Agenda Note - Central Electricity Authority

Transcription

Agenda Note - Central Electricity Authority
375-388
Agenda notes for the 39th Meeting of Standing Committee on Power System Planning in
Western Region
1.0
Confirmation of the minutes of 38th meeting of the Standing Committee on
Power System Planning in Western Region (SCPSPWR) held on 17th July 2015
at NRPC, Katwaria Sarai, New Delhi.
1.1
The minutes of the 38th SCPSPWR were issued vide CEA letter No.26/10/2014SP&PA/ 1- 14 dated 25th August 2015.
1.2
MSETCL vide their letter no. MSECTL/CO/TU/302B/GC/201/12990 dated 8.10.2015
has observed that in item no. 5.2 of the minutes LILO of Parli- Osmanabad 220 kV
D/C line at Parli (PG) 400/220 kV, 2X500 MVA substation may kindly be corrected
as LILO of Parli- Osmanabad 220 kV S/C line at Parli (PG) 400/220 kV, 2X500
MVA substation.
1.3
Taking into consideration the correction suggested by MSETCL, only six no. of 220
kV line bays [4 nos. for LILO of both circuits of Parli-Harngul 220 kV line at Parli (PG)
and 2 nos. LILO of Parli- Osmanabad 220 kV S/C line at Parli (PG)] will be required
instead of eight nos. of 220 bays at Parli (PG) 400/220 kV, 2X500 MVA mentioned at
item no. 5.3 and 5.4 of minutes of the 38th SCPSPWR.
1.4
Members may deliberate and confirm the minutes of the 38th meeting of the Standing
Committee on Power System Planning in Western Region.
2.0
Review of Progress on Earlier Agreed Transmission Schemes.
2.1
The status of implementation of transmission projects under tariff based competitive
bidding are enclosed at Annexure-1 and the status of transmission schemes under
implementation by POWERGRID is enclosed at Annexure-2.
Members may deliberate.
3.0
Proposal for two nos. of 220 kV bays at existing Aurangabad 765/400/220 kV
substation of POWERGRID.
3.1
MSETCL vide their letter dated 19.10.2015 has forwarded the proposal for provision
of 2 nos. of 220 kV bays at the existing Aurangabad 765/400/220 kV substation of
POWERGRID. The two nos. of 220 kV bays are required for termination of Shendra
GIS – Aurangabad 765/400/220 kV substation 220 kV D/C line at Aurangabad
765/400/220 kV substation.
3.2
The Shendra 220 kV GIS has been proposed to meet 200 MW load under DelhiMumbai- Industrial Corridor (DMIC) Phase-I. The scope of works for establishment of
Shendra 220 kV GIS are:
39th SCMPSPWR Agenda
1
(i)
(ii)
(iii)
3.3
Establishment of 220/132/33 kV, Shendra GIS.
3X100 MVA, 220/33 kV Transformers at Shendra GIS. Provision of 132 kV
switchyard for EHV consumer to be taken up in future.
Shendra GIS – Aurangabad 765/400/220 kV substation 220 kV D/C line.
MSETCL may confirm the implementation agency for the Shendra 220 kV GIS
proposal. POWERGRID may confirm the availability of space for 2nos of 220kV bays
at Aurangabad 765/400/220 kV substation.
Members may deliberate.
4.0
4.1
4.2
MSETCL proposal of shifting of Aurangabad (Waluj) – Pune (PG) 400kV D/C
line from 400kV Aurangabad (Waluj) to 765/400kV Aurangabad (PGCIL).
In the 38th SCM of WR held on 17.07.2015, MSETCL has proposed shifting of
Aurangabad (Waluj) – Pune – PG 400kV D/C line from 400kV Aurangabad (Waluj) to
765/400kV Aurangabad (PGCIL) to remove the constraints for import of power in
Maharashtra control area. The loading on the 2X1500 MVA 765/400 kV ICTs at
Aurangabad (PG) substation and Aurangabad- Aurangabad I (Waluj) 400 kV
interconnection was the limiting factor for import of power in Maharastra from ISTS.
In the meeting, it was agreed that MSETCL proposal of shifting of Aurangabad
(Waluj) – Pune (PG) 400kV D/C line from 400kV Aurangabad (Waluj) to 765/400kV
Aurangabad (PGCIL) would be studied jointly by CEA, CTU, WRLDC and MSETCL.
The peak demand met by Maharastra in August 2015 was 18447 MW. Accordingly,
load flow studies were carried out by taking recent load flow file from WRLDC for a
demand of 18,445 MW in Maharashtra. In the studies intrastate generation of
Maharashtra of 11893.4 MW (Tirora – 2418MW, Koyna – 552.8, Jaigad – 1000MW,
Amravati- 750 MW) and import of about 6500 MW from ISTS has been considered.
The load flow study was carried out to see the impact of the following transmission
schemes which are already under implementation by PGCIL/MSETCL on the power
flows in Aurangabad (Waluj)- Aurangabad(PG) 400 kV interconnection:
(i)
LILO of 400kV D/C lines Parli – Pune (PG) at Pune (GIS) - already
commissioned.
(ii)
LILO of Aurangabad – Pune (PG) at Pune(GIS) ) by September 2015
(iii) 2 nos. of 400 kV bays at Dhule (MSETCL) for termination of Dhule(Sterlite) –
Dhule (MSETCL)400 kV D/C line.
(iv) Aurangabad – Sholapur D/C 765kV line by December 2015
(v)
Aurangabad – Boisar D/C 400 kV line by March 2016
(vi) Aurangabad – Padghe 765 kV D/C line by March 2016
(vii) LILO of one circuit of Aurangabad – Padghe 765 kV S/C line at Pune (GIS) –
project under bidding stage.
4.3
The load flow results are attached as Annexure-3. From the load flow analysis it is
evident that with the commissioning of the above mentioned elements loading on
400kV Aurangabad (Waluj) – Aurangabad (PG) D/C line has been reduced from
2200MW to 640MW and Aurangabad (Waluj) – Aurangabad (PG) D/C line would not
be constraint for import of power to Maharashtra. In view of this, MSETCL proposal
Agenda notes - 39th SCMPSPWR
2
of Shifting of Aurangabad (Waluj) – Pune (PG) 400kV D/C line from 400kV
Aurangabad (Waluj) to 765/400kV Aurangabad (PGCIL) is not required.
Members may deliberate.
5.0
Additional 400 kV feed to Goa
5.1
In the 38th SCM of WR the following Inter State Transmission System scheme was
proposed:
(i)
(ii)
5.2
5.3
Establishment of 2X500 MVA, 400/200 kV substation at Xeldam and its
interconnection with Narendra (existing) 400 kV substation through 400 kV
D/C line with quad conductor. The interconnection between the existing 220
kV Xeldam substation and the proposed 400/220 kV Xeldam substation could
be through bus extension or through 220 kV interconnecting lines, as the case
may be.
400kV (Quad) connectivity between the new substation at Xeldem and
Mapusa to take care of any N-1-1 contingencies involving outage of any one
400kV infeed to Goa.
In the meeting POWERGRID has suggested the alternative of LILO of NarendraKolhapur 400 kV D/C line (765 kV line to be initially charged at 400 kV level) at the
proposed Xeldam 400 kV substation as 765 kV operation of Narendra-Kolhapur D/C
line was not envisaged in near future and it would increase the utilisation of
Narendra-Kolhapur D/C line. It was decided that the alternative suggested by
POWERGRID would be studied jointly by CEA and CTU and based on its merit the
same would be included in the scheme that would be put in the SR SCM for their
approval.
POWERGRID has further carried out studies and suggested alternatives(One- LILO
of one ckt of Narendra (existing) – Kaiga 400kV D/c line at Xeldem (New) and
Xeldem (New) – Colvale (Mapusa) 400 kV (Quad/HTLS) D/c line, Two- Kolhapur
(PG) – Colvale (Mapusa) 400kV (Quad/HTLS) 2nd D/c line and Colvale (Mapusa) Xeldem (New) 400 kV(Quad/HTLS) D/c line). Although alternative One is better in
terms of power flow, the LILO shall involve construction of more than 100KM line
length in the hilly and forested areas of Western Ghats. About 30% of the area of the
Western Ghats Region is under forests. In the past, during forest clearance process
of Kaiga-Narendra 400 kV line, POWERGRID faced lot of resistance from various
activists and NGOs. The clearance was recommended by Karnataka government in
2002 only after joint confirmation from POWERGRID and CEA during detailed review
that no further transmission line shall be laid in the area. It is therefore apprehended
that LILO of one ckt of Kaiga-Narendra 400 kV D/C line in Western Ghat area shall
be resisted by the activists/NGOs and obtaining forest clearance and actual
implementation of line may be delayed as in case of Mysore-Kozikode 400 kV line
(Mysore –Kutta portion) due to such resistance and possible legal intervention.
Therefore, alternative Two has been suggested by POWERGRID along with
reconductoring of Sholapur (PG) – Kolapur 400kV Double Circuit Line with HTLS
conductor.
The following alternatives for feeding Xeldam 400 kV substation has been studied
including the alternative proposed in the 38th SCM and the alternative proposed by
POWERGRID:
Agenda notes - 39th SCMPSPWR
3
S. No
1
2
3
4
5
6
7
8
Alternative
Exhibit
Narendra (existing)- Xeldam- Mapusa 400 kV Option
1
(as
D/c quad line
proposed in 38th
SCM)
Kolhapur (PG)- Mapusa – Xeldam 400 kV D/C Option 2
quad line
(suggested by
POWERGRID)
Kolhapur (PG) – Xeldam- Mapusa 400 kV D/C Option 3
quad line
Kolhapur (PG) – Xeldam 400 kV D/C quad Option 4
line and LILO of one ckt at Mapusa
LILO of one ckt. of Narendra (New)- Kolhapur Option 5
(PG) 400 kV D/C line at Xeldam
(suggested by
POWERGRID)
LILO of one ckt. of Narendra (existing) - Option 6
Narendra(New) 400 kV D/C line at Xeldam
LILO of one ckt. of Kaiga-Narendra (existing) Option 7
400 kV D/C line at Xeldam with LILO point at
Narendra end.
LILO of one ckt. of Kaiga-Narendra (existing) Option 8
400 kV D/C line at Xeldam with LILO point at
Kaiga end.
The results of the load flow studies conducted for the above mentioned eight alternatives is
enclosed as Annexure - 4. The observations based on analysis of the results are:
(i) Option 1 is technically best possible alternative for providing ISTS feed to Goa
system since it has successfully relieved loading on existing 220kV network as well
as 400kV network which is feeding power to Goa system.
(ii) For implementation of Option 1 two no. of 400 kV bays would be required at
Narendra (existing) 400/220 kV substation. In case of space constraints GIS bay
may be provided. If no space is available then option 6 or option 7 could be
implemented which are equally good as option1.
(iii) In the all the eight alternatives, the 400 kV lines to Mapusa/ Xeldam has to cross
the Western Ghats section.
(iv) In the corridor through which the Narendra(existing)-Xeldam 400 kV D/C line would
pass, there are already existing Ambewadi – Xeldam/Ponda 220 kV D/C line and
Supa-Ponda 110 kV D/C line. Ambewadi – Xeldam/Ponda 220 kV D/C line is
functional whereas the Supa-Ponda 110 kV D/C line is not in use. These lines are
maintained and operated in their respective geographical areas by Goa and
Karnataka respectively. In case of difficulty in getting RoW for implementation of
Narendra (existing)-Xeldam 400 kV D/C line, the RoW of the existing Supa-Ponda
110 kV D/C line could be used.
(v) Option 2 - there will be only a single source for feeding Goa at 400kV level i.e.,
765/400 kV Kolhapur (PG).
(vi) Option5 i.e, LILO of one ckt. of Narendra(New)- Kolhapur(PG) 400 kV D/C line at
Xeldam which was suggested in the 38th SCM is not a suitable alternative as there is
uneven loading on the 400 kV circuits feeding power to Xeldam ( 540 on one ckt and
82 MW on other ckt.) . Also Narendra(New)- Kolhapur(PG) is a 765 kV D/C line
which in present scenario is being operated at 400 kV level and in future when this
line would be operated at 765 kV voltage level , the Xeldam 400 kV along with the
feeding lines also needs to be upgraded to 765 kV level.
Agenda notes - 39th SCMPSPWR
4
5.4
Members may deliberate and finalize the second 400 kV feed to Goa so that the
same could be taken up for approval in the SCM of SR.
6.0
Connectivity System for Lanco Vidarbha Thermal Power Pvt. Ltd. (LVTPPL)
6.1
In the 21st Meeting of WR constituents regarding Connectivity / Open Access
Applications held on 17.07.2015, the connectivity arrangement agreed earlier (i.e.,
LILO of Seoni - Wardha 765 kV S/C line at LVTPL TPS) for LVTPPL was revised as
below:
(i) LVTPPL TPS Switchyard – Warora Pool 765kV D/c line (to be implemented
through Tariff Base Competitive Bidding route)
In the meeting, M/s LVTPPL was requested to confirm the time frame by which
connectivity line is required so that suitable action may be initiated for
implementation of the line through Tariff Based Competitive Bidding route.
6.2
6.3
M/s LVTPL vide their letter dated 27th August, 2015 has requested for continuation of
the earlier connectivity granted i.e. LILO of Seoni – Wardha 765kV S/c line at
LVTPPL TPS and subsequently a meeting was held in CEA on 2.9.2015 to discuss
the connectivity issue (Minutes enclosed as Annexure- 5). In the meeting M/s
LVTPPL was requested to confirm the following requirements so that the connectivity
line (LVTPPL TPS – Warora Pool 765kV D/c line ) could be included in the agenda
for Empowered Committee for implementation of the scheme through TBCB route.
a.
M/s LTPPL needs to confirm the commissioning schedule of the generation
project
b.
As per CERC sharing regulations, transmission charges are payable by
beneficiaries only after the commercial operation of the generator. Till then, it is
the responsibility of M/s LVTPPL to pay the transmission charges.
c.
M/s LVTPPL need to sign connectivity agreement and submit requisite bank
guarantee.
Response from M/s LVTPPL is awaited. However connectivity of LVTPPL may be
granted through LVTPPL TPS Switchyard – Warora Pool 765kV D/c line. M/s
LVTPPL would be required to sign requisite agreements for taking up the
transmission scheme under Tariff Base Competitive Bidding route.
Members may deliberate.
7.0
Provision of 1x240MVAR line reactor at Pune GIS end for Aurangabad (PG) –
Pune GIS 765kV line (formed after LILO of one ckt of Aurangabad (PG) –
Padghe (PG) 765kV D/c line at Pune GIS - LILO Length Considered - 67KM).
7.1
In 36th Meeting of Standing Committee on Power System Planning in Western
Region held on 29.08.2013, LILO of one ckt of Aurangabad (PG) – Padghe 765kV
D/c at Pune GIS in lieu of Kolhapur-Padghe (PG) 765kV D/c one ckt via Pune GIS
was agreed as System Strengthening Schemes in WR for transfer of power to SR
from IPPs in Chhattisgarh.
Agenda notes - 39th SCMPSPWR
5
7.2
Subsequently, in 32nd meeting of Empowered Committee on Transmission held on
17.01.2014, the above scheme was agreed to be implemented through TBCB under
System Strengthening for IPPs in Chhattisgarh and other Generation Projects
in Western Region. Presently the process of transfer of SPV is under progress.
As per the route survey carried out by the BPC for LILO of one ckt of Aurangabad
(PG) – Padghe (PG) 765kV D/c line at Pune GIS, the route length for LILO portion
comes out to be 67KM approximately. Originally the length of Aurangabad (PG) –
Padghe (PG) 765kV D/c line was about 285KM and 2x240MVAR line reactors along
with 2x1200Ohm NGR are available at both ends of Aurangabad – Padghe 765kV
D/c line. After LILO at Pune GIS, the length of modified sections i.e. Aurangabad
(PG) – Pune GIS 765kV line would be about 254KM and Pune GIS – Padghe (PG)
would be about 165KM. Accordingly, in order to have proper reactive compensation,
1x240MVAR line reactor along with 1200 Ohms is proposed at Pune GIS for
Aurangabad (PG) – Pune GIS 765kV line.
Members may deliberate.
8.0
Replacement of Overhead conductor with UG cable on GETCO portion of
KAPP 1&2 – VAPI/Balitha (GETCO) 220kV D/c line.
8.1
Transmission System for KAPP 1 & 2 consists of KAPP 1&2 – Vapi/Balitha (GETCO)
220kV D/c Single ACSR Zebra line - 117KM which is an ISTS line and tariff of the
same is claimed by POWERGRID. A certain portion of above line towards the end of
Vapi (GETCO) substation is owned and maintained by GETCO. GETCO portion of
KAPP 1&2 – Vapi / Balitha (GETCO) 220kV D/C line is terminated in different D/C
towers upto the point from which POWERGRID portion starts. In order to release the
adjoining land for developing various residential schemes at Vapi / Balitha, GETCO
proposed to replace existing 220kV conductor with approx. 255mtr underground
220kV XLPE cable from their portion of KAPP 1&2 – Vapi 220kV ckt 2 from 220kV
Vapi / Balitha S/s. The cost of the modification work would be borne by M/s GETCO.
8.2
POWERGRID/ GETCO may present the scheme details.
9.0
Conversion of fixed Line Reactors to switchable Line Reactors
9.1
Fixed line reactors on small 400 kV lines may lead to cases of over-compensation in
lines. Several short length 400 kV lines have been identified in Western Region
which has a high degree of compensation and the same have been tabulated below:
Agenda notes - 39th SCMPSPWR
6
Sl.
1
2
3
4
5
9.2
9.3
Name of the Line
Aurangabad(PG) –
Aurangabad I (Waluj)
400kV D/c (Quad)
Itarsi – Indore (MPPTCL)
400kV S/c I
Itarsi – Indore (MPPTCL)
400kV S/c II
Bina (PG) – Shujalpur
400kV D/c
Bhadravati – Dhariwal
400kV S/c
Length
(in km)
Capacity
Switchable (S) /
(MVAR)
Fixed (F)
End I End II End I End II
%
Compensation
52.56
--
50
--
F
158.54
207
50
50
F
F
87.83
214
50
50
F
F
84.96
199.9
4
63
50
S
F
102.76
17.7
63
--
F
--
647.15
POWERGRID has proposed to convert the fixed line reactors into switchable line
reactors so that they may be utilized as Bus Reactors, as and when needed to
improve voltage profile. Further, NGR removal/bypassing may be considered for the
above lines for successful auto-reclose. DOV Studies for the above lines have been
carried out and no DOV phenomenon has been observed in absence of the line
reactor.
POWERGRID may present the DOV studies and members may deliberate.
10 Operational feedback by NLDC.
10.1 The operational feedback by NLDC on Transmission constraints in Western Region
for the quarter July 2015 to September 2015 is summarized below:
10.1.1 Transmission Line Constraints
S. Corridor
No
1. 400 kV
Aurangabad(PG) Aurangabad (MSETCL)
D/C
Antecedent
Conditions
With commissioning of
765 kV Durg-Wardha
D/C, 765kV WardhaAurangabad 4 ckts and
high demand of
Maharashtra, the
constraint has shifted to
400 kV Aurangabad
(PG)-Aurangabad (MS)
Agenda notes - 39th SCMPSPWR
Constraint
Description of the constraint
Critical
Loading of
400 kV
Aurangabad
(PG) Aurangabad
(MSETCL)
D/C leading to
n-1 noncompliance.
Constraint observed from July’14
after commissioning of 765 kV
Wardha-Aurangabad 1 & 2 lines.
Further, 765 kV Wardha-Aurangabad
3 & 4 also have been commissioned
and all 4 ckts are usually not kept in
service in order to control the loading
on the 400 kV Aurangabad (PG)Aurangabad (MS) D/C and to control
the high voltages at Wardha.
With the commissioning of Vadodara
Sub-station along with the 765 kV
Dhule-Vadodara S/C , there is power
flow of around 400MW through
765kV Aurangabad-Dhule-Vadodara
7
S. Corridor
No
D/C in the absence of
220 kV network from
400 kV Aurangabad
(PG) S/S. The 2 x 315
MVA ICTs are in idle
charged condition at
Aurangabad(PG) S/s.
Constraint
2.
400 kV
KhandwaDhule BableshwarPadghe
corridors
carrying more
than 500 MW
in each ckt.
The corridor is
N-1 noncompliant.
3.
Constraints in 400 kV
Khandwa – Dhule Bableshwar-Padghe
corridor
Antecedent
Conditions
With high Maharashtra
Demand of the order of
18500-20000 during
morning peak and no
Generation at RGPPL
and low generation at
Jaigad and Parli and
SSP generation is less.
765/400 kV ICT at
Tirora and 765/400 kV
ICT at Akola II
Antecedent
Conditions
When generation at
Tirora is 1800-2400
MW.
4.
400 kV Wardha-Parli
D/C
Description of the constraint
S/C and 765/400kV Aurangabad
ICTs and 400 kV Aurangabad (PG) Aurangabad (MS) D/C are relieved to
a certain extent.
The system is
not n-1
compliant. It
has been
observed that
tripping of 765
kV Tirora ICT
or 765 Akola II
ICT would
cause sudden
increase in the
loading of
Tirora-Warora
lines causing
oscillations in
the grid.
High loading
of WardhaParli D/C
Antecedent
Conditions
With high Maharashtra
Demand of the order of
18500-20000MW during
morning peak and no
Generation at RGPPL
and low generation at
Agenda notes - 39th SCMPSPWR
8
765 kV Aurangabad-Solapur D/C has
been commissioned and relieved the
line loading of 400kv AurangabadAurangabad D/C.
400 kV Tapthithanda-Bableswar D/C
has been commissioned on 31.12.14,
but in real time operation one circuit
is kept open by MSETCL to control
the loading on 400kV BableshwarPadghe D/C which is generally
loaded above 550 MW each .
Commissioning of 400 kV
Bableshwar-Kudus D/C and Kudus
Sub-station to be expedited by
MSETCL.
765 kV Tiroda-Koradi-III-Akola D/C
commissioned. Due to delay in
commissioning of 765/400 kV Ektuni
(Aurangabad (MS)) S/S, Akola –
Tapthithanda D/C are charged at
400kV. Commissioning of 400 kV
Bableswar-Kudus D/C and Kudus
Sub-station to be expedited by
MSETCL. Single ICT at Tiroda and
Akola-II is a constraint leading to n-1
non-compliance and at present
managed by SPS. Second ICT to be
planned and expedited by APML and
MEGPTCL.
After commissioning of 765 kV
Wardha-Aurangabad ckts, 765kV
Pune-Sholapur S/C and 765kV
Aurangabad-Dhule-Vadodara S/C,
loading 400kV Wardha-Parli D/C is
reduced and is generally loaded
below 600 MW each except under
contingency of unit tripping /
overdrawal of Southern Region. The
Commissioning of 765kV
Aurangabad-Sholapur D/C would
S. Corridor
Constraint
No
Jaigad and Parli.
High drawal of Southern
Region through 765kV
Raichur-Sholapur D/c
also contributes critical
loading of this section.
5. 400kV Parli(PG)Sholapur(PG) D/C
6.
7.
Antecedent
Conditions
With high demand of
Maharashtra, Goa and
high drawal of Southern
Region
400 kV AurangabadPune D/C
Antecedent
Conditions
With commissioning of
765 kV Wardha Aurangabad D/C and
high demand of
Maharashtra, the
constraint has shifted to
Aurangabad. Intra state
transmission within
Maharashtra is not
scheduled along with
Interstate Transmission
schemes.
400 kV SSP-Asoj S/C
and SSP-Kasor S/C
Antecedent
Conditions
SSP generating full and
with high demand in
Gujarat coupled with
less generation at APL
and CGPL, Mundra.
Agenda notes - 39th SCMPSPWR
Description of the constraint
The
transmission
system at
220kV Pune is
inadequate
(only 2 lines
from 220kV
Pune (PG)).
400/220kV
one ICT at
Pune is kept
open to
control loading
on 220kV lines
from Pune
(PG).
Continuous
loading of
above 550
MW in SSPAsoj and SSPKasor.
9
further relieve 400 kV Wardha-ParliSholapur corridor.
The 765 kV Solapur-Aurangabad D/C
has been charged on 30th September
2015 and line loading of 400 kV
Wardha-Parli has been relieved.
765kV Pune-Sholapur S/C helps
under contingency in real time and
has improved reliability in this
corridor.
765 kV Sholapur-Aurangabad D/C
has been charged on 30th September
2015 and line loading of 400 kV ParliSolapur D/C has been relieved.
Constraint on this corridor is relieved.
220 kV network from Pune to be
planned and expedited by MSETCL.
The 765 kV Solapur-Aurangabad D/C
has been charged on 30th September
2015 and line loading of 400 kV
Aurangabad-Pune D/C has been
relieved. Constraint on this corridor is
relieved.
Bus split operation done from 22.930.9.14. Due to less generation at
SSP, constraints were not observed
in last 2 months. Further, with the
commissioning of 765/400kV
Vadodara Pooling station along with
765 kV Indore –Vadodara S/C, 765
kV Dhule –Vadodara S/C along with
400 kV Asoj-Vadodara D/C and 400
kV Vadodara-Pirana(PG) D/C, have
helped in reducing the loading on
SSP-Asoj and SSP-Kasor.
10.1.2 ICT Constraints
S.
No
1.
2.
3.
ICT
Constraint
2 x 315 +1 x 500
MVA Bableshwar
ICTs
It is observed that the
Bableshwar ICTs are fully
loaded and system is n-1
non-compliant. MSETCL
has implemented load
Antecedent
trimming scheme to take
Conditions
With Maharashtra care of overloading.
demand above
17500 MW
It is observed that the
2 X 1500 MVA
Aurangabad (PG) loading on ICTs are more
than 800 MW resulting in
ICTs
‘N-1’ non-compliance.
Antecedent
Conditions
Maharashtra
meeting high
demand of above
18500 MW
2 X 315 MVA
Chakan ICTs
Antecedent
Conditions
Maharashtra
meeting high
demand of above
18500 MW
3 X 315 MVA
Lonikhand ICTs
It is observed that the
loading on ICTs at
Chakan (2x315MVA) are
above 200 MW and
additional ICT has to be
proposed
It is observed that the
loading on ICTs at
Lonikhand 3 x 315 MVA)
are above 200 MW and
Antecedent
additional ICT has to be
Conditions
proposed or 2 x 500 MVA
Maharashtra
ICTs at Lonikhand-II are
meeting high
demand of above underutilized and the 220
kV lines from Lonikhand
18500 MW
II and Pune(PG) to be
expedited.
5.
3 X 315 MVA +
It is observed that the
600 MVA Padghe Padghe ICTs are fully
ICTs
loaded and system is N-1
non-compliant.
MSETCL has
Antecedent
implemented load
Conditions
th
Agenda notes - 39 SCMPSPWR
10
4.
Description of the constraints
One ckt of TapthithandaBableswar as well as AkolaTapthithanda kept out by
MSETCL to control loading on
ICTs and Bableshwar-Padghe
D/c.
Shifting of unutilized ICT from
Warora may be explored by
MSETCL.
Commissioning of 765kV
Aurangabad-Dhule-Vadodara
S/C has relieved ICT loading at
765/400kV Aurangabad to a
certain extent.765kV
Aurangabad- Sholapur D/C
relieve the loading to some
extent.
The 765 kV Solapur-Aurangabad
D/C has been charged on 30th
September 2015 and line loading
of Aurangabad ICT’s has been
relieved. Constraint on this
corridor is relieved.
Discussed in 38th SCM of WR.
MSETCL to plan additional ICTs
at Chakan and Lonikhand I
400/220 kV substations and more
nos. of 220 kV outlets from Pune
(PG) and Lonikhand-II 400/ 220
kV substation.
Discussed in 38th SCM of WR.
MSETCL to plan additional ICTs
at Chakan and Lonikhand I
400/220 kV substations and more
nos. of 220 kV outlets from Pune
(PG) and Lonikhand-II 400/ 220
kV substation.
These ICTs are heavily loaded
with the increase in Maharashtra
demand.
S.
No
6.
7.
8.
9
ICT
Constraint
Maharashtra
meeting high
demand of above
18500 MW
2 X 315 MVA
Khandwa ICTs
trimming scheme to take
care of overloading.
Antecedent
Conditions
Madhya Pradesh
meeting high
demand of above
9000 MW
2 X 315 MVA
Satna ICT
Antecedent
Conditions
Madhya Pradesh
meeting high
demand of above
7000 MW
3 X 315 MVA
Bhopal ICTs
Antecedent
Conditions
Madhya Pradesh
meeting high
demand of above
9000 MW
2 X 315 MVA
Dehgam ICTs
Antecedent
Conditions
Gujarat meeting
high demand and
generation at
Wanakbori being
low.
Description of the constraints
It is observed that the
loading on ICTs at
Khandwa (2x315MVA)
are above 200 MW and
additional ICT has to be
proposed.
Discussed in 38th SCM of
WR.1X315 MVA, 400/220 kV ICT
(2nd) at Chhegaon is under
implementation by MPPTCL and
is expected to be completed by
December 2015. This would
relieve loading on Khandwa
ICTs.
It is observed that the
loading on ICTs at Satna
(2x315MVA) are above
200 MW and additional
ICT has to be proposed.
Discussed in 38th SCM of WR
.500 MVA, 400/220kV ICT at
Satna (PGCIL) S/s with provision
of 2 Nos. 220kV bays approved.
It is observed that the
loading on ICTs at
Bhopal (3x315MVA) are
above 200 MW and
additional ICT has to be
proposed
Discussed in 38th SCM of WR
.1X315 MVA, 400/220 kV ICT
(4th) at Bhopal is under
implementation by MPPTCL and
is expected to be completed by
December 2015.This would
relieve loading on the existing
ICTs at Bhopal
It is observed that the
loading on ICTs at
Dehgam (2 x 315 MVA)
are above 180 MW and
additional ICT has to be
proposed
Agenda notes - 39th SCMPSPWR
11
10.1.3 Lines/ICTs opened to control overloading
S.
No
1.
Transmission Element
(s) opened
400/220
one ICT
kV
Pune(PG)
Overloaded corridor
Remarks
To control loading in Additional 220 kV outlets from
220 kV Pune(PG) – Pune (PG) to be expedited by
MSETCL.
Talegaon D/C lines
Idle charged in the absence of
220kV downstream network,
which has to be expedited by
MSETCL.
2.
400/220 kV 2 x 315 MVA
Aurangabad(PG) ICTs
3.
400/220 kV 2 x 315 MVA
Sholapur(PG) ICTs
4.
400/220kV 2 x 315 MVA
Warora ICTs
5
400/220
400
kV
Akola2Bableshwar
Taptithanda one circuit
loading
In the 38th SCM of WR
MSETCL has proposed LILO of
both circuits of ChitegaonShendra 220 kV D/C line at
Aurangabad (PG) 400/220 kV,
2X315
MVA
substation.
MSETCL may intimate the
implementation schedule.
South Solapur has been
connected which is around 50
MW. Further loads from Solapur
(MS) need to be transferred for
reducing ICTs loading at
Solapur(MS)
Idle charged in the absence of
220kV downstream network,
which has to be expedited by
MSETCL
or
shifting
to
Bableshwar may be explored.
765 kV Ektuni, 765 kV Padghe,
400 kV Kudus and associated
kV circuits need to come along with
ICT 220 kV Associated network in
Western Maharashtra to reduce
the loading.
10.1.4 High Fault Level at Korba Bus: Large fault current was observed during a close in
fault at Korba Sub-station on 6th July 2015. During this event, Y phase to earth fault
occurred on 400 kV Korba-Raipur 3 and the fault current at Korba end was of 45 kA.
The DR from Korba end is given below.
Agenda notes - 39th SCMPSPWR
12
Trigger
06-07-15
2:34:31 PM.033
VA/kV
200
150
100
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
-0.4
-0.2
-0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
t/s
50
VB/kV
150
100
50
t/s
0
VC/kV
200
150
100
50
t/s
VN/kV
200
100
t/s
0
IA/A
400
300
200
100
t/s
0
IB/kA
30
20
10
t/s
0
IC/A
750
500
250
t/s
0
IN/kA
30
20
10
t/s
0
10.1.5 Sub-synchronous resonance due to HVDC: Sub-synchronous resonance at
HVDC Mundra-Mohindergarh at Mundra end has been observed in the past. The
Sub-synchronous study performed was based on the data of 660 MW units of
Mundra and there were no lines between Varsana and Bhachau. In the past the subsynchronous resonance has led to Bipole tripping and loss of generation at APL
during which SSR protection has acted but could not damp the sub-synchronous
resonance. As with the commissioning of 400 kV Bhachau-Varsana circuit, the
electrical distance between CGPL UMPP and Mundra Generation complex has
reduced significantly. Earlier any commutation fault on HVDC side is also felt only by
the Mundra generating complex and CGPL is located at large electrical distance.
However as of now both are experiencing the electrical jerks from these faults. In
view of this there is a chance that Sub-synchronous resonance is going to get
affected with the both generating complex. So, a sub-synchronous resonance study
of HVDC Mundra Mohindergarh considering 330/660 MW units of Mundra and 830
MW units of CGPL may kindly be done in order to take remedial action for damping
of the SSR.
Agenda notes - 39th SCMPSPWR
13
10.1.6 Nodes Experiencing High Voltage:
400 kV Nodes: Khandwa, Dehgam, Satpura, Koradi, Bhadrawati New Koyna,
Karad, Kolhapur, Chandrapur, Dhule , Solapur(MS) , Aurangabad (MS) , Bhilai ,
Rajgarh, Akola, Damoh, Birsinghpur, Katni, Bhatapara, Raigarh, RGPPL.
765 kV Nodes: Durg, Kotra, Raigarh Tamnar, Wardha, Aurangabad
10.2
NLDC may make presentation on the above issues.
Members may deliberate
11 LTA and Connectivity Application of NTPC Ltd. for Khargone TPP (2x660MW) and
Connectivity Application of 2x660MW Dwarkesh Energy Ltd. in Madhya
Pradesh
11.1 In the 38th SCM of WR the following transmission system associated with Khargone
TPP and Dwarkesh TPP was agreed:
A. Transmission System for Khargone TPP (1320 MW)
(i)
(ii)
LILO of one ckt of Rajgarh-Khandwa 400kV D/c line at Khargone TPP#
Khargaon TPP Switchyard – Khandwa pool 400kV D/c (Quad) line
B. Transmission System for strengthening of WR associated with Khargone
TPP (1320 MW)
(i)
(ii)
(iii)
765/400kV, 2x1500MVA pooling station at Khandwa pool.
Khandwa pool – Indore 765kV D/c line.
Khandwa pool – Dhule 765 kV D/C line.
Note: #The LILO shall be used for startup power and commissioning activities
requirement. After commissioning of balance transmission system, the LILO
would be bypassed at Khargone generation switchyard and may be utilized
only under contingency condition.
Transmission system under A is for connectivity for Khargone TPP and Transmission
system under B is for LTA of Khargone TPP
C. Transmission System for DEL TPP (1320 MW)
(i)
DEL TPP Switchyard – Khandwa pool 400kV D/c (Quad) line
Till date, DEL has applied only for connectivity and not for LTA. After receipt of LTA
application from DEL, the additional transmission strengthening required for transfer
of power would be identified.
11.2 In the 35th meeting of Empowered Committee on Transmission, the following
transmission scheme, to be implemented though tariff based competitive bidding,
was recommended for notification by Govt. of India:
Agenda notes - 39th SCMPSPWR
14
Scope of the Transmission Scheme
1. Connectivity system for Khargone STPP
(i) LILO of one ckt of Rajgarh-Khandwa 400kV D/C line at Khargone TPP (The
LILO shall be used for startup power and commissioning activities
requirement. After commissioning of balance transmission system, the LILO
would be bypassed at Khargone generation switchyard and may be utilized
only under contingency condition)
(ii)
2.
(i)
(ii)
(iii)
Khargone TPP Switchyard – Khandwa pool 400 kV D/C (Quad) line
System strengthening in WR in time frame of Khargone TPP
Khandwa Pool – Indore 765kV D/C line
Khandwa Pool – Dhule 765 kV D/C line
Establishment of 765/400kV, 2x1500MVA pooling station at Khandwa pool
765 kV
• ICTs: 7x500MVA, 765/400 kV (1 spare unit)
• ICT bays: 2 no.
• Line bays: 4 no. (2 no. for Khandwa pool – Indore 765 kV D/C & 2 no.
for Khandwa Pool to Dhule 765 kV D/C)
• Bus reactor: 3 X 80 MVAr
• Bus reactor bay: 1 no.
• Switchable Line reactors : 7 X 80 MVAr
(1 unit is as a spare unit) for
Khandwa Pool – Dhule 765 kV D/C
(each reactor with 800 Ω NGR alongwith its auxiliaries)
• Space for line bays (future): 4 no.
• Space for ICT bays (future): 3 no.
• Space for 1500 MVA, 765/400 kV ICTs (future) : 3 no.
400 kV
• ICT bays: 2 no.
• Line bays for termination of Khargone – Khandwa PS 400 kV D/C
line: 2 no.
• Bus reactor: 1 X 125 MVAr
• Bus reactor bay: 1
• Space for line bays (future): 6 no.
• Space for ICT bays (future): 3 no.
(iv) 2 nos. of 765 kV bays and 7 X 80 MVAr switchable line reactors (1 unit as
spare) along with 800 Ω NGR & its auxiliaries for Khandwa Pool – Dhule
765 kV D/C at Dhule 765/400 kV substation of M/s BDTCL
Total Estimated Cost (Rs. Crore)
Note:
• M/s PGCIL will provide 2 no. of 765 kV line bays for termination of Khandwa PS –
Indore 765 kV D/C line and 6 X 80 MVAR switchable line reactors along with 700
Ω NGR & its auxiliaries at 765/400 kV Indore S/s.
• M/s PGCIL will provide 400 kV, 63 MVAr switchable line reactor along with 500
ohm NGR and its auxiliaries at Rajgarh (PG) 400 kV S/s for Khargone TPP –
Agenda notes - 39th SCMPSPWR
15
Rajgarh 400 kV S/C line formed after LILO of one circuit of Khandwa – Rajgarh
400 kV D/C line at Khargone TPP.
• M/s BDTCL will provide space for 2 no. of 765 kV line bays for termination of
Khandwa Pool – Dhule 765 kV D/C alongwith 7 X 80 MVAr switchable line reactor
at 765 kV Dhule S/s.
• NTPC will provide 4 no. of 400 kV line bays at Khargone TPP (2 no. for
termination of Khargone – Khandwa Pool 400 kV D/C and 2 no. for LILO of one
circuit of 400 kV Rajgarh – Khandwa D/C).
• NTPC will provide 400 kV, 1 X 125 MVAr bus reactor along with 400 kV reactor
bay at Khargone TPP.
This is for kind information of the members.
12 Transmission system for Rewa Ultra Mega Solar Ltd. (750MW)
12.1
12.2
In 38th Meeting of Standing Committee on Power System Planning in Western
Region held on 17.07.2015, following transmission system for Rewa Ultra Mega
Solar Ltd. (RUMS) was agreed in-principle by the members with the assumption
that entire power would be evacuated through ISTS.
a.
LILO of Vindhyachal – Jabalpur 400kV 2nd D/c line (circuit-3&4) at Rewa
Pooling Station – 59KM (2x27 = 54Km D/C portion + 5Km M/C portion)
b.
Establishment of 400/220kV, 3x500 MVA Pooling station at Rewa
c.
1x125 MVAr bus reactor at Rewa Pooling Station
d.
6 Nos. 220kV Line bays at Rewa Pooling station (for its interconnection with
solar park)
In the meeting it was noted that the implementation of above system shall be taken
up only after receipt of LTA application from RUMS. Accordingly, RUMS has
applied for LTA of 750MW in Aug’15 with target region as WR: 350MW, ER:
350MW & WR: 50MW. Further, RUMS vide its letter dated 02.11.2015 informed
that the prospects of buyers in ER are not forthcoming. However, they are
envisaging prospective buyers in Northern Region who could buy solar power of
250-350MW. Subsequently, RUMS Ltd. has re-applied for LTA with only WR and
NR as target regions vide application dated 03.11.15. The revised target
beneficiaries for RUMS Ltd. are: WR – 450MW and NR – 300MW.
12.3 This is for kind information of the members.
13
Connectivity System for M/s Jinbhuvish Power Generations Pvt. Ltd. (JPGPL)
(600MW)
13.1 In 21st Meeting of WR constituents regarding Connectivity / Open Access
Applications held on 17.07.2015, following connectivity system for JPGPL was
agreed.
Agenda notes - 39th SCMPSPWR
16
(i) JPGPL TPS Switchyard – Warora Pool 400kV D/c line (to be implemented
through Tariff Base Competitive Bidding route)
The generation developer informed that the commissioning schedule of generating
units is Jan-2017 (1st unit) & March-2017 (2nd unit).
Considering above connectivity arrangement, following provisions need to be kept at
the generation switchyard which shall be under the scope of the M/s JPGPL.
(i) Generation step up Voltage
(ii) 400kV line bays
(iii) 420kV bus reactor
: 400kV,
: 2 nos.
: 1x125MVAR
Members may note
14 Connectivity System for NTPC-SAIL Power Co. Ltd. (2x250MW, Phase III, Stage-II)
14.1
NTPC-SAIL Power Co (P) Ltd (NSPCL) had applied for connectivity of its 500MW
generation project in Chhattisgarh as per the CERC regulation, 2009. The
application was initially discussed in 16th meeting of WR Constituents regarding
Connectivity / Open Access Applications held on 09.05.2012 wherein connectivity
was proposed to be granted through Bus extension of existing 400kV NSPCL
switchyard.
In the meeting, it was decided to defer the grant of connectivity till next meeting in
view of the very little progress with respect to fuel and environmental clearance
made by the generation project. Applicant was requested to keep the status of the
generating project informed so that their application may be processed accordingly.
After that no updates were received from generation developer.
14.2 The application was again discussed in 21st meeting of WR Constituents regarding
Connectivity / Open Access Applications held on 17.07.2015. NSPCL informed that
they are anticipating the COD of generation unit by 2018. He also informed that most
of the power would go to SAIL plant, hence only bus extension is sufficient for said
connectivity. Accordingly, it was decided that intimation for grant of connectivity with
bus extension of existing 400kV NSPCL switchyard to be issued. NSPCL to sign
connectivity agreement within 30 days, otherwise the grant of connectivity shall be
cancelled.
Members may note.
15 Open Access Meeting.
15.1 The 22nd meeting of WR constituents regarding connectivity/ open access applications
would be held after Standing Committee meeting. The agenda would be circulated by
POWERGRID.
16 Any other item with the permission of the chair.
Agenda notes - 39th SCMPSPWR
17
Status of TBCB Tr. Projects
S.
No.
Name of the Project
1.
Scheme for enabling
import of NER/ER
surplus by NR
Estimated Cost
1700 cr
2.
3.
System Strengthening
in NR for import of
power from North
Karanpura and other
projects outside NR
and
System
Strengthening in WR
for import of power
from
North
Karanpura and other
projects
outside
Western Region and
also for projects
within
Western
Region.
Estimated Cost
2700 cr.
Talcher-II
Augmentation System
Estimated Cost
1400 cr
BPC /
Implementing
Agency / Milestones
PFC
Scope of works
Annexure - I
Current Status
(i) Bongaigaon-Siliguri 400
kV Quad D/C
Line Commissioned in
11/2014
(ii) Purnea-Biharsharif 400
kV D/C Quad D/C
Line Commissioned in 9/2013
1. Sipat/Korba (Pooling) –
Seoni
2. Lucknow-Bareilly
3. Bareilly-Meerut
4. Agra-Gurgaon
5. Gurgaon-Gurgaon (PG)
6. Gurgaon S/S
Matter was in CERC for
revision of tariff and extension
of date of commissioning.
NKTCL filed an appeal in
appellate tribunal challenging
CERC order of 9.5.2013.
Appellate Tribunal has given
final judgment on 2.12.13
setting aside CERC order and
allowing the appeal. NKTCL is
initiating
steps
for
implementing of order. The
judgment of Appellate Tribunal
accepts delay in clearance
under section-164 as force
majeure. According NKTCL
have requested MoP to extend
the validity of section 68
clearance vide their letter dtd
14.1.2014
Beneficiaries have appealed
SC.
ENICL(Sterlite
Technologies Ltd)
Milestones :
(i)
LOI place on
7.1.2010,
(ii) SPV acquired on
31.3.2010
(iii) Trans. license
received
on
4.11.2010
(iv) Approval u/s 164
received
on
21.6.2011,
(v) Tariff adoption
on 2.11.2010
Original
March 2013
REC
COD:
NKTCL
(Reliance
Power Transmission
Company Ltd)
Milestones :
(i) SPV acquired by
Reliance on 2005-2010
(Effective date)
(ii) Approval u/s 164
received
on
12.08.2013.
REC
TTCL (Reliance
Power Transmission
Company Ltd.)
Milestones :
(i)
LOI issued on
18-12-2009.
(i)Talcher II- Rourkela 400
kV D/C Quad line
(ii)Talcher II – Behrampur
400 kV D/C line
(iii)Behrampur-Gazuwaka
400 kV D/C line
Work Yet to start.
Matter was in CERC for
revision of tariff and extension
of date of commissioning.
TTCL filed an appeal in
appellate tribunal challenging
CERC order of 9.5.2013.
Appellate Tribunal has given
final judgment on 2.12.13
setting aside CERC order and
S.
No.
Name of the Project
BPC /
Implementing
Agency / Milestones
(ii) SPV acquired by
Reliance on 2704-2010
(Effective date).
Scope of works
(iv)400/220 kV, 2x315
MVA Behrampur
substation
Current Status
allowing the appeal. TTCL is
initiating
steps
for
implementing of order. The
judgment of Appellate Tribunal
accepts delay in clearance
under section-164 as force
majeure. According TTCL have
requested MoP to extend the
validity of section 68 clearance
vide their letter dtd 14.1.2014.
Beneficiaries have appealed
SC.
Work yet to start.
4.
5.
Transmission System
Associated
with
Krishnapattnam
UMPP- Synchronous
interconnection
between SR and WR
(Part-B)
Estimated Cost
440 cr
System strengthening
common for WR and
NR
Estimated Cost
1720 cr
REC
(i) Raichur-Sholapur 765
kV S/C line-1-208 ckm
Commissioned on 30.6.2014
RSTCL(Consortium
of Patel-SimplexBSTranscomm)
Milestones:
(i)
LOI placed on
16.12.2010
(ii) SPV acquired on
7.1.2011
Trans.
license
received
on
24.8.2011
(iii) Approval u/s 164
received
on
29.8.2011.
(iv) Tariff adoption
on 12.8.2011
(v) Original COD :
Jan 2014
PFC
JTCL(Sterlite Grid)
Milestones:
(i)
LOI placed on
31.01.2011
(ii) Special Purpose
Vehicle acquired
on 31.03.2011
(iii)
Scheduled
Completion Date
is 31.03.2014.
(iv)
Transmission
License granted
on 12.10.2011.
(v) Tariff adoption
approval
on
28.10.2011
(vi) Clearance under
Section 164 :
received
on
12.07.13
(i) DhramjaygarhJabalpur 765 kV D/C 765
kV lines
Length-760ckm,
Locations-985,
Foundation-794,
Tower Erection-762,
Stringing completed-416ckm,
Progress affected due to
pending forest Clearance(284
Ha in MP and 114Ha in
Chhattisgarh) and Severe row
problem.
JTCL
informed,
stage-II
clearance has been issued in
MP and is pending in
Chhattisgarh.
Line
expected
to
commissioned by 09/15
be
S.
No.
Name of the Project
BPC /
Implementing
Agency / Milestones
6.
System strengthening
for WR
Estimated Cost
2900 cr
PFC
Scope of works
(ii) Jabalpur-Bina 765 kV
S/C line
BDTCL(Sterlite Grid)
Milestones:
(i)
LOI placed on
19.1.2011
(ii) SPV acquired on
31.3.2011
(iii) Trans. license
received
on
12.10.2011
(iv) Approval u/s 164
received
on29.01.2013
(v)
Tariff adoption
on28.10.2011
Original COD :
Mar2014
Current Status
Length-237ckm,
Locations-610,
Foundation-577,
Tower Erection-577,
Stringing completed-218ckm,
Progress affected due to
pending
forest
Clearance
(140Ha in MP) and Severe row
problem. JTCL informed that
Stage-II clearance has been
issued in MP in March-2015
Line expected to be
commissioned by 06/15
(i) Jabalpur-Bhopal 765 kV
S/C line
Length-260ckm,
Locations-664,
Foundation-644,
Tower Erection-633,
Stringing completed-234ckm,
Progress affected due to
pending
forest
Clearance
(112Ha in MP) and Severe row
problem. Stage-II Clearance is
pending in MP
7.
Transmission system
associated with IPPs
of
Nagapattinam/
Cuddalore
AreaPackage A
Estimated Cost
1025 cr
PFC
(ii) Bhopal-Indore 765 kV
S/C line
Line expected to be
commissioned by 06/15
Line commissioned in 10/14
PGCIL
Milestones:
(i) SPV acquired on
29/03/2012
(ii) Tr. License issued
on 15.7.2013
(iii) Tariff adoption
by CERC on
9.5.2013.
(iii)
Clearance U/s
164 received on
9.12.2013.
(iv) Scheduled COD
29.3.2015
(iii) 2x1500 MVA 765/400
kV substation at Bhopal
(iv) Bhopal-Bhopal
(MPPTCL) 400 kV D/c
quad line.
(v) Aurangabad-Dhule 765
kV S/C line
Commissioned in 7/2014
Commissioned in 7/2014
Line commissioned in 10/14
S.
No.
Name of the Project
BPC /
Implementing
Agency / Milestones
(30months
effective
from
20.6.13, date of
grant of license)
Scope of works
(vi) Dhule-Vadodara 765
kV S/C line
(vii) 2x1500 MVA, 765/400
kV substation at Dhule
Work awarded on
16.5.2014 to M/s
Gammon and M/s
IComm
(viii) Dhule Dhule(Msetcl)400 kV D/C
Line
(i) Nagapattinam Pooling
Station-Salem 765 kV
D/C line - 200ckm
8.
Transmission System
associated with IPPs
of Vemagiri AreaPackage A
PGCIL
Milestones:
SPV acquired
18/04/2012
9.
( ii) Salem-Madhugiri 765
kV S/C line –217km
REC
on
Transmission System
required
for
evacuation of power
from Kudgi TPS
(3x800 MW in PhaseI) of NTPC Limited.
REC
Estimated Cost
1240 cr
Milestones:
(i)
LOI placed
on31/07/13
(ii) SPV acquired on
30.8.2013
(iii) PG submitted on
22.8.2013
(iv)
Tr. License
application filed
in
CERC
on2.9.2013 and
application
for
tariff
adoption
filed on 2.9.2013.
Tr. License issued
on 7.1.2014 and
tariff adoption by
CERC
on
8.1.2014.
KudgiTCL (M/s L&T
Infrastructure
Development Projects
Limited)
(i) Vemagiri Pooling
Station–Khammam 765 kV
1xD/C (1stckt.) line.
(ii) Khamam-Hyderabad
765 kV 1xD/C (1stckt.)
line.
(i)Kudgi TPS – Narendra
400 kV 2xD/C line (I&II)
Current Status
Line ready for commissioning
on 02/15
CEA Inspection completed
and s/s is ready for
energisation since 28.2.14.
Line ready for commissioning
since 9/2014 (400 kV bays by
MSETCL at Dhule s/s is
under
construction
and
schedule for completion by
Mar 2015)
Length-400ckm,
Locations-543,
Foundation-401,
Tower Erection-197,
Stringing completed-36ckm
Length-217ckm,
Locations-619,
Foundation-225,
Tower Erection-55,
Stringing completed-Nil
Put on hold as commissioning
of the associated generating
station is delayed due to nonavailability of gas.
The scheme is under
consideration of CERC for
the decision of its
implementation.
Length-36ckm,
Locations-46,
Foundation-9,
Tower Erection-5,
Stringing completed-0ckm,
Scheduled completion :
28.02.2015(18month)
S.
No.
Name of the Project
BPC /
Implementing
Agency / Milestones
(v)
Clearance U/s
164 – issued
24.4.2014
(vi) Awarded EPC
contract 7.1.2014
(vii)
Detailed
contract signed on
24.2.2014
(viii) Financial
closure on
24.2.2014
10.
Transmission
for
strengthening
for import of
from ER
REC
system
system
in SR
power
Estimated Cost
1180 cr
Scope of works
(ii)Narendra (New) –
Madhugiri 765 kV D/C line
Vizag Transmission
Limited
Milestones:
(i) LOI placed on
31.07.13
(ii) Special Purpose
Vehicle acquired
on 30.8.2013
(iii) Tr. License issued
on 8/1/2014 and
tariff adoption by
CERC
on
23/1/2014
(iv) Clearance U/s 164
– received on
21.05.2014
(v) Schedule
COD
30.8.2016
(iii)Madhugiri – Bidadi 400
kVD/C Line
(i) Srikakulam PP –
Vemagiri-II Pooling
Station 765 kV D/c line334km
Current Status
Length-758ckm,
Locations-870,
Foundation-789,
Tower Erection-720,
Stringing completed-384ckm,
Scheduled completion :
31.12.2015 (28 months)
Length-186ckm,
Locations-256,
Foundation-221,
Tower Erection-189,
Stringing completed-36ckm,
Scheduled completion :
31.12.2015(28 months)
Length- 668ckm,
Locations-877,
Foundation-691,
Tower Erection-372,
Stringing completed-40ckm
Work awarded on
28.2.2014 to Tata
Proj. Icomm, L&T
and M/s Gammon
11
Transmission System
for Patran 400kV S/S
Estimated Cost
200 cr
PFC
PTCL (Techno
Electric and
Engineering Company
Ltd.)
Milestones:
(i) LOI placed
on
(ii)
Khammam(existin
g) – Nagarjuna Sagar 400
kV D/c line-145km
Length- 290ckm,
Locations-388,
Foundation-340,
Tower Erection-273,
Stringing completed-108ckm,
S.
No.
12
Name of the Project
Eastern
Region
System Strengthening
Scheme-VI
Estimated Cost
540 cr
BPC /
Implementing
Agency / Milestones
17.09.2013
(ii) SPVacquired on
13.11.2013
(iii) Application for
adoption of tariff
filed in CERC.
Hearing
on
18.03.2014.
(iv) Application for
grant of License
filed in CERC.
Hearing
on
18.03.2014
(v) Clearance under
Section 164 :
Request
not
received in MoP
Scheduled
COD:
13.05.2016.
Current Status
Work yet to award
Work yet to award
DMTCL (Essel
Infraprojects Ltd.)
Scheduled
01.07.2016.
Part ATS for RAPP
U-7&8 in Rajasthan
Estimated Cost
310 cr
LILO of both circuits of
Patiala-Kaithal 400kV D/c
at Patran (Triple snow Bird
Conductor)
(i) 2x500 MVA, 400/220
kV Substation at Patran
PFC
Milestones:
(i) LOI placed on
17.10.2013
Special Purpose
Vehicle acquired
on 10.12.2013
(ii) Tariff adoption
approval issued
by CERC on
20.5.2014
Transmission
license received
on 30.5.2014
(iii) Clearance u/s
164: received in
4/9/2014.
13
Scope of works
(ii) 2x500 MVA, 400/220
kV GIS Substation at
Darbhanga with space
for future extension
(1x500 MVA)
Land
100%
Civil work
15%
Equip Supply
0%
Equip. Erection 0%
(i) 2x200 MVA, 400/132
kV GIS Substation at
Mothihari with space for
future extension (1x200
MVA)
(ii) Muzaffarpur(PG)Darbhanga 400 kV D/c
line with triple snowbird
conductor
Land
100%
Civil work
7%
Equip Supply
0%
Equip. Erection 0%
COD:
PFC
RAPPTCL(Sterlite
Grid Ltd)
Milestones:
(i) LOI placed on
17/09/13
(ii) Special Purpose
Vehicle acquired on
Loc 173
Fdn
128
TE
106
STG
15/64 KM
S.
No.
14
15
Name of the Project
ATS of Unchahar
TPS
Estimated Cost
70 cr
Eastern
Region
System Strengthening
Scheme-VII
Estimated Cost
370 cr
BPC /
Implementing
Agency / Milestones
12/03/2014
(iii) Scheduled COD:
28.02.2016.
Clearance
under
Section 164 : Request
not received in MoP
REC
UnchaharTCL(PGCIL
)
Milestones:
(i) LOI placed on
14/02/14.
(ii) SPV acquired on
24/03/2014.
(iii) Transmission
license granted
(iv) Tariff
charged
adopted by CERC
and approval recd
on 3.7.2014
(v) Clearance
under
Section
164
:
Newspaper/Gazette
publication
completed,
Application
submitted
to
CEA/MoP is under
process.
PFC
PKTCL(Sterlite Grid
Ltd.)
Milestones:
(i) LOI placed on
17.09.2013
(ii) Special Purpose
Vehicle acquired
on 09.12.2013
(iii)
Application
for adoption of
tariff
filed
in
CERC. Hearing on
27.02.2014.
(iv) Application for
Scope of works
(iii) LILO of Barh –
Gorakhpur 400 kV D/c
line at Mothihari,
400kV 2xD/C quad
(iv) RAPP - Shujalpur
400kV D/C line
(i) Unchahar
Fatehpur400 kV D/C
line
(ii) Purulia PSP(WB) –
Ranchi (PG) 400 kV
D/C line
(iii) Chaibasa – Kharagpur
400 kV D/C line
Current Status
Loc 209
Fdn
109
TE
32
STG
0/76 KM
Engg work started and EPC
Contract awarded. work
expected to start by 11/2014.
Forest proposal (30 ha) has
been initiated.
Loc 521
Fdn 401
TE 482
Stg 227/310 ckm
Scheduled
23/09/2016
(1)Loc: 370
Fnd:302
Erec:35
Stg: 0/35
(ii)
Loc: 421
Fnd:318
Erec:279
Stg:38 cKM
completion
:
S.
No.
Name of the Project
16
NR
System
strengthening
Scheme-NRSSXXXI(Part-A)
Estimated Cost
225 cr
17.
Northern
Region
System Strengthening
Scheme,
NRSSXXXI (Part-B)
Estimated Cost
565 cr
BPC /
Implementing
Agency / Milestones
grant of License
filed in CERC.
Hearing
on
27.02.2014.
(v) Clearance under
Section 164 :
Request
not
received in MoP
(vi) Scheduled COD:
09.03.16.
REC
PGCIL
Milestones:
(i) LOI placed on
26/02/14.
(ii) Special Purpose
Vehicle acquired
on 12/05/2014.
(iii) Transmission
license granted
(iv) Tariff
charges
adopted CERC
(v) Clearance under
Section 164: is
under process will
be applied after
finalisation of land
for s/s which shall
be finalised by
Dec 2014.
REC
M/s Essel
Infraprojects Ltd
Milestones:
(i) LOI placed on
26/02/14.
(ii) SPV acquired on
12/05/2014.
(iii) Transmission
license
application filed
in CERC on
13/05/14.
(iv) Tariff adoption by
CERC:
under
process in CERC
for adoption.
(v) Clearance under
Section 164 :
submitted in MoP
in 9/2014
(vi) Scheduled
Scope of works
Current Status
(i) 7x105 MVA (1 phase),
400/220 kV GIS at Kala
amb
S/s package awarded to
siemens on Aug 2014
(ii) LILO of both ckt of
Karcham WangtooAbdullapur 400 kV D/c
line at Kala Amb(on
M/C tower)
Scheduled
12/07/2017
COD
(iii) 40% series
compensation on 400
kV Karcham Wangtoo –
Kala Amb D/C line at
Kala Amb end
(i) KurukshetraMalerkotla 400 kV
D/C line
1
Loc 375
Fdn 216
TE
100
Stg
2/139 km
(ii) Malerkotla-Amritsar
400 kV D/C line
2 loc 412
Fdn 198
TE 108
Stg 0/149 km
:
S.
No.
Name of the Project
18.
Northern
Regional
System Strengthening
Scheme,
NRSSXXIX
Estimated Cost
2621 cr
19.
20.
Transmission System
associated
with
DGEN TPS (1200
MW) of Torrent
Power Ltd.
275 cr
Transmission System
associated
with
Gadarwara
STPS
(2x800
MW)
of
NTPC (Part-A)
Estimated Cost
2525 cr
21.
Transmission System
associated
with
Gadarwara
STPS
(2x800
MW)
of
NTPC (Part-B).
Estimated Cost
2360 cr
BPC /
Implementing
Agency / Milestones
completion
:
12/09/2016
REC
Sterlite Technologies
Ltd.
Milestones:
The LoI has been
issued on 23.05.2014.
PFC
M/s Instalaciones
Inabensa, S.A. Spain
Milestones:
(i) LoI issued on
19.05.2014
(ii) Approval under
section 68 on
30.01.2014.
REC
PGCIL
Milestones:
(i) Date
of
issuance
of
RFQ
:15.08.2014
(ii) Date
of
RFP:14.11.201
4
(iii) Date of signing
of
TSA:
09.02.2015
REC
PGCIL
Milestones:
(i) Date of issuance
of
RFQ
:07.08.2014
(ii) Date
of
RFP:14.11.2014
(iii) Date of signing
of
TSA:
09.02.2015
Scope of works
(i) Jullandhar – Samba 400
kV D/C line
(ii) Samba – Amargarh 400
kV D/C line
(iii) GIS Sub- station at
Amargarh 400/220 kV
S/s.
(iv) LILO of both circuit
of Uri – Wagoora Line
400 kV D/C line.
(i) DGEN TPS – Vadodara
400 kV D/C, Twin
Moose line.
(ii) Navsari – Bhestan 220
kV D/C line
(i) Gadarwara STPSJabalpu Pool 765 D/C
line
(ii) Gadarwara STPSWarora P.S. (New) 765
D/C line
(iii) LILO of both Ckts. Of
Wardha-Parli 400 kV
D/C at Warora P.S.
(2xD/C).
(iv) Warora 765/400 kV P.S.
(2x1500 MVA).
(i) Warora P.S.-Parli (New)
765 kV D/C line
(ii) Parli(New)-Solapur 765
D/c line
(iii) Parli (New)-Parli (PG)
400 kV D/C (Quad) line
(iv) 765/400 kV Parli (New)
Sub-station (2x1500
MVA).
Current Status
(v) Approval for transfer
of SPV to selected
bidder is pending
with MoP
(vi) Scheduled
completion
:
05/08/18
S.
No.
Name of the Project
22.
Transmission System
Strengthening
associated
with
Vindhyachal- V
Estimated Cost
1050 cr
23
ATS
for
Tanda
Expansion
TPS
(2X660 MW)
Estimated Cost as
provided
by
Empowered
Committee:
Rs. 345 crore
Rs. 336 crore (as per
cost Committee)
25
System strengthening
for
IPPs
in
Chhattisgarh
and
other
generation
projects in Western
Region
Estimated Cost as
provided
by
Empowered
Committee:
Rs. 823 crore
Rs. 1285 crore (as per
cost Committee)
BPC /
Implementing
Agency / Milestones
REC
PGCIL
Milestones:
(i) Date of issuance
of
RFQ
:20.08.2014
(ii) Date
of
RFP:22.10.14
(iii)
SPV
has
been acquired by
the
successful
bidder
on
26.02.2015
(iv) Date of filing of
petition
for
adaptation
of
tariff and grant of
license:
26.02.2015
PFCCL
Milestones:
(i) MoP vide letter
dated
05.06.2013
&
Gazette
Notification
dated 20.05.13
appointed
PFCCL as BPC.
(ii) SPV
incorporated on
09.09.2013
(iii) LoI issued to the
successful
bidder
M/s.
Essel
Infraprojects
Limited
on
09.10.2015
PFCCL
Milestones:
(i) MoP vide letter
dated 15.01.2014
trans dated 15-072014 & Gazette
Notification dated
09.07.14
appointed PFCCL
as BPC.
(ii) SPV incorporated
on 24.12.2014
(iii) RFQ
notice
published
on
29.12.2015.
Scope of works
(i)
Vindhyachal P. SJabalpur P. S. 765 kV
D/C line.
Current Status
Completion Target:
June,2018
(1) Tanda TPS –Sohawal
400 kV D/C Line 400 kV
D/c. length 80 km
Under Bidding Process
(i) Gwalior 765/400 kV –
Morena 400 kV D/C
line 400 kV D/C
Length- 50 km
(ii) Establishment
of
substation at Morena
400/ 220 kV 2X315
MVA
(iii) Vindhyachal-IV & V
STPP – Vindhyachal
Pool 400 kV D/C
(Quad) 2nd line 400 kV
D/C Length-15 km
(iv) Sasan
UMPP
–
The process for Transfer of
SPV is under progress.
S.
No.
26
27
Name of the Project
Additional
System
Strengthening
for
Sipat STPS
BPC /
Implementing
Agency / Milestones
(iv) LoI issued to the
successful bidder
Adani Power Ltd
on 28.07.2015.
PFCCL
Milestones:
(i) MoP vide letter
dated 15.01.2014
trans dated 15-07Estimated Cost as
2014 & Gazette
provided
by
Notification dated
Empowered
09.07.14 appointed
Committee:
PFCCL as BPC.
Rs. 867 crore
(ii) SPV incorporated
Rs. 1097 crore (as per
on 23.12.2014
cost Committee)
(iii) RFQ issued on
01.01.2015.
(iv) LoI issued to the
successful bidder
Adani Power Ltd
on 28.07.2015
Additional
System
PFCCL
Strengthening
Scheme
for Milestones:
Chhattisgarh IPPs – (i) MoP vide letter
dated 15.01.2014
Part B
trans dated 15-072014 & Gazette
Estimated Cost as
Notification dated
provided
by
09.07.14 appointed
Empowered
PFCCL as BPC.
Committee:
(ii) SPV incorporated
Rs. 1930 crore
on 23.12.2014
Rs. 2260 crore (as per
(iii) RFQ
notice
cost Committee)
published
on
01.01.2015.
(iv) LoI issued to the
successful bidder
Adani Power Ltd
on 28.07.2015
Scope of works
Vindhyachal
Pooling
station 765 kV S/C line
765 kV S/C Length-8
km
(v) LILO of one circuit of
Aurangabad – Padghe
765 kV D/C line at Pune
765 kV D/C
Length-50 km
(i) Sipat – Bilaspur Pooling
Station765 kV S/C line
765 kV S/C Length25 km
(ii) Bilaspur Pooling Station
- Rajnandgaon 765 kV
D/C line
765 kV
D/C
Length-180
km
(i) Raipur (Pool) –
Rajnandgaon 765 kV
D/C line
765 KV
D/C
Length-60
KM
(ii) Rajnandgaon – New
Pooling station near
Warora 765 kV D/C line
765 KV D/C
Length- 270 KM
(iii) Establishment of new
substation
near
Rajnandgaon
765/400kV
2x1500 MVA
Current Status
The process for Transfer of
SPV is under progress.
The process for Transfer of
SPV is under progress.
S.
No.
Name of the Project
28
Additional
interRegional AC link for
import into Southern
Region i.e. Warora –
Warangal
and
Chilakaluripeta
Hyderabad - Kurnool
765kV link
Estimated Cost as
provided
by
Empowered
Committee:
Rs. 7760 crore
29
BPC /
Implementing
Agency / Milestones
PFCCL
Milestones:
(i) MoP vide Gazette
Notification dated
06.02.15 appointed
PFCCL as BPC.
(ii) SPV incorporated
on 0.04.20155RFQ
notice published
on 23.04.2015.
(iii) RfQ
responses
received
and
opened
on
22.05.2015. RfQ
evaluation
completed.
(iv) The revised RfQ
has been re-issued
on 11.09.2015 with
submission
of
response due on
12.10.2015.
(v) 5
nos.
RfQ
responses received
on schedule date
i.e 12.10.2015 and
opened on the
same day. The RfQ
evaluation is under
progress.
Common
Transmission System PFCCL
for
Phase-II Milestones:
Generation Projects (i) MoP vide Gazette
Notification dated
in
Odisha
and
06.02.15 appointed
Immediate
PFCCL as BPC.
Evacuation System
for OPGC (1320 (ii) SPV incorporated
on 17.04.2015
MW)
Project
in
(iii) RFQ
notice
Odisha
published
on
23.04.2015.
Estimated Cost as
Scope of works
(i) Establishment of
765/400kV substations
at Warangal (New) with
2x1500 MVA
transformers and 2x240
MVAR bus reactors.
765/400kV
(ii) Warora Pool –
Warangal (New) 765kV
D/c line with 240
MVAR switchable line
reactor at both ends.
765 KV D/C
Length- 350 KM
(iii) Warangal (New) –
Hyderabad 765 kV D/c
line with 330 MVAR
switchable line reactor
at Warangal end.
756 KV D/C
Length- 160 KM
(iv) Warangal (New) –
Warangal (existing) 400
kV (quad) D/c line.
400KV D/C Length10 KM
(v) Hyderabad – Kurnool
765 kV D/c line with
240 MVAR switchable
line reactor at Kurnool
end. 765 KV D/C
Length- 170 KM
(vi) Warangal (New) –
Chilakaluripeta 765kV
D/c line with 240
MVAR switchable line
reactor at both ends.765
KV D/C Length-250
(vii) Cuddapah – Hoodi
400kV (quad) D/c line
with 63 MVAR
switchable line reactor
at both ends. 400 KV
D/C
Length-200
(i) OPGC (IB TPS) –
Jharsuguda
(Sundargarh)
400kV
D/C line with Triple
Snowbird
Conductor
400
kV
D/C
Length- 50 KM
(ii) Jharsuguda
(Sundargarh)– Raipur
Pool 765 kV D/C line
765
KV
D/C
Length- 350 KM
Current Status
Under Bidding process
Under Bidding process
S.
No.
30
32
Name of the Project
BPC /
Implementing
Agency / Milestones
provided
by
Empowered
Committee:
Rs. 2748 crore
Creation of new
400kV
GIS PFCCL
Substations
in Milestones:
(i) MoP vide Gazette
Gurgaon and Palwal
Notification dated
area as a part of ISTS:
22.07.15 appointed
Rs 1759 crore
PFCCL as BPC.
(ii) The agenda for
approval of the
incorporation
of
SPV has been
approved by the
PFC board on
23.09.2015.
(iii) The RfQ is issued
from 15.10.2015
with the last date
of submission of
response
16.11.2015.
Strengthening
of
transmission system
beyond Vemagiri
REC
TPCL
Milestones:
1Date of Notification
09.02.2015
2 Date of RFQ
12.04.2015
3 Date of RFP
10.07.2015
4 Date of
announcement of
successful bidder
21.10.2015
5 Date of issue of LoI
Scope of works
(i) Aligarh–Prithala 400kV
D/C HTLS line
(ii) Prithala–Kadarpur
400kV D/C HTLS line
(iii) Kadarpur–Sohna Road
400kV D/C HTLS line
(iv) LILO of Gurgoan–
Manesar D/C line at
Sohna Road
(v) Neemrana
(PG)–
Dhonanda
(HVPNL)
400kV D/C HTLS line
(vi) Creation
of
400/220kV,
2X500
MVA GIS substation at
Kadarpur in Gurgaon
area.
(vii) Creation of 400/220
kV, 2X500 MVA GIS
substation at Sohna
Road in Gurgaon area.
(viii) Creation of 400/220
kV, 2X500 MVA GIS
substation
at
PrithalainPalwal area
(ix) To cater to the future
load growth of the area,
space provision for
capacity augmentation
by 2X500 MVA
transformations at all
these substations may
be kept.
(x) 2Nos.of bays at 400kV
Dhonanda (HVPNL) S/s
Current Status
Under Bidding process
Under Bidding process
S.
No.
Name of the Project
33
Transmission System
Strengthening
in
Indian System for
transfer of power
from new HEPs in
Bhutan
34
35
Transmission System
for NER System
Strengthening
Scheme-II
System Strengthening
Scheme in Northern
Region
(NRSSXXXVI) along with
LILO
of
SikarNeemrana 400 kV
D/c line at Babai
(RRVPNL)
BPC /
Implementing
Agency / Milestones
29.10.2015
6 Date of acceptance
of offer 02.11.2015
REC
TPCL
Scope of works
Under Bidding process
Milestones:
1 Date of
Notification
09.02.2015
2 Date of RFQ
16.04.2015
3 Date of RFP
08.07.2015
4 Date of
announcement of
successful bidder
21.10.2015
5 Date of issue of
LoI 29.10.2015
6 Date of acceptance
of offer 03.11.2015
REC
TPCL
Milestones:
1 Date of
Notification
09.02.2015
2 Date of RFQ
23.04.2015
3 Response to RFQ
opened on 25.05.2015
REC
TPCL
Milestones:
1 Date of
Notification
24.07.2015
2 Date of RFQ
25.08.2015
Current Status
Under Bidding process
LILO of Sikar- Neemrana
400 kV D/c line at Babai
(RRVPNL)
Under Bidding process
Annexure ‐ 2
S. No.
1
STATUS OF TRANSMISSION SCHEMES UNDER IMPLEMENTATION BY POWERGRID IN WESTERN REGION
Date of firming Estimated Date of up in WR Target date as of Description of Scheme
Cost (Rs.
investment Remarks
standing now
Cr)
approval committee
July’06
Western Region System Strengthening Scheme ‐ II
5222
20th (23.01.04)
Set‐A: For absorbing import in eastern and central part
1700
Commissioned
of WR Grid (POWERGRID)
Set‐B: For regional strengthening in Southern
1050
Commissioned
Maharashtra (100 % private)
Set‐C: For regional strengthening in Gujarat (100 %
600
‐‐‐
Implementation by Reliance private)
a) Rajgarh – Karamsad 400kV D/c
‐‐‐
b) Limdi(Chorania) – Ranchodpura 400kV D/c
commissioned
c) Ranchodpura – Zerda(Kansari) 400kV D/c
Set‐D: For regional Strengthening in Northern Madhya
Pradesh (POWERGRID)
commissioned
Western Region System Strengthening ‐V
2
1050
722
commissioned
25th (30.09.06)
Dec’07
Under implementation a) 400 kV Vapi‐ Kala ‐ Kudus D/c
Jun'16
b) LILO of 400 kV Lonikhand ‐ Kalwa line at Navi
Mumbai
Dec'15
Substation is ready and shall be commissioned matching with line
Commissioned
c) Establishment of 400/220 kV, 2 x 315 MVA new S/s
(GIS) at Navi Mumbai
d) 220 kV Vapi‐ Khadoli D/c.
Tr. System of Mundra Ultra Mega Power Project (4000
MW) a) Mundra – Bachchau ‐Ranchodpura 400 kV (Triple)
D/c
b) Mundra – Jetpur 400 kV (Triple) D/c
4824
26th (23.02.07)
Oct’08
Under implementation Commissioned
Commissioned
c) Mundra – Limbdi 400 kV (Triple) D/c
Commissioned
d) Gandhar‐Navsari 400 kV D/c
Commissioned
e) Navsari ‐ Boisar 400 kV D/c
Mar'16
3
f) LILO of both circuits of Kawas‐Navsari 220 kV D/c at
Navsari (PG)
Severe ROW & Forest issue. Forest Clearance awaited.
Commissioned
g) Wardha‐Aurangabad 400 kV(Quad) D/c (with
provision to upgrade at 1200 kV at later date)
g) Aurangabad (PG) ‐Aurangabad I (Waluj) 400
kV(Quad) Substations
a) 40% Fixed Series Compensation each on Wardha ‐
Aurangabad 400 kV D/c at Wardha end
b) Establishment of new 400/220 kV, 2x315 MVA
substation at Navsari & Bachchau
c) Establishment of new 765/400 kV, 3x1500 MVA,
substation at Wardha for charging of Seoni ‐ Wardha
2xS/c lines at 765 kV level
Transmission system associated with Krishnapatnam
(5x800 MW) (WR Portion)‐ now delinked from
Krishnapatnam UMPP
a) Raichur – Solapur (PG) 765 kV S/c
Vapi‐Kala portion commissioned in Mar'14. Kudus S/s being implemente by MSETCL.
Cable work in progress. Critical ROW issues
Dec'16
Both Contracts terminated due to unsatisfactory performance. Tender awarded for 1 package and fresh tender being taken up for the other package.
Commissioned
Jun'16
Commissioning matching with the line
Commissioned
Commissioned
1928
27th (30.07.07)
Under implementation
Commissioned
S. No.
4
STATUS OF TRANSMISSION SCHEMES UNDER IMPLEMENTATION BY POWERGRID IN WESTERN REGION
Date of firming Estimated Date of up in WR Target date as of Description of Scheme
Cost (Rs.
investment Remarks
standing now
Cr)
approval committee
b) Solapur(PG) – Pune 765 kV S/c
Commissioned
c) LILO of 400kV Aurangabad I (Waluj) ‐ Pune (PG) D/c
& Parli (PG) ‐ Pune (PG) D/c lines at Pune(GIS) Nov'15
d) Establishment of new 765/400 kV substations at
Pune (GIS) with 2x1500 MVA transformation capacity
Commissioned
Associated transmission system of VSTPP‐IV and
Rihand‐III
5
7
29th (10.09.09)
Mar’10
Ready for commissioning
b) Vindhyachal IV ‐ Vindhyachal Pool 400kV D/c(Quad)
Commissioned
c) Vindhyachal Pool ‐ Satna 765 kV 2xS/c
Commissioned
d) Satna ‐Gwalior 765 kV 2xS/c
Commissioned
e) Gwalior – Jaipur(South) 765 kV S/c
Commissioned
f) Vindhyachal Pool‐Sasan 765 kV S/c
Commissioned
Commissioned
63.32
30th (08.07.10)
Oct'13
b) Augmentation of 400/220kV ICT by 1x500MVA
transformer (3rd) at Solapur (PG)
Solapur STPP (2x660MW) transmission system (Part‐
A)
Transmission system for evacuation of Kakrapar
Atomic Power Project unit 3 &4 (2x700 MW)
a) Kakrapar NPP – Navsari 400kV D/c – 38 km
50.52
36th (29.08.13)
Mar'15
Award placed in May'15
Mar'17
378.71
31st (27.12.10)
Feb'14
Under Implementation
Oct'16
Oct'16
1575.3
32nd (13.05.11) Sep'13
Under Implementation
May'16
b) Betul– Khandwa 400KV D/c (Quad)‐180 km
May'16
May'16
May'16
33rd (21.10.11) ‐
29th (10.09.09) May'11
Sep'16
ICT commissioned in Mar'15. Balance work under progress.
Under Implementation
a) Champa Pooling Station ‐ Raipur Pooling Station
765kV D/c
One ckt commissioned
b) Raigarh Pooling Staiton (near Kotra) ‐ Raigarh
pooling (near Tamnar) 765kV D/c
Commissioned
c) Champa Pooling Station ‐ Dharamjaygarh Pooling
Station 765kv S/c
Commissioned by‐
passing Champa Pool
d)Raigarh Pooling Staiton (near Kotra) ‐ Champa
pooling 765kV S/c
e) Establishment of 765/400kV 6x1500MVA Champa
Pooling Station
Line completed in Apr'15
Commissioned
c) Khandwa – Indore(PG) 400kV D/c ‐215 km
d) Establishment of 400/220kV 2x315MVA substation
at Betul Provision of 1x315MVA ICT & Spare Converter Trf for
10 reliable auxlliary power supply at HVDC back to back
143
station at Bhadravati
Establishment of Pooling Station at Champa and Raigarh (Near Tamnar) for IPP Generation Projects in 2066.85
Chhattisagrh
11
Under implementation
Ready for commissioning
a) Solapur STPP – Solapur (PG) 400kV D/c (Quad)
b) Kakrapar NPP – Vapi 400kV D/c ‐ 104 km
Transmission System associated with Mauda Stage‐II
(2x660 MW)
a) Mauda II – Betul 400KV D/c (Quad)‐210 km
9
One ckt charged at 400kV on 26.06.14 by‐passing Vindhyachal PS. Commissioned
MVA
a) Solapur STPP – Solapur (PG) 400kV 2nd D/c (Quad)
8
Under implementation a) Rihand III‐ Vindhyachal Pool 765 kV D/c (initially to
be op. at 400kV)
g) Vindhyachal Pool‐Sasan 400 kV D/c
h) Establishment of 765/400kV, 2x1500
substation at Vindhyachal Pool
Solapur STPP(2x660MW) transmission system
6
4673
LILO of Parli (PG)‐Pune (PG) at Pune (GIS) commissioned
Other ckt terminated at D'jaygarh bypassing Champa
Commissioned
Jun'16
ICTs to be commissioned with C‐K HVDC Link
STATUS OF TRANSMISSION SCHEMES UNDER IMPLEMENTATION BY POWERGRID IN WESTERN REGION
Date of firming Estimated Date of S. up in WR Target date as of Description of Scheme
Cost (Rs.
investment Remarks
No.
standing now
Cr)
approval committee
f)Establishment of 765/400kV 3x1500MVA Raigarh
Commissioned
Pooling Station (near Tamnar)
Transmission system strengthening in Western Part of
2127.51 29th (10.09.09) Nov'11
Under Implemetation
WR for IPP generation proejcts in Chhattisgarh
Stage‐I Forest Clearance a) Aurangabad(PG) – Boisar 400kV D/c (Quad)
Jun'16
received in Aug'15
12 b) Wardha ‐ Aurangabad (PG) 765kV D/c
Commissioned
c) Establishement of 765/400kv 2x1500MVA
Commissioned
auraganbad (PG) S/s
d) Augmentation of transformation capacity at Boisar
Commissioned
by 400/220kV, 1x500MVA
System strengthening in North/West part of WR for
2073.26 29th (10.09.09) Dec'11
Under Implementation
IPP Projects in Chhattisgarh
Matching with Kudus S/s of Sep'16
a) Aurangabad (PG) – Padghe(PG) 765kV D/c
MSETCL
13
b) Vadodara – Asoj 400kV D/c(Quad)
Commisisoned
Matching with Kudus S/s of c) Padghe – Kudus 400kV D/c (Quad)
Sep'16
MSETCL
System Strengthening in Raipur‐Wardha Corridor for
1422.85 29th (10.09.09) Jan'12
Under Implementation
IPP projects in Chhattisgarh (DPR‐6)
14
Stage‐I Forest Clearance a) Raipur Pooling station ‐ Wardha 765kV 2nd D/c
Jun'16
received in Jun'15
29th (10.09.09) WR‐NR HVDC interconnector for IPP Projects in
9569.76
Mar'12
Under Implementation
Chhattisgarh
/30th (08.07.10) a) A + 800kV, 3000Mw HVDC bipole between Champa
Pooling Station‐Kurukshetra (NR) (provision to upgrade
to 6000MW at a latter date)
b) Kurukshetra(NR) ‐ Jallandhar 400kV D/c(Quad) one
ckt. via 400/220kV Nakodar 15
c) LILO of Abdullapur – Sonepat 400kV D/c(triple) at
Kurukshetra
d) Establishment of 3000MW 800KV HVDC bipole
terminal each at Champa Pooling station and
Kurukshetra(NR) respectively: to be upgraded to
6000MW.
e) Establishment of 400/220kV 2x500 MVA S/s at
Kurukshetra (GIS) 2x500MVA
Inter‐regional system strengthening scheme for WR
16 and NR‐Part A
a) Solapur ‐ Aurangabad 765kV D/c
Jun'16
Completion matching with HVDC Champa Station.
Dec'15
Dec'15
Jun'16
Dec'15
1315.9
Transmission System Associated with Lara STPS‐I
400.47
(2x800MW)
a) Lara STPS‐I – Raigarh (Kotra) Pooling Station 400 kV
17
D/c line – 18km
b) Lara STPS‐I – Champa Pooling Station 400 kV D/c
(quad) line.‐112km
Transmission System Strengthening in WR‐NR
5151.37
Transmission Corridor for IPPs in Chattisgarh
a) Up‐gradation of + 800kV, 3000MW HVDC bipole
18
between Champa Pooling Station – Kurukshetra (NR) to
6000MW
b) Kurukshetra (NR) – Jind 400kV D/c (Quad)
Inter‐regional system strengthening scheme for WR
6517.36
and NR‐Part B
(a) 765KV D/C Jabalpur Pooling Station ‐ Orai line 36th (29.08.13) Oct'13
Completed
Commissioned
th 17 LTA (03.01.13) Jun'14
Under Implementation
Dec'15
Apr'17
35th (03.01.13) Jun'14
Tower erection commenced in Oct'15
Award under progress
Mar'18
Mar'18
Dec'14
Award placed in Mar'15
Apr'18
(b) 765KV D/C Orai ‐ Aligarh line Apr'18
19 (c) 400KV D/C Orai ‐ Orai line (Q)
Apr'18
S. No.
STATUS OF TRANSMISSION SCHEMES UNDER IMPLEMENTATION BY POWERGRID IN WESTERN REGION
Date of firming Estimated Date of up in WR Target date as of Description of Scheme
Cost (Rs.
investment Remarks
standing now
Cr)
approval committee
(d) LILO of one ckt of Satna‐Gwalior 765KV 2x S/C line
Apr'18
at Orai
(e) LILO of Agra ‐ Meerut 765KV S/C at Aligarh
Apr'18
(f) LILO of Kanpur ‐ Jhatikara 765KV S/C at Aligarh
Wardha ‐ Hyderabad 765kV Links
(a) 765KV D/C Wardha ‐ Hyderabad line 20
(b) 400KV D/C Nizamabad ‐ Dichpali line Apr'18
3662.02
Jan'15
May'18
May'18
GREEN ENERGY CORRIDORS:‐ Inter State Transmission 3705.61
Scheme (ISTS) ‐ Part B
36 / 37th
(29.08.13 /05.09.14)
Apr'15
Award placed in July'15
Apr'18
(a) 765KV D/C Banaskanta ‐ Chittorgarh (New) line 21
Apr'18
(b) 765KV D/C Chittorgarh (New) ‐ Ajmer (New) line Apr'18
(c) 400KV D/C Banaskanta ‐ Sankhari line (d) Establishment of 765/400/220kV (765/400kV ‐ 2x1500 MVA & 400/220kV ‐ 2x500MVA) substation at Banaskanta Apr'18
GREEN ENERGY CORRIDORS:‐ Inter State Transmission 2247.37
Scheme (ISTS) ‐ Part C
22 (a) 765KV D/C Bhuj Pool ‐ Banaskanta line (d) Establishment of 765/400/220kV (765/400kV ‐ 2x1500 MVA & 400/220kV ‐ 2x500MVA) pooling station at Bhuj Transmission System Strengthening Associated with Vindhyachal V ‐ Part A
23
(a) 1x1500MVA, 765/400kV ICT at Vindhyachal Pooling Station
Transmission System Strengthening Associated with Vindhyachal V ‐ Part B
(a) 2 nos of 765kV Line bays alongwith 2x330MVAR Line 24
Reactor at Vindhyachal Pooling Station
(a) 2 nos of 765kV Line bays alongwith 2x330MVAR Line Reactor at Jabalpur Pooling Station
36 / 37th
(29.08.13 /05.09.14)
July'15
Award under progress.
July'18
July'18
34th (09.05.12)
Feb'15
Award placed in Aug'15
July'17
Investment Approval pending
34th (09.05.12)
Jun'18
Jun'18
STATCOMs in Western Region
25
Award placed in Mar'15
36th (29.08.13)
Mar'15
(a) Aurangabad
Sep'17
(b) Gwalior
Sep'17
Award under progress
(c) Solapur
Sep'17
Award placed in Jun'15
(d) Satna
Western Region System Strengthening Scheme XIV
93.96
37th (05.09.14)
Award placed in Jun'15
Sep'17
Award placed in Jun'15
30 Months from date of investment approval
26 (a)2x500MVA, 400/220kV transformer alongwith six
nos of 220kV bays at Indore (PG) 765/400kV Substation
(b)1x500MVA, 400/220kV transformer alongwith two
nos of 220kV bays at Itarsi (PG) 400/220kV S/s
Powergrid works associated with Part‐A of Transmission system for Gadarwara STPS of NTPC
27
36/37th
(29.08.13 / 05.09.14)
Matching with TBCB Schedule
36/37th
(29.08.13 / 05.09.14)
Matching with TBCB Schedule
(a) 2 nos. 765 kV line bays at 765/400kV Jabalpur
Pooling Station of POWERGRID {for Gadarwara STPS
(NTPC) ‐ Jabalpur PS 765 kV D/c}
Powergrid works associated with Part‐B of
Transmission system for Gadarwara STPS of NTPC i.e.
WRSS XV
STATUS OF TRANSMISSION SCHEMES UNDER IMPLEMENTATION BY POWERGRID IN WESTERN REGION
Date of firming Estimated Date of S. up in WR Target date as of Description of Scheme
Cost (Rs.
investment Remarks
No.
standing now
Cr)
approval committee
(a) 2 nos. 765 kV line bays at 765/400kV Solapur sub‐
28 station of POWERGRID {for Parli New (TBCB) ‐ Solapur
(PG) 765 kV D/c}
(b) 2 nos 400kV line bays at existing 400kV Parli (PG)
Switching Station of POWERGRID {for Parli New (TBCB) ‐
Parli (PG) 400kV D/c (quad)}
Powergrid works associated with System 36th Matching with TBCB Strengthening for IPPs in Chhattisgarh and other (29.08.13) Schedule
generation projects in Western Region
(a) 1 no. 765 kV line bay at 765/400kV Vindhyachal
Pooling Station of POWERGRID {for Sasan UMPP ‐
Vindhyachal PS (PG) 765 kV 2nd S/c}
(b) 2 no. 400 kV line bays at 765/400kV Vindhyachal
Pooling Station of POWERGRID {for Vindhaychal (IV/V)
STPP switchyard (NTPC) ‐ Vindhyachal PS (PG) 400 kV
2nd D/c (quad)}
(c) 2 no. 400 kV line bays at Gwalior Substation {for
Gwalior ‐ Morena 400 kV D/c (quad)}
(d) 2 nos. 765 kV line bays at 765/400kV Pune (GIS) sub‐
station of POWERGRID {for LILO of one circuit of
29
Aurangabad(PG) – Padghe(PG)765 kV D/c at Pune (GIS)
(PG)}
(e) 2 nos. 765 kV line bays at 765/400kV Champa
Pooling Station of POWERGRID {1for Champa PS(PG) ‐
Raigarh (Kotra) PS(PG) 765 kV 2nd S/c, 1 for Champa
PS(PG) – Dharamjaigarh(PG) 765 kV 2nd S/c}
(f) 1 no. 765 kV line bay at 765/400kV Raigarh (Kotra)
Pooling Station of POWERGRID {for Champa PS(PG) ‐
Raigarh (Kotra) PS(PG) 765 kV 2nd S/c}
(g) 1 no. 765 kV line bay at 765/400kV Dharamjaigarh
Pooling Station of POWERGRID {for Champa PS(PG) –
Dharamjaigarh(PG)765 kV 2nd S/c}
Powergrid works associated withAdditional System Strengthening Scheme Chhattisagrh IPPs Part‐B
30
36/37th
(29.08.13 / 05.09.14)
DPR under Preparation
36/37th
(29.08.13 / 05.09.14)
DPR under Preparation
(a) 2 nos. 765 kV line bay at 765/400kV Raipur Pooling Station of POWERGRID {for Raipur PS(PG) – Rajnandgaon (TBCB) 765 kV D/c}
Powergrid workds associated with Additional System Strengthening for Sipat STPS
(a) 3 nos. 765 kV line bays at 765/400kV Bilaspur Pooling Station of POWERGRID (1 no. for Sipat 31
STPS(NTPC) ‐ Bilapur PS(PG) 3rd 765kV S/c, 2 nos. for Bilaspur PS(PG)‐Rajnandgaon(TBCB) 765 kV D/c)
(b) 2 nos. 240 MVAR, 765 kV switchable line reactors at 765/400kV Bilaspur PS end for Bilaspur PS(PG) ‐ Rajnandgaon(TBCB) 765 kV D/c
Transmission System Strengthening associated with 32 Mundra UMPP‐ Part A
(a) LILO of both circuits of Mundra UMPP‐Limbdi 400kV D/c (triple snowbird) line at Bachau
266.19
36th(29.08.13)
30 months from date of investment approval
STATUS OF TRANSMISSION SCHEMES UNDER IMPLEMENTATION BY POWERGRID IN WESTERN REGION
Date of firming Estimated Date of S. up in WR Target date as of Description of Scheme
Cost (Rs.
investment Remarks
No.
standing now
Cr)
approval committee
36/38th
Transmission System Strengthening associated with (29.08.13 33 Mundra UMPP‐ Part B
DPR under Preparation
/17.07.2015)
(a) Mundra UMPP ‐ Bhuj Pool 400kV D/c line (triple snowbird)
13/14th LTA
Bays for Transmission System Associated with DGEN (27.12.10 DPR under Preparation
/13.05.2011)
34 Torrent Energy Ltd (1200MW)
(a) 2nos 400kV Bays at Vadodara (GIS)
(b) 2nos 220kV Bays at Navsari (GIS)
Western Region System Strengthening ‐16
(a) Installation of 2x500MVA, 400/220kV ICTs with associated bays at Parli (PG) switching station along with provision of six nos. of 220 kV bays
(b) Provision of two nos. of 220kV bays at Raipur (PG) S/s
35 (c) Provision of two nos. of 220kV bays at Mapusa (Colvale) 400/220 kV substation
(d) Installation of 500MVA, 400/220kV (3rd) ICT with associated bays at Satna (PG) S/s with provision of two nos. 220kV line bays (e) Provision of two nos. of 400 kV bays at 765/400kV Indore(PG) substation
38th (17.07.15)
DPR under preparation
Annexure-III
Report on MSETCL proposal of shifting of Aurangabad I (Waluj) – Pune (PG) 400kV
D/C line from 400kV Aurangabad I (Waluj) to 765/400kV Aurangabad (PG)
In the 38th SCM of WR held on 17.07.2015, MSETCL has proposed shifting of
Aurangabad I (Waluj) – Pune (PG) 400kV D/C line from 400kV Aurangabad I (Waluj) to
765/400kV Aurangabad (PG) to remove the constraints for import of power in
Maharashtra control area. The loading on the 2X1500 MVA 765/400 kV ICTs at
Aurangabad (PG) substation and Aurangabad (PG) - Aurangabad I (Waluj) 400 kV inter
connection was the limiting factor for import of power in Maharastra from ISTS. In the
meeting, it was agreed that MSETCL proposal of shifting Aurangabad I (Waluj) – Pune
(PG) 400kV D/C line from 400kV Aurangabad I (Waluj) to 765/400kV Aurangabad (PG)
would be studied jointly by CEA, CTU, WRLDC and MSETCL.
The peak demand met by Maharastra in August 2015 is 18447 MW. Accordingly, load
flow studies was carried out by taking recent load flow file from WRLDC for a demand of
18,445 MW in Maharashtra. In the studies intrastate generation of Maharashtra of
11893.4 MW (Tirora – 2418MW, Koyna – 552.8, Jaigad – 1000MW, Amravati- 750 MW)
and import of about 6500 MW from ISTS has been considered.
Load generation balance for Maharashtra Area is given below:
GENE- FROM IND TO IND
TO TO BUS GNE BUS TO LINE FROM TO TO TIE TO TIES
X-- AREA --X RATION GENERATN MOTORS LOAD SHUNT DEVICES SHUNT CHARGING LOSSES LINES + LOADS
3012
11893.4
MAHARASHTRA 119.0
0.0
0.0
0.0
0.0
17784.0
0.0
2598.7 -2104.9
0.0
0.0
0.0
4026.9
0.0
11560.1
671.1 -6561.6 -6631.5
7049.8
108.6
98.5
COLUMN
TOTALS
0.0
0.0
0.0
0.0
17784.0
2598.7
0.0
0.0
0.0
4026.9
0.0
11560.1
671.1 -6561.6 -6631.5
7049.8
108.6 98.5
11893.4
119.0
0.0
-2104.9
The generation dispatch from Maharashtra intrastate generation projects is given below:
Bus No.
331002
331006
331007
331013
331122
331156
331192
331202
331249
331252
331268
331283
331309
331314
331323
331326
332005
332011
332019
332020
Bus Name
BHIPU1
BHIRA1
KHOPO1
BHUSA1
KHAPRALE
BHANRDHR
DAUND
VAITRAN
VIR-HYDR
ELDARI
BHATGHAR
MUKHED
VARASGN
MANDRUP
PANSHET
UJANI-HY
URAN
KOYNA 3-2
KARAD
KOYNA 1-2
MW
70.4
138
45.2
0
7
36
15
0
3
15
13
18
7
12
7
0
265
0
0
50
Bus
No.
332097
332101
332105
332109
332120
332132
332136
332140
332154
332165
332171
332174
332175
332179
332182
332183
332185
332190
332198
332199
Bus Name
BHIRA
VITA
PARAS
JAMDE
BHIGWAN
PURTY
GHATNDAR
GHATGHAR
NIGHDE
PAWAS
SUN-FLEG
VALVE
GANGAPUR
INDORAM
CHND-MDC
MATRDEV
FINOLEX
KSK-WRDH
VIDARBHA
ABHI-NG
MW
72.4
0
402.2
100.6
0
0
50.3
201.1
15.1
20.1
15.1
45.3
0
0
55.3
0
0
201.1
0
150.8
332022
332024
332027
332029
332031
332039
332040
332041
332042
332069
332070
332080
332081
332082
332097
TILLARY
PARLI
CHANDPUR
WARDHA
KORADI
CHALISGAON
NASIK
TROMBAY
KHAPERKHEDA
MALHRPTH
WANKUSWD
KDPH
BHIRA
DAHANU
BHIRA
50
0
201.1
40.2
0
0
550
938.2
380.1
0
0
20.1
150.8
502.8
72.4
334007
334010
334023
334025
334026
334029
334030
334032
334035
334036
334039
337001
CHANDRAPUR
1125.7
KORADI
367.4
JAIGAD
1000
KOYNA
502.8
NEW KHAPKHDA
402.2
DEEPNAGAR
462.6
TIRORA
1206.7
NANDGAONPETH
750
NASIK-SINNER
0
DHARIWAL
0
DHARIWAL
0
TIRORA
1211.4
TOTALS
11893.4
Load flow study has been carried out to see the impact of the following transmission
schemes which are already under implementation by PGCIL/MSETCL on the power flows
in Aurangabad I (Waluj) - Aurangabad (PG) 400 kV interconnection:
(i)
LILO of 400kV D/C lines Parli – Pune (PG) at Pune (GIS) - already
commissioned.
(ii)
2 nos. of 400 kV bays at Dhule (MSETCL) for termination of Dhule (Sterlite) –
Dhule (MSETCL) 400 kV D/C line.
(iii) LILO of both circuits of Aurangabad I (Waluj) – Pune (PG) at Pune(GIS) ) by
September 2015
(iv) Aurangabad (PG) – Sholapur D/C 765kV line by December 2015
(v)
Aurangabad (PG) – Padghe 765 kV D/C line by March 2016
(vi) Aurangabad (PG) – Boisar D/C 400 kV line by March 2016
(vii) Bableshwar – Kudus 400kV D/C line by March 2016.
(viii) LILO of one circuit of Aurangabad (PG) – Padghe 765 kV D/C line at Pune
(GIS) – project under bidding stage.
The load flow results are attached as annexures. The results are summarized in the table
given below. From the load flow analysis it is clearly evident that with the commissioning
of the above mentioned elements loading on 400kV Aurangabad (Waluj) – Aurangabad
(PG) D/C line has been reduced from 2460MW to 706MW and Aurangabad (Waluj) –
Aurangabad (PG) D/C line would not be constraint for import of power from Maharashtra.
S.No
Name of the
transmission line
1
Aurangabad
(Waluj) –
Aurangabad (PG)
400kV D/C line.
Aurangabad (PG)
765/400kV
2X1500MVA
ICT's Flow
2
A :Base B: A+
Case
(ii)
C: B+ (iii)
D: C +
(iv)
E: D + (v)
F: E+ (vi) +
(viii) + (viii)
2460
2256
2196
1500
1158
706
2064
1834
1784
976
598
488
3
4
5
6
Pune (GIS)
765/400kV
2X1500MVA
ICT''s Flow
Aurangabad I
(Waluj) -Pune
(PG) 400kV D/C
line.
Aurngabad I
(Waluj ) - Pune
(GIS) 400kV D/C
line.
400kV D/C line
Pune (GIS) Pune (PG) line.
168
172
192
1092
1080
-
890
552
676
470
1416
-
-
-
384
82
574
800
478
760
In view of the above, MSETCL has proposed shifting of Shifting of Aurangabad I (Waluj)
– Pune(PG) 400kV D/C line from 400kV Aurangabad I (Waluj) to 765/400kV Aurangabad
(PG) is not required.
334055
PUNE_GIS
337009
PUNE_GIS
337004
SOLAPUR
-224.2
-0.0
12.3
-25.0
1.0
793.1
140.0
-139.8
-21.5
34.0
1.0
398.6
351.2
-1188.8
BR
1032.5
-264.4
48.9
1199.8
-1188.8
150.2
1032.5
741.6
-737.8
-178.4
-123.3
741.6
-737.8
-178.4
-123.3
696.5
-693.0
48.9
-303.8
-162.3
0.0
696.5
-693.0
-303.8
-162.3
255.5
1.0
789.2
84.2
-54.5
150.2
-1028.5
334018
BOISAR
-56.3
56.4
-54.1
-51.5
334037
TAPTITHANDA
-66.0
1230.4
-66.0
68.5
1230.4
0.0
251.5
-532.4
17.4
-1028.5
68.5
-1223.2
12.9
-1223.2
12.9
-88.9
89.3
-17.3
-97.8
441.7
55.3
-55.1
-101.3
24.5
466.9
-201.9
1.0
406.7
-47.4
-50.9
50.9
-6.7
-1.9
-50.9
50.9
-6.7
-1.9
334012
BABLESHWAR
462.6
5
547.0
-125.0L
-438.9
-3.9
-438.9
-47.4
-3.9
1.0
413.1
334013
PADGHE
-536.5
-65.8
61.3
547.0
-536.5
-65.8
61.3
-461.0
334022
AKOLA - I
95.8
-333.9
204.1
15.3
-48.8
-201.9
204.1
-2.5
-48.8
1.0
410.0
54.7
-79.2
441.7
-2.5
1.0
402.5
1.0
403.5
334029
DEEPNAGAR
1.0
407.7
-133.2
1.0
793.9
334011
BHUSAWAL
84.6
546.5
0.0
-32.0
1.0
791.7
0.0
-532.4
17.7
258.4
337003
WARDHA
1.0
783.1
34.0
334015
AUR I (WLUJ)
1.0000
-791.3
-58.9
B1
-21.5
546.5
1.0000
794.4
-264.4
-139.8
1.0
403.9
796.6
317001
VADODARA
BR
39.1
1.0
414.1
58.9
1199.8
84.2
140.0
-0.0
-794.4
B2
334042
PUNE-PG
39.1
1.0
790.4
0.0
1.0
414.7
357004
RAIPUR_PS
-38.4
BASE CASE
1.0000
0.0
243.0
84.2
334048
AURANGBD-PG 1.0
769.7
1.0000
0.0
-0.0
-58.0
-84.1
0.0
1.0000 1.0000
1.0000 1.0000
-0.0
-17.6
0.0
-38.4
334009
DHULE
334049
DHULE-BDTCL
226.8
-84.1
1.0
777.3
337006
DHULE-BDTCL
-224.2
1.0000
BR
337010
PADGHE
-58.0
-166.2
1.0000
337005
AURANGABD-PG
0.0
247.8
-17.6
1.0000
12.4
226.8
168.3
1.0000
-168.1
BR
334041
PARLI-PG
1.0 339.0
413.3
-120.3
1.0
412.3
628.6
-614.3
-63.8
111.7
1.0
408.8
1.0
407.8
334055
PUNE_GIS
337009
PUNE_GIS
337004
SOLAPUR
-219.4
334009
DHULE
-33.5
-370.4
371.1
33.4
-33.5
27.5
22.4
317001
VADODARA
-57.6
-264.1
55.0
1217.5
-1206.2
-264.1
B1
1.0
783.1
32.8
-525.9
BR
-525.9
77.0
19.3
-76.0
917.4
-792.0
-178.7
-111.5
796.4
-792.0
-178.7
-111.5
748.0
-743.9
122.2
-914.2
-914.2
-304.2
-151.3
0.0
748.0
-743.9
-304.2
-151.3
334018
BOISAR
-80.8
81.0
-53.3
-51.9
334037
TAPTITHANDA
-56.0
1128.8
-56.0
54.9
54.9
-1122.8
6.1
-1122.8
6.1
-86.2
86.5
-19.5
-96.7
406.8
17.1
-98.6
389.6
-17.0
20.4
-214.6
1.0
408.2
-41.3
-43.7
43.7
-1.7
-43.7
43.7
-7.0
-1.7
334012
BABLESHWAR
462.6
5
577.4
-125.0L
-404.4
-16.7
-404.4
334013
PADGHE
-565.7
-58.7
64.9
577.4
-565.7
-58.7
64.9
-16.7
-41.3
1.0
414.6
-385.5
334022
AKOLA - I
72.4
-312.2
217.1
4.0
1.1
-49.7
217.1
1.1
-49.7
1.0
411.1
76.3
-80.3
-7.0
406.8
-214.6
1.0
402.7
1.0
404.1
334029
DEEPNAGAR
1.0
409.4
-125.9
1.0
794.5
334011
BHUSAWAL
77.4
539.6
0.0
122.2
796.4
1.0
789.5
-132.6
-20.5
19.6
917.4
55.0
255.6
132.8
1.0
399.6
1.0
404.5
1128.8
0.0
251.5
32.8
-30.6
1.0
793.1
-1206.2
-20.5
334015
AUR I (WLUJ)
1.0000
-487.4
-74.6
351.5
-132.6
539.6
1.0000
488.5
0.0
132.8
CASE B
258.9
337003
WARDHA
BR
40.7
1.0
415.5
120.2
1217.5
86.6
1237.1
1.0
794.2
334042
PUNE-PG
40.7
27.5
-1231.7
B2
-40.0
1.0
790.7
-370.6
1.0
415.6
357004
RAIPUR_PS
243.7
86.6
-370.6
1.0000
-22.7
371.1
33.6
-57.1
-86.6
334048
AURANGBD-PG 1.0
770.8
1.0000
370.9
-371.7
-20.2
0.0
-40.0
334049
DHULE-BDTCL
1.0000 1.0000
1.0000 1.0000
372.3
-22.9
221.9
-86.6
1.0
778.1
337006
DHULE-BDTCL
-219.4
1.0000
BR
337010
PADGHE
-57.1
-163.7
1.0000
337005
AURANGABD-PG
0.0
248.3
-20.2
1.0000
9.6
221.9
173.2
1.0000
-173.0
BR
334041
PARLI-PG
1.0 316.6
413.5
-115.9
1.0
413.2
598.5
-585.6
-73.1
108.6
1.0
409.7
1.0
409.5
334055
PUNE_GIS
337009
PUNE_GIS
337004
SOLAPUR
-215.1
334009
DHULE
32.2
-32.1
26.1
375.7
-375.2
32.0
-32.1
26.1
-73.0
1.0
796.5
-1205.6
-275.3
64.2
1216.9
-1205.6
B1
892.1
86.1
892.1
789.2
-784.9
-195.8
-99.3
789.2
-784.9
1.0
783.8
-195.8
-99.3
741.3
-737.2
64.2
-320.9
-140.3
0.0
741.3
-737.2
-320.9
-140.3
256.9
1.0
791.5
-275.9
-15.4
35.2
276.8
-275.9
-15.4
35.2
276.8
-275.9
-15.4
35.2
334018
BOISAR
1.0
400.1
CASE C
334011
BHUSAWAL
445.8
BR
-49.4
86.1
-889.1
1.0
405.8
334029
DEEPNAGAR
-62.1
-889.1
-65.9
66.0
-43.4
-64.3
334037
TAPTITHANDA
-24.7
1098.6
-24.7
17.4
1098.6
0.0
252.0
276.8
-21.5
337003
WARDHA
353.2
35.2
-49.4
0.0
261.3
1.0
793.9
0.0
-15.4
445.8
1.0000
-501.1
-58.3
-275.9
334015
AUR I (WLUJ)
1.0000
502.3
276.8
1.0
407.0
1260.2
45.6
-275.3
-434.7
1.0
791.8
317001
VADODARA
BR
54.5
1.0
416.7
-1254.8
1216.9
96.4
-10.7
-375.0
334042
PUNE-PG
54.5
-375.2
100.7
B2
-53.5
-434.7
375.7
1.0
416.7
357004
RAIPUR_PS
246.1
96.4
-10.7
1.0000
-21.1
-66.0
-96.3
334048
AURANGBD-PG 1.0
774.7
1.0000
-21.2
375.5
-376.3
-13.1
0.0
-53.5
334049
DHULE-BDTCL
1.0000 1.0000
1.0000 1.0000
376.9
217.6
-96.3
1.0
779.6
337006
DHULE-BDTCL
-215.1
1.0000
BR
337010
PADGHE
-66.0
-139.0
1.0000
337005
AURANGABD-PG
0.0
249.2
-13.1
1.0000
-15.8
217.6
192.6
1.0000
-192.4
BR
334041
PARLI-PG
17.4
-1093.1
35.7
-1093.1
35.7
-88.5
88.8
-20.9
-96.7
420.2
41.9
-82.9
434.3
-41.9
3.4
-209.5
1.0
412.4
-40.2
40.2
-2.8
-6.0
334012
BABLESHWAR
462.6
5
612.3
-125.0L
-417.7
-21.7
-35.3
-21.7
1.0
416.7
334013
PADGHE
-599.3
-48.4
67.0
612.3
-599.3
-48.4
67.0
-429.4
334022
AKOLA - I
51.9
-321.6
211.9
1.1
-57.9
-209.5
211.9
7.3
-57.9
1.0
414.2
-6.0
-417.7
7.3
1.0
403.0
40.2
420.2
-100.1
1.0
798.2
-40.2
-2.8
1.0
411.7
-35.3
62.3
-91.8
1.0 326.3
414.0
-112.7
1.0
414.8
595.7
-583.0
-82.4
115.8
1.0
410.9
1.0
411.8
334055
PUNE_GIS
337009
PUNE_GIS
337004
SOLAPUR
-184.7
-42.0
-51.1
-22.7
-91.9
-184.7
186.3
-42.0
-51.1
-56.7
BR
14.0
-1082.9
1088.8
-56.7
337010
PADGHE
14.0
230.0
-229.8
33.1
-33.1
23.8
-229.6
230.0
-229.8
33.0
-33.1
23.8
1.1
421.5
-811.2
-350.3
-24.2
-125.4
1.1
804.9
1278.1
BR
-17.0
488.7
356.6
-199.4
-39.8
-1265.7
1030.4
-1023.2
95.5
-1265.7
B1
1.0
785.3
-199.4
-39.8
967.8
-961.0
95.5
-325.6
-85.1
0.0
967.8
-961.0
-325.6
-85.1
259.3
1.0
795.2
13.7
-377.9
14.4
334018
BOISAR
CASE D
13.7
334011
BHUSAWAL
239.9
BR
-78.8
-17.0
-487.9
1.0
412.6
334029
DEEPNAGAR
-82.8
89.2
-487.9
-77.3
334037
TAPTITHANDA
35.0
749.7
35.0
-63.6
749.7
-286.7
14.4
379.5
-33.4
-1023.2
1278.1
-286.7
-236.8
-78.8
0.0
488.7
1030.4
0.0
13.7
-377.9
-88.9
0.0
252.9
-377.9
-10.5
337003
WARDHA
B2
379.5
239.9
265.3
1.0
798.7
1.0
412.9
13.7
334015
AUR I (WLUJ)
1.0000
350.9
14.4
1.0
415.6
813.5
317001
VADODARA
-377.9
379.5
1.0
801.1
-9.5
379.5
14.4
1.1
421.6
82.2
357004
RAIPUR_PS
91.6
-78.4
1.0000
-28.9
-337.5
-236.8
-230.4
334042
PUNE-PG
91.6
-78.4
1.0000
229.8
-82.2
-337.5
334048
AURANGBD-PG 1.0
790.5
1.0000
-29.1
1.0000 1.0000
1.0000 1.0000
230.6
256.3
-82.2
334009
DHULE
334049
DHULE-BDTCL
338.0
338.0
1.0
796.3
337006
DHULE-BDTCL
0.0
1.0000
1088.8
1.0000
337005
AURANGABD-PG
-1082.9
1.0000
-675.9
1.0000
260.1
186.3
678.2
0.0
BR
334041
PARLI-PG
-63.6
-747.2
62.6
-747.2
62.6
-74.2
74.5
-18.7
-104.3
374.0
-11.5
-76.3
328.5
11.5
-7.2
-261.8
28.5
-261.8
28.5
1.0
406.7
1.1
420.6
1.1
421.2
44.0
5.7
-14.8
-44.0
44.0
5.7
-14.8
334012
BABLESHWAR
462.6
5
450.8
-125.0L
-372.0
-26.9
374.0
-372.0
-42.4
-26.9
1.1
425.1
334013
PADGHE
-444.0
-35.4
-9.1
450.8
-444.0
-35.4
-9.1
-325.8
-98.8
1.1
804.2
-44.0
1.0
419.1
-42.4
83.1
-105.9
334022
AKOLA - I
27.8
-281.9
265.4
-2.1
-66.9
1.1
423.5
265.4
-66.9
1.0 285.4
418.9
-125.5
577.6
-565.8
-112.6
136.4
1.0
414.8
1.0
419.1
334055
PUNE_GIS
337009
PUNE_GIS
337004
SOLAPUR
-149.3
-50.9
-52.0
-43.8
-102.5
-149.3
150.4
-50.9
-52.0
-107.8
882.5
-107.8
-21.8
144.2
-21.7
334009
DHULE
334049
DHULE-BDTCL
-144.6
1.0000 1.0000
1.0000 1.0000
144.7
144.4
337010
PADGHE
7.7
1.1
805.9
337006
DHULE-BDTCL
BR
7.7
-878.7
0.0
235.3
263.4
-80.5
235.3
-80.5
701.0
-698.5
-105.6
-49.7
701.0
-698.5
-105.6
-49.7
-235.1
1.0000
882.5
-235.1
85.2
334048
AURANGBD-PG 1.0
801.5
-23.4
12.7
144.4
-144.3
23.3
-23.4
12.7
1.1
426.1
-549.2
-95.3
-190.0
1.1
815.2
317001
VADODARA
260.3
-259.9
16.6
-175.1
1.0
418.7
-9.9
287.2
-286.3
-9.9
-286.3
30.5
-9.9
287.2
CASE E
-286.3
30.5
-9.9
1.1
421.4
334015
AUR I (WLUJ)
191.9
550.2
17.7
30.5
-190.0
1.1
426.2
27.0
-286.3
287.2
-95.3
23.4
287.2
30.5
-144.3
-144.1
334042
PUNE-PG
85.2
1.0000
337005
AURANGABD-PG
-878.7
1.0000
-470.6
1.0000
266.4
150.4
471.7
0.0
BR
334041
PARLI-PG
334011
BHUSAWAL
-80.4
0.0
191.9
BR
272.5
-80.4
1.0
417.8
334029
DEEPNAGAR
-98.3
-4.5
98.8
-114.2
-42.1
1.1
803.8
1307.6
BR
0.0
-316.0
254.5
1307.6
-1112.4
362.1
-237.7
14.9
-1294.7
1120.8
-1112.4
130.7
B1
-237.7
14.9
1052.7
-1044.8
130.7
-363.8
-35.1
0.0
1052.7
-1044.8
263.3
-363.8
-35.1
1.0
801.3
334018
BOISAR
-27.0
1.0000
1120.8
-1294.7
-316.0
1.0
787.8
0.0
-298.4
1.0000
B2
298.7
1.0000
-27.0
337003
WARDHA
357004
RAIPUR_PS
106.8
-28.1
298.7
1.0000
1.1
814.0
-106.5
-298.4
-84.8
334037
TAPTITHANDA
33.6
33.6
579.0
-577.5
-76.5
56.1
579.0
-577.5
-76.5
56.1
-56.6
56.8
-18.4
-109.2
318.8
-62.6
62.7
-72.3
-12.9
216.8
-280.6
1.1
427.8
334012
BABLESHWAR
462.6
5
253.2
-125.0L
-317.5
-36.3
-43.9
-36.3
1.1
431.5
334013
PADGHE
-251.1
-22.4
-69.5
253.2
-251.1
-22.4
-69.5
-215.7
334022
AKOLA - I
6.4
-233.6
284.8
-10.1
-77.5
-280.6
284.8
42.9
-77.5
1.1
426.7
42.1
-18.8
-317.5
42.9
1.0
409.6
-42.1
318.8
-93.6
1.1
815.2
-18.8
9.4
1.1
425.0
-43.9
42.1
9.4
1.1 236.0
423.2
-131.8
1.1
430.0
548.8
-538.3
-133.8
145.3
1.0
418.4
1.1
424.9
334055
PUNE_GIS
337009
PUNE_GIS
272.3
-430.4
-33.2
-430.4
708.6
2859.8
-2823.3
431.3
337010
PADGHE
-308.0
-142.7
-33.2
1.1
814.8
-20.7
85.5
-20.6
334009
DHULE
334049
DHULE-BDTCL
-85.8
1.0000 1.0000
1.0000 1.0000
85.8
85.6
270.9
431.3
-142.7
337006
DHULE-BDTCL
-120.1
151.6
-151.4
-5.1
-207.0
-81.0
344.4
708.6
-1060.8
1064.2
-81.0
336.5
-333.1
BR
-706.8
118.6
-85.5
21.2
10.0
85.6
334048
AURANGBD-PG 1.1
812.7
50.7
-46.6
334042
PUNE-PG
399.4
-397.7
33.8
1.1
425.0
-4.2
399.4
-397.7
-4.2
399.4
-397.7
-41.4
-116.3
-41.4
1.1
811.1
-85.6
-21.2
-50.5
-69.9
33.8
-85.6
-21.2
50.7
-46.6
118.6
-116.3
21.3
-50.5
-69.9
-706.8
1.0000
337005
AURANGABD-PG
0.0
1.0000
-42.3
0.0
341.9
1.0000
-341.3
1.0000
337004
SOLAPUR
BR
334041
PARLI-PG
33.8
-4.2
399.4
-397.7
33.8
CASE F
-4.2
1.1
427.0
10.0
1.1
429.3
334015
AUR I (WLUJ)
1.1
429.4
-334.9
41.5
335.2
0.2
30.3
317001
VADODARA
163.5
-163.4
41.1
-205.8
334011
BHUSAWAL
-84.2
0.0
41.5
BR
277.0
-84.2
1.1
423.0
334029
DEEPNAGAR
-110.3
-0.3
110.9
-119.8
-43.3
1.1
807.7
1339.8
BR
1221.3
-1211.4
365.6
-255.4
57.8
-1326.3
1221.3
-1211.4
0.0
-332.6
156.7
-255.4
57.8
255.5
1339.8
-1326.3
1147.0
-1137.7
-332.6
B1
1.0
789.4
156.7
-381.7
0.0
1147.0
265.9
-244.2
30.6
30.6
353.2
-352.7
-97.5
60.6
353.2
-352.7
-97.5
60.6
4.5
51.4
-16.8
-113.4
-89.5
89.7
-71.3
-14.8
-49.7
-312.0
1.1
821.9
202.9
-97.4
11.2
-201.8
202.9
-97.4
11.2
1.1
432.1
-22.2
-43.3
43.3
12.6
-22.2
334012
BABLESHWAR
462.6
5
102.4
-125.0L
-294.9
-35.7
296.0
-294.9
-49.7
-35.7
1.1
435.9
-162.8
334022
AKOLA - I
2.7
-15.6
-95.3
-102.0
-15.6
-95.3
102.4
-102.0
-15.6
-95.3
102.4
-102.0
-15.6
-95.3
-215.6
-8.8
-81.1
-312.0
317.0
55.7
-81.1
334013
PADGHE
-102.0
102.4
317.0
55.7
1.1
430.3
43.3
12.6
1.1
428.9
-96.3
4.5
1.0
417.0
-51.2
296.0
163.5
334018
BOISAR
-201.8
-89.7
334037
TAPTITHANDA
-1137.7
-381.7
1.1
805.2
-26.2
1.0000
0.0
-244.2
1.0000
B2
244.4
1.0000
-26.2
337003
WARDHA
357004
RAIPUR_PS
120.3
-24.4
244.4
1.0000
1.1
820.1
-119.8
1.1 217.6
428.0
-139.3
1.1
434.8
536.7
-526.7
-148.3
154.6
1.1
420.8
1.1
428.8
Annexure-IV
Report on 400kV additional in feed to GOA:
In the 38th SCM of WR held on 17.07.2015, the following Inter State Transmission System
scheme was proposed to provide second 400 kV feed to Goa system.
(i)
Establishment of 2X500 MVA, 400/200 kV substation at Xeldam and it’s inter
connections Narendra (Existing) 400kV substation through Quad conductor. The
inter connection between existing Xeldom substation and the proposed Xeldom
400/220KV substation could be through bus extension or through 220kV lines as
the case may be.
(ii) 400kV (Quad) connectivity between the new substation at Xeldem and Mapusa to
take care of any N-1-1 contingencies involving outage of any one 400kV infeed to
Goa.
In the meeting alternative LILO of Narendra – Kolhapur 765kv D/C line charged at 400kV
level was suggested by POWER GRID. It was decided that alternatives would be studied
jointly by CEA and CTU. Accordingly the following alternatives for feeding Xeldam 400 kV
substation has been studied including the alternative proposed in the 38th SCM:
S.No
1
2
3
4
5
6
7
8
Alternative
Narendra (existing)- Xeldam- Mapusa 400 kV
D/c quad line
Kolhapur(PG)- Mapusa – Xeldam 400 kV D/C
quad line
Kolhapur(PG) – Xeldam- Mapusa 400 kV D/C
quad line
Kolhapur(PG) – Xeldam 400 kV D/C quad line
and LILO of one ckt at Mapusa
LILO of one ckt. of Narendra(New)Kolhapur(PG) 400 kV D/C line at Xeldam
LILO of one ckt. of Narendra(existing) Narendra(New) 400 kV D/C line at Xeldam
LILO of one ckt. of Kaiga-Narendra(existing)
400 kV D/C line at Xeldam with LILO point at
Narendra end.
LILO of one ckt. of Kaiga-Narendra(existing)
400 kV D/C line at Xeldam with LILO point at
Kaiga end.
Exhibit
Option 1
Option 2
Option 3
Option 4
Option 5
Option 6
Option 7
Option 8
The results of the load flow studies conducted for the above mentioned eight alternatives
are summarized as given in table.
S.No
1
2
3
Name of the
transmission line
Ambewadi - Xeldom
220kV D/C line.
Kolhapur(PG) Mapusa 400kV 1st
D/C line.
Narenda(New) Kolhapur( PG)
765kV D/C line
(Charged at 400kV)
OPTION
:1
148
OPTION
:2
308
OPTION
:3
308
OPTION
:4
306
OPTION
:5
288
OPTION
:6
148
OPTION
:7
148
OPTION
:8
74
374
469
512
300
346
362
372
216
933
1276
1380
1276
915
932
847
4
5
6
7
8
9
10
11
12
13
Solapur(PG) Kolhapur (MSETCL)
400kV D/C line.
Kolhapur(PG) Mapusa 400kV 2nd
D/C line.
Mapusa - Xeldom
400kV D/C line.
Mapusa - Kadamba
220kV D/C line.
Narendra - Xeldom
400kV D/C line.
Kolhapur (PG) Xeldom 400kV D/C
line.
LILO one ckt of
Narenda(New) Kolhapur( PG)
765kV D/C line
(Charged at 400kV)
at Xeldom (New)
400/220kV S/s
Narendra(New) Xeldom (New)
400kV S/C line.
Kolhapur (PG) Xeldom(New)
400kV S/C line.
LILO one ckt of
Narendra(Existing) Narendra(new) at
Xeldom(New)
400/220kV S/s
Narendra(Existing) Xeldom(New)
400kV S/C line.
Narndra(new)Xeldom(New)
400kV S/C line
LILO one ckt of
Narendra(Existing) Kaiga 400kV D/C
line at Xeldom(New)
400/220kV S/s at
Narendra( Existing)
end.
Narendra(Existing) Xeldom(New)
400kV S/C line.
Xeldom(New) Kaiga 400kV S/C
line
LILO one ckt of
Narendra(Existing) Kaiga 400kV D/C
line at Xeldom(New)
400/220kV S/s at
Kaiga end.
Narendra(Existing) Xeldom(New)
400kV S/C line.
Xeldom(New) Kaiga 400kV S/C
554
794
796
794
816
692
690
650
320
312
484
306
306
306
469
308
250
124
306
310
280
276
750
430
546
82
388
376
378
380
153
860
line
The observations based on analysis of the results are:
• OPTION: 1 is best possible alternative for providing ISTS feed to Goa system since
it has successfully relieved loading on existing 220kV network as well as 400kV
network which is feeding power to Goa system
• For implementation of Option 1 two no. of 400 kV bays would be required at
Narendra (existing) 400/220 kV substation. In case of space constraints GIS bay
may be provided. If no space is available then option 6 or option 7 could be
implemented which are equally good as option1.
• In the all the eight alternatives, the 400 kV lines to Mapusa/ Xeldam has to cross
the Western Ghats section.
• In the corridor through which the Narendra(existing)-Xeldam 400 kV D/C line would
pass, there are already existing Ambewadi – Xeldam/Ponda 220 kV D/C line and
Supa-Ponda 110 kV D/C line. Ambewadi – Xeldam/Ponda 220 kV D/C line is
functional whereas the Supa-Ponda 110 kV D/C line is not in use. These lines are
maintained and operated in their respective geographical areas by Goa and
Karnataka respectively. In case of difficulty in getting RoW for implementation of
Narendra (existing)-Xeldam 400 kV D/C line, the RoW of the existing Supa-Ponda
110 kV D/C line could be used.
• Option5 i.e, LILO of one ckt. of Narendra(New)- Kolhapur(PG) 400 kV D/C line at
Xeldam which was suggested in the 38th SCM is not a suitable alternative as there
is uneven loading on the 400 kV circuits feeding power to Xeldam ( 540 on one ckt
and 82 MW on other ckt.) . Also Narendra(New)- Kolhapur(PG) is a 765 kV D/C line
which in present scenario is being operated at 400 kV level and in future when this
line would be operated at 765 kV voltage level , the Xeldam 400 kV along with the
feeding lines also needs to be upgraded to 765 kV level.
374013
KOLHAPUR
1
-227.5
1
227.5
66.2
-59.1
-59.1
-227.5
1
1
1
-227.5
1
227.5
66.2
227.5
66.2
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
152.8
-152.3
35.3
152.8
-34.3
-152.3
35.3
-34.3
-345.9
350.6
2.4
-345.9
-39.2
350.6
374050
KOLHAPURPG
2.4
1
-59.1
-276.8
277.6
-61.8
-276.8
34.4
277.6
-61.8
34.4
OPTION-1
-187.3
188.3
-60.4
-187.3
-20.3
188.3
-60.4
-20.3
344002
XELDEM4
-154.0
154.1
-38.9
-154.0
-2.7
154.1
-38.9
73.7
-72.9
524012
KAIGA
-465.1
468.2
-14.2
-466.7
-60.4
469.8
-14.0
-60.4
221.1
66.5
221.1
66.5
524047
NAREND-4
-2.2
1.0
216.9
-375.3
377.1
-63.8
-375.3
-10.6
377.1
-63.8
-10.6
2
-90.4L
-37.8
304.1
1.0
400.3
-37.8
1.0
405.6
1
1.0
403.7
1.0
399.3
187.0
304.1
1
-5.8
1.0
219.1
-53.2
1
-2.2
-53.2
-221.1
1
-5.8
-221.1
1
-72.9
1
342006
XELDEM
1
187.0
524015
NARENDR-NEW
-2.7
522031
AMBD
73.7
-90.4L
2
1.0
406.1
1.0
400.3
2
-39.2
1.0
216.3
1.0
217.9
1
1
-338.7
340.5
-20.2
-338.7
-79.7
340.5
-20.2
-79.7
-302.3
1.0
403.6
-3.5
-302.3
-3.5
1
1
1.0
404.7
374013
KOLHAPUR
1
-229.4
1
229.4
75.0
-67.6
-67.6
-229.4
1
1
1
-229.4
1
229.4
75.0
229.4
75.0
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
155.5
-155.0
42.7
155.5
-41.4
-155.0
42.7
-41.4
-397.1
403.4
10.6
-397.1
-30.7
403.4
374050
KOLHAPURPG
10.6
1
1
-30.7
2
1.0
214.7
-67.6
1.0
216.5
-166.0
166.3
-58.3
-166.0
25.5
166.3
-58.3
25.5
1.0
405.5
OPTION - 2
1.0
398.8
-212.0
213.2
-53.7
-257.8
-23.1
258.8
-74.5
-257.8
-19.0
258.8
-74.5
-212.0
-19.0
213.2
344002
XELDEM4
-53.7
125.7
-125.6
15.7
125.7
-57.3
-125.6
15.7
1
153.4
524012
KAIGA
643.1
16.4
-639.3
-31.3
645.3
16.8
-31.3
-52.4
125.6
57.3
125.6
57.3
524047
NAREND-4
10.4
1.0
214.5
2
-90.4L
187.0
-90.4L
-36.7
261.6
1.0
395.6
-36.7
1.0
406.0
1
1.0
401.4
1.0
397.3
187.0
261.6
1
-5.3
1.0
218.6
-149.7
-52.4
-125.6
1
10.4
-125.6
1
-149.7
1
342006
XELDEM
1
-5.3
2
-637.2
-57.3
522031
AMBD
153.4
1
-23.1
524015
NARENDR-NEW
-178.6
179.1
-25.4
-178.6
-96.9
179.1
-25.4
-96.9
-260.3
1.0
402.3
-10.0
-260.3
-10.0
1
1
1.0
405.1
374013
KOLHAPUR
1
-210.6
1
210.6
69.8
-63.5
-63.5
-210.6
1
1
1
-210.6
1
210.6
69.8
210.6
69.8
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
139.3
-138.9
39.7
139.3
-39.1
-138.9
39.7
-39.1
-397.6
403.8
16.3
-397.6
-36.8
403.8
374050
KOLHAPURPG
16.3
1
1
-36.8
2
1.0
215.9
-63.5
1.0
217.5
-168.6
168.9
-77.4
-168.6
44.6
168.9
-77.4
44.6
1.0
405.8
OPTION-3
1.0
400.1
-254.3
256.0
-53.4
-18.7
524015
NARENDR-NEW
-254.3
344002
XELDEM4
-53.4
-61.6
61.6
-51.3
-61.6
7.9
61.6
-51.3
7.9
18.2
153.1
-149.5
1
524012
KAIGA
1
1
-66.7
1
152.6
73.8
152.6
-638.9
644.8
-18.7
25.7
-641.0
-41.9
647.0
26.1
-42.0
-214.2
215.0
-81.7
-214.2
-51.7
215.0
-81.7
-51.7
73.8
524047
NAREND-4
18.2
1.0
216.2
2
-90.4L
187.0
-90.4L
-38.9
261.9
1.0
400.1
-38.9
1.0
406.3
1
1.0
403.7
1.0
398.9
187.0
261.9
2
-13.3
1.0
218.9
-66.7
-152.6
1
-13.3
-152.6
1
-149.5
1
522031
AMBD
153.1
342006
XELDEM
256.0
-177.9
178.5
-30.3
-177.9
-92.6
178.5
-30.3
-92.6
-260.5
1.0
403.3
-8.0
-260.5
-8.0
1
1
1.0
405.6
374013
KOLHAPUR
1
-222.1
1
222.1
71.3
-64.3
-64.3
-222.1
1
1
1
-222.1
1
222.1
71.3
222.1
71.3
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
149.1
-148.6
40.1
149.1
-39.1
-148.6
40.1
-39.1
-397.2
403.4
9.8
-397.2
-29.7
403.4
374050
KOLHAPURPG
9.8
1
1
-29.7
2
1.0
214.2
-64.3
1.0
215.9
-166.0
166.3
-55.8
-166.0
23.1
166.3
-55.8
23.1
1.0
405.4
OPTION - 4
1.0
398.6
-223.7
225.1
-59.2
-271.9
-15.7
272.9
-81.7
-223.7
344002
XELDEM4
-59.2
53.1
-53.1
-13.9
153.1
524012
KAIGA
-4.4
1.0
218.5
-149.4
-55.6
-136.4
-55.6
1
1
9.5
-136.4
136.4
1
-149.4
1
643.0
15.1
-639.2
-29.8
645.2
15.5
-29.8
-219.7
220.6
-93.8
-35.9
61.3
136.4
61.3
524047
NAREND-4
9.5
1.0
214.4
2
-90.4L
187.0
-90.4L
-36.5
261.6
1.0
395.7
-36.5
1.0
406.0
1
1.0
401.1
1.0
396.1
187.0
261.6
1
-637.1
-15.7
342006
XELDEM
1
-4.4
2
225.1
-28.9
522031
AMBD
153.1
1
524015
NARENDR-NEW
-9.4
-178.6
179.1
-24.7
-178.6
-97.5
179.1
-24.7
-97.5
-260.2
1.0
402.1
-10.3
-260.2
-10.3
1
1
1.0
405.1
374013
KOLHAPUR
1
-209.1
1
209.1
69.7
-63.5
-63.5
-209.1
1
1
1
-209.1
1
209.1
69.7
209.1
69.7
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
137.5
-137.1
39.7
137.5
-39.1
-137.1
39.7
-39.1
-408.9
415.5
18.5
-408.9
-34.9
415.5
374050
KOLHAPURPG
18.5
1
1
-34.9
2
1.0
215.7
-63.5
1.0
217.3
-133.4
133.6
-76.4
-133.4
42.4
133.6
-76.4
42.4
1.0
405.7
OPTION - 5
1.0
399.8
-173.0
173.8
-64.3
-17.6
524015
NARENDR-NEW
-173.0
344002
XELDEM4
-64.3
-140.7
140.8
-40.2
-140.7
-1.6
140.8
-40.2
524012
KAIGA
-29.5
-82.3
82.5
-116.3
-87.3
144.7
-141.4
-11.6
1.0
218.9
-62.6
14.7
1
1
14.7
-62.6
-173.5
173.5
1
-11.6
-173.5
1
-141.4
71.4
173.5
71.4
-546.2
187.0
1.0
399.6
-38.6
1.0
406.4
-48.2
1.0
216.0
2
-38.6
258.9
554.0
524047
NAREND-4
-23.2
-90.4L
-90.4L
1
1.0
403.1
1.0
398.5
187.0
258.9
1
704.5
37.6
342006
XELDEM
1
2
-697.4
-17.6
-1.6
522031
AMBD
144.7
1
173.8
-183.9
184.4
-28.4
-183.9
-93.9
184.4
-28.4
-93.9
-257.6
1.0
403.2
-8.6
-257.6
-8.6
1
1
1.0
405.6
374013
KOLHAPUR
1
-227.4
1
227.4
66.2
-59.1
-59.1
-227.4
1
1
1
-227.3
1
227.3
66.2
227.4
66.2
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
152.6
-152.1
35.3
152.6
-34.3
-152.1
35.3
-34.3
-346.4
351.1
2.1
-346.4
-38.8
351.1
374050
KOLHAPURPG
2.1
1
1
-38.8
2
1.0
216.1
-59.1
1.0
217.7
-274.8
275.6
-60.7
-274.8
33.2
275.6
-60.7
33.2
1.0
406.1
OPTION - 6
1.0
400.2
-181.3
182.2
-62.1
-19.2
524015
NARENDR-NEW
-181.3
344002
XELDEM4
-62.1
-159.7
159.9
-37.3
-159.7
-4.2
159.9
-37.3
524012
KAIGA
-62.5
461.7
-13.8
-62.5
73.5
-72.6
-5.3
1.0
219.0
-52.6
-2.7
1.0
216.7
1
1
-2.7
-52.6
-222.5
222.5
1
-5.3
-222.5
1
-72.6
66.0
222.5
66.0
1
1.0
403.5
-388.2
392.1
524047
NAREND-4
-64.6
-376.4
378.3
-59.1
-14.8
1.0
399.0
187.0
-74.9
-319.8
321.5
-26.0
-77.0
2
-90.4L
301.8
1
460.1
-14.1
-458.6
342006
XELDEM
1
2
-457.1
-19.2
-4.2
522031
AMBD
73.5
1
182.2
187.0
-90.4L
-34.5
301.8
1.0
400.0
-34.5
1.0
405.2
-300.0
1.0
403.2
-6.9
-300.0
-6.9
1
1
1.0
404.0
374013
KOLHAPUR
1
-227.7
1
227.7
66.4
-59.3
-59.3
-227.7
1
1
1
-227.7
1
227.7
66.4
227.7
66.4
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
152.9
-152.4
35.4
152.9
-34.5
-152.4
35.4
-34.5
-344.9
349.5
2.6
-344.9
-39.9
349.5
374050
KOLHAPURPG
2.6
1
1
-39.9
2
1.0
216.5
-59.3
1.0
218.1
-279.0
279.9
-63.3
-279.0
36.0
279.9
-63.3
36.0
1.0
406.1
OPTION - 7
1.0
400.4
-185.9
186.8
-58.7
-22.4
524015
NARENDR-NEW
-185.9
344002
XELDEM4
-58.7
-155.7
155.8
-40.9
-155.7
-0.8
155.8
-40.9
524012
KAIGA
380.7
-51.4
1
469.0
-13.8
-467.5
-60.8
470.6
-13.5
-60.9
73.4
-72.5
-6.9
1.0
219.2
-54.2
1
-1.2
-54.2
-221.8
221.8
1
-6.9
-221.8
1
-72.5
1
342006
XELDEM
1
2
-465.9
-22.4
-0.8
522031
AMBD
73.4
1
186.8
67.6
221.8
67.6
524047
NAREND-4
-1.2
1.0
217.1
-377.8
379.7
-59.9
-14.3
-377.6
-73.6
1.0
399.7
187.0
2
-90.4L
-335.5
337.3
-20.6
-335.5
-80.1
337.3
-20.6
-80.1
1.0
400.8
187.0
-90.4L
1
1.0
403.9
263.5
-262.2
-34.5
-12.0
1.0
406.0
1
1.0
403.8
1
1.0
404.9
374013
KOLHAPUR
1
-233.9
1
233.9
65.7
-58.3
-58.3
-233.9
1
1
1
-233.9
1
233.9
65.7
233.9
65.7
374040
SHOLAPUR-PG
342001
MAPUSA2
344001
MAPUSA4
342008
KADMBA2
157.3
-156.8
34.3
157.3
-33.2
-156.8
34.3
-33.2
-325.4
329.5
-1.6
-325.4
-41.1
329.5
374050
KOLHAPURPG
-1.6
1
1
-41.1
2
1.0
216.5
-58.3
1.0
218.1
-313.8
314.9
-59.8
-313.8
34.8
314.9
-59.8
34.8
1.0
406.2
OPTION - 8
1.0
400.5
-108.8
109.1
-71.4
-16.1
524015
NARENDR-NEW
-108.8
344002
XELDEM4
-71.4
-242.0
242.4
-27.2
-242.0
-11.2
242.4
-27.2
524012
KAIGA
2
1
425.8
-18.8
-424.7
-67.1
427.3
-18.6
-67.2
37.8
-37.6
859.1
37.5
-1.2
1.0
219.1
-47.0
1
-9.7
-47.0
-262.2
262.2
1
-1.2
-262.2
1
-37.6
1
342006
XELDEM
1
1
-423.3
-16.1
-11.2
522031
AMBD
37.8
1.0
399.6
187.0
109.1
65.2
262.2
65.2
524047
NAREND-4
-9.7
1.0
217.2
-152.1
152.4
-83.0
-17.7
-857.1
-24.9
2
-90.4L
-361.1
363.2
-20.9
-361.1
-74.6
363.2
-20.9
-74.6
1.0
400.5
187.0
-90.4L
1
1.0
404.0
28.3
-28.2
-57.8
-2.7
1.0
402.0
1
1.0
403.6
1
1.0
404.2
Annexure-V
Minutes of the meeting held on 02.09.2015 on issue related to connectivity
of 2x 660 MW Generation Project of M/s Lanco Vidarbha Thermal Power
Ltd. (LVTPL)
A meeting to discuss the issues related to connectivity of 2x660 MW generation
project of M/s Lanco Vidarbha Thermal Power Limited (LVTPL) was taken by
Member (Power System), CEA on 2nd September 2015 at CEA, New Delhi. The
list of participants is enclosed at Annexure-I.
1. CEA informed that the connectivity arrangement, LILO of Seoni - Wardha
765 kV S/C line at LVTPL TPS, for 2x660 MW generation project of M/s
LVTPL was agreed in the 12th meeting of WR Constituents regarding
Connecitivity / Open Access Applications held on 08-07-2010.
Subsequently, in the 21st meeting of WR Constituents regarding Connectivity
/ Open Access Applications held on 17-07-2015, the connectivity
arrangement for generation project of M/s LVTPL was revised to LVTPL TPS
– Warora pool 765kV D/C line and M/s LVTPL was requested to confirm the
time frame by which connectivity line was required, so that suitable action
may be initiated for implementation of the line through Tariff Based
Competitive Bidding route. M/s LVTPL vide their letter dated 27th August,
2015 has requested for continuation of the earlier connectivity granted i.e.
LILO of Seoni - Wardha 765 kV S/C line at LVTPL TPS.
2. M/s LVTPL informed that
i) They are developing 2X660 MW thermal power project near Mandva
village in Wardha district of Maharashtra. Based on the connectivity
arrangement agreed earlier (i.e., LILO of Seoni - Wardha 765 kV S/C line
at LVTPL TPS), the switchyard equipment has already been ordered and
most of the equipment have been received and the work at their
switchyard end is going on.
ii) The work on the project got hampered for 34 months due to enormous
delay in obtaining the Environmental Clearance (EC). After receipt of EC
in August 2014, approval of the project lenders was obtained in March
2015 for cost overrun funding with a revised completion schedule of May
2017 (for Unit 1) and September 2017(for Unit 2).
iii) The synchronization of Unit 1 is targeted by November 2016, as such the
start-up power would be required for the project by August, 2016. The
connectivity line is required before August 2016. Any change in the
connectivity arrangement already agreed, at this stage, would lead to
schedule mismatch which would be unacceptable to Project Lenders and
would jeopardize the progress work taken up with great difficulty.
iv) Therefore, the connectivity arrangement agreed earlier (i.e., LILO of
Seoni-Wardha 765 kV S/C line at LVTPL TPS) needs to be retained for
the project to achieve it target timelines.
3. CTU informed that the LILO connectivity was agreed in year 2010 and
significant developments have taken place in the transmission system in last
5 years and Seoni - Wardha 765 kV line has become part of the trunk
transmission corridor in WR. LILO interconnection would result into
unbalance power flow in the trunk corridor besides increasing the fault level
at Wardha 765 kV bus, which has already reached near design level of 40
kA. Further, a new 765/400 kV Warora pooling station is under
implementation as a part of transmission system associated with Gadarwara
STPS (2x800MW) of M/s NTPC Ltd., which is scheduled for commissioning
by November 2017. In view of this the connectivity has been revised to
LVTPL TPS – Warora Pool 765kV DC line.
4. POSOCO said that they are not in favour of LILO of trunk lines at generating
stations. They have already filed petition in CERC wherein it has been
prayed that Central Transmission Utility (CTU) should be directed to review
all connectivity granted to ensure that the CEA Standards are followed and
stop granting connectivity through interim LILO arrangement and the
connectivity already granted through interim LILO arrangements may be
shifted to final arrangements. The hearing has been completed and the order
is reserved.
5. CEA and CTU stated that
i) M/s LVTPL has applied only for connectivity. The power to the
beneficiaries of the project on firm basis cannot be transferred without
taking LTA in ISTS and till date M/s LVTPL has not applied for LTA. On
receipt of LTA application, the additional transmission system
strengthening requirement would be identified and LTA would be effective
after implementation of the identified transmission system strengthening.
ii) The connectivity line as agreed in the 21st LTA meeting held on
17.07.2015, LVTPL TPS – Warora pool 765kV DC line, would be
adequate to take care of the evacuation requirements till Warora pool. The
additional transmission system strengthening requirements, if any, based
on LTA application of M/s LVTPL would be only beyond Warora pool.
iii) The implementation of the LVTPL TPS – Warora pool 765kV DC line
would be taken though TBCB route wherein, the completion time of the
line in matching time frame of the generation project would be specified. In
case of mismatch (transmission line along with Warora pooling station not
coming in matching time frame of generation project), interim arrangement
would be evolved.
iv) For taking up the implementation of the line through TBCB route
a) M/s LVTPL needs to confirm the commissioning schedule of the
generation project.
b) As per CERC sharing regulations, transmission charges are payable
by beneficiaries only after the commercial operation of the generator.
Till then, it is the responsibility of M/s LVTPL to pay the transmission
charges.
c) M/s LVTPL needs to sign connectivity agreement and submit requisite
Bank Guarantee.
The issue was further deliberated and M/s LVTPL
above requirements so that the connectivity line
765kV DC line) could be put as agenda in the
meeting on transmission, scheduled to be
implementation of the scheme though TBCB route.
was requested to confirm the
(LVTPL TPS – Warora pool
35th Empowered Committee
held on 14.09.2015, for
M/s LVTPL stated that they would come back on the issues after discussion with
their management.
The meeting ended with thanks to the chair.
Annexure - I
List of Participants of the Meeting held on 02.09.2015 in CEA, Sewa Bhawan,
New Delhi
S.
Name
No.
1.
Shri. S.D. Dubey
Designation
Organization
CEA
CEA
4.
5.
Shri. K.K. Arya
Shri. Awdhesh
Kumar Yadav
Shri. Shiva Suman
Shri. K.V.S. Baba
Member (Power
System)
Chief Engineer
Director
Deputy Director
GM, NRLDC
CEA
POSOCO
6.
Shri. Ashok Pal
AGM (CTU-P)
PGCIL
7.
Shri. Pratyush Singh
Engineer
PGCIL
8.
Shri. K.E. Prasad
Director
LVTPL
9.
Shri. B.L. Jangir
ED
LVTPL
10.
Shri. P.K. Sarma
Sr. VP
LANCO
11.
Shri. Vibhuti
DGM
LANCO
12.
Shri. Harpreet Walia
DGM
LANCO
2.
3.
Mobile No.
e-mail
CEA
8527607575 KVSbaba
@posoco.in
9910378105 ashok@powergridi
ndia.com
8826094863 pratyush.singh@p
owergridindia.com
9650648844 keprasad@lancogr
oup.com
9717395868 jangir.bl@lancogro
up.com
9650415511 sarmapk@lancogr
oup.com
9958699038 vibhuti@lancogrou
p.com
9810707197 harpreet.walia@la
ncogroup.com

Similar documents

Issued on 08.03.16 - Western Regional Power Committee

Issued on 08.03.16 - Western Regional Power Committee REACTIVE ENERGY CHARGES FOR THE WEEK FROM 22-02-16 to 28-02-16 A. Details of VARh charges between SEBs and ISTS GETCO to ISTS High Voltage Low Voltage Net

More information