hydrostatic test plan - Regulatory Document Index
Transcription
hydrostatic test plan - Regulatory Document Index
Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 1 of 49 HYDROSTATIC TEST PLAN Bakken Pipeline Expansion Project, Mainline Pipeline NPS 16 Prepared by: Surerus Pipeline Inc. For: Enbridge Bakken L.P. 20'12-1 '1-09 2 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 2 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN 1. Scope This document was prepared for the hydrostatic pressure testing of the Enbridge Bakken Mainline NPS 16 Pipeline Project planned for construction in the summer/fall of 2012 between Steelman, SK and Cromer, MB. The test shall be completed in two (2) underground sections and two (2) above-ground sections totaling approximately 123,987m in length; the test section end points are detailed within the document below. For the below-ground sections the hydrostatic test consists of a minimum 4.25 hour strength and a minimum 4.25 hour leak test to verify the integrity of the pipeline following installation. At the pipeline end points, the Steelman and Cromer terminal tie-ins, short sections of the pipeline will be tested prior to installation due to access restrictions, these segments will be tested for a minimum period of one (1) hour to permit visual inspection of the pipeline during a combined strength and leak test. 2. Safety 2.1. 2.2. 2.3. 2.4. 2. 5. 2.6. 2.7. 2.8. 2.9. All personnel shall review and follow the Emergency Response Plan (ERP) developed specifically for this project. A copy of the ERP shall be available in each vehicle used on the project and additional copies shall be posted within the test building and other appropriate locations. A pre-phase meeting will be held at the Surerus site office for all personnel involved in the hydrostatic test prior to commencement of the test to ensure that all personnel understand their respective duties. Surerus will install warning signs and barricades to prevent access to the vicinity of the test area. Warning signs shall indicate "DANGER - High Pressure Pipeline Test• and "Restricted Access". All Surerus personnel not involved in the testing shall be removed from the area while the pipeline section is under a pressure equal to or greater than 2,760kPa (-400psi). Test heads and pressurizing pipe shall be secured to limit movement. All testing equipment including compressors, recorders, deadweights, etc. shall be set liP a safe distance from the test section and/or test heads. Surerus employees shall inspect all hoses, lines, and connections for faults prior to pressurizing the lines. The Surerus Hydrotest Pre-test Checklist will be completed to ensure that all components meet the required ratings. Surerus personnel shall ensure pressure hoses/unions are rated to twice the maximum expected hydrotest pressures, and all safety lines are firm ly attached and secured with whip checks. An Enbridge representative will be on site for the duration of test activities. 3. Equipment In addition to the details listed below, all testing materials, equipment, and instrumentation shall comply with relevant Enbridge specifications including section 6.3 of CPSC-SPECHYDR0-005. A detailed list of all testing equipment including make, model and recent calibration certificate shall be available for review prior to commencement of testing activities. Surerlls shall supply the following equipment for com pletion of the hydrostatic test: Pumps including transfer/fill pllmp, and squeeze pump. Air compressors required for pipeline cleaning, pre-pack, and dewatering. All pipeline pigs required for line fill and dewatering. All necessary valves, hoses, and fittings reqllired to successfully complete the test. Calibrated temperature recorders, pressure recorders, ancl cleaclweights. Calibrated flow meter for preparation of the yield plot where applicable. DA\!E REVISION PAGE 2012- '1 '1-09 2 2 ofB Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ------SURI!JJ Appendix A - A3 Sureus Hydrostatic Test Plan Page 3 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Adequate lighting and light towers at all work areas. 3.1 Test Heads 3.1.1 Surerus shall supply Enbridge approved test heads which comply with a ll requirements of relevant specifications including section 6.2 of CPSC-SPECHYDR0-005 . 3.1.2 Test head assemblies shall comply with all requirements of CSA-2662 (latest edition). All documentation certifying test head compliance shall be available for review prior to commencement of testing. 3.1.3 Test heads will be welded to the section and the welds will be inspected by NDE prior to filling the section. A minimum of 4m of heavywall pipe which remains below 90% SMYS at the maximum anticipated test pressure shall be included in the test section immediately adjacent to the test head. 3.2 Pumps 3.2.1 3.2.2 3.2.3 3.2.4 Surerus shall ensure that fill and squeeze pLimps are adequately sized for the length and diameter of the section to be tested. A transfer pump shall be installed at the edge of the water source (Alameda Reservoir). The pump shall be placed within a lined containment berm capable of containing 1.5 times the maximum volume of fuel contained within the pump. The inlet end of the pump will have a screened intake which meets regulatory requirements. The fill pump will be an 8" inlet and 6" discharge pump capable of providing a fill 3 rate up to 7m /min. A second fill pump will be on location for back-up. Surerus anticipates that the fill pump, storage tank, squeeze pump, and test trailer will be set-up within available temporary workspace at the common test point at the junction of section 1 and section 2 near 35+500. - T able 1 Pump Det a1'Is Pump Manufacturer/Model Suction Discharge Flow Pioneer 10" 8" 4m"/min Transfer #1 PP108S17" 4mJ/min 10" 8" Transfer#2 Pioneer PP108S1 7" Fill #1 Pioneer PP86C21· 6" 4.5 - 7m"/min 8" 6" 4.5 - 7m"/min Fill #2 (Back-up} Pioneer PP86C21' 1" TBD 2" 500Umin S_queeze _(Truck) * Pump performance curves are mcluded as an attachment ·co th1s document. a· 3.3 Instrumentation: 3.3. 'I 3.3.2 3.3.3 Surerus shall supply pressure and temperature recorders and dead weights to provide readings for the test data. The pressure shall be measured in kPa, and the temperature measured in degrees Celsius. All test charts and reports, including the depressurizing of tested lines, will be included in the document turnover package. Instrumentation for the test shall be as follows: • Single pen temperature recorders will be located at the 'fill point to record and monitor the test medium temperature through the manifold during the fill. DATE REVISION PAGE 2012-·11 -09 2 3 of8 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 4 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN 3.3.4 Additional single pen temperature recorders will be located at each end of the test section and a third temperature recorder installed near the middle of the test section . • Two dual pen temperature/pressure recorders, a digital deadweight, and a mechanical deadweight will be located at the fill point. • Two additional dual pen temperature/pressure recorders and deadweight shall be located at the section end point. All measurement equipment shall be certified for accuracy not more than 30 days prior to commencement of the pressure test. The calibration certificates and current calibration reports shall be maintained on site and included in the turnover package following completion of the test. 3.4 Cold Weather Provisions 3.4.1 To counteract the effect of below freezing ambient conditions anticipated during testing activities, Surerus shall perform the following : • Erect shelters around or hoard-in all exposed piping on the project. • Place heaters within the hoarding to maintain the pipe temperature above freezing at all test head locations and above ground valve sites along the project. • Promptly drain all f ill lines following water transfer to protect fill pipe and pumps from freezing. 3.4.2 Based upon an expected minimum average ground temperature of 3°C at the time of testing , Surerus does not anticipate a requirement to heat hydrostatic test water. 4. Line Fill 4.1 Test Sections Section 1* 2 3 Start Steelman Terminal (KPO+OOO) Alameda Reservoir East n<P3s+soo) Alameda Reservoir East (KP35+500) End Length Volume 0+094 94m 11m I<P0+100 35,400m 4,275m 3 I<P1 23+27·l 88,350m 10,669m Dewater Location 3 0+094 3 Landspread in Vicinity of KP 35+500 Landspread in Vicinity of KP 35+500 Cromer Terminal 3 74m 9m 123+271 (I<P123+345) " Note that hydrotest water for sections 1 and 4 will be provided by tankel' trucl(s. These sections shall be ·JOO% visible at t he time of tesi:ing and subject to a oneg how· combined strength and leak test. 4'' KP123+27'1 DATE REVISION PAGE 2012-'1"1-09 2 4 or a Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal -----SUR§!Wj Appendix A - A3 Sureus Hydrostatic Test Plan Page 5 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN 4.2 Fill section Test heads will be welded onto the ends of each test section and will be inspected by NDE. NDE documentation shall be retained to support acceptability of the welds. The foreman shall inspect all connections and hoses prior to filling the section. Prior to filling the pipeline, the fill line shall be leak tested for a minimum of 5min at 3,450kPa (- 500psi). To ensure a consistent fill Surerus will monitor and control pressure at the section end during fill. A pre-pack of compressed air will be established to offset the head pressure due to the water column during the line fill; this backpressure will be maintained throughout the fill at a pressure corresponding to the anticipated water pressure according to the elevation profile. The backpressure is anticipated to vary between 345 to 1,250Kpa (-50 to 180psi) throughout the line fill process. A single medium density pig will be pre-loaded into the test head and will be driven through the pipeline by the rate of the fluid insertion. Water shall be pumped from the Alameda Reservoir near the HOD exit location and transferred via fill line to the section fill points at KP35+500. Enbridge shall be responsible for obtaining all required water withdrawal permits. Water shall be left in the pipeline at a pressure of approximately 25% of the maximum test pressure during a stabilization period to ensure that a consistent temperature is achieved. During the line fill process fluid samples shall be obtained by Enbridge Representatives and submitted for analysis as required. The filling operation shall be continuous to prevent air ingress. 4.3 Pressurize and test the section. Before pressurizing the section beyond a pressure of 2,760kPa, all work crews will be notified and removed from the vicinity of the test section . All pipe and fill connections shall be checked for leaks and these test areas shall be maintained as "off-limits" to non-essential personnel. Pressure will be increased to 2,760kPa and all visible piping inspected for leaks. Upon completion of the leak checl<, the line and manifold will be bled off, an inline check valve installed on the squeeze line and the squeeze pump connected to the line. Squeeze pressure will be initiated through a 1" or 2· line rated to 38,00QI(Pa (-5,500psi) ; pressure shall be increased in stages as indicated in the Hydrostatic Test Record Worksheets. 5. Test Stages The pipeline shall be tested in the following stages: e Leak check e Strength test (including yield plot where required) e Leal< test DATE REVISION PAGE 20'12- "11 -09 2 5 of 8 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 6 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN 5.1. Leak Check The first stage involves a leal< check at approximately 2, 7601<Pa to allow visual inspection of exposed piping and fittings included in the test section. Any pressure lost during this period must be explained to the satisfaction of the Company's testing supervisor prior to pressurizing to the target strength test pressure 5.2. Strength Test Following satisfactory completion of the leak checl<, testing will continue by slowly raising the pressure to the strength test pressure as indicated in the attached Hydrotest Calculation Worksheets. The strength test will be held at a pressure greater than the minimum test pressure. 5.2.1 5.2.2 5.2.3 5.2.4 5.2.5 Yield plotting, if required, shall be undertaken as the section is pressurized during the strength test. Yield plotting shall commence at a pressure equivalent to 60% of the maximum anticipated test pressure . Yield plotting shall only be required where the expected maximum hoop stress in the test section during the strength test is greater than 100% SMYS of the pipe. Enbridge shall be responsible for completing all yield plots and associated documents. Pumping shall continue until the selected strength test pressure is achieved or, where a yield plot is required, the point where the yield plot deviates beyond the 0.2% offset line. The strength test will be held at a pressure greater than the minimum test pressure. After pumping has ceased, and the selected strength test pressure has been reached, the strength test will commence. The pressure at the highpoint shall match or exceed this minimum at both the start and the end of the test, and at no time during the test period shall the pressure at the high point drop below the required minimum. The minimum duration for the hold period on the strength test is four and a quarter (4.25) hours. 5.3. Lealt Test After successful completion of the strength test, a minimum four and a quarter (4.25) hour leal< test will be conducted. Pressure will be dropped to a level corresponding to the leal< test pressure indicated in the attached Hydrotest Calculation Sheets. 5.3.1 5.3.2 5.3.3 The minimum pressure at the high point shall be 110% of the intended maximum operating pressure. At the end of the leak test a hold period of two (2) hours is required where no drop in pressure is experienced. The test duration may be extended beyond the four (4) hour period to achieve these requirements. 6. Test Documentation Surerus will submit all required test doCLrmentation within the turnover package. Temperature and pressure readings shall be recorded as follows: DATE REVISION PAGE 2012-'1'1-09 2 6 of8 ____,__ Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN SURERUS - - - •PipellneltJt:.• • • • Appendix A - A3 Sureus Hydrostatic Test Plan Page 7 of 49 Every 5 minutes between 0-30 minutes Every 10 minutes between 30-60 minutes Every 15 minutes for the remainder of the test Records shall include the start and stop times for any pumping, pressunzrng, or depressurizing of the test section. A copy of the test worksheet shall be made available for review prior to commencement of the test. All documentation will be turned over to Enbridge upon completion of testing to facilitate completion of required Leave To Open applications. 7. Leak Detection During the leal< test, any drop in pressure which cannot be correlated to a change in temperature shall be considered a leak. If a leak is suspected Surerus shall notify the Enbridge Representative and further pressurizing of the pipeline shall be halted until the source of the leak can be determined. Should any failure require repair, the line pressure shall be reduced to static pressure, the section dewatered, and the repair completed. 8. Depressurizing Upon the completion of a successful test, the pipeline w ill be depressurized slowly until the energy has reached an acceptable level prior to dewatering. The line will be depressurized into a pressure trucl< rated in excess of the maximum test pressure. Under no circumstances will valves be moved to the full open position to initiate depressurizing. The maximum depressurizing rate shall be equal to 200kPa/min. 9. Dewatering 9.1 All test water shall be disposed of in accordance with applicable regulations. 9.2 Upon successful testing of the sections the water will be discharged by means of a controlled land release in the vicinity of KP 35+500 near the water source. Water discharge volumes correspond to the section volumes. Enbridge shall secure all necessary permits for the discharge of hydrostatic test water. 9.3 Lines will be securely fastened and supported to prevent "whipping" or sudden releases of energy during the dewater or water transfer process. 9.4 A high density coated poly pig or bi-directional multi-disc pig propelled by compressed air will be used for dewatering. 9.5 Surerus w ill utilize additional pigs for de-watering if insufficient volumes of f luid are received at the release point of the section during initial de-water activities. 9.6 Additional runs will be performed as requ ired to ensure that the section is sufficiently de-watered. 9.7 No conditioners, chemicals or additives will be used to alter t he natural quality of the water at any point during the hydro test 9.8 Water shall be discharged into a diffuser and then directed through filter cloth to prevent erosion at the dewater location. 1 0. Pig/Cleaning Runs '10.1 Following completion of testing of each section, multiple dewatering runs shall be completed to remove any free-standing water within the pipe section satisfaction of the Enbridge Representative. DATE REVISION PAGE to the 20'12-'11-09 2 7 of 8 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 8 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN 11 . Caliper Pigging 11 .1 Following completion of pipeline drying each section shall be inspected with an electronic caliper pig supplied by an approved Enbridge sub-contractor. 1'1.2 Caliper pigging shall be completed in accordance with relevant Enbridge specifications. 1'1.3 An inhibitor shall be added to the line following completion of the caliper runs as directed by Enbridge representatives 12. fest Personnel Surerus will utilize the fol lowing l<ey personnel to complete pressure testing activities: Telford Advent Superintendent Surerus Pipeline Inc. Chris Fleming Project Engineer Surerus Pipeline Inc. Ken Hawthorne Test Foreman Surerus Pipeline Inc. Zoran Ponjevic Test Consultant Prepense Specialty Testing 13. SubDContractors e • Transfer and fill pumps along with all interconnecting piping between the pumps , tanks, and test heads shall be provided by Central Water and Equipment Services based in Saskatoon, SK. Electronic caliper pigging shall be completed by an approved Enbridge vendor to be determined prior to caliper pigging activities. 14. Attachments 1. 2. 3. 4. Hydrostatic Test Calculation Worksheets Hydrostatic Test Pressure Profiles Section 1 and Section 2 Water Withdrawal Sketch Pump Performance Curves 15. Reference Documents 1. 2. 3. 4. 5. CPCS-SPEC-HYDR0-005 Rev. 1 Pipeline Hydrostatic Testing CPCS-SPEC-PIPELINE-001 Rev. 1 - Pipeline Construction CPCS-SPEC-PCCT-007 Rev. 1 -Post Construction Caliper Tool. Bakken Pipeline Project Canada Alignment Sheets - D-WM057-05-500-001-A GSA Z662-(Latest Edition) - Oil and Gas Pipeline Systems; Canadian Standards Association 6. Pipeline Act and Regulation - Government of Saskatchewan (Latest Edition) 7. J..\ENV - Code of Practice for TemporanJ Diversion of Water for Hydrostatic Testing of Pipelines 8. AENV - Code of Practice for the Release of Hydrostatic Tes·( Water from the Hydrostatic Testing of Pe·troleum Liquid and Gas Pipelines. 9. DFO - Freshwater Intake End-of-Pipe Fish Screen Guidelines. DATE REVISION PAGE 20•12-1·!-09 2 8 of 8 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 9 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 1 = Hydrostatic Test Calculation Sheets Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 10 of 49 HYDROSTATIC TEST CALCULATION WORKS HEET PROJECT NAME: PROJECT#: TEST DATE: TEST#: SECTION#: jEnbrldga Bakken Mainline 11 202 FILL FLUID SOURCE: IAiameda Reservo1r DEWATER LOCATION:I35+500 PIPELINE DATA PIPE OD (D)= 406.4 (mm) WALL THICKN ESS (I)= 7.14 (mm) PIPE GRADE (S) = (MPa) 414 (kPa) MOP= 9,928 100% SMYS = 14,547 (kPa) 80% SMYS 11 ,638 (kPa) 15,711 (kPa) 108% SMYS 110% SMYS 16,002 (kPa) SECTION LENGTH (m) 35,406 (m} 4,275,675 (litres) SECTION VOLU ME (litres) 0.2% OFFSET (lilres) (litres) 8,551 = = = = = = ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) 578.00 HIGH POINT (HP) = 589.00 LOW POINT (LP} = 544.00 WEST TEST POINT (WTP) = 587.00 = YES -16.00 0.281 60 1,440 2,110 1,688 2,279 2,321 116,161 940,536 1,881 --=- ,_. ~ WEST END I{ .P. LOCATION EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (in) (in) (ksi) (psig) (psig) (psig) (psig) (psig) (ft) (gal) (gal) 26,872 54 (bbls) (bbls) 11 .0 34.0 45.0 2.0 43.0 (m) (m) (m) (m) (m) 108 333 441 20 421 12,759 12,651 13,092 12,671 (I<Pa) (I<Pa) (kPa) (kPa) '1,850 '1,835 1,899 1,838 (psig) (psig) (psig) (psig) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = 14,655 '14,547 14,988 14,567 (kPa) (kPa) (kPa) (kPa) 2,125 2,1 '10 2, 174 2,113 (psig) (psig) (psig) (psig) I 87.7% 87.0% 90.0% 87.1% 100.7% 100.0% 103.0% 100.1% (% SMYS) (o/oSMYS) I (% SMYS) (o/oSMYS) 147.6% 146.5% '151.0% 146.7% CUSHION=! 200 (psig) (psig) (psig) (psig) 102:1% 101 .4% 104.4% 101 .5% (% SMYS) (% SMYS) (% SMYS) (% SMYS) ('110% of MOP at High Point) 11,329 (I<Pa) 1,643 '11,221 (I<Pa) 1,627 '1'1,662 (I<Pa) '1,691 '11 ,2<!-0 (I<Pa) '1,630 (psig) (psig) (psig) (psig) 77.9% 77.1% 80.2% 77.3% CUSHION=! (% SMYS) (% SMYS) (o/o SMYS) (o/oSMYS) = = = CALCULATED BY (Signature 11 Full Name): CHECKED BY CLIENT (Signature 8: Full Name): (kPa) (kPa) (I<Pa) (I<Pa) (I<Pa) (%SMYS) (% SMYS) I(% SMYS) (% SMYS) COMMENCEMENT 'STRENGTH TEST' PRESSURE (LI MIT IS 108% SMYS) (The Lesser oi Min. Strength Test Pressure+ a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 14,855 (I<Pa) 2,15.!!· HIGH POINT (HP) 14,747 (kPa) 2,139 LOW POINT (LP) = 15,188 (I<Pa) 2,203 14,767 (kPa) WEST TEST POINT{WTP}_= 2,142 MINIMUM 'LEAl< TEST' PRESSURE EAST TEST POINT (ETP) HIGH POINT (HP) = LOW POINT (LP) WEST TEST POINT (WTP) = 0+094 35+500 EAST (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) LOW POINT (LP) = WEST TEST POINT (WTP) = = ~ _.,_ HP - ETP= ETP- LP = HP - LP = HP - WTP = WTP-LP = (m) (m) (m) (m) November 18,2012 1 1 Chris Flem1ng I DATE: 300 114.1% 113.0% 117.5% '113.2% (%MOP) (%MOP) I (%MOP) (% MOP) j(kPa) i(I<Pa) (%MOP) I<% MOP) (%MOP) (%MOP) 2012-11-09 DATE: 16/11/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal SURERUS Appendix A - A3 Sureus Hydrostatic Test Plan Page 11 of 49 HYDROSTATIC TEST CALCULATION WORKSHEET ~ne fnc. • PROJECT NAME: PROJECT#: I En bridge Bakken Mainline 11202 FILL FLUID SOURCE:IAiameda Reservoir DEWATER LOCATION: 135+500 PIPELINE DATA PIPE OD (D) = 406.4 (mm) WALL THICKNESS (I) = (mm) 7.14 PIPE GRADE (S) = (MPa) 414 (kPa) MOP= 9,928 100% SMYS = 14,547 (kPa) 80% SMYS = 11 ,638 (kPa) 108% SMYS= 15,71 1 (I<Pa) 110% SMYS = 16,002 (I<Pa) SECTION LENGTH (m) = 87,771 (m) SECTION VOLUME (lilres) = 10,599,342 (litres) 0.2% OFFSET (litres) = 2'1 ,1 99 (litres) ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) = 483.00 HIGH POINT (HP) = 590.00 LOW POINT (LP) = 470.00 WEST TEST POINT (WTP) = 590.00 ~ ~~ ~----:-· -=; 16.00 0.281 60 1,440 2,11 0 1,688 2,279 2,321 287,963 2,331,576 4,663 TEST DATE: TEST#: SECTION#: ' WEST END K.P. LOCATION EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (in) (in) (ksi) (psig) (psig) (psig) (psig) (psi g) (ft) (gal) (gal) 66,616 133 (bbls) (bbls) 107.0 13.0 120.0 0.0 120.0 (m) (m) (m) (m) (m) 1,049 127 1. 176 0 1,176 12,965 11 ,916 '13,092 1'1.916 (kPa) (kPa) (kPa) (I<Pa) 1,880 1,728 1,899 1,728 (psig) (psig) (psig) (psig) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POI NT (LP) = WEST TEST POINT (WTP) = '14,852 13,803 14,979 '13,803 (kPa) (I<Pa) (kPa) (I<Pa) 2,1 54 2,002 2,'172 2,002 (psi g) (psig) (psig) (psig) I 89.1% 81.9% 90.0% 81.9% 102.1% 94.9% 103.0% 94.9% I (% SMYS) (% SMYS) (% SMYS) (% SMYS) I (psig) (psig) (psig) (psig) 103.8% 96.6% 104.7% 96.6% (%SMYS) (% SMYS) (%SMYS) (% SMYS) (11 0% of MOP at High Point) 1,779 12,269 (kPa) 1,627 11,221 (I<Pa) '1,798 12,397 (I<Pa) 1'1,22'1 (I<Pa) '1,627 (psig) (psig) (pslg) (psig) 84.3% 77. 1% 85.2% 77 .'1% CUSHION = ! (% SMYS) (%SMYS) (% SMYS) (% SMYS) CALCULATED BY (Signature & Full Name): CHECf<ED BY CLIENT (Signature 13. Full Name): (kPa) (kPa) (I<Pa) (kPa) (kPa) (%SMYS) (% SMYS) (% SMYS) (%SMYS) COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) (The Lesser of Min. Strength Test Pressure., a Cushion, and '108% SMYS) EAST TEST POINT (ETP) = 2, 190 15,102 (I<Pa) 14,053 (kPa) 2,038 HIGH POINT (HP) = LOW POINT (LP) = 2,209 15,229 (kPa) 14·,053 (kPa) 2,038 WEST TEST POINT {VVTP) = MINIMUM 'LEAK TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (l-IP) = LOW POINT (LP) = WEST TEST POINT (WTP) = 35+500 123+271 WEST (Yes, if Maximum Strength Test Pressure at Low Point > 100% SMYS) YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = YES - 2 ~.,.- HP- ETP = ETP-LP = HP · LP = HP - INTP = VI!TP · LP = (m) (m) (m) (m) November 18, 2012 1 Chris Fleming CUSHION =I I DATE: 149.6% 139.0% 150.9% 139.0% 250 300 '123.6% 113.0% '124.9% 113.0% (%MOP) MOP) I (% (% MOP) (% MOP) l<kPa) I(I<Pa) (%MOP) I<% MOP) (%1'v10P) (%MOP) 2012-11-09 DATE: 16/11/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 12 of 49 SURERUS ---•Pf t»ffM HYDROSTATIC TEST CALCULATION WORKSHEET Inc.• PROJECT NAME: PROJECT#: I Enbrldge Bakken Mainline 11202 FILL FLUID SOURCE: ITanker Truck DEWATER LOCATION: I0+094 PIPELINE DATA PIPE OD (D) = 406.4 (mm) WALL THICKNESS (t) = 7.92 (mm) PIPE GRADE (S) = (MPa) 414 MOP= (I<Pa) 9,928 100% SMYS= 16,136 (kPa) 80% SMYS = 12,909 (kPa) 108% SMYS = 17,427 (kPa) 110% SMYS = 17,750 (kPa) SECTION LENGTH (m) = 94 (m) SECTION VOLUME (litres) = 11 ,261 (litres) 0.2% OFFSET (litres) = (litres) 23 ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) = 587.00 HIGH POINT (HP) = 587.00 LOW POINT (LP) = 587.00 WEST TEST POINT (VVTP) = 587.00 16.00 0.312 60 1,440 2,340 1,872 2,528 2,574 308 2,477 5 TEST DATE: TEST#: SECTION#: 71 0 (bbls) (bbls) 0.0 0.0 0.0 0.0 0.0 (m) (m) (m) (m) (m) 0 0 0 0 0 14,523 14,523 14,523 14,523 (kPa) (kPa) (kPa) (kPa) 2,106 2,106 2, '106 2,106 (psig) (psig) (psig) (psig) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (VVTP) = 15,321 15,321 15,321 15,32'1 (I<Pa) (I(Pa) (I<Pa) (I<Pa) 2,222 2,222 2,222 2,222 (psi g) (psig) (psig) (psig) I 90.0% 90.0% 90.0% 90.0% 94.9% 94.9% 94.9% 94.9% (%SMYS) (% SMYS) I (% SMYS) (% SMYS) 154.3% 154.3% 154.3% 154.3% CUSHION " ! 300 (psig) (psig) (psig) (psig) 96.8% 96.8% 96.8% 96.8% (%SMYS) (% SMYS) (% SMYS) (%SMYS) (110% of MOP a·t High Poini) 11,221 (I<Pa) 1,627 '1 1,221 (I(Pa) 1,627 1'1,221 (I(Pa) '1,627 {I(Pa) '1,627 j-1 ,22'1 (psi g) (psig) (psig) (psig) 69.5% 69.5% 69.5% 69.5% CUSHION= ! (% SMYS) (% SMYS) I (% SMYS) (%SMYS) CALCULATED BY (Signature & Full Name): CI-IECI(ED BY CLIENT (Signaiure 1!: Full Name): (kPa) (I<Pa) (I(Pa) (kPa) (I<Pa) (% SMYS) (% SMYS) I (% SMYS) (% SMYS) COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) (The Lesser of Min. Strength Test Pressure,, a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 15,621 (kPa) 2,266 HIGH POINT (HP) = 15,621 (I<Pa) 2,266 LOW POINT (LP) = 15,621 (kPa) 2,266 WEST TEST POINT (WTP) = 15,621 (I<Pa) 2,266 MINIMUM 'LEAK TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = liVEST TEST POINT (WTP) = 0+094 0+000 WEST (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (VIJTP) = NO WEST END K.P. LOCATION EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (in) (in) (ksi) (psig) (psi g) (psig) (psig) (psig) (fl) (gal) (gal) HP - ETP = ETP- LP = HP- LP = HP -WTP = WTP· LP = (m) (m) (m) (m) November 18, 201 2 1 3 Chris Fleming DATE: 300 '1 13.0% 113.0% 1'13.0% '113.0% (%MOP) I (%MOP) (%MOP) (%MOP) I(I<Pa) I(I(Pa) (%MOP) MOP) (%MOP) (%MOP) I<% 2012-1 1-09 DATE: 16/ 11/ 201 2 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 13 of 49 HYDROSTATI C TEST CALCULATION WORKSHEET PROJECT NAME: PROJECT#: FILL FLUID SOURCE: I Tanker Truck DEWATER LOCATION: j 123+271 PIPELINE DATA (mm) PIPEOD (D) = 406.4 (mm) WALL THICKNESS (t) = 7.92 PIPE GRADE (S) = 414 (MPa) (kPa) MOP= 9,928 100% SMYS = 16,136 (I<Pa) 80% SMYS = 12,909 (kPa) 108% SMYS = 17,427 (kPa) "I"IO%SMYS= 17,750 (kPa) SECTION LENGTH (m) = 74 (m) SECTION VOLUME (litres) = (litres) 8,865 0.2% OFFSET (litres) = 18 (litres) ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) = 587.00 HIGH POINT (HP) = 587.00 LOW POINT (LP) = 587.00 WEST TEST POINT (WTP) = 587.00 -= ~ -.. ~ 16.00 0.312 60 1.440 2,340 1,872 2,528 2,574 243 1,950 4 (m) (m) (m) (m) WEST END K.P. LOCATION EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (in) (in) (ksi) (psig) (psig) (psig) (psig) (psig) 56 0 (bbls) (bbls) HP - ETP= ETP· LP = HP · LP = HP - WTP= WTP - LP = 0.0 0.0 0.0 0.0 0.0 (m) (m) (m) (m) (m) 0 0 0 0 0 2,106 2, 106 2,106 2.106 (psig) (psig) (psig) (psig) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = 15,321 15,321 15,321 15,321 (kPa) (kPa) (I<Pa) (kPa) 2,222 2,222 2,222 2,222 (psig) (psig) (psig) (psig) I 90.0% 90.0% 90.0% 90.0% (%SMYS) (%SMYS) I (%SMYS) (% SMYS) 94.9% 94.9% 94.9% 94.9% (% SMYS) (% SMYS) (%SMYS) (% SMYS) I COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) (The Lesser of Min. Strength Test Pressure·:· a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 15,621 (I<Pa) 2,266 HIGH POINT (HP) = 15,621 (I;Pa) 2,266 LOW POINT (LP) = 15,621 (I<Pa) 2,266 WEST TEST POI NT (WTP) = 15,621 (kPa) 2,266 (psig) (psig) (psig) (psig) 96.8% 96.8% 96.8% 96.8% (% SMYS) (% SMYS) (% SMYS) (% SMYS) (110% of MOP at High Point) "1"1 ,22'1 (I;Pa) 1,627 '1,627 11.221 (I;Pa) (I;Pa) 1"1,221 1,627 11 ,221 (I;Pa) 1.627 (psig) (psig) (psig) (psig) 69.5% 69.5% 69.5% 69.5% CUSHION= ! (% SMYS) (% SMYS) (% SMYS) (% SMYS) CHECI<ED BY CLI ENT (Signature lJ. Full Name): (I<Pa) (I<Pa) (I<Pa) (I<Pa) (I<Pa) (Yes, if Maximum Strength Test Pressure at Low Point > 100% SMYS) (kPa) (I<Pa) (kPa) (kPa) CALCULATED BY (Signature lJ, Full Nama): 123+271 123+345 WEST (ft) (gal) (gal) 14,523 14,523 14,523 14,523 MINIMUM 'LEAl{ TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POI NT (WTP) = 1 4 ~ YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (H P) = LOW POINT (LP) = WEST TEST POINT (WTP) = NO November 18, 2012 TEST DATE: TEST #: SECTION#: 1Enbrldge Bakl(en Mainline 11202 Chris Fleming CUSHION= ! I DATE: 154.3% 154.3% 154.3% 154.3% 300 300 113.0% 11 3.0% 113.0% '11 3.0% (% MOP) I (%MOP) (%MOP) (%MOP) I (I<Pa) j(I<Pa) (% MOP) I<% MOP) (%MOP) (%1\JlOP) 2012-11· 09 DATE: 16/11/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ~URERUS .lillliilliliiPiptl//ne Inc.• Appendix A - A3 Sureus Hydrostatic Test Plan Page 14 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 2- Hydrostatic Test Pressure Profiles ,+500 TO 0+000 Bakken Mainlir SURERUS - •s 16 HYDROSTATIC TEST PLAN ELEVATION PROFILES Pfpeloe·.b:.:• 600 1L!·,300 I<Pa j i' I ' 14.,250 kPa; 14,244 kPa £ High t>oint, 3+400, 589 -v~ ~A I J\1...,./~ v 530 ! I I '' I '1\- 14,200 kPa I I I I 14,150 kPa j I' II I 14,100 l<Pa! i I I I Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal TEST SECTION 1L!.,050 kPa! I 14,000 I<Pa! i ' I 560 \ I i II 13,950 kPa; I I I 13,900 I<Pa1 i 13,850 l<Pa; j' I 1540 ~ 0 ,_, I I -:- ~ 0 ci -;~· ~· -:- 0 1./'l 0 0 0 .--! 0 ci 0 ..... -:- 1./'l ~· 0 13,750 I<Pa 0 0 ci ci ci .-i ~· + .-i 0 + 0 N 0 1./'l N 0 + 0 m 0 ci 0 ~: -:m 1./'l 1205- Enbridge Bakken - Hydrotest Elevation Points- 2012-10-13 Appendix A - A3 Sureus Hydrostatic Test Plan Page 15 of 49 j 13,800 kPa: Low Point, 34+400, 544 13,803 kPa ,.,5-:-500 TO 123+850 Bakken Mainlt . ·- 1\lPS 16 HYDROSTATIC TEST PLAN SURERUS me.. ELEVATION PROFILES ·P1De/IM 15,200 kPai 620 i 600 ! High Wo int, 38-:-500, 590 14,979 kPa isoo j \ 15,000 kPa ! 1 I : 14,800 kPa I~ I I ! 560 I 14,600 kPa: ·sL!.O 14-,400 kPa !' js2o 14,200 kPai i isoo ! ~ 13,803 kPa I low Po;ot, 123•300, 470 ~ 14,000 kPa : 13,800 kPa l i '' L~. 60 0 0 0 c:i 0 !.{] U) !.{] .;; 2; j:, ("() ~- ':::i" c:i 0 0 0 ~ 0 0 0 0 0 Lfl Lfl !.{] 0 c5 Lfl 0 .;; 1./') 0 g 0 0 0 Lfl .;. 1./') '-!:) 0 0 0 0 0 0 0 0 0 0 0 0 !.{] !.{] Lfl L{) !.{] !.{] 2; + 1./') 2; 00 00 0 + 0 r-... 0 + IJ'l 1..... 0 0 0 "' 0 + 1./') "' 0 0 0 0 0 0 0 0 0 0 !.{] 1./') 1./') Lfl !.{] ,_, N 0 + 0 0 .-l 0 + 1./') 0 .-l 0 + 0 .-l ,...., 0 + 1./') ,...., 13,600 kPa I 1 0 + 0 '""' 1205 - En bridge Bakken - Hydrotest Elevat ion Points- 2012-10-13 Appendix A - A3 Sureus Hydrostatic Test Plan Page 16 of 49 1480 i Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal lEST SECTION ... Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 17 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 3 = Water Withdrawal Sketch Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal BAI<t<EN MAINLINE NPS 16 " DETAILED DRAW ING OF TEM PORARY WATER INTAKE FOR HVDROTEST A LL DIMENSIONS IN METERS DATE PREPARED: 12/07/2012 PREPA RED BY: JZ PlAN V~EW SCALf 1:2000 i!t WARNING SIGN ALAMEDA FENCE RESERVOIR BAI<I<EN PIPELINE 16" INTA KE SCREEN T ANK WARNING SIGN I 35 15 I I PIPE 168.33 MM 110 PROFilE VI!EW SCALE 1:2000 HORIZONTAL 1: 500 VERTICAl TAN I( 4 1 Appendix A - A3 Sureus Hydrostatic Test Plan Page 18 of 49 12 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 19 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 4 ~ Pump Performance Curves _?/),? 25 @ ~ Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal 140 . ~ 420 20 tu UJ 15 LLI ' " 120 . 10 ~ CL 5 :z: 360 /, ~ (../) ~ 100 . . . 80 . . (../) = u..J 1-- ::::E = <C LU = _J <C 1-- ~ 1-- UJ w LL I 240 0 u..J I 300 • 60 ~ <C LU :r: I : <i 180 5 ~ 1-- 40~ 120 1.1£ ~ ' 20 . :: 0 v 60 0 1600 2400 4000 3200 4800 5600 FLDWRATE U. S.GALLDNS PER MINUTE u u u a u u u a u a u a u s 1 a u a a s a 1 1 a u u o 1 u a u a u u u ' 0 200 400 600 f) Plf~~~fm'!aEfJl~f:. 800 1000 1200 6400 8000 8800 n u 1 u s B 1 1 a u a u a u o 1400 FLDWRATE CUBIC METERS PER HOUR 7200 1600 1800 2000 MODEL: PP 108Sl 7 IMPELLER OIA . 17 .5" SIZE : 10" SOLIDS SIZE : 3 .5" X 8" -- OWG NO. A71 6SHQNI REVISION: 000 DRAWN BY: ESW DATE: 4/ 2/201 2 Appendix A - A3 Sureus Hydrostatic Test Plan Page 20 of 49 800 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal NOTES : HEADAND EFFICIENCY SHOWN REFLECTLOSSES DUE TO NON-RETURN VALVE, OPENCLEARANCEWEAR-RINGS AND VACUUM PUMP POWER. 225 700 200 600 !75 (./) !50 . ~ L.1J 1L.1J ::;;::: I 125 1- L.1J L.1J L.L I 0 <( :::r: <( L.1J lOO - 1- 11- _.l <( 5 300 _.l <( 0 400 L.1J 0 :::r: 500 75 200 I 50 25 !00 0- 0 !200 800 !600 2000 2400 2800 3200 3600 4000 4400 900 1000 I FLOWRATE U. S.GALLDNS PER MINUTE u I 0 !00 200 300 400 ' 600 500 u 700 BOO FLDWRATE CUBI C M ETERS PER HOUR • p IPCJtL'tcfm'!o~{Jl:Jt:. MODEL: PPB6C21 SIZE: 8" X 6 11 IMPELLER DIA. 21'0" SOLIDS SIZE: 1.s// OWG NO . 078l7HQNl REVISION : 000 DRAWN BY: ESW DATE: 412120 12 Appendix A - A3 Sureus Hydrostatic Test Plan Page 21 of 49 400 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 22 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 1 - Hydrostatic Test Calculation Sheets Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 23 of 49 ____ ,.,_Inc.• SURERUS HYDROSTATIC TEST CALCULATION WORKSHEET PROJECT NAME: PROJECT#: I En bridge Bakken Mainline 11202 TEST DATE : TEST#: SECTION#: November 1, 2012 1 1 FILL FLUID SOURCE:IAiameda Reservoir DEWATER LOCATION : I35+500 PIPELINE DATA PIPEOD (D)= 406.4 WALL THICKNESS (t) = 7.14 PIPE GRADE (S) = 414 MOP= 9,928 100% SMYS = 80% SMYS = 108% SMYS = 110% SMYS = SECTION LENGTH (m) = SECTION VOLUME (litres) = 0.2% OFFSET (litres) = (mm) (mm) (MPa) (kPa) 14,547 (kPa) 11 ,638 (kPa) (kPa) 15,711 16,002 (kPa) 35,400 (m) 4 ,274,951 (Iiires) 8,550 (litres) ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) = 578.00 HIGH POINT (HP) = 589.00 LOW POINT (LP) = 544.00 WEST TEST POINT {WTP) = 587.00 YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT {WTP) NO 60 1,440 2,110 1,688 2,279 2,321 116,142 940,376 1,881 EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (ft) (gal) (gal) 26.868 54 HP- ETP = ETP- LP = (m) (m) (m) (m) 11 .0 34.0 45.0 2.0 43.0 HP - LP = HP - WfP = WfP - LP = 1,850 1,835 1,899 1,838 (psi g) (psig) (psi g) (psi g) 13,911 13,803 14,244 (kPa) (kPa) (kPa) (kPa) 2,018 2,002 2,066 2,005 (psig) (psig) (psig) (psi g) I 87.7% 87.0% 90.0% 87.1% 95.6% 94.9% 97.9% 95.0% COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) (The Lesser of Min. Strength Test Pressure + a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 14,211 (kPa) 2,061 HIGH POINT (HP) = 14,103 (kPa) 2,045 LOW POINT (LP) = 14,544 (kPa) 2,109 WEST TEST POINT {WTP) = 14,123 (kPa) 2,048 (psig) (psig) (psig) (psig) MINIMUM 'LEAK TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = (psig) (psig) (psig) (psi g) (110% of M OP at High Point) (kPa) 1,643 11 .329 11,221 (kPa) 1,627 11.662 (kPa) 1,691 11 ,240 (kPa) 1,630 CALCULATED BY (Signature & Full Name): CHECKED BY CLIENT (Signature & Full Name): 0+100 35+500 WEST (bbls) (bbls) (m) (m) (m) (m) (m) 108 333 441 20 421 (kPa) (kPa) (kPa) (kPa) (kPa) (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) (kPa) (kPa) (kPa) (kPa) 13,823 WEST END K.P. LOCATION (in) (in) (ksi) (psi g) (psig) (psig) (psig) (psig) 12,759 12,651 13,092 12,6 71 E MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT {WTP) = 16.00 0.281 Chris Fleming 97.7% 96.9% 100.0% 97.1% 77.9% 77.1% 80.2% 77.3% (% SMYS) (% SMYS) I(% SMYS) (% SMYS) (% SM YS) (%SMYS) I (% SMYS) (% SMYS) 140.1% 139.0% 143.5% 139.2% CUSHION= 300 (% (% (% (% (%MOP) I (% MOP) (%MOP) (%MOP) (kPa) SMYS) SMYS) SMYS) SMYS) CUSHION =I (% SMYS) (% SMYSJ I (% SMYS) (% SMYS) DATE: 300 114.1% 113.0% 117.5% 113.2% (kPa) (%MOP) I(% MO P) (% MOP) (%MOP) 2012-10- 13 DATE: 15/10/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 24 of 49 SURERUS ---•Pf p«<ne HYDROSTATIC TEST CALCULATION WORKSHEET Inc.• PROJECT NAME: PROJECT#: jEnbridge Bakken Mainline 11202 FILL FLUID SOURCE: IAlameda Reservoir DEWATER LOCATION:IJ5+500 PIPELINE DATA 406.4 (mm) PIPEOD (D)= WALL THICKNESS (t) = (mm) 7.14 PIPE GRADE (S) = 414 (MPa) MOP= 9,928 (kPa) 14,547 (kPa) 100% SMYS = 80% SMYS= 11,638 (kPa) 15,711 (kPa) 108% SMYS = 110% SMYS = 16,002 (kPa) SECTION LENGTH (m) = 88,350 (m) SECTION VOLUME (litres) = 10,669,263 (litres) 0.2% OFFSET (litres) = 21,339 (litres) ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) = 483.00 HIGH POINT (HP) = 590.00 470.00 LOW POINT (LP) = WEST TEST POINT (WTP) = 590.00 16.00 0.281 60 1,440 2,110 1,688 2,279 2,321 289,862 2,346,956 4,694 (m) (m) (m) (m) TEST DATE: TEST#: SECTION#: WEST END K.P. LOCATION EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (in) (in) (ksi) (psig) (psig) (psig) (psig) (psig) 67,056 134 (bbls) (bbls) HP- ETP = ETP- LP = HP - LP = HP - WTP = WTP - LP = 107.0 13.0 120.0 0.0 120.0 (m) (m) 1,049 127 1,176 0 1,176 (m) (m) (m) (kPa) (kPa) (kPa) (kPa) 1,880 1,728 1,899 1,728 (psig) (psig) (psig) (psi g) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = 14,852 13,803 14,979 13,803 (kPa) (kPa) (kPa) (kPa) 2,154 2,002 2,172 2,002 (psig) (psig) (psig) (psig) I 89.1% 81_9% 90.0% 81.9% 102.1% 94.9% 103.0% 94.9% (% SMYS) (% SMYS) I(% SMYS) (% SMYS) (% SMYS) (% SMYSJ I (% SMYS) (% SMYS) 149.6% 139.0% 150.9% 139.0% CUSHION= ! 250 COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) (The Lesser of Min. Strength Test Pressure+ a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 15,102 (kPa) 2,190 HIGH POINT (HP) = 14,053 (kPa) 2,038 LOW POINT (LP) = 2,209 15,229 (kPa) WEST TEST POINT (WTP) = 2,038 14,053 (kPa) (psig) (psig) (psig) (psig) 103.8% 96.6% 104.7% 96.6% (% SMYS) (% SMYS) (% SMYS) (% SMYS) (1 10% of MOP at High Point) 1,779 12,269 (kPa) (kPa) 1,627 11 ,221 12,397 (kPa) 1,798 1,627 11 ,221 (kPa) (psig) (psig) (psig) (psig) 84.3% 77.1% 85.2% 77.1% CUSHION =I (% SMYS) (% SMYSJ I (% SMYS) (% SMYS) CALCULATED BY (Signature & Full Name): CHECKED BY CLIENT (Signature & Full Name): (kPa) (kPa) (kPa) (kPa) (kPa) (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) 12,965 11,916 13,092 11 ,916 MINIMUM 'LEAK TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = 35+500 123+850 WEST (ft) (gal) (gal) YIELD PLOT NEEDED? YIELO PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = YES November 1, 2012 1 2 Chris Fleming DATE: 300 123.6% 113.0% 124.9% 113.0% (%MOP) I (%MOP) (% MOP) (%MOP) (kPa) (kPa) (%MOP) I<% MOP) (%MOP) (%MOP) 2012-10-13 DATE: 15/10/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 25 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 2 - Hydrostatic Test Pressure Profiles TEST SECTION ... .1S+SOO TO 0+000 Bakken MainlinE:: r11PS 16 HYDROSTATIC TEST PLAN SURERUS ELEVATION PROFILES ·~Inc.• I - •600 ; 14,300 kPa ! 14,244 kPa t r 14,250 kPa i i High Point, 3+400, 589 j 14,200 kPa · i 14,150 kPal 580 - - - - - - - - - - - - - - - - --- Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ~,....,.1 I 14,100 kPa ' 14,050 kPa , I i 14,000 kPai - -- - --- 1560 _ 1~ 13,900 kPa l I I ' 1 13,950 kPal .. ! 13,850 kPa 1 Low Point , 34+400, 544 13,803 kPa ;s4o 13,800 kPa i .l I ' ~-----------;-------------.~-------------,,---------------r---------------.---------------.- 0 0 0 ..... + 0 0 0 ..... + U'l 0 ci 0 ..... + 0 ..... 0 ci 0 ..... + U'l ..... 0 0 0 ..... + 0 N 0 0 ci ci ..... ..... 0 ..... 0 U'l M 0 + U'l N 0 + M 13,750 kPa 0 ci + 1205 - Enbridge Bakken- Hydrotest Elevation Points- 2012-10-13 Appendix A - A3 Sureus Hydrostatic Test Plan Page 26 of 49 i ! Bakken Mainlint . •PS 16 HYDROSTATIC TEST PLAN SURERUS ELEVATION PROFI LES ·P.(pefne Inc•• --, 15,200 kPa! !620 600 ·- - - ···- - -- - - - - - - - - - - · - - - - if , - - -- - -- ---- - - --· - l4,979 kPa &i 15,000 kPa l · -- - - ----------- High Point, 38+500, 590 : 580 -- -- . - , -- ... - 14,800 kPa l I -- \1 14,600 kPa ---- -··· --·------ - - ---- - - - - - -- - - - - - - - -- - - - -- - 14,400 kPa 560 ' 540 - - -- - - - - - - - -- - -·--· Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal TEST SECTION 2 · __,+500 TO 123+850 I I I I i' 14,200 kPa ! i520 I I I I isoo I -A-- 14,000 kPa! i 13,803 kPa Low Point, 123+300, 470 1 I I ' - - - -·' - 460 0 ci 0 Lf) + Lf) N'\ 0 0 ci Lf) Lf) Lf) Lf) 0 Lf) Lf) ci Lf) 0 q- + 0 ci ci 0 0 0 + q- 0 + Lf) 0 + - -, -,--- - 13,600 kPa 0 0 0 0 0 0 0 0 0 0 0 0 ci ci ci ci ci ci ci ci ci ci ci ci Lf) Lf) Lf) Lf) Lf) Lf) Lf) Lf) Lf) Lf) 0 Lf) + 0 1.0 0 Lf) + Lf) 1.0 0 + 0 r-... 0 + Lf) r-... 0 + 0 co 0 + Lf) co ---·-~- - - - 0 + en 0 ------ -· 0 + en Lf) - 0 + 0 0 ...... ---- - --- 0 + Lf) 0 ...... 0 + 0 ...... ...... 0 + Lf) ...... ...... 0 ci 0 Lf) + 0 N ...... - -- - - - 1205 - Enbridge Bakken - Hydrot est Elev at ion Point s- 2012-10-13 Appendix A - A3 Sureus Hydrostatic Test Plan Page 27 of 49 13,800 kPa ' 480 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ~URERUS .--Pipeline Inc.• Appendix A - A3 Sureus Hydrostatic Test Plan Page 28 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 3 - Water Withdrawal Sketch Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal BAKKEN MAINLINE NPS 16" DETAILED DRAWING OF TEMPORARY WATER INTAKE FOR HYDROTEST All DIMENSIONS IN METERS DATE PREPARED: 12/07/2012 PREPARED BY: JZ PLAN VIEW SCALE 1'2000 - I~ ' BAKKEN PIPELINE 16" "'"""''"'"'~"-,.------WARNING SIGN 7 ALAMEDA RESERVOIR EXISTING PIPELINES - · -- > <;i <.. __ FENCE INTAKE SCREEN TANK WARNING SIGN PIPE 168.33 MM II 35 15 110 PROFILE VIEW SCALE 1:2000 HORIZONTAl 1: 500 VERTICAL 12 4 1 Appendix A - A3 Sureus Hydrostatic Test Plan Page 29 of 49 TANK Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 30 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Attachment 4 - Pump Performance Curves ),v 25 "' 420 20 tu L.U IS LL 120 I 360 vh 10 ~ CL 5 :z (/) 100 - 300 ~ tl 1-- BO L.U L.U - Cl LL (./) 0<: L1.J I ~ L1.J :::E I = Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal 140 . . 240 S :t <!; L.U 60 :::r:: <i lBO <C L1.J = 1-- __J 1-- rJ Cl <C § 40 . 20 1./.L . : 60 ' 0 1600 BOO I 0 I I I I I 200 2400 I I I I I 400 3200 4000 4BOC 5600 FLDWRATE U.S. GALLDNS PER MINUTE I I I I I I 600 , ,PIPCJ/:ff£/f,{Jo~fJ/:J~ I I I I BOO I I I I I I I 1000 I I I I I I 1200 I I 1400 FLDWRATE CUBIC M ETERS PER HOUR 7200 6400 I I I I I I 1600 BODO I I I I IBOO I BBOO I I I I 2000 MODEL: PP108Sl7 IMPELLER DIA . 17. 5" SIZE: 10" SOLIDS SIZE: 3.5" X 8" DWG NO. A716SHQNI REVISION: 000 DRAW N BY: ESW DATE: 41212012 Appendix A - A3 Sureus Hydrostatic Test Plan Page 31 of 49 0 120 HEAD AND EFFICIENCY SHOWN REFLECT LOSSES DUE TO NON-RETURN VALVE, OPENCLEARANCE WEAR-RINGS AND VACUUM PUM P POWER. 225 700 200 . 500 175 (/)150 c::u L.lJ IL.lJ :::;::: I I I I00 - _j <l: b 300 <r: f- o400 <l: w _j fCl L.lJ L.lJ L.L I 125 Cl <r: L.lJ ..._500 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal NOTES: I- 75 200 I 50 25 0 400 BOO 1200 1500 2400 2000 3200 2000 FLOWRATE U.S.GALLONS PER MINUTE I 0 100 I I 200 300 T 400 500 500 700 3500 . 800 4000 4400 900 1000 FLOWRATE CUB IC METERS PER HOUR ~~ Plpc;//;L~/tlJo~fd!Jfo:. - MODEL : PP86C21 SIZE: 8" X 6" IMPELLER DIA . 21 '0" SOLIDS SIZE: 1.S" DWG NO. 07817HQNI REVISION : 000 DRAWN BY: ESW DATE: 41212012 Appendix A - A3 Sureus Hydrostatic Test Plan Page 32 of 49 0 100 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ------SURI!JJ Appendix A - A3 Sureus Hydrostatic Test Plan Page 33 of 49 HYDROSTATIC TEST PLAN Bakken Pipeline Expansion Project, HOD Sections NPS 16 Prepared by: Sur e r us Pipeline Inc. For: Enbridge Bakken L.P. 20'12-08-"14 0 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ------ Appendix A - A3 Sureus Hydrostatic Test Plan Page 34 of 49 Bakken NPS 16 HDD Sections HYDROSTATIC TEST PLAN SUR~&t~ 1. Scope This document was prepared for the hydrostatic pressure testing of the three (3) watercourse crossing sections on the Enbridge Bakken NPS 16 Pipeline Project planned for installation by Horizontal Directional Drill (HOD) methods. The three watercourse crossings include the Shepherd Creek, Moose Mountain Creek, and the Pipestone Creek. The hydrostatic test consists of a combined one (1) hour strength and leak test to verify the integrity of the pipeline following installation. 2. Safety 2.1. All personnel shall review and follow the Emergency Response Plan (ERP) developed specifically for this project. A copy ·of the ERP shall be available in each vehicle used on the project and additional copies shall be posted within the test building and other appropriate locations. 2.2. A pre-phase meeting will be held at the Surerus site office for all personnel involved in the hydrostatic test prior to commencement of the test to ensure that all personnel understand their respective duties. 2.3. Surerus will install warning signs and barricades to prevent access to the vicinity of the test area. Warning signs shall indicate "DANGER - High Pressure Pipeline Test" and "Restricted Access". 2.4. All Surerus personnel not involved in the testing shall be removed from the area while the pipeline section is under a pressure equal to or greater than 2,760kPa (400psi). 2.5. Test heads and pressurizing pipe shall be secured to limit movement. 2.6. All testing equipment including compressors, recorders, deadweights, etc. shall be set up a safe distance from the test section and/or test heads. 2.7. Surerus employees shal l inspect all hoses, lines, and connections for faults prior to pressurizing the lines . The Surerus Hydrotest Pre-test Checl{list will be completed to ensure that all components meet the required ratings. 2.8. Surerus personnel shall ensure pressure hoses/unions are rated to twice the maximum expected hydrotest pressures, and all safety lines are firmly attached and secured with whip checi\S. 2.9. An Enbridge representative will be on site for the duration of test activities. 3. Equipment Surerus shall supply the following equipment for completion of the hydrostatic test: Pumps including transfer/fill pump, and squeeze pump. Air compressors required for pipeline cleaning, pre-pack, and dewatering. 1-\11 pipeline pigs required for line fill and dewatering. All necessary valves, hoses, and fittings required to successfully complete the test. Calibrated temperature recorders, pressure recorders, and deadweights. Calibrated flow meter for preparation of the yield plot where applicable. Adequate lighting and light towers at all worl\ areas. 3. 1 Test Heads 3:1."1 Surerus shall supply Enbriclge approved i:est heads. DA l E REVISION PAGE 2012-08-1 <!· 0 2 of6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 35 of 49 ------SURiJWJ 3.1 .2 3.1 .3 Bakken NPS 16 HDD Sections HYDROSTATIC TEST PLAN Test head assemblies shall comply with all requirements of CSA-Z662 (latest edition). All documentation certifying test head compliance shall be available prior to commencement of testing . Test heads will be welded to the section and the welds will be inspected by NDE prior to filling the section. 3.2 Pumps 3.2.1 3.2.2 Surerus shall ensure that fill and squeeze pumps are adequately sized for the length and diameter of the section to be tested. Water for the hydrostatic test will be withdrawn from the approved water source (Shepherd's Creek) into tanker trucks and transferred to the test sections according to the details in section 4 below. 3.3 Instrumentatio n: 3.3.1 3.3.2 3.3.3 3.3.4 Surerus shall supply pressure and temperature recorders and dead weights to provide readings for the test data. The pressure shall be measured in psi or kPa, and the temperature measured in degrees Celsius. All test charts and reports, including the depressurizing of tested lines, will be included in the document turnover package. Instrumentation for the test shall be as follows: • Two dual pen temperature/pressure recorders and a digital dead weight will be located at the fill point. All measurement equipment shall be certified for accuracy not more than 30 days prior to commencement of the pressure test. The calibration certificates and current calibration reports shall be maintained on site and included in the turnover package following completion of the test. 4. Line Fill 4.1 Test Sections Section Length Volume Source Dewater Location 1 Shepherd's Creel{ 377m 44m 3 Shepherd's Creel( Transfer to Moose Min. Creek Section 2 Moose Mountain Creek 725m 85m 3 Shepherd's Creek HOD Section Landspread in SE1/4 27-4-2W2 3 Pipestone Creel( 211m 25m 3 Pipestone Creek Landspread in SW1/4 17-9-28WPM DATE REVISION PAGE 20'12-08- ·1t!· 0 3 of6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ------SURlBJI,! Appendix A - A3 Sureus Hydrostatic Test Plan Page 36 of 49 Bakken NPS 16 HDD Sections HYDROSTATIC TEST PLAN 4.2 Fill section Test heads will be welded onto the ends of each test section and will be inspected by NDE. NDE documentation shall be retained to support acceptability of the welds. The foreman shall inspect all connections and hoses prior to filling the section. Prior to filling the pipeline, the fill line shall be leak tested for a minimum of 5min at 3,450kPa (500psi). To ensure a consistent fill Surerus will monitor and control pressure at the section end during fill. Surerus does not anticipate that a pre-pack of the line is required due to the minimal elevation difference throughout the test section. A single medium density pig will be pre-loaded into the test head and will be driven through the pipeline by the rate of the fluid insertion. During the line fill process fluid samples shall be obtained by Enbridge Representatives and submitted for analysis as required. The filling operation shall be continuous to prevent air ingress. 4.3 Pressurize and test the section. Before pressurizing the section beyond a pressure of 2, 760kPa (400 psi), all worl< crews will be notified and removed from the vicinity of the test section. All pipe and fill connections shall be checked for leaks and these test areas shall be maintained as "off-limits" to non-essential personnel. Pressure will be increased to 2,760kPa (400psi) and all visible piping inspected for leaks. Upon completion of the leak check, the line and manifold will be bled off, an in line check valve installed on the squeeze line and the squeeze pump connected to the line. Squeeze pressure will be initiated through a 1" or 2" line rated to 5500psi; pressure shall be increased in stages as indicated in the Hydrostatic Test Record Worl<sheets. 5. Test Stages The pipeline shall be tested in a combined '1-hour strength and leak test. The pipe section will be available for visual inspection throughout the duration of the test. 5.1. Combined One-Hour Strength and Lealt Test The test involves a leal< check at approximately 2,760kPa (400psi) to allow visual inspection of e:<posed piping and fittings included in the test section. Following satisfactory completion of the leak checl<, testing will continue by slowly raising the pressure to the strength test pressure as indicated in the attached Hydrotest Calculation Worksheets . The strength test will be held at a pressure greater than the minimum test pressure. 5.2.1 The combined strength and leal< test will be held at a pressure greater than ths minimum test pressure. The test pressure shall be basecl upon the ma)<imum anticipated pressure the HDD section will e:<perience during the mainline pressure test. 5.2.2 After pumping has ceased, and the selected strength test pressure has been reachecl, the combined strength and leak test will commence. The pressure at the l1ighpoint shall matcl1 or exceecl this minimum at both the start and the encl ohhe DA l E REVISI ON PAGE 2012-08-"14 0 4 of6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ------SUR§!IJ. 5.2.3 Appendix A - A3 Sureus Hydrostatic Test Plan Page 37 of 49 Bakken NPS 16 HOD Sections HYDROSTATIC TEST PLAN test, and at no time during the test period shall the pressure at the high point drop below the required minimum . The minimum duration for the hold period on the combined strength and leal< test is one (1) hour. 6. Test Documentation Surerus will submit all requ ired test documentation within the turnover package. Temperature and pressure readings shall be recorded as follows: • • Every 5 minutes between 0-30 minutes Every 10 minutes between 30-60 minutes Records shall include the start and stop times for any pumping, pressunzmg, or depressurizing of the test section. A copy of the test worl<sheet shall be made available for review prior to commencement of the test. All documentation will be turned over to Enbridge upon completion of testing. 7. Leak Detection During the leak test, any drop in pressure which cannot be correlated to a change in temperature shall be considered a leak. If a leak is suspected Surerus shall notify the Enbridge Representative and further pressurizing of the pipeline shall be halted until the source of the leak can be determined. Should any failure require repair, the line pressure shall be reduced to zero, the section dewatered, and the repair completed. 8. Depressurizing Upon the completion of a successful test, the HOD section will be depressurized slowly until the energy has reached an acceptable level prior to dewatering. The line will be depressLirized into a pressure truck rated in excess of the maximum test pressure. Under no circumstances will valves be moved to the full open position to initiate depressurizing. 9. Dewatering 9. 'I All test water shall be disposed of in accordance with applicable regulations. 9.2 Upon successful testing of the sections, the water will be discharged by means of a controlled land release. Water discharge volumes correspond to the section volumes noted in section 4 of this document. Enbridge shall secure all necessary permits for the discharge of hydrostatic test water. 9.3 Lines will be securely fastened and supported to prevent "whipping" or sudden releases of energy during the dewater or water transfer process. 9.4 A high density coated poly pig or bi-directional multi-disc pig propelled by compressed air will be used for dewatering. 9.5 SLirerus will utilize additional pigs for de-watering if insufficient volumes of fluid are received at the release point of the section during initial de-water activities. 9.6 Additional runs will be performed as required to ensure that the section is sufficiently cle-watered. 9.7 No conditioners, chemicals or additives will be used to alter the natural quality of the vvater ai any point during the hydro test. DATE REVISION PAGE 20'12-08-14· 0 5 of 6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal ------SUR§!JJ Appendix A - A3 Sureus Hydrostatic Test Plan Page 38 of 49 Bakken NPS 16 HDD Sections HYDROSTATIC TEST PLAN 9.8 Water shall be discharged into a diffuser and then directed through filter cloth to prevent erosion at the dewater location. 12. Test Personnel Surerus will utilize the following key personnel to complete pressure testing activities: Telford Advent Superintendent Surerus Pipeline Inc. Julio Zavaleta Project Engineer Surerus Pipeline Inc. Ken Hawthorne Test Foreman Surerus Pipeline Inc. 13. Attachments 1. Hydrostatic Test Calculation Worl<sheets - HOD Sections. 14. Reference Documents 1. 2. 3. 4. 5. CPCS-SPEC-HYDR0-005 Rev. 1 Pipeline Hydrostatic Testing CPCS-SPEC-PIPELINE-001 Rev. 1 - Pipeline Construction CPCS-SPEC-PCCT-007 Rev. 1 - Post Construction Caliper Tool. Bakken Pipeline Project Canada Alignment Sheets - D-WM057-05-500-001-A CSA Z662-(Latest Edition) - Oil and Gas Pipeline Systems; Canadian Standards Association 6. Pipeline Act and Regulation - Government of Saskatchewan (Latest Edition) 7. AENV - Code of Practice for Temporary Diversion of Water for Hydrostatic Testing of Pipelines 8. AENV - Code of Practice for the Release of Hydrostatic Test Water from the Hydrostatic Testing of Petroleum Liquid and Gas Pipelines. 9. DFO - Freshwater Intake End-of-Pipe Fish Screen Guidelines. DAlE REVISION PAGE 2012-08-'14 0 6 of 6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 39 of 49 HYDROSTATIC TEST CALCULATION WORKSHEET PROJECT NAME: PROJECT#: TEST DATE: TEST#: SECTION#: IEnbrldge Bakken Pre-Test Shepherd's Creek 11202 FILL FLUID SOURCE: I Shepherd's Creek DEWATER LOCATION: 130+800 PIPELINE DATA I PIPE OD(D) = (mm) 406.4 WALL THICKNESS (t) = (mm) 10.31 PIPE GRADE (S) = (MPa) 414 MOP = (kPa) 9,928 100% SMYS = 21,006 (kPa) 80%SMYS = 16,804 (kPa) ~ W8% SMYS= 22,686 (I<Pa) 110% SMYS = 23,106 (kPa) SECTION LENGTH (m) = 377 (m) SECTION VOLUME (litres) = 44,067 (litres) 0.2% OFFSET (litres) = 88 (litres) 16.00 0.406 60 1,440 3,046 2,437 3,290 3,351 1,237 9,694 19 ELEVATION AND PRESSURE DIFFERENTIALS V EAST TEST POINT (ETP) = 570.00 (m) HIGH POINT (HP) = 570.00 (m) LOW POINT (LP) = 580.00 (m) WEST TEST POINT (WTP) = 580.00 (m) August 16,2012 1 HOD -SC WEST END K.P. LOCATION EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (in) (in) (ksl) (pslg) (psig) (psig) (pslg) (pslg) 30+490 30+861--.. 'WES:y-' ~ (ft) (gal) (gal) 277 1 (bbls) (bbls) HP - ETP = ETP- LP = HP- LP = HP- WTP = WTP - LP = 0.0 10.0 10.0 10.0 0.0 (m) (m) (m) (m) 0 98 98 98 0 (ml (I<Pa) (I<Pa) (I<Pa) (I<Pa) (kPa) ./h s p_NO~Y YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = (Yes. if Maximum Strength Test Pressure at Low Point> 100% SMYS) '18,807 18,807 18,905 18.905 (I<Pa) (I<Pa) (I<Pa) (I<Pa) 2,728 2,728 2,742 2,742 (psig) (psig) (psig) (psig) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINTJVVT_Pl = '15,24·0 '15,240 15,338 15,338 (I<Pa) (I<Pa) (kPa) (I<Pa) 2.210 2,210 2,225 2,225 (psig) (psig) (psig) (psig) ~ I 89.5% 89.5% 90.0% 90.0% 72.6% 72.6% 73.0% 73.0% I (% SMYS) (%SMYS) (%SMYS) (%SMYS) (% SMYS) (% SMYS) (% SMYS) (%SMYS) I COMMENCEMEN 1 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) (The Lesser or Min. Strength Tes~ Pressure,. a Cushion, and '108% SMYS) EAST TEST POINT (ETP) = '15,540 (I<Pa) 2,254 HIGH POINT (HP) = 15,5-'1·0 (I<Pa) 2,254 LOW POINT (LP) = 15,638 (I<Pa) 2,268 WEST TEST POINT (WTP) = 15,638 (I<Pa) 2,268 (psig) (psig) (psig) (psig) 74.0% 74.0% 74.4% R4% (% SMYS) (% SMYS) (% SMYS) (% SMYS) MINIMUM 'LEAK TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (l-IP) = LOW POINT (LP) = WEST TEST POINT (WTP) = (psig) (psig) (psig) (psig) 53.4% 53.4% 53.9% 53.9% CUSHION =I (%SMYS) (%SMYS) (%SMYS) (% SMYS) (110% of MOP a1High Point) '1'1,22'1 (I<Pa) 1,627 '1'1 .22'1 (I<Pa) 1,627 11.31 g (I<Pa) '1,642 '1 1,3'19 (I<Pa) '1,6~2 CALCUIJ\TED BY (Signature B, Full Name): CHECf<ED 8Y CLIENT (Signature 1!, Full Name): Chns Flem1ng CUSHION • I I DATE: 153.5% 153.5% 154.5% 154.5% 300 300 '113.0% '1'13.0% 114.0% 1'1-4.0% (%MOP) I (%MOP) (%MOP) (%MOP) l(i<Pa) l(kPa) (%MOP) I <% MOP) (%MOP) (%MOP) 2012-08-15 DATE: 15/08/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 40 of 49 HYDROSTATIC TEST CALCULATION WORKSHEET PROJECT NAME: PROJECT#: IEnbridge Bakken Pre-Test Alameda Res 11202 FILL FLUID SOURCE: !Moose Mountain Creek DEWATER LOCATION: 135+800 PIPELINE DATA (mm) PIPE OD(D) = 406.4 (mm) WALL THICKNESS (t) = 10.31 414 (MPa) PIPE GRADE (S) = (kPa) MOP= 9,928 100% SMYS = 21,006 (kPa) 80% SMYS= 16,804 (kPa) 108% SMYS = 22,686 (kPa) 23, 106 (kPa) 110% SMYS = (m) 725 SECTION LENGTH (m) = 84,744 (litres) SECTION VOLUME (litres) = (litres) 169 0.2% OFFSET (litres) = ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) = 580.00 HIGH POINT (HP) = 580.00 LOW POINT (LP) = 575.00 WEST TEST POINT (WTP) = 575.00 NO TEST DATE: TEST#: SECTION#: -,. 16.00 0.406 60 1,440 3,046 2,437 3,290 3,351 2,379 18,641 37 (m) (m) (m) (m) WEST END K.P. LOCATION EAST END K.P. LOCATION TEST POINT IS WEST OR EAST (in) (in) (ksi) (psig) (ps ig) (psig) (psig) (psig) 533 1 (bbls) (bbls) HP · ETP = ETP-LP = HP- LP = HP-WTP = WTP- LP = 0.0 5.0 5.0 5. 0 0.0 (m) (m) (m) (m) (m) 0 49 49 49 0 (kPa) (kPa) (kPa) (kPa) 2,735 2,735 2,742 2.742 (psig) (psig) (psig) (psig) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = 15,240 15,240 15,289 15,289 (kPa) (I<Pa) (I<Pa) (kPa) 2,210 2,210 2,2"17 2,217 (psig) (psig) (psig) (psig) I 89.8% 89.8% 90.0% 90.0% (% SMYS) (%SMYS) I(% SMYS) (% SMYS) 72.6% 72.6% 72 .8% 72.8% (% SMYS) (% SMYS) (% SMYS) (% SMYS) I COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 103% SMYS) (The Lesser of Min. Strength Test Pressure ·:- a Cushion, and 108% SMYS) 2,254 '15,540 (I<Pa) EAST TEST POINT (ETP) = 15,540 (I<Pa) 2,254 HIGH POINT (HP) = 2,261 15,589 (I<Pa) LOW POINT (LP) = 2,261 15,589 (I<Pa) WEST TEST POINT (WTP) = (psig) (psig) (psig) (psig) 74.0% 74.0% 74.2% 74.2% (% (% (% (% (11 0% of MOP at High Point) '1'1,22'1 (I<Pa} ·1,627 1,627 11 ,221 (I<Pa) '1,634 "11 ,270 (I<Pa) '1'1,270 (I<Pa) '1,63•!· (psig} (psig) (psig} (psig) 53 A% 53.4% 53.7% 53.7% CUSHION= I (% SMYS) (% SMYS) (% SMYS) (% SllilYS) CHECI~ED BY CLIENT (Signa·iure (!, Full Name): (kPa) (I<Pa) (I<Pa) (I<Pa) (kPa) (Yes, if Maximum Strength Test Pressure at Low Point > 100% SMYS) '18,856 18,856 18,905 18,905 CALCULATED BY (Signature 8. Full 1\lame): 35+048 35+773 WEST (ft) (gal) (gal) YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = MINIMUM 'LEAK TEST' PRESSURE EAST TEST POINT (ETP} = HIGH POINT (HP} = LOW POINT (LP) = WEST TEST POINT (WTP) = August 23, 2012 1 HDD- AR Chris Fleming CUSHION =I 153.5% 153.5% 154.0% 154.0% 300 (%MOP) I (%MOP) (%MOP) (%MOP) l(kPa) SMYS) SMYS) SMYS) SMYS) I 01-\TE: 300 "113.0% "113.0% 113.5% 1"13.5% I(I<Pa} (%MOP} IC%MOP) (%MOP) (%MOP} 2012-08-15 DATE: 15/08/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal SURERUS Appendix A - A3 Sureus Hydrostatic Test Plan Page 41 of 49 HYDROSTATIC TEST CALCULATION WORKSHEET ~lno.• PROJECT NAME: PROJECT#: IEnbrldge Bakl:en Pre-Test Pipestone Crk 11 202 FILL FLUID SOURCE: {Pipestone Creek DEWATER LOCATION:I123+500 PIPELINE DATA PIPE OD (D) = 406.4 (mm) WALL THICKNESS (t) = (mm) 10.31 PIPE GRADE (S) = (MPa) 41 4 MOP = 9,928 (kPa) 100% SMYS = 21,006 (I<Pa) 80% SMYS = 16,804 (kPa) 108% SMYS = 22,686 (kPa) 110% SMYS = 23,106 (kPa) SECTION LENGTH (m) = (m) 211 SECTION VOLUME (litres) = 24,663 (lilres) 49 (litres) 0.2% OFFSET (litres) = ELEVATION AND PRESSURE DIFFERENTIALS EAST TEST POINT (ETP) = 474.00 HIGH POINT (HP) = 474.00 LOW POINT (LP) = 470.00 WEST TEST POINT (WTP) = 470.00 NO 16.00 0.406 60 1,440 3,046 2,437 3,290 3,351 692 5,425 11 WEST END K.P. LOCATION EAST END K.P. LOCATION TEST POI NT IS WEST OR EAST (in) (in) (ksi) (pslg) (psig) (psig) (psig) (psig) (ft) (gal) (gal) HP - ETP= ETP- LP = HP- LP = HP - WTP = WTP - LP = (m) (m) (m) (m) 155 0 (bbls) (bbls) 0.0 4.0 4.0 4.0 0.0 (m) (m) (m) (m) (m) 0 39 39 39 0 18,866 18,866 18,905 18,905 (I<Pa) (I<Pa) (I<Pa) (I<Pa) 2,736 2,736 2,742 2,742 (psig) (psig) (psig) (psig) MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = 15,24·0 15,240 15,279 15,279 (I<Pa) (I<Pa) (I<Pa) (I<Pa) 2,210 2,210 2,216 2,216 (psig) (psig) (pslg) (psig) I 89 .8% 89.8% 90.0% 90.0% 72.6% 72.6% 72.7% 72.7% (% SMYS) (% SMYS) I (% SMYS) (% SMYS) 153.5% 153.5% 153.9% 153.9% CUSHION = I 300 (psig) (psig) (psig) {psig) 74.0% RO% 74.2% 74.2% (% (% (% (% (11 0% of MOP ai High Poini) 11 ,221 (I<Pa) '1,627 11,221 (I<Pa) 1,627 11,260 (I<Pa) 1,633 '11,260 (I<Pa) '1,633 (psig) (psig) {psig) (psig) 53.4% 53.4% 53.6% 53.6% CUSHION = I (% SMYS) (% SMYS) (% SMYS) (% SMYS) CHECI~ ED BY CLI ENT (Sigi1ature B. Full Name): (kPa) (kPa) (I<Pa) (I<Pa) (kPa) (% SMYS) (% SMYS) I (% SMYS) (% SMYS) COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) (Tha Lesser of Min. Strength Test Pressure-:- a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = '15,540 (kPa) 2,254 HIGH POINT (HP) = 15,540 (I<Pa) 2,254 LOW POINT (LP) = 15,579 (I<Pa) 2,259 WEST TEST POINT (WTP) = 15,579 (I<Pa) 2,259 CALCULATED BY (Signature 1!: Full Name): 123+289 123+500 WEST (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELD PLOT NEEDED? YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (WTP) = MINIMUM 'LEAK 1EST' PRESSURE EAST TEST POINT (ETP) = HIGH POINT (HP) = LOW POINT (LP) = WEST TEST POINT (\/IJTP) = September 1, 2012 1 HOD -PC TEST DATE: TEST#: SECTION#: Chris Flem1ng I (% MOP) (% MOP) (%MOP) (% MOP) l(i<Pa) SMYS) SMYS) SMYS) SMYS) I DATE: 300 113.0% 1'13.0% 113.4% '1 13.4% I(I<Pa) (%MOP) l (%MOP) (%MOP) (%MOP) 2012-08-15 DATE: lS/08/2012 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 42 of 49 Test Head Pre~ Test Hydrostatic Pressure Test Record S RERUS -U --l'lptl/lte lilt.• DATE 15/08/2012 FROM 0+000 TO 0+016 LENGTH SECTION# NPS 16 TH-001/006 16 m VOLUME 2.0 m3 TEST LOCATION .:. .F.;. ;:roc;;.b;.:.;ishc.;.;e"-r.. ;. Y; ;.;ar..: .d_ _ __ __ TEST STAGES 1) 2) 3) TIME Combined Leak/StrenQth kPa psi 2,760 400 1,160 8,000 19,300 2,799 Target Test Pressure(+/- 10psi) DEADWEIGHT PRESSURE (kPa) SURERUS REPRESENTATIVE HYDROSTATIC TEST PRESSURE RE CORD TEMPERATURE t;;t-<UUND (•C) (· c ) 1-\MCit:N I VOLUME (m3) NOTES CLI ENT REPRESENTATIVE Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 43 of 49 Test Head Pre-Test Hydrostatic Pressure Test Record FROM IO+OOO TO I0+016 LENGTH ! SECTION# NPS 16 TH-004/005 16m 2.0 m3 VOLUME TEST LOCATION . :. .F.:.: ro:.: ;b:.: :ishe:.:.: :.:. .r. :. .Y: .:ar.: .d_ _ __ __ TEST STAGES 1) 2) 3) TIME Combined Leak/StrenQth psi kPa 2,760 400 1,160 8,000 19,300 2,799 Target Test Pressure(+/- 10psi) DEADWEIGHT PRESSURE (kPal SURERUS REPRESENT.IHIVE HVDROSTA TIC TEST PRESSURE RECORD TEMPERATURE AMI:!It:N I GKOUNU (•C) ("C) VOLUME (m3} NOTES CLI ENT REPRESENTATIVE Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 44 of 49 I HYDROSTATIC TEST PLAN Bakken Pipeline Expansion Project, Mainline Pipeline NPS 16 Steelman Section Prepared by: Surerus Pipeline Inc. For: Enbridge Bakken L.Pm DATE REVISION 2012-1·1-16 0 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 45 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Steelman Section 1. Scope This document was prepared for the hydrostatic pressure testing of the En bridge Bakl<en Mainline NPS 16 Pipeline Project planned for construction in the summer/fall of 2012 between Steelman, SK and Cromer, MB. This test plan encompasses approximately 94m of pipe from the Steelman terminal eastbound; the test section end points are detailed within th e document below. The Steelman section of the pipeline will be tested above ground prior to installation due to access restrictions. The segment will be tested for a minimum period of one (1) hour to permit visual inspection of the pipeline during a combined strength and leak test utilizing a water/methanol mix to prevent freezing during testing. 2. Safety 2.1. All personnel shall review and follow the Emergency Response Plan (ERP) developed specifically for this project. A copy of the ERP shall be available in each vehicle used on the project. 2.2. A pre-phase meeting will be held at the Surerus site office for all personnel involved in the hydrostatic test prior to commencement of the test to ensure that all personnel understand their respective duties. 2.3. Surerus will install warning signs and barricades to prevent access to the vicinity of the test area. Warning signs shall indicate "DANGER - High Pressure Pipeline Test" and "Restricted Access". 2.4. All Surerus personnel not involved in the testing shall be removed from the area wh ile the pipeline section is under a pressure equal to or greater than 2,760kPa (-400psi) . 2.5. Test heads and pressurizing pipe shall be secured to limit movement. 2 .6. All testing equipment including compressors, recorders, deadweights, etc. shall be s et up a safe distance from the test section and/or test heads. 2.7. Surerus employees shall inspect all hoses, lines, and connections for faults prior to pressurizing the lines. The Surerus Hydrotest Pre-test Checklist will be completed to ensure that all components meet the required ratings. 2.8. Surerus personnel shall ensure pressure hoses/unions are rated to twice the maximum expected hydrotest pressures, and all safety lines are firmly attached and secured with whip checks. 2.9. Test crews shall review the requirements for working with methanol and wear appropriate PPE at all times w here the risk of exposure to the test fluid exists. 2.10. An En bridge representative will be on site for the duration of test activities. 3. Equipment Surerus shall supply the following equipment for completion of the hydrostatic test: Tanker trucks to transfer test fluid. Truck-mounted squeeze pump to complete pressure testing. Air compressor required for pipeline cleaning and dewatering. All pipeline pigs required for line fill and dewatering. All necessary valves, hoses, and fittings required to successfully complete the test. Calibrated temperature recorders, pressure recorders, and deadweights. Calibrated flow meter for preparation of the yield plot wl1ere applicable. Adequate lighting and light towers at all work areas. DATE REVISION PAGE 2012-1·1-"16 0 2 of6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 46 of 49 Bakken Mainline NPS 1 6 HYDROSTATIC TEST PLAN Steelman Section 3.1 Tes t Heads 3.1 .1 3.1 .2 3.1. 3 Surerus shall supply Enbridge approved test heads which comply with all requirements of relevant specifications including section 6.2 of CPSC-SPECHYDR0-005. Test l1ead assemblies shall comply with all requirements of CSA-Z662 (latest edition). All documentation certifying test head compliance shall be available for review prior to commencement of testing. Test heads will be welded to the section and the welds will be inspected by N DE prior to filling the section. 3.2 Pumps 3.2.1 Test fluid shall be transferred to the pipeline segment via tanker truck. A truck mounted squeeze pump shall be utilized to increase pressure up to the required test pressure. 3.3 Instrumentation : 3.3. 1 3. 3.2 3.3.3 3. 3.4 Surerus shall supply pressure and temperature recorders and dead weights to provide readings for the test data. The pressure shall be measured in kPa, and the temperature measured in degrees Celsius. All test charts and reports, including the depressurizing of tested lines, will be included in the document turnover package. Instrumentation for the test shall be as follows: e A dual pen temperature/pressure recorder and a digital deadweight will be located at the fill point. e An additional dual pen temperature/pressure recorder shall be located at the section end point. All measurement equipment shall be certified for accuracy not more than 30 days prior to commencement of the pressure test. The calibration certificates and current calibration reports shall be maintained on site and included in the turnover package following completion of the test. 4. Line Fill 4.1 Test Sections Sec tion Start End Length Volume Dew ater locatio n Steelman Tanker Truck 3 11m Terminal 0+094 94m at Section End (KPO+OOO) ... ·· Note that hycl rotest fl u1d for section 1 w 111 be provaded by tanker trucks . 1,, 4 .2 Fill section Test heads will be welded onto the ends o-r each test section and will be inspected by NDE . NDE documentation shall be retained to support acceptability of the welds. The foreman shall inspect all connections and hoses prior to filling the section. DATE REVISION PAGE 2012-11-·16 0 3 of 6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 47 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Steelman Section The filling operation shall be continuous to prevent air ingress. 4.3 Pressurize and test the section. Before pressurizing the section beyond a pressure of 2,760kPa, all work crews will be notified and removed from the vicinity of the test section . All pipe and fill connections shall be checked for leal<s and these test areas shall be maintained as "off-limits" to non-essential personnel. Pressure will be increased to 2,760kPa and all visible piping inspected for leaks. Upon completion of the leak check, the line and manifold will be bled off, an in line check valve installed on the squeeze line and the squeeze pump connected to the line. Squeeze pressure will be initiated through a 1" or 2" line rated to 38,000kPa (- 5,500psi); pressure shall be increased in stages as indicated in the Hydrostatic Test Record Worksheets. 5. Test Stages The pipeline shall be tested in the following stages: • Leak check • Combined Strength and Leak test (including yield plot where required. 5.1. Leak Check The first stage involves a leak checl<at approximately 2,760kPa to allow visual inspection of exposed piping and fittings included in the test section. Any pressure lost during this period must be explained to the satisfaction of the Company's testing supervisor prior to pressurizing to the target strength test pressure 5.2. Combined Strength and Leak Test The minimum duration for the combined strength and leak test is one (1) hour. Following satisfactory completion of the leak checl<s, testing will continue by slowly raising the pressure to the test pressure. 5.2.1 5.2.2 5.2.3 5.2.4 Yield plotting, if required , shall be undertaken as the section is pressurized during the strength test. Yield plotting shall commence at a pressure equivalent to 60% of the maximum anticipated test pressure. Yield plotting shall only be required where the expected maximum hoop stress in the test section during the strength test is greater than 100% SMYS of the pipe. Enbridge shall be responsible for completing all yield plots and associated documents. Pumping shall continue until the selected strength test pressure is achieved or, where a yield plot is required, the point where the yield plot deviates beyond the 0.2% offset line. The strength test will be held at a pressure greater than the minimum test pressure. After pumping has ceased, and the selected strength test pressure has been reached, the strength test will commence. The pressure at the highpoint shall match or e}cceed this minimum at both the start and the end of the test, and at no time DATE REVISION PAGE 2012-'1'1-'16 0 4 of6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 48 of 49 Bakken Mainline NPS 1 6 HYDROSTATIC TEST PLAN Steelman Section 5.2.5 during the test period shall the pressure at the high point drop below the required minimum. The minimum duration for the hold period on the strength test is one (1) hour. 6. Test Documentation Surerus will submit all required test documentation within the turnover package. Temperature and pressure readings shall be recorded as follows: • • Every 5 minutes between 0-30 minutes Every 15 minutes for the remainder of the test Records shall include the start and stop times for any pumping , pressunzmg , or depressurizing of the test section. A copy of the test worksheet shall be made available for review prior to commencement of the test. All documentation will be turned over to Enbridge upon completion of testing to facilitate completion of required Leave To Open applications. 7. Leak Detection During the leal< test, any drop in pressure which cannot be correlated to a change in temperature shall be considered a leak. If a leak is suspected Surerus shall notify the Enbridge Representative and further pressurizing of the pipeline shall be halted until the source of the leal< can be determined . Should any failure require repair, the line pressure shall be reduced to static pressure, the section dewatered, and the repair completed. 8. Depressurizing The line will be depressurized into a pressure truck rated in excess of the maximum test pressure. Under no circumstances will valves be moved to the full open position to initiate depressurizing. 9. Dewatering 9.1 Upon completion of the test, the test fluid will be transferred into tanker trucl<s for disposal. 9.2 All transfer lines will be securely fastened and supported to prevent "whipping" or sudden releases of energy during the dewater process. 9.3 The pipeline will be dewatered with a high density coated poly pig or bi-directional multi-disc pig propelled by compressed air. 12, Test Personnel Surerus will utilize the following l<ey personnel to complete pressure testing activities: Telford Advent Superintendent Surerus Pipeline Inc. Julio Zavaleta Project Engineer Surerus Pipeline Inc. Ken Hawtl1orne Test Foreman Surerus Pipeline Inc. DATE REVISION PAGE 2012-1'1-'16 0 5 of6 Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 49 of 49 Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN Steelman Section 13. Reference Documents 1. 2. 3. 4. 5. 6. CPCS-SPEC-HYDR0-005 Rev. 1 Pipeline Hydrostatic Testing CPCS-SPEC-PIPELINE-001 Rev. 1 - Pipeline Construction CPCS-SPEC-PCCT-007 Rev. 1 - Post Construction Caliper Tool. Bakken Pipeline Project Canada Alignment Sheets - D-WM057-05-500-001-A CSA Z662-(Latest Ed ition) - Oil and Gas Pipeline Systems; Canadian Standards Association Pipeline Act and Regulation - Government of Saskatchewan (Latest Edition) DATE REVISION PAGE 2012-1'1-16 0 6 o·r-6