application of lean manufacturing principles to construction
Transcription
application of lean manufacturing principles to construction
APPLICATION OF LEAN MANUFACTURING PRINCIPLES TO CONSTRUCTION by James E. Diekmann, Mark Krewedl, Joshua Balonick, Travis Stewart, and Spencer Won A Report to The Construction Industry Institute The University of Texas at Austin Under the Guidance of Project Team Number 191 Austin, Texas July 2004 Executive Summary Over the past three decades, the US construction industry has seen a decline in both its share of the gross national product and its annual productivity growth rate. The quality of construction has faltered during this period as well. In contrast, the US manufacturing industry has made significant progress in increasing productivity and product quality while lowering product lead times. Manufacturing has essentially made the transition from second class to world class. The improvements in manufacturing processes have included reducing the amount of human effort, space and inventory required in the factory and increasing the quality and variety of products and the flexibility of manufacturing operations. The application of “lean production” principles to manufacturing processes has been instrumental in achieving these results. Lean principles were developed in post–World War II Japan at the Toyota Motor Company. These principles evolved from geographic and economic constraints, from top-down, management-led innovation and from bottom-up pragmatic problem solving. They became collectively known as the Toyota Production System (Womack et al. 1990). The principles of lean theory are conceptualized at the process, project and enterprise or organization levels. Various principles, methods and tools can be applied at each level, so that lean production becomes an inclusive philosophy aimed at continuously improving the entire production organization as well as the physical production process. If manufacturing can make such vast improvements in quality and productivity, while reducing costs and lead times, why not construction? This report identifies the core principles of lean production, compares and contrasts the manufacturing and construction industries, and identifies the potential for implementing lean principles in the construction industry. The research team started with the following definition of lean construction: Lean construction is the continuous process of eliminating waste, meeting or exceeding all customer requirements, focusing on the entire value stream and pursuing perfection in the execution of a constructed project. This definition includes many fundamental aspects of a lean philosophy. It is a philosophy that requires a continuous improvement effort that is focused on a value stream defined in terms of the needs of the customer. Improvement is, in part, accomplished by eliminating waste in the process. Lean philosophy, broadly defined, can apply to design, procurement and production functions. To help define and direct research efforts and to present an elemental contribution to understanding lean principles in construction, the scope of this report was limited primarily to construction field operations. Although the focus of the inquiry was field operations, researchers were sensitive to the effects of policy and actions that occur at the enterprise, project and process levels. Two considerations led the research team to focus primary attention on construction field operations. First, field operations are where most of the value is added from the customer’s point of view. Cognizance of customer value is central to a lean philosophy. Second, other researchers have studied value streams and other aspects of lean philosophy. iii From this basis, the following questions were developed: • Are lean principles as defined in manufacturing applicable to the construction industry? If not, are there other principles that are more appropriate for construction? • What is the nature of the typical construction production value stream? • How should conformance to lean principles be measured? • Are lean principles commonly used in the construction industry? • What is the path forward to becoming lean? • What are the roadblocks to adopting a lean culture? These questions were investigated using a multifaceted approach. First, lean literature was examined from manufacturing, construction and other industries such as shipbuilding, aerospace, and software engineering. Second, advice from lean manufacturing pioneers was used, and the construction production value stream was studied. Next, contractors (both lean and non-lean) were surveyed to learn about lean practices that are currently employed in the construction industry. Using all of this information, a set of lean principles was developed that is appropriate for construction. In general, it can be concluded that construction owners and contractors would significantly benefit from the adoption of lean principles and behaviors. The value added portion of the typical field construction value stream is exceedingly small, comprising approximately 10 percent of all crew level activities. It was determined that lean behavior among construction contractors is rare, even with contractors who are actively pursuing the lean ideal, because being truly lean requires changes to every aspect and level of a company. Additionally, becoming a lean contractor is difficult in part because of the dynamic nature of construction, but mostly because construction contractors control such a small portion of the construction value stream. For those wishing to start the lean journey in their company, a lean workplace can be created using the following steps: • Identify waste in field operations. • Drive out waste. • Standardize the workplace. • Develop a lean culture. • Involve the client. • Continuously improve. iv Becoming lean is a long-term, comprehensive commitment; it amounts to a cultural change for the company. Construction is no simple deterministic system. Lean principles must be understood and applied in a context and require a comprehensive understanding of a complex, interacting and uncertain construction system. Many lean principles can be understood as attempts to increase preplanning ability, improve organizational design and increase flexibility. In this light, the final conclusion is that lean cannot be reduced to a set of rules or tools. It must be approached as a system of thinking and behavior that is shared throughout the value stream. Given that contractors control such a small portion of the construction value stream (as compared to their manufacturing counterparts), this is the challenge that faces the potential lean contractor. If successfully applied, however, lean has the potential to improve the cost structure, value attitudes and delivery times of the construction industry. v Contents Executive Summary ....................................................................................................................... iii 1.0 Introduction ........................................................................................................................ 1 1.1 Are Lean Manufacturing Principles Useful in Construction? ............................... 1 1.2 History of Lean Production ................................................................................... 1 1.3 The Diffusion of Lean Ideas.................................................................................. 5 1.4 Research Questions ............................................................................................... 5 1.5 Organization of Report.......................................................................................... 7 2.0 Lean Theory and Literature ................................................................................................ 8 2.1 Predominant Types of Manufacturing in the 20th Century: Conversion Model Versus Flow Model.................................................................................... 8 2.2 Fundamental Lean Principles .............................................................................. 12 2.3 Beyond Lean Manufacturing............................................................................... 16 3.0 Differences Between Construction and Manufacturing ................................................... 25 3.1 Lean Principles .................................................................................................... 25 3.2 Core Manufacturing Lean Principles................................................................... 25 3.3 Core Construction Lean Principles...................................................................... 27 3.4 Comparison of Construction and Manufacturing ................................................ 27 4.0 Research Methodology..................................................................................................... 34 4.1 Restatement of Research Questions .................................................................... 34 4.2 Developing Lean Principles for Construction ..................................................... 34 4.2.1 Goals.....................................................................................................34 4.2.2 Approach ..............................................................................................34 4.3 Measuring Lean Conformance ............................................................................ 35 4.3.1 Goals.....................................................................................................35 4.3.2 Approach ..............................................................................................35 4.4 Value Stream Mapping........................................................................................ 38 4.5 Bringing It Together............................................................................................ 39 5.0 Creation and Use of a Lean Assessment Instrument ........................................................ 41 5.1 Foundation/Design of the Questions ................................................................... 41 5.2 Design of the Questionnaire Using Field Studies................................................ 43 5.3 Case Study Interviews ......................................................................................... 44 5.4 Early Adopter Interviews .................................................................................... 44 5.5 Validation of the Questionnaire .......................................................................... 45 5.5.1 Stage One: Pilot Work .........................................................................45 5.5.2 Stage Two: Focus Group Responses ...................................................45 5.5.3 Stage Three: Statistical Reliability Analysis .......................................46 5.6 Use of Lean Principles in Construction............................................................... 47 5.6.1 Customer Focus ....................................................................................47 5.6.2 Culture/People ......................................................................................49 5.6.3 Workplace Standardization...................................................................49 5.6.4 Waste Elimination ................................................................................49 5.6.5 Continuous Improvement/Built-In Quality...........................................49 vi Contents (Continued) 5.7 5.8 5.9 6.0 Case Study Interview Results.............................................................................. 50 5.7.1 Customer Focus ....................................................................................50 5.7.2 Culture/People ......................................................................................50 5.7.3 Workplace Standardization...................................................................50 5.7.4 Waste Elimination ................................................................................51 5.7.5 Continuous Improvement/Built-In Quality...........................................51 Early Adopter Interview Results ......................................................................... 51 5.8.1 Customer Focus ....................................................................................51 5.8.2 Culture/People ......................................................................................52 5.8.3 Workplace Standardization...................................................................52 5.8.4 Waste Elimination ................................................................................52 5.8.5 Continuous Improvement/Built-In Quality...........................................53 Survey of Lean Implementation in Construction Literature................................ 53 5.9.1 Lean Implementation Case Studies at the Process Level......................53 5.9.2 Lean Implementation Case Studies at the Project Level ......................55 5.9.3 Lean Implementation Case Studies at the Organization Level.............57 Evaluating a Construction Value Stream ......................................................................... 59 6.1 Construction’s Production Value Stream ............................................................ 59 6.2 Categories of Work ............................................................................................. 59 6.2.1 VA Definition .......................................................................................59 6.2.2 NVAR Definition .................................................................................59 6.2.3 NVA (Waste Definitions) .....................................................................60 6.3 Data Collection Procedure................................................................................... 61 6.3.1 Hand Data Collection Method ..............................................................61 6.3.2 Video Data Collection ..........................................................................64 6.4 Case Studies ........................................................................................................ 64 6.4.1 Case Study No. 1 ..................................................................................64 6.4.2 Case Study No. 2 ..................................................................................64 6.4.3 Case Study No. 3 ..................................................................................66 6.4.4 Case Study No. 4 ..................................................................................66 6.4.5 Case Study No. 5 ..................................................................................66 6.4.6 Case Study No. 6 ..................................................................................66 6.4.7 Data Analysis........................................................................................66 6.5 Value Stream Analysis Results ........................................................................... 69 6.5.1 Structural Steel Case Studies ................................................................70 6.5.2 Process Piping Case Studies .................................................................73 6.5.3 Comparison of Processes......................................................................75 6.5.4 Value Stream Analysis .........................................................................76 6.6 Identifying Construction’s Value Stream............................................................ 76 6.7 Developing a Construction Value Stream Map................................................... 77 6.8 Building a Value Stream Map ............................................................................. 77 6.9 New Approach to Value Stream Mapping .......................................................... 78 6.9.1 Level Three...........................................................................................78 6.9.2 Level Two.............................................................................................82 6.9.3 Level One .............................................................................................84 6.10 New Idea for Displaying the Construction Value Stream ................................... 87 6.11 How Do the Value Stream Maps Differ Between Processes?............................. 90 vii Contents (Continued) 7.0 Results - Lean Principles for Construction....................................................................... 91 7.1 Assessing Lean Principles for Construction........................................................ 91 7.1.1 Customer Focus ....................................................................................92 7.1.2 Culture/People ......................................................................................95 7.1.3 Workplace Organization/Standardization.............................................98 7.1.4 Waste Elimination (Aspect 1: Process Optimization) .......................101 7.1.5 Waste Elimination (Aspect 2: Supply Chain)....................................106 7.1.6 Waste Elimination (Aspect 3: Production Scheduling) .....................106 7.1.7 Waste Elimination (Aspect 4: Product Optimization) .......................110 7.1.8 Continuous Improvement and Built-In Quality ..................................112 7.2 An Information-Based Perspective on Lean Principles..................................... 115 7.3 Applying Lean Principles to Construction ........................................................ 117 8.0 Conclusions and Recommendations............................................................................... 121 8.1 Reasons to Apply Lean Principles to Construction........................................... 121 8.2 Path Forward to Becoming Lean....................................................................... 121 8.2.1 Identify Waste in Field Operations.....................................................121 8.2.2 Drive Out the Waste ...........................................................................122 8.2.3 Standardize the Workplace .................................................................122 8.2.4 Develop a Lean Culture ......................................................................122 8.2.5 Get the Client Involved with the Lean Transformation ......................122 8.2.6 Continuously Improve ........................................................................122 8.3 Barriers to Developing a Lean Company .......................................................... 122 8.3.1 Little General Understanding of Lean ................................................123 8.3.2 Unique Projects and Unique Design...................................................123 8.3.3 Lack of Steady-State Conditions ........................................................123 8.3.4 No Control of the Entire Value Stream ..............................................123 8.4 Future Research................................................................................................. 123 8.4.1 Lean Coordination ..............................................................................123 8.4.2 Economics of Lean .............................................................................124 8.4.3 Importance of Repetition ....................................................................124 8.4.4 Reliability in Construction..................................................................124 8.4.5 Metrics for Lean Construction............................................................124 Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I Appendix J Case Study No.1 - Structural Steel .................................................................... 125 Case Study No. 2 - Structural Steel ................................................................... 152 Case Study No. 3 - Structural Steel ................................................................... 192 Case Study No. 4 - Process Piping .................................................................... 227 Case Study No. 5 - Process Piping .................................................................... 252 Case Study No. 6 - Process Piping .................................................................... 274 Lean Questionnaire and Principle Cross-Reference.......................................... 277 Interview Notes ................................................................................................. 285 Worker Movement Study No. 1 ........................................................................ 300 Worker Movement Study No. 2 ........................................................................ 308 References ................................................................................................................................... 313 Glossary....................................................................................................................................... 318 Acknowledgments ....................................................................................................................... 325 viii List of Tables Table 2.1 Table 2.2 Table 3.1 Table 3.2 Table 5.1 Table 6.1 Table 6.2 Table 6.3 Table 6.4 Table 6.5 Table 6.6 Table 6.7 Table 6.8 Table 6.9 Table 6.10 Table 6.11 Table 6.12 Table 6.13 Table 6.14 Table 6.15 Table 6.16 Table 7.1 Table 7.2 Table 7.3 Comparison of the Conversion Model and Flow Model ......................................11 Knowledge Areas of Management Theories ........................................................19 Comparison of Lean Manufacturing to Lean Construction Principles.................28 Lean Construction Principles ...............................................................................32 Cronbach’s Alpha Results ....................................................................................48 Comparison of Lean Manufacturing to Lean Construction Waste.......................62 Advantages and Disadvantages of Different Data Collection Methods ...............65 Typical Results for Welder Completing an Eight Inch Diameter Spool Section..................................................................................................................67 Typical Results for an Entire Crew ......................................................................68 Results for Case Study No.1 - Structural Steel Erection Process.........................70 Quick Summary for Case Study No. 1 .................................................................70 Results for Case Study No. 2 - Structural Steel Erection Process........................71 Quick Summary for Case Study No. 2 .................................................................71 Results for Case Study No. 3 - Structural Steel Erection Process........................71 Quick Summary for Case Study No. 3 .................................................................72 Results for Case Study No. 4 - Piping Installation Process..................................73 Quick Summary for Case Study No. 4 .................................................................73 Result for Case Study No. 5 - Piping Installation Process ...................................74 Quick Summary for Case Study No. 5 .................................................................74 Comparison of Different Processes ......................................................................75 Work Distribution Lifecycle Data ........................................................................89 Principles that Reduce Uncertainty in the Production Environment without Increased Planning or Information Handling ........................................118 Principles that Require Added Planning or Information Handling but Reduce Uncertainty in the Production Environment..........................................119 Principles that Require Added Planning or Information Handling but Reduce the Negative Effects of Instability in Production ..................................120 x List of Figures Figure 1.1 Figure 1.2 Figure 2.1 Figure 2.2 Figure 2.3 Figure 2.4 Figure 2.5 Figure 2.6 Figure 2.7 Figure 4.1 Figure 4.2 Figure 5.1 Figure 6.1 Figure 6.2 Figure 6.3 Figure 6.4 Figure 6.5 Figure 6.6 Figure 6.7 Figure 6.8 Figure 6.9 Figure 6.10 Figure 6.11 Manufacturing Performance (Anecdotal)...............................................................2 The Beginnings of Lean Production.......................................................................4 Conversion Process ................................................................................................8 The Conversion Model of Production ....................................................................8 Generalized Flow Model ......................................................................................10 Simplified Value Stream ......................................................................................10 The Flow Model of Production ............................................................................10 Delineation of Activities ......................................................................................12 Lean Production Conceptualization .....................................................................17 Overall Lean Construction Research Plan............................................................36 The Lean Wheel (after Tapping, Luyster et al. 2002) ..........................................37 Example of a Seven-Point Likert Scale Question ................................................42 Hand Data Collection Sheet .................................................................................63 Typical Results for Welder Completing an Eight Inch Diameter Spool Section..................................................................................................................68 Typical Results for an Entire Crew ......................................................................69 Traditional Value Stream Map .............................................................................79 Structure for a New Value Stream Map ...............................................................80 Level Three Data ..................................................................................................81 Level Two ............................................................................................................82 Typical Setup for a Substage Box in the Value Stream .......................................82 Main Stage from Level One Along with Required Substages from Level Two ............................................................................................................83 Level One .............................................................................................................86 Work Distribution Life Cycle Graph....................................................................88 xii 1.0 Introduction 1.1 Are Lean Manufacturing Principles Useful in Construction? Over the past three decades, the US construction industry has seen a decline in both its share of the gross national product and its annual productivity growth rate. The quality of construction has faltered during this period as well, with studies showing the cost of construction nonconformance reaching as high as 12 percent of total project costs (Koskela 1992). In contrast, the US manufacturing industry has made significant progress in increasing productivity and product quality while lowering product lead times: How have manufacturing organizations achieved the following results? • Half the amount of human effort required in the factory. • Half the manufacturing space required. • Half the engineering hours to develop a new product. • Less than half the inventory needed onsite. • Increased quality of products. • Increased variety of products. • Increased flexibility of manufacturing operations. • Decreased lead times. (Womack et al. 1990) The application of lean production principles to manufacturing processes has been instrumental in achieving these results. This report explores whether these same principles may be applied to construction processes to effect similar production improvements. 1.2 History of Lean Production Over the past three decades, US manufacturing has seen a resurgence in quality, flexibility and productivity, while also managing to lower product lead times and the cost of production. In other words, US manufacturing has made the transition from second class to world class (Schonberger 1996). According to Richard J. Schonberger, World Class Manufacturing: The Next Decade, much of this rebirth has been the result of an increased focus on production cycle times and quality. Subsequently, manufacturing management has seen a shift from conventional practices of planning and control to a focus on interactive sets of principles aimed at achieving and facilitating benefits, such as lower cycle times. Figure 1.1 (adapted from Schonberger 1996) illustrates the described performance trend in US manufacturing over the last half of the 20th century. 1 Figure 1.1: Manufacturing Performance (Anecdotal) Schonberger provides the “v-pattern” to illustrate the fall and rise of US manufacturing performance caused by both internal and external factors. The figure is not a direct depiction of economic indicators, but rather a representation of anecdotal evidence (Schonberger 1996). The negative trend seen between the 1950s and 1970s occurred at a time when manufacturing in the United States was just coming out of what is known as the post–World War II production era. At this time, product shortages within the United States increased demand and, subsequently, manufacturing was focused on producing large quantities of products. When supply had finally surpassed demand, the nation began to see the proliferation of excess capacity. During the early 1960s, international competition also began to increase its share of the world manufacturing market. With the immediate threats of excess capacity and foreign competition, the focus of manufacturing in the United States needed to change from producing volume to producing higher quality products at minimal cost and lead times. But how was the United States going to change from large-scale mass production pioneered by the late Henry Ford to more agile, customerfocused production? The answer to this question has been the diffusion of Japan’s highly successful production and management system termed “lean production” (Womack et al. 1990). The term was coined by John Krafcik, a researcher on the team from the International Motor Vehicle Program (IMVP) (Womack et al. 1990). IMVP was a team organized at the Massachusetts Institute of Technology during the mid-1980s with the objective of studying the innovative techniques used by the Japanese in their highly successful automotive industry (Womack et al. 1990). The logic of using the term “lean” will become clearer as the principles are clarified. The fundamental ideas of lean production have been described under numerous names as researchers and practicing professionals have sought to study and diffuse the core ideas. Names such as World Class Manufacturing (Schonberger 1997), New Production Philosophy (Koskela 1992), Lean Thinking (Womack and Jones 1996), Just-in-Time/Total Quality Control, Time Based Competition, and many similar methods and principles have been used to describe the same fundamental collection of ideas (Koskela 1992). The foundations of lean production were developed in post–World War II Japan, when the Japanese manufacturing industry underwent a complete rebuilding (Womack et al. 1990). Lean pioneers Kiichiro Toyoda, Eiji Toyoda and Taiichi Ohno of the Toyota Motor Company developed many of the underlying principles of lean production in response to pragmatic considerations and existing geographic circumstances. The impetus for lean production occurred when Kiichiro, president of Toyota at the time, demanded that Toyota “…catch up with America in three years. Otherwise the automobile industry of Japan will not survive” (Ohno 1988; Hopp 2 1996). At the time, limited supply of raw materials and inadequate space for inventory in Japan fostered an atmosphere in which concepts such as just-in-time (JIT) and zero inventories became necessary. During the spring of 1950, Eiji Toyoda visited American manufacturers, namely Ford’s Rouge Plant in Detroit, to study mass production and perhaps look for ways to improve the country’s own rebuilding industry (Womack et al. 1990). This was the second visit to study US manufacturing practices made by the Toyoda family; the first was made by Kiichiro in 1929. What Eiji Toyoda found was a system rampant with muda, a Japanese term that encompasses waste (Womack 1996). He noted that only the worker on the assembly line was adding value to the process. Another striking feature was the emphasis placed by their American counterparts on continually running the production line. This common practice was thought to be justified by the expense of purchasing such equipment. To the Japanese, this practice appeared to compound and multiply errors, a mistake the Japanese could not afford to make. Japan’s labor productivity at the time was one ninth that of the United States, and it became obvious to Toyota that it could not compete with the United States by depending on economies of scale to produce massive volumes for a small market that did not have the same type of demand (Ohno 1988; Shingo 1981; Hopp 1996). Toyota then made the strategic decision to focus its manufacturing efforts not on massive volumes of a product but, rather, on many different products in smaller volumes. In his numerous experiments focused on reducing machine setup times, Ohno, Toyota’s chief production engineer, noted that the cost of producing smaller batches of parts was less than that of producing larger quantities as practiced in the United States. This was true because making small lot sizes greatly reduced the carrying costs required for huge inventories, and the cost of rework was reduced because defects showed up instantly in smaller batches (Womack et al. 1990). Ohno also managed to reduce the amount of time required for machine setup from an entire day to three minutes, a task that enabled Toyota to increase the flexibility of its production lines as well as reduce production times. The concept of JIT was developed to complement this new production philosophy undertaken at Toyota. The model for JIT was the American supermarket, a relatively new idea to the Japanese in the 1950s (Hopp 1996). The American supermarket provided customers with what they needed, when they needed it and in the right amount needed. JIT further evolved to include concepts found to be crucial to the effective operation of the JIT system and that would later become goals of the system. These concepts are referred to as the seven zeros: zero defects, zero lot size, zero setups, zero breakdowns, zero handling, zero lead time and zero surging (Hopp 1996). The contributions of quality pioneer W. Edwards Deming to post–World War II Japan altered the way Japanese manufacturers viewed quality. Deming’s Total Quality Management (TQM) system permeated throughout organizations to create a quality culture, where quality became the primary goal of producers. After World War II, quality had taken a back seat to production, and it was reasoned that intensive inspection at the end of the process would be adequate. With its focus on the entire organization, TQM addressed issues that were relatively new to the manufacturing industry at that time, such as employee empowerment, continuous improvement and the concept of proactively building quality into products versus the reactive nature of inspecting for quality at the end of the process (Walton 1986). The Japanese would improve on the teachings of Deming and create what is known as Total Quality Control (TQC). Thus, coupled with the company’s move toward multi-skilled teams, guarantees of lifetime employment and pay raises linked only to seniority within the company, Toyota began to create a culture in which the quality of its product improved dramatically. In addition to shifting the focus of Japanese manufacturers to quality, Deming also equipped them with the statistical tools to achieve it, such as Statistical Quality Control (SQC). The teachings of Deming and other quality gurus, such as Joseph Juran and Philip Crosby, fueled a quality movement within the Japanese manufacturing industry that would take decades to diffuse into mainstream Western 3 manufacturing and that would be highly influential to the development of lean production techniques. From this background, the Toyota Production System was created in the early 1960s through the combination of compensation for geographical restrictions, astute observation of current problems within the industry, development of JIT and the teachings of the quality movement, among other factors. It seems that postwar Japan, in its state of chaos, provided a perfect laboratory in which innovative thinking could be implemented and practiced (Womack et al. 1990). The actual process, however, took many years of trial and error. The Toyota Production System presents an outline of the foundations of lean production. Figure 1.2 illustrates the forces that influenced the development of lean production. Post World War II Japan (Toyota Motor Company) Limited Natural Resources Development of JIT Lower Demand Limited Space Quality Movement Mass Production Practices Additional Factors Beginnings of Lean Production Figure 1.2: The Beginnings of Lean Production In the late 1970s, this new production system was brought to the United States and contributed to a manufacturing renaissance that continued within the United States for the next three decades (Schonberger 1996). Studies have shown the incredible benefits lean production methods have brought specifically to the automobile manufacturing industry where the ideas originated. According to James P. Womack and Daniel T. Jones, two of the leading researchers of lean production systems and coauthors of numerous lean texts such as The Machine That Changed the World and Lean Thinking, lean automobile manufacturing has been characterized as using the following: …half the human effort in the factory, half the manufacturing space, half the investment in tools, half the engineering hours to develop a new product in half the time. Also, it requires keeping far less than half the needed inventory on site, results in many fewer defects, and produces a greater and ever growing variety of products (Womack et al. 1990). The visible success of lean principles in the automobile industry and in manufacturing generally has prompted other industries to adapt and apply these concepts to achieve similar benefits. 4 1.3 The Diffusion of Lean Ideas Lean principles have been amended and expanded over the decades by those in other industries who are transferring lean ideas and successes to their respective industries. The software, aerospace, air travel and shipbuilding industries all have extensive efforts directed at applying lean principles to improve profitability and quality and reduce waste. The architecture, engineering and construction (AEC) industry has a far-reaching, worldwide effort to apply lean principles and practices. North America, Europe and South America have organizations devoted exclusively to studying lean ideas and applying them. In fact, the efforts of the AEC industry have led the way toward innovative ideas about the application of lean thinking to the construction industry. Koskela (1992, 2000) originated the idea that construction processes must be viewed as systems of transformations, flows and value adding actions, the so-called TFV model. Bertelsen (2002) expanded the manufacturing model of lean to include the ideas of construction as one-of-a-kind production, construction as a complex system and construction as cooperation. Ballard and Howell (1998) in their paper, “What Kind of Production is Construction,” describe differences between manufacturing and construction. In the United Kingdom, the Construction Task Force produced “Rethinking Construction” (The Egan Report) that applies the lessons of the manufacturing revolution to the construction sector in the United Kingdom. Another innovation in the application of lean theory to construction was the development of the Last Planner (Ballard 2000a) that emphasizes reliability in the planning function. Others (Matthews 2003; Ballard 2002c; Tommelein 2003; dos Santos 1999) have addressed the impact that lean principles have had on contracts, project delivery and project supply chains. In this way, the core idea of lean principles as originally set forth by Ohno was expanded and adapted throughout the manufacturing sector. Other management thinkers have coupled diverse management theories such as concurrent engineering and TQM to these core lean principles. “Lean theory” and “lean applications” for AEC design, procurement and production functions have received significant attention in many quarters around the world. 1.4 Research Questions The goal of the research team was to take what is already known about lean theory and practice from manufacturing and from construction’s early adopters and distill that information into a straightforward set of lean principles for construction. The research team started with the following definition of lean construction: Lean construction is the continuous process of eliminating waste, meeting or exceeding all customer requirements, focusing on the entire value stream and pursuing perfection in the execution of a constructed project. This definition includes many fundamental aspects of a lean philosophy: • Lean requires a continuous improvement effort. • Improvement focuses on a value stream that is defined in terms of the needs of the customer. • Improvement is, in part, accomplished by eliminating waste in the process. 5 A lean philosophy, broadly defined, can apply to design, procurement and production functions. Lean can apply to the enterprise or company level, to the project level and to the individual process level. To help define and direct research efforts and to present an elemental contribution to the understanding of lean principles in construction, the scope of this report was limited primarily to construction field operations. Though the focus of the inquiry was field operations, researchers were sensitive to the effects of policy and actions that occur at the enterprise, project and process levels. Two considerations led the research team to focus its primary attention on construction field operations. First, field operations are where most of the value is added from the customer’s point of view, so cognizance of customer value is central to a lean philosophy. Second, others have studied various aspects of lean philosophy, and this information could be used as a foundation for this report. For example, Seymour (1996) and Ballard (2000c) have defined an agenda for lean construction across the entire project life. Arbulu (2002), Tommelein (2003) and London (2001) have addressed construction supply chains. Likewise, aspects of the design process to promote lean principles are discussed by Ballard (2000d), Koskela (1997) and Freire (2002), who have all addressed different aspects of lean design. Taking into consideration the history of lean principles and prior research, the following question was posed: • Are lean principles as defined in manufacturing applicable to the construction industry? If not, are there other principles that are more appropriate for construction? To explore how manufacturing principles map to the construction process, these questions were defined: • What is nature of the typical construction production value stream? • What is the value stream for field production activities and for the field portion of material delivery and handling? After an understanding is gained about how lean principles apply or can be modified for construction, these questions may be addressed: • How should conformance to lean principles be measured? • Are lean principles commonly used in the construction industry? Finally, to benefit the Construction Industry Institute (CII) membership, the following two questions were considered: • What is the path forward to becoming lean? • What are the roadblocks to adopting a lean culture? 6 1.5 Organization of Report This report is organized into eight chapters and 10 appendices. Chapter 2 presents a comprehensive review of both manufacturing and construction literature on lean principles. Chapter 3 explores the differences between the manufacturing and construction domains. Chapter 4 describes the methodology used for this study. Chapter 5 describes the development of a questionnaire that can be used by a contractor to self-assess lean behavior. Chapter 6 describes the results of the value stream mapping studies. Chapter 7 communicates the study findings regarding lean principles for construction. Finally, Chapter 8 describes research team recommendations for the future of lean principles in construction. The appendices contain the details of each of the value stream case studies as well as information on the validation of the questionnaire and questionnaire interview notes. Additionally, the appendices contain two studies on the impacts of excess worker movement. 7 2.0 Lean Theory and Literature 2.1 Predominant Types of Manufacturing in the 20th Century: Conversion Model Versus Flow Model To fully understand lean production, it is important to become familiar with the two predominant types of production systems of the 20th century. Traditionally, US manufacturing has been viewed as a mass production system focusing primarily on the process of conversions (Koskela 1992). Figure 2.1 (adapted from Figure 3, Koskela 2000) illustrates this basic concept. Figure 2.1: Conversion Process The conventional breakdown of the manufacturing process into a series of activities, each undertaking the conversion of an input to an output, referred to as the conversion model or transformation model, is illustrated on Figure 2.2 (adapted from Rother 1998). This type of production system historically uses what is called a batch and queue theory (Womack 1996). Batch and queue refers to the theory that for machines to achieve a high utilization rate, they must be run continually. As a result of this, parts are manufactured in large batches at one process within a plant and then queued for the next process. Batch and queue theory leads to many manufacturing problems, such as bottlenecking and large inventories from high work-in-progress (WIP) levels. Figure 2.2: The Conversion Model of Production The inventories created by WIP are referred to in manufacturing as buffers (Womack 1996). Buffers generally reduce the variability of workflows within a plant by shielding downstream activities from uncertainties that might occur upstream, such as machine failure or differing machine output rates. Such buffers may be the result of WIP or even planned into the 8 manufacturing process. Buffers can be viewed as an advantage if high degrees of variability exist within the manufacturing process. Disadvantages associated with overbuffering include increased product lead times, increases in required working capital, as well as increased space requirements to produce and store the additional parts and components acting as the buffers. By using such queuing techniques, manufacturers also become susceptible to quick changes in the marketplace. For example, if demand in the market for a certain product decreases, the manufacturer may be caught with high levels of WIP acting as buffers and be forced to decide whether it would be financially feasible to complete the production of the product or to terminate production and scrap the partially completed work. The concept of manufacturing a product based on forecasted sales data and then selling it is referred to as “push” production (Womack 1996). This differs greatly from the idea of producing an item only when it has been ordered or purchased, which is “pull” production. In other words, the market for the product is pulling the production versus pushing the product out to the customer. The view of manufacturing as a process of conversions tends to emphasize push production. Thus, products are created because demand has been forecasted and then pushed onto the market. The conversion model of production views improvement of the production process as a subprocess task. For example, to improve the process on Figure 2.2, the producer would make efforts to improve each subprocess individually by either reducing the cost of the specific activity and/or by increasing the efficiency of the activity. Thus, in theory, by improving each activity (A, B, C), the entire conversion process will improve. This view is termed “reductionist” because it uses analytical reduction to break the process into its individual components and view each as a separate entity in need of improvement (Koskela 1992). Historically, improvements to the conversion model have focused on the implementation of new technologies such as automation and computerization (Koskela 1992). In their book, The Machine That Changed the World, James P. Womack, Daniel T. Jones and Daniel Roos provide an excellent descriptive summary of the typical mass producer: The mass producer uses narrowly skilled professionals to design products made by unskilled or semiskilled workers tending expensive, single-purpose machines. These churn out standardized products in very high volume. Because the machinery costs so much and is so intolerant of disruption, the mass producer adds many buffers – extra supplies, extra workers, and extra space to assure smooth production. Because changing over to a new product costs even more, the mass producer keeps standard designs in production for as long as possible. The result: The consumer gets lower costs but at the expense of variety and by means of work methods that most employees find boring and dispiriting (Womack et al. 1990). The view of production as a series of conversions is fundamentally different from the second dominant type of production in the 20th century, the view of manufacturing as a flow model (Koskela 1992). Production as a flow process is one of the core ideas of lean production. Figure 2.3 (adapted from Rother 1998) represents a generalized flow model of production. 9 Figure 2.3: Generalized Flow Model Unlike the traditional view of production, the flow process does not view the production stream solely as a series of conversions. The conceptualization of manufacturing as a flow model delineates between those activities that add value to the process (conversion) and those that do not (Koskela refers to them as flow activities) (Koskela 1992). It should be noted that to avoid confusion about flow, this report will refer to activities that do not add value as non-value adding. By defining the different types of activities that occur in production, the focus of improvement does not become compartmentalized as on Figure 2.2, but rather envelops the entire value stream (Womack 1996). The value stream of a particular product consists of all activities and parties involved in its creation, from raw material suppliers to the customer as illustrated on Figure 2.4. Compartmentalized improvements can become troublesome to downstream activities if the particular cycle times of sequential operations are not matched. In other words, if Process A has half the cycle time of Process B, a material buffer will occur at Process B because it cannot keep up with the amount of work produced by Process A. Figure 2.4: Simplified Value Stream Examples of non-value adding activities, or muda, are large inventories, wait times, inspection time, WIP and overproduction (Womack 1996). Improvement to the system would then entail not only reducing the cost and improving the efficiency of the value adding activities, but also reducing and/or eliminating the non-value adding activities. Figure 2.5 (adapted from Koskela 2000) illustrates these concepts. Figure 2.5: The Flow Model of Production 10 Improving the system through waste elimination and conversion activity improvement allows all elements of the entire production process to be enhanced. The flow process tends to focus on the elimination of the large buffers found within mass manufacturing by emphasizing the constant movement of components from one value adding activity to the next. This type of system, also referred to as single-piece flow (Womack 1996), is associated with several benefits. First, the WIP levels are dramatically reduced, which also reduces the inventory space required as well as the capital to produce and stock extra inventories of partially completed products. Combined with reducing equipment setup times, low WIP levels can help a manufacturer become more responsive to market conditions. As a result, the producer lets the customer, or market, pull the production. Compared to the conversion model, flow operations are much more tightly controlled in terms of production times and supply chain coordination to minimize variability within the process. In fact, the introduction of time as an input to the production process is fundamentally different from the conversion model of production because the process is no longer conceptualized as solely an economic abstraction, but rather as a physical process (Koskela 1992). Time was considered important before the advent of the flow model, but the entire production system was not centered on time as a goal. This view of time is important because the flow process does not contain the buffers necessary to minimize variability within the manufacturing process and, therefore, must rely on the coordination of processes both internal and external to the plant. Table 2.1 and Figure 2.6 summarize the major differences between the two predominant production theories of the 20th century. Table 2.1: Comparison of the Conversion Model and Flow Model Description Conversion Model Flow Model Conceptualization Manufacturing as a series of conversion activities Manufacturing as a combination of value and non-value adding activities Basic Queuing Theory Batch and queue Single-piece flow Inventory Implications Large inventories as a result of batch and queue production and WIP Minimal inventories Production Trigger Products pushed onto the market as a result of forecasted demand Products pulled onto the market by demand Focus on Improvement Improvement focused on lowering cost and increasing productivity of each activity (analytical reductionism) Improvement focused on lowering cost and increasing productivity of value adding activities and reducing/eliminating non-value adding activities Variability Control Buffers used to control variability Use of coordination among internal operations as well as supply chain management to reduce variability Focus of Control Cost and time of activities Cost, time and value of value adding and non-value adding activities 11 Figure 2.6: Delineation of Activities 2.2 Fundamental Lean Principles The work of Lauri Koskela has yielded the following list of principles believed to be crucial to lean production: • Meeting the Requirements of the Customer. Attention must be paid to quality as defined by the requirements of the customer. The success of production hinges on the satisfaction of the customer. A practical approach to this is to define the customers for each stage and analyze their requirements. • Reducing Non-Value Adding Activities. Non-value adding activities generally result from one of three sources: the structure of the production system, which determines the physical flow that is traversed by material and information; the manner in which the production system is controlled; and the nature of the production system such as defects, machine breakdowns and accidents. • Reducing Cycle Time. Cycle time is defined as the total time required for a particular piece of material to traverse the flow. Cycle time can be represented as follows: Cycle Time= Processing Time +Inspection Time +Wait Time +Move Time Research has identified the following activities that reduce cycle time: − Eliminating WIP. − Reducing batch sizes. − Changing plant layout so that moving distances are minimized. − Keeping things moving; smoothing and synchronizing flows. − Reducing variability. − Isolating the main value adding sequence from support work. − Changing activities from sequential to parallel ordering. − Solving problems caused by constraints slowing down material flow. 12 • • Reducing Variability. Variability of activity duration increases the volume of non-value adding activities. It may be shown through queuing theory that variability increases cycle time. Variability reduction is aimed at reducing both the nonconformance of products as well as duration variability during both value adding and non-value adding activities. A few strategies aimed at variability reduction are as follows: − Standardization of activities by implementing standard procedures. − Mistake-proofing devices (poke yoke). Increasing Flexibility. The ability of the production line to meet the demands of the marketplace and change must be increased. Research has recognized the following activities aimed at increasing output flexibility (Stalk 1990): − Minimizing lot sizes to closely match demand. − Reducing the difficulty of setups and changeovers. − Customizing as late in the process as possible. − Training a multi-skilled workforce. • Increasing Transparency. The entire flow operation must be made visible and comprehensible to those involved so that mistakes can be located and solved quickly. • Maintaining Continuous Improvement. The organization must continually strive to incrementally improve operations and management methods. The following methods have been classified as necessary for institutionalizing continuous improvement: • − Measuring and monitoring improvement. − Setting stretch targets (e.g., for inventory elimination or cycle time reduction) by means of which problems can be found and solved. − Giving responsibility for improvement to all employees; steady improvement from every organizational unit should be required and rewarded. − Using standard procedures as hypotheses of best practices, to be constantly challenged by better ways. − Linking improvement to control; improvement should be aimed at the current control constraints and problems of the process. The goal is to eliminate the root of problems rather than to cope with their effects. Simplifying by Minimizing the Number of Steps, Parts, and Linkages. Complexity produces waste as well as additional costs. When possible, the process should be streamlined through efforts such as consolidating activities; 13 standardizing parts, tools and materials; and minimizing the amount of control information needed. Practical approaches to simplification include the following: − Shortening flows by consolidating activities. − Reducing the part count of products through design changes or prefabricated parts. − Standardizing parts, materials, tools, etc. − Decoupling linkages. − Minimizing the amount of control information needed. • Focusing Control on the Complete Process. Segmented flow leads to suboptimization and should be avoided; thus, control should be focused on the entire process for optimal flow. • Balancing Flow Improvement with Conversion Improvement. Flow improvement and conversion improvement are interconnected; therefore, their individual improvements should be analyzed to create balance within the process. • Benchmarking. Benchmarking can provide the stimulus to achieve breakthrough improvement through radical reconfiguration of processes. James P. Womack and Robert T. Jones (1996) have identified five fundamental and sequential steps that create a conceptual outline of what they call “lean thinking.” A quick comparison with the ideas outlined by Koskela reveals many similarities, as the works of Womack and Jones have proven to be influential within this particular field of study. The steps are as follows: • • Step 1. Specify value from the standpoint of the customer: − Understand the customer. − Target cost. − Look at the whole. − Specify value by product/service. − Value must be defined for each product family, along with a target cost based on the customer’s perception of value. Step 2. Identify the value stream for each product family: − Understanding flow is the key technique for eliminating waste (muda). − Create a vision of flow. 14 • • • − Compete against perfection by eliminating muda. − Identify value adding activities. − Identify contributory non-value adding but required activities (Type I muda). − Identify non-value adding activities (Type II muda). − Rethink operating methods. − Eliminate sources or root causes of waste in the value stream. Step 3. Make the product flow: − Focus on actual object from beginning to completion and produce continuous flow. − Ignore traditional boundaries (department). − Apply all three of these steps at the same time. − Work on the remaining non-value adding activity (Type I muda). − Synchronize and align so there is little waiting time for people and machines. − Match workload and capacity. − Minimize input variations. Step 4. Ensure that this happens at the pull of the customer: − Communicate. − Apply level scheduling. − Release resources for delivery just when needed. − Practice JIT supply rather than JIT production. − Continue to work on the remaining non-value adding activity (Type 1 muda). Step 5. Manage toward perfection: − Increase transparency. − Form a picture of perfection. 15 Individually, the principles, methods and techniques have been applied with partial success, but together, they create a powerful framework and philosophy for improving manufacturing performance. It is important to realize that this framework affects not only the production process; it requires a fundamental shift in how an organization thinks about itself. The ideas behind these principles create the backbone of a lean production environment. The overlap of ideas from JIT, TQM, Visual Management, Time Based Competition and other manufacturing methodologies, philosophies and practices are explored in the following sections. 2.3 Beyond Lean Manufacturing With the basic idea of flow production systems established, it is important to look beyond core manufacturing ideas to the broader context of “lean.” Figure 2.7 illustrates an example of how one might conceptualize lean production. First, it might be conceptualized as a grouping of principles and goals crucial to the operation of a flow system, such as reducing lead times and variability. Second, it might be conceptualized as a set of methods aimed at facilitating the principles and goals of flow operations, such as pull scheduling. Third, it might be conceptualized as a set of tools that aid the methods, such as utilizing Kanban cards to trigger pull scheduling. The level of detail increases as one views the chart from left to right. Although the figure does not include all elements of lean production, it does provide a basic outline of the lean production process. The ideas of lean can also be conceptualized on the following three levels (Koskela 2000): 1. Process Level--A set of tools, such as Kanban cards, poke yoke, etc. 2. Project Level--A production planning method, such as JIT. 3. Organization Level--General management theory, such as TQM. Lean implementation may consist of applying lean principles at any of the three levels. A comprehensive lean implementation will cover all aspects of the business directly related to production, transport, supply or service activities (dos Santos 1999; Schroeder 1993; Wild 1995). An examination of several knowledge areas can aid in the understanding of how lean principles affect the different aspects of a production organization. The knowledge areas of a production organization can be generalized as follows (Fearon et al. 1979): 1. Design and Development. Design and development of products and/or services that meet the needs of customers as well as the needs of the manufacturing process (manufacturability) is one element of a production organization; it typically includes product life-cycle analysis, value engineering, product prototyping, market research and product specification. 16 Figure 2.7: Lean Production Conceptualization 2. Work Configuration. Work configuration refers to the design of the operating system for an organization. Location of the facilities, plant layout and work study are considered the three most important factors when determining a particular organization’s work configuration. 3. Scheduling and Planning. This portion of a production organization refers to the determination of demand for a specific product and the planning of production as well as the scheduling of resource requirements to meet that demand. 4. Quality. Quality in a production organization includes the determination of what constitutes quality in the process, what relevant costs are linked to quality, how quality is to be achieved and ensured and what level of quality is desired. 5. Inventory Management. Inventory management refers to issues such as how much of a particular item should be produced to replenish stocks as well as how stocks should be stored and handled. 6. Human Resources Management. This element of a production organization concerns how a producer organizes and interacts with its employees. Human resources management also affects the corporate culture of a company. 17 7. Supply Chain Management. Supply chain management involves the management of internal and external sources of materials, supplies and services to support operations. Manufacturing has seen a proliferation of theories directed toward improving different aspects of production and operations management. Many of these theories share similar fundamental goals with lean production and, in many cases, were highly influential in the development of lean principles. It can be difficult to distinguish between overlapping concepts in these theories. Table 2.2 organizes selected manufacturing theories, methodologies and techniques into the respective knowledge areas of the production organization to which they apply. A brief review of the concepts of these methodologies reveals that there is a considerable amount of overlap that occurs when these movements are compared to the principles identified as crucial to lean. For example, Time Based Competition (TBC) directly relates to the principle of reducing lead times, while Visual Management (VM) strives to make the process transparent to those involved. It can be concluded that lean, as it is understood today, is a conglomeration or synthesis of many theories, philosophies, methods and techniques, many of which are individual methodologies within the manufacturing community. The evolution of lean ideas within manufacturing has been a process of trial and error that has incorporated both “top down” (theoretical) and “bottom up” (pragmatic) problem solving and many of the ideas discussed in Table 2.2. As a first step toward establishing a set of lean principles for construction, Chapter 3 considers the similarities and differences between construction and manufacturing. Chapter 5.0, Section 5.9, surveys available literature on the implementation of lean principles in construction. 18 Table 2.2: Knowledge Areas of Management Theories 1. Design and Development A. Concurrent Engineering (CE) Concurrent (or simultaneous) engineering deals primarily with the product design phase. The term refers to an improved design process characterized by rigorous upfront requirements analysis, incorporating the constraints of subsequent phases into the conceptual phase, and the tightening of change control toward the end of the design process. Compression of the design time, increase of the number of iterations (i.e., increase in the frequency of information exchange), and reduction of the number of change orders are three major objectives of CE. B. Poke Yoke This is a manufacturing technique for preventing mistakes by designing the manufacturing process, equipment and tools so that an operation literally cannot be performed incorrectly; an attempt to perform incorrectly, in addition to being prevented, is usually met with a warning signal of some sort; the term poke yoke is sometimes used to signify a system where only a warning is provided. C. Modular Design Modular design is organizing a set of distinct components that can be developed independently and then “plugged together.” D. Value Engineering Value engineering is the systematic application of recognized techniques by a multidisciplined team to identify the function of a product or service, establish a worth for that function, generate alternatives through the use of creative thinking, and provide the needed functions to reliably accomplish the original purpose of the project at the lowest life-cycle cost without sacrificing safety, necessary quality and environmental attributes of the project. E. Standard Work Design Standard work design is the design of each work activity specifying cycle time, work sequence of specific tasks and minimum inventory of parts on hand needed to conduct the activity. 19 Table 2.2: Knowledge Areas of Management Theories (Continued) 2. Work Configuration A. Visual Management (VM) VM is an orientation toward visual control in production, quality and workplace organization. The goal is to render both the standard to be applied and a deviation from it as immediately recognizable by anyone. This is one of the original JIT ideas that has been systematically applied only recently in the West. B. Cellular Manufacturing Cellular manufacturing is an approach in which manufacturing work centers (cells) have all the necessary capabilities to produce an item or a group of similar items. C. Flexible Manufacturing Flexible manufacturing is an integrated manufacturing capability to produce small numbers of a great variety of items at a low unit cost. Flexible manufacturing is also characterized by low changeover time and rapid response time. 3. Scheduling and Planning A. Line Balancing Line balancing is a means of balancing the appropriate number of workers needed for a production line by satisfying cycle time and precedence constraints. B. Just-in-Time (JIT) JIT is a scheduling philosophy that emphasizes delivery (when needed) of small lot sizes. JIT includes focusing on setup cost reduction, small lot sizes, pull systems, level production and elimination of waste. C. Critical Path Method/PERT (CPM/PERT) CPM/PERT is a method of determining the critical path by examining the earliest and latest start and finish times for each activity. D. Aggregate Planning Aggregate planning includes the broad, overall decisions that relate to the programming of resources for production over an established time horizon. E. Master Production Schedule (MPS) MPS is a time-phased plan specifying the number and the time frame for building each end item. F. Distribution Requirements Planning (DRP) DRP is the function of determining the need to replenish inventory at branch warehouses over a period of time. 20 Table 2.2: Knowledge Areas of Management Theories (Continued) 3. Scheduling and Planning (Continued) G. Queuing Theory Queuing theory is a branch of mathematics that deals with understanding systems with customers (orders, calls, etc.) arriving and being served by one or more servers. Queuing theory models are usually concerned with estimating the steady-state performance of the system such as the utilization, the mean time in queue, the mean time in system, the mean number in queue and the mean number in the system. H. Theory of Constraints (TOC) TOC is a management philosophy that recognizes that there are very few critical areas, resources or policies that truly block the organization from moving forward. If performance is to be improved, an organization must identify its constraints, exploit the constraints in the short run and, in the longer term, find ways to overcome the constraints (limited resources). 4. Quality A. Total Quality Management (TQM) TQM is an approach for improving quality that involves all areas of an organization: sales, engineering, manufacturing, purchasing, etc., with a focus on employee participation and customer satisfaction. TQM can involve a variety of quality control and improvement tools and emphasizes a combination of managerial principles and statistical tools. B. Statistical Quality Control (SQC) SQC uses statistical methods to identify, prioritize and correct elements of the manufacturing process that detract from high quality. C. Taguchi Methods Taguchi methods were developed to improve the implementation of TQC in Japan. They are based on the design of experiments to provide near optimal quality characteristics for a specific objective. The goal is to reduce the sensitivity of engineering designs to uncontrollable factors or noise. This is sometimes referred to as “robust design” in the United States. D. ISO 9000 ISO 9000 is a standard that provides an external motivation to say what you do and do what you document. E. Quality Function Deployment (QFD) QFD is a method for ensuring that the customer has a voice in the design specification of a product. QFD uses inter-functional teams from manufacturing, engineering and marketing. QFD is the only comprehensive quality system aimed specifically at satisfying the customer. 21 Table 2.2: Knowledge Areas of Management Theories (Continued) 4. Quality (Continued) F. Total Quality Control (TQC) The difference between TQM and TQC is epitomized by the phrase “management vs. control.” Most companies “control” quality by a series of inspection processes, but “managing” quality is a continuous quality improvement program. However, a good control system is the first step in the development of a management system. G. Acceptable Quality Level (AQL) AQL is a concept that holds that there is some non-zero level of permissible defects. H. Six Sigma Six Sigma is a structured application of the tools and techniques of TQM on a project basis to achieve strategic business results. It is sometimes defined as a failure rate of 3.4 parts per million. I. Zero Defects Zero defects is a concept introduced by Japanese manufacturers that stresses the elimination of all defects. This concept contrasts with the idea of AQL. J. Quality Circles Quality circles are teams that meet to discuss quality improvement issues. 5. Inventory Management A. Just-in-Time (JIT) This scheduling philosophy emphasizes delivery when needed of small lot sizes. JIT includes focusing on setup cost reduction, small lot sizes, pull systems, level production and elimination of waste. B. Material Requirements Planning (MRP) MRP is a system to support manufacturing and fabrication organizations by the timely release of production and purchase orders using the production plan for finished goods to determine the materials required to make the product. C. Manufacturing Requirements Planning (MRP II) MRP II is a method for effective planning of all the resources of a manufacturing company. Ideally, it addresses operational planning in units, financial planning in money, and has a simulation capability to answer “what-if” questions. D. Economic Order Quantity (EOQ) EOQ deals with the optimal order quantity (batch size) that minimizes the sum of the carrying and ordering cost. E. Period Order Quantity (POQ) POQ is a lot sizing rule that defines the order quantity in terms of the period’s supply. F. Stock Keeping Unit (SKU) SKU is a unique identification number (or alphanumeric string) that defines an item for inventory. 22 Table 2.2: Knowledge Areas of Management Theories (Continued) 6. Human Resources Management A. Total Quality Management (TQM) TQM is a an approach for improving quality that involves all areas of an organization: sales, engineering, manufacturing, purchasing, etc., with a focus on employee participation and customer satisfaction. TQM can involve a variety of quality control and improvement tools and emphasizes a combination of managerial principles and statistical tools. B. Employee Involvement Rapid response to problems requires empowerment of workers. Continuous improvement is heavily dependent on day-to-day observation and motivation of the workforce, hence, the idea of quality circles. To avoid waste associated with division of labor, multiskilled and/or self-directed teams are established for product/project/customer based production. C. Cross Training and Job Rotation Under this theory, employees are rotated out of their jobs after a certain duration and trained in new jobs. They are not only trained how to do the job, but they are also trained about the quality and maintenance issues that go along with the job. The principle here is that an employee with a well-rounded background about how the company operates will be more valuable to the company in making improvements. 7. Supply Chain Management A. Outsourcing Outsourcing is that practice of procuring raw materials and components externally rather than creating them internally. B. Strategic Partnering Partnering is a structured management approach to facilitate teams working across contractual boundaries. With such coordination, construction companies may benefit from reductions in delivery times, improved supplier responsiveness, improved quality of products and services, as well as reductions in costs. Miscellaneous A. Kaizen Kaizen is the philosophy of continual improvement. This approach proposes that every process can and should be continually evaluated and improved in terms of time required, resources used, resultant quality and other aspects relative to the process. B. Kanban Kanban is a card or sheet used to authorize production or movement of an item. The quantity authorized per individual kanban is minimal, ideally one. 23 Table 2.2: Knowledge Areas of Management Theories (Continued) Miscellaneous (Continued) C. Total Productive Maintenance (TPM) TPM refers to autonomous maintenance of production machinery by small groups of multiskilled operators. TPM strives to maximize production output by maintaining ideal operating conditions. D. Continuous Improvement Continuous improvement, associated with JIT and TQC, has emerged as a theme itself. A key to this approach is to maintain and improve the working standards through small, gradual improvements. The inherent wastes in the process are natural targets for continuous improvement. The term “learning organization” refers partly to the capability of maintaining continuous improvement. E. Benchmarking Benchmarking refers to comparing one’s current performance against the world leader in any particular area. In essence, it means finding and implementing best practices in the world. Benchmarking is essentially a goal setting procedure. F. Time Based Competition (TBC) TBC refers to compressing time throughout the organization for competitive benefit. Essentially, this is a generalization of the JIT philosophy. G. Value Based Management (VBM) VBM refers to conceptualized and clearly articulated value as the basis for competing. Continuous improvement to increase customer value is one essential characteristic of VBM. H. Re-Engineering Re-Engineering is the radical reconfiguration of processes and tasks, especially with respect to implementation of information technology. Recognizing and breaking away from outdated rules and fundamental assumptions is a key issue of re-engineering. I. Computer-Aided Design/ Computer-Aided Manufacturing (CAD/CAM) In this approach, engineering designs may be created and tested using computer simulations and then transferred directly to the production floor where machinery uses the information to perform production functions. J. Activity-Based Costing Activity-based costing attempts to collect cost data on all activities that occur rather than on just the three primary resources (i.e., materials, labor and machinery). This is an attempt to define the components of burden. The objective of this system is to look at all areas where cost reductions can be implemented. 24 3.0 Differences Between Construction and Manufacturing 3.1 Lean Principles The previous chapter clearly establishes the widespread consideration that has been given to the lean idea in the manufacturing domain. Fujimoto (1999), Womack and Jones (1996), MacInnes (2002) and others have codified sets of lean principles for manufacturing, some of which are briefly listed in Section 3.2. The core principles of the concept emanate directly from the Toyota Production System. However, as application of lean ideas became more prevalent, the fundamental principles of the Toyota Production System were expanded to incorporate a broader array of processes, tools and techniques (Schonberger 1996; Plossl 1991). 3.2 Core Manufacturing Lean Principles Fujimoto (1999) summarizes the essence of the Toyota Production System into the following three principles: • Routinized manufacturing capability--Standard ways of production. • Routinized learning capability--Standard ways of problem solving and solution retention. • Evolutionary learning capability--Learning for system change and improvement. Womack defines the following five principles: • Specify value from the standpoint of the customer. • Identify the value stream. • Make the product flow. • Ensure that this happens at the pull of the customer. • Manage toward perfection. Both of these characterizations of lean are too abstract for the purposes of this report. MacInnes provides a more comprehensive set of principles for manufacturing: • Reduce Waste: − Produce only to order. − Minimize product inventory. 25 − • • 1 Minimize the seven wastes: a. Overproduction. b. Waiting. c. Transport. d. Extra processing. e. Inventory. f. Motion. g. Defects. Ensure Quality/Continuous Improvement: − Focus on the customer. − Apply error-proofing techniques. − Apply visual management and the 5S’s.1 Reduce Lead Time: − Through product design. − Through supply chains − In production: a. One-piece flow. b. Reduce WIP. c. Pull scheduling. d. Quick changeover. e. Standardization. f. Total productive maintenance. This is derived from the Japanese words for five practices leading to a clean and manageable work area. 26 • • Reduce Total Costs: − Target pricing. − Value engineering. Use Metrics to Ensure Improvement: − Financial. − Behavioral. − Core process. 3.3 Core Construction Lean Principles Koskela (1992), Ballard, Koskela et al. (2001), Picchi (2001) and others have proposed lean principles for construction. In addition, many other authors have interpreted individual lean principles for construction. For example, Lane and Woodman (2000) investigated the value of flexibility in construction processes, dos Santos, Powell et al. (2000) investigated WIP and Lantelme and Formoso (2000) and dos Santos (1998) studied the value of process transparency. Pull scheduling was studied by dos Santos (1999) and Tommelein (1998). The application of the flow concept has been investigated by Ballard (1999) and Alves and Formosa (2000). The application of metrics and benchmarking has been considered by Alarcon (1996) and Lantelme (2000). The effects of work flow variability have been examined by Tommelein, Riley et al. (1998) and Alarcon (1996). Finally, Ballard (1999) studied the value of reliable production planning. 3.4 Comparison of Construction and Manufacturing Table 3.1 uses the “principles” of the four primary authorities on lean principles (two from manufacturing and two from construction) to compare lean manufacturing principles and lean construction principles. To gain an understanding of the differences in lean principle between manufacturing and construction, the fundamental differences between manufacturing and construction had to be investigated. Literature on these differences includes documents by Crowley (1998) and Winch (2003). The research team compiled the following comparison list using existing literature and information obtained from questionnaires: • Customer Focus: − Constructors do not control the entire supply chain. − The largest constructors control only 1 percent of the market, whereas in manufacturing the largest manufacturers may control 20 percent or more. 27 Table 3.1: Comparison of Lean Manufacturing to Lean Construction Principles Manufacturing Construction Womack MacInnes Koskela Ballard1 Meet the requirements of the customer X X X X Define value from the point of view of the customer, not from the point of view of individual participants X X X Principle Customer Focus Use flexible resources and adaptive planning X Cross train crew members X Use target costing/value engineering X X X X Culture/People Provide training X 2 Encourage employee empowerment X Ensure management commitment X Work with subcontractors and suppliers to regularize processes and supply chains X 2 X X X Workplace Organization and Standardization Use 5S’s X X Implement poke-yoke devices X X X X Provide visual management devices X X X X Create defined work processes X X X Create logistic/material movement plans X X3 X3 Practice JIT delivery X X Minimize double handling, minimize movement X Balance crews, synchronize flows X Use kitting, remove material constraints, reduce input variations X Waste Elimination Use production planning, detailed crew instructions X1 X X X X X X X 28 Table 3.1: Comparison of Lean Manufacturing to Lean Construction Principles (Continued) Manufacturing Principle Womack MacInnes Construction Koskela Ballard1 Waste Elimination (Continued) Implement last planner/reliable production scheduling/short interval production scheduling X Practice last responsible moment/pull scheduling X Ensure predictable takt times X Minimize WIP; use small batch sizes X X X Reduce parts count, use standardized parts X X X X X X X X Optimize production by pre-assembly/ prefabrication X Use preproduction engineering/ constructability analysis X Reduce difficult setup/changeovers X X Use decoupling linkages, understand buffer size/location X X X X Reduce scrap X Use Total Productive Maintenance (TPM) X Continuous Improvement/Built-in Quality Prepare for organizational learning/root cause analysis, suggestion program X Develop and use metrics for material, labor, equipment, WIP, quality, financial performance, productivity and rework X X X Create defect response plan X Encourage employee to develop a sense of responsibility for correcting defects X Use stretch targets X X 1 Supply chain and design management principles ignored to be consistent with research scope. 2 Implied. 3 Womack treats waste at a high level: identify Type I contributory activity waste and Type II nonvalue adding waste, perform root cause analysis and identify value stream. 29 • • • − Owners are much more involved configuration, cost, schedule and process. − In construction, the responsibility for success is shared between producer and consumer construction. in product features/ Culture/People: − In construction, high turnover results in less opportunity for training. − Construction workers are craft skilled; in manufacturing, they are process specialized. − There are alternate ways of doing each task; production methods are in the hands of the workers not the manufacturing engineers. − Production requirements, access and schedules are governed by multiple contracts. Workplace Organization and Standardization: − Construction has a fluid organization at the project level. − The configuration of the production environment changes constantly; it is more difficult to maintain visual management systems. − Production people move through product, rather than the product moving through production people. − Construction has a more difficult supply change relationship, including different suppliers/subcontractors in different geographic regions. − There are alternate ways of doing each task; production methods are in the hands of the workers not the manufacturing engineers. − The typical construction project is what manufacturers would consider a prototype; it produces a unique product. Waste: − The production sequence is discretionary to a very large extent. − Material flow is not steady state; supply lines are different at different project locations. − Construction material storage locations and amounts vary at different points in the project. − Construction can change the execution time by adding or subtracting resources. 30 • − Construction is resource paced, and manufacturing is typically machine paced. − Construction is affected by weather. Continuous Improvement/Built-In Quality: − There is high turnover/less opportunity for training. − The ability to develop a quality tracking program is limited. − Production time is measured in hours in contrast to manufacturing where it is measured in minutes or seconds. The primary issues common to this list are the greater degree of discretionary behavior and increased uncertainty evident in construction. In manufacturing, production systems are defined by and controlled by the configuration of the production line. In contrast, with construction, the production system is defined by project managers and the individual workers. With this in mind, the manufacturing lean principles were modified, and the subprinciples shown in Table 3.2 were developed. Table 3.2 includes the question numbers that are relevant to each subprinciple from the questionnaire (Appendix G) that was developed to assess lean behavior in construction. Chapter 4 organizes these principles and subprinciples into a graphic “lean wheel” configuration. This list of principles, although similar to conventional manufacturing principles, separates “waste elimination” into four related principles: optimize the process of construction (by optimizing the production process itself), optimize the production process through supply chain management, optimize the production process through production planning and optimize the product design through constructability reviews and pre-assembly. The increased emphasis on planning is necessary in light of the uncertainty and process discretion prevalent in construction production. It is from this list of “presumptive” construction lean principles that the inquiry into lean construction could be started. 31 Table 3.2: Lean Construction Principles Principle Subprinciple Question Customer Focus Meet the requirements of the customer 1 Define value from the viewpoint of the customer (project) 2 Use flexible resources and adaptive planning to respond to changing needs and opportunities 3, 4, 5 Cross train crew members to provide flexibility 6 Use target costing and value engineering 7 Provide training at every level 8, 9, 10 Encourage employee empowerment 11, 12 Ensure management commitment 13 Work with subcontractors and suppliers to regularize processes and supply chains 14 Encourage workplace organization and use of the 5S’s 15, 16 Implement error-proofing devices 17, 18 Provide visual management devices 19, 20 Create defined work processes for repetitive tasks 21 Create logistic, material movement and storage plans that adapt to changes in workplace configuration 22, 23, 24 Minimize double handling and worker and equipment movement 25, 26 Balance crews, synchronize flows 27, 28 Remove material constraints, use kitting, reduce input variation 29 Reduce difficult setups and changeovers 30 Reduce scrap 31, 32 Use TPM 33 Culture/People Workplace Organization/ Standardization Waste Elimination Part I (Process Optimization) 32 Table 3.2: Lean Construction Principles (Continued) Principle Subprinciple Question Waste Elimination, Part II (Supply Chain) Institute JIT delivery, supply chain management 34 Waste Elimination, Part III (Production Scheduling) Use production planning and detailed crew instructions, predictable task times 35 Implement last planner/reliable production scheduling/short interval production scheduling 36 Practice last responsible moment/pull scheduling 37 Use small batch sizes, minimize WIP 38, 39 Use decoupling linkages, understand buffer size and location 40 Reduce parts count, use standardized parts 41 Use pre-assembly and prefabrication 42 Use preproduction engineering and constructability analysis 43, 44 Prepare for organizational learning and root cause analysis 45, 46 Develop and use metrics to measure performance; use stretch targets 47, 48, 49 Create a standard response to defects 50 Encourage employees to develop a sense of responsibility for quality 51, 52 Waste Elimination, Part IV (Product Optimization) Continuous Improvement and Built-In Quality 33 4.0 Research Methodology This chapter describes the overall plan for original data collection, data analysis and methods for answering the research questions stated in Chapter 1. 4.1 Restatement of Research Questions The fundamental goal of this research was to determine whether the construction industry could benefit from the innovative approaches adopted by manufacturing during the past decade. Specifically, the research team sought to answer the following questions: • Are lean principles as defined in manufacturing applicable to the construction industry? If not, are there other principles that are more appropriate for construction? • What is nature of the typical construction production value stream? • What is the value stream for field production activities and for the field portion of material delivery and handling? • How should conformance to lean principles be measured? • Are lean principles commonly used in the construction industry? • What is the path forward to becoming lean? • What are the roadblocks to adopting a lean culture? 4.2 Developing Lean Principles for Construction 4.2.1 Goals The following goals were set for the research: • Develop a comprehensive set of lean principles for construction. • Validate principles by field observations of lean behavior, value stream mapping and interviews with early lean adopters. 4.2.2 Approach The approach used was to synthesize the available literature and original field data into a set of lean principles for construction. There exists a complex set of relationships between the various questions and the methods used to answer them. Investigations began with a thorough review of the literature to establish a set of lean manufacturing principles. Next, using the literature and interviews with lean construction and lean manufacturing experts, a presumptive set of lean principles for construction was established. Two tasks were then performed in parallel. In accordance with the recommendations of 34 Ohno (1988), a value stream analysis was conducted to understand the nature of production value and waste. The other task was to gain an understanding of the lean behaviors (as defined by the presumptive set of lean principles) that are actually practiced in construction. As a basis for defining lean construction behaviors, three sources were relied upon: evaluation of the behaviors of the companies involved in the value stream analysis case studies, evaluation of companies who identified themselves as attempting to apply lean principles (early adopters), and evaluation of behaviors of early adopter companies that were reported in the literature. Finally, using the knowledge gained by the value stream studies and the evaluation of lean behaviors, a final set of lean principles for construction was established. From research team observations, recommendations were developed for actions an organization must take to become lean and potential problems to avoid. The relationships among these various research tasks are shown on Figure 4.1. The following sections describe in detail the goals and methods used for analyzing the value stream, measuring lean conformance and developing an understanding of lean behavior in construction. 4.3 Measuring Lean Conformance 4.3.1 Goals The following goals were set for measuring conformance to lean principles: • Develop a simple instrument for measuring conformance to lean principles. • Use this instrument for assessing adoption of lean principles in construction: − Assess field case study contractors. − Assess early adopters of lean principles. 4.3.2 Approach The approach used included the following actions: • Identify lean principles for construction. • Develop lean conformance questionnaire. • − Test, modify and redesign instrument. − Validate and calibrate answers from survey. Characterize lean behaviors in construction: − Compare early adopters and case study contractors. 35 Figure 4.1: Overall Lean Construction Research Plan 36 As discussed in Chapters 2 and 3, there are many forms of lean principles in the literature. The first task was to organize the presumptive set of principles in a manner that would facilitate an evaluation of AEC organizational behavior against the principles. Additionally, the research team interviewed several leading lean researchers and early adopters of lean principles. Finally, the team relied on the experience and opinions of its members, many of whom had lean clients or who were themselves adopting lean ideas. A simple visual device, called the “lean wheel,” was developed for the manufacturing industry (Tapping, Luyster et al. 2002). This tool was adapted for use with the presumptive set of lean construction principles (Figure 4.2). The wheel is a device to simplify and organize lean principles into a format that is easily communicated to and understood by those new to lean theory. At the highest level, the wheel organizes lean ideas into the following five fundamental principles: • Customer focus. • Culture/people. • Workplace standardization. • Waste elimination. • Continuous improvement/built-in quality. Each of these principles was further divided into 16 subprinciples, represented graphically on Figure 4.2. Customer Focus Continuous Improvement/ Built-In Quality Error Proofing Optimize Value Flexible Resources Metrics Training Organizational Learning Response To Defects People Involvement Optimize Production Schedule Waste Elimination Organizational Commitment Supply Chain Management . Visual Management Optimize Production System Workplace Organization Optimize Work Content Defined Work Processes Workplace Standardization Figure 4.2: The Lean Wheel (after Tapping, Luyster et al. 2002) 37 Culture/ People One of the goals for this project was to develop a questionnaire that could be used by companies to help them self-assess their lean behavior. The lean wheel was used as the foundation for the questionnaire. In addition to helping companies conduct a self-assessment, the questionnaire had a secondary purpose of helping the research team assess the lean behavior of the lean and nonlean contractors on this project. Starting with each subprinciple, questions were developed that were relevant to construction practices and lean theories. The questionnaires progressed through several iterations as early drafts were administered at jobsites and company headquarters. Additionally, early versions of the questionnaire were reviewed by lean practitioners and academics. These early trials led to further modifications of the questions to make them clearer and more concise and to eliminate questions that were not effectively measuring lean behavior. The last step in the questionnaire development was to evaluate its validity. University of Colorado academic resources helped establish the validity of the questionnaire using both quantitative and qualitative means. Faculty from Sociology, Psychology, Marketing and Applied Math were enlisted to improve and test the final questionnaire. Their suggestions prompted modifications of question phraseology and the scoring scale. In addition, they directed the research team toward the Cronbach’s alpha technique to measure questionnaire consistency. The final step in developing the lean wheel was to use the final, validated questionnaire to guide interviews with case study and early adopter contractors. A more detailed discussion of this process is presented in Chapter 5. 4.4 Value Stream Mapping A fundamental maxim of lean production systems is the need to understand the value stream of a product. Taiichi Ohno (1988) and Shigeo Shingo (1981) spent years identifying and defining the components of the value stream within the Toyota Production System. To this day, Toyota continues to redefine the shape and function of its value stream. How does one define waste so that all parties involved with the construction value stream can recognize it? It is the goal of these field studies to help shape, define and quantify construction wastes and thereby improve the typical construction value stream. Waste is commonplace in typical construction projects and processes. The waste that can be identified on the jobsite represents only a small fraction of the waste in the entire delivery process. At every level in the typical construction organization, waste is evident. Many top manufacturing companies reach levels of 60 to 70 percent value adding (VA) time on their shop floors; most will claim only 5 to 10 percent contribution over their entire value stream from development to delivery. Using lean concepts as the foundation, the nature of VA actions and waste can be defined. Ohno (1988) subcategorizes waste into non-value adding but required (NVAR) Type I muda, and non-value adding (NVA) Type II muda. Because of the relatively uncontrolled and changeable nature of the construction production environment, the NVAR actions are relatively more common than in manufacturing production. For instance, in-process inspections (NVA-Type I muda) are typical for any process piping. The material and welds must be checked during installation; otherwise, the safety of the workers, and possibly the future owners of that pipe, may be compromised. While the action of inspecting the pipe does not add value for the customer, it is an action that is required by current codes and industry standards; therefore, it cannot be eliminated. This type of action can, however, be limited through 38 reorganization of the work processes or even through the development of an entirely new process for installing pipe. After definitions for VA, NVAR and NVA actions were created, the research team focused on procedures for collecting and analyzing these data for typical construction tasks. Development of procedures for a construction value stream analysis followed the self-imposed limits of this study. First, the effects of design activities on lean performance were excluded. Projects can be designed to facilitate lean performance. Project design can be delivered in such a way so as to enable lean production. These factors were not considered in the value stream studies. The effects of supply chain issues that are manifested away from the jobsite were also excluded, but material supply from the time that materials entered the jobsite was included. Others (Arbulu 2002; Tommelein and Li 1999; Tommelein, Akel et al. 2003) have studied supply chain issues and lean performance. Another issue affecting value stream mapping is the time scale over which waste becomes evident. Most wastes, such as worker inactivity (waiting), are immediately evident and quantifiable by observing the value creation process of the crews. However, other wastes, such as punch list items, are only evident to those who can observe the project over a long time. Since data collection for this study was organized around short site visits, the data analysis was concentrated on the wastes that were evident over a short time. The typical value stream map must describe the entire construction process flow (Rother and Shook 1998). Theoretically, the value stream would begin with the collection of raw material and end when the owner (end customer) receives the finished product. This study focused on individual construction production processes in the overall value stream. Specifically, data was collected, analyzed and then used to create value stream maps for a typical structural steel erection process and the installation process for large bore piping. These specific processes represent two very different value generation mechanisms. The structural steel erection process is an equipment intensive, highly repetitive, configuration driven process with relatively short cycle times. In contrast, piping installation is a labor intensive, nonrepetitive process that has flexible work sequences with long cycle times. By focusing on these different processes, it was possible to show that the value stream mapping procedures are flexible enough to represent most construction production processes. Ultimately, value stream maps will be used to quantify and track wastes related specifically to material in their respective processes, as well as the production operation itself. These ideas are further clarified and expanded in Chapter 6, where the detailed definitions for waste and the methods used to identify and quantify waste are presented. Chapter 6 also separates the conventional value stream map into three distinct levels. Level One is used to track wastes associated with material and provide an overview for the work distribution values related to VA, NVAR and NVA for an entire construction production process. Level Two tracks wastes associated with worker and material flow as the process proceeds through the various construction stages. Level Three dives deeper into the process and analyzes each worker’s contribution to the various work categories. 4.5 Bringing It Together The ultimate task was to combine the knowledge gained through interviews and the literature search with the knowledge gained from the value stream study to define and refine an accurate set of lean principles for construction. This was accomplished by first evaluating the applicability of 39 each of the lean principles identified in the presumptive set. Next, an evaluation was made to determine which participant in a project should exhibit this lean behavior: the owner, constructor, subcontractor, material supplier or designer. Finally, it was determined whether the lean principle should be applied at the contractor’s organization level, project level or crew level. 40 5.0 Creation and Use of a Lean Assessment Instrument 5.1 Foundation/Design of the Questions A primary goal of this research was to develop an instrument to measure a company’s conformance to lean construction principles. The team chose to develop a questionnaire that would accurately measure conformance to the lean principles and subprinciples and at the same time would be concise and easy to use. The literature on questionnaires indicated that lengthy surveys elicit casual answers. The research team relied on expertise available among colleagues (Professors Luftig, McClelland and Boardman) in Sociology, Psychology, Marketing and Applied Mathematics at the University of Colorado to achieve both of these goals. The literature on questionnaire design stresses the need to verify the survey by distributing sample versions. Oppenheim (1992) suggests that “Questionnaires have to be composed and tried out, improved and then tried out again, often several times over, until we are certain that they can do the job for which they are needed. This whole lengthy process of designing and trying out questions and procedures is usually referred to as pilot work.” In accordance with this rule, research team members repeatedly asked coworkers to complete the questionnaire and provide comments. Additionally, early versions of the questionnaire were reviewed by contractors and academics familiar with lean principles. The following feedback/suggestions were obtained: • Reword questions for clarity. • Ensure that the questions not lead the respondent toward a “right” answer. • Clarify the completion instructions. • Simplify the questions by using familiar vocabulary terms. • Number the questions. When comments from evaluators were consistent with advice from survey design literature, changes were made and the questionnaire was re-administered to new test groups. More details on this test, modify and re-test procedure are provided in Section 5.5. “It is essential to pilot every question, every question sequence, every inventory and every scale in your study. If the pilot work suggests improved wordings, you need to pilot those, too. Take nothing for granted. Pilot the question lay-out on the page, pilot the instructions given to the respondents, pilot the answer categories, pilot even the question-numbering system” (Oppenheim 1992). The research team adhered to this advice and developed the questionnaire with the utmost care. As the research design became more definitive, the questionnaire changed accordingly. For example, one part of the research dealt with data collection from field studies pertaining to value stream mapping. As the lessons from the value stream mapping studies became clearer, certain aspects of the questionnaire were emphasized or reduced. The process of design and redesign had unanticipated positive outcomes. First, the overall questionnaire was shortened, which served to increase the voluntary accurate response rate. Second, questions became more explicit, which again led to more accurate responses. On the advice of the sample group, some questions were 41 reworded to make them more understandable. Oppenheim (1992) spoke in depth in his book about the difficult task of the respondent to answer the questions accurately: ...it is difficult enough to obtain a relatively unbiased answer even from a willing and clear-headed respondent who has correctly understood what we are after, without making our task virtually impossible by setting off this ‘train of responding’ on the wrong track through poor question wording. The questionnaire was designed around pairs of statements. One half of the pair of statements described a non-lean behavior, and the other half described a corresponding lean behavior. Since applying lean principles leads to many effective jobsite behaviors, it was difficult to avoid making those choices more attractive. Wording was selected that made both statements seem favorable so that the respondent would be forced to choose the one that more accurately described his or her company. If one statement seemed more favorable than its counterpart, then it could be perceived as a leading question. Another suggestion that was implemented from the sample group feedback was to add question numbers. The first draft consisted of 55 unnumbered statements. Rea and Parker (1997) stated that “...being sensitive to questionnaire length is to make certain that the questionnaire is not so long and cumbersome to the respondent that it engenders reluctance to complete the survey instrument, thereby jeopardizing the response rate.” When question numbering was added, the respondents had an idea as to the parameters of the document, which in turn focused their attention on answering the questions rather than on the duration of the process. A Likert scaling system was used for the questionnaire. “A Likert scale entails a five-, seven-, or nine-point rating scale in which the attitude of the respondent is measured on a continuum from highly favorable to highly unfavorable, or vice versa, with an equal number of positive and negative response possibilities and one middle or neutral category” (Rea and Parker 1997). The Likert scale is the most popular scale in use today (Oppenheim 1992). It is simple to understand, and it provides the evaluator more information than that provided by simple yes/no or agree/disagree responses. A five-point Likert scale was initially used, but on the advice of faculty colleagues (McClelland 2003), it was changed to a seven-point scale and an N/A response was included. Figure 5.1 shows an example of a seven-point Likert scale question, in which a score of “1” corresponds to the statement on the left and a score of “7” corresponds to the statement on the right. Larger response ranges lead the respondents to answer more accurately and more honestly. The project is built precisely according to plans The Contractor discusses ways to 1 2 3 4 5 6 7 N/A modify the plans to reduce costs while maintaining quality. Figure 5.1: Example of a Seven-Point Likert Scale Question Experts in questionnaire design agree that questionnaires cannot be perfect. There will always be some degree of uncertainty in the responses. “The function of a question in an interview schedule or questionnaire is to elicit a particular communication. We hope that our respondents have certain information, ideas or attitudes on the subject of our enquiry, and we want to get these from them with a minimum of distortion” (Oppenheim 1992). In summary, the Likert scale scoring system allowed the desired information to be acquired while at the same time keeping the survey simple for respondents. “The Likert scale works particularly well in the context of a series 42 of questions that seek to elicit attitudinal information about one specific subject matter” (Rea and Parker 1997). The specific subject matter was lean construction practices. 5.2 Design of the Questionnaire Using Field Studies The survey was administered to contractor managers and employees at each of the jobsites that were visited for the value stream case studies (six case studies in all). In the first field data collection, the questionnaire was distributed to employees ranging from the project manager to a crewman responsible for bolting steel girders and bar joists into place. Many of the responses to this first questionnaire from the crew were marked N/A. It was discovered that many of the lean behaviors that were being measured were not the responsibility of the crew members. As a result of these first trials, the original questionnaire was split into three separate questionnaires, one for the project management level, one for the crew level, and one for the executive or organization level. Of the original 55 questions, there was only one question that was applicable to all three levels. Thirty-four of the questions were applicable to two of the levels, while the remaining 20 questions were applicable to only one facet of the company. Ultimately, the organizational questionnaire contained 26 questions, the project level questionnaire contained 50 questions and the crew level questionnaire contained 17 questions. While the respondents were filling out the questionnaires, the field study team was evaluating the contractor’s lean behavior. At the end of each field data gathering phase, the study team graded the contractor’s lean behavior using the questionnaire. The study team’s average answer was then compared to the average response from the contractor’s personnel. Attention was focused on those questions in which the research team’s assessment differed from the contractor personnel’s assessment by two or more points on the Likert scale. This analysis was repeated so that questions that had confusing wording or leading answers could be identified. This process was a principal tool for improving the questionnaire. The research team distributed and administered the questionnaires in person and was able to achieve a 100 percent response rate. A response rate of 50 to 60 percent is considered satisfactory when administering a questionnaire (Rea and Parker 1997). The ability to achieve full participant response made the task of analyzing the questionnaires much easier. It was not necessary to establish the type of people that filled out the survey; the participants worked in the construction industry. This was the anticipated population at which the survey was directed. It was very beneficial to the team to visit each of the case study jobsites. Each trip presented an opportunity to explain the questionnaire, its current use and its end goal to a wide variety of participants. Ultimately, the questionnaire was distributed to the focus group. The focus group consisted of the employees working at the jobsites that were visited for data collection. The research team visited six jobsites, value stream data was collected at all six sites, and the questionnaire was distributed at five of the jobsites. The sites were located in various parts of the United States: • Richmond, Virginia--Steel Erection. • Kirtland, New Mexico--Process Pipe. • Michigan City, Indiana--Process Pipe. • Birmingham, Alabama--Steel Erection. 43 • Birmingham, Alabama--Process Pipe. • Smyrna, Delaware--Steel Erection. At each site, the questionnaire was distributed to approximately 10 employees of the onsite contractor. On average, four crew members, four project management level employees and two executives filled out the questionnaire. Each work level received a different questionnaire that contained only questions relevant to their job. 5.3 Case Study Interviews To further scrutinize lean principles, a parallel study to the questionnaire using oral interviewing techniques was conceived to capture the lean behaviors and opinions of contractors and owners. The questionnaire was used as a structured interview guide. The oral interview techniques provided explanations of lean practices, as opposed to a simple numerical response. These explanations and insights helped simplify the questionnaire and shift emphasis to specific principles. At a minimum, the contact person from the research team was interviewed for each jobsite. Since they had a better grasp of lean principles than their peers, administering the interview was straightforward. Each of the subprinciples was defined for the interview participant, and they were then asked to state which practices they used followed that lean subprinciple. At several of the case study sites, field management personnel also participated in oral interviews. The purpose of the interviews and questionnaire was to understand which lean principles were actually used in construction. In other words, if a company was using a lean principle and it was effective, then it may be concluded that the principle may be translated from its manufacturing base to the construction industry. The more difficult task was determining whether non-use of a principle indicated unfamiliarity with the concept or inapplicability of the principle in construction. Often, an employee of one of the interviewees would relate plans for implementing or trying a certain lean practice in the near future. It was felt that when the company had a better grasp of lean construction as a whole, the implementation of more innovative ideas would be easier to introduce. This relates to an important concept: the role culture plays in the success of lean principles. Employees have an easier time supporting a practice if it is not completely foreign to them. Changing a company’s culture in a short period of time is a difficult task. The interview process produced results in all subprinciples that could not have been achieved solely through the questionnaire. The questionnaire provided a broad understanding of each company, while the interviews provided greater depth. Companies that professed to be early adopters of lean principles were also interviewed. These early adopters shared their insights and helped the research team understand their approaches for implementing lean in construction. 5.4 Early Adopter Interviews The goal of interviewing early adopters was to gain a better picture of which lean principles were practiced in the field when a company was trying to implement lean practices on its projects. The people interviewed understood lean from the manufacturing point of view, often using the Japanese word or phrase for a subprinciple that was discussed. Most had a clear understanding of the existing work in lean construction. The one common theme from each early adopter was their belief that lean theory is helpful; however, the focus of each early adopter’s lean implementation was highly variable. Some focused on field production, others on developing a lean culture and others on supply chain issues. The early adopters were very clear about their intentions to use 44 lean, as opposed to the others interviewed who were more skeptical about implementing lean theories. This was evidenced by the fact that early adopters had schedules for implementation of certain lean practices. Some lean practices were being held for a smaller project so they could be tested prior to full company implementation. Other lean behaviors were being implemented right after a previous one was fully absorbed. The difference between the early adopters and the case study participant companies was the adherence to a schedule for lean implementation. The results and conclusions from both the early adopters’ interviews and the case study participant interviews are discussed later in this chapter. 5.5 Validation of the Questionnaire The validation of the questionnaire progressed through three stages. The first stage was the pilot work. This included the creation of the questionnaire using the lean principles and the distribution of the questionnaire to the sample groups. After the pilot stage, the questionnaire was administered to employees of the jobsites that were visited by the research team. In this second stage, the validation work came from deciphering the participants’ responses. The third and final stage in the validation process was the statistical analysis of all the responses. The statistical analysis led to conclusions about whether the questionnaire was reliable as a self-assessment tool in lean construction. 5.5.1 Stage One: Pilot Work The pilot work was vital in bringing the questionnaire up to standards. This stage did not actually validate the tool, but was a method for fine-tuning the questionnaire. The sample group respondents offered suggestions that were utilized in the final design of the questionnaire. The pilot work was necessary for eventually administering a simple, understandable questionnaire to the focus group. The participants in the pilot stage were all construction professionals, and if they were unfamiliar with some terminology used, the questionnaire had to be changed. The main goal of the pilot work was the development of a comprehensible and clear tool. Eventually, the questionnaire will be used as the basis for a lean self-assessment tool; therefore, it was developed to be as easy as possible to administer and understand. The process of improving the questionnaire continued until there were no more remarks regarding instructions or terminology definitions. 5.5.2 Stage Two: Focus Group Responses After the pilot work was complete, the questionnaires were administered to the focus group. The focus group consisted of employees from each jobsite visited. The questionnaire pertaining to employees on the crew level was distributed to the field labor, while the questionnaire relevant to project management was distributed to employees located onsite. The questionnaire pertaining to the executive level was mailed to the organizational employees working at headquarters. While in the field, a technique called “debriefing” was used. Fowler (1995) explains that “the most universal strategy for evaluating self-administered questionnaires is to have respondents complete them, then carry out a brief interview with the respondents about the survey instrument. In addition, respondents can be asked about any problems they had with reading and answering questions.” 45 Evaluation of the accuracy of the participants’ responses was accomplished by measuring them against an agreed upon standard. The consistent standard used was the research team’s assessment. Members of the research team who were present at each case study visit completed a questionnaire based on their personal observation of the activities and practices at the jobsite. The comparison between the research team’s average answer for each question and the answer given by the respondents was used to validate the questionnaire. As stated before, if there was an average discrepancy larger than two on the Likert scale between research team answers and the respondent’s answer, the question wording and content were further analyzed. Of the 55 original questions, eight questions were eliminated as a result of this process. Other questions that were borderline in terms of validity were reworded and retested for adherence to this standard. It was important to understand how the research team’s unbiased assessment of jobsite lean performance compared to the contractor’s staff assessment. Differences between the two assessments could be caused by a poorly worded question or by bias on the part of the contractor personnel. Some degree of bias from the project management staff and the craft workers was to be expected. Results were analyzed for a limited degree of bias and a consistent trend in the bias. That is, if a question exhibited contractor responses that were consistently higher (better) than the research team responses, the difference was attributed to bias, pride in workmanship, etc. On the other hand, if the contractor responses showed a large differential, or if the differential was sometimes higher and sometimes lower than the research team, the difference was attributed to a misunderstood question. Using this process, questions were improved, reworded and, in some cases, eliminated from the questionnaire. Interestingly, the resultant scores from the organization level were the most consistent with those of the research team observers. The project management level was also very consistent with those of the research team. The crew level, on the other hand, had the largest discrepancy from the observers. At the organization level, the average differential between a respondent and the research team was 1.4 points. At the project management level, the difference was 1.5 points. At the crew level, the difference was 2.3 points. These results were consistent across all jobs. The crew level always had the highest discrepancy, while the other two levels were lower and within decimal points of each other. Since the discrepancies were consistent between company levels and between jobsites, the final validation test was to statistically analyze the response results for reliability. 5.5.3 Stage Three: Statistical Reliability Analysis The final step in validating the questionnaire was through statistical reliability testing. Cronbach’s alpha coefficient was used to measure the reliability of the questionnaire. “Cronbach’s alpha is an index of reliability associated with the variation accounted for by the true score of the ‘underlying construct.’ The construct is the hypothetical variable that is being measured” (Hatcher 1994). Cronbach’s alpha can be written as a function of the number of test items and the average inter-correlation among the items. The formula for the standardized Cronbach’s alpha is as follows: α= N*r 1 + ( N − 1) * r 46 Where: N is the number of items, and r is the average inter-item correlation among the items. Cronbach’s alpha is a coefficient from 0 to 1 that measures the consistency and correlation between responses to a set of similar questions. For this report, the construct measured was the correlation between the responses for the questions pertaining to certain lean construction principles. This reliability coefficient test was recommended by several researchers at the University of Colorado (McClelland, Luftig, Boardman) and by other experts. “You may compute Cronbach Coefficient Alpha, Kuder Richardson (KR) Formula, or Split-half Reliability Coefficient to check for the internal consistency within a single test. Cronbach Alpha is recommended over the other two.” (Yu 1997) “When items are used to form a scale, they need to have internal consistency. The items should all measure the same thing, so they should be correlated with one another. A useful coefficient for assessing internal consistency is Cronbach’s alpha” (Cronbach 1951). In this questionnaire, questions were developed around each of the five main principles. Cronbach’s alpha test demonstrated whether the grouped questions were consistent in measuring the same lean construction principle. Five tests were conducted wherein each of the five main principles was treated as the single construct. The results of each test were taken to see if the questions asked were consistent in focusing on that one principle. Since alpha is a coefficient, its range of values is from 0 to 1 and, therefore, each result was given as a decimal. “There isn’t a generally agreed cut-off. Usually 0.7 and above is acceptable” (Nunnally 1978). The goal of the research team was to produce an alpha score of at least 0.7 for all five tested principles. To perform the statistical tests, SPSS/PC+, a powerful software package for microcomputer data management and analysis, was used. Questionnaire results were entered into the software database as an Excel spreadsheet, and then the Cronbach’s alpha coefficient was completed for the designated questions. The SPSS results for each of the five tests are shown in Table 5.1. The results of the Cronbach’s alpha tests were positive. All five principles had coefficients of at least 0.76 and up to 0.95. As a result, it was concluded that this questionnaire was valid and reliable tool for its purpose of measuring conformance to lean principles. The final questionnaire can be found in Appendix G. 5.6 Use of Lean Principles in Construction The following subsections summarize the important findings about the use of lean principles in construction. These results were derived from analysis of the questionnaires administered at the five value stream case study sites. Each section examines application of one lean principle at each of the three study levels: crew, project management and executive or organization level. 5.6.1 Customer Focus The responses from the completed questionnaires indicated that communication with the client was not as central to the construction process as lean theory would suggest. Contractors were unclear about who the owner (client) actually was. Value added processes were not always defined by the owner’s needs or in terms of the project as a whole. There is still work to be done in terms of understanding the customers’ requirements and being flexible in meeting their needs. 47 Table 5.1: Cronbach’s Alpha Results Principle Cronbach’s Alpha Coefficient Customer Focus 0.7467 Culture/People 0.8564 Workplace Standardization 0.8642 Waste Elimination 0.9548 Continuous Improvement/Built-In Quality 0.9039 R E L I A B I L I T Y A N A L Y S I S - S C A L E (A L P H A) Reliability Coefficients N of Cases = 24.0 Alpha = 0.7467 N of Items = 7 Reliability Coefficients N of Cases = 41.0 Alpha = 0.8564 N of Items = 7 Reliability Coefficients N of Cases = 41.0 Alpha = 0.8642 N of Items = 10 Reliability Coefficients N of Cases = 41.0 Alpha = 0.9548 N of Items = 18 Reliability Coefficients N of Cases = 41.0 Alpha = 0.9039 N of Items = 8 48 5.6.2 Culture/People Training was prevalent in the industry, but not to the extent that companies were taking the time to teach their employees about lean practices. For the most part, training occurred on company time, and training on matters outside of specific job responsibilities was not common practice. However, companies were trying to empower their employees to share their improvement ideas. This was a lean practice that even non-lean companies supported. There was an overall sense of the need for improvement in the industry by people at the organization level. 5.6.3 Workplace Standardization Companies encouraged their employees to be clean and organized on the jobsite. These recommendations, however, were not always followed. There was a need for the project management level to increase its use of visual aids to encourage the workflow and cleanliness of the jobsite. It was generally agreed that visual aids would help, but the implementation of this practice was still in its inception for many of the focus group companies. The documentation of work processes and a defined logistics plan were inconsistently used within the focus group. 5.6.4 Waste Elimination The focus group lacked consistency concerning balancing crew sizes, crew sequencing and minimizing movement by people, materials and equipment. For the most part, respondents answered that there was room for improvement in this regard. The question and/or subprinciple that garnered the most negative responses dealt with the optimization of design with field installation. Most respondents answered that certain design aspects of their project made construction more difficult than necessary. The consensus from the completed questionnaires was that JIT delivery of supplies was still in its adolescent stage. Some contractors were trying to use this method with large suppliers, but they would generally feel more comfortable with the needed materials stored in a lay-down area. In terms of completing work products for the next crew to use, respondents were evenly divided between making them available in small batches or in large batches of the finished products. Unlike the lean manufacturing industry, these respondents answered that they try to start a work activity as soon as possible rather than waiting until the last responsible moment that still supports the schedule. 5.6.5 Continuous Improvement/Built-In Quality One tool that almost all lean construction companies used was a lessons learned file. The questionnaire results showed that companies that were the least lean also did the least in terms of lessons learned. The companies that were in the beginning stages of becoming lean tried to incorporate some sort of lessons learned file into their corporate knowledge base. There was a split between the focus group as to which companies made a consistent effort to monitor their work using established metrics. These measurements consisted of productivity reports, quality assurance reports and sometimes cost reports. In terms of error-proofing, there was still a need to conduct more constructability reviews before the design was complete. Most of the contractors made it a point to place some sort of directional marking on their supplies to ease the job of the installer. Lastly, the focus group was not consistent regarding having a plan in place to deal with defects. 49 5.7 Case Study Interview Results1 These interviews were conducted primarily by members of the research team with representatives of the companies working on the value stream case study jobsites. Of those interviewed, only one of the companies used lean practices on its project. The interviews were valuable in gathering information that could not have been collected through the questionnaires. All the participants were eager to describe current practices on their jobsites. The face-to-face interviews provided deeper understanding of current lean (and non-lean) practices on typical construction jobsites. The following subsections summarize the results of these interviews according to each of the major lean principles. 5.7.1 Customer Focus The interviews did not indicate that an intense focus on customer value was common in construction. Understanding the customer’s requirements is a focal point of lean theory in construction and manufacturing. The only practice commonly noted by the participants was the use of formal design review sessions with the owner during the preconstruction phase of their jobs. 5.7.2 Culture/People An important aspect of lean behavior is creating a culture wherein employees are confident about the process and strive for continual improvement. Employee empowerment and the commitment of the organization to improve its processes are essential for creating a lean culture. Training sessions are necessary to educate employees about lean principles. All of the participating companies trained their employees in construction practices, but only one of the companies focused training sessions on lean behavior. The participants stated that their company encouraged employees to provide feedback on improvement. This company created a tool called the Lean Daily Management System which fostered a process of feedback participation. The participants stated that more people had become involved and empowered because of this tool. All the companies stated that they were looking for ways to improve their processes. 5.7.3 Workplace Standardization Workplace organization is a significant part of this principle. Each company works to maintain a clean and organized workplace, since this invariably increases safety standards. However, no specific lean practices such as the 5S’s were used by any of the participant companies. Visual management is an important lean behavior on a manufacturing floor. There was some use of visual aids regarding schedule, safety and, occasionally, productivity. For the most part, visual devices were posted in the project management trailers, but not at the worksite as one would expect for proper lean implementation. The defined work processes used by each company were typically in the form of site logistics. One company had a lessons learned file for work tasks. 1 Interview notes for the case study contractors can be found in Appendix H. 50 5.7.4 Waste Elimination This principle was not actively employed by the participant companies. The desire to improve practices was often cited as a goal; however, most work tasks were organized and planned by individual work crews. None of contractors used staff to support the planning of individual work operations. One company stated that a great deal of planning went into minimizing the movement of its employees between and during work activities. All the participant companies mentioned the lack of communication between the design team and the field installation team. One of the companies used a modified version of the “last planner” technique. Another company made an effort to pass along products in small batches or continuous streams. None of the companies set their schedule to the last responsible moment that still supported the schedule; they all believed that was too risky. JIT delivery is still only a vision for most of the companies; however, some companies made efforts to deliver in smaller batches to eliminate excessive handling. 5.7.5 Continuous Improvement/Built-In Quality Most companies had a lessons learned file on their internal intranet. Effectiveness of lessons learned appeared to be linked to similarities between a company’s projects. Companies with many dissimilar jobs did not utilize lessons learned as often as those with jobs that were similar in nature. All of the companies stated that they measured quality on all their projects. Only two of the participant companies measured productivity on each job. Regarding error-proofing, the companies specializing in steel erection were more prone to use poke-yoke (error-proofing) devices to ensure a one-way only fit and no erection mistakes. Finally, two of the participant companies had a response plan in place in case a defect occurred. The plan essentially consisted of “stopping the line” and making a decision about the path forward. In general, it appeared that case study contractors adhered to industry best practices. With a few exceptions, most of the contractor personnel were unaware of lean manufacturing principles. 5.8 Early Adopter Interview Results1 Early adopters were contractors who were aware of lean principles and were actively trying lean techniques on their projects. Each of the three early adopter companies interviewed employed lean practices in their everyday functions. Lean construction is a relatively new concept, and these early adopters are still learning and expanding their lean functions. 5.8.1 Customer Focus There were numerous practices incorporated by these companies to try to meet customer requirements. Target costing and value engineering were used to show clients alternate scenarios. One company encouraged a design-build or design-assist delivery system that forced communication between the contractor and designer to give the customer the most value. Some will argue that these are simply best practices in construction; however, all three companies were steadfast in their belief that constant communication between the client and contractor was essential in bringing the client the most value. Each of the early adopters used some form of 1 Notes from the interviews with the early adopter contractors can be found in Appendix H. 51 short-term planning to be proactive, rather than reactive, with any new project development. This type of planning creates flexibility because of the increased communication between all involved parties. 5.8.2 Culture/People A clear difference between the early adopters and the case-study companies was the outlook on creating a lean culture. The early adopters made it a point to push lean thinking throughout their companies; each had mandatory training sessions based solely on lean behavior. These sessions ranged from eight-hour sessions to mandated courses that educated on three different levels of lean theory. The early adopters took training very seriously and spent a considerable amount of time and money to ensure that their employees were properly trained. The three companies used different practices to empower their employees, although they all had the same underlying motive: to create an environment in which employees are always looking for ways to improve. These practices ranged from the creation of award programs for implemented suggestions to the mandate that employees provide feedback in the form of opportunities for improvement (OFIs). These practices encouraged employees to participate in the continual improvement of company processes. Finally, organizational commitment was obvious for each of the early adopter companies. 5.8.3 Workplace Standardization Workplace organization varied a great deal in the early adopter companies. One company was steadfast in its implementation of the 5S tool (sort, straighten, sweep, standardize and systematize); while another company said that it was working on implementing 5S in the future. They all strove for clean and organized jobsites. One company created a box for each crewman that contained everything he or she would need for the upcoming day. Another difference between the early adopter companies and the case-study contractors was the use of visual management. These companies used visual aids to a much greater degree than the other contractors. It was seen on the actual worksite and in the distribution of project information. Visual aids representing workflow and site logistics were more available on the early adopter’s jobsites. One of the companies went to great lengths to produce visual tools that helped employees plan, communicate and coordinate their activities. They also created numerous checklists that gave their employees a better picture of what was required for each activity or overall project. Each of these companies distributed visual aids that tracked productivity, safety, short-term schedules and material handling requirements. The defined work processes of each company were communicated through the use of the visual tools. 5.8.4 Waste Elimination The lean tools used by these early adopters consisted of last planner meetings or four-week lookahead schedules that helped balance and track crew flow. Checklists were used by one of the contractors to see if the current project was similar to a previous project; this information could then be used to see how that project was planned. Regarding optimizing work content, one of the companies provided its architects/engineers with JIT training to improve design coordination and planning. Two of the companies requested that the design be conceived with more standardized materials to make installation in the field easier. Prefabrication was another alternative considered to ensure smooth field installation. 52 Surprisingly, supply chain management was not widely used by the early adopter contractors. They spoke of JIT delivery, but stated that it was not in prevalent use in their companies. There were too many possibilities in the current environment for supplies or materials to be delivered late, which could affect the critical path. Obviously, this is a risk that these companies are not willing to accept at the present time. However, these companies are focused on the handoff of finished products between subcontractors and crews. The objective is to hand off the finished product in a continuous stream or in small batches. This is a lean behavior that is supported by using the four-week look-ahead tool or the Last Planner System approach. 5.8.5 Continuous Improvement/Built-In Quality Similar to the case-study contractors, each of the early adopter companies maintained lessons learned files. These files included OFIs or Continuous Improvement Messages (CIMs), depending on the nomenclature used by the company. One of the companies went so far as to have a separate lessons learned file solely for lean practices. Each of these companies monitored quality and productivity. One of the companies even measured the amount of unused supplies and materials on each jobsite as a way of reducing scrap. Another company decentralized its quality control down to the lowest level of the organization. This practice goes along with the theory that each worker should check his or her work and ensure its quality before passing the work down the line. Surprisingly, little emphasis was placed on error-proofing by any of the early adopters; however, each company encouraged field empowerment so that the affected employee would raise the flag and act on a defect. 5.9 Survey of Lean Implementation in Construction Literature Investigation of current applications of lean construction included a survey of the literature. The following subsections detail lean applications that have been reported in the literature. These applications are organized according to the process level, project level and organization level. 5.9.1 Lean Implementation Case Studies at the Process Level 5.9.1.1 The Oscar J. Boldt Construction Company (Tsao 2000). This case study examined the following lean principles, methods and/or tools: • Work structuring. • Implementation of “5-Whys” to determine root causes of problems/errors. • Value stream mapping. This case study focused on the construction of the Redgranite Correctional Institution in Wisconsin. This project consisted of two housing buildings that covered a total of 140,000 square feet. These buildings were two stories tall, and their walls were made from precast concrete panels. The first-level floors were slab-on-grade, while the second-level floors were precast concrete slabs. The Oscar J. Boldt Construction Company was the construction manager, and Venture was the project architect. The state awarded Boldt this design-build project based upon a guaranteed maximum price bid of $48 million. To illustrate current practices and the opportunities provided by work structuring, this case study discussed the installation of 510 hollow metal doorframes at the prison project. Because the 53 project was a correctional facility, the doorframe installation process involved a special grouting procedure, which made the installation process less routine. Those personnel involved recognized the difficulty of the situation, but better solutions were impeded by the demands of the installation process. This case study thus provided the opportunity to illustrate how one may come up with alternative ways to perform the work when not constrained by contractual agreements and trade boundaries. In addition, the importance of dimensional tolerances in construction and how these affected the handoff of work chunks from one production unit to the next were discussed. 5.9.1.2 JIT Practices in Ready-Mix Concrete Delivery (Tommelein and Li 1999a). This case study examined the following lean principles, methods and/or tools: • JIT practices within ready-mix batching and delivery. • Value stream mapping. Ready-mix concrete is a prototypical example of a JIT production system in construction. Practices regarding ready-mix batching and delivery were described in this paper and depicted using value stream mapping symbols. Each case highlighted the presence of buffers of information, materials and time, as well as production order and withdrawal mechanisms positioned at strategic locations to meet specific system requirements, as defined by the nature of the contractor’s work. In this paper, the batching and delivery of ready-mix concrete were used to illustrate a pull system. Ready-mix concrete is a prototypical example of a batch process, where a customer process (the contractor) releases an order to batch to the supplying process (the batch plant) and receives product as a result. This batch process does not allow any inventory of product to be maintained, because the product is perishable. While these practices clearly exemplify JIT production, the paper was limited in scope. No data was included to characterize the actual performance in terms of timeliness, buffer sizes, error rates, etc. Moreover, the paper focused on batching and delivery, which are only parts of the entire concrete production system. Current practices for managing the concrete supply chain upstream in terms of raw materials acquisition or prerequisite work onsite are not geared toward JIT production. Further investigation is therefore warranted, and significant process improvements may be achieved by those working toward fully implementing a lean construction system. 5.9.1.3 JIT Practices in Steel Fabrication and Erection (Tommelein 1996b). This case study examined the following lean principles, methods and/or tools: • JIT practices within steel fabrication and delivery. • Buffer location analysis. • Value stream mapping. The erection of a building’s structural steel frame is a major construction phase on many projects. The main resource in this process, the steel erector’s crane, defines not only the pace of steel erection, but also the pace for handling and installing many other structural and non-structural materials. This production system cannot afford any delays. Some claim that structural steel is therefore managed as a JIT process with materials being delivered to the site as needed and installed promptly. This is the case only in appearance, as is clear when one considers the JIT 54 principles that were developed as part of Toyota’s lean production philosophy. To illustrate the point, this paper drew on examples of typical structural steel supply chains from the industrial and building construction sectors. The use of symbols from manufacturing was investigated to map key production steps, as well as buffers in between them, to elucidate where resources do and do not flow. Industry practices in these two construction sectors vary significantly. Neither one is lean. This paper reported on a preliminary investigation into the location of buffers in the structural steel supply and construction process. The reasons for having buffers at various locations were explored. A more in-depth investigation is recommended to gain a deeper understanding of the buffer sizing criteria and steel component sequencing rules that govern current practices. Insight into these will then help determine which buffers can be trimmed to reduce WIP cycle times. This will support the effort of achieving “more JIT” by making processes within individual companies, as well as across the entire steel supply chain, leaner. 5.9.2 Lean Implementation Case Studies at the Project Level 5.9.2.1 PARC Project (Ballard, Casten et al. 1997). This case study examined the following lean principles, methods and/or tools: • Increased production planning. • Work method design. • Decrease variability-increase reliability. • Continuous improvement. • Increased project coordination. The PARC project was a refinery expansion costing approximately $2.1 billion. In 1994, consultants Mike Casten, Greg Howell and Glenn Ballard initiated a productivity improvement program at the PARC project following an initial site visit and diagnosis. The program duration was from November 1994 until August 1995. Before the program was implemented, the project suffered from poor labor productivity. As a result, the current direct labor force of 10,000 needed to be increased to approximately 18,000. This increase in labor force, however, was not an option because of a lack of skilled workers and the inability of the project to accelerate the supply of work. As a result, this particular improvement program focused on production planning, since it was determined that the current planning methods were insufficient to complete the job. The current project management model needed to be changed from a contract management model to a production management model, which would be oriented toward the way work is done. The following three factors were determined as key areas for project improvement: • How well the project is supplying the basic elements of work to the crews. These elements include information, materials, tools, equipment, etc. • The method used by the crew to perform the work. • How well the accomplishment of the work itself meets the needs of the workers. 55 It was determined that planning reliability was important to improved project performance. To increase planning reliability, the team of consultants introduced the subcontractors to the Last Planner System, a system developed to improve production planning, which includes the following: • Using six-week look-ahead schedules. • Screening processes for creating workable assignments. • Sizing assignments to crew capacity. • Charting and acting on reasons for not doing planned work. • Using percentage of planned weekly assignments completed (PPC charts). Subcontractors were also introduced to first fun studies (FRS), which entailed detailed planning, study and improvement of field operations. The results from these changes were improved quality of subcontractor production planning as well as improvements in field operations. The improvement program resulted in substantial increases in productivity as well as a project completed on schedule. This particular case study implemented production planning to increase the reliability of the subcontractors’ work plans by allowing them to better match labor to their work and identify reasons why work was not completed. 5.9.2.2 Linbeck Construction (Pappas 1990). This case study examined the following lean principles, methods and/or tools: • Increased production planning. • Decreased variability-increased reliability. • Increased project coordination. Linbeck Construction used the Last Planner System of production control on a remodel of the chemistry building at Rice University. The project was a complete demo-to-structure renovation of a university chemistry building originally built in 1925. The general contractor studied was a merit shop contractor who specializes in commercial and building construction. Approximately 90 percent of the work on this project was subcontracted; both union and merit shop subcontractors were involved. The construction contract was $22 million. The entire project, including assessment and design, was $28.5 million. The construction duration was 12 months. The contractor was responsible for all material procurement, including laboratory equipment. The owner procured the furniture. Project staffing included one project manager, two project engineers, one superintendent, one assistant superintendent, 15 foremen (nine from subcontractors), and 78 craftsmen (65 from subcontractors). The construction contract was a negotiated, cost plus fixed fee/guaranteed maximum price contract with graded incentive bonuses. The five major subcontractors were also under the same contract arrangement. The incentive bonuses were based primarily on the cost performance of the project. 56 Lean construction methods were fully embraced by the owner, general contractor and all major subcontractors. There was obviously a great deal of coordination and communication; contractors worked together, instead of at each other’s expense. This level of commitment was critical to the success of the project. The designer was willing to implement lean construction as long as it provided some benefit, but did not fully embrace the program. This had detrimental effects on the timely completion of the design documents, which negatively affected the start of the construction schedule. To mitigate some of these delays, the construction permits were obtained individually for each floor as parts of the design were completed. The renovation of a 70-year-old building is a challenging task. Add to this the fact that the work was 90 percent subcontracted, and the project appeared to be a prime candidate for major coordination problems. The lean construction approach clearly had a positive impact on the project. Foreman delay survey data showed that delays due to common problems with tools, information and materials were a fraction of what is experienced on most projects. This indicates that the planning process was very effective for improving field productivity. The increased planning, communication and coordination among project participants allowed the work to progress smoothly, without major conflicts between contractors. This degree of cooperation indicated that the project team accepted the concept of optimizing the project as a whole, as opposed to optimizing individual activities or optimizing the work of individual companies. 5.9.3 Lean Implementation Case Studies at the Organization Level 5.9.3.1 Pacific Contracting (Eagan 1998). This case study examined the following lean principles, methods and/or tools: • Three-dimensional design system, resulting in increased constructability and increased reliability of information. • Construction method planning. • Employee motivation. • Increased production planning. Pacific Contracting of San Francisco, a specialist cladding and roofing contractor, has used the principles of lean thinking to increase its annual turnover by 20 percent in 18 months with the same number of staff. The key to this success was improving the design and procurement processes to facilitate construction onsite and investing in the front end of projects to reduce costs and construction times. The company identified two major problems to achieving flow in the entire construction process: inefficient supply of materials that prevented site operations from flowing smoothly and poor design information from the prime contractor that frequently resulted in a large amount of redesign work. To tackle these problems, Pacific Contracting combined the more efficient use of technology with tools for improving planning of construction processes. A computerized 3D design system was used to provide a better, faster method of redesign that led to better construction information. The design system provided a range of benefits, including isometric drawings of components and interfaces, fit coordination, planning of construction methods, motivation of work crews through visualization, first run tests of construction sequences and virtual walk-throughs of the product. A process-planning tool known as Last Planner, developed by Glen Ballard of the Lean 57 Construction Institute, was used to improve the flow of work onsite by reducing constraints such as lack of materials or labor. 5.9.3.2 The Neenan Company (Eagan 1998). This case study examined the following lean principles, methods and/or tools: • Increased production planning. • Increased project coordination. • Multi-functional teams. The Neenan Company, a design-build company, is one of the most successful and fastest growing construction companies in Colorado. It has worked to understand the principles of lean thinking and looked for applications to its business using “Study Action Teams” of employees to rethink the way they work. Neenan has reduced project times and costs by up to 30 percent through developments such as the following: • Improving the flow of work onsite by defining units of production and using tools such as visual control of processes. • Using dedicated design teams working exclusively on one design from beginning to end and developing a tool known as “Schematic Design in a Day” to dramatically speed up the design process. • Innovating in design and assembly; for example, through the use of prefabricated brick infill panels manufactured offsite and preassembled atrium roofs lifted into place. • Supporting subcontractors in developing tools for improving processes. 5.9.3.3 Argent (Eagan 1998). This case study examined the following lean principles, methods and/or tools: • Strategic partnering. Argent, a major commercial developer, has used partnering arrangements to reduce the capital cost of its offices by 33 percent and total project time in some instances by 50 percent since 1991. It partners with three contractors and a limited number of specialist subcontractors, consultants and designers. 5.9.3.4 Neil Muller (Eagan 1998). This case study examined the following lean principles, methods and/or tools: • TQM. Neil Muller Construction, South Africa, has used TQM techniques to achieve an 18 percent increase in output per employee in a year, a 65 percent reduction in absenteeism in four years and a 12 percent savings on construction time on a major project. 58 6.0 Evaluating a Construction Value Stream 6.1 Construction’s Production Value Stream To understand where value is added in a production process, one must first learn the steps or phases a product goes through to reach a finished state. The developers of the Toyota Production System (Ohno 1988; Shingo 1989) and other early adopters of lean principles have emphasized the importance of mapping out the entire production process. Mapping out all of the steps of a production process allows one to focus on eliminating steps that are not required. Relating this to the construction industry, value stream mapping allows each party involved in the construction process to understand where value is generated. Tapping, Luyster et al. (2002) define a value stream as “everything - including non-value adding activities - that makes the transformation possible.” For construction, a transformation is the process of converting raw materials and labor into a finished product (building, bridge, road, etc.). In other words, the value stream represents the channels that material, equipment and workers move through to produce the finished product. Fundamentally, value stream mapping allows one to differentiate between value adding (VA), non-value adding but required (NVAR) (Type I muda), and pure non-value adding (NVA) actions (Type II muda) in a construction process. To highlight areas of waste, work must be defined as VA, NVAR or NVA. Section 6.2 defines each of these categories of work relative to the processes of the construction industry. 6.2 Categories of Work In general terms, inefficiencies are classified as one of three types: inefficiency due to waste (NVA activities), inefficiency due to work that does not directly contribute value (NVAR activities) and inefficiency due to poorly designed work processes (ineffective VA activities). 6.2.1 VA Definition For this research, the team adopted Walbridge-Aldinger’s strict definition for VA activities as “…any activity that changes the shape, form, or function of materials or information to meet customer’s needs” (Walbridge-Aldinger 2000). This definition excludes common construction work such as material handling, inspection or temporary structures. Another less precise way of thinking about VA activities is that they are those activities that the client is actually interested in purchasing. For example, one could say that the client is interested in purchasing a steam line for a power plant, but not the temporary support or testing activities that are needed to produce a finished pipeline. A VA action in this process is the physical welding of the pipe spools into their final position. This strict definition for VA activities has been adopted in this report to provide pinpoint focus on the customer value equation. 6.2.2 NVAR Definition This category can be separated into three subcategories that are required for construction operations, yet have no permanent effect on the finished product. These subcategories include material positioning, in-process inspection, and temporary work and support activities (TWSA). 59 6.2.2.1 Material Positioning. This subcategory includes all activities that involve the movement of a structural steel member or pipe spool into its final position. For example, flying a column into its final position in the structure is a required action, but it does not actually change the physical characteristic of the finished product. The structure is physically changed only when bolts are tightened around the baseplate. (Note: one must be careful when labeling an activity as material positioning. Material positioning does not include moving a steel member from the laydown yard to a staging area. This action should be labeled as “transport,” which is an NVA activity.) 6.2.2.2 In-Process Inspections. This subcategory includes actions such as the leveling, plumbing and/or final field measurements of installed material. It also includes in-process or production weld inspections that are required in accordance with individual project specifications. This subcategory accounts for current construction requirements of inspecting ongoing and finished products to ensure quality to the customer. For example, continually plumbing and leveling the structure as steel members are erected would fall under this subcategory. 6.2.2.3 Temporary Work and Support Activities (TWSA). This subcategory includes all actions that must occur while activity-specific equipment is being used to erect and secure a member into its final position. Attaching or adjusting rigging, setting up temporary supports or wrapping a steel member with the hoist line to lift it into its final position would fall under the TWSA subcategory. It also includes those actions needed to ensure that equipment in use during the activity continues to work in the most optimal manner, such as replacing welding rods when they are too short or refueling a scissors lift with gas. Each NVAR activity provides an opportunity to redesign the process to eliminate or reduce the NVAR component in a cycle. For example, one could redesign a building to allow for multiple repetitions and reuses of formwork, thereby reducing the work content of the formwork activity. Alternatively, one could redesign the structure to use precast foundation elements, thereby eliminating the need for formwork altogether. 6.2.3 NVA (Waste Definitions) Interest in lean construction has increased academic and industry interest in waste reduction in construction. Waste reduction and elimination is one of the core principles of lean production, and although it is not the only benefit of lean implementation, it does provide a logical starting point. The potential cost and time savings achieved by eliminating or reducing NVA activities are significant. Studies show that only 3 to 20 percent of tasks add value (Ciampa 1991), with their share in total cycle time measuring between 0.5 and 5 percent (Stalk and Hout 1990). Womack and Jones (1996) define waste as “…any human activity that absorbs resources but creates no value.” The definition developed by Walbridge-Aldinger (2000) better conforms to construction production; waste is defined “…as anything that takes time, resources or space but does not add value to the product or service delivered to the customer.” To develop the construction production value stream, Ohno’s concepts of production will be modified to more closely conform with construction production as follows: • Overproduction--Products being produced in excess quantities or products being made before customers need them. This implies that production on a late-start schedule is the ideal. Indeed, from the client’s viewpoint, if a late-start schedule could be guaranteed in the face of weather, supplier schedules and other uncertainties, a late-start schedule would minimize WIP and cash flow requirements. • Waiting--Products, equipment or people that must wait because of poor scheduling, production control or unbalanced crew size. Changing work tasks in 60 the course of a typical construction sequence make establishing a proper crew composition difficult. • Transport--Unnecessary movement of materials. Material handling and transport necessitated by the relocation of work are unavoidable in construction. This type of waste includes excessive, multiple and suboptimal movements of material. • Extra Processing--Rework, rehandling or storage that is caused by defects in design, fabrication or construction activities. This type of waste occurs within crews. • Inventory--Extra raw or fabricated materials, excess construction equipment. • Motion--Extra movement by employees or movement of equipment caused by inefficient layout, remote lay-down areas or improper work sequences. • Defects--Errors or deficiencies in finished products that require a crew to return to a work item or require a follow-up crew to perform added work (punch list items). This type of waste occurs between crews. Table 6.1 compares the seven major classifications of waste in both manufacturing and construction contexts. 6.3 Data Collection Procedure A total of six value stream case studies were conducted as part of this research. Three cases focused on structural steel erection and three cases focused on large bore pipe installation. For each case study, operations were observed for two days. Two different methods were used to gather value stream data. The first method (hand data collection) required one observer to monitor each crew member in the observed crew. The second method (video data collection) required two observers and two digital cameras to record each crew’s movements. Both methods required data to be entered into spreadsheets so that the necessary tabular results could be generated for each job. Figure 6.1 is an example of one of the data sheets used for the hand data collection method. 6.3.1 Hand Data Collection Method Each worker in a crew is represented in the first column of the data sheet. Names for each worker were determined by the position that they were observed in during the various cycles. The second column describes the specific building component that the worker was working on at a specific point in an observation period. The third column represents the “real” clock time during the observation period as measured from the first activity.1 The fourth column indicates the activity observed for that specific time period. The fifth column shows the duration of time spent on that activity. The sixth column specifies whether an activity is VA, NVAR or NVA. The seventh column provides for a further subcategorization of each activity into one of the seven wastes or one of the three subcategories of NVAR activities. 1 The time shown in Column No. 3 is not in temporal order because analysis of the data required each row of information to be sorted. 61 Table 6.1: Comparison of Lean Manufacturing to Lean Construction Waste Type of Waste Manufacturing Construction 1. Overproduction Production of too many units or parts due to push nature of manufacturing. Overbuilding a particular aspect of a project, either because it was overengineered or a process was started before it was really needed. 2. Waiting Time spent waiting for the next batch of parts to arrive from the previous conversion process. Time spent waiting for a machine to finish. Time spent waiting for other work crews to finish their particular conversion process so that the next conversion process may begin. Time spent waiting on crew members of a specific team. Time spent waiting for parts or instructions. 3. Transport Wasted effort to transport materials, parts or finished goods into or out of storage between processes. Wasted effort to transport building components or tools into or out of job trailers or storage between processes. 4. Extra Processing (Operations) Doing more work than is required. Waste associated with rework, rehandling or storage caused by defects in design, fabrication or construction activities. 5. Inventory Maintaining excess inventory of raw materials, parts in process or finished goods. Maintaining excess inventory of construction components, equipment or tools. 6. Motion Waste associated with Waste associated with unnecessary unnecessary worker/equipment worker/equipment movement around movement between work stations. the construction site. 7. Defects Repair or rework. Deficiencies in the finished product that require additional work or rework to correct punch list items. 62 FieldObservationSheet CaseStudy#5 Date: Personor Equipment: EntireGroupCycle#1 Worker Member Classification Time Activity 1/15/2003 Timeat Activity Waste Activity Classification Classification GroundCrewman#1 Column 1:13:12 Waiting 00:18 NVA Waiting GroundCrewman#1 Column 1:14:50 Waiting 00:10 NVA Waiting GroundCrewman#1 Column 1:51:40 Waiting 01:30 NVA Waiting GroundCrewman#1 Column 1:13:30 PositioningColumnontoBasePlate 00:30 NVAR Mat. Pos GroundCrewman#1 Column 1:50:40 PositioningColumnontoBasePlate 01:00 NVAR Mat. Pos GroundCrewman#1 Column 1:17:12 ReleasingTagLine 00:48 NVAR T.W.S.A. GroundCrewman#1 Column 1:14:00 BoltingColumnBase 00:50 VA ValueAdding GroundCrewman#1 PodBeamCombo 0:09:20 Walking 04:25 NVA Motion GroundCrewman#1 PodBeamCombo 0:16:00 Walking 00:50 NVA Motion GroundCrewman#1 PodBeamCombo 0:18:10 Walking 00:20 NVA Motion GroundCrewman#1 PodBeamCombo 0:22:25 Walking 00:21 NVA Motion GroundCrewman#1 PodBeamCombo 0:22:50 Walking 01:40 NVA Motion GroundCrewman#1 PodBeamCombo 0:39:50 Walking 00:10 NVA Motion GroundCrewman#1 PodBeamCombo 0:41:05 Walking 00:15 NVA Motion GroundCrewman#1 PodBeamCombo 0:51:15 Walking 01:28 NVA Motion GroundCrewman#1 PodBeamCombo 0:57:30 Walking 00:30 NVA Motion GroundCrewman#1 PodBeamCombo 1:01:44 Walking 00:16 NVA Motion GroundCrewman#1 PodBeamCombo 1:04:47 Walking 00:43 NVA Motion GroundCrewman#1 PodBeamCombo 1:08:30 Walking 04:42 NVA Motion GroundCrewman#1 PodBeamCombo 1:16:50 Walking 00:22 NVA Motion GroundCrewman#1 PodBeamCombo 1:18:00 Walking 00:20 NVA Motion GroundCrewman#1 PodBeamCombo 1:39:55 Walking 00:27 NVA Motion GroundCrewman#1 PodBeamCombo 1:42:50 Walking 00:20 NVA Motion GroundCrewman#1 PodBeamCombo 1:46:00 Walking 00:15 NVA Motion GroundCrewman#1 PodBeamCombo 1:54:40 Walking 01:20 NVA Motion GroundCrewman#1 PodBeamCombo 2:10:40 Walking 00:30 NVA Motion GroundCrewman#1 PodBeamCombo 0:24:30 Movingequipment andtools (carryingtaglinefromprevious columnline) 01:08 NVA Transport GroundCrewman#1 PodBeamCombo 0:43:30 Movingequipment andtools (carryingtaglinefromprevious columnline) 01:20 NVA Transport GroundCrewman#1 PodBeamCombo 0:49:50 Movingequipment andtools (carryingtaglinefromprevious columnline) 01:25 NVA Transport GroundCrewman#1 PodBeamCombo 1:18:20 Movingequipment andtools (carryingtaglinefromprevious columnline) 00:40 NVA Transport GroundCrewman#1 PodBeamCombo 1:57:30 Movingequipment andtools (carryingtaglinefromprevious columnline) 01:40 NVA Transport GroundCrewman#1 PodBeamCombo 0:54:08 Movingequipment andtools (movingdunage) 02:22 NVA Transport GroundCrewman#1 PodBeamCombo 1:15:00 Movingequipment andtools (movingdunage) 00:50 NVA Transport GroundCrewman#1 PodBeamCombo 1:45:30 Movingequipment andtools (movingdunage) 00:30 NVA Transport GroundCrewman#1 PodBeamCombo 1:53:10 Movingequipment andtools (movingdunage) 01:30 NVA Transport GroundCrewman#1 PodBeamCombo 0:00:00 Waiting 00:20 NVA Waiting GroundCrewman#1 PodBeamCombo 0:02:00 Waiting 05:20 NVA Waiting GroundCrewman#1 PodBeamCombo 0:19:00 Waiting 02:30 NVA Waiting GroundCrewman#1 PodBeamCombo 0:22:46 Waiting 00:04 NVA Waiting GroundCrewman#1 PodBeamCombo 0:25:50 Waiting 02:10 NVA Waiting GroundCrewman#1 PodBeamCombo 0:28:40 Waiting 08:00 NVA Waiting GroundCrewman#1 PodBeamCombo 0:41:20 Waiting 02:10 NVA Waiting GroundCrewman#1 PodBeamCombo 0:44:50 Waiting 03:50 NVA Waiting GroundCrewman#1 PodBeamCombo 0:48:50 Waiting 01:00 NVA Waiting GroundCrewman#1 PodBeamCombo 0:53:33 Waiting 00:35 NVA Waiting GroundCrewman#1 PodBeamCombo 0:56:30 Waiting 01:00 NVA Waiting GroundCrewman#1 PodBeamCombo 0:58:00 Waiting 01:25 NVA Waiting Figure 6.1: Hand Data Collection Sheet 63 Comments/Remarks During the hand collection method, each observer was equipped with a stopwatch and a clipboard containing data sheets. Data was recorded as the activities occurred. Each time a new task was started, an entry was made on the data sheet. For example, an entry might indicate that a worker was rigging a bar joist for the crane. The next entry might indicate that the worker was “waiting” until the crane lowered its hook so that the rigging for the next bar joist could be attached. The elapsed time for each task was recorded, as well as the observer’s judgment regarding whether the task was “value-adding” to the process. A digital video camera was also used to record all actions during the erection sequence. The videotapes were used to conduct a more detailed analysis of the activities. 6.3.2 Video Data Collection Video data collection required two observers each to operate a video camera. The digital video cameras were positioned to view the activity area at right angles to provide “depth” in both directions being viewed. In the lab, two televisions were placed next to each other and used to view the recorded operations. Using both cameras provided a three-dimensional view of the workspace. Viewing the tapes several times allowed one to record data on each of the observed crew members. Both the hand data collection method and the video data collection method worked satisfactorily. Table 6.2 summarizes the advantages and disadvantages of each collection method. 6.4 Case Studies The six case studies focused on two trades: the structural steel erection process and the large bore pipe installation process. The structural steel erection process represents a process in which cycles are relatively fast and repetitive. The structural steel cycles require large crews and heavy equipment. The pipe spool installation process has opposite traits. Pipe installation is characterized by long, nonrepetitive cycles. The spools often vary significantly from one to another. The pipe crew can be quite small, and the tasks can be labor intensive The following subsections provide a brief description of the case study projects and the cycle(s) observed during the observation period. Site-specific information has been removed to prevent disclosure of proprietary information. A complete analysis of each case study is presented in Appendices A through F. 6.4.1 Case Study No. 1 Structural Steel Erection Job No. 1. The project was a 200,000 square foot structure, 660 feet long and 300 feet wide. The entire area was divided into 55 bays, each measuring 60 feet by 60 feet. The team observed the erection activities associated with four bays. Hand data collection was used. 6.4.2 Case Study No. 2 Structural Steel Erection Job No. 2. The site included roughly 1,700 acres (another 300 acres were reserved for future development). Several buildings will eventually occupy the site. The case study focused on an area in the largest of these buildings. The structure was approximately one million square feet and, when viewed from the plan view, resembled the shape of the letter 64 Table 6.2: Advantages and Disadvantages of Different Data Collection Methods Data Collection Method Advantages Disadvantages Real-Time Hand Collection (Method No. 1) Initial observations are captured as they occur. Minimal amount of time required to record data. Different interpretations of waste categories occur between the observation team members. Requires one observer per member in the crew. Digital Video Collection (Method No. 2) Observations outside of the camera’s view are captured by observation team members (e.g., crew members may be working on different cycles outside of the camera’s view, in which case data collection method No. 2 might assume the crew member’s activities to be waiting). Task durations sometimes occur at such a rapid pace that the initial observation may be missed. Allows for a more detailed review of each cycle. Limited by the camera’s view of the cycle. Activities outside the camera’s view are not captured. Leaves room for error. Data collection process can be accomplished with only two observers. Longer periods of time required to analyze each crew member’s action in a cycle. 65 “F.” The structure was composed of several smaller bay sections which roughly measured 60 feet by 60 feet. The team observed the erection activities associated with two new bays performed by one crew and the finishing activities of erecting purlins on top of a completed bay section done by a second crew. Hand data collection was used. 6.4.3 Case Study No. 3 Structural Steel Erection Job No. 3. Three main structures were being erected at this jobsite. The total square footage for all buildings erected on this site was roughly 1.3 million. The observation period focused on the largest of these structures, which accounted for more than half of the total square footage. The structure was composed of several smaller bay sections, roughly measuring 60 feet by 60 feet. The team observed the erection activities that occurred in four new bays, with a focus on column, pod beam and spandrel beam erection for one crew, as well as the erection activities associated with the bar joist members with a second follow-up crew. 6.4.4 Case Study No. 4 Pipe Spool Installation Job No. 1. This project involved the installation of an auxiliary boiler in an existing power plant. The housing for the boiler was located adjacent to the main power plant boiler room. From the existing structure, four inch natural gas pipes and eight inch steam piping were connected by a tee from the existing lines back to the new auxiliary boiler housed in the new structure. Two separate areas were observed in this study. The focus in Area 1 was the installation of an eight inch pipe spool approximately two feet long, a relief valve and an eight inch elbow pipe spool approximately five feet long. All of the piping components observed in Area 1 were prefabricated and had flanged/bolted connections. The focus of Area 2 was the erection of an elbow pipe spool in a steam line that will be used as a bypass from the main boiler’s steam line during down times. 6.4.5 Case Study No. 5 Pipe Spool Installation Job No. 2. The project observed included the construction of a new chemical processing plant. Several mechanical components and interconnecting pipes were being installed during the observation period. The main focus during this study was the preparation and welding of two sections of eight inch diameter prefabricated pipe into one large section. The case study also included all activities required to lift the final spool into position and temporarily support the spool section until its final supports could be erected/installed. 6.4.6 Case Study No. 6 Pipe Spool Installation Job No. 3. This case study took place at a large manufacturing facility. Several large structures were being erected around the site; the study was focused on the largest of these structures. Unfortunately, during the observation period, several factors prevented the team from observing VA activities so this became a “lessons learned” case study. This case study highlights areas that, from the observation teams perspective, were not lean. 6.4.7 Data Analysis The following section describes the process used to analyze the data for each case study. The purpose of this section is to introduce the reader to the tables and figures located in the appendices that show the individual and crew results for the various case studies. One or more 66 cycles were observed at each jobsite. A cycle was defined according to the nature of the work being performed. The structural steel erection process involved three main cycles: column, girder (beam) and joist (truss) erection. Because the erection process for structural steel is repetitive, the research team was able to obtain several iterations for each cycle. On the other hand, piping installation consists of long cycle times. For this reason, the cycles for process piping were defined as one entire viewing period (i.e., the whole observation period). The detailed case studies in the appendices provide additional information on the definition of each cycle. During each cycle, each individual crew member was evaluated to capture his or her specific contribution to the various cycles. Each crew was also evaluated as a group to illustrate the “crew’s value creation” during a cycle. Tables 6.3 and 6.4 show the tabulated results for a crew member and a crew, respectively. Furthermore, Figures 6.2 and 6.3 graphically represent the data in Tables 6.3 and 6.4. These results were obtained after all required information was entered into the data collection spreadsheet for each worker (refer to Figure 6.1). Table 6.3 and Figure 6.2 show the typical results for an individual worker in a cycle. The first column lists each work category (i.e., VA, NVAR and NVA). In some cases, a worker may not dedicate any time to a specific work category; this results in the category not being shown at all. The second column associates each activity with the specific waste category. The third column represents the total time in a cycle that the crew member spends on a specific waste category. The final column represents the percentage of the total time a worker spends on each waste category in a cycle. Showing this level of detail allows one to better understand what is happening during the construction process. Additionally, analysis at this level of detail highlights areas where improvement efforts should be focused. For example, time wasted on waiting is typical in a crew that has unbalanced work assignments. To address this problem, the required work tasks could be more evenly dispersed throughout the crew or in some cases, crew members could be eliminated. Table 6.3: Typical Results for Welder Completing an Eight Inch Diameter Spool Section Activity Classification VA Waste Classification Time at Activity % of Time at Activity Value Adding 1:24:11 1:24:11 24.58 24.58 Waiting Extra Processing Transport Motion 1:42:37 0:36:28 0:25:23 0:55:21 3:39:49 29.96 10.65 7.41 16.16 64.18 Material Positioning In-Process Inspection TWSA NVAR Total 0:05:33 0:16:17 0:16:40 0:38:30 1.62 4.75 4.87 11.24 Grand Total 5:42:30 100.00 VA Total NVA NVA Total NVAR 67 Table 6.4: Typical Results for an Entire Crew 10:40:25 VA Crew Member Foreman - Pipe Fitter Field Laborer Welder Group Percentage Waste Extra All Activities Waiting Processing Transport NVAR Material Movement Pos. In Proc. Ins. TWSA Total VA + NVAR 0% 0% 25% 19% 52% 30% 10% 21% 11% 6% 5% 7% 22% 2% 16% 12% 2% 2% 18% 1% 5% 14% 16% 100% 100% 44% 20% 5% 100% 36% 13% 30% 12% 7% 15% 5% 8% 10% 100% 36% Figure 6.2: Typical Results for Welder Completing an Eight Inch Diameter Spool Section 68 Figure 6.3: Typical Results for an Entire Crew When the entire crew was evaluated, each crew member’s individual results were combined with those of other crew members. Table 6.4 and Figure 6.3 show the typical results for an entire crew during one typical cycle. In the upper right corner of Table 6.4, the cumulative time spent by the crew on the specific work element is shown. The first column lists each worker involved in the crew, along with the entire crews’ weighted average values on the bottom. For each worker, the percentages shown are based on the total time that each crew member contributed to the cycle, not the total cumulative time shown in the upper right corner. This was done because unequal amounts of time were spent on a cycle by various crew members. Furthermore, if one person was involved in a cycle longer than another, their time should affect the weighted average values the most. The next column shows the percentage of time that a crew member contributed toward VA actions. Columns 3 thru 6 represent each NVA subcategory. Columns 7 thru 9 represent the three subcategories associated with NVAR actions. The tenth column verifies that all of the individual crew member’s time in a cycle was accounted for. The remaining column (11) shows the total percentage value for VA time and NVAR time committed by that crew member to the building component. Notice that only four of the seven types of waste are represented in these tabular results. 6.5 Value Stream Analysis Results In the following subsections, the results for each case study are discussed, and comparisons are made among across similar processes. Observations are then made about the differences between the structural steel value stream and the large bore piping value stream. 69 6.5.1 Structural Steel Case Studies Case Study No. 1 (Appendix A) involved the erection process for light-gauge structural steel. This study examined the extended control the contractor had on the value stream. The contractor controlled all aspects of material purchasing, delivery and erection proceedings. The material element of the value stream included when it was shipped, how it was shipped and the level of organization in which steel was placed on the ground prior to the erection process. The contractor controlled the labor component by specifying the number of workers per crew and the specific tasks each worker was responsible for during the erection cycle. Table 6.5 shows the results from the observation period. Table 6.5: Results for Case Study No.1 - Structural Steel Erection Process2 Activity Classification VA Waste Classification Value Adding VA Total Total Time at Activity % of Total Time 2:51:04 24.89% 2:51:04 24.89% 1:26:53 0:02:58 12.64% 0.43% NVAR Mat. Pos. In-Process-Ins. T.W.S.A. NVAR Total 1:00:44 8.84% 2:30:35 21.91% 3:12:03 0:41:04 0:15:28 1:56:56 27.95% 5.98% 2.25% 17.02% NVA Waiting Extra Proc. Transport Motion NVA Total Grand Total 6:05:31 53.19% 11:27:10 100.00% Table 6.6 shows the Quick Summary results from the value stream map for Case Study No. 1. Of the 792 total workable hours committed to the steel erection process, only 161 were VA. Table 6.6: Quick Summary for Case Study No. 1 Quick Summary for Level One Working Days 24 days Working Time 792 man-hours VA Total 161 man-hours NVAR Total 95 man-hours NVA Total 536 man-hours Case Study No. 2 involved the erection process for heavy-gauge steel. Large joist girders and trusses were required for the structural steel skeleton of the facility. The main point of interest for this study was the material delivery process. The contractor was restricted to delivering only one phase (three to six bays) of steel ahead of the erection crew; the delivery process resembled a JIT delivery system. However, the current delivery system was put in place after the original system of unrestricted deliveries had created safety issues. A direct result of this restriction was the low inventory days required for each phase. The contractor controlled the movement of steel from the manufacturer’s facility to its storage position in the parking lot and, finally, to the material laydown area. A separate subcontractor controlled the labor portion for erecting the steel, as well as the steel movement from the lay-down area into its final position. Table 6.7 portrays the results from the observation period. 2 The crane operator’s time was not included in this analysis because one member of the data collection crew was called away. However, had his time been included it would have shown that the VA/NVA “% of Total Time” values dropped slightly, and the NVAR percentage values acquired the difference. 70 Table 6.7: Results for Case Study No. 2 - Structural Steel Erection Process Activity Classification VA Waste Classification Time at Activity Value Adding % of Time at Activity 1:00:18 10.54% 1:00:18 10.54% 1:21:51 2:00:56 14.31% 21.14% 3:22:47 35.45% 2:18:55 0:22:42 0:41:40 1:45:42 24.28% 3.97% 7% 18.48% NVA Total 5:08:59 54.01% Grand Total 9:32:04 100% VA Total NVAR Mat. Pos. T.W.S.A. NVAR Total NVA Waiting Extra Proc. Transport Motion Table 6.8 shows the Quick Summary results from the value stream map for Case Study No. 2. Of the 2,016 total workable hours committed to the 14 phases of the steel erection process, only 181 were VA. Table 6.8: Quick Summary for Case Study No. 2 Quick Summary for Level One For One Phase (three to six bays) Working Days 4 Working Days Work Time 144 man-hours Work Time VA Total 13 man-hours VA Total NVAR Total 48 man-hours NVAR Total NVA Total 83 man-hours NVA Total For 14 Phases 56 2016 181 674 1162 man-hours man-hours man-hours man-hours Case Study No. 3 involved the erection process for light-gauge steel. The main point of interest for this case study included the use of two separate crews to erect the various steel elements. For this project, the subcontractor controlled the entire labor value stream and a portion of the material value stream after the steel had been delivered to the site. The contractor controlled the portion of the material value stream from procurement to delivery of the steel onto the site. The subcontractor chose to use two crews for the production process. One crew was responsible for erecting columns and pod beam combinations (pod beam and spandrel beam connected as one unit). The second crew was responsible for erecting the interleaving bar joists for each bay. The design of this multiple crew system was closer to a lean manufacturing ideal. The higher density of workers provided higher throughput and a smaller amount of WIP. However, while the process was fast, adding new crew members to the production process caused waste attributed to “waiting” that consumed nearly half of the total time because of synchronization problems between Crew 2 and Crew 1. Table 6.9 shows the results from the observation period. Table 6.9: Results for Case Study No. 3 - Structural Steel Erection Process Activity Classification VA Waste Classification Total Time at Activity Value Adding VA Total % of Total Time 2:04:45 9.77% 2:04:45 9.77% NVAR Mat. Pos 2:00:32 9.44% In-Process Ins. T.W.S.A. 0:06:15 3:10:01 0.49% 14.89% 5:16:48 24.82% 9:41:12 0:08:09 0:59:17 3:06:19 45.53% 0.64% 4.64% 14.60% NVAR Total NVA Waiting Extra Proc. Transport Motion NVA Total 13:54:57 65.41% Grand Total 21:16:30 100.00% 71 Table 6.10 shows the Quick Summary results from the value stream map for Case Study No. 3. Of the 1,544 total workable hours committed to the steel erection process, only 152 were VA. Table 6.10: Quick Summary for Case Study No. 3 Quick Summary for Level One Working Days 37 Working Time 1544 man-hours VA Total 152 man-hours NVAR Total 373 man-hours NVA Total 1018 man-hours 6.5.1.1 Comparison of Structural Steel Cases. Case Studies No. 1 and No. 3 offer insight into to the effects of crew variation in a steel erection process. Material on both sites was organized in a similar fashion. The main difference between these studies was the additional erection crew in Case Study No. 3. Lean ideology requires balancing processes to create flow in the value stream. Flow was generated in Case Study No. 3 at the crew level. In Case Study No. 3, no back-tracking was required such as that observed during Case Study No. 1 (crew erected two columns and girders, then backtracked to erect bar joists). While the erection process proved to be faster compared to Case Study No. 1, the waste attributed to waiting nearly doubled for Case Study No. 3. Similar complications resulting from unbalanced crewmember responsibilities were present in each study. Three lessons were learned from this comparison: (1) Introducing two (or more) crews to the erection process does not necessarily create additional value, even though it does increase throughput and reduce WIP. Multiple ill-designed crews only increase the rate at which waste is accumulated. The VA percentage dropped from 25 percent for Case Study No. 1 to roughly 10 percent for Case Study No. 2. (2) Adding another crew to the process can add waste to the value stream if the work progress of the individual crews is not synchronized. The increase of NVA percentages from 53 percent (Case Study No. 1) to 65 percent (Case Study No. 3) highlights this effect. (3) Even though VA percentages dropped at the project level, the reduction in overproduction (WIP) and inventory wastes, as viewed from the owner’s perspective, may offset the decrease in the VA percentage (i.e., the project is completed earlier, thus allowing income to be generated earlier from a finished facility). Comparing Case Study No. 2 to Case Studies No. 1 and No. 3 shows the effect structural design has on a value stream. The light-gauge steel in Case Studies No. 1 and No. 3 required smaller amounts of NVAR actions (21.9 and 24.8 percent, respectively) than the heavier-gauge steel for Case Study No. 2 (35.5 percent). More actions were required during Case Study No. 2 to safely hoist and secure each structural element into its final position. A decrease in the NVA percentage would have been shown had material organization in the lay-down area been different in Case Study No. 2 (i.e., offloading steel elements from the truck to a position on the ground next to their final place in the structure). 72 The largest VA percentage (24.9 percent) was found in Case Study No. 1 and the smallest (9.8 percent) in Case Study No. 3. The largest NVAR percentage (35.5 percent) was found in Case Study No. 2 and the smallest (21.9 percent) in Case Study No. 1. The largest NVA percentage (65.45 percent) was found in Case Study No. 3 and the smallest (53.2 percent) in Case Study No. 1. 6.5.2 Process Piping Case Studies Case Study No. 4 (Appendix D) involved the installation process for eight inch diameter piping components. Two points of interest were highlighted in this case study. First, the contractor controlled all aspects of the material and labor value streams. Second, the observations included both prefabricated and field-fabricated piping processes. This second point was of particular interest because it highlighted the different labor requirements for each piping process. The prefabricated spool and valve installation process required one fifth of the time needed to field fabricate and install pipe spools using a similar crew structure. The VA percentage was 18 percent for the prefabricated process and 8 percent for the field-fabricated process. The weighted VA, NVAR and NVA percentages for the entire observation period are shown in Table 6.11. Notice the large value for pure NVA waste (Type II muda). Table 6.11: Results for Case Study No. 4 - Piping Installation Process Activity Classification VA Waste Classification Value Adding Time at Activity % of Time at Activity 1:14:07 10.43% 1:14:07 10.43% Mat. Pos. 1:26:55 12.23% In-Process Ins. T.W.S.A. 0:16:00 0:49:11 2.25% 6.92% 2:32:06 21.40% VA Total NVAR NVAR Total NVA Waiting 3:14:31 27.37% Extra Proc. Transport 1:37:57 1:16:51 13.78% 10.81% Motion NVA Total Grand Total 1:55:08 16.20% 8:04:27 68.17% 11:50:40 100.00% Table 6.12 shows the Quick Summary results from the value stream map for Case Study No. 4. Of the 1,267 total workable hours committed to the piping installation process, only 98 were VA. Table 6.12: Quick Summary for Case Study No. 4 Quick Summary for Level One For All Spools Worked on During Observation Period Working Days 33 Working Time 1267 man-hours VA Total 98 man-hours NVAR Total 266 man-hours NVA Total 904 man-hours Case Study No. 5 (Appendix E) involved the installation of prefabricated pipe spools. The major point of interest for this study was the cause and effect relationship between the material and labor value streams. Multiple parties controlled the material value stream before the prefabricated spools were shipped to the site (e.g., spool fabricator, cleaning and painting subcontractor). The contractor oversaw the movement of material between each party. The 73 installing subcontractor controlled the material value stream once it was delivered to the site. The installing subcontractor controlled all aspects of the labor value stream as well. Obstructed information flow between the various parties resulted in a large extra processing percentage (e.g., paint was ground off each end of the delivered spools from the painting subcontractor). Table 6.13 shows the weighted average values for the entire installation period. Table 6.13: Result for Case Study No. 5 - Piping Installation Process Activity Classification VA Waste Classification Time at Activity Value Adding VA Total % of Time at Activity 1:24:11 8.19% 1:24:11 8.19% NVAR Material Pos. 0:39:13 3.82% In-Process Ins. T.W.S.A 1:21:47 1:15:48 7.96% 7.38% 3:16:48 19.15% 5:15:40 3:13:17 1:19:17 30.72% 18.81% 7.72% NVAR Total NVA Waiting Extra Proc. Transport 2:38:17 15.40% NVA Total Motion 12:26:31 72.65% Grand Total 17:07:30 100.00% Table 6.14 shows the Quick Summary results from the value stream map for Case Study No. 5. Of the 800 total workable hours committed to the piping installation process, only 58 were VA. Table 6.14: Quick Summary for Case Study No. 5 Quick Summary for Level One For All Spools Worked on During Observation Period Working Days 35 Working Time 800 man-hours VA Total 58 man-hours NVAR Total 153 man-hours NVA Total 590 man-hours In Case Study No. 6 (Appendix F) installation of Victaulic pipe was observed. No VA actions were observed during this visit. The observation period was not representative of the site’s average work distribution values; therefore, only a “lessons learned” synopsis for Case Study No. 6 is included. 6.5.2.1 Comparison of Piping Process Cases. Greater control of the process piping value stream in Case Study No. 4 resulted in the best average work distribution values. Comparing only the VA percentages from the prefabricated spool processes of each job shows that there was a net difference of 10 percent (18 percent from Case Study No. 4, 8 percent from Case Study No. 5). Furthermore, the VA percentage from Case Study No. 5 for prefabricated spools more closely resembles the field-fabricated values found in Case Study No. 4. When the value stream is not monitored at the level required, defects pass through the value stream; the final erection crew was required to fix all upstream defects. These defects were the cause for the lower VA percentage of the prefabricated spool installation in Case Study No. 5. Both cases included extra processing (rework) wastes. More than two thirds of the installation processes resulted in pure waste (NVA). Also, the VA percentage for process piping ranged from 8 to 10.5 percent. Finally, defects pushed through the value stream that required rework on the 74 part of the crew caused variations from the expected work distribution values and the actual work distribution values. 6.5.3 Comparison of Processes Table 6.15 compares the weighted average work values found for each case study. Excluding Case Study No. 1, the majority of processes analyzed in this report resulted in VA percentages between 8 and 10.5 percent. In other words, at the production level, the typical construction production process was found to contain from 8 to 10.5 percent VA actions. At best, for a simple, highly repetitive process, a contractor (one who is trying to apply lean principles) attained a VA percentage of 25 percent. The objective of a typical lean manufacturing company, in contrast, is to achieve 75 percent VA activities on an entire assembly line. The construction industry realizes one sixth (at worst) to one third (at best) of the VA time of the manufacturing industry. Table 6.15 also shows that process piping jobs incur higher percentages of pure waste (NVA) in the production process. Specifically, the piping production process contributes larger amounts of time to transport and extra processing waste than does the steel production process. This extra processing is directly related to defects occurring upstream in the piping value stream. Table 6.15: Comparison of Different Processes On average, steel production processes require more NVAR actions than do piping processes. A large contributor to the steel process NVAR category is material positioning. Because steel erection processes are more repetitive than piping processes, more time is spent on the act of aligning each new member into a final position. More time is also required in the steel erection process for TWSA. However, NVAR waste due to in-process inspections is more typical for piping processes than for steel processes. 6.5.3.1 Limitations of this Study. The value streams for each case study represent only those elements specific to the process observed. To map out the entire value stream for the construction production process, the job would need to be monitored in its entirety. For example, Toyota’s entire value stream related to its production process can be observed in one day (i.e., a car takes one full day to go from start to finish). Therefore, to view the entire value stream for a construction production process, the process must be observed from the start of the project through completion. 75 6.5.4 Value Stream Analysis What can be learned from the results of the construction value stream analysis? First, the value stream map is flexible enough to accommodate two very different construction processes, and since most construction processes fall between these extremes, the value stream map is capable of representing most, if not all, remaining processes. Second, by implementing the value stream map, a systematic approach to identifying problem areas in the production process can be created. If the problem is not caused at the production level, the value stream map will highlight the bottlenecked area. One generalization is obvious. In construction, NVA activities consume between 50 and 75 percent of the productive time on the job. It is worthwhile to note that this percentage was derived from crews doing direct work. Many crews on the typical jobsite perform indirect work (warehousing, laydown and cleanup). If their work efforts were included, the NVA percentage would certainly rise. NVAR work on the typical construction job consumes between 20 and 25 percent of the productive time. This is much higher than that experienced at the typical manufacturing plant. A high fraction of NVAR work is expected in construction because of the nature of the work and the fact that it is performed in relatively uncontrolled environments. It also seems obvious that the construction industry should take advantage of the ability to reduce the NVA component of construction value streams. This can be done by working to balance crews and to make work tasks and task times more predictable. Assigning crews of the appropriate size and eliminating double and triple handling of materials will also help reduce the NVA component. Significant gains can be realized by reducing the NVAR component. However, this will require changes that are broader in scope. Some changes to erection/assembly techniques will need to be made if the frequency of in-process inspection is to be reduced. Changes to design will be needed to enable less reliance on temporary supports. More work with suppliers will be necessary to eliminate excess material positioning time. Finally, improving VA times will require changes in project design to provide for more repetition, more standardization and more preassembly and prefabrication. Perhaps the greatest contribution of these value stream studies is to demonstrate in an objective way how much improvement is possible in construction value generation. 6.6 Identifying Construction’s Value Stream There are two aspects one must investigate to identify waste on a construction site. The first involves the material required to construct a facility. The second entails the multiple activities required for the installation of material into its final position. Each aspect of the value stream occurs on a different time scale. The material value stream includes all materials that are delivered to the site in a “post” manufactured state, such as a structural columns or the bolts required to secure that column into place. Piping material might be a pipe spool or a welding rod. In short, materials include everything that will remain with the facility after the construction phase is completed. The labor aspect of the value stream encompasses all labor required to erect and install material into its final position. Closely associated with labor is construction equipment. For every piece of equipment on a construction site, there is a human operator. Workers along with machines will bolt, frame and weld components into their final position. Workers, aided by machines, add 76 value to the final product. How much value they are capable of adding depends upon management, work processes, information flow and the skill of the crews. According to the definitions of waste, waiting, transport, extra processing and motion are most closely related to the actual work process (i.e., labor and equipment). Overproduction, inventory and defects are associated with the material supply chain and production scheduling functions. The observation periods for each case study were brief and focused, which limited the team’s ability to quantify wastes associated with overproduction, inventory and defects in specific detail. 6.7 Developing a Construction Value Stream Map As demonstrated in Chapter 3.0, construction is different from manufacturing. One can assume that a value stream representation for a construction process will likewise be very different from one for a manufacturing value stream. Review of value stream mapping in manufacturing is a useful starting point for developing value stream mapping in construction. Duggan and Liker (2002) expand on procedures developed by Rother and Shook (1998) for value stream mapping models of manufacturing plants. In a typical plant, the material would flow in one side and proceed through the various processes (stamping presses, grinders, paint shops, etc.) to produce the finished product required by the customer. Viewed in its entirety, this model represents a first in first out (FIFO) process. While this idea does accommodate many manufacturing processes, it does not relate as well to a typical construction jobsite. Duggan and Liker took this idea and expanded it to include manufacturing plants that have multiple inputs coming together through the same value stream to produce a variety of outputs (products). This process is further identified as mixed model production. In the Duggan and Liker mixed model production, two new concepts are found that aid in the development and implementation of the value stream on a construction site. The first concept requires one to look at activities in a value stream not at the individual level, but rather at the value stream as a mix of activity groups labeled by Duggan as “product families.” The second concept builds on the first by requiring one to focus on the “total” time associated with the product families, rather than on the individual times required for each product. For the purpose of this study, “products” will be considered to be “processes.” In other words, the construction value stream at the topmost level will be represented through a series of process families. Duggan and Liker define product family as “a group of products that pass through similar processes or equipment and have similar work content.” For construction, it can be said that a process family is a group of processes that require similar crew members or equipment and have similar work content. For example, a process family incorporates all subtasks required to take a structural/piping member from the material lay-down yard on a site, through its final preparation stages and into its final position in the facility. The following section describes the steps one should take to create a value stream map. 6.8 Building a Value Stream Map The conventional method used to create value stream maps was developed specifically for the manufacturing industry. This conventional approach was used as a point of departure for developing a construction value stream mapping process. Figure 6.4 shows how a value stream for a structural steel erection process would be depicted using the conventional manufacturing method (Tapping, Luyster et al. 2003). This method cannot accommodate the multiple variables of a construction value stream. To overcome this difficulty, the conventional manufacturing value stream map has been modified to match construction industry characteristics. The typical manufacturing approach identifies all elements in the value stream. The arrows represent the flow of material and/or information through the production line. The logic progresses from the left to right, with each box representing a different stage in the production 77 line. For this study, the production line has been limited to the highly repetitive process of erecting bar joists. The flow in this map begins when steel members are ordered from the manufacturer. They are then shipped to the jobsite and stored onsite before erection. Finally, the map shows the individual substages that each crew member participates in during the erection of the bar joist members. A construction value stream cannot be represented like a manufacturing value stream. The major difference between the two systems occurs at the project level when material reaches the site. Material on the construction site does not flow past the worker, rather the worker must move (flow) to the material. In manufacturing, the “work station,” where a transformation of the final product occurs, never has to move in the “ideal” manufacturing line, yet for a construction process the “work station” continually moves around the jobsite as work progress. Furthermore, the conventional model on Figure 6.4 assumes a linear relationship between its elements, creating what is known as a FIFO process. In construction, several tasks in an activity can and/or must occur simultaneously. The simple manufacturing value stream model does not easily allow for parallel activities. 6.9 New Approach to Value Stream Mapping This report focused on defining “process family” activities and measuring the time that it took to transform materials (post-fabrication), beginning with procurement, through the construction phase and ending with the turnover of the facility to the owner in its finished state. Figure 6.5 shows the new value stream map in its entirety for the structural steel erection process. Modifications have been introduced in this new map to better represent processes dealing with multiple variables (inputs or outputs), as well as multiple activities occurring at the same time in each stage. The new format separates the conventional manufacturing value stream into three levels. Level One includes the main stages material must go through for installation. Both information flow and material movement are represented at this level in the value stream. The second level expands the main stages in Level One to show substages that occur simultaneously to complete each main stage. Level Two is useful for showing the multiple phases a material element might go through during a process-specific value stream. Furthermore, it allows one to see where most of the time in a stage is spent and can even highlight steps in a process that need special attention. Finally, Level Three details the various crew members associated with each substage displayed in Level Two. The contribution of each crew member to the VA, NVAR and NVA categories are displayed for each substage in these tables. The following sections describe the details of this value stream map, beginning with Level Three, and explain how each sublevel relates to the one above. 6.9.1 Level Three Level Three, shown in greater detail on Figure 6.6, consists of three main elements. Area 1 (circled on the figure and labeled Area 1) includes a different table for every major task observed during the case study. Level Three details how much time each crew member contributed to the waste category. The specific wastes Level Three details are waiting, extra processing, transport, and movement. Furthermore, one can see if a crew was sized correctly to minimize waste caused by waiting. If a worker was waiting for the majority of all tasks, it would be beneficial to the crew’s productivity to redesign the tasks to eliminate the need for that member. In addition, if one observed that the majority of the work was carried out by one worker, then balancing the individual crew member responsibilities more evenly across the crew would be appropriate. The last table in Area 1 shows the weighted averages of the crew for all tasks. These weighted averages were combined to create VA, NVAR and NVA total values for the crew shown in Area 2. 78 Production Control Every 1-3 days Project Engineer 1 Order for all Bar Joist Project Feedback Project Superintendent Percent Complete Steel In Place awaiting welding Steel Supplier As Required 2 Shipments O Daily O OO Forklift Operator Fifo Forklift Operator Fifo Forklift Operator Fifo Forklift Operator Fifo Forklift Operator Staggard Ground Crewmen Staggard Left Connector Staggard Left Connector Staggard Right Connector Staggard Right Connector Staggard X-Bracing Connector Staggard X-Bracing Connector Staggard CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= CT= CO= Uptime Uptime Uptime Uptime Uptime Uptime Uptime Uptime Uptime Uptime Uptime Uptime Avail time Avail time Avail time Avail time Avail time Avail time Avail time Avail time Avail time Avail time Avail time Avail time Figure 6.4: Traditional Value Stream Map 79 Production Control Project Engineer Every 1-3 days Triggering Event Level One 2 phases of steel are ordered Percent Complete Project Superintendent Distribution of time from VSM Steel In Place awaiting welding Time Allocation Field NVA Time Project Feedback Steel Supplier NVAR Time 1 Daily As Required VA Time Work Time 5 cumulative days to deliver steel O OO 0 O 100 200 300 400 500 600 700 800 Manhours Stage One - Steel is offloaded in respective Bays Days Required Stage Two (A,B) - Steel Shake out Process Days 5 Required 2 Equipment involved: Forklifts Workers involved Crew WT VA ( 0%) NVAR (20%) NVA (80%) Stage Three - Steel Erection Process Days Required Equipment involved: 2 Forklifts 32 0 6.4 25.6 1 Workers involved Crew WT VA ( 0%) NVAR (0%) NVA (100%) 2 Inv 2 80 0 0 80 8 Stage Two (B) - Specific Bar Joists and girders are pulled from Days 2.5 Required Equipment involved: Stage Two (A) - Bar Joists bundles are shook out Days 2.5 Required Equipment involved: 1 Forklifts Workers involved Crew WT VA ( 0%) NVAR (0%) NVA (100%) Forklifts 2 40 0 0 40 Columns Crew Member Fork Lift Operator Level Three Ground Crewmen Left Connector X-Bracing Con. Right Connector Group Percentage 6% Waiting 14% 0% 40% 66% 53% 35% Waste Extra Transport Processing 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% NVA Sum 0% 61% Crew Member Fork Lift Operator Ground Crewmen Left Connector X-Bracing Con. Right Connector Group Percentage VA All Activities 0% 0% 16% 0% 16% 8% Waiting 66% 0% 12% 87% 24% 47% Waste Extra Transport Processing 0% 3% 0% 0% 44% 0% 0% 0% 60% 0% 0% 27% NVA = 77% Fork Lift Operator Ground Crewmen Left Connector X-Bracing Con. Right Connector Group Percentage VA All Activities 25% 0% 41% 57% 25% 31% Waiting 24% 40% 16% 11% 27% 34% Waste Extra Transport Processing 5% 12% 0% 4% 0% 0% 0% 0% 0% 0% 4% NVA = Steel Erection - Entire Process VA Crew Member All Waiting Activities Fork Lift Operator 17% 28% Ground Crewmen 0% 40% Left Connector 32% 17% X-Bracing Con. 38% 35% Right Connector 21% 29% Group Percentage 25% 28% 9% 60% 2 40 0 0 40 6% 2% Days Required Crane, 2 Skylift, Forklift Workers involved Crew WT= VA ( 8%) = NVAR (15%) = NVA (77%) = 5 78.7 4.7 26.8 47.2 1:19:32h:m:s 16% 0% 46% 34% 18% 26% 7% Total % VA + NVAR % 100% 0% 100% 100% 100% 70% 0% 13% 0% 29% 100% 34% 2:10:31h:m:s 39% In Proc. Ins. T.W.S.A 4% 0% 0% 0% 0% 52% 0% 0% 0% 0% 2% 24% NVAR 11% 0% 2% 1% 0% Material Pos. 6% 0% 27% 0% 0% 3% 9% Movement In Proc. Ins. T.W.S.A Total % VA + NVAR % 0% 0% 0% 0% 0% 14% 0% 0% 12% 0% 100% 0% 100% 100% 100% 21% 0% 42% 12% 16% 6% 101% 23% 0% 15% 7:57:07h:m:s NVAR 20% 0% 16% 30% 22% Material Pos. 4% 18% 27% 0% 24% 13% 1% Movement In Proc. Ins. T.W.S.A Total % VA + NVAR % 1% 0% 0% 0% 0% 8% 38% 0% 3% 2% 100% 100% 100% 100% 100% 39% 56% 68% 60% 51% 3% 99% 40% 5% 9% 11:27:10h:m:s NVAR In Proc. Ins. T.W.S.A Total % VA + NVAR % 2% 0% 0% 0% 0% 19% 38% 0% 5% 2% 100% 100% 100% 100% 100% 43% 56% 57% 42% 42% 9% 100% 46% 18% 0% 16% 23% 17% Material Pos. 5% 18% 25% 0% 19% 17% 13% 0% % of Total Time % of Total Time each steel element requires Movement Table represents the time distribution for each element viewed during the observation period Cumulative Number of Cycle time for each Time for members Cumulative Time for each Element element installed various observed categories 1:19:32 2 0:39:46 Total cumulative Time for two columns Total Cumulative Time for 2 Girders 2:10:31 2 1:05:15 Total Cumulative Time for 26 Bar Joists 7:57:07 26 0:18:21 Total Time 11:27:10 12% 19% 69% Average VA Percentage Average NVAR Percentage 25% 22% Average NVA Percentage 53% 5.8% 9.5% 2.7% Figure 6.5: Structure for a New Value Stream Map 80 3.2 Equipment involved: NVAR Material Pos. 7% 0% 0% 0% 29% Movement NVAR = Total Cumulative Time for Steel Erection Waste Extra Transport Processing 3% 8% 0% 4% 11% 0% 0% 0% 12% 0% Joist Girder is erected 2.0 2 Workers involved Crew WT= VA ( 6%) = NVAR (34%) = NVA (60%) = NVAR = Total Cumulative Time Spent on Bar Joists Bar Joists Crew Member Crane, Forklift NVAR Sum Total Cumulative Time Spent on Girders Girders Summary of all stages in Level 1 Working Days 24 days Woking Time 792 man hours VA Total 161 man hours NVA Total 95 man hours NVAR Total 536 man hours 10 Equipment involved: Total Cumulative Time Spent on Columns VA All Activities 7% 0% 13% 0% 0% 2 to 4 Columns Erected Days Required 1 Workers involved Crew WT VA ( 0%) NVAR (0%) NVA (0%) **Graph shows the amount of man-hours atributed to each work category. VA time + NVAR time + NVA time = Work Time 17.0 680 161 89 430 Inventory Days 10 Note: These Steps occur at the same time. Columns and Girders are erected first but cannot be continued until the inner supporting bar joist have been erected. Inv 2 Level Two Equipment involved: Forklift, crane, skylifts Workers involved Crew WT= VA ( 7%, 13%) NVAR (28%, 21%) NVA (100%) 4 5 129.2 10.3 19.4 99.4 Bar Joist installed along with x-bracing members Days Required 11.8 Equipment involved: Crane, Forklift, 2 4 Skylifts Workers involved Crew 5 WT= 472 VA ( 31%) = 146 NVAR (9%) = 42 NVA (60%) = 283 Columns Crew Member Level Three Fork Lift Operator Ground Crewmen Left Connector X-Bracing Con. Right Connector Group Percentage VA All Activities 7% 0% 13% 0% 0% 6% Waiting 14% 0% 40% 66% 53% 35% NVA Sum Girders Crew Member Fork Lift Operator Ground Crewmen Left Connector X-Bracing Con. Right Connector Group Percentage VA All Activities 0% 0% 16% 0% 16% 8% Waiting 66% 0% 12% 87% 24% 47% NVA = Bar Joists Crew Member Fork Lift Operator Ground Crewmen Left Connector X-Bracing Con. Right Connector Group Percentage VA All Activities 25% 0% 41% 57% 25% 31% Steel Erection - Entire Process VA Crew Member All Activities Fork Lift Operator 17% Ground Crewmen 0% 32% Left Connector 38% X-Bracing Con. 21% Right Connector Group Percentage 25% Waiting 24% 40% 16% 11% 27% 34% NVA = Waiting 28% 40% 17% 35% 29% 28% Total Cumulative Time Spent on Columns Waste Extra Transport Movement Processing 0% 0% 16% 0% 0% 0% 0% 0% 46% 0% 0% 34% 0% 0% 18% 1:19:32 h:m:s NVAR Material Pos. 7% 0% 0% 0% 29% 70% 0% 13% 0% 29% 100% 34% 2:10:31 h:m:s 39% 52% 0% 0% 0% 0% 0% 0% 26% 7% 2% NVAR Sum Total Cumulative Time Spent on Girders Waste NVAR Extra Material Transport Movement In Proc. Ins. Processing Pos. 0% 3% 11% 6% 0% 0% 0% 0% 0% 0% 44% 0% 2% 27% 0% 0% 0% 1% 0% 0% 60% 0% 0% 0% 0% 24% 0% 3% 9% 0% NVAR = 15% Total Cumulative Time Spent on Bar Joists Waste NVAR Material Extra Movement In Proc. Ins. Transport Pos. Processing 5% 12% 20% 4% 1% 0% 4% 0% 18% 0% 0% 0% 16% 27% 0% 0% 0% 30% 0% 0% 0% 0% 22% 24% 0% Total % VA + NVAR % 14% 0% 0% 12% 0% 100% 0% 100% 100% 100% 21% 0% 42% 12% 16% 6% 101% 23% T.W.S.A 77% 5% 13% 1% NVAR = 9% Total Cumulative Time for Steel Erection Waste NVAR Extra Material Transport Movement In Proc. Ins. Processing Pos. 3% 8% 18% 5% 2% 0% 4% 0% 18% 0% 11% 0% 16% 25% 0% 0% 0% 23% 0% 0% 12% 0% 17% 19% 0% 4% 9% 7:57:07 h:m:s Total % VA + NVAR % 8% 38% 0% 3% 2% 100% 100% 100% 100% 100% 39% 56% 68% 60% 51% 3% 99% 40% T.W.S.A 60% 6% 2% 17% 13% 0% Table represents the time distribution for each element viewed during the observation period Cumulative Number of Cycle time for each % of Total Time for Cumulative Time for each Element members element installed Time various observed categories Total cumulative Time for two columns Total Cumulative Time for 2 Girders Total Cumulative Time for 26 Bar Joists Total Time 100% 0% 100% 100% 100% 4% 0% Area 1 0% 61% 27% VA + NVAR % T.W.S.A 0% 0% Total % In Proc. Ins. 1:19:32 2:10:31 7:57:07 11:27:10 2 2 26 0:39:46 1:05:15 0:18:21 12% 19% 69% Area 3 Figure 6.6: Level Three Data 81 % of Total Time each steel element requires 5.8% 9.5% 2.7% 11:27:10 h:m:s Total % VA + NVAR % 19% 38% 0% 5% 2% 100% 100% 100% 100% 100% 43% 56% 57% 42% 42% 9% 100% 46% T.W.S.A Average VA Percentage Average NVAR Percentage 25% 22% Average NVA Percentage 53% Area 2 Finally, Area 3 breaks down the proportion of time each substage requires in the main stage. This distribution is necessary when determining the weighted percentage of total time spent on each substage in Level Two. From this table, the cycle times can be computed for each building component erected. For example, the average cycle time to erect a bar joist from the ground into its final position was calculated by taking the time required to install one element (18 minutes, 21 seconds) and dividing it by the total number of crew members (5). The cycle time for one bar joist was determined to be three minutes, 40 seconds. 6.9.2 Level Two Level Two, shown on Figure 6.7, details the substages that occur in one of the main stages of Level One. Again, this level is necessary when multiple tasks or crews in one process occur at the same time. The hatched arrows represent the order of occurrence for each substage. The number of substages shown in Level Two will be dependent on the level of detail that an observation team makes while collecting data. For example, on Figure 6.7, three distinct activities are highlighted: column, girder and bar joist erection. However, in a second structural steel case study, the column and pod/spandrel beam combination (girder section) is represented as one substage. This simplifies the data analysis, but limits the information that can be obtained if these two substages (i.e., crew balance information) are separated. Note: These Steps occur at the same time. Columns and Girders are erected first but cannot be continued until the inner supporting bar joist have been erected. Stage Two (A) - Bar Joists bundles are shook out Level Two Days Required 2.5 Days Required Workers involved Crew WT VA ( 0%) NVAR (0%) NVA (100%) 2.5 1 Forklifts 2 40 0 0 40 Workers involved Crew WT VA ( 0%) NVAR (0%) NVA (0%) Joist Girder is erected 2 Columns Erected per bay Days Required Equipment involved: Equipment involved: Forklifts Stage Two (B) - Specific Bar Joists and girders are pulled from bundles to be placed in each bay 2.0 Days Required Crane, Forklift 2 40 0 0 40 2 Workers involved Crew WT= VA ( 6%) = NVAR (34%) = NVA (60%) = 3.2 Equipment involved: Crane, 2 Skylift, Forklift Workers involved Crew WT= VA ( 8%) = NVAR (15%) = NVA (77%) = Equipment involved: 1 5 78.7 4.7 26.8 47.2 Bar Joist installed along with xbracing members Days Required 4 5 129.2 10.3 19.4 99.4 Equipment involved: Crane, Forklift, 2 Skylifts Workers involved Crew WT= VA ( 31%) = NVAR (9%) = NVA (60%) = 11.8 4 5 472 146 42 283 Figure 6.7: Level Two Figure 6.8 shows one substage box from the steel erection process. The box is developed into two main sections. Section 1 lists the substage process requirements: days required, equipment involved and workers involved. Section 2 details the work distribution categories: work, VA, NVAR and NVA time. Section 1 Joist Girder is Erected Days Required 3.2 Equipment involved: Crane, 2 Skylift, Forklift Workers involved Crew WT= VA ( 8%) = NVAR (15%) = NVA (77%) = 4 Section 2 5 129.2 10.3 19.4 99.4 Figure 6.8: Typical Setup for a Substage Box in the Value Stream 82 To further illustrate the calculation process for this level the main stage from Level One must be introduced, along with its required substages in Level Two (Figure 6.9) and the steps in the calculation demonstrated. Stage Three - Steel Erection Process Days Required 17.0 Equipment involved: Forklift, crane, 2 to 4 skylifts Workers involved Crew 5 WT= 680 VA ( 7%, 13%) 161 NVAR (28%, 21%) 89 NVA (100%) 430 Columns Erected Days Required 2.0 Days Required Equipment involved: Crane, Forklift Workers involved Crew WT= VA ( 6%) = NVAR (34%) = NVA (60%) = Bar Joist installed along with xbracing members Joist Girder is erected 3.2 Days Required Equipment involved: Crane, 2 Skylift, Forklift 2 5 78.7 4.7 26.8 47.2 Workers involved Crew WT= VA ( 8%) = NVAR (15%) = NVA (77%) = 11.8 Equipment involved: Crane, Forklift, 2 Skylifts 4 5 129.2 10.3 19.4 99.4 Workers involved Crew WT= VA ( 31%) = NVAR (9%) = NVA (60%) = 4 5 472 146 42 283 Figure 6.9: Main Stage from Level One Along with Required Substages from Level Two 6.9.2.1 Step 1. The “days required” value is calculated using the weighted percentage of time spent on a substage. This number is found in Area 3 of Level Three, “% of total time” (19 percent). This calculation (Equation 6.1) focuses on the days required for girder installation. Multiply 19 percent by the total number of days required value (17) found in the main stage of Level One. Equation 6.1: 17 days x 19% = 3.23 (cumulative days to erect every girder) The result is 3.23 days. This value indicates that if the crew focused only on the girder erection process, it would take them a cumulative time period of 3.23 days to erect every girder. Using this value, the values found in Section 2 of the substage box can be calculated. The equipment category shows which resources are used for each substage. These values can be used to aid in balancing the total equipment on a job with the crew to create the best possible flow in the work process. To complete Section 1, the total number of workers required for the substage was entered. If the same crew was used for each substage, then this value would remain the same. However, if two separate crews were involved with the process, these values may not remain the same between the substage processes. 83 6.9.2.2 Step 2. Section 2 breaks down the work distribution values for that substage. Work time (WT) is defined as the total workable man-hours a crew can contribute assuming that they work five days a week, eight hours a day. The calculation for WT is as follows: Equation 6.2: WT = 8 hours per (day per crew member) x 5 crewmembers x 3.23 days = 129.2 total available person-hours for the girder erection process 6.9.2.3 Step 3. This WT value must be used as the basis for the remaining categories of VA, NVAR and NVA. The percentages shown next to VA, NVAR and NVA were developed from the Level Three tables.3 For each substage, a table was developed with values for NVA and NVAR. These values were obtained by totaling the subcategory values that contributed to each of the main work distribution categories (e.g., NVAR = Mat Pos. Value + In-Process Ins. Value + TWSA Value = 15 percent for girders). The number of man-hours that were contributed to each work category can now be calculated. Equation 6.3: NVAR Time = 15% x 129.2 man-hours = 19.4 man-hours This step was repeated using the VA and NVA percentages to find their respective values. 6.9.2.4 Step 4. These steps were repeated for each substage until all the categories were complete. Once completed, the main stage box found on Level One totaled all of the values found in Section 2 of each substage box, resulting in a weighted final value for each stage in Level One. Equation 6.4: WT (Stage Three) = WT Substage 1 + WT Substage 2 +WT Substage 3 WT (Stage Three) = 78.7 + 129.2 + 472 WT (Stage Three) = 680 available man-hours Levels Two and Three are structured to give the contractor (subcontractor) a detailed view of material movement while onsite, as well as the crew actions required for the installation/erection of the material into final position. Levels Two and Three allow the contractor to better control wastes associated with waiting, transport, extra processing and movement. At the project level, the contractor can use Levels Two and Three to balance crews and the respective tasks required from each crew member. A balanced crew allows material and processes to reach their ideal flow. The main reason for the separation of these levels is to give the contractor the ability to track material movement on two separate time scales. The time required to design, procure and deliver material to the jobsite (Level One) can be substantially larger than the time required to install or erect the material after it is onsite (Levels Two and Three). 6.9.3 Level One Level One of the new value stream (Figure 6.10) is nearly identical to the conventional method. The solid black arrows represent information paths. Information arrows depict the “routes” information must currently travel to allow certain activities to proceed. For example, information flows from the Project Engineer to the steel manufacturer in the form of a “notice to proceed.” 3 For those stages in which material was offloaded from the truck to the ground, a 20 percent standard value has been assigned for the NVAR category. This is to accommodate for the NVAR actions of setting up hoist lines, safety lines or whatever else was required to safely move the material to the ground. 84 The manufacturer then produces the required steel elements and ships them to the jobsite. Once the steel (or any other material) is onsite, it is tracked in stages until it has been installed or erected into its final position. Information arrows also show how often communication is made between each party, as the “As Required” and “Daily” notations signify. The dark arrows leading from the last stage box “Steel in Place Awaiting Welding” to the “Production Control” box offer a means to track overproduction and defect wastes. Overproduction is represented in various forms depending on the hierarchy in the project’s management team. At the owner level, overproduction results from “over designing” the facility. At the project level, overproduction results from starting activities before they are required by the ideal “latest responsible start schedule.” Defect wastes are also represented in various forms depending on the hierarchy in the project’s management team. At the owner level, a defect may result from a facility not meeting its requirements because of underdesign or overdesign. At the project level, a defect can be quantified by determining the amount of time a follow-up crew is required to fix errors or unfinished work left by a previous crew. Using material as the “traceable” element, a stage or process box (as is shown on the bottom row of Figure 6.10) must be created to represent the material at that point in the process cycle. Stages occur each time the material is touched onsite, beginning with offloading the material into a laydown yard or staging area. Every time the material is moved or transformed (e.g., two structural elements are combined on the ground but then left there until the installation stage) prior to the actual installation process, it must be accounted for by a separate stage box. For the remaining stages that do not have field data to support the required information, the weighted average values found in Level Three, Area 2, must be used. Below the stage boxes is a staggered line with numbers placed between each stage box. These numbers represent the days of inventory that occur between each stage. The number is based on each shipment of material to the site. Inventory waste is quantified in Level One by totaling all inventory days. An inventory day starts when the material is received onsite, and ends when the last material piece in the shipment is moved to its next staging position or is installed. For example, if two shipments of steel are delivered to the site, each shipment is treated separately to identify the element in that shipment that remains on the ground the longest before being moved to its next stage in the process life cycle. The period of time between each phase gives a portion of the total inventory waste. The goal of tracking this waste is to reduce the inventory days to the ideal value of zero. At this point, material flows onto the site, proceeds through all necessary stages and is installed into its final position without being stored in various completion stages. Another way to shrink this value is to order smaller batches of material for each delivery. If the batch size is smaller, the time required to use up all the material in that one batch should decrease. Therefore, the piece of material remaining longest onsite is governed by the consumption rate of the crew erecting or installing those elements. In a financial sense, this means that the “front end” costs of material delivered to the site may not rise as fast as it would with the current practice of large batch material orders. Once all stages are complete, the finished process box can be shown. In this example, it is labeled “Steel in Place Awaiting Welding.” From the finished process box, the information arrows relate process-specific information such as overall feedback on productivity and percent complete for billing applications. 85 Production Control Project Engineer Every 1-3 days Triggering Event Project Feedback Level One Distribution of time from VSM 2 phases of steel are ordered Percent Complete Project Superintendent Time Alloc ation Field NVA Time Steel In Place awaiting welding NVAR Time 1 VA Time Steel Supplier Supplie Daily As Required 5 cumulative days to deliver steel O OO 0 Stage Two (A,B) - Steel Shake out Process Days 5 Required Equipment involved: 2 Equipment involved: Forklifts Workers involved Crew WT VA ( 0%) NVAR (20%) NVA (80%) 2 Forklifts 2 32 0 6.4 25.6 100 200 300 400 500 600 700 800 Manhours O Stage One - Steel is offloaded in respective Bays Days Required Work Time Inv 2 1 Workers involved Crew WT VA ( 0%) NVAR (0%) NVA (100%) 2 80 0 0 80 Inv 8 Figure 6.10: Level One 86 Stage Three - Steel Erection Process **Graph ** Graph shows the amount of man-hours atributed to each work category. VA time + NVAR time + NVA time = Work Days Required 17.0 Time Equipment involved: Forklift, crane, 2 to 4 Summary of all stages in Level 1 skylifts Workers involved Working Wor king Days 24 days Woking Time 792man 792 man hours Crew 5 WT= 680 VA Total 161man 161 man hours VA ( 7%, 13%) 161 NVA Total 95 man hours NVAR (28%, 21%) 89 NVAR Total 536man 536 man hours NVA (100%) 430 Inventory Days 10 Finally, the table to the right of the stages provides a “quick” summary for all of the stages in Level One. The bar chart above the table represents these values in a graphical display. In summary, Level One is structured to allow the contractor to directly control waste associated with overproduction (WIP) and inventory. Pure overproduction is rare on a construction site, since most construction is built for a specific order. However, any time that a contractor orders more material than is required during the project for a specific time period, it contributes to overproduction waste. Overproduction also accounts for WIP where an activity is left partially completed because insufficient materials were available or the activity was started before it was called for by the construction schedule. A late start schedule is ideal for limiting waste resulting from WIP. Inventory accounts for instances when the contractor orders more material than is required to complete the job, thus resulting in excess raw material at the completion of the project. A well developed value stream map at this level will also indirectly affect how much waiting occurs between construction activities, amount of transport required for materials around the jobsite and the proportion of extra processing (rework) required because of defective materials delivered onsite. 6.10 New Idea for Displaying the Construction Value Stream Figure 6.11 represents the work distribution life cycle graph for the first case study; it demonstrates how the work distribution values grow throughout the process (steel erection, piping installation, etc.). The chart’s main goal is to represent how each work category grows as work progresses through the various stages in Level One. The vertical line marks the point where work activities change from the delivery and preparation stages to the actual erection stage. There are five lines shown in the chart: the Cumulative Calendar Hours, Cumulative Workable Hours, Cumulative VA Hours, Cumulative NVAR Hours, and Cumulative NVA Hours. The data table for this graph is shown in Table 6.16. Each of the lines is based on an eight hour workday. For Cumulative Calendar Hours, the available work hours include weekends, where the Cumulative Workable Hours only account for a five day work week. The remaining Cumulative VA, NVAR and NVA Hours are calculated using the daily available work hours (shown in Column 11 of Table 6.16) as the multiplier. To create Figure 6.11, the following steps must be repeated. The first step is to create the value stream map. From the results of this map, the stages defined in Level One can be used to create a schedule of events, as shown in Table 6.16. In the first column of Table 6.16, the individual stages are defined. Column 2 lists the primary specific activity that is occurring for that day. The primary activity is determined by which task is absorbing the majority of the crew’s time for that day. Each row represents another day, moving left to right across the table. Column 3 details which day the activity occurred. For simplicity, all processes begin on a Monday. Column 4 shows a running total of calendar days the process takes to complete. Column 5 details the available hours possible for that day. This value is calculated using the total available crew for the day multiplied by eight hours. These values will be the same for the Column 11, Workable Hours, except for the rows representing weekends. Calendar hours include possible weekend hours. To calculate the possible work hours for each day of the weekend, the total available crew from the Friday before is used, and then the crew size is multiplied eight hours. Column 11 assumes zero workable hours for the weekend; however, this would change should a process require weekend shifts. The Cumulative Calendar Hours, Column 6, is a running total of all available calendar hours. The logic is similar for the Cumulative Workable Hours, Column 12, except that it is a running total of workable hours. 87 Work Distribution 1200 1000 800 Time (man hours) Cumulative Calendar Hours Cumulative Work Hours 600 400 Cumulative VA Hours Delivery and Preparation Process Erection Process is underway Cumulative NVAR Hrs. Cumulative NVA Hrs 200 Note: the percentages used to create this chart are the average values from the work distribution values found for the entire crew. 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Calendar Days Figure 6.11: Work Distribution Life Cycle Graph 88 Table 6.16: Work Distribution Lifecycle Data Stage Stage 1 Stage 1 Stage 2 Stage 2 Stage 2 Weekend Weekend Stage 2 Stage 2 Stage 3 Stage 3 Stage 3 Weekend Weekend Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Weekend Weekend Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Weekend Weekend Stage 3 Stage 3 Stage 3 Stage 3 Primary Activity for the Day Steel is moved from truck to ground Steel is moved from truck to ground Steel is shook out Steel is shook out Steel is shook out Weekend Weekend Steel is shook out Steel is shook out 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) Weekend Weekend 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) Weekend Weekend 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) Weekend Weekend 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) 1 crew erecting S.S. (Columns, Joist Girder and Bar Joists) Day Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Cumulative Cumulative Hours Calendar Calendar Workable Crew Workable Cumulative VA NVAR NVA VA Cumulative NVAR Cumulative NVA Cumulative Calendar Workable worked Days Hours Days available Hours Work Hours Percentage Percentage Percentage Hours VA Hours Hours NVAR Hrs. Hours NVA Hrs Hours days per day 1 16 16 1 1 2 8 16 16 0% 20% 80% 0 0 3.2 3.2 12.8 12.8 2 16 32 1 2 2 8 16 32 0% 20% 80% 0 0 3.2 6.4 12.8 25.6 3 16 48 1 3 2 8 16 48 0% 0% 100% 0 0 0 6.4 16 41.6 4 16 64 1 4 2 8 16 64 0% 0% 100% 0 0 0 6.4 16 57.6 5 16 80 1 5 2 8 16 80 0% 0% 100% 0 0 0 6.4 16 73.6 6 16 96 0 5 2 0 0 80 0% 0% 100% 0 0 0 6.4 0 73.6 7 16 112 0 5 2 0 0 80 0% 0% 100% 0 0 0 6.4 0 73.6 8 16 128 1 6 2 8 16 96 0% 0% 100% 0 0 0 6.4 16 89.6 9 16 144 1 7 2 8 16 112 0% 0% 100% 0 0 0 6.4 16 105.6 10 40 184 1 8 5 8 40 152 25% 22% 53% 10 10 8.8 15.2 21.2 126.8 11 40 224 1 9 5 8 40 192 25% 22% 53% 10 20 8.8 24 21.2 148 12 40 264 1 10 5 8 40 232 25% 22% 53% 10 30 8.8 32.8 21.2 169.2 13 40 304 0 10 5 0 0 232 25% 22% 53% 0 30 0 32.8 0 169.2 14 40 344 0 10 5 0 0 232 25% 22% 53% 0 30 0 32.8 0 169.2 15 40 384 1 11 5 8 40 272 25% 22% 53% 10 40 8.8 41.6 21.2 190.4 16 40 424 1 12 5 8 40 312 25% 22% 53% 10 50 8.8 50.4 21.2 211.6 17 40 464 1 13 5 8 40 352 25% 22% 53% 10 60 8.8 59.2 21.2 232.8 18 40 504 1 14 5 8 40 392 25% 22% 53% 10 70 8.8 68 21.2 254 19 40 544 1 15 5 8 40 432 25% 22% 53% 10 80 8.8 76.8 21.2 275.2 20 40 584 0 15 5 0 0 432 25% 22% 53% 0 80 0 76.8 0 275.2 21 40 624 0 15 5 0 0 432 25% 22% 53% 0 80 0 76.8 0 275.2 22 40 664 1 16 5 8 40 472 25% 22% 53% 10 90 8.8 85.6 21.2 296.4 23 40 704 1 17 5 8 40 512 25% 22% 53% 10 100 8.8 94.4 21.2 317.6 24 40 744 1 18 5 8 40 552 25% 22% 53% 10 110 8.8 103.2 21.2 338.8 25 40 784 1 19 5 8 40 592 25% 22% 53% 10 120 8.8 112 21.2 360 26 40 824 1 20 5 8 40 632 25% 22% 53% 10 130 8.8 120.8 21.2 381.2 27 40 864 0 20 5 0 0 632 25% 22% 53% 0 130 0 120.8 0 381.2 28 40 904 0 20 5 0 0 632 25% 22% 53% 0 130 0 120.8 0 381.2 29 40 944 1 21 5 8 40 672 25% 22% 53% 10 140 8.8 129.6 21.2 402.4 30 40 984 1 22 5 8 40 712 25% 22% 53% 10 150 8.8 138.4 21.2 423.6 31 40 1024 1 23 5 8 40 752 25% 22% 53% 10 160 8.8 147.2 21.2 444.8 32 40 1064 1 24 5 8 40 792 25% 22% 53% 10 170 8.8 156 21.2 466 89 Column 7, Workable Days, provides a base for the remaining calculations. If a 1 is shown in Column 7, then the row represents an actual workday; if the value is 0, then it represents a nonworking day (i.e., a weekend or a holiday). Column 8, Cumulative Workable Days is a running total of possible workdays. The columns representing percentage values for VA, NVAR and NVA obtain their values from the stage boxes in Level One of the value stream map. 6.11 How Do the Value Stream Maps Differ Between Processes? For both steel and piping processes, the same steps are required to develop a value stream map. The main difference between the structural steel value stream map and that of the piping process is that the steel production process requires several substages. The substages occur simultaneously in a “family” of processes to complete the entire erection cycle. In general, the steel production process represents the multiple inputs coming together to produce the single output of a completed structure. Multiple substages in Level Two of the value stream map are not evident for the piping production process because of the nonrepetitive elements being installed and the amount of time required to install each piping component. Structural steel elements typically consist of columns, girders and bar joists (trusses). 90 7.0 Results - Lean Principles for Construction 7.1 Assessing Lean Principles for Construction In this chapter, the findings from the literature, the interviews and the case studies are synthesized into a comprehensive assessment of the applicability of lean principles to the construction process. The following analysis is organized by major principle and then subprinciple. Each subprinciple was evaluated for its applicability to the construction industry and given a rating of 0, 25, 50, 75 or 100 percent. A principle that is clearly applicable to the construction industry (i.e., 100 percent) will be denoted with the following graphic: 100% In addition, an assessment was made regarding applicability of the principle by industry role; that is, whether it applies to the owner, contractor, subcontractor, designer or supplier. The roles of both designers and the material suppliers have been evaluated, although supply chain and design issues were excluded from the study. Accordingly, the judgments about designer and supplier roles are not based on the same degree of evidence as are the judgments about the roles of contractors and subcontractors. These judgments are represented as bar charts, as follows: Meeting Requirements of the Customer 100% 80% 60% 40% 20% 0% 50% 20% 10% 10% G EN H C (A R D es ig ne r Su pp li e rs or ra ct Su bc on t on tra ct or C O w ne r ) 10% Finally, each subprinciple was evaluated for applicability at all three levels of the organization; namely, crew, project management and enterprise. This evaluation is both an assessment of the level at which the principle is best applied and an appraisal of the organization level that has the primary responsibility for implementing the given principle. This judgment is represented as follows: Meeting Requirements of the Customer 100% 100% 100% 80% 80% 60% 40% 20% 0% Enterprise Level Project Level 91 Crew Level 7.1.1 Customer Focus Subprinciple No. 1.1: Meet the Requirements of the Customer. Customer focus is a key principle for lean construction. However, implementation of this principle differs significantly from implementation in other industries because of the intimate relationship between the customer (owner) and contractor in construction. Ironically, customer focus is a lean behavior of both the owner and the contracting team. Construction team focus on customer value must be a culture that is adhered to at the workface, at the project level and at the enterprise level. However, in construction, the contractor must also advise the customer about the appropriateness of his/her definition of value. The contractor may help the customer develop a better definition of value; i.e., defining what the customer needs, not what the customer wants. 100% Customer focus in construction is more intimate than in manufacturing; it is more dependent on the needs and behaviors of a specific customer. Manufacturing is like speculative building in construction. In speculative building, one tries to build the most desirable house for the least money, targeting a particular market demographic. In custom construction, customer focus is more of a give-and-take process; the customer can be asked to change its idea of value for the good of the project; e.g., if a design standard is changed, the project will save money and time. Customer focus is a matter of culture. “Lean” customer focus requires a culture different from “normal” construction culture. Lean customer focus is quite different from adherence to the principles of the contract. It is about an exchange of values, but not as currently defined by contract law, and it has little to do with the commercial terms of the contract. It has everything to do with the concept that if the customer receives value, both from the product and the process of construction, the customer will seek return business. The customer must be part of the value generation process. The customer must understand the importance of certain aspects of value. This is very different from the current value calculus for manufacturing. In fact, the singular customer-centric definition of value that is used in custom construction is an aspiration of the manufacturing sector; e.g., cars built exclusively to order. Meeting Requirements of the Customer Meeting Requirements of the Customer 100% 100% 100% 100% 80% 80% 80% 50% 60% 60% 40% 20% 10% 20% 10% 10% 40% 0% r s ig ne rs De pp Su tr a 0% bc on li e or ct ct ra nt Enterprise Level Su Co O wn er or 20% Project Level Crew Level Therefore, meeting the requirements of the customer is a principle that must be followed by both the contractor and the owner. It must be part of the culture of the contracting company at both the enterprise level and the project management level. Meeting the requirements of the customer is 92 also applicable at the worksite/crew level; however, the involvement at this level is more limited than it is at the higher levels. Subprinciple No. 1.2: Define Value from the Viewpoint of the Customer (Project). Perhaps this is the essence of lean: the unrelenting focus on delivering value to the 100% customer. However, for many companies involved in construction, there is a genuine problem of identifying the customer. From the point of view of the subcontractor on a commercial building project: is the customer the general contractor, the developer or the ultimate owner of the building? This ambiguity is the source of a considerable amount of suboptimization in the construction process. It is the challenge of the lean contractor to organize the delivery process in such a way that the intermediate views of value are reconciled with the customer’s view of value. Value Adding Is Defined from the View of the Project Value Adding Is Defined from the View of the Project 100% 100% 100% 100% 100% 100% 100% 100% 80% 80% 80% 60% 60% 40% 20% 0% 40% r s ig ne rs 0% De pp Su ct tr a 20% bc on li e or or ct ra nt Enterprise Level Su Co O wn er 0% Project Level Crew Level Defining value from the point of view of the ultimate customer is applicable to all major groups (contractor, subcontractor, designer and supplier) in construction. Likewise, every level in the project organization must be prepared to add value for the customer. The contractor must take the lead in establishing the value structure both for its own organization and for all of the other subordinate organizations involved with the project. Subprinciple No. 1.3: Use Flexible Resources and Adaptive Planning. Manufacturers employ many devices to allow them to respond to changing market conditions. Pull production schedules and flexible manufacturing systems are just two methods. Construction companies must also be able to respond rapidly to changing owner needs and marketplace conditions. It is common for changes in the market to cause industrial owners to change product mixes. Likewise, it is common for belatedly identified requirements to cause changes in project design. To define value from the customer’s viewpoint, the lean contractor must be able to respond to these changing needs by employing flexible resources and adaptive planning systems. However, contract arrangements between multiple project participants often inhibit the contractor’s ability to quickly change the scope or schedule of a project. Implied by this need for flexibility must be an understanding by the owner that flexibility comes at the price of disrupting established systems and standardized processes. 100% 93 Flexible Resources and Adaptive Planning 100% 100% 100% Flexible Resources and Adaptive Planning 100% 100% 100% 100% Enterprise Level Project Level Crew Level 100% 100% 80% 80% 60% 60% 40% 40% 20% 0% 0% r ne rs Su De pp s ig li e or ct tr a 0% Su Co bc on nt O ra wn ct er or 20% Flexible and responsive systems must be developed at every level in the project and by every member of the project team. The need for flexibility is a natural outgrowth of defining value from the customer’s viewpoint. Subprinciple No. 1.4: Cross Train Crew Members to Provide Production Flexibility. Manufacturing industries use cross training to provide work floor flexibility and to provide job enrichment. Cross training is already used in some open shop sectors of construction. Cross training to provide flexibility is more difficult in a union environment. However, cross training within a crew is very useful for improving the production management aspects of construction operations. One of the most vexing problems in construction production system design is sizing a crew to perform multiple operations (installing columns, girders and joists). Cross training can enable planners to distribute work and balance crews. 100% Cross Trained Crew Members Cross Trained Crew Members 100% 100% 100% 100% 100% 80% 80% 60% 60% 40% 20% 10% 0% 10% 50% 40% r ne rs s ig 0% De pp Su tr a 20% 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 0% Project Level Crew Level Cross training is applicable for both contractors and subcontractors. The field staff must take primary responsibility for cross training to the extent that it is permitted by labor agreements. Both designers and suppliers may have minor opportunities to help allow for cross training by understanding jurisdictional boundaries in union labor agreements. 94 Subprinciple No. 1.5: Use Target Costing and Value Engineering. Manufacturers use target costing as a device to focus their cost reduction efforts. In manufacturing, Toyota made famous the idea that “Profit = Market Price Costs.” That is, the market determines the price, and profit can only be increased by reducing costs. This idea is similar to the competitive bidding culture prevalent in construction. In fact, construction’s intense reliance on low-bid pricing shifts the focus away from customer quality to price. The lean contractor can rely on target costs as a device for reducing costs but not to the disadvantage of quality. Value engineering is the method commonly used in construction both to reduce costs and to maintain quality and functionality. 100% Target Costs - Value Engineering Target Costs - Value Engineering 100% 100% 100% 100% 100% 100% 100% 100% 80% 80% 60% 60% 40% 20% 50% 40% 0% O wn er Co n tr a ct or S c ub on c tr a to r Su li pp s er D ig es ne 20% r 0% 0% Enterprise Level Project Level Crew Level Target costing (appropriately applied) and value engineering can be practiced by every member of the project team. The main responsibility lies with the enterprise level. 7.1.2 Culture/People Subprinciple No. 2.1: Provide Training at Every Level. The need for training in developing a lean organization and a lean culture is undisputed. Lean thinking requires modification of long-standing ideas about every aspect of the construction process. All of the “lean” companies encountered in the study emphasized the need for training. Some lean contractors also train their suppliers, subcontractors and craftspersons. 100% Training 100% Training 100% 100% 100% 100% 100% 100% 100% Enterprise Level Project Level Crew Level 100% 75% 80% 80% 60% 60% 40% 20% 40% r De s ig ne rs pp Su tr a 20% 0% Su bc on li e or ct ct ra nt Co O wn er or 0% 95 All parties to the process must support the central role of training for implementing lean principles. Even owners must participate in training so that they understand the potential of lean construction. Subprinciple No. 2.2: Encourage Employee Empowerment. One of the most difficult challenges of becoming lean is the task of empowering employees at every level. Empowerment is important for implementing improvements and suggestion programs and for having all workers feel personal responsibility for process improvement and quality. Employee empowerment in manufacturing found its most profound application in the idea that any employee could “stop the line” if he or she noticed a quality problem. The transient nature of the construction workforce and the temporary nature of the construction team make employee empowerment difficult. 100% Employee Empowerment 100% Employee Empowerment 100% 100% 100% 100% 100% 100% 80% 80% 60% 40% 25% 20% 60% 25% 0% 40% r De s ig ne rs pp Su ct tr a 20% 0% Su bc on li e or or ct ra nt Co O wn er 0% Enterprise Level Project Level Crew Level Owners, designers and suppliers have little involvement in employee empowerment. Contractors and subcontractors, on the other hand, must institute programs that motivate employees to take responsibility for quality and process improvement. Some lean contractors use “gain sharing” as a device to engage the construction workforce in process improvement. All levels of the organization have significant accountability for ensuring that employees feel empowered to act to improve project outcomes. Subprinciple No. 2.3: Ensure Management Commitment. Creating a lean culture is perhaps the best precursor of superior lean performance. Management commitment to the lean ideal is fundamental to lean culture. Lean behavior that is an everyday work ethic of managers, employees and strategic partners is best ensured by unrelenting commitment to lean ideals. Toyota has been working on developing the Toyota Production System for decades. Lean construction will require a commitment of similar duration. Several lean contractors reported that they have stayed committed to lean principles even though they have not realized improved profits. Rather, many have cited the need for continued application and extensions of lean concepts beyond those already adopted to realize the full promise of a lean system. In the absence of improved profits, many lean contractors cite benefits other than improved profits, such as improved quality and better employee morale. 100% 96 Management Commitment 100% 100% 100% Management Commitment 100% 100% 100% 100% 100% 100% Enterprise Level Project Level Crew Level 100% 80% 80% 60% 40% 60% 20% 40% r ne rs Su De pp s ig li e or tr a 20% 0% Su bc Co on nt O ra ct ct wn or er 0% Owner, contractor and subcontractors must all embrace the lean ideal for a long period of time. The use of strategic partnerships between contractor and subcontractor make it easier to sustain lean behaviors from job to job. All levels of management from the CEO down to the first-line crew supervisor must be committed to lean practices. Subprinciple No. 2.4: Work with Subcontractors and Suppliers. Much of the benefit of lean systems derives from the partnerships that develop between supplier and manufacturer. However, in construction, it is difficult to develop long-term relationships between contractor and subcontractor or contractor and supplier because of the location variability customary to construction production. Another problem not generally experienced by the lean manufacturer is the lack of control that contractors have over their supply chain. A large manufacturer (e.g., Toyota, Ford) buys such a large quantity of goods (e.g., tires or windshields) that it has significant influence on the terms of the transaction. In contrast, any single contractor represents only a small fraction of any supplier’s sales; therefore, the contractor has less influence over the supplier. Also, the materials that must be procured are typically specified by the design, and the contractor often has no opportunity to work with a preferred supplier. Thus, the form of project delivery system (design-build, designbid-build) has an impact on possible supplier-contractor relationships. Despite all of these obstacles, it is very important that suppliers and contractors/subcontractors understand and maintain lean behavior in construction. Long-standing relationships between suppliers and subcontractors will facilitate adoption of lean ideas. Developing long-standing relationships will require basic changes in construction routines. 100% Subcontractor and Supplier Interactions 100% 100% Subcontractor and Supplier Interactions 100% 100% 100% 100% 100% 80% 75% 80% 60% 40% 60% 25% 20% 0% 40% r De s ig ne rs pp Su ct tr a 20% 0% bc on li e or or ct ra nt Enterprise Level Su Co O wn er 0% 97 Project Level Crew Level Owners have little involvement in maintaining the contractor/subcontractor or contractor/supplier relationship other than to provide a delivery system that enables these relationships. Clearly, the main responsibility for establishing and maintaining strategic relationships is with the contractor. Contractor personnel at every level have a role to play in maintaining effective working relationships with suppliers and subcontractors. 7.1.3 Workplace Organization/Standardization Subprinciple No. 3.1: Encourage Workplace Organization and Use 5S’s. The main imperative of manufacturing production is to eliminate waste. One technique manufacturers use is to make it obvious when something is wrong with the tools, materials or processes of production. One method that manufacturers use is to make everyday aspects of the process routine: tools and materials are organized in the same way, work areas are kept neat and clean. This is a more difficult undertaking in construction because the “factory” is always changing configuration. However, strict adherence to a policy that requires cleanliness, organization and orderly storage and movement plans is a necessary step toward lean production. Gang boxes, tools and consumable supplies should be stocked and organized so that no time is spent searching for or retrieving common tools or materials. Some lean contractors develop and distribute weekly plans that detail traffic, lay-down and work area assignments. 100% 5s's 100% 5s's 100% 100% 100% 100% 80% 80% 60% 60% 20% 0% 0% 0% 40% r 40% 20% 50% ne rs s ig De pp Su tr a 0% 0% bc on li e or ct ct ra nt Enterprise Level Su Co O wn er or 0% Project Level Crew Level Jobsite cleanliness, organization and logistics are the primary responsibility of the contractor and the subcontractors. Field management must set the requirement for jobsite organization, but it must be implemented by the work crews and first-line supervisors. Subprinciple No. 3.2: Implement Error-Proofing Devices. Error-proofing (poke yoke) devices are commonplace in manufacturing. The simplest manufacturing operations are guided by jigs and fixtures. Error-proofing is another way that manufacturing firms standardize the production process. Error-proofing devices lessen the demands on the work, improve throughput and enhance quality. Error-proofing devices are used to a small extent in construction (directional piece marks, welding fixtures, etc.); however, much more could be done. Principally, error proofing is the responsibility of the individual worker and post-construction quality inspections. The attitude in manufacturing is to 100% 98 “build quality in”; the attitude in construction is often to “inspect quality in.” The significant attribute that enables error proofing is repetition. Repetition allows the production process to move toward production work and away from craftwork. Poke Yoke Devices Poke Yoke Devices 100% 100% 100% 100% 100% 100% 100% 80% 80% 60% 60% 40% 20% 50% 40% 0% 0% r ne rs Su De pp s ig li e or ct tr a 0% 0% Enterprise Level Su Co bc on nt O ra wn ct er or 20% Project Level Crew Level The responsibility for error proofing rests with all contributors to the construction production process. Designers have opportunities to use standard design elements and features that allow error proofing. Suppliers can be alert for opportunities to mark or modify products to facilitate error proofing. Contractors and subcontractors alike can standardize processes. Subprinciple No. 3.3: Provide Visual Management Devices. Visual management is the practice of using graphical and visual devices to help manage and make routine the production processes. Visual management tools in manufacturing cover an array of applications from production control through quality control. Some lean contractors use visual management devices to relate cost, quality and schedule status. Others use visual devices to regulate traffic, lay-down and work zone assignments. Visual management devices are another means to reduce the load on the workforce and communicate goals and production metrics. 100% Visual Management Visual Management 100% 100% 100% 100% 100% 100% 80% 80% 60% 60% 40% 20% 0% 0% 50% 40% 0% 0% r De s ig ne rs pp Su ct tr a 0% bc on li e or or ct ra nt Enterprise Level Su Co O wn er 20% Project Level Crew Level Visual management is the prime responsibility of field personnel. Both the contractor and subcontractor can employ visual management tools. The impetus for visual management comes 99 from the enterprise level in the organization; the implementation is the responsibility of the project site management and first-line supervisors. Subprinciple No. 3.4: Create Defined Work Processes. Defined work processes are the essence of manufacturing methods. Much of the production planning and scheduling that is needed to produce a manufactured item is determined by the production line. Work tasks occur in a defined sequence, with fixed timing and with standardized techniques. Manufacturers have the advantage of recouping the cost of developing defined work processes from the sale of thousands of product items. Construction is not as fortunate; only in residential building are there multiple replications of the same project. However, most individual work processes in construction are subject to repetition. Common work processes (erecting steel, fabricating formwork, prefabricating pipe spools) will benefit from standard work practices, tools and techniques. Construction has a heritage of craft work. Typically, work methods and tools are the province of individual workers and work crews. Manufacturing employs production engineers to define work processes and required equipment. Lean contractors will need to move toward a more rigorous definition of common work tasks. 100% Defined Work Processes 100% Defined Work Process 100% 100% 100% Project Level Crew Level 100% 100% 80% 80% 60% 40% 25% 20% 60% 25% 50% 40% 0% r De s ig ne rs pp Su tr a 20% 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 0% As with most construction production principles, the foremost responsibility for creating standard work processes rests with the contractor and subcontractor. Material suppliers and designers have the prospect of enabling defined work processes through more standardization in design and materials. Development of standard work processes occurs in the field with field management and the crew. The enterprise level has the responsibility for ensuring that the standards are applied across all projects. Reapplication of standardized processes will allow for the amortization of the cost of development of lean work processes. Subprinciple No. 3.5: Create Logistic, Material Movement and Storage Plans. Manufacturing production is defined by the configuration of the factory plant and equipment. When a lean contractor defines storage, movement and logistics plans, a temporary but standard production infrastructure is created. As with most production standardization techniques, it is relatively costly to maintain and communicate standardized site logistics. However, as the value stream studies show, excessive time is spent in construction moving, shifting and double handling materials. The lean contractor 100% 100 believes that time and money spent in organizing the worksite and creating production infrastructure is repaid by reducing waste in direct production activities. Logistics Material Movement Plan 100% Logistics Material Movement Plan 100% 100% 100% 100% 80% 80% 60% 40% 60% 25% 20% 0% 40% 0% r De s ig ne rs pp Su tr a 25% 20% 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 0% 50% Project Level Crew Level The main responsibility for creating logistics and material movement plans rests at the jobsite. Both the contractor and subcontractors can contribute, but it is the prime contractor that has overall responsibility for creating the plans. Prime contractors and subcontractors share implementation responsibilities. The executive level of the company is responsible for disseminating the practice across all projects. Site management creates and implements the principle, and site workers must follow the plan. 7.1.4 Waste Elimination (Aspect 1: Process Optimization) Subprinciple No. 4.1: Minimize Double Handling and Worker and Equipment Movement. Both construction and manufacturing operations handle large quantities of material frequently. In a manufacturing environment, material handling operations are predictable and governed by the configuration and speed of the assembly line. In construction, material handling requirements are much more variable. Not only must workers and machines move variously sized and different numbers of items, they must also move them to diverse locations with variable frequency. Thus, the lean construction company must spend more time organizing and planning logistical efforts. Maximum use of Ready for Installation (RFI) tags and bar codes can aid this process. One lean contractor’s efforts to arrange for steel deliveries in order of erection were stymied when multiple steel fabrication companies were employed (e.g., one firm for columns and girders, another for bar joists). 100% Part of the challenge is to coordinate the material handling and storage needs among the various subcontractors. Individual subcontractors attempt to reduce delays by ordering and storing large quantities of materials near their workplaces (i.e., just-in-case material delivery). However, it is evident that the more materials stored by subcontractors, the higher the incidence of multiple handling of stored materials to eliminate space conflicts. This illustrates an important point: for lean construction to be successful, contractors must find ways to eliminate subcontractors’ attempts to optimize their individual goals (profit, productivity, production) at the expense of the whole production system. Lean is by its nature an optimization of the whole system. 101 To eliminate storage conflicts, one can closely control access to work locations, require intermediate storage in remote locations or use just-in-time (JIT) delivery of material. Controlling and scheduling subcontractor access to work areas tends toward a batch and queue approach to scheduling. Reducing material storage conflicts at the worksite by requiring intermediate remote storage causes double (or triple) handling, which is by definition a form of waste. Relying on JIT deliveries, given the activities of a construction site, is (in the current climate) very risky. The research for this study found no perfect (i.e., similar to manufacturing performance) solution for storage conflicts in construction. The best solution appears to be a tightly defined batch and queue management of work locations, coupled with small batch (almost JIT) deliveries of material. Minimized Double Handling Minimized Double Handling 100% 100% 100% 100% 100% 80% 80% 60% 60% 40% 20% 0% 0% 50% 40% 0% 0% r ne s ig De li e rs pp r 0% 0% Enterprise Level Su bc on Su c to tr a ac n tr Co Ow ne to r r 20% Project Level Crew Level Just because it is difficult to achieve manufacturing style material handling performance does not mean that construction cannot benefit from attention to material handling performance. During the value stream studies, multiple incidences were observed where coordination with suppliers or preplanning for staging materials would have significantly reduced double handling. Contractors and subcontractors must expend more effort in planning and managing the material handling aspects of the production system if they are to improve lean performance. The responsibility for these actions rests with field management and the individual crews. Subprinciple No. 4.2: Balance Crews, Synchronize Flows. The flow principle, as described in Chapter 2, is central to lean production. Flow permits high throughput and fast cycle times. In a (relatively) steady-state manufacturing environment, it is easier 75% to establish balanced operations than it is in construction. In construction, flow is viewed at several levels. First, there is flow within a crew. Crews often perform different tasks (e.g., erect columns, erect girders, erect joists); it is difficult to internally balance the crew so that it is “right-sized” for each individual task. Second, there is flow between crews. In value stream Case Study No. 3, crews were organized to synchronously follow one another; the first erected columns and beams, the second the joists. It is possible to maintain synchronous flow between crews on repetitive projects (highrise buildings, multi-unit housing). However, it is very difficult to maintain tight coupling between crews when work tasks are variable (e.g., process piping). Loose coupling between crews can be achieved by creating buffers between consecutive crews; however, buffers are discouraged in “pure” lean production schemes. Third, there is flow among subcontractors, which is very much like flow between crews with the added complication of contractual 102 scheduling commitments. All flow/crew balancing tasks are made easier if the individual work task times are reliable. Reliable flow is also facilitated through production/look-ahead planning. Synchronize Flow 100% Synchronize Flow 100% 100% 100% 100% 80% 75% 80% 60% 60% 40% 20% 0% 0% 40% 0% 0% r ne li e rs s ig Su De pp r c to tr a 0% 0% bc Co on n tr Ow ac ne to r r 20% Su Enterprise Level Project Level Crew Level Creating flow and synchronized operations is clearly a field responsibility. However, production planners cannot rely on the configuration of the assembly line to determine sequence. Also, production planners must adapt flow to the changing configuration of the product itself. Therefore, communication of production goals and responsibility is mostly maintained through strict production planning between contractor and subcontractor and between individual crews. Subprinciple No. 4.3: Remove Material Constraints, Use Kitting, Reduce Input Variation. Kitting is a technique that is common in construction, especially in the process industries. It has no precise analogue in manufacturing, but it has its roots in manufacturing planning. Removing material constraints is important for reducing waste (i.e., waiting time) for individual crews. In tightly coupled production sequences, material constraints for an upstream crew ripple downstream to succeeding crews. Kitting can be accomplished either by the contractor’s own forces assigned to support crews or in conjunction with material suppliers. Kitting for a task may encompass materials, consumables, design data, equipment and even space. 100% Kitting, Material Constraints, and Minimizing Input Variation 100% Kitting, Material Constraints, and Minimizing Input Variation 100% 100% 100% 100% 80% 80% 60% 40% 60% 25% 20% 0% 0% 50% 40% 0% r ne s ig De li e rs Su 0% 0% bc on pp r c to tr a ac n tr Enterprise Level Su Co Ow ne to r r 20% 103 Project Level Crew Level Kitting is primarily a field activity carried out by project management personnel working with suppliers. In some jurisdictions, kitting is accomplished by dedicated crews established to support production work. Subprinciple No. 4.4: Reduce Difficult Setup/ Changeover. Single Minute Exchange of Dies (SMED) is a manufacturing technique that focuses on quickly modifying the production facility for manufacturing different products. By allowing fast changeover between alternative products, manufacturers can produce products in smaller quantity runs without concern for long plant changeover-related downtime. Changeover from one task to the next is routine in construction; it takes the form of moving from work location to work location and from one task to another. 50% Reduce Difficult Ssetup/Changeover Reduce Difficult Setup/Changeover 100% 100% 100% 100% 100% 80% 80% 60% 60% 40% 20% 0% 0% 50% 40% 0% 0% r s ig ne rs De pp Su ct tr a 0% 0% Enterprise Level Project Level Crew Level Su bc on li e or or ct ra nt Co O wn er 20% Minimizing changeover is a field production planning task. The need for changeover can be reduced by producing larger batches of one product before switching to the next (e.g., erecting multiple bays of steel before returning to erect the bar joists). Using larger batch sizes increases work in progress (WIP), however, which is contrary to lean practices. Subprinciple No. 4.5: Reduce Scrap. Scrap reduction is a principle that is commonly used in construction. Contractors historically have managed formwork, concrete and 100% other scrap producing activities. Repetitive tasks offer increased savings from scrap reduction. One lean contractor reduced piping purchases by 5 percent by ordering exact lengths for repetitive floor-to-floor runs in a high-rise project. Aggressively managing scrap requires confidence in design data and tolerance control, because some construction material waste is caused by allowances for out-of-tolerance construction and design inaccuracy. Many supply firms are instituting innovative site warehousing programs that inevitably reduce waste by reducing overstock and restocking charges. 104 Reduce Scrap Reduce Scrap 100% 100% 100% 100% Project Level Crew Level 100% 100% 75% 80% 80% 50% 60% 60% 40% 20% 40% 0% r ne rs Su De pp s ig li e or ct tr a 25% 20% 0% Enterprise Level Su Co bc on nt O ra wn ct er or 0% Scrap reduction efforts require cooperation between contractor, subcontractor, material supplier and designer. Planning for scrap reduction occurs at the enterprise and project level. Proactive management of materials is the responsibility of the crews and field management staff. Subprinciple No. 4.6: Use Total Productive Maintenance. Total productive maintenance (TPM) is a manufacturing technique for using “off-shift” labor to proactively maintain production machinery and infrastructure. Construction normally uses TPM to maintain large equipment during downtimes or at “off-shift” times. Unplanned equipment downtime can idle an entire crew. During one of the site visits, a crane operator was discharged for failing to fuel the crane before starting work. His failure to fuel the machine caused the entire crew and several other pieces of construction equipment to experience nonproductive time. This is another example where minor, standardized practices can lead to large production system improvements. 100% Total Productive Maintenance 100% Total Productive Maintenance 100% 100% 100% Project Level Crew Level 100% 100% 80% 80% 60% 60% 20% 0% 0% 0% 40% r 40% 20% ne rs s ig De pp Su tr a 0% 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 0% TPM activities are administered by the field staff. All field personnel have opportunities to organize rational maintenance activities for site tools and equipment. 105 7.1.5 Waste Elimination (Aspect 2: Supply Chain) Subprinciple No. 4.7: Institute Just in Time (JIT) Delivery. JIT delivery of materials in manufacturing is a well developed practice. In large-scale manufacturing (e.g., automobiles) major suppliers co-locate fabrication facilities with the main 75% production plant to allow rapid response to production needs. JIT in manufacturing relies on the relative steady-state nature of production. Construction production is not (generally) steady-state; therefore, more planning is required to establish JIT delivery of most construction materials. Despite the difficulty of instituting JIT, it would have a number of benefits for the construction industry. Later delivery of materials would reduce the carrying costs for the contractor or owner; site congestion; the need for double handling; and the opportunity for theft, damage or loss. However, JIT presupposes a close working relationship with suppliers, which is a more difficult problem in construction than it is in manufacturing because of the relatively smaller scale of individual contractor purchases. Also, contractors move about the country (and world), and often preferred suppliers are too distant to be used economically. There is also the issue of incompatibility of construction needs and cost-effective manufacturing sequences. JIT delivery for a steel contractor is ideally sequenced in erection order. Cost-effective manufacturing for a (non-lean) steel fabricator would be by member size. Thus, even when materials are delivered to the site in the erection order, they are often produced and stored offsite in the manufacturer’s preferred fabrication sequence. For this reason, one of the advantages of JIT, that of reducing buffers, is often not achieved in construction. Buffers are simply moved upstream from the building site to the fabricator’s storage area. JIT 100% JIT 100% 100% 100% 100% 100% 100% 80% 80% 60% 60% 40% 20% 0% 50% 40% 0% 0% r ne s ig De li e rs Su 0% bc on pp r c to tr a ac n tr Enterprise Level Su Co Ow ne to r r 20% Project Level Crew Level JIT is a high-gain, high-risk strategy in construction. In general, the construction sequence is variable; production is not steady state and is subject to substantial uncertainty. However, contractors and subcontractors alike can produce substantial benefits by developing strategic relationships with preferred suppliers. Owners that purchase long lead-time items must coordinate with the contractor to appropriately schedule delivery of owner-furnished items. 7.1.6 Waste Elimination (Aspect 3: Production Scheduling) 100% Subprinciple No. 4.8: Use Production Planning and Detailed Crew Instructions, Predictable Task Times. The heritage of construction is in guilds and craft 106 production. The craftsman controlled the means and methods of construction. Indeed, even today, many workers are expected to arrive at the jobsite with their own tools of the trade. Manufacturing has a different tradition. Tools and methods of production are provided by and determined by the manufacturer. Accordingly, it is customary in manufacturing to employ production engineers to help define and design production processes. Manufacturing engineers determine sequence, materials, fixtures, jigs and tools for the work. They determine storage location and processing times. In construction (with a few exceptions), all of the functions of the production engineer are entrusted to the individual craftsperson or the first-line supervisor (foreman). The disparity between the production engineering approach in manufacturing and the lack of a production engineering tradition in construction can be explained, in part, by the highly repetitive nature of most manufacturing tasks. Manufacturers can afford to spend effort on optimizing the production system, knowing that they will reap benefits on every unit of production. In construction, the means of production are often entrusted to the worker simply because each production unit is somewhat unique (e.g., craftwork). However, craft workers are not typically trained in the methods of production engineering. Often craft workers perform work in the manner that they were first taught. There is not a practice of thinking about the most efficient way to sequence the work, stage the materials or the myriad other details of a fully formed production engineering approach. Production Planning, Detailed Crew Instructions Production Planning, Detailed Crew Instructions 100% 100% 100% 100% Project Level Crew Level 100% 100% 80% 80% 60% 40% 0% 0% 0% 40% r 60% 20% 20% De s ig ne rs pp Su ct tr a 25% 0% bc on li e or or ct ra nt Enterprise Level Su Co O wn er 0% Manufacturers can afford to spend a thousand dollars to save a dime on every unit produced. Constructors do not have this luxury. However, given the cost of labor, and more specifically, given the degree of waste prevalent in construction operations, contractors should do more to focus on more effective production methods. This focus should not be to find faster ways to weld or to erect steel. That is, the initial focus should not be on the value adding (VA) activities, but rather on the non-value adding (NVA) activities. By planning worker sequences, material staging and equipment allocation, production engineers can do much to reduce the 50 percent of the time that is consumed by NVA activities. Contractors and subcontractors at every level of the organization should start to move away from the craft approach to construction production toward a more controlled and defined production attitude. 100% Subprinciple No. 4.9: Implement Last Planner, Reliable Production Scheduling, Short Interval Schedules. Every lean contractor interviewed used some method to organize, coordinate and plan the production aspects of their work. Many contractors in this study used the last planner system developed by the Lean Construction Institute. 107 Others started using the last planner system and then developed other systems that were more suitable for their individual production systems. The use of a formalized production planning system is a keystone of becoming a lean constructor. Production planning is not the same as project planning. Project planning seeks to coordinate delivery of material, design and other resources in accordance with a sequence of construction to support the required end date of the project. Production planning is also not production engineering (refer to Subprinciple 4.8, Subsection 7.1.6), which seeks to organize individual works tasks. Production planning is systematizing the way in which various crews and subcontractors support the overall production. To a large extent, production planning is obtaining commitments from individual crews and subcontractors to perform a given work task by a specified time. These production commitments are essential for the production planning of the downstream contractors. Part of the last planner method is to track the proportion of the commitments that were kept by crews and subcontractors. Metrics are used to measure the degree to which parties kept commitments, thereby allowing for more reliable project schedules. Last Planner/Reliable Scheduling etc. 100% Last Planner/Reliable Scheduling etc. 100% 100% 100% 100% Project Level Crew Level 100% 80% 80% 50% 60% 40% 60% 25% 20% 40% 0% r De s ig ne rs pp Su tr a 25% 20% 0% bc on li e or ct ct ra nt Enterprise Level Su Co O wn er or 0% Production planning is just one more method used to gain control of the production process. Production planning involves all of the contractors and subcontractors involved in the production process. Designers and suppliers are involved in production planning to the extent to which commitments for delivery of design or materials impede construction progress. Production planning is primarily a field responsibility. Subprinciple No. 4.10: Practice the Last Responsible Moment, Pull Scheduling. Pull scheduling is used by manufacturers to help with production scheduling and to reduce WIP. The notion of pull (as opposed to push) scheduling is that a production item is pulled into the system only as it is 75% needed. Specifically, demand by a downstream production task indicates the need for production by an upstream task. Using pull scheduling reduces WIP and increases throughput. Conceptually, pull scheduling is very like “late start” scheduling in the Critical Path Method (CPM). One lean contractor refers to construction pull scheduling as “scheduling at the last responsible moment.” Since WIP is generated later in the construction process, the main benefit of pull scheduling is a reduction in early cash requirements by the owner and contractors and less site congestion. The main disadvantage is that pull scheduling uses project float. In the current uncontrolled production environment, trading float for a reduction in WIP is a risky choice. 108 Last Responsible Moment/Pull Scheduling Last Responsible Moment/Pull Scheduling 100% 100% 100% 100% 100% Project Level Crew Level 100% 100% 80% 80% 50% 60% 60% 40% 20% 40% 0% 0% 25% r ne rs Su De pp s ig li e or ct tr a 0% bc Co on nt O ra wn ct er or 20% Su Enterprise Level Pull scheduling is a field responsibility. Given the risky nature of a full pull schedule, the concept must receive complete support from the executive level of the company. Subprinciple No. 4.11: Use Small Batch Sizes, Minimize WIP. Manufacturers use small batch sizes (or, better yet, continuous flow manufacturing) to boost plant throughput, reduce manufacturing cycle time and decrease WIP. WIP reduction is a matter of considerable importance for the manufacturer. Given the steady-state nature of manufacturing, WIP creates a continuous inventory (partially completed goods) 75% for the manufacturer that must be stored and financed until the product is completed and sold. The nature of WIP is somewhat different in construction. Most construction is accomplished using progress payments. From the point of view of the typical contractor, WIP is actually production that can be “sold” at the end of the period. Also, WIP might represent additional “factory space” for the contractor. For example, for a high-rise building, each floor of the building frame that is completed represents additional areas in which the contractors can work. However, from the point of view of the owner, WIP is still inventory that will not produce revenue until it is put into service. The dual nature of WIP in construction highlights another area of potential conflict and suboptimization in construction. Minimize WIP - Small Batch Size 100% 100% 75% 20% 40% r De s ig ne rs li e pp Su 0% bc on Crew Level 25% 20% Enterprise Level Su Co nt tr a ra ct ct or or 0% er Project Level 60% 25% 40% wn 100% 80% 60% O 100% 100% 100% 75% 80% Minimize WIP - Small Batch Size 109 Unlike most production decisions, WIP decisions directly affect cash flow and production progress. Therefore, the owner of a lean jobsite must be involved with implementing WIP reduction programs. This can be accomplished through changes to contract language and strategy. Operationally, however, WIP reduction and use of small batch sizes are decisions implemented by the field organizations. Subprinciple No. 4.12: Use Decoupling Linkages, Understand Buffer Size and Location. Buffers are devices often used in construction to provide a cushion between upstream crews and those downstream. In true lean production, 75% buffers are discouraged because they increase WIP and cycle time. Given the complexity and uncertainty of the construction production process, limited use of buffers can help production scheduling on the project. For example, on a high-rise building, a contractor may choose to provide for one empty floor between the mechanical, electrical, and plumbing subcontractor and the following electrical subcontractor. However, buffers as they are currently used in construction are a source of considerable waste. Large material buffers on the construction site increase project time by requiring earlier design and procurement actions to support early delivery of material. Buffers cause excess material handling and increased carrying costs. Decoupling Buffers, Buffer Size and Location Decoupling Buffers, Buffer Size and Location 100% 100% 100% Project Level Crew Level 100% 100% 100% 80% 80% 60% 40% 25% 20% 60% 25% 40% 0% 0% 25% r s ig ne rs De Su pp li e r c to tr a bc on 0% Enterprise Level Su Co nt O ra wn c to r er 20% The use of buffers is an action taken in the field in coordination with production scheduling. Buffer size can be reduced through appropriate cooperation with material suppliers (supply chain management) and by appropriate release of design information. 7.1.7 Waste Elimination (Aspect 4: Product Optimization) Subprinciple No. 4.13: Reduce the Parts Count, Use Standardized Parts. Although lean design is specifically excluded from this study, there are some obvious design actions that will facilitate lean production. One is to use standard design details and standard sized materials. At one case study site, a simple frame distribution center, the steel design called for more than 40 different sizes of bar joists. Each of the 40 shapes had to be designed, manufactured, shipped and inventoried. If the design engineer had reduced the number of shapes to 20, considerable savings would have accrued along the value stream. No doubt, the engineer was producing an “optimized” design that reduced the weight of steel. However, from a production system view, a 100% 110 slight increase in material costs could easily be recovered by economies in procurement, material handling and erection. At another site, long bar joists needed to be reinforced in the field by welding bridging that ran between the joists at set intervals. The bridging was lifted to the level of the joists and threaded through the web, positioned, measured and welded in place. This activity consumed as much labor and equipment as did erecting the bar joist. Again, a design solution that used a heavier joist that did not require bridging would have substantially saved money in the field. Standardized Parts Standardized Parts 100% 100% 100% 100% 100% 100% 80% 80% 60% 40% 25% 60% 25% 20% 40% 0% 25% 25% Su r De s ig ne rs pp li e or tr a 0% bc Co on nt O ra ct ct wn or er 20% Su Enterprise Level Project Level Crew Level Using standardized parts and reduced parts count is a cooperative activity between the designer and contractor or subcontractor. The owner can influence the use of this principle by the choice of a project delivery system. Design-build projects have a better chance of optimizing design to allow lean construction. Subprinciple No. 4.14: Use Pre-Assembly and Prefabrication. Pre-assembly and prefabrication are not new concepts for construction. However, any action that removes labor from the relatively uncontrolled field environment to the more controlled shop environment promises to 100% improve quality and reduce labor costs. Manufacturers have increasingly used more pre-assembly from their vendors. For all of their apparent benefits, pre-assembly and prefabrication are rarely used in construction. For example, at two of the process piping jobsites that were visited, large bore process piping was field fabricated onsite rather than using a fabrication plant. Pre-assembly and Prefabrication Pre-assembly and Prefabrication 100% 100% 100% 100% 100% 100% 100% 80% 80% 60% 40% 60% 25% 20% 40% r De s ig ne rs pp Su tr a 25% 20% 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 0% 50% 111 Project Level Crew Level Adopting more pre-assembly and prefabrication is a choice that must involve the owner. Generally, prefabrication will require a higher early case flow. Pre-assembly and prefabrication decisions require close cooperation between designer, supplier and construction. Subprinciple No. 4.15: Use Preproduction Engineering and Constructability Analysis. Constructability analysis or preproduction engineering is not a new idea in construction. The ability to use constructability analysis is limited by the project delivery system chosen for the job. The value generation process used in construction often encourages suboptimization by the various players in the process. Cooperative project delivery arrangements allow for more effective use of 100% constructability methods. Preproduction Engineering/Constructibility Preproduction Engineering/Constructibility 100% 100% 100% 100% 100% 100% 100% 80% 80% 50% 60% 60% 40% 20% 50% 40% r ne rs s ig 0% De pp Su tr a 20% 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 0% Project Level Crew Level As with prefabrication, effective constructability processes require close cooperation between designer, supplier and construction. Often the crew is one of the best sources for good constructability ideas. 7.1.8 Continuous Improvement and Built-In Quality Subprinciple No. 5.1: Prepare for Organizational Learning and Root Cause Analysis. Stability in manufacturing is a tremendous advantage to a company that is attempting organizational learning. Manufacturers will devote substantial time toward understanding why a defect occurred or why a process failed. They do so against the backdrop of a steady-state manufacturing setting in which suppliers, machinery and personnel change more slowly than in the construction domain. In contrast to manufacturing, construction organizations are (by nature) temporary project organizations. Not only do personnel change from project to project but the companies (subcontractor, suppliers) that make up the projects change. The dynamic nature of the construction organization makes it more difficult, and all the more important, to create a learning organization. Also, construction operations can be dispersed across regions, the country, or even the world, making it difficult to sustain a corporate culture of improvement. Yet, continuous improvement and the relentless elimination of waste are linchpins of the lean process. 100% 112 Organizational Learning Organizational Learning 100% 100% 100% 100% 100% 75% 80% 75% 75% 80% 60% 60% 40% 20% 50% 40% 0% 0% r s ig De pp Su bc on 0% Enterprise Level Su Co ne rs li e or ct tr a ra nt O wn ct er or 20% Project Level Crew Level The impetus for creating a learning organization must originate at the highest levels of the contractor organization. It is the responsibility of the field office to execute organizational practices. To the extent possible, subcontractor, designer and supplier strategic partners should be included in learning and root cause analysis. Subprinciple No. 5.2: Develop and Use Metrics to Measure Performance, Use Stretch Targets. It has been said, “If you are not measuring your results, you are just practicing.” Lean manufacturers develop and use a wide array of metrics to measure performance. Quality, cost, financial and other aspects of company performance are represented by metrics. Those metrics are then used to establish goals (stretch targets) for process improvement. Manufacturers use sophisticated quality performance and quality metrics that are made possible by the stable manufacturing domain. Manufacturers also use many metrics that are unusual in construction. Manufacturers use measures of throughput, cycle time and Takt time to examine the state of the manufacturing system. It was Einstein who said, “Not every thing that counts is countable, not everything that is counted counts.” Yet, if an organization understands the purpose, even an imperfect metric will be useful. The metric that was called VA work in the value stream studies is subject to criticism because it narrowly defines the nature of work included in the definition. Yet, if it is understood that the purpose of the metric is to highlight the number of tasks that fall outside of this definition, its rigorous nature is more defendable. 100% Initially, as construction goes lean, some of the standard “lean metrics” used in manufacturing may not be significant metrics for construction. As the value stream analysis showed, the amount of waste (NVA) activities that exists in the typical construction process should encourage development of metrics to help identify and eliminate waste. After production operations become more efficient, the industry can start to focus on more traditional metrics that measure the effectiveness of the VA processes. Metrics Metrics 100% 100% 100% 100% 100% 80% 80% 100% 60% 60% 40% 25% 25% 25% 20% 40% 0% 25% r s ig ne rs De pp Su tr a 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 20% 113 Project Level Crew Level Since metrics are cross-company measures, the leadership for their institution must come from the enterprise level. The owner also has a role to play by allowing project performance to be measured by nonstandard means. It is a “leap of faith” to establish a new performance measurement standard and the owner’s support in these endeavors is crucial. Field management’s role is to implement the metrics and field crews must be trained in their importance. Subprinciple No. 5.3: Create a Standard Response to Defects. A standard response to a defect is almost a subset of creating an environment for organizational learning. A standard procedure allows quick response and systematic understanding of the cause of the defect. In the value stream studies, multiple instances of rework were observed. In each instance, the goal was to rectify the fault quickly and efficiently. However, in only one instance was a process seen that tried to understand the cause of the fault and ensure that it would not occur on future jobs. 100% Defect Response Plan Defect Response Plan 100% 100% 100% 100% 100% 75% 80% 80% 60% 40% 25% 20% 60% 25% 50% 40% 0% r De s ig ne er s Su p tr a 20% 0% Enterprise Level Su bc on pli or ct ct ra nt Co O wn er or 0% Project Level Crew Level A standard response plan is created by corporate management to reduce future defects by alerting other projects to the nature of the problem and its causes. A standard response plan should provide field management with a reliable way of correcting the defect. Defects in subcontractor’s work must be managed in the same careful manner as those in prime contractor work. Feedback to designers and suppliers is a key ingredient of a standard response plan. Subprinciple No. 5.4: Encourage Employees to Develop a Sense of Responsibility for Quality. “Stop the line,” a maxim that originated with the Toyota Production System, relates to the practice that allows all assembly workers to stop the entire production line if they observe a defective product at their work stations. This maxim implies that is unacceptable to send defective work to the next work station. It is every worker’s responsibility to proactively manage quality. The lean ideal is to build quality in, not to inspect quality in. For the most part, the construction industry continues to inspect quality in. Rework and punchlist items continue to consume a large fraction of labor costs. The nature of the industry, including the prevalence of temporary workers, union hiring rules and the interdependency of work tasks, makes it difficult to establish this philosophy in the construction production environment. 100% 114 Employee Responsibility for Correcting Defects Employee Responsibility for Correcting Defects 100% 100% 100% 100% Project Level Crew Level 100% 100% 80% 80% 60% 60% 20% 0% 0% 0% 40% r 40% 20% De s ig ne rs pp Su tr a 25% 0% Enterprise Level Su bc on li e or ct ct ra nt Co O wn er or 0% Developing the concept of personal responsibility for quality is the province of field management. Some lean contractors maintain a cadre of key field people to act as guides and mentors for craft workers who are hired temporarily for a project. 7.2 An Information-Based Perspective on Lean Principles The preceding analysis of the lean principles that apply to construction is based on the experience of the research team and the early adopters who participated in the study. Chapter 3.0 catalogued some of the fundamental differences between manufacturing and construction. This section reexamines these differences to validate the analysis of which lean principles best apply to construction. Some of the differences between manufacturing production and construction production (e.g., the role of the owner in design of the product) arise from the dissimilar nature of the respective businesses. However, a review of Chapter 3.0 suggests that the majority of the differences between manufacturing and construction resolve themselves into one factor: the stability of the manufacturing environment compared to the construction production environment. Application of lean principles to construction must account for the inescapable fact that manufacturing takes place in a steady-state environment (established design, stable machinery and plant, long-term supplier relationships, long-standing employees, etc.), and construction production is the converse. The absence of steady-state operating conditions introduces variability and uncertainty into the production process. Therefore, one way to identify which principles are appropriate for construction is to evaluate whether the principle serves to make the production system more stable or, alternatively, whether the principle serves to reduce the negative impacts of nonreducible uncertainty. Because of the repetition and certainty in the manufacturing environment, manufacturers can use assembly lines and production systems to guide products with high efficiency through the production cycle. Construction processes are repetitive only at the task level, and the production facilities are rarely static. Instead of using assembly lines and other production systems to govern production flow, sequence and throughput, construction often uses an increased level of planning. As a consequence, lean construction production involves handling an increased amount of information. Construction production is already dependent on up-to-date project information. Information that describes progress by upstream contractors, changes to design and status of material deliveries is central to the effective operation of construction production systems. Construction managers already use face-to-face meetings, emails, memos and telephone conversations to gather and disseminate such information. From the perspective of construction 115 managers, the desirability of applying any given lean principle is partially contingent on whether the principle increases the current information handling requirements of the construction team. Those principles that create conditions that are closer to manufacturing (i.e., more stability) will ultimately reduce information processing demands and will be attractive principles to apply. Those principles that increase the information processing demands without a concomitant increase in system stability will be attractive only to the extent that the increased information workload improves quality, reduces costs or increases the reliability of the schedule. A perspective on how organizations react to increased information processing needs is suggested by the work of Galbraith (1974). Galbraith’s work starts from the proposition that greater task uncertainty requires an organization to process more information because it is difficult to plan and schedule the execution of uncertain tasks. Therefore, during actual execution of the task, the need for more knowledge and information processing leads to changes in schedules and resource assignments. Since organizations are limited in their ability to process information, they institute strategies for dealing with this limited ability. Generally, organizations deal with the increased information processing demands by using the following strategies: • Increasing coordination through rules and procedures. • Creating strong hierarchies to deal with the exceptions that uncertainty creates. • Establishing clear targets and goals that allow lower organizational levels increased discretion and responsibility. If these organizational strategies are inadequate to deal with the uncertainty, organizations may react in one of the following ways: • Decreasing the informational processing needs by creating “slack resources,” e.g., contingency funds, contingency time or capacity and material buffers. • Increasing the organization’s ability to deal with information through the creation of information processing systems (meetings, reports, computer systems) or by creation of “lateral” relationships (coordinators, teams, task forces) that cut across hierarchies. To help confirm the experientially based conclusions about which principles are applicable to construction, each principle was reevaluated using the following three conditions: 1. The principle, without the need for increased planning or information handling, reduces the uncertainty in the production environment. 2. The principle requires increased planning and information handling that will lead to a more stable production environment and reduce the negative effects of the instability. 3. The principle requires increased planning and information handling that will reduce the negative effects of the uncertain production environment, e.g., high costs, poor quality, unreliable execution. 116 Tables 7.1 through 7.3 group the subprinciples into one of these three categories and describe the information handling mechanism used to apply the principle. 7.3 Applying Lean Principles to Construction An appropriate, practical set of lean principles for the construction industry would be invaluable for companies searching for ways to improve productivity and quality and reduce costs. The principles established in this chapter can be used as a guide toward creating a construction organization that moves closer to the ideal of lean production. This process must involve the entire organization and address all aspects of lean production: customer focus, culture and people, workplace organization, waste elimination and continuous improvement. Chapter 8.0 discusses the application of lean principles in construction organizations. 117 Table 7.1: Principles that Reduce Uncertainty in the Production Environment without Increased Planning or Information Handling Principle Subprinciple Mechanism Customer Focus Cross Train Crew Members Create Slack Resources Use Flexible Resources Create Slack Resources Ensure Management Commitment Establish Clear Target and Goals that Allow Increased Employee Discretion Encourage Employee Empowerment Establish Clear Target and Goals that Allow Increased Employee Discretion Use 5S’s Establish Clear Target and Goals that Allow Increased Employee Discretion Provide Visual Management Establish Clear Target and Goals that Allow Increased Employee Discretion Develop and Use Metrics Establish Clear Target and Goals that Allow Increased Employee Discretion Create Standard Response to Defects Establish Clear Target and Goals that Allow Increased Employee Discretion Encourage Employees to Develop Responsibility for Quality Establish Clear Target and Goals that Allow Increased Employee Discretion Culture and People Workplace Organization and Standardization Continuous Improvement and Built-In Quality 118 Table 7.2: Principles that Require Added Planning or Information Handling but Reduce Uncertainty in the Production Environment Principle Subprinciple Mechanism Customer Focus Meet Customer Requirements Establish Lateral Relationships Establish Lateral Relationships Culture and People Define Value from Viewpoint of Customer Provide Training Workplace Organization and Standardization Work with Suppliers and Subcontractors Implement Error-Proofing Devices Create Defined Work Processes Waste Elimination Create Logistic Material Movement and Storage Plans Minimize Double Handling and Worker and Equipment Movement Remove Material Constraints Understand Buffer Size and Location Reduce Difficult Setup/Changeover Use Total Productive Maintenance Use Production Planning and Detailed Crew Instructions Implement Last Planner, Reliable Production Scheduling Use Standard Parts Continuous Improvement and Built-In Quality Use Pre-assembly and Prefabrication Use Preproduction Engineering and Constructability Analysis Prepare for Organizational Learning 119 Increase Coordination Using Rules and Procedures Create Strong Hierarchies Increase Coordination with Rules and Procedures Increase Coordination with Rules and Procedures Increase Coordination with Rules and Procedures Increase Coordination with Rules and Procedures Establish Lateral Relationships Create Slack Resources Increase Coordination with Rules and Procedures Increase Coordination with Rules and Procedures Increase Coordination with Rules and Procedures Establish Lateral Relationships and Clear Target and Goals that Allow Increased Employee Discretion Increase Coordination with Rules and Procedures Increase Coordination with Rules and Procedures Increase Coordination with Rules and Procedures Increase Information Processing Ability Using Information Systems Table 7.3: Principles that Require Added Planning or Information Handling but Reduce the Negative Effects of Instability in Production Principle Subprinciple Mechanism Customer Focus Use Target Costs and Value Engineering Increase Information Processing Ability Using Information Systems Waste Elimination Balance Crews and Synchronize Flows (Opposite of Creating Slack Resources) Reduce Scrap (Opposite of Creating Slack Resources) Use JIT Scheduling (Opposite of Creating Slack Resources) Practice Pull Scheduling (Opposite of Creating Slack Resources) Use Small Batch Sizes and Minimize WIP (Opposite of Creating Slack Resources) 120 8.0 Conclusions and Recommendations 8.1 Reasons to Apply Lean Principles to Construction The project team reviewed the combined findings of research into lean construction and determined that there is an extraordinary opportunity for individual companies to develop worldclass production systems by carefully applying lean principles to the construction process. Although the project delivery process was not studied in detail, there is clearly a coupled opportunity to apply lean thinking to the supply chain and design and contracting processes to create what the Lean Construction Institute calls a Lean Project Delivery Process. Investigations of the construction production process indicated that construction activities are typically only 10 percent value adding (VA). If a contractor could improve the VA portion to just 15 or 20 percent, the lean contractor would have a significant competitive advantage. However, when one looks at construction operations with “lean eyes,” little standardization or preplanning is evident. In fact, the construction process includes little that manufacturing engineers would recognize as production planning or production engineering. Often, the design of construction operations is consigned to the individual crews. While the crew members often have the skill and experience to design specific construction operations, typically they do not have the training or the mind-set that will lead to a lean operation. Some will contend that construction is too different from manufacturing to expect “manufacturing-like” lean results. While acknowledging that manufacturing and construction operate in different environments and that lean in construction will be more difficult than lean in manufacturing, interviews with early adopters of lean construction principles cited increased quality, increased safety, better schedule performance and decreased costs as some of the benefits of starting the lean journey. 8.2 Path Forward to Becoming Lean Observations of early adopters of lean principles suggest that there is no one prescribed way to become lean. Each early adopter in this study used a different starting point, and each progressed along the path at a different rate. However, based on the totality of the research, the evidence suggests that an engineering, procurement and construction (EPC) company that wants to start a lean process should start with its field operations. 8.2.1 Identify Waste in Field Operations There is historical precedent for starting with production activities; Toyota started its lean work by concentrating on its shop floor. Starting lean activities with field operations also has a good rational basis because value is added (from the customer’s viewpoint) during the construction process. Finally, the strict value definition that was used for the field studies1 provides a lens through which one can start to identify waste in the field processes. 1 “…any activity that changes the shape, form, or function of materials or information to meet customer’s needs” (Walbridge-Aldinger 2000). 121 8.2.2 Drive Out the Waste After a type of waste has been identified, the next step is to drive it out. A given type of waste (e.g., rework) might have one or several different causes. To drive out the waste, the root cause must be understood. If the root cause is worker training, design errors or tolerance errors from an upstream crew, appropriate steps should be taken to eliminate or reduce the waste on future work. The process of driving out waste leads naturally to many of the other lean principles such as constructability reviews and Just-In-Time (JIT) scheduling. The EPC contractor should start by concentrating on the non-value adding (NVA) (i.e., pure waste) activities. With construction averaging 50 percent NVA activities, there are ample opportunities to reduce these wastes before turning to the non-value adding but required (NVAR) or VA activities. 8.2.3 Standardize the Workplace After lean practices have been identified, they should be formalized as company standards. Developing standard practices for construction processes reduces the information burden on the crew members. One early adopter contractor that was studied created identical gang boxes so that the crews knew what tools were commonly available and where to find them. 8.2.4 Develop a Lean Culture Depending upon how much of the value stream a company controls (i.e., construction only or EPC), the processes should be formalized within the organization and with strategic partners, subcontractors and suppliers. One early contractor spent considerable effort training its entire staff and most of its supplier and subcontractor staffs. Other lean early adopters trained key partners on a project-by-project basis. A key difference between manufacturing and construction is the rapidity with which construction partnerships and alliances change with time and location. 8.2.5 Get the Client Involved with the Lean Transformation After a company has experience with lean principles, its clients should be educated about the benefits, costs and risks of going lean. The company should start defining value from the customer’s viewpoint. In some cases, the impetus for going lean has actually originated with a client organization that had experience with the successes of lean manufacturing. 8.2.6 Continuously Improve With all of the above steps under way, a company can start to improve on improvements. Everyone involved with the project should begin to understand their responsibility for reducing waste and improving quality. Continuous improvement requires that lean practices and lean culture be the common basis for doing business. 8.3 Barriers to Developing a Lean Company There are several barriers to “going lean” in construction that are not found in a manufacturing environment. The following subsections review the most significant barriers to lean construction. 122 8.3.1 Little General Understanding of Lean Unlike manufacturing, there is little understanding of lean practices or potential among construction personnel. Lean has made significant inroads into construction in those environments where lean practices are commonplace in other aspect of the business environment; e.g., automotive, pharmaceuticals. Due to the innate differences between manufacturing and construction, there is significant skepticism concerning the applicability of lean principles to construction. 8.3.2 Unique Projects and Unique Design Manufacturers develop their lean practices and systems over long production runs. Manufacturers may produce a million or more units before there is a significant change to a product line. Long stable production runs allow manufacturers to fine-tune processes and relationships to a degree that is not feasible in construction. This lack of long-term, repetitive projects limit the degree to which lean can be fully implemented. On the other hand, many EPC projects have multi-year construction schedules that will allow ample time to develop lean practices. 8.3.3 Lack of Steady-State Conditions Again as contrasted to manufacturing, construction suffers from lack of steady-state conditions. Most contractors perform several different types of work, in different locales, with different clients. It is difficult to reposition lean practices from one job or location to another. Often it is not feasible to maintain a relationship with a key supplier for projects that are located across the country or around the world. 8.3.4 No Control of the Entire Value Stream Manufacturers control their value stream. They control design details, materials and the production environment. Construction companies rarely pick the site, often do not control the design and are frequently constrained to develop strategic relationships based on a low-bid model. The lack of control of the entire value stream makes a case for stronger owner involvement in the lean process. An owner that fully understands the importance of lean as a “system of interacting behaviors” will be more amenable to changes in project design and project delivery so that the full potential of the lean concept may be realized. 8.4 Future Research The research team was charged with investigating lean principles to determine whether lean practice holds potential for improving construction. The conclusion is an unequivocal YES! However, the sheer scope of other potential lean applications is daunting. The following subsections propose areas where follow-up work will enhance understanding of the significance of lean principles in construction. 8.4.1 Lean Coordination For this study, the value stream analyses were conducted at the worksite. There is an entire set of analyses that should be conducted at the level of interacting crews/subcontractors. It is at this interface where the true value of buffers and pull scheduling may be most apparent. This topic can be broadened to include the entire supply chain. 123 8.4.2 Economics of Lean The economics of manufacturing and construction are different. Minimizing inventory and WIP is important for a manufacturer because inventory is essentially steady-state; i.e., it is always there. Construction production experiences fluctuating levels of inventory that are less noticeable from day to day. Also, manufacturers own their inventory and WIP until they are converted into sales. In contrast, a contractor’s inventory and WIP are often converted to revenue by the progress payment process. Finally, from the owner’s viewpoint, the cost of a facility (chip fabrication, pharmaceutical plant) is often a very small portion of the project’s life-cycle cost. The owner is often more focused on maintaining schedule than on controlling costs. 8.4.3 Importance of Repetition Manufacturers develop lean principles to a much higher degree than do EPC companies because of the high degree of repetition in manufacturing. Some types of construction (high-rise buildings, single-family home developments) have a higher amount of inherent repetition than do other types of construction. What is the importance of repetition as regards implementing lean principles in construction? What is the importance of “granularity” of the repetition? For example, if the work of only one crew is repetitive (e.g., a repetitive foundation), how does that compare to an entire project (e.g., a single-family house) that is repetitive? 8.4.4 Reliability in Construction Ensuring reliable construction schedules is fundamental to attaining efficient production systems and interfaces. Reliable construction schedules are required to schedule deliveries and to make subcontract time commitments. One can achieve reliability either by trying to synchronize production systems (additional planning) or by building time buffers (in the form of WIP and inventory buffers) between trades. 8.4.5 Metrics for Lean Construction It has been said that if you are not measuring, you are only practicing. Continuous improvement suggests that the results obtained from applying lean principles need to be measured and benchmarked. Lean manufacturers use many metrics to measure lean performance (e.g., inventory turns, throughput, cycle time). The appropriate metrics for measuring lean construction performance need to be determined, which is beyond the scope of this report. 124 Appendix A Case Study No.1 - Structural Steel 1.0 Overview 1.1 Project Goal The purpose of this case study was to collect data to develop a value stream map for the construction process. Observation was limited to structural steel erection. Field data gathered on two separate value streams included the following: the actual flow of the steel from the time it arrived on the jobsite until it was erected into final position, and the flow of worker activities performed to erect the steel. 1.2 Data Collection Procedure Data collection was accomplished in two consecutive days. Data observations were recorded on prepared data sheets. The steel erection crew consisted of the following six workers: four laborers, a forklift operator and a crane operator. Each of the crew members was individually monitored by one member of the data collection team. Each observer was equipped with a stopwatch and a clipboard with the data sheets. Two digital video cameras were positioned to view the activity area at views intersecting at 90 degrees. The videotapes were taken to provide a means for a more detailed analysis of the activities. Data was recorded as the activities occurred. An entry was made on the data sheet each time a new task was started. For example, an entry might indicate that a worker was rigging a bar joist for the crane. The next entry might indicate that the worker was waiting until the crane had lowered its hook so the worker could attach the rigging to the hook. The elapsed time for each task was recorded as well as the observer’s judgment regarding whether the task was value adding (VA), non-value adding (NVA) or non-value adding but required (NVAR). 1.3 Project Description The project was a 200,000 square foot warehouse. The warehouse was 660 feet long and 300 feet wide. The entire area was divided into 55 bays, each measuring 60 feet by 60 feet. The team observed the erection activities associated with four bays. The subset of the observed operations formed part of the overall sequence of steel erection. The steel erection activities were preceded by the foundation work, which was succeeded by the installation of steel bridging between joists, final aligning, and bolting of the structure. The steel erection activities were partially constrained by the fact that foundations along one column line were not yet installed. The team observed little impact on the efficiency of the steel erection activities caused by the constraint. However, late installation of these foundations will cause unnecessary equipment moves and other inefficiencies after this observation period. 2.0 Steel Erection Process Steel erection consists of the following three distinct cycles: column, girder and bar joist erection. The pictures on the following page illustrate the erection cycle. The process starts with a column erection along a bay section. Generally, the crane can reach three columns without moving; each 125 Step 1: Column Erection Step 2: Support Bar Joist Step 3: Next Column Erected Step 4: Support Bar Joist Erected Along with Girder Step 5: Final Column Erected Step 6: Final Girder Erected Step 7: Interior Bar Joist Installed 126 column is pre-positioned at the time of shakeout, with its baseplate oriented toward the appropriate foundations and anchor bolts. Next, girders are placed between columns. Finally, bar joists are erected. Typically, two bar joists are erected between each bay along the column line to provide stability while the remainder of the bay is erected. Once all the columns, girders and stabilizing bar joist are erected along a column line, the interleaving bar joists are installed in a highly repetitive process. For this case study, the configuration of the building frame necessitated that the steel erection crew perform three separate tasks. The sequence of tasks required movement from location to location, and each task also required a different mix of equipment and workers. Therefore, in contrast to a highly repetitive manufacturing sequence, it was very difficult to design an erection sequence that had the correct number of workers or equipment for each of the three separate tasks. The contractor for this case study chose to size the crew and equipment mix to be most efficient at the bar joist erection stage. The following materials were installed during the observation period: • Two columns. • Two girders. • 27 bar joists. Likewise, the following equipment and crew structures were observed: • One forklift. • Three sky lifts (Genie lifts). • One boom crane. • One boom crane operator. • Four to five personnel in the steel erection crew. The following section analyzes each worker’s contributions to each cycle. Tables and figures were developed for each worker and task. The tables and figures describe the time spent on VA, NVA and NVAR actions within each cycle. 2.1 Observation of Steel Erection Process In the following subsections, each worker is referred to by the position that he or she occupied during the bar joist cycles. These references are used for all other cycles to maintain consistency throughout the analysis. (Refer to the end of this case study to review the data sheets.) 2.1.1 Column Erection Cycle The column erection cycle consisted of the following tasks: preparing the column base, rigging the column for the crane to lift, guiding the column into place, bolting the column to the foundation and unhooking the rigging from the column. Figure A.1 shows the major tasks 127 required to complete the steel erection. The shaded areas are used to visually indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations (e.g., two hours to rig the steel member for the crane). Column Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Prepping Column Base Rigging Column for Crane Column Lifted into Place Column Base Bolted Down Rigging Unhooked from Crane Plumbing Columns Note: This schedule is based on a five day workweek; weekends are excluded. Typically after girders are in position between columns. Figure A.1: Critical Path Method (CPM) Schedule for a Column Erection Cycle Only two members of the crew, the forklift operator and the left connector, were involved with this activity. The two other crew members were not needed for this task and, therefore, all of their time was classified as NVA. The forklift operator was responsible for bracing the columns with the forklift, while the alignment and bolting of the column to the baseplate occurred on the ground. Table A.1 and Figure A.2 show the VA, NVA and NVAR values for the forklift operator. During the column cycles, the forklift operator spent most of his time performing NVAR actions. The only VA actions for the forklift operator occurred while bolting the column to the baseplate. Table A.1: Column Data for the Forklift Operator Activity Classification VA Waste Classification Total Time at Activity % of Total Time 0:02:33 6.83% 0:02:33 6.83% 0:05:05 0:06:09 13.62% 16.48% 0:11:14 30.10% 0:02:36 0:01:28 0:19:28 6.97% 3.93% 52.17% NVAR Total 0:23:32 63.06% Grand Total 0:37:19 100.00% Value Adding VA Total NVA Waiting Motion NVA Total NVAR Mat. Pos. In-Process-Ins. T.W.S.A. 128 Forklift Operator - Column Cycle VA 7% NVA Waiting 14% NVAR TWSA 52% NVA Motion 16% NVAR Material Positioning 7% NVAR In-Process Inspections 4% Figure A.2: Column Data for the Forklift Operator The left connector was responsible for aligning the column and bolting the column to the baseplate. Table A.2 and Figure A.3 show the VA, NVA and NVAR values for the left connector. The majority of the left connector’s time was NVA and was spent waiting and/or moving machinery (sky lift). The left connector was only involved in bolting one of the columns. Table A.2 and Figure A.3 show that 13 percent of the time was spent on bolting, while 87 percent of the time was spent on wasted actions. Table A.2: Column Data for the Left Connector Activity Classification VA Waste Classification Value Adding Total Time at Activity % of Total Time 0:02:00 13.42% 0:02:00 13.42% 0:05:59 0:06:55 40.16% 46.42% NVA Total 0:12:54 86.58% Grand Total 0:14:54 100.00% VA Total NVA Waiting Motion 129 Left Connector - Column Cycle VA 13% NVA Motion 47% NVA Waiting 40% Figure A.3: Column Data for the Left Connector The right connector and X-bracing connector had limited involvement with the column cycles. Table A.3/Figure A.4 and Table A.4/Figure A.5 show the VA, NVA and NVAR values for each crew member. Table A.3: Column Data for the Right Connector Activity Classification NVA Waste Classification Total Time at Activity % of Total Time 0:06:00 0:02:00 53.02% 17.67% 0:08:00 70.69% 0:03:19 29.31% NVAR Total 0:03:19 29.31% Grand Total 0:11:19 100.00% Waiting Motion NVA Total NVAR Mat. Pos. 130 Right Connector - Column Cycle NVAR Material Positioning 29% NVA Waiting 53% NVA Motion 18% Figure A.4: Column Data for the Right Connector Table A.4: Column Data for the X-Bracing Connector Activity Classification NVA Waste Classification Total Time at Activity % of Total Time 0:10:30 0:05:30 65.63% 34.38% NVA Total 0:16:00 100.00% Grand Total 0:16:00 100.00% Waiting Motion X-Bracing Connector - Column Cycle NVA Motion 34% NVA Waiting 66% Figure A.5: Column Data for the X-Bracing Connector 131 2.1.2 Girder Erection Cycle The girder erection process detailed on Figure A.6 included the following subtasks: rigging the girder, guiding the girder into hands of crew members stationed at the top end of the columns, adjusting/hammering the girder to fit into slots, bolting the girder into place and unhooking the crane rigging from the girder. Girder Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Two Columns Erected Rigging Girder for Crane Girder Erected into Place Aligning Girder Bolting Girder into Place Unhooking Rigging from Crane Plumbing Structure Note: This schedule is based on a five day workweek; weekends are excluded. Occurs simultaneously with column plumbing Figure A.6: CPM Schedule for Girder Erection Data for the four remaining crew members is presented below.* The forklift operator focused on setting up the rigging for the crane and guiding the girder into the hands of the crew members above. Table A.5 and Figure A.7 show the VA, NVA and NVAR summary values for the forklift operator. During the girder cycle, the forklift operator spent most of the time waiting (approximately 66 percent). None of the forklift operator’s actions were VA. The only NVAR actions of the forklift operator were rigging the girder and guiding it while it was being lifted by the crane. Table A.5: Girder Data for the Forklift Operator Activity C lassification NV A W aste C lassification W aitin g T ran spo rt M otion NV A T otal T otal T im e at Activity % of T otal T im e 0:15:50 0:00:40 0:02:37 65.61% 2.76% 10.84% 0:19:07 79.21% NV AR M at. P o s. 0:01:33 6.42% T .W .S.A. 0:03:28 14.36% NV AR T otal 0:05:01 20.79% G rand T otal 0:24:08 100.00% *Four members of the five-man crew were observed during the girder erection cycle. The fifth observer was unable to record data during this period. 132 Forklift Operator - Girder Cycle NVAR TWSA 14% NVAR Material Positioning 6% NVA Motion 11% NVA Waiting 66% NVA Transport 3% Figure A.7: Girder Data for the Forklift Operator The left connector performed the following actions: maneuvered the girder to fit into the sleeve connection point on the column, made final adjustments and bolted the girder into place. Table A.6 and Figure A.8 show the VA, NVA and NVAR times for the left connector. Table A.6: Girder Data for the Left Connector Activity Classification VA Waste Classification Value Adding VA Total Total Time at Activity % of Total Time 0:06:00 15.50% 0:06:00 15.50% 0:04:30 0:17:00 11.63% 43.93% NVA Waiting Extra Proc. Motion NVA Total 0:00:55 2.37% 0:22:25 57.92% NVAR 0:10:17 26.57% NVAR Total Mat. Pos. 0:10:17 26.57% Grand Total 0:38:42 100.00% 133 Left Connector - Girder Cycle VA 16% NVAR Material Positioning 27% NVA Waiting 12% NVA Motion 2% NVA Extra Processing 43% Figure A.8: Girder Data for the Left Connector The right connector accomplished the following: maneuvered the girder to fit into the sleeve connection point on the column, made final adjustments and bolted the girder into place. Table A.7 and Figure A.9 show the VA, NVA and NVAR data for the right connector. The left and right connectors’ responsibilities were the same for the girder cycle; these included operating the sky lift, aligning and positioning the girders and bolting each member into its final place. During the girder cycle, both connectors spent the majority of their time aligning and fitting the girder into place. During one of the girder cycles, approximately 24 minutes of hammering and adjustments were needed to fit the girder in place. The remaining time was spent bolting the girder and waiting on other team members. Table A.7: Girder Data for the Right Connector Activity Classification VA Waste Classification Value Adding Total Time at Activity % of Total Time 0:04:50 15.50% 0:04:50 15.50% 0:07:30 0:18:51 24.05% 60.45% NVA Total 0:26:21 84.50% Grand Total 0:31:11 100.00% VA Total NVA Waiting Extra Proc. 134 Right Connector - Girder Cycle VA 15% NVA Waiting 24% NVA Extra Processing 61% Figure A.9: Girder Data for the Right Connector Finally, the x-bracing connector was responsible for releasing the crane rigging from the girder after the member was in place and secured between the two columns. Table A.8 and Figure A.10 show the VA, NVA and NVAR data for the x-bracing connector. Table A.8: Girder Data for the X-Bracing Connector Activity Classification NVA Waste Classification Total Time at Activity % of Total Time 0:31:45 0:00:15 86.99% 0.68% 0:32:00 87.67% 0:04:30 12.33% NVAR Total 0:04:30 12.33% Grand Total 0:36:30 100.00% Waiting Motion NVA Total NVAR T.W.S.A. 135 X-Bracing Connector - Girder Cycle NVAR TWSA 12% NVA Motion 1% NVA Waiting 87% Figure A.10: Girder Data for the X-Bracing Connector The majority of the x-bracing connector’s time was NVA. Table A.8 shows that more than one half hour was spent on waiting. The x-bracing connector’s only physical involvement with the girder cycle was the release of the crane rigging after the left and right connectors secured the girder. 2.1.3 Bar Joist Cycle The bar joist cycle detailed on Figure A.11 included the following subtasks: bolting the x-bracing to the bar joists while it was on the ground, attaching the rigging, maneuvering the bar joist into the hands of the connectors, aligning and positioning the bar joist into its final position on the structure, bolting the bar joist, attaching the x-bracing to the adjacent bar joist already in place on the structure and releasing the crane rigging from the bar joist. Bar Joist Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIE) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Columns and Girders Erected X-Bracing Attached on Ground Rigging Bar Joist for Crane Bar Joist Erected into Place Aligning Bar Joist Bolting Ends of Bar Joist Bolting Other End from X-Bracing Unhooking Rigging from Crane Note: This schedule is based on a five day workweek; weekends are excluded. Figure A.11: CPM Schedule for the Bar Joist Erection All five members were active during this cycle. Two different crew compositions were used in different cycles. The first crew was composed of a ground crewman (making a five-man crew), and the other crew omitted the ground crewman (making a four-man crew). 136 The individual task responsibilities for the bar joist cycle were broken down as follows. The forklift operator was responsible for positioning bundles of bar joist under the crane hook, attaching the first half of the x-bracing member on the ground and guiding the bar joist members into the hands of the crewmen above. Table A.9 and Figure A.12 show the VA, NVA and NVAR summary values of the forklift operator. During the bar joist cycle, the forklift operator was involved in positioning the bar joist bundles under the crane hook to maximize the crane’s actions in lifting the bar joists straight up, rather than having to swing the material from side to side. This action was not included in the bar joist cycle times, though it was a required movement to enable the cycle to start. The forklift operator contributed 25 percent of his total time to VA activities, which involved bolting the first end of x-bracing to the bar joist while it remained on the ground. The average time for this action was one minute and five seconds. Considerable time was also spent on waiting and moving material. Waiting time was governed by the time it took the crane to be freed from the previous bar joist. Table A.9: Bar Joist Data for the Forklift Operator Ac tivity C la ssific ation VA W aste C lassification T otal T im e a t Ac tivity V alu e Ad d in g % of T otal T im e 0:26:07 25.22% 0:26 :07 2 5.2 2% W aitin g E xtra Pro c. 0:24:28 0:05:13 23.63% 5.04% T ran sp o rt 0:12:48 12.36% M o tio n 0:21:00 20.28% 1:03 :29 6 1.3 1% 0:03:58 0:01:30 0:08:29 3.83% 1.45% 8.19% NV AR T otal 0:13 :57 1 3.4 7% G rand T otal 1:43 :33 10 0.0 0% V A T otal NV A NV A T ota l NV AR M at. Po s. In -P ro cess-In s. T .W .S .A. Forklift Operator - Bar Joist Cycle NVAR In-Process Inspections 1% NVAR TWSA 8% VA 26% NVAR Material Positioning 4% NVA Motion 20% NVA Waiting 24% NVA Transport 12% NVA Extra Processing 5% Figure A.12: Bar Joist Data for the Forklift Operator 137 The ground crewman was responsible for guiding the bar joist members into the hands of the crewmen above and positioning the x-bracing material next to the bar joist bundles to be attached by the forklift operator. Table A.10 and Figure A.13 show the VA, NVA and NVAR summary values for the ground crewman. The ground crewman did not complete any VA actions during the bar joist cycles. It was further noted that the ground crewman was the least effective member of the group. The forklift operator was more productive when the ground crewman was not involved. In fact, when the ground crewman was absent, the forklift operator’s waiting time decreased to almost nothing. This point is made clearer by the crew balance charts presented later in this case study. Table A.10: Bar Joist Data for the Ground Crewman Activity Classification NVA Waste Classification Total Time at Activity % of Total Time 0:22:31 0:02:00 40.45% 3.59% 0:24:31 44.04% Mat. Pos. 0:10:05 18.11% T.W.S.A. 0:21:04 37.84% NVAR Total 0:31:09 55.96% Grand Total 0:55:40 100.00% Waiting Transport NVA Total NVAR Ground Crewman - Bar Joist Cycle NVA Waiting 40% NVAR TWSA 38% NVA Transport 4% NVAR Material Positioning 18% Figure A.13: Bar Joist Data for the Ground Crewman 138 The left connector was responsible for positioning and aligning the bar joist into its final position on top of the girder. Bolting the bar joist to the girder below followed the positioning and alignment process. Table A.11 and Figure A.14 show the VA, NVA and NVAR summary values for the left connector. Table A.11: Bar Joist Data for the Left Connector Activity Classification VA Waste Classification Total Time at Activity Value Adding VA Total % of Total Time 0:42:28 40.87% 0:42:28 40.87% 0:16:13 0:16:40 15.61% 16.04% 0:32:53 31.65% NVA Waiting Motion NVA Total NVAR 0:28:33 27.48% NVAR Total Mat. Pos. 0:28:33 27.48% Grand Total 1:43:54 100.00% Left Connector - Bar Joist Cycle NVAR Material Positioning 27% VA 41% NVA Motion 16% NVA Waiting 16% Figure A.14: Bar Joist Data for the Left Connector The right connector was responsible for positioning and aligning the bar joist into its final position on the side opposite the left connector. Bolting the bar joist to the girder followed the positioning and alignment process. Table A.12 and Figure A.15 show the VA, NVA and NVAR results for the right connector. The right and left connectors had similar cycles. The only VA action completed by the connectors involved bolting the bar joist to the girder. On average, the left connector spent one minute 42 seconds on this task, and the right connector spent one minute five seconds. Note that the right connector’s VA contribution was significantly less than that of the left connector. Even with both workers’ contributions to VA actions, a considerable amount of time was still spent on NVA activities. Another observation made concerning the left 139 connector was that he did not use the Genie lift provided for him. Had he done so, he would have only needed to tie off one time. Instead, he preferred to walk the girder between joist placements and tie off with two safety lines to the girder. This added to the total number of actions needed for him to complete each bar joist cycle. Both workers spent an equal amount of time on NVA activities. Table A.12: Bar Joist Data for the Right Connector Activity Classification VA Waste Classification Value Adding Total Time at Activity % of Total Time 0:29:21 26.09% 0:29:21 26.09% 0:30:42 0:24:55 27.29% 22.15% 0:55:37 49.44% 0:26:32 0:01:00 23.59% 0.89% NVAR Total 0:27:32 24.47% G rand Total 1:52:30 100.00% VA Total NVA Waiting Motion NVA Total NVAR Mat. Pos. T .W.S.A. Right Connector - Bar Joist Cycle NVAR TWSA 1% NVAR Material Positioning 24% VA 26% NVA Motion 22% NVA Waiting 27% Figure A.15: Bar Joist Data for the Right Connector The x-bracing connector’s tasks included bolting the opposite end of the x-bracing member to the adjacent, already in-place bar joist, and releasing the crane rigging from the bar joist member after it was secured. Table A.13 and Figure A.16 show the VA, NVA and NVAR results for the x-bracing connector. 140 Table A.13: Bar Joist Data for the X-Bracing Connector Activity Classification VA Waste Classification Total Time at Activity Value Adding VA Total % of Total Time 0:57:45 56.90% 0:57:45 56.90% 0:11:00 0:30:00 10.84% 29.56% 0:41:00 40.39% NVA Waiting Motion NVA Total NVAR 0:02:45 2.71% NVAR Total T.W.S.A. 0:02:45 2.71% Grand Total 1:41:30 100.00% X-Bracing Connector - Bar Joist Cycle NVAR TWSA 3% NVA Motion 30% VA 56% NVA Waiting 11% Figure A.16: Bar Joist Data for the X-Bracing Connector The x-bracing connector’s job was a critical factor in the cycle because the crane was not allowed to unhook from the bar joist until the x-bracing was bolted to the adjacent bar joist. This VA action was more than 57 percent of the total time spent by the x-bracing connector during the bar joist cycle. This worker also maneuvered the sky lift under each new bar joist as it was brought up by the crane, which accounted for more than 30 percent of his time. 3.0 Results for the Crew: Crew Balance Charts As previously mentioned, two different crew compositions were observed. To the casual observer, the difference in crew makeup between the two crews was minimal. From a crew 141 balance perspective, however, the difference in efficiency/productivity was significant. Figures A.17 and A.18 show the two balance charts for the separate crew structures. These charts were compiled using the average times generated from the entire set of data observations. These average times resulted in an “idealized” crew balance. Due to the lack of sufficient repetition of the column and girder cycles, the crew balance charts were constructed using only the bar joist data. 3.1 Crew Composition 1: With Ground Crewman The crew balance chart on Figure A.17 includes the ground crewman data. Different shaded sections within the chart represent the separate tasks for each worker. For example, the dotted area represents a portion of the activity in which waiting occurred. The driver for this cycle was the left connector. Crew Balance With Ground Crewman TIME 0:10:00 0:09:45 0:09:30 0:09:15 0:09:00 0:08:45 0:08:30 0:08:15 0:08:00 0:07:45 0:07:30 0:07:15 0:07:00 0:06:45 0:06:30 0:06:15 0:06:00 0:05:45 0:05:30 0:05:15 0:05:00 0:04:45 0:04:30 0:04:15 0:04:00 0:03:45 0:03:30 0:03:15 0:03:00 0:02:45 0:02:30 0:02:15 0:02:00 0:01:45 0:01:30 0:01:15 0:01:00 0:00:45 0:00:30 0:00:15 0:00:00 Waiting Bolting X-Bracing Bolting BJ Waiting Aligning BJ Positioning BJ Waiting Aligning BJ Hook Up Rigging Move Move Move Unhook Rigging Hook Up Rigging Waiting Attach X-Bracing Bolting BJ Bolting BJ Bolting BJ Aligning BJ Waiting Aligning BJ Waiting Waiting Move Move Move Unhook Rigging Positioning BJ ` Hook Up Rigging Hook Up Rigging Waiting Attach X-Bracing Bolting BJ Bolting BJ Bolting BJ Aligning BJ Waiting Aligning BJ Waiting Move Move Move Unhook Rigging Positioning BJ Hook Up Rigging Hook Up Rigging Bolting BJ Waiting Bolting BJ Bolting BJ Ground Crewman Left Connector Aligning BJ Right Connector Attach X-Bracing Forklift Operator Figure A.17: Crew Balance Chart With Ground Crewman 142 Waiting X-B Connector Crew Balance TIME Waiting Bolting X-Bracing Bolting BJ Positioning BJ Aligning BJ Waiting Aligning BJ Hook Up Rigging Move N o t In v o lv e d in P ro c e s s 0:10:00 0:09:45 0:09:30 0:09:15 0:09:00 0:08:45 0:08:30 0:08:15 0:08:00 0:07:45 0:07:30 0:07:15 0:07:00 0:06:45 0:06:30 0:06:15 0:06:00 0:05:45 0:05:30 0:05:15 0:05:00 0:04:45 0:04:30 0:04:15 0:04:00 0:03:45 0:03:30 0:03:15 0:03:00 0:02:45 0:02:30 0:02:15 0:02:00 0:01:45 0:01:30 0:01:15 0:01:00 0:00:45 0:00:30 0:00:15 0:00:00 Attach X-Bracing Waiting Positioning BJ Hook Up Rigging Attach X-Bracing Waiting Positioning BJ Hook Up Rigging Move Move Unhook Rigging Bolting BJ Bolting BJ Bolting BJ Aligning BJ Aligning BJ Waiting Waiting Move Move Move Unhook Rigging Bolting BJ Bolting BJ Bolting BJ Aligning BJ Aligning BJ Waiting Move Move Bolting BJ Bolting BJ Left Connector Aligning BJ Right Connector Move Unhook Rigging Bolting BJ Attach X-Bracing Forklift Operator Ground Crewman Waiting X-B Connector Figure A.18: Crew Balance Chart Without Ground Crewman This idealized balance chart shows that the left connector had no waiting time throughout the multiple cycles. During a typical cycle, the forklift operator waited an average of one minute 15 seconds, and the ground crewman waited an average of two minutes. The rest of their time was spent rigging the crane and attaching the x-bracing to the bar joist on the ground. As a result, one third to one half of the crew time was wasted on waiting for the crane to be released on top. It is important to note that this is an idealized crew balance using average task times. This ideal cycle is typically shorter than the actual cycle time in which task time variability causes an increase in the overall cycle time. 3.2 Crew Composition 2: Without Ground Crewman On Figure A.18, it is immediately apparent that without the ground crewman, the forklift operator’s idle time was reduced to 15 seconds. Also, he was able to accomplish the tasks of 143 attaching the x-bracing, hooking up the rigging for the crane and positioning the bar joist to those above without delaying the cycle time. The left connector was still the driver (i.e., bottleneck activity) for this cycle, and the other two workers (right connector and x-bracing connector) were not affected at all by the reduction of the crew size from a five-man to a four-man crew. This presents an opportunity to improve the overall cycle time by redesigning the left connector’s work tasks and practices. The overall outcome shows that crew productivity can be increased by this minor restructuring of the group. 3.3 General Observations about Crew Composition During the column cycle, an observation was made that at least two of the five workers were waiting throughout the entire cycle because the crew was too large for that activity. Again, during the girder cycle, the majority of the five-member crew remained idle. A large portion of this waiting was attributed to the difficulty that the right and left connectors had in setting the girder connections. Most of the crew wasted roughly one-half hour because the girder connections did not fit onto the knife plate connected to the column. As can be seen from the previous tables, the variation between the different cycles of VA to NVA and/or NVAR highlights the dilemma currently plaguing the construction industry. These findings demonstrate that while a crew can be efficient for one cycle (e.g., the bar joist cycle), the same crew may not be sized correctly for other activities on the jobsite. 4.0 Process Improvement Opportunities A goal of this report was to examine and document the different forms of waste that occur in construction operations. In general terms, inefficiencies were classified as the following three types: inefficiency due to waste (NVA activities), inefficiency due to unnecessary work (excessive NVAR activities) and inefficiency due to poorly designed work processes (ineffective VA activities). The following section identifies opportunities for process improvement by applying Ohno’s (Shingo and Dillon 1989) seven wastes in production and then evaluating the production process against a more comprehensive set of lean principles. Table A.14 shows the percentage of time spent on VA, NVA and NVAR as a percentage of total cumulative time available to each worker for the entire work cycle observed. Table A.15 lists the subset of activities that occurred to accomplish the entire erection process. In particular, the NVA category is further divided into time spent in the waiting, extra processing, transport and movement categories. Additionally, NVAR is broken down into its three subcategories to clarify how time was spent within the observed cycles. The following analysis categorizes and describes the various wastes viewed on the jobsite. Table A.14: Entire Activity Steel Erection - Entire Process VA Crew Member All Activities 17% Forklift Operator 0% Ground Crewman 32% Left Connector 38% X-Bracing Connector Right Connector 21% Group Percentage 25% 11:27:10 h:m:s NVAR Material In-Process Extra Total Waiting Processing Transport Movement Positioning Inspection TWSA 28% 3% 8% 18% 5% 2% 19% 100% 40% 0% 4% 0% 18% 0% 38% 100% 17% 11% 0% 16% 25% 0% 0% 100% 35% 0% 0% 23% 0% 0% 5% 100% 29% 12% 0% 17% 19% 0% 2% 100% Total Cumulative Time for Steel Erection Waste 28% 6% 2% 144 17% 13% 0% 9% 100% VA + NVAR 43% 56% 57% 42% 42% 46% Table A.15: Summary of Subactivities Columns Crew Member Forklift Operator Ground Crewman Left Connector X-Bracing Connector Right Connector Group Percentage Girders Total Cumulative Time Spent on Columns VA Waste All Extra Activities Waiting Processing Transport Movement 7% 14% 0% 0% 16% 0% 0% 0% 0% 0% 13% 40% 0% 0% 46% 0% 66% 0% 0% 34% 0% 53% 0% 0% 18% 6% 35% 0% Forklift Operator Ground Crewman Left Connector X-Bracing Connector Right Connector Group Percentage Bar Joists Crew Member Forklift Operator Ground Crewman Left Connector X-Bracing Connector Right Connector Group Percentage 26% 7% 2% Total Cumulative Time Spent on Girders VA Crew Member 0% Material Positioning 7% 0% 0% 0% 29% NVAR In-Process Inspection 4% 0% 0% 0% 0% Waste 46% 27% 0% 3% Material Positioning 6% 0% 27% 0% 0% In-Process Inspection 0% 0% 0% 0% 0% 9% 0% Total Cumulative Time Spent on Bar Joists VA Waste All Extra Activities Waiting Processing Transport Movement 25% 24% 5% 12% 20% 0% 40% 0% 4% 0% 41% 16% 0% 0% 16% 57% 11% 0% 0% 30% 25% 27% 0% 0% 22% 32% 34% 4% TWSA 52% 0% 0% 0% 0% Total 100% 0% 100% 100% 100% 24% 100% 2:10:31 h:m:s VA + NVAR 70% 0% 13% 0% 29% 39% NVAR All Extra Activities Waiting Processing Transport Movement 0% 66% 0% 3% 11% 0% 0% 0% 0% 0% 16% 12% 44% 0% 2% 0% 87% 0% 0% 1% 16% 24% 60% 0% 0% 8% 1:19:32 h:m:s 9% 13% TWSA 14% 0% 0% 12% 0% Total 100% 0% 100% 100% 100% 6% 100% 7:57:07 h:m:s VA + NVAR 21% 0% 42% 12% 16% 23% Material Positioning 4% 18% 27% 0% 24% NVAR In-Process Inspection 1% 0% 0% 0% 0% TWSA 8% 38% 0% 3% 2% Total 100% 100% 100% 100% 100% VA + NVAR 39% 56% 68% 60% 51% 1% 5% 3% 100% 41% 4.1 Waste Associated with Laborers and Equipment 4.1.1 Waiting Several incidences of waiting occurred throughout the observation period. Table A.15 shows for the column, girder and bar joist cycles that 35, 46 and 34 percent, respectively, of cumulative cycle time was attributed to waiting. Even with the highly repetitive actions of the bar joist erection process, a quarter of the available work time was wasted on waiting. Waiting time for a crew or equipment was highly dependent on the reliability of the work processes. If an individual worker or work process is subject to variable completion times for the same task, it disrupts the entire subsequent operation. Analyses of the variability of individual work tasks are presented in subsequent sections of this report. 4.1.2 Waste of Motion Wasted movement was observed every time the workers moved the sky lift or the ground crew had to walk to retrieve material for the erection process. Since motion from one work location to another was part of the construction process, the motion category needed to be divided into wasted motion (i.e., unnecessary motion due to unsuitable process design) and NVA motion. The percentage of total time wasted due to motion for the column, girder and bar joist cycles was 26, 3 and 13 percent, respectively. An additional analysis of motion segregated by NVAR and NVA categories was conducted to illuminate this difficult area (refer to Appendix I). 145 4.1.3 Waste of Extra Processing (Rework) The interpretation of this category included the use of defective materials delivered onsite that required modification to be operable. During both girder erection cycles, the crew made site adjustments to the manufactured connections. This rework accounted for more than 27 percent of the time available for the girder connections. 4.1.4 Waste of Transportation Few instances were observed in which material was rehandled. The forklift operator and ground crewman were required to move bar joist bundles between the column lines. They also moved xbracing components next to the crane’s “pick point” to attach the x-bracing to the bar joist just prior to being lifted. For the column, girder and bar joist cycles, the respective percentage of time spent on material movement was 0, 0 and 9 percent. 4.2 Waste Associated with Materials 4.2.1 Overproduction (WIP) Overproduction waste (meaning too much of a building is produced) is rare in construction. Most construction reflects a “build to contract mentality” that requires a specific product(s) to be produced. Work in Progress (WIP), on the other hand, is evident in construction but is dependent on the activity level being viewed. At the process-specific level, WIP is seldom observed. However, at the management level, each unfinished component of the production process represents WIP. For this study, WIP was represented by the unfinished structure. 4.2.2 Inventory Material deliveries were made twice to this project: once at the beginning of erection, and once halfway through. On average, structural steel members were onsite for two weeks prior to erection. Also, in addition to the main steel members, there was an inventory of bridging/stiffening material onsite to be used after the main structure was erected. 4.2.3 Defects Defects are defined as errors or deficiencies in a finished product that require additional work on the part of the original crew or a follow-up crew. A defective structural element (e.g., column, girder, etc.) is an example of a defect (i.e., the material has been passed through the value stream to the next workstation). Another example of a defect is included in the punch list process at the end of a job. When a defect in the finished product is found at this stage, a separate follow-up crew is activated to correct the defect. Hence, the defect is pushed onto the next workstation. No waste associated with defects was observed. 5.0 Value Stream Analysis The following paragraphs describe the current value stream map for this structural steel erection process, beginning from the time the material was ordered and shipped from the manufacturer, through the construction production process, and ending with the material in final position in the facility. Figure A.19 is a simple flow diagram, with each box representing a point in time when 146 the material was touched, either to be moved or transformed into its next stage (phase) in the construction life cycle. Interior joist beams members moved to final staging area in each bay Manufacturer Initial dropoff Initial shakeout Secondary shakeout of different joist beams and girder members for each bay Specific girders and joist beams moved to final staging area for each bay Picked up and positioned by forklift Final placement by crane Figure A.19: Material Flow Diagram Information on delivery and handling of the steel members was obtained from the site foreman. Once it arrived onsite, the basic flow of the steel was as follows: • Steel was delivered from the factory by truck: − Each load was handled for the first time by forklifts, and the entire load was removed from the truck bed. This minimized the amount of time that the truck was required to stay onsite. − The first loads were offloaded at, or near, their final staging position. However, as more loads were delivered, they were required to be placed in staging areas farther away until space became available for the remaining bar joists to be placed in their final staging area. − The design called for several types of bar joists, roughly 40 different shapes and sizes. After the initial unloading, the next step was to shake out the bundles. The interior joist members (within each bay, there was a series of joist beams that were identical in shape and size, which were always placed in the interior portion of the bay) were bundled together and could be picked up and dropped off in one move to their next staging area under their designated bay section. − The remaining bar joist members required in each bay section were broken out of their respective bundles, shaken out, and moved with all other required bar joists in each respective bay. This act of shaking out the bar joists introduced one more touch to the value stream and a minimum of four touches by the forklift operator. − After the joists were placed in their respective staging areas, one of two patterns was followed. The first pattern involved the crane moving the girders, bar joists and columns from the staging position to their final position in the structure. The second pattern involved an extra step for some of the interior bar joists. Specific bar joist bundles were picked up by the forklift and rotated 90 degrees to a point directly under their final place in the structure, and then lifted one by one into position. 147 − X-bracing members were pre-assembled prior to connection to the bar joists. The two pieces of the x-bracing were delivered onsite and stacked in the material yard. When the joist beams were ready to be installed, this pile was then moved to another staging area next to the interior joist beams.* 5.1 Case Study No. 1--Value Stream Map For the value stream map analysis depicted on Figure A.20, three levels were needed to represent both the material and labor components. Level One represents the major staging positions that material must go through to reach its finished state. Each time material was moved or transformed, a stage box is used to represent the process. Some of the stages include substages (Level Two) to represent processes that occurred simultaneously. The individual crew contributions to the value stream are represented on Level Three. The value stream map shown on Figure A.20 was created using the information described in the preceding section. Each major stage that the structural steel members went through is represented on Level One. The steel went through two substages during Stage Two before it reached Stage Three. Although these actions were not observed, the project superintendent confirmed that they did occur. An estimate of five days total is shown for completion of Stage Two. Each substage required 50 percent of the total time to accomplish Stage Two. The value stream ended once the steel erection process reached the detailing and welding stage. Again, the limited observation period prevented acquiring data about this stage for the entire steel erection process. Attention was instead focused on the three substages required for Stage Three of the value stream. In Levels Two and Three, the majority of time spent during the steel erection process was on the bar joist erection phase. Note that even though the crew was sized specifically for this activity, more than 60 percent of the time spent on erecting bar joists was NVA. The largest portion of VA actions was also observed during this substage. Table A.16 and Figure A.21 show the quick summary results for the work distribution values. Of the 792 total workable hours committed to the steel erection process, only 161 of them were VA. The least amount of time was spent on NVAR actions. This number is a little skewed because the time contributed by the crane operator was not included in the work distribution values for VA, NVAR and NVA. If his time had been included, a small drop in the VA value and a small increase in the NVAR value would be evident. During the steel erection process, NVA actions accounted for the majority of the time expended. Finally, Figure A.22 and Table A.17 illustrate how the work distribution values changed and grew throughout the process life cycle. The weighted average results found in Level Three of the value stream map were used to calculate all of the VA, NVAR and NVA values (Table A.17). As shown on Figure A.22, the cumulative NVA hours line grew the fastest compared to the other work distribution values. The black vertical line indicates when the steel delivery and shakeout processes finished and the steel erection process began. The slope change for the cumulative workable hours line indicates that more crew members were introduced to the process. As seen on the figure, the cumulative VA line finally started to grow. *One idea was to have the cross bracing assembled by the steel manufacturer before it arrived onsite. The contractor stated that it leaves activities like this to be completed onsite to provide activities for the workers on inclement weather days. 148 Production Control Every 1-3 days Project Engineer Triggering Event Level One Two Phases of Steel are Ordered Percent Complete Project Superintendent Distribution of Time from VSM Steel Supplier Time Allocation Field Steel In Place awaiting welding Project Feedback Daily As Required NVA Time NVAR Time 1 VA Time Work Time Five Cumulative Days to Deliver Steel O OO 0 O 100 200 300 400 500 600 700 800 Man-Hours Stage One - Steel is Offloaded in Respective Bays Days Required Stage Two (A,B) - Steel Shakeout Process 2 Days Required Equipment involved: Forklifts Workers involved Crew WT VA ( 0%) NVAR (20%) NVA (80%) 5 Days Required Equipment involved: 2 Forklifts 32 0 6.4 25.6 1 Workers involved Crew WT VA ( 0%) NVAR (0%) NVA (100%) 2 Inv 2 80 0 0 80 Stage Two (A) - Bar Joists Bundles Are Shook Out Days required Days required Equipment involved: Forklifts Forklifts 2 40 0 0 40 Columns Forklift Operator Level Three Ground Crewman Left Connector X-Bracing Con. Right Connector Group Percentage Waiting 14% 0% 40% 66% 53% Extra Processing 0% 0% 0% 0% 0% All Activities 7% 0% 13% 0% 0% 6% 35% 0% NVA Sum Transport 0% 0% 0% 0% 0% 0% VA Group Percentage Waiting 66% 0% 12% 87% 24% Extra Processing 0% 0% 44% 0% 60% 8% 47% 27% NVA = VA Movement 16% 0% 46% 34% 18% 26% 7% Waste Transport 3% 0% 0% 0% 0% 0% Waiting 24% 40% 16% 11% 27% Extra Processing 5% 0% 0% 0% 0% 5 78.7 4.7 26.8 47.2 TWSA 52% 0% 0% 0% 0% 2% 24% 31% 34% 4% NVA = 25% 9% 100% 34% 2:10:31 h:m:s 28% 6% 39% NVAR In-Process Inspection 0% 0% 0% 0% 0% TWSA 14% 0% 0% 12% 0% Total 100% 0% 100% 100% 100% VA + NVAR 21% 0% 42% 12% 16% 3% 9% 0% 6% 101% 23% 15% 7:57:07 h:m:s Movement 20% 0% 16% 30% 22% 13% Material Positioning 4% 18% 27% 0% 24% NVAR In-Process Inspection 1% 0% 0% 0% 0% 1% 5% NVAR = Waste TWSA 8% 38% 0% 3% 2% Total 100% 100% 100% 100% 100% VA + NVAR 39% 56% 68% 60% 51% 3% 99% 40% 9% 11:27:10 h:m:s Total Cumulative Time for Steel Erection Extra Processing 3% 0% 11% 0% 12% VA + NVAR 70% 0% 13% 0% 29% Material Positioning 6% 0% 27% 0% 0% 60% Waiting 28% 40% 17% 35% 29% Total 100% 0% 100% 100% 100% Movement 11% 0% 2% 1% 0% Waste Transport 8% 4% 0% 0% 0% Movement 18% 0% 16% 23% 17% Material Positioning 5% 18% 25% 0% 19% NVAR In-Process Inspection 2% 0% 0% 0% 0% TWSA 19% 38% 0% 5% 2% Total 100% 100% 100% 100% 100% VA + NVAR 43% 56% 57% 42% 42% 2% 17% 13% 0% 9% 100% 46% Table represents the time distribution for each element viewed during the observation period. Cumulative Number of Cycle Time for Time for Members Each Element Cumulative Time for each Element Various Observed Installed 1:19:32 2 0:39:46 Total Cumulative Time for Two Columns 2:10:31 2 1:05:15 Total Cumulative Time for Two Girders 7:57:07 26 0:18:21 Total Cumulative Time for 26 Bar Joists Total Time 11:27:10 % of Total Time Each % of Total Steel Element Time Requires 12% 5.8% 19% 9.5% 69% 2.7% Figure A.20: Value Stream Map 149 3.2 Equipment involved: Crane, Two Skylifts, 4 Forklift Workers involved: Crew 5 WT= 129.2 VA ( 8%) = 10.3 NVAR (15%) = 19.4 NVA (77%) = 99.4 2 NVAR In-Process Inspection 4% 0% 0% 0% 0% NVAR = Transport 12% 4% 0% 0% 0% Days required 1:19:32 h:m:s Material Positioning 7% 0% 0% 0% 29% 77% All Activities 25% 0% 41% 57% 25% Steel Erection - Entire Process VA Crew Member All Activities Forklift Operator 17% Ground Crewman 0% Left Connector 32% X-Bracing Con. 38% Right Connector 21% Group Percentage 40 0 0 40 Total Cumulative Time Spent on Bar Joists Crew Member Group Percentage 2 NVAR Sum Bar Joists Forklift Operator Ground Crewman Left Connector X-Bracing Con. Right Connector Crane, Forklift Workers involved: Crew WT= VA ( 6%) = NVAR (34%) = NVA (60%) = 61% All Activities 0% 0% 16% 0% 16% Joist Girder is Erected 2.0 Total Cumulative Time Spent on Girders Crew Member 680 161 89 430 Equipment involved: Waste Girders Forklift Operator Ground Crewman Left Connector X-Bracing Con. Right Connector Days required Total Cumulative Time Spent on Columns VA Crew Member Quick Summary for Level One Working Days 24 days Working Time 792 man-hours VA Total 161 man-hours NVAR Total 95 man-hours NVA Total 536 man-hours 5 Inventory Days 10 Note: These steps occur at the same time. Columns and Girders are erected first but cannot be continued until the inner supporting bar joist has been erected. 1 Workers involved: Crew WT VA ( 0%) NVAR (0%) NVA (100%) 2 to 4 Columns Erected 2.5 Equipment involved: 1 **Graph shows the amount of man-hours attributed to each work category. VA time + NVAR time + NVA time = Work Time 17.0 Equipment involved: Forklift, crane, skylifts Workers involved Crew WT= VA ( 6%, 8%, 31%) NVAR (34%, 15%, 9% NVA (60%, 77%, 60% Stage Two (B) - Specific Bar Joists and Girders Are Pulled From 2.5 Workers involved: Crew WT VA ( 0%) NVAR (0%) NVA (100%) Inv 8 2 Level Two Stage Three - Steel Erection Process Average VA Percentage Average NVAR Percentage Average NVA Percentage 25% 22% 53% Bar Joist installed Along with X-Bracing Members Days required 11.8 Equipment involved: Crane, Two Skylifts, 4 Forklift Workers involved: Crew 5 WT= 472 VA ( 31%) = 146 NVAR (9%) = 42 NVA (60%) = 283 Table A.16: Quick Summary of Steel Process Quick Summary for Level One Working Days 24 days Working Time 792 man-hours VA Total 161 man-hours NVAR Total 95 man-hours NVA Total 536 man-hours Time Allocation Field Distribution of Tim e from VSM NVA Time NVAR Time 1 VA Time Work Time 0 100 200 300 400 500 600 700 800 Man-Hours Figure A.21: Graphical Display for the Quick Summary Table Work Distribution 1200 1000 Time (man-hours) 800 Cumulative Calendar Hours Cumulative Workable Hours 600 400 Cumulative VA Hours Delivery and Preparation Process Erection Process Is Under Way Cumulative NVAR Hours. Cumulative NVA Hours 200 Note: the percentages used to create this chart are the average values from the work distribution values found for the entire crew. 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Calendar Days Figure A.22: Work Distribution Life Cycle Graph 150 Table A.17: Spreadsheet of Values Used to Create Work Distribution Life Cycle Graph Stage Stage 1 Stage 1 Stage 2 Stage 2 Stage 2 Weekend Weekend Stage 2 Stage 2 Stage 3 Stage 3 Stage 3 Weekend Weekend Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Weekend Weekend Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Weekend Weekend Stage 3 Stage 3 Stage 3 Stage 3 Primary Activity for the Day Steel is moved from truck to ground Steel is moved from truck to ground Steel is shaken out Steel is shaken out Steel is shaken out Weekend Weekend Steel is shaken out Steel is shaken out One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) Weekend Weekend One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) Weekend Weekend One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) Weekend Weekend One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) One crew erecting S.S. (Columns, Joist Girder and Bar Joists) Day Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Cumulative Cumulative Hours Cumulative Cumulative NVAR NVA Cumulative VA NVAR NVA VA Cumulative NVAR Calendar Calendar Calendar Workable Workable Crew Worked Workable Workable Hours Hours NVA Hours Hours Percentage Percentage Percentage Hours VA Hours Hours Days Available per Day Hours Hours Days Days Hours 1 16 16 1 1 2 8 16 16 0% 20% 80% 0 0 3.2 3.2 12.8 12.8 2 16 32 1 2 2 8 16 32 0% 20% 80% 0 0 3.2 6.4 12.8 25.6 3 16 48 1 3 2 8 16 48 0% 0% 100% 0 0 0 6.4 16 41.6 4 16 64 1 4 2 8 16 64 0% 0% 100% 0 0 0 6.4 16 57.6 5 16 80 1 5 2 8 16 80 0% 0% 100% 0 0 0 6.4 16 73.6 6 16 96 0 5 2 0 0 80 0% 0% 100% 0 0 0 6.4 0 73.6 7 16 112 0 5 2 0 0 80 0% 0% 100% 0 0 0 6.4 0 73.6 8 16 128 1 6 2 8 16 96 0% 0% 100% 0 0 0 6.4 16 89.6 9 16 144 1 7 2 8 16 112 0% 0% 100% 0 0 0 6.4 16 105.6 10 40 184 1 8 5 8 40 152 25% 22% 53% 10 10 8.8 15.2 21.2 126.8 11 40 224 1 9 5 8 40 192 25% 22% 53% 10 20 8.8 24 21.2 148 12 40 264 1 10 5 8 40 232 25% 22% 53% 10 30 8.8 32.8 21.2 169.2 13 40 304 0 10 5 0 0 232 25% 22% 53% 0 30 0 32.8 0 169.2 14 40 344 0 10 5 0 0 232 25% 22% 53% 0 30 0 32.8 0 169.2 15 40 384 1 11 5 8 40 272 25% 22% 53% 10 40 8.8 41.6 21.2 190.4 16 40 424 1 12 5 8 40 312 25% 22% 53% 10 50 8.8 50.4 21.2 211.6 17 40 464 1 13 5 8 40 352 25% 22% 53% 10 60 8.8 59.2 21.2 232.8 18 40 504 1 14 5 8 40 392 25% 22% 53% 10 70 8.8 68 21.2 254 19 40 544 1 15 5 8 40 432 25% 22% 53% 10 80 8.8 76.8 21.2 275.2 20 40 584 0 15 5 0 0 432 25% 22% 53% 0 80 0 76.8 0 275.2 21 40 624 0 15 5 0 0 432 25% 22% 53% 0 80 0 76.8 0 275.2 22 40 664 1 16 5 8 40 472 25% 22% 53% 10 90 8.8 85.6 21.2 296.4 23 40 704 1 17 5 8 40 512 25% 22% 53% 10 100 8.8 94.4 21.2 317.6 24 40 744 1 18 5 8 40 552 25% 22% 53% 10 110 8.8 103.2 21.2 338.8 25 40 784 1 19 5 8 40 592 25% 22% 53% 10 120 8.8 112 21.2 360 26 40 824 1 20 5 8 40 632 25% 22% 53% 10 130 8.8 120.8 21.2 381.2 27 40 864 0 20 5 0 0 632 25% 22% 53% 0 130 0 120.8 0 381.2 28 40 904 0 20 5 0 0 632 25% 22% 53% 0 130 0 120.8 0 381.2 29 40 944 1 21 5 8 40 672 25% 22% 53% 10 140 8.8 129.6 21.2 402.4 30 40 984 1 22 5 8 40 712 25% 22% 53% 10 150 8.8 138.4 21.2 423.6 31 40 1024 1 23 5 8 40 752 25% 22% 53% 10 160 8.8 147.2 21.2 444.8 32 40 1064 1 24 5 8 40 792 25% 22% 53% 10 170 8.8 156 21.2 466 151 Appendix B Case Study No. 2 - Structural Steel 1.0 Overview 1.1 Project Goal The purpose of this case study was to collect data to develop a value stream map for construction processes. Observations were limited to structural steel erection. Field data was gathered on two separate value streams. The first was the actual flow of the steel from the time it arrived on the jobsite until it was erected into final position. The second value stream was the flow of worker activities performed to erect the steel. 1.2 Data Collection Procedure Data collection was accomplished in two consecutive days. Data observations were recorded on prepared data sheets (refer to the end of this case study to view these spreadsheets). Two different erection crews were observed. The first erection crew consisted of the following six workers: four laborers, a steel erection foreman and a crane operator. The second erection crew consisted of the following five workers: three laborers, a steel erection foreman and a crane operator. Each laborer, along with the crane operator, was monitored by one member of the data collection team. The foreman was not observed because of his lack of physical involvement with the erection cycle. Each observer was equipped with a stopwatch and a clipboard containing data sheets. One digital video camera was positioned to record all actions during the erection sequence. The video recordings were taken to provide a means to do a more detailed analysis of the activities. Data was recorded as the activities occurred. Each time a new task was started, an entry was made on the data sheet. For example, an entry might indicate that a worker was rigging a bar joist for the crane. The next entry might indicate that the worker was waiting until the crane lowered its hook so the worker could attach the rigging to the hook. The elapsed time for each task was recorded as well as the observers’ judgment regarding whether the task was value adding (VA), non-value adding (NVA) or non-value adding but required (NVAR). 1.3 Project Description The site included roughly 1,700 acres plus additional 300 acres reserved for future development. Several buildings will eventually occupy the site. The case study focused on an area in the largest of these buildings. The structure was approximately one million square feet and, when viewed from the plan view, resembled the shape of the letter “F.” The structure was composed of several smaller bay sections that roughly measured 60 feet by 60 feet. Two bays were erected using one crew. A second crew finished the activities dealing with erecting purlins on top of a completed bay section. The subset of operations formed part of the overall sequence of steel erection. The steel erection activities were preceded by the foundation work, which was succeeded (following the purlin erection) by the installation of wind bracing, final alignment and bolting. The steel erection activities were partially constrained by the fact that nearly half of the caissons, drilled and poured, were off by more than six inches; the caissons were being replaced during the observation period. This constraint had little impact on the efficiency in each observed bay of 152 steel erection activities. However, delayed installation of these caissons would cause unnecessary equipment movement and other inefficiencies to steel erection activities after this observation period. 2.0 Steel Erection Process 2.1 Erection Cycle No. 1 The steel erection process consisted of the following three separate cycles: column erection, joist girder erection and truss erection. The following pictures illustrate the steps taken to erect the steel. Step 1: Beginning of Process Step 2: Girder, Column and Truss Erected Step 4: Crane Moves Back, Erects Two Columns Step 5: Crane Moves, Erects Two Girders Step 6: Trusses are Erected on Both Sides Step 7: Crane Moves, Erects Trusses 153 Step 3: Exterior Column and Girder Erected The process started with a column erection along a bay section. The area observed focused on a three by 26 bay section of the entire structure. A Manitoc 4100 crane was used for the steel erection process. Ideally, the crane could reach three columns along the outside bay, as well as setting all joist girders and trusses between the columns in one crane movement. During steel delivery, the columns, girders and trusses were placed around the area of the bay in piles of “like” members. A ground crewman or foreman then searched the respective piles to locate and draw directional lines and a north arrow on each steel member. Numbers, originally marked by the manufacturer on each of the steel members indicated their final location in the structure according to the given plans. The foreman constructed the erection order on paper that the crane operator followed. After two neighboring columns were erected, a joist girder was placed between the columns. Once the columns and joist girders were placed in their final positions in the bay, the interleaving trusses were installed in a repetitive process. 2.2 Erection Cycle No. 2 - Purlins The purlin erection cycle consisted of one primary cycle. The diagram below illustrates the erection methodology used during the purlin erection cycle: Diagram Representing Purlin Erection Process The process started after the erection of columns, girders and trusses was completed in three bay sections. A Manitoc 4400 crane was used during the purlin erection cycle. The purlins were delivered in large bundles next to the bays. No pre-shakeout was completed before delivery. After the foreman located the purlins on the ground, they were lifted one by one into their respective positions in the structure. The purlins were placed into their final locations starting with the outer corner bay (relative to the position of the cranes) of the newly erected structure and continuing across the back row of the structure. The process started again by filling the middle row of the three bay sections, and finished with the inner row of bay sections. The configuration of the building frame necessitated that the steel erection crew perform four separate tasks. Each task required movement from task location to task location. Each task also required different amounts of equipment and workers. Therefore, in contrast to a highly repetitive manufacturing sequence, it was very difficult to design an erection sequence that had the correct number of workers or equipment for each of the four separate tasks. 154 During the period of observation, the following steel members were installed: • Three columns. • Two joist girders. • Two trusses. • Twelve purlins. In addition, the following equipment and crew structures were observed: • Four sky lifts (Genie lifts). • Two cranes (Manitoc 4100 and 4400). • One crane operator. • Eight to 10 crew personnel. The following section analyzes each worker’s contributions to each cycle. Tables and figures were developed for each worker and task. The tables and figures describe the time spent on VA, NVA and NVAR actions in each cycle. 2.3 Observation of Steel Erection Process 2.3.1 Steel Erection Process - Cycle No. 1 In the following subsections, each worker is referred to by the position that he or she occupied during the truss cycles. These references are used for the column and joist girder cycles to maintain consistency throughout the analysis. (Refer to the end of this case study to review the data sheets.) 2.3.1.1 Column Erection Cycle. The column erection cycle consisted of the following tasks: preparing the column base, rigging the column for crane, guiding the column into place, bolting the base of the column to the baseplate on the foundation and unhooking the rigging from the column. Figure B.1 shows the major tasks required to complete the column installation. The shaded areas are used to indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations. Column Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Prepping Column Base Rigging Column for Crane Column Lifted Into Place Column Base Is Bolted Down Rigging Unhooked from Crane Plumb Columns Note: Continual shipment of material to site. Typically after girders are in position between columns. Figure B.1: Schedule for a Column Erection Cycle 155 All members of the crew were involved with the erection of the columns. The main participants in the column cycles included connector 1, 2 and the ground crewman. The crane operator and second ground crewman were also involved; however, all of their movements were NVA or NVAR. Connector 1 was responsible for preparing the anchor bolts, aligning and bolting the column to the baseplate, and releasing the crane rigging after the bolting was complete. Table B.1 and Figure B.2 show the VA, NVA and NVAR values for connector 1. During the column cycles, connector 1 spent most of his time (46.61 percent) performing NVAR actions. The only VA actions occurred while bolting the column to the baseplate. Table B.1: Column Data for Connector 1 Ac tiv ity C la ss ific a tio n VA W a s te C la ssific a tio n V alu e A d d in g V A T o ta l T im e a t Ac tiv ity % o f T im e a t Ac tiv ity 0 :0 8:2 3 27 .49 % 0 :0 8 :2 3 2 7 .4 9 % 0 :0 1:3 7 0 :0 1:4 7 5.3 0% 5.8 5% NVA E xtra P ro c . M o tio n W aitin g 0 :0 4:3 0 14 .75 % 0 :0 7 :5 4 2 5 .9 0 % 0 :1 0:0 1 0 :0 4:1 2 32 .84 % 13 .77 % N V AR T o ta l 0 :1 4 :1 3 4 6 .6 1 % G ra n d T o ta l 0 :3 0 :3 0 100% N V A T o ta l N V AR M at. P o s. T .W .S .A . Connector #1 Column Data NVAR TWSA 14% VA 27% NVA Extra Processing 5% NVAR Material Positioning 33% NVA Motion 6% NVA Waiting 15% Figure B.2: Column - Connector 1 156 Connector 2 mirrored the actions of connector 1 for all tasks involved with the column cycles. Table B.2 and Figure B.3 show the VA, NVA and NVAR values for connector 2. Again, connector 2 time spent the largest amount of time on NVAR actions (47 percent). Table B.2: Column Cycle - Connector 2 Activity C lassificatio n VA W aste C lassificatio n T im e at Activity % o f T o tal T im e (b lan k) 0:08:23 0:08:23 27.49% 27.49% E xtra P ro c. M o tio n W aitin g 0:01:37 0:01:47 0:04:30 0:07:54 5.30% 5.85% 14.75% 25.90% E q u ip . R eq . M at. P o s. N V A R T o tal 0:04:12 0:10:01 0:14:13 13.77% 32.84% 46.61% G ran d T o tal 0:30:30 100.00% V A T o tal NVA N V A T o tal NVAR Connector #2 Column Data NVAR TWSA 14% VA 27% NVA Extra Processing 5% NVAR Material Positioning 33% NVA Motion 6% NVA Waiting 15% Figure B.3: Column Cycle - Connector 2 Ground crewman 1 contributed his largest percentage of VA activities during the erection of the steel columns. Table B.3 and Figure B.4 show the VA, NVA and NVAR values for ground crewman 1. Thirty-seven percent of the time attributed by ground crewman 1 involved bolting the column to the baseplate. Note that the largest amount of time was spent on the NVA action of waiting. Ground crewman 1 was only a part of one column cycle. The rest of his time was spent locating steel and assisting the foreman with the steel erection sequence. 157 Table B.3: Column Cycle - Ground Crewman 1 A c tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n V a lu e A d d in g T im e a t A c tiv ity % o f T im e a t A c tiv ity 0 :0 4 :4 9 3 6 .8 2 % 0 :0 4 :4 9 3 6 .8 2 % 0 :0 1 :0 3 0 :0 5 :1 9 8 .0 3 % 4 0 .6 4 % 0 :0 6 :2 2 4 8 .6 6 % 0 :0 0 :3 4 0 :0 1 :2 0 4 .3 3 % 1 0 .1 9 % N V A R T o ta l 0 :0 1 :5 4 1 4 .5 2 % G ra n d T o ta l 0 :1 3 :0 5 100% V A T o ta l NVA E x tra P ro c . W a itin g N V A T o ta l NV AR M a t. P o s . T .W .S .A . Ground Crewman #1 (White Shirt) Column Data NVAR TWSA 10% NVAR Material Positioning 4% VA 37% NVA Waiting 41% NVA Extra Processing 8% Figure B.4: Column Cycle - Ground Crewman 1 Ground crewman 2 was not involved in any VA tasks during the column erection cycles. Table B.4 and Figure B.5 show the VA, NVA and NVAR values for ground crewman 2. The majority of the crewman’s time was spent on the NVA action of waiting (53 percent). A minimal amount of time was contributed to material positioning and equipment requirements. 158 Table B.4: Column Cycle - Ground Crewman 2 Activity Classification NVA Waste Classification Time at Activity Waiting Extra Proc. Transport Motion NVA Total % of Time at Activity 0:17:03 0:02:02 0:02:05 0:06:57 53.14% 6.34% 6% 21.66% 0:28:07 87.64% NVAR Mat. Pos. 0:02:10 6.75% T.W.S.A. 0:01:48 5.61% NVAR Total 0:03:58 12.36% Grand Total 0:32:05 100% Ground Crewman #2 (Orange Shirt) Column Data NVAR TWSA 6% NVA Extra Processing 6% NVAR Material Positioning 7% NVA Motion 22% NVA Transport 6% NVA Waiting 53% Figure B.5: Column Cycle - Ground Crewman 2 The crane operator contributed no VA activities to the column erection cycle. Table B.5 and Figure B.6 show the VA, NVA and NVAR values for the crane operator. The crane operator was primarily involved with transporting columns from their lay-down area to their final position in the structure. The transport action occurred after the column was “picked” from the lay-down area to the point above the baseplate. After reaching the baseplate, the crane held the member in a temporary bracing position until the bolts were sufficiently tightened. These actions contributed to the NVAR value of 68.76 percent for the temporary work and support activities (TWSA) category. 159 Table B.5: Column Cycle - Crane Operator Activity Classification NVA Waste Classification Time at Activity Motion Transport Waiting NVA Total % of Time at Activity 0:02:02 0:05:44 0:01:52 6.59% 19% 6.05% 0:09:38 31.24% NVAR 0:21:12 68.76% NVAR Total T.W.S.A. 0:21:12 68.76% Grand Total 0:30:50 100% Crane Operator - Column Data NVA Motion 7% NVA Transport 19% NVA Waiting 6% NVAR TWSA 68% Figure B.6: Column Cycle - Crane Operator 2.3.1.2 Girder Erection Cycle. The girder erection process included the following subtasks: preparing the girder with rigging for the crane, guiding the girder into the hands of crew members stationed at the top end of the columns, adjusting/hammering girders to fit into slots, bolting the girders into place, and unhooking crane rigging from the girder. Figure B.7 shows the major tasks required to complete the girder installation. The shaded areas are used to indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations. Joist Girder Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Three Columns Have Been Erected Rigging Girder for Crane Girder Erected Into Place Aligning Girder Bolting Girder Into Place Unhooking Rigging from Crane Plumb Structure (with Columns) Note: Continual shipment of material to site. Occurs simultaneously with column plumbing. Figure B.7: Schedule for a Girder Erection 160 All five members of the crew were observed during the girder erection cycle. Data for the five crew members is presented below. Connector 1 spent the majority of his time aligning and securing the joist girder after it was lifted into position by the crane operator. Table B.6 and Figure B.8 show the VA, NVA and NVAR values for connector 1. Notice that a slightly larger percentage of time was spent on VA actions during the joist girder cycle than was spent during the column cycle. The majority (27 percent) of the NVA time was attributed to movement of the sky lift between upper and lower connections as well as between opposite ends of the bay section where the girders were placed. Table B.6: Joist Girder Cycle - Connector 1 Activity C lassification VA W aste C lassification Value Add in g T im e at Activity % of T im e at Activity 0:12:18 34.18% 0:12:18 34.18% 0:09:34 0:03:35 26.59% 9.96% 0:13:09 36.54% 0:08:38 0:01:54 23.99% 5.28% NV AR T otal 0:10:32 29.27% G rand T otal 0:35:59 100% V A T otal NV A M o tion W aitin g NV A T otal NV AR M at. P os. T .W .S.A. Connector #1 - Joist Girder Data NVAR TWSA 5% VA 34% NVAR Material Positioning 24% NVA Waiting 10% NVA Motion 27% Figure B.8: Joist Girder Cycle - Connector 1 161 Connector 2 was also involved with aligning and bolting the joist girder after it was lifted into position by the crane. Table B.7 and Figure B.9 show the VA, NVA and NVAR values for connector 2. One point of interest between the two connectors was the jump in percentage of time spent on NVA actions to 51 percent. A significant portion of time for connector 2 was spent hammering and readjusting (extra processing) the girder to fit correctly. This extra processing required connector 2 to move the sky lift around the girder connection accounting for the extra time attributed to the NVA waste category of motion (36.35 percent). Table B.7: Joist Girder Cycle - Connector 2 Ac tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n V a lu e A d d in g V A T o ta l T im e a t Ac tiv ity % o f T im e a t Ac tiv ity 0 :0 5 :4 8 1 5 .8 3 % 0 :0 5 :4 8 1 5 .8 3 % 0 :0 2 :3 7 0 :1 3 :1 9 7 .1 4 % 3 6 .3 5 % NVA E x tra P ro c . M o tio n W a itin g 0 :0 2 :4 3 7 .4 2 % 0 :1 8 :3 9 5 0 .9 1 % 0 :1 1 :3 9 0 :0 0 :3 2 3 1 .8 0 % 1 .4 6 % N V AR T o ta l 0 :1 2 :1 1 3 3 .2 6 % G ra n d T o ta l 0 :3 6 :3 8 100% N V A T o ta l N V AR M a t. P o s . T .W .S .A . Connector #2 - Joist Girder Data NVAR TWSA 1% VA 16% NVAR Material Positioning 32% NVA Extra Processing 7% NVA Waiting 7% NVA Motion 37% Figure B.9: Joist Girder Cycle - Connector 2 Ground crewman 1 was responsible for locating individual members in the material yard, rigging the girder for the crane and attaching a structural element used to support the edge of the building parapet. Table B.8 and Figure B.10 show the VA, NVA and NVAR values for ground crewman 1. The attachment of the parapet member accounted for the VA time (10 percent for the crewman). The rest of the crewman’s time (90 percent) was attributed to NVA actions. 162 Table B.8: Joist Girder Cycle - Ground Crewman 1 Activity Classification VA Waste Classification Value Adding Time at Activity % of Time at Activity 0:01:53 10.13% 0:01:53 10.13% Extra Proc. Motion 0:08:58 0:03:53 48.25% 20.90% Transport 0:01:47 10% VA Total NVA 0:02:04 11.12% NVA Total Waiting 0:16:42 89.87% Grand Total 0:18:35 100% Ground Crewman #1 (White Shirt) Joist Girder Data NVA Waiting 11% VA 10% NVA Transport 10% NVA Motion 21% NVA Extra Processing 48% Figure B.10: Joist Girder Cycle - Ground Crewman 1 Ground crewman 2 was responsible for rigging each girder member for the crane with a tag line to help position the girder into the hands of the connectors above. Table B.9 and Figure B.11 show the VA, NVA and NVAR values for ground crewman 2. Ground crewman 2 accomplished no VA actions during the girder cycle. The largest portion of time (63 percent) was spent waiting on other crew members. 163 Table B.9: Joist Girder Cycle - Ground Crewman 2 Activity Classification NVA Waste Classification Motion Transport Waiting NVA Total Time at Activity % of Time at Activity 0:01:28 0:04:50 0:22:22 4.13% 14% 63.00% 0:28:40 80.75% 0:03:00 8.45% NVAR Mat. Pos. 0:03:50 10.80% NVAR Total T.W.S.A. 0:06:50 19.25% Grand Total 0:35:30 100% Ground Crewman #2 (Orange Shirt) Joist Girder Data NVAR TWSA 11% NVA Motion 4% NVA Transport 14% NVAR Material Positioning 8% NVA Waiting 63% Figure B.11: Joist Girder Cycle - Ground Crewman 2 The crane operator was responsible for lifting and positioning each member into final position in the structure, as well as providing temporary support for those members during alignment and bolting into place. Table B.10 and Figure B.12 show the VA, NVA and NVAR values for the crane operator. Note that the majority of the crane operator’s time was spent on temporary support activities (63 percent) while the connectors bolted each girder into place. This portion of NVAR highlights an area in which the cost of crane operation time could be reduced. The time attributed to transport included all movements of the girder after being lifted from the lay-down yard until the crane was temporarily supporting the member in final position in the structure. 164 Table B.10: Crane Operator Activity Classification NVA Waste Classification Motion Transport Waiting NVA Total Time at Activity % of Time at Activity 0:03:08 0:02:41 0:01:17 8.60% 7% 3.52% 0:07:06 19.49% NVAR 0:29:20 80.51% NVAR Total T.W.S.A. 0:29:20 80.51% Grand Total 0:36:26 100% Crane Operator - Joist Girder Data NVA Motion 9% NVA Transport 7% NVA Waiting 4% NVAR TWSA 80% Figure B.12: Crane Operator 2.3.1.3 Truss Cycle. The truss cycle included the following subtasks: setting up the crane rigging, positioning the truss into the hands of the connectors above, aligning and positioning the truss into its final position on the structure, bolting the truss and releasing the crane rigging from the truss. Figure B.13 shows the major tasks required to complete the truss installation. The shaded areas are used to indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations. Truss Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Two Columns and Two Girders Erected Rigging Truss for Crane Truss Erected Into Place Aligning Truss Bolting Ends of Truss Unhooking Rigging from Crane Purlins Erected After Bay Complete Note: Continual shipment of material to site. Figure B.13: Schedule for Truss Erection 165 All five members of the crew were observed during the girder erection cycle. Data for the five crew members is presented below. Connector 1 was involved with aligning and positioning each truss member, bolting the end connections and releasing the crane rigging after the connections were completed. Table B.11 and Figure B.14 show the VA, NVA and NVAR values for connector 1. Notice the large jump in NVA time (62 percent) spent by the connector during the column and girder cycles. Connector 1 contributed the largest portion of his time to the NVA activities of waiting and wasted movement. The waiting was due to the slow hookup for each member to the crane, along with the large swing distance required for each pickup between the lay-down yard and the final position of the truss member in the structure. Another notable observation was the amount of time wasted in motion, or the movement of the sky lift between each truss (25 percent). Finally, despite the erection of the truss being the most repetitive activity observed, it proved to be the largest contributor of NVA activities of all cycles observed for this crewman. Table B.11: Truss Cycle - Connector 1 Activity Classification VA Waste Classification Value Adding Time at Activity % of Time at Activity 0:03:44 12.17% 0:03:44 12.17% 0:07:40 0:11:25 24.99% 37.21% 0:19:05 62.19% 0:06:50 0:01:02 22.27% 3.37% NVAR Total 0:07:52 25.64% Grand Total 0:30:41 100% VA Total NVA Motion Waiting NVA Total NVAR Mat. Pos. T.W.S.A. 166 Connector #1 - Truss Data NVAR TWSA 3% VA 12% NVAR Material Positioning 22% NVA Motion 25% NVA Waiting 38% Figure B.14: Truss Cycle - Connector 1 Connector 2 was involved with aligning and positioning each truss member, bolting the end connections and releasing the crane rigging after the connections were completed. Table B.12 and Figure B.15 show the VA, NVA and NVAR values for connector 2. The NVA time spent by the connector during all cycles remained the same, roughly 50 percent. Connector 2 contributed the largest portion of his time to NVA activities. Time attributed to connecting the bolts was nearly twice that of connector 1 for the truss cycle. The difference may be attributed to observer discretion in determining when the individual tasks would start and stop. Finally, despite the erection of the truss being the most repetitive activity observed, it proved to be the largest contributor of NVA actions of all cycles observed for this crewman. Table B.12: Truss Cycle - Connector 2 Activity Classification VA Waste Classification Value Adding VA Total Time at Activity % of Time at Activity 0:07:40 25.46% 0:07:40 25.46% 0:00:49 0:06:06 2.71% 20.25% NVA Extra Proc. Motion Waiting 0:08:16 27.45% 0:15:11 50.42% 0:07:01 0:00:15 23.30% 0.83% NVAR Total 0:07:16 24.13% Grand Total 0:30:07 100% NVA Total NVAR Mat. Pos. T.W.S.A. 167 Connector #2- Truss Data NVAR Material Positioning 23% NVAR TWSA 1% VA 25% NVA Extra Processing 3% NVA Waiting 28% NVA Motion 20% Figure B.15: Truss Cycle - Connector 2 Ground crewman 1 was responsible for locating and marking individual truss members with a “north direction” arrow, rigging the truss for the crane and directing the crane operator for material positioning. Table B.13 and Figure B.16 show the VA, NVA and NVAR values for ground crewman 1. The largest percentage of time was attributed to NVA actions (96 percent), mainly waiting around. Note that a smaller amount of time was observed for this worker. The ground crewman left the observation area for the remainder of the observation time and, therefore, was no longer contributing any action to the cycle. Table B.13: Truss Cycle - Ground Crewman 1 - White Shirt Activity Classification NVA Waste Classification Extra Proc. Motion Waiting Time at Activity % of Time at Activity 0:02:50 0:03:22 0:05:11 23.81% 28.29% 43.56% 0:11:23 95.66% 0:00:31 4.34% NVAR Total 0:00:31 4.34% Grand Total 0:11:54 100% NVA Total NVAR Mat. Pos. 168 Ground Crewman #1 (White Shirt) Truss Data NVAR Material Positioning 4% NVA Extra Processing 24% NVA Waiting 44% NVA Motion 28% Figure B.16: Truss Cycle - Ground Crewman 1 Ground crewman 2 was responsible for rigging each truss member for the crane and using a tag line to position each truss into the hands of the connectors above. Table B.14 and Figure B.17 show the VA, NVA and NVAR values for ground crewman 2. The ground crewman accomplished no VA actions during the truss erection. The largest portion of time was spent waiting on the NVAR action of material positioning, roughly 67 percent. Notice that the amount of time contributed by the ground crewman was smaller than the other crew members. This was due to the ground crewman’s involvement in locating and rigging joist girders while the remainder of the crew continued to work on the truss cycle. Table B.14: Truss Cycle - Ground Crewman 2 Activity Classification NVA Waste Classification Waiting Time at Activity % of Time at Activity 0:02:59 32.55% 0:02:59 32.55% 0:05:46 0:00:25 62.91% 4.55% NVAR Total 0:06:11 67.45% Grand Total 0:09:10 100% NVA Total NVAR Mat. Pos. T.W.S.A. 169 Ground Crewman #2 (Orange Shirt) Truss Data NVAR TWSA 5% NVA Waiting 33% NVAR Material Positioning 62% Figure B.17: Truss Cycle - Ground Crewman 2 The crane operator was responsible for lifting and positioning each truss member into its final position in the structure, and providing temporary support while each member was aligned and bolted into place. Table B.15 and Figure B.18 show the VA, NVA and NVAR values for the crane operator. Note that the majority of crane operator time was spent on temporary support activities (73 percent) while the connectors aligned and bolted each truss into position. This portion of NVAR highlights an area in which the cost of crane operation time could be reduced. The time attributed to transport included all movements of the truss after being lifted from the lay-down yard until the crane was holding/bracing the member in final position in the structure. Table B.15: Truss Cycle - Crane Operator Activity Classification NVA Waste Classification Motion Transport Time at Activity % of Time at Activity 0:01:09 0:06:53 3.80% 23% 0:08:02 26.56% 0:22:13 73.44% NVAR Total 0:22:13 73.44% Grand Total 0:30:15 100% NVA Total NVAR T.W.S.A. 170 Crane Operator - Truss Data NVA Motion 4% NVA Transport 23% NVAR TWSA 73% Figure B.18: Truss Cycle - Crane Operator 2.3.2 Purlin Erection Process - Cycle No. 2 Following the erection of the columns, girders and truss, the crew returned to each erected bay to install the purlins. This cycle was completed before the distance of the farthest bay from the base of the crane became too great for the crane to safely position the purlin on top of the trusses. The data collected for the purlins involved a second crew; therefore, the referenced crew members in the following sections do not correlate to the crew members referenced during steel erection Cycle No. 1. In the following suibsections, each worker is referenced by the position that he/she occupied during the purlin cycle. These referenced names were used to identify crew members throughout the entire erection sequence. (Refer to the end of this case study to view these data sheets.) 2.3.2.1 Purlin Cycle. Figure B.19 shows the schedule for purlin erection. The purlin cycle included the following subtasks: setting up the crane rigging, positioning the purlin into the hands of the connectors above, aligning and positioning the purlin into its final position on the structure, bolting the truss and releasing the crane rigging from the truss. Purlin Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 One Bay Minimum Is Erected Rigging Purlin for Crane Purlin Erected Into Place Aligning Purlin Bolting Ends of Purlin Unhooking Rigging from Crane Entire Bay Is Plumbed and Welded Note: Continual shipment of material to site. Figure B.19: Schedule for the Purlin Erection Four crew members were observed during the purlin erection cycle. Data for the four crew members is presented in the following paragraph. 171 Connector 1 was involved in aligning/positioning purlin members, bolting the end connections and releasing the crane rigging after the connections were complete. Table B.16 and Figure B.20 show the VA, NVA and NVAR values for connector 1. Notice the large percentage of NVA time (66 percent) that was wasted during the cycle. Connector 1 contributed the largest portion of his time to the NVA subcategories of waiting and wasted movement (motion). Waiting was due to the slow hookup for each purlin to the crane along with the large swing distance required for each pick up between the lay-down yard and the final position of the purlin member in the structure. Note the amount of time used just for motion, or the movement of the sky lift between each purlin position (38 percent), which accounted for the largest portion of time consumed during the purlin cycle. Table B.16: Purlin Cycle - Connector 1 Activity Classification VA Waste Classification T ime at Activity % of T ime at Activitiy Value Adding 0:02:20 0:02:20 5.86% 5.86% Extra Proc. Motion Waiting 0:00:30 0:14:57 0:10:39 1.26% 37.55% 26.75% 0:26:06 65.55% NVAR T otal 0:05:51 0:05:32 0:11:23 14.69% 13.90% 28.59% Grand T otal 0:39:49 100.00% VA T otal NVA NVA T otal NVAR Mat. Pos. T .W.S.A. Connector #1 - Purlin Data NVAR TWSA 14% VA 6% NVAR Material Positioning 15% NVA Extra Processing 1% NVA Motion 37% NVA Waiting 27% Figure B.20: Purlin Cycle - Connector 1 172 Connector 2 had similar responsibilities to those of connector 1. Table B.17 and Figure B.21 show the VA, NVA and NVAR values for Connector 2. The results for connector 2 are identical to those of connector 1. Table B.17: Purlin Cycle - Connector 2 Activity Classification VA Waste Classification Time at Activity % of Time at Activitiy Value Adding 0:05:00 0:05:00 12.56% 12.56% Extra Proc. Motion Waiting 0:00:39 0:16:27 0:08:09 1.63% 41.31% 20.47% 0:25:15 63.42% NVAR Total 0:06:51 0:02:43 0:09:34 17.20% 6.82% 24.03% Grand Total 0:39:49 100.00% VA Total NVA NVA Total NVAR Mat. Pos. T.W.S.A. Connector #2 - Purlin Data NVAR Material Positioning 17% NVAR TWSA 7% VA 13% NVA Extra Processing 2% NVA Motion 41% NVA Waiting 20% Figure B.21: Purlin Cycle - Connector 2 The ground crewman was responsible for locating and marking the individual purlin members with a “north direction” arrow, rigging the purlin for the crane, using the tag line to position the purlins into the hands of the connectors above, and directing the crane operator for material positioning. Table B.18 and Figure B.22 show the VA, NVA and NVAR values for the ground crewman. The largest percentage of time was attributed to NVA actions (63 percent), mainly consisting of waiting around. There was a substantial amount of time spent on TWSA (30 percent). Support activities for the crane required the worker to attach rigging for each 173 purlin. The time contributed to the motion category was due to the worker walking between purlin locations on the ground. Table B.18: Purlin Cycle - Ground Crewman Activity Classification NVA Waste Classification Time at Activity % of Time at Activitiy Motion Transport Waiting 0:05:04 0:01:15 0:19:02 0:25:21 12.61% 3.11% 47.37% 63.09% Mat. Pos. 0:02:58 7.38% T.W.S.A. NVAR Total 0:11:52 0:14:50 29.53% 36.91% Grand Total 0:40:11 100.00% NVA Total NVAR Ground Crewman - Purlin Data NVA Motion 13% NVAR TWSA 30% NVA Transport 3% NVAR Material Positioning 7% NVA Waiting 47% Figure B.22: Purlin Cycle - Ground Crewman The crane operator was responsible for lifting and positioning each member into final position in the structure and providing temporary support of those members during alignment and bolting into place. Table B.19 and Figure B.23 show the VA, NVA and NVAR values for the crane operator. The crane operator spent most of his time (41 percent) transporting each purlin from the material lay-down area to the final position in the structure. Also, none of the crane operator time was VA, which was to be expected since he never physically changed the shape of the structure. 174 Table B.19: Purlin Cycle - Crane Operator Activity Classification NVA Waste Classification Time at Activity % of Time at Activitiy Motion Transport Waiting 0:07:02 0:16:25 0:07:59 0:31:26 17.58% 41.04% 19.96% 78.58% T.W.S.A. 0:08:34 21.42% NVAR Total 0:08:34 21.42% Grand Total 0:40:00 100.00% NVA Total NVAR Crane Operator - Purlin Data NVAR TWSA 21% NVA Motion 18% NVA Waiting 20% NVA Transport 41% Figure B.23: Purlin Cycle - Crane Operator 3.0 Results for the Crew: Crew Balance Charts As previously mentioned, two different crews were observed. The crew balance chart for the structural steel erection (Cycle No. 1) is shown on Figure B.24. The crew balance for the purlin erection cycle (Cycle No. 2) is shown on Figure B.25. These charts were compiled using the average times generated from the entire set of data observations. These average times resulted in an “idealized” crew balance. Due to the lack of sufficient repetition of the columns and girders, the crew balance charts were developed using only the truss data for Cycle No. 1. A crew balance chart was created for the purlin cycle as well. 175 Crew Balance - Truss Cycle TIME 0:15:45 0:15:30 0:15:15 0:15:00 0:14:45 0:14:30 0:14:15 0:14:00 0:13:45 0:13:30 0:13:15 0:13:00 0:12:45 0:12:30 0:12:15 0:12:00 0:11:45 0:11:30 0:11:15 0:11:00 0:10:45 0:10:30 0:10:15 0:10:00 0:09:45 0:09:30 0:09:15 0:09:00 0:08:45 0:08:30 0:08:15 0:08:00 0:07:45 0:07:30 0:07:15 0:07:00 0:06:45 0:06:30 0:06:15 0:06:00 0:05:45 0:05:30 0:05:15 0:05:00 0:04:45 0:04:30 0:04:15 0:04:00 0:03:45 0:03:30 0:03:15 0:03:00 0:02:45 0:02:30 0:02:15 0:02:00 0:01:45 0:01:30 0:01:15 0:01:00 0:00:45 0:00:30 0:00:15 0:00:00 Swinging Truss to Final Position Waiting Positioning Truss w/ Tag Line Preparing Truss Locate Steel Piece Waiting Waiting Truss Piece Attached Hooking Up Tag Line Swinging to Pick Next Truss Remove Truss Rigging Remove Truss Rigging Bolting Bottom Connection Waiting Bolting Bottom Connection Waiting Aligning Truss Bottom Connection Waiting Waiting Aligning Truss Bottom Connection Temporarily Supporting Truss Member Waiting Move Lift Waiting Move Lift Waiting Bolting Top Connection Bolting Top Connection Waiting Aligning Truss Top Connection Waiting Waiting Aligning Truss Top Connection Waiting Waiting Waiting Waiting Positioning Truss Tag Line Swinging Truss to Final Position Waiting Waiting Hooking Up Tag Line Preparing Truss Waiting Truss Piece Attached Waiting Waiting Locate Steel Piece Ground Crewman #1 Ground Crewman #2 Note: Average times for each task were used to construct this chart. Swinging to Pick Next Truss Crane Operator Connector #1 Figure B.24: Crew Balance Chart - Cycle No. 1 176 Connector #2 Crew Balance - Purlins - Cycle No. 2 TIME 0:10:00 0:09:45 0:09:30 0:09:15 0:09:00 0:08:45 0:08:30 0:08:15 0:08:00 0:07:45 0:07:30 0:07:15 0:07:00 0:06:45 0:06:30 0:06:15 0:06:00 0:05:45 0:05:30 0:05:15 0:05:00 0:04:45 0:04:30 0:04:15 0:04:00 0:03:45 0:03:30 0:03:15 0:03:00 0:02:45 0:02:30 0:02:15 0:02:00 0:01:45 0:01:30 0:01:15 0:01:00 0:00:45 0:00:30 0:00:15 0:00:00 Set Up Rigging for Purlin Holding Piece in Place to Be Bolted Unhooking Rigging Bolting Purlin Bolting Purlin Positioning Purlin Positioning Purlin Positioning Purlin Waiting Waiting Lifting/Swinging Purlin from Material Yard to Final Position in Structure Holding Tag Line and Positioning Waiting Moving to Next Purlin Position Attaching Rigging Holding for Hookup Set Up Rigging for Purlin Holding Piece in Place to Be Bolted Unhooking Rigging Bolting Purlin Moving to Next Purlin Position Unhooking Rigging Bolting Purlin Positioning Purlin Positioning Purlin Positioning Purlin Waiting Waiting Lifting/Swinging Purlin from Material Yard to Final Position in Structure Holding Tag Line and Positioning Waiting Moving to Next Purlin Position Attaching Rigging Holding for Hookup Set Up Rigging for Purlin Holding Piece in Place to Be Bolted Ground Crewman Crane Operator Note: Average times for each task were used to construct this chart. Unhooking Rigging Bolting Purlin Positioning Purlin Connector #1 Figure B.25: Crew Balance Chart - Cycle No. 2 177 Moving to Next Purlin Position Unhooking Rigging Bolting Purlin Positioning Purlin Connector #2 3.1 Crew Composition 1: Steel Erection (Cycle No. 1) The crew balance chart on Figure B.24 compares the five crew members observed during the truss cycle. Different shaded sections in the chart represent the separate tasks for each worker. For example, the dotted area represents a portion of the activity in which waiting occurred. The drivers for this cycle are connectors 1 and connector 2. The crane operator may appear to have been the driver because he had no waiting time in his cycle. However, if the two connectors had aligned the end connections at a faster rate, there would not have been much downtime for the crane while it temporarily supported the truss in final position. The average time from each activity was used to create a cycle duration. However, there was considerable variation between the two truss cycles observed. One timed cycle was six minutes 45 seconds in duration, and the other was 13 minutes 52 seconds. This kind of variability highlights an area where waste from an activity could be reduced. It is important to note that Figure B.24 represents an idealized crew balance using average task times. This ideal cycle is typically shorter than the actual cycle time in which task time variability causes an increase in the overall cycle time. The average time it took the crane to lift a truss from the material lay-down area on the ground and position it into final position in the structure, was two minutes 14 seconds. As noted on the crew balance chart on Figure B.24, the majority of time for both ground crewmen was spent waiting. The average waiting time during each cycle was three minutes 48 seconds for ground crewman 1, and one minute two seconds for ground crewman 2.1 Waiting accounted for 25 percent of the total time contributed by the group to the truss cycle (refer to the Table B.20 summary sheet for the entire truss cycle). The crew balance chart does not account for individuals working on other cycles while the remainder of the crew completed the truss cycle; therefore, in actuality the waiting periods shown for either ground crewman represent time in which the workers could have been locating and preparing girders and/or columns for their respective erection cycle. 3.2 Crew Composition 2: Purlin Erection (Cycle No. 2) Figure B.25 shows the crew balance chart for the purlin erection cycle. The cycle time for each purlin erection was significantly shorter than the cycle times observed for the truss erection. The driver for this activity was the crane operator. The crane operator contributed a significant portion of cycle time to transporting the purlins from the lay-down yard to their final position in the structure. This waste indicated a possible problem with the organization in the material laydown yard. The existing material layout required the crane to be rotated nearly 180 degrees for each pickup. For such a short cycle time, this material movement accounted for a large portion of the cycle. By reducing the time required to move each purlin by roughly one minute 45 seconds, the driver of the group then became connector 1, and the wasted time in waiting dropped to nearly zero for the entire group. 1 Note that the discrepancy between the two members may have been due to observer error. The crew balance chart is the idealized representation for the crew for erecting a truss. This ideal crew balance was structured around the crane operator’s movements. 178 The average time that it took the crane to move a purlin from the material lay-down area on the ground and position it into final position in the structure was one minute 12 seconds. The crew balance chart, Figure B.25, shows that a large portion of time for the remaining crewmen was wasted on waiting. The average waiting time during each cycle was 54 seconds for the ground crewman; 58 seconds for connector 1; and 41 seconds for connector 2.1 Waiting accounted for 28.67 percent of the total time attributed by the crew members to the erection of all purlins during this observation period. Refer to Table B.20 for the purlin cycle waste percentage breakdown. 3.3 General Observations about Crew Composition During the column cycle (Crew Composition 1), one ground crewman (No. 2) was observed waiting through nearly the entire cycle because the crew was oversized for that activity. The time attributed by ground crewman 1 during the column cycle was misleading because most of his time was spent on activities in other cycles (e.g., preparation work for the girders and trusses while the rest of the crew worked on columns). During the joist girder cycle, the majority of the total time for ground crewman 2 was attributed to waiting, while ground crewman 1 focused the majority of his time in extra processing activities. A large portion of waiting was attributed to aligning the joist girder with the free-standing column (i.e., the column was not connected to any other structural member at the time). The variations between the different cycles for VA, NVA and NVAR actions highlight the difficulty of correctly sizing a crew for multiple activities on a construction site. 4.0 Process Improvement Opportunities A goal of this report was to examine and document the different forms of waste that occur in construction operations. In general terms, inefficiencies were classified as the following three types: inefficiency due to waste (NVA activities), inefficiency due to unnecessary work (excessive NVAR activities) and inefficiency due to poorly designed work processes (ineffective VA activities). The following section identifies opportunities for process improvement by applying Ohno’s (Shingo and Dillon, 1989) seven wastes in production and then evaluating the production process against a more comprehensive set of lean principles. Table B.20 shows a summary for each cycle as well as the average weighted values for both cycles. Table B.21 lists the subset of activities that occurred to accomplish Cycle No. 1. Cycle No. 2 did not have any subset activities. The NVA and NVAR categories were broken down to clarify how time was spent in the observed cycles. 1 The crew balance chart is the idealized representation for the crew for erecting a purlin. This ideal crew balance was structured around the crane operator’s movements, and the averages for each crew member were used to best fit the cycle observed. 179 Table B.20: Entire Activity Steel Erection - Entire Process Steel Erection - Column, Girder, Truss VA Crew Member All Activities Ground Crewman #1 15% Ground Crewman #2 0% Connector #1 25% Connector #2 22% Crane Operator #1 0% Group Percentage Steel Erection - Purlins 13% Total Cumulative Time Observed for Entire Process Total Cumulative Time Observed for Cycle 1 Waste NVAR Extra Material In Proc. Waiting Processing Transport Movement Pos. Ins. 29% 30% 4% 17% 2% 0% 55% 3% 9% 11% 14% 0% 20% 2% 0% 20% 26% 0% 16% 5% 0% 22% 29% 0% 3% 0% 16% 6% 0% 0% 23% VA Crew Member Ground Crewman #3 Connector #3 Connector #4 Crane Operator #2 Group Percentage - Cycle 2 Weighted Average Percentages for Group 5% 6% 15% 16% Total Cumulative Time Observed for Cycle 2 Waste Extra Material Processing Transport Movement Pos. 0% 3% 13% 7% 1% 0% 38% 15% 2% 0% 41% 17% 0% 41% 18% 0% 0% 9:32:04 h:m:s 6:52:15 h:m:s TWSA 3% 8% 7% 5% 75% Total 100% 100% 100% 100% 100% 22% 100% 2:39:49 h:m:s VA + NVAR 21% 22% 59% 57% 75% 51% NVAR In Proc. Ins. 0% 0% 0% 0% TWSA 30% 14% 7% 21% Total 100% 100% 100% 100% VA + NVAR 37% 34% 37% 21% All Activities 0% 6% 13% 0% Waiting 47% 27% 20% 20% 5% 29% 1% 11% 27% 10% 0% 18% 100% 32% 11% 24% 4% 7% 18% 14% 0% 21% 100% 46% Table B.21: Summary of Subactivities Columns VA Crew Member Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 Group Percentage Joist Girder All Activities 37% 0% 27% 27% 0% Waiting 41% 53% 15% 15% 6% 16% 24% VA Crew Member Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 Group Percentage Truss All Activities 10% 0% 34% 16% 0% Waiting 11% 63% 10% 7% 4% 12% 20% VA Crew Member Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 Group Percentage All Activities 0% 0% 12% 25% 0% Waiting 44% 33% 37% 27% 0% 10% 25% Total Cumulative Time Spent on Column Waste Extra Material Processing Transport Movement Pos. 8% 0% 0% 4% 6% 6% 22% 7% 5% 0% 6% 33% 5% 0% 6% 33% 0% 19% 7% 69% 6% 9% 17% 5% Total Cumulative Time Spent on Joist Girder Waste Extra Material Processing Transport Movement Pos. 48% 10% 21% 0% 0% 14% 4% 8% 0% 0% 27% 24% 7% 0% 36% 32% 0% 7% 9% 0% 6% 19% 14% 7% Total Cumulative Time Spent on Truss Waste Extra Material Processing Transport Movement Pos. 24% 0% 28% 4% 0% 0% 0% 63% 0% 0% 25% 22% 3% 0% 20% 23% 0% 23% 4% 0% 3% 6% 180 16% 18% 2:17:00 h:m:s NVAR In Proc. Ins. 0% 0% 0% 0% 0% 0% NVAR In Proc. Ins. 0% 0% 0% 0% 0% 0% TWSA 10% 6% 14% 14% 0% Total 100% 100% 100% 100% 100% 24% 100% 2:43:08 h:m:s TWSA 0% 11% 5% 1% 81% Total 100% 100% 100% 100% 100% 22% 100% 1:52:07 h:m:s VA + NVAR 51% 12% 74% 74% 69% 56% VA + NVAR 10% 19% 63% 49% 81% 48% NVAR In Proc. Ins. 0% 0% 0% 0% 0% TWSA 0% 5% 3% 1% 73% Total 100% 100% 100% 100% 100% VA + NVAR 4% 67% 38% 50% 73% 0% 21% 100% 49% 4.1 Waste Associated with Laborers and Equipment 4.1.1 Waiting Waiting accounted for roughly one quarter of the total time observed during each cycle shown in Tables B.20 and B.21. The percentage of total time spent on waiting for the various cycles was as follows: • Column cycle--24 percent. • Joist girder cycle--20 percent. • Truss cycle--25 percent. In addition, the second crew spent 29 percent of its total time on waiting. For both crews, time spent waiting was highly dependent on the structure of the crew and the task that the crew was focused on during this observation period. For example, the column erection cycle required both ground crewmen to help align and position the column on the baseplate. In contrast, the erection of a truss may have only required one ground crewman to hold the tag line while positioning the truss member into the hands of the connectors above. 4.1.2 Waste of Motion For both crews, wasted motion occurred each time the sky lift was moved between truss, joist girder and purlin members that were erected during each cycle. Wasted motion also occurred each time the ground crew walked from point to point to locate material on the ground, or to position themselves near the next structural member to be erected in the lay-down yard. Finally, wasted movement occurred each time the crane swung from its holding position above the structure to the material lay-down area, where each structural member was temporarily located. The percentage of total time wasted due to motion for the column, joist girder, truss and purlin cycles was nine, 19, 16 and 27 percent, respectively. 4.1.3 Waste of Extra Processing Interpretation of this category included the use of defective materials delivered onsite that required modification to be operable. This included any preparation work around connection points such as cleaning out any metal slag that remained in the bolt holes from the manufacturer, and any other preparation work required for the bolts prior to insertion into the bolt holes. During truss and joist girder erection, the connection points were hammered to make the connections fit together. For the column, joist girder, truss and purlin cycles, the respective percentage of time spent on extra processing was five, seven, four and one percent. 4.1.4 Waste of Transportation Several instances were observed in which material was rehandled and moved into a more accessible position for the installation process. Transportation absorbed a significant amount of the crane operator’s time when moving each structural element from the lay-down yard to its holding position above the structure. Other material transportation observations included the ground crew carrying rigging from one steel piece to the next. Transport waste also occurred 181 when the material was positioned in the lay-down yard prior to the crane picking it up. However, this waste could not be quantified due to a limited observation period. 4.2 Waste Associated with Materials 4.2.1 Overproduction/Work in Progress (WIP) Overproduction waste (meaning too much of a building is produced) is rare in construction. Most construction reflects a “build to contract mentality” that requires a specific product(s) to be produced. WIP, on the other hand, is evident in construction but is dependent on the activity level being viewed. At the process-specific level, WIP is seldom observed. However, at the management level, each unfinished component of the production process represents WIP. For this study, WIP was represented by the unfinished structure. 4.2.2 Inventory/WIP Material deliveries were made continually throughout the construction process. The steel was delivered onsite on large flatbed trailers. It was observed sitting in the parking lot on top of trailers (minus the cab) for several days until the steel was needed in the structure. The material was moved into the lay-down area next to the structure, where it waited anywhere from one day to two weeks before being erected in place. The variability of the amount of material onsite was heavily influenced by the sporadic nature of the erection process. The caisson driller sustained abnormally high numbers of rejected caisson placements, with several of the concrete caissons being removed and replaced. The erection crew relocated several times to adjust to the caisson problem. 4.2.3 Defects Defects are defined as errors or deficiencies in a finished product that require additional work on the part of the original crew or a follow-up crew. A defective structural element (e.g., column, girder, etc.) is an example of a defect (i.e., the material has been passed through the value stream to the next work station). Another example of defects is included in the punch list process at the end of a job. When a defect in the finished product is found at this stage, a separate follow-up crew is activated to correct the defect. Hence, the defect is pushed onto the next work station. No waste associated with defects was observed. 5.0 Value Stream Analysis The following paragraphs describe the current value stream map for this structural steel erection process, beginning from the time the material was ordered and shipped from the manufacturer, through the construction production process, and ending with the material in final position in the facility. Figure B.26 is a simple flow diagram with each box representing a point in time when the material was handled, either to be moved or transformed into the next stage (phase) in the construction life cycle. 182 Manufacturer stores material onsite in its warehouse. Material is trucked to site and stored on flatbeds until needed. Material is trucked from parking lot to small material lay-down area near bay. Steel is offloaded by a heavy-duty forklift onto the ground. Each steel member is identified by a ground crewman and north arrow marked on it. Final placement of steel member by crane. Figure B.26: Material Flow Diagram Information on delivery and handling of the steel joists was obtained from the project manager. (Jackson 2003) Once it arrived onsite, the basic flow of the steel was as follows: • After the steel was manufactured, it remained onsite at the manufacturer’s warehouse until needed. • Each steel shipment consisted of all structural steel members required in one bay. Steel could not be stored onsite in a large material lay-down yard due to safety restrictions. The steel for three to four bays was stored on truck trailers (minus the cab) in the parking lot until needed. It usually remained in the parking lot for one week before being handled again and moved to the second staging area - a small material lay-down area next to the bay being erected. • Each load was handled by a heavy-duty forklift. Depending on the steel member type, one to three separate lifting actions were needed by the forklift operator to remove the entire load from the truck bed. • The load from the truck was placed on the ground in the same manner as it was on the truck. No shakeout occurred from the truck to the ground. • The piles from the truck were organized by member type (columns with columns, trusses with trusses, etc.). • Each steel member had a number that correlated to a number on the drawings. Following the placement of each pile on the ground, a ground crewman located the number on each steel piece and related it back to the foreman. This number helped the erection crew foreman with the proper erection sequence. • No shakeout occurred after placement on the ground. The crane was required to swing over the material lay-down area in random picks to reach each steel piece. One piece was picked at a time. This created a large material transport time for the crane operator. • After the steel members were placed near their respective bay staging areas, the crane moved the girders, bar joists and columns from the staging position to final position in the structure. 183 5.1 Case Study No. 2 Value Stream Map For the value stream map analysis depicted on Figure B.27, three levels were needed to represent both the material and labor components. Level One represents the major staging positions that material must go through to reach a finished state. Each time material was moved or transformed, a stage box is used to represent the process. Some of the stages included substages (Level Two) to represent processes that occurred simultaneously. The individual crew contributions to the value stream are represented on Level Three. Figures B.28, B.29 and B.30 show magnified views for each level introduced on Figure B.27. For this case study, this value stream represents material and worker movements associated with one crane. The project required three cranes of similar capacity to erect all the steel. The weighted average values for each work distribution category represent input from two of the construction teams. These values are assumed to be a reasonable representation for the entire erection process on the project. The steel members initially went through three major stages, which are represented on Level One. In Stage Two, each crane movement was observed; these crane movements included substages required for the entire steel erection process. Notice that the steel went through two stages before it reached Stage Three. Before the steel reached Stage One it sat in the parking lot for an average of five days. This did not occur for all the steel; however, the rule for inventorying was to represent the material piece in the order that it remained in one of the “inventory” positions the longest period. This stage was not observed directly. However, it was identified by the project superintendent as having occurred. The combined time period for both Stages One and Two was one day. The value stream ended once the steel erection process reached the detailing and welding stage. Again, the limited observation period prevented acquiring data about this stage for the entire steel erection process. Attention was focused on the four substages required for Stage Three of the value stream. In Levels Two and Three, the majority of time spent during the steel erection process was on the truss erection phase. Even though the crew was sized specifically for this activity, more than 50 percent of the time spent erecting trusses was NVA! Many NVAR actions were also observed during this substage process. The most significant contribution to the NVAR category was the crane operator being required to temporarily hold the steel members in position while bolt-up occurred. The most notable area for this value stream involved the multiple crane movements depicted in Level One, Stage Three. Material was not organized around the worker in any particular fashion. Instead, the crane was required to move several times in order to pick up a steel member, transport it to its final position and then hold it in place while being bolted. Waste attributed to waiting, transport and motion could be significantly reduced if the steel was delivered to the work area in a more efficient manner. Table B.22 shows the quick summary results for the work distribution values from Level One. The value stream map depicts the flow of material and workers for one phase of the steel erection. This is shown in the Quick Summary Table on the left-hand side. The right side of the table shows the results for all 14 phases when complete. These values are found by multiplying the results for one phase by 14. Figures B.31 and B.32 show the results for both sides of the Quick Summary Table. 184 Production Control Project Engineer Every 1-3 days Triggering Event Distribution of Tme from VSM For 14 Phases Project Feedback Percent Complete Time Allocation Field 14 Phases for the Steel Erection Process Level One Project Superintendent NVA Time NVAR Time 1 VA Time Work Time 0 Steel Supplier Daily As Required 1500 2000 2500 Man-hours Time Allocation Field OO 1000 Distribution of Time from VSM For One Phase All Steel for One Phase Is Ordered in One Shipment (6 bays per order on avg.) O 500 Steel In Place Awaiting Welding O NVA Time NVAR Time 1 VA Time Work Time 0 20 40 60 80 100 120 140 160 Man-hours Stage One - Steel is moved from parking lot to work area; has not been removed Days required 0.5 Equipment involved: Truck Inv Stage Two - Steel is offloaded in bundles of like S.S. members. Days required 0.5 Equipment involved: 1 Workers involved: Crew WT VA ( 0%) NVAR (0%) NVA (100%) Truck, forklifts Workers involved: Crew WT VA ( 0%) NVAR (20%) NVA (80%) Inv 2 8 0 0 8 Material Waits on Trailers in Parking Lot 5 2 16 0 3.2 12.8 0 4 Crane, two skylifts Workers involved: Crew WT VA ( 25%, 12%) NVAR (40%, 36%) NVA (45%, 52) Two Exterior columns erected Days required Equipment involved: Crane, two skylifts Workers involved: Crew Days required Equipment involved: Crane, two skylifts Workers involved: Crew WT VA ( 12%) NVAR (36%) NVA (52%) 3 5 WT VA ( 25%) NVAR (41%) NVA (44%) 7.3 1.1 2.9 3.2 Columns VA Crew Member Level Three Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 Group Percentage All Activities 37% 0% 27% 27% 0% 16% Waiting 41% 53% 15% 15% 6% Days required 24% 5% Crew Member Group Percentage All Activities 10% 0% 34% 16% 0% Waiting 11% 63% 10% 7% 4% 12% 20% 14% 10% 25% 3% 6% 16% 18% Waiting 47% 27% 20% 20% 5% 29% 50% 1% 13% Waiting 29% 55% 20% 16% 3% 23% VA Crew Member All Activities 0% 6% 13% 0% Waiting 47% 27% 20% 20% 11% 27% 68% 10% 5% 6% 15% 16% Total Cumulative Time Observed for Cycle 2 Waste Extra Processing Transport Movement Material Pos. 0% 3% 13% 7% 1% 0% 38% 15% 2% 0% 41% 17% 0% 41% 18% 0% 5% 29% 1% 11% 24% 4% 3 2 2 12 Two Interior Girders erected 0.18 Days required Equipment involved: Crane, two skylifts Workers involved: Crew WT VA ( 12%) NVAR (36%) NVA (52%) 3 5 7.3 1.1 2.9 3.2 0.32 3 5 13.0 1.6 4.7 6.7 2:17:00 h:m:s NVAR In Proc. Ins. 0% 0% 0% 0% 0% T.W.S.A 10% 6% 14% 14% 0% Total % 100% 100% 100% 100% 100% VA + NVAR % 51% 12% 74% 74% 69% 0% 24% 100% 56% 2:43:08 h:m:s NVAR In Proc. Ins. 0% 0% 0% 0% 0% T.W.S.A 0% 11% 5% 1% 81% Total % 100% 100% 100% 100% 100% VA + NVAR % 10% 19% 63% 49% 81% 0% 22% 100% 48% 36% In Proc. Ins. 0% 0% 0% 0% 0% T.W.S.A 0% 5% 3% 1% 73% Total % 100% 100% 100% 100% 100% VA + NVAR % 4% 67% 38% 50% 73% 0% 21% 100% 49% 39% 2:39:49 h:m:s NVAR In Proc. Ins. 0% 0% 0% 0% T.W.S.A 30% 14% 7% 21% Total % 100% 100% 100% 100% VA + NVAR % 37% 34% 37% 21% 0% 18% 100% 32% NVAR= Total Cumulative Time Observed for Entire Process Total Cumulative Time Observed for Cycle 1 Waste Extra Processing Transport Movement Material Pos. 30% 4% 17% 2% 3% 9% 11% 14% 2% 0% 20% 26% 5% 0% 22% 29% 0% 16% 6% 0% Table represents the time distribution for each element viewed during the observation period Cumulative Time Number of for Various Members Cumulative Time for Each Element Categories Observed 2:17:00 Total Cumulative Time for Three Columns 2:43:08 Total Cumulative Time for Two Girders 1:52:07 Total Cumulative Time for Two Trusses 2:39:49 Total Cumulative Time for Twelve Purlins Total Time 9:32:04 7.3 1.1 2.9 3.2 NVAR = Total Cumulative Time Observed for Cycle 2 Waste Extra Processing Transport Movement Material Pos. 0% 3% 13% 7% 1% 0% 38% 15% 2% 0% 41% 17% 0% 41% 18% 0% NVA= 5 1:52:07 h:m:s Material Pos. 4% 63% 22% 23% 0% All Activities 0% 6% 13% 0% Crane, two skylifts Workers involved: Crew WT VA ( .12%,10%) NVAR (36%,39%) NVA (52%,51%) 3 NVAR Movement 28% 0% 25% 20% 4% 28% 9:32:04 h:m:s 6:52:15 h:m:s NVAR In Proc. Ins. 0% 0% 0% 0% 0% 0% For 14 Phases 56 2016 man-hours 181 man-hours 674 man-hours 1162 man-hours Crane Movement #4 1.44 Days Required T.W.S.A 3% 8% 7% 5% 75% Total % 100% 100% 100% 100% 100% 22% 100% 2:39:49 h:m:s VA + NVAR % 21% 22% 59% 57% 75% 51% NVAR In Proc. Ins. 0% 0% 0% 0% T.W.S.A 30% 14% 7% 21% Total % 100% 100% 100% 100% VA + NVAR % 37% 34% 37% 21% 11% 27% 10% 0% 18% 100% 32% 7% 18% 14% 0% 21% 100% 46% Cycle Time for % of ETTRP % of Observed Avg # of Elements Estimated Time to % of ETTRP for % of Total Each Element Each Element Consumed by Each Time Each Steel Within One Phase Erect All Elements Time Observed (6 Bays) in a Phase Installed Category Element in a Phase Element Requires 0:45:40 24% 8% 8 6:05:20 12% 1.5% 1:21:34 29% 14% 8 10:52:32 22% 2.7% 0:56:03 20% 10% 30 4:01:45 56% 1.9% 0:13:19 28% 2% 24 5:19:38 11% 0.4% 50:19:15 Estimated Total Time Req. for One Phase (ETTRP) Average VA Percentage Average NVAR Percentage Average NVA Percentage 11% 35% 54% Figure B.27: Value Stream Map 185 0.87 Equipment involved: Equipment involved: NVAR = Transport 0% 0% 0% 0% 23% Steel Erection - Entire Process Steel Erection - Column, Girder, Truss VA Crew Member All Activities Ground Crewman #1 15% Ground Crewman #2 0% Connector #1 25% Connector #2 22% Crane Operator #1 0% Group Percentage - Cycle 2 Weighted Average Percentages for Group 19% Extra Processing 24% 0% 0% 3% 0% Crew Member Ground Crewman #3 Connector #3 Connector #4 Crane Operator #2 6% 52% NVA = Days required 41% Waiting 44% 33% 37% 27% 0% VA Group Percentage Steel Erection - Purlins 17% VA Total NVAR Total NVA Total Crane Movement #3 0.18 NVAR Sum All Activities 0% 0% 12% 25% 0% Steel Erection - Purlins Group Percentage - Cycle 2 9% Total Cumulative Time Spent on Truss Waste Crew Member Ground Crewman #3 Connector #3 Connector #4 Crane Operator #2 5 6% 7% NVA = VA Group Percentage 3 13 man-hours 48 man-hours 83 man-hours 120.0 12.9 44.9 62.2 Inventory Days per Phase 9 Two Interior columns erected 0.32 Total Cumulative Time Spent on Joist Girder Waste Extra Processing Transport Movement Material Pos. 48% 10% 21% 0% 0% 14% 4% 8% 0% 0% 27% 24% 7% 0% 36% 32% 0% 7% 9% 0% Truss Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 13.0 1.6 4.7 6.7 Days required Equipment involved: Crane, two skylifts Workers involved: Crew WT VA ( 25%) NVAR (41%) NVA (44%) 5 44% VA Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 20.2 2.7 7.6 9.9 Crane, two skylifts Workers involved: Crew WT VA ( .25%) NVAR (40%) NVA (45%) 3 Total Cumulative Time Spent on Columns Waste Extra Processing Transport Movement Material Pos. 8% 0% 0% 4% 6% 6% 22% 7% 5% 0% 6% 33% 5% 0% 6% 33% 0% 19% 7% 69% NVA Sum Joist Girder 5 Equipment involved: Two Exterior Girders erected 0.18 VA Total NVAR Total NVA Total Crane Movement #2 0.51 Equipment involved: Level Two Workers involved: Crew WT VA ( 11%) NVAR (34%) NVA (55%) Inv 4 Crane Movement #1 Days required Quick Summary for Level One For One Phase (3-6 bays) Working Days 4 Working Days Work Time 144 man-hours Work Time Stage Three - Structural steel erection process. Days required 3 Equipment involved: Crane, 3 two skylifts Crane, two skylifts Workers involved Crew WT VA ( 10%) NVAR (39%) NVA (51%) 3 5 57.5 6.1 22.2 29.2 Exterior Bays - Trusses are Erected Days required 1.11 Equipment involved: Crane, 3 two skylifts Workers involved: Crew 5 WT 44.6 VA ( 10%) 4.5 NVAR (39%) 17.5 NVA (51%) 22.5 3 5 35.0 2.9 12.2 19.9 Interior Bay - Trusses are Erected Days Required Equipment involved: Crane, two skylifts Workers involved Crew WT VA ( 10%) NVAR (39%) NVA (51%) Purlin Installation Process 0.56 Days Required Equipment involved: 3 Crane, 2 skylifts 5 22.3 2.3 8.8 11.2 Workers involved Crew WT VA ( 5%) NVAR (27%) NVA (68%) 0.32 3 5 12.7 0.6 3.4 8.6 Production Control Project Engineer Level One Distribution of Time from VSM for 14 Phases Project Feedback Percent Complete T im e A llo c a tio n F ie ld 14 Phases for the Steel Erection Process E v e ry 1 -3 d a y s Triggering Event Project Superintendent NVA Time NVAR Time 1 VA Time Work Time 0 Steel Supplier Daily As Required 1500 2000 2500 Man-hours T im e A llo c a tio n F ie ld OO 1000 Distribution of Time from VSM for One Phase All Steel for One Phase Is Ordered in One Shipment (6 bays per order on avg.) O 500 Steel In Place Awaiting Welding O NVA Time NVAR Time 1 VA Time Work Time 0 20 40 60 80 100 120 140 160 Man-hours Stage One - Steel is moved from parking lot to work area; has not been removed from trailers. Days required 0.5 Equipment involved: Truck Inv Material Waits on Trailers in Parking Lot 5 Workers involved: Crew WT VA ( 0%) NVAR (0%) NVA (100%) Stage Two - Steel is offloaded in bundles of like S.S. members. 1 Inv 2 8 0 0 8 0 Days required Equipment involved: Truck, Forklifts Workers involved: Crew WT VA ( 0%) NVAR (20%) NVA (80%) Stage Three - Structural steel erection process. 0.5 2 Inv 4 16 0 3.2 12.8 4 Days required 3 Equipment involved: Crane, 3 2 skylifts Workers involved: Crew 5 WT 0.0 VA ( 11%) 0.0 NVAR (34%) 0.0 NVA (55%) 0.0 Inventory Days per Phase 9 Figure B.28: Level One 186 Quick Summary for Level One For One Phase (3-6 bays) Working Days 4 Work Time 144 man-hours Working Days Work Time VA Total NVAR Total NVA Total VA Total NVAR Total NVA Total 13 man-hours 48 man-hours 83 man-hours For 14 Phases 56 2016 man-hours 181 man-hours 674 man-hours 1162 man-hours Level Two Two Exterior Columns Erected Days 0.18 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 7.3 VA ( 25%) 1.1 2.9 NVAR (41% 3.2 NVA (44%) Crane Movement #1 Crane Movement #2 Crane Movement #3 Crane Movement #4 Days 0.51 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 20.2 VA ( 25%, 2.7 7.6 NVAR (40% 9.9 NVA (45%, Days 0.18 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 7.3 VA ( .25%) 1.1 NVAR (40% 2.9 NVA (45%) 3.2 Days 1.44 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 57.5 VA ( .12%, 6.1 NVAR (36% 22.2 NVA (52%, 29.2 Days 0.87 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 35.0 VA ( 10%) 2.9 NVAR (39% 12.2 NVA (51%) 19.9 Two Exterior Girders Erected Days 0.32 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 13.0 VA ( 12%) 1.6 NVAR (36% 4.7 NVA (52%) 6.7 Two Interior Columns Erected Days 0.18 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 7.3 VA ( 25%) 1.1 NVAR (41% 2.9 NVA (44%) 3.2 Two Interior Girders Erected Days 0.32 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 13.0 VA ( 12%) 1.6 NVAR (36% 4.7 NVA (52%) 6.7 Figure B.29: Level Two 187 Exterior Bays Trusses Are Erected Days 1.11 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 44.6 VA ( 10%) 4.5 NVAR (39% 17.5 NVA (51%) 22.5 Interior Bay - Trusses Are Erected Days 0.56 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 22.3 VA ( 10%) 2.3 NVAR (39% 8.8 NVA (51%) 11.2 Purlin Installation Process Days 0.32 required Equipment involved: Crane, two 3 skylifts Workers involved: Crew 5 WT 12.7 VA ( 5%) 0.6 NVAR (27% 3.4 NVA (68%) 8.6 Columns VA Crew Member Level Three Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 Group Percentage All Activities 37% 0% 27% 27% 0% 16% Waiting 41% 53% 15% 15% 6% 24% Total Cumulative Time Spent on Columns Waste Extra Processing Transport Movement Material Pos. 8% 0% 0% 4% 6% 6% 22% 7% 5% 0% 6% 33% 5% 0% 6% 33% 0% 19% 7% 69% VA Group Percentage All Activities 10% 0% 34% 16% 0% Waiting 11% 63% 10% 7% 4% 12% 20% 7% NVA = 100% 56% 19% 14% 2:43:08 h:m:s NVAR In-Proc. Ins. 0% 0% 0% 0% 0% TWSA 0% 11% 5% 1% 81% Total 100% 100% 100% 100% 100% VA + NVAR 10% 19% 63% 49% 81% 0% 22% 100% 48% NVAR = 36% 1:52:07 h:m:s NVAR Movement 28% 0% 25% 20% 4% Material Pos. 4% 63% 22% 23% 0% In-Proc. Ins. 0% 0% 0% 0% 0% TWSA 0% 5% 3% 1% 73% Total 100% 100% 100% 100% 100% VA + NVAR 4% 67% 38% 50% 73% 10% 25% 3% 6% 16% 18% 0% 21% 100% 49% All Activities 0% 6% 13% 0% Waiting 47% 27% 20% 20% 5% 29% 50% Steel Erection - Entire Process Steel Erection - Column, Girder, Truss VA Crew Member All Activities Ground Crewman #1 15% Ground Crewman #2 0% Connector #1 25% Connector #2 22% Crane Operator #1 0% 1% 13% Waiting 29% 55% 20% 16% 3% 23% VA Crew Member NVAR = Total Cumulative Time Observed for Cycle 2 Waste Extra Processing Transport Movement Material Pos. 0% 3% 13% 7% 1% 0% 38% 15% 2% 0% 41% 17% 0% 41% 18% 0% NVA= Group Percentage - Cycle 2 Weighted Average Percentages for Group 24% Transport 0% 0% 0% 0% 23% VA Ground Crewman #3 Connector #3 Connector #4 Crane Operator #2 0% Extra Processing 24% 0% 0% 3% 0% Crew Member Group Percentage Steel Erection - Purlins VA + NVAR 51% 12% 74% 74% 69% Waiting 44% 33% 37% 27% 0% NVA = Group Percentage - Cycle 2 Total 100% 100% 100% 100% 100% All Activities 0% 0% 12% 25% 0% Steel Erection - Purlins Ground Crewman #3 Connector #3 Connector #4 Crane Operator #2 6% 52% VA TWSA 10% 6% 14% 14% 0% 41% Total Cumulative Time Spent on Truss Waste Crew Member Group Percentage 17% In-Proc. Ins. 0% 0% 0% 0% 0% NVAR Sum Total Cumulative Time Spent on Joist Girder Waste Extra Processing Transport Movement Material Pos. 48% 10% 21% 0% 0% 14% 4% 8% 0% 0% 27% 24% 7% 0% 36% 32% 0% 7% 9% 0% Truss Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 9% 44% Crew Member Ground Crewman #1 Ground Crewman #2 Connector #1 Connector #2 Crane Operator #1 6% 5% NVA Sum Joist Girder 2:17:00 h:m:s NVAR 11% 27% 68% 10% 39% 2:39:49 h:m:s NVAR In-Proc. Ins. 0% 0% 0% 0% TWSA 30% 14% 7% 21% Total 100% 100% 100% 100% VA + NVAR 37% 34% 37% 21% 0% 18% 100% 32% NVAR= Total Cumulative Time Observed for Entire Process Total Cumulative Time Observed for Cycle 1 Waste Extra Processing Transport Movement Material Pos. 30% 4% 17% 2% 3% 9% 11% 14% 2% 0% 20% 26% 5% 0% 22% 29% 0% 16% 6% 0% 5% 6% 15% 16% Total Cumulative Time Observed for Cycle 2 Waste Extra Processing Transport Movement Material Pos. 0% 3% 13% 7% 1% 0% 38% 15% 2% 0% 41% 17% 0% 41% 18% 0% 28% 9:32:04 h:m:s 6:52:15 h:m:s NVAR In-Proc. Ins. 0% 0% 0% 0% 0% 0% TWSA 3% 8% 7% 5% 75% Total 100% 100% 100% 100% 100% 22% 100% 2:39:49 h:m:s VA + NVAR 21% 22% 59% 57% 75% 51% NVAR Total 100% 100% 100% 100% VA + NVAR 37% 34% 37% 21% All Activities 0% 6% 13% 0% Waiting 47% 27% 20% 20% 5% 29% 1% 11% 27% 10% 0% 18% 100% 32% 11% 24% 4% 7% 18% 14% 0% 21% 100% 46% In-Proc. Ins. 0% 0% 0% 0% TWSA 30% 14% 7% 21% Table represents the time distribution for each element viewed during the observation period % of Observed Avg # of Elements Estimated Time to % of ETTRP for % of ETTRP Cumulative Time Number of Cycle Time for % of Total Time Each Steel Within One Phase Erect All Elements Each Element Consumed by Each for Various Members Each Element Cumulative Time for Each Element Time Observed Element Requires Element in a Phase Categories Observed Installed (6 Bays) in a Phase Category Total Cumulative Time for Three Columns 2:17:00 3 0:45:40 24 8 8 6:05:20 12 1.5 Total Cumulative Time for Two Girders 2:43:08 2 1:21:34 29 14 8 10:52:32 22 2.7 Total Cumulative Time for Two Trusses 1:52:07 2 0:56:03 20 10 30 4:01:45 56 1.9 2:39:49 12 0:13:19 28 2 24 5:19:38 11 0.4 Total Cumulative Time for Twelve Purlins Total Time 9:32:04 50:19:15 Estimated Total Time Req. for One Phase (ETTRP) Average VA Percentage Average NVAR Percentage Average NVA Percentage Figure B.30: Level Three 188 11% 35% 54% Table B.22 Quick Summary of Steel Process Quick Summary for Level One For One Phase (3-6 bays) Working Days 4 Working Days Work Time 144 man-hours Work Time VA Total 13 man-hours VA Total NVAR Total 48 man-hours NVAR Total NVA Total 83 man-hours NVA Total For 14 Phases 56 2016 181 674 1162 man-hours man-hours man-hours man-hours Time Allocation Field Distribution of Tim e from VSM for One Phase NVA Time NVAR Time 1 VA Time Work Time 0 20 40 60 80 100 120 140 160 Man-hours Figure B.31: Quick Summary Table - One Phase of the Steel Process T im e A llo catio n F ield Distribution of Tme from VSM for 14 Phases NVA Time NVAR Time 1 VA Time Work Time 0 500 1000 1500 2000 Man-hours Figure B.32: Quick Summary - 14 Phases of the Steel Process 189 2500 Of the 2,016 total workable hours committed to the steel erection process by this crew, only 181 of them were VA. Notice also that the greatest amount of time was spent on NVA actions (1,162 man-hours). A significant amount of the NVAR time was from the crane operator. This number could be reduced significantly if the erection processes were streamlined, e.g., by reducing the amount of waiting by each crew member. When just one phase in the cycle is considered, the numbers do not stand out as much when compared to the entire process. The fact that more than half of the man-hours contributed on the job were in the form of waste highlights an area needing vast improvement. Figure B.33 and Table B.23 illustrate how the work distribution values changed and grew throughout the process life cycle. The weighted average results found in Level Three of the value stream map were used to formulate all the VA, NVAR and NVA values in Table B.23. As shown on Figure B.33, the cumulative NVA line increased the fastest compared to the other work distribution values. The black vertical line indicates when the steel delivery and shakeout processes finished and the steel erection process began. This occurred periodically throughout the life cycle. The slope change in the cumulative calendar hours line resulted from additional workers periodically being added to the team to position each new phase of steel in front of the erection crew. This crew variation affected the data results for the remaining lines shown on Figure B.33. Material did not require multiple touches before erection. However, because the material was not organized on the ground in any systematic fashion, this disorganization resulted in larger values in the waste categories of motion and transportation for the erection crew. Work Distribution 3000 2500 Time (man-hours) 2000 Cumulative Calendar Hours Cumulative Work Hours Cumulative VA Hours 1500 Cumulative NVAR Hours. Marks Finishing Point of Initial Delivery Cumulative NVA Hours 1000 500 Note: the values used to create this chart are the average values from the Work Distribution values found for the entire crew. 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 Calendar Days Figure B.33: Work Distribution Life Cycle Graph 190 Table B.23: Spreadsheet of Values Used to Create Work Distribution Life Cycle Graph Stage Primary Activity for the Day Stage 1,2 Steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 Weekend Stage 3 Weekend Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 Weekend Stage 3 Weekend Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 Weekend Stage 3 Weekend One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 Weekend Stage 3 Weekend Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 Weekend Stage 3 Weekend Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 Weekend Stage 3 Weekend One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 Weekend Stage 3 Weekend Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins); Stage 1,2,3 steel is moved to work area and offloaded for next phase Stage 3 Weekend Stage 3 Weekend Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 One crew erecting S.S. (Columns, Joist Girder, Bar Joists and Purlins) Stage 3 Two crews erecting S.S. (Columns, Joist Girder and Bar Joists) Calendar Day Days Monday 1 Tuesday 1 Wednesday 1 Cumulative Calendar Days 1 2 3 Calendar Hours 32 40 40 Cumulative Cumulative Hours Calendar Workable Workable Crew Worked Hours Days Days Available Per Day 32 1 1 4 8 72 1 2 5 8 112 1 3 5 8 Workable Cumulative VA NVAR NVA VA Cumulative Hours Work Hours Percentage Percentage Percentage Hours VA Hours 32 32 0% 20% 80% 0 0 40 72 11% 35% 54% 4.4 4.4 40 112 11% 35% 54% 4.4 8.8 NVAR Hours 6.4 14 14 Cumulative NVAR Hours 6.4 20.4 34.4 NVA Hours 25.6 21.6 21.6 Cumulative NVA Hours 25.6 47.2 68.8 Thursday Friday Saturday Sunday Monday 1 1 1 1 1 4 5 6 7 8 72 40 40 40 40 184 224 264 304 344 1 1 0 0 1 4 5 5 5 6 9 5 5 5 5 8 8 0 0 8 72 40 0 0 40 184 224 224 224 264 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 7.92 4.4 0 0 4.4 16.72 21.12 21.12 21.12 25.52 25.2 14 0 0 14 59.6 73.6 73.6 73.6 87.6 38.88 21.6 0 0 21.6 107.68 129.28 129.28 129.28 150.88 Tuesday Wednesday Thursday 1 1 1 9 10 11 72 40 40 416 456 496 1 1 1 7 8 9 9 5 5 8 8 8 72 40 40 336 376 416 11% 11% 11% 35% 35% 35% 54% 54% 54% 7.92 4.4 4.4 33.44 37.84 42.24 25.2 14 14 112.8 126.8 140.8 38.88 21.6 21.6 189.76 211.36 232.96 Friday Saturday Sunday Monday Tuesday 1 1 1 1 1 12 13 14 15 16 72 40 40 40 40 568 608 648 688 728 1 0 0 1 1 10 10 10 11 12 9 5 5 5 5 8 0 0 8 8 72 0 0 40 40 488 488 488 528 568 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 7.92 0 0 4.4 4.4 50.16 50.16 50.16 54.56 58.96 25.2 0 0 14 14 166 166 166 180 194 38.88 0 0 21.6 21.6 271.84 271.84 271.84 293.44 315.04 Wednesday Thursday Friday Saturday Sunday 1 1 1 1 1 17 18 19 20 21 72 40 40 40 40 800 840 880 920 960 1 1 1 0 0 13 14 15 15 15 9 5 5 5 5 8 8 8 0 0 72 40 40 0 0 640 680 720 720 720 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 7.92 4.4 4.4 0 0 66.88 71.28 75.68 75.68 75.68 25.2 14 14 0 0 219.2 233.2 247.2 247.2 247.2 38.88 21.6 21.6 0 0 353.92 375.52 397.12 397.12 397.12 Monday Tuesday Wednesday 1 1 1 22 23 24 72 40 40 1032 1072 1112 1 1 1 16 17 18 9 5 5 8 8 8 72 40 40 792 832 872 11% 11% 11% 35% 35% 35% 54% 54% 54% 7.92 4.4 4.4 83.6 88 92.4 25.2 14 14 272.4 286.4 300.4 38.88 21.6 21.6 436 457.6 479.2 Thursday Friday Saturday Sunday Monday 1 1 1 1 1 25 26 27 28 29 72 40 40 40 40 1184 1224 1264 1304 1344 1 1 0 0 1 19 20 20 20 21 9 5 5 5 5 8 8 0 0 8 72 40 0 0 40 944 984 984 984 1024 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 7.92 4.4 0 0 4.4 100.32 104.72 104.72 104.72 109.12 25.2 14 0 0 14 325.6 339.6 339.6 339.6 353.6 38.88 21.6 0 0 21.6 518.08 539.68 539.68 539.68 561.28 Tuesday Wednesday Thursday 1 1 1 30 31 32 72 40 40 1416 1456 1496 1 1 1 22 23 24 9 5 5 8 8 8 72 40 40 1096 1136 1176 11% 11% 11% 35% 35% 35% 54% 54% 54% 7.92 4.4 4.4 117.04 121.44 125.84 25.2 14 14 378.8 392.8 406.8 38.88 21.6 21.6 600.16 621.76 643.36 Friday Saturday Sunday Monday Tuesday 1 1 1 1 1 33 34 35 36 37 72 40 40 40 40 1568 1608 1648 1688 1728 1 0 0 1 1 25 25 25 26 27 9 5 5 5 5 8 0 0 8 8 72 0 0 40 40 1248 1248 1248 1288 1328 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 7.92 0 0 4.4 4.4 133.76 133.76 133.76 138.16 142.56 25.2 0 0 14 14 432 432 432 446 460 38.88 0 0 21.6 21.6 682.24 682.24 682.24 703.84 725.44 Wednesday Thursday Friday Saturday Sunday 1 1 1 1 1 38 39 40 41 42 72 40 40 40 40 1800 1840 1880 1920 1960 1 1 1 0 0 28 29 30 30 30 9 5 5 5 5 8 8 8 0 0 72 40 40 0 0 1400 1440 1480 1480 1480 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 7.92 4.4 4.4 0 0 150.48 154.88 159.28 159.28 159.28 25.2 14 14 0 0 485.2 499.2 513.2 513.2 513.2 38.88 21.6 21.6 0 0 764.32 785.92 807.52 807.52 807.52 Monday Tuesday Wednesday 1 1 1 43 44 45 72 40 40 2032 2072 2112 1 1 1 31 32 33 9 5 5 8 8 8 72 40 40 1552 1592 1632 11% 11% 11% 35% 35% 35% 54% 54% 54% 7.92 4.4 4.4 167.2 171.6 176 25.2 14 14 538.4 552.4 566.4 38.88 21.6 21.6 846.4 868 889.6 Thursday Friday Saturday Sunday Monday 1 1 1 1 1 46 47 48 49 50 72 40 40 40 40 2184 2224 2264 2304 2344 1 1 0 0 1 34 35 35 35 36 9 5 5 5 5 8 8 0 0 8 72 40 0 0 40 1704 1744 1744 1744 1784 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 7.92 4.4 0 0 4.4 183.92 188.32 188.32 188.32 192.72 25.2 14 0 0 14 591.6 605.6 605.6 605.6 619.6 38.88 21.6 0 0 21.6 928.48 950.08 950.08 950.08 971.68 Tuesday Wednesday Thursday 1 1 1 51 52 53 72 40 40 2416 2456 2496 1 1 1 37 38 39 9 5 5 8 8 8 72 40 40 1856 1896 1936 11% 11% 11% 35% 35% 35% 54% 54% 54% 7.92 4.4 4.4 200.64 205.04 209.44 25.2 14 14 644.8 658.8 672.8 38.88 21.6 21.6 1010.56 1032.16 1053.76 Friday Saturday Sunday Monday Tuesday Wednesday 1 1 1 1 1 1 54 55 56 57 58 59 72 40 40 40 40 72 2568 2608 2648 2688 2728 2800 1 0 0 1 1 1 40 40 40 41 42 43 9 5 5 5 5 9 8 0 0 8 8 8 72 0 0 40 40 72 2008 2008 2008 2048 2088 2160 11% 11% 11% 11% 11% 11% 35% 35% 35% 35% 35% 35% 54% 54% 54% 54% 54% 54% 7.92 0 0 4.4 4.4 7.92 217.36 217.36 217.36 221.76 226.16 234.08 25.2 0 0 14 14 25.2 698 698 698 712 726 751.2 38.88 0 0 21.6 21.6 38.88 1092.64 1092.64 1092.64 1114.24 1135.84 1174.72 Average VA Percentage Average NVAR Percentage Average NVA Percentage 191 11% 35% 54% Appendix C Case Study No. 3 - Structural Steel 1.0 Overview 1.1 Project Goal The purpose of this case study was to collect data to develop a value stream map for the construction process. Observation was limited to structural steel erection. Field data were gathered on two separate value streams: the actual flow of the steel from the time it arrived on the jobsite until it was erected into final position, and the flow of worker activities performed to erect the steel. 1.2 Data Collection Procedure Data collection was accomplished in two consecutive days. Data observations were recorded on prepared data sheets (refer to the end of this case study to view these spreadsheets). Two different erection crews were observed. The first erection crew consisted of the following five workers: two ground crewmen, a foreman, one connector, and a crane operator. The second erection crew consisted of the following seven workers: two ground crewmen, two (end) connectors, two x-bracing connectors and a crane operator. Each observer was equipped with a digital camera. The digital video cameras were positioned to view the activity area at right angles to provide “depth” in both viewing directions. In the lab, two televisions were placed next to each other and used to view the recorded steel erection process. Using both cameras provide a three-dimensional view of the workspace for the data collection process. Each time a new task was started, an entry was made on the data sheet. For example, an entry might indicate that a worker was positioning a bar joist member. The next entry might indicate that the worker was bolting the end connection to the girder beneath. The elapsed time for each task was recorded as well as the observer’s judgment regarding whether the task was value adding (VA), non-value adding (NVA) or non-value adding but required (NVAR). 1.3 Project Description Three main structures were erected at this site. The case study focused on an area within the largest building. The total square footage for all buildings erected on this site was approximately 1.3 million. The observation period focused on the largest structure, which accounted for more than half of the total constructible square footage onsite. The structure was composed of several smaller bay sections, roughly measuring 60 feet by 60 feet. The observed erection activities for one crew occurred within four new bays, with a focus on columns, pod beam and spandrel beam erection. The second follow-up crew was observed handling the erection activities for bar joist members. The subset of the observed operations form part of the overall sequence of steel erection. The steel erection activities were preceded by foundation work, which was succeeded (following purlin erection) by the installation of wind bracing, final alignment and finish bolting. There were no visible constraints for the erection crews during this observation period; however, it was noted that an unfinished foundation wall along the north side of the structure will affect future erection sequences. The steel erection crews will not be able to erect the structure to the 192 end column line and will be required to return after the foundation pour to erect the remaining steel members. This future constraint had no impact on the efficiency within each bay of steel erection activities. 2.0 Steel Erection Work Process The steel erection process consists of the following two separate cycles: column erection and pod beam combo (PBC) erection. A PBC consists of a spandrel beam and a pod beam that are bolted together before Crew No. 1 takes the steel and erects it into position. Figure C.1 shows an elevation view of this configuration with the PBC in its final position on top of a column. Bolted Connection Spandrel Beam Pod Beam Column Figure C.1: Elevation View of a PBC on Top of a Column The following figures illustrate the erection cycle available for each movement of the crane. Figure C.2 shows a column and PBC already erected by Crew No. 1. Figure C.3 shows Crew No. 1 erecting the next column and PBC, while Crew No. 2 follows behind erecting the bar joists. This same process is followed for each new bay Crew No. 1 leads, while Crew No. 2 follows. Bar Joists Crew No. 2 PBC Crew No. 1 Column Figure C.3: Column, PBC and Bar Joists Erected Figure C.2: Column and PBC Erected 193 2.1 Erection Cycle No. 1 - Column, Spandrel Beam and Pod Beam Erection Cycle No. 1 focused on the erection of one column and one PBC per crane movement. Four iterations of this cycle occurred during this observation period. The cycle began when the crane operator lifted the column into position on top of the baseplate. Two ground crewmen and the foreman aligned and bolted the column to the baseplate. The choker was then removed from the crane ball. Beam clamps and tag lines (cable lines) were attached to the PBC, which was then lifted by the crane into final position. The connector used the sky lift to bolt the extruding spandrel beam section from the PBC to the adjacent PBC. The connector then moved with the sky lift to the top of the newly erected column and bolted the pod beam base to the top of the column. From there, the ground crewmen secured tag lines to an anchor device on either side of the column to temporarily support the member until the interconnecting bar joist was erected. For safety reasons, the crew could erect only two columns and PBCs ahead of the bar joist crew (Crew No. 2). Continuing with the cycle, the beam clamps were released from the PBC and the crane and crew moved to the next column line to continue the erection process. The cycle ended at the point chosen by the crane operator for the next column; then, the cycle was repeated. 2.2 Erection Cycle No. 2 - Bar Joists The bar joist erection cycle consisted of one main task, erecting the bar joist member. Twentyfour bar joist members were observed waiting to be erected. Twelve members were erected per crane movement. The process started after four columns and two PBCs were erected within a 60 foot by 60 foot bay. A second 30 ton crane was used during the bar joist erection cycle. The bar joist cycle began as ground crewman 3 attached an x-bracing member to a bar joist member while it was on the ground. Each bar joist was then lifted and positioned into place on top of the supporting roof beams (pod beam and spandrel beam). The members were bolted down on each end while the remaining sections of the x-bracing member were bolted into place. The crane was then released to pick up the next bar joist from the ground. After 12 bar joists were erected, the crane was moved to the next bay to continue the erection process. The configuration of the building frame necessitated that the steel erection crews perform four separate tasks. The bolting of each spandrel beam to a pod beam on the ground was not observed, but was included as one of the four tasks. Each task required movement from location to another and also required different amounts of equipment and workers. Therefore, in contrast to a highly repetitive manufacturing sequence, it was difficult to design an erection sequence that had the correct number of workers or equipment for each of the four separate tasks. During this observation period, the following materials were installed: • Four columns. • Four spandrel beams. • Four pod beams. • 24 bar joists. 194 • In addition, the following equipment and crew structures were observed: − Two sky lifts. − Two cranes. − Two crane operators. − 12 crew personnel. The following section analyzes each worker’s contributions to each cycle. Tables and figures were developed for each worker and for each task. The tables and figures describe the time spent on VA, NVA and NVAR actions within each cycle. 2.3 Steel Erection Process - Cycle No. 1 In the following subsections, each worker is referred to by the position that he/she occupied during the column and PBC erection sequence. These references are used to maintain consistency throughout the analysis. (Refer to the end of this case study to review the data sheets.) The cycle consisted of the following tasks: rigging the column for the crane, lifting the column into place, positioning the column, bolting the base of the column to the baseplate, unhooking the rigging from the column, attaching beam clamps to the PBC, lifting the PBC, positioning the PBC into place, bolting the PBC to adjacent PBC, bolting pod beam base to top of column, releasing beam clamps and moving to the next column line. Figure C.4 shows the major tasks required to complete the column installation. The shaded areas are used to visually indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations. Column and Pod Beam Combo Erection Task Order (process flow is shown, NOT TIME) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Rigging Column for Crane Column Lifted Into Place Positioning Column On Base Column Base Is Bolted Down Rigging Unhooked from Crane Beam Clamps Attached to PBC PBC Is Lifted Into Place Positioning PBC Into Place Bolting to Adjacent PBC Bolting to Column Releasing Beam Clamps Moving to Next Column Line Figure C.4: Schedule for a Column-PBC Erection Cycle The following analysis details the two structural members (column and PBC) separately to show how a crew may be sized efficiently for one structural member but over/undersized for another. Notice also the actual amount of time contributed to the cycle by each crew member. While a crew member may have a large VA value for his or her result, the total time attributed by that crew member to the cycle may be minuscule compared to other crew members. 195 2.3.1 Column Erection Cycle All members of the crew were involved with the column erections. The main participants in the column cycles included ground crewmen 1 and 2, the crew foreman, the connector and the crane operator. Ground crewman 1 was responsible for positioning the column, bolting the column to the baseplate and releasing the crane rigging after the bolting was complete. Table C.1 and Figure C.5 show the VA, NVA and NVAR values for ground crewman 1. During the column cycles, ground crewman 1 spent most of his time (45.10 percent) performing NVAR actions. The only VA actions occurred while he was bolting the column to the baseplate. Table C.1: Column Data for Ground Crewman 1 Activity Classification VA Waste Classification Total Time at Activity Value Adding VA Total % of Total Time 0:00:50 16.34% 0:00:50 16.34% NVA Waiting 0:01:58 38.56% 0:01:58 38.56% 0:01:30 0:00:48 29.41% 15.69% NVAR Total 0:02:18 45.10% Grand Total 0:05:06 100.00% NVA Total NVAR Mat. Pos T.W.S.A. Ground Crewman #1 Column Data NVAR TWSA 16% VA 16% NVAR Material Positioning 29% NVA Waiting 39% Figure C.5: Column Data for Ground Crewman 1 196 Ground crewman 2 rigged the column with a choker, positioned the column, bolted the column to the baseplate and released the choker from the crane once the column was set. Table C.2 and Figure C.6 show the VA, NVA and NVAR values for ground crewman 2. The time spent by ground crewman 2 on the column was more than what ground crewman 1 spent. In Table C.2, a large portion of time was spent on NVA actions, specifically on NVA waiting (32.76 percent). The different results of the two ground crewmen were due to ground crewman 2 spending more time on column activities. Table C.2: Column Data for Ground Crewman 2 A c tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n T o ta l T im e a t A c tiv ity V a lu e A d d in g % o f T o ta l T im e 0 :0 5 :1 1 1 9 .9 0 % 0 :0 5 :1 1 1 9 .9 0 % W a itin g 0 :0 8 :3 2 3 2 .7 6 % T ra n s p o rt 0 :0 2 :3 0 9 .6 0 % M o tio n 0 :0 2 :4 6 1 0 .6 2 % 0 :1 3 :4 8 5 2 .9 8 % 0 :0 2 :1 3 0 :0 4 :5 1 8 .5 1 % 1 8 .6 2 % N V A R T o ta l 0 :0 7 :0 4 2 7 .1 3 % G r a n d T o ta l 0 :2 6 :0 3 1 0 0 .0 0 % V A T o ta l NVA N V A T o ta l NV AR M a t. P o s T .W .S .A . Ground Crewman #2 Column Data NVAR TWSA 19% VA 19% NVAR Material Positioning 9% NVA Motion 11% NVA Waiting 32% NVA Transport 10% Figure C.6: Column Data for Ground Crewman 2 197 The crew foreman was involved with positioning and bolting the column into final position. Table C.3 and Figure C.7 show the VA, NVA and NVAR values for the crew foreman. According to Table C.3, 25.5 percent of time attributed to the column was VA. The largest portion of time (52.92 percent) was attributed to NVA actions. Table C.3: Column Data for the Foreman Ac tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n T o ta l T im e a t Ac tiv ity V a lu e A d d in g % o f T o ta l T im e 0 :0 4 :5 3 2 5 .5 0 % 0 :0 4 :5 3 2 5 .5 0 % W a itin g 0 :0 8 :4 6 4 5 .7 8 % E x tra P ro c . 0 :0 1 :2 2 7 .1 4 % 0 :1 0 :0 8 5 2 .9 2 % 0 :0 3 :2 8 0 :0 0 :4 0 1 8 .1 0 % 3 .4 8 % N V AR T o ta l 0 :0 4 :0 8 2 1 .5 8 % G ra n d T o ta l 0 :1 9 :0 9 1 0 0 .0 0 % V A T o ta l NVA N V A T o ta l N V AR M a t. P o s T .W .S .A . Crew Foreman Column Data NVAR Material Positioning 18% NVAR TWSA 3% VA 26% NVA Extra Processing 7% NVA Waiting 46% Figure C.7: Column Data for the Foreman The connector was not involved for a significant amount of time; he only assisted in positioning and bolting the column into its final place. Table C.4 and Figure C.8 show the VA, NVA and NVAR values for the connector. Contributing only three minutes 10 seconds to the cycle, the majority of the connector’s time was spent on the NVA action of waiting (86.84 percent). This left 25 seconds for the VA action of tightening one bolt on the baseplate. 198 Table C.4: Column Data for the Connector Activity Classification VA W aste Classification T otal Time at Activity Value Adding VA Total % of Total T ime 0:00:25 13.16% 0:00:25 13.16% NVA 0:02:45 86.84% NVA T otal M otion 0:02:45 86.84% G rand Total 0:03:10 100.00% The Connector Column Data VA 13% NVA Motion 87% Figure C.8: Column Data for the Connector The crane operator did not contribute any VA activities to the column erection cycle. Table C.5 and Figure C.9 show the VA, NVA and NVAR values for the crane operator. The crane operator was primarily involved with transporting columns from their lay-down area to their final position in the structure. After reaching the baseplate, the crane held the member in a temporary bracing position until the bolts are sufficiently tightened. These actions contributed to the NVAR subcategory TWSA value of 59.27 percent. 199 Table C.5: Column Data for the Crane Operator Activity Classification NVA Waste Classification Total Time at Activity Motion NVA Total % of Total Time 0:01:00 6.86% 0:01:00 6.86% 0:04:56 33.87% NVAR Mat. Pos 0:08:38 59.27% NVAR Total T.W.S.A. 0:13:34 93.14% Grand Total 0:14:34 100.00% The Crane Operator Column Data NVA Motion 7% NVAR TWSA 59% NVAR Material Positioning 34% Figure C.9: Column Data for the Crane Operator 2.3.2 Pod/Spandrel Beam Erection Cycle All five members of the crew were observed during the PBC erection cycle. Data for the five crew members are presented below. Ground crewman 1 positioned the PBC using tag lines and secured each tag line to anchors (an adjacent column or bar joist bundle lying on the ground) for temporary support. Table C.6 and Figure C.10 show the VA, NVA and NVAR values for ground crewman 1. The majority of ground crewman 1’s time (52.39 percent) was spent waiting. The small amount of VA actions shown in Table C.6 came from bolting stringer members to the PBC while it was on the ground. A significant amount of time (19.25 percent) was spent on TWSA functions. 200 Table C.6: PBC Data for Ground Crewman 1 A c tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n V a lu e A d d in g T o ta l T im e a t A c tiv ity % o f T o ta l T im e 0 :0 0 :5 5 0 .6 8 % 0 :0 0 :5 5 0 .6 8 % W a itin g 1 :1 0 :5 6 5 2 .3 9 % T ra n s p o rt M o tio n 0 :1 1 :2 5 0 :1 9 :1 4 8 .4 3 % 1 4 .2 0 % 1 :4 1 :3 5 7 5 .0 2 % 0 :0 6 :0 0 0 :0 0 :5 0 0 :2 6 :0 4 4 .4 3 % 0 .6 2 % 1 9 .2 5 % N V A R T o ta l 0 :3 2 :5 4 2 4 .3 0 % G ra n d T o ta l 2 :1 5 :2 4 1 0 0 .0 0 % V A T o ta l NVA N V A T o ta l NV AR M a t. P o s In -P ro c e s s In s . T .W .S .A . Ground Crewman #1 PBC Data NVAR TWSA 19% NVAR In-Process Inspection 1% NVAR Material Positioning 4% NVA Motion 14% NVA Transport 8% VA 1% NVA Waiting 53% Figure C.10: PBC Data for Ground Crewman 1 Ground crewman 2 mirrored ground crewman 1 during the PBC erection cycle. He positioned the PBC with tag lines and secured the tag lines to anchors (an adjacent column or bar joist bundles). Table C.7 and Figure C.11 show the VA, NVA and NVAR values for ground crewman 2. Again, a small percentage of VA time was spent bolting stringers to the PBC. The largest percentage of ground crewman 2’s time was spent on waiting (48.30 percent). The TWSA category made up 25.29 percent of ground crewman 2’s time. 201 Table C.7: PBC Data for Ground Crewman 2 Ac tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n T o ta l T im e a t Ac tiv ity V a lu e A d d in g % o f T o ta l T im e 0 :0 3 :1 4 2 .8 3 % 0 :0 3 :1 4 2 .8 3 % W a itin g 0 :5 5 :1 7 4 8 .3 0 % T ra n s p o rt 0 :0 5 :5 3 5 .1 4 % M o tio n 0 :1 2 :2 6 1 0 .8 6 % 1 :1 3 :3 6 6 4 .3 1 % 0 :0 7 :1 0 0 :0 1 :3 0 0 :2 8 :5 7 6 .2 6 % 1 .3 1 % 2 5 .2 9 % N V AR T o ta l 0 :3 7 :3 7 3 2 .8 7 % G ra n d T o ta l 1 :5 4 :2 7 1 0 0 .0 0 % V A T o ta l NVA N V A T o ta l N V AR M a t. P o s In -P ro c e s s In s . T .W .S .A . Ground Crewman #2 PBC Data VA 3% NVAR TWSA 25% NVAR In-Process Inspection 1% NVAR Material Positioning 6% NVA Motion 11% NVA Waiting 49% NVA Transport 5% Figure C.11: PBC Data for Ground Crewman 2 The foreman was responsible for the following actions: checking each member to ensure the proper erection sequence, attaching beam clamps to each PBC, positioning the PBC while it was hoisted off the ground and attaching stringer bars to the PBC while it was on the ground. Table C.8 and Figure C.12 show the VA, NVA and NVAR values for the foreman. NVA actions, specifically waiting (73.42 percent), consumed nearly the entire time spent by the foreman on the PBC. The remaining VA and NVAR actions contributed by the foreman made up only 15 percent, or roughly 16 minutes of the total time. 202 Table C.8: PBC Data for the Foreman A c tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n T o ta l T im e a t A c tiv ity V a lu e A d d in g % o f T o ta l T im e 0 :0 2 :4 2 2 .2 2 % 0 :0 2 :4 2 2 .2 2 % W a itin g 1 :2 9 :0 6 7 3 .4 2 % T r a n s p o rt 0 :0 4 :0 5 3 .3 6 % M o tio n 0 :1 0 :5 3 8 .9 7 % 1 :4 4 :0 4 8 5 .7 6 % 0 :0 7 :0 1 0 :0 3 :5 5 0 :0 3 :3 9 5 .7 8 % 3 .2 3 % 3 .0 1 % N V A R T o ta l 0 :1 4 :3 5 1 2 .0 2 % G r a n d T o ta l 2 :0 1 :2 1 1 0 0 .0 0 % V A T o ta l NVA N V A T o ta l NV AR M a t. P o s In -P ro c e s s In s . T .W .S .A . Crew Foreman PBC Data NVAR Material Positioning 6% NVAR TWSA 3% NVAR In-Process Inspection 3% VA 2% NVA Motion 9% NVA Transport 3% NVA Waiting 74% Figure C.12: PBC Data for the Foreman The connector was involved with the following: positioning and bolting the PBC next to the adjacent PBC, positioning and bolting the PBC on top of the column, moving the sky lift between locations and releasing the beam clamps from the PBC after boltup was complete. Table C.9 and Figure C.13 show the VA, NVA and NVAR values for the connector. The largest contribution to VA actions during Cycle No. 1 is shown. This accounted for nearly 25 percent of the connector’s time. However, over two thirds of the connector’s time (70 percent) was spent on the NVA actions of excess movement and waiting. 203 Table C.9: PBC Data for the Connector A c tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n T o ta l T im e a t A c tiv ity V a lu e A d d in g % o f T o ta l T im e 0 :3 3 :4 7 2 4 .6 0 % 0 :3 3 :4 7 2 4 .6 0 % W a itin g 0 :4 4 :3 7 3 2 .4 9 % E x tra P ro c . T ra n s p o rt M o tio n 0 :0 1 :3 2 0 :0 2 :5 8 0 :4 7 :0 1 1 .1 2 % 2 .1 6 % 3 4 .2 4 % 1 :3 6 :0 8 7 0 .0 0 % 0 :0 4 :5 2 0 :0 2 :3 3 3 .5 4 % 1 .8 6 % N V A R T o ta l 0 :0 7 :2 5 5 .4 0 % G ra n d T o ta l 2 :1 7 :2 0 1 0 0 .0 0 % V A T o ta l NVA N V A T o ta l NV AR M a t. P o s T .W .S .A . The Connector PBC Data NVAR Material Positioning 4% NVAR TWSA 2% VA 25% NVA Motion 34% NVA Transport 2% NVA Waiting 32% NVA Extra Processing 1% Figure C.13: PBC Data for the Connector The crane operator was responsible for lifting and positioning each PBC into its final position, as well as providing temporary support for the PBC while alignment and bolting took place. Table C.10 and Figure C.14 show the VA, NVA and NVAR values for the crane operator. The majority of the crane operator’s time was spent on TWSA (56.66 percent). This high value for NVAR actions highlights an area that should be focused on to reduce crane operating costs. Transport actions occurred when the PBC was lifted one foot off the ground, then held for a period of time before it was lifted the remaining distance up into position. 204 Table C.10: PBC Data for the Crane Operator Ac tivity C la ssific a tio n NV A W a ste C la ssific a tio n T o ta l T im e a t Ac tivity % o f T o ta l T im e W aitin g 0:10:30 8.34% E xtra P ro c. 0:01:04 0.85% T ran sp o rt M o tio n 0:20:36 0:17:24 16.36% 13.82% 0 :4 9 :3 4 3 9 .3 6 % NV A T o ta l NV AR M at. P o s 0:05:01 3.98% T .W .S .A. 1:11:21 56.66% NV AR T o ta l 1 :1 6 :2 2 6 0 .6 4 % G ra n d T o ta l 2 :0 5 :5 6 1 0 0 .0 0 % Crane Operator PBC Data NVA Waiting 8% NVA Extra Processing 1% NVA Transport 16% NVAR TWSA 57% NVA Motion 14% NVAR Material Positioning 4% Figure C.14: PBC Data for the Crane Operator 2.3.3 Bar Joist Cycle The bar joist cycle included the following subtasks: attaching x-bracing to the bar joist on the ground, setting up choker (rigging) for the crane, positioning the bar joist into the hands of the connectors above, aligning and positioning the bar joist into its final position, bolting each bar joist to roof beams, bolting x-bracing to adjacent bar joist and releasing the choker (rigging) from the bar joist. Figure C.15 shows the major tasks required to complete the bar joist installation. The shaded areas were used to visually indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations. 205 Bar Joist Erection 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Column and Pod Beam Combo Erected X-Bracing Attached on Ground Rigging Bar Joist for Crane Bar Joist Erected Into Place Aligning Bar Joist Bolting Ends of Bar Joist Bolting Opposite End of X-Bracing Unhooking Rigging from Crane Figure C.15: Schedule for Bar Joist Erection Cycle The second crew was involved with the erection of the bar joist members, and seven new crew members were observed during this cycle. Again, each worker was referred to by the position that he/she occupied during the bar joist erection sequence. These references are used to maintain consistency throughout the analysis. Data for the seven crew members is presented below. (Refer to the end of this case study to review the data sheets) The left connector was responsible for aligning and positioning each bar joist member and bolting the end connections. Table C.11 and Figure C.16 show the VA, NVA and NVAR values for the left connector. The left connector spent 17.6 percent of his time on VA activities. However, the largest portion of his time was spent waiting (47.66 percent). This highlights an area that should be focused on when trying to balance a crew for different activities. Table C.11: Bar Joist Data for the Left Connector Ac tivity C la ssific a tio n VA W a ste C la ssific a tion V alu e Ad d in g T ota l T im e a t Ac tivity % o f T o ta l T im e 0:14:26 17.60% 0 :1 4 :2 6 1 7 .6 0 % W aitin g 0:39:05 47.66% E xtra P ro c. T ran sp o rt M o tio n 0:03:25 0:01:05 0:07:51 4.17% 1.32% 9.57% 0 :5 1 :2 6 6 2 .7 2 % V A T o ta l NV A NV A T o ta l NV AR 0:16:08 19.67% NV AR T o ta l M at. P o s 0 :1 6 :0 8 1 9 .6 7 % G ra n d T o ta l 1 :2 2 :0 0 1 0 0 .0 0 % 206 Left Connector Bar Joist Data NVAR Material Positioning 20% VA 18% NVA Motion 10% NVA Transport 1% NVA Waiting 47% NVA Extra Processing 4% Figure C.16: Bar Joist Data for the Left Connector The right connector’s actions mirrored those of the left connector. He was involved with aligning and positioning each bar joist and bolting the end connection to the roof beam. Table C.12 and Figure C.17 show the VA, NVA and NVAR values for the right connector. Notice the similarities in the percentage breakdown of time between the right connector and the left connector. A similar amount of time was spent on VA actions (18.5 percent). Note that roughly 50 percent of the right connector’s time was wasted on waiting between bar joist cycles. Table C.12: Bar Joist Data for the Right Connector Ac tivity C la ssific a tio n VA W a ste C la ssific a tio n V a lu e A d d in g T o ta l T im e a t Ac tivity % o f T o ta l T im e 0:1 5 :10 1 8.5 0% 0 :1 5 :1 0 1 8 .5 0 % W a itin g 0:4 4 :36 5 4.3 9% E x tra P ro c. 0:0 0 :46 0.9 3% M o tio n 0:1 2 :31 1 5.2 6% 0 :5 7 :5 3 7 0 .5 9 % V A T o ta l NV A N V A T o ta l N V AR 0:0 8 :57 1 0.9 1% N V AR T o ta l M at. P o s 0 :0 8 :5 7 1 0 .9 1 % G ra n d T o ta l 1 :2 2 :0 0 1 0 0 .0 0 % 207 Right Connector Bar Joist Data NVAR Material Positioning 11% VA 18% NVA Motion 15% NVA Extra Processing 1% NVA Waiting 55% Figure C.17: Bar Joist Data for the Right Connector X-bracing connector 1 was responsible for moving and positioning the sky lift under each bar joist, hand tightening the bolts and “finish” tightening each bolt with a torque gun. Table C.13 and Figure C.18 show the VA, NVA and NVAR values for x-bracing connector 1. For Crew No. 2, x-bracing connector 1 performed the largest percentage of VA actions; nevertheless, his NVA activities still consumed the majority of his time. This sizable NVA amount resulted from moving the sky lift between each bar joist. The NVA subcategory motion accounted for more than 41 percent of x-bracing connector 1’s time. Table C.13: Bar Joist Data for X-Bracing Connector 1 A c tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n V a lu e A d d in g V A T o ta l T o ta l T im e a t A c tiv ity % o f T o ta l T im e 0 :2 5 :4 5 3 1 .4 0 % 0 :2 5 :4 5 3 1 .4 0 % NVA W a itin g 0 :2 0 :5 6 2 5 .5 3 % M o tio n 0 :3 4 :2 6 4 1 .9 9 % 0 :5 5 :2 2 6 7 .5 2 % N V A T o ta l NV AR 0 :0 0 :5 3 1 .0 8 % N V A R T o ta l T .W .S .A . 0 :0 0 :5 3 1 .0 8 % G ra n d T o ta l 1 :2 2 :0 0 1 0 0 .0 0 % 208 X-Bracing Connector #1 Bar Joist Data NVAR TWSA 1% VA 31% NVA Motion 42% NVA Waiting 26% Figure C.18: Bar Joist Data for X-Bracing Connector 1 X-bracing connector 2 was responsible for aligning each x-bracing member into its final position, assisting in boltup activities and releasing the choker line following boltup. Table C.14 and Figure C.19 show the VA, NVA and NVAR values for x-bracing connector 2. For the majority of the bar joist cycle, x-bracing connector 2 was waiting. When the bar joist was in motion, x-bracing connector 2 focused his time aligning the x-bracing member (32.42 percent) while x-bracing connector 1 bolted the member into its final position. X-bracing connector 2 contributed time to VA actions when he assisted in bolting the x-bracing member to the adjacent bar joist. Table C.14: Bar Joist Data for X-Bracing Connector 2 Activity C lassifica tio n VA W a ste C lassific ation V alu e Ad d in g V A T o tal T ota l T im e a t Ac tivity % o f T o tal T im e 0:05:40 6.91% 0 :05 :4 0 6 .91 % NV A W aitin g 0:45:28 55.45% 0 :45 :2 8 55 .4 5% 0:26:35 0:04:17 32.42% 5.22% NV AR T o ta l 0 :30 :5 2 37 .6 4% G ra n d T o tal 1 :22 :0 0 1 0 0.0 0 % NV A T o ta l NV AR M at. P o s T .W .S .A. 209 X-Bracing Connector #2 Bar Joist Data VA 7% NVAR TWSA 5% NVAR Material Positioning 32% NVA Waiting 56% Figure C.19: Bar Joist Data for X-Bracing Connector 2 Ground crewman 3 was involved with the following: bolting one side of the x-bracing member to the bar joist while it was on the ground, rigging the bar joist with a choker line and removing/reattaching the choker line for each bar joist lifted into position. Table C.15 and Figure C.20 show the VA, NVA and NVAR values for ground crewman 3. Attaching the x-bracing members to the bar joist while it remained on the ground contributed to the 14.37 percent VA value. Again, the largest percentage of time was wasted on waiting (60.61 percent). Table C.15: Bar Joist Data for Ground Crewman 3 Ac tivity C la ssific a tio n VA W a ste C la ssific a tio n V alu e Ad d in g T o ta l T im e a t Ac tivity % o f T o ta l T im e 0:11:47 14.37% 0 :1 1 :4 7 1 4 .3 7 % W aitin g 0:49:42 60.61% T ran sp o rt M o tio n 0:03:40 0:04:42 4.47% 5.73% 0 :5 8 :0 4 7 0 .8 1 % V A T o ta l NV A N V A T o ta l N V AR 0:12:09 14.82% N V AR T o ta l T .W .S .A . 0 :1 2 :0 9 1 4 .8 2 % G ra n d T o ta l 1 :2 2 :0 0 1 0 0 .0 0 % 210 Ground Crewman #3 Bar Joist Data NVAR TWSA 15% VA 14% NVA Motion 6% NVA Transport 4% NVA Waiting 61% Figure C.20: Bar Joist Data for Ground Crewman 3 Ground crewman 4 was solely responsible for positioning each bar joist member into the hands of the right connector above as the crane was hoisted. Table C.16 and Figure C.21 show the VA, NVA and NVAR values for ground crewman 4. No VA time was contributed to the cycle by ground crewman 4. For nearly the entire bar joist cycle, ground crewman 4 was waiting (81.44 percent). While his presence was needed for those few seconds in a cycle when the bar joist was being lifted, eliminating this crewman from the group may be a way to increase productivity. Table C.16: Bar Joist Data for Ground Crewman 4 Ac tivity C la ssific a tio n NV A W a ste C la ssific a tio n T o ta l T im e a t Ac tivity % o f T o ta l T im e W aitin g 1:06:47 81.44% T ran sp o rt 0:01:35 1.93% M o tio n 0:00:30 0.61% 1 :0 8 :5 2 8 3 .9 8 % NV A T o ta l NV AR 0:13:08 16.02% NV AR T o ta l M at. P o s 0 :1 3 :0 8 1 6 .0 2 % G ra n d T o ta l 1 :2 2 :0 0 1 0 0 .0 0 % 211 Ground Crewman #4 Bar Joist Data NVAR Material Positioning 16% NVA Motion 1% NVA Transport 2% NVA Waiting 81% Figure C.21: Bar Joist Data for Ground Crewman 4 Crane operator 2 was responsible for lifting and positioning each bar joist into its final position, as well as providing temporary support for the bar joist while alignment and bolting took place. Table C.17 and Figure C.22 show the VA, NVA and NVAR values for crane operator 2. The percentage of TWSA time (30.71 percent) was slightly higher than the percentage of time spent waiting (30.41 percent). Waiting occurred each time the crane sat while ground crewman 3 hooked up the choker line to the crane ball. It also occurred after the crane lifted the bar joist one foot off the ground and held it there until the connectors above were ready to receive the next bar joist. Table C.17: Bar Joist Data for Crane Operator 2 A c tiv ity C la s s ific a tio n NVA W a s te C la s s ific a tio n T o ta l T im e a t A c tiv ity % o f T o ta l T im e W a itin g 0 :2 4 :5 6 T ra n s p o rt 0 :0 5 :3 0 6 .7 1 % M o tio n 0 :1 2 :5 0 1 5 .6 5 % 0 :4 3 :1 6 5 2 .7 6 % 0 :1 3 :3 3 0 :2 5 :1 1 1 6 .5 2 % 3 0 .7 1 % N V A R T o ta l 0 :3 8 :4 4 4 7 .2 4 % G ra n d T o ta l 1 :2 2 :0 0 1 0 0 .0 0 % N V A T o ta l 3 0 .4 1 % NV AR M a t. P o s T .W .S .A . 212 Crane Operator #2 Bar Joist Data NVAR TWSA 30% NVA Waiting 30% NVA Transport 7% NVAR Material Positioning 17% NVA Motion 16% Figure C.22: Bar Joist Data for Crane Operator 2 3.0 Results for the Crew: Crew Balance Charts As previously mentioned, two different crews were observed. The crew balance chart for Crew No. 1 is shown on Figure C.23. The crew balance chart for Crew No. 2 is shown on Figure C.24. These charts were compiled using the average times generated from the entire set of data observations. These average times were used to create an “idealized” crew balance. 3.1 Crew Composition 1: Column and PBC Erection (Cycle No. 1) This crew balance chart includes the five crew members observed during the column and PBC erection cycle. The different sections represent the major tasks for each worker. The driver for Cycle No. 1 was the connector. While the connector was not significantly involved in the column cycle, his time attributed to the PBC caused the remaining members of the crew to wait while he completed all of his tasks to free up the crane for the next column. The average computed time from each task was used to create a cycle’s duration. Once an iteration of the cycle started, the times for each activity were observed to maintain similar results during each new cycle. However, variations in total cycle time occurred due to Crew No. 2’s inability to keep up with Crew No. 1. The average cycle time for Crew No. 1 was 20 minutes 30 seconds. This time did not include the total time required to reposition the crane, sky lift and crew at the new position. The high percentage of waiting within Cycle No. 1 highlights an area where waste could be reduced. It is important to note that Figure C.23 represents an idealized crew balance using average task times. This ideal cycle is typically shorter than the actual cycle time in which task time variability causes an increase in the overall cycle time. 213 TIME 0:20:30 0:20:15 0:20:00 0:19:45 0:19:30 0:19:15 0:19:00 0:18:45 0:18:30 0:18:15 0:18:00 0:17:45 0:17:30 0:17:15 0:17:00 0:16:45 0:16:30 0:16:15 0:16:00 0:15:45 0:15:30 0:15:15 0:15:00 0:14:45 0:14:30 0:14:15 0:14:00 0:13:45 0:13:30 0:13:15 0:13:00 0:12:45 0:12:30 0:12:15 0:12:00 0:11:45 0:11:30 0:11:15 0:11:00 0:10:45 0:10:30 0:10:15 0:10:00 0:09:45 0:09:30 0:09:15 0:09:00 0:08:45 0:08:30 0:08:15 0:08:00 0:07:45 0:07:30 0:07:15 0:07:00 0:06:45 0:06:30 0:06:15 0:06:00 0:05:45 0:05:30 0:05:15 0:05:00 0:04:45 0:04:30 0:04:15 0:04:00 0:03:45 0:03:30 0:03:15 0:03:00 0:02:45 0:02:30 0:02:15 0:02:00 0:01:45 0:01:30 0:01:15 0:01:00 0:00:45 0:00:30 0:00:15 0:00:00 Crew Balance Chart Cycle No.1 Waiting Waiting Waiting Waiting Waiting Waiting Booming down to move to next position Waiting Booming Down Moving to next position Releasing Beam Clamps from P.B.C. Waiting Waiting Waiting Waiting Waiting Waiting Moving Waiting Waiting Waiting Waiting Waiting Waiting Waiting Waiting Waiting Bolting First Side of P.B.C. again Holding PBC In Position while Bolt-Up occurs Moving Sky Lift Waiting Bolting opp. Side of P.B.C. to top of Column Moving Sky Lift Securing Tag Line to adjacent Column Securing Tag Line to adjacent Column Waiting Holding PBC In Position while Bolt-Up occurs Bolting P.B.C. to top of Column Waiting walking walking Moving to top of Column in Sky Lift Securing Tag Line to material on ground Securing Tag Line to material on ground Bolting Opp. Side of connection Waiting Moving Sky Lift Walking Using tag lines to Position P.B.C. while it is lifted into position Walking Using tag lines to Position P.B.C. while it is lifted into position Bolt two P.B.C. Together Waiitng Positioning PBC next to adjacent PBC Moving Sky Lift Waiting Removing Tag Line from previous P.B.C Releasing Crane Rigging Removing Tag Line from previous P.B.C Waiting Holding Pod Beam Combo Inspecting Plans Waiting Releasing Crane Rigging Waiting Bolting Stringers onto P.B.C. Bolting Column to Base Plate Bolting Column to Base Plate Positioning Col Onto =Base Plate Positioning Col onto Base Plate Ground Crewman 1 Lifting Waiitng Waiting Waiting Holding PBC In Position while Bolt-Up occurs Moving Sky Lift to Next Position Holding P.B.C. while on ground Attaching Rigging to Crane ball Securing Beam Clamps around P.B.C. Bolting Column to Base Plate Holding Column In Position While Bolting occurs Positioning Col onto Base Plate Lifting Column into position Attaching Rigging to Crane - COL. Rigging Column With Crane hoist Line Ground Crewman 2 Connector Foreman Figure C.23: Crew Balance Chart - Cycle No. 1 214 Lowering Hoist Line to be removed Moving and Setting up For Next Lift Crane Op. The average time that it took the crane to lift the column into position was one minute 14 seconds, and it took four minutes 53 seconds to lift the PBC from the ground into position. The PBC time included lifting the member one foot off the ground, holding it in that position until the connectors were ready, and finally lifting the PBC the remaining distance into position. The crew balance chart shows that the majority of time for both ground crewmen was spent waiting. The average waiting time during each cycle for ground crewman 1 was two minutes 46 seconds, and the average waiting time for ground crewman 2 was three minutes 13 seconds.1 Waiting accounted for 41 percent of the total time contributed by the group to the column and PBC cycle (refer to Table C.20 summary sheet for Cycle No. 1). For each cycle, each crewman contributed roughly seven minutes to the NVA category of waste. This value sums up the multiple independent waiting periods that occurred between activities for each ground crewman. It is shown as one lump segment to simplify the balance chart for easier reading. 3.2 Crew Composition 2: Bar Joist Erection (Cycle No. 2) Figure C.24 shows the crew balance chart for the bar joist erection cycles. The cycle times for the bar joist erection were significantly shorter than the cycle times observed for the column and PBC erection. Even though less time was required for the erection of each bar joist, Crew No. 2 had to erect 12 bar joists per bay before the crane could be moved to the next position. Cycle No. 2 was assumed to have fewer waiting periods because there was only one type of structural member the crew erected (as compared to Crew No. 1 with the column and PBC members). However, each member in Crew No. 2 spent large amounts of time waiting. Each bar joist member took roughly two minutes 45 seconds to erect. It took Crew No. 2 approximately 33 minutes to erect the 12 bar joists per bay. The driver for this activity was the crane operator, who contributed a large portion of the cycle time to holding the bar joist in position while boltup occurred. This action contributed to the NVAR time for the cycle. While this action may never be completely eliminated from the erection cycle, it could be minimized by focusing on each crew member’s task while the crane holds the bar joist in position. Refer to Table C.18 for the waste percentage breakdown for Cycle No. 2. On average, it took 51 seconds for the crane to hold the bar joist in final position to allow boltup to occur. The minimum time for this activity was 19 seconds, while the maximum time was two minutes 55 seconds. This variability in task time highlights an area where cycle time could be reduced. If Crew No. 2 could consistently position and bolt each bar joist member in 19 seconds, 41 seconds could be eliminated from the bar joist cycle time. This in turn could shave more than 6 minutes from the “ideal” cycle represented on Figure C.24. A large portion of time for the remaining crewmen was wasted on waiting; roughly 51 percent of the total crew time during Cycle No. 2 was wasted on waiting. This amounted to four hours 51 minutes 30 seconds of waiting time shared between the members of Crew No. 2. Refer to Table C.21 for the bar joist cycle waste percentage breakdown. 1 Note that the discrepancy between the two ground crewmen may be due to observer error. The crew balance chart is an idealized representation for a column and PBC erection crew. This ideal crew balance is structured around the crane operator’s movements. 215 TIME 0:10:00 Hand Tightening Bolts 0:09:45 0:09:30 Moving Sky Lift 0:09:15 Waiting 0:09:00 0:08:45 Waiting 0:08:30 0:08:15 0:08:00 0:07:45 Tightening bolts 0:07:30 with an impact gun 0:07:15 Hand Tightening Bolts 0:07:00 0:06:45 0:06:30 Moving Sky Lift 0:06:15 Waiting 0:06:00 0:05:45 Waiting 0:05:30 0:05:15 0:05:00 0:04:45 Tightening bolts 0:04:30 with an impact gun 0:04:15 Hand Tightening Bolts 0:04:00 0:03:45 0:03:30 Moving Sky Lift 0:03:15 Waiting 0:03:00 0:02:45 Waiting 0:02:30 0:02:15 0:02:00 0:01:45 Tightening bolts 0:01:30 with an impact gun 0:01:15 Hand Tightening Bolts 0:01:00 0:00:45 0:00:30 Moving Sky Lift 0:00:15 Waiting 0:00:00 X-BConnector #1 CrewBalance Chart Cycle #2 Pos. Bar Joist Pos. Bar Joist Positioning XB Waiting Waiting Waiting Waiting Waiting Waiting Moving Moving Bolting Bar Joist Bolting Bar Joist to Girder Waiting Releasing Crane Rig Positioning Bar Joist Positioning XB Lifting B.J. into Pos. Waiting Waiting Waiting Waiting Moving Moving Bolting Bar Joist Bolting Bar Joist to Girder Waiting Releasing Crane Rig Positioning Bar Joist Lifting B.J. into Pos. Waiting Waiting Waiting Waiting Moving Moving Bolting Bar Joist Bolting Bar Joist to Girder Waiting Positioning Bar Joist Waiting Left Connector Waiting Waiting Right Connector Lifting 1ft off ground Waiting For Hookup Lowering Hoist Line Waiting Holding Bar Joist While Bolt up occurs Waiting Lifting B.J. into Pos. Waiting Positioning Bolting one side of X-B to Bar Joist Ground Crewman #3 Waiting Waiting Waiting X-BConnector #2 Waiting Waiting Positioning XB Waiting Positioning Waiting Waiting Releasing Crane Rig Holding Bar Joist While Bolt up occurs Waiting Bolting one side of X-B to Bar Joist Hooking up Hoist line Prepping Bar Joist Positioning Bar Joist Waiting Lifting 1ft off ground Waiting For Hookup Lowering Hoist Line Waiting Waiting Positioning XB Waiting Waiting Positioning XB Waiting Positioning Waiting Waiting Positioning Bar Joist Holding Bar Joist While Bolt up occurs Waiting Bolting one side of X-B to Bar Joist Hooking up Hoist line Prepping Bar Joist Positioning XB Waiting Lifting 1ft off ground Waiting For Hookup Lowering Hoist Line Waiting Waiting Waiting Waiting Waiting Positioning Bar Joist Lifting B.J. into Pos. Waiting Waiting Bolting one side of X-B to Bar Joist Hooking up Hoist line Prepping Bar Joist Positioning XB Waiting Positioning Waiting Ground Crewman #4 Lifting 1ft off ground Crane Operator #2 Figure C.24: Crew Balance Chart - Cycle No. 2 3.3 General Observations About Crew Composition During both observed cycles, the majority of time was spent waiting. In Crew No. 1, the foreman waited for nearly the entire cycle time. His contributions to the NVAR action of in-process inspections involved checking the plans to ensure a correct erection sequence. This action of checking the steel members appears to be redundant because the columns and roof beam components were already placed on the ground in the order of erection. The remaining actions contributed by the foreman in Cycle No. 1 could have easily been handled by crew members 1 and 2, thus eliminating the foreman from the cycle. In Crew No. 2, ground crewman 4 was expendable since his only contribution was positioning each bar joist into the hands of the connectors above as it was lifted by the crane. This task could have easily been handled by ground crewman 3, reducing his waiting time, as well as the entire waiting percentage for the entire crew on the bar joist cycle. The results in Tables C.18 through C.21 show the variations of VA, NVA and NVAR for each cycle. These variations highlight the difficulty of correctly sizing a crew for multiple activities on a construction site. 216 Table C.18: Waste Percentage Breakdown with Both Crews Steel Erection - Cycle #1 Crew Member Total Cumulative Time for Steel Erection VA All Activities Crew for Cycle 1 Ground Crewman #1 Ground Crewman #2 Connector Foreman Crane Operator #1 Crew For Cycle 2 Left Connector Right Connector X-Bracing Con. #1 X-Bracing Con. #2 Ground Crewman #3 Ground Crewman #4 Crane Operator #2 Group Percentage Waste VA + NVAR % 19% 24% 2% 3% 57% 100% 100% 100% 100% 100% 26% 38% 30% 19% 64% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 5% 15% 0% 31% 100% 100% 100% 100% 100% 100% 100% 37% 29% 32% 45% 29% 16% 47% 0% 15% 100% 35% 14% 11% 35% 8% 13% 5% 7% 3% 7% 7% 1% 1% 0% 3% 0% 1% 0% 0% 0% 4% 2% 7% 10% 15% 42% 0% 6% 1% 16% 20% 11% 0% 32% 0% 16% 17% 5% 15% 9% Waiting Extra Processing 1% 6% 24% 5% 0% 52% 45% 32% 70% 7% 0% 0% 1% 1% 1% 8% 6% 2% 3% 15% 18% 19% 31% 7% 14% 0% 0% 48% 54% 26% 55% 61% 81% 30% 4% 1% 0% 0% 0% 0% 0% 10% 46% 1% Transport Movement 21:16:30 AM h:m:s Total % Material Pos. NVAR In Proc. Ins. T.W.S.A Table C.19: Summary of Cycle No. 1 - Column and PBC Columns Crew Member Ground Crewman #1 Ground Crewman #2 Connector Foreman Crane Operator #1 Total Cumulative Time Spent on Columns VA All Activities 16% 20% 13% 26% 0% Group Percentage Pod Beam Combo Crew Member Ground Crewman #1 Ground Crewman #2 Connector Foreman Crane Operator #1 17% Waste 39% 33% 0% 46% 0% Extra Processing 0% 0% 0% 7% 0% 28% 2% Waiting 0% 10% 0% 0% 0% 0% 11% 87% 0% 7% Material Pos. 29% 9% 0% 18% 34% 4% 10% 18% Transport Movement NVAR In Proc. Ins. 0% 0% 0% 0% 0% 0% Total Cumulative Time Spent on PBC VA All Activities 1% 3% 25% 2% 0% Group Percentage 6% Waiting 52% 48% 32% 73% 8% 43% Waste Extra Transport Movement Processing 0% 8% 14% 0% 5% 11% 1% 2% 34% 0% 3% 9% 1% 16% 14% 0% 7% 17% Material Pos. 4% 6% 4% 6% 4% NVAR In Proc. Ins. 1% 1% 0% 3% 0% 5% 1% 1:08:02 h:m:s T.W.S.A 16% 19% 0% 3% 59% Total % 100% 100% 100% 100% 100% 100% 22% 10:34:28 h:m:s VA + NVAR % 61% 47% 13% 47% 93% 56% 19% 25% 2% 3% 57% 100% 100% 100% 100% 100% VA + NVAR % 25% 36% 30% 14% 61% 21% 100% 33% T.W.S.A Total % Table C.20: Summary of Subtasks for Cycle No. 1 Steel Erection - Cycle #1 Crew Member Ground Crewman #1 Ground Crewman #2 Connector Foreman Crane Operator #1 Group Percentage Total Cumulative Time for Steel Erection VA Waste All Extra Material Waiting Transport Movement Activities Processing Pos. 1% 52% 0% 8% 14% 5% 6% 45% 0% 6% 11% 7% 24% 32% 1% 2% 35% 3% 5% 70% 1% 3% 8% 7% 0% 7% 1% 15% 13% 7% 7% 41% 1% 7% 217 16% 6% NVAR In Proc. Ins. 1% 1% 0% 3% 0% 1% 11:42:30 h:m:s 19% 24% 2% 3% 57% 100% 100% 100% 100% 100% VA + NVAR % 26% 38% 30% 19% 64% 21% 100% 35% T.W.S.A Total % Table C.21: Summary for Cycle No. 2 Bar Joists Bar Joists Crew Member Left Connector Right Connector X-Bracing Con. #1 X-Bracing Con. #2 Ground Crewman #3 Ground Crewman #4 Crane Operator #2 Group Percentage Total Cumulative Time Spent on Bar Joists VA All Activities 18% 19% 31% 7% 14% 0% 0% 13% Waste 48% 54% 26% 55% 61% 81% 30% Extra Processing 4% 1% 0% 0% 0% 0% 0% 51% 1% Waiting 1% 0% 0% 0% 4% 2% 7% 10% 15% 42% 0% 6% 1% 16% Material Pos. 20% 11% 0% 32% 0% 16% 17% 2% 13% 14% Transport Movement NVAR In Proc. Ins. 0% 0% 0% 0% 0% 0% 0% 0% 9:34:00 h:m:s 0% 0% 1% 5% 15% 0% 31% 100% 100% 100% 100% 100% 100% 100% VA + NVAR % 37% 29% 32% 45% 29% 16% 47% 7% 100% 34% T.W.S.A Total % 4.0 Process Improvement Opportunities A goal of this report was to examine and document the different forms of waste that occur in construction operations. In general terms, inefficiencies were classified as the following three types: inefficiency due to waste (NVA activities), inefficiency due to unnecessary work (excessive NVAR activities) and inefficiency due to poorly designed work processes (ineffective VA activities). The following section identifies opportunities for process improvement by applying Ohno’s (Shingo and Dillon 1989) seven wastes in production and then evaluating the production process against a more comprehensive set of lean principles. Table C.18 shows the time spent on VA, NVA and NVAR activities as a percentage of total cumulative time spent by both crews during the observation period of the steel erection process. Table C.19 shows the subset of activities that occurred to accomplish the column and PBC erection process. Tables C.20 and C.21 show the total percentage breakdown for the observed cycles. The NVA category is further divided into time spent in the waiting, extra processing, transport and movement categories. Additionally, NVAR is broken down into its three subcategories to clarify how time was spent within the observed cycles. 4.1 Waste Associated with Laborers and Equipment 4.1.1 Waiting Waiting accounts for nearly half of the total time observed for each cycle shown above in Tables C.18 through C.21. The column erection cycle shows the least amount of waiting at 28 percent, followed by the PBC cycle at 43 percent. Waiting for both crews was highly dependent on the structure of the crew and the task that the crew was focused on during the observation period. For example, the column erection cycle required both ground crewmen to help align and position the column on the baseplate, while the erection of a bar joist might have only require one ground crewman to position it into the hands of the connectors above. 4.1.2 Waste of Motion For both crews, wasted motion occurred each time the sky lift was moved between column lines, roof beam connection points and bar joist members that were erected during each cycle. Wasted motion also occurred each time the ground crewmen walked between anchor points to secure the column and PBC during Cycle No. 2. Finally, motion was wasted each time the connectors moved between connection points for each bar joist member. The percentage of total time wasted due to motion for the column, PBC and bar joist cycles was 10, 17, and 13 percent, respectively. 218 4.1.3 Waste of Extra Processing The interpretation of this category included the use of defective materials delivered onsite that required modification. This included any preparation work around connection points such as cleaning out any metal slag that remained in the bolt holes from the manufacturer and any preparation work required for the bolts prior to insertion into the bolt holes. During the PBC and bar joist erection, connection points were hammered to make the connections fit together. While this type of waste did not consume a large portion of time during either cycle (one percent), it could still be easily eliminated. 4.1.4 Waste of Transportation Minimal amounts of transportation waste (five percent) occurred during either cycle. The largest percentage of transportation waste (seven percent) occurred during the PBC erection cycle when one of the PBC members was lifted and positioned in a different location so that the column for that bay could be erected. Material layout on the jobsite minimized this type of waste. Material transport occurred when each structural element was maneuvered via hauling trucks to their temporary positions along the column lines. Due to the limitations of the study, this action was not observed by the team and is not accounted for in this case study. Other observations of material transportation occurred with the ground crew as they carried rigging from one column line to the next. 4.2 Waste Associated with Materials 4.2.1 Overproduction/(WIP) Overproduction waste (meaning too much of a building is produced) is rare in construction. Most construction reflects a “build to contract mentality” that requires a specific product(s) to be produced. Work in Progress (WIP), on the other hand, is evident in construction but is dependent on the activity level being viewed. At the process-specific level, WIP is seldom observed. However, at the management level, each unfinished component of the production process represents WIP. For this study, WIP was represented by the unfinished structure. 4.2.2 Inventory Material deliveries were made continually throughout the construction process. The steel was delivered onsite on large flatbed trucks. Typically four rows of steel, each row consisting of 10 bays, were delivered in one shipment to the jobsite. The material remained onsite anywhere from one day to a week and a half before being erected into place. The systematic process of erecting a column, PBC, then bar joists within each bay continued through the first four rows; the foundation walls were unfinished along the north side of the structure. While the cycles viewed were not affected by the incomplete foundation, future cycles will be. The outcome will be a sporadic erection sequence in which the structural members remain as inventory until the foundation wall is finished. 4.2.3 Defects Defects are defined as errors or deficiencies in a finished product that required additional work on the part of the original crew or a follow-up crew. A defective structural element (e.g., column, 219 girder, etc.) is an example of a defect (i.e., the material has been passed through the value stream to the next work station). Another example of a defect is included in the punch list process at the end of a job. When a defect in the finished product is found at this stage, a separate follow-up crew is activated to correct the defect. Hence, the defect is pushed onto the next work station. No waste associated with defects was observed. 5.0 Value Stream Analysis The following paragraphs describe the current value stream map for this structural steel erection process, beginning with the time the material was ordered and shipped from the manufacturer, through the construction production process, and ending with the material in final position in the facility. Figure C.25 is a simple flow diagram, with each box representing a point in time when the material was touched either to be moved or transformed into its next stage (phase) in the construction life cycle. Manufacturer Initial Dropoff Pod Beam Connected to Spandrel Beam, Positioned with Column Next to Bay Initial Shakeout. All Structural Elements for One Bay Are Pulled from Pile Bar Joists are Organized in Order of Erection and Positioned Parallel to Column Lines Final Placement by Crane Bar Joist Bundles Are Picked Up and Positioned under Crane Figure C.25: Material Flow Diagram Information on delivery and handling of the steel members was obtained from the project superintendent. Once it arrived onsite, the basic flow of the steel was as follows. The steel subcontractor was responsible for ordering and ensuring on-time delivery of all steel used on the project. The bar joists used on the project were provided by the subcontractor’s own steel manufacturing plant. The tube columns, spandrel beams and pod beams were all produced by various steel manufacturers throughout the United States. This required an onsite steel erector’s management team to coordinate the deliveries from each mill. The responsibility for handing material (steel) movement once it was delivered onsite was transferred to the project’s general contractor. The delivery of the erected steel was not observed. The basic movement of the steel was as follows. The steel was ordered in three phases for the structure; each phase contained all the steel necessary to erect four rows and the interconnecting bays. The steel members were delivered in bundles of like elements. From the truck, the bundles were positioned on the ground next to the truck. The truck then left the site, allowing for the next truck to enter the lay-down area. One forklift was dedicated to moving the material from the truck onto the ground, and a second forklift was used to shake out the material and position it so that it lay parallel to the column lines. Each structural element required in a bay was positioned on the ground in the adjacent bay until the erecting crew was ready. Finally, a third forklift repositioned the bar joist bundles so that they were in the correct order of the erection sequence. After the material was positioned on the ground, the erection crews moved in to start the erection cycles. There were minimal incidences of double handling occurred by either crew once the erection process was started. 220 5.1 Case Study No. 3’s Value Stream Map For the following value stream map analysis, three levels were required to represent both the material and labor components. Level One represents the major “Staging Positions” material went through to reach its finished state. Each time material was moved or transformed, a stage box is used to represent the process. Some of the stages include substages (Level Two) that represent processes that occurred simultaneously. The individual crew contributions to the value stream are represented on Level Three. The value stream map on Figure C.26 was created using available information; Figures C.27 C.28, and C.29 show magnified views for each level. For this case study, the value stream represents material and worker movements associated with both crews. The weighted average values for each work distribution category represent input from both crews. These values are assumed to be a reasonable representation for the entire steel erection processes on the project. Each major stage that the steel members went through is represented on Level One. For Stage Four, substage boxes are assigned to each crew. Taken together, all tasks necessary for completion of the structural steel erection process are identified. The steel was offloaded from the truck, shaken-out and prepped (PBC bolted together on the ground) before the erection process Stage Four could begin. All shakeout activities were represented as one stage (Stage Two). Stage Three covered the first VA actions committed by the crew. The value stream ended once the steel erection process reached the detailing and welding stage. Again, the limited observation period prevented acquisition of data at this stage in the entire steel erection process. Attention was instead focused on the two substages required for Stage Four of the value stream. The majority of time spent in Levels Two and Three was on the column and PBC erection phase. The amount of time spent on the bar joist erection process was not far behind. The separation of the required erection tasks between the two crews allowed for a more balanced production process. Even though the total time spent by each crew on its respective tasks was relatively equal, the overall work distribution values for waste were still high (65 percent weighted NVA value). Attention should be placed on the individual tasks required of each crew member. Once the tasks within each crew become balanced, the overall process will go faster and the VA percentage will rise. The largest contribution to the NVAR category was when the crane operator was required to temporarily hold the steel members in position while boltup occurred. Table C.22 and Figure C.30 show the Quick Summary results for the work distribution values from Level One. The value stream map depicts the flow of material and workers for the entire steel erection process. Of 1,544 total workable hours committed to the steel erection process by these crews, only 152 of them were VA. The largest amount of time was spent on NVA actions (1,018 man-hours). A significant amount of NVAR time came from the crane operators. This number could be reduced even further if the tasks required of each crew member were evenly distributed. The ground crewmen in Crew No. 1 also contributed to this number by securing tag lines. 221 Production Control Every 1-3 days Project Engineer Triggering Event Percent Complete Order is made for all SS within one of three zones Project Feedback Project Superintendent Level One Distribution of time from VSM Steel In Place awaiting welding Steel Supplier As Required Time Allocation Feild Daily 3 days of shipments for each zone O O OO NVA Time NVAR Time 1 VA Time Work Time 0 Stage One - Steel is offloaded in respective Bays Days Required Equipment involved: Forklifts Workers involved Crew WT VA ( 0%) NVAR (20%) NVA (80%) 2 2 3 48 0 9.6 38.4 Inv Stage Two - Steel is shookout Days 2 Required Equipment involved: Forklifts 2 Workers involved Crew 2 WT 32 VA ( 0%) 0 NVAR (0%) 0 NVA (100%) 32 2 Stage Three - Pod Beam are attached to Spandel Beam Days Required 5 Equipment involved: Forklifts Workers involved Crew WT VA ( 10%) NVAR (25%) NVA (65%) Inv Stage Four - Steel Erection Process Days Required 2 80 8 20 52 Inv 5 Level Three 16.5 Equipment involved: Forklift, Skylift Workers involved Crew WT= VA ( 7%) = NVAR (28%) = NVA (65%) = 5 Avail time/day 8 Days Required 660 46 185 429 Column and Pod Beam Erection Cycle-Case study #5 Total Cumulative Time for Steel Erection Waste NVAR VA Crew Member All Extra Transport Movement Material Pos. Waiting In Proc. Ins. Processin Activitie Ground Crewman #1 Ground Crewman #2 Connector Foreman Crane Operator #1 1% 6% 24% 5% 0% Group Percentage 7% 52% 45% 32% 70% 7% 0% 0% 1% 1% 1% 41% 1% NVA Sum Bar Joist Data from Case Study #5 VA Crew Member All Waiting Activitie Left Connector 18% 48% Right Connector 19% 54% X-Bracing Con. #1 31% 26% X-Bracing Con. #2 7% 55% Ground Crewman #3 14% 61% Ground Crewman #4 0% 81% Crane Operator #2 0% 30% Group Percentage 13% 51% Group Percentage 10% Waiting 7% 14% 11% 35% 8% 13% 5% 7% 3% 7% 7% 16% 6% 65% Avail time/day T.W.S.A 1% 1% 0% 3% 0% 19% 24% 2% 3% 57% 1% 21% NVAR Sum Waste Extra Transport Movement Processin 4% 1% 10% 1% 0% 15% 0% 0% 42% 0% 0% 0% 0% 4% 6% 0% 2% 1% 0% 7% 16% 2% 1% T.W.S.A 20% 11% 0% 32% 0% 16% 17% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 5% 15% 0% 31% 0% 7% VA + NVAR % 100% 100% 100% 100% 100% 26% 38% 30% 19% 64% 100% 35% Total % VA + NVAR % 100% 100% 100% 100% 100% 100% 100% 37% 29% 32% 45% 29% 16% 47% 100% 34% Total % VA + NVAR % 21% NVAR Sum Waste Extra Transport Movement Processin Total % NVAR 14% 8 28% In Proc. Ins. 13% 755 98 159 499 9:34:00 h:m:s Material Pos. 66% Note: Step 1 and 2 occur at the same time. Step 1 is required to occur first, but cannot proceed to far in the erection sequence until step 2 is completed per bay. 11:42:30 h:m:s Total Cumulative Time Spent on Bat Joists NVA Sum Average Values for Case Study VA Crew Member All Activitie Crew for Cycle 1 Ground Crewman #1 1% Ground Crewman #2 6% Connector 24% Foreman 5% Crane Operator #1 0% Crew For Cycle 2 Left Connector 18% Right Connector 19% X-Bracing Con. #1 31% X-Bracing Con. #2 7% Ground Crewman #3 14% Ground Crewman #4 0% Crane Operator #2 0% 8% 6% 2% 3% 15% 13.5 Equipment involved: Forklift, Skylift 2 Workers involved Crew 7 WT= VA ( 13%) = NVAR (21%) = NVA (66%) = 2 NVAR Material Pos. In Proc. Ins. T.W.S.A 52% 45% 32% 70% 7% 0% 0% 1% 1% 1% 8% 6% 2% 3% 15% 14% 11% 35% 8% 13% 5% 7% 3% 7% 7% 1% 1% 0% 3% 0% 19% 24% 2% 3% 57% 100% 100% 100% 100% 100% 26% 38% 30% 19% 64% 48% 54% 26% 55% 61% 81% 30% 4% 1% 0% 0% 0% 0% 0% 1% 0% 0% 0% 4% 2% 7% 10% 15% 42% 0% 6% 1% 16% 20% 11% 0% 32% 0% 16% 17% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 5% 15% 0% 31% 100% 100% 100% 100% 100% 100% 100% 37% 29% 32% 45% 29% 16% 47% 15% 9% 0% 15% 100% 35% 46% Cumulative Time for each Element Total Cumulative Time - Column and Pod Beam Total Cumulative Time - Bar Joists Total Time 1% 5% Cumulative Time for various 11:42:30 9:34:00 21:16:30 Number of members observed 4 24 Cycle time % of Total Time % of Total Time for each each steel element element requires 2:55:38 55% 47% 0:23:55 45% 6% 6:14:49 Man-Hours for one Bay Average VA Percentage Average NVAR Percentage Average NVA Percentage Figure C.26: Value Stream Map 222 2000 Quick Summary for Level One Working Days 39 Working Time 1576 man hours VA Total 152 man hours NVAR Total 373 man hours NVA Total 1050 man hours Step 2: Bar Joist installed along with x-bracing members Step 1: Column and Spandel Beam Days Required 1500 Inventory Days 12 5 Level Two 1000 Manhours 30 Equipment involved: Forklifts 4 Workers involved Crew 12 WT= 1416 VA ( 7%, 13%) 144 344 NVAR (28%, 21 928 NVA (65%,66% 1 500 10% 25% 65% Production Control Triggering Event Order is made for all SS within one of three zones E v e ry 1 -3 d a y s Project Engineer Percent Complete Project Feedback Project Superintendent Level One Distribution of time from VSM Steel In Place awaiting welding Steel Supplier As Required T im e A llo c a tio n F e ild Daily 3 days of shipments for each zone O O OO NVA Time NVAR Time 1 VA Time Work Time 0 Stage One - Steel is offloaded in respective Bays Days Required Equipment involved: Forklifts Workers involved Crew WT VA ( 0%) NVAR (20%) NVA (80%) 2 2 3 48 0 9.6 38.4 Inv 2 Stage Two - Steel is shookout Days 2 Required Equipment involved: Forklifts 2 Workers involved Crew 2 WT 32 VA ( 0%) 0 NVAR (0%) 0 NVA (100%) 32 Stage Three - Pod Beam are attached to Spandel Beam Days Required Inv Equipment involved: Forklifts Workers involved Crew WT VA ( 10%) NVAR (25%) NVA (65%) Stage Four - Steel Erection Process 5 Days Required 1 2 80 8 20 52 Inv 5 5 500 1000 1500 2000 Manhours 30 Equipment involved: Forklifts 4 Workers involved Crew 12 WT= 1416 VA ( 7%, 13%) 144 344 NVAR (28%, 21 NVA (65%,66% 928 Quick Summary for Level One Working Days 39 Working Time 1576 man hours VA Total 152 man hours NVAR Total 373 man hours NVA Total 1050 man hours Inventory Days 12 Figure C.27: Level One Step 1: Column and Spandel Beam Level Two Days Required 16.5 Equipment involved: Forklift, Skylift Workers involved Crew WT= VA ( 7%) = NVAR (28%) = NVA (65%) = 5 Avail time/day 8 2 660 46 185 429 Figure C.28: Level Two 223 Step 2: Bar Joist installed along with x-bracing members Days Required 13.5 Avail time/day 8 Note: Step 1 and 2 occur at the same time. Step 1 is required to occur first, but cannot proceed to far in the Equipment involved: erection sequence until step 2 is completed per bay. Forklift, Skylift 2 Workers involved Crew 7 WT= 755 VA ( 13%) = 98 NVAR (21%) = 159 NVA (66%) = 499 Level Three Total Cumulative Time for Steel Erection Column and Pod Beam Erection Cycle-Case study #5 Waste NVAR VA Crew Member All Extra Waiting Transport Movement Material Pos. In Proc. Ins. Activitie Processin Ground Crewman #1 1% 52% 0% 8% 14% 5% 1% Ground Crewman #2 6% 45% 0% 6% 11% 7% 1% 24% 32% 1% 2% 35% 3% 0% Connector Foreman 5% 70% 1% 3% 8% 7% 3% Crane Operator #1 0% 7% 1% 15% 13% 7% 0% Group Percentage 7% 41% NVA Sum Bar Joist Data from Case Study #5 VA Crew Member All Waiting Activitie 18% 48% Left Connector 19% 54% Right Connector X-Bracing Con. #1 31% 26% X-Bracing Con. #2 7% 55% Ground Crewman #3 14% 61% Ground Crewman #4 0% 81% Crane Operator #2 0% 30% Group Percentage 13% 51% NVA Sum Average Values for Case Study VA Crew Member All Waiting Activitie Crew for Cycle 1 Ground Crewman #1 1% 52% Ground Crewman #2 6% 45% 24% 32% Connector Foreman 5% 70% Crane Operator #1 0% 7% Crew For Cycle 2 Left Connector 18% 48% Right Connector 19% 54% X-Bracing Con. #1 31% 26% X-Bracing Con. #2 7% 55% Ground Crewman #3 14% 61% Ground Crewman #4 0% 81% Crane Operator #2 0% 30% Group Percentage 10% 46% Cumulative Time for each Element Total Cumulative Time - Column and Pod Beam Total Cumulative Time - Bar Joists Total Time 1% 7% 65% 16% 6% Waste Extra Transport Movement Material Pos. Processin 4% 1% 10% 20% 1% 0% 15% 11% 0% 0% 42% 0% 0% 0% 0% 32% 0% 4% 6% 0% 0% 2% 1% 16% 0% 7% 16% 17% 1% 1% NVAR Sum Total Cumulative Time Spent on Bar Joists 2% 13% 19% 24% 2% 3% 57% 21% Total % VA + NVAR % 100% 100% 100% 100% 100% 26% 38% 30% 19% 64% 100% 35% 28% 9:34:00 h:m:s NVAR Total % VA + NVAR % 0% 0% 1% 5% 15% 0% 31% 100% 100% 100% 100% 100% 100% 100% 37% 29% 32% 45% 29% 16% 47% 7% 100% 34% Total % VA + NVAR % T.W.S.A 0% 0% 0% 0% 0% 0% 0% 0% NVAR Sum Waste Extra Transport Movement Material Pos. Processin T.W.S.A In Proc. Ins. 14% 66% 11:42:30 h:m:s 21% NVAR In Proc. Ins. T.W.S.A 0% 0% 1% 1% 1% 8% 6% 2% 3% 15% 14% 11% 35% 8% 13% 5% 7% 3% 7% 7% 1% 1% 0% 3% 0% 19% 24% 2% 3% 57% 100% 100% 100% 100% 100% 26% 38% 30% 19% 64% 4% 1% 0% 0% 0% 0% 0% 1% 0% 0% 0% 4% 2% 7% 10% 15% 42% 0% 6% 1% 16% 20% 11% 0% 32% 0% 16% 17% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 5% 15% 0% 31% 100% 100% 100% 100% 100% 100% 100% 37% 29% 32% 45% 29% 16% 47% 15% 9% 0% 15% 100% 35% 1% 5% Cumulative Time for various 11:42:30 9:34:00 21:16:30 Number of members observed 4 24 % of Total Time Cycle time % of Total Time each steel for each element requires element 2:55:38 55% 47% 0:23:55 45% 6% 6:14:49 Man-Hours for one Bay Figure C.29: Level Three Table C.22: Quick Summary of Steel Process Quick Summary for Level One Working Days 37 Working Time 1544 man hours VA Total 152 man hours NVAR Total 373 man hours NVA Total 1018 man hours 224 Average VA Percentage Average NVAR Percentage Average NVA Percentage 10% 25% 65% Time Allocation Field Distribution of Time from VSM NVA Time NVAR Time 1 VA Time Work Time 0 500 1000 1500 2000 Man-hours Figure C.30: Quick Summary Graph - One Phase of the Steel Process Figure C.31 and Table C.23 illustrate how the work distribution values changed and grew throughout the process life cycle. The weighted average results found in Level Three of the value stream map were used to formulate all the VA, NVAR and NVA values in Table C.23. On Figure C.26, the cumulative NVA hours line grew the fastest compared to the other work distribution values. The black vertical line (on the left) indicates when the steel delivery and shakeout processes finished and the PBC process began. The next vertical line indicates the start of the steel erection process using both crews. The slope change in the cumulative calendar hours line resulted from additional workers being added to the team between the various stages. This crew variation affected the data results for the lines shown on Figure C.31. Table C.23 includes inventory positions; in these positions, the steel was not touched at all. These inventory days occurred so that the required crews for the erection phase could be gathered and organized. The crew was under contract with a second subcontractor, while the material for the job was controlled by the first subcontractor. This highlights how multiple contracts could affect the value stream. One subcontractor’s goals were not the same as the second. Until the ultimate goal (value) is defined by the customer, this value stream will not be capable of reaching its full potential. Work Distribution 4500 4000 Time (man-hours) 3500 3000 Cumulative Calendar Hours 2500 Cumulative Work Hours Cumulative VA Hours Cumulative NVAR Hrs. 2000 Cumulative NVA Hrs Erection Process Begins 1500 Stage 1 Finishes 1000 Pod Beams attached to Spandrel 500 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 Note: The percentages used to create this chart are the average values from the work distribution values found for the entire crew. Calendar Days Figure C.31: Work Distribution Lifecycle Graph 225 Table C.23: Spreadsheet of Values Used to Create Work Distribution Life Cycle Graph Stage Stage 1 Stage 1 Stage 1 Stage 1 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Primary Activity for the Day Day Steel is moved from truck to ground Monday Steel is moved from truck to ground Tuesday Steel waits on the ground until erected Wednesday Steel waits on the ground until erected Thursday Pod beam connected to spandle beam on ground Friday Weekend Saturday Weekend Sunday Pod beam connected to spandle beam on ground Monday Pod beam connected to spandle beam on ground Tuesday Pod beam connected to spandle beam on ground Wednesday Pod beam connected to spandle beam on ground Thursday Steel waits on the ground until erected Friday Weekend Saturday Weekend Sunday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Monday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Tuesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Wednesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Thursday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Friday Weekend Saturday Weekend Sunday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Monday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Tuesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Wednesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Thursday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Friday Weekend Saturday Weekend Sunday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Monday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Tuesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Wednesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Thursday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Friday Weekend Saturday Weekend Sunday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Monday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Tuesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Wednesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Thursday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Friday Weekend Saturday Weekend Sunday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Monday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Tuesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Wednesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Thursday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Friday Weekend Saturday Weekend Sunday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Monday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Tuesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Wednesday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Thursday 2 crews erecting structural steel, 1st crew = columns and pod beams, 2nd crew = bar joi Friday Calendar Calendar Days Hours 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 24 24 24 24 16 16 16 16 16 16 16 16 16 16 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 96 Cumulative Cumulative Hours Workabl Crew Workable Cumulative VA NVAR NVA VA Cumulative NVAR Cumulative NVA Cumulative Calendar Workable worked e Days available Hours Work Hours Percentage Percentage Percentage Hours VA Hours Hours NVAR Hrs. Hours NVA Hrs Hours days per day 24 1 1 3 8 24 24 0% 20% 80% 0 0 4.8 4.8 19.2 19.2 48 1 2 3 8 24 48 0% 20% 80% 0 0 4.8 9.6 19.2 38.4 72 1 3 3 8 24 72 0% 0% 100% 0 0 0 9.6 24 62.4 96 1 4 3 8 24 96 0% 0% 100% 0 0 0 9.6 24 86.4 112 1 5 2 8 16 112 10% 25% 65% 1.6 1.6 4 13.6 10.4 96.8 128 0 5 2 0 0 112 10% 25% 65% 0 1.6 0 13.6 0 96.8 144 0 5 2 0 0 112 10% 25% 65% 0 1.6 0 13.6 0 96.8 160 1 6 2 8 16 128 10% 25% 65% 1.6 3.2 4 17.6 10.4 107.2 176 1 7 2 8 16 144 10% 25% 65% 1.6 4.8 4 21.6 10.4 117.6 192 1 8 2 8 16 160 10% 25% 65% 1.6 6.4 4 25.6 10.4 128 208 1 9 2 8 16 176 10% 25% 65% 1.6 8 4 29.6 10.4 138.4 224 1 10 2 8 16 192 0% 0% 100% 0 8 0 29.6 16 154.4 240 0 10 2 0 0 192 10% 25% 65% 0 8 0 29.6 0 154.4 256 0 10 2 0 0 192 10% 25% 65% 0 8 0 29.6 0 154.4 352 1 11 12 8 96 288 10% 25% 65% 9.6 17.6 24 53.6 62.4 216.8 448 1 12 12 8 96 384 10% 25% 65% 9.6 27.2 24 77.6 62.4 279.2 544 1 13 12 8 96 480 10% 25% 65% 9.6 36.8 24 101.6 62.4 341.6 640 1 14 12 8 96 576 10% 25% 65% 9.6 46.4 24 125.6 62.4 404 736 1 15 12 8 96 672 10% 25% 65% 9.6 56 24 149.6 62.4 466.4 832 0 15 12 0 0 672 10% 25% 65% 0 56 0 149.6 0 466.4 928 0 15 12 0 0 672 10% 25% 65% 0 56 0 149.6 0 466.4 1024 1 16 12 8 96 768 10% 25% 65% 9.6 65.6 24 173.6 62.4 528.8 1120 1 17 12 8 96 864 10% 25% 65% 9.6 75.2 24 197.6 62.4 591.2 1216 1 18 12 8 96 960 10% 25% 65% 9.6 84.8 24 221.6 62.4 653.6 1312 1 19 12 8 96 1056 10% 25% 65% 9.6 94.4 24 245.6 62.4 716 1408 1 20 12 8 96 1152 10% 25% 65% 9.6 104 24 269.6 62.4 778.4 1504 0 20 12 0 0 1152 10% 25% 65% 0 104 0 269.6 0 778.4 1600 0 20 12 0 0 1152 10% 25% 65% 0 104 0 269.6 0 778.4 1696 1 21 12 8 96 1248 10% 25% 65% 9.6 113.6 24 293.6 62.4 840.8 1792 1 22 12 8 96 1344 10% 25% 65% 9.6 123.2 24 317.6 62.4 903.2 1888 1 23 12 8 96 1440 10% 25% 65% 9.6 132.8 24 341.6 62.4 965.6 1984 1 24 12 8 96 1536 10% 25% 65% 9.6 142.4 24 365.6 62.4 1028 2080 1 25 12 8 96 1632 10% 25% 65% 9.6 152 24 389.6 62.4 1090.4 2176 0 25 12 0 0 1632 10% 25% 65% 0 152 0 389.6 0 1090.4 2272 0 25 12 0 0 1632 10% 25% 65% 0 152 0 389.6 0 1090.4 2368 1 26 12 8 96 1728 10% 25% 65% 9.6 161.6 24 413.6 62.4 1152.8 2464 1 27 12 8 96 1824 10% 25% 65% 9.6 171.2 24 437.6 62.4 1215.2 2560 1 28 12 8 96 1920 10% 25% 65% 9.6 180.8 24 461.6 62.4 1277.6 2656 1 29 12 8 96 2016 10% 25% 65% 9.6 190.4 24 485.6 62.4 1340 2752 1 30 12 8 96 2112 10% 25% 65% 9.6 200 24 509.6 62.4 1402.4 2848 0 30 12 0 0 2112 10% 25% 65% 0 200 0 509.6 0 1402.4 2944 0 30 12 0 0 2112 10% 25% 65% 0 200 0 509.6 0 1402.4 3040 1 31 12 8 96 2208 10% 25% 65% 9.6 209.6 24 533.6 62.4 1464.8 3136 1 32 12 8 96 2304 10% 25% 65% 9.6 219.2 24 557.6 62.4 1527.2 3232 1 33 12 8 96 2400 10% 25% 65% 9.6 228.8 24 581.6 62.4 1589.6 3328 1 34 12 8 96 2496 10% 25% 65% 9.6 238.4 24 605.6 62.4 1652 3424 1 35 12 8 96 2592 10% 25% 65% 9.6 248 24 629.6 62.4 1714.4 3520 0 35 12 0 0 2592 10% 25% 65% 0 248 0 629.6 0 1714.4 3616 0 35 12 0 0 2592 10% 25% 65% 0 248 0 629.6 0 1714.4 3712 1 36 12 8 96 2688 10% 25% 65% 9.6 257.6 24 653.6 62.4 1776.8 3808 1 37 12 8 96 2784 10% 25% 65% 9.6 267.2 24 677.6 62.4 1839.2 3904 1 38 12 8 96 2880 10% 25% 65% 9.6 276.8 24 701.6 62.4 1901.6 4000 1 39 12 8 96 2976 10% 25% 65% 9.6 286.4 24 725.6 62.4 1964 4096 1 40 12 8 96 3072 10% 25% 65% 9.6 296 24 749.6 62.4 2026.4 226 Appendix D Case Study No. 4 - Process Piping 1.0 Overview 1.1 Project Goal The purpose of this case study was to collect data to develop a value stream map for the construction process. During this study, observations focused on the installation of eight-inch diameter steel pipe. Field data were gathered on two separate value streams: the actual flow of the pipe from the time it arrived on the jobsite until it was erected into final position, and the flow of worker activities performed to install the eight-inch diameter steel pipe. 1.2 Data Collection Procedure Data collection was accomplished in two consecutive days, with video footage taken during both sessions. Two different piping crews were observed; each consisted of two pipe fitters. Each observer was equipped with a digital camera. The digital video cameras were positioned to view the activity area at right angles to provide “depth” in both viewing directions. In the lab, two televisions were placed next to each other and used to view the recorded piping operations. Using both cameras provided a three-dimensional view of the work space for the data collection process. Each time a new task was started, an entry was made on the data sheet. For example, an entry might indicate that a worker was grinding a pipe. The next entry might indicate that the worker had moved to gather the tools or materials necessary to continue prepping the pipe for installation. The elapsed time for each task was recorded as well as the observer’s judgment regarding whether the task was value adding (VA), non-value adding (NVA), or nonvalue adding but required (NVAR). 1.3 Project Description The project involved the installation of an auxiliary boiler in an existing power plant. The housing for the boiler was located adjacent to the main power plant boiler room. From the existing structure, four-inch natural gas pipes and eight-inch steam piping were routed from the existing lines back to the new auxiliary boiler housed in the new structure. The purpose of the auxiliary boiler is to provide energy to the power plant’s “life systems” when the main boiler is shut down for maintenance or repair. Two separate areas were observed for this study. The first area was in the new structure housing the auxiliary boiler, which was located north of the main power plant facility. The room was roughly 30 feet wide by 60 feet long and 40 feet high. The focus of the video footage taken in this area was the erection of an eight-inch pipe spool approximately two feet long, a relief valve and an eight-inch elbow pipe spool approximately five feet long. All piping components observed had flanged/bolted connections. The second area was within the main power plant facility adjacent to the wall between the power plant facility and the new auxiliary boiler room. The focus of the video footage in this area was the erection of a pipe elbow piece for the steam line that was to be used to bypass the main boiler 227 steam line. Other work within the same area included placement and welding of a four-inch natural gas line that was pulled off the main gas line to fire the burner for the auxiliary boiler. The area of work was located 15 feet above the ground floor on top of temporary scaffolding erected earlier by a separate carpentry crew. The elbow was constructed with the eight-inch pipe and was considered a subset of the observed operations that formed part of the overall steps required to erect the entire steam line. The elbow erection activities were preceded by the following: cutting the new pipe spool section to the desired length while it was in the material lay-down yard and installing pipe hangers to hold the pipe in final position within the structure. It was succeeded by X-ray testing of each weld along the line as well as a pressurized line test to discover leakage. The material lay-down yard was located 150 to 200 yards away from the final erection area within the main boiler structure. 2.0 Eight-Inch Spool Erection Process During both piping operations, few repetitive tasks occurred. A repetitive task was defined as one in which the worker repeated the same movement or action for every “member” (e.g., one pipe spool, valve, elbow) that was erected. For example, in a steel erection process, a repetitive task would include a worker rigging a steel member to the hoist line each time a similar member was lifted into final position. A repetitive task within the pipe spool erection process was the physical act of welding. While the weld might not occur in the same position each time, the process of completing that weld was the same. An activity included all tasks required to erect one specific member, such as a prefabricated valve, into final position. For the following sections, the activity cycle started when work began in the area of the spool erection and finished when the pipe was welded into final place within the entire pipeline. Diagrams 1 through 9 show the erection of an eight-inch steam line at two separate locations on the line. Diagrams 1 through 4 show the process observed to install the prefabricated components. Diagrams 5 through 9 show the process observed to install the field fabricated components. Crew No. 1 - Cycle One Diagram 1: Existing Pipe and Valve Diagram 2: Two-Foot Spool Bolted On Diagram 3: Second Valve Attached 228 Diagram 4: Elbow Spool Bolted On Crew No. 2 - Cycle Two Tee Section Diagram 6: Elevation View of Existing Pipe Diagram 5: Plan View of Work Area Pipe Stands Diagram 7: Tee Section Removed Diagram 8: Tee Section Attached to New Spool 229 Diagram 9: Finished Line 2.1 Erection Process - Data Collection for Cycle No. 1 The erection of a two-foot section of eight-inch diameter pipe was observed with each end having the following: a flanged (bolted) connection, a release valve with two flanged connections, and a five-foot long pipe spool with an elbow in which only one end of the spool had a flanged connection. The opposite end of the spool was later welded to an adjacent pipe spool member. The observation period started with the positioning of the two-foot pipe spool under its respective position within the line. A chain fall was used to hoist the pipe spool into position. For each connection a “greased” gasket was placed between the flange connections. The adjacent members were then bolted by hand, and an electric torque gun was used to apply the required torque pressure on the bolt connections. Following the first spool’s erection, a relief valve was hoisted into position using the chain fall. The connection process was repeated for the flanged connection as described above. Finally, the five-foot elbow pipe spool was transported from the material lay-down yard to the work area. It was hoisted into position and its flanged connection was bolted in a similar fashion as described above. Because of the limited amount of space in the work area, all of the pipe sections were first stored within the material lay-down yard and retrieved as required for the erection process. Each of the pipe sections observed during this erection cycle was prefabricated offsite. 2.2 Erection Process - Data Collection for Cycle No. 2 The erection of one eight-foot pipe spool (eight-inch diameter) was observed. During this cycle, observed activities included the cutting of a previously erected pipe spool that lay adjacent in the pipeline to where the new pipe spool was to be erected. The final location of the spool was approximately 15 feet above the floor. Several intermediate steps were required to position the spool into its final position in the pipeline. The cycle started when the new pipe spool section was transported from the material lay-down yard to the work area in the main power plant. The spool was hoisted 15 feet up onto temporary scaffolding using chain falls. The spool was then placed on temporary bracing while further prep work was completed. The end piece of the previously erected pipe was prepared using a hand-held grinder. Removal of this section of pipe was required to realign the section at the correct angle for the steam line to continue inside the power plant. Once removed, the cut section resembled a fire hydrant with an end cap (nipple drain) at the bottom and an eight-inch open orifice that was 230 connected to the new spool already positioned on temporary bracing. The cut ends, both on the remaining section of hung pipe and the end piece that was removed, were ground and beveled prior to re-welding the connection. The end section was attached to the new spool while it remained on the temporary bracing. Once completed, the entire section of new pipe (new spool welded to cut section) was positioned into final alignment under the existing hung spool. Tack welds were completed first to provide stability and alignment between the two spools while the production weld was completed. The completion of this weld ended the data collection period and was the end of the cycle. The erection process for both cycles required a two-man crew. However, the tasks for the two cycles required different movements and equipment to erect and secure each spool into its final position. One crewman was required to bolt the connecting members, while the other crewman was required to install pipe hangers to support the long sections of pipe, as well as weld connections between the spools. While the crew size was the same for the two cycles, the time required to perform the separate tasks was not. Therefore, in contrast to the “ideal” highly repetitive and balanced manufacturing sequence, it would be difficult to design an erection sequence that balanced the amount of time needed as well as the equipment necessary to complete each task. During the observation period, the following materials were installed: • One two-foot section of eight-inch diameter steel pipe with two flanged connections. • One release valve. • One five-foot section of eight-inch diameter steel pipe with a 90 degree elbow and one flanged connection. • Eight-foot section of eight-inch diameter pipe. In addition, the following equipment and crew structures were observed: • Five pipe fitters. • Four to five crew personnel. The following section analyzes each worker’s contributions to each cycle. Tables and figures were developed for each worker and task that describe the time spent on VA, NVA, and NVAR actions within each cycle. 2.3 Piping Installation Process In the following subsections, each worker within the crew is referred to by a number. (Refer to the end of this case study to review the data sheets for Cycle No. 1.) Piping installation with flanged connections included the following tasks: rigging of the spool/valve to the chain fall, placing the piping member into final position, preparing and applying the gasket to the spool connection, bolting the flanged connection and inspecting the finished product. Other minor 231 tasks occurred, but were not recorded. Figure D.1 shows the major tasks required to complete the prefabricated pipe spool installation. The shaded areas are used to indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations (e.g., two days for material delivery). Prefabricated Pipe Spool Installation Process Task Order (process flow is shown, NOT TIME) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Material Delivered to Site (Material Yard) Transported to Work Area Piping Member is Rigged for Chain Pull Piping Member is Hoisted into Place Final Prep Work (Grinding Flange Area) Gaskets Greased and Fit Between Members Bolts Inserted and Hand Tightened Final Adjustments (Leveling/Inspections) Bolts Machine Tightened to Specification Test and Balance Line Note: This schedule shows process flow. It does not show actual task durations. Note: Eight inch piping components for this process include: (1) two foot spool, (1) release valve and (1) five foot elbow spool section. Figure D.1: Schedule for Piping Erection Process with Flanged Connections Two workers in a piping crew were the main participants involved with installing the various piping components during this observation period. One other worker was in the area, but his contributions of time to the work process were minimal. Worker 1 was involved with the installation of all four piping components erected during the observation period. His responsibilities included positioning each piping component into final position, leveling and adjusting pipe segments to correct levels, bolting and final inspections of the finished product. Table D.1 and Figure D.2 show the VA, NVA and NVAR values for worker 1. During the piping installation process, worker 1 contributed the majority of his time (68 percent) to NVA actions. The only VA actions for the worker occurred while applying the greased gasket to the connection and physically bolting the flanged connection to its adjacent piping component. Table D.1: Prefabricated Piping Data for Worker 1 A c tiv ity C la s s ific a tio n VA W a s te C la s s ific a tio n V a lu e A d d in g V A T o ta l T im e a t A c tiv ity % o f T im e a t A c tiv ity 0 :1 4 :4 6 1 7 .1 7 % 0 :1 4 :4 6 1 7 .1 7 % 0 :2 1 :4 3 0 :0 8 :3 0 0 :0 9 :1 5 0 :1 8 :5 8 2 5 .2 5 % 9 .8 8 % 1 0 .7 6 % 2 2 .0 5 % 0 :5 8 :2 6 6 7 .9 5 % NVA W a itin g E x tra P ro c . T ra n s p o rt M o tio n N V A T o ta l NV AR M a t. P o s . 0 :0 1 :0 0 1 .1 6 % In -P ro c e s s In s . T .W .S .A 0 :0 1 :0 1 0 :1 0 :4 7 1 .1 8 % 1 2 .5 4 % N V A R T o ta l 0 :1 2 :4 8 1 4 .8 8 % G r a n d T o ta l 1 :2 6 :0 0 1 0 0 .0 0 % 232 Worker #1 Prefabricated Piping Data - Cycle #1 NVAR TWSA 13% NVAR In-Process Inspection 1% NVAR Material Positioning 1% VA 17% NVA Motion 22% NVA Waiting 25% NVA Transport 11% NVA Extra Processing 10% Figure D.2: Prefabricated Piping Data for Worker 1 Worker 2 was involved with two of the four piping components installed during this observation period (a five-foot elbow section and release valve component). His responsibilities included the following: setup and removal of chain fall rigging, greasing and installing gaskets for flanged connections, placing piping components into final position, final preparation of flanged connections (filing) and final bolting. Table D.2 and Figure D.3 show the VA, NVA and NVAR amounts for worker 2. Notice that worker 2 contributed the majority of his time (54 percent) to NVA actions. The only time contributed to VA actions occurred while applying the greased gaskets to the flanged connection area and the physical bolting of flanged connections. Table D.2: Prefabricated Piping Data for Worker 2 Ac tivity C la ssific a tio n VA W a ste C la s sific a tio n V a lu e A d d in g T im e a t Ac tivity % o f T im e a t Ac tivity 0 :16 :1 0 1 8 .8 0 % 0 :1 6 :1 0 1 8 .8 0 % 0 :20 :5 1 0 :04 :3 0 0 :03 :2 5 0 :17 :3 0 2 4 .2 4 % 5 .2 3 % 3 .9 7 % 2 0 .3 5 % 0 :4 6 :1 6 5 3 .8 0 % M at. P o s . 0 :16 :4 4 1 9 .4 6 % In -P ro c e s s In s. T .W .S .A 0 :01 :4 0 0 :05 :1 0 1 .9 4 % 6 .0 1 % N V AR T o ta l 0 :2 3 :3 4 2 7 .4 0 % G ra n d T o ta l 1 :2 6 :0 0 1 0 0 .0 0 % V A T o ta l NVA W a itin g E x tra P ro c . T ra n s p o rt M o tio n N V A T o ta l N V AR 233 Worker #2 Prefabricated Piping Data - Cycle #1 NVAR TWSA 6% NVAR In-Process Inspection 2% NVAR Material Positioning 19% VA 19% NVA Waiting 25% NVA Motion 20% NVA Extra Processing 5% NVA Transport 4% Figure D.3: Prefabricated Piping Data for Worker 2 2.4 Piping Installation Process - Cycle No. 2 - Welded Connections As in the previous sections, each worker within the crew is referred to by a number (refer to the end of this case study to review the data sheets for Cycle No. 2). Piping installation with field welded connections included the following tasks: rigging the spool/valve to the chain pull, placing the piping component into final position, cutting the existing hung pipe to remove and realigning it, beveling each end that would have a production weld, tack welding and producing a final production weld. Other minor tasks occurred, but were not recorded. Figure D.4 below shows the major tasks required to complete the prefabricated pipe spool installation. The shaded areas are used to indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations (e.g., two days for material delivery). Field Fabricated Pipe Spool Installation Process Task Order (process flow is shown, NOT TIME) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Material delivered to site (Mat. Yard - 1 load) Pipe is pulled from shipment bundle Pipe sections are cut to specified spool length Grinding on both end to create bevel Production weld made between spools (if needed) OR: Spool is transported to directly to work area Spool is positioned into final placement in pipe line Alignment jigs are secured around spool ends Tack welds are made to temporarily secure spools Production weld made between adjacent spools In-process inspections for production welds Tack welds are ground out Finish grinding occurs on outside weld Test and balance of line (leaks and valve adj.) Note: this schedule shows process flow. It does not show actual task durations. Eight inch piping components for this process include: (1) new eight foot pipe spool. Figure D.4: Schedule for Piping Erection Process with Welded Connections The crew was composed of two workers (labeled worker 3 and worker 4). The focus of the crew was the installation of an eight-inch diameter pipe spool. Each worker shared all of the tasks required to erect the spool. The schedule on Figure D.4 represents the erection of a pipe spool 234 from start to finish in an “ideal situation.” In fact, the following data analysis includes time attributed to the rework of a previously hung section of pipe. All time contributed to the rework of this prehung spool (labeled as “hung pipe,” and “cut section” on the data spreadsheet) is classified as “Extra Processing” (NVA). Worker 3 was involved with two of the following three activities: new pipe spool erection, hung pipe removal and new pipe spool erection. Worker 4 was involved with all three activities: hung pipe removal, cut section prep work and new pipe spool erection. 2.4.1 Hung Pipe Spool Removal Worker 3 was involved with cutting the existing hung spool and positioning the cut section next to the new pipe spool that was temporarily positioned on stands within the work area. Table D.3 and Figure D.5 show the VA, NVA and NVAR percentages for worker 3. Nearly one hour of time was dedicated to this process. Of the time spent on the hung pipe, no VA actions occurred, and 94 percent of the time was classified as NVA. The small amount of time for NVAR actions came from setting up temporary lighting around the work area and using pipe fitter paper to align a “cut line” around the hung pipe. Table D.3: Field Welded Piping Data for Worker 3 - Hung Pipe Activity Classification Waste Classification Time at Activity % of Time at Activity NVA Waiting 0:12:09 21.19% Extra Proc. 0:18:25 32.12% Transport 0:06:41 11.66% Motion 0:16:35 28.92% NVA Total 0:53:50 93.90% NVAR NVAR Total T.W.S.A. 0:03:30 0:03:30 Grand Total 0:57:20 6.10% 6.10% 100.00% Worker 4 was involved with the following: cutting the existing hung spool, grinding/beveling the remaining exposed end of the hung pipe and positioning the cut section next to the new pipe spool that was temporarily positioned on stands within the work area. Table D.4 and Figure D.6 show the VA, NVA and NVAR percentages for Worker 4. Approximately half an hour was spent by this worker on the hung section of pipe. The majority of his time was attributed to beveling (NVA, extra processing) the remaining end of the hung section of pipe to be welded once again to the cut section with new spool attached. Roughly 94 percent of the time spent was contributed to NVA actions, leaving 6 percent for NVAR actions. 235 Worker #3 - Previously Hung Pipe Field Welded Piping Data NVAR TWSA 6% NVA Waiting 21% NVA Motion 29% NVA Extra Processing 32% NVA Transport 12% Figure D.5: Field Welded Piping Data for Worker 3 - Hung Pipe Table D.4: Field Welded Piping Data for Worker 4 - Hung Pipe Activity Classification NVA Waste Classification Time at Activity % of Time at Activity Waiting Extra Proc. 0:05:21 0:14:07 19.96% 52.67% Transport 0:05:27 20.34% Motion 0:00:10 0.62% 0:25:05 93.59% 0:00:30 0:01:13 1.87% 4.54% NVAR Total 0:01:43 6.41% Grand Total 0:26:48 100.00% NVA Total NVAR In-Process Ins. T.W.S.A. 236 Worker #4 - Previously Hung Pipe Field Welded Piping Data NVAR In Process Inspection 2% NVAR TWSA 5% NVA Motion 1% NVA Waiting 20% NVA Transport 20% NVA Extra Processing 52% Figure D.6: Field Welded Piping Data for Worker 4 - Hung Pipe 2.4.2 Cut Section Prep Work Worker 3 contributed no time to the rework required to prep the cut section for attachment back to the remaining hung pipe section. The opposite end of the cut section that was to be attached to the new spool section had already been prepared prior to erection into place in the pipeline. Worker 4 is involved with the following activities: grinding the same end previously attached to the hung pipe, beveling the end section to prepare it for production weld, positioning the pipe onto temporary supports to continue prep work for weld, positioning the cut section next to the new pipe spool and continually inspecting the spool end to ensure a flush connection for the production weld. Table D.5 and Figure D.7 show the VA, NVA and NVAR percentages for worker 4. No VA actions were noted throughout this work process. Worker 4 spent the majority of his time on rework activities such as grinding and beveling the connection point in preparation for the final production weld between the “cut section” and the “previously hung pipe.” NVAR actions occurred when the worker rigged and positioned the cut section next to the new pipe spool to complete the production weld (20 percent). Table D.5: Field Welded Piping Data for Worker 4 - Cut Section Activity Classification NVA Waste Classification Time at Activity Waiting Extra Proc. 0:08:49 0:38:21 % of Time at Activity 13.49% 58.68% Transport 0:04:24 6.73% Motion 0:00:47 1.20% 0:52:21 80.11% 0:05:51 0:07:09 8.95% 10.94% NVAR Total 0:13:00 19.89% Grand Total 1:05:21 100.00% NVA Total NVAR Mat. Pos. T.W.S.A. 237 Worker #4 - Cut Section Field Welded Piping Data NVAR TWSA NVA Material 11% NVA Waiting 13% Positioning 9% NVA Motion 1% NVA Transport 7% NVA Extra Processing 59% Figure D.7: Field Welded Piping Data for Worker 4 - Cut Section 2.4.3 New Pipe Spool Worker 3 was involved with the following activities: aligning/leveling the new pipe spool to the level of the cut section of pipe, securing pipe alignment guides and inspecting tack welds and production welds. In addition, worker 3 positioned the entire welded component (both the new pipe spool and cut section as one piece) under the hung pipe and completed a production weld between the new spool section and hung pipe. Table D.6 and Figure D.8 show the VA, NVA and NVAR percentages for worker 3. Notice the VA actions in the process. VA levels increased to more than 20 percent of the total time attributed to the new spool. There was still a large portion of waste, 54 percent, which highlights an area for improvement in the overall process. Table D.6: Field Welded Piping Data for Worker 3 - New Spool Section Ac tiv ity C la ss ific a tio n VA W a s te C la s sific a tio n V a lu e A d d in g T im e a t Ac tivity % o f T im e a t Ac tivity 0 :4 3 :1 1 2 0 .3 7 % 0 :4 3 :1 1 2 0 .3 7 % 0 :4 1 :4 9 0 :0 5 :4 3 0 :2 5 :1 5 0 :4 1 :2 5 1 9 .7 2 % 2 .7 0 % 1 1 .9 1 % 1 9 .5 4 % 1 :5 4 :1 2 5 3 .8 7 % 0 :3 1 :2 0 0 :0 9 :0 9 0 :1 4 :0 8 1 4 .7 8 % 4 .3 2 % 6 .6 7 % N V AR T o ta l 0 :5 4 :3 7 2 5 .7 6 % G ra n d T o ta l 3 :3 2 :0 0 1 0 0 .0 0 % V A T o ta l NVA W a itin g E x tra P ro c . T ra n s p o rt M o tio n N V A T o ta l N V AR M a t. P o s . In -P ro c e s s In s . T .W .S .A . 238 Worker #3 - New Spool Field Welded Piping Data NVAR TWSA 7% NVAR In-Process Inspection 4% VA 20.4% NVAR Material Positioning 15% NVA Waiting 20% NVA Extra Processing 3% NVA Motion 20% NVA Transport 12% Figure D.8: Field Welded Piping Data for Worker 3 - New Spool Section Worker 4 was involved with the following: aligning/leveling the new pipe spool to the same height as the cut section of pipe, securing pipe alignment guides, inspecting tack welds and production welds, positioning the entire welded component (including both the new pipe spool and cut section as one piece) under the hung pipe and grinding sections of the production weld created by worker 3 to ensure a quality production weld. Table D.7 and Figure D.9 show the VA, NVA and NVAR percentages for worker 4. Notice that worker 4 contributed no VA actions to the process. The majority of his time was spent waiting while worker 3 created the production weld. Table D.7: Field Welded Piping Data for Worker 4: - New Spool Section Activity Classification NVA Waste Classification Time at Activity % of Time at Activity Waiting Extra Proc. 1:23:49 0:08:21 47.31% 4.71% Transport 0:22:24 12.64% Motion 0:19:43 11.13% 2:14:17 75.79% 0:32:00 0:03:40 0:07:14 18.06% 2.07% 4.08% NVAR Total 0:42:54 24.21% Grand Total 2:57:11 100.00% NVA Total NVAR Mat. Pos. In-Process Ins. T.W.S.A. 239 Worker #4 - New Spool Field Welded Piping Data NVAR TWSA 4% NVAR In-Process Inspection 2% NVA Waiting 47% NVAR Material Positioning 18% NVA Motion 11% NVA Transport 13% NVA Extra Processing 5% Figure D.9: Field Welded Piping Data for Worker 4 - New Spool Section 3.0 Results for the Crew A work distribution chart (Figure D.10) depicts the time spent on various activities for the prefabricated pipe with flange connection process (Cycle No. 1). Figure D.11 represents work distribution amounts for the field fabricated pipe spool process (Cycle No. 2). During the observation period, the erection of four “new” piping components was observed. Each of these components varied in size and shape and required different equipment and erection procedures. No similar cycle occurred during the observation. Therefore, “one cycle” was defined as the entire period of observation. For example, Cycle No. 1 started with the “finish” installation of a two-foot spool section and concluded when the bolts were tightened around the flanged connection for the five-foot spool section. The different shading on the chart represents the VA and waste tasks for each worker. 3.1 Crew Composition for Prefabricated Steel Pipe Erection (Cycle No. 1) Each worker contributed similar amounts of time to each of the categories, as shown on Figure D.10. There was a difference at the bottom of the chart because worker 1 was more involved with extra processing, transportation and equipment requirements (extra prep work on the end connection, tool gathering and rigging setup). Worker 2 was responsible for the majority of material positioning. Both workers spent most of their time on waiting and wasted movement. 240 Worker Task Breakdown - Pre-fabbed Pipe Cycle #1 1:26:24 1:23:31 1:20:38 1:17:46 Value Adding 0:14:46 1:14:53 Mat. Pos . 0:01:00 1:12:00 1:09:07 1:06:14 1:03:22 Value Adding 0:16:10 T.W.S.A 0:10:47 In-Proces s Ins . 0:01:01 Mat. Pos . 0:16:44 1:00:29 0:57:36 0:54:43 0:51:50 Trans port 0:09:15 In-Proces s Ins . 0:01:40 Time(h,m,s) 0:48:58 0:46:05 0:43:12 Value Adding T.W.S.A 0:05:10 Transport 0:03:25 Extra Proc. 0:04:30 Extra Proc. 0:08:30 0:40:19 0:37:26 0:28:48 In-Process Ins. T.W.S.A Transport Extra Proc. Waiting 0:34:34 0:31:41 Mat. Pos. Motion Waiting 0:21:43 Waiting 0:20:51 0:25:55 0:23:02 0:20:10 0:17:17 0:14:24 0:11:31 0:08:38 Motion 0:18:58 Motion 0:17:30 Worker # 1 Worker # 2 0:05:46 0:02:53 0:00:00 Figure D.10: Work Distribution Chart - Cycle No. 1 3.2 Crew Composition for Field Fabricated Steel Pipe Erection (Cycle No. 2) Figure D.11 shows that worker 3 contributed the only VA time to the erection of the new spool. All of worker 4’s actions were NVA and NVAR. Worker 4 waited for more than one and a half of the four and a half hours observed. A large amount of waiting occurred while worker 3 beveled and welded each connection. Each worker contributed similar amounts of time to the following: material positioning, temporary work and support activities, in-process inspections, and transportation actions. Worker 4 contributed a large portion of his time to extra processing. This included recutting the hung pipe, grinding and beveling each cut end and extra preparation work that was required to fix the defect. 241 Worker Task Breakdown - Field Fabricated Cycle #2 4:48:00 4:40:48 4:33:36 4:26:24 4:19:12 4:12:00 4:04:48 Mat. Pos. 0:37:51 Value Adding 0:43:11 3:57:36 In-Process Ins 0:04:10 3:50:24 3:43:12 3:36:00 3:28:48 T.W.S.A. 0:15:36 Mat. Pos. 0:31:20 3:21:36 In-Process Ins. Transport 0:32:15 0:09:09 3:14:24 3:07:12 3:00:00 2:52:48 T.W.S.A. 0:17:38 Value Adding Tim e(h,m ,s) 2:45:36 2:38:24 2:31:12 Mat. Pos. Transport 0:31:56 Extra Proc. 1:00:49 2:24:00 2:02:24 T.W.S.A. Transport 2:16:48 2:09:36 In-Process Ins. Extra Proc. Extra Proc. 0:24:08 Waiting Motion 1:55:12 1:48:00 1:40:48 1:33:36 1:26:24 1:19:12 Waiting 0:53:58 Waiting 1:37:59 1:12:00 1:04:48 0:57:36 0:50:24 0:43:12 0:36:00 0:28:48 Motion 0:58:00 0:21:36 0:14:24 Motion 0:20:40 0:07:12 0:00:00 Worker 3 Worker 4 Figure D.11: Work Distribution Chart - Cycle No. 2 3.3 General Observations about Crew Composition During the observation period for Cycle No. 1, no rework occurred. The erection work involved for the three different piping components appeared to be assigned equally to each worker. However, the time contributed to wasted motion, transport and waiting highlights areas in which crew efficiency could be improved. During the observation period for Cycle 2, a significant portion of the time attributed to the erection of the new pipe spool involved rework. The limited work space inhibited movement and affected the ease in which the spool was erected. In addition, incidences occurred in which workers had to share equipment, which resulted in higher waiting times. Finally, several movements were attributed to gathering new grinding pads and welding rods that were scattered around the work area. 242 4.0 Process Improvement Opportunities A goal of this report was to examine and document the inefficiencies in construction operations. In general terms, inefficiencies were classified as the following three types: inefficiency due to waste (NVA activities), inefficiency due to unnecessary work (excessive NVAR activities) and inefficiency due to poorly designed work processes (ineffective VA activities). The following section identifies opportunities for process improvement by applying Ohno’s (1988) seven wastes in production and then evaluating the production process against a more comprehensive set of lean principles. Tables D.8 and D.9 list the subset of activities specific to each crew that occurred to accomplish the entire erection process. The NVA category is further divided into the time spent in the waiting, extra processing, transport and movement categories. Additionally, NVAR is broken down into its three subcategories to clarify how time was spent within observed cycles. Table D.8: Crew No. 1 Subactivities Prefabricated Pipe: Two-Foot Spool Total Cumulative Time Spent on Spool 0:02:55 h:m:s VA Waste NVAR Crew Member Material In Proc. Extra All Transport Movement TWSA Waiting Total Pos. Ins. Processing Activities Worker #1 48% 10% 0% 28% 0% 0% 14% 0% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% Worker #2 VA + NVAR 62% 0% Group Percentage 0% 48% 10% 0% 28% 0% 0% 14% 62% 100% Prefabricated Pipe: Release Valve Total Cumulative Time Spent on Release Valve 0:36:50 h:m:s VA Waste . VA + Crew Member All Extra Material In Proc. Waiting Transport Movement Total NVAR TWSA Activities Processing Pos. Ins. Worker #1 9% 58% 0% 11% 0% 0% 0% 22% 100% 31% 30% 12% 0% 11% 10% 25% 6% 6% 100% 67% Worker #2 Group Percentage 25% 21% 0% 11% 8% 20% 5% 10% 100% Prefabricated Pipe: Elbow Spool Total Cumulative Time Spent on Spool 2:04:44 h:m:s Waste NVAR VA Crew Member Extra Material In Proc. All Total Waiting Transport Movement TWSA Activities Processing Pos. Ins. Worker #1 14% 24% 12% 9% 27% 2% 0% 12% 100% 13% 30% 8% 0% 26% 17% 0% 6% 100% Worker #2 Group Percentage 13% 28% 10% 6% 243 26% 8% 0% 9% 100% 60% VA + NVAR 28% 36% 30% Table D.9: Crew No. 2 Subactivities 1:05:21 h:m:s Field Welded - Cut Section Total Cumulative Time Spent on Section VA Waste NVAR All Extra Material In Proc. Crew Member Total Activities Waiting Processing Transport Movement Pos. Ins. TWSA 0% 0% 0% 0% 0% 0% 0% 0% 0% Worker #3 Worker #4 0% 13% 59% 7% 1% 9% 0% 11% 100% Group Percentage 0% 13% 1% 9% 0% 11% 100% 59% 7% Field Welded - Hung Pipe 1:24:08 h:m:s Total Cumulative Time Spent on Pipe VA Waste NVAR Crew Member All Extra Material In Proc. Total Activities Waiting Processing Transport Movement Pos. Ins. TWSA Worker #3 0% 21% 32% 12% 29% 0% 0% 6% 100% 0% 20% 53% 19% 1% 0% 2% 5% 100% Worker #4 Group Percentage 0% 21% 39% 14% 19% 0% 1% 6% 100% 6:29:11 h:m:s Field Welded - New Pipe Spool Total Cumulative Time Spent on Spool VA Waste NVAR All Extra Material In Proc. Crew Member Total Activities Waiting Processing Transport Movement Pos. Ins. TWSA Worker #3 20% 20% 3% 12% 20% 15% 4% 7% 100% Worker #4 0% 47% 5% 13% 11% 18% 2% 4% 100% Group 11% 32% 4% 12% 16% 16% 3% 5% 100% Percentage VA + NVAR 0% 20% 20% VA + NVAR 6% 7% 7% VA + NVAR 46% 24% 36% Table D.10 shows the weighted averages for the observed processes. These averages were used to represent the piping process in its entirety for this specific case study. Table D.10: Summary Table for Piping Process - Weighted Averages Pipe Spools - Entire Process Pre-Fabbed Pipe: Entire Process VA Crew Member All Activities Worker #1 17% Worker #2 19% Field Welded - Entire Process Worker #3 16% Worker #4 0% Weighted Average Percentages for 10% Group Waiting 25% 25% 20% 36% 27% Total Cumulative Time Observed for all Process 11:50:40 h:m:s Total Cumulative Time Observed for Cycle 1 6:52:15 h:m:s Waste NVAR Total % Extra Transport Movement Material Pos. In Proc. Ins. T.W.S.A Processing 10% 11% 22% 3% 1% 11% 100% 5% 4% 20% 19% 2% 6% 100% Total Cumulative Time Observed for Cycle 2 2:39:49 h:m:s 9% 12% 22% 12% 3% 7% 100% 23% 12% 8% 14% 2% 6% 100% 14% 11% 16% 12% 2% 7% 100% VA + NVAR % 32% 46% 38% 21% 32% 4.1 Waste Associated with Laborers and Equipment 4.1.1 Waiting Waiting accounted for roughly one third of the total time observed during each cycle shown in Tables D.8 and D.9. For the two dominant tasks of each cycle (elbow spool erection for Cycle No. 1 and new pipe spool erection for Cycle No. 2), a consistent one third of total time was wasted waiting. Waiting periods are nearly identical for each member within Crew No. 1. Table D.9 shows that for the Field Welded – New Pipe Spool activity, worker 4 waited twice as long as worker 3. This variation in waiting was because only one worker was able to weld the connection at any specific time. 244 4.1.2 Waste of Motion Tables D.8 and D.9 show waste due to excess motion for both crews. The work areas were limited in size, which prevented the workers from storing material around the work area. For example, for Cycle No. 1, there was a 21 percent overall waste percentage. For each piping component, one worker had to walk to the material lay-down yard to retrieve and transport that component back to the work area. For Cycle No. 2, a smaller value for motion was recorded – 15 percent of the total time. The majority of the time wasted on motion came from workers walking around the platform looking for tools/material necessary to continue their work. 4.1.3 Waste of Extra Processing Interpretation of this category included the use of defective materials delivered onsite that required modification to be operable. This included any preparation work around connection points such as cleaning out any metal slag from the spool, beveling and grinding the end connections prior to welding them and all preparation work required for the bolts prior to insertion into the bolt holes. This type of extra preparation work on the flanged connections accounted for the extra processing time spent during Cycle No. 1. During Cycle No. 2, rework (extra processing) accounted for over 16 percent of the total time attributed to the piping process. Worker 4 devoted more than 50 percent of his time to cutting, beveling and reconnecting the defective hung section of pipe.1 4.1.4 Waste of Transportation Several instances were observed in which equipment and material had to be rehandled and moved into an accessible position for the installation process. Transportation absorbed roughly 12 percent of each worker’s time during the cycles observed. A large portion of the time attributed to transportation involved positioning piping components from the lay-down yard into their holding position below the “final pipeline.” However, it was the small movements contributed by each worker while looking for tools and equipment that added large amounts of time to this waste category. Transport waste also occurred during Cycle No. 2 during positioning of the pipe on top of pipe stands to further prepare the new pipe spool for installation into final position in the line. 4.2 Waste Associated with Materials 4.2.1 Overproduction/Work in Progress (WIP) Overproduction waste (meaning too much of a building is produced) is rare in construction. Most construction reflects a “build to contract mentality” that requires a specific product(s) to be produced. WIP, on the other hand, is evident in construction but is dependent on the activity level being viewed. At the process-specific level, WIP is seldom observed. However, at the management level, each unfinished component of the production process represents WIP. For this study, WIP was represented by the unfinished pipeline. 1 Note: This differed from the waste category defects discussed in Section 4.2 in that the current crew was responsible for erecting the hung pipe incorrectly. The defect was not passed downstream to the next work station, but was reworked by the existing crew. 245 4.2.2 Inventory Material deliveries were made continually throughout the construction process. The steel pipe was delivered onsite on a large flatbed and placed within the material lay-down yard in bundles of similar pipe. The material was then moved to the tent for field fabrication or, when possible, it was moved directly to its position within the pipeline. The material was retrieved from the pipe bundles as needed. The variability of the amount of material onsite was heavily influenced by the sporadic nature of the pipe erection process. The limited area within the structure where the installation occurred created a problem for the erection crew to install the pipeline in linear order. Due to the brief observation time period onsite, it was difficult to quantify the inevitable waste in inventory that occurred. 4.2.3 Defects Defects are defined as errors or deficiencies in a finished product that require additional work on the part of a crew or a follow-up crew. A defective release valve or piping component delivered onsite from the manufacturer is an example of a defect (i.e., the material has been passed downstream through the value stream to the next work station). Another example of a defect is included in the punch list process at the end of a job. When a defect in the finished product is found at this stage, a separate follow-up crew is activated to correct the defect. Hence, the defect is pushed onto the next work station. Time associated with the crew members having to rework the hung pipe section was accounted for in the Extra Processing column shown in Table D.10. Furthermore, because of the brief site visit, no waste due to defects was observed. 5.0 Value Stream Analysis The following paragraphs describe the current value stream map for this piping erection process, beginning from the time material was ordered and shipped from the manufacturer, through the construction production process and ending with the material in final position within the facility. Figure D.12 is a simple flow diagram, with each box representing a point in time when the material was handled, either to be moved or transformed into its next stage (phase) in the construction life cycle. Manufacturer delivers material to site in one large shipment Pipe spool is pulled from bundle and transported to work area Material is delivered to material laydown yard in piping bundles Pipe spool is pulled from bundle to be field fabricated to specified requirement Spool is erected and secured into final position Spool positioned in work area beneath installation point Fabricated spool is transported to work area Final prep work is performed on spool Figure D.12: Material Flow Diagram Information on delivery and handling of the piping components was obtained from the project manager. Once it arrived onsite, the basic flow of the steel pipe was as follows: • Post-piping components were delivered to the site in bundles to the lay-down yard. • Raw pipe was pulled from the separate bundles in the yard. 246 • Pipe was cut to desired length. • Pipe followed one of two paths after being cut: − Pipe was welded to other pipe sections while remaining in the tent inside the material lay-down yard. (1) − Entire spool was moved to final location for installation. Pipe was erected into intended location within the power plant. • Pipe was welded at joints. • Pipe was X-rayed following erection: − Pass - Finished for painting. − Fail - Weld was cut out and welded again: (1) Pass - Finished for painting. 5.1 Value Stream Map for Case Study No. 4 For the value stream map analysis depicted on Figure D.13, three levels were needed to represent both the material and labor components. Level One represents the major staging positions that material must go through to reach finished state. Each time material was moved or transformed, a stage box is used to represent the process. Some of the stages include substages (Level Two) to represent processes that occurred simultaneously. The individual crew contributions to the value stream are represented on Level Three. The value stream map shown on Figure D.13 was created using the information described in the preceding section. Each major stage that the piping components went through is represented on Level One. Two different manufacturers were used to supply piping components to the job and are represented in this map. Ideally, the material should be tracked separately; however, lack of information prevented this from occurring. During Stage Two, the components went through two substages to complete the main stage. Notice that the steel had inventory position here, which represented the time that the steel sat between fabrication and erection. Stage One of the value stream was not observed during this site visit. However, the project superintendent confirmed that Stage One occurred. An estimate of three days’ total was shown for Stage One completion. This value stream ended once the piping erection process reached the testing and detailing stage. Again, the brief observation period prevented acquiring data about this stage in the entire steel erection process. Attention was instead focused on the two substages required for Stage Two. As shown in Levels Two and Three, the majority of time spent during the steel erection process was on the field fabricated spools. Furthermore, the total linear footage required to be field fabricated and prefabricated was estimated in Area Three of Level Three. Using this value and the value found for cumulative time spent per linear foot of pipe, the man-hours required to complete each line (field or prefabricated process) were estimated. These values were used to determine the total “Days required” for the main substages in Level Two. Refer to the circled areas on Figure D.13; these values are subject to change with actual data entered in the Estimated Total Linear Feet for Each Pipe column. 247 Every 1-3 days Production Control Project Engineer Level One Distribution of time from VSM for entire process Project Feedback Triggering Event Steel Is ordered in one large shipment Percent Complete NVA Time Pipe Component (valves, flangeplates, etc…) Supplier Pipe Spool Supplier Time Allocation Field Project Superintendent Spools are in place awaiting final testing and detailing. As Required NVAR Time 1 VA Time Work Time Daily 0 Spools are delivered to the site in bundles of like sizes in standard lengths. O O 200 400 Pipe components are shipped to material yard on the site O O O 600 800 1000 1200 Manhours O O Stage One - Spools and Pipe Components are Offloaded from Trucks and positioned in material yard Days required 3 Equipment involved: Forklift 1 Workers involved 4 Crew WT VA ( 0%) NVAR (0%) NVA (100%) O 96 0 0 96 Stage Two - Pipe Elements (Raw Spools, Valves, etc…) Are Pulled from Material Yard, Prepped, and Erected into Final Position. Days required 30 Equipment involved: 0 Workers involved Crew 9 WT 720.0 VA ( 8%) 61.5 NVAR (19%) 151.6 NVA (73%) 506.9 Inv Quick Summary for Level One For All Spools Worked on During Observation Period Working Days 33 Working Time 1267 man hours VA Total 98 man hours NVAR Total 266 man hours NVA Total 904 man hours Inventory Days 22 20 Level Two 14.1 Level Three 4 451.2 36.1 94.7 320.3 Crew #2: Field Welded - Entire Process VA Crew Member All Activities Waiting Worker #3 Worker #4 Group Percentage 16% 0% 20% 36% 8% 28% In v 2 All Activities Waiting 25% 25% 17% 25% NVA VA All Activities Worker #1 Worker #2 Field Welded - Entire Process Worker #3 Worker #4 Weighted Average Percentages for Group Waiting 17% 19% 25% 25% 16% 0% 20% 36% 10% Cumulative Time for Each Element Cumulative Time for Field Fabricated Cumulative Time for Piping Components Total Time 1.8 0 3 43.2 7.3 9.5 26.4 8:58:40 12% 12% 12% 71% Extra Processing 10% 5% Movement Material Pos. 22% 8% 12% 14% 15% 13% NVAR Total Cumulative Time Spent on Spool 27% 14% Linear Feet of Various Spools 8 8 In Proc. Ins. 3% 2% 2% TWSA Total 7% 6% 100% 100% 38% 21% 100% 30% 6% Transport 11% 4% Movement 11% Material Pos. 22% 20% 16% Estimated Total Cumulative Linear Feet for Time Spent Each Pipe Per Linear Foot 1:07:20 100 0:21:30 20 Total Estimated Mhrs 21% 2:52:00 h:m:s In Proc. Ins. 3% 19% 1% 2% 11% 2% NVAR TWSA Total VA + NVAR 11% 6% 100% 100% 32% 46% 100% 39% 9% 22% 11:50:40 6:52:15 h:m:s h:m:s NVAR Material Pos. In Proc. Ins. 3% 19% 1% 2% 12% 14% 3% 2% 12% Estimated Man-hours to Complete Each Line 112:13:20 7:10:00 119:23:20 2% % of Total Time 94% 6% TWSA 11% 6% 2:39:49 7% 6% 7% Total Figure D.13: Value Stream Map VA + NVAR 100% 100% h:m:s 100% 100% 38% 21% 32% 46% 100% 32% % of Total Time each LF of Pipe Spool 0.9% 0.3% Average VA Percentage Average NVAR Percentage Average NVA Percentage 248 VA + NVAR NVAR 8% 7% 21% 61% Total Cumulative Time Observed for all Process Total Cumulative Time Observed for Cycle 1 Waste Extra Transport Movement Processing 10% 11% 22% 5% 4% 20% Total Cumulative Time Observed for Cycle 2 9% 12% 22% 23% 12% 8% Cumulative Time Observed for Various 8:58:40 2:52:00 11:50:40 h:m:s NVAR Transport 16% Pipe Spools - Entire Process Prefabricated Pipe: Entire Process Crew Member 676.8 54.1 142.1 480.5 Waste 17% 19% Group Percentage 6 Total Cumulative Time Spent on Column NVA Crew Member 0 Waste Extra Processing 9% 23% Prefabricated Pipe: Entire Process VA Worker #1 Worker #2 Final Preparation for Piping Components and Final Bolt-Up Days required Equipment involved: Handtools Workers involved: Crew WT VA ( 17%) NVAR (22%) NVA (61%) 28.2 Final Preparation for Onsite Fabricated Spools and their Installation Days required 14.1 Equipment involved: Handtools 0 Workers involved: Crew 2 WT 225.6 VA ( 8%) 18.0 NVAR (21%) 47.4 NVA (71%) 160.2 Raw Spools Are Pulled from Bundles and Fabricated Onsite to Specified Dimensions Days required Equipment involved: Handtools Workers involved: Crew WT VA ( 8%) NVAR (21%) NVA (71%) Pipe Spools Fabricated Onsite Days required Equipment involved: Handtools Workers involved: Crew WT VA ( 8%) NVAR (21%) NVA (71%) 10% 21% 68% 1400 Another substage process was required for the field fabrication process in Level Two. The spools were fabricated in a temporary shop designated the “tent.” Four crewmen were entered into this substage to represent the average number of pipe fitters working in the tent. It was assumed that the weighted average values found from the observations were representative of the work distribution values for this substage. Table D.11 and Figure D.14 show the Quick Summary results for the work distribution values. Of the 1,267 total workable hours committed to the piping erection process, only 98 of them were VA. The NVAR category consisted of 266 hours; this value was high as a result of moving the pipe 15 feet above the ground floor. Finally, the majority of time spent during the piping erection process was on NVA actions. Table D.11: Quick Summary of Steel Process Quick Summary for Level One For All Spools Worked on During Observation Period Working Days 33 Working Time 1,267 Man-hours 98 Man-hours VA Total NVAR Total 266 Man-hours 904 Man-hours NVA Total Distribution of Time from VSM for Entire Process Time Allocation Field NVA Time NVAR Time 1 VA Time Work Time 0 200 400 600 800 1000 1200 1400 Man-hours Figure D.14: Graphic Display for the Quick Summary Table Figure D.15 and Table D.12 illustrate how the work distribution values changed and grew throughout the process life cycle. The weighted average results found in Level Three of the value stream map were used to formulate all the VA, NVAR and NVA values in Table D.12. As shown on Figure D.15, the cumulative NVA hours line grew the fastest compared to the other work distribution values. The black vertical line indicates when the pipe delivery process finished and the steel erection process began. The slope change for the cumulative work hours line indicates that more crew members were introduced to the process. As seen on the figure, the cumulative VA hours line finally started to grow. 249 4000 3500 Time (man-hours) 3000 2500 Cumulative Calendar Hours Cumulative Workable Hours 2000 Cumulative VA Hours Cumulative NVAR Hours Cumulative NVA Hours 1500 1000 Fabrication and Installation Begin 500 Note: The values used to create this chart are the average values from the work distribution values found for the entire crew. 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 Calendar Days Figure D.15: Work Distribution Life Cycle Graph 250 Table D.12: Spreadsheet of Values Used to Create Work Distribution Life Cycle Graph Stage Primary Activity for the Day Day Stage 1 Stage 1 Stage 1 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Stage 2 Steel is delivered and offloaded from Paint Subcontractor Steel is delivered and offloaded from Paint Subcontractor Steel is delivered and offloaded from Paint Subcontractor Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Weekend Weekend Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Weekend Weekend Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Weekend Weekend Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Weekend Weekend Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Weekend Weekend Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Piping Components are fabbed onsite, prepped and Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday Tuesday Wednesday Thursday Friday Cumulative Cumulative Hours Calendar Cumulative Calendar Workable Crew Workable Cumulative VA NVAR NVA VA Cumulative NVAR Cumulative NVA Cumulative Calendar Workable worked Days Calendat Days Hours Days available Hours Work Hours Percentage Percentage Percentage Hours VA Hours Hours NVAR Hrs. Hours NVA Hrs Hours days per day 1 1 32 32 1 1 4 8 32 32 0% 20% 80% 0 0 6.4 6.4 25.6 25.6 1 2 32 64 1 2 4 8 32 64 0% 20% 80% 0 0 6.4 12.8 25.6 51.2 1 3 32 96 1 3 4 8 32 96 0% 20% 80% 0 0 6.4 19.2 25.6 76.8 1 4 88 184 1 4 11 8 88 184 10% 21% 68% 8.8 8.8 18.48 37.68 59.84 136.64 1 5 88 272 1 5 11 8 88 272 10% 21% 68% 8.8 17.6 18.48 56.16 59.84 196.48 1 6 88 360 0 5 11 0 0 272 10% 21% 68% 0 17.6 0 56.16 0 196.48 1 7 88 448 0 5 11 0 0 272 10% 21% 68% 0 17.6 0 56.16 0 196.48 1 8 88 536 1 6 11 8 88 360 10% 21% 68% 8.8 26.4 18.48 74.64 59.84 256.32 1 9 88 624 1 7 11 8 88 448 10% 21% 68% 8.8 35.2 18.48 93.12 59.84 316.16 1 10 88 712 1 8 11 8 88 536 10% 21% 68% 8.8 44 18.48 111.6 59.84 376 1 11 88 800 1 9 11 8 88 624 10% 21% 68% 8.8 52.8 18.48 130.08 59.84 435.84 1 12 88 888 1 10 11 8 88 712 10% 21% 68% 8.8 61.6 18.48 148.56 59.84 495.68 1 13 88 976 0 10 11 0 0 712 10% 21% 68% 0 61.6 0 148.56 0 495.68 1 14 88 1064 0 10 11 0 0 712 10% 21% 68% 0 61.6 0 148.56 0 495.68 1 15 88 1152 1 11 11 8 88 800 10% 21% 68% 8.8 70.4 18.48 167.04 59.84 555.52 1 16 88 1240 1 12 11 8 88 888 10% 21% 68% 8.8 79.2 18.48 185.52 59.84 615.36 1 17 88 1328 1 13 11 8 88 976 10% 21% 68% 8.8 88 18.48 204 59.84 675.2 1 18 88 1416 1 14 11 8 88 1064 10% 21% 68% 8.8 96.8 18.48 222.48 59.84 735.04 1 19 88 1504 1 15 11 8 88 1152 10% 21% 68% 8.8 105.6 18.48 240.96 59.84 794.88 1 20 88 1592 0 15 11 0 0 1152 10% 21% 68% 0 105.6 0 240.96 0 794.88 1 21 88 1680 0 15 11 0 0 1152 10% 21% 68% 0 105.6 0 240.96 0 794.88 1 22 88 1768 1 16 11 8 88 1240 10% 21% 68% 8.8 114.4 18.48 259.44 59.84 854.72 1 23 88 1856 1 17 11 8 88 1328 10% 21% 68% 8.8 123.2 18.48 277.92 59.84 914.56 1 24 88 1944 1 18 11 8 88 1416 10% 21% 68% 8.8 132 18.48 296.4 59.84 974.4 1 25 88 2032 1 19 11 8 88 1504 10% 21% 68% 8.8 140.8 18.48 314.88 59.84 1034.24 1 26 88 2120 1 20 11 8 88 1592 10% 21% 68% 8.8 149.6 18.48 333.36 59.84 1094.08 1 27 88 2208 0 20 11 0 0 1592 10% 21% 68% 0 149.6 0 333.36 0 1094.08 1 28 88 2296 0 20 11 0 0 1592 10% 21% 68% 0 149.6 0 333.36 0 1094.08 1 29 88 2384 1 21 11 8 88 1680 10% 21% 68% 8.8 158.4 18.48 351.84 59.84 1153.92 1 30 88 2472 1 22 11 8 88 1768 10% 21% 68% 8.8 167.2 18.48 370.32 59.84 1213.76 1 31 88 2560 1 23 11 8 88 1856 10% 21% 68% 8.8 176 18.48 388.8 59.84 1273.6 1 32 88 2648 1 24 11 8 88 1944 10% 21% 68% 8.8 184.8 18.48 407.28 59.84 1333.44 1 33 88 2736 1 25 11 8 88 2032 10% 21% 68% 8.8 193.6 18.48 425.76 59.84 1393.28 1 34 88 2824 0 25 11 0 0 2032 10% 21% 68% 0 193.6 0 425.76 0 1393.28 1 35 88 2912 0 25 11 0 0 2032 10% 21% 68% 0 193.6 0 425.76 0 1393.28 1 36 88 3000 1 26 11 8 88 2120 10% 21% 68% 8.8 202.4 18.48 444.24 59.84 1453.12 1 37 88 3088 1 27 11 8 88 2208 10% 21% 68% 8.8 211.2 18.48 462.72 59.84 1512.96 1 38 88 3176 1 28 11 8 88 2296 10% 21% 68% 8.8 220 18.48 481.2 59.84 1572.8 1 39 88 3264 1 29 11 8 88 2384 10% 21% 68% 8.8 228.8 18.48 499.68 59.84 1632.64 1 40 88 3352 1 30 11 8 88 2472 10% 21% 68% 8.8 237.6 18.48 518.16 59.84 1692.48 251 Appendix E Case Study No. 5 - Process Piping 1.0 Overview 1.1 Project Goal The purpose of this case study was to collect data to develop a value stream map for the construction process. During this study, observations were focused on the installation of an eightinch diameter pipe spool. Two 10-foot sections of eight-inch diameter pipe were joined on the ground to form the spool. Work was observed on two-inch diameter and four-inch diameter spools, and a 10-inch diameter prefabricated elbow section. Field data collected on two separate value streams included the actual flow of the prefabricated pipe from the time it arrived on the jobsite until it was erected into final position, and the flow of worker activities performed to install the several sections of steel pipe. 1.2 Data Collection Procedure Data collection was accomplished in two consecutive days, with video footage taken during both sessions. One crew consisting of three men was observed during both days. Each observer was equipped with a digital camera. The digital video cameras were positioned to view the activity area at right angles to provide depth in both viewing directions. In the lab, two televisions were placed next to each other and used to view the recorded piping operations. Using both cameras provided a three-dimensional view of the work space to document the data collection process. Each time a new task was started, an entry was made on the data sheet. For example, an entry might indicate that a worker was grinding a pipe. The next entry might indicate that the worker had moved to gather the tools or materials necessary to continue preparing the pipe for installation. The elapsed time for each task was recorded as well as the observer’s judgment regarding whether the task was value adding (VA), non-value adding (NVA) or non-value adding but required (NVAR). 1.3 Project Description Construction of a new chemical processing plant was observed. Several mechanical components and interconnecting pipes were in the process of being installed. The purpose of the facility is to supply the surrounding region with a type of chemical fire suppressant agent. The study focused on one work area within the construction site, specifically, the final preparation and hoisting of various prefabricated process piping components into final position. This could only be done after all mechanical components were set into final position. Subsequent activities included X-ray testing of each weld and a pressurized line test to determine any leakage. The material lay-down yard was located 50 to 75 yards away from the final erection area located on the north side of the facility. 252 2.0 Prefabricated Spool Erection Process Few repetitive tasks occurred during the prefabricated spool erection process. A repetitive task was defined as one in which the worker repeated the same movement or action for every “member” (one pipe spool, valve and elbow) that was erected. For the following sections, an activity cycle is defined as starting when work began in the area of the spool erection, and finishing when the pipe was welded or bolted into its final place in the pipeline. The following sections describe the erection cycles of a four-inch diameter spool approximately eight feet long, and an eight-inch diameter spool approximately 20 feet long with an elbow in the center of the spool. Data are also included from work attributed to a two-inch diameter spool and a 10-inch diameter elbow section. Neither of these spools, however, was erected into final position before the observation period ended. Figure E.1 shows the layout of the observed work area and includes the relative position for each piping component. Figure E.1: Layout for Observed Work Area 2.1 Spool Section Two-Inch Diameter - Data Collection The cycle started when the pipe fitter touched the spool section that was sitting on a pipe stand. The spool was prepared by grinding off two inches of paint from both ends. The spool was painted offsite by a subcontractor separate from the spool fabricator. The painting subcontractor failed to cover the ends of the spool with tape to prevent the ends from being painted; therefore, all spools required rework (extra processing) to remove the paint from the ends. Following the paint removal, the pipe fitter beveled each end in preparation for the production weld. This data collection period ended before any further work was conducted on the two-inch spool. 2.2 Spool Section Four-Inch Diameter - Data Collection The cycle started when the four-inch diameter spool was transported from the material lay-down yard to the work area next to the facility. The spool was positioned on two pipe stands using a forklift. The spool had a flanged connection on one end, and the other end was to be welded. The welded end was ground down to remove the excess paint, and then beveled in preparation for the production weld. Along with the preparatory work on the spool itself, temporary pipe stands 253 were constructed to hold the pipe in position. The spool was then wrapped with two hoist lines and lifted into position with a boom crane. The crane held the spool in position while the temporary bracing was adjusted and the flanged end of the spool was bolted to one of the mechanical components. This observation cycle ended with the release of the hoist lines from the spool. 2.3 Spool Section Eight-Inch Diameter - Data Collection The cycle started when two of the eight-inch diameter spool sections (approximately 10 feet each) were transported from the material lay-down yard to the work area next to the facility. The spools were positioned on four pipe stands using a forklift. One spool had a flanged end and a weld end; the other spool had two weld ends. All of the weld ends required paint removal, then each weld was ground and beveled. A pipe guide was used to align and brace the two ends while tack welds were made. Upon completion of the tack welds, the pipe guide was removed and a production weld was made. The remaining weld end was ground and beveled. Figure E.2 shows the finished spool. Three hoist lines were attached to lift the entire spool section into final position. The flanged end of the spool combination was bolted to one of the mechanical components, while the opposite end was rigged with chain falls and temporarily braced in position until it could be secured to the structure. This observation cycle ended when the hoist lines were removed from the spool. Figure E.2: Complete Spool Section 2.4 Spool Section 10-inch Diameter Elbow Section Data Collection The following section covers observed rework. The prefabricated elbow section (shown on Figure E.3) did not meet the field requirements. Therefore, a two-inch section of pipe was removed from the elbow section. The observation cycle started when the worker touched the elbow section. Before the laborer began work on the elbow section, it was first positioned on two pipe stands. Four inches of paint were then removed around the middle of the elbow. A cut was made to sever the elbow piece and was followed by a second cut to remove two inches from the spool section. The data collection period ended before any further work was conducted on the elbow section. 254 Figure E.3: Cut Elbow Section The work process for all observed cycles required a three-man crew; however, the tasks for the four cycles required different movements and equipment to erect and secure each spool into its final position. One cycle required bolting of the flanged end to the mechanical member, while another cycle required the crew to bolt and weld a connection between different spools. The crew size also changed during the actual erection process of the spool members, with a second pipe fitter and a crane operator joining the three-man crew. Due to their limited involvement with the entire cycle, this data was excluded from the analysis. While the three-man crew remained constant for all of the cycles, the time required to perform the separate tasks did not. Therefore, in contrast to the “ideal” highly repetitive and balanced manufacturing sequence, it would be difficult to design an erection sequence that balanced both the amount of time needed as well as the equipment necessary to complete each task. The following section analyzes the workers’ contributions to each cycle. Table and figures show the work distribution values for each worker and describe the time spent on VA, NVA, and NVAR actions within each cycle. During the observation period, the following materials were installed: • Two 10-foot sections of eight-inch diameter steel pipe, with one having a flanged connection. • One 10-foot section of four-inch steel pipe with one flanged connection. • One six-foot section of 10-inch steel pipe with a 90 degree elbow and one flanged connection. • One three-foot section of two-inch steel pipe with one flanged connection. In addition, the following equipment and crew structures were observed: • One pipe fitter. • One welder. • One field laborer. • One boom crane. • One forklift. 255 2.5 Piping Installation Process In the following subsections, each worker in the crew is referred to by a field name that is used to track his/her actions for each identified activity. (Refer to the end of this case study to review the data collection sheets.) The spool installation process was similar for all components during the observation period. Each spool installation required the following: final preparation work on the ground, rigging to lift the spool section, greasing of the flanged connection point, bolting, final adjustment and inspections. One spool (eight-inch diameter) required an additional step before being lifted into final position in the pipeline. Ground welding occurred to secure two 10-foot sections of eightinch pipe together; Figure E.4 includes this process. Note that ground welding did not occur for any other spool section during this observation period and should be excluded when looking at the remaining spool sections. Other minor subcategory tasks occurred, but were not recorded. Figure E.4 shows the major tasks required to complete the prefabricated pipe spool installation. The shaded areas are used to indicate that some tasks took longer to complete than others, and that those tasks could occur simultaneously with other tasks. The shaded regions are not intended to show actual task durations (e.g., two days for material transport to the work area). Prefabricated Pipe Spool Installation Process 1 2 3 4 5 6 Task Order (process flow is shown, NOT TIME) 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Material delivered to site (material yard) Transported to work area Final prep work (grinding/filing flange area) "Ground Welding" of neighboring spools Inspection of welds Rigging spool section for lift Piping member is hoisted into place Gasket is greased and fit btwn. flanged spools Bolts are inserted and hand tightened Adjacent spools are hoisted into place Final adjustments (leveling/inspections) of spool Bolts are machine tightened to Specification Final production welds are made on joint Test and balance of line (leaks, and valve adj.) Note: This schedule shows process flow. It does not show actual task durations. Note: Process is similar for all prefabricated spool components (2", 4", 8", and 10" diameter spool components). Figure E.4. Schedule for Piping Erection Process for Two-, Four-, Eightand 10-Inch Diameter Spools 2.5.1 Spool Section - Two-inch Diameter The pipe fitter and field laborer were the only people involved with the two-inch spool section. The welder did not contribute time to any task involving the two-inch spool section. The field laborer was responsible for grinding and beveling the spool section while it remained on the ground. Table E.1 and Figure E.5 show the VA, NVA and NVAR values for the field laborer. When working with the two-inch spool section, the field laborer contributed nearly all of his time (93 percent) to NVA actions. This was a result of the grinding and beveling actions required for preparation of the pipe spool. 256 Table E.1: Prefabricated Piping Data for the Field Laborer - Two-Inch Diameter A c t iv it y C la s s if ic a t io W a s t e C la s s if ic a t io n NVA T im e a t A c t iv it y W a itin g E x tra P ro c . T ra n s p o rt M o tio n % o f T im e a t A c t iv it y 0 :2 3 :1 6 0 :2 4 :1 3 0 :0 6 :3 0 0 :0 1 :5 5 3 8 .8 9 % 4 0 .4 7 % 1 0 .8 6 % 3 .2 0 % 0 :5 5 :5 4 9 3 .4 3 % 0 :0 0 :3 5 0 :0 1 :1 0 0 :0 2 :1 1 0 .9 7 % 1 .9 5 % 3 .6 5 % N V A R T o ta l 0 :0 3 :5 6 6 .5 7 % G ra n d T o ta l 0 :5 9 :5 0 1 0 0 .0 0 % N V A T o ta l NVAR M a te ria l P o s . In -P ro c e s s In s . T .W .S .A Field Laborer – 2 Inch Pipe Spool NVAR Material Positioning 1% NVA Motion 3% NVA Transport 11% NVAR In-Process Inspection NVAR TWSA 2% 4% NVA Waiting 39% NVA Extra Processing 40% Figure E.5: Prefabricated Piping Data for the Field Laborer - Two-Inch Diameter The pipe fitter field verified the dimensions of the two-inch diameter spool by measuring and checking them with the latest construction documents. He was also responsible for final inspection of the beveled ends. Table E.2 and Figure E.6 show the VA, NVA and NVAR values for the pipe fitter. Notice that the pipe fitter contributed the majority (83 percent) of his time to NVA actions. No time was spent on VA actions. Table E.2: Prefabricated Piping Data for the Pipe Fitter - Two-Inch Diameter Ac tivity C la ssific a tio n NV A W a ste C la ssific a tio n W aitin g E xtra P ro c. M o tio n NV A T o ta l T im e a t Ac tivity % o f T im e a t Ac tivity 0:02:47 0:03:13 0:07:47 16.78% 19.40% 46.93% 0 :1 3 :4 7 8 3 .1 2 % NV AR 0:02:48 16.88% NV AR T o ta l In -P ro cess In s. 0 :0 2 :4 8 1 6 .8 8 % G ra n d T o ta l 0 :1 6 :3 5 1 0 0 .0 0 % 257 Pipe Fitter – 2 Inch Spool Section NVAR In-Process Inspection 17% NVA Waiting 17% NVA Extra Processing 19% NVA Motion 47% Figure E.6: Prefabricated Piping Data for the Pipe Fitter - Two-Inch Diameter 2.5.2 Spool Section - Four-Inch Diameter The pipe fitter was the only crew member involved with the four-inch diameter spool section. His main responsibilities included field verification of the dimensions of the four-inch spool by measuring and checking them with the most up-to-date construction documents, preparing the spool section with a hoist line, constructing temporary stands for the four-inch spool to rest on until the adjacent spool section could be erected into place, and completing all final leveling and adjustments while a second pipe fitter secured the flanged end to the mechanical component. Table E.3 and Figure E.7 show the VA, NVA and NVAR values for the pipe fitter. Notice that no actions were contributed to VA time during this erection sequence and all time attributed to the four-inch spool section was evenly split between NVA and NVAR actions. A second pipe fitter was introduced for a brief period to secure the flanged end to the mechanical component, which removed any possible VA actions from the original pipe fitters. Table E.3: Prefabricated Piping Data for the Pipe Fitter - Four-Inch Diameter Activity Classification NVA W aste Classification W aiting Extra Proc. T ransport M otion T ime at Activity % of T ime at Activity 0:18:12 0:08:48 0:08:10 0:06:19 22.80% 11.02% 10.23% 7.91% 0:41:29 51.96% 0:07:03 0:25:37 0:05:41 8.83% 32.09% 7.12% NVAR Total 0:38:21 48.04% G rand Total 1:19:50 100.00% NVA T otal NVAR M aterial Pos. In-Process Ins. T .W .S.A 258 Pipe Fitter – 4 Inch Spool Section NVAR TWSA 7% NVA Waiting 23% NVAR In-Process Inspection 32% NVA Extra Processing 11% NVAR Material Positioning 9% NVA Transport 10% NVA Motion 8% Figure E.7: Prefabricated Piping Data for the Pipe Fitter - Four-Inch Diameter 2.5.3 Spool Section - Eight-Inch Diameter All three members of the crew were involved with the eight-inch diameter spool section. The overall tasks required to erect the eight-inch spool section were similar to those for the two- and four-inch sections. With the eight-inch section, the added step of welding together the 10-foot sections of pipe on the ground was included in the overall process. The field laborer was responsible for the following: grinding off the excess paint, beveling each end that needed to be welded, aligning the ends of each 10-foot section of pipe using a pipe guide, and continually inspecting the work on the spool section as it progressed. Table E.4 and Figure E.8 show the VA, NVA and NVAR values for the field laborer. More than 80 percent of his time was spent on NVA actions, and waiting consumed the largest amount of time of all the waste categories (52 percent). Table E.4: Prefabricated Piping Data for the Field Laborer - Eight-Inch Diameter Ac tivity C la ssific a tio n NVA W a ste C la ssific a tio n W aitin g E xtra P ro c. T ran sp o rt M o tio n T im e a t Ac tivity % o f T im e a t Ac tivity 0:57:06 0:23:26 0:05:43 0:02:09 51.75% 21.24% 5.18% 1.95% 1 :2 8 :2 4 8 0 .1 2 % 0:02:30 0:01:26 0:18:00 2.27% 1.30% 16.31% N V AR T o ta l 0 :2 1 :5 6 1 9 .8 8 % G ra n d T o ta l 1 :5 0 :2 0 1 0 0 .0 0 % N V A T o ta l N V AR M aterial P o s. In -P ro cess In s. T .W .S .A 259 Field Laborer – 8 Inch Pipe Spool NVAR In-Process Inspection 1% NVAR Material Positioning 2% NVAR TWSA 16% NVA Motion 2% NVA Waiting 53% NVA Transport 5% NVA Extra Processing 21% Figure E.8: Prefabricated Piping Data for the Field Laborer - Eight-Inch Diameter The pipe fitter was involved with the following: positioning the two 10-foot sections onto pipe stands within the work area, aligning the two sections together with a pipe guide, and continually inspecting the work as grinding and welding occurred on the spool. When the weld was finished, the pipe fitter was involved with rigging and positioning the spool while it was lifted into place. He was also required to secure the unsupported spool end with temporary bracing until the adjacent section could be erected. Table E.5 and Figure E.9 show the VA, NVA and NVAR values for the pipe fitter. No VA actions occurred during the erection sequence. The time spent on NVA and NVAR actions was evenly split, with NVA and NVAR actions consuming 56 and 44 percent, respectively, of the time. Table E.5: Prefabricated Piping Data for the Pipe Fitter - Eight-Inch Diameter A c t iv it y C la s s if ic a t io n NVA W a s t e C la s s if ic a t io n W a itin g E x tra P ro c . T ra n s p o rt M o tio n T im e a t A c t iv it y % o f T im e a t A c t iv it y 0 :3 4 :5 4 0 :1 7 :5 1 0 :1 0 :5 2 0 :4 0 :4 7 1 8 .6 1 % 9 .5 2 % 5 .7 9 % 2 1 .7 4 % 1 :4 4 :2 4 5 5 .6 6 % 0 :2 2 :3 2 0 :3 4 :1 4 0 :2 6 :2 5 1 2 .0 1 % 1 8 .2 5 % 1 4 .0 8 % N V A R T o ta l 1 :2 3 :1 1 4 4 .3 4 % G ra n d T o ta l 3 :0 7 :3 5 1 0 0 .0 0 % N V A T o ta l NVAR M a te ria l P o s . In -P ro c e s s In s . T .W .S .A 260 Pipe Fitter – 8 Inch Spool Section NVAR TWSA 14% NVA Waiting 19% NVA Extra Processing 10% NVAR In Process Inspection 18% NVA Transport 6% NVAR Material Positioning 12% NVA Motion 21% Figure E.9: Prefabricated Piping Data for the Pipe Fitter - Eight-Inch Diameter The welder was responsible for the following: positioning the 10-foot sections of pipe onto the temporary stands, beveling the ends of each 10-foot section to be welded together, aligning the two ends together using a pipe guide, tack welding, performing final production weld, continuously inspecting the production weld, rigging the finished spool section for the crane, positioning and securing the eight-inch spool into its final position, and releasing the crane rigging from the spool section once secured. Table E.6 and Figure E.10 show the VA, NVA and NVAR values for the welder. Twenty-five percent of the welder’s actions were attributed to the VA category. This value was the largest for the observed three-man crew because of welder involvement with beveling the end sections and the final production weld. NVA actions consumed the majority of his time at 64 percent, with the subcategory of waiting being the primary activity. Extra processing (rework) also consumed a significant portion of time in this cycle. Table E.6: Prefabricated Piping Data for the Welder - Eight-Inch Diameter A c t iv it y C la s s if ic a t io n VA W a s t e C la s s if ic a t io n V a lu e A d d in g V A T o ta l T im e a t A c t iv it y % o f T im e a t A c t iv it y 1 :2 4 :1 1 2 4 .5 8 % 1 :2 4 :1 1 2 4 .5 8 % NVA W a itin g 1 :4 2 :3 7 2 9 .9 6 % E x tra P ro c . T ra n s p o rt M o tio n 0 :3 6 :2 8 0 :2 5 :2 3 0 :5 5 :2 1 1 0 .6 5 % 7 .4 1 % 1 6 .1 6 % 3 :3 9 :4 9 6 4 .1 8 % 0 :0 5 :3 3 0 :1 6 :1 7 1 .6 2 % 4 .7 5 % N V A T o ta l NVAR M a te ria l P o s . In -P ro c e s s In s . 0 :1 6 :4 0 4 .8 7 % N V A R T o ta l T .W .S .A 0 :3 8 :3 0 1 1 .2 4 % G ra n d T o ta l 5 :4 2 :3 0 1 0 0 .0 0 % 261 Welder – 8 Inch Spool Section NVAR In-Process NVAR TWSA Inspection 5% 5% NVAR Material VA Positioning 25% 2% NVA Motion 16% NVA Transport 7% NVA Extra Processing 11% NVA Waiting 29% Figure E.10: Prefabricated Piping Data for the Welder - Eight-Inch Diameter 2.5.4 Spool Section - 10-Inch Diameter Elbow Section The field laborer and pipe fitter were the only members of the three-man crew to work on the 10-inch elbow section. The spool section was already in the work area prior to the recording of this data. The elbow section needed to be cut due to field variations from the construction documents. The field laborer was responsible for the following: positioning the elbow section on the pipe stands, cutting the elbow section in half, cutting the elbow section down to the desired length and grinding/beveling the cut ends of the two separated pieces in preparation for further welding. Table E.7 and Figure E.11 show the VA, NVA and NVAR values for the field laborer. No VA action occurred during this cycle. Nearly the entire time (96 percent) was spent on NVA actions, with approximately 28 percent of the time spent on extra processing actions and 32 percent of the time spent waiting for the pipe fitter. Table E.7: Prefabricated Piping Data for the Field Laborer - 10-Inch Diameter Ac tivity C la ssific a tio n NVA W a s te C la s sific a tio n W a itin g E x tra P ro c . T ra n s p o rt M o tio n T im e a t Ac tiv ity % o f T im e a t Ac tiv ity 0 :5 5 :5 6 0 :4 7 :3 6 0 :2 0 :2 9 0 :4 0 :5 3 3 2 .4 6 % 2 7 .6 2 % 1 1 .8 9 % 2 3 .7 2 % 2 :4 4 :5 4 9 5 .6 9 % 0 :0 1 :0 0 0 :0 0 :1 5 0 :0 6 :1 1 0 .5 8 % 0 .1 5 % 3 .5 9 % N V AR T o ta l 0 :0 7 :2 6 4 .3 1 % G ra n d T o ta l 2 :5 2 :2 0 1 0 0 .0 0 % N V A T o ta l N V AR M a te ria l P o s . In -P ro c e s s In s . T .W .S .A 262 Fie ld Labore r - 8" Pipe Spool NVAR In-Process Ins. NVAR T.W.S.A 1% 16% NVAR Material Pos. 2% NVA Motion 2% NVA Waiting 53% NVA Transport 5% NVA Extra Proc. 21% Figure E.11: Prefabricated Piping Data for the Field Laborer - 10-Inch Diameter The pipe fitter was responsible for the following: field verifying the correct length for the elbow section, preparing the pipe to be cut and continually inspecting the work as it progressed. Table E.8 and Figure E.12 show the VA, NVA and NVAR values for the pipe fitter. Table E.8: Prefabricated Piping Data for the Pipe Fitter - 10-Inch Diameter A c tiv ity C la s s ific a tio n NVA W a s te C la s s ific a tio n W a itin g E x tra P ro c . T ra n s p o rt M o tio n N V A T o ta l T im e a t A c tiv ity % o f T im e a t A c tiv ity 0 :2 0 :5 2 0 :3 1 :4 2 0 :0 2 :1 0 0 :0 3 :0 6 3 5 .6 7 % 5 4 .1 9 % 3 .7 0 % 5 .3 0 % 0 :5 7 :5 0 9 8 .8 6 % NV AR 0 :0 0 :4 0 1 .1 4 % N V A R T o ta l T .W .S .A 0 :0 0 :4 0 1 .1 4 % G ra n d T o ta l 0 :5 8 :3 0 1 0 0 .0 0 % Fie ld Labore r - 10" Elbow Se ction NVA Motion 5% NVAR T.W.S.A 1% NVA Transport 4% NVA Waiting 36% NVA Extra Proc. 54% Figure E.12: Prefabricated Piping Data for the Pipe Fitter - 10-Inch Diameter 263 3.0 Results for the Crew A work distribution chart (Figure E.13) depicts the time spent on various actions for the prefabricated pipe with flange and the field fabrication production processes. During the observation period, the erection of two spools was completed. Ground work associated with preparing the two-inch and 10-inch spools was also observed, but not the actual installation of these components. This resulted in two incomplete cycles. Figure E.13 provides an accurate representation of the cycles observed for the four-inch diameter and eight-inch diameter spools. Both piping components varied in size and shape and required different equipment and erection procedures. Similar cycles did not occur during the observation; therefore, a cycle was defined as the entire observation period. For example, the cycle started with the positioning of the eight-inch spool onto pipe stands within the temporary workstation and concluded with the bolting and securing of the eight-inch diameter spool into final position. The mini cycles involving the two-, four- and 10-inch spools all occurred within the total eight-inch cycle time. The different shading on the chart represents the VA and waste tasks for each worker. 3.1 Crew Composition The crew member controlling the flow of work around the workstation was the pipe fitter. He dictated the actions of the field laborer and welder on each of the spool components. In an ideal situation, the pipe fitter would form the bottleneck in the work flow. During this observation period, however, the welder held back crew productivity. Several instances occurred in which the production weld did not meet project specifications, requiring the weld to be removed and redone. Notice that the time attributed to each “work classification category” varied significantly between crew members. The largest proportion of VA actions was contributed by the welder. While the pipe fitter contributed no VA actions to the entire process, it was his continual “in-process inspections” which ensured that defects were not pushed on to future crews. The largest amount of waiting occurred with the field laborer. Finally, the pipe fitter contributed the most time to material positioning. 3.2 General Observations About Crew Composition During the observation period, rework was a significant contributor to the high NVA value for the entire crew. This value may have been larger than normal due to the welder’s inexperience. Several instances occurred in which the production weld for the eight-inch diameter spool had to be ground out and redone to meet the weld requirements. Also, it was shown through the results of the data analysis that the pipe fitter contributed a large proportion of NVA actions to the overall work process. Several of these actions were noted as “support” activities for the rest of the crew. The pipe fitter constantly moved between the field laborer and welder to ensure that quality work was being completed and the correct sequence of work was occurring. Had the other two crew members been more experienced, the value for NVA actions would have been lower. Finally, the entirety of the field laborer’s time was spent on NVA and NVAR actions. Had the painting subcontractor taped the ends of each spool, the field laborer would have saved more than one hour that was spent removing the excess paint from the ends. 264 Worker Task Breakdown 6:00:00 5:24:00 Material Pos. 0:04:05 4:48:00 In-Process Ins. 0:02:51 4:12:00 T.W.S.A 0:26:22 Material Pos. 0:29:35 In-Process Ins. 1:02:39 Material Pos 0:05:33 Value Adding 1:24:11 T.W.S.A 0:32:46 3:36:00 Transport 0:21:12 Transport 0:32:42 3:00:00 In-Process Ins. 0:16:17 T.W.S.A Value Adding Motion T.W.S.A 0:16:40 Transport Extra Proc. In-Process Ins. Extra Proc. 1:35:15 2:24:00 Extra Proc. 1:01:34 Waiting Material Pos. Extra Proc. 0:36:28 1:48:00 1:12:00 Transport 0:25:23 Waiting 2:16:18 Waiting 1:16:45 Waiting 1:42:37 0:36:00 0:00:00 Motion 0:44:57 Field Laborer Motion 0:57:59 Motion 0:55:21 Pipe Fitter Welder Figure E.13: Work Distribution Chart 4.0 Process Improvement Opportunities A goal of this report was to examine and document the inefficiencies in construction operations. In general terms, inefficiencies were classified as the following three types: inefficiency due to waste (NVA activities), inefficiency due to unnecessary work (excessive NVAR activities) and inefficiency due to poorly designed work processes (ineffective VA activities). The following section identifies opportunities for process improvement by applying Ohno’s (1988) seven wastes in production and then evaluating the production process against a more comprehensive set of lean principles. Table E.9 shows the percentage of time spent on VA, NVA and NVAR as a percentage of total cumulative time available to each worker for the entire work cycle observed. Table E.10 lists the subset of activities that occurred to accomplish the entire erection process. In particular, the 265 NVA category is further divided into time spent in waiting, extra processing, transport and movement categories. Additionally, NVAR actions are broken down into three subcategories to clarify how time was spent within the observed cycles. Table E.9: Entire Activity Prefabricated Pipe - Entire Process Total Cumulative Time Spent on Spool VA Waste NVAR Crew Member All Extra Material In Proc. Waiting Transport Movement Activities Processing Pos. Ins. 0% 22% 18% 6% 17% 9% 18% Foreman - Pipe Fitter Field Laborer 0% 40% 28% 10% 13% 1% 1% 25% 30% 11% 7% 16% 2% 5% Welder Group Percentage 8% 31% 19% 8% 15% 4% 8% 17:07:30 h:m:s TWSA Total VA + NVAR 10% 8% 5% 100% 100% 100% 37% 10% 36% 7% 100% 27% 4.1 Waste Associated with Laborers and Equipment 4.1.1 Waiting Waiting accounted for roughly one-third of the total time observed during the cycle (Table E.9). Except for the slightly lower value of the four-inch diameter spool, the waiting time for the remaining subcategories consistently stayed near one third (Table E.10). Waiting durations for each member of the crew fluctuated between the different subactivities, which coincided with the problem of balancing a crew for one work activity; this sometimes resulted in other work activities being under- or overstaffed. Table E.10 also reflects how crew member experience affected the amount of time spent on waiting. Table E.9 shows that the pipe fitter contributed the least amount of time to waiting. This could be attributed to the fact that he was the most skilled worker in the crew, and that he was coordinating work activities. 4.1.2 Waste of Motion Table E.9 shows that excess movement accounted for roughly 15 percent of the entire time spent during the cycle. Table E.10 shows relatively equal amounts of time contributed to wasted movement. The crew members walked from the workstation to the tool shed (100 yards away) several times to retrieve new grinder pads and welding rods. (Note: When the workers carried material back to the workstation, it was recorded as transport, not movement.) 4.1.3 Waste of Extra Processing The interpretation of this category included the use of defective materials delivered onsite that subsequently required modification to be operable. This included any preparation work around connection points such as cleaning out any metal slag from the spool, beveling and grinding the end connections prior to welding, and removing paint from all end connections. Extra processing (rework) accounted for more than 19 percent of the total time attributed to the piping process. The field laborer contributed roughly 28 percent of his time to grinding off the paint and cutting the elbow spool to meet the field measurements. The pipe fitter contributed roughly 18 percent of his time to the following: rechecking plans, taking field measurements to ensure that the prefabricated spools would fit, and aligning the correct cut line on the elbow section to guide the field laborer. 266 Table E.10: Subactivities Pre-Fabbed Pipe: 2" Pipe Spool Total Cumulative Time Spent on Spool Waste NVAR VA Crew Member Extra All Material In Proc. Waiting Transport Movement Processing Activities Pos. Ins. Foreman - Pipe Fitter 0% 17% 19% 0% 47% 0% 17% Field Laborer 0% 39% 40% 11% 3% 1% 2% Welder 0% 0% 0% 0% 0% 0% 0% 0% 34% 36% Group Percentage 9% 13% 1% 5% Pre-Fabbed Pipe: 4" Pipe Spool Total Cumulative Time Spent on Spool Waste NVAR VA Crew Member All Extra Material In Proc. Waiting Transport Movement Activities Processing Pos. Ins. Foreman - Pipe Fitter 0% 23% 11% 10% 8% 9% 32% Field Laborer 0% 0% 0% 0% 0% 0% 0% Welder 0% 0% 0% 0% 0% 0% 0% Group Percentage 0% 23% 11% 10% 8% 9% 32% Pre-Fabbed Pipe: 8" Pipe Spool Total Cumulative Time Spent on Spool VA Waste NVAR Crew Member All Extra Material In Proc. Waiting Transport Movement Ins. Activities Processing Pos. Foreman - Pipe Fitter 0% 19% 10% 6% 22% 12% 18% Field Laborer 0% 52% 21% 5% 2% 2% 1% Welder 25% 30% 11% 7% 16% 2% 5% Group Percentage 13% 30% 12% 7% 15% 5% 8% Pre-Fabbed Pipe: Elbow Section Total Cumulative Time Spent on Spool Waste NVAR VA Crew Member Material In Proc. Extra All Transport Movement Waiting Pos. Ins. Processing Activities Foreman - Pipe Fitter 0% 36% 54% 4% 5% 0% 0% Field Laborer 0% 32% 28% 12% 24% 1% 0% 0% 0% 0% 0% 0% 0% 0% Welder Group Percentage 0% 33% 34% 10% 19% 0% 0% 1:16:25 h:m:s T.W.S.A 0% 4% 0% Total % 100% 100% 0% 3% 100% 1:19:50 h:m:s T.W.S.A 7% 0% 0% Total % 100% 0% 0% 7% 100% 10:40:25 h:m:s T.W.S.A 14% 16% 5% Total % 100% 100% 100% 10% 100% 3:50:50 h:m:s VA + NVAR % 17% 7% 0% 9% VA + NVAR % 48% 0% 0% 48% VA + NVAR % 44% 20% 36% 36% 1% 4% 0% 100% 100% 0% VA + NVAR % 1% 4% 0% 3% 100% 4% T.W.S.A Total % 4.1.4 Waste of Transportation Transportation was not as large a contributor to wasted time as the other categories. However, it did consume 8 percent (Table E.9) of the total time. Each time a worker walked back from the tool shed carrying a new grinder pad or welding rod, time was added to the transportation category. Transport waste also occurred when positioning the pipe on the pipe standings to further prepare the spools. 4.2 Waste Associated with Materials 4.2.1 Overproduction (WIP) Overproduction waste (meaning too much of a building is produced) is rare in construction. Most construction reflects a “build to contract mentality” that requires a specific product(s) to be produced. WIP, on the other hand, is evident in construction but is dependent on the activity level being viewed. At the process-specific level, WIP is seldom observed. However, at the management level, each unfinished component of the production process represents WIP. For this study, WIP was represented by the unfinished pipeline. 4.2.2 Inventory Material deliveries consisted of two large shipments from the manufacturer. The prefabricated steel pipe was delivered from the manufacturer to the painting subcontractor. The subcontractor painted each spool section, then delivered the painted spools to the material lay-down yard. The spools were then pulled from the material lay-down yard and moved to the workstation, where 267 final preparation work and production welds were completed. Finally, the spools were erected into final position. It was recognized that waste in inventory occurs; however, it was not possible to quantify this waste through physical observation. 4.2.3 Defects Defects are defined as errors or deficiencies in a finished product that required additional work on the part of the original crew or a follow-up crew. A faulty release valve or piping component delivered onsite from the manufacturer is an example of a defect (i.e., the material has been passed through the value stream to the next workstation). Another example of a defect is included in the punch list process at the end of a job. When a defect in the finished product is found at this stage, a separate follow-up crew is activated to correct the defect. Hence, the defect is pushed on to the next workstation. Time spent on reworking the elbow section was accounted for in the extra processing section. No waste associated with defects was observed. 5.0 Value Stream Analysis The following paragraphs describe the current value stream map for this piping erection process, beginning from the time the material was ordered and shipped from the manufacturer, through the construction production process, and ending with the material in final position. Figure E.14 is a simple flow diagram with each box representing a point in time when the material was touched, either to be moved or transformed into the next stage (phase) in the construction life cycle. Manufacturer delivers material to site in two large shipments Material is delivered to material laydown yard Fabricated spool is transported to work area Spool is positioned in work area onto temporary pipe stands Rework occurs on spools that do not meet field measurements Spool is erected and secured into its final position Final prep work is performed on spool Figure E.14: Material Flow Diagram Information on delivery and handling of the piping components was obtained from the steel erector. The basic flow of the prefabricated spools was as follows: • Pipe was cut, shaped and welded to specification at the manufacturer’s plant. • Pipe manufacturer delivered spools to cleaning and painting facility in two large shipments. • Cleaning and painting subcontractor prepared spools for the site. • Cleaned and painted spools were delivered in two large shipments to the laydown yard. • Spools were pulled from the lay-down yard as needed by the field foreman (pipe fitter) and positioned on temporary pipe stands for final preparation work within the workstation. 268 • If the spool did not meet the field measurements, rework (cutting spool to desired shape) occurred on the spool until a perfect fit could be made. • Crane rigging was attached to the spool sections and the spool was hoisted into its final position within the pipeline as follows: − Flanged ends were bolted. − Pipe alignment and leveling occurred. − Production welds were completed on nonflanged ends. • Temporary bracing and supports were put in place until permanent supports could be installed. • Crane rigging was released. 5.1 Value Stream Map for Case Study No. 5 For the value stream map depicted on Figure E.15, three levels were needed to represent both the material and labor components. Level One represents the major staging positions that material must go through to reach its finished state. Each time material was moved or transformed, a stage box is used to represent the process. Some of the stages include substages (Level Two) to represent processes that occurred simultaneously. The individual crew contributions to the value stream are represented on Level Three. The value stream map shown on Figure E.15 was created using the information described in the preceding section. Each major stage that the piping components went through is represented on Level One. Two different manufacturers were used to supply piping components to the job and are represented on this map. The material flowed from the fabricator to the painting subcontractor. An inventory position of five days between the two parties is shown. This uses an assumption for the amount of time that the material sat before being cleaned and painted. No substages for Level Two are represented; all values from Level Three can be directly entered into Stage Two. No observations were made regarding Stage One since it was not directly witnessed; however, the project superintendent confirmed that those activities occurred. An estimate of three days total is shown for completion of Stage Two. The value stream ended once the piping erection process reached the testing and detailing stage. Again, the limited observation period prevented acquiring data on this stage in the entire steel erection process. Attention instead was focused on the two substages required for Stage Two of the value stream. In Levels Two and Three, the majority of time spent during the steel erection process was on the field fabricated spools. In Area Three of Level Three, the total linear footage that was required to be field fabricated or prefabricated was estimated. Using this value and the value determined for Cumulative Time Spent per Linear Foot of Pipe, the total man-hours required to complete each line (field or prefabricated process) could be estimated. These values are subject to change from actual data entered into the Total Linear Feet for Each Pipe Diameter column. 269 Figure E.15: Value Stream Map 270 Table E.11 and Figure E.16 show the quick summary results for the work distribution values. Of the 800 total workable hours committed to the piping erection process, only 58 of them were VA. Of the total, 153 hours contributed to the NVAR category. This value was high as a result of moving the pipe 15 feet above the floor. Finally, the overwhelming period of time spent during the piping erection process was on NVA actions. Table E.11: Quick Summary of Steel Process Quick Summary for Level One For All Spools Worked on During Observation Period Working Days Working Time VA Total NVAR Total NVA Total 35 800 58 153 590 Man-hours Man-hours Man-hours Man-hours Time Allocation of Field Distribution of Time from VSM for One Phase NVA Time NVAR Time 1 VA Time Work Time 0 100 200 300 400 500 600 700 800 Manhours Figure E.16: Graphical Display for the Quick Summary Table Figure E.17 and Table E.12 illustrate how the work distribution values changed and grew throughout the process life cycle. The weighted average results found in Level Three of the value stream map were used to calculate all of the VA, NVAR and NVA values in Table E.12. As shown on Figure E.17, the cumulative NVA line grew the fastest compared to the other work distribution values. The black vertical line indicates when the pipe delivery process finished and the steel erection process began. The slope change for the cumulative workable hours line indicates that more crew members were introduced to the process. As seen on the figure, the cumulative VA hours line finally started to grow. 271 Work Distribution 1800 1600 1400 1200 Stage 1, 2 Delivery and material handling Time (man-hours) 1000 Cumulative Calendar Hours Cumulative Work Hours Cumulative VA Hours 800 Cumulative NVAR Hrs Cumulative NVA Hrs Linear (Cumulative VA Hours) 600 Stage 3 - Final Prep and Erection process 400 Linear (Cumulative NVA Hrs) y = 17.384x - 20.703 200 y = 1.8922x - 6.4148 0 1 -200 3 5 7 9 Note: The values used to create this chart are the average 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 values from the work distribution values found for the entire crew. Calendar Days Figure E.17: Work Distribution Life Cycle Graph 272 Table E.12: Spreadsheet of Values Used to Create Work Distribution Life-Cycle Graph Stage Stage 1 Stage 1 Stage 2 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 2,3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 2,3 Stage 3 Stage 3 Stage 3 Stage 2,3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 2,3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 2,3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 2,3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Stage 3 Primary Activity for the Day Day Steel is delivered and offloaded from Paint Subcontractor Monday Steel is delivered and offloaded from Paint Subcontractor Tuesday Spools are pulled from Yard and Positioned in work area Wednesday Thursday Final Prep Work Friday Final Prep Work Weekend Saturday Weekend Sunday Monday Final Prep Work and Erection Process Spools are pulled from Yard and Positioned in work area, Final Prep Work Tuesday Final Prep Work Wednesday Final Prep Work Thursday Friday Final Prep Work and Erection Process Weekend Saturday Weekend Sunday Spools are pulled from Yard and Positioned in work area, Final Prep Work Monday Final Prep Work Tuesday Wednesday Final Prep Work Final Prep Work and Erection Process Thursday Spools are pulled from Yard and Positioned in work area, Final Prep Work Friday Weekend Saturday Weekend Sunday Final Prep Work, Second Delivery of Spools arrives and is positioned on groun Monday Final Prep Work, Second Delivery of Spools arrives and is positioned on groun Tuesday Final Prep Work and Erection Process Wednesday Spools are pulled from Yard and Positioned in work area, Final Prep Work Thursday Final Prep Work Friday Weekend Saturday Weekend Sunday Final Prep Work Monday Tuesday Final Prep Work and Erection Process Spools are pulled from Yard and Positioned in work area, Final Prep Work Wednesday Final Prep Work Thursday Friday Final Prep Work Weekend Saturday Weekend Sunday Final Prep Work and Erection Process Monday Spools are pulled from Yard and Positioned in work area, Final Prep Work Tuesday Wednesday Final Prep Work Final Prep Work Thursday Final Prep Work and Erection Process Friday Weekend Saturday Weekend Sunday Spools are pulled from Yard and Positioned in work area, Final Prep Work Monday Final Prep Work Tuesday Final Prep Work Wednesday Thursday Final Prep Work and Erection Process Final Prep Work and Erection Process Friday Hours Cumulative Cumulative Workable Cumulative VA NVAR NVA VA Cumulative NVAR Cumulative NVA Cumulative Crew Workable Calendar Cumulative Calendar worked Workable Calendar Hours Work Hours Percentage Percentage Percentage Hours VA Hours Hours NVAR Hrs. Hours NVA Hrs available Days Days Calendat Days Hours per day days Hours 1 1 16 16 1 1 2 8 16 16 0% 20% 80% 0 0 3.2 3.2 12.8 12.8 1 2 16 32 1 2 2 8 16 32 0% 20% 80% 0 0 3.2 6.4 12.8 25.6 1 3 16 48 1 3 2 8 16 48 0% 0% 100% 0 0 0 6.4 16 41.6 1 4 24 72 1 4 3 8 24 72 8% 19% 73% 1.92 1.92 4.56 10.96 17.52 59.12 1 5 24 96 1 5 3 8 24 96 8% 19% 73% 1.92 3.84 4.56 15.52 17.52 76.64 1 6 24 120 0 5 3 0 0 96 8% 19% 73% 0 3.84 0 15.52 0 76.64 1 7 24 144 0 5 3 0 0 96 8% 19% 73% 0 3.84 0 15.52 0 76.64 1 8 40 184 1 6 5 8 40 136 8% 19% 73% 3.2 7.04 7.6 23.12 29.2 105.84 1 9 40 224 1 7 5 8 40 176 8% 19% 73% 3.2 10.24 7.6 30.72 29.2 135.04 1 10 24 248 1 8 3 8 24 200 8% 19% 73% 1.92 12.16 4.56 35.28 17.52 152.56 1 11 24 272 1 9 3 8 24 224 8% 19% 73% 1.92 14.08 4.56 39.84 17.52 170.08 1 12 40 312 1 10 5 8 40 264 8% 19% 73% 3.2 17.28 7.6 47.44 29.2 199.28 1 13 40 352 0 10 5 0 0 264 8% 19% 73% 0 17.28 0 47.44 0 199.28 1 14 40 392 0 10 5 0 0 264 8% 19% 73% 0 17.28 0 47.44 0 199.28 1 15 40 432 1 11 5 8 40 304 8% 19% 73% 3.2 20.48 7.6 55.04 29.2 228.48 1 16 24 456 1 12 3 8 24 328 8% 19% 73% 1.92 22.4 4.56 59.6 17.52 246 1 17 24 480 1 13 3 8 24 352 8% 19% 73% 1.92 24.32 4.56 64.16 17.52 263.52 1 18 40 520 1 14 5 8 40 392 8% 19% 73% 3.2 27.52 7.6 71.76 29.2 292.72 1 19 40 560 1 15 5 8 40 432 8% 19% 73% 3.2 30.72 7.6 79.36 29.2 321.92 1 20 40 600 0 15 5 0 0 432 8% 19% 73% 0 30.72 0 79.36 0 321.92 1 21 40 640 0 15 5 0 0 432 8% 19% 73% 0 30.72 0 79.36 0 321.92 1 22 40 680 1 16 5 8 40 472 8% 19% 73% 3.2 33.92 7.6 86.96 29.2 351.12 1 23 40 720 1 17 5 8 40 512 8% 19% 73% 3.2 37.12 7.6 94.56 29.2 380.32 1 24 40 760 1 18 5 8 40 552 8% 19% 73% 3.2 40.32 7.6 102.16 29.2 409.52 1 25 40 800 1 19 5 8 40 592 8% 19% 73% 3.2 43.52 7.6 109.76 29.2 438.72 1 26 24 824 1 20 3 8 24 616 8% 19% 73% 1.92 45.44 4.56 114.32 17.52 456.24 1 27 40 864 0 20 5 0 0 616 8% 19% 73% 0 45.44 0 114.32 0 456.24 1 28 40 904 0 20 5 0 0 616 8% 19% 73% 0 45.44 0 114.32 0 456.24 1 29 24 928 1 21 3 8 24 640 8% 19% 73% 1.92 47.36 4.56 118.88 17.52 473.76 1 30 40 968 1 22 5 8 40 680 8% 19% 73% 3.2 50.56 7.6 126.48 29.2 502.96 1 31 40 1008 1 23 5 8 40 720 8% 19% 73% 3.2 53.76 7.6 134.08 29.2 532.16 1 32 24 1032 1 24 3 8 24 744 8% 19% 73% 1.92 55.68 4.56 138.64 17.52 549.68 1 33 24 1056 1 25 3 8 24 768 8% 19% 73% 1.92 57.6 4.56 143.2 17.52 567.2 1 34 40 1096 0 25 5 0 0 768 8% 19% 73% 0 57.6 0 143.2 0 567.2 1 35 40 1136 0 25 5 0 0 768 8% 19% 73% 0 57.6 0 143.2 0 567.2 1 36 40 1176 1 26 5 8 40 808 8% 19% 73% 3.2 60.8 7.6 150.8 29.2 596.4 1 37 40 1216 1 27 5 8 40 848 8% 19% 73% 3.2 64 7.6 158.4 29.2 625.6 1 38 24 1240 1 28 3 8 24 872 8% 19% 73% 1.92 65.92 4.56 162.96 17.52 643.12 1 39 24 1264 1 29 3 8 24 896 8% 19% 73% 1.92 67.84 4.56 167.52 17.52 660.64 1 40 40 1304 1 30 5 8 40 936 8% 19% 73% 3.2 71.04 7.6 175.12 29.2 689.84 1 41 40 1344 0 30 5 0 0 936 8% 19% 73% 0 71.04 0 175.12 0 689.84 1 42 40 1384 0 30 5 0 0 936 8% 19% 73% 0 71.04 0 175.12 0 689.84 1 43 40 1424 1 31 5 8 40 976 8% 19% 73% 3.2 74.24 7.6 182.72 29.2 719.04 1 44 24 1448 1 32 3 8 24 1000 8% 19% 73% 1.92 76.16 4.56 187.28 17.52 736.56 1 45 24 1472 1 33 3 8 24 1024 8% 19% 73% 1.92 78.08 4.56 191.84 17.52 754.08 1 46 40 1512 1 34 5 8 40 1064 8% 19% 73% 3.2 81.28 7.6 199.44 29.2 783.28 1 47 40 1552 1 35 5 8 40 1104 8% 19% 73% 3.2 84.48 7.6 207.04 29.2 812.48 273 Appendix F Case Study No. 6 - Process Piping 1.0 Overview This case study took place at a large manufacturing facility. Several large structures were being erected in various locations onsite, and the study focused on the largest of these structures. Unfortunately, during the observation period, several factors prevented observation of any value adding (VA) activities. Thus, this study became a “lessons learned” case study whose purpose was to highlight areas that, from the perspective of the observation team, were not lean. 1.1 Project Logistics The site included roughly 1,700 acres plus an additional 300 acres reserved for future development. Several buildings would eventually occupy the site. The case study focused on piping installation in the largest of these buildings, an approximately one million square foot structure. Work was observed in two different locations in the building. 1.2 Work Observed The observation period took place over two consecutive days. It focused on the installation of Victalic piping components. Victalic pipe sections were manufactured offsite and offered the advantage of faster installation using couplings and gaskets for each connection point rather than requiring welding. Approximately 30 crewmen were identified in the installation crews. These crewmen were divided into multiple subcrews. Each crew was observed transporting piping components from the ground to the rafters and temporarily storing the components there until trapezoidal hangers were erected to support the pipe in final position. During the observation period, no VA actions were evident (i.e., no hangers were erected, nor were any spools coupled). In fact, the majority of the time during the observation period was spent on waiting and transportation waste. Rather than exclude this case study from the report, areas are identified, at both the crew level and at higher levels that caused the non-value adding (NVA) actions to occur. 2.0 Non-Lean Activities This section identifies areas of non-lean conformance including complications due to the following: material organization and delivery, nondefined work processes, conflicts resulting from upstream processes such as incomplete slabs, and unfamiliarity with new piping material. The material for the observed work was purchased and handled by the subcontractor. This included all Victalic spools, couplings, gaskets and trapezoidal hangers. The larger equipment, such as pumps, air handling units and fans, was purchased by the owner of the facility. For the work observed, only the spools, couplings, gaskets and trapezoidal hangers were required. The material that was onsite during the observation period was stored in two lay-down areas. The first area was located on the north side of the facility, roughly 800 yards away from the work area. This lay-down area served as the first staging area for material delivered from the manufacturing facility. The second lay-down area was located in the facility. The bundles of 274 “like” spool diameters were positioned inside the facility at this point. The spools were pulled from their respective bundles to a staging area on the ground. Different spool sizes were required in each bay section of the building. The third staging position allowed each required spool diameter, for each bay section, to be organized and moved at one time to the final staging position below the rafters. From this final staging position, the spools wre lifted one at a time onto the rafters (roof trusses). The trapezoidal hangers were not in position at this time. Each spool was secured above its final position using cables until it could be lowered on top of the trapezoidal hangers. The missing hangers highlighted an area of non-lean conformance, i.e., the lack of available materials. Several spools were temporarily positioned in the trusses even before the observation period began. This material represented overproduction waste, which is a component of work in progress (WIP). The cause of this particular WIP was a shortage of couplings and gaskets that were required to connect each spool. Because these components were not ordered at the same time as the spools, the assembly of each section was delayed. Another area of non-lean conformance was the multiple handling of material. Roughly seven touches were required for each spool section installed in the facility. Ideally, the piping components would be delivered from the manufacturing facility to their final position in the rafters. This excess material handling increased the transportation waste associated with NVA actions. A gas pipe spool section was observed being hoisted into the trusses and then lowered back to the ground. Further investigation revealed that the spool was the wrong diameter for that section of the pipeline, thus requiring it to be removed. Lean philosophy recommends incorporating “error proof” processes whenever possible. This can be accomplished, for example, by labeling each pipe component with a bar code, directional arrows and spool diameter. The result of lifting the gas spool up and then down again was wasted movement, wasted transportation, extra processing and waiting. Five crewmen were involved with the process. There was no well-defined work process for the construction activity. At one point during the observation period, a majority of the crewmen were working in one location. Work was then stopped in that area of the building, and the workers were shifted to another location. This “jumping around” was an example of the material value stream not “flowing” as it should. The non-ideal work flow for installing spools was a result of management requiring one area of the building to be finished one week, then shifting the focus to another area of the building the following week before the first area was completed. The critical completion items never stayed the same. Lean philosophy recommends starting an activity at its latest possible point. This limits extra processing waste (another component of WIP) and also allows an activity to be completely finished so that follow-up crews may begin their scheduled tasks. It was observed that work at the crew level was restricted by activities occurring upstream. Specifically, the final pour for the concrete slab occurred in the center of the building. This prevented the pipe installation crew from erecting and installing piping components in a linear fashion. Instead, the crews installed erected spools in one location until they reached the incomplete section. Then they started in another location, until once again reaching the incomplete portion. The piping foreman notified the observation team that coupling and bolting could not begin until the slab was completed because of two 90 degree turns occurring over the unfinished concrete slab. 275 Another non-lean area of the case study dealt with training. Several members of the crew were not educated on the capabilities of Victalic pipe. Many crew members did not think highly of the material because it did not require them to weld connections, as they had on previous jobs. Lean philosophy recommends that each worker to be trained and educated in applicable work practices. Several of the crewmen were not trained in the installation of Victalic pipe resulting in a trial and error learning atmosphere on the job. 3.0 Concluding Remarks The main lesson to learn from this case study is that a lack of planning and communication at the management level affects the crews’ ability to produce VA actions. In summary, multiple work crews were observed over a period of two days, and no VA actions were identified. For the most part, all of the workers were reasonably busy and to a casual observer, the productivity of the subcontractor would have appeared adequate. 276 Appendix G Lean Questionnaire and Principle Cross-Reference This appendix contains the final version of the questionnaire. This questionnaire forms the basis for the Lean Assessment Tool created by the PT 191 Team. In addition to the questionnaire, this appendix contains a table that cross-references the individual questions with the lean principle that is being assessed. Customer Focus Meeting the Requirements of the Customer Project objectives and 1 customer requirements are not usually discussed with all parties involved. 2 3 4 5 6 7 N/A Project objectives and the customer's requirements are known by all parties involved. 1 2 3 4 5 6 7 N/A Value added is defined in terms of the entire project by all the participants. 3 The project is made up of 1 individuals who focus on their own needs and own goals. 2 3 4 5 6 7 N/A Teams are formed to develop strategies to accomplish project goals. 4 Refocusing and reorganizing to 1 meet changing customer requirements is a large burden for the contractor to bear. 2 3 4 5 6 7 N/A Contractor is often able to refocus and reorganize to meet changing customer requirements. 5 Project participants are often 1 inflexible due to high costs for added changes. 2 3 4 5 6 7 N/A Project participants are flexible in meeting situations with the required materials, tools, labor, etc. 2 3 4 5 6 7 N/A Crew members are able to perform multiple tasks. 1 Define Value from the Viewpoint of the Customer 2 Value added for the project is defined individually by each respective project participant. Use Flexible Resources and Adaptive Planning Cross Train Crew Members to Provide Production Flexibility 6 Crew members are encouraged 1 to stick to one specific task. Use Target Costing and Value Engineering 277 7 The project is built precisely according to plans. 1 2 3 4 5 6 7 N/A The Contractor discusses ways to modify the plans to reduce costs while trying to maintain quality. Culture/People Training 8 Employees are expected to possess the required skills to perform their job. 1 2 3 4 5 6 7 N/A Employees use a learning plan to guide their development process. 9 Contractor likes training to be 1 performed on employee's personal time. 2 3 4 5 6 7 N/A Management encourages development and training even on company time. 1 10 Contractor participates in training solely as a participant. 2 3 4 5 6 7 N/A Contractor presents training sessions to help employees, suppliers, and customers. Employee Empowerment 11 Employees feel that it takes a great deal of effort to have their supervisors hear what they have to say. 1 2 3 4 5 6 7 N/A Employees feel that their ideas matter to the project team. 12 Employees are focused on completing their personal tasks. 1 2 3 4 5 6 7 N/A Employees coordinate their work with others to complete the whole task. 1 2 3 4 5 6 7 N/A Top management feels the need to change the company's culture to improve organizational effectiveness. 14 The company does not need to 1 work outside their own organization to improve project effectiveness. 2 3 4 5 6 7 N/A The company works with suppliers, subs, and owners to improve project effectiveness. Management Commitment 13 Top management is satisfied with the status quo. Work with Subcontractors and Suppliers Workplace Organization/ Standardization Encourage Workplace Organization and Use 5S's 278 15 Materials and tools are located 1 about the jobsite where they were last used or where workers think they are most convenient. 2 3 4 5 6 7 N/A Workstations are organized with materials and tools in their designated places. 16 The workplace can be unkempt 1 and disorganized. 2 3 4 5 6 7 N/A The workplace follows the principles of Sort, Straighten, Sweep, Standardize, Systematize. 1 2 3 4 5 6 7 N/A An in-process inspection plan is in place to prevent rework. 18 Materials arrive on-site without 1 directional marks or any specific assembly instructions, and require communications with the supplier, engineer, or fabricator to assemble. 2 3 4 5 6 7 N/A Methods for site assembly show piece marks or other methods to assure a "one way only fit" such as color coding, numbering, etc. 19 Posting information regarding 1 schedule, quality, safety, productivity for the current job is not of great importance. 2 3 4 5 6 7 N/A The jobsite has visual aids that show the job status on schedule, quality, safety, and productivity. 20 The posted information is not 1 in a place that all the workers can see on a daily basis, and it is not up-to-date. 2 3 4 5 6 7 N/A The posted information is in places that most workers can see it on a daily basis, and it is upto-date. 2 3 4 5 6 7 N/A Work processes are documented and available to the project team. 22 The jobsite's plan for flow of 1 materials and supplies is conceived at the point of need. 2 3 4 5 6 7 N/A Jobsite has a logistics plan defining access, deliveries, movement and work progression. 23 Workers collect materials, tools, instructions/ specifications from locations away from work site. 2 3 4 5 6 7 N/A Tools, materials, instructions/ specifications are collected at the work site. Error Proofing Devices 17 There is no inspection plan in place to prevent rework. Visual Management Create Defined Work Processes 1 21 Work processes are not documented or communicated to the project team. Create Logistic, Material Movement, and Storage Plans 1 279 24 There is no posted site laydown 1 plan/drawing for storage of equipment/materials. 2 3 4 5 6 7 N/A There is a posted site laydown plan/drawing for storage of equipment/materials. 2 3 4 5 6 7 2 3 4 5 6 7 N/A Work activities are planned to minimize the movement of people, materials, and equipment. N/A Material/equipment is delivered from supplier to point of use. 1 2 3 4 5 6 7 N/A Crew sizes are usually balanced and members are working nonstop. 28 Crew stacking or over-manning 1 is often used to maintain schedule. 2 3 4 5 6 7 N/A Crews are usually sequenced with regard for the schedule. 2 3 4 5 6 7 N/A Materials and information are prepared before releasing a work task to a crew. 2 3 4 5 6 7 N/A The crew has the ability to switch from one task to another to minimize downtime. 1 2 3 4 5 6 7 N/A Materials are ordered as close as possible to exact needs. 32 Unused materials and supplies 1 are put aside and returned to the supplier at the end of the job or thrown out. 2 3 4 5 6 7 N/A There is a system that measures the amount of unnecessary or unused supplies that are ordered. Eliminate Waste Part I: Process Optimization Minimize Double Handling and Worker and Equipment Movement 1 25 Work activities are planned without regard for movement of people, materials, and equipment. 26 Large material/large equipment 1 is stored in separate laydown/storage areas or in areas away from the jobsite. Balance Crews, Synchronize Flows 27 Crew members may have idle or free time on the job. Remove Material Constraints, Use Kitting, Reduce Input Variation 1 29 Crews are individually responsible for gathering the tools and information for their work task. Reduce Difficult Setup/Changeovers 30 Large batches of materials are 1 produced before changing to the next task to avoid downtime. Reduce Scrap 31 Extra materials are ordered to ensure that there is always enough. 280 Use TPM (Total Productive Maintenance) 33 The upkeep of production machinery and jobsite tools occurs as needs arise. 1 2 3 4 5 6 7 N/A The upkeep of production machinery and jobsite tools is scheduled for workers with down-time or off-shift time. 1 2 3 4 5 6 7 N/A Bulk materials are delivered just prior to installation. 1 2 3 4 5 6 7 N/A Crew is given specific instruction as to overall job requirements. 1 2 3 4 5 6 7 N/A Work assignments are complete in accordance with a production schedule. 37 Work activity is started as early 1 as possible. 2 3 4 5 6 7 N/A Work is started to the latest possible start date that still supports the schedule. 38 Completed work products are 1 made available to the next crew in large batches or when all items are completed. 2 3 4 5 6 7 N/A Completed work products are made available to the next crew in a continuous stream or in small batches. 39 Job is not complete before passing on to next crew or subcontractors. 2 3 4 5 6 7 N/A Job is completed before passing on to next crew and subcontractors. Part II: Production Scheduling JIT Delivery 34 Bulk materials are stored onsite. Production Planning and Detailed Crew Instructions 35 Crew is not aware of the overall job requirements. Last Planner, Reliable Production Scheduling, Short-Interval Schedules 36 Work assignments are not completed per original schedule. Pull Scheduling, The Last Responsible Moment Use Small Batch Sizes, Minimize WIP 1 281 Use Decoupling Linkages, Understand Buffer Size and Location 1 40 Schedules, material, or equipment buffers are incorporated into daily practice to accommodate unforeseen circumstances. 2 3 4 5 6 7 N/A Material, equipment, and resources are provided precisely when needed. 1 41 Non-standard materials, dimensions, and specifications are used for ease in configuring the design. Use Pre-Assembly and PreFabrication 2 3 4 5 6 7 N/A Design uses readily available materials, and emphasizes repetitive tasks. 42 Jobs are on site labor intensive. 1 Little use of off site shops, or jobsite pre-fabrication or modularization. 2 3 4 5 6 7 N/A Materials are assembled in off site shops or are pre-fabricated on jobsite, and delivered to work area. 1 2 3 4 5 6 7 N/A Design is made with the material cost and the field installation cost in mind. 44 Project designs/constructability 1 reviews are not used or needed by the contractor before construction starts. 2 3 4 5 6 7 N/A The contractor has verified that the design is ready for construction. 45 Lessons learned in the field are 1 not documented. 2 3 4 5 6 7 N/A Lessons learned in the field are documented, and passed on to others. 46 A written procedure is not in place for dealing with problems discovered in the field. 2 3 4 5 6 7 N/A A written procedure is in place for dealing with problems discovered in the field. Part III: Product Optimization Use Standard Parts, Reduce the Parts Count Use Pre-Production Engineering and Constructability Analysis 43 Design is conceived without consideration for the field labor. Continuous Improvement/BuiltIn-Quality Prepare for Organizational Learning and Root Cause Analysis 1 282 Develop and Use Metrics to Measure Performance, Use Stretch Targets 47 There is not a system in place 1 that tracks Works-In-Progress, or where unfinished parts are placed. 2 3 4 5 6 7 N/A Works-In-Progress are monitored throughout the job. 48 Quality is not monitored. 1 2 3 4 5 6 7 N/A Quality is monitored. 49 Productivity is not monitored to planned requirements. 1 2 3 4 5 6 7 N/A Productivity is monitored against the plan and shared with the crew. 50 When defects are discovered, 1 the project crew(s) are allowed to shut down or pass the defect on to another sub to fix. 2 3 4 5 6 7 N/A A plan exists that says what to do when a defect is discovered. 1 51 A Suggestions for Improvement program does not exist at the jobsite level. 2 3 4 5 6 7 N/A A Suggestions for Improvement program exists at the jobsite level. 52 Employees feel that a defect is 1 someone else's responsibility. 2 3 4 5 6 7 N/A Employees feel the duty to report defects. Create a Standard Response to Defects Create in Employees a Sense of Responsibility for Quality 283 Lean Principle/Questionnaire Cross-Reference Principle Customer Focus Meeting the requirements of the customer Value is defined from the point of view of the customer, not from the point of view of individual participants Flexible resources and adaptive planning Cross trained crew members Target Costs/Value Engineering Culture/People Training Employee Empowerment Management Commitment Work with subcontractors and suppliers to regularize processes and supply chains Workplace Organization and Standardization 5s Poke-yoke devices Visual management Defined work processes Logistic/material movement plan Eliminate Waste JIT Minimize double handling, minimize movement Kitting, removing material constraints, reducing input variations Balance crews, synchronized flows Production planning, detailed crew instructions Last planner/reliable production scheduling/short interval production scheduling Last responsible moment/pull scheduling Predictable task times Minimize WIP, Small batch sizes Reduce parts count, Use standardized parts. Production optimized by pre-assembly/pre-fabrication Pre-production engineering/constructability Reduce difficult set up/changeovers Decoupling linkages, buffer size/location Reduce Scrap Total Productive Maintenance Continuous Improvement/Built-in Quality Organizational learning/root cause analysis, Suggestion program Metrics for Material, Labor, Equipment, WIP, Quality, Financial, Productivity, and Rework Defect response plan Employee responsibility for correcting defects 284 Question Number(s) 1 2 3, 4, 5 6 7 8, 9, 10 11, 12 13 14 15, 16 17, 18 19, 20 21 22, 23, 24 34 25, 26 29 27, 28 35 36 37 27, 28 38, 39 41 42 43, 44 30 40 31, 32 33 45, 46 47, 48, 49 50 51, 52 Appendix H Interview Notes This appendix contains a summary of the interview notes that were created during and after the site visit for each case study project. The interviews used the lean questionnaire as a guide to discover lean practices used on the project. Also, this appendix contains the interview notes from our meetings with lean construction early adopters. In some cases, the notes cover projects/companies that are both case study projects and lean early adopters. In this case, the interview notes are presented with the case study interview notes. Case Study #1 and Early Adopter #1 – Structural Steel Customer Focus Optimize Value • They are in constant contact with the customer regarding their needs and requirements. • Their practice consists of trying to “look through the customer’s eyes” to understand how to meet their needs in a better manner. Flexible Resources • They make their schedule based on the customer’s requirements, meaning they’ll fast track it if cost is not an issue, but time is. And vice-versa if time is not an issue, but cost is the underlying element. • Resources are moved or the schedule of erection is changed if the customer needs to use a certain area, or wants a certain part completed. Culture/People Training • No lean behaviors. People Involvement • They try to involve as many people as possible in the schedule. • Daily startup sessions/meetings are held everyday at the jobsite and at the corporate office (kaizen). Organizational Commitment • Personal performance evaluations are conducted at the end of every project. 285 • Each engineer (structural, material coordinator, technicians) needs to come up with at least one cost-saving idea for every project they work on. The goal of this is to force people to “think outside the box.” Workplace Standardization Workplace Organization • All laydown areas are pre-planned prior to construction beginning. • They try to promote the idea of “put it away if not using it.” Visual Management • Safety signs are posted all over the site. • Productivity charts are posted in the trailer. • Schedule is posted in the trailer. Defined Work Processes • They post a flow chart for access/egress for suppliers to gain access to the site. Eliminate Waste Optimize Work Content • No lean behavior. Optimize Production System • Crew size is optimized to remove inefficient or unnecessary workers. Supply Chain Management • Try to implement JIT as much as possible, but have difficulty due to normal outside barriers that come about in the construction industry. Optimize Production Scheduling • On a daily basis, they look at the schedule and evaluate if the resources are adequate or being used efficiently. Continuous Improvement/Built-In Quality Organizational Learning • They use a post-job audit to evaluate how they performed on the last project, and then they classify it as a job specific issue or something that can go into a Lessons Learned type file. 286 Metrics • They measure productivity off of their schedule. • They measure how they performed versus cost. Error Proofing − There are one-way only markings on the steel. − They provide tension control bolts so that the ironworkers always apply the correct torque to the bolts. Response to Defects • No real lean behavior. Case Study #2 – Structural Steel Data Unavailable Case Study #3 and Early Adopter #1 – Structural Steel Customer Focus Optimize Value • They conduct formal design review sessions with the owner during the preconstruction phase of the job. • These design reviews are combined with milestone identifications and explanations of milestones for the owner. Flexible Resources • No specific lean practices. Culture/People Training • Training is done on company time. It includes training on lean behavior, and driving out waste from current practices. They also train their employees to focus on continuous improvement. People Involvement • This company created a tool or system called LDMS, which stands for Lean Daily Management System. This is a vehicle that allows all the participants (subs, crews, Project Management, owner) to bring their ideas to the job. 287 Organizational Commitment • This company has a system called Supply Chain Integration, which they bring/show to their suppliers and explain their processes to the supplier. Workplace Standardization Workplace Organization • They have a posted site laydown in their trailer. Visual Management • Productivity reports are distributed to General Foreman and posted in the trailer. • Signs are posted in work area concerning safety (hardhats, safety glasses). Defined Work Processes • These are included in their visual management. Eliminate Waste Optimize Work Content • They prefab as much as possible. The Designer, in their case the structural engineer meets with the field labor to discuss Constructability. This is a new phenomenon used since the engineer visited a couple of sites previously and realized this was a necessary function. Optimize Production System • No specific lean practices or behaviors. Supply Chain Management • No specific lean behaviors. Optimize Production Scheduling • They make an effort to pass things on in small batches or continuous streams. This is not always met, but the effort is there. Continuous Improvement/Built-In Quality Organizational Learning • Have a lessons learned file, but not used often due to dissimilar projects. • Written procedures are placed in the lessons learned file. 288 • There is a Suggestions for Improvement box. • They monitor quality and productivity. Metrics Error Proofing • They make sure their steel is delivered with a “one-way only fit.” Response to Defects • They have written plans of what to do when a defect occurs. Forms must be submitted when there is a defect, and these are also placed in their lessons learned file. Case Study #4 – Piping Customer Focus Optimize Value • They advocate their General Foremen and Foremen to meet with the Owner’s operators to understand their specific needs for the site. • They are flexible with the Owner’s request to meet them on site to discuss any needs or requirements by the Owner. Flexible Resources • They are flexible with their labor workforce since their location is near the largest local pipe fitter union in the country. Culture/People Training • Training under a person that has already done one’s job is required in the project management level, meaning there is a specific ladder to climb to finally be able to run a job. People Involvement • This company creates milestones for its workers to strive for, in the purpose of promoting employee empowerment. Organizational Commitment • The company is committed to improvement by using employee teams to further research and find more cost effective ways to construct and do business. Workplace Standardization 289 Workplace Organization • They have a standard tool trailer with labeled bins for all the tools. • They place their laydown area where the owner designates. Visual Management • Productivity reports are distributed to General Foreman and posted in the trailer. • Signs are posted in work area concerning safety (hardhats, safety glasses). Defined Work Processes • They use a material coordinator to help with the flow of their jobsite. Eliminate Waste Optimize Work Content • No lean behaviors. Optimize Production System • They go to great detail to plan activities that will result in the least amount of movement. Supply Chain Management • No lean behaviors. Optimize Production Scheduling • No lean behaviors. Continuous Improvement/Built-In Quality Organizational Learning • Have a lessons learned file, but not used often due to dissimilar projects. • They monitor quality as often as they can. Metrics Error Proofing • Use chalk/markers to label ends of pipes. Response to Defects 290 • They have a Quality Assurance person flag the ISO, a decision will be made if work can continue or if repairs need to be done before moving on. Case Study #5 – Piping Data not available. Case Study #6 – Piping Customer Focus Optimize Value • No specific lean practices or behaviors. Flexible Resources • No specific lean practices or behaviors. Culture/People Training • Routine training occurs. They focus on crisis management in training sessions. That is not a lean behavior; it is a reactionary behavior as opposed to proactive behavior, which would be lean. People Involvement • They encourage feedback from the field labor. Organizational Commitment • The company is not satisfied with current practices, and looking to improve. That is necessary in lean thinking (continually eliminate the waste). Workplace Standardization Workplace Organization • No specific lean practices or behaviors. Visual Management • Visual tools are solely in the trailer. Defined Work Processes • They have a formal contract work process. ISO 9000 related. This work process is in electronic form. 291 • They conduct weekly meetings to discuss access, logistics. Eliminate Waste Optimize Production System • No specific lean practices or behaviors. Optimize Work Content • No specific lean practices or behaviors. Supply Chain Management • They are practicing JIT, but it is due to conditions and not planning. They are doing JIT by default on this job. Optimize Production Scheduling • They make an effort to pass things on in small batches or continuous streams. This is not always met, but the effort is there. Continuous Improvement/Built-In Quality Organizational Learning • They have a Value Awareness Report. Lessons Learned are included in this file. • QA/QC is monitored daily in accordance to the specifications. Metrics Error Proofing • No specific lean practices or behaviors. Response to Defects • No specific lean practices or behaviors. Early Adopter #2 – General Contractor – Commercial Buildings Customer Focus Optimize Value • They use target costing to communicate with the customer. • Value Engineering is implemented to give the customer function analysis. This shows them pricing and costs if they want certain things. 292 Flexible Resources • No specific lean practices. Culture/People Training • There is a “Boldt University” that mandates courses on three different levels of lean training. Over 200 Boldt employees have been trained on lean theory, and how to use their Last Planner model. People Involvement • The Last Planner system that Boldt emphasizes inherently creates employee empowerment. It forces each participant to explain the work they are doing, when it will be completed, and also allows them to make suggestions. • Crews have daily meetings as well to keep them involved. Organizational Commitment • Every year 7-8 strategic goals are stated by the company. At least one of these goals is focused on innovation and using Lean Construction Initiatives to improve processes. Workplace Standardization Workplace Organization • No specific lean behaviors. Looking to implement the 5 S’s next year. Visual Management • Production information is distributed to all participants at each weekly Last Planner meeting. This information includes the detailed plan for the next week along with plan reliability measurements from the previous week and the whole job. This allows everyone to see status on schedule and productivity. Defined Work Processes • No specific lean practices or behaviors. Eliminate Waste Optimize Production System • They use the combination of CPM and Last Planner to balance their work flow and crew flow. • They track manpower hours to figure out optimal sequencing. 293 Optimize Work Content • No specific lean practices or behaviors. Supply Chain Management • No specific lean practices or behaviors. Want to implement more JIT principles in the near future. Optimize Production Scheduling • Again using the Last Planner system to hand-off products in small batches or in a continuous stream. They have focused real hard in the last 4 years on the handoff principle. Their goal is to better manage the actual hand-off of work between activities as opposed to managing the activity itself. Continuous Improvement/Built-In Quality Organizational Learning • Boldt implemented an OFI program 12 years ago. Opportunities For Improvement are suggestions employees make to improve processes. Last year 250-300 OFIs were documented. The employees earn “Boldt bucks” for submitting an OFI and even more Boldt bucks if the ideas are implemented. • They also have a Lessons Learned File that can be accessed through their intranet. • They measure productivity. • They are intent on having quality measurements decentralized all the way down to the lowest level of the organization. This is the theory that each worker should check his/her own work and make sure it is of good quality before passing it on. Metrics Error Proofing • No specific lean practices or behaviors. Response to Defects • No specific lean practices or behaviors. 294 Early Adopter #3 – Mechanical Design/Build Customer Focus Optimize Value • Have implemented Design-Build and Design-Assist Delivery systems where they have a full understanding of customer’s needs from the inception of the project. • Make employees fill out a Planning Checklist for each project where questions are asked to see if the employees know the client’s goals and what business the clients are in. Flexible Resources • Makes sure project teams have clear lines of communication to help if changes need to be made on the project, especially if made by the client. Culture/People Training • The company has its own Internet system that is used as a tool in many regards. There are numerous training sessions on the system. • Foremen are trained once a month as well as whenever there is something they need to be trained in. People Involvement • Employees are rewarded as a team when a project goes well, and not by individual trades. This forces them to think as a team. • Cross-functional teams are formed to keep coordination between trades. Organizational Commitment • Organization is very committed to continual improvement. Empowerment of employees is driven from the top down with encouragement from above to find more effective processes. • Company asks suppliers to find more effective practices, which is complied with since same suppliers are on 95 percent of their projects. Workplace Standardization Workplace Organization • Boxes are created for each crewman with everything they would need for that day. 295 Visual Management • There is a visual for the material handling process. • There is a visual of the productivity analysis. • Safety is measured and reported every month. • All of their work processes are in some form of visual aid. Defined Work Processes • There internal system prints out visual reports that define all work processes. • They have checklists that each employee must follow which include what their task is, how it should be done, what tools and materials are needed, and the possible safety hazards and how to prevent them. Eliminate Waste Optimize Work Content • Effort is put in the design phase to standardize their materials, joints. Optimize Production System • Lessons Learned file is used to see how to optimize current project. • Checklist is used to see how current project is similar to a previous project. Supply Chain Management • No specific lean behaviors. Optimize Production Scheduling • They make an effort to pass things on in small batches or continuous streams. Continuous Improvement/Built-In Quality Organizational Learning • Lessons Learned files are made at the close-out of every project. • They have OFIs (Opportunities For Improvement) that they encourage employees to fill out. • Meetings are held to talk about innovative ideas to improve processes for the future. 296 Metrics • They monitor quality and productivity. • They measure the amount of unused supplies and materials for each job. This is done with the help of one of their suppliers. Suppliers are in accordance with this program since they are usually the same for each job. Error Proofing • They color-code their fire sleeves to clarify between supply lines and return lines. Response to Defects • Field empowerment is encouraged to raise the flag and deal with the defect at hand. Early Adopter #4 – General Contractor Industrial Buildings Customer Focus Optimize Value • Company supplies JIT training to its A/E so they can understand lean and its communication tools for the owner. • Program called VAVE (Value Added Value Engineering) is used to help communicate the owner’s needs and goals on every level. Flexible Resources • Two week look-ahead planning is used with subcontractors to combat problems early on. Culture/People Training • Mandatory 8 hour lean training sessions for all employees. • Lean “best practices” mandatory for every project. • Average of 40 hours training/employee/year. People Involvement • Use CIM (continuous improvement message) to keep employees thinking and involved. Also use OFIs (Opportunities for Improvement) cards, which are along the same lines as CIM. 297 Organizational Commitment • Organization is very committed to continual improvement. • Training and conversations always occur with Subs regarding lean practices. Workplace Standardization Workplace Organization • 5s is used on all jobsites for cleanliness and organization. Visual Management • Everything that is tracked is posted. One of the only companies visited that posted numerous visual aids at the workplace. • Visual aids are updated weekly. Defined Work Processes • A jobsite logistics plan is used that defines workflow, access, etc. This is a visual aid as well. Eliminate Waste Optimize Work Content • Pre-Fabrication is used whenever possible. • Architects and Engineers are trained in Just-In-Time concepts. This teaches them about the benefits of using standardized materials for repetitive tasks. Optimize Production System • A four-week look ahead to plan subs movement is used. • They coordinate weekly sub-contractors meetings. Supply Chain Management • Have trained approximately 160 suppliers and sub-contractors about lean behaviors and principles. Optimize Production Scheduling • The four-week look ahead planning is used here to support smooth flow from sub to sub. 298 Continuous Improvement/Built-In Quality Organizational Learning • They keep three lessons learned files. One for lean behaviors, one for activities, and one with the CIMs. • They monitor quality and productivity. Metrics Error Proofing • No specific lean behaviors. Response to Defects • Employees and subs are encouraged and empowered to report defects, especially with matters concerning safety. 299 Appendix I Worker Movement Study No. 1 1.0 Worker Movement Analysis 1.1 Background In the manufacturing world, where the lean idea was first developed, intercell flow has been extensively analyzed to optimize factory layout, work space sequence and equipment selection and to improve overall productivity. An efficient flow of workers, materials and information among various cells or workstations is one of most important requisites for overall productivity improvement. However, the construction industry has not readily adopted this flow analysis concept because of the difficulties of applying the analysis to the construction process. The following are some characteristics that hamper the construction industry from adopting movement (flow) analysis: • Single unique project rather than multiple products. • Different environment for each jobsite. • Dynamic workstation; locations change as work progresses. • Three-dimensional oriented workstation locations, which are difficult to analyze. Despite the difficulties of conducting movement (flow) analysis in construction, the need for such information continues. Although this analysis does not apply to all construction processes, it serves as an experimental attempt at movement analysis of the steel erection process. 1.2 Scope and Goal Essentially all movements - either worker or material - are considered to be non-value adding (NVA) activities. However, some movements are non-value adding but required (NVAR). NVAR movements are unavoidable; therefore, to promote more efficient or “leaner” construction, NVA movement has to be minimized. This study has the following three main goals: • To develop an appropriate scheme for the evaluation of flow efficiency. • To evaluate the process and measure the degree of leanness. • To analyze causes of NVA movements and suggest solutions. Due to the complexity of the construction process mentioned earlier, this analysis has a few scope limitations, which are described in the following subsections. 1.2.1 Only Worker Movements Were Analyzed This study evaluated the movement of workers in the Noland Project steel erection process. As mentioned earlier, there are three types of flow: workers, materials and information. Unlike 300 manufacturing, where most of the workers are stationary and material moves from one location to another, in construction, both workers and materials move from one location to another. Therefore, both worker and material movements are equally important. However, material movement was excluded from this study mainly because the materials were already delivered and positioned before the observation started. Despite the improvement of communication tools, the information flows primarily between workers. Therefore, information flow is very much tied to worker movement and was not considered separately in this study. 1.2.2 Type and Number of Crew; Equipment Was Not Changeable There are several factors that contribute to NVA movements. These include inefficient layout, work space congestion and improper crew and equipment selection. One goal of this study was to find the cause of unnecessary movement using the perspective of site layout and the work sequence plan. However, understanding that each project has a unique environment and there are thousands of other associated activities, this study assumed that the crew and equipment selection was not changeable. 1.3 Methodology 1.3.1 Worker Movement Diagram Construction Using field observations, videotape review and the site plan, the structure being constructed and the movement paths of four workers (forklift operator, x-bracing connector, right connector and left connector) were sketched. The locations of various workstations and the places where workers stopped were indicated with marks and numbers. The Actual Movement Diagram, which contains both the NVA and NVAR movements of workers, is located at the end of this appendix. Using observations and a logical thinking process, NVAR movements and unavoidable stops were identified. With minimum moving distances and stops, an Ideal Movement Diagram was constructed, which is located at the end of this appendix. 1.3.2 Numerical Analysis Frequent, unnecessary stops are an indicator of unproductive worker movement. When a worker finishes or hands off a task and moves to another location, time and energy are consumed. Therefore, the number of stops can be directly correlated to the level of productivity; fewer stops mean less wasted movements. The number of stops was counted for both actual and ideal movements for this analysis. For each worker, this number was then given a rating to convey stop efficiency as follows: Efficiency = Resources Expected to Be Spent/Resources Actually Spent. Stop Efficiency = Number of Ideal Stops/Number of Actual Stops. A higher efficiency rate signifies better productivity in terms of worker movements. 301 Even if one worker made the same number of stops as another, his movement may still be NVA if he went the long way around from one point to another. Therefore, total distance traveled is an equally important factor in the movement efficiency rating, which is computed as follows: Distance Efficiency = Ideal Travel Distance/Actual Travel Distance. Measuring distance can be a very complex process because of the nature of worker movement in construction. The construction process can be very three-dimensionally oriented, which means that activities are carried out above as well as on the ground. This makes it harder to measure the exact distance between two locations. To overcome this difficulty and achieve more accurate measurements, a three-dimensional coordinate system was adopted. A reference point was selected and each workstation and stop were assigned X, Y, and Z coordinates, so that distance measurement could become simpler. Curved movement path was another problem in distance measurement. Most construction activities take place in an open field where no aisle, corridor or walking path yet exists. To overcome this difficulty, an approximated distance measurement method was used. The curve connecting Points A and B is arbitrary and makes it very difficult to measure the length. However, it is obvious that the curve length will be longer than the straight (Euclidian) distance represented by the single-dotted line and shorter than the double-dotted line (Rectilinear). Therefore, the curved line length was approximated by the average of the Euclidian and Rectilinear distances. When the end point coordinate is known, Euclidian and Rectilinear distances can be measured using the following equations: Rectilinear Distance = |XB - XA| + |YB - YA | + |ZB - ZA| Euclidian Distance = {|XB - XA|2 + |YB -YA |2 + |ZB - ZA|2}1/2 Actual Distance ≈ (Rectilinear Distance + Euclidian Distance)/2 1.4 Analysis Results and Evaluation 1.4.1 Forklift Operator Stop Efficiency Actual Stops 20 Ideal 12 302 Efficiency 0.6 Distance Efficiency Actual Rectilinear 892 Euclidian 735.0 Average Ideal 695.0 578.3 Efficiency 0.78 0.79 0.78 Although the forklift operator had significant wasted movements, the efficiency was relatively high. This resulted from on-the-ground oriented workstation locations. The two main tasks of the forklift operator were delivering steel parts from the stock yard to the erection location and hooking the parts onto the crane cable. Both types of work were conducted on the ground, so the forklift operator only had two-dimensional oriented movements, which tended to have less waste relative to three-dimensional movements. The following is a description of some key wasted movements, corresponding causes and possible solutions for improvement: NVA Occurred Between 02 - 04 Cause Task in other location 07 - 09 Inefficient routing Solution Complete all other tasks before moving on to the next location Carefully select route 1.4.2 X-Bracing Connector Stop Efficiency Actual Stops 31 Distance Efficiency Actual Rectilinear 1557.0 Euclidian 1157.2 Average Ideal 18 Efficiency 0.58 Ideal 312.0 241.3 Efficiency 0.20 0.21 0.20 The x-bracing connector encountered the most interference from other workers’ movements because he worked at an internal location. Therefore, his efficiency was generally lower than the others. There was not much significance in the stop efficiency, but the distance efficiency was very low. The x-bracing connector got in the way of material delivery a few times, and it forced him to pull back from his workstation and led to a significant increase in movement distance. NVA Occurred Between 05 – 06 08 – 12 16 – 20 Cause Unexpected trouble in the girder erection Space congestion Space congestion 303 Solution Pause the process until one problem is completely solved Preplan work sequence Preplan work sequence 1.4.3 Right Connector Stop Efficiency Actual 21 Ideal 16 Efficiency 0.76 Distance Efficiency Actual Rectilinear 488 Euclidian 445.5 Average Ideal 230.0 230.0 Efficiency 0.47 0.52 0.49 Stops Although the right connector had very similar tasks as the left connector, the right connector had better stop efficiency and worse distance efficiency. The right connector had better stop efficiency because, by the nature of the work, he could stay on one side of the structure for both girder and bar joist erection, while the left connector had to move to various locations. The reason for lower distance efficiency was interference from the crane. During the erection process, the crane was located at the right side of the structure and got in the way of the right connector’s man-lift movement. NVA Occurred Between 07 – 09 11 – 15 Cause Manlift position adjustment Detour around the crane Solution Minimize worker mistakes Improve site layout 1.4.4 Left Connector Stop Efficiency Actual 27 Ideal 17 Efficiency 0.63 Distance Efficiency Actual Rectilinear 694 Euclidian 595.1 Average Ideal 410.0 343.0 Efficiency 0.59 0.58 0.58 Stops The left connector had relatively good overall efficiency. The left connector worked mostly on top of the existing structure instead of using a man-lift, and he had little wasted movement. In addition, the left connector had no significant NVA movement during the observation. The efficiency rate was not particularly good mainly due to the up and down movements of the manlift when moving from one workstation to the next. NVA Occurred Between 11 - 15 Cause Gets onto the structure for bar joist erection 304 Solution Work from the top of the structure which brings better overall efficiency 1.5 Further Analysis Plan 1.5.1 Comparative Case Study of Various Projects Because of the diversity of task types, equipment and other circumstances, a simple efficiency rate cannot properly evaluate the movement of various workers. Therefore, analysis of one single project will not provide reliable, generalizable conclusions. To moderate this obscurity, more case studies of similar and different project types should be conducted. 1.5.2 Improvement of Analysis Tool As discussed earlier, measuring the exact distance of the arbitrary movements of workers is not an easy job. Finding a proper tool, such as computer software, will improve the accuracy of analysis. Employing a Global Positioning System (GPS), which has been significantly enhanced in terms of accuracy and cost, can be another method to improve analysis. 305 306 307 Appendix J Worker Movement Study No. 2 1.0 Worker Movement Analysis 1.1 Overview This study presents an analysis of two workers (left and right connectors) during two hours of real-time work. The tasks and installation methods of these connectors were very similar to the left and right connectors in the Noland Project. However, unlike the Noland Project, only the beam installation process was effectively filmed and available and only two workers were visible most of the time in the film. Therefore, this study analyzes only these two workers as they performed the beam installation; a diagram of their actual movements is included at the end of this appendix. A total of 13 beams were installed during the time of analysis. Among 13 beams, six were shorter and seven were longer. The shorter beams were one span length, and the longer ones three span lengths. Due to the two different beam sizes, the work order was somewhat complex; workers had to travel longer distances than necessary and the efficiency of worker movement was affected. 1.2 Analysis Results and Evaluation 1.2.1 Right Connector The right connector had two major duties: to connect the delivered beam and to unhook the crane cable from the beam. As in the first case study project, the right connector worked on top of a man-lift. After connecting the beam, he made small movements such as walking a few steps or bending over to unhook the beam within the lift space. Such small movements were ignored in the analysis. The primary movements were made between one beam installation and the next. Therefore, most movements were made among various workstations. The order of beam installation was mainly left to right, one row at a time. After the connector moved all the way to the right, he lowered the man-lift to the ground and drove back to the far left to work on the next row. This travel distance was significant and lowered efficiency. On the Ideal Movement Diagram located at the end of this appendix, the work process was designed to work north to south in zigzag order to minimize travel distance and number of stops. The following tables show the stop number and travel distance efficiency of the right connector: Stop Efficiency Actual 17 Ideal 13 Efficiency 0.76 Distance Efficiency Actual Rectilinear 480 Euclidian 453.7 Average Ideal 220.0 194.8 Efficiency 0.46 0.43 0.44 Stops 308 1.2.2 Left Connector The left connector had the same duties as the right connector. The work time for each task was almost identical and movements were made in a very synchronic manner. Therefore, the distance efficiency and stop numbers of the left connector were almost the same as those of the right connector. The small difference in distance efficiency was caused by the different man-lift operation styles of the left and right connectors. The following are the results of the analysis: Stop Efficiency Actual 17 Ideal 13 Efficiency 0.76 Distance Efficiency Actual Rectilinear 510 Euclidian 461.8 Average Ideal 260.0 218.6 Efficiency 0.51 0.47 0.49 Stops 1.3 Comparison between Case Study No. 1 and Case Study No. 2 The analysis involved only two workers, the left and right connectors. However, the tasks, equipment and work environments of connectors for both projects were very similar. Therefore, the evaluations of the connectors’ movements can be analyzed to formulate a conclusion. The results of both Case Study No. 1 and Case Study No. 2 for worker movement are presented in the table below: Right Left Case No. 1 Case No. 2 Stop No. 0.76 0.76 Distance 0.45 0.44 Stop No. 0.63 0.76 Distance 0.58 0.49 When compared to the others, the Case No. 1 left connector had a somewhat lower stop efficiency and higher distance efficiency. This was due to the special circumstance of working on top of the structure next to workstations instead of riding the man-lift. Because of this, he has been omitted from consideration. The resulting efficiencies of all other workers were very similar; therefore, it can be concluded that the overall job efficiencies were comparable for both projects. However, the causes of efficiency drop between the two projects were quite different. Many unnecessary stops were made and travel distance was increased due to space congestion in Case Study No. 1. In Case Study No. 2, an inefficient work order was the primary cause of the efficiency drop. To further increase efficiency and minimize worker movement at the jobsite, optimal work orders and space sharing arrangements should be preplanned. 309 An interesting finding in Case Study No. 1 was that space congestion was minimal. The forklift and ground crews worked from the actual jobsite where the installation took place. This made the swing angle and carry-over distances greater for the crane; however, it helped to minimize space congestion on the jobsite. 310 311 312 References Alarcon, L., 1996, “Performance Measuring Benchmarking and Modeling of Construction Projects,” Proceedings of the Fourth Annual Conference of the International Group for Lean Construction (IGLC-4), Birmingham, UK. Alves, T. and C. Formosa, 2000, “Guidelines for Managing Physical Flows in Construction Sites,” Proceedings of the Eighth Annual Conference of the International Group for Lean Construction (IGLC-8), Brighton, UK. Arbulu, R., I. Tommelein, et al., 2002, “Contributors to Lead Time in Construction Supply Chains: Case of Pipe Supports Used in Power Plants,” 2002 Winter Simulation Conference, San Diego, CA. Ballard, G., 1999, “Improving Work Flow Reliability,” Proceedings of the Seventh Annual Conference of the International Group for Lean Construction (IGLC-7), Berkeley, CA. Ballard, G., 2000a, “Last Planner System of Production Control,” Thesis submitted to Faculty of Engineering, University of Birmingham, Birmingham, 192. Ballard, G., 2000b, “Lean Project Delivery System,” White Paper No. 8, Lean Construction Institute. Ballard, G., 2000c, “Managing Work Flow on Design Projects,” CIB W96, Atlanta, GA. Ballard, G., M. Casten, et al., 1997, “PARC: A Case Study,” Proceedings of the Fourth Annual Conference of the International Group for Lean Construction (IGLC-4), Birmingham, UK. Ballard, G. and G. Howell, 1998, “What Kind of Production Is Construction,” Proceedings of the Sixth Annual Conference of the International Group for Lean Construction (IGLC-6), Guarujá, Brazil. Ballard, G., L. Koskela, et al., 2001, “Production System Design: Work Structuring Revisited,” White Paper, Lean Construction Institute. Bertelsen, S. and L. Koskela, 2002, “Managing the Three Aspects of Production in Construction,” Proceedings of the Tenth Annual Conference of the International Group for Lean Construction (IGLC-10), Gramado, Brazil. Ciampa, D., 1991, “The CEO’s Role in Time-Based Competition,” J. D. Blackburn, ed., In TimeBased Competition, Business One Irwin, Homewood, IL. Cronbach, L. J., 1951, “Coefficient Alpha and the Internal Structure of Tests,” Psychometrika 16, 297-234. Crowley, A., 1998, “Construction as a Manufacturing Process: Lessons from the Automotive Industry,” Computers & Structures, 67, 389-400. 313 dos Santos, A., 1998, “Principle of Transparency Applied in Construction,” Proceedings of the Sixth Annual Conference of the International Group for Lean Construction (IGLC-6), Guarujá, Brazil. dos Santos, A., 1999, “Application of Flow Principles in the Production Management of Construction Sites,” School of Construction and Property Management, University of Salford. dos Santos, A. J. Powell, et al., 2000, “Reduction of Work-In-Progress in the Construction Environment,” Proceedings of the Eighth Annual Conference of the International Group for Lean Construction (IGLC-8), Brighton, UK. Duggan, K. and J. Liker, 2002, Creating Mixed Model Value Streams: Practical Lean Techniques for Building to Demand, New York, NY, Productivity Press. Eagan, J., 1998, Rethinking Construction, London Department of the Environment, Transport and the Regions, 40. Fearon, H., W. Ruch, et al., 1979, Fundamentals of Production/Operations Management, New York, NY, West Publishing Company. Fowler, F. J., 1995, Improving Survey Questions: Design and Evaluation, Thousand Oaks, CA, Sage Publications. Freire, J. and L. Alarcon, 2002, “Achieving Lean Design Process: Improvement Methodology,” Journal of Construction Engineering and Management, Volume 128, No. 3, May-June 2002, 248-256. Fujimoto, T., 1999, The Evolution of a Manufacturing System at Toyota, New York, NY, Oxford University Press. Galbraith, J., 1974, “Organization Design: An Information Processing View,” Interfaces, 4, 2836. Hatcher, L., 1994, “A Step-by-Step Approach to Using the SAS(R) System for Factor Analysis and Structural Equation Modeling,” Cary, North Carolina, SAS Institute. Hopp, W. and M. Spearman, 1996, Factory Physics: Foundations of Manufacturing Management, Boston, MA, Irwin/McGraw-Hill. Howell, Greg and Glenn Ballard, “Implementing Lean Construction: Understanding and Action,” Proceedings of the Sixth Annual Conference of the International Group for Lean Construction (IGLC-6), Guarujá, Brazil. Koskela, L., 1992, “Application of the New Production Philosophy to Construction,” Technical Report 72, CIFE, Stanford University, 75. Koskela, L., 2000, An Exploration into a Production Theory and Its Application to Construction, Helsinki University of Technology, Espoo, Finland, VTT Publications, 298. 314 Koskela, L., G. Ballard, et al., 1996, “Towards Lean Design Management,” Proceedings of the Fourth Annual Conference of the International Group for Lean Construction (IGLC-4), Birmingham, UK. Lane, R. and G. Woodman, 2000, “Wicked Problems, Righteous Solutions, Back to the Future on Large Complex Projects,” Proceedings of the Eighth Annual Conference of the International Group for Lean Construction (IGLC-8), Brighton, UK. Lantelme, E. and C. Formoso, 2000, “Improving Performance Through Measurement: The Application of Lean Production and Organizational Learning Principles,” Proceedings of the Eighth Annual Conference of the International Group for Lean Construction (IGLC-8), Brighton, UK. Lareau, W., 2000, Lean Leadership: From Chaos to Carrots to Commitment, Tower II Press, Carmel, Indiana. London, K. and R. Kenley, 2001, “An Industrial Organization Economic Supply Chain Approach for the Construction Industry: A Review,” Construction Management and Economics, 19, 777788. MacInnes, R., 2002, The Lean Enterprise Memory Jogger, Salem, NH, Goal/QPC. Matthews, O., G. Howell, et al., 2003, “Aligning the Lean Organization: A Contractual Approach,” Proceedings of the Eleventh Annual Conference of the International Group for Lean Construction (IGLC-11), Blacksburg, VA. McClelland, G., 2003, Personal Communication, Department of Psychology, University of Colorado. Nisbett, R., 2003, The Geography of Thought: How Asians and Westerners Think Differently and Why, New York, NY, The Free Press. Nunnaly, J., 1978, Psychometric Theory, New York, NY, McGraw-Hill. Ohno, T., 1988, Toyota Production System, New York, NY, Productivity Press. Oppenheim, A. N., 1992, Questionnaire Design and Attitude Measurement, London, Pinter Publishing, Ltd. Pappas, M., 1999, “Evaluating Innovative Construction Management Methods through the Assessment of Intermediate Impacts,” Civil Engineering, Austin, TX, University of Texas at Austin. Picchi, F., 2001, “System View of Lean Construction Application Opportunities,” Proceedings of the Ninth Annual Conference of the International Group for Lean Construction (IGLC-9), Singapore. Plossl, G., 1991, Managing in the New World of Manufacturing, Englewood Cliffs, NJ, PrenticeHall. 315 Rea, L. and R. Parker, 1997, Designing and Conducting Survey Research: A Comprehensive Guide, San Francisco, CA, Jossey-Bass. Rother, M. and J. Shook, 1998, “Learning to See: Value Stream Mapping to Create Value and Eliminate Muda,” Brookline, MA, The Lean Enterprise Institute. Schonberger, R. J., 1996, World Class Manufacturing: The Next Decade, New York, NY, The Free Press. Schroeder, R., 1993, Operations Management: Decision Making in the Operations Function, Columbus, OH, McGraw-Hill International Editions. Serpell, A., 1966, Proceedings of the Fourth Annual Conference of the International Group for Lean Construction (IGLC-4), Birmingham, UK. Seymour, D., 1996, “Developing Theory in Lean Construction,” University of Birmingham, 24. Shingo, S., 1981, Study of the Toyota Production System, Japan Management Association, New York, NY, Productivity Press. Stalk, G. J. and T. Hout, 1990. Competing Against Time, New York, NY, Free Press. Tapping, D., T. Luyster, et al., 2002, Value Stream Management, New York, NY, Productivity Press. Tommelein, I., 1998, “Pull-Driven Scheduling of Pipe-Spool Installation: Simulation of Lean Construction Technique,” ASCE Journal of Construction Engineering and Management, Vol. 124, No. 4 (July/August), 279-288. Tommelein, I., N. Akel, et al., 2003, Capital Projects Supply Chain Management: SC Tactics of a Supplier Organization, Construction Research Congress, Honolulu, HI, ASCE. Tommelein, I. and A. Li, 1999, “Just in Time Concrete Delivery: Mapping Alternatives for Vertical Supply Chain Integration,” Proceedings of the Seventh Annual Conference of the International Group for Lean Construction (IGLC-7), Berkeley, CA. Tommelein, I., D. Riley, et al., 1998, “Parade Game: Impact of Work Flow Variability on Succeeding Trade Performance,” Proceedings of the Sixth Annual Conference of the International Group for Lean Construction (IGLC-6), Guarujá, Brazil. Tommelein, I. and M. Weissenberger, 1999, “More Just-In-Time: Location of Buffers in Structural Steel Supply and Construction Processes,” Proceedings of the Seventh Annual Conference of the International Group for Lean Construction (IGLC-7), Berkeley, CA. Tsao, C., I. Tommelein, et al., 2000, “Case Study for Work Structuring: Installation of Metal Door Frames,” Proceedings of Eighth Annual Conference of the International Group for Lean Construction (IGLC-8), Brighton, UK. Walbridge Aldinger, 2000, Lean Fundamentals, Detroit. 316 Walton, M., 1986, The Deming Management Method, New York, NY, Putnam Publishing. Wild, R., 1995, Production and Operations Management, 5th Ed., London, Cassell Educational Ltd. Winch, G., 2003, “Models of Manufacturing and the Construction Process: The Genesis of ReEngineering Construction,” Building Research & Information, 31 (2), 107-118. Womack, J. P. and D. T. Jones, 1996, Lean Thinking, New York, NY, Simon & Schuster. Womack, J. P., D. T. Jones, et al., 1990, The Machine That Changed the World, New York, NY, Rawson. 317 Glossary Sources: □ □ □ □ □ Lean Thinking, James P. Womack and Daniel T. Jones The Encyclopedia of Operations Management Terms, Arthur V. Hill Competing in World Class Manufacturing, Craig Giffi, Aleda V. Roth and Gregory M. Seal Fundamentals of Production/Operations Management, Harold E. Fearon, W. Ruch et al. Factory Physics, Wallace Hopp and Mark Spearman Acceptable Quality Level (AQL)--A concept that states there is some nonzero level of permissible defects. Activity-Based Costing--Collecting cost data on all activities that occur rather than just the three primary resources (materials, labor and machinery). This is an attempt to define the components of burden. The objective of this system is to look at all areas where cost reductions can be made. Aggregate Planning--The broad, overall decisions that relate to the programming of resources for production over an established time horizon. Batch and Queue--The mass production practice of making large lots of a part and then sending the batch to wait in the queue before the next operation in the production process. Contrast with single-piece flow. Benchmarking--Refers to comparing one’s current performance against the world leader in any particular area. In essence, it means finding and implementing best practices in the world. Benchmarking is essentially a goal setting procedure. Cells--The layout of different types of machines performing varied operations in a tight sequence, typically in a U-shape, to permit single-piece flow and flexible deployment of human effort by means of multimachines. Contrast with process villages. Cellular Manufacturing--An approach in which manufacturing work centers (cells) have the total capabilities needed to produce an item or a group of similar items. Critical Path Method/Program Evaluation and Review Technique (CPM/PERT)--A method for determining the critical path by examining the earliest and latest start and finish times for each activity. Cycle Time--The time required to complete one cycle of an operation. If cycle time for every operation in a complete process can be reduced to equal takt time, products can be made in single-piece flow. Computer-Aided Design/Computer-Aided Manufacturing (CAD/CAM)--Engineering designs created and tested using computer simulations and then transferred directly to the production floor where machinery uses the information to perform production functions. 318 Concurrent (or Simultaneous) Engineering (CE)--Deals primarily with the product design phase. The term refers to an improved design process characterized by rigorous up-front requirements analysis, incorporating the constraints of subsequent phases into the conceptual phase and tightening of change control toward the end of the design process. Compression of the design time, increase in the number of iterations (i.e., increase in the frequency of information exchange) and reduction in the number of change orders are three major objectives of concurrent engineering. Continuous Improvement--Associated with Just-in-Time (JIT) and Total Quality Control (TQC), continuous improvement has emerged as a theme itself. A key to this concept is to maintain and improve the working standards through small, gradual improvements. The inherent wastes in the process are natural targets for continuous improvement. The term “learning organization” refers partly to the capability of maintaining continuous improvement. Cross Training and Job Rotation--Employees are rotated out of their job after a certain duration and trained into a new job. They are not only trained how to do the job, but are also informed of the quality and maintenance issues that go along with the job. The principle here is that an employee with a well rounded background of how the company operates will be more valuable to the company. Distribution Requirements Planning (DRP)--The function of determining the need to replenish inventory at branch warehouses over a forward period of time. Economic Order Quantity (EOQ)--The optimal order quantity (batch size) that minimizes the sum of the carrying and ordering cost. Employee Involvement--Rapid response to problems requires empowerment of workers. Continuous improvement is heavily dependent on day-to-day observation and motivation of the work force; hence, the idea of quality circles. To avoid waste associated with division of labor, multiskilled and/or self-directed teams have been established for product/project/customer based production. Five Whys--Taiichi Ohno’s practice of asking “why” five times whenever a problem was encountered so that the root cause of the problem can be identified and effective countermeasures can be developed and implemented. Five S’s--Derived from the Japanese words for five practices leading to a clean and manageable work area: seiri (organization), seiton (tidiness), seiso (purity), seiketsu (cleanliness) and shitsuke (discipline). Flexible Manufacturing--An integrated manufacturing capability to produce small numbers of a great variety of items at low unit cost. Flexible manufacturing is also characterized by low changeover time and rapid response time. Flow--The progressive achievement of tasks along the value stream so that a product proceeds from design to launch, order to delivery and raw materials into the hands of the customer with no stoppages, scrap or backflows. ISO 9000--A set of process quality standards developed by the International Organization for Standardization and recognized worldwide. 319 Just-in-Time (JIT)--A system for producing and delivering the right items at the right time in the right amounts. JIT approaches just-on-time when upstream activities occur minutes or seconds before downstream activities, so single-piece flow is possible. The key elements of JIT are flow, pull, standard work (with standard in-process inventories) and takt time. Kaikaku--Radical improvement of an activity to eliminate muda; for example, reorganizing processing operations for a product so that instead of traveling to and from isolated “process villages,” the product proceeds through operations in single-piece flow in one short space. Also called breakthrough kaizen, flow kaizen and system kaizen. Kaizen--Continuous, incremental improvement of an activity to create more value with less muda. Also called point kaizen and process kaizen. Kanban--A small card attached to boxes of parts that regulates pull in the Toyota Production System by signaling upstream production and delivery. Lead Time--The total time a customer must wait to receive a product after placing an order. When a scheduling and production system is running at or below capacity, lead time and throughput time are the same. When demand exceeds the capacity of a system, there is additional waiting time before the start of scheduling and production, and lead time exceeds throughput time. Refer to throughput time. Line Balancing--A means of balancing the appropriate amount of workers needed for a production line by satisfying cycle time and precedence constraints. Manufacturing Requirements Planning (MRP II)--A method for effective planning of all the resources of a manufacturing company. Ideally, it addresses operational planning in units, financial planning in money, and has a simulation capability to answer what-if questions. Master Production Schedule (MPS)--A time-phased plan specifying how many units are requested and when the firm plans to build each end item. Material Requirements Planning (MRP)--A computerized system used to determine the quantity and timing requirements for materials used in a production operation. MRP systems use a master production schedule, a bill of materials listing every item needed for each product to be made, and information on current inventories of these items in order to schedule the production and delivery of the necessary items. Manufacturing Resource Planning (often called MRP II) expands MRP to include capacity planning tools, a financial interface to translate operations planning into financial terms and a simulation tool to assess alternative production plans. Modular Design--Organizing a set of distinct components that can be developed independently and then “plugged together.” Muda--Any activity that consumes resources but creates no value. Operation--An activity or activities performed on a product by a single machine. Contrast with process. 320 Outsourcing--Procuring raw materials and components externally rather than creating them internally. Perfection--The complete elimination of muda so that all activities along a value stream create value. Period Order Quantity (POQ)--A lot sizing rule that defines the order quantity in terms of the period’s supply. Poke Yoke--A mistake-proofing device or procedure to prevent a defect during order taking or manufacture. An order-taking example is a screen for order input developed from traditional ordering patterns that questions orders falling outside the pattern. The suspect orders are then examined, often leading to the discovery of input errors or buying based on misinformation. A manufacturing example is a set of photocells in parts containers along an assembly line to prevent components from progressing to the next stage with missing parts. The poke yoke in this case is designed to prevent movement of a component to the next station if a light beam is not broken by the operator’s hand in each bin containing a part for the product under assembly at that moment. A poke yoke is sometimes also called a baka yoke. Process--A series of individual operations required to create a design, completed order or product. Processing Time--The time a product is actually being worked on in design or production and the time an order is actually being processed. Typically, processing time is a small fraction of throughput time and lead time. Processing Villages--The practice of grouping machines or activities by type of operation performed; for example, grinding machines or order entry. Contrast with cells. Pull--A system of cascading production and delivery instructions from downstream to upstream activities in which nothing is produced by the upstream supplier until the downstream supplier signals a need. The opposite of push. Refer also to kanban. Quality Circles--Teams that meet to discuss quality improvement issues. Quality Function Deployment (QFD)--A visual decision-making procedure for multiskilled project teams that develops a common understanding of the customer’s voice and a consensus on the final engineering specifications of the product that has the commitment of the entire team. QFD integrates the perspectives of team members from different disciplines, ensures that their efforts are focused on resolving key trade-offs in a consistent manner against measurable performance targets for the product, and deploys these decisions through successive levels of detail. The use of QFD eliminates expensive backflows and rework as projects near launch. Queuing Theory--A branch of mathematics concerned with systems in which customers (orders, calls, etc.) arrive and are served by one or more servers. Queuing theory models are usually concerned with estimating the steady-state performance of the system such as the utilization, the mean time in queue, the mean time in system, the mean number in queue and the mean number in system. 321 Queue Time--The time a product spends in line awaiting the next design, order processing or fabrication step. Re-Engineering--The radical reconfiguration of processes and tasks, especially with respect to implementation of information technology. Recognizing and breaking away from outdated rules and fundamental assumptions is a key issue of re-engineering. Right-Sized Tool--A design, scheduling or production device that can be fitted directly into the flow of products within a product family so that production no longer requires unnecessary transport and waiting. Seven Muda--Taiichi Ohno’s original enumeration of the wastes commonly found in physical production. These are overproduction ahead of demand, waiting for the next processing step, unnecessary transport of materials (for example, between process villages or facilities), over processing of parts due to poor tool and product design, inventories more than the absolute minimum, unnecessary movement by employees during the course of their work (looking for parts, tools, prints, help, etc.) and production of defective parts. Single-Piece Flow--A situation in which products proceed, one complete product at a time, through various operations in design, order taking and production, without interruptions, backflows or scrap. Contrast with batch-and-queue. Six Sigma--Structured application of the tools and techniques of TQM on a project basis to achieve strategic business results. Sometimes defined as a failure rate of 3.4 parts per million. Standard Work--A precise description of each work activity specifying cycle time, takt time, the work sequence of specific tasks and the minimum inventory of parts on hand needed to conduct the activity. Standard Work Design--The design of each work activity specifying cycle time, work sequence of specific tasks and minimum inventory of parts on hand needed to conduct the activity. Statistical Quality Control (SQC)--Using statistical methods to identify, prioritize and correct elements of the manufacturing process that detract from high quality. Strategic Partnering--A structural management approach to facilitate teamwork across contractual boundaries. With such coordination, construction companies may benefit from reductions in delivery times, improved supplier responsiveness and improved quality of products and services as well as reductions in costs. Stock Keeping Unit (SKU)--A unique identification number (or alphanumeric string) that defines an item for inventory. Taguchi Methods--Developed to improve the implementation of TQC in Japan. They are based on the design of experiments to provide near optimal quality characteristics for a specific objective. The goal is to reduce the sensitivity of engineering designs to uncontrollable factors or noise. Sometimes referred to as “robust design” in the United States. 322 Takt Time--The available production time divided by the rate of customer demand. Takt time sets the pace of production to match the rate of customer demand and becomes the heartbeat of any lean system. Theory of Constraints (TOC)--A management philosophy that recognizes that there are very few critical areas, resources or policies that truly block the organization from moving forward. If performance is to be improved, an organization must identify its constraints, exploit the constraints in the short run and, in the longer term, find ways to overcome the constraints (limited resources). Throughput Time--The time required for a product to proceed from concept to launch, order to delivery or raw materials into the hands of the customer. This includes both processing and queue time. Contrast with processing time and lead time. Time Based Competition (TBC)--Refers to compressing time throughout the organization for competitive benefit. Essentially, this is a generalization of the JIT philosophy. Total Productive Maintenance (TPM)--Refers to autonomous maintenance of production machinery by small groups of multiskilled operators. TPM strives to maximize production output by maintaining ideal operating conditions. Total Quality Control (TQC)--The difference between total quality management and total quality control is epitomized by the phrase “management vs. control.” Most companies “control” quality by a series of inspection processes, but “managing” quality is a continuous quality improvement program. However, a good control system is the first step in the development of a management system. Total Quality Management (TQM)--An approach for improving quality that involves all areas of an organization (sales, engineering, manufacturing, purchasing, etc.) with a focus on employee participation and customer satisfaction. TQM can involve a wide variety of quality control and improvement tools and emphasizes a combination of managerial principles and statistical tools. Transparency/Visual Control--The placement in plain view of all tools, parts, production activities and indicators of production system performance so that the status of the system can be understood at a glance by everyone involved. Value--A capability provided to a customer at the right time at an appropriate price, as defined in each case by the customer. Value Based Management (VBM)--Refers to conceptualized and clearly articulated value as the basis for competing. Continuous improvement to increase customer value is one essential characteristic of value based management. Value Engineering--The systematic application of recognized techniques by a multidisciplined team to identify the function of a product or service, establish a worth for that function, generate alternatives through the use of creative thinking and provide the needed functions to accomplish the original purpose of the project reliably and at the lowest life-cycle cost without sacrificing safety, necessary quality and environmental attributes of the project. 323 Value Stream--The specific activities required to design, order and provide a specific product, from concept to launch, order to delivery and raw materials into the hands of the customer. Value Stream Mapping--Identification of all the specific activities occurring along a value stream for a product or product family. Visual Management (VM)--An orientation toward visual control in production, quality and workplace organization. The goal is to make the applicable standard and any deviation from it immediately recognizable by anybody. This is one of the original JIT ideas which has been systematically applied only recently in the West. Zero Defects--A concept introduced by Japanese manufacturers that stresses the elimination of all defects. This contrasts with the idea of AQL. 324 Acknowledgments Students Sincere thanks to all of the students in the Construction Engineering and Management Program at the University of Colorado who contributed work, thought and care to this project. Thanks to Jeff Hlad, Travis Stewart, Spencer Won, Poon Thiengburanthum and Brian Saller and especially to Mark Krewedl and Josh Balonick. Practitioners To those industry people who were so generous with their time and their knowledge - genuine thanks go out to Greg Holroyd (Southland Industries), Remo Mastriani (Walbridge-Aldinger), Paul Reiser (Boldt Industries) and Russell Batchelor (BAA). Academics and Lean Theorists Many others who studied lean manufacturing and lean construction contributed to this effort. Thanks go out to Professor Glen Ballard, Greg Howell, Gene Lazaroff, Professor Iris Tommelein, Professor Lauri Koskela, Professor Gary McCelland and Professor Jeffrey Luftig. Former Team Members And finally, Bob Knapp and Tom Searl contributed significantly to the early efforts of the team; their involvement was most appreciated. 325