Update â Restraining a Principle`s call on security
Transcription
Update â Restraining a Principle`s call on security
28 April 2015 CDI Lawyers Update Construction, Development & Infrastructure Restraining a Principle’s call on security: is a Bona Fide claim still enough? TCS argued that NSS was not entitled to have recourse to the security on three grounds: 1. 2. In TCS Civil & Building Pty Ltd (TCS) v Northern Stevedoring Services Pty Ltd (NSS), TCS applied for an interlocutory injunction to prevent NSS from having recourse to bank guarantees it had provided as security for performance under an AS 4902 – 2000 Standards Australia design and construct contract. The Arguments Both parties alleged the other had wrongfully terminated the contract. On 28 October 2014, NSS issued a notice to TCS that it elected to terminate the contract as a result of TCS’s alleged substantial breach. On 20 November 2014, the superintendent issued a certificate for liquidated damages for late completion, totalling $352,500.00. On 28 November 2014, TCS issued a notice to NSS that it had elected to terminate the contract for NSS’s repudiation. It followed that the contract was terminated by no later than 28 November 2014. On 28 January 2015, TCS received a notice from NSS advising that it intended to have recourse to the bank guarantees in order to offset claims for current and future rectification costs, along with the certified liquidated damages for late completion up to 15 January 2015. TCS disputed both claims. cdilawyers.com.au 3. that there was no amount due and payable under the terms of the contract; section 67J of the Queensland Building and Construction Commission Act 1991 (Qld); and an equitable right to the return of the guarantees. Reasoning of Justice P Lyons Most significant was His Honour’s reasoning as to when, and on what grounds, a party may have recourse to security provided for performance. Clause 5.2 of the AS 4902 – 2000 contract provided: “[Security] …shall be subject to recourse by a party who remains unpaid after the time for payment where at least five days have elapsed since that party notified the other party of its intention to have recourse." Lyons J adopted the Full Court’s reasoning in Clough Engineering Limited v Oil and Natural Gas Corporation Limited that the terms of a contract need to be construed in each particular case and that clear words are required to support a construction that inhibits a beneficiary from calling on a performance guarantee where a breach is alleged in good faith, i.e. not fraudulently. However, His Honour took a different view of the effect of clause 5.2 than had previously been expressed by Siopis J in Redline Contracting Pty Ltd v MCC Mining (Western Australia) Pty Ltd (No 2) (Redline) which featured a clause 5.2 in identical terms. In Redline, Siopis J adopted the approach taken in a line of cases including the Victorian Court of Appeal cases of Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd and Bachmann Pty Ltd v BHP Power New Zealand Ltd, both of which were approved by the Full Federal Court in Clough. His Honour concluded that the likely construction of clause 5.2 was that it allocated risk to a particular party when a dispute arose, and that recourse to security would not be conditional upon there being an undisputed amount due and payable. His Honour considered that it would be sufficient for a party resorting to security to honestly believe that there was an amount due and payable and that recourse would not be precluded simply by reason of the disputed claim being an unliquidated claim for damages. Lyons J took the view that clause 5.2 of the contract regulated the conduct of NSS in two ways. Firstly, NSS was required to give notice that it intended to have recourse to the security, and secondly, NSS could only have recourse where there was a time for payment and it remained unpaid after the expiration of that time. His Honour found that, with respect to the rectification works, that there was no basis on which it could be said that an amount had been determined as payable, or a time for payment determined. The demand from NSS was not sufficient and merely particularised a claim for unliquidated damages. With respect to the claim for liquidated damages for late completion, His Honour took the view that it was strongly arguable that, for the purposes of determining whether recourse could be had under clause Update 5.1, the mechanism in clause 29.3 of the contract gave the principal a right to the payment of an amount due at that time. Lyons J rejected TCS’ argument that practical completion had been deemed to have been extended by the superintendent’s failure to respond to EOT claims, as the relevant claims had not been made by TCS within time. Having found that TCS had real difficulty in establishing an entitlement to restrain NSS only with reference to the terms of the contract, His Honour then considered whether NSS was obliged to have given a notice under section 67J of the Queensland Building and Construction Commission Act 1991. His Honour determined that it was not arguable that TCS had an accrued right to be given notice under section 67J following termination of the contract, on the basis that the language of the section and its general structure were that it did not remain operative after termination. Further, clause 34.7 of the contract contemplated that an amount for liquidated damages could be certified after termination. Conclusion The decision was made in the context of an AS 4902 -2000 contract and in circumstances where the QBCC Act did not apply by reason that the contract had been terminated. @cdilawyers.com cdilawyers.com.au Lyons J has casted doubt as to whether the approach taken in Redline is correct, and suggests that there must be more than a bona fide belief that an amount is due and payable or that there is an unliquidated amount claimed for damages, where there is a contractual mechanism for the superintendent to certify amounts as due and payable. Ultimately, the position remains that clear words will be required to have the effect of limiting the principal’s entitlement to have recourse to security. It remains to be seen whether Lyons J’s interpretation of clauses such as those in the unamended clause 5.2 of AS4902 - 2000 will be followed in Queensland or whether the more established line of authority adopted in Redline prevails. If the QBCC Act does still apply to the contract, the requirement of section 67J that the amount proposed to be deducted is an amount “owed” will preclude recourse where the amount is merely “claimed to be owing” but not, in truth, payable or owed under the contract. What this means for you Principals should consider amending their contracts to preserve the entitlement to have recourse to security where they hold a bona fide belief that an amount is due and payable or will become due and payable. Contractors should seek a more balanced clause, at the minimum with the protection afforded by the unamended form in AS 4902. Key Contacts Stephen Pyman Principal p. 07 3367 7102 e. [email protected] Gareth Rogers Principal p. 07 3367 7104 e. [email protected] Josh Kemp Principal p. 07 3367 7103 e. [email protected]