- Helm Group
Transcription
- Helm Group
PEOPLE BUILDING VALUE - Helm Group Newsletter | Fall 2014 Mechanical Opens New Sheet Metal Fabrication Shop In June, Mechanical moved into its new sheet metal fabrication shop on Falcon Road in Rockford, IL. The 38,000 square-foot facility includes office space and new fabrication equipment. Prior to the move, Mechanical had a smaller shop in Rockford where they only fabricated fittings from sheets. The new shop allows high-production fabrication from coil rolls and allows the company to have more control over their duct cost. Mechanical decided to upgrade their fabrication capabilities because they were buying duct from outside vendors. Pricing for the outside fabrication was volatile depending on the vendors workload and there was the potential for late deliveries if the vendor could not meet the required lead times. Mechanical buys and installs between 2 million and 3 million pounds of duct annually so they made a decision to take more control over this aspect of the work. The company found an old industrial tool shop building on the grounds of the Rockford Airport and invested money to upgrade the office space and clean up the shop. They installed 4 new recessed loading docks, 3 at-grade overhead doors, and 3 overhead cranes. To keep up with deliveries, they also bought a fleet of trailers and box trucks. Bill Hoffman, Todd Whitlock, and Scott Hoffman handled the layout of the equipment to make the operation as productive as possible. The first goal was to optimize the flow of fabrication from the coil unloading to the coil line and plasma tables. An overhead door was installed to allow access for the truck to pull into the building. A 7.5 ton overhead crane unloads the coil stock and places it in the storage area. The same crane is also used to load the coil onto the coil line. As duct comes off of the coil line, the seams are made and the corners are installed with automated machines. Then each piece goes to the spooling area. In the fitting operation, the new plasma table has a de-coiler and each piece is cut on the 20’ table. The shape of each piece comes from the CAD file for the project where CAD Technician, Joe Parker, interfaces the CAD to the CAM system. After the shapes are cut by Eric Lizer, a sticker is applied to each shape showing the job number and piece number. The piece is then assembled on one of three fitting tables in the shop. After the fitting table, the completed piece goes to the spooling area where multiple pieces are joined so that large sections of duct can be shipped to the field. Before being loaded on a truck, the ends are wrapped to keep out duct and debris. In addition to the spooling operation, duct hangers are fabricated in the shop. Both of these activities are easier to perform in a controlled environment. In the hanger area, threaded rod, bolts, nuts, strut, and straps are assembled for multiple projects, then wrapped and tagged so that they can be delivered to the exact floor and area where they will be installed. Article continued on page 9. Inside This Issue Reaching the Next Milestone................................. 2 Choose the Behavior Choose the Consequence... 3 Highway 20 Bridges............................................ 4-5 2014 Helm Group Project Photos........................6-7 Route 26 Paving.................................................... 8 Mechanical New Fab Shop Continued................... 9 Chicago Athletic Association............................10-11 Heavy Launches New Website.............................12 United Way Donation............................................12 Reaching the Next Milestone Most of us have been on construction projects where a milestone date is part of the schedule. The milestone isn’t necessarily the end of the project, but a point in the project where a major part of the project is completed. As a company, we have milestones too. The milestones aren’t necessarily planned well in advance like on a construction project, but they are points in time when there was a significant change to the company. In the last 15 years, I can point to 7 milestones that made our company better and one of those milestones happened this year. The first milestone was the structures work we had in 2002. That year, we were the low bidder on two bridges totaling $50 million. Those two projects, one on I-74 over the Rock River in Moline and the other over the Rock River in Dixon, accounted for half of the Helm Group’s previous year’s revenue. There were significant penalties for late completion and the projects were so tough that many of our own employees questioned whether we knew what we were doing. After extensive planning, we were able to accelerate our work to gain an early completion bonus and both jobs turned out to be huge successes. Most of all, the two jobs gave us confidence that we can build tough jobs by planning the work and executing our plan. That confidence would lead to many other great bridge opportunities in the years to come. The next milestone was the acquisition of Borg Mechanical in 2003. Although the acquisition made 2003 a very tough year, the addition of mechanical capabilities in the Chicago area propelled the Helm Group to a new source of revenue and profit that we were not previously able to capture. The Chicago market has proven to be much more consistent than most of our other markets and the expertise we acquired helped us not just in Chicago, but in other markets as well. The Abraham Lincoln Bridge project on I-39 over the Illinois River from 2007-2008 was also a milestone. At the time, this was the largest project we had ever bid; it was also outside of our home IDOT District and used local union labor that was not part of our core workforce. We had some previous experience with structures work away from home, but nothing of this magnitude. When the bid results came in, we were the low bidder at $33 million, but had left $7.4 million on the table. Although it looked like it could be a big problem, the project turned out to be a success. The project was profitable, we were able to develop some new core employees, and best of all, the project helped instill a culture of travel that today has taken us to projects like Biggsville and Effingham. In 2009, we acquired Norstar, a Rockford-based sheet metal company. Prior to Norstar, we self-performed only the piping side of the HVAC scope and we subcontracted our sheet metal. The problem was that there were only a few stand-alone sheet metal contractors to team up with and often times, the double mark-up on their scope would make us uncompetitive. Since the acquisition, we have seen very few projects where piping and 2 sheet metal are bought separately and there are only one or two stand-alone sheet metal contractors remaining. The combination of both scopes has helped us become one of the leading commercial mechanicals in the region. Also in 2009, our Mechanical Service group, which had been steadily growing since its inception in 2000, was awarded an important facility Brian Helm, maintenance agreement with Helm Group CEO full-time dedicated staff at Rock Valley College. The work included traditional HVAC service as well as building automation and has since led to similar agreements at other education and corporate campuses. The award helped solidify the strategy that we were not a traditional service contractor, but instead a facility solutions provider that could complete with the national players. The next milestone was in 2012 when we acquired Northwest Illinois Construction in Sterling, Illinois. We had previously owned 1/3 of this company, but ran it with separate management and the entity struggled to make a profit most years. In 2012, we acquired the other 2/3 and combined Northwest with our Civil Roads division. The biggest assets purchased with the company were the quarry and asphalt plant on Palmyra Road. Prior to Northwest, we paved in three counties, and after, we could easily reach six. This asphalt plant was critical in 2013 because almost all of the paving work we performed came from this plant. Going forward, we expect the acquisition to continue to prove itself as a major milestone by opening up this new geographic region. The most recent milestone came this year in the form of a sheet metal fabrication shop. Mechanical installs around 3 million pounds of fabricated duct per year and previously bought it from outside suppliers. There are only 2-3 vendors capable of handling our workload on most projects and many times, the vendors’ pricing and lead time reflect their dominant position in the market. By investing in a new facility and equipment, we are able to bring the sheet metal fabrication in-house and have more control over our costs and schedule. We are also able to put ourselves on the same playing field as our competitors, all of whom have strong fabrication capabilities. Those are the seven milestones I can point to that defined our last 15 years. In addition, there were hundreds of projects made possible by our outstanding employees. The seven major events propelled our growth and profitability, but these were just the most recent seven. With your help, I fully expect to continue the milestone list well into the future. Choose the Behavior, Choose the Consequences Every day we are faced with thousands of decision making opportunities. Some studies suggest that an average person can be faced with up to 35,000 decision making opportunities in one day. That’s a lot of chances to make decisions with negative outcomes. There is the deliberate, logical, attentive part of our mind that is capable of analyzing a problem and coming up with a rational answer. This is the part that we are aware of, and it is expert at solving problems. It works slower and requires a lot of energy. The simple act of walking is enough to occupy a great deal of attentive mind. Try calling someone on the cell phone while they are walking and ask them to solve a problem that requires a lot of thought. The majority of the time they will have to stop walking so their mind can concentrate on what is being said. The mind needs to slow down so it can process the information and come up with a solution Then there is the other part of our mind that is intuitive, fast and automatic. This fast way of thinking is incredibly powerful and is responsible for most of the things that we say, do, think, and believe. Most of the time this “auto pilot” part of our mind makes the thousands of decisions needed each day without even realizing it. This is where the mistakes start to happen. While the second part of our mind is busy working, it will continue to do so until something negative happens. When this happens, the first part of the mind will take over to determine if it is a serious enough consequence to change our behavior. How about using a saw to cut a piece of wood, pipe, or steel by Shawn Meier without wearing eye protection? The act of sawing has become automatic as there have not been serious negative outcomes, so we don’t wear safety glasses all the time. Lose an eye while sawing and the logical slower part of our mind tells us to wear safety glasses as we only have one left. The mistake happened in our fast “get it done” automatic part of the mind, until something serious enough happened to cause our logical part of the mind to change our behavior. We now wear safety glasses all the time because we don’t want to lose the other eye. It is estimated that it takes 21 days of bad behavior to form a bad habit. If our fast mind goes 21 days without a negative consequence from the bad behavior, then it will become a bad habit. The severity of any consequence determines if it is worth changing the behavior and making it a good habit. Choose the behavior, choose the consequence. Good Behavior + Good Consequence = Good Habit. A small mistake in our fast mind is a warning sign that we need to Stop, Look, and Analyze the mistake to determine if we need to change our way of doing something. Mistakes are a tremendous opportunity for improving our safety efforts, production, and quality. By identifying that a mistake was made and analyzing it to change a bad habit to a good habit, we can dramatically reduce any negative outcomes Stop, Look, and Analyze the behavior or condition to reduce the negative consequence. Change a bad habit into a good habit, pick one…..lets change together. 2014 OSHA Safety Stand-Down Fall 2014 3 Highway 20 Bridges The spring of 2014 brought a new year for Civil Structures in the Rockford area with once again another challenging project. US 20 in Rockford between IL 251 and IL 2, is the site of this new project where 4 bridges carry traffic across the main channel and a tributary of the Rock River. This $22 Million dollar contract includes the full replacement of these four bridges and new concrete pavement between them. Each bridge will be a two span structure with 81”deep steel plate girders approx 420 ft long. Gerry Fye is the Carpenter Foreman leading the charge on behalf of the tradesmen. The project began on March 24th with the construction of concrete crossovers to facilitate shifting all the traffic onto the WB lanes in order for the EB bridges to be constructed. The crossovers proved to be a very tedious pre-stage piece of work. This work would ultimately not allow the bridge work to begin until May 29th. With two full bridges to remove and replace, it by John Schneider became extremely necessary to hit the ground running with a solid plan given that the interim completion date is November 30 when all traffic has to be restored to its original configuration. Once traffic was removed from the EB lanes, the demolition process began. Unlike traditional multi girder bridges, these existing structures only had two larger girders with transverse floor beams spaced at 13 feet on center. This condition made the deck slab removal a little tricky given that the excavator would have to be positioned just right for the transverse floor beams to carry the load back to the longitudinal girders. The position of the excavator made it difficult to pick the slabs with a fixed slab bucket attachment. Therefore, the purchase of a rotating coupler (Roto-Tilt) which allowed the slab pieces to be picked from different angles became the key to our success. When it came time to remove the beams, the excessive weight per foot of these existing 81” deep steel girders offered additional challenges given that the span length from pier to pier was between 100 and 130 feet long. A pre-engineered demolition plan was followed with very little deviation given the instability of the girders once the floor beams were removed. After demolition of the first structure was complete, we immediately went into the substructure construction by driving steel sheet piling in the river for the cofferdam of the lone pier. There were 72 14” diameter steel shell pile in the pier driven to an average depth of 35 ft and then a 70’x20’ footing 3.5’ thick poured around them. After the pier and both abutments were constructed, we were ready for the daunting task of erecting the new steel girders. Given the excessive weight of these 132 ft long beams and the very limited room to place a crane, we hired an outside crane company to bring in a 550 ton capacity truck crane to hoist 4 the beams over the pier into position without getting into the traffic in the existing WB lanes. We supplemented this crane with one of our own Link Belt 110 ton track cranes and a 50 ton Grove truck crane. The complete erection of the 18 beams (6 lines of 3 beams each) and 12 splices took 12 days. Just like in the demolition phase, there was a threat of buckling when a girder line was erected without intermediate cross bracing. We avoided this by having the 50 ton Grove hold the first girder line until the second one was installed and braced to the first one. The erection of the first structure finished without a hitch due to the relentless pursuit of excellence and creativity of the iron worker foreman, Doug Diddens and his great staff of iron workers. Worthy of special recognition are the operators, Mark Leverton and Vance VanOosten, who remained very calm and focused throughout all the difficult picks of the heavy beams. The second bridge lagged behind the first by approximately 2 weeks. Maintaining this lag time proved to be the key to staying on schedule and meeting the completion date. The second bridge was very similar in many ways with the exception of the 2015 will bring a mirror image of this year with the exception of an earlier start date since the crossovers are already built. Thanks to all of those who were an integral part in the 2014 construction. Some of those names include, but are not limited to: Jerry Fye, Bob Dixon, Brian Dixon, Jeff Johnson, Jerry Pardus, Mark Grobe, Adam Ruchti, Ben Higley, Ben Lipnitzky, Tim Powers, Trent Tipton, Dustin Cassidy, Becky Near, Willie Schmelzer, and Curt Ihrig. steel erection. This structure still had two spans but had an additional beam on each girder line creating two more splices per girder line. This resulted in a very unique 4 crane pick to erect the first girder line from the abutment to the pier. Getting all four cranes to work in concert without overstressing any of the beams was very difficult but armed with a good steel erection plan along with superior communication, it became manageable. Some other points of interest were pouring the first concrete deck with a 300 ft back out conveyor system, as well as pouring the second concrete deck with a 61 meter truck-mounted concrete pump that reached 180 ft. This pump was one of the largest truck mounted in the United States. The total amount of structural steel set this year exceeded 3.5 million pounds and the portland cement concrete poured was approximately 2700 cy. Fall 2014 5 2014 Helm Group Projects 6 I90 WB over the Kishwaukee River Elizabeth Quarry Woodward Governor John Deer Road Overpass Cuyahoga County Convention Center Hotel Railroad Ave. Bridge A Year in Review Freeport Fab Shop Plumbing PreFab Adkins Energy Effingham Highway 70 Bridge Lake Central High School Skokie Surgical Pavilion Fall 2014 Jane Adams Bike Trail 7 IL Route 26 Paving by Denny Heer This summer, Civil Roads successfully completed the second night paving project in its history on IL 26 through Freeport. High traffic counts made the project a challenge to plan and execute. To minimize disruption, the Illinois Department of Transportation decided to use a 25 night schedule rather than a longer schedule where work would be done during daytime with more traffic. The project consisted of pavement patching, miscellaneous curb repairs, selected inlet reconstructions, adjustment of manhole and water valve castings, milling 2 ¼” of asphalt, and replacement of the asphalt in two lifts. The schedule restrictions prevented us from working on the roadway between the hours of 1:00 PM to 6:00 PM with a fine of $500 for every 15 minutes work extended into this time frame. The acquisition of a complete set of lights from our purchase of Northwest Construction benefitted the project due to the high percentage of work performed at night. Kevin Powers and crew removed the manhole and water valve castings and, along with Scott Hayes’ crew, performed pavement patching on a nightly basis to prepare the surface for milling. It was determined that starting at 3:00 AM allowed the patching to be poured by 7:00 AM. The necessary strength could be obtained by 12:00 PM (noon) and the roadway could be cleared for traffic by 1:00 PM without a fine. The Ready-Mix supplier worked very effectively with the Civil crews to provide quality 5-hour concrete and timely service which allowed the project to progress quickly. Once the patching was completed and the utilities were lowered, Steve Rhode and crew took over along with Javelina Construction, the subcontractor that performed the milling. The project was sectioned into 4 nights of milling and paving level binder as the milled pavement was not allowed to have traffic placed on it until it was covered with level binder. This operation started around 8:00 PM and was completed by 8:00 AM most mornings. Many people were involved with this process as it was also our responsibility to make and ship the asphalt and perform the quality control on the mix. The city of Freeport restricts the use of vibration to compact asphalt mixes therefore Greg Peet and Heavy Construction Services were enlisted to rent heavy static rollers which allowed us to obtain the necessary compaction without vibration. After the level binder was complete, Pete Rhode and crew placed the surface mix on the mainline and Steve’s crew completed the incidental paving on all of the side roads. It was time to bring the utilities back to grade and Randy Quies led a crew to raise all of the manholes and water valves. This crew also worked at night and Scott Hayes’ crew would arrive at 4:00 AM to pour the concrete before they went on to work at other projects. The concrete again was poured using a 5-hour mix to get strength prior to 1:00 PM. The project was completed in 23 working days with only two items on the punchlist, one of which was cleaning up the staging area. There were a total of 68 different people on Civil’s payroll for this project. The expertise and dedication of all 68 individuals involved ensured the successful completion of this project. Thank you all and congratulations on a job well done! 8 Sheet Metal Fabrication Shop (continued from p.1) There is a production goal for each operation in the shop and the actual progress toward that goal hangs on the wall so that all employees know how they are doing. From late summer through the fall, the crews have hit their production goals. One of the changes made after the first few months that helped increase production was adding an extra fitting table and moving the tables to an area with more working area. The fitting operation is more labor-intensive than the other operations, so the team needed the area to be congestion-free. Another section of the shop is the weld area. Here, stainless steel and black iron duct is made for special applications such as industrial and kitchen exhaust. John McNamara and Steve Baxter manage the weld shop. The office area of the shop was renovated along with the shop area. In addition to the fabrication staff, offices are also used by Mechanical Service and Civil Structures employees that all have projects in the area. So far, the sheet metal shop has proven to be a huge advantage for the company. The investment has led to more projects by having lower costs and more control over the projects by selfperforming the work. Fall 2014 9 Chicago Athletic Association Mechanical is performing the plumbing for a major historic adaptive reuse of the former Chicago Athletic Association at 12 S. Michigan in the heart of downtown Chicago. The facility is being completely overhauled from the social/athletic club that closed in 2007 into a 240 room high end hotel complete with a new rooftop bar and banquet facilities throughout. It is a nineteen story building originally completed in 1893 that is designated as a historic landmark. The project has had and will have many obstacles and challenges, beginning with the new site water and sewer that required the closing of lanes on Michigan and Madison Avenues. To add to the logistical challenges of closing down the major roads, the work had to occur with limited interruption to attempt to alleviate the concerns of the neighboring building’s tenants and occupants. We were very happy to wrap up the site work in early April. The interior plumbing is currently being roughed in from the top down, while the lower floors are still being demolished and the CAD/BIM coordination team continues to iron out the 10 by Joel Maevers challenges below. The major challenges with the interior work of the project have come from the structural considerations and site logistics. The building’s floor supporting structure is clay tile that is held in place with tie rods. This represents quite a challenge with coring and being inventive with the layout as it has to be somewhat flexible to miss the tie rods. It also creates a little more difficulty when it comes to the hanging and securing of piping. The site logistics are difficult due to limited floor access and skip hoist access. Foreman Bill Mullner overcame one access challenge by using a combination of chutes and ramps to deliver stone to the basement through an opening at street level. Pipe was moved to the basement in a similar fashion. The project to date has gone well due to excellent planning and execution by the project team. In addition to Bill Mullner in the field, Bob Brady managed the prefabrication of the guestroom plumbing and John Lehane coordinated the BIM model. The project is scheduled to be turned over and ready for occupancy in March of 2015. The History of the Chicago Athletic Association The Chicago Athletic Association was founded in 1890 by prominent Chicagoans including retail magnate Marshall Field, inventor Cyrus McCormick, and A.G. Spalding. The CAA building was built in 1893 at 12 South Michigan Avenue. It was designed by Henry Ives Cobb in a Venetian Gothic style, rare for Chicago. The building’s façade, which is strongly reminiscent of the Doges Palace in Venice, was designed to give the CAA a distinctive identity when viewed from the lakefront, particularly by visitors to the World’s Columbia Exposition of 1893 and to be one of the most important and exclusive men’s clubs in the country. The architect, who was a club member, was well known for his designs for the Chicago Historical Society (more currently the Excalibur Club in River North), the Newberry Library, and several buildings at the University of Chicago. The building is widely considered one of the finest examples of Venetian Gothic architecture in the United States, and is one Fall 2014 of Chicago’s most adored buildings. It exudes an air of a faded glamour, but has architectural bones that are beyond reproach. It is often described as one of the most beautiful and highly detailed buildings in the country. The Chicago Athletic Association was a not-for-profit organization that provided a setting for athletic, business, and social activities. In 1915, when member William Wrigley bought the Chicago Cubs, the team adopted the club’s logo, permanently securing its place in Chicago history. The club survived until 2007 when it filed for bankruptcy. The Hyatt family recently purchased the building and the renovation in which we are a part of continues until the boutique hotel is complete. 11 P.O. Box 750 2283 US 20 BR E Freeport, IL 61032 PRSRT STD U.S. Postage PAID Rockford, IL Permit No. 781 Heavy Launches New Website During the past year, Heavy has been working closely with M45 Marketing Services to re-design the company website. The new website showcases all of Heavy’s traditional capabilities: parts, service, sales, as well as new product offerings such as Capello cornheads, tire sales and aluminum wheel polishing. Every department has its own page where customers can find specific information and the contact information they need to quickly get in touch with the proper representative. Customers searching for a used truck now have the ability to view current trucks for sale and make an offer online as well as request a quote for their own custom build. Parts customers can order and even pay for truck and agricultural parts online and have them shipped anywhere in the United States. Along with ordering agricultural equipment parts online, customers can check out the new Capello cornheads and see them in action with the videos on the Capello page. There is also a link to Heavy’s eBay store where customers nationwide can purchase anything from truck parts to pickup trucks. Heavy’s Service Department is also featured with full-service tire sales and aluminum wheel polishing pages. Heavy’s website prominently spotlights and markets our many offerings and is crucial to attracting new customers and meeting the dynamic needs of existing customers. Be sure to check it out! http://heavy.helmgroup.com United Way Donation Thank you to all employees that donated two hours of pay to the United Way and it’s member agencies in October. Employees donated $43,702 and the Helm Group matched this amount for a total donation of $87,404.