Overview of AI Motorway Corridor Vc and Corridor X

Transcription

Overview of AI Motorway Corridor Vc and Corridor X
Overview of the Adriatic-­Ionian Motorway (Mediterranean corridor)
Albanian and Montenegrin sections
•
Start: Neum Northwest/CRO border/Debeli Brijeg (MNE)
•
End: Kakavije (ALB-­GRE border)
•
Length: approx. 342 km (MNE:110 km, ALB: 232 km)
•
Average daily traffic : 9,593 veh/day (Route 1), 6,302 veh/day (Route 2b)
ADRIATIC-­IONIAN MOTORWAY
Ongoing projects:
1) Feasibility Study for the Adriatic-­Ionian Motorway/Expressway • WBIF grant, 4 million EUR (2.5 ml Euro to Albania and 1.5 ml Euro to Montenegro)
2) Route 2c – Construction of Levan – Tepelene (95% completed)
• Total cost 106 million EUR
Projects in preparation (*)
1) Adriatic-­Ionian Motorway/Expressway -­ Route 1 (MNE)
• Total est. cost 880 million EUR
2) Adriatic-­Ionian Motorway/Expressway -­ Route1/Route 2b/Corridor VIII/Route 2c (ALB)
• Total est. cost 698 million EUR
I.
Route 2b -­ Upgrade of Thumane-­Kashar-­Vore Road connection node
•
Total est. cost 90 million EUR
II. Route 2b – Construction of Tepelene bypass
•
Total est. cost 38 million EUR
III. Route 2b – Construction of Lezha bypass
•
Total est. cost 24 million EUR
(*) Based on the Multi-­annual Plan (MAP) Priority project list
ADRIATIC-­IONIAN MOTORWAY
Total estimated cost for these sections : 1.850 M€ of which 200 M€ already spent.
1.650 M€ still to be invested
Overview of Corridor Vc
(Mediterranean Corridor road and rail)
Start: Bosanski Samac (BiH/Croatian border -­ North)
End: Bijaca (BiH/Croatian border –
South)
Length: 400 km
AADT: 9,120 veh/day
Start: Bosanski Samac (BiH)
End: Capljina (BiH)
Length: 428 km
Ton km: 1,020 million tkm (24% of regional freight traffic)
PROJECTS ON CORRIDOR Vc
ROAD PROJECTS:
Ongoing projects:
1) Construction of motorway section Svilaj-­ Odžak, Border Crossing and Interstate Bridge on the Sava River”. WBIF Contribution of 22 million EUR (investment co-­financing grant) + 350,000 (TA grant)
Ø est. cost of project: 109,35 million EUR (WBIF financing approved in 2015)
2) Upgrade of motorway section Zenica North-­Zenica South/Drivusa
Ø est. cost of project: 227,9 million EUR
ROAD PROJECTS:
Potential projects for funding (*) :
1)
Ø
Construction of motorway section Odzak Vukosavlje – Podnovolje – Rudanka –
Doboj south est. cost :356 million EUR
2) Completion of motorway section Tarcin – Konjic
Ø est. cost: 400 million EUR
3) Completion of motorway section Mostar north – Pocitelj
Ø est. cost: 350 million EUR
4) Motorway section: Buna – Počitelj
Ø est. cost : 35,5 million EUR
5) Motorway section: Mostar south–Buna
Ø Test. cost: 183 million EUR
6) Motorway section: Nemila–Zenica North
Ø est. cost : 146,06 million EUR
7) Motorway section: Tunnel Zenica-­ Tunnel Pečuj
est. cost : 37,47 million EUR
(*) Based on the Multi-­annual Plan (MAP) Priority project list, Single Pipeline projects
ROAD PROJECTS corridor Vc:
Total amount estimated : 1.827 M€
of which 227 M€ on going activities
and
109 M€ allocated from WBIF
Investment still needed: approx. 1.600 M€
RAILWAY PROJECTS:
Ø Ongoing project:
1)
Track rehabilitation and signalling improvement of section Sarajevo -­ Bradina
Ø Total est. cost-­ 41 million EUR (EBRD loan)
Ø Projects Eligible for Funding -­ Multi-­ annual Plan (MAP) Priority project list :
1)
Overhaul of railway section Sarajevo – Podlugovi (nominated in MAP 2016 and pre-­identified list of Core Network projects)
Ø Total est. cost – 22,5 million EUR
Total investment forseen in rail on Corridor Vc = 65 M€
How much still needed to improve the corridor's
performance?
Overview of Corridors X, Xb,Xc
(Orient East Road Corridor : road)
Corridor X
Start: Batrovci R/Croatian border)
End: Bogorodica (MKD/Greek border)
Branch Xb
Start: Hungarian border/Horgos
End: New Belgrade (SER)
Branch Xc
Start: Nis (SER)
End: Gradina/BG Border
Length: 1,021 km
AADT: 30,129 veh/day
Overview of Corridors X, Xb,Xc
(Orient East Med : rail)
Corridor X
Start: Sid (SER)
End: Gevgelija/GR border)
Branch Xb
Start: Hungarian border/Kelebija
End: Stara Pazova (SER)
Branch Xc
Start: Nis (SER)
End: Dimitrovgrad/BG Border
Length: 985 km
Ton km: 2,142 million tkm
ROAD PROJECTS ON CORRIDORS X, Xb, Xc
ONGOING ROAD PROJECTS
ROAD PROJECTS
Projects for preparation -­ Multi-­annual Plan (MAP) 2016 Priority project list :
1) Implementation of ITS on Road Corridor X (MKD)
Ø Total est. cost: 20 million EUR
Projects eligible for funding -­ Multi-­annual Plan (MAP) 2016 Prority project list :
1) Completion of Belgrade bypass, sector 6: Strazevica – Bubanj Potok (SER)
Ø Total est. cost: 97 million EUR
2) Rehabilitation of the road section Negotino – Demir Kapija (MKD)
Ø Total est. cost: 9 million EUR
ROAD PROJECTS ON CORRIDORS X, Xb, Xc
Total cost of on-­going ROAD PROJECTS : approx 1.560 M€
Investment foreseen : 130 M€
RAILWAY PROJECTS ON CORRIDORS X, Xb, Xc
ONGOING RAILWAY PROJECTS
RAILWAY PROJECTS
Potential projects(*) :
1)
Modernization of Nis – Presevo (border with MKD) railway line
Ø Total est. cost: 265 million EUR
2)
Reconstruction, modernization and construction of the second track on section Stalac –
Djunis of the railway Belgrade – Nis
Ø Total est. cost: 106 million EUR
3)
Modernization for the contemporary double-­track traffic of the single-­track section of railway line Resnik – Klenje – Mali Pozarevac – Velika Plana
Ø Total est. cost: 368 million EUR
4)
Corridor Xb: Reconstruction and modernization of track from Belgrade – Novi Sad –
Serbian/Hungarian border (Horgos)
Ø Total est. cost: 791 million EUR
5)
Corridor Xc: Electrification and upgrading of Nis – Dimitrovgrad – Serbian/Bulgarian border (Dimitrovgrad)
Ø
Total est. cost: 170 million EUR
(*) Based on the Multi-­annual Plan (MAP) Priority project list
Total investment on-­going in rail : 214 M€
Investment needed 1.680 M€