Tappan Zee Bridge Deck Panel Reuse From the Tappan Zee Contract: “Precast concrete deck panel substructure units: A total of 150 units shall be salvaged. The units shall be from the 2005 and 2010 contracts (by others) undertaken at the existing bridge and shall be located on the tangent section of the existing causeway between spans 70 and 165. Units that have bump-outs for light standards shall not be included. Twenty units shall be from existing lanes 1 and 7, with 10 units being taken from each lane, and these units shall be retained with the existing steel traffic barrier remaining attached. One hundred and thirty units shall be from existing lanes 1, 4 and 7 (without barrier). The Authority’s Project Manager shall provide to the Design-Builder a list of the available units after existing traffic has been removed from relevant lanes. Ten units with the barrier and 60 units without barrier shall be removed and delivered by the Design-Builder to a designated location in Syracuse, NY. Ten units with the barrier and 70 units without barrier shall be removed and delivered by the Design-Builder to a designated location in Albany, NY. All 150 units shall be removed, transported, delivered and unloaded by the Design-Builder without introduction of further defects (cracks, chips, spalls) that would reduce the service life or adversely affect the immediate in-service use of the precast concrete deck panel units, unless such further defects are repaired such that the service life or immediate in-service use is not adversely affected. Any damaged units that are not repaired by the Design-Builder shall be replaced by other units that conform to the requirements herein; In addition to the barrier for salvage with deck panels, a total of 15,000 feet of steel barrier and associated hardware and appurtenances installed on precast deck panels shall be removed from the panels and salvaged. The Authority’s Project Manager shall provide to the Design-Builder a list of the available steel barrier sections for salvage after existing traffic has been removed from relevant lanes. Following removal by the Design-Builder of the steel barrier system, the Design-Builder shall deliver it as follows: 10,000 feet shall be delivered to a designated location in Albany, NY area; 2,500 feet shall be delivered to a designated location in the Syracuse, NY area; and 2,500 feet shall be delivered to a designated location in the Buffalo, NY area. All lengths of barrier and associated hardware and appurtenances shall be removed, transported, delivered and unloaded by the Design-Builder without introduction of further defects (bending, denting, cracking, chipping) that would reduce the service life or adversely affect the immediate in-service use of the barrier systems, unless such further defects are repaired such that the service life or immediate in-service use is not adversely affected. Any damaged barrier and barrier appurtenances that are not repaired by the Design-Builder shall be replaced by barrier and barrier appurtenances that conform to the requirements herein;” Tappan Zee Bridge Deck Panel Reuse Existing Tappan Zee Bridge Information: The proposed contract calls for removal and storage of superstructure units from the existing Tappan Zee Bridge. These units are located on the tangent causeway section west of the Main Span. These units will come from Lanes 1 and 7 as fascia units and Lane 4, an interior unit. Lane 1 and 7 units consist of 2 galvanized rolled beams approximately 50 feet in length with an 8 ¼ inch monolithic HP concrete deck. Longitudinal grooving is installed on the surface. The fascia rolled beam is a W27x102 with the interior beam a W27x94. The units were fabricated between 2007-2008 and have been in service for about 5-7 years. These prefabricated units have a deck areas that typically measures approximately 12’-7” W x 50’ L. The expansion end consists of the steel beam welded to an elastomeric bearing. The fixed end consists of a concrete footer that sits on a neoprene pad. The existing anchor bolts were used/extended and grouted. The estimated weight of each unit is approximately 75500lbs, not including the steel barrier. Lane 4 units consists of 3 galvanized rolled beams approximately 50 feet in length with an 8 ¼ inch monolithic HP concrete deck. Longitudinal grooving is installed on the surface. The rolled beams are W27x114. The units were fabricated between 2011-2012 and have been in service for about 2-4 years. These prefabricated units have a deck areas that typically measures approximately 13-3” W x 50’ L. The expansion end consists of the steel beam welded to an elastomeric bearing. The fixed end consists of a concrete footer that sits on a neoprene pad. The existing anchor bolts were used/extended and grouted. The estimated weight of each unit is approximately 86500lbs. Existing Superstructure Drawings: Typical Bridge Cross Section Lane 4 Units - Deck Panel Detail Spans 82 -165 Lane 4 Units - Deck Panel Detail Span 166 Lane 4 Units - Superstructure Details Lane 1 and 7 Units - Deck Panel Detail Spans 2 -166 Lane 1 and 7 Units - Superstructure Details Lane 1 and 7 Units – Expansion Bent Details Lane 1 and 7 Units – Fix Bent Details Lane 1 and 7 Units - Deck Panel Fixed end Details Steel Bridge Railing Details 1 Steel Bridge Railing Details 2 Traffic is scheduled to be removed from the existing bridge late 2016. Based on the current demolition schedule, these panels could become available Summer of 2017. If you would like to receive more information when it becomes available or are interested in deck panels for reuse, please feel free to contact me. Christopher Millington, PE Major Projects Structural Engineer Federal Highway Administration, NY Division 11A Clinton Ave, Suite 719 Albany, NY 12207 Phones: 518-431-8853 e-mail: [email protected] 12176m 1It'-M :l.U:I..1:1.U4· -:I.::', Kt.MUVt. t.X1~I\Nti ~UI"'="'''v';IUKt. llillIS 27.737m 3.4BOm NB TRAFFIC lANE 3.556m NB TRAFfiC lANE 3.632m NB TRAFFIC lANE 1.067 ®~ 76-:1~H...........-_""",<;>~ CD ::~ 3.657m REVERSIBLE TRAFFIC lANE @~ ~ r EXISTING DECK SUPPORT AT END DIAPHRAGMS TO REMAIN (TYP) ~ 1:321 DIAPHRAGM i, (TYP.) '\ m IIII r:= LJ r"I @ n ~ ::-'-'-IMOVABLE 210 II ~ .l. r ]1 " I II ® ® I-- I R~ EXIST./pRO STRINGER I D~ 1/.1 / I t<-.. \ (TYP.) rMOVABLE \ BARRIER (PM HOURS) 1.524m r:-76 I 13.843m "ci 1.473m l7. ~~ ~.. , ~~~ ~ "'"' I h (TYP.) . I. r !;Z ~ I III ' i\~ ~ @ €0 JWI ' REFER TO DWGS SlU-l0 TO SlU-15 FOR PRE-FABRICATED OECK OErAlLS. 3. REFER TO DWGS. DTL-l TO DTL-7 FOR BEARING AND PEDESTAl DErAILS. 4. MOVABLE BARRIER IS POSmONED BY "THE AUlHORIlY TO "THE A.M. AND P.M. PEAK TRAFFIC HOURS lOCATION. FOR MOVABLE BARRIER LOCATION DURING CONSTRUCTION. SEE TCP DWGS. 5. CONTRACTOR SHAll TAKE, CARE NOT TO DAMAGE EXISTING EDGE BEAM. 6. PROVIDE TEMPORARY SUPPORT FOR UTlLmES WHICH ARE TO REMAIN. SEE UTlLl1Y PlANS. ill I @ 1.829m AND 565.2022 8~ 851 1.829m ~ ITEMS ,202..,200,525. 582.0632--25. 565.1922 r=;=-, !."I l 602 1.98 EXISTING 5kV AND COMMUNICATION CONDUITS TO BE REMOVED 13.843m 1.702m (5 1.676m REMOVE AND DISPOSE OF EXISTING ABER OPTIC UNES AND CONDUITS AFTER NEW ABER OPTIC UNE INSTAllATION AND COMMISSIONING BY OTHERS AXED - EVEN BENTS EXPANSION - ODD BENTS SCALE:: I : 50 i ~ II III 1.981m EXISTING PIERS 81 - 166 I 2. TRAFFIC BARRIER EXISTING EDGE BEAM TO REMAIN ( ~ ~\ L ,:: - -1---"'--25' 1.56'-= ' - - - - V ------: \ " REFER TO DWGS. CS-2. CS-3 FOR SUGGESTED CONSTRUCTION SEQUENCE AND mU-l FOR TEMPORARY SUPPORTS. LEGEND III I ~~ ~ 1.524m w .. A 1J'£>.~--~ SAWCUT E X I ! \ SlAB FUll BRIOGE:- @ ® 1.9Blm 1.981m r III ~~ ~ ~,.473m I~ ~ 1.B29m I BARRIER .I (AM HOURS~ \ 1111 1111 ~~ 1 1.829m 1.702m 1.676ril 1.56'-= ' 1m I 85~ B51 I y li! 8 ~ o ®tlt 1. 1.067m UGHTlNG~ ~ (TYP.) . ~I---' (TYP.) TRAFFIC BARRIER "z 3.632m SB TRAFFIC lANE SAWCUT EXIST SLAB FUll DEP"TH Ir--~ I "'"' AND CONDUITS 3.556m SB TRAFFlC lANE ®tlt 0~ I , (TYP.) 3.4BOm SB TRAFFIC lANE ROADWAY 26-l-l-i- LmLl1Y HANGERS- 610 II I i 12176m I III:.M bti4.1UtlZ· -2b. IN~IAI.L BIN 5516340 Ut.(';K t'ANIoUi II:'U 27.737m 1.067 3.4BDm 3.556m NB TRAFFIC lANE 3.632m 3.657m REVERSIBLE TRAFFIC lANE 610 3.4BOm . SB TRAFFIC LANE 0S ®~ 3.556m SB TRAFFIC lANE ®tlt 3.632m SB TRAFFIC lANE 1.067m o tlt£>. ®tlt -:11-76 ~~,..., ROADWAY UGHTlNG---...... """ (TYP.) L CROWN 26-tt--I- I ~~I TRAFFI~:)RIER l NEW CONDUIT AND -~ I Ul 'f iii 0 0:: m II ~ II I /7" .... V ISl --./ r--- SUPPORT TO BE INSTAlLED BY CONTRACTOR. NEW ABER OPTIC UNE TO BE INSTAlLED BY,O"THERS. ::> , 210 ~ I . It BRIDGE ,,~-rt:::'rf I \ SS~P~ ~ -" ~ /~:e:'t I Vf-~~·ra DIAPHRAGM r~ISTlNG TRA~~srRIER ~-B' I EDGE -1---'''-25 'BfEAMiE=(nP=='=)===liI~::~=i!E======jj::~~~~~ ~~~f;~~~r:=====:Hl~~~IAP~~~AA~GjMil\El~====;TIff;~~~~~~~_=':'5~6~~=;li~;;~=lI~Ii!(~AM==H=O=U~RS~~==~li/~I~I~~(P~M;;HO~U~R~S~~'~=6=~~:;ii!~~~/~ ® UTlUTY HANGERS AND CONDUITS (TYP.) tVoGtP~~~~~~ORT-' III II @ I III @ l. -III r 1 IL 1,/1 II" f [%;: ~ ! ;;zjl.473m 0.11 ~ ::+/ EXlST./pR,~ ~ STRINGER III II ~~ ® III ~~ r0 ~L (:!) @ II IIII \ 1.473m."Jr ~ ~~ p.: ~I .~@ ~ Jj r II r II I - v TO BE INCLUDED IN ITEMS 202.12001525, 582.0632--25 AND 565.1922. AXED BEARINGS FOR SPAN 166 PAID UNDER ITEM 565.2022. (TYP.) 13.843m \ 1.9Blm I" I --y - 1.981m 1.524m r= ~ BY SYV. § § 602 1.524m II 1.981m 1.9Blm I " --y - 1.829m 1.B29m, _ NEW 4BOV CONDUIT NOTICE: THIS DOCUMENT CONTAINS SENSITIVE AND/OR CONADENlIAI. INfORMATION THAT MAY ONLY BE USED FOR THE SOLE PURPOSE OF PREPARING A 810 FOR THIS PROJECT. ANY OTHER USE IS STRICTLY PROHIBITED. IF YOU HAVE RECEIVED THIS DOCUMENT IN ERROR OR ARE NOT lIjE INTENDED RECIPIENT. BE ADVISED THAT ANY USE. 0lSSEMlNAll0N OR COPYING OF THIS DOCUMENT IS STRICTLY PROHIBITED AND YOU MUST DESTROY IT ,IMMEDlAffiY. ,,~ Iml r=;=-, 8 1.702m fiR ~ @ 1.676m --- NEW YORK STAlE THRUWAY AUTHORITY DEPARIiIENT OF ENGINEERING SERVICES 2DO SOUlHERN BLW. ~. N.Y. 12209 v-- lTTLE OF' PROJECT TAPPAN ZEE BRIDGE REPAIR PROJECT 13.843m PROPOSED PIERS 81 - 166 SCALE:: 1 : 50 lOCATlON OF PROJECT TAPPAN ZEE BRIDGE lAP 14.67:1: lTllE oF' DRAWING: AXED - EVEN BENTS EXPANSION - 000 BENTS CAUSEWAY TYPICAL SECTION PIERS 81- 166 ci .i!! 0;; TANY 10-9B i i:!i DESCRIPTION I I~1~.3=2~li~~~~1:·6~7~6~m~~~,~.7~0~2~m~i.;;;~1.~B~29~m~;i.:;~~~;;==~~~==~~::::====::~~~==~~~==::~::~====::~~~~~~::==~::::====::====:±::::::==:±::::==~~~ L, f\..c.L... THE COST OF AlL BEARING AND PEDESTAl MODIACATIONS I '\_ ~ _ 1.B29m DAlE REVISIONS I NEW PREFABRICATED DECK PANEl (TYP.) -- NOTE: 12/22/09 ALL DIMENSIONS ARE SHOWN IN M1UUMEIERS UNlESS OTHERWISE N01EO. TSU-1 , Ii Il Il 2S~~----------------~~~~~~~~~~~------------------~r-2S i / <i<. GIRDER SYMMETRICAL ABOUT <i<. 0w '"w j'.!: e 0 0 I I I I, .,I I, I ~ ~~ 00 zo g:I: I <0 go'" E - III .... I til ~ ID li, I I 3-,'6 BARS AT 150 EQ. SPA. ,'9 TRANSVERSE STAGGER TOP '" BOT. MATS I lDDmm UFnNG· HOLE wrrn B TOP AND BOrr. 610 MIN. LENGTH (lYP.) ,'9 1 '" ~ I , I I 1 I I I I I 1 , , , I I. , , , , , z n. 0 0 0 :I: w < 0 g .... 0 0 w a (!) -' E ~ 0 III ~ i1'. 0 til ..J W ~ -' ('j n. ~ 100mm UFlING HOLE LOCAnON , I <D z 9 < E 0 '" ...: <D ! I I I I I I I I I, I I I I I I I I , NQlES;. 1. AlL DIMENSIONS MEASURED ARE HORIZONTAL AClUAL DIMENSIONS SHALL BE PROVIDED BY THE CONTRACTOR AFTER SURVEY· AND DETERMINING CROSS SLOPE AND LONGITUDINAL SLOPE. 2. SEE PRECAST SUPERSTRUCTURE NOTES (G-3) FOR TOP SURFACE REQUIREMENTS. 3. SEE G-4 FOR GROUTING REQUIREMENTS. I I I I I I I I I I I I I I 4. FOR. EDGE BEAM REINFORCEMENT SEE DWG. DPU-3. 5. FOR END BEAM REINFORCEMENT.· SEE DWG DTL-2. ::--EDGE OF : PANEL I I I I I I I I I 1 1 I I I I I I I I I I I I I I I I I 1 i • I I I I I I I I I ·1 I I o Ul I I I I I I 1 I I I ~5t:Q.~~~ I I I I I I 1 I I I I 1 I I I I I 1 I I I I 1 I I I I 1 I I 1 1 I I I I I I I I I I 1 I I I I Ii I I 1. til l'.~ li, <> L50 0 <>' , 300 <>'tIl z , , , , 200 I!! z m;!; 1E m (TiP;) , , w w (!) 0 a aw 1E m 0 I I I ) -' w a: m )i -' ~ til ;;;;, ::l; < w m 0 '" t:i I I I I I I I I 1 1 I I I < -' ,.: < n. "a ~ 400 EDGE BEAM --+---11 en n. z 0 I,. I, I, I I n. g 14-'29T&B I OF EDGE BEAM I ID ~ I I <>'tIl n. m I I 35?: § I I afil ::l; I ! I I 1 I I I I 1 I I I I I I 1 1 I I I I I I 1 I I I I I I I I I I I I I 1 I I I 1 1 1 I I I 1 1 1 I I I I 1 1 I I I I SYMMETRICAL ABOUT . <i<. GIRDER I -EDGE OF PANEL ID / <i<. GIRDER <i<. PANEL" I I I I I I I I I I I I I JOINT (SEE DETAIL "A" DWG. OTL-B) 25-;r-_________~~·4~.0~0~4~m~~~O~N~GITU~D~INAL~~GR~O~0~VI~N~G~_---------*--25 4.011 m LONGITuDINAL GROOVING <i<. GIRDER ~3j/ Il JOINT (SEE DETAIL "A" DWG. DTL-B) JOINT (SEE DETAIL "A" DWG. DTL-B) JOINT (SEE DETAIL "A" DWG. DTL-B) ATlti I . 3-,'6 BARS AT 150 EQ. SPA. ,'9 TRANSVERSE STAGGER TOP & BOT. MATS BIN 5516340 o z I I I ! I I ~ : I (I) I DATE I~~! 1.47Bm 1.9Blm I ~5~0~C~O~V~.__~_____-..~~~~~~~~~3~.~96~'~m~~~~~~~~~~_ _ _ _-rr-SO CO~ fl16 BARS LONG. 0 150 - 27 BARS TOP/Borr. (STAGGERED) 4.061m DECK REINFORCEMENT PANEL PLAN - LANE 3 (LANE 5, PANEL OPPOSITE HAND) SCALE: 1 : 20 NOTICE: THIS DOCUMENI CONlA1NS SENSITNE AND/OR CONFlOEllTlAL INFORWITION THAT WlY ONLY BE USED FOR THE SOLE PURPOSE OF PREPARING A BID FOR nils PROJECT. ANY OTHER USE IS STRICTLY PROHIBI1£D. IF YOU HAVE RECEIVED THIS DOCUMENI IN ERROR OR ARE NOT THE INIENDED RECIP1ENI. BE ADVISED THAT ANY USE. DISSEMINATION OR COPYING OF THIS DOCUUENI IS STRICTLY PROHIBI1£D AND YOU MUST DESTROY IT IUUEDIATaY. t:1il 100mm UFnNG HOLE wrrn B fl19 TOP AND BOrr. 610 MIN. LENGTH (lYP.) I I SYM. /lEYISIONS -100inm UFlING HOLE LOCAnON (TiP.) ~ ARCHITECT & ENGtNEER. P.e. ,-"sw.~.1'10~,, "...:t:Ull_~!II.T.lml' HR NEW YORK STATE THRUWAY AUTHORIlY DEP.IRIIIENI Of ENGINEERING SEIMCfS 2DO SOUTHERN BlVD.. NllNIY. N.Y. 12209 I cov. l.Soom L'50 -~r- llTlE L5D COV. or PROJECT TAPPAN ZEE BRIDGE REPAIR PROJECT LOCATION OF' PROJECT ~ 602 OESCRIPTlON 503 1.524m 1.524m 503 SPANS 82-165 PREFABRICATED DECK PANEL DETAILS ~5~0_C~0~V~'__+r_____~~~~~~~~~_3~.~95~4~m~~~~~~~~==~_____-H__-50 CO~ fl16 BARS LONG. 0 150 - 27 BARS TOP/Borr. (STAGGERED) CONTRACT NUldBER: TANY 10-98 4.0S4m DECK REINFORCEMENT PANEL PLAN SCALE: ! : 20 TAPPAN ZEE BRIDGE UP 14.67± lTTl.£ OF DRAWING LANE 4 NOTE: All DIMENSIONS ARE SHOWN IN f..tlWf..tETERS UNLESS O1HERWISE NOTED. 12/22/09 DRAWING NUMBER: DPU-l ~ JOINT (SEE DETAIL "B" owe. OlL-B) ~ JOINT (SEE DETAIL "B" owe. DlL-B) ~ JOINT (SEE DETAIL "B" DWG. DlL-B) 2S~~------------------4~.0~1~I~m~L~0~NG~ITU~0~INAL~~G~RO~0~~~N~G~--------------------~-2M~~~~~~ I EDGE TERMINATES BEAM 76 FROM END OF nANEL (TYP) ADDITIONAL /116 LONG. BARS, 930 LENGTH, AT ISO , Jr.-GIRDER ~ GIRDER -5'0 C O V . . . . r.. I 26 TOP /~SLAB CANllLEVERED ' 4 6 3 (SEE I__Lr~.-~N~O~~~~~T , • ~ JOINT (SEE DETAIL "B" owe. DlL-B) 4.004m LONGITUDINAL GROO~NG EDGE BEAM~~ ~RMINATES 76 FROM END OF PANEL (TYP.) ADDITIONAL #16 LONG. BARS, 930 LENGTH, AT ISO - J r.- ... GIRDER r50 COV. 26 TOP ~ GIRDER mm II V I MMEE T MODULAR JOINT HEADER 2S-;t--'------------..2::=:!!!..=====....::=~~-----------tl_2S ~ GIRDER /~~~LEVERED 1'1 *1m 463 (SEE NO~ 2) V ----"-r-/----.---==r=--r , I, I I, I, I, I, ,I I, I, I, I ( \ ~ I. All DIMENSIONS MEASURED ARE HORIZONTAL ACTUAL DIMENSIONS SHAll BE' PRO~DED BY THE CONTRACTOR AFTER SURVEY AND DETERMINING CROSS SLOPE AND LONGITUDINAL SLOPE. 2. GROUT HOLES ARE REOUIRED AT THE PORllON OF THE STRINGER SLAB THAT RESTS ON THE EXISllNG . STEEL STRINGER ENDS. SEE DWG. JTW-2FOR DETAILS. 3. FOR EDGE BEAM REINFORCEMENT SEE DWG. DPU-3 4. FOR END BEAM REINFORCEMENT SEE DWG. DlL-2. I EDGE OF PANEL I o I I I I I I ,I· I, I, I, I, I, I I I I I I I . I I I I I w I I (!) IX: 8 I I I I I I I (!) ci I I i \ \ \ o to ~ o 1 400 EDGE BEAM --+',, ----!JI ~w ..J (!) W Cl Z « a. 1i! ... CD " (!) , ,, ! ! I, I, I, I, I (!) z ~ 4 /J29T"'B~: I, OF EDGE BEAM . : AND 2 ADo'lL : /122 AT BOTTOM I• ,,: . I / I, I /J19 TRANSVERSE--. , 3-/J16 BARS AT STAGGER , ISO EO. SPA. TOP '" BOT. I ~ -tl::l:±:Jil ,~il 1\1 v:100 HOLEmm WITHUFllNG B /J19 , !~ I . ~ ·E !:; ~ , Iii I, I I I, I ,I I I i ~= i ~ I I I I I I o IJ) ~ i i i ..J ~ § CD o ! I, I I, I, '"u:i '" u:i I I I I B~TT. TOP. AND 610 MIN. LENGTH (TYP.) o i i~ MATS I, <II ~ z EDGE OF PANEL 3-/116 BARS AT 150 EO. SPA. /119 TRANSVERSE STAGGER TOP '" BOT. MATS ( II- 100mm UFllNG 100 mm UFllNG HOLE WITH B /J19 TOP AND BOTT. 610 MIN. LENGTH (TYP.) ! I, ,I I, I I, I, I BIN 5516340 3-/116 BARS AT 150 EO. SPA. ' I-.....,r------r----....-I I'. .! ~ i ~ I I I I DATE DESCRIPTION BY SYI.I. REY1SIDNS -IOOmm UFllNG HOLE LOCAnON I HOLE LOCAnON (TYP.) ~TYP.) NOnCE: THIS DOCUMENT CONTAINS SENSIlNE AND/OR CONflDENllAL INFORMAll0N THAT MAY ONLY BE USED FOR lliE SOLE PURPOSE OF PREPARING A BID FOR llilS PROJECT. ANY OlliER USE IS STRICTLY PROHIBITED. IF YOU HAVE RECIlVEO THIS DOCUMENT IN ERROR OR ARE NOT THE INTENDED RECIPIENT, BE ADVISED THAT ANY USE, OlSSEMlNAll0N OR COP'llNG OF llilS OOCUMENT 15 STRICTLY PROHIBITED AND YOU MUST DESTROY IT IMMEOIAmy. .'~. , I HR i L NEW YORK STATE THRUWAY AUTHORITY ~ EXP. . I BEARINGS I.SOOm (TYP.) 602 50 COV. I J 'ISO 200! I 300 EXP.BEARINGS LS~ I 3.961m 27 BARS TOP/BOTT. (STAGGERED) 4.061m DECK REINFORCEMENT PANEL PLAN - LANE 3 . (LANE 5 PANEL OPPOSITE HAND) I I DEPARIIIENT Of ENGINEERING SEJMCES 200 9lIIrHERN BLVD.. AlBNff. N.Y. 12209 I COV. l.S00m 150~ J (TYP.). ~ 1.9Blm f/16BARS LONG. 0 ISO - ~ I ~ Lso llTLE OF PROJECT cov. . TAPPAN ZEE BRIDGE REPAIR PROJECT LOCATION OF PROJECT TAPPAN ZEE BRIDGE lAP 14.67:1: 503 50 COV. 1.524m 50 COV. /J16 BARS LONG. C ISO 1.S24m llTLE OF DRAWING 503 I 3.954m 27 BARS TOP/BOTT. (STAGGERED) SPAN 166 PREF'ABRICATED DECK PANEL DETAILS 50 COV. TANY 10-9B 4.0S4m DECK REINFORCEMENT PANEL PLAN SCN.E: 1 : 20 LANE 4 NOTE: 12/22/09 AlL OIMENSIONS ARE SHOWN IN MIWMETERS UNLESS OlliERWISE NOlED. DPU-2 ( ~ ~ JOINT JOINT CROWN ,I " 4.064m 200 100 146 187 4 200 - #13 BARS 0 250 .1 87 200 4 - 200 187 50 (lYP.)-t ISEE DETAIL 'B' DWG DTLMATCH TO LANE 3 PANEL t T- , {l19s 0 l . . . . '1) • V e;; :;:] .. \. . . . .. . _D 57~o- .- , Mtr- !"j / I ~/f !I , . I 178 EXIST. ANCHOR BOLT ci . 508 I , I : 178 -r 0 n ii I; , 63 IBENTS /"#13 (lYP.) . -. ~ 6 ~I ~50 MIN. I, 200 -. , .I:l.QIfS;. 50 (lYP.) I I--MATCH TO LANE 5 PANEL '-- I-lEVa 2-122 BARS ' fll! JlI "' I ,. " t- 1-50. r57 !"! THE CONTRACTOR SHALL REDUCE DEPTH OF THE CONCRETE BELOW FLANGE TO MAKE ElEVATION ADJUSTMENT. 3. AFTER INSTALLATION OF CONCRETE SUPERSTRUCTURE, THE CONTRACTOR SHALL GROUT ANCHOR BOLTS. SEE G-4 FOR GROUT GENERAL NOTES. 4. BEARINGS ON TOP OF DIAPHRAGMS ARE SIMIlAR TO BEARINGS AT GIRDERS. SIKAOUR 31 EPOXY SHALL BE USED TO ATTACH ELASTOMERIC PAD TO THE STEEL DIAPHRAGM. 5. STEEL LAMINATED BEARINGS ON TOP OF DIAPHRAGMS TO BE PAID UNDER 565.1921. .. ,1111 III, . ! it VARIES !- (SEE NOTE 2) 63 I, I, I -: 1.524m 2. r-- ;JJ1 1111 SEE DWGS. DPU-l, DTL-2 AND DTL-3 FOR ADDmONAL DETAILS. ..... - !II 1. e;; 340 (SPACED EVEN) j 1.524m 400 508 ~ STRINGER 9 ~ STRINGER 8 ~ STRINGER 7 100 690- I, I 82 THRU 166 146 . . . . v ,I ~ EXIST. ANCHOR BOLT fur- I ! ! iiri f- I, I, I ~ 2-/113 lYPE (26) VARIES (SEE NOTE 2) iili! il,ll , / ii;ii '-lEVa l- t~501 57 187 - _~ n I LEVEL..-' DTL-2 200 \~ • - ~) v~ommlll SLEEVE ~d CiT' '" lYPE (Tl) IIII! I I 340 :-t-- 0 2-113 t- 340 • 6 ~ I ~99 1-113 lYPE (T',) VB\ ~d Ii lEVa- t--"' C) • r50mmlll 340 -- ~ • -• 210 r690 ..... VARIES (SEE NOTE 2)----...... o 1501 #13 BARS 0 250 #160 150 TOP <Ie BOTTOM~ STAGGERED I 360.180x25 STEEL LAMINATED ELASTOMERIC BEARING lYPE E.L WITH ONE 3mm INTERNAL STEEL PLATE AND TWO LAYERS OF l1mm THICK ELASTOMER (SEE NOTE 4 AND 5) PRECAST PANEL ELEVATION LANE 4 AT FIXED END V N.T.5o BIN 5516340 1====:d;]~~~=1 85X13 SllFF. I( SIDE OF WEB 8 DESCRIPTION TIGHT FIT BY SYN. REVISIONS W 410 X 85 DIAPHRAGM /""3 (lYP.) ~ 1--.. 5 ~ ~ .m ci ~ := ~ l!i N! 7 D- 2-#13 lYPE (26) . I LEVEL./' 2-#13 J 0;--., ~ / ~ ~ '" / J L. 50 IJ. ~f+~ri!'iitl'H-II#:h{-/~,.._-tI':::j:::HtiliH:,t':+ 178 VARIES (SEE NOTE EXI~~5T. ANCHOR 602 BOLT I' , BENTS 82 THRU 166 EXTsT. ANCHOR BOLT 400 EDGE BEAM BEARING DETAIL N.T.5o CONCRETE EDGE BEAM HR ill t- ! I r;r-' 1 2)~ 63 178 J V.50mmlll PVC. SLEEVE 'rtP) MIN. Lr~H~!,i'.~iY~~/~'____i~',~oi~ I if- 2-,22 BARS J ~ 50(SPACED E V E N ) y 5~ lYPE (Tl) ~/f iI 1-#13 lYPE ( T l ) - - l - - - - . , J 40 0 -'---lllEVaEVELl? ..... '=O'T"llU2~9~9I--Ul1- VARIES (SEE NOTE 2) 340 NOTICE: THIS DOCUMENT CONTAINS SENSITIVE mO/OR CONFIDENTIAL INFORMATION lIlA! MAY ONLY BE USED FOR THE SOLE PURPOSE OF PREPARING A BIO FOR . THIS PROJECT. ANY OTHER USE IS STR/C1l.Y PROHIBITED. IF YOU HAVE RECEIVED THIS DOCUMENT IN ERROR OR ARE NOT THE INTENDED RECIPIENT. BE AOVlSED lIlAT ANY USE. DISSEMINATION OR COPYlNG OF THIS DOCUMENT IS STRIC1l.Y PROHIBITED mo YOU MUST OESTROY IT IMMEDIATELY. ill I l Jlli ! I, ,I n I I 1.981m <t 360.,80.25 STEEL LAMINATED ELASTOMERIC BEARING lYPE E.L WITH ONE 3mm INTERNAL STEEL PLATE AND TWO LAYERS OF llmm THICK ELASTOMER (SEE NOTE 4 AND 5) . PRECAST PANEL ELEVATION - LANE 3 (LANE 5 PANEL OPPOSITE HAND) N.T.S. DEPARlIIENT Of ENGINEERING SfIMC£S 200 SOU1HERH BlW. AIIlNfr. N.Y. 12209 TITLE or PROJECT TAPPAN ZEE BRIDGE REPAIR PROJECT LOCATION OF PROJECT. TAPPAN ZEE BRIDGE UP 14.67± l1ll..E OF DRAWINC SPANS 82-165 SUPERSTRUCTURE DETAILS FIXED END 1.473m ~ STRINGER 6 OR 10 STRINGER 5 OR 11 NEW YORK STATE THRUWAY AUTHORITY CONTRACT NUMBER: TANY 10-9B W410 X 85 DIAPHRAGM NOTE: @~!.iCTION All DIMENSIONS ARE SHOWN IN MIWMEIERS UNlESS OTHERWISE NOTED. 12/22/09 DRAWING NUMBER: DPU-3