PROJECT HOMANIT KROSNO ODRZAŃSKIE, POLAND JUNE

Transcription

PROJECT HOMANIT KROSNO ODRZAŃSKIE, POLAND JUNE
PROJECT HOMANIT KROSNO ODRZAŃSKIE, POLAND
JUNE 2012
Takeover of Hardex SA by Homanit – Hardex was a wet process Hardboard facility
JUNE 2013
Extension of the finishing hall with the installation of folding machines and warehouse/shipping area
SEPTEMBER 2013
Extension of warehouse/shipping area and installation of two cut-to-size saws
NOVEMBER 2013
Planning start of THDF line
MAY 2014
Project start for THDF line with energy plant (biomass) and wood chip preparation
JUNE 2014
Construction progress/preparation of building area/first concrete sections
JUNE 2014
Construction progress according to schedule, preparation for value added department ,
Construction Stage V
JUNE 2014
Construction progress according to schedule - concrete base for energy plant/
first section foundation of press line
SEPTEMBER 2014
Construction progress THDF and finishing – installation of combustion chamber of energy plant,
column for finishing area; construction of ancillary rooms for installation of THDF-Line, partially under roof
OCTOBER 2014
Construction progress THDF and lacquering hall - steel structure of dryer tower and
forming machine; preparation column for lacquering hall
NOVEMBER 2014
Construction progress THDF and lacquering hall - start of steel construction chip preparation;
housing of press and roofing of cooling line and final stacking; erection of columns for lacquering hall
FEBRUARY 2015
Commissioning phase/first fibres – construction progress lacquering hall
MARCH 2015
Before and afterwards view
JUNE 2012
Takeover of Hardex SA by Homanit – Hardex was a process Hardboard facility
JUNE 2013
Extension of the finishing hall with the installation of folding machines and warehouse/shipping area
SEPTEMBER 2012 Extension of warehouse/shipping area and installation of two cut-to-size saws
NOVEMBER 2013
Planning start of THDF line
VORAB
MAY 2014
Project start for THDF line with energy plant (biomass) and wood chip preparation
JUNE 2014 Construction progress/preparation of building area/first concrete sections
JUNE 2014
Construction progress according to schedule, preparation for value added department ,
Construction Stage V
JUNE 2014
Construction progress according to schedule - concrete base for energy plant/
first section foundation of press line
SEPTEMBER 2014 Construction progress THDF and finishing – installation of combustion chamber of energy plant,
column for finishing area; construction of ancillary rooms for installation of THDF-Line, partially under roof
OCTOBER 2014
Construction progress THDF and lacquering hall - steel structure of dryer tower and
forming machine; preparation column for lacquering hall
NOVEMBER 2014
Construction progress THDF and lacquering hall - start of steel construction chip preparation;
housing of press and roofing of cooling line and final stacking; erection of columns for lacquering hall
FEBRUARY 2015
Commissioning phase/first fibres – construction progress lacquering hall
JUNE 2012 Takeover of Hardex SA by Homanit
MARCH 2015 After Establishment and commissioning of a THDF plant