ReNew Canada - Top100 Projects
Transcription
ReNew Canada - Top100 Projects
2013 top100projects.ca 2013 Top 100 Projects The 2013 Top 100 Projects Top 100 Projects — 2013 An annual report inserted in ReNew Canada’s January/February 2013 issue EDITOR Mira Shenker [email protected] RESEARCH Douglas McCallum, ASSOCIATES René Biberstein PUBLISHER Todd Latham [email protected] ART DIRECTOR Donna Endacott & DESIGN ASSOCIATE Kerry Freek EDITOR CIRCULATION James Watson, ADPIC [email protected] P. 416-444-5842, ext 211 ADVERTISING Chris Tully [email protected] Todd Latham [email protected] Lee Scarlett [email protected] ReNew Canada is published six times a year by Actual Media Inc. 218 Adelaide St. W., 3rd Flr, Toronto, ON M5H 1W7 Phone: 416.444.5842 Fax: 416.444.1176 Toll Free: 1.877.663.6866 T his year, we added an impressive 49 new projects to the list of Canada’s biggest infrastructure projects. That’s double the value of last year’s 29 new additions ($60 billion versus $30 billion). That means twice the renewed investment in Canada’s construction industry. Last year’s number one project was a transit project—the notorious Eglinton Crosstown LRT, making headlines for its increased scope and cost. This year, energy is back on top, with hydroelectric projects claiming the top three spots (see “Value by Energy Type,” page 32). There are $57-billion worth of energy projects on this year’s Top 100—that’s 40 per cent of the total list value. (For the full breakdown, see page 54.) Of course, by “top,” we simply mean most expensive. Projects listed in this annual report are ranked by dollar value—not the cost of individual contracts, but the cost of the entire project, including materials and labour. In some cases, it includes the cost attached to a long-term, fixed-price contract to not only build an asset, but to maintain or operate it over a period of time. To secure a spot on the list, projects must still be underway, whether undergoing an Environmental Assessment, in procurement, or under construction. Oil and gas pipelines are ineligible because they’re not public works; they’re also too big. Including them would skew the list, taking over almost the entire Top 10. This year, we invited some of the list’s most visible key players to a roundtable discussion about the Top 100. (Look for the story in ReNew Canada’s January/February 2013 issue). Our decision to exclude oil and gas projects was at the centre of a discussion about what this report says about Canada, and how Canada is seen by other countries. One point upon which all of the roundtable participants agreed is that Canada, relative to other countries, consistently delivers an impressive amount of mega-projects across several sectors. This seventh annual report has the highest total value of any previous Top 100. It represents over $140 billion in investment—an affirmation that Canada’s infrastructure industry is thriving. Mira Shenker Editor, ReNew Canada Subscription services: 416-444-5842, ext 211 ReNew Canada subscriptions are available for $29.95/year or $54.95/two years and include the annual Top 100 Projects. ©2013 Actual Media Inc. All rights reserved. The contents of this publication may not be reproduced by any means in whole or in part, without prior written consent from the publisher. Looking for a more detailed company directory? Visit top100projects.ca/company-directory To create your own report, visit top100projects.ca/ 2013filters and sort by project cost, key players, location, sector, and more. Printed in Canada "ReNew Canada" and "ReThink. ReBuild. ReNew" are Trademarks of Actual Media Inc. It’s never too soon to get started on next year’s list. Our research team is already taking submissions and filing information on funding and key players. Contact [email protected] to submit information or visit top100projects.ca/submit-a-project top100projects.ca ReNew Canada 3 2013 Top 100 Projects Top 100 Project Index (continued) Buildings page By Rank, Project Title and Page Reference Energy page 71BC Children’s Hospital / BC Women’s Hospital & Health Centre Redevelopment 62 83Armow Wind Farm 65 8Bipole II Transmission Line 14 54Canadian Forces Base (CFB) Trenton Expansion 38Boundary Dam Integrated CCS Demonstration Project 44 58Canpotex Potash Terminal 58 78Darlington Refurbishment Project 64 98Des Moulins Wind Farm 70 54 15CHUM (Centre hospitalier de l’université de Montréal) Redevelopment 20 94Edmonton Arena 68 66Expansion and Renovation of L’Hôtel-Dieu de Québec 60 22Humber River Regional Hospital 28 52Long-Term Accommodation (LTA) Project 52 33McGill University Health Centre (MUHC) at Glen Campus 40 100 New Colisée 70 19New Oakville Hospital 68Forrest Kerr Run-of-River Project 61 88Gordon M. Shrum Generating Station Refurbishment 66 95Grand Renewable Energy Park 69 81Greenfield South (previously Sherway) Natural Gas Plant 64 12Muskrat Falls Hydroelectric Project 18 84Northwest Transmission Line 65 47Pehonan Hydroelectric Dam 51 96Pointe Du Bois Spillway Replacement Project 69 25Renovations to Beauharnois Hydroelectric Station 32 59Riviere du Moulin Wind Farm 58 28Rocky Creek Wind Energy Project 34 2Romaine Complex 10 53Ruskin Dam and Powerhouse Upgrade 54 60Seigneurie de Beaupré Wind Farms 2 and 3 58 35Shepard Energy Centre 42 1Site C Clean Energy Project 9 26 26H.R. Milner Coal Plant Expansion 32 61South Kent Wind Project 59 79North Island Hospitals Project 64 67Interior to Lower Mainland Transmission Project 60 80Southern Alberta Transmission Reinforcement 64 24Outremont Campus, Université de Montréal 30 40John Hart Replacement Project 46 27Swan Hills ISCG/ Power Project 32 49Sainte-Justine University Hospital Centre Modernization 51 72Juan de Fuca Power Cable 62 51Waneta Expansion 52 57K2 Wind Project 58 Other 85Shields Health and Education Centre 3Keeyask Hydroelectric Project 10 62Capital Region District Sewage Treatment Plant 65 70St. Joseph’s Healthcare Hamilton, West 5th Campus Redevelopment 61 page 59 17Labrador Island Transmission Link 22 42Deep Geological Repository 48 69Lac Alfred Wind Farm 61 89Hanlan Feedermain 14Lower Mattagami Hydroelectric Complex 20 99Lions Gate Secondary Wastewater Treatment Plant 70 66 55St. Joseph’s Healthcare: London’s Specialized Mental Health Care and Forensic Mental Hospital 56 41Maritime Transmission Link 48 36Port Hope Area Initiative 42 86Surrey Memorial Hospital Expansion 66 73Marmora Pumped Storage Project 62 82Southeast Collector Trunk Sewer 65 90Waypoint Centre for Mental Health Care 67 65Mica Generating Station Upgrade 60 48Mount MacDonald Wind Project 51 91Women’s College Hospital Redevelopment 67 top100projects.ca 97Sydney Tar Ponds Cleanup 69 77Woodward Avenue Wastewater Treatment Plant Expansion and Upgrades 63 ReNew Canada 5 2013 Top 100 Projects Top 100 Project Index (continued) Transit 5Eglinton Crosstown page By Rank, Project Title and Page Reference 31York Viva Bus Rapid Transit (BRT 12 Transportation 29Evergreen Line Rapid Transit Line 36 18Calgary International Airport Developments 46Finch LRT 50 Light Rail Transit (LRT 38 page 76Routes 73/ 175 Widening 63 34Route 185 Widening 42 24 37South Fraser Perimeter Road (SFPR) 11East Side Transportation Initiative 16 63Southeast Section, Calgary Ring Road 59 68 10Turcot Interchange 44 39Georgetown South Track Layout and Grading 46 92Extension of Autoroute 35 32Hurontario – Main LRT 40 43Highway 63 Twinning 48 64North LRT Extension, Downtown to NAIT 60 44Highway 407 East Extension 50 16Ottawa Light Rail Project 22 30Windsor-Essex Parkway Project 21Scarborough LRT 28 4New Bridge for the St. Lawrence 11 Figures 50Sheppard East LRT 51 6New International Trade Crossing 13 Projects by Province and Major Metro Area 8 9Southeast to West LRT 14 20Northeast Anthony Henday Drive 26 Projects by Sector 8 13Spadina Subway Extension 18 45Train de l’Ouest 50 75Union Station Revitalization 63 56Waterloo Region LRT 56 87Wilson Facility Enhancement and Yard Expansion 66 7Port Mann Bridge / Highway 1 Improvements 13 16 23Vancouver International Airport Upgrades 30 38 page Project Delivery 12 Value by Energy Type 34 Transmission Funding 34 74Prince Rupert Container Terminal Development, Phase 2A 62 Energy Coming Online 35 93Repairs to Route 389 68 Total Investment 58 Visit top100projects.ca where the list can be filtered by sector, key player, location, and more. top100projects.ca ReNew Canada 7 Top 100 Projects Projects by Province and Major Metro Area Total Total Projects Projects by by Major Province Metro Area 101* 53 Yukon, N.W.T., Nunavut 0 Newfoundland and Labrador 3 New Brunswick, P.E.I. 0 Edmonton 4 Victoria 2 Calgary 3 Vancouver 8 British Columbia Quebec City Montreal 3 Winnipeg 1 7 Ottawa 2 Toronto 17 Saskatchewan 23 2 Alberta 12 Nova Quebec Scotia Ontario Manitoba 4 2 19 36 London Hamilton Kitchener1 2 Waterloo Windsor 2 1 * Interprovincial projects counted twice. Projects by Sector energy Hydroelectric Wind Transmission Coal Natural Gas Nuclear 15 10 7 3 2 1 transit buildings LRT Rail Subway BRT Health Care 10 3 2 1 14 transportation 2 2 1 other Highway Airport Bridge Port 13 2 2 2 8 ReNew Canada Public Facilities Social Infrastructure Education Water/ Wastewater 5 Environment Waste Management 2 1 top100projects.ca 2013 Credit: BC Hydro 1 Site C Clean Energy Project $7.9 billion 2012 Rank: 2 Location: Near Fort St. John, British Columbia Owner: BC Hydro Engineer: SNC-Lavalin Funding: Public • Provincial BC Hydro: $7.9 billion top100projects.ca This 1,100-megawatt (MW) hydroelectric earthfill dam on the Peace River is the source of considerable debate. Proponents, primarily BC Hydro and the Province of British Columbia, argue that the project will be a source of long-term, low-cost clean energy, taking advantage of water already stored in the Williston Reservoir. Opponents are concerned about the cost of the project, the lack of public input, and the environmental impact of the dam itself. The Site C environmental assessment (EA) process has moved into Stage 3, which involves a review of the project by the Canadian Environmental Assessment Agency (CEAA) and the British Columbia Environmental Assessment Office (EAO), as well as a joint review panel. Preliminary engineering work will also take place during the third stage of the process, including the development of plans for construction access roads, clearing plans, construction materials, geotechnical shoreline investigations, and reviews of relevant highways. ReNew Canada 9 Top 100 Projects Credit: AECOM 2 Romaine is one of 15 hydro projects on this year’s list. Romaine Complex $6.5 billion 2012 Rank: 3 Location: Havre-Saint-Pierre, Quebec Owner: Hydro-Québec Engineer: AECOM, SNC-Lavalin, Dessau, LVM Contractor: Thirau, a subsidiary of CVTech Group Supplier: Alstom (turbines: Romaine 2) Funding: Public • Provincial Hydro-Québec: $6.5 billion Hydro-Québec’s 1,550 MW hydroelectric complex on the Romaine River is still on track for completion in 2020, with the first generator coming online in 2014. It involves four generating stations and reservoirs spaced over 150 kilometres (km) in a remote area on the north shore of the Gulf of St. Lawrence. Each one will have an associated rockfill dam, two or three generating units, and a spillway. Two access roads will also need to be built, one 10 km stretch linking to Romaine-1, and one 150 km connection to Romaine-4. Top 100 Timeline: Romaine Complex 2004: Pre-project studies begin 2009: Construction begins, enters Top 100 as number 1 2014: Expected commissioning of first generator 2020: Commissioning of final generator Keeyask Hydroelectric Project Credit: AECOM 3 2008: Environmental assessment completed $5.6 billion NEW Location: Lower Nelson River, Split Lake Resource Management Area, Manitoba Owner: Keeyask Hydropower Limited Partnership Engineer: AECOM Funding: Public • Provincial /First Nations Keeyask Hydropower Limited Partnership (co-owned by Manitoba Hydro and Keeyask Cree Nations): $5.6 billion This project is proceeding in a fashion similar to the Wuskwatim Generation Project, number 13 on the Top 100 list in 2011. The design for the project agreement is based on a partnership model between Manitoba Hydro and the Keeyask Cree Nations—including the Tataskweyak Cree Nation, War Lake First Nation, Fox Lake Cree Nation, and York Factory First Nation. 10 ReNew Canada The 695 MW Keeyask hydroelectric facility will produce an average of 4,400 gigawatt hours per year of electricity for the Manitoba energy grid. In 2012, work began on the support infrastructure for the facility through a project titled the Keeyask Infrastructure Project that built the required support roads and camp developments. The Environmental Impact Statement for this project was submitted in July 2012 to the Manitoba Conservation and Water Stewardship, along with the Canadian Environmental Assessment Agency. If approval is granted, construction will begin in 2014 and finish in 2019. top100projects.ca 2013 Credit: ociété PJCCI Annual Crossings of Current Champlain Bridge Total Vehicles: 60 million Trucks: 6.2 million Buses: 200,000 Transit Users: 11 million Eventual International Trade: $20 billion This archival image shows Quebec’s Champlain Bridge under construction in the 1950s. 4 New Bridge for the St. Lawrence $5 billion NEW Location: Montreal to Brossard, Quebec Owner: Jacques Cartier and Champlain Bridges, a subsidiary of the Federal Bridge Corporation, which falls under the jurisdiction of Transport Canada Engineer: Morrison Hershfield, Groupe SM, Arup Canada Other: Dessau, CIMA+ (environmental assessment) Funding: Public • Details not yet available Financing A consortium led by PricewaterhouseCoopers has been selected to provide financial, technical, and engineering services. The group is currently involved in preparing a complete business case for the bridge, which will involve a public-private partnership (P3) component, and could also see tolls being collected again, as they were until 1990. The structure of the P3 is not yet clear. The business case is expected to be finished by mid-2013, and the federal EA should be complete by the end of that year. top100projects.ca The yet unnamed “New Bridge for the St. Lawrence” is set to replace Montreal’s 3.4 km Champlain Bridge, the country’s busiest and most economically significant water crossing. Built in 1962, the Champlain Bridge has been deteriorating due to increasing traffic loads and the corrosive effects of road salt. (For details, visit renewcanada.net and search “Champlain.”) The local Catholic church went so far as to erect a billboard near its entrance with a cheeky message to motorists: “Say Your Prayers.” In 2011, the federal government announced that it would replace the bridge over a 10year period. Construction is anticipated to take place between 2016 and 2021, followed by the demolition of the old bridge over the following two years. The project will also require a number of smaller surrounding renovations, including the building of a temporary bridge or causeway to Nuns’ Island. This will allow for the replacement of the current Nuns’ Island Bridge, which forms part of the route to the Champlain Bridge. A pre-feasibility study has suggested that the new bridge should have three lanes of traffic in each direction, plus a designated bus lane. Currently, AECOM is under a separate contract to study the possibility of adding some form of rapid transit to the A-10 corridor, including the New Bridge for the St. Lawrence. At the time of press, the results of that study were expected to be made public by the end of 2012. ReNew Canada 11 Top 100 Projects Credit: Kristin Foster 5 Eglinton Crosstown Light Rail Transit (LRT) Engineer: AECOM (consulting engineer, preliminary planning/study, design); Arup (fire vent, Keele and Caledonia station—design); CH2M HILL (owner’s engineer); URS/Parsons joint venture (systems design) $4.9 billion Architect: JHDR (Eglinton-Yonge interchange station) 2012 Rank: 1 Contractor: James Elliott Underground, Kanaiden (tunnel launch site) Location: Toronto, Ontario Supplier: Bombardier (LRT vehicle supplier); Caterpillar Tunnelling, formerly Lovat (tunnel boring machines); Munro (tunnel liners) Owner: Metrolinx Other: AECOM (Black Creek EA); Delcan (EA, signalling/train control, communications, traction power, and tunnel ventilation systems); exp Services (condition surveying and monitoring consultant) Project/Construction Manager: Metrolinx (project manager); Delcan, in a joint venture with Hatch Mott MacDonald, MMM Group, and McCormick Rankin Corporation (project management consultants) Funding: Public • Provincial Ministry of Transportation capital allotment to Metrolinx: $4.9 billion The Province of Ontario will fund this entire project under Metrolinx’s Big 5 priority transit projects. Phase 1 of the line will be 19 km of light rail service across the Eglinton Avenue corridor in midtown Toronto, with a 12 km segment to be tunnelled from near Black Creek Drive in the west to Brentcliffe Road in the east. Metrolinx has purchased four tunnel boring machines (TBMs) for the job. In a major shift from how the Toronto Transit Commission (TTC) organizes bidding processes for its projects, Metrolinx opened up the procurement process to any company that believes it can handle the project. The TTC has a standing policy of only allowing companies that employ unionized workers to bid on its projects. However, Metrolinx stated that any company can bid, regardless of the type of labour it employs. Work began in 2011, and is expected to be complete by 2020. In 2012, this project was listed as the largest infrastructure project in Canada on the Top 100 list, at a value of $8.2 billion. However, part of its funding has now been reallocated to other LRT lines in Toronto, shifting it down to number five. The reduction in budget was made possible by reverting to the original design scheme, running partially above ground in a designated right-of-way, as opposed to fully underground. After some discussion in 2012, it was agreed that the municipal TTC will operate the line, although it will remain under provincial ownership. 2013 Top 100: Project Delivery 44 Public Total Investment: $140.7 billion 27 24 5 $70.68 billion Public-Private Partnerships $39.98 billion $25.52 billion Public/Private $4.48 billion (50.3% of list value) (28.4% of list value) (18.1% of list value) (3.2% of list value) 12 ReNew Canada Private top100projects.ca 2013 6 New International Trade Crossing $4 billion NEW Location: Windsor, Ontario to Detroit, Michigan Owner: Federal Bridge Corporation Project Management: Deloitte Engineer: Morrison Hershfield, Delcan, Davis Langdon (an AECOM company) Funding: • Federal The Canadian customs plaza and adjacent highway interchange, as well as land acquisition for the bridge • U.S. Federal Government The American customs plaza Financing The $4-billion bridge will likely be delivered through a design-build-finance-maintain (DBFM) P3. The private sector partners are to be selected by mid-2013, at which point further details of the project budget should be made public. 7 In June 2012, Canada and the State of Michigan finalized a deal to construct a second bridge between Windsor and Detroit to resolve a long-time bottleneck on the busiest border crossing between Canada and the United States, which is currently served by the Ambassador Bridge and DetroitWindsor Tunnel. The Ambassador Bridge remains the only privately owned connection between the two countries, and its owner, Detroit billionaire Manuel “Matty” Moroun, has campaigned vigorously against the new bridge. The international agreement requires that all steel and other materials used to build the bridge must be of North American origin, resolving what had been a major sticking point. The American government had wanted to use exclusively American materials, while the Canadian government wanted to open bidding to international sources, a move that likely meant using cheaper Chinese steel. The federal government has stated that it has so far spent $35 million to acquire property in Windsor for the bridge and plaza. The Government of Canada will also spend approximately $300 million to construct traffic plazas and supporting border infrastructure leading up to the new crossing. The U.S. government will contribute only the costs of the American customs plaza. The $1.4 billion Windsor-Essex Parkway (number 29 on this year’s Top 100), which will connect Highway 401 with the new bridge, is already well under construction through a P3 contract. Port Mann Bridge / Highway 1 Improvements $3.3 billion 2012 Rank: 12 Location: Langley to Vancouver, British Columbia Owner: Transportation Investment Corporation (Province of British Columbia) Engineer: Delcan (program engineer); MMM Group, Golder Associates, CH2M HILL (subconsultants to Delcan); H5M—a joint venture of Hatch Mott MacDonald and MMM Group (prime design consultants— onshore works); T.Y. Lin International (prime design consultant— New Concession Bridge) Contractor: Kiewit-Flatiron General Partnership (design-build) Other: Partnerships BC (procurement manager and project developer) Funding: Public • Provincial Transportation Investment Corporation: $3.3 billion Financing The work was originally intended to take place through a P3 contract with the Connect BC Development Group. However, it was subsequently changed to a design-build arrangement, using the KiewitFlatiron General Partnership. This project involves widening Highway 1 over 37 km and replacing the existing Port Mann Bridge across the Fraser River. Under construction since 2010, it is expected to be mostly wrapped up by the end of 2013 (with the removal of the existing bridge taking place in 2014). Top 100 Timeline: Port Mann Bridge / Highway 1 Improvements 2006: Provincial government announces the project as part of Gateway Program to improve highways around Vancouver top100projects.ca 2009: Joins Top 100 as number 7 2010: Construction begins 2012: Completion of new Port Mann Bridge 2013: •O pening of Port Mann Bridge •E xpected completion of road 2014: Removal of old Port Mann Bridge ReNew Canada 13 2013 Top 100 Projects 8 Bipole III Transmission Line $3.28 billion 2012 Rank: 6 Location: Gillam to Winnipeg, via The Pas (west of Lakes Winnipeg, Manitoba, and Winnipegosis), Manitoba Owner: Manitoba Hydro Other: North/South Consultants (environmental consulting); CMC Consultants (initial routing study); Joro Consultants and Wildlife Resources Consulting Services (wildlife impact consulting) Funding: Public • Provincial Manitoba Hydro: $3.28 billion This transmission line, planned to run approximately 1,400 km from the Keewatinoow Converter Station down the west side of the province to Riel Converter station near Winnipeg, has generated considerable debate throughout the province. Initially, Manitoba Hydro had planned to run the line down the eastern side of the province. However, the eastern route would run through boreal forest that the Manitoba government is hoping to have designated as a UNESCO World Heritage Site, and might also have led to conflicts with First Nations groups. The present western route has also garnered criticism, both for its greater cost and for its environmental and social impact. The possibility of an independent review of the current plan was rejected in 2012. Construction is expected to begin in 2013, with an estimated in-service date of 2017. Credit: City of Edmonton The Churchill transfer station in downtown Edmonton will be one of three new stations on the 27-stop line, which will connect to the existing LRT line at Churchill. The City estimates future daily ridership will be 100,000. 9 Southeast to West LRT $3.2 billion NEW Location: Edmonton, Alberta Owner: City of Edmonton Engineer: AECOM Funding: Public • Details not yet available, through the City of Edmonton has requested provincial funding for the project. 14 ReNew Canada Edmonton’s new LRT line promises a more “urban” style, with low-floor vehicles, smaller, more closely-spaced stops, and a higher standard of landscape and architectural design. The route will extend north from the Mill Woods Town Centre to Downtown and then west, past the West Edmonton Mall to Lewis Farms. Preliminary engineering work began in 2011, and Council approved a draft concept plan in February 2012. The design phase and public consultations are expected to be complete by the end of 2013, with construction finishing in 2018. All major buildings associated with the LRT will be built to LEED-Silver standards. Financing As of late 2012, the funding structure of the project was not yet finalized, but Edmonton City Council had voted to pursue a P3 option, a first for transit in that city. This would allow access to $300-$400 million from the federal P3 Canada Fund. top100projects.ca 2013 Top 100 Projects Credit: AECOM 10 Turcot Interchange $3 billion 2012 Rank: 7 Location: Montreal, Quebec Engineer: SNC-Lavalin, CIMA+ (feasibility study); LVM (environmental, geotechnical and materials engineering) Owner: Transports Québec Contractor: MTQ (principal contractor) Project/Construction Manager: AECOM (project manager) Funding: Public • Provincial Transports Québec: $3 billion 11 In May 2012 the Government of Quebec unveiled the final plans for this project to reconstruct the crumbling expressway interchange. The revised plan includes more space allocated to public transit, cyclists, pedestrians, and green space. A corridor along Notre Dame and St. Ambroise streets will be reserved for a possible future LRT and several busonly lanes have been reserved along Highway 20, Notre Dame Street West, and St. Patrick Street. At the same time, one of the consortia competing for the contract to design and build the new Turcot publicly stated that it intended to file a notice with the project arbitrator over its decision to allow a consortium comprised of SNC-Lavalin, CIMA +, and Louisbourg SEC to bid on the project. A spokesperson for the consortium claimed that because SNC-Lavalin had prepared the preliminary specifications and design criteria that are being used to evaluate the submitted bids, the company had an unfair advantage. SNC-Lavalin spokesperson Leslie Quinton refuted this claim, stating “being involved in the preliminary process is in no way a guarantee of winning the contract and we believe there will be a fair evaluation of all submissions.” Louisbourg SEC is owned by Antonio Accurso, who, in April 2012, was arrested on a number of fraud-related charges. His arrest prompted former Quebec premier Jean Charest to call an inquiry into the construction industry in Quebec. East Side Transportation Initiative $3 billion 2012 Rank: NEW Location: Eastern Manitoba Owner: East Side Transportation Authority Engineer: SNC-Lavalin, AECOM Funding: Public • Provincial $3 billion 16 ReNew Canada Credit: East Side Transportation Authority This is a long-term project aimed at connecting the east side of Lake Winnipeg, and eastern Manitoba in general, with the wider road network. The East Side Transportation Initiative will see 1,028 km of all-season road built. Administered under a new provincial body known as the East Side Transportation Authority, the new roads are expected to reduce the cost of transporting goods to remote communities by 50 per cent. The project will include a 156 km road from Hollow Water First Nation to Berens River First Nation (with a 93 km extension to Poplar River First Nation), a 131 km road connecting the first route to Little Grand Rapids and Pauingassi First Nations, and a 648 km road from Island Lake and Northern Cree communities to Provincial Road 373. Work began when the first phase of the project received environmental approval in 2012. The project is intended not to conflict with the region’s proposed UNESCO World Heritage designation, for which the Bipole III Transmission Line was rerouted to the west of Lake Winnipeg. top100projects.ca 2013 Top 100 Projects 12 Muskrat Falls Hydroelectric Project $2.9 billion 2012 Rank: 4 Location: Muskrat Falls, Labrador Owner: Emera, Nalcor Energy Engineer: SNC-Lavalin (EPCM) Funding: Private • Emera, Nalcor Energy: $2.9 billion View all hydro projects on this year’s Top 100 by visiting the database at top100projects.ca/ 2103filters 13 The Muskrat Falls Hydroelectric Project consists of an 824 MW hydroelectric facility, located on the Churchill River in Labrador. The project was originally scheduled to be under construction in 2012. However, the project has faced numerous delays related to lawsuits brought by First Nations groups and a delay in creating the final agreement. In July, after 20 months of negotiations, Nalcor Energy and Emera Energy, the Nova Scotia utility that is helping to fund part of the group of projects, signed the final agreement. Under these terms, Nova Scotia will receive 25 per cent of the energy generated in the first five years and 20 per cent per year after that. The agreement also covers cost overruns for the project. Nalcor will cover 100 per cent of any potential cost overruns that have to do with construction of the dam or the Labrador Island Transmission Link. SNC-Lavalin’s role as engineering procurement and construction manager (EPCM) is for Phase 1. This includes the development of the Muskrat Falls Generating Facility and the Labrador-Island Transmission Line. Phase 2 of the project will be the development of Gull Island, the construction of which is expected to start several years after Muskrat Falls. Nalcor will transmit surplus power from the island to Nova Scotia Power, a subsidiary of Emera, across the Cabot Strait into Cape Breton, Nova Scotia. Previously this project was combined with the Labrador Island Transmission Link and Maritime Transmission Link projects, known together as the Lower Churchill Falls Hydro Project. However, as ReNew Canada works to clarify our definitions for various sectors, we decided that the project would be better evaluated on its individual parts. Spadina Subway Extension $2.63 billion 2012 Rank: 8 Location: Toronto, Ontario Owner: TTC Project/Construction Manager: Morrison Hershfield (construction management); Spadina Link Project Managers, a joint venture between Delcan, Hatch Mott MacDonald, and MMM Group (project management consultants); TTC (project manager, design and construction) Engineer: AECOM (engineering design); Arup (York University and Vaughn Station designs); Coffey Geotechnics (geo-engineering consultants and electrical engineering consultants); Golder Associates (principal geoengineering consultant); H. H. Angus (mechanical, electrical consultants); Hatch Mott MacDonald (tunnel design consultant); INSPEC-SOL (geotechnical engineering consultant); Morrison Hershfield (consulting engineer) Architect: Aedas (Sheppard West Station; Arup Canada in association with Foster + Partners (York University Station); A joint venture of IBI Group Architects, LEA Consulting, and Halsall Associates, in association with Will Alsop (Finch West and Steeles West Subway Stations) Contractor: Belor Construction (Downsview Station to Wilson Yard Connection); A joint venture of McNally Construction, Kiewit, and Aecon (construction of 2.6 km of wind tunnel subway track, construction of new Sheppard West station); Varcon Construction (tunnel boring machines launch shaft at Sheppard West Station); Fomento de Construcciones y Contratas, Obrascon Huarte Lain (north tunnels and Highway 407 station) 18 ReNew Canada Supplier: Caterpillar Tunnelling, formerly Lovat (TBMs) Other: IBI Group (subconsultant to Hatch Mott MacDonald for tunnelling contract); exp Services (condition surveying and monitoring consultant) Funding: Public • Federal FLOW program: $697 million (including $622 million from the Building Canada Fund and $75 million from the Public Transit Capital Trust) • Provincial Move Ontario Trust (including interest gathered by the Trust): $1.055 billion • Municipal City of Toronto: $526 million from the TTC Capital Program Budget; York Region: $352 million The 8.6 km extension to the existing Spadina subway line will include six new stations, including one at York University. In July 2012, Holey (one of four TBMs for the project) began its second section of tunnelling and will now bore through 1.2 km of earth from the new Sheppard subway station to the extraction shaft at the existing Downsview subway station. However, there are concerns that the project will not be completed on time. A fatal accident on the subway station construction site at York University prompted the Ministry of Labour to enact a Do Not Disturb order, which prevents work from being carried out on the site. As a result, the project will take almost a year longer than planned to complete, and is now expected to finish in 2016. top100projects.ca 2013 Top 100 Projects Lower Mattagami Hydroelectric Complex Credit: AECOM 14 $2.6 billion 2012 Rank: 9 Location: 70 km northeast of Kapuskasing, Ontario Owner: Ontario Power Generation (OPG), Moose Cree First Nation Engineer: AECOM (civil, mechanical, electrical); Aecon (design) Architect: AECOM Contractor: The Kiewit Alarie Partnership—Kiewit, Leo Alarie and Sons Construction, a subsidiary of Aecon (construction); SNC-Lavalin (design build) Supplier: Alston (hydro turbine generators) Other: AECOM, Genivar, Roche, SNC-Lavalin (impact studies) Funding: Public • Provincial OPG: $2.6 billion CHUM (Centre hospitalier de l’université de Montréal) Redevelopment Credit: PCHUM 15 The Lower Mattagami project has four components. These include the rebuilding of the Smoky Falls Generating Station as well as the addition of new generating units at the Harmon, Kipling, and Little Long generating stations. The intent of the project is to add 438 MW, distributed throughout the various generating stations. Smoky Falls was originally constructed in 1931, while the others were built in the 1960s. In order to accommodate the additional energy that will be supplied because of this project, Hydro One is adding an additional 230-kilovolt circuit to the transmission line that runs from the Harmon Junction to the Kipling Generating Station, running approximately four km. This project should be completed in 2015. $2.5 billion 2012 Rank: 10 Location: Montreal, Quebec Owner: CHUM Engineer: AECOM, Dessau Architect: Birtz Bastien Beaudoin Laforest Architectes, Provencher Roy, Yelle Maillé, Arcorp Research Tower DBFM Team: Accès Recherche Montréal—a joint venture of Pomerleau and Verreault, a subsidiary of Dessau. Hospital DBFM Team: Collectif Santé Montréal—a joint venture of Laing O’Rourke, Obrascón, Huarte Lain, Innisfree, and Dalkia Canada. Other: Infrastructure Québec, formerly PPP Québec (procurement advisor); SNCLavalin and Genivar (owner’s advisors) Funding: Public • Provincial $2.5 billion 20 ReNew Canada Financing This project will be delivered through a P3 (DBFM). The financial arrangement is underwritten by RBC Capital Markets. To finance the CHUM project, Collectif Santé Montréal placed short term bonds with Canadian institutional investors and long-term senior bonds for a total of over $392 million. The sponsors are also providing liquidity by way of a mezzanine facility. A new hospital and research centre will replace the three facilities which currently make up the CHUM—the Hôtel-Dieu de Montréal, Hôpital NotreDame, and Hôpital Saint-Luc. Following years of delay, the project received its go-ahead in 2010. The Research Centre is targeting LEED-Silver certification. By late 2012, construction had begun. Work is expected to be finished by 2015. top100projects.ca 2013 Top 100 Projects 16 Ottawa Light Rail Project $2.1 billion 2012 Rank: 14 Location: Ottawa, Ontario Owner: City of Ottawa Engineer: Capital Transit Partners— a joint venture of Morrison Hershfield, Jacobs Associates, STV Canada Consulting, and URS Canada (preliminary engineering); Delcan (functional design); Halcrow Group (tunnel design for EA report) Other: Delcan (LRT planning, EA) Funding: • Municipal City of Ottawa: $900 million • Provincial $600 million • Federal Major Infrastructure Component of the Building Canada Fund: $400 million; Canada Strategic Infrastructure Fund: $200 million 17 Labrador Island Transmission Link $2.1 billion 2012 Rank: 4 Location: Muskrat Falls, Labrador to Soldiers Pond, Newfoundland and Labrador Owner: Nalcor Energy, Emera Engineer: Nalcor Funding: Private • Nalcor Energy, Emera: $2.1 billion 22 ReNew Canada Financing This project will be delivered through a P3 (DBFM). Shortlisted bidders for the project include: Ottawa Transit Partners (led by VINCI Concessions, includes ACCIONA, Aecon, Bombardier, and VINCI Construction Grands Projets), Rideau Transit Group (led by ACS, includes EllisDon, Dragados—part of ACS, SNC-Lavalin, and Veolia), and Rideau Transit Partners (led by Guyancourt, France-based Bouygues, includes Brookfield Financial, Fiera Axium Infrastructure Canada LP, Parsons, Colas Rail, and Johnson Controls). Ottawa’s second LRT line includes 13 new stations from Tunney’s Pasture to Blair Road, four of which are in a 3.2 km tunnel located under downtown Ottawa. It will intersect with the existing O-Train line at Bayview station. Some parts of the existing BRT will be converted to LRT use, while others will be converted to park, pedestrian, or cycling areas. Unlike the existing O-Train, which is diesel-powered, the new LRT will be electric. Federal EA approval was given in 2012, with the RFP process scheduled for completion by December 2012. Construction is set to begin by 2013, and finish in 2017, allowing the line to begin operating the following year. This 900 MW transmission line will link the Muskrat Falls Hydroelectric Project with Newfoundland and facilitate the transmission of electricity to Nova Scotia and on to export markets in the United States. According to Nalcor, the in-service date for this project is 2016. However, the start date for construction was originally listed as 2012 and work has apparently not yet begun. The ability of the two utilities to get this project off the ground is dependent on whether the Muskrat Falls project receives its final environmental approval from the provincial government . Previously this project was folded in with the Muskrat Falls Hydroelectric Project and Maritime Transmission Link projects, known together as the Lower Churchill Falls Hydro Project. However, as ReNew Canada works to clarify our definitions for various sectors we decided that the project would be better evaluated on its individual parts. top100projects.ca Credit: Ottawa Light Rail Rendering of the proposed LeBreton Station. Top 100 Projects Credit: Hatch Mott MacDonald This land for the 4,200-metre runway was acquired and designated for this purpose in the 1970s and has been a part of the CAA’s long-term master plan since 1992. It will be the airport’s fourth runway and the longest civil aviation runway in Canada, capable of landing the world’s largest aircraft. 18 Calgary International Airport Developments $2 billion 2012 Rank: 26 (facilities expansion), 60 (runway)* Location: Calgary, Alberta Owner: Calgary Airport Authority (CAA) Project/Construction Manager: EllisDon (construction manager, airport facilities); PCL-ParsonsDufferin JV (construction manager, runway development) Engineer: CH2M HILL, Associated Engineering (prime consultants); AECOM (electrical, mechanical consultant); Hatch Mott MacDonald (civil airside consultant on facilities and engineering design manager on runway development); Reed Jones Christoffersen (structural consultant) Architect: Cohos Evamy, a part of DIALOG (prime design consultant) 24 ReNew Canada Other: AirBiz (Airport Planning Consultant); AECOM (program manager); LVM (quality assurance) Funding: Private • Calgary Airport Authority (CAA), a not-for-profit established by the Province: $2 billion This project includes a temporary baggage hall expansion, terminal renovations, terminal expansion for the E Pier, and a new runway. There will be an addition to the existing terminal and extensive renovations to address projected passenger levels for both trans-border and international travel. Under construction with completion scheduled for 2015, the development has a number of interesting design features including a geothermal heating/cooling system combined with radiant floor heating/cooling. To date, 425 (75 per cent) of the geothermal wells have been dug and 42,000 square metres of concrete has been poured. Structural steel installation began in July 2012 and construction is on schedule and on budget. *This listing combines two aspects of the project which were listed separately in the 2012 edition of Top 100, but are more accurately described as a single undertaking. top100projects.ca 2013 Top 100 Projects New Oakville Hospital Credit: Infrastructure Ontario 19 $2 billion 2012 Rank: 15 Location: Oakville, Ontario Owner: Halton Health Services Architect: A joint venture of Parkin Architects and Adamson Associates Architects Contractor: Carillion Canada, EllisDon Facility Manager: Honeywell Other: Fengate Capital Management, Scotia Capital (financial advisors); Infrastructure Ontario (procurement manager and project development) DBFM Team: Hospital Infrastructure Partners—Carillion Canada, EllisDon, Fengate Capital Management Limited, Parkin Architects in joint venture with Adamson Associates Architects Funding: Public • Provincial: $2 billion This project will be delivered through a DBFM P3. The full value of this project over a 30-year contract with Hospital Infrastructure Partners is $2.7 billion. This new hospital, which is targeting LEEDSilver certification, will replace the existing Oakville-Trafalgar Memorial Hospital and provide state-of-the-art health services for the surrounding area. Ground was broken in the summer of 2011, with concrete foundations poured in 2012. Completion is scheduled for the summer of 2015. Northeast Anthony Henday Drive Ongoing work on cloverleaf interchange on Anthony Henday Drive. $1.8 billion 2012 Rank: NEW Location: Edmonton, Alberta Owner: Alberta Transportation Engineer: ISL Land and Engineering, AECOM, MMM Group Contractor: Flatiron Constructors, Dragados—part of ACS, Aecon, Lafarge DBFMO Team: Capital City Link General Partnership: Meridiam Infrastructure NEAH ULC (a subsidiary of Meridiam Infrastructure North America), ACS NEAH Partner (a subsidiary of ACS Infrastructure Canada) and HOCHTIEF NEAH Partner (a subsidiary of HOCHTIEF PPP Solutions) Facilities Manager: Volker Stevin Highways Supplier: Structural-Bridges, Rapid-Span Structures (steel bridge structures) Funding: Public • Provincial: $1.8 billion 26 ReNew Canada Financing The project is being delivered through Alberta’s P3 model. The federal government will contribute up to $36.8 million through the P3 Canada Fund towards the project. The Capital City Link General Partnership, will design, build, partially finance, and operate and maintain the project over the course of the 34-year contract. This project is the last leg of the Anthony Henday Drive project (listed at 17 in the 2011 Top 100 Projects report). Scheduled to open in 2016, this 26 km, sixand eight-lane highway is part of the larger Edmonton Ring Road project, worth an estimated $4 billion. Construction will also include nine interchanges, two flyover roads, eight rail crossings, and two bridges over the North Saskatchewan River. top100projects.ca Credit: AECOM 20 Financing 2013 Top 100 Projects 21 Scarborough LRT $1.8 billion 2012 Rank: NEW Financing Metrolinx is considering a P3 model to deliver this project, but no team has been selected. Location: Toronto, Ontario Owner: Metrolinx Project/Construction Manager: Metrolinx (project manager), Delcan, in a joint venture with Hatch Mott MacDonald, MMM Group and McCormick Rankin (project management consultants) Engineer: AECOM (station design); C2HM HILL (owner’s engineer) Supplier: Bombardier (LRT vehicles) Funding: Public • Provincial Ministry of Transportation capital allotment to Metrolinx: $1.8 million Humber River Regional Hospital Credit: Infrastructure Ontario 22 This project will replace Toronto’s aging Scarborough Rapid Transit (RT) line with LRT technology, while extending it northward to meet the planned Sheppard East LRT. The Scarborough RT currently connects the end of the subway system at Kennedy station with the Scarborough Town Centre shopping mall and McCowan Road. The total length of the new line will be 10 km. Like the Sheppard LRT, the project was originally part of the TTC’s Transit City program, which was cancelled by the current municipal government. It has now been taken up by the Province, which will wholly fund it through the Metrolinx regional transit agency. Work is expected to begin in 2014 and be complete by 2020. $1.75 billion 2012 Rank: 16 Location: Toronto, Ontario Owner: Humber River Regional Hospital Engineer: Morrison Hershfield (consulting engineer); Smith and Andersen Consulting Engineers (mechanical/electrical consultant); Modern Niagara Toronto (mechanical); and Plan Group (electrical) Architect: HDR Architects, C.F. Møller Architects Contractor: PCL Constructors Canada DBFM Team: Plenary Health Care Partnerships: C.F. Møller Architects, Halsall Associates, HDR, Hewlett-Packard, Johnson Controls, Modern Niagara, PCL Constructors Canada, Plan Group, Plenary Group/HCP Canada, RBC Capital Markets, Smith+Anderson Facilities Manager: Johnson Controls Other: Plenary Group Canada, HCP Social Infrastructure Canada Limited/Innisfree (developers); RBC Capital Markets (financial advisor); Michael Brothers Excavating, a division of Royal Excavating & Grading, Caledon Structures (formwork); Harris Rebar, a division of Harris Steel ULC, Innocon (concrete); Prestressed Systems (precast); Infrastructure Ontario (procurement manager and project development) Funding: Public • Provincial $1.75 million 28 ReNew Canada Financing A $1.75-billion contract (in today’s dollars) with Plenary Health Care Partnerships covers the design, construction, maintenance, renewal/repair, and financing for the project. Aiming for LEED-Silver certification, this new hospital complex will be the first in Canada to be designed and constructed as a fully digital facility. Technology will be used in every facet of the building to improve efficiency and patient care, allowing a total of 107,000 visits a year for a catchment area of 850,000 people. Construction began in 2011 and is scheduled for completion by 2015. top100projects.ca 2013 Top 100 Projects Credit: Vancouver International Airport Artist’s rendition of the upgraded Domestic Terminal Building. 23 Vancouver International Airport Upgrades $1.74 billion NEW Location: Vancouver, British Columbia Owner: Vancouver Airport Authority Project Manager: Vancouver Airport Authority Engineer: Stantec Funding: Private • Vancouver Airport Authority (a private non-profit corporation): $1.743 billion (collected through an increased Airport Improvement Fee) Outremont Campus, Université de Montréal $1.6 billion NEW Credit: Provencher Roy + Associés Architectes 24 In early 2012, the Vancouver International Airport announced a 10-year strategy to upgrade and expand its facilities to accommodate projected increases in travelers. The first of this series of improvements include some 700 metres of additional secure corridors, new high-speed baggage systems, upgrades to the original 1968 Domestic Terminal Building, and runway safety enhancements. The work is being funded by a $5 increase in the Airport Improvement Fee (from $15 to $20) which is levied on all departing passengers going to destinations outside of British Columbia or the Yukon. The university has made a commitment to soil remediation and LEEDPlatinum certification for new buildings. Location: Montreal, Quebec Owner: Université de Montréal Architects: Cardinal Hardy, Provencher Roy Other: DDH Environment (soil remediation consultants) Funding: Public • Municipal City of Montreal: $60 million for remediation • Provincial Ministère de l’Éducation/ Université de Montréal: Most of the remainder of the funding coming from the provincial government through the university • Federal Building Canada Fund: $60 million for remediation • Philathropy Université de Montréal: Private donations to the university 30 ReNew Canada First proposed in 2005, Quebec’s largest university unveiled the revised development plan for its Outremont campus in 2010, including 20 new buildings and 300,000 square metres of floor area. Located further east along the Montreal Metro Blue Line on the site of a former rail yard, the new site will take pressure off of the overcrowded main campus, which has seen an increase of 12,000 students since 2000. Central to the campus will be a new Science Pavilion, containing the chemistry, physics, biology, and geography departments. It will also include a library, a cafeteria, and daycare. Remediation and new road construction is expected to be completed by 2014, university buildings by 2017, and privately built residential accommodations (not included in the project costs listed here) by 2022. top100projects.ca in balance, ACE insures progress Property & Casualty Accident & Health Life To maintain harmony between industry and the environment, it takes the right people, experienced underwriting, a strong balance sheet and a flexible approach. These are the strengths of ACE that allow us to customize environmental risk solutions for your specific needs. We take on the responsibility of your risks so that you can take on the responsibility of making things happen. We call this insuring progress. Visit us at ace-ina-canada.com © 2013 ACE Group. Coverages underwritten by one or more of the ACE Group of Companies. Not all coverages available in all jurisdictions. ACE, ACE Logo and insuring progress are registered trademarks of ACE Limited. 2013 Top 100 Projects Credit: Hydro-Québec Construction on the Beauharnois Hydroelectric Station, one of Canada’s largest infrastructure projects of all time, started in 1929. The last of its 38 generation units went online in 1961. 25 Renovations to Beauharnois Hydroelectric Station Funding: Public • Provincial Hydro-Québec: $1.6 billion $1.6 billion Since 1994, the Beauharnois Hydroelectric Station has been undergoing gradual renovations and replacement of its generation units. This is its first year on the Top 100 list. The plant was powered by the Beauharnois Canal, which had been newly dredged and expanded to one km in width for that purpose. At the time of its construction, it was considered to be the largest hydroelectric station in Canada. Today, at 1900 MW, it is still one of the largest run-of-river plants in the world. The current project also includes restoration of the station’s historic art deco architecture, which led it to be designated as a National Historic Site. Work is expected to be completed in 2019. NEW Location: Melocheville, Quebec Owner: Hydro-Québec Project Management: Hydro-Mécanique Engineering: Dessau, SNC-Lavalin Contractor: Cegerco (various renovations to the building) Supplier: Alstom Hydro Canada, Voith Hydro 26 H.R. Milner Coal Plant Expansion 27 Swan Hills ISCG/Power Project $1.5 billion 2012 Rank: 19 $1.5 billion 2012 Rank: 21 Location: Swan Hills, Alberta Location: Grande Cache, Alberta Owner: Swan Hills Synfuels Owner: Maxim Power Corp. Funding: Private • Maxim Power: $1.5 billion Funding: Private/Public • Swan Hills Synfuels: $1.215 billion • Provincial Carbon Capture and Storage Fund: $285 million In August 2012, Maxim Power received the final approvals required to begin the expansion of the 40-year-old, 150 MW H.R. Milner Power plant to a 500 MW power plant. Construction on what the company dubs “M2” began in 2012 and is expected to be completed by 2015. According to Maxim, the facility will include an advanced emissions control system designed to meet provincial air quality guidelines. However, environmental organizations have criticized this project, as well as the Alberta Utilities Commission for allowing this project to proceed. For details on new coal emissions regulations, visit bit.ly/U11I45 This project taps into deep coal beds that are not considered practical to mine traditionally, using a process called in situ coal gasification (ISCG). Instead, the coal is turned directly into a synthetic gas while remaining in the coal seam underground. The gas is then pumped to the surface, purified, and used to power a combined cycle turbine. The project promises to deliver 300 MW with approximately one-third of the emissions of a conventional coal plant. However, the relatively unproven nature of the ISCG technology has caused some concern about the project’s viability. Swan Hills Synfuels has already constructed a small demonstration project 17 km away, which has provided the company with insight into the larger, commercial-scale operation that is planned. That facility is expected to come online in 2015. 32 ReNew Canada top100projects.ca Top 100 Projects 28 Rocky Creek Wind Energy Project Owner: Rupert Peace Power Holdings $1.5 billion Funding: Private • Prince Rupert Power Holdings: $1.5 billion NEW Location: Tumbler Ridge, British Columbia Other: ECL Environmental Solutions (project development consultant) Once complete, this 500 MW wind farm will likely be the largest in Canada. Under development since 2009, it is currently undergoing an environmental review. 2013 Top 100: Value by Energy Type $57.66 Billion $34.06 billion The total investment in energy projects on the Top 100 $9.08 billion $7.8 billion Hydroelectric (59.07% of list value) Transmission (15.75% of list value) Wind (13.53% of list value) $4.24 billion $1.88 billion $600 million Coal (7.35% of list value) Natural Gas (3.26% of list value) Nuclear (1.04% of list value) 2013 Top 100: Transmission Funding 4 Private 3 Public Top 100 Badge Program PLATINUM ELITE 2013 20 projects or more PLATINUM 2 013 10 projects or more GO LD 2 013 SI LVER 2 013 6 to 9 3 to 5 projects projects BRONZE 2 013 2 projects Badges are sent to key players involved in multiple infrastructure projects on the Top 100 list. Companies use these icons to identify themselves as top key players. Visit top100projects.ca for a company index and list of badge recipients. 34 ReNew Canada top100projects.ca 2013 2013 Top 100: Energy Coming Online From Top 100 20,930 MW Saskatchewan 360 MW Newfoundland and Labrador 824 MW Natural Gas 1,080 MW Manitoba 772 MW Alberta 1,600 MW British Columbia 7,245 MW Coal 910 MW Hydroelectric 12,631 MW Wind 2,797 MW Ontario 5,601 MW Quebec 4,528 MW Wind 750 MW The total energy coming online from Top 100 projects, including refurbishments Nuclear 3,512 MW Hydroelectric 6,495 MW Coal 800 MW Natural Gas 800 MW Coal 110 MW Hydroelectric 250 MW Hydro Nuclear Wind Natural Gas Coal British Columbia Alberta Saskatchewan 7,245 MW 1,600 MW 360 MW Hydroelectric 772 MW Hydroelectric 840 MW Wind 969 MW Nuclear 3,512 MW Natural Gas 280 MW Wind 1,078 MW Hydroelectric 3,450 MW Manitoba Ontario Quebec 772 MW 5,601 MW 4,528 MW top100projects.ca Hydroelectric 824 MW Newfoundland and Labrador 824 MW ReNew Canada 35 2013 Top 100 Projects Credit: TransLink Artist’s rendition of Coquitlam Central Station on the Evergreen Line. 29 Evergreen Rapid Transit Line $1.4 billion 2012 Rank: 24 Location: Burnaby, Coquitlam, and Port Moody, British Columbia Owner: TransLink Engineer: SNC-Lavalin (lead engineer); International Bridge Technologies (bridges); CH2M HILL (owner’s engineer) Contractors: Graham Building Services, SNC-Lavalin Constructors, SELI Canada, Rizzani de Eccher, MMM Group, Jacobs Associates Canada DBF Team: SNC-Lavalin, Graham Building Services, International Bridge Technologies, Jacobs Associates Canada, Rizzani de Eccher, SELI Canada, SNCLavalin Constructors, MMM Group Other: Partnerships BC (procurement partner and project implementation) 36 ReNew Canada Funding: Public • Municipal TransLink: $400 million • Provincial Transit Plan: $583 million • Federal Public Transit Capital Trust: $66.7 million, Building Canada Fund: $350 million, P3 Canada Fund: $7 million Financing In 2012, TransLink announced that the project would be completed mostly as a design-build-finance P3, delivered through a consortium led by SNC-Lavalin. TransLink will continue to operate the line, except for Lincoln Station, which will be operated by the Coquitlam Centre mall through a separate arrangement. This 11 km rapid transit rail line was delayed repeatedly while municipal governments came to an agreement on how to to raise the necessary funds. However, the British Columbia government recently passed new legislation—the Greater Vancouver Transit Enhancement Act— which allowed Metro Vancouver to raise the gas tax by two cents per litre, providing dedicated funding for the project. The relocation of a section of CPR tracks in Port Moody was scheduled to be done by mid-2013, to free up space for the Evergreen Line. Total completion of the project is scheduled for 2016. The route will add seven new stations, and is expected to have a daily ridership of 70,000 by 2021. It includes a two km bored tunnel, as well as elevated sections. top100projects.ca 2013 Top 100 Projects 30 Financing Windsor-Essex Parkway Project $1.4 billion This project will be delivered through a DBFM P3. Windsor Essex Mobility Group (WEMG) will receive annual payments from the Province. Over the 30-year life of the contract, the total payments will add up to $2.2 billion (nominal cost). Annual payments to WEMG are performance based. If WEMG does not meet the Ministry of Transportation’s performance standards, the Province can withhold payment. 2012 Rank: 22 Location: Windsor, Ontario Owner: Ontario Ministry of Transportation (MTO) Engineer: AECOM (consulting/owner’s engineer); Golder Associates (subconsultant to URS, geotechnical advisor); Morrison Hershfield (consulting/owner’s engineer); URS Canada (prime consultant) Contractor: Facca Construction (bridges, noise barrier) DBFM Team: The Windsor Essex Mobility Group— Acciona, ACS Infrastructure, Dragados—part of ACS, Fluor, Hatch Mott MacDonald Other: Arup (lender’s technical advisor); CH2M HILL, Infrastructure Ontario (procurement manager and project development); Infrastructure Ontario, CH2M HILL (procurement manager and project development); Morrison Hershfield (Infrastructure Ontario’s technical advisory team); exp Services (quality control, materials inspection) Funding: Public Top 100 Timeline: Windsor-Essex Parkway Project 2008: Windsor-Essex Parkway proposal presented by Detroit River International Crossing (DRIC) study team 2010: Windsor-Essex Mobility Group awarded DBFM contract for Parkway, joins the Top 100 as number 7 2011: Construction begins 2014: Expected completion of project York VIVA Bus Rapid Transit (BRT) Credit: vivaNext 31 2009: Ontario Environmental Assessment Act (OEAA) approval granted This 11 km stretch will connect Highway 401 to the proposed New International Trade Crossing, and ultimately to the U.S. Interstate system, while separating local and international traffic and eliminating stop-and-go traffic on the way to the border. The project has generated a number of local controversies, relating to the lower than expected number of jobs created, traffic noise, expropriation of properties, and treatment of neighbourhoods surrounding the Parkway. Consultations, particularly related to issues of noise control and landscaping, took place over the summer of 2012. Meanwhile, construction of the roadway and bridges began. The project is expected to be completed by 2014. $1.4 billion 2012 Rank: 23 Location: York Region, Ontario Owner: York Region Rapid Transit Corporation and Metrolinx Construction Manager: Kiewit EllisDon (KED) Engineers: KED, Delcan (engineering lead); McCormick Rankin, EcoPlans, MMM Group (owner’s engineers) Architect: IBI Group Contractor: KED Supplier: NovaBus, Van Hool Other: Ecoplans Limited, a member of MMM Group (design review and advice for environmental specialty areas); Hanscomb (costing); Revay and Associates (controls) Funding: Public • Provincial Capital allotment to Metrolinx, the regional transportation authority: $1.4 billion 38 ReNew Canada The dedicated bus lanes, which VIVA is calling Rapidways, are separate centre lanes that will allow VIVA buses to travel freely no matter how much traffic is using the conventional roadway. Some of the new stations will connect to the TTC subway system, GO Transit commuter rail, express buses, York Rapid Transit local bus services, and other transit systems operating in neighbouring regions. The project is currently under construction. Segments will start operating as soon as they are completed, starting with Davis Drive in 2014.The Enterprise Drive, Highway 7, and Yonge Street lines should all be completed in 2020. top100projects.ca 2013 Top 100 Projects Hurontario-Main LRT Credit: City of Mississauga 32 $1.35 billion NEW Location: Mississauga and Brampton, Ontario Owner: Metrolinx Engineering: SNC-Lavalin (project lead) Other Key Players: Steer Davies Gleave (initial transit system planning); DIALOG (urban design); Lea Group (ITS) Rendering of LRT designated right-of-way down the centre of Hurontario Street, adjacent to the Square One shopping mall. Funding: Details not yet available This 23 km LRT line will run from Port Credit, through Mississauga to downtown Brampton where Hurontario Street becomes Main Street. Included will be 32 stations and two loops, one around downtown Brampton and the other around the Mississauga City Centre/Square One node. Based on the 2010 Master Plan for the area, the focus of the project will be to build transit-oriented development and pedestrian-oriented development along the length of the line. The Hurontario-Main LRT is currently in the preliminary design phase, which will last until 2013. Procurement is expected to take until 2014 and construction should be completed by approximately 2020. McGill University Health Centre (MUHC) at Glen Campus The funding and management structure for the project has not yet been decided. Mississauga and Brampton are currently leading the planning process, but have indicated their interest in letting Metrolinx operate the line. Metrolinx will likely provide much of the funding, alongside the two cities. Mississauga and Brampton are currently applying for money through the P3 Canada Fund, meaning that there could be a private component to its financing and operation. The MUHC’s new Glen Campus, currently under construction, is targeting LEED-Silver certification. Collectively, the MUHC will be the largest hospital in Canada. $1.34 billion 2012 Rank: 25 Location: Montreal, Quebec Owner: MUHC Project/Construction Manager: SNC-Lavalin (project manager) Engineer: Bouthillette, Parizeau et Associés (mechanical, electrical design); SNC-Lavalin (primary engineer); Dessau (mechanical and electrical) Architect: HDR, IBI Group, NFOE, Yelle Maillé, N.F.O.E. et Associés Architectes Contractor: SNC-Lavalin in partnership with Pomerleau, Verreault (a subsidiary of Dessau), Simard-Beaudry Facility Manager: SNC-Lavalin O&M, in collaboration with Johnson Controls DBFM Team: Groupe immobilier santé McGill (GISM)—SNC-Lavalin, Innisfree Funding: Public • Provincial $1.34 billion 40 ReNew Canada Financing The Glen Campus, delivered through a DBFM P3, is part of the MUHC’s $2.34-billion redevelopment, which also includes the Lachine and Mountain campuses. Lachine and Mountain will be built through public financing methods and are currently being planned. As of 2012, the framework and cladding for the hospital were complete, following two years of construction. Work on the underground parking lot below the plaza is expected to finish in late 2013, with operation commencing in 2014. In late 2012, the offices of MUHC were raided by Quebec’s anti-corruption police task force, and computers were seized. One of the firms involved with the project, Simard-Beaurdy, is owned by construction magnate Tony Acurso, who is being investigated for fraud and corruption in a number of public projects. top100projects.ca Credit: McGill University 33 Financing 2013 Top 100 Projects Route 185 Widening Credit: Transports Quebec 34 $1.34 billion 2012 Rank: 27 Location: Rivière-du-Loup to the New Brunswick border, Quebec Owner: Transports Québec Project/Construction Manager: Transports Québec Engineer: AECOM (preliminary and final designs, work supervision); Dessau (transportation and bridge engineering) Other: AECOM (environmental impact study, hydraulic and hydrologic studies) Funding: Public • Federal $336 million • Provincial $1 billion Shepard Energy Centre $1.3 billion NEW Location: Calgary, Alberta Owner: Enmax Engineer: Black and Veatch Contractor: Keiwit Energy Supplier: Mitsubishi (steam and gas turbines) Funding: Private • Enmax: $1.3 billion 36 When completed, this 800 MW natural gas fired power plant will produce energy via two natural gas turbines and one steam turbine. The gas turbines are each capable of producing 240 MW and the steam turbine is capable of producing up to 320 MW. The waste heat produced from the two gas turbines will be captured and used to produce steam for the third turbine. Located in southeast Calgary, the facility will be able to produce half of the current energy requirements for the entire city. Port Hope Area Initiative $1.28 billion 2012 Rank: 97 Location: Port Hope and Clarington, Ontario Owner: Port Hope Area Initiative (Natural Resources Canada, Atomic Energy of Canada Limited, and Public Works and Government Services Canada) Engineer: MMM Group (EPCM) Contractor: Atomic Energy of Canada Limited Other: AECOM (EA) Funding: Public • Federal $1.28 billion 42 ReNew Canada Credit: Enmax 35 The project will expand 94 km of Route 185 from two lanes to a divided four-lane highway connecting Autoroute 20 to the New Brunswick border. As a part of the Trans Canada Highway and the main route between the Maritimes and the rest of Canada, the project has received significant federal funding. The Port Hope Area Initiative involves the remediation of 1.2 million cubic metres of low-level radioactive soil. There are two distinct projects under the initiative: the Port Hope Project and Port Granby Project. Long-term waste storage facilities will be constructed at each location and will be designed to contain the waste for hundreds of years. Additionally, a number of private properties in the Port Hope area will be inspected and, if necessary, decontaminated. The process can be exceedingly costly, especially since some mid-century houses in Port Hope were built with material contaminated before construction. In late 2012, newspapers reported that $465,000 had been spent to remove and replace radioactive elements of a home valued at only $130,000. The project has an estimated timeline of between six and eight years. Construction of supporting infrastructure, such as access roads, is underway with the entire project expected to be complete around 2020. This project was listed at number 97 on the 2012 Top 100 Projects report. This placement was made based on a much lower early estimate of $260 million. The new cost of the project was released in early 2012. top100projects.ca 2013 Top 100 Projects South Fraser Perimeter Road (SFPR) $1.26 billion 2012 Rank: 47 Location: Surrey/Delta, British Columbia Owner: BC Ministry of Transportation and Infrastructure Engineer: Delcan (program engineer) DBFM Team: The Fraser Transportation Group (FTG)—ACS Infrastructure, Ledcor Development, Dragados—part of ACS, Ledcor CMI, Belpacific Excavating & Shoring, Vancouver Pile Driving Other: Partnerships BC (procurement manager and project development); Hemmera (EA lead, environmental manager) Funding: Public • Federal Asia-Pacific Gateway and Corridor Initiative: $363 million, plus an additional $2 million contribution towards the EA • Provincial $899 million Credit: Hemmera 37 The SFPR, running adjacent to lands with important environmental value, includes one of the largest environmental and agricultural mitigation and enhancement plans in British Columbia. Financing The B.C. Ministry of Transportation has a DBOFM P3 contract with the FTG. The operation and maintenance part of this agreement has a term of 20 years from the completion of construction. The new 40 km, four-lane SFPR will run along the south side of the Fraser River, extending from Deltaport Way in the southwest Delta to 176th Street in Surrey. Construction is ongoing and completion is scheduled for the end of 2013. Credit: SaskPower The Boundary Dam’s integrated CCS system has the potential to capture an estimated one million tonnes of CO2 annually, roughly 90 per cent of the CO2 produced by Unit 3. 38 Boundary Dam Integrated CCS Demonstration Project $1.24 billion 2012 Rank: 28 Location: Estevan, Saskatchewan Owner: SaskPower Engineer: SNC-Lavalin (engineering, procurement, construction) Contractor: Stantec (design, construction); SNC-Lavalin (CCS system) 44 ReNew Canada Supplier: Cansolv, wholly owned subsidiary of Shell Global Solutions (carbon capture process); Hitachi (steam turbine); Babcock and Wilcox (boiler upgrade); MAN Turbo (CO2 compressor) Funding: Public • Federal $240 million • Provincial SaskPower: $1 billion The Boundary Dam Integrated CCS Demonstration Project will refurbish Unit 3 at the Boundary Dam coal power station. The refurbishment includes the world’s largest CCS project that will utilize carbon capture for enhanced oil recovery. Procurement for the project is close to 90 per cent complete and construction is on track. In 2013, Unit 3 will be shut down for 180 days while it is rebuilt to adapt it to the CO2 capture and storage system. The commissioning of the CO2 system should take place in the first quarter of 2014. top100projects.ca 2013 Top 100 Projects 39 Financing Georgetown South Track Layout and Grading $1.2 billion The Air Rail Link (or “spur line”) portion of the project is being executed as a DBF project under the Ontario government’s alternative financing and procurement (AFP) program. Financing is being provided by Canadian Imperial Bank of Commerce, Laurentian Bank of Canada, National Bank of Canada, and Toronto-Dominion Bank. National Bank Financial has acted as financial advisor for the project. 2012 Rank: 18 Location: Toronto, Ontario Owner: Metrolinx Project/Construction Manager: Morrison Hershfield, AECOM, Stantec, McCormick Rankin Engineer: AECOM, R.V. Anderson, Delcan, Stantec, McCormick Rankin, Hatch Mott MacDonald Contractor: EllisDon, Dufferin Construction, Kenaidan Contracting/Obiyashi, Bot Engineering, Aecon, Soncin Construction DBF Team: A joint venture between Aecon Group and Dufferin Construction, a division of Holcim Funding: Public • Federal Canadian Strategic Infrastructure Fund, Investment Strategy Fund: $165 million • Provincial Capital allotment to Metrolinx John Hart Replacement Project Credit: Partnerships BC 40 This expansion will address both the forecasted increase in GO Transit ridership along the 14.8 km corridor as well as the Union-Pearson Air Rail Link. The project will see one new bridge structure at Weston, with 15 other bridges widened or modified and seven new underpasses or overpasses. A rail tunnel will be built under Highway 401. Metrolinx and Infrastructure Ontario awarded the DBF contract for the Air Rail Link in October 2011 and financial close was reached in December 2011. Construction began in July 2012 and completion is expected in the third quarter of 2014. $1.2 billion NEW Location: Campbell River, British Columbia Owner: BC Hydro Funding: Public • Provincial BC Hydro: $1.2 billion The John Hart Replacement Project includes the replacement of three 1.8 km penstocks with a 2.1 km tunnel through bedrock; construction of a replacement generation station adjacent to the existing station; replacement of the water intake station at the John Hart Spillway Dam; and the construction of a new water bypass facility. The current station has been providing energy to British Columbia’s energy grid for over 65 years and this project aims to improve safety features to protect it against seismic activity and increase water flows to benefit fish habitats. Controversial changes to the federal environmental assessment protocol mean that the project will no longer be subject to an EA because it does not increase generating capacity by more than 50 MW or 200 per cent. 46 ReNew Canada Financing Partnerships BC began the procurement process for the project in 2012 and expects to award a P3 contract in 2013, with construction planned to start as early as summer 2013 and finish in 2017. Currently three teams have been short-listed to provide design, construction, partial financing, and rehabilitation: SNC-Lavalin (also involving IMPSA), Elk Falls Energy Partners (a consortium including Brookfield Financial, Fiera Axium, Gracorp, Bouygues Travaux Publics, Graham, Alstom and Knight Piesold Consultants) and Salmon River Partners (a consortium including Bilfinger, ACCIONA, Barnard, Klohn Crippen Berger, Voith Hydro and Siemens AG). top100projects.ca 2013 Top 100 Projects 41 Maritime Transmission Link $1.2 billion 2012 Rank: 4* Location: Cape Ray, Newfoundland to Cape Breton, Nova Scotia Owner: ENL Maritime Link (a subsidiary of Emera Energy and Labrador Holdings) Funding: Private • ENL Maritime Link: $1.2 billion 42 This 500 MW undersea cable will span 180 km and connect Newfoundland to Nova Scotia. The purpose of the project is to facilitate the transfer of energy from the Muskrat Falls Hydroelectric project to Nova Scotia and on to export markets. It is currently undergoing an environmental assessment, with construction expected to begin in 2014 and complete in 2016-2017. The need for this cable was determined due to the reluctance of the Newfoundland and Labrador and Nova Scotia governments to use territory in Quebec to construct a more direct transmission line. The trepidation to have energy from the Muskrat Falls project flow through Quebec is the result of what was widely considered by Newfoundlanders to be one of the most unfair energy contracts ever signed. Under the terms of the 1969 agreement, Newfoundland agreed to sell the Deep Geological Repository $1 billion 2012 Rank: 29 Location: Kincardine, Ontario Owner: Ontario Power Generation (OPG) Other: Golder Associates (Environmental Impact Statement); Nuclear Waste Management Association (regulatory and approvals assistance) Funding: Public • Provincial OPG: $1 billion *On the 2012 Top 100 list, this project was combined with the Muskrat Falls Hydroelectric Project and Labrador Island Transmission Link projects, known together as the Lower Churchill Falls Hydro Project, and ranked at number four. However, as ReNew Canada works to clarify our definitions for various sectors, we decided that the project would be better evaluated on its individual parts. OPG is building this 680-metre deep underground storage facility to house low and intermediate level radioactive waste. Low-level waste consists of material that may be contaminated through the normal course of operations at a nuclear facility and includes paper towels, mops, and used tools. While lowlevel waste does not require specialized shielding for workers, the intermediate waste will require special handling and it can consist of items such as irradiated core components, ion exchange resins, and various filters. Used fuel, considered high-level waste, is not to be stored in the Deep Geological Repository. As of late 2012, the review period for the project had been extended to allow for OPG to respond to information requests. Public hearings are expected to take place in the spring of 2013, with construction starting in 2014. Public opposition has been vocal, with some citizens questioning the safety of having such a facility in their community. The site appears to have been selected because of its proximity to the Bruce Nuclear Generating Station as well as its apparent low-permeability and seismic stability. Highway 63 Twinning Credit: Alberta Transportation 43 vast majority of the energy produced from the massive Churchill Falls generating station for three-tenths of a cent per kilowatt hour for the first five years, with the price declining to onefifth of a cent by 2016. The agreement runs until 2041 and the contract does not account for inflation, making the energy essentially free. By most accounts Quebec has reaped approximately $19 billion in profit so far, while Newfoundland has made only $1 billion. $1 billion 2012 Rank: 70 Location: Fort McMurray, Alberta Owner: Alberta Transportation Engineer: AECOM, CH2M HILL (design); Gan & Gan Utilities & Engineering (utilities); Stantec (prime consultant and design); Thurber Engineering (geotechnical) Other: Dallas E. Maynard and Associates (land acquisition); HyRoad Surveys (survey) Funding: Public • Federal Canada Strategic Infrastructure Fund: $150 million (for bridge twinning); Building Canada Fund: $53 million • Provincial Capital allocation based on projected needs of the departments involved 48 ReNew Canada This major highway project in the rapidly growing Fort McMurray area includes construction of a new Franklin Avenue Tunnel to. Some 255 km of highway, both north and south of Fort McMurray, are to be twinned, increasing from two for four lanes. Increased capacity for traffic is expected to reduce delays and improve safety. Construction is underway in a number of segments, with 50 per cent completion estimated for 2015. top100projects.ca Top 100 Projects 44 Highway 407 East Extension $1 billion Financing This project will be delivered through a DBFM P3 (or AFP, as Ontario terms it). Concessionaires Cintra and SNC-Lavalin (partners in 407 East Development Group General) are the owners and operators of the existing 407 toll road. However, unlike the existing stretch of the 407, which was sold by the Conservative government in 1999 for $3.1 billion in exchange for a 99-year lease, the Province will retain ownership of the new extension and retains the right to set the tolls and levels of operation. NEW Location: Pickering to Clarington, Ontario Owner: Ontario Ministry of Transportation (MTO) Project Management: SNC-Lavalinin Engineer: SNC-Lavalin, CH2M HILL, AECOM DBFM Team: 407 East Development Group General Partnership (Cintra Infraestructuras, SNC-Lavalin) Other: Bank of Montreal and Desjardins (financing, bond underwriting, and lenders); AECOM (landscape architecture, planning, traffic and revenue forecasts); Infrastructure Ontario (procurement manager and project development); LVM (pavement and quality assurance services) Funding: Public • Provincial MTO: $1 billion 45 Train de l’Ouest $1 billion NEW Location: Montreal to Hudson, Quebec Owner: Agence métropolitaine de transport (AMT) Engineer: AECOM Funding: Public • Municipal AMT: $1 billion 46 Finch LRT Following on the heels of the Train de l’Est (Eastern Commuter Train Line), which appeared as number 64 in the 2012 Top 100 list, Montreal’s AMT regional commuter authority is preparing studies for upgrades to the Western Commuter Train Line. Currently, the line is limited to rush hour service, due to conflicts with road traffic and sharing track with freight trains. The proposed project would add additional passenger-dedicated tracks adjacent to the existing tracks, with Lucien L’Allier Station as the downtown terminus. This would allow an increase from 144 to 456 trains per week, and an anticipated growth in line ridership from 3.6 to 9.15 million. In 2012, the project was undergoing engineering studies, which should have been complete as of December that year. Engineer: C2HM HILL (owner’s engineer) $1 billion Supplier: Bombardier (LRT vehicles) NEW Location: Toronto, Ontario Owner: Metrolinx Project/Construction Manager: Metrolinx (project manager) Submit projects for our 2014 list The 407 East extension will be a 65 km toll highway built in two phases. Phase one extends the 407 east from Brock Road in Pickering to Harmony Road in Oshawa. This phase will include the West Durham Link (WDL) which is made up of a four lane north/south highway linking the 407 to the 401, freeway to freeway interchanges from the WDL to the 401, and three new interchanges. A six-lane highway will connect Brock Road to the WDL and a four-lane highway will connect the WDL to Harmony Road in Oshawa. Another six interchanges will allow for on/off access to the extension. Phase two, beginning in 2014, extends the highway from Oshawa to Clarington. Both phases include provision for a busway/ transit corridor. Funding: Public • Provincial Ministry of Transportation capital allotment to Metrolinx: $1 billion Update existing projects The Finch LRT will be new 11 km line operating along Finch Avenue and connecting the North Campus of Humber College to the subway system at Finch West Station (part of the ongoing extension of the Spadina line). Like the Eglinton Crosstown LRT, the project was originally part of the TTC’s Transit City program, which was cancelled by the current municipal government. It has now been taken up by the Province, which will wholly fund it through the Metrolinx regional transit agency. Work is expected to begin in 2015 and be complete by 2020. View unique video and news content Locate projects using ESRI interactive map top100projects.ca 50 ReNew Canada top100projects.ca 2013 47 Pehonan Hydroelectric Dam $1 billion This 250 MW hydroelectric dam on the Saskatchewan River is being constructed by a partnership that includes the James Cree First Nations (made up of James Smith Cree Nation, Cumberland 100A First Nation/Peter Chapman Band, and Chakastaypasin Band of the Cree), Brookfield Power, and Kiewit. The group is currently negotiating an energy purchase agreement with the publically owned SaskPower. It is intended that the project will provide employment and economic development opportunities for the First Nations communities involved in it. NEW Location: Fort La Corne, Saskatchewan Owner: James Smith Cree Nations, Brookfield Power, Kiewit Contractor: Kiewit Funding: Public/Private • First Nations James Cree First Nations • Brookfield Power, Kiewit 48 Mount MacDonald Wind Project $1 billion NEW Location: Port Edward, British Columbia 49 Owner: Rupert Peace Power Holdings Consulting: ECL Environmental Solutions Funding: Private • Municipal AMT: $1 billion Sainte-Justine University Hospital Centre Modernization $995 million Location: Montreal, Quebec • Philanthropy Ste. Justine University Hospital Foundation: $70 million Owner: Sainte-Justine University Hospital Centre Project/Construction Manager: TDC Consortium—Tecsult, DECASULT, and CIMA+ (project manager) Engineer: Pellemon/Bouthillette, Parizeau et Associés (electrical, mechanical); SKD/NCK Consortium— Saïa, Deslauriers, Kadanoff, Leconte, Brisebois, Blais and Nicolet Chartrand Knoll (civil, structural); Dessau (mechanical, electrical) Sheppard East LRT $950 million NEW Location: Toronto, Ontario Owner: Metrolinx Project/Construction Manager: Metrolinx (project manager) top100projects.ca Architect: AECOM, Brière, Demontigny, Gilbert et Associés, Hébert Fortin Martin Consortium, Jodoin Lamarre Pratte et Associés, Lemay et Associés, Métivier Funding: Public/Philanthropy • Provincial $925 million 2012 Rank: 31 50 This 250 MW wind farm will be located on the highest peaks of Mount MacDonald and Smith Island, near Port Edward, British Columbia. It is sited on the traditional territory of the Gitxaala Nation. A turbine supplier has not yet been selected, but Rupert Peace has suggested that each generator will be between 1.5 and 2.5 MW, and they will number between 100 and 150. It is currently undergoing a provincial EA. The expansion and retrofit project, which is targeting LEEDSilver certification, is being carried out in several phases, some of which have already been completed. Significant construction activity was ongoing in 2012, and final completion is scheduled for 2018. Sainte-Justine University Health Centre is a teaching hospital affiliated with the Université de Montreal. It specializes in obstetrics and other care for mothers and children. The Sheppard East LRT will be new 13 km line extending the Sheppard subway line eastward from Don Mills Station to Morningside. It will intersect Contractor: Dufferin Construction with the extended Scarborough LRT line, which is replacing the Scarborough RT. Supplier: Bombardier Like the Scarborough LRT, the project was originally (LRT vehicles) part of the TTC’s Transit City program, which was Funding: Public cancelled by the current municipal government. It has • Provincial Ministry of now been taken up by the Province, which will fund Transportation capital allotment it through the Metrolinx regional transit agency and a to Metrolinx: $633 million contribution from the federal government. Work is expected to begin in 2017 and be complete by 2021. • Federal: $317 million Engineer: C2HM HILL (owner’s engineer) ReNew Canada 51 2013 Top 100 Projects Waneta Expansion Credit: Fortis 51 $900 million 2012 Rank: 33 Location: At the confluence of the Pend d’Oreille and Columbia Rivers, south of Trail, British Columbia Owner: Fortis, Columbia Power Corporation (CPC) and Columbia Basin Trust (CBT) Project/Construction Manager: SNC-Lavalin (project manager) Engineer: Golder Associates (environmental consulting engineers); Hatfield Consultants Contractor: Aecon (civil design, construction); SNC-Lavalin (prime contractor, design) The Waneta Expansion is currently under construction and expected to be finished by 2015. Design-Build Team: Aecon, SNC-Lavalin Funding: Private • Fortis $459 million • CPC/CBT $441 million Long-Term Accommodation (LTA) Project Credit: Plenary Group 52 This project involves the addition of a second powerhouse downstream from the Waneta Dam on the Pend d’Oreille River, producing 335 MW of power. The energy will be sold to BC Hydro under a long-term energy purchase agreement. $867 million 2012 Rank: 35 Location: Ottawa, Ontario Owner: Long-Term Accommodation (LTA) Project Project/Construction Manager: PCL Constructors Canada (builder, construction manager) Engineer: Adjeleian Allen Rubeli (structural designer); Enermodal Engineering (green designer); MMM Group (mechanical, electrical, security, IT design); Modern Niagara (mechanical subcontractor); Plan Group (electrical subcontractor) Architect: HDR Architecture (associate architect, engineer); WZMH Architects (architect of record) Facilities Manager: Honeywell DBFM Team: Plenary Properties LTAP LP, Plenary Canadian Holdings (financial arranger); RBC Capital Markets (equity investor, debt underwriter) Other: Defence Construction Canada (procurement) Funding: Public • Federal $867 million 52 ReNew Canada Financing The government has chosen a P3 approach (DBFM) for the project. The contract, valued at $4.6 billion over 34 years (including the $867 million in capital costs), is expected to save $176 million (based on the value for money report). Communications Security Establishment Canada (CSEC) is responsible for the collection of electronic intelligence to support national defence and the foreign policy of the Canadian government, as well as the protection of information and communication. The new 72,000 m2 facility, which is targeting LEED-Gold certification, will include general office space and special purpose space, as well as employee amenities such a cafeteria and gym and a substantial outdoor landscaped area. Currently under construction, completion is scheduled for 2014. All contractors are closely screened and a CSEC security expert is overseeing the security aspects of the project. top100projects.ca 2013 Top 100 Projects Credit: BC Hydro The existing Ruskin generating facility consists of a concrete gravity dam and a 105 MW powerhouse. 53 Ruskin Dam and Powerhouse Upgrade $857 million NEW Location: Ruskin, British Columbia Owner: BC Hydro Engineer: Flatiron-Dragados joint venture (major civil work); Golder Associates (right abutment) Supplier: Voith Hydro (turbines and generator) Funding: Public • Provincial BC Hydro: $857 million 54 Canadian Forces Base (CFB) Trenton Expansion $840 million NEW Location: Trenton, Ontario Owner: Department of National Defence (DND) Other: LVM (environmental services) Funding: Public • Federal DND: $840 million 54 ReNew Canada This generation station has supplied power to the BC Hydro grid for almost 80 years and requires upgrades to ensure operational reliability and improve safety in the event of an earthquake. There are four major components to this project including the reinforcement of the right bank of the dam with a specially designed cutoff watt, which will control and manage water seepage. Seven concrete piers and spillway gates will be removed and replaced with five new ones and the road on top of the dam with be replaced with a two-lane road, from its current onelane format. The powerhouse facility will be seismically upgraded and the powerhouse equipment will be replaced, this will include upgrades to penstocks and intake tunnels that move water from the reservoir to the powerhouse. The final component of the project will see the switchyard, currently located on the roof of the powerhouse, rebuild and relocated to the left bank behind the road. Approved by the Province in April 2012, construction began in that year and is expected to finish in 2018. Established in 1929, CFB Trenton has traditionally been an air base, home to the 8 Wing unit. It is one of Canada’s primary launching sites for military missions abroad. It’s now undergoing a major expansion that will add the Land Advanced Warfare Centre (a multi-functional training and administrative campus), as well as new hangers and runways to accommodate additional aircraft and a new fire hall. It will also see the relocation of the elite Joint Task Force (JTF) 2 to the base. The project involves acquiring an additional 401 hectares (ha) of land—a move that has been controversial as it involves expropriating neighbouring farms, some more than 200 years old. The 10-year expansion program has already begun construction, and is expected to be complete by 2022. top100projects.ca 2013 Top 100 Projects Credit: Infrastructure Ontario 55 St. Joseph’s Healthcare: London’s Specialized Mental Health Care and Forensic Mental Hospital $830.5 million NEW Location: London/St. Thomas, Ontario Owner: St. Joseph’s Healthcare DBFM Team: Integrated Team Solutions (ITS)—Fengate Capital Management, OE Infrastructure Fund, TCPP Infrastructure Fund, LPF Infrastructure Fund, EllisDon, and Honeywell. 56 Waterloo Region LRT $818 million 2012 Rank: 36 Other: Infrastructure Ontario (procurement manager and project development); Honeywell (facilities management) Construction: EllisDon Funding: Public • Provincial $830.5 million Financing The project has been undertaken as a P3, with ITS receiving a 30-year DBFM contract from St. Joseph Health Services. St. Joseph’s is constructing two new facilities in London and St. Thomas, Ontario. Mental Health Care London will be located adjacent to the Parkwood Hospital and will include 156 beds (later expandable to 168 beds). The smaller Mental Health Care St. Thomas facility will include 89 beds. The St. Thomas facility is scheduled to open in the spring of 2013, while the London facility will open in December 2014. Financing The project is to be delivered as a DBOFM P3 over a 30-year contract. In 2012, the Region issued a Request for Qualifications (RFQ), but as of late 2012, a team had not yet been selected. Location: Waterloo, Kitchener and Cambridge, Ontario Owner: Region of Waterloo Engineer: Parsons Brinkerhoff (owner’s engineer) Other: Hatch Mott MacDonald, AECOM, MMM (transit project assessment process team) Funding: Public • Federal Building Canada Fund: $265 million • Provincial Ontario Ministry of Transportation: $300 million • Municipal Region of Waterloo: $253 million 56 ReNew Canada After a lengthy debate about whether to adopt light rail or rapid bus technology for regional public transit, the Region of Waterloo decided that light rail technology offered the best long-term value for expanding its public transit system. In May 2012, the Ontario Ministry of the Environment approved the final stages of the EA for the project. This approval removes one of the final hurdles to starting construction in 2014. The project will be going ahead as a P3, through a designbuild-finance-operate-maintain contract. Service is expected to begin in 2017. The region has chosen to use Bombardier as the supplier for the LRT vehicles, piggybacking on an existing agreement that provincial transit agency Metrolinx has already approved. This agreement will allow the region to capitalize on a larger volume purchase, potentially reducing the individual cost of the vehicles, as well as the cost of spare parts and maintenance contracts. Siemens Canada disapproved of the process and criticized the region for not being transparent. The initial proposed route is limited to Waterloo and Kitchener, but a second phase is expected to extend the line to Cambridge. top100projects.ca Top 100 Projects 57 K2 Wind Project $800 million Other: SENES Consultants, Stantec Consulting, AMEC Environment & Infrastructure, Timmins Martelle Heritage Consultants, Selde Corporation and Zephyr North Canada (Renewable Energy Approval application) 2012 Rank: 34 Location: Township of Ashfield-ColborneWawanosh, Ontario Supplier: Siemens (turbines) Owner: Capital Power, Samsung Renewable Energy, Pattern Renewable Holdings Funding: Private • Capital Power: $266.6 million • Samsung Renewable Energy: $266.6 million • Pattern Renewable Holdings: $266.6 million Contractor: Samsung (engineering, procurement, construction) 58 Canpotex Potash Terminal $800 million NEW Owner: Canpotex Location: Prince Rupert, British Columbia Funding: Private • Canpotex: $800 million 59 Owner: EDF Energies Nouvelles $800 million Engineer: LVM (geotechnical and materials) Location: MRC de Charlevoix and MRC du Fjord de Saguenay, Quebec 60 In response to the growing demand for Canadian potash exports, Canpotex is proposing to build a potash port terminal on Ridley Island, near Prince Rupert. The facility will be able to accept shipping up to 180,000 DWT (dead weight tonnes), increasing the total potash export capacity up to 13 million tonnes annually. It will also include an 180,000 tonne potash storage building, and associated maintenance and personal structures. The terminal is planned to be accessible by rail, with an automated railcar unloading and conveyer system. The company hoped to have all environmental approvals complete by the end of 2012. Riviere du Moulin Wind Farm NEW Seigneurie de Beaupré Wind Farms 2 and 3 $800 million Supplier: REpower Funding: Private • EDF: $800 million Owner: Boralex, Gaz Métro Engineering: LVM (geotechnical and materials) NEW Supplier: ENERCON Location: MRC Côte-de-Beaupré, Quebec Funding: Private • Boralex, Gaz Métro: $800 million Total Public $106.36 billion Total Private $27.62 billion Other $6.68 billion 58 ReNew Canada The project, formerly known as the Kingsbridge II Wind Power Project, has a 20-year power purchase agreement (PPA) from the Ontario Power Authority (OPA) under the Feed-in Tariff (FIT) program. Commercial operation is expected to begin in 2014 on the 270 MW wind energy facility near Goderich—the largest of its kind in Ontario. It will involve 140 turbines, and sit adjacent to the much smaller K1 Wind Project, which has been operating since 2006. Like nearly all rural wind farms in Ontario, K2 has seen opposition from some locals. In response, the owners of K2 are proposing to compensate not only the owners of the sites where the turbines will go, but also those who live within one kilometre of a turbine. This 350 MW wind farm consisting of 175 turbines is expected to be the largest in Canada once completed. Located on remote unincorporated land northeast of Quebec City, its proponents plan to use existing logging roads to access the turbine construction sites. It will be built in two phases. The first, consisting of 150 MW, is expected to begin construction in 2013 and be complete by the end of 2014. The second, 200 MW, will be complete by the end of the following year. Hydro-Québec has agreed to buy the power produced by the farm, and will be building a 345 kV transmission line to link it to the power grid. Two adjacent wind farms with a total generating capacity of 272 MW and 126 turbines are being constructed by a private consortium made up of Boralex and Gaz Métro. They are located in the historic, forested lands of the Seigneurie de Beaupré, owned by a seminary of the Quebec diocese of the Catholic Church. Aside from the wind farms, the uninhabited lands are used by the seminary for selective logging, and are partially leased to hunting and fishing clubs. The smaller Wind Farm 1 is already running, while Wind Farm 4, currently undergoing environmental approval, could be built by 2015. 2013 Top 100 Energy Transportation Total Investment $57.66 billion $33.62 billion $140.66 billion Provincial $34.17 billion Private $22.12 billion Other $1 billion Federal $370 million Provincial $16.14 billion Federal $11.5 billion Private $5.19 billion Other $794 million top100projects.ca 2013 61 South Kent Wind Project $800 million NEW Location: Chatham-Kent, Ontario Owner: Pattern Energy, Samsung Supplier: Siemens (turbines) Funding: Private • Pattern Energy, Samsung: $800 million 62 This 270 MW, 124-turbine wind farm, is currently being appealed to the Environmental Review Tribunal. As yet, no wind energy projects in Ontario have been permanently stopped because of a Tribunal ruling. If the appeal is overruled, this project should be under construction by 2013 and completed in 2014. This project is being undertaken in partial fulfillment of the Green Energy Investment Agreement, which commits Samsung to invest $7 billion in Ontario’s renewable energy manufacturing and energy production industries. For details about the agreement, visit bit.ly/Vjyawj Capital Regional District Sewage Treatment Plant $782.7 million 2012 Rank: 37 Location: Southern Vancouver Island, British Columbia Owner: Capital Regional District (CRD) Engineer: CH2M HILL (preliminary planning study); C.N. Ryzuk & Associates (geotechnical consultant); Westland Resource Group, Associated Engineering, Kerr Wood Leidal Associates (consultants) Other: CH2M HILL (preliminary planning/study); Ernst & Young (business case); Stantec (business case and technical planning services) Funding: Public • Federal Building Canada Fund: $260.9 million • Provincial Ministry of Community and Rural Development: $260.9 million • Municipal $260.9 million 63 Southeast Section, Calgary Ring Road $769 million NEW Location: Calgary, Alberta Owner: Alberta Transportation DBFM Team: Chinook Roads Partnership (SNC-Lavalin, Acciona) Engineer: SNC-Lavalin, CH2M HILL Other: LVM (quality assurance and surveying) Funding: Public • Provincial Alberta Transportation: $232 million • Federal Major Infrastructure Component of the Canada Building Plan: $100 million • Private Chinook Roads Partnership: $437 million The system configuration will include centralized, liquids only treatment facility at McLoughlin Point in Esquimalt and a separate biosolids digestion facility, located either at the Hartland Landfill or another suitable location. The Clover and Macaulay facilities will be upgraded to pump wastewater to McLoughlin, and grit removal facilities will be added to the existing screening facilities at both locations. The Craigflower pump station will also be upgraded. Currently, the sewage management system in the CRD consists of a six-millimetre screen to remove inorganic material from the waste prior to it being pumped a kilometre offshore into the Pacific Ocean. However, new federal wastewater regulations require municipalities to implement secondary wastewater treatment before sewage can be discharged into the environment; these measures must be in place by 2020. While delayed for several years, the CRD project will be soon be moving forward. In 2012, both the provincial and federal governments re-committed to funding the project after substantial delays to the project. Financing Alberta Transportation has a 33-year DBFM contract with Chinook Roads Partnership. The P3 will see Chinook maintain the highway for 30 years (after a three-year construction period). The southeast section of Calgary’s six-lane ring road stretches 25 km, has nine interchanges, one road flyover, two railway flyovers and 27 bridges. It is being constructed and operated as a public-private partnership, with SNC-Lavalin and Acciona S.A. responsible for its maintenance over 30 years. Construction began in the spring of 2010 and is expected to finish by fall of 2013. Transit Buildings Water/Wastewater Environment Waste Management $25.64 billion $18.23 billion $2.83 billion $1.68 billion $1 billion Provincial Other Municipal Federal $14.11 billion $4.49 billion $4.31 billion $2.73 billion Provincial Federal Private Municipal $15.95 billion $1.77 billion $304 million $218 million Federal Provincial $1.56 billion $120 million Provincial $1 billion top100projects.ca Municipal Other Federal $1.71 billion $400 million $361 million Provincial $361 million ReNew Canada 59 Top 100 Projects 64 North LRT Extension, Downtown to NAIT Other: AMEC Earth and Environmental (environmental consulting), LVM (materials testing and construction surveying) $755 million 2012 Rank: 40 Location: Edmonton, Alberta Owner: City of Edmonton Project/Construction Manager: SNCLavalin and Graham Construction (construction manager); AECOM (project manager, coordination of consultant team) Engineer: AECOM (detailed design); ILF Consulting Engineers, ISL Engineering and Land Services, Stantec (design consultants); SMA Consulting (detailed design, project controls, value engineering, risk management) 65 Mica Generating Station Upgrade $739 million NEW Location: Revelstoke, British Columbia Owner: BC Hydro 66 Contractor: Mitsubishi Electric Power Products Incorporated (MEPPI) Supplier: Andritz Hydro (turbines) Funding: Public • Provincial BC Hydro: $739 million Expansion and Renovation of L’Hôtel Dieu de Québec $715.6 million 2012 Rank: 41 Location: Quebec City, Quebec Owner: Centre Hospitalier Universitaire de Québec (CHUQ) Project/Construction Manager: BPR-Batiment, CIMA + (project manager) 67 $709 million 2012 Rank: 51 Location: Merritt to Coquitlam, British Columbia Owner: BC Hydro Project/Construction Manager: Hatch (construction program management) Two additional 500 MW generators are being added to the Mica Generating Station, located north of Revelstoke on the Columbia River. Originally built in 1977, the Station was intended to have six generators, but only four were initially installed. This project brings it up to full capacity: 2,805 MW. It will also require the construction of a new capacitor halfway along the Mica to Nicola 500 kV transmission line, near Seymour Arm. The Mica Generating Station provides 15 per cent of BC Hydro’s energy capacity. Unit 5 is expected to be operational by October 2014; Unit 6 by October 2015. Architect: St-Gelais Montminy Vallières, Provencher Roy + Associés Architectes, Birtz Bastien Beaudoin Laforest Architectes, Corriveau Girard et Associés, DMG Architecture, Lemay Associés, Brière Gilbert + Associés Architects, Bélanger Beauchemin Morency Architectes et Urbanistes, Dan S. Hanganu Architectes Engineer: Dessau, Genivar Funding: Public • Provincial CHUQ: $715.6 million Interior to Lower Mainland Transmission Project 60 ReNew Canada Funding: Public • Federal Building Canada Fund: $100 million • Provincial Green Trip: $497 million • Municipal City of Edmonton: $158 million, through a combination of reserve, tax-supported debt, the municipal sustainability initiative (MSI) and other programs The City of Edmonton’s 3.3 km LRT expansion is on track for completion in December 2013. Three stations are being designed as part of the extension: MacEwan Station, Kingsway Station, and NAIT Station, linking the city’s rapid transit system to Grant McEwan University, the Royal Alexandra Hospital, and the Northern Alberta Institute of Technology (NAIT). The new line will connect to the existing LRT at Churchill station downtown via a tunnel, and is expected increase daily ridership by 45,000. This project is the first step in a plan that will ultimately see the LRT extended to the City’s northwestern limits near St. Albert. The line is expected to be operational by April 2014. Engineer: AECOM Contractor: FlatironGraham Joint Venture (design, procurement, construction) Other: Golder Associates (environmental program management) Funding: Public • Provincial BC Hydro: $709 million First announced in 2010, the renovations to L’Hôtel Dieu de Québec will include three new buildings and the complete overhauling of another three. Demolition has been completed and construction work on Phase 1 of the project is underway. The project is aiming for LEED-Silver certification. Founded in 1639, L’Hôtel Dieu de Québec is the oldest hospital in North America. It is affiliated with Laval University. BC Hydro’s plan to build a new 500 kV transmission line mostly along an existing rightof-way between the Nicola substation near Merritt and Meridian was initially met with opposition from First Nations groups. However, three First Nations reached an agreement on August 2011 with BC Hydro and the project is now going ahead. It is expected to be completed by spring of 2014. The increased transmission capacity will meet an estimated 50 per cent increase in electricity demand in the province over the next 20 years, most of it coming from the Lower Mainland. top100projects.ca 2013 68 Financing Forrest Kerr Run-of-River Project $700 million 2012 Rank: 43 Location: North of Stewart, British Columbia Owner: Coast Mountain Hydro Limited Partnership, a wholly owned subsidiary of AltaGas Engineer: SNC-Lavalin (EPCM) Funding: Private • AltaGas: $700 million Lac Alfred Wind Farm $700 million Funding: Private • EDF-EN: $350 million • Enbridge: $350 million Credit: Saint-Laurent Énergies 69 AltaGas has a 60-year Electricity Purchase Agreement with BC Hydro and has an impact benefit agreement with the Tahltan Nation, as well as an agreement to contribute to the construction of the Northwest Transmission Line, which runs from Terrace to the proposed interconnection point of Forrest Kerr. WestLB is providing partial financing. This 195 MW run-of-river hydroelectric generation project will channel a portion of the Iskut River flow and deliver electricity to the BC Hydro grid at its proposed Bob Quinn Lake Substation. It involves the construction of a power tunnel paralleling the Iskut River from its confluence with Forrest Kerr Creek, to a 300 m tailrace three kilometres away. It should be complete by 2014. NEW Location: MRC La Matapédia/ MRC La Mitis, Quebec Owner: Saint-Laurent Énergies (a subsidiary of EDF-EN), Enbridge Engineer: LVM (geotechnical and materials); Dessau (telecommunications) Contractor: RES Canada Supplier: REpower (turbines) St. Joseph’s Healthcare Hamilton, West 5th Campus Redevelopment $698 million Credit: Infrastructure Ontario 70 Set to be one of the largest wind farms in Canada, Lac Alfred will produce 300 MW of energy using 150 turbines spread over 169 km2. The first phase of the project, consisting of 75 turbines, was scheduled for completion by December 2012. The remaining 75 turbines are to be operational by December 2013. 2012 Rank: 44 Location: Hamilton, Ontario Owner: St. Joseph’s Healthcare Hamilton Engineer: Cannon Design (design); MMM Group (mechanical, electrical, information technology, security, civil) Architect: Zeidler Partnership Architects Contractor: PCL Construction Canada Facilities Manager: Honeywell DBFM Team: Plenary Health Hamilton—Cannon Design, Honeywell, Innisfree, PCL Construction Canada, Plenary Group, Royal Bank of Canada Other: Innisfree (developer); Royal Bank of Canada (financial advisor); Infrastructure Ontario (procurement manager and project development) Funding: Public • Provincial $698 million top100projects.ca Financing This project is being delivered through a DBFM P3. RBC Dominion Securities, which is the bond underwriter and original purchaser , is providing short- and long-term bonds. Equity is being provided by Plenary Group and Inisfree PFI Secondary Fund LP. As this facility is being built to LEED-Silver standards, construction involves sourcing materials locally and diverting approximately 90 per cent of material from landfill. This new health facility will feature more natural light in patient rooms and focus on family-based care. Construction is expected to be complete by the summer of 2014. ReNew Canada 61 Top 100 Projects 71 BC Children’s Hospital / BC Women’s Hospital & Health Centre Redevelopment $682.2 million 2012 Rank: 46 Location: Vancouver, British Columbia Owner: Provincial Health Services Authority Engineer: Bird Construction (design); Callison (clinical support building—indicative design) Architect: Hugh Condon Marler Architects (HCMA) Contractor: Bird Construction (construction) 72 Juan de Fuca Power Cable NEW Location: Victoria, British Columbia, to Port Angeles, Washington Owner: Sea Breeze Power Funding: Private • Sea Breeze Power: $665 million Marmora Pumped Storage Project $660 million NEW Location: Marmora, Ontario Owner: Northland Power Engineer: Hatch Funding: Private • Northland Power: $660 million 74 Funding: Public • Provincial $532.2 million • Philanthropy BC Children’s Hospital Foundation: $150 million This 400 MW pumped storage project will make use of an abandoned water-filled open-pit mine in Marmora, Ontario to store energy like a battery. The project will use cheaper low rate off-peak energy to pump water into a raised reservoir, which will be located above the existing mine. During peak hours when energy prices are higher, the water will be released into the mine through a hydroelectric turbine to generate electricity. In this way, excess electricity from non-controllable sources such as solar and wind generators, can effectively be stored for any desired period of time. Although pumped storage technology is Prince Rupert Container Terminal Development, Phase 2A $650 million 2012 Rank: 48 Location: Prince Rupert, British Columbia Owner: Maher Terminals (owned by Deutsche Bank) Other: Stantec (environmental mitigation strategy report) Funding: Private • Maher Terminals: $650 million 62 ReNew Canada The first phase will include the opening of additional neonatal intensive care unit beds at the BC Women’s Hospital & Health Centre, site preparations for the new hospital, scheduled to begin in early 2014, and construction of a new clinical support building and free-standing child daycare centre. The second and third phases of the project will include building the new BC Children’s Hospital and renovations and expansion of the BC Women’s Hospital. Tendering for the clinical support building was finalized in 2011 and Bird Construction was selected as the preferred proponent to design and build the facility. By 2012, construction on Phase 1 was well underway. The project is expected to be completed in 2018. This cable, linking Vancouver Island to the Angeles Peninsula, will be the first international power connection across the Strait of Juan de Fuca. A total of 50 km in length, 30 km of it will be under water. Although Vancouver Island is already connected to the British Columbia mainland, the new cable is intended to increase speed and efficiency of transmission between Canada and the United States, a particular issue for certain types of fluctuating renewable energy, such as $665 million 73 Other: Resource Planning Group (clinical specifications) wind and solar. It is intended to be bidirectional. After undergoing a lengthy regulatory and consultations process, including with both the Canadian and U.S. governments, First Nations, and the general public, the project is expected to be underway by the end of 2013. It could be complete by as early as 2015. Sea Breeze Power is currently negotiating sales and procurement contracts with purchasers in both Canada and the United States. new to Canada, it has been in use in the Europe, the United States, and Japan since at least the 1960s. As with many rural power generation projects in Ontario, the proposal has been controversial. Although endorsed by the County and Township governments, some local opponents fear that an accident at the plant could flood their town. The company insists the technology is safe and sustainable and that they have they support of many local residents. As of late 2012, Northland Power was working to secure an energy sales contract with OPG with the goal of launching operations by 2016. This expansion is being undertaken to accommodate the continued growth in export traffic anticipated over the next decade. The 32 ha Phase 2 expansion of Prince Rupert’s Fairview Container Terminal will upgrade the Port’s total capacity to two million twenty foot equivalent units (TEUs). It will be directly serviced by CN Rail. Some concerns were initially raised about the original environmental impact statement and new mitigation measures have since been drafted. Construction should begin after all regulatory approvals have been received. It is expected to be complete by 2015. top100projects.ca 2013 75 Union Station Revitalization $640 million 2012 Rank: 49 Location: Toronto, Ontario Owner: City of Toronto Project/Construction Manager: Carillion Construction (contractor, construction management) Engineer: NORR Limited Architects & Engineers, part of the IngeniumGroup (design) Contractor: Clifford Restoration (building envelope restoration) Other: Arup Canada (4D modelling, pedestrian flow, construction coordination analyses) 76 Routes 73/175 Widening $637.5 million NEW Location: From Quebec City to Saguenay, Quebec Owner: Transports Quebec Project Management: Dessau Engineer: Dessau, LVM Funding: Public • Federal Building Canada Fund: $133 million, VIA Rail: $25 million, Transit-Secure Trust: $6 million • Provincial $172 million • Municipal City of Toronto: $304 million The project includes a threefold increase in the GO Transit concourse space to accommodate the expected doubling of GO passengers at Union Station by 2030, and restoration of heritage aspects of the main building. There are also plans to enhance pedestrian concourses, including the construction of a new northwest PATH connection that will join the northwest corner of Union Station to Wellington Street. The City also plans to create a new lower retail level below the station. Restoration includes the rebuilding of the support columns underneath the lowest level of the station, as well as the installation of a completely new mechanical and electrical system. The new mechanical/electrical system was required to bring the building up to code. Contractor: Enterprises Alfred Boivin, Excavation de Chicoutimi, Pavex, Dynaroc, Inter-Cité, Fernand Gilbert, Hamel Construction, Construction FGN, Construction Genix, Huronne-Wendat First Nation, CharlesAuguste Fortier, RAMTelecom Other: Inspec-Sol, BPR, LVM, Groupe Qualitas, Genivar, SNC-Lavalin, CIMA+, AECOM, LEQ-LSB, EBC, Laboratoire Géo Construction (major studies and quality control) The conversion of Routes 73/175 to a four-lane, twinned highway began in 2006 and was originally expected to be completed in 2010. However, significant delays in the project have pushed its completion back to late 2013 and increased its original projected cost (the figures above represent the original budget). The federal government has contributed a significant part of its funding since 77 Woodward Avenue Wastewater Treatment Plant Expansion and Upgrades $600 million 2012 Rank: 53 Location: Hamilton, Ontario Owner: City of Hamilton Project/Construction Manager: AECOM (construction manager) Engineer: AECOM (lead subconsultant, detail design); CH2M HILL (design) top100projects.ca Funding: Public • Provincial $262.5 million • Federal $375 million the road is used to access several National Historic Sites. Because the highway extends through the Laurentides Wildlife Reserve and Jacques Cartier National (Quebec) Park north of Quebec City, conservation is a major part of the project. It will include protective fencing along the roadside and a number of wildlife bridges. Funding: Public • Federal/Provincial Green Infrastructure Fund: $200 million • Municipal City of Hamilton: $400 million (financed through water rates and development charge revenues) Hamilton’s main wastewater treatment facility will be expanded to accommodate population growth, improve effluent quality, and increase treatment for wet weather flow. The program includes a new 1,700-millilitre per day raw sewage pumping station, upgrades to existing primary clarifiers, a new membrane bioreactor facility (it will be one of the largest in the world), a new chlorine contact tank, a new tertiary effluent outfall, upgrades to the Red Hill Creek (such as widening the creek to accommodate increased flows and works to mitigate erosion), upgrades to the power supply, electrical distribution system and standby power, solids handling, and other ancillary upgrades. The project is expected to be completed in 2015. ReNew Canada 63 Top 100 Projects Darlington Refurbishment Project $600 million NEW Location: Clarington, Ontario Owner: OPG Engineer: SNC-Lavalin, AECOM Funding: Public • Provincial Ontario Power Generation: $600 million 79 North Island Hospitals Project $600 million NEW Location: Campbell River and Comox, British Columbia Owner: Vancouver Island Health Authority Funding: Public • Provincial $365 million, ComoxStrathcona Regional Hospital District: $235 million 80 This project consists of two phases: definition and execution. The $600-million cost of this project is limited to the definition phase, which will run from 20122016. The execution phase is expected to cost several billion dollars. The initial phase will consist of the construction of a mock reactor, as well as the development, procurement, and testing of the specialized tooling that will be required to complete the execution phase of this project. Financing This project will be delivered through a DBFM P3. As of late 2012, three consortiums had been shortlisted to build the hospitals. The winner is to be selected by spring of 2013. Southern Alberta Transmission Reinforcement $600 million NEW Location: From Calgary to the US border, Alberta Owner: Altalink Engineer: SNC-Lavalin (EPCM) Funding: Private • Altalink: $600 million 81 Greenfield South (previously Sherway) Natural Gas Plant $580 million NEW Location: St. Clair Township, Ontario Owner: Greenfield South Power Corporation, Eastern Power Funding: Public/Private • Greenfield South Power Corporation, Eastern Power: $400 million • Provincial $180 million 64 ReNew Canada Credit: SNC-Lavalin 78 The purpose is to support the refurbishment of the four operating nuclear reactors at the Darlington Nuclear facility. The definition phase will also include the development of a budget, scope, and schedule for the execution phase. The Vancouver Island Health Authority will replace the aging Campbell River District General Hospital and St. Joseph’s General Hospital with two new facilities. As of late 2012, proposals were being received for the renewed Campbell River District General Hospital and the replaced (and renamed) Comox Valley General Hospital. The former is planned to have 95 beds, while the latter will have 153. Both of the hospitals will serve the local population, with an emphasis on improved service, including a greater number of private rooms and washrooms. Both facilities are aiming for LEEDGold certification, as well as maximizing the exterior use of wood, in keeping with British Columbia’s Wood First Act. Construction is expected to begin by early 2014, and be complete by 2017. Increased production of energy from wind farms in southern Alberta has led to a demand for additional transmission capacity. The Southern Alberta Transmission Reinforcement (SATR) project stems from a formal application put forward to the Alberta Utilities Commission (AUC) in 2008 by the Alberta Electric Systems Operator (AESO), and approved in 2009. Altalink is completing the project is a number of stages, which consist of individual substations and transmission line segments. A private company that owns much of the energy transmission network in southern and central Alberta, Altalink operates around the cities of Calgary, Edmonton, Red Deer, Medicine Hat, and Lethbridge. This controversial 280 MW generator was originally proposed for Mississauga, but was relocated nearby Sarnia in 2012. Opposition parties accused the provincial government of cancelling the Mississauga project in order to save Liberal members’ seats in the 2011 election, while the government argued that they were appropriately responding to the citizens’ demands. The cancellation is also proving to be costly. Relocating the plant— which was already partially constructed—is estimated to cost $180 million, including a court settlement with the original project financiers. This adds substantially to the original $400-million price tag. The new site, currently occupied by the coal-powered Lambton Generating Station, is convenient in that it already has a transmission network in place. A 20-year contract has been secured to sell energy to OPA. The plant is expected to be operational by 2017. top100projects.ca 2013 Southeast Collector Trunk Sewer $654 million 2012 Rank: 56 Location: Durham and York Regions, Ontario Owner: York Region Project/Construction Manager: A joint venture of Hatch Mott MacDonald and AECOM (detailed design and construction management) Contractor: Zublin/Strabag (prime contractor, tunnel contractor) 83 Suppliers: Armtec Holdings (pre-cast concrete tunnel lining); Caterpillar, formerly Lovat (tunnel boring machines); Salit Steel, Schoek (pipes) Other: AECOM (integrated EA); LVM (geotechnical engineer, materials testing, quality assurance) Funding: Public • Municipal York Region: $564 million This project has been in development since 2002—though the EA was not approved until early 2010. The earth pressure balance TBMs, which avoid requirements for dewatering and impacting the aquifers, and the segmental precast concrete tunnel lining, have both been procured. Construction began in 2011 and is scheduled for completion in 2015. Armow Wind Farm Owner: Pattern Energy $550 million Supplier: Siemens (turbines) NEW Location: Kincardine, Ontario 84 Northwest Transmission Line $525 million NEW Location: Terrace to Bob Quinn Lake, British Columbia Owner: BC Hydro Project/Construction Manager: Hatch (construction program management) 85 Credit: AECOM 82 Shields Health and Education Centre $520 million 2012 Rank: 58 (formerly Peace Country Regional Health Centre) Location: Grande Prairie, Alberta Owner: Peace Country Health Engineer: Stantec, MMM Group top100projects.ca Funding: Private • Pattern Energy: $550 million Other: Golder Associates (environmental program management) Funding: Public/Private • Provincial BC Hydro: $215 million • Federal Green Infrastructure Fund: $130 million • AltaGas: $180 million Architect: DIALOG (prime consultants); Stantec with HOK (design); Stantec (landscape architecture) Contractor: Graham Group Other: Stantec (transportation and helicopter consulting) Funding: Public • Provincial Alberta Health Services: $520 million The Armow Wind Farm will use 92 turbines to produce 180 MW of energy. With the Renewable Energy Approvals process expected to be complete in late 2012, construction was set to begin as early as 2013. (The approvals process was still underway at press time.) The 344 km, 287 kV Northwest Transmission Line connects the Skeena Substation, near Terrace, to a new substation at Bob Quinn Lake. Its aim is to supply power to upcoming industrial developments and remote communities currently off the grid, as well as to transmit power from local generation projects. In particular, the line will connect Altagas’s Forrest Kerr Run-of-River Hydroelectric Project into the wider grid. Altagas, which recently entered into a purchase agreement with BC Hydro, is helping to fund the transmission line and has also reached an impact benefit agreement with the Tahltan Nation. Clearing and road access work began in 2012. The project is expected to be complete by spring of 2014. Originally called the Peace Country Regional Health Centre and the Grande Prairie Regional Health Centre, the completed project is now to be called the Shields Health and Education Centre. Some controversy arose over the new name—chosen in honour of Tom Shields, a local realtor and Progressive Conservative party organizer—by those who felt naming rights should have been reserved for a donor. The regional hospital and cancer care centre is expected to provide 200 beds and a training facility. Although delayed, construction began in September 2011 and is ongoing. Completion is estimated for 2016. ReNew Canada 65 Top 100 Projects Surrey Memorial Hospital Expansion $512 million 2012 Rank: 59 Location: Surrey, British Columbia Owner: Fraser Health Engineer: Enermodal Engineering, a member of MMM Group (consulting engineer) Architect: CEI Architecture Planning Interiors, Parkin Architects Contractor: EllisDon Facilities Manager: Honeywell 87 Wilson Facility Enhancement and Yard Expansion $500 million 2012 Rank: 61 Location: Toronto, Ontario Owner: TTC 88 Gordon M. Shrum Generating Station Refurbishment $500 million 2012 Rank: NEW Location: Peace River, British Columbia Owner: BC Hydro 89 DBFM Team: Integrated Team Solutions (ITS)—CEI Architecture Planning Interiors, EllisDon, Fengate Capital Management, Honeywell, Parkin Architects Funding: Public • Provincial: $512 million Financing This project is being delivered as a P3, with ITS winning the DBFM contract. A LEED-Gold-certified eight-storey tower which will contain the new emergency department is being constructed at Surrey Memorial Hospital. It will add 151 beds, 48 private rooms for neonatal services, an expanded laboratory, a rooftop helipad, 440 new parking stalls, and space for the hospital’s clinical academic campus. Construction began in 2011 and completion is scheduled for 2014. According to Fraser Health, this project is the largest capital health expense in British Columbia’s history. Engineer: AECOM (consulting engineer, design) Project/Construction Manager: AECOM (project manager) Funding: Public • Municipal TTC: $500 million Supplier: Voith Hydro (turbines); Andritz Hydro (rotor poles) Funding: Public • Provincial BC Hydro: $500 million 2012 Rank: 63 Location: Mississauga, Ontario Owner: Region of Peel Engineer: CH2M HILL (south section); MMM Group (detailed design consultants); The Municipal Infrastructure Group (value engineering for preliminary design) 66 ReNew Canada Work at Wilson Yard includes expansion of the Wilson Carhouse to the north and south to fully convert it for the maintenance of fixed six-car Toronto Rocket (TR) subway trains, construction of an overhaul shop for heavy maintenance of TR subway train trucks and air conditioning units, additional tracks and connections to facilitate efficient train storage and movement in the yard and a new access roadway into the expanded Wilson Yard. This project consists of a major refurbishment of eight of the ten generating units at the facility, located at the W.A.C. Bennett Dam. Turbine rehabilitation will take place on units one through five, which could potentially add an additional 20 per cent generation capacity to each unit. Units one through four will have their generator stators replaced Hanlan Feedermain $480 million Credit: Fraser Health 86 Other: AECOM (EA, preliminary design report) Funding: Public • Municipal Peel Region: $140 million • Municipal York Region: $340 million and six, seven, and eight will have their rotor poles replaced. The transformer will also be replaced, along with the gantry crane and station service system. Constructed in 1968, the Gordon M. Shrum Hydroelectric Station is the largest in British Columbia and supplies 24 per cent of BC Hydro’s power. The refurbishment is expected to be complete in 2017. The 2,400-millimetre (mm)-diameter Hanlan Feedermain will run approximately 14.5 km from the Lakeview Water Treatment Plant on Lake Ontario to the Hanlan Reservoir and Pumping Station at Tomken Road and Britannia Road East. Part of the same project, the 1,500-mm-wide Mississauga City Centre Subtransmission Main will run approximately six km from the Hanlan Reservoir and Pumping Station to the intersection of Cawthra Road and Burnhamthorpe Road. The York-Peel Water Agreement insures that Peel Region will provide water to York Region. In exchange, York Region will provide $340 million to update Peel Region’s water infrastructure. Construction began in 2011, and is expected to finish by 2016. top100projects.ca 2013 Waypoint Centre for Mental Health Care Credit: Infrastructure Ontario 90 $474 million 2012 Rank: 65 Location: Penetanguishene, Ontario Owner: Mental Health Centre Penetanguishene Engineer: Hidi Rae Consulting Engineers, Morrison Hershfield (engineering consultant, LEED consultant, durability consultant, energy modeller); Univex (electrical); Mulvey & Banani International (electrical); Stephenson Engineering (structural engineering for inpatient building and parking garage) Architect: Cannon Design Contractor: EllisDon DBFM Team: Integrated Team Solutions— Cannon Design, EllisDon Corporation, Fengate Capital Management, Geo. A. Kelson Company, Hidi Rae Consulting Engineers, Honeywell, Mulvey & Banani International, National Bank Financial, Stephenson Engineering, Univex Financing This project is being delivered through a DBFM P3. Shortterm financing is provided by National Bank of Canada and the Toronto-Dominion Bank. Equity is being provided by Fengate Capital Management on behalf of LPF Infrastructure Fund and OE Infrastructure Fund and EllisDon Corporation. Facilities Manager: Honeywell Supplier: CleanEnergy Developments (geothermal system) Other: Infrastructure Ontario (procurement manager and project development) Funding: Public •P rovincial: $474 million Women’s College Hospital Redevelopment Credit: Infrastructure Ontario 91 The new hospital will replace the existing 160-bed Oak Ridge Facility and the 20-bed Brebeuf Facility, and will consolidate mental health services into a more efficient and integrated complex. Under construction, completion is scheduled for 2014 and the building is expected to achieve LEED-Gold certification. The Oak Ridge building was constructed in 1933, and the Brebeuf in 1967. The site had previously held a variety of other mental health, corrections, and military facilities. $460 million 2012 Rank: 66 Location: Toronto, Ontario Owner: Women’s College Hospital Architect: Perkins Eastman Black/IBI Architects Contractor: Bondfield Construction, Black & McDonald DBFM Team: Women’s College Partnership—Bilfinger Berger Project Investments, Black & McDonald/HSG Zander, IBI Architects, The Walsh Group/Bondfield Construction Other: Infrastructure Ontario (procurement manager and project development) Funding: Public • Provincial $460 million top100projects.ca Financing This project is being delivered through a DBFM P3. Construction and longterm financing for the Women’s College Hospital project is being provided by Banco Espirito Santo de Investimento, Credit Agricole Corporate and Investment Bank, ING Capital, and Société Générale. Women’s College Hospital traces its history to 1883, and the current Grenville Street complex was built in the 1930s. The new facility is being built on the current Grenville Street site. The redeveloped Women’s College Hospital is targeting LEEDSilver certification and will replace all existing buildings and consolidate most hospital services into one location. Construction is underway, with completion scheduled for 2016. ReNew Canada 67 Top 100 Projects 92 Extension of Autoroute 35 $460 million NEW Location: MRC du Haut-Richelieu and MRC de Brome-Missisquoi, Quebec Owner: Transports Québec Contractor: Neilson-EBC consortium, L.A. Hébert, DJL Other: LVM (quality assurance) 93 Repairs to Route 389 $489 million NEW Location: Baie-Comeau/ Fermont, Quebec Owner: Transports Quebec Project/Construction Manager: AECOM • Federal: $44 million from the Canada Strategic Infrastructure Fund (CSIF) and $13 million from the Border Infrastructure Fund (BIF) • Provincial: $403 million A 37.5 km extension of Autoroute 35 is being added from Saint-Jean-sur-Richelieu to the Vermont border. This gap is the only part of the busy Montreal-Boston corridor not currently served by a limited-access highway system. At present, motorists must switch onto local road 133, which is ill-suited for large volumes of through-traffic. At the border, it will link to Interstate 89 which follows the east side of Lake Champlain through Burlington, Vermont. The first of four construction segments is to open in 2013, and the last in 2017. The relatively long completion time for the project is due to the number of land acquisitions, studies, and utility relocations that must happen before construction can begin. Engineering: Dessau (transportation engineering, design and specification) Funding: Public • Provincial Transports Québec: $459 million The 570 km Route 389 extends north from BaieComeau to Fermont at the Labrador border, passing the Manicougan Reservoir. It is significant not only as the primary land route to Labrador, but also to access the hydroelectric dams and power stations along the Manicougan River. The project calls for resurfacing and other improvements to the highway. Currently in the study phase, construction is expected to begin in 2015 and extend until 2021. Edmonton Arena Credit: City of Edmonton 94 Funding: Public $450 million NEW Location: Edmonton, Alberta Owner: City of Edmonton Contractor: PCL (construction) Architect: 360 Architecture DBFOM Team: Katz Group (developer/operator) Funding: Public/Private • Municipal City of Edmonton • Private Katz Group Financing In May 2012, Edmonton’s city council voted to pursue a P3 option to fund the $1.8 billion cost for the Southeast to Downtown segment of the 27 km line. The City has since applied for federal funding through the P3 Canada fund, along with a request for provincial funding to support its delivery as a P3 project. 68 ReNew Canada The new downtown Edmonton arena will be the centre point of the new Arena District and home to the Edmonton Oilers. Its unique shape was designed by 360 Architecture to resemble a drop of oil. The new downtown Edmonton arena will be the centre point of the new Arena District and home to the Edmonton Oilers. Its unique shape was designed by 360 Architecture to resemble a drop of oil. The schematic design was approved by Council in July 2012 and the budget reaffirmed, moving the project into the detailed design phase. However, by late 2012, tensions over funding had turned into a public dispute, with the Katz Group not only threatening to abandon the project, but to move the Edmonton Oilers to Seattle, unless the City agreed to their terms. City Council responded by voting to cease all negotiations with the Katz Group and consider other options for the project, including direct public management of the arena. Bradley Leeman, acting director of the City’s Office of Infrastructure and Funding Strategy, cautioned that, while it has the potential to be an exceptional infrastructure project, it’s still contingent on securing the appropriate funding from the other two orders of government. top100projects.ca 2013 95 Grand Renewable Energy Park $450 million NEW Location: Haldimand County, Ontario Owner: Samsung C&T, Pattern Energy Supplier: Siemens (turbines) Funding: Private • Samsung, Pattern Energy: $450 million 96 The Grand Renewable Energy Park is set to produce 148.6 MW of wind power through 67 turbines, as well as 100 MW of solar power. Turbines and solar panels will be dispersed across southeastern Haldimand County, which borders on Lake Erie and the Grand River. In a move unprecedented in the region, Samsung has negotiated a profit-sharing settlement with Six Nations of the Grand River, Canada’s most populous First Nation. While the development does not fall on reserve lands, it does fall within Pointe Du Bois Spillway Replacement Project Owner: Manitoba Hydro Other: MMM Group, North South Consultants (EA) $400 million Funding: Public • Provincial Manitoba Hydro: $400 million 2012 Rank: 71 Location: Pointe Du Bois, Manitoba 97 Sydney Tar Ponds Cleanup $400 million 2012 Rank: 69 Location: Sydney, Nova Scotia Owner: Sydney Tar Ponds Agency Engineer: AECOM, CBCL (design), LVM (materials engineering and design services) Contractor: HAZCO Environmental Services (builder—protective cap); L.P. (S/S remediation); MB2 Excavating and Construction and Beaver Marine in a joint venture (groundwater collection system, water treatment plant) Other: exp Services, AMEC Earth and Environmental (environmental impact statement); Mikjikj Enterprises (plant operations, maintenance); Stantec (environmental consultant) Funding: Public • Federal $280 million • Provincial $120 million the larger Haldimand Tract claimed by Six Nations. However, like most rural wind farm projects, the Grand Renewable Energy Park has drawn complaints from local residents and landowners who fear negative environmental and social impacts. The project received environmental approval last year, but was subsequently appealed to the Environmental Review Tribunal. That body was expected to make a ruling by the end of 2012. Manitoba Hydro is replacing and upgrading various components of its Pointe du Bois Generating Station, a 77 MW hydroelectric dam. Replacing the spillway will improve dam safety for the public and workers. The plan was revised in 2012 and Manitoba Hydro is seeking new regulatory approval. Proposed since the 1980s, the Sydney Tar Ponds cleanup is Canada’s most prominent environmental remediation. It aims to convert one of the country’s most polluted sites, the Sydney Tar Ponds and coke ovens, into a public park that includes sports and cultural facilities, a golf course, road and bridge infrastructure and landscaped and naturalized areas. That site had been used for the manufacturing of steel between 1901 and 2000. Work began in 2009 and to date, the south tar pond has been remediated. The north pond, from Ferry Street to the north pond narrows, was treated in fall 2012. The final phase is scheduled for remediation in 2013, with the park opening at the end of that year. Top 100 Timeline: Sydney Tar Ponds Cleanup 1986: Original remediation plan to dredge tar ponds and incinerate sludge announced 2005: Full panel review of cleanup plan, the most rigorous form of environmental assessment, announced by federal government top100projects.ca 1988: Coke ovens close 1995: Original remediation plan abandoned due to engineering problems 2006: Barrier built at mouth of Muggah Creek to prevent further contamination of Sydney Harbour 2000: Steel mill closes. Serious pollution-related health problems, including cancer, documented in surrounding community 2007: Panel issues report, which is approved by federal government, allowing plan to proceed 2008: Joins the Top 100 as number 29 2004: Canada and Nova Scotia announce new joint $400-million cleanup plan 2009: Work begins on the new remediation process, using a solidification and stabilization approach rather than incineration 2013: Remediation is expected to finish and the site will reopen as a public park ReNew Canada 69 2013 Top 100 Projects 98 Des Moulins Wind Farm $400 million NEW Location: Thetford Mines/ Kinnear’s Mills/ Saint-Jean-de-Brébeuf, Quebec 99 Engineer: LVM (geotechnical and materials) Supplier: ENERCON Canada (turbines) Funding: Private • Énergie Éolienne Des Moulins: $400 million Lions Gate Secondary Wastewater Treatment Plant $400 million NEW Location: North Vancouver, British Columbia Owner: Metro Vancouver Engineer: AECOM Architect: Miller Hull Other: KPMG (business advisor); BTY Group (cost consultant); Maple Reinders (compatibility advisor); 7group (integrated design facilitator) Funding: Public • Details not yet available Financing Currently in the project definition phase, it’s not yet been decided whether the project will be delivered traditionally or through a P3. That is to be decided by the end of 2013. This wind farm project will eventually produce 156 MW of energy. The project cost includes 40 km of new roads on private land in order to access the 77 turbines. The first phase was completed in 2011, and the entire project is expected to be constructed by 2015. The original project developer, 3Ci, sold the farm to Chicago-based Invenergy in 2011. A 20-year contract has been secured to sell electricity to Hydro-Québec. The proposed Lions Gate Secondary Wastewater Treatment Plant will replace an existing primary treatment plant. New federal and provincial regulations require that all primary treatment plants be upgraded or replaced with secondary treatment facilities. The existing primary plant is only capable of removing 40 to 60 per cent of materials in the wastewater, which is then pumped directly into the ocean—a long-time matter of concern for some environmentalists—and is located on land leased from the Squamish Nation. The new plant will be able to remove over 90 per cent of materials, and will be located on a site two km east. Design and construction will take place between 2014 and 2020—federal/province/municipal cost sharing arrangements will also be developed during that time. Decommissioning and demolition of the existing plant will take place shortly thereafter. New Colisée Credit: J’ai ma place 100 Owner: Énergie Éolienne Des Moulins S.E.C. (a subsidiary of Invenergy) $400 million NEW Location: Quebec City, Quebec Owner: Quebec City Architect: ABCP Architecture Engineer: LVM (materials testing and environmental monitoring) Contractor: Charles-Auguste Fortier Funding: Public/Private • Provincial Approximately half of the costs • Municipal Approximately half of the costs • Private $33 million by Quebecor for naming rights (to be increased to $63.5 million if an NHL team is secured) • Sales $50 million raised through advanced seat sales • Philanthropy $1 million in donations 70 ReNew Canada Quebec City’s New Colisée will replace the aging Colisée Pepsi, in which the Nordiques played, although that building will continue to stand adjacent to the new one. The architecture of the new building is designed to recall Quebec City’s maritime past, and it will include an adjacent outdoor wading pool / skating rink. Since the loss of the Nordiques, Quebec City has dreamed about attracting a new hockey franchise. As a league requirement—although no team has yet been secured—a modern, 18,000-seat NHL-quality arena is under construction. While it may also host minor league play, the financial success of the building clearly depends on the NHL. Quebec-based media firm Quebecor has purchased the naming rights to the arena, which is still tentatively being referred to as Le Nouveau Colisée or L’Amphithéâtre de Québec. Construction began in the fall of 2012. During the 2012 provincial election, the building became a political issue, visited by several leading politicians. Former Premier Jean Charest threatened that electing a PQ government would jeopardize Quebec City’s chances of winning an NHL team. top100projects.ca