water-powered drilling in the changuinola 1 rcc dam
Transcription
water-powered drilling in the changuinola 1 rcc dam
WATER-POWERED DRILLING IN THE CHANGUINOLA 1 RCC DAM PROJECT REPORT 2015.12 PROJECT REPORT - The Changuinola I Dam © LKAB Wassara, All rights reserved. December 2015 The Changuinola I Dam PROJECT REPORT 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved PROJECT SUMMARY INTRODUCTION KEY STAKEHOLDERS The Changuinola I dam construction project in Bocas del Toro, will significantly increase Panamá’s hydroelectricity production. Once it’s complete, the country will be less dependent on other energy resources – including imported oil – and its CO2 footprint will be considerably reduced. The power generators in this new roller-compacted concrete dam will be integrated with the Province of Bocas del Toro into the Panamánian grid. • Owner/commissioner/object: Panamánian Ministry for Energy supported by AES Changuinola I Hydroelectric Project S. A., a subsidiary of the US-based AES Corporation that generates and distributes energy in 27 countries. Wassara technology was used to drill the foundation, drainage and grouting holes. Water-powered drilling was chosen for this prestigious project as it has delivered successful results at a number of similar dam projects around the world. The drilling was finished more than three months ahead of schedule, in May 2011. • Main contractor: Changuinola Civil Works Joint Venture (Changuinola Civil Works), a consortium comprising of two Danish firms, E. Phil & Søn and MT Højgaard, in a joint venture with Alstom Hydro of Brazil • Main design engineer: Malcolm Dunstan & Associates engineering and construction company. • Sub-design engineer within geo-technique and rock reinforcement as well as supervisor on behalf of AES Changuinola S. A.: Golder Associates • Consultant within different stress-relaxation creep behaviour of RCC to contractor: ARQ Consulting Engineers*. • Feasibility study: Vattenfall Power Consultant. * The dam design was based on ARQ’s different stress-relaxation creep behaviour of different RCC types. LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 2 (12) December 2015 The Changuinola I Dam PROJECT REPORT TABLE OF CONTENTS Introduction...........................................................................................................................................................2 Key Stakeholders...................................................................................................................................................2 The Changuinola I dam..........................................................................................................................................3 Background...........................................................................................................................................................4 Project Objectives and Limitations........................................................................................................................4 The Wassara Equipment Description....................................................................................................................7 Results and Experiences.......................................................................................................................................9 Project costs – Evaluation.....................................................................................................................................9 Other outcomes from the project........................................................................................................................10 Drilling Results....................................................................................................................................................11 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved References...........................................................................................................................................................11 THE CHANGUINOLA I DAM Installed capacity: 223 Megawatts (15% of the national consumption) Investment: 563 million US dollars Power generation: 1 046.3 GWh per year Construction start: October 25th, 2007 Construction period: 49 months (of which the drilling with Wassara ~20 months) Commercial start (planned): November 19th, 2011 Height / Length: 99.2 m / 595 m (326 ft. / 1 952 ft.) Reservoir level: 165 m (541 ft.) above sea level Unload level: 55 m (180 ft.) above sea level Spillway flow: 11 040 m3 (2 914 560 US gallons/s) per second Power house: 106.4 MW x 2 Francis turbine-generator Ecological flow: 13.4 m3 (3 538 US gallons/s) per second, 9.66 MW LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 3 (12) December 2015 The Changuinola I Dam PROJECT REPORT BACKGROUND Illustration from Wikipedia: Panamá relief location map by Alexrk2 (public domain) GEOGRAPHY Location of the Changuinola I Dam in Bocas del Toro, Panamá PROJECT OBJECTIVES AND LIMITATIONS POLITICAL GOALS 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved The Changuinola I construction project in Bocas del Toro is a key part of the Panamá Government’s plans to increase the economic growth of Panamá at a lower energy cost per kWh. The roller-compacted concrete (RCC) hydroelectric dam has been designed to provide the national energy system with 15% of current national consumption: 223 megawatts. Once complete it will decrease the country’s dependence on other energy resources, such as imported oil, and in doing so greatly reduce Panamá’s CO2 footprint. The power generators in this new roller-compacted concrete dam will be integrated with the Province of Bocas del Toro into the Panamánian grid. Panamá has a long way to go to reach its final goals, but with the construction of Changuinola I, the country is making good progress. Changuinola II– also an RCC dam – is already in the construction start-up phase, and completion is planned for 2019. ENVIRONMENTAL CONCERNS Environmental concerns were raised prior to construction, as the dam is located on the Changuinola River, which constitutes part of the La Amistad International Park – a UNESCO World Heritage site. Despite the recognised value of the region’s biological diversity – including hundreds of rare, endemic, endangered, and migratory species – the Panamánian power company, AES, and the National Environmental Authority (ANAM), failed to conduct an appropriate environmental impact assessment. POLITICAL AND SOCIAL CONCERNS Another concern was the impact on the indigenous groups living in the La Amistad Biosphere Reserve, the internationallyrecognised protected area also shared with the Republic of Costa Rica. In the end, the project was started in 2007 and was completed ahead of schedule, in June 2012. IMPORTANT TO SEAL-OFF A NEW DAM FROM SEEPAGE When constructing a new dam, it needs to be sealed-off all the way down to competent rock in order to minimise seepage through and beneath the dam body. This is a vital part of the project in order to maintain dam stability. Water seepage is common in more or less all dams, therefore there is a constant need for monitoring, controlling and sealing-off of the seepage. The most frequent sealing method for minimising seepage is to drill numerous holes down to competent rock. Grout cement is then injected through the boreholes, filling any small pockets around the holes. This creates a so-called grout curtain. The higher the quality of this curtain, the lower the rate of seepage and the longer the lifetime of the dam – and ultimately the lower the risk of the dam collapsing. The proven Wassara method of borehole water-powered drilling has shown to be superior in numerous aspects and applications within dams. Drilling for grout and drainage holes is one such application. The drilling of foundation, drainage and grouting started in September 2009 and ended in May 2011. LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 4 (12) December 2015 The Changuinola I Dam PROJECT REPORT PROJECT NEEDS PLANNING FOR THE DRILLING During the construction process, delays were out of the question. Therefore when it came to the drilling of grout and drainage holes, Wassara technology was the only feasible drilling choice. This is a well-proven fact, established by the key stakeholders Golder Associates and the Grouting superintendent at the Changuinola Civil Works consortium. The mission set for Wassara technology was to drill the grout and drainage holes for the new dam without incident. In total, ~30 000 m (~100 000 ft.) was drilled. The body of the dam itself consisted of hard concrete (80% of the drilling), whereas the formation beneath the dam was very soft volcanic and sedimentary rock, e. g., basalt (abrasive) (20% of the drilling), see figure below. But it’s not only penetration speed that is a benefit of using Wassara water-powered technology. Another reason for the construction company using Wassara equipment is the ability to drill long straight, clean boreholes that allows cement grout to reach further into cavities without the interference of dust or oil traces. Also, the versatile characteristics of the technology (one hammer can penetrate different geologies) as well as its benign impact on the geology, was crucial in the decision to choose Wassara. DRILLING DESCRIPTION In brief, the project required around 400 unique holes measuring Ø 95 mm (3.5”), to be drilled vertically downwards (max. inclination of +/- 20 degrees to the vertical) and with depths ranging from 20 to 75 m (66 and 246 ft.) along the 595 m (1 952 ft.) dam crest, for grout curtain and drainage. This was done from the two 2.5 m x 2.5 m (8.2 ft. x 8.2 ft.) cross-section galleries of the concrete dam. Drilling-of-hole-plan of the Changuinola I Dam Upstream face 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved Downstream face Galleries for service and drainage Diversion Schematic view of the drilling grout and drainage holes Drilling holes for the grout curtain and drainage in a dam gallery This is one of the typical dam applications where Wassara drilling technology has proved to be superior LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 5 (12) December 2015 The Changuinola I Dam THE DRILLING AND GROUTING PROCEDURE Drilling and grouting was performed in three steps and included the essential hydraulic conductivity Lugeon test*: 1. Drill primary holes at c/c: 6 m (20 ft.) down to 25 m (82 ft.), pressure test the permeability of the hole with max pressure of 3 bar (44 psi) – with the criteria Lugeon value < 2. Then refill the hole with grout. 2. Drill down the same hole (after the hardening of the grout); this time to a depth of 50 m, pressure test the permeability of the hole in the 20-50 m (66-164 ft.) zone with max pressure of 2 bar (29 psi) – with the criteria Lugeon value < 2. Then refill the hole with grout. 3. Drill down the same hole once again (re-grouted) to 70 m depth, pressure test the permeability of the hole in the 50-70 m (164-230 ft.) zone with max pressure of 10 bar (149 psi) – with the criteria Lugeon value < 2. Then refill the hole with grout. * The Lugeon test is used to measure the amount of water injected into a zone of the bored hole under a steady pressure. The Lugeon value is defined as the amount of water lost to the surrounding formation, in litres per minute and per m borehole at an overpressure of 10 bar (145 psi). 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved In case pressure tests do not fulfil the Lugeon criteria value < 2, a secondary hole is drilled in between two primary holes (at a c/c: distance of 3 m (9.8 ft.) and the same three procedural steps (above) are taken. This project, however, showed to be fortunate in regards of geology impermeability since only a few of the holes showed a Lugeon value > 2; meaning that few extra secondary grout holes had to be drilled. Drilling in action in one of the galleries PROJECT REPORT REQUIREMENTS CONNECTED TO THE GROUTING PROCEDURE For the construction of the grout curtain, the main requirement was to ensure the holes were drilled as straight and parallel as possible. Max allowed deviation was 2%. Additionally, the grout hole wall finishing was very important. It had to be up to standard throughout the entire length of the holes, so as not to lower the quality of the grout curtain. The importance of having a clean hole for successful grouting is described in “Practical handbook on grouting”: “The cuttings removal method is essential to the cleanliness of the hole, however, for holes more than 3 m (10 ft.) deep, standard rotary percussive button head bits are most commonly used. These literally pulverize the rock, producing very fine cuttings. Many drillers prefer to blow the cuttings to the surface with compressed air but this has not proved satisfactory for grout holes. If the drilling is in moist or wet conditions, as is common in dams, the cuttings combine with the moisture to form a fine slurry, which can easily block any cracks or crevices it comes into contact with. Although contamination of defects with at least some cuttings is avoidable, water has been found to be the most innocuous flush medium for use in rock.” REQUIREMENTS FOR MONITORING INSTALLATION As stated earlier, borehole accuracy was essential to provide the tightest possible grout curtain. Also, the holes needed to be straight so that pendulum-monitoring instruments could be inserted. These instruments detect deformation behaviour due to seismic activities – if any – of the dam. Hole straightness is important in this process since the pendulum, which has a diam of 25 mm (1”), cannot function properly if it comes into contact with the borehole wall at any point in the hole. Water-powered drilling (left) gives cleaner bore holes compared to air drilling (right) LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 6 (12) December 2015 The Changuinola I Dam PROJECT REPORT THE WASSARA EQUIPMENT DESCRIPTION THE WASSARA DRILLING HAMMERS AND CONSUMABLES DRILLING EQUIPMENT The Wassara equipment used consisted of hammers and consumables as well as service equipment tools as shown below: The drilling equipment directly connected to the Wassara drilling activities consisted of: THE WASSARA SOLUTION – EQUIPMENT DESCRIPTION 6. Drill rig: Comacchio rig MC600 7. High-pressure water pump: Uraca high-pressure cleaning unit RS3-45E/250 (electric), providing 216 litres/minute (57 USgpm) at 220 bar (3 190 psi) 8. Water handling: On-site construction consisting of a container of 1.2 m x 2 m 1.5 m (W x L x H), (3.9 ft. x 6.6 ft. x 4.9 ft.), to which fresh river water was pumped and then continuously re-cycled back to the high-pressure pump. The rig was modified on-site with a Wassara high-pressure water swivel fitted to it. 6 7 8 5 4 3 2 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved The top-mounted high-pressure water swivel is adapted to fit the rig 1 TECHNICAL START-UP SUPPORT AND TRAINING – ONE IMPORTANT KEY TO SUCCESS IN PRODUCTION 1. Drill bit: Ø 95 mm (3.75”) 2. Hammer model W80 3. Check valve 4. Drill rods: Wassara 1 – 2 m (3.3 – 6.6 ft.), including O-rings; OD 76 mm (3”) 5. High-pressure water swivel - Service equipment tools incl. service bench built on-site (not in figure) The Wassara hammers and consumables were initially purchased as a package – including technical on-site support with a drilling expert from Wassara. The rig was easily modified by attaching a high-pressure water swivel to it. After the modifications, initial test drillings – 100 m (328 ft.) depth in basalt – were carried out close to the dam itself to verify that all components, from water handling to drill bit, were working together as planned. LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 7 (12) December 2015 The Changuinola I Dam Initial test drilling down to 100 m (328 ft.) depth PROJECT REPORT Pumping the river water from the container into the high-pressure pump INCOMING AND OUTGOING WATER Fresh water was taken from the nearby Changuinola river and pumped in to a 1.2 m x 2.0 m x 1.5 m (3.9 ft. x 6.6 ft. x 49 ft.) sized container. This water was then filtered and transported to the high-pressure pump that powered the water hammer at a rate of up to 180 bar (2 610 psi). In order to keep the water as clean as possible (particles must be 50 microns or smaller so as not to impact hammer operation) the water filters were exchanged for new ones every two months. This ensured smooth running of the drilling operation. The Uraca high-pressure pump pressurizes the water to power the hammer 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved The outgoing water was, together with the borehole cuttings, pumped out from the galleries into a sedimentation container from which the water was pumped out to the nearby river. The remaining cuttings in the container was transported away and dumped nearby. No control of cuttings or water was considered needed. LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 8 (12) December 2015 The Changuinola I Dam PROJECT REPORT RESULTS AND EXPERIENCES PROJECT RESULTS The drilling project was considered a complete success. The borehole and grouting results were as hoped for and the costs of drilling was much lower compared to what alternative core drilling methods would have cost. In addition, the drilling phase was finalised well in advance of schedule – three months ahead to be exact. With alternative methods, such as air powered or rotary drilling, the project would have taken at least three months longer than the original proposed schedule and the labour costs would have been considerably higher. 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved Two reasons for the success could be derived from the fact that the key stakeholders were experienced from earlier similar projects and, thus, understood how to work with waterpowered drilling technology with a limited need of technical support during the project start-up. One reason that the drilling project was finished so far ahead of schedule was that the construction company had on-site technical support and training in connection with drilling start-up. This is often one of the key factors to success when drilling with Wassara equipment for the first time. A few days of training and support for customers and other members involved in the drilling project will often ensure any possible issues are easily cleared up: saving time, money and minimising misunderstandings. Impoundment at the Changuinola I Dam commenced on May 22, 2012, with closure of the two 9 m x 9 m (30 ft. x 30 ft.) river diversion culverts. This made it the first RCC arch/gravity dam to be brought into operation outside of South Africa and China. The 105 m (345 ft.) high dam contains approximately 895 000 m³ (236 280 000 US gallons) of RCC. At 12 midday on Friday, June 25, 2012, the Changuinola I Dam finally reached full capacity and only started spilling after 33 days filling at an average inflow of 127 m³ (33.528 US gallons) per second. The completion of the project now brings urgently needed additional electrical power to the southern-most country of Central America, where many towns currently rely on diesel generators. ANALYSIS AND EVALUATION OF HAMMER AND COMPONENT WEAR Based on Wassaras knowledge of the hammers and spare parts, together with experience from similar projects, a thorough analysis and evaluation of the drilling could be conducted. The following conclusions were made: • Due to abrasive rock conditions, wear of drill bits (high wear on bit body whilst very low wear of the buttons) and hammer casing was quite high, giving life length of 1 154 m (3 786 ft.) and 6 000 m (19 685 ft.), respectively. • Wear of the chuck was relatively low with life length of 1 579 m (5 180 ft.) • The component most affected by the water quality and rate of penetration was the valve, which had an average life of 2 500 m (8 200 ft.) • The hammer piston had a longer average life than usual, of 2 308 m (7 572 ft.) due to softer rock conditions • T he average life of the sliding cases was unusually short at 1 765 m (5 791 ft.). This is probably because they were incorrectly replaced together with the valve house before their due time. The normal life time of a sliding case in similar dam rehabilitation projects is 10 times longer PROJECT COSTS – EVALUATION As stated earlier, the drilling results were very successful both in regards to borehole quality and drilling speed; the job was completed three months ahead of schedule. Also, the drilling cost per m, EUR 27*, was within budget, while the Rate of Penetration was 49 m (161 ft.) per day on average, or, when drilling in action 0.5 m (1.64 ft.) per minute. (* including costs showed in graphics below) • The average of 49 m per day comes from the fact that drilling was made on day 1, whilst on day 2 the grouting and testing of the hydraulic conductivity was made In brief, the project costs for the drilling-of-grout-and-drainagehole-activities for the ~30 000 m (~100 000 ft.) was kEUR 822, i. e., EUR 27 per m (kEUR 1.4 per hole). Summary of figures of interest: • Average Rate Of Penetration (ROP): 0.5 m/min (1.64 ft/min) • Average drilled m per day: 49 m (489 ft.), with 1 rig and 2 shifts per day • T he drilling part of the project was finalized in 20 months; thanks to Wassara 3-4 months ahead scheduled period of 24 months • 55% of the total cost for drilling was labour costs • 1 5% of the total cost was related to the hammers and consumables incl. service equipment LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 9 (12) December 2015 PROJECT REPORT The Changuinola I Dam OTHER OUTCOMES FROM THE PROJECT MAIN COST CATEGORIES WHEN DRILLING WITH WASSARA (kEUR) 500 455 450 400 350 300 250 200 150 122 100 100 50 0 57 9 35 6 13 17 9 THE DISTRIBUTION OF MAIN COST CATEGORIES WITH WASSARA (%) 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved Safety & Environment 1% Media 2% Hammers & Consumables 15% Labour 55% Service 1% Rig 7% Pump 4% Training & Support 2% Energy/Fuel 12% Water Handling 1% LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 10 (12) December 2015 The Changuinola I Dam PROJECT REPORT DRILLING RESULTS REFERENCES Drilling resulted in a ROP of 0.5 m/min (1.64 ft./min) at the slowest rate and sometimes as fast as 0.8 m/min (2.6 ft./min). The hole wall finishing was also to the customer’s satisfaction, particularly as the water-pressure Lugeon tests were successful. • Lars Bäcklund, Equipment Supervisor at the Changuinola Civil Works Joint Venture AWARDED THE “MILESTONE INTERNATIONAL RCC PROJECT” • Dr. Lars Hässler, Golder Associates; Supervising consultant rock re-inforcement at the Changuinola Civil Works Joint Venture The Changuinola I Dam in Panamá was recently awarded “Milestone International RCC Project”, an award supported by the International Committee on Large Dams, ICOLD that recognised the dam as being one of the 15 dams to date to have contributed most significantly to the development of RCC technology. As the first RCC arch dam outside South Africa and China, the RCC design of Changuinola I Dam was based on the South-African consulting company ARQ’s research that recognises the different stress-relaxation creep behaviour of different RCC types. • Peder Petersson, Drilling and grouting Superintendent at the Changuinola Civil Works Joint Venture • Practical Handbook of Grouting: Soil, Rock, and Structures (720 p.) by James Warner, P. E., Copyright © 2004, John Wiley and Sons, ISBN: 978-0-471-46303-0 • Magnus Hörman, Senior Engineer at LKAB Wassara • Björn Öderyd, Technical Support at LKAB Wassara WEBSITES: • https://en.wikipedia.org/wiki/Changuinola_Dam • http://www.power-technology.com/projects/changuinola75 CONCLUSIONS Wassaras water-powered drilling technology has once again proved to be the optimal choice for this kind of projects. In the main, this was thanks to in-depth knowledge and extensive understanding of the technology, as well expert technical support in the planning, start-up and drilling stages of the process by the key stakeholders. Or, as the project’s Supervising consultant rock reinforcement Lars Hässler, Technology Dr. at Golder Associates, states it: 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved “The water-powered technology from Wassara was chosen for the Changuinola I Hydroelectric Project in Bocas del Toro, Panamá, since it was evaluated to be the most feasible drilling method to solve the drilling within the given time and quality frames.” LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100 11 (12) WASSARA – COST-EFFICIENT AND ENVIRONMENTALLY FRIENDLY DRILLING LKAB Wassara is a Swedish company developing and manufacturing unique water-powered drilling systems for high performance in surface- as well as underground drilling operations. The heart of the Wassara drilling system is the world patented water-powered down-the-hole hammer. The drilling systems have been used for more than 20 years in various applications within many industries; mining, exploration, ground engineering, dams, geothermal, marine, oil & gas storage. Our experience covers more than 25 million drilled meters, working in different locations around the world. Reference studies can be found on our website. LKAB Wassara was founded in 1988 and is owned by LKAB. LKAB is an international high-tech minerals group that produces iron ore products for the steel industry and other mineral products for many other industries and applications. 1400092, Project Report: Changuinola I , ENG, 2015.12, © LKAB Wassara, All rights reserved Explore more at www.wassara.com LKAB Wassara AB | www.wassara.com | [email protected] | +46 771 760 100