Perfect-Integrated Lightning Surge Protection Solution
Report for Survey & < eca3G > Installation
for Royal Malaysia Police - 6 Sites
June 21. 2011
THAMES TECHNOLOGY SDN BHD
< eca3G > Installation for Royal Malaysia Police
- 6 Sites
SITE Name
1. Balai Polis
Setapak
2. Balai Polis
Trafik KL
3. Balai Polis
Sungei Besi
4. Balai Polis
Sri Permaisuri
Survey date
Installation Date
Installed <eca3G>
Remark
MAR 13 (Tue),2012.
Apr 10 (Tue),2012.
Two <eca3G-LP, 3P>
One <eca3G-LP, 1P>
SETAPAK Police
Station
Mar 14 (Wed),2012.
Apr 13 (Fri),2012.
Apr 20 (Fri),2012
Three <eca3G-LP, 3P>
One <eca3G-LP, 1P>
Mar 14 (Wed),2012.
Apr 16(Thu). 2012
May 29 (Mon). 2012
Two <eca3G-LP, 3P>
Sungei Besi
Police Station
Apr 20 (Fri),2012.
Apr 20 (Fri),2012.
One <eca3G-LP, 3P>
Sri Permaisuri
Police Station
May 22 (Tue),2012.
Jun 05 (Tue),2012.
Two <eca3G-LP, 3P>
Transport Work shop
Branch station
May 24(Thu),2012.
Two <eca3G-LP, 3P>
Police Training Center
( PULAPOL) ,
Branch Commander
Office
May 29 (Tue),2012.
One <eca3G-LP, 3P>
One <eca3G-LP, 1P>
Police Training Center
( PULAPOL) ,
Branch School
5. Cawangan
Pengangkutan
May 18(Fri),2012.
6.PULAPOL
a. Cawangan
Kem Komandan
6.PULAPOL
May 18 (Fri),2012.
b. Cawangan
Sekolah
Total 6 sites
Kuala Lumpur Traffic
Control Center
1. Balai Polis Setapak
(Setapak Police Station)
- Survey Date : Mar 13 (Tue), 2012.
- Installation Date : Apr 10 (Tue), 2012.
1. Balai Polis Setapak : <eca3G> Installation / Apr 10 (Tue),2012.
SITE Name
Balai Polis Setapak
Protected Facility
Frequent Power Trip
PRS Cabinet & PABX
Surveyed Date
Mar 13 ( Tue), 2012
PDRM : ISP Azizi
Thames : Rahim, Norshabudin, JB
Installation Date
Installed <eca3G>
<eca3G> Location
Site Status
Improvement Work
Apr 10 ( Tue),2012. 09:30pm~1:30 am
PDRM : ISP Azizi, encik Nazmi, encik Fikri, encik Amier
Thames : Rahim, Norshabudin, Anwar, JB , Mr Woo
DB at Ground Floor
: One <eca3G-LP, 3P>
DB at !FL
: One <eca3G-LP, 3P>
PRS room at 1 FL
: One <eca3G-LP, 1P>
DB : Inside of DBs
PRS : inside of Cabinet
- Frequent Power trip
- PRS system damages
- PABX damage, hang
- Power grounding & communication grounding is not connected.
- PRS cabinets have not groundings
- Combine groundings of PRS cabinets, PABX, connect to <eca3G>.
- Improve bonding status of rack & equipment in cabinets
- <eca3G> monitors power line surge, reverse surge, induced surge,
via Distribution Boards , and eliminate with equi-potential status
- N-G : 3.8 V (before) , N-G : 0.026 (after )
1. Balai Polis Setapak : <eca3G> Installation
TNB Meter
Ground
PRS
PABX
DB at Ground
PRS
Room
1 FL
DB with TNB
Meter / 1 FL
Reporting
Room /GL
1. Balai Polis Setapak : <eca3G> Installation
<eca3G> preparation
DB at Ground Floor
<eca3G> preparation
<eca3G> installation at GL-DB
<eca3G> preparation
TNB Meter at Ground Floor
1. Balai Polis Setapak : <eca3G> Installation / Apr 10 (Tue),2012.
DB at 1st Floor – burn mark
<eca3G> installation at 1 FL-DB
TNB Meter for 1 FL-DB
PRS Room preparation
N-G : 0.026V after <ec3G> installation
PRS room grounding to <eca3G>
1. Balai Polis Setapak : <eca3G> Installation / Apr 10 (Tue),2012.
PRS Cabinet without Grounding
Grounding improvement for equipment
Bonding improvement for PABX
Bonding improvement for PABX
<eca3G> for PRS Cabinet grounding
Bonding improvement for PRS
2. Balai Polis Trafik KL
( Kuala Lumpur Traffic Control Center
Station)
- Survey Date : Mar 14 (Wed), 2012.
- Installation Date :
Apr 13 (Fri), 2012 for Main DB, DBs
Apr 20 (Fri), 2012 for PRS cabinet.
2. Balai Polis Trafik KL : <eca3G> Installation / Apr 20 (Fri),2012.
SITE Name
Protected Facility
Surveyed Date
Installation Date
Installed <eca3G>
<eca3G> Location
Site Status
Improvement Work
Balai Polis Trafik KL
Frequent Power Trip
PRS Cabinet & PABX
Mar 14 ( Wed), 2012
PDRM : ISP Azizi
Thames : Rahim, Norshabudin, JB
Apr 13 ( Fri),2012. 09:30pm~3:30 am for Main DB, two DBs
Apr 20 ( Fri),2012. 10:00pm~11:30 am for PRS cabinet
PDRM : ISP Azizi, encik Nazmi, encik Fikri, encik Amier
Thames : Rahim, Norshabudin, Anwar, JB
Main DB with TNB Meter , DB for PRS, DB for PABX
: Three <eca3G-LP, 3P>
PRS Cabinet
: One <eca3G-LP, 1P>
Main DB : Inside of Main DB
DB for PABX : beside of DB, on the wall
DB for PRS : beside of DB, on the wall
PRS Cabinet : behind of Cabinet
- Frequent Power trip
- PRS system damages
- PABX damage, hang
- Power grounding & communication grounding is not connected.
- PRS cabinets have not groundings
- Improve bonding status of rack & equipment in cabinet ,
provide grounding & surge protection for PRS
- Connect PABX communication grounding to power grounding, with
<eca3G >
- <eca3G> monitors power line surge, reverse surge, induced surge,
via Distribution Boards , and eliminate with equi-potential status
- N-G : 2.1 V (before) , N-G : 0.03 (after )
2. Balai Polis Trafik KL : <eca3G> Installation
PRS
Room
PABX
Room
TNB TR
Main DB
DB
2. Balai Polis Trafik KL : <eca3G> Installation
<eca3G> preparation
N-G potential difference before
<eca3G> installation : 2.1 V
Connect all <eca3G>s with bomba
piping
N-G after <eca3G> installation at
Main DB : 0.03 V
Bonding with conductive conduit
<eca3G> connection to Main DB
Bus Bar
2. Balai Polis Trafik KL : <eca3G> Installation
<eca3G> install at Main DB
Grounding connection at Main DB
<eca3G> at DB for PRS
<eca3G> at DB for PRS
<eca3G> for PRS Cabinet grounding
Bonding improvement
2. Balai Polis Trafik KL : <eca3G> Installation / Apr 10 (Tue),2012.
<eca3G> installation at
PABX room DB
<eca3G> installation at
PABX room DB
Pipe Bonding at PABX room
Bonding improvement at Cabinet
equipment
Grounding connection for PRS cabinet,
Router cabinet, conductive pipe
<eca 3G > for PRS cabinet
3. Balai Polis Sungei Besi
( Sungei Besi Police Station)
- Survey Date : Mar 14 (Wed), 2012.
- Installation Date :
Apr 19 (Thu), 2012 - install <eca3G>
Apr 20 (Fri), 2012 - connect to power line
May 29 (Mon), 2012 – improve N-G bonding
3. Balai Polis Sungei Besi : <eca3G> Installation / Apr 20 (Fri),2012.
SITE Name
Protected Facility
Surveyed Date
Installation Date
Installed <eca3G>
<eca3G> Location
Site Status
Improvement Work
Balai Polis Sungei Besi
Frequent Power Trip
PRS Cabinet & PABX
Mar 14 ( Wed), 2012
PDRM : ISP Azizi
Thames : Rahim, Norshabudin, JB
Apr 19 ( Thu ),2012. 09:00pm~1:00 am , cabling, installtion
Apr 20 ( Fri),2012. 3:00pm~5:00 pm , power line connect
May 29 (Mon). 2012. 11:00 am – 12:00 , N-G improvement
PDRM : ISP Azizi, encik Nazmi, encik Fikri, encik Amier
Thames : Rahim, Norshabudin, Anwar, JB
Main DB with TNB Meter : One <eca3G-LP, 3P>
DB for PRS
: One <eca3G-LP, 3P>
Main DB : Inside of Main DB
DB for PRS : beside of DB, on the wall
- Frequent Power trip
- PRS system damages
- Power grounding & communication grounding is not connected.
- PRS cabinets have not groundings
- Improve bonding status of rack & equipment in PRS cabinet , connect
to <eca3G> for grounding & surge protection for PRS
- Connect PABX communication grounding to power grounding,
- <eca3G> monitors power line surge, reverse surge, induced surge,
via Distribution Boards , and eliminate with equi-potential status
- N-G : 0.48 V (before) , N-G : 0.035 V (after )
3. Balai Polis Sungei Besi : <eca3G> Installation
Reporting
Room
DB
PRS
PABX
Main DB
IP PABX
Room
3. Balai Polis Sungei Besi : <eca3G> Installation
Grounding Cable for PRS : float
Isolate grounding for PABX
PRS Cabinet – improvement of bonding,
grounding, connect to <eca3G>
PABX communication grounding
connect to power grounding
< eca 3G > preparation
Main DB connection
3. Balai Polis Sungei Besi : <eca3G> Installation
<eca3G> connection at Main CB
<eca3G> connection at Main DB
<eca3G> at DB for PRS
<eca3G> at DB for PRS
N-G after <eca3G> installation at
Main DB : 0.035 V
< eca3G> connection at DB
4. Balai Polis Sri Permaisuri
( Sri Permaisuri Police Station)
- Survey Date : Apr 20 (Fri), 2012.
- Installation Date : Apr 20 (Fri), 2012
4. Balai Polis Sri Permaisuri : <eca3G> Installation / Apr 20 (Fri),2012.
SITE Name
Protected Facility
Balai Polis Sri Permaisuri
Frequent Power Trip
PRS Cabinet
Surveyed Date
Mar 20 ( Fri ), 2012
PDRM : ISP Azizi
Thames : Rahim, Norshabudin, JB
Installation Date
Apr 20 ( Fri),2012. 5:30pm~7:30 pm
PDRM : ISP Azizi, encik Nazmi, encik Fikri, encik Amier
Thames : Rahim, Norshabudin, Anwar, JB
Installed <eca3G>
DB for building : One <eca3G-LP, 3P>
<eca3G> Location
beside of DB, on the wall
- Frequent Power trip
- Power grounding & communication grounding is not connected.
- PRS cabinets have not groundings
- Improve bonding status of rack & equipment in PRS cabinet , connect
to <eca3G> for grounding & surge protection for PRS
- Connect antenna grounding to <eca3G>
- <eca3G> monitors power line surge, reverse surge, induced surge,
via Distribution Boards , and eliminate with equi-potential status
- N-G : 4.1 V (before) , N-G : 0.012 V (after )
Site Status
Improvement Work
4. Balai Polis Sri Permaisuri : <eca3G> Installation
4. Balai Polis Sri Permaisuri : <eca3G> Installation
Power supply to the building
DB : 3P 4W
PRS Cabinet - no grounding,
Wireless system antenna : isolate
grounding
N-G before install : 4.1 V
MGB to external Grounding rod
4. Balai Polis Sri Permaisuri : <eca3G> Installation
Grounding connection to PRS
cabinet to <eca3G>
<eca3G> at DB
Grounding cabling : bonding
improvement
<eca3G> at beside of DB
<eca3G> preparation
N-G after <eca3G> installation at
DB : 0.012 V
5. Cawangan Pengangkutan
( Transport Branch )
- Survey Date : May 22 (Tue), 2012.
- Installation Date : June 05 (Tue), 2012
5. Cawangan Pengangkutan ( Transport Branch )
SITE Name
Protected Facility
Cawangan Pengangkutan ( Transport Branch )
Frequent Power Trip
PRS Cabinet and PABX
CCTV , DVR,
Surveyed Date
May 22 ( Tue) , 2012
PDRM : ISP Azizi
Thames : Rahim, Norshabudin, JB
Installation Date
Installed <eca3G>
<eca3G> Location
Site Status
Improvement Work
June 05 ( Tue ),2012. 11:00pm~3:30 pm
PDRM : ISP Azizi, encik Nazmi, encik Fikri, encik Amier
Thames : Rahim, Norshabudin, Anwar, JB
DB 1 for PRS cabinet building
: One <eca3G-LP, 3P>
DB 2 for Monitoring building ( DVR, PABX) : One <eca3G-LP, 3P>
beside of DB 1, on the wall
beside of DB 2, on the wall
- Frequent Power trip
- Power grounding & communication grounding is not connected./PABX
- PRS cabinet has not grounding, frequent damaged
- CCTV, DVR damaged
- PC damaged
- Improve bonding status of rack & equipment in PRS cabinet , connect
to <eca3G> for grounding & surge protection for PRS
- Connect PABX grounding to power grounding
- <eca3G> monitors power line surge, reverse surge, induced surge,
via Distribution Boards , and eliminate with equi-potential status
- Surge eliminate through coaxial cable
- N-G : 0.46 V (before) , N-G : 0.003 (after )
5. Cawangan Pengangkutan : <eca3G> Installation
Lake side
CCTV – 8 units
Grounding Rod
Work shop
<eca3G-LP>, 3P
8 SPD for DVR
cable connection
GR
Office B/D
10M x 20M
Meeting B/D
6M x 10M
GR
GR
DB 2
HUB
Cabinet
DB 1
GR
Monitoring
5M x 6M
Meer
GR
GR
Monitor
DVR
GR
Motor driven
Sliding Door
Road side
PABX
5. Cawangan Pengangkutan : <eca3G> Installation
PRS cabinet bonding improvement
< eca3G> at PRS DB ( DB 1)
< ROUTER>- grounding point
connected to <eca3G> MGB
< eca 3G > installation at DB 1
Grounding cabling of PRS to
<eca3G>
N-G after < eca3G > installation :
0.003 V
5. Cawangan Pengangkutan : <eca3G> Installation
< eca 3G > installation at DB 2
( for DVR, PABX building )
< eca 3G > installation at DB 2
( for DVR, PABX building )
<video SPD > preparation for DVR
< video SPD > installed at DVR input
CCTV ( eight ) – 4 CCTV were
damaged
PABX grounding connect to power groun
6-a. Cawangan Kem Komandan
( PULAPOL)
Police Training Center , Branch Commander Office
- Survey Date : May 18 ( Fri ), 2012.
- Installation Date : May 24 (Thu ), 2012
6-a. Cawangan Kem Komandan ( PULAPOL)
SITE Name
Protected Facility
Cawangan Kem Komandan ( PULAPOL)
Frequent Power Trip
PRS Cabinet and PCs damages
Surveyed Date
May 18 ( Fri ) , 2012
PDRM : ISP Azizi
Thames : Rahim, Norshabudin, JB
Installation Date
Installed <eca3G>
<eca3G> Location
Site Status
Improvement Work
May 24 ( Thu ),2012. 11:00pm~4:00 pm
PDRM : ISP Azizi, encik Nazmi, encik Fikri, encik Amier
Thames : Rahim, Norshabudin, Anwar, JB
DB 1 for Office 1 : One <eca3G-LP, 1P>
DB 2 for Office 2 : One <eca3G-LP, 1P>
beside of DB 1, on the wall
beside of DB 2, on the wall
- Frequent Power trip
- Power grounding & communication grounding is not connected./PABX
- PRS cabinet has not grounding, frequent damaged
- PC damaged
- Improve bonding status of rack & equipment in PRS cabinet , connect
to <eca3G> for grounding & surge protection for PRS
- <eca3G> monitors power line surge, reverse surge, induced surge,
via Distribution Boards , and eliminate with equi-potential status
- N-G : 6.95 V (before) , N-G : 0.057 (after ) / DB 1
- N-G : 7.19 V (before) , N-G : 0.027 (after ) / DB 1
6-a. Cawangan Kem Komandan ( PULAPOL) : <eca3G> Installation
6-a. Cawangan Kem Komandan ( PULAPOL) : <eca3G> Installation
PRS cabinet bonding improvement
N-G : 6.95V before install < eca3G>
at DB 1
1P 2W power supply from TNB
Grounding point of DB is floating, not
connected to grounding rod.
DB 1 and PRS Cabinet ( no
grounding)
Grounding improvement for
PRS cabinet
6-a. Cawangan Kem Komandan ( PULAPOL) : <eca3G> Installation
< eca 3G > installation at DB 1
< eca 3G > installation at DB 1
N-G : 0.053 V after install < eca3G>
at DB 1
< eca 3G > installation at DB 2 at
Office 2
< eca 3G > installation at DB 2 at
Office 2
N-G : 0.019 V after install < eca3G>
at DB 2 at Office 2
6-b. Cawangan Sekolah
( PULAPOL)
Police Training Center , Branch School
- Survey Date : May 18 ( Fri ), 2012.
- Installation Date : May 24 (Thu ), 2012
6-b. Cawangan Sekolah ( PULAPOL)
SITE Name
Protected Facility
Surveyed Date
Installation Date
Installed <eca3G>
<eca3G> Location
Site Status
Improvement Work
Cawangan Sekolah ( PULAPOL)
Frequent Power Trip ( Whole building )
Hub Cabinet ( 1 FL) : surge damages
May 18 ( Fri ) , 2012
PDRM : ISP Azizi
Thames : Rahim, Norshabudin, JB
May 24 ( Thu ),2012. 2:00pm~6:00 pm : Install & improving
May 29 ( Tue ). 2012. 11:00am~1:00 pm : Connect grounding cable
between Switched and Main DB
June 20 (Wed ). 2012, 6:00pm~6:30 pm : Grounding cable connection
between Main DB eca3G and Hub Cabinet eca3G directly
PDRM : ISP Azizi, encik Nazmi, encik Fikri, encik Amier
Thames : Rahim, Norshabudin, Anwar, JB
Main DB at the Lobby : One <eca3G-LP, 3P>
Hub Cabinet at 1 FL : One <eca3G-LP, 1P>
Main DB : inside of Main DB
Hub Cabinet : inside of Cabinet
- Frequent Power trip
- Power grounding & communication grounding is not connected.
- Grounding cable connection status is poor, between Main DB and
Switched, Main DB to upper floor DBs,
( no connectivity from Main DB to Hub Cabinet )
- Hub cabinet has not grounding, Surge damaged
- Improve bonding status of rack & equipment in Hub cabinet , connect
to <eca3G> for grounding & surge protection for PRS
- <eca3G> monitors power line surge, reverse surge, induced surge,
via Distribution Boards , and eliminate with equi-potential status
- Additional Grounding cabling between Main DB and Switched.
- Grounding cable connection between Main DB eca3G and Hub
Cabinet eca3G directly
- Main DB : N-G : 3.6 V (before) , N-G : 0.054 (after )
- Hub Cabinet : N-G : 6.9 V (before) , N-G : 0.145 (after ) at Receptacle
6-b. Cawangan Sekolah ( PULAPOL ) : <eca3G> Installation
Hub Cabinet
Room / 1FL
Meer
Main DB
Main Lobby
GD FL
HUB
Cabinet
6-b. Cawangan Sekolah ( PULAPOL ) : <eca3G> Installation
<Switches> and Main DB
- no grounding connection
Grounding cable installed between
<Switches> and Main DB
( a little improved at 1 FL )
Grounding cable in Main DB : float
ZCT, <eca3G> cable connections in
Main DB
< eca 3G > preparation
< eca 3G > installation at Main DB at
the Lobby
6-b. Cawangan Sekolah ( PULAPOL) : <eca3G> Installation
N-G : 0.054 V after install < eca3G>
at Main DB at the Lobby2
Main DB
Grounding Cable in Main DB : connect
to MGB ( improvement )
Hub cabinet at 1 FL, no grounding
Grounding cable installed between
<Switches> and Main DB
Bonding improvement of Hub Cabinet
at 1 FL
6-b. Cawangan Sekolah ( PULAPOL) : <eca3G> Installation
Direct grounding cable connection
between Main DB ecaG and Hub
cabinet eca 3G
Grounding cable connection at <eca3G>
of Main DB from <eca3G> of hub
cabinet
N-G improve 0.145 V from 4.9 V
after direct connection for two
<eca 3G > at Receptacle , 1 FL
<eca3G> at Hub Cabinet - Direct
connected grounding cable from
Main DB
<eca3G> at Hub Cabinet - Direct
connected grounding cable from Main
DB
N-G improve 0.211 V from 4.9 V
after direct connection for two
<eca 3G > at Cabinet , 1 FL
THANK YOU !!

Similar documents

Bandar Kinrara TM Sites survey

Bandar Kinrara TM Sites survey Perfect-Integrated Lightning Surge Protection Solution Ebor North Toll , Shah Alam Report for < eca3G > Installation

More information

N Washington State Convention Center Level One: Entrances

N Washington State Convention Center Level One: Entrances 3. Theater, Classroom and “At Rounds” sets in the following meeting rooms include front of room space adequate for head table on a riser: Rooms 602-614 @ 10’ to 12’ deep; Rooms 615-620, 4C1-4 and ...

More information