Experiences of Ground Improvement for Urban Tunnels in Difficult
Transcription
Experiences of Ground Improvement for Urban Tunnels in Difficult
Akira Koshima, Giorgio Guatteri -1- Experiences of Ground Improvement for Urban Tunnels in Difficult Conditions Authors: Akira Koshima -- technical manager, Novatecna Consolidações e Construções S/A and 2002-2006 president of the Brazilian Tunnelling Committee, ABMS, São Paulo, Brazil, [email protected] Giorgio Guatteri -- CEO, Novatecna Consolidações e Construções S/A, and Terrajato, São Paulo, Brazil, [email protected] SUMMARY A brief overview of jet grouting in Brazil is followed by “why and when” basics in relation to ground improvement for safe tunnel excavating. A number of case histories are reported - mostly NATM tunnels involving what were seen as difficult, new, or unusual situations. Our report is based on our own ground improvement experience - over a million meters for 56 tunnels and 26 years of specialized geotechnical work in Brazil, Portugal, Madeira, and Venezuela. 1. JET GROUTING TECHNOLOGY IN BRAZIL As far as Brazilian engineers are concerned, Guatteri [1] introduced jet grouting in the early 1980s, and it spread to the rest of the Americas, north and south -- Argentina (1983), California (1983), and then other LatinAmerican countries (except Venezuela where it had already been used in 1979) [2] – followed by Iraq (1987) and Taiwan (1993). In the 1990s, jet grouting was used for Lisbon’s subway modernization (Novatecna Portugal, 1994 - 1998), more recently Caracas subway (Novatecna Caracas, 2000 and ongoing), and there is a project underway in Spain. Japanese engineers have done development work on jet grouting since the 1970s. More specifically CCP (Cement Churning Pile or single fluid ) is attributed to Nakanishi (1970); JSG or JG (Jumbo Special Grout or Jumbo Grout or double fluid, air and cement slurry) to Yahiro (1970) (panel jet) and Yahiro and Nakanishi (1975) (column); CJG (Column Jet Grout or triple fluid) to Yahiro et al (1976); SSS Man (Super Soil Stabilization Management) to Nakanishi (1985); Cross Jet to Shibazaki et al (1996) and Superjet to Yoshida et al (1996). In Brazil, the CCP or single-fluid technique was initially used in the 1980s (Novatecna); JSG or JG double-fluid method was introduced in 1985 (Novatecna); and horizontal jet grouting in 1987 (Novatecna & Rodio); in 1988 the Column Jet Grout (CJG, Embrajet), and 1989 Extended Nozzle Jet (ENJ, Novatecna) [3]. In 1998, Novatecna was the first to use horizontal jet grouting for full excavation profile (360o) and front septum. Novatecna played a leading role in developing the technology in Brazil, together with consultants, designers and construction companies, and led the more innovative uses of jet grouting in tunnels, including some major underground structures [3 - 33]. The basic jet grouting concept is driving a metallic rod (diameter 7-10 cm) into the ground mass and then injecting soil and cement slurry under high pressure ( 800 to 1000 km/h nozzle speed) to break down soil into a homogeneous soil-cement slurry hardening into a cylindrical format (diameter 0.4 to 2 m) from the hole. Fig. 1 – View of jets Fig .2 – Test Field Akira Koshima, Giorgio Guatteri-- 2 – The resulting consolidated mass is very strong and highly impermeable after curing. Since they depend on drilling alone, columns may be restricted to the strictly necessary cross section, and may be positioned at any angle from vertical to horizontal, and in any type of soil without restrictions in relation to granulometrics, geological origin, or presence of water (figs. 1 and 2). 2. NEED FOR TREATMENT 2.1. Arch effect On excavating the tunnel, pre-existing ground mass stresses are channeled along its profile, so certain areas on the walls of the excavation come under pressure. This channeling of stress along the cavity profile is referred to as the “arch effect” and this phenomenon means that a cavity may be created in the ground. [39 - 40] The extent of the “arch effect” will depend on the magnitude of pre-existing ground stresses and their strength and deformability, which may be manifested in the following ways (fig. 3): a) in the proximity of the excavation surface; b) further away from the excavation surface; c) it may not occur at all EFEITO ARCO EFEITO ARCO 3 1 2 NATURAL 2 DESVIADO 1 3 INEXISTENTE Fig. 3 – Arch effect The first case (a) occurs when ground mass is well able to support the flow of diverted stresses and responds in the elastic field in terms of active tensions and deformations. The second case (b) occurs when the solid responds by plastifying and deforming radially. Thus stress canalization is diverted within the ground mass, until the triaxial state of tensions becomes compatible with strength and deformation characteristics. In this situation the “arch effect” occurs far from the excavation walls and disintegrated ground around the profile may contribute to the final statics with residual strength alone. Major deformations, convergences, etc. may occur in this way. The third case (c) occurs when the ground around the excavation profile is not capable of supporting the new pattern of diverted stresses and responds at the failure stage, causing cavity collapse. From these three cases, we see: · The arch effect is produced as a natural consequence only in the first case. The ground is resistant and selfstanding, so no treatment is required. · In the second case, the arch effect occurs as a natural consequence only if the ground is “helped” through stabilizing interventions, or based on a major deformation. Treatment may be necessary in this case. . In the third case, the arch effect does not occur as a natural consequence, and must be created “artificially” by intervening in the ground prior to excavation. Treatment is required. Akira Koshima, Giorgio Guatteri-- 3 – 2.2. Intervention system “Intervention systems” may be divided in two main groups: “Sustaining approach” (passive) and “confinement approach” (active), (Lunardi, 1994). (fig. 4) AÇÃO INTERVENÇÃO SUSTENTAÇÃO ESCORAS DE MADEIRA PASSIVO EFEITO ARCO PRÉ-SUSTENTAÇÃO TUBOS EM PRÉ-FUROS E CAMBOTAS CONTENÇÃO (CONFINAMENTO) CHUMBADORES RADIAIS E CONCRETO PROJETADO ATIVO PRÉ-CONTENÇÃO (PRÉ-CONFINAMENTO) BARRAS DE FIBRA DE VIDRO NA FRENTE DE AVANÇO Fig. 4 – Intervention systems Either approach may intervene after excavation (sustentation / contention) or prior to starting excavation (presustentation / pre-contention). 2.2.1. Sustaining approach (passive) The “sustaining” approach assumes that even the use of structural elements supported on steel ribs along the arch is not capable of creating an arch effect on an advance, due to the lack of reciprocal collaboration transversally, as well as being based on a passive intervention concept. Sustentation includes: timber props, steel ribs, etc; Pre-sustentation includes tubes or short bars of any type, possibly placed in pre-drilled holes, which may be filled with cement slurry and supported by steel ribs, such as driven metallic sheet forepoling, also known as marciavante, extended reinforced low pressure injected forepoles for structural purposes. 2.2.2. Confinement approach (active) . The interventionist or “confinement approach” is based on producing and controlling an arch effect (transversally) in the ground, naturally or artificially. The active intervention concept emphasizes protection of the excavation face, as theorized by Kastner in the 1950s and developed by Rabcewicz in the 1960s. Confinement includes shotcreting, several types of radial bolts, different types of TBM shields (open face, compressed air, slurry, EPB, etc.). Pre-confinement includes ground treatments by injecting cement of different types and textures; chemical injections; freezing; jet grouting; mechanical pre-cut; reinforcing core with fiberglass nailings / spilings or other processes; cellular arch with jacked tubes or pipe-roof etc. (fig. 5, Lunardi, 1994) INTERVENÇÃO SOLOS ARGILA INJEÇÕES CONVENCIONAIS CONGELAMENTO JET-GROUTING HORIZONTAL PRÉ-TUNEL REFORÇO DO NÚCLEO COM TUBOS DE FIBRA DE VIDRO PRÉ-CORTE MECÂNICO ARCO CELULAR Fig. 5 – Pre-confinement processes SILTE AREIA CASCALHO ROCHA FRATURADA ROCHA Akira Koshima, Giorgio Guatteri-- 4 – 3. GROUND IMPROVEMENT EQUIPMENT AND ACCESSORIES 3.1. Drilling and injection rigs Novatecna has designed and built new or modified existing drilling rigs for ground improvement based on the needs experienced in each project. On this basis, we have worked with tunnel diameters ranging from 3.0m to over 10m (floor-to-vault). In the basic concept, the drilling-injection device, known as the positioner, is prepared for a 12m perforation without maneuvering the rod and without needing a platform. The horizontal drilling and jetting positioner is assembled with one or two telescopic hydraulic pistons as mast supports, with fully independent motion so as to provide quick and accurate set up of the drilling string along the required direction (fig. 6). In addition to its versatility for precise guidance and speed of positioning holes, a laser beam cannon is used to focus the design with homothetic projections of the drill points located on the treatment face, with inclination and spacing as designed. (fig. 7) Fig. 6 – Modern horizontal drill rig (positioner) Fig. 7– Drill guidance using template and laser beam Pumped water for drilling and cleaning the hole, or cement slurry during the injection phase, flows through highpressure hoses driven by a pump (approx. 300 HP) located outside the tunnel. Coupled to the pump system is an automated high-turbulence mixer-agitator system preparing and continuously loading 18,000 liters or more of cement slurry per hour. After positioning the machine, rotational drilling starts with water circulating and proceeds until a predetermined drill-hole length is reached. This machine may be adapted for rotary-percussion drilling when working in ground containing rock blocks, without altering the other sequences described below. On withdrawing the drilling string, the injection phase starts immediately; ground mass is disintegrated by kinetic action and the impact of the cement slurry jet originated by potential energy equivalent to 2000 - 4000 meters of water column. The slurry is thoroughly mixed with the disintegrated ground by rotating and withdrawing the drilling string to form soil-cement columns. Note that these operations are fully automated. Excess soil-cement mixture (reflux) has to be removed through the drill-hole itself. For treatment around the tunnel profile and the front septum, the horizontal drilling and jetting positioner allows a wider range of movements by means of specific gearing, so that the mast may rotate 360° in relation to the rig and be set up in an advanced position to execute invert and septum columns. The positioner is also equipped with two 360° rotational gears, one mounted on the frontal mast support and the second placed onto the vertical axis of the crawler rig (fig. 8). Due to the versatility of this type of positioner, face teams often call it the “Kamasutra.” Fig. 8 – Horizontal drilling rig executing HJG and front septum Akira Koshima, Giorgio Guatteri-- 5 – 3.2. Accessory “preventer valve” for drilling and horizontal jet grouting This oil engineering accessory is called a “preventer valve” (or “blow-up preventer”) and is used to avoid gas leaks and explosions when drilling oil wells. Preventer valves and retainers at the mouth of the hole control outflows of solid or liquid spoils from drilling when ground is sandy and susceptible to “piping.” They also facilitate control of reflux (excess soil-cement mixture) during jet horizontal grouting jobs, thus avoiding “piping” along the hole or the column. (figs. 9, 10) Major tunnelling jobs using preventers: Fig. 9 – Preventer valve schematic Fig. 10 – Preventer valve view - Tamanduateí Tunnel, in the city of São Paulo, Brazil. Excavated in coarse sandy-gravel ground to a depth of 25m under the Tamanduateí River with the top of its diaphragm walls around 5m from the tunnel roof. This was the 1st use of preventer valves and 360o front septum treatment solution using horizontal jet grouting, in 1998. - Copacabana Subway Tunnel, Rio de Janeiro, Brazil. Excavated in saturated beach sand and in silty sandy micacious gneiss residual soil under a 7-storey building with direct foundations. The distance between the tunnel roof and the foundation base was about 6m. Treatment was 360o and front septum using HJG (in 2000). - Subway tunnel in Caracas, Venezuela. Excavated in sandy paleovale with gravel - solution similar to the Copacabana tunnel, in 2002. - Cidade Jardim Tunnel, São Paulo, Brazil. Very shallow traffic tunnel with 2 - 5m overburden and vault excavated in saturated sandy alluvium with gravel. Pre-lining executed on the vault using horizontal jet grouting reinforced with metallic piping and front septum, in 2004. - São Paulo Subway Lines 2 and 4, Brazil.- Used on 9 sites where Novatecna is or was involved using preventer sporadically. 4 CASE HISTORIES 4.1. Campinas traffic tunnel, São Paulo, Brazil This was the 1st tunnel in Brazil (in 1987) to use horizontal jet grouting (HJG) with a diameter of 0.50m on sections not accessible from the surface and also with Jumbo Grout columns (diameter 1.6m), when ground treatment was possible from the surface. [12] The tunnel cuts through Tubarão and Itararé formation sedimentary ground mass, which includes porous colluviums, sand and sandy siltstone, with groundwater level above the tunnel vault. Since this was a large urban tunnel (125m2), with shallow overburden (3 -15m) in unfavorable geological conditions, horizontal (HJG) and jumbo grout (JG) methods were used, being entirely new solutions for tunnel engineering at that time. Jet grouting (HJG) facilitated ground mass consolidation through the tunnel excavation face in sections under the avenues, houses and the rail classification yard without affecting the surface. This technique involves laying a consolidated arch of juxtaposed soil-cement columns prior to excavation, which minimizes settlement and avoids soil loss, particularly in sandy, low-cohesion, low-strength soils immersed in Akira Koshima, Giorgio Guatteri-- 6 – groundwater. Due to the porous and low-strength supporting soil, the HJG solution for the vault was combined with prior widening of the arch foot (elephant foot) using forward sloping CCP columns, thus reducing settlement under the railroad. In addition, in order to confine the saturated siltstone ground mass for benching, jet grouting columns were executed sloping from mid-cross-section and interlinked through a shotcrete shoe projected over the arch support or elephant foot. Another technique used was jumbo grout, with vertical side-by-side columns around the excavated section (diameter 1.6m), executed from the surface when possible (certain limited areas such as the portal or sides of the retaining wall) of trench excavations. This concept, with an arch formed by JG columns was used for the north portals (railway classification yard) where tunnel width reached 18m due to the curved geometry of the alignment, with only 3m overburden under the main railroad. A JG gravity wall was executed along the railroad alignment as retention for 15m excavations. (figs. 11, 12) Fig. 11 – Shallow rail tunnel portals (3.0m) Fig. 12 – Jet grouting 15m high gravity wall 4.2. Copacabana subway tunnel, Rio de Janeiro, Brazil Rio de Janeiro' s subway company planned a 750m extension to line 1, from Cardinal Arcoverde Station to the center of Copacabana, also building Siqueira Campos Station and turn-offs or maneuvering areas. The underground structure comprised two independent but juxtaposed “eyeglass type” tunnels crossing gneissic rock, saprolite and micacious residual silty-sandy soil and sandy clayish soil of marine origin, of high hydrogeological complexity; the route also crossed a densely populated built-up area. [27] One of the greatest challenges was the NATM section of the tunnels under the direct foundations of a 50-yearold 7-storey building, standing on sandy sediment (beach sand), with around 6m overburden. These tunnels were previously treated with horizontal jet grouting forming a closed 360o conical chamber with treatment throughout the excavation cross section and front septums protecting each advance module. (figs. 13, 14) The work was successfully concluded on time and the preventer valve was a crucial factor in ground treatment with maximum settlement of 30mm. Fig. 13 – Face treatment Fig. 14 – Front septum excavated by horizontal jet grouting 4.3. Ipiranga Station in 300 m2 cave in soil, São Paulo Subway, Brazil Ipiranga Station, now fully excavated with civil engineering work in the final phase, is on a 3km extension of São Paulo Subway Line 2 from Ana Rosa Station. Akira Koshima, Giorgio Guatteri-- 7 – The cave is all underground and is the largest São Paulo Subway has excavated in soil in a built-up urban area. The cross section (some 300m 2) was excavated from a central shaft about 35m in depth. The station tunnel (diameter 35m) was excavated in predominantly clayish-silty varved São Paulo Tertiary soil , interspersed with discontinuous layers of fine-to-medium slightly clayish sands with SPT ranging from 20 to 40, and groundwater level around 3.0m from the surface. The station tunnel overburden varies from 9 to 24m. Excavation of the cave proceeded in 4 phases, initially executing 2 side-drifts with invert at the turnstile level, excavation of the vault to the height of the top of the side-drift, excavation of a partial bench to the invert of the side-drift, and finally final benching down to the final invert. (fig. 15, 16). CCPH PREGAGENS 1,40 CALOTA PONTEIRAS c/ 2,0m DHPV DHPV 17,35m 1,40 EIXO S. DRIFT DA ESTAÇÃO DHPV PFV 6,15m EIXO S. DRIFT PFV 0m DHPV ,2 SD 1 1 =1 REBAIXO - AID 4 R SD 1 EIXO DO TÚNEL 2 REBAIXO 1/2 SEÇÃO 3 23,30m Fig. 15 – 300m² station cavern excavated below two rail lines Fig. 16 – Cavern cross section Due to the dimension of the tunnel cross section all sequential cross sections were treated with horizontal jet grouting columns in the weaker sandy and clayish layers and in the remainder with injected pipe-roofing, besides nailing the face and executing deep horizontal drains. With such a large vault, 2 positioners were used simultaneously to speed treatment work for this section. For final benching in sandy soils, we also used the well points system under vacuum to reduce neutral pressure. 4.4. Tunnel under Av. Cidade Jardim - Av. Brig. Faria Lima, São Paulo, Brazil The Cidade Jardim traffic complex comprises 2 tunnels, with 2 traffic lanes and a pedestrians walkway over each; the route eliminates a chronic traffic jam at the intersection between Av. Cidade Jardim - Av. Brig. Faria Lima and under Rua Dr. Mário Ferraz, with a total length of 1,657 m, of which 880m is tunneled. [33] Execution was planned for 7 months in order to minimize disruption. The 528m tunnel (in the center-suburb direction) was excavated through three shafts and the ramp at the suburb end, thus providing access for 7 points of attack. The other tunnel (length 535m, direction suburb-to-center) was executed from two service tunnels excavated sideways from intermediate points between the shafts from the 1st tunnel, providing access to 4 excavation faces. Due to the difficult geometry of the road complex, horizontal space restrictions and shallow overburden, four very different types of cross section were used: typical, widened bay, double and triple. The following ground mass features were intercepted by the deeper excavations: Crystalline bed, mixture of micacious sandy-silt residual soil and weathered gneiss rock. The upper part of the bed was completely weathered (saprolite); The Resende Tertiary formation, aka taguá, has two main facies: one clayish and one sandy. These facies occur in the form of sub-horizontal layers, usually with well individualized and marked contacts In the portal areas and the section under Av. Brig. Faria Lima where the alluvium layer was present, soil treatment was required. This method was frequently used in areas with shallow overburden, varying from 1.5m to 6m (over the length of the tunnels). Closed chambers were executed with multidirectional composition of horizontal and vertical jet grouting columns in materials such as gravel, sands and organic clays commonly found in alluvium regions. Particularly in shallow overburden sections such as the one under Av. Faria Lima, the double-line treatment comprised horizontal jet grouting and the internal one was reinforced with 2.1/2” schedule 40 piping (HJG-CB). The use of HJG or HJG-CB in permeable soils ensures that the excavation perimeter is protected, even if located below groundwater level. However, the excavation face remained exposed to water filtration and washing, thus Akira Koshima, Giorgio Guatteri-- 8 – facilitating “piping” in sandy soil. Several septums were required with sufficient thickness and impermeability to provide safe excavating in stable watertight chambers for the crossing under Av. Faria Lima. These septums were executed in three ways: · from the surface: in double walls of vertical or angled (Ø=0.8m) grouting columns. · inside the cross section: in sections where execution from the surface was not possible. HJG columns were juxtaposed inside the tunnel to form a septum in front of the section to be excavated. · combined solution: part of the septum was executed by vertical and the rest by horizontal jet grouting. The section under Avenida Faria Lima was divided in three sub-sections in terms of treatment, with different executive characteristics. (figs 17, 18 and 19): ELÉTR TEL ELÉTR TEL. GÁS ÁGUA ÁGUA ELÉTR CET TEL PLUVIAL ELÉTR CET ESGOTO GREIDE SEPTO VERTICAL SEPTO HORIZONTAL 129 CCPH-BC CCPH-BC CCPH-BC 130 CCPH-BC CCPH-BC MACIÇAMENTO ARGILA RIJA (TAGUÁ) (ESTACAS) 131 132 CCPH-BC (AUTO PERFURANTE) Fig. 17 – Longitudinal section of ramp center CCPH-BC CCPH AREIAS MÉDIAS E FINAS DHP DHP AREIA GROSSA E CASCALHO Fig. 18 – Double treatment 15 AV. FARIA LIMA 20 25 30 Figure 19 - Triple section RAMO 300 TAGUÁ 10 RAMO 200 5 RAMO 100 0 35 40 Akira Koshima, Giorgio Guatteri-- 9 – The C section, starting from the ramp center in “cut and cover”, comprises a “big block” of vertical jet grouting columns (Ø = 0.8m) and was executed as a mass of consolidated soil, thus acting as a wall to counteract ground mass thrust when excavating the portal and “cut and cover” sections. This section presented particular difficulty due to the numerous interferences from large numbers of utilities in this underground area. In section B, the tunnel has very shallow overburden and the design included vertical jet grouting columns around the excavation profile. This is the section under the two carriageways of Av. Faria Lima. Due to the low overburden and presence of dynamic load, treatments were executed in HJG-CB and minimum lateral penetration of 1 meter in the taguá ground. The combination of large cross section (119 m2) with the great thickness of sandy, permeable soil and shallow overburden required double-layer treatment. The internal layer was executed with HJG-CB and the outside with HJG (fig. 18). Deep horizontal drains were placed between these two layers to ensure absolute safety for excavation. The presence of thick sand and gravel in the bottom meter of the sandy alluvium layer was constant throughout all treatments; due to the ascending grade of the tunnel, this difficulty gradually and significantly worsened; in particular due to the presence of water associated with the high permeability of this layer (fig. 19). The initial drives from the attack shaft met with gravel in the final meters of perforation of the upper columns and required the preventer valve to ensure quality treatment. For the next drive, the “preventer” had to be used on every column. Some columns were located entirely in the gravel layer and presented particular difficulty. Drilling in gravel raised friction between rod and soil and forced operators to be very quick and skillful; it also blocked use of the positioner' s automatic HJG system. Friction significantly reduces the working life of rods and injector devices. On occasion, lateral friction exceeded positioner torque or rod strength and they had to be left in the ground. In these cases, repair columns were executed outside the unfinished columns. Face impermeability was achieved by execution of vertical septums comprising two lines of juxtaposed jet grouted columns (diameter 0.80 m). Using HCCP for executing the septum would require a large number of columns and take a long time due to the great thickness of the sandy soil layer. Executing these septums meant partially closing traffic lanes on the avenue early mornings and weekends. Positioning for these septums was adjusted in order to provide an appropriate length for treatment drill holes around the tunnel and avoid deviations due to interferences, and position them along the avenue lanes. HJG -CB around the profile was inset 0.5m in these septums. The large cross section meant that two positioners could act simultaneously for several drives on this section (fig. 20). This required more coordination from support teams and extra effort from the instrumentation team, since faster treatment has a bigger effect on ground mass and requires “online” monitoring. Positioners should ideally work at opposite ends in these cases. HJG and horizontal drains were used in residual soil sections when necessary. Holes drilled to execute treatment often intercepted interfaces between weathered rock and soil to reach within a few centimeters of alluvium interface. In these cases, HJG was reinforced by introducing schedule piping along the axis. Another major innovation was the use of video to monitor work inside the tunnel. The monitor in the containeroffice showed progress on the job and any difficulties arising, so measures could be taken quickly, thus benefiting overall progress and optimizing decision-taking. (fig. 21) Fig. 20 – Double section tunnel treatment with two horizontal drill rigs Fig. 21 – Internal TV circuit to track progress below Akira Koshima, Giorgio Guatteri-- 10 – 4.5. Consolidation of Tagus River Alluvium for the EPB shield under the Cais do Sodré railway station in Lisbon, Portugal The initial excavation region for the EPB shield (diameter 9.8m), the departure point for the shield (cut-andcover future Cais do Sodré subway station) had to be consolidated with jet grouting to sustain the shield that would start excavating “Tagus River mud” and crossing under the century-old Cais do Sodré railway station building. This was the first of a series of projects for Novatecna Portugal in Lisbon in 1994. [19] It was feared that there might be an irreparable loss of control over the shield excavating the clayish alluvium soil with sandy lenses, soft, very saturated, dark gray, known as “Tagus River mud “. The consequences could be settlement under the station building. Single-fluid jet grouting was executed from the surface with sloping holes, from the vertical to about 30o to horizontal, to form a consolidated mass supported on the Myocene layer. The length of the treatment across the projection of the railway station was 62m. (figs. 22, 23) ESTAÇÃO FERROVIÁRIA CAIS DO SODRÉ ED. ANEXO TAPUME FUNDAÇÃO SHIELD ATERRO ALUVIÃO DO RIO TEJO MIOCENIO Fig. 22 – Typical jet grouted envelope section Fig. 23 – Cut and cover shield starting 4.6. Other new uses Certain projects are worthy of special mention for their innovative use of jet grouting: 4.6.1. Tunnel under Av. Sto. Amaro, center-suburb direction, with up to 2.0m overburden, São Paulo, Brazil Due to the shallow overburden and geology indicating the presence of clayish and organic waterlogged alluvium, with sandy intercalations of very low strength, overlaying taguá (hard greenish gray clay), the solution designed was concrete-filled jacked steel pipes (∅ =1.0m) around the tunnel vault starting from a trench in the central divide between the carriageways on Avenida Santo Amaro. The pipes were jacked in both directions to cross the two lanes (suburb-center and vice-versa). The geometry for the distribution of the pipes around the cross section of the tunnel involved pipejacking as far as possible through a central trench, without necessarily reaching the alluvium / taguá contact. This pipe roof was supplemented with HJG on the two excavation faces of the tunnel to provide supplementary support for the pipe roof in the taguá soil. HJG columns were also executed to block and seal space between pipes. Two supports were executed from inside the two faces, in the form of HJG arch segments to sustain the tunnel vault pipe roof, as in the two partial septums at each end of the pipes supported on taguá, in addition to HJG forepoling for the core [18]. (figs. 24, 25) Akira Koshima, Giorgio Guatteri-- 11 – Fig. 24 – Longitudinal section Fig. 25 – Typical tunnel cross section, steel pipes and HJG 4.6.2. Nailing subway tunnel face with fiberglass (length 28 m) in Lisbon, Portugal. This was the first time fiberglass nailing was used with 3 tape reinforcement elements (rectangular-cross-section, composed of fiberglass) attached to the outer face of triangular spacers, with concentric rigid PVC piping to ensure seamless 28m lengths. These fiberglass tapes were delivered and stored in reels to be cut into 28m lengths on-site. Nailing elements were placed using a process similar to the self-drill method, with low water/cement factor (0.4) cement slurry containing liquefier and expansion additives. The special positioner used featured two long 25m masts with 11m vertical reach for excavating the tunnel full-section [37, 38]. (figs. 26, 27) Fig. 26 – Two mast horizontal driling rig with 11m range Fig. 27 – 28 m fiberlass nailing 5. CONCLUDING POINTS Brazil' s major tunnel project of the early 1980s involved over 75 km of tunnels on the Steel Railroad from Minas Gerais to Rio de Janeiro. The technology available for ground improvement for excavation purposes was noreturn valve (manchette) forepoling reinforced with schedule tube as described in several articles in the Annals of the Underground Excavation Symposium, 1982 [42] and [43]. We would add that the last 20 years have seen major advances in ground improvement for tunnel excavation, particularly in urban areas, with the introduction and evolution of jet grouting technology in Brazil and worldwide. The extent of this development is clearly seen in the review of tunnelling experiences in São Paulo compiled by Negro, Sozio and Ferreira in 1992 [44], when the use of jet grouting for ground improvement was still incipient. Major road, subway, and sanitation tunnels in São Paulo materialized thereafter - with more than 56 tunnels totaling over one million linear meters in 26 years, reflecting the authors'experience. What is unarguable is that for safe excavation in adverse geotechnical conditions, the jet grouting solution of creating a pre-lining over the tunnel vault prior to excavation is one of the most recommendable techniques, and one of high productivity and efficiency as a treatment method. Tunnelling on this basis is a planned and industrialized activity. The average time required to execute an HJC column varies from 60 to 75 minutes, which beats the average for any other technique available in Brazil, with fine technical performance and increasingly less interference in the excavation cycle when working from inside the tunnel. Obviously if treatment is executed in advance, from the surface if possible, with vertical and/or sloping jet grouting, the treatment period does not extend the tunnel execution schedule. Akira Koshima, Giorgio Guatteri-- 12 – Acknowledgements On behalf of Novatecna S.A, the authors thank the tunnelling community in Brazil for support, recognition, and encouragement in using and developing this technology. In countries where we have been active, this has facilitated transfer to the international community of the best applications of jet grouting on the same level as the best international companies. In particular we owe gratitude and special recognition to Paolo Mosiici and to the late Victorio Doro Altan who were decisive in the use of this technology for so many years at Novatecna. REFERENCES [1] Abramento, M.; Koshima, A; Zirlis, AC. – chapter 18, Reforço do Terreno; in Fundações: Teoria e Prática, published by PINI-ABMS ABEF, various authors and editors, 2nd edition / August 1998 [2] (Perri, G. – La Tecnologia “CCP” em el Metrô de Caracas, 8th Panamerican Congress of Soil Mechanics and Foundation Engineering (CPMSEF), Cartagena, Colombia, August 1987) [3] Mosiici, P. – High Pressure Injection Columns; ABEF Research on Foundation Engineering, XII ICMSF, 1989. [4] Construção São Paulo, nº 2013/2014/2015 – Técnica “CCP” de consolidação de solos por cimentação a jatos, 3 parts, September 1986 [5] Teixeira, A H; Guatteri, G; Doro Altan, V. – The CCP Jet Grouting Method for Soil Improvement; VIII E.C.S.M.F.E, Helsinki, May 1983 [6] Guatteri, G.;Teixeira A H – The Use of CCP Jet Grouting Method for Soil Improvement in Tunnelling; Tunnelling in Soft and Water Bearing Grounds – AFTES – Paris, 1985 [7] Guatteri, G; Teixeira, A H; Martins, A. - Solutions of Stability Problems in Tunnelling by the CCP Method; International Congress on Large Underground Openings, ITA International Tunnelling Association, Firenze, Italy, June 1986 [8] Guatteri G., Mosiici, P.; - O Uso do Jet Grouting em Obras Subterrâneas Urbanas, 1st SEFE, September 1985 [9] Guatteri, G.; Mosiici, P.; Doro Altan, V – Jet Grouted Cut-off Walls, Proceedings of REMR Workshop on New Remedial Seepage Control Methods for Embankment – Dams and Soil Foundations – U S Army Corps of Engineers, Vicksburg, Mississipi, January 1988 [10] Teixeira, AH, Guatteri, G – Improvement of Soft Clays by Jet Grouting Technology, 8th CPMEF, Cartagena, Colombia, August 1987 [11] Guatteri, G.; Kauschinger, J.L.; Doria, A C.; Perry, E.B. – Advances in the Construction and Design of Jet Grouting Methods in South America; Second Internacional Conference on Case Histories in Geotechnical Engineering, Missouri, St. Louis, June 1988. [12] Dugnani, G; Guatteri, G.; Roberti, P; Mosiici, P. – Subhorizontal Jet Grouting Applied to a Large Urban Twin tunnel in Campinas, Brazil, 12th International Conference on Soil Mechanics and Foundation Engineering (ICMSF), vol 2, Rio Janeiro, October 1989 [13] Mosiici, P. – Jet Grouting Quality Control; Grouting in the Ground; Conference Proceedings, Institution of Civil Engineers (PCICE), November 1992 and Annals published by Thomas Telford in 1994. [14] Guatteri, G.; Mosiici, P.; Koshima, A ; Doro Altan, V. – Application of Jet Grouting to Tunnel Portals and Top Headings in NATM Tunnelling: the Brazilian Experience; PCICE, November 1992 and Annals published by Thomas Telford in 1994. [15]Guatteri, G.; Mosiici, P.; Koshima, A - Túneis em Solos Tratados com Jet Grouting; 3rd Brazilian Underground Escavation Symposium, Brasilia, August 1994 [16]Guatteri, G; Mosiici, P.; Koshima, A; Postiglione, P; Costa da Silva, A F. – Jet Grouting Horizontal no Túnel Travessia sob o Rio Tietê; 3rd Brazilian Underground Escavation Symposium, Brasília, August 1994. [17] Guatteri, G; Mosiici, P.; Koshima, A; Postiglione, - Enfilagem de Bulbo Contínuo no Tratamento de Túneis do Mini Anel Viário; 10th Brazilian Soil Mechanics and Foundation Engineering Congress (X COBRAMSEG), November 1994 [18] Guatteri, G; Mosiici, P.; Koshima, A; Harada, T.; Sozio, L.E. – Jet Grouting and Pipe Jacking in a Shallow Urban Tunnel Construction; IS Tokyo´96, 2nd International Conference on Ground Improvement Geosystems, Grouting and Deep Mixing, May 1996 [19] Doro Altan, V.; Mosiici, P – Jet Grouting Allows Passage of a 9.8 Shield Under a Building in Lisbon; IS Tokyo´96, Grouting and Deep Mixing, May 1996. [20] Postiglione, P.; Abrantes, J R C; Pinto, F; Mosiici, P.; Doro Altan, V; Consolidamentos com Jet Grouting na Estação Poente do Complexo “Estações Baixa-Chiado” do Metropolitano de Lisboa; 6th National Geotechnics Congress; Lisbon, Portugal, September 1997 [21] Guatteri, G; Mosiici, P.; Koshima, A; Doro Altan, V – Case History Related to a Jet Grouting Tunnels PreConsolidation With Minimun Coverage of 0.7m to 1.0 m – Under 345 Kv Cables and 8 Rapid Transit Road Railway Lanes; International Tunnelling Congress, ITA, Prague, Czechoslovakia, October 1997 Akira Koshima, Giorgio Guatteri-- 13 – [22] Guatteri, G; Mosiici, P.; Doro Altan, V.; Koshima, A – Brazilian Experience of Jet Grouting Treatment in Difficult Tunnels; World Tunnel Congress 98, ITA CBT, Tunnels and Metropolises, São Paulo, April 1998. [23] Guatteri, G; Doro Altan, V. – Jet Grouting Horizontal Permite Escavar Túnel sob Residência com Valioso Painel Cerâmico; Tunnelling Seminar ( IST), Lisbon, Portugal, June 1998 [24] Guatteri, G; Koshima, A; Doro Altan V. – Enfilajes de Bulbo Continuo em Tuneles Excavados em Macizos Terrosos Vs Enfilajes Tradicionales de Tubos a Manchettes, XI CPMSEF, Foz Iguaçu, Brazil, August 1999 [25] Guatteri,G; P.; Koshima, A.; Lopes, J ; Doro Altan V. – 360º Jet Grouted Conical Chamber Allows Safe Tunnelling Under River Within a Highly Pervious Enviroment; Geoenge 2000 – An International Conference on Geotechnical & Geological Engineering; Melbourne, Australia, November 2000 [26] Guatteri, G, Koshima, A.; Lopes J R; Pieroni, M R – Jet Grouting Horizontal em 360º e Septo em Túnel em Areia sob o Rio Tamanduateí, 4th Urban Tunnel Symposium (4º TURB) , São Paulo, June 2002 [27] Guatteri, G; Lopes J R; Primo C R N P ; Brautigam, V.M.; Sózio, L.E; Koshima, A de Mello, L,G. – A Construção de Dois Túneis do Metrô RJ sob o Edifício de 7 Andares em Copacabana. um Desafio a Engenharia de Túneis, XII COBRAMSEG, 1st Luso-Brazilian Geotechnics Congress (1 CLBG), São Paulo, October 2002 [28] ] Guatteri, G; Martinati, R.; Moreira , L.A S; Koshima, A; Motidome, M- Concepção e Execução dos Tratamentos do Túnel 3/4 , Emboque Santos da Nova Pista Rodovia Imigrantes, XII COBRAMSEG , I CLBG, S.Paulo, October 2002 [29] Guatteri, G; Lopes J R; Koshima A; Guaraná, C A – A Aplicação de Técnica Inovadora na Execução de Túnel Muito Raso sob a Rodovia Presidente Dutra; 1st Brazilian Tunnelling Congress (1º CBT/SAT 2004), March 2004 [30] Guatteri, G; Koshima, A; Matsui, M; Andrade Junior, J C O, Pieroni, M R; Modesto Junior, C – A Viabilização do Empreendimento com Uso do Jet Grouting Metrô Vila Madalena São Paulo; 1CBT/SAT 2004, March 2004 [31] Guatteri, G; Koshima, A; Pieroni, M.R.; Moreira, L.A.S.; Lopes, J.R. – Jet Grouting Horizontal como Condicionamento do Maciço para Escavação do Túnel Após Ruptura; 1º CBT , São Paulo, March 2004 [32] Guatteri, G; Koshima, A; Ravaglia,A, Duarte,M.. – Soluções em Jet Grouting para a linha 4 do Metrô Caracas – Desafios em Obras Urbanas, XIII COBRAM SEG/III CLBG, Curitiba, August 2006 [33] Guatteri, G; Koshima, A; Pieroni, M.R.; Murakami, C.; Lopes, J.R. – A viabilização do Túnel Raso em Aluvião Saturado Arenoso com Cascalho, em Jet Grouting – Túnel Travesia da Av. Cidade Jardim sob a Faria Lima em São Paulo, XIII COBRAM SEG/III CLBG, Curitiba, August 2006 [34]Cruz, H J V; Couto, JVS; Hori, K; Salvoni,J. L; Ferrari, O A; Os Túneis do Prolongamento Norte – Uma Primeira Avaliação do NATM em Área Urbana; Anais do Simpósio sobre Escavações Subterrâneas (Annals of Underground Excavation Simposium), Vol. 1, RJ, November 1982 [35] Martinati, R – Aspectos Construtivos e Geotécnicos Relativos e Construção de um Túnel de 5,4 km de Extensão Escavado ao Longo da Bacia Sedimentar de São Paulo; 3rd Urban Tunnel Symposium, October 1999 [36] Camara, F H; Debelin, P O; Gama E Silva R L – Urban Enviromental and Traffic Problems and The Underground Solution; North Americam Tunnelling’ 96, ITA, Washington, USA, Abril 1996. [37]Rocha, H C; Hori, K – Aspectos Construtivos dos Túneis do Metrô Paulista nos Sedimentos da Bacia de São Paulo; 9th Brazilian Geology Congress, São Pedro, SP, November 1999 [38] Sózio, L E – Jet Setting in Rio; Tunnels & Tunnelling International, Abril 2002 [39] Lunardi, P. – Projeto e Construção de Túneis Segundo o Método Baseado nas Análises das Deformações Controladas nas Rochas e nos Solos; Article translated by Pucci, M. and Mosiici, P., Published by ABMS in 1995. [40] Lunardi, P. – Projeto e Construção de Túneis Segundo o Método Baseado nas Análises das Deformações Controladas nas Rochas e nos Solos; part 2; Article translated by Pucci, M. and Mosiici, P., Published by ABMS in 1995. [41] Maffei, C.E.M.; Gonçalves H.H.S.; Guazzelli,M.C. – Uma Utilização Pioneira de Jet Grouting como Escoramento, XI COBRAMSEG, Brasília, November 1998 [42] Anais do Simpósio Sobre Escavações Subterrâneas, various authors, Vol I E II, November 1982 [43]Carneiro, B P; Elias Filho, A; Campos, C.B ; Pinto, F A A; Carvalho, S A; Dias, J M V; Abijaodi R C; Schettino, J N F – Experiências Práticas Obtidas no Avanço de Túneis sob Condições Especiais, Simpósio sobre Escavações Subterrâneas , Volume 1 , November 1982 [44]Negro Jr, A; Sozio, L.E. ; Ferreira A. A . - Túneis; Solos da Cidade de São Paulo, Published by ABMS/NRSP May 1992.