6A - Attach 1

Transcription

6A - Attach 1
FIXED LANDING
EXISTING PIER
TO REMAIN
PIER EXTENSION
BOARDING PLATFORM APRON
E
LEASE LIN
GANGPLANKS (4 TOTAL)
GANGWAY
FIXED BOARDING RAMP (2 TOTAL)
FLOAT
SLIP 2
TEMPORARY PIER
BOARDING PLATFORM
DONUT FENDER (2 TOTAL)
SLIP 1
FLOAT GUIDE PILE (5 TOTAL)
(E) PIER, GANGWAY AND
FLOAT TO BE REMOVED
(SHOWN IN WHITE)
VESSEL TO BERTH THIS SIDE ONLY
AT TEMPORARY TERMINAL
-15 M
LLW
RELOCATED (E) GANGWAY AND FLOAT
FOR TEMPORARY TERMINAL
Item 6A - Attach 1
12-02-14
Page 1 of 7
Item 6A - Attach 1
12-02-14
Page 2 of 7
Item 6A - Attach 1
12-02-14
Page 3 of 7
SEQUENCE - PHASE I
2
3
5
6
1
3
DISCONNECT UTILITIES TO EXISTING TERMINAL. UTILITIES ON
EXISTING GANGWAY AND EXISTING FLOAT TO REMAIN FOR
FUTURE USE AT TEMPORARY TERMINAL.
4
RELOCATE EXISTING GANGWAY AND FLOAT TO TEMPORARY
TERMINAL LOCATION.
5
CONNECT TEMPORARY TERMINAL UTILITIES.
6
DEMOLISH EXISTING CONCRETE PIER.
4
SEQUENCE - PHASE I
1
CONSTRUCT TEMPORARY ACCESS PIER INCLUDING UTILITIES
FOR FUTURE CONNECTION.
2
CONSTRUCT TEMPORARY BARRIER FENCE. REMOVE
EXISTING GUARDRAIL AND INSTALL NEW ACCESS GATE.
5
PHASE I - CONSTRUCT TEMPORARY TERMINAL
SEQUENCE - PHASE II
9
SEQUENCE - PHASE II
7
CONSTRUCT NEW CONCRETE PIER.
10
DISCONNECT AND REMOVE TEMPORARY UTILITIES.
8
INSTALL NEW GANGWAY, FLOAT, DONUT FENDERS AND COMPLETE UTILITIES.
11
REMOVE AND DISPOSE OF TEMPORARY TERMINAL.
9
REMOVE AND INSTALL GUARD RAIL ON EXISTING PIER.
8
9
7
8
10
PHASE II - CONSTRUCT NEW TERMINAL
& REMOVE TEMPORARY TERMINAL
Item 6A - Attach 1
12-02-14
Page 4 of 7
Item 6A - Attach 1
12-02-14
Page 5 of 7
Item 6A - Attach 1
12-02-14
Page 6 of 7
Item 6A - Attach 1
12-02-14
Page 7 of 7

Similar documents