Part 5 Project Scheduling OPMA 5364 Project Management

Transcription

Part 5 Project Scheduling OPMA 5364 Project Management
OPMA 5364
Project Management
Part 5
Project Scheduling
Topic Outline: Project Scheduling
•
•
•
•
•
•
•
•
•
Identifying relationships among activities
Project network diagrams
Identifying critical paths and critical activities
Determining activity slack times
Gantt charts
Project scheduling exercise
Microsoft Project example
Other precedence relationships
Management of project schedules
Part 5 - Project Scheduling
2
Identifying Activity Relationships
In addition to estimating activity time duration and cost,
relationships among activities must also be identified
Relationships:
• What task immediately precedes this task?
• What task immediately follows this task?
• What tasks can be done concurrently?
These are referred to as precedence relationships
The main relationship for scheduling is ‘what task
immediately precedes the current task,’ which is
referred to as the immediate predecessor task
Part 5 - Project Scheduling
3
Project Network Diagrams
• Network diagrams show the precedence
relationships among activities
• It’s easier to understand these relationships
graphically
• Network diagrams help to understand the flow of
work in a project
• Network diagrams are a useful tool for project
planning and control, as well as for scheduling
• One (perhaps exaggerated) claim is that the
network represents ¾ of the planning process
Part 5 - Project Scheduling
4
2 Versions of Network Diagrams
Activity-on-Arrow (AOA) networks
–
–
–
–
also called Arrow Diagramming Method (ADM)
simpler for projects with many dependencies
emphasizes events; milestones can be easily flagged
sometimes requires dummy activities
Activity-on-Node (AON) networks
–
–
–
–
also called Precedence Diagramming Method (PDM)
easier to draw for simple projects
emphasizes activities
no dummy activities
Part 5 - Project Scheduling
5
Activities vs. Events
• Activity – a chunk of work that is part of the
project; an activity may be broken down into
multiple subactivities
• Event – a significant point in time during the
project, such as a milestone event; an event
could be the time at which an activity is
completed or the time at which related
concurrent activities have all completed
• Dummy Activity – an artificial activity with zero
time duration that only shows a precedence
relationship among activities
Part 5 - Project Scheduling
6
Activity-on-Arrow (AOA) Networks
c
e
b
g
d
f
k
k
k
or
j
j
j
Dashed lines are called dummy activities
Activity
m
n
r
s
Predecessor
_
_
m, n
n
m
r
n
s
Part 5 - Project Scheduling
7
Install rough
electrical & plumbing
6
Pour
basement
floor
Install
finished
plumbing
Install
drywall
Install
cooling &
heating
7
11
8
Install
drains
10
9
Erect
frame & roof
1
Excavate
& pour
footings
2
Pour
foundation
3
Lay
flooring
12
Install
kitchen
equipment
Paint
4
Lay
brickwork
Finish
carpeting
5
16
Finish
electrical
work
Finish
roof
Project Network for
House Construction
Lay
storm
drains
13
14
Finish
floors
Install
roof
drainage
(AOA network)
15
Part 5 - Project Scheduling
Finish
grading
18
Pour
walks;
Landscape
17
8
Project Network Example
Task Pred. Dur.
Task Pred. Dur.
a
-4
g
c,d
1
b
-3
h
e
4
c
a
3
i
f
5
d
a
2
j
e,g
6
e
b
6
k
h,i
1
f
b
4
Draw AOA and AON networks
Part 5 - Project Scheduling
9
Activity-on-Arrow (AOA or ADM) Network
(Initial Network)
Part 5 - Project Scheduling
10
Activity-on-Arrow (AOA or ADM) Network
(Final Network)
c
a
d
g
j
b
e
h
f
i
k
Part 5 - Project Scheduling
11
Activity-on-Node (AON or PDM) Network
Part 5 - Project Scheduling
12
Project Network Example
A project has the following activities and
precedence relationships:
Predecessor
Predecessor
Activity Activities
Activity Activities
a
-f
c,e
b
a
g
b
c
a
h
b,d
d
a
i
b,d
e
b
j
f,g,h
Draw AOA and AON networks
Part 5 - Project Scheduling
13
Activity on Arrow
(Initial Network)
Part 5 - Project Scheduling
14
Activity on Arrow
(Final Network)
g
b
a
e
c
d
j
f
h
i
Part 5 - Project Scheduling
15
Activity on Node
Part 5 - Project Scheduling
16
Critical Path
path – any route along the network from start to
finish
Critical Path – path with the longest total duration
This is the shortest time in which the project can
be completed.
Critical Activity – an activity on the critical path
*If a critical activity is delayed, the entire project
will be delayed. Close attention must be given
to critical activities to prevent project delay.
There may be more than one critical path.
Part 5 - Project Scheduling
17
Critical Path
Brute force approach to finding critical path:
1. identify all possible paths from start to finish
2. sum up durations for each path
3. largest total indicates critical path
(This approach is inefficient, but is instructive)
Part 5 - Project Scheduling
18
2
1
b=2
d=4
4
3
6
g=9
7
5
h=9
Part 5 - Project Scheduling
19
Slack Times
• EST—Earliest Start Time
– Largest EFT of all predecessors
• EFT—Earliest Finish Time
– EST + duration for this task
• LFT—Latest Finish Time
– Smallest LST of following tasks
• LST—Latest Start Time
– LFT – duration for this task
• Slack—LFT – EFT or LST – EST
Part 5 - Project Scheduling
20
Computing Slack Times
EST
EFT
Task = duration
slack = xxxx
LST
LFT
Part 5 - Project Scheduling
21
Slack Times Example
Task Pred. Dur.
Task Pred. Dur.
a
-4
g
c,d
1
b
-3
h
e
4
c
a
3
i
f
5
d
a
2
j
e,g
6
e
b
6
k
h,i
1
f
b
4
For each task, compute ES, EF, LF, LS, Slack
Part 5 - Project Scheduling
22
c=3
slack=
EST
Task=dur
slack=xxx
LST
g=1
slack=
a=4
slack=
EFT
LFT
j=6
slack=
d=2
slack=
Finish
Start
e=6
slack=
h=4
slack=
b=3
slack=
k=1
slack=
f=4
slack=
i=5
slack=
Part 5 - Project Scheduling
23
Gantt Charts
• The main purpose of a Gantt chart is to display
the schedule of activities
• They are easy to understand
• They are flexible in that you can also show other
information on the chart, such as resources
required, who is responsible, critical activities,
percent complete, etc.
• All project management software packages will
create Gantt charts
Part 5 - Project Scheduling
24
Gantt Chart
Activity
a
b
c
d
e
f
g
h
i
Time (weeks)
Part 5 - Project Scheduling
25
Project Scheduling Exercise
DynaTech Equipment Corp. case
• Divide into small groups
• Read case (5 minutes)
• Assignment:
(40 minutes)
– List the immediate predecessors and WBS
number for each activity
– Draw project network diagram (lowest level)
– Draw Gantt chart
– Determine project completion time
Part 5 - Project Scheduling
26
Microsoft Project Example
Part 5 - Project Scheduling
27
Microsoft Project Example
Part 5 - Project Scheduling
28
Microsoft Project Example
Part 5 - Project Scheduling
29
Other Precedence Relationships
• The typical precedence relationship between
two activities is that when the first activity has
finished, then the second activity can start. In
this case the first activity is called the immediate
predecessor of the second activity.
• This is referred to as a Finish-to-Start linkage.
• Other precedence relationships, or linkages, are
also possible.
• Lead and lag times are also possible.
Part 5 - Project Scheduling
30
Other Precedence Relationships
Finish-to-Start
Linkage (FS)
Start-to-Start
Linkage (SS)
Finish-to-Finish
Linkage (FF)
Activity 1
Lead and Lag Times
Activity 2
Activity 1
Activity 2
Activity 1
Activity 2
Activity 1
Start-to-Finish
Linkage (SF)
Lead (-) and Lag (+) times are
expressed as part of the
immediate predecessor
notation. So 1FS+3 listed for
the immediate predecessor of
Activity 2 means that Activity 1
is the predecessor with a Finishto-Start linkage and a 3-day lag
time after Activity 1 finishes
before Activity 2 can start.
1FS-3 means that Activity 2 can
start 3 days before Activity 1
finishes.
1FF+3; 1SF-5; 1SS+4
Activity 2
Part 5 - Project Scheduling
31
Management of Project Schedules
• Meeting project deadlines is often the most
important goal in project management
• Careful scheduling of project activities is critical
to meeting the project due date
• Effective project managers should have a good
understanding of the issues involved in activity
scheduling
Part 5 - Project Scheduling
32
Ineffective Scheduling
Notice:
As of tomorrow, employees will only be
able to access the building using individual
security cards. Pictures will be taken next
Wednesday, and employees will receive
their cards in two weeks.
Part 5 - Project Scheduling
33