washington street and reche canyon road intersection
Transcription
washington street and reche canyon road intersection
WASHINGTON STREET AND RECHE CANYON ROAD INTERSECTION IMPROVEMENT PROJECT FUNDING SOURCE: CONGESTION MITIGATION AND AIR QUALITY (CMAQ) PROJECT LOCATION: WASHINGTON STREET AND RECHE CANYON ROAD ESTIMATED START/COMPLETION DATE: FEBRUARY 2015 – JUNE 2015 PROJECT DESCRIPTION: THE PROJECT WILL PROVIDE TWO DEDICATED LEFT TURN AND TWO DEDICATED RIGHT TURN POCKET ALONG RECHE CANYON ROAD AT THE INTERSECTION OF WASHINGTON STREET. THE SCOPE OF THE PROJECT INCLUDES WIDENING AT RECHE CANYON ROAD WITHIN CITY RIGHT OF WAY, STORM DRAIN PIPE EXTENSION AND CATCH BASIN RELOCATION, CURB AND GUTTER CONSTRUCTION, STRIPING, AND TRAFFIC SIGNAL MODIFICATION. SINCE THIS IS A CMAQ (CONGESTION MITIGATION AND AIR QUALITY) FUNDED, THIS IS A NON-CAPACITY INCREASING PROJECT BUT WILL PROVIDE A BETTER LEVEL OF SERVICE (LOS) FOR THE INTERSECTION. PLAN: NEXT PAGE