Section 12 â Earth Works Related to Buildings
Transcription
Section 12 â Earth Works Related to Buildings
QCS 2014 Section 12: Earth Works Related to Buildings Part 01: General Page 1 GENERAL ...................................................................................................... 2 1.1 INTRODUCTION ........................................................................................... 2 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 1.1.8 1.1.9 Scope References Ground Investigation Site Clearance Preservation of Property Not to be Affected by the Works Disposal of Historical Artefacts Special Requirements of Utility Authorities Control of Ground Water Record Procedure AM TC 1 2 2 2 3 3 4 4 4 4 QCS 2014 Section 12: Earth Works Related to Buildings Part 01: General Page 2 GENERAL 1.1 INTRODUCTION 1.1.1 Scope 1 This Section specifies the requirements for excavation and filling as necessary to facilitate the construction of the Works. It does not include earthworks associated with trenches for pipelines or service ducts. 2 The cost of all operations needed for the excavation and disposal work as required and specified, including temporary and permanent support work, breaking, loading, hauling and dumping in accordance with the provisions of the Project Documentation shall be included in the Contractor’s rates. 3 The Contractor shall be deemed to have examined the site and verified for himself the exact nature and quality of the materials to be excavated. The Contractor shall carry out his own survey of the existing ground levels and satisfy that the quantities of all excavated and imported materials are correct. 4 Removal operations shall be conducted with the least interference to the public and shall not be started until approved by the Engineer. 5 Related Sections and Parts are as follows: TC 1 Filling Section 1 Section 2 Section 6 Section 8 Section 28 General Building Demolition Roadworks Sewerage Landscaping AM This Section Part 3 1.1.2 References 1 The following standards are referred to in this Section: BS 812........................Testing Aggregates BS 1377 .....................Methods of test for soils for civil engineering purposes BS 6906 .....................Methods of tests for geotextiles 1.1.3 Ground Investigation 1 The Contractor shall be deemed to have satisfied himself as to the character of the Site and all the various materials, strata, ground water levels, etc., and of all items liable to affect, or be encountered in, the excavations and earthworks. QCS 2014 Section 12: Earth Works Related to Buildings Part 01: General Page 3 If a ground investigation is not included in the Project Documentation the Contractor shall immediately after taking possession of the Site prepare a minimum of two trial pits in positions to be agreed with the Engineer. Chemical analysis tests are to be carried out on the materials from each of the pits and the results submitted to the Engineer. Similarly, chemical analysis tests shall be carried out on any water present in the pits and the results submitted to the Engineer. Ground investigation tests in accordance with the relevant provisions of BS 812, BS 1377 and BS 6906 shall be undertaken where geotextiles are to be used for temporary or permanent protection. 3 The Contractor shall inform the Engineer when the trial pits are ready for inspection and shall not commence excavation work until approval to proceed has been given. All trial holes and their subsequent backfilling shall be carried out at the Contractor’s expense and will only be allowed in positions approved by the Engineer. All trial holes shall be backfilled as soon as the required information has been obtained and open excavations shall be adequately protected and cordoned off using temporary lights and barriers or similar method approved by the Engineer. 4 If a ground investigation is included in the Project Documentation, it is provided solely for the guidance of the Contractor and no guarantee is given regarding its accuracy, nor is it guaranteed that similar conditions apply elsewhere on the Site. 1.1.4 Site Clearance 1 Before commencing any excavation or fill, the area shall be cleared of all trees, stumps, roots, bushes, vegetation, debris, materials or other obstructions. 2 Before removal of any trees or shrubs the Contractor shall obtain written consent from the Engineer at least two weeks in advance of the planned removal. 3 All bushes, undergrowth, etc. to be removed shall be grubbed up and disposed of in a manner as agreed with the Engineer. Holes left by stumps or roots shall be filled with suitable material, compacted to the Engineer’s satisfaction in accordance with Part 3 of this Section within one week of the work being performed. 4 The Contractor shall at his own expense make good any damage done to other property during the site clearing. Sweet soil excavated during the course of these works shall be preserved and protected by the Contractor, until removed by the Employer or until the expiration of the Contract. 1.1.5 Preservation of Property Not to be Affected by the Works 1 Attention is directed to the Contractor’s obligations with regards to damage, particularly with regard to protection of property, plants and landscape and to responsibility for damage claims. 2 The form of protection to vegetation within the Site shall be as agreed with the Engineer. AM TC 2 QCS 2014 Section 12: Earth Works Related to Buildings Part 01: General Page 4 1.1.6 Disposal of Historical Artefacts 1 Where specified, certain materials arising from site clearance and excavation work are to remain the property of the Owner. All fossils, antiquities and other objects of interest or value which may be found or uncovered on the Site shall remain or become the property of the Owner. Upon discovery of such an object the Contractor shall forthwith: (a) use his best endeavours not to disturb or damage the object (b) cease work which would endanger the object or prevent or impede its removal (c) inform the Engineer of the discovery and precise location of the object. The Engineer will issue an instruction on the procedure to be adopted which may include conditions to permit the examination, excavation or removal of the object by a third party. 1.1.7 Special Requirements of Utility Authorities 1 Prior to commencing excavation work, the Contractor shall ascertain from the responsible Utility Authorities whether any mains or services need to be diverted or cut-off in accordance with the procedure described in Part 19 of Section 1. 1.1.8 Control of Ground Water 1 Prior to the commencement of construction at any particular location, the Contractor shall install and maintain a system of standpipes and other devices to monitor ground water levels in any area, which in the opinion of the Engineer, is likely to be affected by the dewatering. The number, location and depth of all standpipes shall be to the satisfaction of the Engineer. 2 The Contractor shall check ground water levels weekly or when instructed by the Engineer. The results of such checks shall be submitted to the Engineer in a written report within 24 hours of the level being taken. The format of the report shall be as agreed with the Engineer. 3 In the case of uncontrolled flow of water into any excavation, the Engineer reserves the right to order the Contractor to take immediate action to control the inflow of water. Such actions and remedial works shall be to the Engineer’s approval. 1.1.9 Record Procedure 1 If the Engineer requires foundation or formation level depths to be varied from those shown on the drawings it shall be the responsibility of the Contractor to ensure that proper records of the actual excavated levels are kept. AM TC 2 END OF PART QCS 2014 Section 12: Earth Works Related to Buildings Part 02: Excavation Page 1 2 EXCAVATION ................................................................................................ 2 2.1 GENERAL ...................................................................................................... 2 2.1.1 2.1.2 Scope References 2.2 EXCAVATION FOR STRUCTURES .............................................................. 2 2.2.1 2.2.2 2.2.3 2.2.4 2.2.5 2.2.6 2.2.7 2.2.8 Excavation Support Removal of Water Approvals Inspection Unsound Materials Over-Excavation Finishing to Excavation Storage of Excavated Material 2.3 MATERIALS .................................................................................................. 4 2.3.1 2.3.2 2.3.3 2.3.4 Excavated Material Common Excavation Rock Excavation Blasting 2.4 DISPOSAL OF SURPLUS MATERIAL .......................................................... 5 2.4.1 General AM TC 2 2 2 3 3 3 4 4 4 4 4 4 5 5 5 QCS 2014 Section 12: Earth Works Related to Buildings Part 02: Excavation Page 2 2 EXCAVATION 2.1 GENERAL 2.1.1 Scope 1 This Section specifies the requirements for the excavation for structures, culverts, headwalls, catch basins, manholes, inlets, retaining walls and the like. The work includes all necessary clearing and grubbing and the disposal of all material resulting from such excavation. The work also includes the provision, and subsequent removal, of all necessary bailing, drainage, pumping, sheeting, strutting, coffer dam construction and crib construction. 2 Rates for excavation shall include for excavation in any material. Excavation in any material shall include common excavation, side shoring, support systems, excavation in artificial hard material and shall be inclusive of all encountered impediments, including roots, boulders etc. Blasting will not be permitted without the written approval of the Engineer. 3 Related Sections and Parts are as follows: Section 1 Section 6 General Roadworks References 1 The following standards are referred to in this Part; TC 2.1.2 AM BS 1377 .....................Method of test for soils for civil engineering purposes 2.2 EXCAVATION FOR STRUCTURES 2.2.1 Excavation Support 1 Prior to Commencing any structural excavation work which is 1.5 m or greater in depth, the Contractor shall design an excavation support system. 2 Details of the excavation support system shall be submitted to the Engineer for review and approval at least one week before any excavation work commences. Details of the excavation support system shall be complete with, but not limited to, the following: (a) drawings of the structural support members showing materials, sizes and spacing, (b) calculations showing the maximum theoretical deflection of the support member. 3 The system is to be designed so that no members extend through surfaces exposed in the finished construction, and no shoring or bracing is placed under permanent structures. 4 The Contractor shall submit to the engineer calculations of lateral earth pressure for the full excavation depths, surcharge loads of any description, equipment loads, forces at various stages of support during excavation, the maximum design loads to be carried by various members of the support system and strut pre-load forces. 5 If the structure support system proposed includes tieback anchors, the Contractor’s submitted details shall include drawings that show the profile of the soil in which each anchor is to be installed. QCS 2014 Section 12: Earth Works Related to Buildings Part 02: Excavation Page 3 Tieback anchors that project beyond the vertical limits of the Site boundary on to adjoining property shall only be permitted if permission to do so is given by the owner of the property in writing. Copies of such written permission shall be submitted to the along with excavation support system proposals. 2.2.2 Removal of Water 1 At locations where the excavation extends below the groundwater table, a dewatering system is to be provided which will lower ambient groundwater levels. The resulting groundwater level shall be at a depth which is sufficiently below the excavation level so as to allow the safe and proper execution of the work. The resulting foundation level shall be a stable, dry sub-grade which is suitable for the execution of subsequent operations. 2 The Contractor is to design the dewatering methods and settling basins so that no critical amounts of soil, sand or silt are removed during either the dewatering operations. 3 Complete working drawings showing the type of dewatering and groundwater control system proposed shall be submitted to the Engineer for his review. The Contractor’s submittal shall include drawings that show the arrangement, location and depths of the proposed dewatering system. A complete description of the equipment and materials to be used and the procedures to be followed to be given, together with details of required standby equipment and standby power supply. The Contractor shall also indicate his proposed location(s) for the discharge of extracted groundwater. 4 The dewatering system design should also include the details of measures required to prevent damage due to settlement of roads, pavements, utilities, sewers, buildings and other structures outside the excavation but within the area affected by the dewatering. 2.2.3 Approvals 1 The designs of the structure excavation support system and the dewatering systems specified above is to be prepared by and signed by a qualified engineer experienced in this type of design work. Approval of the designs and shop drawings will not relieve the Contractor of the adequacy and performance of these temporary works. 2.2.4 Inspection 1 In addition to the provisions of Part 13 of Section 1, the Contractor shall also undertake the following described in the following Clauses unless otherwise instructed by the Engineer. 2 Following a detailed inspection of all adjacent structures, the Contractor shall prepare a report on the pre-construction condition of all structures that may be affected during construction of the Works. The report will include photographs, drawings and sketches with levels and dimensions fully illustrating the structure's condition. In particular, it shall note any existing damage or structural inadequacy. Deficiencies and damage are to be suitably marked on the structure in a way that it is not permanently defaced. 3 Three (3) copies of the Report shall be submitted for the approval of the Engineer. Once approved, five (5) additional copies shall be supplied to the Engineer. 4 The Contractor shall carry out a survey of levels of undisturbed ground before commencing any excavations. AM TC 6 QCS 2014 Section 12: Earth Works Related to Buildings Part 02: Excavation Page 4 When the excavation has been carried down to formation level the Contractor shall advise the Engineer’s Representative that the excavation is ready for inspection and the Engineer’s Representative shall, without reasonable delay, inspect the excavation unless he considers it unnecessary. 2.2.5 Unsound Materials 1 Any loose, improperly compacted, soft or other unsuitable material which is encountered below or adjacent to structural foundation levels shall be completely removed, backfilled with a suitable material and compacted to 95% of the maximum dry density as determined by BS 1377 Part 4. Backfilling shall be done in layers with an unconsolidated thickness not exceeding 200 mm up to the foundation level. The limits of such work shall be as directed by the Engineer. Alternatively, the Engineer may instruct that removed material be replaced with Class C25 concrete. 2.2.6 Over-Excavation 1 Any over excavation is to be backfilled with Class C25 concrete at the Contractors expense. 2.2.7 Finishing to Excavation 1 All rock or other hard foundation material is to be cleaned of all loose material. All seams or crevices are to be cleaned and grouted. All loose and disintegrated rock and thin strata is to be removed. 2 When the structure is to rest on material other than rock, excavation to final grade should not be made until just before the structure is to be placed/constructed and special care is to be taken not to disturb the excavated surface. The surface required shall be rolled and compacted to 95% of the maximum dry density. 2.2.8 Storage of Excavated Material 1 Excavated material is not to be stored or deposited in such a way as to endanger structures or cause an obstruction of any kind. 2.3 MATERIALS 2.3.1 Excavated Material 1 All excavated material will be the property of the Owner and no material shall be removed, transported and disposed of without the prior written approval of the Engineer. 2.3.2 Common Excavation 1 Common excavation consists of the excavation and satisfactory disposal of all soils, certain strata and rock boulders less than one (1) cubic metre in volume. Strata which are altered and weathered and are in place, but which are not firm enough, or in the opinion of the Engineer are not rigid enough to have all the characteristics of rock excavation is to be classified as common excavation. AM TC 5 QCS 2014 Section 12: Earth Works Related to Buildings Part 02: Excavation Page 5 2.3.3 Rock Excavation 1 Rock excavation consists of the excavation and satisfactory disposal of all unaltered and unweathered firm and rigid igneous, metamorphic and sedimentary solid rock that in the opinion of the Engineer can only be excavated by the use of pneumatic hammers or other such similar apparatus. 2.3.4 Blasting 1 Blasting will not be permitted without prior approval. (Refer to Section 6: Roadworks). 2.4 DISPOSAL OF SURPLUS MATERIAL 2.4.1 General 1 All materials arising from site clearance or excavation which are surplus, suitable or unsuitable for use in the Works will become the property of the Owner and will not be disposed of by the Contractor either off the Site to an approved tip without written approval from the Engineer. If directed, or otherwise agreed by the Engineer, the Contractor may dispose of surplus material on the Site in an approved manner as directed by the Engineer. AM TC END OF PART QCS 2014 Section 12: Earth Works Related to Buildings Part 03: Filling Page 1 3 FILLING ......................................................................................................... 2 3.1 GENERAL ...................................................................................................... 2 3.1.1 3.1.2 Scope References 3.2 EARTHWORKS MATERIALS ........................................................................ 2 3.2.1 3.2.2 3.2.3 3.2.4 Top Soil Suitable Material Unsuitable Material Utilisation of Excavation Materials 3.3 MAIN PLANT FOR EARTHWORKS CONSTRUCTION ................................ 3 3.3.1 General 3.4 BACKFILLING ............................................................................................... 3 3.4.1 General 3.5 COMPACTING IMPORTED OR SELECTED EXCAVATED FILL MATERIAL ..................................................................................................... 4 3.5.1 3.5.2 General Water 3.6 FILL BELOW GROUND SLABS .................................................................... 5 3.6.1 General 3.7 FILLING ......................................................................................................... 5 3.7.1 Concrete Blinding 2 2 2 2 3 3 3 AM TC 3 4 5 5 5 QCS 2014 Section 12: Earth Works Related to Buildings Part 03: Filling 3 FILLING 3.1 GENERAL 3.1.1 Scope 1 This Part specifies materials for filling purposes. 2 Related parts and Section are as follows: Page 2 This Section Part 2 Section 6 Excavation Roadworks 3.1.2 References 1 The following Standards are referred to in this Part: BS 812........................Testing Aggregates BS 1377......................Methods of test for soil for civil engineering purposes EARTHWORKS MATERIALS 3.2.1 Top Soil 1 Top soil is to be fertile, friable soil obtained from well drained arable land and to be free draining, non-toxic and capable of sustaining healthy plant growth. 3.2.2 Suitable Material 1 Suitable material for earthworks shall be approved soil with a liquid limit not exceeding 35% and a plasticity index not exceeding 10%. The material passing the 0.075 mm sieve shall not exceed 20% and the organic matter content shall not exceed 2% (as determined by BS 1377 – Part 3). 2 Where excavated rock is to be used as fill material elsewhere on the site, the Contractor is responsible for ensuring that the excavated rock meets the requirement of the Specification for fill material. 3 The Contractor is responsible for mixing the excavated rock with suitable fill material imported and/or excavated from within the site should it be necessary in order to produce a suitable fill material that complies with the requirements of the Specification and he should allow in his rates and programme for carrying out the work. 4 Sweet soil and any excavated materials which are considered re-usable by the Engineer, shall be preserved and protected by the Contractor, until they are removed by the Owner or until the expiration of the Contract. AM TC 3.2 QCS 2014 Section 12: Earth Works Related to Buildings Part 03: Filling Page 3 5 No excavated suitable material is to be removed from the Site without the Engineer’s written permission. Should the Contractor be permitted to remove suitable material from the site to suit his operational requirements, then he is to make good any consequent deficit or filling arising therefrom at his own expense. 3.2.3 Unsuitable Material 1 Unsuitable materials include: rock particle exceeding 75mm in size (b) organic material (as defined in BS 1377 Part 3) containing greater than 2% stumps and other perishable material (c) material susceptible to spontaneous combustion (d) soils of a liquid limit exceeding 35% and/or a plasticity index exceeding 10%. (e) material containing more than 5% of water soluble salts by weight of dry soil (individually, water soluble chloride exceeding 1% or water soluble sulphate exceeding 1.5%) or more than 10% of acid-soluble salts (individually, acid soluble chloride exceeding 2% or acid soluble sulphate exceeding 3.0%) as determined by BS 1377: part 3 (f) any other material which the Engineer may deem to be unsuitable for earthworks TC (a) Utilisation of Excavation Materials 1 All excavated material determined as suitable by the Engineer, is to be utilised as backfill. The surplus material shall be disposed of as specified in Part 2 of this Section. 3.3 MAIN PLANT FOR EARTHWORKS CONSTRUCTION 3.3.1 General 1 The Contractor is to employ only plant which is suited to the soils to be handled. He should not at any time use plant which damages or reduces the natural strength of the soil either in its in-situ state or during handling and placing or in its final compacted state. Unsuitable or faulty plant shall be removed from the work site and borrow pits at the order of the Engineer. 3.4 BACKFILLING 3.4.1 General 1 Excavation is only be backfilled after the permanent works therein have been approved and after the removal of any building debris or deleterious material from the excavations. 2 Selected excavated material will normally be used or backfilling in the manner described in Clause 3.5 of this Part. Where the excavated material is not considered suitable, selected material form an approved source is to be used. 3 The backfill will be brought to a suitable level above grade to provide for anticipated settlement and unless indicated otherwise, is to be sloped away from the structure. AM 3.2.4 QCS 2014 Section 12: Earth Works Related to Buildings Part 03: Filling Page 4 The bottom of all excavations are to be probed and any poor bearing area shall be reported to the Engineer who will direct remedial work. Soft spots and other unsound materials are to dealt with as specified in Part 2 of this Section. 5 In circumstances where backfill has to be deposited below standing water, only rock, as specified in Section 6, Roadworks, is to be used. 3.5 COMPACTING IMPORTED OR SELECTED EXCAVATED FILL MATERIAL 3.5.1 General 1 Fill to be compacted by a suitable plate type vibrator, pedestrian operated vibrator roller, small tandem roller or other approved compaction plant. 2 The material is to be placed in layers within the effective range of compaction of the plant provided that the maximum loose (uncompacted) thickness of each layer dose not exceed 200 mm. 3 The material is to be watered and mixed as necessary to ensure that prior to compaction the moisture content of the whole layer is ± 3% of the optimum moisture content. Compaction of each layer is to continue until a density of a least 95% of the maximum dry density has been achieved. 4 The dry density/moisture content relationship will be determined by the heavy compaction test (4.5% rammer method) of BS 1377. 5 All fill material used in earthworks shall be compacted as per related Specification by plant approved by the Engineer for that purpose. If required by the Engineer the Contractor shall carry out compaction trials on the material supplemented by laboratory testing to determine the correct plant and number of passes required to achieve the specified requirements. 6 Potable water shall be used for compaction of all fill material within the area of excavation. 7 The Contractor shall carry out moisture content determinations at frequent intervals or when there is a change in the material on the soils undergoing compaction so as to ensure that the moisture content of the soil is within the optimum range for the field compaction determined from compaction trials. 8 All adjustment of moisture content shall be carried out in such a way that the specified moisture content remains uniform through out compaction. 9 No completed fill layer shall be covered by the next layer until it has been tested, inspected and approved by the Engineer. 10 The finished surface of earthworks for paved surfaces (other than public roads) shall be shaped and rolled and then tested for accuracy so that maximum local irregularities in the finished profiles lie within the tolerance of 20mm for formation, as well as 10mm and 5mm respectively for longitudinal and transverse profiles of finished surfaces, when tested by a straight edge or level instrument. The frequency of local irregularities shall be at the discretion of the Engineer. AM TC 4 QCS 2014 Section 12: Earth Works Related to Buildings Part 03: Filling Page 5 Where fill material is to be deposited in areas where the existing ground is sloping, the Contractor shall excavate benches so that fill material is deposited onto a horizontal surface. The levels of the benching terraces shall match the layers of the fill material that are deposited in the adjacent areas. 3.5.2 Water 1 The water to be mixed with the soil / fill materials to achieve the desired moisture content in the filling / earthworks operations shall be potable. 3.6 FILL BELOW GROUND SLABS 3.6.1 General 1 The installation of cable ducts for service entries and service pipework is to be completed before placing of the fill to receive the ground slab. 2 The compacted fill or hardcore is to be shaped and trimmed to the required levels and dimensions and blinded with sand. 3.7 FILLING 3.7.1 Concrete Blinding 1 Immediately on completion of excavations for concrete structures a blinding layer of concrete Grade OPC 25 not less than 75mm thick shall be placed to prevent deterioration of the formation and to provide a clean working surface for the structure. AM TC 11 END OF PART QCS 2014 Section 12: Earth Works Related to Buildings Part 04: Utility Trenches Page 1 4 UTILITY TRENCHES ..................................................................................... 2 4.1 GENERAL ...................................................................................................... 2 4.1.1 4.1.2 4.1.3 4.1.4 Scope References Excavation of Utility Trenches Backfilling of Utility Trenches AM TC 2 2 2 2 QCS 2014 Section 12: Earth Works Related to Buildings Part 04: Utility Trenches Page 2 4 UTILITY TRENCHES 4.1 GENERAL 4.1.1 Scope 1 This Part specifies the requirement for utility trenches. It does not include trenchworks for pipelines and service ducts. 2 Related Sections and Parts are as follows: This Section Part 2 Filling Part 3 Excavation 4.1.2 References 1 The following standards are referred to in this Part: BS 1377 Methods of tests for soils for civil engineering purposes. Excavation of Utility Trenches 1 The trench to be excavated with the width and to the depth shown on the drawings or as indicated by the Engineer. 2 The sides of pits and trenches are to be vertical and adequately supported at all times. Excavation may if considered necessary be battered with a safe slope, but only with the Engineer’s written permission. 3 Care is to be taken to excavate to the depths indicated. Where rock is encountered, the rock is to be excavated 150 mm lower than the required depth. Such depth in rock is to be backfilled with approved fill material and compacted as specified and/or as directed by the Engineer. 4 Excavated material will, if found unsuitable as defined in Part 3 of this Section, be disposed of to an approved tip and replaced with suitable material. All surplus material to be disposed of in accordance with Part 2 of this Section. 4.1.4 Backfilling of Utility Trenches 1 After the utilities have been laid, the trench refilling is to commence with approved fill in compacted layers not exceeding 150 mm unconsolidated thickness. Each layer shall be well compacted by hand with iron rammers weighing not less than 5 kg, until the trench has been filled to a height of 300 mm above the top of the utility. 2 The remainder of the trench is then to be refilled in compacted layers not exceeding 250 mm unconsolidated thickness. Each layer being well compacted, with power rammers, vibrating plate compactors or other mechanical means of a type to be approved until the ground is thoroughly consolidated up to the required level for surface reinstatement. Each layer is to be compacted to 95% of its maximum dry density as determined by BS 1377. AM TC 4.1.3 QCS 2014 Section 12: Earth Works Related to Buildings Part 04: Utility Trenches Page 3 3 Trenches are not to be backfilled until all required tests are performed on the utilities and until the Engineer has verified that the utilities have been installed in accordance with the Project Documentation. 4 Where cover to utilities is less than 400 mm, or where ordered by the Engineer, protection in the form of precast concrete tiles is to be provided according to an approved drawing or as ordered by the Engineer. 5 PVC warning tape shall be laid above the utility or the concrete tiles, after partial backfilling and approximately 300 mm below finished ground level. AM TC END OF PART QCS 2014 Section 12: Earth Works Related to Buildings Part 05: Installation of Protective Membranes Page 1 5 INSTALLATION OF PROTECTIVE MEMBRANES ....................................... 2 5.1 GENERAL ...................................................................................................... 2 5.1.1 5.1.2 5.1.3 Scope References General Requirements AM TC 2 2 2 QCS 2014 Section 12: Earth Works Related to Buildings Part 05: Installation of Protective Membranes Page 2 5 INSTALLATION OF PROTECTIVE MEMBRANES 5.1 GENERAL 5.1.1 Scope 1 This Part specifies geotextile fabric systems used for temporary or long term stabilisation of earthworks during construction. 2 Related Sections and Parts are as follows: Section 5 Concrete Section 6 Roadworks 5.1.2 References 1 The following standards are referred to in this part: BS 6906......................Methods of test for Geotextiles General Requirements 1 In areas where the Engineer deems the use of geotextile fabric necessary, the Contractor is to furnish and place geotextile fabric as specified and as directed by the Engineer. TC 5.1.3 AM The geotextile fabric furnished by the Contractor is to be of an approved grade suitable for placement over fine sand. The geotextile fabric shall be a woven or non-woven fabric consisting only of long chain polymeric filaments or yarns formed into a stable network such that the filaments or yarns retain their relative position to each other. The fabric is to be stabilised against ultra violet light, inert to commonly uncounted chemicals and chemical properties of the in-situ soil and water, and it should conform to the following minimum requirements: Weight 135 g/m 2 2 2 Thickness under load (2 kN/m ) 0.7 mm Tensile Strength (200 mm width) ASTM D1682 1.6 kN Puncture Resilience (DIN 54307) 1.5 kN Permeability 50 litres/m /s 2 The surface to receive the geotextile fabric is to be prepared to a relatively smooth condition free of obtrusions, depressions, and debris. The geotextile fabric should not be laid in a stretched condition. In the event that the width of the proposed area for fabric requires more than one panel width of fabric, the panels are to be overlapped a minimum 15 percent of the panel width. Longitudinal joints in the fabric are to have an overlap of 500 mm. To prevent slippage of the overlapping fabric, the areas of overlap are to be stabilised as approved by the Engineer with pins, anchor blocks, or aggregate piles. In the event that construction machinery is used to place the fabric, the working platform for the machinery should be the soil and not the previously laid fabric. QCS 2014 Section 12: Earth Works Related to Buildings Part 05: Installation of Protective Membranes Page 3 3 Prior to placement of the granular material (stabilising crushed material) the Contractor is to spread a layer of sand over the geotextile fabric as directed by the Engineer. The aggregate material should not be dumped directly on the fabric. Haulage trucks are not to be driven on the fabric. The aggregate is to be spread by a wheeled front-end loader. The blade or bucket is to be kept sufficiently high so that the aggregate is not being pulled over the fabric, but being dropped at a minimum height to the satisfaction of the Engineer. 4 Fabric damaged or displaced before or during installation or during placement of overlaying aggregate material is to be replaced of repaired to the satisfaction of the Engineer at the Contractor’s expense. 5 Where pipes or other elements pass through the geotextile fabric, the openings around such are to be made watertight by methods as approved by the Engineer. AM TC END OF PART