CSB: Lighting Columns (3) - Installation DS/CSB/512
Transcription
CSB: Lighting Columns (3) - Installation DS/CSB/512
Issue No 03 Issue Date July 09 Concrete Step Barrier Design Guidance CSB: Lighting Columns (3) - Installation Associated Data Sheets DS/CSB/510 DS/CSB/511 APPLICATIONS •Signs and gantries •Lighting columns Design Guidance Notes Installation The recommended method of installation of lighting column anchorages is by post drilling as this ensures continuity of the slipforming process. All anchorages must be fixed at the correct centres to suit the flange plate design and must be parallel to the axis of the column. The drilling system proposed by the installer must demonstrate a proven capability to achieve this requirement. It is important to ensure that the drill is vertically plumb. Drilling into WCSB (Figure 1a and 1b) must use a diamond core system for any drill hole ≥20 mm diameter x 50 mm depth to avoid damage to the concrete from rotary percussion methods. Figure 1b Drilling should only take place whenthe concrtete has reached a compressive strength of 25 N/mm2. The illustrations show the SSR-128-Karat-164 diamond core drilling system by Fixing Centre Ltd. Drilling for flange plate anchors Figure 1a Removing concrete core Drilling for flange plate anchors 1 BS 5080 - 1 Structural fixings in concrete and masonry. Method of test for tensile loading. CONCRETE STEP BARRIER Design Guidance Prepared for Britpave by Arup DS/CSB/512 CSB: Lighting Columns (3) - Installation CSB: Lighting Columns (3) - Installation DRAWINGS CSB/1005 CSB/1006 CSB/1007 DS/CSB/512 THE KNOWLEDGE DS/CSB/512 CSB: Lighting Columns (3) - Installation THE KNOWLEDGE Issue No 03 Issue Date July 09 Weep holes Figure 2 Where weep holes are required (Figure 3), they should be located at the bottom of the cable trough. Weep holes should have a gradual downward slope from the base of the trough to the outer face of the barrier to facilitate drainage. Accuracy of drilling is essential and only diamond coring systems should be used to avoid damage to the barrier concrete. Weephole location should not coincide with lighting column locations. Weepholes are typically 30 mm diameter. However dimensions should be determined by the designer on a project specific basis. Figure 3 Cable trough Weep hole Finished Road Level TWCSB with weep hole Finished installation Britpave Riverside House, 4 Meadows Business Park, Station Approach, Blackwater, Camberley, Surrey GU17 9AB Website www.britpave.org.uk Facsimile 01276 33160 E-mail [email protected] Standard anchor centres for flange plates are as Table 1 below: Column height Figure 4 Anchor centres WCSB TWCSB (with trough) 12 m 300 mm x 300 mm 400 mm x 400 mm 15 m 300 mm x 300 mm 400 mm x 400 mm Table 1: Anchor centres for standard flange plates Note: 300 mm x 300 mm is the standard detail A typical installation rate is eight to twelve anchorage sets per shift, for a two-man team working with a drilling rig. Installing weep holes Testing Tensile axial load site tests are required to demonstrate that the anchors have been installed correctly. The project engineer should nominate which anchors are to be tested. Testing should not take place until the concrete reaches its 28 day strength (i.e. 35 N/mm2). The test load should be set at the nominal load in the anchor at the collapse of the column increased by 10% (serviceability limit state). Testing should conform to BS 5080-11 using incremental loading as clause 7.13. CONCRETE STEP BARRIER Design Guidance Prepared for Britpave by Arup DS/CSB/512 CSB: Lighting Columns (3) - Installation