In the context of attorney-client protection, a “client” is “a person who . . . consults a lawyer for the purpose of retaining the lawyer or securing legal service or advice from him in his professional capacity.” No attorney-client relationship exists where the attorney’s role is non-legal in nature. For instance, “it is settled that the attorney-client privilege is inapplicable where the attorney merely acts as a negotiator for the client, gives business advice or otherwise acts as business agent.” Naturally, there are situations in which an attorney’s legal and business purposes intertwine. In such instances, courts have shown a willingness to protect communications with a predominant law-related purpose, but to allow into evidence communications with a predominant businessrelated purpose. However, where an attorney’s business and legal roles effectively merge, attorney-client protection may become entirely unavailable. This risk is especially prevalent in companies where in-house counsel also perform business tasks. For example, in one case, in-house counsel for a title company was responsible for monitoring funds entering and leaving escrow accounts. The court held that the counsel acted in such a substantial business capacity that the attorney and client effectively became “indistinguishable,” and denied attorney-client protection over the subject communications. Messages to or from outside counsel also are not categorically protected. While outside counsel is presumed to serve purely a legal services role, this presumption may be rebuttable in circumstances where the counsel deals primarily with the non-legal aspects of a transaction or operation. Establishing That a Message Was Transmitted in the Course of the Attorney-Client Relationship If a court determines that an attorney-client relationship exists, it will look at whether the communication in question was transmitted in the course of that relationship. Merely copying counsel on a communication does not create a privilege. In determining whether a given communication is protected, courts may review various factors, including the parties to the message. For instance, in cases where a message was sent simultaneously to a lawyer and non-lawyer for both their consideration, courts have denied privilege on the basis that the primary purpose of the message could not have been to request legal advice. Even merely copying a non-attorney on a message to an attorney can jeopardize the “privileged” status of the message. In some states, courts also scrutinize the contents of the message before ruling on privilege, whereas in California, for one, such an examination of contents is generally prohibited. In theory, a privileged communication must be germane to the attorney-client relationship and must consist of “information transmitted between a client and his lawyer, advice given by the lawyer, or a legal opinion formed and given by the lawyer…” However, in practice, if a court may not review the contents of a communication (as is the case in California), determining whether the substance of the communication fulfills these criteria might not be possible, forcing the court to rely only on contextual factors, such as who partook in the communication. Practice Tips 1. Do not automatically assume that an email or other written communications are privileged merely because it was sent to or received by an attorney. If the context in which the message is sent suggests that the message does not pertain to a legal matter, it may very well be discoverable. 2. Strictly limit the number of recipients of any message that contains potentially sensitive content. Where possible, include only attorneys in the communication, and particularly in the “To:” line of an email, while placing non-attorneys in the “cc:” line. 3. If a company relies on its in-house counsel to perform significant non-legal business functions, it would be advisable to direct sensitive legally related communications to outside counsel for direction and advice. n Costco Wholesale Corp. v. Superior Ct. (2009) 47 Cal.4th 725, 740-741 (emphasis added). vii Chicago Title Ins. Co., 174 Cal.App.3d at 1154. This is the law in California, pursuant to statute, though the standard in other states may differ. Of course, facts are not deemed privileged merely by virtue of their being communicated in a privileged transmission. viii See 2,022 Ranch L.L.C. v. Superior Court (2003) 113 Cal.App.4th 1377, 1388-89. i ii In re Vioxx Prods. Liab. Litig., 501 F. Supp. 2d 789, 805 (E.D. La. 2007) (citing United States v. Chevron Corp., No. C 94-18855BA, 1996 WL 444597, at *2 (N.D. Cal. 1996). ix Id. at 733, citing Cal. Evid. Code § 952. iii Cal. Evid. Code § 951. iv US ex rel Kalid-Kunz v. Halifax Hospital Medical Center, et al., 2012 WL 5415108 (M.D. Fla., November 6, 2012) (citing In Re Vioxx, 501 F. Supp. 2d at 812). x Chicago Title Ins. Co. v. Superior Court (1985) 174 Cal.App.3d 1142, 1151. v vi See, e.g., Wellpoint Health Networks, Inc. v. Superior Court (1997) 59 Cal.App.4th 110, 122. xi Benge v. Superior Court (1982) 131 Cal.App.3d 336, 345. 9 Frank A. Hess and Michael S. Zicherman Frank A. Hess Michael S. Zicherman NEW JERSEY COURT PROVIDES “PATCH” FOR GENERAL CONTRACTORS WHEN THEIR INDEMNITY CLAIMS AGAINST SUBS ARE BARRED BY THE STATUTE OF REPOSE When a general contractor (GC) or construction manager (CM) is sued due to its subcontractor’s defective work or a subconsultant’s professional negligence, the general contractor or construction manager will naturally protect itself by asserting claims for indemnity and contribution against the sub. However, under New Jersey law, all claims against the sub could be barred due to the expiration of the statutes of limitations or repose, measured from the last date the sub-performed work on the project. In many cases, the last day of the sub’s performance is likely to be much earlier than the substantial completion date of the entire project, the date by which claims against the general contractor or construction manager are measured. This potentially leaves the general contractor or construction manager liable for the sub’s performance deficiencies with no recourse against the sub. Fortunately, the June 2013 New Jersey Supreme Court decision, in Town of Kearny v. Brandt, 214 N.J. 76 (2013), has partially mitigated the harshness of this outcome. In Kearny, the Court fashioned a remedy that would allow the GC or CM to at least obtain apportionment of damages for any fault attributable to the sub, while at the same time affording the sub the benefit of the expiry of the statutory limitations period. A summary of the facts illustrates the issue. 10 Following structural failures in a public safety facility, the Town of Kearny sued its architect, Brandt-Kuybida Architects (Brandt), and soils engineer, Solis Engineering Services, Inc. (SESI), and the architect’s structural steel consultant, Harrison–Hamnett, P.C. (Harrison–Hamnett), for breach of contract and professional negligence. Kearny had directly retained SESI to conduct a soils investigation; SESI completed and reported on the results in July 1990 and had no further involvement with the facility. Brandt retained Harrison–Hamnett to serve as the structural engineer with responsibility to design the facility’s foundations, piles, roof structure and wall reinforcement. Harrison–Hamnett completed its work on October 30, 1995. The completion of the entire project and Brandt’s work were not completed until some time later, the exact completion date being disputed. On November 24, 1995, Brandt and Kearny signed a “Certificate of Substantial Completion” (Certificate). However, neither an issue date nor a date of completion was inserted in the appropriate part of the Certificate. On April 9, 1996, Kearny’s construction official issued the first Temporary Certificate of Occupancy, limited to the police section of the building and subject to completion of punch list items. On May 23, 1996, the construction official issued the second Temporary Certificate of Occupancy, permitting the Kearny Fire Department to use its section of the building. According to the Reported Decision: Structural defects in the facility surfaced shortly after the Police Department took occupancy. The building settled differentially, causing gaps between the ceiling and a wall, as well as leaks, buckled tiles and cracks in the walls. The Police Department reported leaks in various parts of the building and doors that could not close because they did not fit in their frames. Although the Town continued to use the facility, there were further complaints about structural flaws in the building. In 2003, the Town’s Construction Official received an emergency call that the ceiling in the police dispatch area of the building was about to collapse. By 2007, ceilings in the facility had fallen, pipes had separated and pulled, and glass had broken, all of which were attributed to uneven settlement. The Town never issued a final certificate of occupancy. The Town’s construction official ordered all occupants to evacuate the building on February 8, 2007. The building has been vacant and unused since that date. Kearny filed suit against the design professionals on April 7, 2006; the design professionals in turn filed crossclaims against each other seeking contribution and indemnification. Thereafter, all defendants filed motions to dismiss the claims asserting that New Jersey’s ten-year statute of repose and tenyear statute of limitations applicable to public entities barred Kearny’s claims. The trial court denied Brandt’s motion, concluding that the ten-year period for purposes of the statute of repose began for Brandt on the date of substantial completion of the project, ruling that the critical date was April 9, 1996 when the first Temporary Certificate of Occupancy was issued. This meant that the tenyear period for filing suit against Brandt expired on April 9, 2006, two days after the Town sued. The trial court, however, granted the motions filed by SESI and Harrison–Hamnett, ruling that the tenyear period commenced for these parties on the date that their involvement in the project ended, July 31, 1990 for SESI and October 30, 1995 for Harrison–Hamnett. With Brandt the only defendant left in the case, the trial court then precluded Brandt from asserting its right to seek apportionment of fault from the dismissed parties, SESI and Harrison– Hamnett. The trial court held that by virtue of the dismissal of the Town’s claims against them, those defendants were no longer in the case and Brandt was not entitled to an apportionment of fault against them. At trial, Brandt was found solely liable to Kearny in the amount of $800,000. Brandt appealed both the finding of the date of substantial completion, claiming that it should date back to the Certificate, as well as the denial of apportionment against the dismissed parties. The appellate court, while upholding the trial court’s ruling that substantial completion did not occur until the first Temporary Certificate of Occupancy was issued, remanded the case for a new trial to allow Brandt to seek allocation of fault against SESI and Harrison–Hamnett, ruling that the judgment against Brandt should be reduced based on the fault that would have been attributed to these parties had Kearny timely sued them. Both Brandt and Kearny appealed to the Supreme Court, Brandt seeking to overturn the trial court’s finding of when substantial completion occurred and Kearny appealing the ruling allowing Brandt to reduce its judgment by apportionment against the dismissed parties. The Supreme Court affirmed the trial court’s ruling that since the Certificate was never fully completed and issued and because work needed to be performed before the building could even be partially occupied, substantial completion did not occur until the first temporary certificate of occupancy was issued on April 9, 1996. In dealing with this issue, the Court stated that the law distinguishes between contractors who are hired to perform continued on page 15 CALIFORNIA APPELLATE COURT RULES A CONTRACTUAL AGREEMENT BETWEEN AN OWNER AND A BUILDER TO SHORTEN THE STATUTE OF LIMITATIONS IS ENFORCEABLE, EVEN IF IT RESULTS IN A CLAIM BEING TIME-BARRED BEFORE IT IS DISCOVERED 11 Joseph S. Sestay In a recent California Appellate Court decision, Brisbane Lodging, L.P. v. Webcor Builders, L.P. the Court upheld a clause in a construction contract that shortened the statute of limitations and abrogated California’s delayed discovery rule as to latent defects. Joseph S. Sestay This decision was a case of first impression in the state and is bound to have significant implications for contractors, owners, and developers in drafting their construction contracts. The Facts in Brisbane Brisbane Lodging, L.P. and Webcor Builders, Inc. entered into a contract for the design and construction of a large hotel. The AIA contract1 used by the parties modified California’s applicable statute of limitations with respect to claims between Brisbane and Webcor. Article 13.7.1.1 provided that the time in which to bring any causes of action began to run at substantial completion: “any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion.” The hotel was substantially completed on July 31, 2000. In 2005, a break in an underground sewer line caused wastewater to flow under the hotel. Webcor admitted that the problem was caused by a latent plumbing defect and made some remedial repairs. When the problem reoccurred, Brisbane discovered that the plumbing contractor had constructed the sewer line with ABS pipe material rather than cast iron pipe, contrary to the requirements of the Uniform Plumbing Code. In response to Brisbane’s complaint for breach of contract, negligence, and breach of implied and express warranties, Webcor moved for summary judgment on the grounds that the suit was barred by the contractual limitations period provided for in Article 13.7.1.1 of the parties’ construction contract. The trial court agreed with Webcor and granted summary judgment. Brisbane appealed. Appellate Arguments 12 Although Brisbane conceded that Article 13.7.1.1 waived the statutory 10-year limitations period as to latent defects (whether discovered or not) under Code of Civil Procedure 337.15, it argued that the four- and three-year statutes under Code of Civil Procedure 337.1 and 338 respectively were applicable and, in addition, asserted that the “delayed discovery rule” provided that these statutes did not begin to run, at the earliest, until the first manifestation or discovery of the defects by the owner in 2005. The delayed discovery rule, in the construction context, is a long standing legal doctrine recognized by California courts (as well as other jurisdictions) which holds that statutes of limitation for latent construction defects do not begin to run until the defects are or should have been discovered. Thus, the earliest that the four- and three-year statutes could have commenced running was in 2005, which would make Brisbane’s claims timely. Brisbane then argued that to hold that Article 13.7.1.1 abrogated the delayed discovery rule was against public policy, noting that courts only approve contractual agreements shortening statutes of limitations with great caution, if the shortened time to file suit is deemed to be “reasonable.” Brisbane asserted that it would be unreasonable to abrogate the delayed discovery rule in this instance, since to do so would essentially bar Brisbane’s claims before they were (or could have been) discovered. Brisbane relied on the case of Moreno v. Sanchez which the court declined to enforce a contractual provision shortening the limitations period and waiving the delayed discovery rule. Moreno involved claims by purchasers of a home against a home inspector who failed to detect asbestos and other contaminants in the home. The inspection contract provided for a shortened one-year limitations period, commencing on the date of inspection. The Moreno court refused to enforce this provision, finding that it was unreasonable as a matter of law and void as against public policy. Webcor countered that the delayed discovery rule did not apply, that all of Brisbane’s claims were time-barred by the unambiguous language of Article 13.7.1.1 even though the latent defects were not discovered until after the shortened limitations time period had run, and that the strong public policy favoring freedom of contract supported upholding Article 13.7.1.1. The Appellate Court’s Reasoning The Appellate Court agreed with Webcor and affirmed the trial court’s granting of summary judgment, dismissing all of Brisbane’s claims. The Court acknowledged that this was a case of first impression in that no prior California Appellate Court had upheld a contractual provision abrogating the delayed discovery rule in a latent construction defect dispute. The Court, however, noted that courts in other states – including Kentucky, Maryland, Massachusetts, New York, and Pennsylvania – had upheld similar or identical language, and that Article 13.7.1.1 was a standard provision in the industry-wide accepted AIA contract form. The Court relied on “longstanding established public policy in California, which respects and promotes freedom of private parties to contract.” While acknowledging that the Moreno decision struck down a similar contractual clause, the Court reasoned that, unlike the parties in Moreno, both Brisbane and Webcor were “sophisticated parties of equal bargaining strength where there is no claim of misrepresentation or undue influence.” As such, the Court found that Article 13.7.1.1 was not unreasonable in that it allowed the parties to “structure risk-shifting as they see fit without judicial intervention.” Implications of Brisbane Under certain conditions, California courts may be willing to enforce contractual provisions in construction contracts that substantially alter the parties’ statutory rights, even if those modifications result in a party being barred from presenting an otherwise valid claim. However, it is important to note that the current (2007) version of the AIA A201 General Conditions2 no longer contains the language that was enforced by the Court in Brisbane, and simply defers to “applicable law but in any case not more than 10 years after the date of Substantial Completion.” In other words, the current AIA A201 language leaves California’s statutory scheme intact, including the delayed discovery rule. Authors’ Note | For parties to construction contracts who wish to modify California’s statutory scheme with respect to the time limit within which to bring construction related claims, Brisbane stands for the proposition that the courts will likely support such modifications, but only if (a) entered into freely as a result of arms-length negotiations (b) between informed parties of arguably equal bargaining power. In order for such clauses to be enforceable, it is important for owners and contractors to communicate with their counsel, who can assist them in making informed decisions that are consistent with the holding in Brisbane. And, from a public policy standpoint, the court’s holding in Brisbane appears to be consistent with California’s statutory scheme regarding claims for latent defects, which strives for certainty and limitations on liability in barring the assertion of any such claim more than 10 years after substantial completion – no matter when they are discovered. n 1 AIA A201- General Conditions – 1997 edition, Article 13.7.1.1 2 AIA A201- General Conditions – 2007 edition, Article 13.7.1.1 PECKAR & ABRAMSON AWARDED NATIONWIDE “LAW FIRM OF THE YEAR” DISTINCTION IN LITIGATION CONSTRUCTION BY BEST LAWYERS© PECKAR & ABRAMSON AWARDED NATIONWIDE “LAW FIRM OF THE YEAR” DISTINCTION IN LITIGATION–CONSTRUCTION BY BEST LAWYERS© U.S. News – Best Lawyers® “Best Law Firms” has named Peckar & Abramson, P.C. “Law Firm of the Year” in Litigation– Construction for 2014. Nationally, only one law firm per area of practice is selected for this prestigious honor each year. In addition, the firm was recognized among the top tier in several practice areas in national and multiple metropolitan categories. Law Firm of the Year Metropolitan Awards Litigation–Construction Tier 1, Miami, Construction Law Tier 1, Miami, Litigation–Construction Tier 1, Miami, Litigation–Real Estate Tier 1, Miami, Real Estate Law Tier 1, New Jersey, Construction Law Tier 1, New Jersey, Litigation–Construction Tier 1, New York City, Construction Law National Awards Tier 1, Construction Law Tier 1, Litigation–Construction Tier 1, New York City, Litigation–Construction Tier 1, Washington DC, Litigation–Construction Tier 2, Los Angeles, Construction Law Tier 2, Miami, Commercial Litigation Tier 2, New Jersey, Commercial Litigation Tier 2, Washington DC, Arbitration Tier 2, Washington DC, Mediation 13 CONGRATULATIONS TO THE PECKAR & ABRAMSON ATTORNEYS NAMED TO 2014 BEST LAWYERS© IN AMERICA LIST PECKAR & ABRAMSON IS PLEASED TO ANNOUNCE THAT 21 ATTORNEYS AT THE FIRM HAVE BEEN NAMED TO THE 2014 EDITION OF BEST LAWYERS®, THE OLDEST AND MOST RESPECTED PEER–REVIEW PUBLICATION IN THE LEGAL PROFESSION. Attorneys Named to the 2014 Best Lawyers in America List Richard L. Abramson Litigation–Construction Adrian L. Bastianelli, III Arbitration, Litigation– Construction, Mediation Jerry P. Brodsky Litigation–Construction Steven M. Charney Construction Law, Litigation– Construction Gregory H. Chertoff Litigation–Construction Robert A. Drucker Litigation–Construction Melinda S. Gentile Litigation–Construction Patrick J. Greene, Jr. Construction Law, Litigation–Construction John D. Hanover Construction Law Charles F. Kenny Construction Law, Litigation–Construction Roger S. Markowitz Litigation–Construction Bruce D. Meller Construction Law, Litigation–Construction Paul G. Monte Construction Law, Litigation–Construction Gerard Onorata Litigation–Construction Robert S. Peckar Construction Law, Litigation–Construction Stephen H. Reisman Construction Law, Litigation–Construction Howard M. Rosen Construction Law, Litigation–Construction Donald S. Rosenberg Construction Law, Litigation–Real Estate, Real Estate Law Neal I. Sklar Construction Law, Litigation–Construction Gary M. Stein Commercial Litigation, Construction Law, Litigation– Construction Michael Zicherman Commercial Litigation 2014 Lawyer of the Year Award Robert S. Peckar 2014 “Lawyer of the Year” for Construction Law and Litigation– Construction in the New York Area Stephen H. Reisman 2014 “Lawyer of the Year” for Litigation–Construction in the Miami Area Charles F. Kenny 2014 “Lawyer of the Year” for Litigation–Construction in the Newark Area PECKAR & ABRAMSON WELCOMES THREE PARTNERS TO ITS LOS ANGELES AND ATLANTA OFFICES Peckar & Abramson is proud to welcome three new partners to the firm — Mark Stapke and Nicholas Sarris to our Los Angeles office, and Thomas Hall to our Atlanta office. 14 A B O U T M A R K S TA P K E | Mark Stapke represents public owners, general contractors, specialty subcontractors, developers, architects, engineers and material suppliers. Mark’s practice focuses on time-related claims and litigation, offering legal advice and counsel regarding the contracting process, payment/performance bond enforcement/defense, administrative proceedings and counseling and transactional services with an emphasis on assisting public owners. Mark currently serves as legal advisor to the Board of Directors of the Western Council of Construction Consumers, as Judge Pro Tem of the Los Angeles Superior Court, and has served on the Citizens Advisory Committee to the California State Contractor’s License Board. Mark frequently contributes to construction industry publications, including the Western Council Connection, the Construction Law Anthology, Western Construction Executive and Pool and Spa News. He has served as an arbitrator and mediator for the Los Angeles Superior Court since 1990, and regularly lectures to trade groups on legal cost control methods. In 2009, Mark was selected as the Western Council of Construction Consumers “Member of the Year” for the fifth time. A B O U T N I C H O L A S S A R R I S | Nicholas Sarris defends Employment Practice Liability Insurance and Directors & Officers claims on behalf of employers in state and federal courts. He has also successfully defended employers before various governmental administrative bodies, including the Equal Employment Opportunity Commission, the National Labor Relations Board, the California Department of Fair Employment and Housing and the California Department of Industrial Relations – Division of Labor Standards Enforcement. Well-versed in the California Labor Code and the Fair Labor Standards Act, Nicholas represents employers in wage and hour matters, including class actions and representative actions brought under the California Private Attorneys General Act. Nicholas advises employers on a wide variety of employment related matters and compliance issues, including employment policies and procedures, contracts, disciplinary issues, leaves of absence and accommodations, complaints, benefits, proprietary information and restrictive covenants and compensation. A B O U T T H O M A S H A L L | Thomas Hall’s practice focuses on construction and design claim resolution on public and private projects throughout the United States. Thomas works with clients on the drafting and negotiation of construction contracts, design-build agreements and subcontracts. Prior to joining Peckar & Abramson, Thomas transitioned from his successful construction litigation practice to serve for six years as lead U. S. internal legal counsel for one of the largest general contractors operating in the U. S., ranked amongst the top 10 by Engineering News Record. He oversaw legal matters for all of their U. S. operations, working directly with executives and project staff to implement a variety of risk mitigation strategies and to resolve hundreds of disputed matters. In this role, Thomas gained valuable perspective on the internal challenges presented to construction and design firms by the current complex regulatory environment and by the financial and reputational losses that may arise from project disputes and litigation. FLORIDA SUPREME COURT LIMITS THE APPLICATION OF THE ECONOMIC LOSS RULE continued from page 4 Ricky Polston stated in his dissent: [T]he majority obliterates the use of the doctrine when the parties are in contractual privity, greatly expanding tort claims and remedies available, without deference to contract claims. Florida contract law is seriously undermined by this decision. 7 Joining Chief Justice Polston’s dissent, Justice Canady declared “[w]ith today’s decision, we face the prospect of every breach of contract claim being accompanied by a tort claim.” 8 As predicted by Chief Justice Polston and The ELR is a judicially created doctrine setting forth the circumstances under which a tort action is prohibited if the only damages suffered are purely economic losses and the defendant has not breached an independent duty apart from the breach of contract. AFM Corp. v. Southern Bell Tel. & Tel. Co., 515 So. 2d 180, 181 (Fla. 1987) ; and Indem. Ins. Co. of N. Am. v. Am. Aviation, Inc., 891 So. 2d 532, 536 (Fla. 2004). 1 Am. Aviation, 891 So. 2d at 536 (citing Ginsberg v. Lennar Fla. Holdings, Inc., 645 So. 2d 490, 494 (Fla. 3d DCA 1994) (“Where damages sought in tort are the same as those for breach of contract a plaintiff may not circumvent the contractual relationship by bringing an action in tort. ”). 2 AFM Corp., 515 So.2d at 181. Justice Canady, Florida courts appear to be allowing an influx of tort claims such as negligence, negligent misrepresentation, and breach of fiduciary duty to proceed notwithstanding the existence of a contractual relationship between the parties. 9 n Kuehne v. FSM Capital Management, LLC 2013 WL 1814903 *4 (S. D.Fla. Apr. 29, 2013) (relying on Tiara, the court declined to dismiss the plaintiff’s tort claims in managing the plaintiff’s financial accounts) ; Wiand v. Wells Fargo Bank, N.A. 2013 WL 1401414 *6 (M. D. Fla. Apr. 5, 2013) (citing Tiara 5 Id. Concurring Op. at 408 and finding that the ELR did not bar a negligence claim arising out of (Pariente, J.). a bank’s participation in derivative transactions with hedge funds involved in a 6 Ponzi scheme) ; F. D.I. C. v. Floridian Title Group Inc., 2013 WL 5237362 *16 (S. D.Fla. Id. Sept. 17, 2013) (denying a defendant’s motion for summary judgment as to 7 Id. Dissenting Op. at 411 (Polston, C.J.). claims of breach of fiduciary duty and negligent misrepresentation based upon 8 Id. Dissenting Op. at 414 (Canady, J.). the ELR and rejecting an argument that these claims 3 9 Tiara Condo. Ass’n, Inc., 110 So.3d at 407. 4 15 NEW JERSEY COURT PROVIDES “PATCH” FOR GENERAL CONTRACTORS WHEN THEIR INDEMNITY CLAIMS AGAINST SUBS ARE BARRED BY THE STATUTE OF REPOSE continued from page 10 limited services (such as subcontractors and subconsultants), and contractors with supervisory responsibilities that span the entire project (such as general contractors and construction managers). In determining the date upon which the ten-year period begins to run for purposes of the statute of repose for the former category, it is at the conclusion of the contractor’s specific task; for the latter category, it begins to run at the time of occupancy. Turning to the apportionment issue, the Court affirmed the appellate court’s decision, ruling that allocation of fault to the dismissed defendants—who will, in any event, pay no damages—does not subvert the statute of repose’s purpose to give construction defendants “the right not to have to defend ancient claims or obligations.” Further, the Court stated that the goals of the comparative fault statutory scheme are advanced if the jury assesses the SESI and Harrison– Hamnett defendants’ potential fault, noting that within the time constraints imposed by the statute of repose, the Town had the opportunity to assert a cause of action against SESI and Harrison–Hamnett period. The Court ruled that the jury’s assessment of SESI and Harrison–Hamnett’s fault promotes fair allocation of responsibility and avoids creating an incentive for a plaintiff to strategically target only one of a range of culpable defendants. n Editors’ Note | The Supreme Court’s decision is a literal application of the statute of repose. The statute does not distinguish between claims made by owners or by contractors, and it applies as much to claims for indemnification and contribution as it does to direct claims for damages. Though a contractor may no longer be liable in damages for the defective work of its subcontractor, the contractor still is not made whole by the Court’s decision. The contractor, through no fault of its own, still has lost its ability to obtain indemnification from its subcontractor for attorney’s fees and other costs of litigation, and to the extent that the contractor has insurance coverage, it may be subject to increased premiums. The only way to rectify such a result is either by amending the statute of repose, or possibly by way of a provision in the subcontract, which states that for purposes of the subcontractor’s indemnity obligations, the subcontractor’s work shall not be deemed to be substantially complete until a certificate of occupancy is issued for the entire project or until the contractor’s work is substantially completed. Such a provision may be effective to extend the statute of repose for the subcontractor to make it commensurate with that of the general contractor. continued from page 2 AVOIDING THE DISPUTE RESOLUTION DISCONNECT applicable to the subcontractor. Otherwise, a general incorporation-by-reference provision may be construed only to bind the subcontractor to those provisions of the prime contract specifically relating to the scope, quality, character, and manner of the work to be performed by the subcontractor.8 Even where the necessary specificity referencing the ADR provisions of the prime contract in the subcontract are present, it remains incumbent on the contractor to carefully review those ADR provisions in order to ensure that those requirements can be reconciled with the other provisions of the subcontract, lest the ADR provisions prove unenforceable or procedurally troublesome. For example, an ADR provision in a prime contract limiting the arbitrability of claims to those not exceeding $10,000 will prove useless in the event of a $100,000 pass-through claim by a subcontractor, notwithstanding that the same ADR clause may have been properly incorporated into the terms of the subcontract. subcontractors, or others, into the ADR proceedings, and particular care must be taken to ensure those provisions are appropriately incorporated into the terms of any subcontract. n This concern about reconciling the agreements applies with equal force to the notice provisions in the subcontract, as well. 1 S ee, e.g., New York CPLR §601(a), cf. New Jersey’s “Entire Controversy Rule,” New Jersey CPR Rule 4:30A. See, AIA Form A201-1997, §§ 4.5 and 4.6, addressing mediation and arbitration, respectively. 2 See, AIA Form A201-1997, § 4.6.4, precluding joinder of the architect and limiting the ability to join other parties to those “substantially involved in a common question of fact or law whose presence is required if complete relief is to be accorded in arbitration.” 3 Conclusion See, e.g., Kaufman v. Towers Trans., Inc., 63 AD2d 669, 404 NYS2d 684 (2d Dep’t 1978). 4 In sum, a contractor must take great care when drafting and reviewing any contractual agreements in order to ensure it is protected to the greatest extent possible. Where ADR provisions are present in the prime contract, they must be scrutinized for the ability to join 5 S ee, e.g., Thomas Crimmins Contr. Co. v. City of New York, 74 NY2d 166, 171, 544 NYS2d 580 (1989) See, AIA Form A401-1997, Mutual Rights and Responsibilities, §2.1 6 7 S ee, e.g., Navillus Tile, Inc. v. Bovis Lend Lease LMB, Inc., 74 AD3d 1299, 1302, 904 NYS2d 207 (1st Dep’t 2010) 8 S ee, e.g., Bussanich v. 310 East 55th Street Tenants, 282 AD2d 243, 244, 723 NYS2d 444 (2d Dep’t 2001) 16 PECKAR & ABRAMSON 41 Madison Avenue | 20th Floor New York, NY 10010 www.pecklaw.com NEW The information provided in this Newsletter does not, nor is it intended to, constitute legal advice. Readers should not take or refrain from taking any action based on any information contained in this Newsletter without first seeking legal advice. YORK I L L I N O I S • NEW • JERSEY G E O R G I A • • FLORIDA • CALIFORNIA P E N N S Y L V A N I A • • DISTRICT OF COLUMBIA W W W . P E C K L A W . C O M