First PVC Spiral Wound Liner Installation in Hawaii

Transcription

First PVC Spiral Wound Liner Installation in Hawaii
Lining the Slippery Slopes of
Wilhelmina Rise
Honolulu’s First Installation of PVC Spiral
Wound Liner and Lateral Part-Liner
32nd Annual HWEA Conference
Presented by:
Shannon Holman, PE, URS
List of Credits
• Owner: City and County of Honolulu
– Project Design Engineer: Lynn Kurashima
– Construction Engineer: Ted Saito
• Design Consultant: URS Corporation
• Contractor: Parsons
• Construction Manager: Yogi Kwong
Engineers
Presentation outline
• Project background
• Condition assessment
• Rehabilitation methods evaluated and
design approach
• Construction
– Installation challenges
– Observations
– Lessons learned
Project located along Wilhelmina Rise
Project consists of ~ 40,000 LF of
gravity sewer and over 500 laterals
Kaimuki
Community
Park
Sierra Dr
Maunalani Park
Wilhelmina Rise
Waialae Ave
16th Ave
•
•
•
•
6-, 8-, 10-, and 12-inch pipe
Minor and major root
intrusion
Legend
Cured-in-Place Pipe
Structural damage
Joint offsets Open Cut Pipe Replacement
Condition assessment identified various
defects: collapsed pipe, fractures
…..pipe cracking…..
…..and minor and major root intrusion
Various rehabilitations methods
evaluated for project
• Cured-in-place pipe (CIPP)
• PVC spiral wound pipe (Rib Loc)
• Service connection lateral liners
– Top-hat liner
– Lateral part liner (T-Liner)
Difficult access along East and West lines
results in Rib Loc being the selected method
Kaimuki
Community
Park
Sierra Dr
Maunalani Park
Wilhelmina Rise
Waialae Ave
16th Ave
Legend
Cured-in-Place Pipe (CIPP)
Rib Loc or CIPP
Open Cut Pipe Replacement
Description of Rib Loc installation
1) Pre-cleaning
2) Lateral logging
5) Lateral reconnection
PVC liner spool
3) Winding process
Cutting wire
4) Expansion Process
Description of T-liner installation
1
Clean and inspect lateral to main connection
2 T-liner inspected, coated w/ resin, & loaded into t-loader device
Description of T-liner installation
3
T-Liner loader inserted through mainline pipe
4
T-liner loader is aligned with lateral connection opening
Description of T-liner installation
5
T-liner is inverted into lateral
Construction overview
• Schedule duration
– 12 weeks for Rib-loc installation
– 4 months to date (300 out of 500 T-Liner
installations)
• Training requirements
• Remote location, steep terrain and limited
access
Rib Loc equipment
Silicone
Generator
Wire puller
Hydraulic
power pack
Rib Loc profile
on spool
Control panel
Rib-loc equipment set-up
Rib Loc installation
Rib Loc installation
Rib Loc installation – lateral cutout
Remote cutter machine
T-liner wet-out procedure
T-liner (wetted out)
Inflatable bladder
T-liner tube
T-liner installation at manholes
T-loader positioner
T-Liner
Installed T-liner
O-ring gasket
Smooth transition from
liner to host pipe
Lateral portion of
T-liner
Challenges and lessons-learned for
Rib-loc installation
•
•
•
•
•
Mobilization plan
Rapid root re-growth
Modification to manholes
Measure twice, cut once (laterals)
Flow bypassing not required for low flow
conditions
• Air testing constraints
Manhole modification required to install
Rib Loc in steep grades
Mobilization plan in tight quarters
Observations and challenges for
T-Liner installation
•
•
•
•
•
Cleanout requirement for 3rd access point
Double wye lateral connections
Occasional o-ring gasket detachment
Excess resin, resin bumps
Occasional failures during initial
installations
Double wye lateral connection
O-ring detachment
Exposed o-ring gasket on
lateral portion of T-Liner
Second o-ring gasket
Exposed o-ring gasket on
mainline portion of T-Liner
Excess resin
Rib Loc Conclusions
• Appropriate for this application
• Equipment was portable and easily
transported
• Immediate confirmation on installation
allowing for removal if necessary
• No curing process
• Can improve hydraulic capacity
• Uses existing MH’s for access
• No sewer bypass for low flow conditions
T-Liner Conclusions
• Allowed for less disruption to property
owners
• Full circumferential seal – awaiting air test
results
• Uses existing MH’s for access
• Hydrophilic gaskets on mainline and lateral
provides better seal
Questions ??