View Report - Lexam VG Gold Inc.
Transcription
View Report - Lexam VG Gold Inc.
V G G o ld C o r p . Fuller Project Preliminary Economic Assessment March 2008 VETRIN Mine Planners Ltd. R. D. Moran P. Eng. P.A. Bevan P. Eng. Consulting Mining Geologist J. R. Doran P. Eng. VETRIN Mine Planners Ltd. TABLE OF CONTENTS Section 1.0 SUMMARY……………………………………………………………...… INTRODUCTION: PROPERTY DESCRIPTION AND LOCATION: LOCAL INFRASTRUCTURE AND RESOURCES: HISTORIC DRILLING: GEOLOGICAL SETTING: DEPOSIT TYPES: DATA VERIFICATION: MINERAL PROCESSING: MINERAL RESOURCE ESTIMATES: ECONOMIC ANALYSIS: RECOMMENDATIONS: Section 2.0 TERMS OF REFERENCE Section 3.0 RELIANCE ON OTHER EXPERTS Section 4.0 PROJECT BACKGROUND INFORMATION Section 5.0 GEOLOGICAL SETTING Section 6.0 EXPLORATION DRILLING Section 7.0 ASSAY QUALITY CONTROLS Section 8.0 MINERAL PROCESSING Section 9.0 HW and CW ZONE RESOURCES Section 10.0 PERMITTING, SOCIAL CONSULTATION & ENVIRONMENTAL COMPLIANCE Section 11.0 PROJECT BUDGET & ECONOMICS Section 12.0 CONCLUSIONS Section 13.0 RECOMMENDATIONS Section 14.0 REFERENCES Section 15.0 APPENDIX VETRIN Mine Planners Ltd. List of Tables Table 1.1 - Mining Resource Summary Table 1.2 - LOM Cash Flow Table 4.1- Claim List Table 9.1- Undiluted Resource Estimate @.075 oz cut-off Table 9.2- Stope Block Tons & Grade Summary Table 11.1- Closure Bond, Surface plant & Mine Dewatering Budget Table 11.2- Unit Mining Costs Table 11.3- Mining Cost Summary Table 11.4- Internal rate of Return Table 11.5- Cash Flow Sensitivity Analysis Table 11.6- 2008 – 2013 Cash Flow Forecast VETRIN Mine Planners Ltd. List of Figures Figure 1.1- Regional Location Map Figure 1.2- Fuller Project Location in the Timmins Gold Camp Figure 4.1- Timmins Mining Camp Gold Production Figure 4.2- Fuller Property & VG Gold Corp. Adjoining Property Figure 4.3- MNDM Land Tenure Figure 5.1- Regional Geology Figure 5.2- Property Geology Figure 9.1- Hanging Wall Zone Long Section Figure 9.2- Contact Zone Long Section Figure 11.1- Fuller Project –Location & Surroundings Figure 11.2- 375 Haulage GA Figure 11.3- 650 Haulage GA Figure 11.4- 500 Sill GA Figure 11.5 150 Sill GA VETRIN Mine Planners Ltd. 1.0 SUMMARY Introduction: The Fuller Project is a proposed underground mining program which will extract 824,400 tons of ore in order to recover 153,970 ounces of gold bullion. Phase I of the mine plan expands the existing ramp access and lateral development to the 650 foot level in order to mine 476,000 tons while Phase II of the plan involves deepening of the ramp to the 950 foot horizon and associated lateral work to extract an additional 348,400 tons. The overall activities will consist of dewatering, mine rehab, surface plant procurement and setup, 22,000 feet of lateral and vertical development and shrinkage mining of multiple ore blocks. The waste produced during this project will be stockpiled on site. Ore grade material will be trucked via highway haulage equipment to a local mill for processing under a custom milling agreement. The tailings will be stored in the custom mill’s existing tailings pond and will be treated and monitored by the custom miller. Exploration on the property began in 1910 through to the 1920’s and 30’s resulting in a small scale mining operation in 1940. Belmoral Mines completed 10,000 feet of underground development work during the period from 1986 to 1989. VG Gold Corp.’s direct exploration activity began in 1996 in the form of over 120,000 feet of diamond drilling from 1996 to 2007. Wardrop prepared the NI 43101 compliant mineral resource estimate in May of 2006. Access to this report can be achieved by viewing VG Gold’s press releases on the Sedar.com website. The mineral resources outlined in this report were reviewed with the assistance of Peter Bevan, P. Eng., an independent consulting geologist with over 25 years of mine operations, exploration and property evaluation experience. From this review, ore grade mining blocks where delineated and volumes and grade calculated. These mining resources then became the basis for the overall mining plan and budget. VG Gold Corp. has also advanced the permitting process up to and including, submission of an application for a C of A to discharge process water, and is in the final stage of fulfilling the requirements in order to submit a closure plan for approval. Public consultations have been held to respond to and address their issues. The writer has been informed by VG Gold personnel that consultations with the First Nations have taken place. Mr. Tom Meredith, President of VG Gold Corp., has engaged Vetrin Mine Planners Ltd. (VMPL) to prepare a preliminary economic assessment study for the Fuller deposit using the resources above the 950’ level elevation. VETRIN Mine Planners Ltd. Property Description & Location: The Fuller project is located within the city limits of Timmins Ontario which is located approximately 700 kms. north of Toronto, Ontario (figure 1.1). The Fuller property is on the south-central boundary of Tisdale Township, approximately 3.5 miles southeast of the Timmins city centre. VG Gold holds 100% interest in the Fuller property. The Fuller property consists of 14 patented mining claims covering an area of about 207.22 hectares in Tisdale and Deloro Townships within the Porcupine Mining Division. The claims comprise parts of nine separate surveyed lots and five unsurveyed lots. An inclined shaft excavated in 1920’s and a ramp-decline excavated in the 1980's are collared on a single patented claim, called the “Fuller claim” (P13189). VG Gold owns both the surface and mineral rights of the Fuller claim. The Fuller claim is the only claim that is not subject to net profits interest (NPI). VG Gold also owns the mineral rights to surrounding properties; of which 50 claims are subject to an NPI with The Summit Organization, Inc amounting to a 10 % NPI royalty on all tons mined within the 50 claims. This study does not analyse whether any part of the mining resource to the 950 level falls outside the Fuller claim. Figure 1.1 Regional Map Timmins Ontario Timmins VETRIN Mine Planners Ltd. Local Infrastructure and Resources: The Timmins area is well serviced by mine contracting and mine equipment suppliers. Several underground gold mines (Hoyle Pond & Dome) are active under the Porcupine Joint Venture between Kinross and Goldcorp. Xstrata and Liberty Resources are operating base metal mines for nickel, zinc and copper and an open pit over the former Pamour mine is also active through the Porcupine Joint Venture group. Figure 1.2 illustrates the density of past mining activity around the project site. Figure 1.2 Fuller Project Location in the Timmins Gold Camp VG Gold Corp. Fuller Project Paymaster Mine 1915 – 1966 1,192,206 oz. City of Timmins Aunor Mine Buffalo Ankerite/March Mine 1926 -1953 Delnite Mine 1940 – 1984 1,019,130 oz. 2,502,214 oz. 1937-1964 920,404 oz. VG Gold Corp. Buffalo Ankerite South Pit Project VETRIN Mine Planners Ltd. Historic Exploration: A 228-foot inclined shaft (the “Edwards shaft”) was sunk some time after 1924. In 1940-1941 Nakhodas Mining Company Limited (“Nakhodas”) developed 2,100 feet of lateral workings at the 160 foot level, and mined 44,028 tons grading 0.149 oz/t Au (recovered) above the level in four stopes. Nakhodas also drilled at least 10,919 feet of surface drilling in 41 drill holes (S 1 to S41). In the late 1930's, Hollinger Consolidated Gold Mines conducted a 14,000 foot drilling program in 25 holes on the claims in Tisdale Township. In the early 1950’s the Buffalo Ankerite mine explored the apparent down plunge onto their property of the north limb of the Fuller zone from their #5 Shaft. This work was done on the 1,550 ft. and 2,550 ft. levels and records indicate the removal of 14,000 tons grading 0.21 ounces per ton. The Buffalo Ankerite mine suspended operations in 1953. Geological Setting: Geology mapping in Tisdale Township depicts the Property as being underlain by a generally eastwest trending assemblage of massive and pillowed mafic metavolcanic flows with minor variolitic flows. These have been traced onto the adjacent Goldcorp’s (formerly Placer Dome) Paymaster mine and Dome mine properties to the east. To the west the units are traceable into complex fold structures; part of the package is believed to be folded to the south around the South Tisdale anticline, while the northerly part of the package appears to trend onto the Hollinger mine property (Ferguson and others, 1968). Deposit Type: Gold mineralization on the VG Gold property belongs to the structurally controlled Archean lode gold class of deposits. Structurally hosted, low-sulphide, lode gold vein systems in metamorphic terrains from around the world possess many characteristics in common, spatially and through time; they constitute a single class of epigenetic precious metal deposits, formed during accretionary tectonics or continental delamitation. Data Verification: Wardrop carried out an internal validation from the original drill hole logs and the drill hole database on 45 (5%) of the 880 drill holes in the total database. Data verification was completed on collar coordinates, end of hole depth, down-the-hole survey measurements, from and to footage measurements of geology and assay sampling intervals, lithological unit and gold grades that were compiled from hand written drill logs into an ACCESS database. Most errors were insignificant and related to mistakes in transcription. Details of the verification are VETRIN Mine Planners Ltd. set out in Table 14.1 of the May 2006 Wardrop NI 43-101 report. The digitizing of drawings and maps were validated on an on-going basis, with information being visually checked while importing the digitized areas to Gemcom geological software. The data verification had an error rate lower then less than 1%. Mineral Processing: At the time of this report VG Gold Corp. had not pursued any metallurgical testing on the Fuller material. Records of the milling during the 1988 exploration program are not available for review. Data recovered previously while evaluating VG Gold’s Buffalo Ankerite Project established a historic figure for mill recoveries in the economic model. Production statistics from the Ontario Department of Mines annual reports from the 1940’s indicate that gold recoveries above 92% using the Merrill Crowe metallurgical process was the norm for the Buffalo Ankerite, the property directly to the south of the Fuller claim. The potential custom mill that is being considered for this project is a Merrill Crowe operation built in the late 1980’s. Establishing milling characteristics such as energy requirements, retention times, and filtration rates will be beneficial in establishing a base line for a custom milling agreement. Barring the discovery of technical reports from the past, the option of sending core samples to a qualified lab would be recommended to establish a base line for a custom milling agreement. Mining Resource Estimate: Ore polygons greater then 0.10 where grouped into practical mining blocks or stopes. In some cases lower grade material was added to the stope profile to account for actual mining practices where the use of gravity flow of material has to be designed into the stope profiles. These lower grade portions have been factored into the overall grade calculation. After accounting for 15% external dilution, a minimum mining width of 5 feet was used for volume and grade estimates. Stope sizes ranged from 16,000 to 40,000 tons and in some cases carried through to several haulage levels. There was no accounting for sill pillars or stope backfilling which can occur during an actual mining operation. Table 1.1 Mining Resource Summary to the 950’ Elevation – 15 % Diluted Tons and Grade Total Diluted Tons & Grade Tons Grade Ounces 824,420 0.203 167,678 VETRIN Mine Planners Ltd. Economic Analysis: For the purpose of this evaluation, a 750 $US gold price and an exchange rate of 1.0 CDN was used to establish a base price of $750 / oz. CDN for the revenue calculation. No inflation factor has been included in the production costs. The cost of capital and corporate taxation has not been factored into this evaluation. Table 1.2 provides the LOM cumulative cash flow of the project. A detailed cost and revenue stream is contained in Section 11, Table 11.6. Total recovered ounces for the project stands at 153,790 using a mill recovery of 92%, which produces a recovered grade of 0.196 ounce per ton. The project achieves a positive cash flow in year three in this model and generates a gross value of $13 million. Total cost per ounce is estimated at $664.83 CDN. The calculated capital and operating cost per ounce is $161.14 and $503.69 respectively. A daily ore production rate of 500 tons per day was used to produce the development and mining schedule. Milling of the ore would be batched through a custom mill in 15,000 ton monthly lots. Table 1.2 LOM Cash Flow in (000’s) $CDN CUMMULATIVE CASH FLOW CASH FLOW AFTER CAPEX UNITS YEAR 2008 TOTAL 2009 TOTAL 2010 TOTAL 2011 TOTAL 2012 TOTAL 2013 PROJECT TOTAL -$3,611 -$10,911 -$9,321 -$2,901 $5,004 $13,112 $13,112 Recommendations: The economic model demonstrates a healthy IRR return of 28% using the parameters specified. The Fuller deposit’s advanced nature in terms of completed diamond drilling and underground development provides a major lead time advantage in achieving positive cash flow by the third year of production. Vetrin Mine Planners Ltd. (VMPL) recommends that VG Gold Corp. proceed with permitting and procurement of a milling agreement which are critical components to the project going forward. All other data is available to proceed to a full feasibility study in order to optimize and firm up the production plan. The short and long term benefits of the alternative mining methods outlined in Section 13 can be evaluated and if warranted be incorporated in this study. VETRIN Mine Planners Ltd. 2.0 TERMS OF REFERENCE The Fuller property located in Timmins, Ontario contains historic underground mine production and underground exploration workings dating back to 1924 in the form of the 228 foot deep “Edwards Shaft” and a decline ramp to the 650 foot level dating from the 1980’s. Mr. Tom Meredith, President of VG Gold Corp., has secured the services of Vetrin Mine Planners Ltd. to complete a preliminary economic assessment for the mining of the Fuller Property’s resources. A mining resource estimate has been prepared by Mr. Peter Bevan, P.Eng., an independent consulting geologist. All information contained in this report was compiled and gathered by VG Gold Corp. from recent and past 43-101 compliant exploration drilling, and from past production data and studies completed by others. The Qualified Persons who contributed to this report include Mr. Peter Bevan, P.Eng., Mr. Rodney Doran P.Eng., and Mr. Ronald Moran P.Eng. All three individuals have visited the project site as recently as April 2007. The physical conditions of the project location were studied in order to locate the following; ore stockpile, waste stockpile and settling pond & surface plant locations. For the purpose of this study the ore will be trucked and milled via a custom milling agreement with a local mill facility. This study includes inferred mineral resources which are defined as being too speculative, to be counted on as having a positive economic impact on the project. VETRIN Mine Planners Ltd. 3.0 RELIANCE ON OTHER EXPERTS The authors of this Technical Report have reviewed and analyzed data provided by VG Gold Corp. and the technical team listed in Section 15.1 and have drawn their own conclusions therefrom, augmented by its direct field examination. Vetrin has not carried out any independent exploration work, drilled any holes or carried out any sampling and assaying. However, the presence of gold in the local rocks is substantiated by the previous exploration and historic development work completed on the property. The authors have relied upon the data presented by VG Gold Corp. and from the feasibility technical team in formulating its opinion, although all reasonable diligence in checking, confirming and validating data was exercised. Vetrin accepts in good faith that VG Gold Corp. and the members of the feasibility technical team, not working under Vetrin’s direct supervision, disclosed all relevant data during the development and preparation of the feasibility study. The various agreements under which VG Gold Corp. holds title to the mineral lands for this project have not been investigated or confirmed by Vetrin and Vetrin offers no opinion as to the validity of the mineral title claims. The description of the property, and ownership thereof, lease payments, royalties, etc. as set out in this report, are provided for general information purposes only. The description of the geology, mineralization, exploration and resource estimate included in the Preliminary Economic Assessment (PEA) study and this report are based on the NI 43-101 Technical Report completed by Wardrop in May of 2006 and referred to as “Mineral Resource Estimate of the Fuller Gold Property”. The location and volume calculations of the mining blocks used in this study were compiled by the author with the assistance of P. Bevan, P. Eng. All currency amounts are stated in Canadian dollars. Quantities are stated solely in Imperial Units, due to the historical and current database existing in Imperial Units, unless otherwise specified. Vetrin Mine Planners Ltd. is pleased to acknowledge the helpful cooperation of VG Gold Corp.’s management and the following consultants, Peter Bevan, P. Eng., Rodney Doran, P. Eng., and Ken Guy, P.Geo., all of whom made available and all data requested, and responded promptly, openly and helpfully to all questions, queries and requests for material. VETRIN Mine Planners Ltd. 4.0 PROJECT BACKROUND INFORMATION 4.1 Property Description and Location The Fuller property is located in the heart of the Timmins gold mining district, about three kilometres southeast of Timmins (Figure 4.1). A paved road to Timmins, locally referred to as the “Timmins Back Road”, crosses the northern part of the property. The dormant underground workings on the Fuller claim are accessible by gravel covered side-roads. The southeastern portion of the property is undeveloped, but there are roads within two kilometres of any point. There is an electrical power line to the Fuller underground workings, an old warehouse building and a small core shack building. Figure 4.1 Timmins Mining Camp Gold Production VETRIN Mine Planners Ltd. 4.1.2 Claims VG Gold holds 100% interest in the Fuller property. The Fuller property consists of 14 patented mining claims covering an area of about 207.22 hectares in Tisdale and Deloro Townships within the Porcupine Mining Division. The claims comprise parts of nine separate surveyed lots and five unsurveyed lots as shown in Figure 4.2 and Figure 4.3, and as outlined in Table 4.1. An inclined shaft excavated in 1920’s and a ramp-decline excavated in the 1980's are collared on a single patented claim, called the “Fuller claim” (P13189). VG Gold owns both the surface and mineral rights of the Fuller claim. The Fuller claim is the only claim that is not subject to net profits interest (NPI). Table 4.1 Claim List VETRIN Mine Planners Ltd. Figure 4.2 Fuller Property & VG Gold Corp. Adjoining Properties VETRIN Mine Planners Ltd. Figure 4.3 MNDM Land Tenure Map Fuller claim Dobie claim VETRIN Mine Planners Ltd. 5.0 GEOLOGICAL SETTING (The following material has been extracted by the author from the NI 43-101 report by Wardrop Engineering, dated May 3rd. 2006. This report can be read in full by downloading it from www.sedar.ca under VG Gold Corp’s May 5th. 2006 news release) 5.0.1 Regional Geology The geology of Tisdale Township and the northern part of Deloro Township is shown in Figure 5.1. The Timmins area is underlain principally by Archean-aged supracrustal rocks of the southern Abitibi greenstone belt. These rocks are subdivided into two major assemblages: the Deloro and Tisdale groups. The Deloro group, approximately 4,500 to 5,000 metres in thickness, consists of a lower volcanic formation of ultramafic rocks and diorite, a middle volcanic member of calc-alkaline basalt and andesite with minor pyroclastic rocks, and an upper volcanic member consisting mainly of calc-alkaline felsic pyroclastic rocks. Iron formation is common at or near the top of the sequence (Pyke, 1982). In the stratigraphic reassignment of Jackson and Fyon (1991), the “Deloro assemblage” consists only of the middle volcanic member, and the “Eldorado assemblage” consists of the upper volcanic member. The Tisdale group, estimated to be up to 7,000 metres thick, consists of a 300 to 3,000 metre thick lower volcanic formation of komatiitic and tholeiitic basalt flows, a middle volcanic formation of tholeiitic basalt, and an upper volcanic formation consisting dominantly of felsic calc-alkaline pyroclastic rocks (Pyke, 1982). Jackson and Fyon (1991) include only the lower two formations in the “Tisdale assemblage”, and the upper formation in the “Krist assemblage”. A roughly 3,000 metre thick sequence of clastic sedimentary rocks (turbidites), known as the Porcupine group was deposited from the time of the upper Deloro group through the period of deposition of the Tisdale group (Pyke, 1982). Jackson and Fyon (1991) have included in the “Porcupine assemblage” only those rocks within the Porcupine syncline. Intrusive rocks in the district include sill-like bodies of ultramafic rocks intruded into the Deloro group; they may be related to the overlying Tisdale group ultramafic volcanic rocks. There are many small epizonal quartz-feldspar porphyry intrusions in the Porcupine district. Pyke (1982) notes that many of them occur within a restricted stratigraphic interval, and they may therefore be subvolcanic intrusions or volcanic domes; they tend to coalesce at depth, however, suggesting a deep-seated intrusive origin (Jackson and Fyon, 1991). Most have been subjected to intense deformation. There is also a strong spatial and possible genetic link between gold mineralization and porphyries. There are northeast and north trending diabase dykes of early to late Precambrian age. VETRIN Mine Planners Ltd. Figure 5.1 Regional Geology (not to scale) VETRIN Mine Planners Ltd. 5.0.2 Regional Structures The Porcupine-Destor fault is a major structural zone, which can probably be traced for a total distance of 440 kilometres. It is at least 150 metres wide, shows evidence of left-lateral displacement, and is offset by younger, brittle faults. On the north side of the fault zone, there have been at least two periods of folding, consisting of a north trending series of folds and folds with an east-northeast axis such as the Porcupine syncline. Hattori and Hodgson (1991) have interpreted five periods of deformation; the Porcupine Destor fault zone and the Porcupine syncline are thought to be relatively old. 5.1 GEOLOGY of the PROPERTY 5.1.1 General Setting In the 1980's, VG Gold and Belmoral mapped the Fuller claim and immediately adjacent areas. Wardrop is unaware of any recent detailed mapping of the main areas of interest. The simplified geology of the Property is shown in Figure 5.2. The most recent mapping available is by the Ontario Department of Mines (Ferguson, 1959 a,b; Carlson, 1967; Ferguson and others, 1968). Geology mapping in Tisdale Township depicts the Property as being underlain by a generally eastwest trending assemblage of massive and pillowed mafic metavolcanic flows with minor variolitic flows. These have been traced onto the adjacent Placer Dome’s Paymaster mine and Dome mine properties to the east. To the west the units are traceable into complex fold structures; part of the package is believed to be folded to the south around the South Tisdale anticline, while the northerly part of the package appears to trend onto the Hollinger mine property (Ferguson and others, 1968). It has long been thought that the structure from the Edwards shaft to the Buffalo Ankerite south zone is dominated by an S-shaped fold pattern expressed by the contact between an assemblage of largely massive to pillowed metavolcanic flows on the west, and talc-chlorite schist (meta-ultramafic rocks) with lesser mafic volcanic rock to the east and south (see Figure 5.2). The mineralization on the VG Gold property occurs stratigraphically above what appears to be the contact between the older ultramafic lower formation and the basaltic middle formation of the Tisdale group. The area south of the Porcupine Destor fault is underlain by metasedimentary rocks (slate and argillite), rhyodacite and other metamorphosed felsic volcanic rocks (sericitic schist), mafic metavolcanic flows and agglomerate. The geology is best known in the immediate area of the Fuller deposit in and around the VG Gold ramp where the most thorough geological data has been collected in recent years. VETRIN Mine Planners Ltd. Figure 5.2 Property Geology (not to scale) VETRIN Mine Planners Ltd. The ramp was put down in the vicinity of a proposed hinge of an interpreted easterly plunging, local synclinal fold (the “Fuller syncline”). In a general south to north direction, the succession of rocks includes talc-chlorite schist (metamorphosed ultramafic rocks), quartzfeldspar porphyry, pillowed amygdaloidal basaltic flows, massive basaltic flows, and a series of alternating units of massive, pillowed and amygdaloidal volcanic rocks (see Figure 5.2). The porphyry is interpreted to have been intruded prior to folding. Hydro thermally altered volcanic rocks, including a strongly altered unit with more than 50% quartz flooding, green mica and pyrite mineralization, are spatially associated with the porphyry; there are also large folded zones of highly carbonate altered volcanic rocks in contact with the porphyry stocks. Although the concept of an easterly plunging local fold (the Fuller syncline) in the ramp area has been used since at least the early 1980's, there is some doubt regarding its validity. In the 1980's VG Gold interpreted a fold axis apparently plunging at 40 degrees (°) to 50° to the east, based on the north limb of the “syncline” dipping about 70° to the south (to a depth of about 500 feet in the vicinity of the Fuller deposit) and the western limb (around the “nose” of the fold) dipping about 50° to the east. It should be noted, however, that a dip of at least 62° (probably about 70°) is apparent in the Contact Zone through the Edwards shaft just north of the interpreted fold axis (see Figure 7.2). Drilling well west of the projected theoretical fold axis at depth (1,550 to 2,550 foot levels) has failed to identify any sign of a major fold within a few hundred feet of the Imperial shaft. There is little doubt that the north limb of the Fuller Deposit is broadly folded from a roughly east-west strike in its eastern portions, to roughly southwest in its western, presently delineated portions. The trend may eventually turn to the south and southeast, and be connected to the southeast trending limb of the large scale “S” fold on which the north and south workings of the Buffalo Ankerite deposit are located. The mineralization on the east-west trending north limb can be alternately interpreted to be offset by an as yet unidentified fault. At depth, below the VG Gold ramp-decline between the Buffalo Ankerite 1,550 foot and 2,550 foot levels, the north limb appears to dip steeply to the north. Older ultramafic units structurally overlie younger rocks in the area of the ramp-decline, suggesting that the stratigraphic sequence is overturned in upper levels. VETRIN Mine Planners Ltd. 5.1.2 Deposit Type The following section has been extracted from ACA Howe 2004 Report. Gold mineralization on the VG Gold property belongs to the structurally controlled Archean lode gold class of deposits. Structurally hosted, low-sulphide, lode gold vein systems in metamorphic terrains from around the world possess many characteristics in common, spatially and through time; they constitute a single class of epigenetic precious metal deposits, formed during accretionary tectonics or continental delamination. The observation that a large proportion of lode gold deposits in Archean cratons formed between 2.75 and 2.62 Ga (Barley et al., 1998) is instrumental in formulating a depositional model. However, the gold endowment of individual Late Archean granite-greenstone belts is highly variable. For example, most of Canada's world-class lode gold deposits occur within a small region of the 2.752.68-Ga Abitibi sub-province (Robert and Poulsen, 1997). Gold production from this area represents approximately 5,000 tons of the total 8,000 tons extracted from the entire Superior Province. In contrast, the dominantly Late Archean Wabigoon sub province lacks major gold deposits. Any deposit model must account for this apparent discrepancy. The majority of lode gold deposits formed proximal to regional terrain-boundary structures that acted as vertically extensive hydrothermal plumbing systems. Major mining camps are sited near deflections, strike slip or dilational jogs on the major structures. In detail, most deposits are situated in second or third order splays, or fault intersections that define domains of low mean stress and correspondingly high fluid fluxes. Accordingly, the mineralization and associated alteration is most intense in these flanking domains. The largest lode gold mining camps are in terrains that possess greenschist facies hydrothermal alteration assemblages developed in cyclic ductile to brittle deformation. Smaller deposits are present in amphibolite to granulite facies terrains characterized by amphibolite to granulite facies alteration assemblages, ductile shear zones, and ductilely deformed veins (McCuaig and Kerrich, 1998). In order to formulate a workable exploration model for this class of deposit it has been assumed that most, if not all, Archean lode gold deposits are fundamentally similar. Based on this premise, researchers and field geologists have assembled data from many individual deposits and mining camps into a composite depositional/genetic lode gold model. Inherent characteristics common to most lode gold deposits are their occurrence within regional scale linear composite shear systems, their apparently similar late Archean age, and their spatial association with a late Archean suite of felsic intrusions. Form and distribution of gold mineralization and associated wall rock alteration, however, show a high degree of variability from one deposit to another. Research during the past several decades has focused on understanding the fundamental characteristics of lode gold deposits and has therefore focused on topics such as the tectonic framework of the mineralizing systems, the relative and absolute age of gold emplacement, the tenor VETRIN Mine Planners Ltd. of mineralizing fluids, the interaction of ore-bearing fluids with host lithologies, and the nature of local structural controls on ground preparation and gold emplacement. Much of the basic data, both empirical and theoretical has come from deposits within the Canadian Superior Province and most specifically from those deposits in the Abitibi sub-province. Although the deposits of the district have been extensively studied, little consensus has emerged regarding several key points of district geology. In particular, the interrelationships among early mineralizing events, felsic porphyry emplacement, and formation of the exploited ores remain contentious. The Superior Province is the largest exposed Archean craton in the world, and has accounted for more gold production than any other Archean craton, with more than 55 million ounces produced to date. The Abitibi belt is the most prolific gold-producing greenstone terrain in the Superior Province: the Timmins (Porcupine) camp alone has contributed in excess of 51 million ounces of gold, far greater than production from the Kalgoorlie camp in Western Australia, or from the Homestake deposits in South Dakota. Characteristically the largest gold deposits of the district are spatially associated with, but not in, porphyries similar to those exposed at the Dome mine. This association has led to considerable speculation regarding the genetic relationship of felsic porphyry emplacement to ore formation. The results of a study on the various generations of gold mineralization in the Porcupine Camp by Gray (2001) indicates that although some gold was deposited during a copper goldmolybdenum (Cu-Au-Mo) event temporally linked to porphyry emplacement, most of the gold was emplaced significantly later than the porphyries. The documentation of at least three broad periods of gold emplacement, two of which were pre-metamorphic, is permissive and supportive of genetic hypotheses that invoke metamorphogenic remobilization of Au from earlier formed deposits. Lowsulfide quartz gold deposits of all ages constitute a coherent group in terms of geological characteristics, chemistry of ore-fluids, and occurrence in accretionary tectonic environments (Hodgson 1993). The origin of these deposits must be linked to convergent margin processes accompanying the generation of major volumes of syn- to post- tectonic felsic intrusions. The genesis of the ore fluids is more complex than a simple dewatering of oceanic crust and sediments. The evidence points toward deposit formation late in the evolution of a convergent continental margin. The origin of the fluid is complex. From the evidence, it can be concluded that the ore fluid is a product of deep crustal prograde metamorphism. Input of CO2 from the mantle is not necessary, and the field data speaks against this idea. The deposits are associated with deep transcrustal faults that are characterized by carbonation, thus implying that the primary fluid reservoirs are deep and large. Virtually all lode gold deposits are hosted in metamorphosed terrains, and this feature is arguably one of the most significant unifying characteristics. On this basis and from the structural style of the host terrains it can be argued that many lode gold provinces are an integral part of the development of high-temperature, low-pressure type subduction- accretion complexes. VETRIN Mine Planners Ltd. 5.1.3 Mineralization The following section has been extracted from ACA Howe 2004 Report. The bulk of the more than 60 million ounces of gold production in the Porcupine district in the Timmins area has been from well-known deposits in Tisdale Township north of the PorcupineDestor fault zone. These include the producing Dome Mine (more than 12 million ounces) and the past-producing Hollinger (19.35 million ounces), McIntyre (10.36 million ounces), Coniaurum (1.11 million ounces), Paymaster (1.19 million ounces) and Preston East Dome mines (1.54 million ounces). In the northern part of Deloro Township are the former Buffalo Ankerite (1.0 million ounces), Aunor (2.5 million ounces) and Delnite (0.92 million ounces) mines, as well as one of the Paymaster shafts on the Placer Dome property. Most of the production has been from deposits, which occur within or immediately adjacent to the Tisdale group. The average historical underground-recovered grade of Timmins area deposits has been about 0.25 oz/t Au. The Dome mine is currently producing from an open pit (the “superpit”) at a grade of about 0.07 oz/t Au, as well as underground operations at a grade of about 0.13 oz/t Au. Within the district, gold mineralization occurs as quartz-carbonate vein (lode) type and as sulphiderich zones (disseminated-type). A common feature of all gold deposits is carbonate-rich rocks (Karvinen, 1982). Most of the lode-type mineralization occurs in and adjacent to shear-hosted quartz veins or small veins associated with fold closures. Mineralized veins are associated with alteration zones consisting of chlorite, dolomite, ankerite, sericite and green mica. Stock work stringers and veins occurring within or at the margins of porphyry bodies have comprised a relatively small but locally important source of gold ore (Jackson and Fyon, 1991), such as at the Preston East Dome mine (Hawley and Hart, 1948) and the #2 and #3 shaft area on the Paymaster property (Longley and Lazier, 1948). Disseminated type mineralization is exemplified by the Bell Creek deposit in Hoyle Township. Copper and molybdenum were also produced from a disseminated sulphide and veinlets ore body in the Pearl Lake porphyry intrusion within the McIntyre mine property. Mineralization consists of the native element and in fine-grained pyrite, concentrated along sericitic wall rock selvages. There are other sulfides in ore mineralization, but pyrite dominates; tellurides are uncommon. The gold:silver ratio in the district varies from 1:6 to 1:10. VETRIN Mine Planners Ltd. 6.0 EXPLORATION DRILLING (The following material has been extracted by the author from the NI 43-101 report by Wardrop Engineering, dated May 3rd. 2006. This report can be read in full by downloading it from www.sedar.ca under VG Gold Corp’s May 5th. 2006 news release) 6.1 Historical Drilling The current VG Gold property has a long history of exploration and limited gold production. Since 1910, periodic surface exploration, underground and limited production has been carried out on the Fuller deposit on the Fuller claim. A 228-foot inclined shaft (the “Edwards shaft”), was sunk some time after 1924. In 1940-1941 Nakhodas Mining Company Limited (“Nakhodas”) developed 2,100 feet of lateral workings at the 160 foot level, and mined 44,028 tons grading 0.149 oz/t Au (recovered) above the level in four stopes. The rock was processed in the Faymar mill in Deloro Township (Ferguson, 1968). The mill was destroyed by fire in 1942, and was not rebuilt. In addition to 83 underground drill holes, Nakhodas also drilled at least 10,919 feet of surface drilling in 41 drill holes (S 1 to S41). In the late 1930's, Hollinger Consolidated Gold Mines conducted a 14,000 foot drilling program in 25 holes on the claims in Tisdale Township, previously referred to as the “Tisdale Ankerite claims” (Ferguson and others, 1968). Drilling was also done by Pamour (Noranda Explorations Ltd.) in 1974 to 1976. One of these drill holes deviated onto the (then) single VG Gold claim, and intersected three well-mineralized zones at a depth of about 500 feet, encouraging VG Gold to drill beneath the 160 foot level (Vedron, 1979). In 1985, VG Gold consolidated the Fuller and Dobie claim, which together hosts the Fuller property. Exploration work from 1986 to 1989 focused on the area of the synclinal structure previously mined from the inclined Edwards shaft. Exploration conducted by VG Gold on the Fuller property was a 1996-98, multi-phase drilling program. The initial phases of the program began on July 22, 1997 and were completed on March 25, 1998. During this program holes VG 97-64 through VG 98-78 were completed producing a total of 20,993 feet of BQ drill core in 15 holes. An additional phase of drilling was completed during November 1998. Holes VG 98-79 through VG 98-83 were completed during this phase generating a total of 3,164 feet of BQ drill core in five holes. The purpose of the overall program was twofold: i) to locate and define the on-strike and down dip continuation of the gold bearing horizons within the Fuller deposit between 1,600 feet and 2,500 feet below surface, and ii) to investigate the probability of additional gold zones proximal to the VG VETRIN Mine Planners Ltd. Gold underground workings as well as confirm the wide mineralized zone intersected along the south limb- 375 foot level where pervasive gold values were detected in drifting and in bazooka holes. Following their optioning of the property in 2001, Placer Dome carried out both field exploration and office database management activities on the Fuller property including the VG Gold’s North target area and the Paymaster 31 Zone Extension in the main Fuller area. The following is a summary of the 2002 exploration activities conducted by Placer Dome (CLA) Limited - Dome Mine and the Porcupine Joint Venture on the Vedron (now VG Gold) property option in 2002. All the underground and surface diamond drill hole logs available from the Fuller deposit were recoded to Dome Mine terminology, which includes lithology, assays, alteration, percent sulphides and percent veining. The down hole surveys and X, Y, Z drill hole collar co-ordinates for these holes were converted to the Dome Mine co-ordinate system. Validation of the drill holes was checked from plots including the Fuller-Dobie level plans. The diamond drill hole database was created in Access and imported into Vulcan for 3-D modeling. Initial field activities in early 2002 involved a surface diamond-drilling program on the North VG Gold target. The four holes, 2,050.4 metre (6,727 foot) drill program was carried out between January 16th and February 19th, 2002. It was designed to test along the highly prospective Central and Vipond Series contact for gold mineralization, focusing on the strong sericite/ankerite alteration, increased pyrite content and coincident gravity high anomaly in the hanging wall of the contact zone. The North VG Gold target geology is the structurally controlled North VG Gold Shear and the “Paymaster 18 Vein Shear” between the Central and Vipond series mafic volcanic units. The Paymaster 31 Zone Extension surface diamond drill program was carried out on the VG Gold portion of the South Tisdale Anticline (“STA”) project between April 7th and May 10th, 2002. The five hole, 2,032.7 metre (6,669.0 foot) drill program was designed to test: i) a porphyry trend with associated gold values intersected in hole VG98-82, and ii) the western strike projection of the 31 Vein structure on 150 m (500 ft) step-outs between –3500E and – 4500E (Dome co-ordinates). Holes were also designed to test the up-plunge potential of the porphyry trend defined by underground exploration on the Paymaster 2575 (Dome 3493 elevation) and 4075 levels (Dome 2007 elevation). Eight core samples from the 31 Zone, along with selective geochemical data, were submitted for petrographic analysis, gold mineralogy and interpretation. 6.2 1998 - 2007 EXPLORATION During 2006 and 2007, VG Gold drilled 11 drill holes targeting the Fuller zones plus, a Buffalo VETRIN Mine Planners Ltd. Ankerite deep hole which was collar on the Fuller property, with the following results. 6.2.1 Fuller Green Carb Zone Five holes, totaling 937 metres, were drilled to test for extensions of the Green Carb Zones 1 and 2 of the Vedron Fuller deposit. The drill holes tested for extensions of the Green Carb zone within 50 metres of the existing ramp and underground workings, 50 to 100 metres along strike from historic green carb zone intersects. Every hole intersected gold mineralization within or adjacent to the fuchsite and ankerite altered Quartz Feldspar porphyry, host rock to the Fuller Green Carb zone mineralization. Assays include 9.22 grams Au per tonne over 1.22 metres within a wider zone of 3.17 grams Au per tonne over 9.14 metres including 5.08 grams Au per tonne over 4.88 metres – hole VG-06-99 and 10.32 grams Au per tonne over 0.98 metres – hole VG-06-102. 6.2.2 Fuller North Four holes, totaling 1,243 metres, were drilled to test for new mineralized zones to the north of the Fuller deposit and the known mineralization on the Vedron property. The drill holes tested for strike extensions of known mineralization and historic mining on the Goldcorp/Kinross PJV owned Paymaster property to the east. The holes intersected wide widths of favourable alteration and mineralization, but gold values were low, 1.6 grams Au per tonne over 3.2 metres including 3.43 grams Au per tonne over 1.19 metres – hole VG0696. Historic underground drilling between 300 metres deep and 1,500 metres deep near the east boundary with the Paymaster property had intersected values over 30 grams Au per tonne. The shallow Vedron drilling reported here failed to repeat the high grade assays but was successful in intersecting wide zones of alteration and mineralization with anomalous gold at shallow depths. 6.2.3 Fuller ML Zone Two holes, 358 metres were drilled to test for extensions of the ML Zone of the Vedron Fuller deposit. The ML zone has not been included in the 43-101 compliant resource of the Fuller deposit. The ML zone likely represents the extension of the more extensively drilled Green Carb Zones that are located on the east side of the fold from the Fuller deposit underground workings. Exploration data is very sparse on the western extensions of the Fuller deposit situated on the west side of the fold. Historic interpretation of the Fuller deposit was that of a single fold, however evidence existed that in fact the Fuller deposit was an “S” fold with the stratigraphy and mineralization extending to the west rather than trending southeast. Earlier exploration had just begun to confirm this. Drill Holes VG-06- 104 and 105 confirmed the existence of the Fuller zones with wide intersections of fuchsite ankerite alteration corresponding to the extension of the Green Carb 1 and 2 Zones. Near surface assays include 2.08 grams Au per VETRIN Mine Planners Ltd. tonne over 4.54 metres and 3.09 grams Au per tonne over 3.51 metres. 6.2.4 Hole VG-07-106 This was a deep hole collared north of the Fuller zone, targeted on a postulated depth extension of the Buffalo Ankerite South zone at a depth of 3500 to 4000 feet below surface. The hole passed below and to the east of the Fuller fold nose and therefore did not intersect the Fuller stratigraphic package. 6.3 Vedron Drilling 2004 In the summer of 2004, VG Gold completed a total of seven diamond drill holes, totaling 4356.4 feet. The purpose of the program was to test some of the targets recommended in the 2004 ACA Howe technical report, including the east Paymaster boundary area and the south to southeast extension of Contact Zone mineralization on the south limb of the “Fuller syncline” towards the Buffalo Ankerite 5 shaft area. Assay results, in general, were mixed. Several mineralized /carbonate altered zones were intersected, but gold assay results associated with these altered zones were predominantly not anomalous. The best assays returned included: from VG04-90 (east property boundary area), 0.036 ounces per ton Au/5.3 feet at 681.7 feet, 0.031 ounces per ton/7.1 feet at 714.9 feet, and 0.103 ounces per ton/1.5 feet at 744.1 feet; from VG04-92 (infill drill hole testing contact zone), 0.134 ounces per ton/7.9 feet including 0.348 ounces per ton/1.3 feet at 966.7 feet and 0.084 ounces per ton/5.3 feet at 983.1 feet. 6.4 Placer Dome Drilling 2002 The North VG Gold surface diamond drill program was carried out between January 16th and February 19th , 2002. The four holes, 2,050.4 metre (6,727 foot) drill program was designed to test along the highly prospective Central and Vipond Series contact for gold mineralization, focusing on the strong sericite/ankerite alteration, increased pyrite content and a coincident gravity high anomaly in the hanging wall of the contact zone. According to the interpretation of Placer Dome the general geology in the VG Gold North area consists of east west trending Tisdale Group rocks of the “Vipond and Central Series”. This is a sequence of Fe-rich tholeiitic massive, pillowed and amygdaloidal flows. All units are sub-vertical to steeply dipping to the north. Felsic to intermediate porphyries and late northwest trending diabase dykes intrude the rocks. The North VG Gold target geology is the structurally controlled North VG Gold Shear and the “Paymaster 18 Vein Shear” between the Central and Vipond series mafic volcanic units. The Vipond Series mafic volcanic units, which form the hanging wall, are strongly sericite-ankerite altered with elevated pyrite content. The strongest alteration in this area has an associated gravity high anomaly. Historical drilling has located gold intercepts along the contact of 193 grams per tonne gold over 0.2 metres, to the west and 8.6 grams per tonne gold over 0.2 metres; 6.9 grams per tonne gold over 0.4 metres to the east. VETRIN Mine Planners Ltd. The Paymaster 31 Zone Extension surface diamond drill program was carried out on the VG Gold portion of the South Tisdale Anticline project between April 7th, and May 10th, 2002. The five hole, 2,032.7 metre (6,669.0 foot) drill program was designed to test: 1) a porphyry trend with associated gold values intersected in hole VG98-82, and 2) the western strike projection of the 31 Vein structure on 150 metre (500 foot) step-outs between -3500E and - 4500E (Dome co-ordinates). Holes were also designed to test the up-plunge potential of the porphyry trend defined by underground exploration on the Paymaster 2575 and 4075 levels. The drill program intersected a number of wide intervals of encouraging 31 Zone style alteration and sulphide mineralization, but only scattered gold values in the 1.7 to 3.4 grams per tonne gold range were returned. Eight core samples from the 31 Zone, along with selective geochemical data, were submitted for petrographic analysis, gold mineralogy and interpretation. According to Placer Dome (Gliddon, 2003) the petrography and geochemistry are interpreted to suggest gold mineralization on the projected trend of the 31 Zone structure on the Vedron property has syn-volcanic and lode gold characteristics (low gold/silver ratios <1, high base metals – copper, lead, zinc, high arsenic, potassium metasomatism and sodium depletion), whereas the Simpson Lake (along trend to the east on Placer Dome property) samples have lode gold characteristics with intense deformation, carbonate-sericitetourmaline alteration, K metasomatism, gold/silver ratios between 1 and 10 (average 5) and low base metals (copper, lead, zinc). 6.5 Holes VG-07-107 to 110 Four holes were targeted to follow up on 2 holes drilled in 1988, testing the south west edge of the ultramafic, between the Buffalo Ankerite North zone and the Fuller deposit. Historic holes S88-118 and 119 had intersected gold values in this gap between the 2 mineralized zones. Hole S88-119 intersected 0.11opt/10 ft, and S88-118 returned values of 0.10opt/3.6 ft, as well anomalous gold assays. Four holes, 3286.3 feet, were drilled to follow up on historic results and to test the gap area. Results were negative with no significant assays. 6.5 1996 to 1998 Program In 1996 VG Gold (then called Vedron Gold) completed the Phase 1 diamond drill program on the property. A total of 105,772 feet of BQ diamond drill core were completed in 63 holes: VG96-01 to VG96-63. Kuehnbaum (1997) recommended in his report, following the historical resource estimate by Bevan (1997), that additional drilling be conducted on main Fuller deposit area and high priority adjacent targets. The purpose was to locate and define the on-strike and down dip continuation of the gold bearing horizons within the Fuller deposit between 1,600 feet and 2,500 feet below surface. VETRIN Mine Planners Ltd. VG Gold acted on the recommendations and instigated a result driven, multi-phase drill coring program on July 22nd, 1997 consisting of holes spaced about 400 feet apart, horizontally, on three tiers at the 1,800 foot, 2,100 foot and 2,500 foot levels. This phase of the program was completed in late October 1997. This program was successful in defining additional mineralization on the Fuller below the 1600 foot level. The second phase of the drilling program began on March 17th, 1998 and was completed on March 25, 1998. A total of 4,000 feet of BQ drill core was obtained in seven holes (VG 98- 72 to VG 9878). This phase of drilling was specifically designed to investigate the probability of additional gold zones proximal to the Fuller underground workings as well as confirm the wide mineralized zone intersected along the south limb -375 foot level where pervasive gold values were detected in drifting and in bazooka (compressed air short-hole [30-90 metres] drill rig) holes. A final phase of near surface drilling totaling 3,164 feet of BQ drill core in 6 holes (VG 98- 79 to VG 98-83) was completed during November 1998. This drilling was successful in establishing the continuation of mineralization near to surface. VETRIN Mine Planners Ltd. 7.0 ASSAY QUALITY CONTROL (The following material has been extracted by the author from the NI 43-101 report by Wardrop Engineering, dated May 3rd. 2006. This report can be read in full by downloading it from www.sedar.ca under VG Gold Corp’s May 5th. 2006 news release) 7.0.1 Sampling Method and Approach Ken Lapierre, VG Gold’s Contract Geologist, was in charge of exploration during the 1996-98 drill campaign. Sampling procedures and protocols as well as a Quality Assurance/Quality Control (QA/QC) were not described and/or documented in detail in previous internal VG Gold reports or memoranda. However, upon further review of the original Fuller drill logs, it is reported in the Howe report that they have reconstructed the sampling procedures and protocols utilized by VG Gold during the 1997-98 drill programs. The sampling procedures and protocols are described below. Upon the completion of the geological core logging of a diamond drill hole, VG Gold’s geologist then identified the section(s) of core that would be sampled and analyzed for gold. Once the mineralized sections for sampling were identified, VG Gold’s geologist would measure and mark out the sample intervals onto the uncut core and record the individual sample intervals onto the geological log sheet. All of the drill core sections were sampled according to lithological and/or alteration boundaries and vein(s) width. However, the maximum sample interval did not exceed 5.0 feet in length. The sections of core to be sampled were split, half-core sampled for assay and the remainder was then stored in core boxes. All of the sections of sampled core were cut using a manual core splitter. 7.0.2 Sampling Method and Procedures for the 2004 and 2006-2007 Drill Program In 2004, the procedure was similar to the one in 1996-98. The drilling crew delivered the sealed core boxes to the core shack at Fuller site. The boxes were opened by VG Gold Geologist Blair Needham. The core was logged and sampled by Blair. The samples were shipped for analysis to Expert Laboratory in Rouyn Noranda, Quebec. In 2006-2007 VG Gold used similar sampling methods and procedures as outlined previously. 7.0.2 Sample Preparation, Analyses and Security In preparing samples for cutting/shipping, the geologist along with core technician both play a crucial role in the quality control of samples submitted for assays. A double check is conducted by comparing the sample tags with those identified by the geologist and any discrepancies are found before samples are sent to the laboratory. VETRIN Mine Planners Ltd. During VG Gold’s 1997-98 drill program the sample preparation and analytical work was carried by Swastika Labs of Kirkland Lake, Ontario. Samples collected from VG Gold drill holes VG97 and VG98 were shipped to Swastika for analysis. All of the core samples were crushed to 70% -2 millimetres (mm) and 250 grams (g) were then collected, pulverized to 85% < 75 microns (µm) in a ring mill. The pulverized sample was then split utilizing a riffle splitter. After each sample was crushed and pulverized, both the jaw crusher and ring mill were then “washed” with a blank quartz wash in order to avoid sample contamination/smearing. Each sample was analyzed for gold using a one ton (30 g) fire assay with an AAS finish. The Swastika one assay ton (30 g) fire assay/Atomic Absorption Spectroscopy (AAS) method has a lower detection limit of 0.003 opt Au. Swastika routinely ran random check assays for each sample batch. However, when the lab was notified of possible samples containing high values of gold for the core samples, Swastika carried out a fire assay/AAS method (with repeat in places) as well as fire assay/gravimetric analysis for samples > 0.50 oz/t Au. Swastika did not provide VG Gold with its internal QA/QC data during the analysis period. During VG Gold’s 2004 drill program the sample preparation and analytical work was carried by Expert Laboratories of Rouyn Noranda, Quebec. A copy of the “Certificate of Laboratory Proficiency” and assay results employed by the laboratory is included in Appendix B of this report. Wardrop recommends that VG Gold incorporate a QA/QC program in future drilling using blind duplicates, blanks and standards. 7.0.3 Data Verification Shahé Naccashian, Wardrop’s Geologist visited the Fuller Property site from April 18th, to April 20th, 2006. This visit is intended to fulfill the NI 43-101 requirement of a site visit by the Qualified Person for the May 2006 report. At the site, Shahé was accompanied by VG Gold’s Consulting Geologist, Ken Guy. 7.0.4 Assays Wardrop carried out an internal validation from the original drill hole logs and the drill hole database on 45 (5%) of the 880 drill holes in the total database. Data verification was completed on collar coordinates, end of hole depth, down-the-hole survey measurements, from and to footage measurements of geology and assay sampling intervals, lithological unit and gold grades that were compiled from hand written drill logs into an ACCESS database. Most errors were insignificant and related to mistakes in transcription. Details of the verification are set out in Table 14.1. The digitizing of drawings and maps were validated on an on-going basis, with information being visually checked while importing the digitized areas to Gemcom geological software. The data verification had less than 1% of errors. VETRIN Mine Planners Ltd. 7.0.5 Core Review At Fuller site, VG Gold has a core shack building. All the mineralized zones are stored inside this building. Almost all of the split core of VG96, VG97, VG98 and VG04 mineralized sections are preserved. The building is secured and padlocked by VG Gold. The remainder of the core is crosspiled outside on palettes. The labels on the core boxes are deteriorating. Wardrop recommends that VG Gold go through the core and label all the boxes. Wardrop carried out a geological core review on lithology, mineralization and sampling, checking against drill logs on the following drill holes: VG04-90, VG04-91, VG04-92, VG04-93, and VG0494. In addition to the five drill holes from the 2004 drill campaign, Wardrop checked mineralized sections of holes: VETRIN Mine Planners Ltd. 8.0 MINERAL PROCESSING 8.0.1 Historic Mill Recoveries In the early 1940’s, mineral processing and metallurgical testing was completed during the mine operation by Nakhodas Mining Company. This information is not available for review by Wardrop. At the time of this report VG Gold Corp. has not pursued any metallurgical testing on the Fuller Zones. A study dated June 2007 of an adjoining property, titled “Preliminary Economic Assessment of the Buffalo Ankerite South Zone”, published historic milling data in Section 8 of the report. The historic milling data suggests a recovery in the 92% range, using the Merrill Crowe system, was achieved. This recovery rate is an accepted target in today’s mining industry and for the purpose of this economic model a gold recovery rate of 92% has been used. A potential custom milling source is a Merrill Crowe mill built in the late 1980’s. VETRIN Mine Planners Ltd. 9.0 FULLER PROJECT – MINING RESOURCES ESTIMATE Section 17 of the Wardrop 43-101 report for the Fuller property; details the various calculation methods, modeling parameters, and validation procedures used to calculate the mineral resources on the Fuller property. The data in Table 9.1 summarizes the “Wardrop 43-101” calculation of the indicated and inferred resources using a .075 ounce per ton cut off grade. Table 9.1 Undiluted Resource Estimate @ .075 oz cut off Indicated Resources: 1,533,489 tons grading 0.162 oz. Au/ton Containing 248,000 oz. gold Inferred Resources: 1,813,065 tons grading 0.165 oz. Au/ton Containing 299,960 oz. gold 3,346,554 tons grading 0.163 oz. Au/ton Containing 547,960 oz. gold Total : The author reviewed the resource data compiled within the NI 43-101 report and with the assistance of Peter Bevan, P. Eng, developed tonnages and grades for mining blocks above the 950’ Level elevation. The mining blocks, also referred to as stope limits, were identified using the following criteria: - Include ore polygons that exceeded 0.100 oz. in grade over a minimum true width of 4 ft. Join polygons that follow historic plunge directions of the ore shoots. Sub-divide the ore shoots into practical mining block sizes in order to create a consistent mill feed. The spacing of the 4 existing levels also influenced the vertical stope limits. These mining blocks became the bases for the development and production plan outlined in Section 11 and drove the mining cost estimates also contained in Section 11. Figures 9.1 and 9.2 illustrate the stope block limits developed to the 650’ level for the CZ and HW zones. These stope block volumes are summarized, along with 4 other “secondary” mineralized zones, in Table 9.2 using a mining dilution factor of 15 % applied to the final calculations. VETRIN Mine Planners Ltd. Table 9.2 VG Gold Corp. - Fuller Project - Mining Resources Stope Block Tons & Grade Summary above the 950 Level Contact Zone Hanging Wall Zone Secondary Zones Contact Zone - 650 Level to Surface Hanging Wall Zone - 650 Level to Surface Indicated Secondary Zones - 950 Level to Surface Indicated tons 321 Stope 351 Stope 361 Stope 102 Stope 103 Stope 15% diluted tons & grade 36,691 14,377 24,453 45,316 72,918 grade contained ounces 0.218 0.260 0.199 0.139 0.163 8,000 3,744 4,876 6,304 11,899 sub-total 193,755 0.292 222,818 0.156 34,823 34,823 Contact Zone - 800 Level to 650 Level tons 321 Stope 351 Stope 361 Stope 401 Stope 281 Stope 341 Stope 15% diluted tons & grade 14,658 1,001 10,442 49,385 10,533 11,086 sub-total 97,105 0.292 111,671 0.254 28,393 28,393 Contact Zone - 950 Level to 800 Level 15% diluted tons & grade 15% diluted tons & grade grade contained ounces 3,884 145 3,080 15,754 4,276 1,253 tons 320 Stope 350 Stope 360 Stope 320 HW #1 320 HW #2 South Limb of HW **** 650 - 275 Level 320 Stope 350 Stope 360 Stope 176,666 203,166 0.194 39,423 39,423 9,141 19,323 8,929 As per Wardrop Block Model As per Wardrop Block Model As per Wardrop Block Model 15% diluted tons & grade sub-total 37,393 43,002 0.207 0.180 F1 GC1 CZ1 INT 15% diluted tons & grade 6,660 5,970 107,279 43,446 diluted grade contained ounces 0.179 0.329 0.143 0.153 1,192 1,964 15,341 6,647 163,355 187,858 0.134 25,144 25,144 6,660 5,970 36,013 38,314 0.179 0.329 0.152 0.173 1,192 1,964 5,474 6,628 86,957 100,000 0.153 15,258 15,258 By Selective Mining Assume grade contained ounces 0.326 0.182 0.140 As per Wardrop Block Model 2,980 3,517 1,250 100 % of F1 100 % of GC1 33 % of CZ1 100 % of INT 15% diluted tons & grade grade contained ounces 0.301 0.336 0.155 0.209 0.443 5,632 5,297 1,482 129 3,171 sub-total 51,814 59,586 0.303 0.264 15,711 15,711 tons 320 Stope 350 Stope 360 Stope 15% diluted tons & grade 7,747 7,747 grade contained ounces 32,395 29,076 11,726 0.366 0.433 0.160 11,857 12,590 1,876 sub-total 73,197 84,177 0.360 0.313 26,323 26,323 diluted-short diluted grade contained ounces 394,075 0.200 12,518 5,950 9,339 1,720 1,141 8,755 tons diluted-short diluted Total CZ above 950 Level 0.221 0.160 0.219 0.187 0.156 0.206 tons Hanging Wall Zone - 950 Haulage Level to 800 Level 18,711 15,764 9,563 618 7,158 tons 49,269 32,426 37,140 8,000 7,331 42,500 grade contained ounces Hanging Wall Zone - 800 to 650 Level 0.265 0.145 0.295 0.319 0.406 0.113 321 Stope 401 Stope 361 Stope 281 Stope 341 Stope tons 78,927 tons Total HW above 950 Level diluted-short diluted grade contained ounces 330,345 0.222 73,492 Total Secondary Zones above 950 Level **** from Wardrop Block Model tons grade contained ounces 100,000 0.153 15,258 diluted-short diluted tons grade contained ounces Total Mining Resource 824,420 0.203 167,678 VETRIN Mine Planners Ltd. Figure 9.1 Long Section to the 650 Level showing the North Limb of the Hanging Wall Zone (HW) Undiluted Mining Block Tonnage & Grades 375-360 Stope Block 30,976 tons @ .276 650-360 Stope Block 5,329 tons @ .148 650-320 Stope Block 49,269 tons @ .221 650-350 Stope Block 32,426 tons @ .160 VETRIN Mine Planners Ltd. Figure 9.2 Long Section to the 650 Level showing the North Limb of the Contact Zone (CZ) Undiluted Mining Block Tonnage & Grade 375-361 Stope Block 14,128 tons @ .193 375-321 Stope Block 10,515 tons @ .187 500-321 Stope Block 6,370 tons @ .180 650-321 Stope Block 18,979 tons @ .258 650-351 Stope Block 14,377 tons @ .260 650-361 Stope Block 9,775 tons @ .213 VETRIN Mine Planners Ltd. 10.0 PERMITTING, SOCIAL CONSULTATION AND ENVIRONMENTAL COMPLIANCE 10.0.1 Overview and Approach The permitting, social consultation and environmental compliance are some of the risk factors of any project. The following sections outline some of the environmental and social considerations for the Fuller Mine. Permitting requirements and potential risks associated with the permitting and social consultation for this project are identified. The location of the project and the extent of the nine patented mining claims that comprise the Fuller Mine project are illustrated in the following drawing: VETRIN Mine Planners Ltd. 10.0.2 Environmental Baseline Studies The Fuller Mine project is located within the boundaries of the City of Timmins and adjacent to a residential housing cluster of approximately twenty-six homes. One of the homes, the original Mine Manager’s home is located on Cook Road some 210 metres from the Fuller Mine Portal. The mine site location is classified as AW (Agricultural Wilderness) by the City planning department. The residences located along Cook Road, Gold Mine Road and Ankerite Road are classified as Residential. The mine is accessed from Gold Mine Road that joins Timmins and South Porcupine. A secondary gated access that is only used infrequently is located off of Cook Road. Access to the mine site is gained by a single lane approximately 800 metre long gravel road that joins Gold Mine Road adjacent to the paved entrance to the Buffalo Ankerite property via Shaw Creek Road. The average annual temperature at the site is 1.3 degrees C with average extremes ranging from minus 17.3C in January to a high of plus 17.3 C in July. The total annual precipitation is in the order of 839 mm with approximately 68 percent of the precipitation as rain. The project is located within the southern limit of the Boreal – Predominantly Forest Region of Canada. The principal tree species in this area include white and black spruce, balsam fir, jack pine, white birch and trembling aspen. Tree species composition will vary according to soil types and topographic position. Large wildlife species include bear, moose and wolf. Various fish species are present in lakes and streams in the area including northern pike, walleye, small mouth bass and non-sport fish. A cursory aquatic environmental baseline study was completed in late 2006 by B. Z. Environmental Consulting of Timmins, Ontario. This study provides the basis for the environmental considerations in the permitting that will be filed for the mine including the Ministry of Environment’s Certificate of Approval for the mine water discharge and the Ministry of Northern Development and Mines’ Closure Plan. During negotiations with government regulators regarding effluent limits and discharge points we have learned there is a possibility that additional background studies including the determination of resident fish populations will be required. 10.1 SOCIAL BASELINE STUDIES 10.1.1 First Nations Meaningful communication and consultation with First Nations are essential elements to develop and operate a mine in Ontario. It has been determined that three native groups may have an interest in the Buffalo Ankerite project. These groups include the Mattagami, Matachewan and Wahgoshig First Nations. Letters detailing the project plans were sent out to all of the listed groups providing a 30 day notification of interest period. Following no apparent interest in the project follow up telephone calls were made that discovered that all groups were interested in learning more about the project. Formal consultation was held with all of the groups at which time support for the project was asked in the form of a letter of support in VETRIN Mine Planners Ltd. return for the offer of employment opportunities for qualified personnel. To date no letters of support have been received. 10.1.2 Archaeology and Heritage Resources Mining activities and site disturbances at the Fuller Mine took place during the early part of the twentieth century and again in the 1980’s when the mine was converted to a trackless operation. Since the Fuller Mine project will be a continuation of previous underground mining activities, it is not expected that future activities will significantly alter the existing disturbed mining footprint or further disturb the land surface. These facts together with the geographical (not close to a navigable waterway) and insignificant topographic features of the mine location (not a height of land) lead us to conclude that an archaeological or heritage investigation would not be required. 10.1.3 Socio-economics The project is located within the City of Timmins Limits, population 43,000. The Fuller Mine is located south of Schumacher, east of Timmins proper and southwest of South Porcupine. Approximately twenty-six home owners are located in the old Fuller Mine town site (locally known as McDonald Hill), located on the north side of Gold Mine Road. Two homes on Cook Road, one being the old Mine Managers’ residence are situated more than two hundred metres from the existing mine portal. The closest homes located along Gold Mine Road and along Ankerite Road are all more than 300 metres from the mine portal. Section 3.2.3 of the City of Timmins official plan (January 1998) states that mining activities are prohibited within 150 metres of any residence, cottage, lodge, other human habitation, public park or commercial intensive or linear recreational facility. A draft of the new proposed Official Plan – City of Timmins adopts the separation distances established by the Ontario Ministry of the Environment (MOE) Guidelines. The current MOE minimum separation distance for mining activities is now one thousand (1000) metres. If the closest point of reception (i.e. a residence) is closer than the minimum required separation distance further assessment is required. Therefore in the case of the Fuller Mine additional site specific assessment requirements apply which will include an acoustic assessment report and a vibration assessment report. There is a risk associated with these additional assessments in that the required mitigating measures may be costly and in the worst case the application may be refused. Based on public meetings and correspondence with local residents there is local concern with noise, vibration and visibility of this project. Some active resistance to the advancement of this project based on these concerns is a possibility. Timmins is a mining community with more than ten operating and historic mines located within the city boundaries. The general public recognizes the present and past mining activity and is generally receptive to new mining activity. There is a risk that the residents in the area may view the project VETRIN Mine Planners Ltd. and its associated effects as an infringement on their quality of life and a threat to their property values. A plan to address the mitigation of known resident’s concerns is being developed. Due to the proximity of the proposed mine to the residences, blasting times and the hours of ore and waste hauling may be restricted. 10.2 CONSULTATION AND PERMITTING 10.2.1 Consultation An inter-ministerial meeting, as required under the Mining Act was held jointly for both the Fuller and Davidson Tisdale Mines. This meeting was attended by government representatives of all Provincial and Municipal agencies having an interest in the development of these mines. A public meeting, as required under the Mining Act was jointly held for both the Fuller and Davidson Tisdale Mines. In addition residence concerns were aired at a pubic meeting that was held primarily for the Buffalo Ankerite project. A citizen’s liaison committee for the Fuller Mine has been established and correspondence has been exchanged addressing their concerns. This consultation process is ongoing in an effort to alleviate the expressed level of concern. 10.2.2 Permitting The environmental approval and permitting process under the Ontario Environmental Protection Act and the Ontario Water Resources Act is the critical path in obtaining permits for the operation of the Buffalo Ankerite project. The Ontario Mining Act requires that the company submit a certified Closure Plan along with adequate financial assurance to complete closure activities to legislated standards. According to legislation certified Closure Plans are filed (approved) within 45 day of submission however, plans judged to be incomplete are returned to the Company and must be resubmitted, subject to the standard timelines of 45 days, upon completion of the revisions. No mining may proceed without receipt of notice that the submitted Closure Plan has been filed. Any potential for fish habitat alteration or destruction from the Fuller project will be assessed by the Department of Fisheries and Oceans under provisions of the Federal Fisheries Act. Since the property is located within the boundaries of the City of Timmins the city noise bylaw will apply to mining activities such as drilling, blasting, crushing and hauling. VETRIN Mine Planners Ltd. Any building construction on site will require a Building Permit issued by the City of Timmins. The City of Timmins will not issue a building permit until a Mine Closure Plan for the proposed open pit has been filed (approved) by the Director of Mine Rehabilitation. We anticipate that the ongoing permitting process will take another four to six months; however, this process may be extended due to availability and demand on the reviewers and the complexity of issues that may arise from the reviews. There is difficulty in establishing mutually acceptable effluent limits in headwater areas such as the Fuller Mine due to the policies of the MOE. Headwater areas lead to more stringent discharge requirements due to the lack of dilution. At the Fuller site the background water quality has returned to an almost pristine condition which MOE policies do not allow much alteration to the local environment. There is a risk that protests by adjacent home owners may delay the granting of approvals by the regulating agencies particularly given the non compliance with the standard separation distances for mines and residences. Persistent objectors have the capacity to delay the project for an indefinite period of time. 10.3 REHABILITATION AND CLOSURE Financial assurance will have to be submitted with the Closure Plan to cover the costs of securing the present and planned shafts, raises and mine portal. These costs will also have to include monitoring and rehabilitating the mine site, and long term post closure environmental monitoring. Submission of financial assurance will likely be required in the form of a liquid security (cash or letter of credit). The objectives of the mine site rehabilitation and closure are to return the land to compatibility with surrounding land uses. Rehabilitation is anticipated to be carried out progressively following an adaptive management approach. A crown pillar has been identified on the site and will have to be assessed for long term stability. There is a possibility the crown pillar area may require fencing in perpetuity. Other rehabilitation measures required for the property will be installation of concrete shaft caps on existing openings, removal of buildings, leveling of the concrete foundations that currently exist on the site, contouring of waste rock piles, backfilling of the waste water pond and general site re-vegetation. These rehabilitation measures are estimated to cost less than $300,000. Recent testing of the existing mine rock and observations of the historic tailings and waste rock exposure show no potential for acid generation. 10.4 WASTE AND WATER MANAGEMENT The mine ore will be shipped offsite for processing therefore storage and management of tailings will not be an issue. Waste rock stockpiles will have to be re-sloped, covered with overburden and VETRIN Mine Planners Ltd. vegetated. Drainage from the waste rock piles will have to be managed to prevent erosion of the rehabilitation works. No landfills will be established on site. All mine garbage will be hauled offsite for disposal at licensed facilities. Proposed water management systems will form the basis of the necessary approval instruments. Waste assimilation challenges may be presented by the headwater location and design low flows in the receiving waters made up of Davidson Creek and the South Porcupine River. Waste load allocation considerations may also be an issue due to proposed and existing discharges to these receiving waters. 10.5 TAILINGS All of the ore produced will be hauled offsite to a custom mill. Unless the Closure Plan and the Certificate of Approval of the custom mill presently specify milling from the Fuller project, amendments to these approval instruments to include milling of this ore will be required. 10.6 INFRASTRUCTURE Given the past production history and proximity to service structures electric power and access to the site is readily available. An electric supply is available at the site, however the capacity is not known at the time of writing of this report. Should development work determine that the existing electrical infrastructure is inadequate, then sufficient power is expected to be available to the site by upgrading the existing facilities. The mine is accessed from the Back Road or Gold Mine Road that joins Timmins and South Porcupine. Access to the mine site is gained by the single lane gravel service road that is located opposite the paved Shaw Creek Road to the Buffalo Ankerite site. A secondary gated access that is only used infrequently is located off of Cook Road. 11.0 MINE PLAN & BUDGET 11.1 Infrastructure The project is located in the heart of the Timmins mining camp containing paved access roads, power lines, communications and mine service industries in the immediate area. The Fuller Project is located immediately to the north of VG Gold’s Buffalo Ankerite property, off the original road between Timmins and South Porcupine. Currently, gold mining is taking place to the immediate east of the VETRIN Mine Planners Ltd. Fuller property by the Goldcorp /Kinross joint venture at the Dome Mine, and further east, at the Hoyle Pond operation. The Dome Mine has returned to its roots as an underground operation after reaching the economic depth with the open pit started in the mid 1990’s. The Timmins camp also has a history of base metal mines. Currently there are 3 active producers in the form of the Kidd Creek, zinc/copper mine, and the Redstone and Montcalm nickel operations. Mining equipment and mining material suppliers are well established within Timmins and also to the south in the Sudbury Nickel Camp. Various surface and underground development and construction contractors have their offices and shops established within the Timmins, Sudbury and North Bay triangle. The site was very active during the mid to late 1980’s at which time a surface plant was constructed and underground development consisting of roughly 4,500 feet of haulage ramp to the 550 foot level was driven, combined with 2,500 feet of lateral ore drifting on three levels. At today’s costs, this work would represent in the order of $15 million worth of pre-production and production development already in place on the property. The surface plant from the 1980’s included an overland power line and substation. This infrastructure will have to be re-certified by Hydro One and in the case of the substation, completely rebuilt and certified. The other remaining structures from that era consist of a small shop or warehouse building, a capped ventilation shaft and waste pads and or cleared lay-down areas where previous structures or material storage sites existed. Figure 11.1 illustrates where the property is relative to past producers and the proximity of local roads and residences. The Buffalo Ankerite Mine, located to the immediate south, closed down in 1953 due to rising costs and a fixed gold price. Unlike other surrounding mines which produced into the 1960’s, apparently the foreign-owned Buffalo Ankerite operation did not qualify for the Canadian gold mine subsidy which took effect in the early 1950’s. VETRIN Mine Planners Ltd. Figure 11.1 Fuller Project – Location and Surroundings VG Gold’s – Fuller Project Paymaster Mine 1915 – 1966 1,192,206 oz. Buffalo Ankerite/March Mine 1926 -1953 Delnite Mine 1,019,130 oz. 1937-1964 Aunor Mine 920,404 oz. 1940 – 1984 2,502,214 oz. VG Gold’s South Pit Project VETRIN Mine Planners Ltd. 11.2 Project Schedule Progress on permitting and addressing the potential social concerns of the nearby residents is ongoing. The lead time required to receive an approved closure plan is the one activity that is out of an operator’s direct control. The economic study evaluates the mining of a total of 824,000 tons at a maximum annual rate of 180,000 tons per year. The actual mining of this volume will require 4.6 years to complete, plus the initial first year of plant set up and mine dewatering. The mining method used will be the standard shrinkage stoping method which will provide the best control over the final mining grade. This method has low productivity rates which are off-set by lowering underground haulage costs, surface trucking and custom milling charges. The ore zone geometries, such as vein width, vein dip angle and host rock competencies adapt to the shrinkage mining method. At full production an average mining rate of 500 tons per day has been used for budgeting and cash flow calculations. Development crews will provide 80 to 100 tons per day with the remaining tonnage coming from stope swell muck and eventually free pull from the stopes. The multiple zones and preexistence of roughly 7000 feet of ramp and sill development will provide a variety of options, above the 550 level, to reach a production rate of 500 tons per day. 11.3 Surface Plant Budget The surface plant and dewatering budget is itemized below in Table 11.1. A contingency of 20% has been added to cover potential mandates from city ordinances such as sound damping equipment and or sound barriers for surface fans and compressors, fencing of the plant site, power line upgrade and other security or environmental upgrades. For the purpose of projecting cash flow requirements the surface plant and mine dewatering has been scheduled to take up all of the first year’s activity with ideally the planning and equipment procurement occurring during the first and second quarter, followed by a spring construction startup and dewatering and mine rehab to follow in the 3rd and 4th quarters. 11.4 Pre-Production Capital & Operating Costs The resources above the 650’ level were reviewed in detail and a conservative mining plan was developed using the standard haulage, draw point and service raise development approach. Stope sizes ranged from 16,000 to a maximum of 40,000 tons in volume. Production rates within the stope were set at 25 tons per man-shift and a development rate of 14 feet per day per heading was used to calculate labour and consumable costs. The capital costs of the underground mobile equipment are rolled into the development and production costs in the form of rental or lease purchase amounts. Maintenance costs are included in the development and production costs in the form of hourly operating rates for each type of equipment needed for each activity. VETRIN Mine Planners Ltd. Table 11.1 Closure Bond, Surface Plant & Mine Dewatering Budget Closure Bond Pre-Eng/Geol.- Mine Pre-Engineering - Electrical Site Prep. Mine Office Eng./Geology Office Eng./Geol Office Equip Compressor Building/Shop Extension Mine dry Compressors Settling Ponds Pump House + pipe line Grout Pump Mine Dewatering Mine Rehab Surface Fan Install Surface Fans Propane Farm Fuel Tank 1500 kva Sub Station Surface Electrical Distribution U/G Electrical (cable, portable subs, etc.) U/G pumps (pumps & pump line to surface) Toyotas/Man carriers $375,000 $227,500 $39,000 $27,300 $39,000 $39,000 $26,000 $76,000 $260,000 $195,000 $65,000 $10,400 $45,500 $292,500 $104,000 $16,250 $68,250 $13,000 $13,000 $169,000 $390,000 $292,500 $135,200 $91,000 Sub-Total 20 % Contingency TOTAL $3,009,400 $601,880 $3,611,280 Pre-production capital includes all lateral and vertical development, either in ore or waste, which is required to actually bring an ore block to the point where stoping can begin. The extension of the main ramp to the 950’ level is scheduled for early in year 2 of the actual start of mining. The scheduling of the 950’ ramp extension as soon as possible allows for production tonnage from the 800’ and 950’ levels while at the same time tonnage is available from 500’ and 650’ levels thereby smoothing out the demands on the size and number of trucks. Project costs where developed assuming a Mining Contractor would be involved with the project. There is a “Contractor’s” fee added into the cost per foot and cost per ton calculations. VG Gold will provide the project administration, engineering and geology while the Contractor supplies direct VETRIN Mine Planners Ltd. supervision, maintenance and mining labour. The underground equipment fleet is also supplied by the Contractor on a rental basis throughout the project. For a project of this duration the ownership of the equipment and or a final buyout of the equipment would normally be factored into the tender document. For this study, no residual value of the surface plant or underground fleet has been factored into the final cash flow model. Daily labour costs for VG Gold and Contractor staff have been estimated at $3,366 and $6,493 per day respectively. An additional VG Gold cost of $233 per day for office supplies and fire assay charges has been budgeted for the duration of the project. A third party contract for definition diamond drilling in the amount of $84,000 per year has also been included into the operating budget for VG Gold’s staff. Examples of direct unit costs for the mining cycle are illustrated in Table 11.2 below. Activities 1 through 4 include direct mining labour, maintenance labour, mining consumables, equipment parts and consumables, and equipment rentals. Item 5, Mine Services, contains daily overheads such as the daily VG Gold and Contractor staff costs, plus other indirect costs such as underground construction, power and propane charges. These unit rates are calculated using the feet per day and tons per man-shift rates outlined above in the opening paragraph of section 11.3. Unit Mining Costs - Table 11.2 Item 1 2 3 4 5 Activity Ramp Development Haulage & Sill Development Stope Mining Underground Trucking Mine Services $ / Foot $ 820.96 $ 820.96 $/Ton $36.47 $10.86 $27.32 Figures 11.2 through to 11.5 are several illustrations of development general arrangements used to produce the budgeted advance for the Fuller project. The mine plan for the zones above the 650’ level where designed in some detail to establish an “ore tons per foot of advance” factor which was then used to produce development and production costs for the resources from the 650’ to 950’ level. 11.5 VG Gold Labour Project supervision and technical support by VG Gold employed staff is accounted for in the cash flow model under “VG Gold Overheads”. Within these costs, are staff salaries, assaying, and consumable costs associated with the day to day operations of a mine plant alone with a 5% administration cost on every staff work-hour. VETRIN Mine Planners Ltd. 11.6 Trucking Local rock trucking firms; (i.e. Transport Norwest, Savard, etc.) are well established in the Timmins camp and are now actively hauling run of mine rock to the “Kidd Creek ( Estrata) mill and smelter complex or to the Estrata (Kidd Mine site) on a daily basis. For the purpose of this study a rate of $4.75 per dry ton was used to evaluate the loading and trucking cost to a potential custom milling source. 11.7 Milling A custom milling cost of $27.50 per short dry ton was used for this study. This number is within the range that would be expected for a mill of this size and would include the operators’ markup. The rate also includes a VG Gold milling representative on site to oversee the day to day quality controls required for a successful medium term milling agreement. Mining Cost Summary - Table 11.3 Activity Plant Capital Pre-Production Capital Production Mining Surface Trucking Milling Total LOM Costs $ 3,611,000 $ 21,200,000 $ 50,966,000 $ 3,916,000 $ 22,672,000 $ 102,364,000 $/Ton $ 4.38 $ 25.72 $ 61.82 $ 4.75 $ 27.50 $ 124.17 11.8 ECONOMIC ANAYLSIS 11.8 .1 Economic Parameters For the purpose of this evaluation, a 750 US$ gold price and an exchange rate of 1.00 CDN was used to establish a base price of $750 / oz. CDN for the revenue calculation. No inflation factor has been included in the production costs. The cost of capital and corporate taxation has not been factored into this evaluation. Given the above assumptions, the project cash flows deliver a 28% internal rate of return. If revenues were based on $900 per oz., the IRR increases to 78%. VETRIN Mine Planners Ltd. Table 11 .4 Internal Rate of Return Calc. VG Gold Corp. Internal Rate of Return (IRR) - Fuller Project Jan. 2008 Project Costs Value Capital Costs Mine Operating Costs Revenue $24,811,280 $77,553,189 115,476,509 Interest rate 6.25% Expenses Term in years 0 1 2 3 4 5 Capital Costs Operating Costs $3,611,280 $11,900,000 $9,407,000 $6,690,000 $16,932,600 $1,860,000 $16,932,600 $375,000 $16,932,600 $375,000 $17,348,389 Income Total $3,611,280 $21,307,000 $23,622,600 $18,792,600 $17,307,600 $17,723,389 Gold Sales @ $750/0z. Forward Sales $14,007,000 $25,212,600 $25,212,600 $25,212,600 $25,831,709 Total $14,007,000 $25,212,600 $25,212,600 $25,212,600 $25,831,709 Cash flows ($3,611,280) ($7,300,000) $1,590,000 $6,420,000 $7,905,000 $8,108,320 $13,112,040 IRR = 28.10% Table 11.5 Cash Flow Sensitivity Analysis $30,000 $25,000 $24,660 $20,867 (CDN $000) $20,000 $18,886 $16,990 $15,593 $15,000 $14,353 $13,112 $11,871 $10,000 $10,631 $9,234 $7,338 $5,357 $5,000 $ $1,564 1 2 3 4 5 90% 95% 100% 105% 110% Gold Price $1,564 $7,338 $13,112 $18,886 $24,660 Exchange Rate $1,564 $7,338 $13,112 $18,886 $24,660 Operating Costs $20,867 $16,990 $13,112 $9,234 $5,357 Capital Costs $15,593 $14,353 $13,112 $11,871 $10,631 x VETRIN Mine Planners Ltd. Table 11.5 illustrates the impact that a change of a plus or minus 10% in revenue and costs will have to the cash flow model of $750 CDN. The chart demonstrates that the gold price and exchange rate have the largest impact on the projects profitability followed by fluctuations in operating costs. Other factors that are within the control of the operator will have significant impacts as well. A 1% variance in mill recoveries will influence the cash flow by over $1.2 million CDN in this model or a mining grade variance of 1 % will also add or subtract $1.2 million from the bottom line. Table 11.7 provides the year by year breakdown of the cost versus revenue stream for the project. The project is expected to recover 153,696 ounces, at a mill recovery rate of 92%. The model becomes cash flow positive in the 3rd year of operation. Using the parameters outlined above the project generates revenue of over $13 M. VETRIN Mine Planners Ltd. 12.0 CONCLUSIONS Ramp access and lateral development down to the 950’ level are roughly 60% completed due to the advanced exploration activities started in the mid 1980’s. The existence of this development work is the major contributor toward the project achieving a positive cash flow by the third year of production at a $750 CDN gold price. The site’s location within the heart of the Timmins mining camp provides several advantages. The presence of a skilled work force and equipment suppliers and also of custom milling capacity within the camp will fulfill the major requirements needed for this mining project to proceed. In summary, the logistical and economic conditions currently exist for this deposit to be economically viable. Section 13 contains several recommendations for more in depth studies which may have a positive impact on operating costs and production schedules. VETRIN Mine Planners Ltd. 13.0 RECOMMENDATIONS The budget was developed using a conventional ramp access and shrinkage stope mining approach with haulage and draw point extraction drifts on the 375, 650, 800 and 950 levels. The following recommendations are suggestions for further in-depth studies of production alternatives which may either lower the operating costs or ensure that production schedules are met. The trade off will be the requirement for additional up-front capital. 13.1 Truck Haulage versus Hoisting: The budgeted figure for hauling the 824,000 tons to surface is in the order of $8.4 million. This number includes labour, truck rentals, truck maintenance and fuel. An alternative to ramp haul trucking would be to excavate and construct a small scale hoist and skip arrangement. The basic configuration would be a single drum hoist combined with 3 to 4 ton skip in a two compartment shaft. The shaft would have a profile of less than 100 square feet in order to use a raise climber to complete the excavation and install the shaft timber and man-way sets. The head frame would be a portable prefabricated unit with a side chute dumping the ore into a rock box which would then be loaded into surface trucks. An example of the use of this configuration would be the former Bond Gold operation west of Pickle Lake, Ontario. The Bond Gold operation reached 1600 feet in several phases, using this method in combination with a fleet of two 15 ton trucks which hauled to the shaft at a rate of 425 tons per day. The budget contains $400,000 for lateral development and raise work required to establish a second exit from the mine between the 950 and 500 foot levels. These funds can be pooled with the haulage budget of $8.4 million in evaluating the capital and operating cost comparisons of the two ore haulage methods. Pros: Lower operating costs as the project goes deeper Multiple use infrastructure (escape-way, ore handling & possible vent shaft) 16 to 20 hours per day dedicated to ore and waste handling Lowers diesel equipment numbers, lowers ventilation volumes, lowers winter heating costs Improves the economics of mining below 950 level Potential of utilizing off-peak power rates Cons: Increases up-front capital requirements Requires more lead time to fabricate head-frame and source hoist Would require amendment to closure plan VETRIN Mine Planners Ltd. 13.2 Intermediate Levels: The current level intervals are at the 150’, 275’, 325’ and 500’ elevations with future sill and extraction levels planned for the 650’, 800’ and 950’ horizons. An alternative approach would be to develop intermediate levels early in the project schedule between the 150’ and 500’ elevations in order to divide the mining blocks up into smaller volumes. The extraction cycle of the shrinkage mining method requires that roughly 66 % of the mining costs are not recovered until the complete ore block is mined. By creating smaller blocks the cycling rate from development through to milling would be shortened, resulting in a more predictable project schedule. The increase in ore development footage would impact slightly on consumable costs only. Budgeted labour productivities for ore development and stope production are virtually the same on a tons per man-shift basis. This strategy would also have a positive impact on grade control, and would also open up the option of using remote control mucking equipment in order to minimize waste development of haulageways and draw points. The shortened level spacing may also lessen the need for Alimak raise equipment and raise crews to establish service raises into the stopes. The option of bulk mining portions of zones that fit the width and dip geometries necessary for this mining method would also be an alternative available with tighter level intervals. VETRIN Mine Planners Ltd. 14.0 REFERENCES 1. Wardrop doc # 15861101000-rep-L0001-00 “Mineral Resource Estimate of the Fuller Gold Property” 2. 3. 4. Google Earth , 48 deg. 27 ‘ 45” N, 81deg. 17’ 44” W “P. Bevan” ______________________ Peter Bevan, P. Eng. “Rodney Doran” ______________________ Rodney Doran, P. Eng. March 2008 __________________ Date March. 2008 __________________ Date VETRIN Mine Planners Ltd. 15. APPENDIX 15.0.1 Certificate for Peter Bevan As a co-author of this report entitled “Preliminary Economic Assessment for the Fuller Project”, I, Peter Bevan do here by certify that: 1. I am an independent consulting mining geologist, and carried out this assignment for, VG Gold Corp., Suite 520, 65 Queen St. West, Toronto, Ontario M5H 2M5, tel. (416) 368-0099, fax (416) 368-1539. 2. I hold the following academic qualifications: B.Sc. Mining Geology and Associate ship from the Royal School of Mines in London, England in 1960. 3. I am a registered Professional Engineer in the Province of Ontario since 1973 with specialization in development and production. I am a member of: (a) The Canadian Institute of Mining, Metallurgy and Petroleum (Life Member) (b) The Prospectors and Developers Association of Canada 4. I have worked as a geologist in the minerals industry for 47 years since my graduation from university, the last 25 years as a consultant. 5. I am responsible for the preparation of in part or whole of Section 9 of this report; 6. I have had no prior involvement with the properties that are the subject of the Technical Report, in the estimation of resources in 2006-07. 7. I am not aware of any material fact, or material change with respect to the subject matter of the Technical Report that is not reflected in the Technical Report, the omission to disclose which makes the Technical Report misleading. 8. I am independent of VG Gold Corp. (the issuer) applying all the tests in section 1.4 of National Instrument 43-101. 9. I consent to the filing of the report with any Canadian stock exchange or securities regulatory authority, and any publication by them of the report. Dated this 1st day of March., 2008. “Peter Bevan” Peter Bevan VETRIN Mine Planners Ltd. 15.0.2 Certificate for Ronald Moran As a co-author of portions of this report titled “Preliminary Economic Assessment for the Fuller Project”, I, Ron Moran, do certify that: 1. I am principal owner of Vetrin Mine Planners and carried out this assignment for: VG Gold Corp. Suite 520, 65 Queen St. West, Toronto, Ontario M5H 2M5. tel. (416) 368-0099 fax. (416) 368-1539 2. I hold the following academic qualifications: B.Sc. Mine Engineering, Michigan Technological University, 1980; 3. I am a Professional Engineer registered with the Professional Engineers for the Province of Ontario (registration number 90243288); 4. I have worked in the minerals industry for over 25 years; 5. I am responsible for the preparation in part or whole of Sections 1.0, 2.0, 3,0 ,11.0, 12.0 &13.0; 6. I do by reason of education, experience and professional registration; fulfill the requirements of a Qualified Person as defined in NI 43-101. My work experience includes over 25 years as a mine engineer and planner in the base metals and gold sector of the industry and most recently as an independent consultant. 7. I have visited the Fuller Project Site; 8. I am independent of the parties involved in the transaction for which this report is required, as defined in Section a.4 of NI43 101; 9. I have had no prior involvement with the mineral properties in question; 10. I have read NI 43-101 and portions of this report for which I am responsible and which have been prepared in compliance with the instrument; 11. As of the date of this certificate to the best of my knowledge, information and belief, the technical report contains all scientific and technical information that is required to be disclosed to make this report not misleading; Dated this 1st day of Feb. 2008. “Ronald Moran” Ronald Moran, P. Eng. VETRIN Mine Planners Ltd. 15.0.3 Certificate J. R. Doran, P. Eng. As a co-author of portions of this report titled “Preliminary Economic Assessment for the Fuller Project”, I, J.R.Doran, do certify that: 1. I am a Senior Mining Engineer with B. H. Martin Consultants Ltd., and carried out this assignment for VG Gold Corp., Suite 520, 65 Queen St. West, Toronto, On M5H 2M5, tel. (416) 368-0099, fax (416) 368-1539; 2. This certificate applies to the Permitting, Social Consultation & Environmental Compliance sections of the technical report titled “Preliminary Economic Assessment Fuller Project” prepared for Vetrin Mine Planners Ltd. 3. I hold the following academic qualifications; B.S. Mining Engineering from South Dakota School of Mines & Technology, and B.S. Engineering Administration Michigan Technological University. 4. I am a Professional Engineer registered with the Professional Engineers of Ontario (registration number 11936010); 5. I have worked in the mineral industry for more than thirty-five years; 6. I am responsible for the preparation of Section 10, titled Permitting, Social Consultation and Environmental Compliance of this report; 7. I have visited the Fuller Project Site; 8. I am independent of the parties involved in the transaction for which this report is required, 9. I have had no prior involvement with the mineral property or the issuer. 10. I have read NI 43-101 and portions of this report for which I am responsible and which have been prepared in compliance with the instrument; 11. As of the date of this certificate, I am not aware of any material fact, or change in reported information, in connection with the subject property, not reported or considered by me, the omission of which makes this report misleading. 12. I consent to the filing of the report with any Canadian stock exchange or securities regulatory authority, and any publication by them of the report. Dated this 1st day of March, 2008. “J.R. Doran” J.R. Doran, P, Eng.