Severna Park High School
Transcription
Severna Park High School
ANNE ARUNDEL COUNTY PUBLIC SCHOOLS Severna Park High School Feasibility Study January 21, 2011 GWWO, Inc./Architects 800 Wyman Park Drive, Suite 300 Baltimore, MD 21211 410.332.1009 KCI Technologies Site Engineering Weigand Associates, Inc. M/P/E Engineering Faisant Associates, Inc. Structural Engineering Oak Contracting, LLC Cost Estimating Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects Table of Contents Study Team ............................................................................................................................ 1 Executive Summary ................................................................................................................. 3 Introduction ............................................................................................................................ 6 Purpose .................................................................................................................................. 8 History .................................................................................................................................... 9 Existing Conditions ................................................................................................................. 10 Code Analysis ......................................................................................................................... 45 Option A – Do Nothing ............................................................................................................. 47 Option B – Patch and Paint....................................................................................................... 48 Option C – Revitalization ......................................................................................................... 50 Option D – Modernization ........................................................................................................ 60 Option E – Replacement ‘A’ ...................................................................................................... 70 Option F – Replacement ‘B’ ..................................................................................................... 78 Appendix A – Detailed Cost Estimates ...................................................................................... 85 Appendix B – Life Cycle Cost Comparison ................................................................................. 92 Appendix C – Project Schedules ............................................................................................... 93 Appendix D – Function and Area Summaries ............................................................................. 98 Appendix E – Sustainable Design ........................................................................................... 109 Appendix F – Building Security and Site .................................................................................. 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland STUDY TEAM Severna Park High School Representatives Patrick Bathras Principal Kurt Maisel Assistant Principal Pat Lynard Business Manager Wayne Mook Athletic Director Amy Lippincott Art Department Chair Marianne Fitzgerald Media Specialist Timothy Dunbar Social Studies Chair Brad Hill Technology Education Chair Andrea Willey Signature Program Facilitator Vicki Wuest Counselor Taylor Davenport Student Colin Heil Student Maryland State Department of Education Gloria Mikolajczyk School Facilities Architect Supervisor Community Representatives Leette Reynolds Gwen Douma Harring Terra Snider Maureen Carr-York PTSO CAC CAC Greater Severna Park Council AACPS Lisa Seaman Crawford Catherine Herbert Larry Alberts Greg Stewart Mary Patz Acting Director of Facilities Regional Assistant Superintendent Manager of Planning Senior Manager of Design Design Architect Architects and Engineers Alan Reed John Easterling Brian Eschman Sarah Gratz Michael Lambert Michael Weigand Atul Patel GWWO, Inc./Architects GWWO, Inc./Architects GWWO, Inc./Architects GWWO, Inc./Architects KCI, Inc. (Civil) Weigand Associates, Inc. (MEP) Faisant Associates, Inc. (Structural) Construction Manager Joe Tiberi Steve Krell Oak Contracting, LLC (Cost Estimating) Oak Contracting, LLC (Cost Estimating) Page 1 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland This page intentionally left blank. Page 2 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects EXECUTIVE SUMMARY Constructed in 1957, with a major addition in 1971, Severna Park High School in Severna Park, Maryland is well maintained and structurally sound. However, it does not provide an optimum teaching and learning environment for the students of Anne Arundel County. As it exists, the facility does not meet the current Educational Specifications requirements for a standard Maryland high school in several categories of program and area. Overall, the physical learning environment at Severna Park High School is deficient due to a lack of space, inflexibility of the existing spaces, a dearth of natural light in classrooms, aging building systems, and a sprawling layout. Site safety and vehicular circulation are difficult to manage as buses line up in the same lanes as parents and wind through the staff parking lot. This study was commissioned to assist the Board of Education in assessing its options to improve Severna Park High School’s facility to meet the approved Educational Specifications. Following AACPS’s established protocol for feasibility studies, five options were evaluated. Due to the significance of considering relocating the existing stadium to fully assess Option E - Complete Replacement On-Site, an alternative on-site replacement scheme was evaluated and is presented in this study as Option F. Conclusions: 1. Option A – Do Nothing In this no cost option, no work would occur on site, or in the building. This option establishes a base line for comparison to other schemes. 2. Option B – Patch and Paint This minimum approach will repair some deferred maintenance items and provide a fresh coat of paint throughout the existing facility. Building and life safety concerns will not be addressed. Building systems will not be updated or replaced. No site improvements will be made to improve circulation and safety. Students will remain in the facility during the maintenance work. 3. Option C – Revitalization Building and life safety issues will be corrected in the existing building. Additions will be constructed to provide new spaces for a gymnasium, physical education department, auditorium, theatre, music, some classrooms, and food service areas. Portions of the existing building are required to be demolished to accommodate the additions. New windows, doors, casework, and finishes will be provided in the remaining areas of the existing building though no significant structural changes will be made. Thus, deficiencies will remain with regard to the area requirements of the Educational Specifications. Site improvements will include a separate lot for bus stacking. Relocatable classrooms will be required as students will remain in the facility during construction. 4. Option D – Modernization This option completely renovates the existing building so that with additions, the facility will comply with all requirements of the Educational Specifications and current codes. The building efficiency is equivalent to Revitalization as the general floor plan is the same and remains expansive. Site circulation and safety are improved with the creation of a separate bus stacking Page 3 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects lot. Relocatable classrooms will be required as students will remain in the facility for the duration of construction. 5. Option E – Complete Replacement On-Site ‘A’ A new facility designed in accordance with the Educational Specifications will comply with current building, life safety, and accessibility codes and standards. Designed to achieve the United States Green Building Council’s (USGBC) Leadership in Energy and Environmental Design (LEED™) Silver certification, the new building will provide a safe, healthy, and inspiring learning environment. To accommodate the existing stadium, the building will be constructed in phases and located on existing play fields. Students will remain in the existing building during construction of the new building, but will also have to occupy the first phase of the new building while the second phase is under construction. Site safety and circulation will be improved. 6. Option F – Complete Replacement On-Site ‘B’ Similar to Option E, this new building will comply with the Educational Specifications, current codes, and be designed to achieve USGBC LEED™ Silver certification. Relocation of the stadium in this option allows for the design of the most compact floor plan which optimizes building efficiency, requires the shortest construction timeframe, minimizes disruptions to school operations, and allows for optimal solar orientation to maximize daylighting in classrooms. Play fields and courts are grouped together efficiently. Site safety and circulation will be improved with full separation of vehicular circulation patterns. Following, on page five, is a comparison of overall building area, estimated construction cost, and 40-year life cycle operational cost between the options. Refer to Appendices A and B for detailed analyses of the construction costs and life cycle costs presented. Page 4 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland PATCH AND PAINT Construction duration will be 1 year. Area of Existing Building Total Estimated Const. Cost* 40-year Life Cycle Cost* 296,191 GSF $5,824,086 $44,095,086 *Costs for replacement of systems are not included. REVITALIZATION Total construction duration will be 4.5 years. Area of Existing Building Area of Demolition Area of Revitalization Area of New Construction Total Area Total Estimate Const. Cost 40-year Life Cycle Cost MODERNIZATION Total Estimate Const. Cost 40-year Life Cycle Cost 296,191 GSF 86,780 GSF 209,411 GSF 151,277 GSF 360,688 GSF $119,174,734 $277,963,468 Total construction duration will be 4 years. Building construction duration will be 2.75 years. Area of Existing Building Area of Demolition Area of Revitalization Area of New Construction Total Area Total Estimate Const. Cost 40-year Life Cycle Cost REPLACEMENT B $103,845,136 $249,320,272 Total construction duration will be 5.5 years. Area of Existing Building Area of Demolition Area of Modernization Area of New Construction Total Area REPLACEMENT A 296,191 GSF 86,780 GSF 209,411 GSF 148,577 GSF 357,988 GSF 296,191 GSF 296,191 GSF 0 GSF 342,517 GSF 342,517 GSF $103,748,361 $242,901,722 Total construction duration will be 3.5 years. Building construction duration will be 2.25 years. Area of Existing Building Area of Demolition Area of Revitalization Area of New Construction Total Area Total Estimate Const. Cost 40-year Life Cycle Cost 296,191 GSF 296,191 GSF 0 GSF 333,735 GSF 333,735 GSF $98,931,568 $232,360,136 Page 5 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects INTRODUCTION This feasibility study was conducted for Anne Arundel County Public Schools. The Study Committee, included educators, planners, parents, community members, architects and engineers as well as a participant from Maryland State Department of Education. The existing State Rated Capacity of the facility is 1,805 and the current Full Time Enrollment is 1,923. Projected Full Time Enrollment in 2016 is 1,819 with a State Rated Capacity of 1,993 upon completion of renovations to bring the facility in to compliance with the approved Educational Specifications. The focus of this study is to evaluate design options for five approaches to modify Severna Park High School. These are as follows: No Changes; Patch/Paint; Revitalization; Modernization; and Replacement School. GWWO, Inc./Architects would like to thank the members of the Severna Park High School Study Committee for their time and effort in helping to develop this study. The Committee’s input and creativity has proved invaluable in understanding and addressing the needs of Severna Park High School. Methodology / Process The Study Committee completed multiple tasks to develop this Feasibility Study. The process involved multiple meetings to identify project goals, evaluate and identify approaches and individual schemes. Additional tasks, including field investigations; review of drawings of the existing building; code/ADA analysis and preliminary reviews were conducted by the Architect/Engineering team to determine the impact of the existing building systems on the various schemes. Based on the above analysis, the Study Committee developed advantages, disadvantages and costs associated with each of the schemes. The Committee then evaluated these factors to consider how each scheme addressed the project goals and facility needs of Severna Park High School. AACPS System Goals: GOAL I – ACADEMIC ACHIEVEMENT All diploma-bound students will reach high standards, as established by Anne Arundel County Public Schools and state performance level standards in English/Reading/Writing/, Mathematics, Science and Social Studies. Achievement disparities among all No Child Left Behind (NCLB) groups of students will be eliminated. GOAL II – SAFE AND SUPPORTIVE LEARNING ENVIRONMENT All students will be educated in a safe, positive, and supportive learning environment with a focus on security enhancements that support system-wide safety and discipline standards. AACPS will eliminate disparities among all No Child Left Behind (NCLB) student groups in the referral, suspension, and expulsion rates for violation of the Code of Student Conduct. Page 6 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects GOAL III – WORKFORCE QUALITY Anne Arundel County Public Schools will ensure and maintain a work environment of respect and mutual collaboration by attracting and retaining a quality work force that demonstrates a commitment to providing a positive learning environment, values diversity, and reflects the diversity of the county and the relative labor market. GOAL IV – COMMUNITY ENGAGEMENT All Anne Arundel County Public School students will be educated in schools that are family-friendly, welcoming environments. Anne Arundel County Public Schools will eliminate disparities in parent and community representation and participation in traditional and non-traditional school-community activities. GOAL V – EQUITY Anne Arundel County Public Schools will address the diversity that students and staff bring to the learning environment and organize schools and classrooms to support the academic achievement and success of all students. AACPS Study Goals: The major goals of this study are to: Create a flexible facility to support a contemporary instructional program and enhance student success through the application of inter-disciplinary instructional approaches. Identify building concepts which facilitate instructional groupings while fostering intracooperative educational experiences between students and teachers alike. Create an environment which highlights the identity and image of the school within the community and encourages stability of the student population, exemplary educational programs, and positive multi-cultural experiences. Identify a site layout which respects the surrounding community while providing safe, organized on-site pedestrian, automotive, and bus circulation patterns. Improve the security, operational, and maintainability aspects of the facility to increase resources available to school staff and faculty to focus on student success. Provide enhanced interior environmental quality through improved building systems and attractive finishes. Provide building improvements while maintaining instructional capability on-site throughout construction. Identify a capital improvement project which can provide the above goals on a compressed schedule at optimum cost. Page 7 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects PURPOSE The purpose of this feasibility study is to develop instructionally sound and cost effective alternatives for the improvement of Severna Park High School. The alternatives presented in this study were influenced primarily by the facility requirements of the Educational Specification, as well as the tiered scope parameters established by AACPS for the options to be considered. Six options are presented for consideration: 1. 2. 3. 4. 5. 6. Option Option Option Option Option Option A – Do Nothing B – Patch and Paint C – Revitalization D – Modernization E – Replacement A F – Replacement B It is expected that the information presented in this study will assist the Board of Education in determining the most appropriate alternative that satisfies the Ed Spec and optimizes the delivery of a contemporary instructional program, at a reasonable cost. Page 8 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland HISTORY Severna Park High School is a two story masonry building of 296,191 GSF located at the convergence of Robinson Road and Benfield Road in Severna Park, Maryland. The original building was constructed in 1957. A major addition in 1971 included a new media center, classrooms, minigymnasium with support space, and new administration offices. In 1982 the cafeteria was expanded. Other renovations have included HVAC improvements, boiler replacement, roof replacement, science lab renovations in 2003, and installation of an artificial turf field in 2008. Toilet rooms were upgraded to meet requirements of the Americans with Disabilities Act (ADA). However, the remainder of the building has not been renovated to comply with ADA codes. There is currently one relocatable classroom on site which houses a music class. The existing building is not known to be historically significant, but the school and local community take great pride in the high school. Most of the existing finishes in the school are original. Many of the interior materials, such as casework, masonry walls, and doors, are in good condition. A good portion of exterior brick veneer on the original building however is deteriorating due to water infiltration. The site is just over 40 acres and has approximately 485 parking spaces. The following athletic facilities are on site: football field, bleachers, tennis courts, practice and multi-purpose fields, baseball field, softball field, and basketball courts. Construction History: Original 1957 building 1971 additions 1982 addition Page 9 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland EXISTING CONDITIONS 1.0 1.1 Site Site Description JENNINGS RD REC. AREA Severna Park High School resides at 60 N Robinson Road in Severna Park, MD S ITE 21146. The site is 40.30 acres and is WICKLOW located at the intersection of Benfield SEVERNA FOREST Road and Robinson Road, approximately 1,100’ southeast of Governor Ritchie EVERGREEN Highway (MD Route 2). The property is ESTATES also known as parcel 218 on tax map SEVERNA GARDENS 31, grid 6. The tax account number for the property is 03-000-00477223. The site is comprised of several properties WEST SEVERNA PARK purchased by the Board of Education of Anne Arundel County beginning in 1956 and ending in 1977. Deeds for the property can be found at the Anne Arundel County courthouse at Liber/Folio’s 1052/207, 1107/ 578, 1155/413, 1222/298, 2804/720, 2812/ and 2953/181. The property is bounded by an Anne Arundel County Recreation and Parks property known as Cool Pond Park and/or the Jennings Road recreational area (which also currently contains a portion of the High School’s baseball field and the softball field) and a single family home residential development known as Wicklow to the east. Robinson Road, Benfield Road and several single family home residential developments known as Severna Gardens, West Severna Park and Evergreen Estates to the south. A single family home residential development known as Severna Forest is located to the west and a single family home residential subdivision is also located to the north. 1.2 Site Circulation and Parking There are two access points into the site. The main entry is located along Robinson Road and allows for bus and a majority of the vehicles to access the school. A loop road is located approximately 100’ into the site along the left hand side of the drive. This loop road parallels the front of the school and is approximately 650’ long. The secondary access is via a lighted intersection at the convergence of Benfield Road, Evergreen Road and Robinson Road and allows for access into the main student parking area. Page 10 of 112 FACULTY, VISITOR AND STUDENT PARKING BUS STACKING N STUDENT PARKING SIGNALIZED INTERSECTION MAIN ENTRY BUS STACKING Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects Pedestrian access mainly occurs off of Benfield Road and Robinson Road along the entire property frontage and requires pedestrians to cross vehicular drives to gain access to the building. The concrete walks and paving throughout the site are in poor condition. There are three distinct parking areas indentified on site. The main student lot is located off of the signalized intersection to the west of the building and allows for the parking of 228 vehicles (4 Handicap). The location of this lot is also conducive to parking for sporting events occurring at the stadium field, tennis courts and/or any of the turf fields. Additional vehicular access from this lot to other paved areas on site is not available. The second large parking area is located to the far east of the school and is accessed via the main drive. This parking lot is mainly used by faculty and visitors and allows for the parking of 203 vehicles (12 Handicap). There is a third and smaller parking lot located east of this parking area adjacent to the existing basketball courts which allows for the parking of 54 vehicles (0 handicap spaces). Both of these lots are somewhat conducive to parking for sporting events that occur at the baseball and softball fields. Vehicles were noticed parked in the service yard but no striped spaces were observed. The school is currently served by 26 buses which enter the site via the main entry drive. Stacking for the buses is awkward and requires the buses to meander through the main parking lot along the perimeter parking lot drive, eventually ending up at the loop road in front of the school. The buses begin stacking at the egress of the drive and then continue stacking along the loop road, back along the perimeter parking lot drive isle located closest to the school eventually ending at the tech wing. The perimeter drive within this parking lot is signed one way requiring vehicles that enter to do so directly into the parking bays. Once in the lot vehicles have the option of driving approximately 300’ and making a left into an expanded parking area, making a u-turn and exiting or entering the main loop road, or continuing straight to the tech wing. The remaining two drive isles within the expanded parking area are both signed two way. The smaller parking area can also be accessed off of the perimeter drive approximately 575’ into the site. This parking area is not signed although by design it appears that vehicles proceed in a one way manner looping around the lot in a right to left manner. The student lot is also signed one way with the entrance into this lot being directly in the middle requiring vehicles to make a either a left turn or right turn immediately upon entering the site. Once in the left hand or right hand parking area, drivers must continue through in a loop to park or exit. Emergency vehicle access does not meet current code. Although there is perimeter access around the front and eastern side of the building there is no access that would meet current standards for the rear and/or western side of the building and/or site. Consideration should be given to creating a safer environment for vehicles and pedestrian traffic, while also separating the bus traffic from the main vehicular traffic. In addition, complete perimeter emergency vehicle access should be added to allow for fire vehicles to access the building and ambulances to access any of the outdoor sports fields. 1.3 Zoning Information The school property is currently zoned R-5, single family residential. The properties surrounding the school site to the north, south, east and west are also zoned R-5. The Page 11 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland following specific development standards for the R-5 zone (an excerpt from Article 18-Zoning) of the Anne Arundel County Code are provided for guidance only. Per Article 18, §18-2-101(a) This article (Zoning) applies to all land located in the County, except that it does not apply to land owned or leased and developed by the County or the Board of Education unless Federal or State law requires compliance with this article. Therefore the project would essentially be exempt from the zoning regulations unless Federal or State law required compliance. Although the site is exempt from all local codes it is currently in compliance. OS R2 SITE N C3 R1 R5 R2 R2 Bulk Zoning Regulations relating to a non residential use in an R-5 are as follows. Minimum lot size 7,000 square feet Maximum coverage by structures 40% of gross area Minimum width at front building restriction line 60 feet Minimum setbacks for principal structures: Front lot line 25 feet Rear lot line 20 feet Side lot lines 7 feet Corner side lot line 20 feet Principal arterial or higher classification road 35 feet Minimum setbacks for accessory structures other than sheds that do not exceed 64 square feet in area and eight feet in height: Front lot line 50 feet Side and rear lot lines 7 feet or, for structures less than 8 feet in height (other than swimming pools, tennis courts, basketball courts, and similar private recreational facilities accessory to single-family detached, duplex, or semi-detached dwellings), 5 feet Corner side lot line 15 feet Maximum height limitations: Principal structures 35 feet Accessory structures 25 feet or the height of the principal structure, whichever is less Page 12 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland 1.4 Site Soils According to information obtained from the United States Department of Agriculture Natural Resources Conservation Service, the site falls into four (4) distinct soil groups: DvC N UoB DwB DvC – Downer-Hammonton complex, 5 to 10 percent slopes. DwB – Downer-Hammonton complex, 0 to 5 percent slopes. PgB – Patapsco-Fort Mott-Urban Land complex, 0 to 5 percent slopes. UoB – Udorthents loamy, 0 to 5 percent slopes. PgB Additional information regarding these soils is indentified below: 1.5 Map Unit Percent of Site Area Hydric Soils Dvc 1.2% No DwB 2.5% No PgB 83.5% No UoB 12.8% No Classification Varies by depth SC, SM, SP, CL, ML Varies by depth SC, SM, SP, CL, ML Varies by depth SC, SM, SP, CL Varies by depth SC, SM, CL, GC, GM, GS, ML Topsoil Source Drainage System Fair Well drained Not rated Well drained Poor Somewhat excessively drained Poor Well drained Site Topography The site topography generally slopes away from the building in all directions. The building floor elevations vary between 63.5+ at the main building, to 62.25+ at the media center, to 60.9+ at the tech wing (approximate elevations adjusted to NAD 83). Elevations along the front (south) of the building range from 63.0+ to and elevation of 56.0+ within Robinson road with slopes between 0.5% - 2.5%. Elevations along the parking side (east) of the building range from 62.0+ to an elevation of 46.0+ behind the existing basketball courts. Slopes within both the staff parking lot and student parking adjacent to the basketball court are at 1.5% with slopes of 5.0% - 20% in the wooded areas surrounding the basketball court and associated parking. Elevations at the rear (north) of the building range from 62.0+ to an elevation of 30.0+ located in the forested (outfall) area east of the existing grassed ball fields with slopes ranging from 1.5% - 20%. Elevations along the track side (west) of the building range from 63.0+ to an elevation of 54.0+ along the far corner of the property adjacent the track. In general terms the site was essentially constructed with three distinct plateaus. The first containing the school, associated parking and grassed ball field, the second containing the baseball and softball fields and the third containing all of the remaining sports fields. Page 13 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects N LEGEND WATER SEWER STORM GAS ELECTRIC 1.6 Utilities Water The site is currently served by a 6” public water line with two fire hydrants located along the front of the school. One hydrant is located adjacent to the drop off loop road and gymnasium and the other adjacent to the student parking and grassed ball field. The 6” waterline is served via an 8” line located within Robinson Road and the meter is located within the grassed area between the drop off loop and Robinson Road. A smaller water line tapped from the main building also serves the concession building located adjacent to the stadium and all of the natural turf fields are irrigated. Any new construction will most likely require the existing system to be looped around the building and additional fire hydrants installed to meet current fire code. Sanitary Sewer The site is currently served by a public gravity sanitary sewer system. There is a small 6” gravity line that leaves the building adjacent to the existing cafeteria. Based on our review of the as-built documents it appears that this line was installed in 1982 and serves the existing kitchen. This line connects into a manhole located within Robinson Road. The remainder of the building is served by a gravity system with lines ranging from 6” to 8” and leaving the building at various points around the building. All of these lines eventually tie into an existing 8” public line that is buried under the school’s grassed multi-purpose fields. Page 14 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects The public line enters the site off of Cottonwood Road adjacent to the existing tennis courts, it then turns and heads in an easterly direction under the fields and then exits the site in the wooded area north of the existing baseball field. It should be pointed out that the site was initially served by a private septic system. As-built documents indicate that an existing 50,000 gallon septic tank was abandoned in place behind the school. The school’s original septic fields were located in the area that is now utilized for the three multi-purpose fields. Storm Drains The site is currently served by a closed storm drain system. Storm drain pipe sizes range from 6” to 48”. The site is split into two distinct drainage areas. The first drainage area is approximately 12+ acres and contains a large portion of the building including everything with the exception of the rear classroom and tech wing, the student parking area, main loop drive and entry. Stormwater within this drainage area is conveyed in a southerly direction offsite into a system located within Robinson Road. The second and much larger drainage area contains the remainder of the building and site. These areas include the rear classroom and tech wing, the faculty and visitor parking lots, the stadium, tennis courts and all of the sports fields. A public storm drain system was installed through the site in the 1970’s; this 48” storm drain is located under the three existing grassed multi-purpose fields and picks up all of the drainage area mentioned above in addition to portions of Benfield Road and a majority of the Severna Gardens subdivision. The total drainage area being conveyed through this public system is approximately 60 to 80 acres. The outfall for this system is located within the forested area east of the grassed multi-purpose fields. During our field review which occurred on a warm sunny day with little to no rain preceding, a constant flow of water was noted exiting the 48” pipe at the outfall. Based on the level of scouring noted on the concrete it appears that this flow remains constant and has done so for many years. A request has been made to have the existing 48” pipe investigated via scoping and video tape in an attempt to determine the source of the water flow. Gas, Electric, Cable, Telephone The site is served via a 3” gas line which enters the site from Benfield Road, traverses the student parking lot and grass field and then enters the building in the courtyard between the existing gymnasium and media center. During our field investigation several old gas valves were noted along with a very large vault. Based on our discussions with the building superintendant while on site it was unclear whether the meter is located in the vault or inside the boiler room. Electric enters the site at the far southeast corner of the property nearest to the visitor parking. The electric is overhead to a pole located near the entrance to the secondary parking area located adjacent to the basketball courts. From this pole the electric service is underground through the faculty parking lot to the east side of the building. See the mechanical, electrical section of this report for additional information regarding the gas, electric, cable and telephone. Page 15 of 112 Severna Park High School Severna Park, Maryland 1.7 Feasibility Study GWWO, Inc./Architects Stormwater Management Although on site construction has occurred at various points since the school was initially constructed the site does not contain any stormwater management facilities. A large pond does exist north of the site adjacent to Thomas Way in the subdivision known as Cool Pond. This facility was constructed in the early 1980’s and should account for stormwater quantity management for the large drainage area discussed above. The drainage area to this facility which traverses the site is a total of 116 acres. Any new construction that occurs will be required to meet the requirements established by the Stormwater Act of 2007. These guidelines establish a process by which new construction needs to utilize sustainable or environmental site design (ESD) to the maximum extent possible to satisfy water quality requirements. ESD’s include but are not limited to micro-bioretention, dry and/or wet swales, rain gardens, etc. Attempts should be made to provide for impervious disconnects and to allow for adequate open space to construct multiple smaller facilities throughout the site to satisfy these requirements. Based on our preliminary review of the soils information it appears that infiltration of stormwater should be achievable on site and cursory conceptual layouts have been reviewed to provide areas for ESD’s to the maximum extent possible. 1.8 Floodplains, Wetlands and Waterways The site is not located within the 100 year floodplain as delineated on FEMA flood insurance rate map 240008-0020-C. The site is located in zone C which means an area of minimal flooding. A review of NWI mapping indicates the headwaters of a wetland area which is located within the forested area north of the existing baseball field. In addition to the continuous flow of water noted in the existing storm drain section of this report additional discussions have occurred during the committee meetings which also indicate wet areas during various times along the north side of the site in the vicinity of the existing grass multipurpose fields, tennis court and track. Additional historical as-built documentation review performed did not indicate any previous wetland, underground stream, etc. A request has been issued to have the Maintenance Department scope and video the existing storm drain line in an attempt to further determine the source of the water. An environmental features assessment and if required, wetland delineation should be performed at the early stage of design of the project. 1.9 Landscape, Trees and Forest Conservation Landscaping throughout the site consists of lawn and sporadic planting. The planting areas are mainly concentrated at the front of the school within the open space located between Robinson Road and the main loop road in addition to an area located between the rear of the classroom wing and the tech wing. Plantings in both of these areas consist of mature deciduous trees, several of which are very large. The western and northern sides of the site Page 16 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects are heavily buffered from the adjoining residential homes by a combination of evergreens and deciduous trees. Areas north of the existing baseball field are heavily wooded and lead to the County owned property (Jennings Road Recreational Area) and portions of the site around the existing basketball court and small parking lot are also wooded. There are no documented forest conservation easements on site. Any construction exceeding 40,000 SF will require compliance with the Maryland Forest Conservation Act. A forest stand delineation should be completed at the beginning of the design phase of the project to determine the quality of all on site forested areas and to determine if any of the mature trees qualify as specimen trees. During this time a forest conservation worksheet should be completed to more adequately determine the forest conservation acreage required based on the construction option chosen. On site afforestation may likely be required and could possibly be met at various locations on site. If it is determined that the selected construction option chosen will not allow for adequate on site afforestation then a fee in lieu to the County will be required to meet these regulations. 1.10 Site Entrance There are two entry drives into the site. One entry point is a signalized intersection at the convergence of Benfield Road, Evergreen Road and Robinson Road. This entry allows for access into the main student parking lot located west of the building and 700’+ from the building’s main entry. The second entry point is 1000’+ easterly heading towards Governor Ritchie Highway (Maryland Route 2) and is 300’+ from the building’s main entry. This entrance allows for access to the remaining parking (faculty, visitor and student) in addition to access for the bus drop off. A loop road is located approximately 100’ into the site that parallels the building as it heads to the west; the loop road is 650’+ long and allow for egress of the bus traffic. 1.11 Practice Fields /Athletic Fields / Athletic Courts The stadium track/field is located at the far western corner of the property. The stadium field was upgraded to artificial turf in 2008. Lighting around the stadium field is very outdated. It also appears that the bleachers were recently upgraded, although the seating on the visitor side is much larger than the home side. There are currently 8 tennis courts located immediately behind the stadium field. The school’s practice field is located between the school building and stadium field adjacent to the student parking. There are 3 natural turf multi-purpose fields located east of the tennis courts immediately behind the building. The school’s baseball field and softball field are located along the east side of the building on Page 17 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland County owned property and neither of these fields is lighted. The basketball courts consist of three full courts which are located east of the main parking lot. The court paving and fencing around the courts is in poor condition. The school also has a fenced area for child development measuring approximately 100’ x 85’ which is located along the side of the tech wing portion of the building. MULTI‐ PURPOSE N BASEBALL & SOFTBALL FIELD PRACTICE FIELD TENNIS STADIUM FIELD BASKETBALL 1.12 Site Educational Adequacy 1. Areas of Program Deficiencies Stadium field track should be 8 lanes, it’s currently 6 lanes. 2 long jump/triple jump sand pits, currently 1. Stadium seating includes 1,664 on the home side and 756 on the visitor’s side. Tennis courts should be a total of 10, there are currently 8. 5 natural turf fields, there are currently 4. Inadequate pitching warm up areas for home and visiting team. Inadequate batting cage area. Baseball and softball fields are not lighted. No separate bus and vehicular drop off areas. No separate perimeter emergency vehicle access. 2. Functional Concerns Bus, vehicular and pedestrian traffic are intermingled with no separation between buses and vehicles. No separate defined parent drop off area. Baseball and softball fields are located on County owned property. No perimeter access for emergency vehicles. Dumpsters sporadically located within the service yard; no defined dumpster pad. Need to increase seating on the home and visitor sides of the stadium field. Need to upgrade lighting at the stadium. Page 18 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects EXISTING CONDITIONS 2.0 BUILDING 2.1 Exterior Roof: The existing roofing is a 4-ply built-up membrane with aluminum coating on tapered insulation which was installed in 2000. The overall condition is generally good although there are existing leaks at various penetrations. Coping appears to be in good condition. Replacement of the roofing will be required within five years. Exterior Walls: The original building and additions are brick veneer on concrete block backup. There is no cavity or insulation in the walls of the original building. Seals around stucco panels that replaced original windows have allowed water to penetrate the envelope in a significant amount of area. This continuous water penetration has resulted in failing cast stone sills, rusting shelve angles, and deterioration of mortar. Repair of these items is critical. Emergency egress panels within the in-filled area are located in each classroom. Typical roof. Stucco in-fill panels. Exterior Windows: Most of the original window area was in-filled in 1971 with stucco covered panels. Classroom windows throughout provide a minimum amount of daylight. All windows are single glazed. Exterior entrances and storefront: A number of exterior hollow metal door frames and metal doors are rusting through and must be replaced. Doors and hardware have not been upgraded to meet accessibility requirements. The single glazed metal frame entrance system at the main entry and gymnasium lobby should be replaced. All exterior doors and hardware should be updated. Exterior cast stone sill. Metal framed entry system at gymnasium. Page 19 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects EXISTING CONDITIONS 2.2 Interior Ceilings: A mixture of 2x2 and 2x4 acoustical panel ceiling exist in corridors. Glued on 12x12 acoustic tiles are found in many of the original classrooms. In the 1971 addition there are mixture of 2x4 acoustical panel ceilings and exposed ceilings. Overall ceilings are in fair condition. However, the 2x2 acoustical panel ceiling in the cafeteria should be replaced. Flooring: Terrazzo flooring is in good condition in the corridors of the original building. Cracks were observed in the terrazzo flooring in the cafeteria. Classrooms have vinyl composition tile (VCT) flooring. VCT is also throughout the corridors and classrooms of the 1971 addition, with the exception of carpet in the media center. Ceramic tile in the toilet rooms should be replaced. The stage and gym wood floors should be reconditioned. Typical narrow corridor. Interior Partitions: Typical classroom partitions are painted CMU with structural glazed tile base. Many corridor walls are full height structural glazed tile. Most partitions are in good condition. Doors/Hardware: Typical door hardware does not meet accessibility requirements. Corridor classroom doors in the original building have louvers which do not comply with current building code requirements regarding fire ratings and the passage of smoke. Most corridor doors and hardware should be replaced. Typical corridor door. Toilet Rooms: Plumbing fixtures all appear to be original or dated and beyond their useful life. The water closets are floor-mounted, urinals are floor and wall-mounted, and lavatories are individual wall hung type. Plumbing fixtures no longer meet code requirements for water usage and are not properly configured for ADA accessibility. Casework and Equipment: Typical classroom casework is original to the building and is in poor condition. Science classrooms were renovated in 2003 and do not meet current requirements. Page 20 of 112 Typical classrom casework. Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects EXISTING CONDITIONS 2.3 Structural System Severna Park High School is a one/two story structure comprised of a variety of structural framing systems, including steel frame, cast in place concrete, load bearing masonry, open web steel joists, and precast plank. Existing structural drawings for the original building are dated 1957 with subsequent additions or renovations in 1971, 1982, 1996, 1997 and 2003. Existing structural drawings indicate that the structure was designed for a roof live load of 30 pounds per square foot. The 1971 structure classrooms were designed for a live load of 50 pounds per square foot, corridors for a live load of 75 pounds per square foot and toilet for a live load of 50 pounds per square foot. The 1971 and 1982 additions were designed for a floor live load of 100 pounds per square foot. The building is supported by a shallow spread footing foundation system, designed for an allowable bearing pressure of 4000 pounds per square foot for 1957 building and an allowable soil bearing pressure for 1971 and 1982 are not available on the drawings. Building areas indicated in the following descriptions of the existing structural systems refer to the diagram below: Part A The area identified in the existing structural drawings as Part A is a one story structure with the gymnasium and supporting area having a higher roof elevation. The high roof deck consists of a 3” thick insulating roof plank and is supported by the 12” deep purlins. The high roof purlins are supported by 36” deep wide flange steel girders spanning the width of the gym and supported on each side by wide flange steel columns located in the gym walls. The low roof deck consists of a 2” poured gypsum on a 1” form board with Bulb-T sub- Page 21 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects purlins. Framing for the low roofs consists of 14” deep open web steel joists at roughly 42” to 48” on center supported by the load bearing exterior and interior walls. The first floor of the gymnasium and other area consists of 6” deep precast concrete planks with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry walls are supported on a continuous spread footing. There is a fairly substantial crawl space under the entire area. The 1971 addition to Part A is a one story structure. The low roof deck consists of a 3” Insulrock roof plank with Bulb-T sub purlins. Framing for the roofs consists of steel beams and open web steel joists supported by the load bearing exterior and interior walls. The floor consists of 6” deep precast concrete planks with a 2” topping slab over a crawl space, supported by load bearing masonry walls. The load bearing masonry walls are supported on a continuous spread footing. Part B Part B is a one story classroom wing. The roof deck consists of a 2” poured gypsum on a 1” form board with Bulb-T sub-purlins. Framing for the roof consists of 14” deep open web steel joists over the classroom and 8” deep open web joists over the corridor at roughly 48” on center supported by the load bearing exterior and interior walls. The first floor consists of 6” deep precast concrete planks with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry walls are supported on a continuous spread footing. There is a fairly substantial crawl space under the entire area. The 1971 addition to Part B is a one story structure. The roof deck consists of a 3” metal deck supported by 14” deep wide flange beams on a steel columns and a spread footing foundation. The slab on grade is a 5” thick concrete slab. Part C The area identified in the existing structural drawings as Part C is a one story structure with the auditorium, cafeteria and supporting area having a higher roof elevation. The high roof deck over auditorium consists of a 3” thick insulating roof plank and is supported by the 12” deep purlins. The high roof purlins are supported by about 5’-0” deep open web steel trusses spanning the width of the auditorium and supported on each side by wide flange steel columns located in the walls. The low roof deck consists of a 2” poured gypsum on a 1” form board with Bulb-T sub-purlins. Framing for the roof over cafeteria consists of 32” deep open web steel joists at roughly 52” on center supported by steel beams and columns at the exterior walls and the load bearing interior walls. Other low roof framing consists of joists of various depths and spacing and supported by load bearing walls. The first floor of the cafeteria and other areas consists of 6” deep precast concrete planks with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry walls are supported on a continuous spread footing. There is a fairly substantial crawl space under the entire area. Page 22 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects Part D and E Parts D and E are two story classroom wings. The roof deck consists of a 2” poured gypsum on a 1” form board with Bulb-T sub-purlins. Framing for the roofs consists of 14” deep open web steel joists over the classroom and 8” deep open web joists over the corridor at roughly 48” on center supported by the load bearing exterior and interior walls. The second floor consists of 6” and 8” deep precast concrete planks with 2” topping, and is supported by load bearing masonry walls. The first floor consists of 6” deep precast concrete planks with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry walls are supported on a continuous spread footing. There is a fairly substantial crawl space under the entire area. Part F Part F is a one story wing with a partial basement. The high and low roof deck consists of a 2” poured gypsum on a 1” form board with Bulb-T sub-purlins. Framing for the roofs consists of 8” to 18” deep open web steel joists at roughly 48” on center at the high roof and 36” on center at the low roof. The high roof structure is supported by a combination of steel beam & columns at the exterior and load bearing interior walls. The low roof structure at the second floor level is supported by the exterior and interior load bearing walls. The first floor except the basement area consists of 6” and 8” deep precast concrete planks with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry walls are supported on a continuous spread footing. There is a crawl space under the entire area. The first floor over basement consists of 6” deep precast planks with a 2” topping slab supported by interior concrete beam and columns, and perimeter load bearing walls. The slab on grade at the basement consists of 5” thick concrete floor on grade. Interior columns and walls are supported on spread footings. Part G This is a two story 1971 media center and classroom addition with a partial basement. The roof deck consists of a 3” steel deck supported on wide flange purlins and girders. The second floor consists of 3½” light weight concrete on a 1½” composite steel deck supported by wide flange beams and girder. The first floor consists of 5” slab on grade at the media center and 3½” light weight concrete on a 1½” composite steel deck supported by wide flange beams and girder at other areas. The building structure is supported by steel columns on a spread footing foundation. Page 23 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects 1982 addition This is a small one story addition with a crawl space. The roof structure consists of 1½” steel roof deck supported by steel joists and girders supported by a load bearing wall. The floor construction is 3” light weight concrete on a 9/16” form deck supported by open web steel joists on load bearing walls. The exterior and interior walls are supported on spread footings. Existing Conditions Based on our limited visual observations, the existing structure appears to be in a good condition. Observations of the underside of the gypsum roof decks were made in a limited number of areas. In all instances the deck appeared to be in good condition. It should be noted however, that AACPS’s experience at other schools undergoing re-roofing or major renovations has uncovered areas of gypsum roof decks that have deteriorated due to water infiltration requiring replacement of the deck. The same unforeseen condition is possible here. The masonry load bearing walls appear to be in good condition. There were spalling, cracking, exposed joint reinforcement and loose mortar joints observed at the brick veneer and window sill at various locations (Photos 1, 2 & 3). In addition, cracks in the terrazzo floor were observed at the cafeteria and adjacent corridor floor (Photo 4), but not in other corridor floors. Also, observed settlement at the plaza level pavement, loose rails and spalling at the retaining walls outside the Gymnasium (Photos 5 & 6). A lack of an overflow drain or scupper at small area of Part-C roof was observed. In addition, at the basement mechanical room, leakage was observed through the metal hatch located at the ground level. All in all, we found the structure to be in a good condition. Based on our visual observations, which were limited to those areas that were accessible, we saw no indications of anything that would cause any concern with respect to the structural integrity of the structure. The building appears to be structurally sound. Photo 1: Exterior brick veneer deterioration Page 24 of 112 Photo 2: Exterior brick veneer deterioration Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects Photo 3: Spalled sill stone Photo 4: Cracks in Terrazzo floor at Cafeteria Photo 5: Plaza level pavement settlement Photo 6: Loose rails and spalled bricks Page 25 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects EXISTING CONDITIONS 2.4 Mechanical Systems 2.4.1 History of Mechanical System Installations and Retrofits The original drawings for the building were completed in 1957. The original HVAC design for the building was a central heating plant of three boilers supplying hot water to convectors and unit ventilators throughout the building. Offices were heated with wall to wall convectors and classrooms were heated and ventilated with unit ventilators. Piping to units is located in crawl spaces below the first floor. Toilet rooms and storage areas are exhausted by powered roof fans. Upper floor corridors were ventilated by gravity roof ventilators. Shop classrooms and arts and crafts classrooms were located on the upper floors and ventilated by powered roof fans located directly above the space. In 1971 additions were made to the building. These included a mini gym and support spaces for the main gymnasium in Area A, a new media center building in Area G, and additional administrative spaces in area B. The new gymnasium areas are heated by central station heating-ventilating air handling units. The administrative area is heated and cooled by three roof top gas fired/packaged DX multi-zone units. Perimeter areas of the administrative section are heated with convectors on the wall. Incremental conditioners were installed on the stage support areas. Many classrooms had unit ventilators removed and new incremental conditioners installed. In the basement of the media center building a water cooled chiller connected to a cooling tower outside the building and constant volume terminal reheat air systems were installed. These provide heating and cooling to both floors on the media center and supporting rooms. The perimeter areas of the building had convectors to provide additional heating. During these renovations boiler #2 and #3 were replaced. In 1993 many of the unit ventilators were replaced. Two of the new unit ventilators (in the Management and Foods Classrooms) were ceiling mounted horizontal units with split new roof mounted condensing units. In 1996 the roof top units on the administrative portion of the building were removed along with much of the associated ductwork and replaced with new rooftop units. The unit ventilators for the painting classrooms and the P.E. classroom were also removed and replaced with new incremental units. All incremental units in the classrooms of Area B were replaced. The air handling units serving the auditorium were designed to be replaced; however, it appears that this did not occur since the original design remained when the air system was reconfigured later. Unit ventilators in the surrounding music rooms were replaced. The existing cooling tower and chiller were removed and replaced. In 1982 a cafeteria expansion occurred; a new packaged gas fired DX cool rooftop unit was installed at this time. There is no mechanical documentation for this period. In 1997 the science classroom area was renovated, the incremental units were removed, two new packaged constant volume roof top units with duct mounted hot water heating coils, and several split systems were installed. Page 26 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects In 2000 boilers #1, #2, #3 were removed and replaced by two new boilers. All pumps in the boiler room were replaced as well as the expansion tanks. In 2002 the kitchen hood was replaced and a new hood, fan, and make-up air unit was installed. In 2003 the mechanical equipment serving the auditorium was removed. Two new energy recovery units with heat recovery wheels were installed to serve auditorium. 2.4.2 Heating Water Description: The majority of the building is heated from the hydronic heating water system. Two nominal 500 horsepower fire tube boilers exist in the boiler room. The current boilers were installed in 2000 and are the third set of boilers since the original plant construction in 1957. The boilers are dual fuel and can be fired on #2 fuel oil or natural gas. We are unsure if the school is utilizing an interruptible natural gas service in order to capitalize on the dual fuel capability of the boilers. The heating water is circulated through 20 individual heating water zone pump systems. The portion of the heating water system which services Area G of the building utilizes a primary-secondary pumping arrangement. 16 of the 21 pumps were replaced in the year 2000. The pumps that were not replaced are all located in Area G and date back to the original 1971 construction. The major portions of the heating water piping system were constructed with the original building in 1957 and the major addition of 1971. Some runouts have been replaced with the replacement of the terminal units throughout the years. However, the majority of the piping is 53 years old with the next largest portion being 39 years old. Dual Fuel Fired Boilers Fuel Oil Pump & Controls The expansion tanks were replaced in 2000 during the boiler replacement. All the hydronic specialties which are not directly attached to the 16 replaced pumps are original. 2.4.2.1 Condition: The boilers and the pumps in the boiler room are relatively new and appear to be in good condition. The pumps in the Area G mechanical room are Heating Water Zone Pumps Page 27 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects operating but are aged significantly beyond their rated useful life. The condition of the piping is unknown; however, the majority of the heating water piping in the building has exceeded its rated useful life. 2.4.2.2 Efficiency: Boilers: Fire tube boilers were once considered highly efficient but have been exceeded by modern condensing type boilers. While rugged, these boilers have a maximum efficiency of 85%. Condensing type boilers can reach operating efficiencies of 95%+ (if operating in the condensing water temperature range). Heating Water Zone Pumps Pumping Systems: The pumping systems are all constant volume and thus are inefficient. The pumps operate with a constant energy draw circulating a constant flow rate regardless of the heating load. Modern energy efficient hydronic systems utilize variable flow with variable frequency pump drives. The use of the constant flow arrangement should be discontinued. 2.4.2.3 Recommendation: The hydronic heating system is subservient to overall HVAC system configurations. The two boilers have 15 years of remaining rated useful life. The selection of a replacement HVAC system should not focus solely on reuse of these boilers since there are higher efficiency heating alternatives. The reuse of the boilers should be considered in one of the four HVAC system options that would be studied in a life cycle cost analysis. However, these boilers may be more valuable being relocated to another school in need of a boiler retrofit rather than their reuse at this facility. Continued long term reuse of the original 1957 piping should be avoided unless the condition of the piping can be documented through destructive testing; and even in that case only the largest sizes should be reused. Reuse of any of the year 2000 replacement pumps should be dependent upon an overall HVAC system selection and the pumps capacity. Page 28 of 112 Heating Water Zone Pumps Heating Water Zone Pumps Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects 2.4.3 Chilled Water 2.4.3.1 Description: Area G of the building, the Media Center Addition, utilizes a chilled water system consisting of a 275 ton Carrier water cooled centrifugal chiller, a single frame mounted end suction chilled water pump and condenser water pump, and an induced draft cross flow cooling tower located in a pit in the court yard. The cooling tower is has a masonry screening wall installed on three sides, but a large non-masonry access area on one side. The tower is not provided with any attenuation features. The result is that mechanical noise from the cooling tower can be heard in the court yard and is very disruptive. The Area G mechanical room is provided with a refrigerant leak detection and evacuation exhaust system per ASHRAE Standard 15. 2.4.3.2 Condition: The chiller, pumps, and cooling tower were all replaced in 1996. All appear to be in good working order. The chiller has 9 years of remaining rated useful life. The cooling tower and pumps have 6 years of remaining rated useful life. The cooling tower lacks proper sound attenuation. The requisite emergency breathing apparatus associated with the refrigerant leak detection system has been removed from the site; its absence is a life safety hazard. 2.4.3.3 Efficiency: The chiller itself is reasonably efficient (although not highly efficient); however, the system as a whole is inefficient for its class. The primary issue is that the system design does not address efficiency at partial cooling load conditions. The chilled water pump is constant flow and the cooling tower fan is constant volume. The system lacks the capacity to reduce pumping energy and cooling tower fan energy as is typical for current chilled water system designs. If the system is to remain in place, as a minimum it should be retrofitted with two way control valves on the chilled water coils, and a variable frequency drive (with associated controls) on the chilled water pump and cooling tower fan. Centrifugal Chiller Condenser Water Pump Chilled Water Pump Page 29 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects 2.4.3.4 Recommendation: This chilled water system services a relatively small portion of the overall building. A full building HVAC retrofit should utilize a one system type of the majority of the building. Thus while a chilled water system may be a viable solution for the overall building; this chiller and cooling tower in their current configuration are too small - the system should be completely reconfigured. It may be possible to relocate this chiller to a new central chilled water plant and use this machine in conjunction with additional chillers. The cooling tower is not well located and creates acoustical problems in the court yard; a new cooling tower location for a much larger plant (under a chilled water plant study option) should be considered. 2.4.4 Classroom Incremental Units 2.4.4.1 Description: The majority of the classrooms are conditioned by self contained incremental cooling units. These units are DX cooling and utilize hot water heating coils. Each unit is provided with a large through the wall louver which draws air into the condensing section for heat rejection and also exhausts this same air. In addition, a portion of the louver is dedicated to outside ventilation air intake. The units installed in Areas C, D, and E are currently 17 years old and have exceeded their rated useful life of 15 years. The units installed in Area B are 14 years old and will reach the end of their rated useful life in one year. Cooling Tower. Noise Enters Court Yard Through Chain Link Fence. A Typical Classroom Incremental Unit The units do not appear to be classroom unit ventilator grade in that they appear to lack an air side economizer. Each unit was designed for an outside ventilation air supply of 250 CFM which is significantly below the current standard of 465 CFM per classroom (based upon occupancy of 30 students and one teacher at a rate of 15 CFM of outside air per person). 2.4.4.2 Condition: The classroom incremental units are generally in poor condition. The installation method of the retrofit installation of the through wall louver is problematic on multiple fronts; it is Page 30 of 112 Classroom Incremental Unit Wall Louvers on an Elevation. Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects unsightly, and is a source of water infiltration into the building. A majority of the units have exceeded their rated useful life and are experiencing failures, including compressors and fans. The maintenance staff report that the parts for condenser fans are long lead items. During our walk through inspection of the building we found many units which were either inoperable or operating at a significantly reduced capacity. By nature self contained DX cooling units provide poor relative humidity control at partial cooling load conditions. The units have a compressor, evaporator fan, and condenser fan all contained within one housing with little opportunity for sound attenuation; the result is a relatively high background noise level (above classroom NC target levels). 2.4.4.3 Efficiency: In terms of cooling, the classroom incremental units are particularly inefficient. This type of unit is not used in modern high performance educational facilities. A Close-up of an Incremental Unit Wall Louver. Note That Rain Easily Penetrates the Louver. 2.4.4.4 Recommendation: The units should be removed and replaced with a modern classroom HVAC system. 2.4.5 Constant Volume Terminal Reheat Air Systems 2.4.5.1 Description: The spaces of Area G, including the Media center, are provided with HVAC service from a constant volume reheat system. The system is comprised of five constant volume central station type air handling units, four of which utilize separate centrifugal return fans. Each air handling unit has a hot water heating coil and chilled water cooling coil. The design drawings indicate that these units provide a discharge air temperature of approximately 55 degrees. Each individual temperature control zone is provided with a constant volume reheat box with a heating water coil and a space thermostat. In the cooling mode, once the space temperature is satisfied the supply air is reheated to prevent overcooling of the zone. This obviously is an inefficient method of space temperature control. There does not appear to One of the Constant Volume Terminal Reheat System Air Handling Units. Page 31 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects be a discriminator control, which would allow for the discharge air temperature set point to be reset upward matching the critical zone cooling load, thus reducing the required reheat energy load. 2.4.5.2 Condition: The air handling units are approaching 40 years old and have exceeded their rated useful life of 25 years. The maintenance staff report that the units have faulty outside air dampers which tend to cause coil freezing damage to the water coils. They report that the fan bearings are in relatively good condition; however, the overall unit condition appears to be marginal, with some units missing panels and shields. A Return Fan for a Constant Volume Terminal Reheat Air System 2.4.5.3 Efficiency: This system type requires the reheating of air which has been mechanically cooled in order to prevent over-cooling of spaces. This is a highly inefficient means of temperature control. 2.4.5.4 Recommendation: This system should be removed and replaced with a modern educational HVAC system. 2.4.6 Multi-zone Air Systems 2.4.6.1 Description: The administration spaces of Area B are conditioned by forced air multi-zone systems. Three rooftop gas fired heating and packaged DX cooling units service this area. Two of the RTU's (RTU-1 & 3) have eight zones each and RTU-2 has ten zones. Each zone is provided with a thermostat and dedicated supply air duct distribution system. Each RTU has a hot deck and a cold deck. The controls mix air from each deck using zone dampers to provide a discharge air temperature that matches the zone heating or cooling load. The hot deck and cold deck discharge air temperature set points are typically reset to match the heating and cooling load (respectively) of the critical zones (i.e. a discriminator control sequence). The rooftop multi-zone units are currently 14 years old and have one year of remaining rate useful life. Whereas the cooling side of the units is Page 32 of 112 AHU with a Missing Filter Access Door Three Gas Fired/DX Rooftop Multi-zone Units over the Administration Office in Area B. Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects packaged DX, these units are not highly energy efficient. However, the areas they service are broken into many individual temperature control zones, allowing the system to modulate its capacity to provide a fairly high level of occupant comfort control. 2.4.6.2 Condition: The rooftop multizone air handling units have one year of remaining rated useful life. The maintenance staff has stated that these rooftop units have been experiencing problems with the condenser fans. 2.4.6.3 Efficiency: We were not able to ascertain the specific KW per ton energy efficiency; however the scheduled full load amps of these units in comparison with the rated cooling capacity is higher than expected for packaged rooftop equipment. Given that packaged DX system are generally not highly efficient, these units should be considered relatively inefficient. 2.4.6.4 Recommendation: The area serviced by these multizone units should be retrofitted with a highly efficient HVAC system in coordination with an overall building HVAC retrofit. 2.4.7 Packaged Rooftop Constant Volume 2.4.7.1 Description: Two science classrooms in Area E are conditioned by dedicated packaged rooftop DX air conditioning units with duct mounted hot water heating coils (one unit per classroom). Each unit is controlled by a space thermostat. The units do not have a means to modulate their cooling capacity at partial cooling load conditions other than cycling the compressor on/off. This results in high indoor relative humidities at partial cooling load conditions. 2.4.7.2 Condition: The units were installed in 1997 and have two years of remaining service life of their 15 year rated useful life. One of the two units was inoperable at the time of the building inspection. Science Classroom Area Packaged Rooftop Units 2.4.7.3 Efficiency: The packaged DX cooling system is inefficient. 2.4.7.4 Recommendation: These units should be removed and the classrooms should be provided with a highly efficient educational grade HVAC system as part of a total building HVAC retrofit. Page 33 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects 2.4.8 Split Systems 2.4.8.1 Description: The building is provided with a variety of split DX cooling systems, primarily located in the Science classrooms of Area E. These include: ceiling concealed indoor, vertical indoor unit ventilator, and horizontal console unit ventilator units, each with a paired outdoor condensing unit. Similar to other DX cooling units, these are relatively inefficient systems with have difficulty maintaining indoor relatively target levels at partial cooling load conditions. Ceiling Mounted Split System Indoor Unit 2.4.8.2 Condition: The units were installed in 1997 and have two years of remaining service life of their 15 year rated useful life. The systems were in various states of operating conditions during our walk though, with one vertical unit spilling condensate on the floor. Many of the classrooms serviced by these units were particularly humid and had buckling ceiling tiles. 2.4.8.3 Efficiency: The packaged DX cooling systems are inefficient. 2.4.8.4 Recommendation: These units should be removed and the classrooms should be provided with a highly efficient educational grade HVAC system as part of a total building HVAC retrofit. Split System Vertical Indoor Unit in Science Classroom. Note the Damage to the Floor Tile from Repeated Condensate Drainage Failures. 2.4.9 Window Air Conditioners Several areas of the building have been retrofitted with window air conditioning units. These are inappropriate for an institutional building, are noisy, inefficient, and should be removed. These areas should be provided with an appropriate educational grade HVAC system. Window Air Conditioning Units in the Dance Studio Page 34 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects 2.4.10 Hydronic Terminal Heating 2.4.10.1 Description: The building is provided with a variety of different hydronic terminal heating units from the original construction of 1957 and 1971. While the majority of the original 1957 hydronic fin tube heating units have been removed, some other types of units remain. The remaining unit types from these two construction periods include: hot water unit heaters, cabinet unit heaters, and convectors. 2.4.10.2 Condition: Our inspection was conducted during the summer so we do not have first hand information on the operating condition of this equipment. The maintenance personal did not report any specific system wide problems with this type of equipment. All of these units exceeded their rated useful service life decades ago. 2.4.10.3 Efficiency: The efficiency of the actual terminal units depend on the cleanliness of the heat exchanger; which should be considered somewhat as it is expected that internal surfaces of the heat exchanger are coated with mineral deposits thus diminishing the heat transfer capacity of the unit. The system efficiency is also driven by the combustion efficiency of the boilers. A Typical Fin Tube Element with End Removed. 2.4.10.4 Recommendation: The units should be replaced under a full building HVAC retrofit. Fin Tube Heating in a Classroom. A Hot Water Unit Heater in an Industrial Arts Classroom. A wall convector. Page 35 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects 2.4.11 Heating Ventilating Units 2.4.11.1 Description: The main gymnasium and the mini-gym are conditioned by central station type heating ventilating units, capable of providing 100% outside air for summer time ventilation, and mixing return air with outside air for heating season service. Each unit is provided with a hot water heating water coil, mixing box, and filter bank. These units are original to the 1957 and 1971 construction and are currently 53 and 39 years old; dramatically exceeding their rated useful service lives of 25 years. These units do not provide air conditioning service. While this is typical for many public school gymnasiums, the mechanical supply of un-dehumidified air into the gymnasiums, which are interior to the building's vapor barrier envelope, introduces a very large dehumidification load onto the adjacent air conditioned spaces. 2.4.11.2 Condition: The units are operating but appear to be worn. 2.4.11.3 Efficiency: The motor efficiencies are low compared with modern premium efficiency motors. 2.4.11.4 Recommendation: Replace these units and consider air conditioning the spaces as a means to aid in maintaining the overall school relative humidity level. 2.4.12 Ventilation & Exhaust Systems 2.4.12.1 Description: The building uses a distributed ventilation and exhaust approach utilizing approximately 78 individual exhaust fans; nearly all of which appear to be original to the 1957 and 1971 construction. Ten fans were replaced in 1980. The fans range in age from 53 to 30 years old. The most typical ventilation method for the classroom areas is that outdoor ventilation air is introduced into the building via the classroom incremental units and is transferred into the corridors where it migrates to exhaust air intake locations, many of these being exhaust registers in the corridor ceilings. Although this was a common ventilation method at the time the building was originally constructed, this arrangement poses a significant life safety threat since the system could mechanically force smoke from a classroom fire into the means of egress. This air transfer method is not allowed by modern building codes and should be discontinued. The building also uses roof gravity ventilators for what appear to be both intake and pressure relief service. The crawl space under the first floor is provided with several side wall brick vents for air inlets and several open end vertical ducts terminating at the roof level with gravity ventilators for air discharge. 2.4.12.2 Condition: The general duty exhaust fans are all long past their rated useful life and are in various states of physical condition. The Art Room kiln exhaust hood is too small to Page 36 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects cover all three kilns. The brick vents inlets are in various conditions. The crawl space is very humid. The gravity vents appear to be in working order. The general configuration of the ventilation system for the typical classrooms poses a life safety hazard. The stage exceeds 1,000 square feet in area and is required to be provided with an emergency ventilation system for smoke control (which is missing). 2.4.12.3 Efficiency: This is a passive ventilation system which does not consume energy. However, there does not appear to be insulation under the floor, thus the ventilation system induces a heat transfer load on the building. 2.4.12.4 Recommendation: Nearly all exhaust fans should be replaced. A replacement kiln exhaust hood should be provided of adequate size to cover all three kilns. The brick vents inlets are in various conditions; these should be replaced as a whole grouping with heavy duty vents to provide several decades of continued use. The crawl space is very humid. The gravity vents could remain in place; consideration should be given to replacing some roof terminals with power roof ventilator type fans to increase the ventilation in the crawl space. A radon test should be conducted to determine of the earth is releasing radon gas into the crawl space. The general ventilation system configuration poses a life safety concern and should be changed. In addition, a Dedicated Outside Air System (DOAS) should be incorporated to decouple the treatment of outside air from space conditioning since there is no relationship between these functions and it is the primary reason for poor indoor air quality). Provide a stage emergency ventilation system as required by code. 2.4.13 Kitchen Exhaust & Make-up 2.4.13.1 Description: The kitchen is provided with a gas fired make-up air unit and an upblast grease exhaust type exhaust fan. These units are provided with basic operational functioning controls. The system is not provided with the heat sensing controls to automatically energize the exhaust fan when cooking operations occur as is required by current code. 2.4.13.2 Condition: The units were installed in 2002 and are in good condition. The make-up air unit has seven years of remaining rated useful life and the upblast exhaust fan has 12 years of remaining rated life. 2.4.13.3 Efficiency: The motor efficiencies are unknown. The gas fired heater is a conventional 80% efficient type, not a high efficiency condensing type unit. 2.4.13.4 Recommendation: This system should remain in place, but be retrofitted with code compliant controls. Page 37 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland EXISTING CONDITIONS 2.5 Electrical Systems 2.5.1 Power Power Distribution: Electrical service for the building is provided via several services in different sections of the building. The main service is provided via a secondary substation located in a vault next to the boiler room. The power generation company is ‘PEPCO Energy Services’ and the power distribution company is ‘BGE’. According to BGE, total of 3 meters/electric services/accounts exist in the building. Voltage systems used in the building are 480Y/277V and 208Y/120V. There is a switchboard with capacity of 3000A located next to the vault in boiler room area for the main electric service. Electrical power throughout the building is distributed via high voltage and low voltage branch panelboards and dry-type transformers located in several electrical rooms/closets in different part of the building. Most of the existing panelboards/equips seems in a good condition and working properly. Existing main switchboard in main electric room and some panelboards are old and have a poor condition. Power Company pole Primary service. Emergency power for building is provided by a 15 KW generator. The existing generator feeds emergency loads (mostly lighting) in the building. The unit is located inside the chiller room. Uninterruptible power for data racks/equipment in server rooms are provided by multiple small capacity UPS units in each location. Electrical panel board Page 38 of 112 Electrical panel board Main Switchboard Electrical panel board Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects Interior Lighting: The lighting systems throughout the building are based upon the original designs. Most of the fixtures are old. The additions, which were constructed at different times, vary in lighting design style and fixture selections. The most recent addition has a design approach which eliminates the traditional ceiling, paints the underside of the deck above black, and suspends troffers or pendant fixtures (depending on the space). There has been some recent luminaire retrofit activity in which the older T-12 fluorescent lamps and magnetic ballasts have been replaced by T-8 lamps and electronic ballasts. Following are the lighting conditions for some of the areas: Corridors: mostly 2X4 recessed fixtures with fluorescent lamps are used. Many of these fixtures have been retrofitted with the T-8 lamps and electronic ballasts. These fixtures seem to be in a good condition. Classrooms: different fixtures are used. In most classrooms fixtures are 1X4 surface mounted with fluorescent lamps. Light fixtures in most of classrooms are old and are not in a good condition. Science Labs Addition: Fixtures in this part are mostly1x4 and 2X4 with fluorescent lamps. This part of building was renovated recently and light fixtures in these areas seem in fair condition. Ceiling Light Fixtures Ceiling Light Fixtures Auditorium Lighting Auditorium: Different down light fixtures and also fluorescent fixtures are used in this area. Stage lighting is provided by projector fixtures. Some projectors are used in audience area. There is a dimming system to control lighting in auditorium. Emergency Lighting and Exit Lights: Auditorium Lighting Emergency lighting in different parts of the building are provided by wall mounted double-head battery pack fixtures or ceiling fixtures with battery ballasts. Most of recently renovated areas have ceiling fixtures with battery ballasts for emergency lighting. Exit Sign Page 39 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects The existing exit lights throughout the building differ in appearance and lamping depending upon the age of the given area of the building and whether the fixture is original or has been replaced. Generally they are single or double faced, green LED fixtures. The condition of these fixtures in renovated areas seems fair. Power for emergency lighting as part of critical loads is provided by the existing emergency generator. Exterior Lighting: Driveway Lighting Lighting for parking lots and driveways on the site is provided by exterior fixtures with HID lamps. Fixtures for Parking lot areas are mounted on high poles with single or double arms. Lighting in regular driveways is provided by fixtures with reflector and lens mounted on top of shorter poles. Some light fixtures and poles are not in a good condition. It seems the exterior lighting is controlled via time switch. 2.5.2 Fire Alarm System Parking Lot Lighting Existing System: Building has a conventional fire alarm system with multiple control panels from manufacturers such as Simplex and Notifier. Fire alarm control panels are located in different part of the building. There are 2 main fire alarm annunciator panels (FAAP) which are located in front of reception area in the entrance lobby. Both have graphic faceplates showing building floor plans. Initiation Devices: Fire Alarm Control Panel Fire alarm Pull boxes provided at exit doors. Smoke detectors installed in some areas of corridors and some classrooms. No smoke detector provided in front of elevator door, elevator machine room. Many classrooms even without sprinkler system have no smoke detector. Pull stations in some locations are not ADA compliant. They’re installed too high. Smoke Detector Page 40 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland Notification Appliances: Strobes, horns and alarm bells are installed in corridors and media center. There are no notification devices in classrooms, bathrooms electric and server rooms. In term of installation, notification devices in most locations are not ADA compliant. Audio/Visual Notification Device Fire Alarm Control Panel Fire Alarm Control Panel Fire Alarm Graphic Annunciator 2.5.3 Public Address System There is an existing public address (PA) / intercommunication system in school. Existing PA system has been renovated in recent years. Existing system includes central control by TELECOR II, ceiling speakers mostly in corridors, media center and cafeteria and wall speakers in classrooms and gymnasium. Call stations are provided in all classrooms. Wall mounted volume control switches are installed mostly in office areas. Existing PA system seems generally in fair condition. Protection cover on some speakers in gymnasium is broken. Speakers in classrooms are not in a good condition. PA System Main Control 2.5.4 Data & Wireless Systems There are 2 server rooms in school. Each includes data racks and wireless devices. Small size UPS units are provided to feed data equipment. Data outlets are provided in classrooms, most of offices and media center. As part of science lab addition, complete data network is installed for all locations in this part of building. Air conditioning systems in both existing server rooms are not working properly. Server Room Page 41 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland 2.5.5 Security System There is an existing security system in school. Existing security system includes security control panel, security cameras, motion sensors and other initiation and notification devices. For outdoor security, wall mounted cameras are installed outside the building. Also security lighting via wall mounted outdoor type light fixtures with HID lamps is provided at the perimeter walls of the building. Inside the building motion detectors are provided mostly in corridors. Other security devices are provided in other locations throughout the building. Security system coverage throughout the building and system operation needs to be verified. Security Lighting Motion Sensor Security Camera 2.5.6 Grounding and Lightning Protection System Existing grounding system includes main building grounding electrodes, main grounding terminal and ground terminals in several locations in the building. It appears grounding conductors and bonding are provided for all panelboards and equipment. Existing lightning protection system consists of air terminals at the roof around the building and related bonded copper conductors. While the air terminals and bonding to copper conductors at the roof is visible from grade, the balance of Lightning Protection Air Terminal the system is concealed. Normally the conductors are connected to the ground via grounding electrodes. Regarding the age of the system, complete verification of both systems including all devices and connections necessary tests and measurement seems necessary. Page 42 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects EXISTING CONDITIONS 2.6 Plumbing Systems The building is served by the County water system. The existing 8" water main enters the front of the site through a meter vault and distributes to two hydrants at the front of the building. The sprinkler service enters the front of the building at the west end of the administration wing where an existing water room is located. The domestic hot water is generated by circulating heating water from the boilers though tubes of a shell and tube heat exchanger which heats water in the shell of the heat exchanger. The domestic hot water is drawn out of a large horizontal storage tank through the shell - and back to the tank by in-line circulator pumps. The tank is insulated and we were not able to locate a nameplate with a size; however, we estimate that the tank stores approximately 2,500 gallons. The age and capacity of the system is unknown (it was not documented on the available materials). Natural gas fired water heaters were added in parallel during the renovation of the science wing in 1997; thus allowing the boilers to be shut down at the end of the heating season. This installation does not meet current code requirements. The equipment needs to be modified or replaced and appropriate tempering valves added to provide tepid water. Plumbing fixtures all appear to be original or dated and beyond their useful life. The water closets are floor-mounted, urinals are floor and wall-mounted, and lavatories are individual wall hung type. Plumbing fixtures no longer meet code requirements for water usage and are not properly configured for ADA accessibility. The building has a crawl space throughout, which accommodates accessibility to distribution and drainage piping for repair, inspection, and replacement. The existing exposed piping in the crawl spaces can be inspected to determine its condition, allowing significant savings if it is determined that the piping is in fair to good condition. Since this piping is accessible, a decision to delay replacement even if only for 5-10 years is not critical because this piping can be easily replaced. Based on the age of the original building and additions, the existing water distribution system should be tested for lead content. If tests conclude that lead is present in unacceptable levels, then the distribution system should be replaced in its entirety. Due to the age of the installed plumbing lines, it will be necessary to cut out sections of sanitary, domestic cold and domestic hot water lines in several locations in the subbasement, and inspect this piping for scale and/or corrosion. The inspection results will contribute to deciding the scope of piping replacement required during a building renovation/modernization program. Minimum recommended actions include: 1. Replace all domestic water, sanitary and storm piping located outside of existing crawl spaces. 2. Replace all plumbing fixtures. New plumbing fixtures will be installed with provisions for ADA accessibility. Page 43 of 112 Severna Park High School Severna Park, Maryland 3. 4. 2.7 Feasibility Study GWWO, Inc./Architects The existing sanitary and storm water piping within the crawl space will be utilized where deemed possible. All risers and branches to new fixture layouts will be new piping. New modular high efficiency gas-fired water heaters should be installed. This domestic water heating system will serve the entire building and will be equipped with hot water circulators, expansion tank, and tempering valves as required. Fire Protection System The building currently is not protected by a full coverage fire sprinkler system. The media wing and portions of the existing administration wing are protected with automatic fire sprinklers. If the school is revitalized, modernized, or replaced, a full coverage sprinkler system will need to be installed in order for the building to be code compliant. The existing water service is adequate for flow to supply a sprinkler system; however, a fire pump will need to be added to boost the pressure for distribution to the extremities of the building. An alternative to the fire pump may be to feed the site from another section of the grid which would divide the flow and thereby increase pressure available by reducing pressure drop to the site during flow conditions. This option should be evaluated by the civil engineer for feasibility. Recommended minimum actions include: 1. Provide a fire pump to boost pressure to the building. The sprinkler service and all zone valves will be located in a new fire pump room. 2. Extend systems to all parts of the building for a fully sprinklered facility in accordance with all applicable NFPA standards. Multiple sprinkler zones will be provided for the building. 3. The sprinkler system will be hydraulically designed to minimize pipe size requirements and to provide an economical distribution system for the building. Page 44 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects CODE ANALYSIS Accessibility Evaluation: The existing school is generally accessible in that an accessible ramp at the main entry permits public access into the school and an elevator installed with the 1971 addition makes the second floor generally accessible. It was noted that the public entrance to gymnasium is not accessible as there are exterior steps and no accessible ramp. A general examination of the existing school found the following areas to be deficient. All must be further reviewed and addressed during the schematic design phase of this project: Accessible entry and exits to and from the school must be added. Toilet rooms and stalls must be made accessible, including all plumbing equipment. Required clearances at some doors may not be adequate for accessibility. Door hardware must generally be replaced with accessible door hardware. Height of all pull stations, switches and signage does not comply, and must be fixed. Classroom and other public space entries must be reviewed for ADA compliance. All egress door swings and clearances must be reviewed and brought into compliance. Door closers must be tested, so that force required to open doors is compliant. Assistive listening devices will be required in public spaces. ADA compliant signage will be required. Building/Life Safety Code Evaluations: The existing school is a mixture of concrete masonry bearing wall and steel frame construction types totaling 296,191 GSF. Only a portion of the building is currently sprinklered. These areas include the 1971 additions of the media center and administration offices. The building can be classified as Type 2C (non-combustible/unprotected) construction in accordance with the 2006 IBC code. The occupancy classification is Mixed Use, including Educational and Assembly type occupancies. Both of these classifications must be confirmed with the Anne Arundel County code officials during schematic design if the Board of Education selects to move forward with either Revitalization or Modernization. The existing school is currently non-compliant in terms of area allowed. In the options including Code Upgrade work, an automatic fire sprinkler system would be added. This will result in the allowable area limitation being increased. However, given the size of the existing building and the additions proposed in both the Revitalization and Modernization options, the building will still exceed the increased area limitations requiring the building be divided into separate fire areas. The additions will have to be separated from the existing building with a fire wall, making them entirely separate buildings from a code standpoint. Special considerations should be given to the following code concerns in future phases: The fire alarm system will require upgrading to interface with the new addition(s). Assembly uses shall be properly separated from Educational uses. Existing Hazardous Materials must be abated. Sprinkler system must be installed. Fire alarm must be upgraded. Any new fire alarm with the addition must be tied into the existing system, or the existing system must be replaced. Smoke barriers must be installed between the corridors and other spaces. A paved fire lane must be installed around the perimeter of the building to enable fire truck access. Page 45 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland This page intentionally left blank. Page 46 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION A: DO NOTHING Assessment This is the no-cost option of doing nothing to the existing facility. This option establishes a base line for comparison to other schemes. Advantages: 1. School operations will not be disrupted since there will be no construction activities. Disadvantages: 1. Spatial requirements set forth in the Educational Specifications will not be met by the existing building. 2. The existing building does not meet current life safety and building codes. 3. The existing building will remain inefficient with regard to energy and water consumption. 4. Maintenance items which have been deferred will remain deferred. 5. Costs will be incurred in the near future to replace many building systems that are reaching, or are beyond their rated useful lives. 6. Congestion will continue to be an issue in the main corridor during lunch periods and at dismissal. 7. Bus traffic and parent drop off traffic will remain in conflict. Page 47 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION B: PATCH AND PAINT ASSESSMENT This option provides for a minimal repair and painting of the existing facility, incorporating minor repairs to systems and construction to provide continuing service for the foreseeable future. No significant changes to the existing structure will be made to conform to the proposed Educational Specification or to address building and life safety concerns. Advantages: 1. Most of this work will be completed during summer break and after hours so school operations will be minimally disrupted. 2. Deferred maintenance items will be prioritized and completed as the budget allows. 3. Exterior brick veneer will be repaired. 4. Interior finishes will be repaired and in some cases replaced. 5. There is no loss of use of the existing stadium and play fields. Disadvantages: 1. The existing facility falls short of meeting the program, area, and adjacency requirements of the Educational Specifications. 2. Indoor air quality and comfort will remain inadequate as the existing distribution system will not be upgraded to meet current standards. 3. Existing window systems will remain and continue to provide only minimal amounts of daylight in the classrooms 4. Exterior walls will remain uninsulated, thus the thermal performance will continue to be poor in relation to a new facility and energy consumption will not be improved. 5. Accessibility, building, and life safety code upgrades will not occur. The majority of the building will remain unprotected by an automatic fire sprinkler system. 6. Costs will be incurred in the near future to replace many building systems that are reaching, or are beyond their rated useful lives. ANTICIPATED SCOPE OF WORK Architectural – Interior Existing interior wall finishes will be repaired and painted. Floor finishes will be changed out in those spaces where the Educational Specifications call for a different finish than exists in a space. All acoustical ceiling panels will be replaced and the existing suspended metal grid system will be repainted. Interior doors will be refinished. Existing hardware will be repaired where possible. In some instances, hardware may be replaced. Casework in classrooms and offices will be repaired as required. Science classroom equipment and fixtures will be replaced as required. Page 48 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland OPTION B: PATCH AND PAINT EXISTING SITE PLAN 6 LANE TRACK STADIUM FIELD TENNIS COURTS PLAY FIELD #1 PLAY FIELD #2 PLAY FIELD #3 BASEBALL SOFTBALL SEATING: 1,664 HOME 756 VISITORS FIELD HOUSE PLAY FIELD #4 STUDENT PARKING MEDIA CENTER GYMNASIUM STAFF PARKING/ BUS STACKING AUDITORIUM CAFETERIA SIGNALIZED INTERSECTION B-BALL STUDENT COURTS PARKING STAFF & VISITOR PARKING/ PARENT DROP OFF/ BUS STACKING BUS STACKING MAIN ENTRY DRIVE PLAY FIELD #5 Severna Park High School Severna Park, Maryland OPTION B: PATCH AND PAINT EXISTING FIRST FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION B: PATCH AND PAINT EXISTING SECOND FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION B: PATCH AND PAINT Architectural – Exterior Only those areas of the roof which require repair will be repaired. The existing brick veneer and cast stone sills will be repaired and re-pointed where required. Severely corroded doors and frames will be replaced. All doors and frames will be repainted. Windows, doors, and masonry expansion joints will be resealed. Site No significant changes will occur. Structural Existing to remain. HVAC Existing to remain; though as noted previously in this report, many system components are approaching or have surpassed their rated useful life and will need to be replaced in the near future. Plumbing Existing to remain; though as noted previously in this report, many system components are approaching or have surpassed their rated useful life and will need to be replaced in the near future. Fire Protection System The building will remain only partially protected by an automatic sprinkler system. Electrical Existing to remain. Fire Alarm System Existing to remain. Intercom and Sound System Existing to remain. Voice, Data and Video Systems Existing to remain. Security System Existing to remain. Page 49 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION ASSESSMENT Revitalization of the existing building will reuse most of the existing building though portions will be demolished to accommodate new additions that are required to meet programmatic requirements of the Educational Specifications. Spaces within the additions will meet the area requirements of the Educational Specifications, but rooms in the existing building will not be structurally modified. Therefore, most classrooms will continue to be either over or under their specified area. Advantages: 1. 2. 3. 4. 5. 6. 7. Program areas are grouped by program/department. Existing courtyards are kept; two new ones are created. Stadium remains in existing location. Existing fields remain in current locations; act as a good buffer. No further impact on the surrounding neighborhoods. The facility will meet the EdSpec program requirements, but not all area requirements. The facility will comply with current building, life safety, and accessibility codes and standards. 8. Interior circulation is improved through the addition of cross halls and multiple entrances to the cafeteria. 9. Energy efficient electrical and mechanical systems will be installed in the existing building. 10. Site safety and circulation are improved by separating bus queuing and parent drop off traffic. Disadvantages: 1. Multiple phases of construction. 2. Construction staging area must be relocated for phases 3 and 4 with limited staging and construction parking. 3. Building is occupied during construction activities. 4. Minimum of sixteen relocatable classrooms are needed during construction. 5. Only spaces in the new additions will meet Ed Spec area requirements since there won’t be structural modifications made to spaces in the existing building. 6. Distance between departments can be great since the building is spread out. 7. Possibility that stadium will not be able to be used for athletic events during the first two phases of construction. 8. No student parking on site for duration of construction. 9. There will be one less play field than currently exists. 10. Entrance drives for buses and cars are not separated. 11. Narrow hallways in the existing building will remain. 12. Programs and students will be relocated a minimum of two times to facilitate renovations. 13. Daylighting will not be increased in existing classrooms as windows will be replaced in existing openings. 14. Track will remain only six lanes wide. 15. Limited school activities after hours due to construction. 16. No outside agency use (Parks & Rec) of building during duration of construction. 17. No evening high school. 18. No summer school. Page 50 of 112 Severna Park High School Severna Park, Maryland OPTION C: REVITALIZATION SITE PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION C: REVITALIZATION FIRST FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION C: REVITALIZATION SECOND FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION ANTICIPATED SCOPE OF WORK Architectural – Interior Spaces in all additions will be designed to meet the Educational Specifications. Spaces in the existing building will not be reconfigured as interior walls will remain in place. Therefore, many of the existing spaces will not comply with the Educational Specifications. Existing finishes will be upgraded in accordance with the Educational Specifications. All floor tile, base, ceiling panels, suspended grids, and ceramic tile will be replaced. All casework will be replaced and redesigned to meet the Educational Specifications. Interior doors, frames, and hardware will be replaced to meet accessibility requirements. Existing terrazzo flooring will be maintained. Lockers will be replaced in accordance with the Educational Specifications. The existing elevator will be upgraded to meet current codes. Three sections of the existing building which include the gymnasium, physical education, food services, music, auditorium, and technology education program spaces will be demolished to accommodate new additions. Architectural – Exterior Site Failing window sills will be replaced. Brick will be re-pointed where required and replaced where new flashing is required. Existing windows and exterior doors will be replaced within existing window openings. Areas of the existing roof will be repaired. New bus staging loop capable of supporting 26 buses to be constructed at the front of the school to allow for the separation of the bus and vehicular traffic. Reconfiguration of the existing faculty/visitor parking lot. A large portion (approximately 27,000 SF) of the parking lot will be removed to accommodate the new food services wing. New paved surface will be constructed in the location of the existing auditorium wing. This paved area will serve as a new designated student drop off as well as to provide visitor parking. A new service yard area will be constructed adjacent to the new food services wing. A 20’ wide paved fire lane will be constructed to connect the staff/visitor parking lot with the student parking lot and also provide emergency vehicle access to the grassed multi-purpose fields. The student parking area will be expanded to accommodate the parking lost for the construction of the food services wing. Milling and resurfacing of all existing paved services. Removal of approximately 500 LF of various sized (15” to 27”) storm drain lines, and approximately 450 LF of 8” sanitary sewer around the existing gymnasium. Relocation of the school’s 3” gas service. Removal of approximately 17,000 SF of concrete sidewalk around the existing gymnasium. Page 51 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION Site - continued New concrete sidewalks throughout. Ten foot (10’) wide walks will be constructed along the front of the school and new bus staging loop, five foot (5’) walks will be constructed around the perimeter of the remainder of the new construction to allow for pedestrian access around the campus. Moderate grading for all construction. Five areas have been identified to construct underground infiltration trenches and four additional areas have been identified for micro bio-retention areas. The underground trenches range in size from 2,040 SF to 8,800 SF. The areas identified are under the parking adjacent to the new food services wing, behind the existing classroom wing and adjacent to the new physical education wing. The micro-bio-retention areas range from approximately 1,500 SF to 2,500 SF and are located along the frontage of the site between Robinson Road and the new bus staging loop and between Benfield Road and the existing student parking area. Structural Existing building: Minor repairs as required. Modify roof and floor framing and provide additional foundation for new fire walls. Modify and reinforce existing structure for new mechanical units and related work. Modify and reinforce existing structure for new clerestory at the roof level above the existing Media center. New exterior elevator masonry shaft with foundation at upgraded elevator. Roof structure capacity will be assessed for new roof top mechanical equipment. Additional structural work will be required to accommodate the anticipated mechanical, electrical and other upgrades. Reinforcing of isolated structural elements may be required. New roof openings will likely need to be framed for new roof penetrations. Existing abandoned roof penetrations will be patched. Auditorium, Gymnasium, Physical Education, Tech Ed and Lab, Cafeteria and Kitchen additions: Tech Ed and Lab addition will be a two story. All other additions will be a single story. Load bearing CMU walls with structural steel framed structure. The roof structure at the Auditorium and Gymnasium will consist of long span open web steel joists at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck or Tectum deck. The roof structure at all other areas will consist open web K-series steel joists at 5’-0” on center with 1-1/2”, 22 gage, galvanized metal roof deck. The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck. Masonry walls at the auditorium and gymnasium will be a load bearing 12” thick reinforced CMU. Page 52 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION Structural - continued Walls less than 18’-0” tall can be 8” thick reinforced CMU. Second floor construction at the lab addition will consist of 3”concrete on a form deck supported by open web joists at 24” to 36” on center. This floor structure will be supported by load bearing masonry walls. Steel beams and columns will be provided as required by the architectural layout. The new additions will abut the existing building, which have a framed first floor with a crawl space. The existing finished floor elevation is close to the exterior grade. A geotechnical investigation will be conducted during the design phase to determine foundation recommendations. If a slab on grade is feasible from a geotechnical standpoint, then a 5” concrete slab on grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost effective compared to a framed structure with a crawl space. However, if the recommendations of the geotechnical report indicate that a slab on grade is not feasible, and a framed first floor structure be required, 8” precast concrete plank with a 2” lightweight concrete topping slab supported by masonry bearing walls in the crawl space is a viable option. Additional deeper foundation walls will likely be required at the juncture of the additions with the existing to “close off” existing crawl spaces from the backfill. We anticipate a shallow spread footing foundation system, consistent with the existing building, will be appropriate. However, this must be confirmed by a geotechnical investigation. Mechanical A. General Overview The mechanical systems will be designed in compliance with DGS and all industry standards essentially replacing the entire HVAC system as a means to: bring the system up to current standards, increase system efficiency, address the user's needs for the next 20+ years, and improve sustainability. The overall goals of the system retrofit are: provide good indoor air quality, to be highly energy efficient, to be easily maintainable, to have low first cost as well as low life cycle costs, and to be cognizant of project construction budget limitations. The system we are recommending is Active Chilled Beams supplied from Dedicated Outside Air Systems (DOAS) with a Central Geothermal Water to Water Heat Pump Plant. B. Ventilation System The first major component of the proposed overall HVAC system is the Dedicated Outside Air System (DOAS) which delivers code required outside air directly to the room level. The purpose of the dedicated ventilation system is to decouple the conditioning of outside air used for ventilation from the conditioning of room air. The primary advantage of the decoupling is that the outside air can be properly dehumidified regardless of the sensible cooling load of the space, assuring improved room relative humidity levels during space partial cooling load conditions. The use of the DOAS also reduces the operating cost by only Page 53 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION Mechanical – continued requiring the conditioning of the quantity of outside air required to meet the sum of all space ventilation loads. C. Overhead Active Chilled Beams The chilled beam provides heating or cooling on demand on a room by room basis. The unit has no fan; it uses the induction air principal, driven by ventilation air, to cause 3 to 4 times the air flow rate of the DOAS ventilation air to be drawn up through the perforated panel in the center of the chilled beam – across the terminal unit coil – and be discharged with the DOAS ventilation air out the two linear slot diffusers on the perimeter of the chilled beam. The hydronic arrangement of the system is four pipe. The chilled beams use the return chilled water from the DOAS unit. D. Central Geothermal Water to Water Heat Pump Plant The main component is a modular water to water heat pump which uses multiple nominal thirty to seventy ton modules. Each module is an independently controlled (staged) heat pump capable of producing chilled and hot water. The modular unit as a whole can produce chilled and heating water simultaneously. The source side of the modular unit is piped to a geothermal well field which provides a heat source/sink. E. System Equipment The system is comprised of: 1. A modular geothermal grade water to water heat pump unit with VME valving using fifteen 70 ton modules. Basis of design: Multistack 2. Two variable volume frame mounted end suction geothermal well field water pumps with variable frequency drives. 3. Two variable volume frame mounted end suction heating water pumps with variable frequency drives. 50 HP 4. Two variable volume frame mounted end suction chilled water pumps with variable frequency drives, 1,700 GPM, 100 HP. 5. One geothermal well field with approximately 180 wells using a depth of 600 feet, using 1-1/4" SDR-9 in the vertical bore hole and SDR-11 or 15 piping for the horizontals. Wells to be grouted with high conductivity (1.2) bentonite grout. 3,150 GPM, 100 HP 6. Five 20,000 CFM ERU’s for the DOAS 7. Five 7,500 CFM large space AHU's, 8. Fan coil units for the entry areas (areas subject to very high infiltration loads). 9. A chilled beam(s) for each remaining occupied room. A typical classroom for 30 students would take three six foot chilled beams. 10. Heating water convectors or hot water unit heaters for restrooms and utility spaces. 11. A DDC Building Management System. 12. Some miscellaneous utility fans (propeller and cabinet type). Page 54 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION Mechanical – continued F. Advantages Some of the advantages of the chilled beam and modular water to water geothermal heat pump system include the following: 1. Superior indoor air quality due to: a. Excellent cooling season relative humidity control. b. The high ventilation effectiveness due to the characteristics of the induction air method. 2. The highest degree of zoning with essentially every occupied space being provided with individual temperature control. 3. Space by space heating or cooling on demand. 4. A reduction in ductwork when compared with a VAV system or ducted water source heat pump system with DOAS. 5. Very high operating efficiency. a. Mass energy storage over time for reuse in the building. b. High efficiency heating and cooling plant at design temperatures (COP = 4+, EER = 14+). These improve dramatically at partial load conditions due to the geothermal characteristics. c. An efficiency improvement from the increased chilled water temperature difference. 6. While the four pipe system arrangement requires a second piping network inside the building, the delta Tee of both systems is greater than 500% larger than the first three options minimizing the cost impact of the additional piping. 7. First cost and maintenance cost savings from the consolidation of all heating and cooling plant equipment into a single unit. This includes: a. Savings from centralized compressor maintenance. b. Savings from the elimination of 85% of the filter maintenance. 8. A first cost and maintenance cost reduction on the electrical power distribution system associated with the elimination of a water source heat pump unit for each room. This eliminates: a branch circuit to each unit, several electrical panel boards, a feeder for each panel board and a switchboard switch for each feeder. Some cost is added back in for the circuiting to the modular water to water heat pump and extra pumps, however, all of those units are located immediately adjacent to the main electrical room. 9. Very low background noise levels due to the elimination of a terminal unit fan. Plumbing All existing plumbing fixtures will be removed. New fixtures will be provided. New layouts and fixture clearances will comply with the Americans with Disabilities Act. Cold and tempered water will be provided to all lavatories. Hot and cold water will be provided to all sinks. Fixtures will be high efficiency, low flow and lowest water usage available at time of design. Page 55 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION Plumbing – continued All above ground domestic water, sanitary and storm piping will be removed and new piping will be provided. The adequacy of the existing domestic water service needs to be verified according to new layouts, additions, and final fixture count for new design. The entire domestic water system will be brought into compliance with current codes regarding cross connection control and metering will be provided in accordance with the requirements of the local water authority and owner's requirements. The existing underground sanitary and storm water piping will be utilized where possible; however, all new piping will be installed above grade in crawlspace due to major changes planned for toilet partitioning in the building. The domestic water heating system for the main building will be a central system in the main boiler room. Separate, dedicated gas fired water heaters will be provided for the kitchen. The main domestic water heating system being proposed for use in this building is a geothermal heat pump system with new double wall heat exchangers and hot water being stored in the existing storage tank. The existing tank will be cleaned and relined. The kitchen water heater will be gas fired storage type, direct vented, condensing high efficiency heater with piped outside air intake. Fire Protection System Existing fire sprinkler system will remain and a new system will be installed in all unsprinklered areas. Extension of the system will require the installation of a fire pump in order to overcome the friction losses for the greater lengths of piping required. System will be zoned in accordance with NFPA 13, and each zone will follow the boundaries of the fire alarm system zones. Electrical A. Power Distribution System Existing power distribution system including panelboards, transformers and related wiring will be removed and new equipment and wiring will be provided. Also existing wall devices will be removed and based on requirement, new devices will be installed. Existing grounding system including all ground conductors, grounding bonds, connection/connectors, ground rods and terminals will be verified and grounding system resistance will be measured. In case of any issue in the system, appropriate correction/modifications will be suggested. In new addition buildings new ground terminals will be provided for equipment ground connections and panelboards. Electrical power in new addition buildings specified in this option, such as new Gymnasium, Auditorium, music and related spaces and cafeteria/kitchen will be distributed via a new Page 56 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION Electrical – continued panelboard which will be located in each building. For new portable classrooms, a separate distribution panel will be specified to feed power box in each classroom trailer. All these panels will be fed from the existing main distribution panel inside the main electrical room. Existing demand load in the building will be evaluated and new electrical load will be calculated for entire school. Based on new load situation, the existing electrical service will have an upgraded power transformer/substation. In order to feed loads related to life safety system and other loads which will required standby power a new power generator with two automatic transfer switches, and related distribution system will be provided. B. Lighting All existing lighting fixtures will be removed and new light fixtures will be provided. Based on new lighting distribution, extra fixtures will be provided as necessary. New lighting control system will be installed in each location. In order to save energy, occupancy sensors will be specified for existing spaces to turn off the lights when it is not in use. Complete new lighting system will be designed for each new addition building. Type of light fixtures in each space will depend on the application and the character of the space. Light fixtures with direct/indirect distribution will be used for all classrooms and teaching spaces. Light fixtures/lamps types, and related controls will be selected such that the system’s energy saving is as much as possible. Occupancy sensors will be provided for all spaces to turn off lights when the space is not in use. Day light harvesting system will be specified for applicable spaces. Light fixtures in gymnasium shall have wire guards. Exit lights and emergency lighting will be provided for exit entrance and all means of egress. New exit lights and emergency fixtures shall include battery back-ups. Battery back-up chargers for these fixtures will be connected to emergency circuits. Fire Alarm System The existing fire alarm system will be removed and a new addressable fire alarm system will be provided to cover entire school including the existing building and new additions. Fire alarm booster panels/sub-panels will be provided if necessary. New initiation and notification devices will be provided for all locations. In each space based on the requirement, notification devices will be audio or visual types or combination of both. In all assembly areas, voice alarm system will be specified. Page 57 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION C: REVITALIZATION Public Address and Sound System A new public address system will be provided for the entire school including the existing building and new additions. Ceiling and wall speakers will be installed in different spaces. Call buttons and volume control devices will be installed as necessary. Special sound systems will be provided in the gymnasium, auditorium, and music spaces. The new sound system will include speakers, microphone/jacks and control panels with necessary components/devices. Data, Telephone and Intercommunication Systems New data, telephone, and intercommunication systems located in server rooms/closets will be provided for entire school. These systems include all servers, wireless communication devices and UPS units to maintain the operation of servers and other equips without any interruption in case of power outage. Security System New security system will be provided for entire school. New system includes door contacts, window contacts, motion detectors and security monitoring system with CCTV cameras. This system will be designed by a security consultant and will be installed under supervision of school security personnel. Page 58 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland This page intentionally left blank. Page 59 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION ASSESSMENT Modernization will result in a facility that meets the Educational Specifications. It requires a combination of demolition, renovation, and new construction. Advantages: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Program areas are grouped by program/department. Existing courtyards are kept; two new ones are created. Stadium remains in existing location. All areas meet all EdSpec requirements. Existing fields remain in current locations; act as a good buffer. No further impact on the surrounding neighborhoods. The facility will comply with current building, life safety, and accessibility codes and standards. Interior circulation is improved through the addition of cross halls and multiple entrances to the cafeteria. Energy efficiency will be increased with new lighting and mechanical systems installed throughout the existing building. Daylighting in existing classrooms will increase as existing window openings will be increased. Site safety and circulation are improved by separating bus queuing and parent drop off traffic. Disadvantages: 1. Multiple phases of construction. 2. Construction staging area must be relocated for phases 3 and 4 with limited staging and construction parking. 3. Building is occupied during construction. 4. Minimum of sixteen relocatable classrooms are needed during construction. 5. Distance between departments can be great since the building is spread out. 6. Possibility that stadium will not be able to be used for athletic events during the first two phases of construction. 7. No student parking on site for duration of construction 8. There will be one less play field than currently exists. 9. Entrance drives for buses and cars are not separated. 10. Narrow hallways in the existing building remain. 11. Programs and students will be relocated a minimum of two times to facilitate major renovations in the existing building. 12. Longest construction period both overall and within the building in comparison with the other options. 13. Track will remain only six lanes wide. 14. Limited school activities after hours due to evening construction. 15. No outside agency building use (Parks & Rec) due to evening construction. 16. No evening high school. 17. No summer school. Page 60 of 112 Severna Park High School Severna Park, Maryland OPTION D: MODERNIZATION SITE PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION D: MODERNIZATION FIRST FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION D: MODERNIZATION SECOND FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION ANTICIPATED SCOPE OF WORK Architectural – Interior Many interior partitions will be relocated so program areas meet the Educational Specifications. All doors and hardware will be replaced and brought into compliance with ADA standards. Most interior door frames will be replaced. Existing terrazzo floors will be maintained and repaired. New acoustical panel ceilings and grids will be installed throughout. All existing ceramic tile will be replaced. Lockers will be replaced. All toilet partitions and accessories will be replaced. All classroom and office casework will be replaced including science classroom casework. Interiors within the new additions will comply with AACPS Design Guidelines. Architectural – Exterior All exterior windows, doors, and frames will be replaced. New windows will be larger than the existing to provide more daylight and natural ventilation in classrooms. Existing deteriorated brick veneer will be either re-pointed, or removed and re-installed. Roofing systems will be replaced with roof insulation values increased to meet current energy codes. Exterior signage will be replaced and updated. Exteriors of the new additions will be designed to be compatible with the existing building proportions and materials. Site New bus staging loop capable of supporting 26 buses to be constructed at the front of the school to allow for the separation of the bus and vehicular traffic. Reconfiguration of the existing faculty/visitor parking lot. A large portion (approximately 27,000 SF) of the parking lot will be removed to accommodate the new food services wing. New paved surface will be constructed in the location of the existing auditorium wing. This paved area will serve as a new designated student drop off as well as to provide visitor parking. A new service yard area will be constructed adjacent to the new food services wing. A 20’ wide paved fire lane will be constructed to connect the staff/visitor parking lot with the student parking lot and also provide emergency vehicle access to the grassed multi-purpose fields. The student parking area will be expanded to accommodate the parking lost for the construction of the food services wing. Milling and resurfacing of all existing paved services that remains. Removal of approximately 500 LF of various sized (15” to 27”) storm drain lines, and approximately 450 LF of 8” sanitary sewer around the existing gymnasium. Relocation of the school’s 3” gas service. Page 61 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION Site - continued Removal of approximately 17,000 SF of concrete sidewalk around the existing gymnasium. New concrete sidewalks throughout. Ten foot (10’) wide walks will be constructed along the front of the school and new bus staging loop, five foot (5’) walks will be constructed around the perimeter of the remainder of the new construction to allow for pedestrian access around the campus. Moderate grading for all construction. Five areas have been identified to construct underground infiltration trenches and four additional areas have been identified for micro bio-retention areas. The underground trenches range in size from 2,040 SF to 8,800 SF. The areas identified are under the parking adjacent to the new food services wing, behind the existing classroom wing and adjacent to the new physical education wing. The micro-bio-retention areas range from approximately 1,500 SF to 2,500 SF and are located along the frontage of the site between Robinson Road and the new bus staging loop and between Benfield Road and the existing student parking area. Structural Existing building: Minor repairs as required. Modify roof and floor framing and provide additional foundation for new fire walls. Modify and reinforce existing structure for new mechanical units and related work. Modify and reinforce existing structure for new clerestory at the roof level above the existing Media center. Relocation of interior non-loadbearing walls will require structural reinforcement of existing floor system. New exterior elevator masonry shaft with foundation at upgraded elevator. Roof structure capacity will be assessed for new roof top mechanical equipment. Additional structural work will be required to accommodate the anticipated mechanical, electrical and other upgrades. Reinforcing of isolated structural elements may be required. New roof openings will likely need to be framed for new roof penetrations. Existing abandoned roof penetrations will be patched. Auditorium, Gymnasium, Physical Education, Tech Ed and Lab, Cafeteria and Kitchen additions: Tech Ed and Lab addition will be two stories. All other additions will be a single story. Load bearing CMU walls with structural steel framed structure. The roof structure at the Auditorium and Gymnasium will consist of long span open web steel joists at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck or Tectum deck. The roof structure at all other areas will consist open web K-series steel joists at 5’-0” on center with 1-1/2”, 22 gage, galvanized metal roof deck. The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck. Page 62 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION Structural – continued Masonry walls at the auditorium and gymnasium will be a load bearing 12” thick reinforced CMU. Walls less than 18’-0” tall can be 8” thick reinforced CMU. Second floor construction at the lab addition will consist of 3”concrete on a form deck supported by open web joists at 24” to 36” on center. This floor structure will be supported by load bearing masonry walls. Steel beams and columns will be provided as required by the architectural layout. The new additions will abut the existing building, which have a framed first floor with a crawl space. The existing finished floor elevation is close to the exterior grade. A geotechnical investigation will be conducted during the design phase to determine foundation recommendations. If a slab on grade is feasible from a geotechnical standpoint, then a 5” concrete slab on grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost effective compared to a framed structure with a crawl space. However, if the recommendations of the geotechnical report indicate that a slab on grade is not feasible, and a framed first floor structure be required, 8” precast concrete plank with a 2” lightweight concrete topping slab supported by masonry bearing walls in the crawl space is a viable option. Additional deeper foundation walls will likely be required at the juncture of the additions with the existing to “close off” existing crawl spaces from the backfill. We anticipate a shallow spread footing foundation system, consistent with the existing building, will be appropriate. However, this must be confirmed by a geotechnical investigation. Mechanical A. General Overview The mechanical systems will be designed in compliance with DGS and all industry standards essentially replacing the entire HVAC system as a means to: bring the system up to current standards, increase system efficiency, address the user's needs for the next 20+ years, and improve sustainability. The overall goals of the system retrofit are: provide good indoor air quality, to be highly energy efficient, to be easily maintainable, to have low first cost as well as low life cycle costs, and to be cognizant of project construction budget limitations. The system we are recommending is Active Chilled Beams supplied from Dedicated Outside Air Systems (DOAS) with a Central Geothermal Water to Water Heat Pump Plant. B. Ventilation System The first major component of the proposed overall HVAC system is the Dedicated Outside Air System (DOAS) which delivers code required outside air directly to the room level. The purpose of the dedicated ventilation system is to decouple the conditioning of outside air used for ventilation from the conditioning of room air. The primary advantage of the Page 63 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION Mechanical – continued decoupling is that the outside air can be properly dehumidified regardless of the sensible cooling load of the space, assuring improved room relative humidity levels during space partial cooling load conditions. The use of the DOAS also reduces the operating cost by only requiring the conditioning of the quantity of outside air required to meet the sum of all space ventilation loads. C. Overhead Active Chilled Beams The chilled beam provides heating or cooling on demand on a room by room basis. The unit has no fan; it uses the induction air principal, driven by ventilation air, to cause 3 to 4 times the air flow rate of the DOAS ventilation air to be drawn up through the perforated panel in the center of the chilled beam – across the terminal unit coil – and be discharged with the DOAS ventilation air out the two linear slot diffusers on the perimeter of the chilled beam. The hydronic arrangement of the system is four pipe. The chilled beams use the return chilled water from the DOAS unit. D. Central Geothermal Water to Water Heat Pump Plant The main component is a modular water to water heat pump which uses multiple nominal thirty to seventy ton modules. Each module is an independently controlled (staged) heat pump capable of producing chilled and hot water. The modular unit as a whole can produce chilled and heating water simultaneously. The source side of the modular unit is piped to a geothermal well field which provides a heat source/sink. E. System Equipment The system is comprised of: 1. A modular geothermal grade water to water heat pump unit with VME valving using fifteen 70 ton modules. Basis of design: Multistack 2. Two variable volume frame mounted end suction geothermal well field water pumps with variable frequency drives. 3. Two variable volume frame mounted end suction heating water pumps with variable frequency drives. 50 HP 4. Two variable volume frame mounted end suction chilled water pumps with variable frequency drives, 1,700 GPM, 100 HP. 5. One geothermal well field with approximately 180 wells using a depth of 600 feet, using 1-1/4" SDR-9 in the vertical bore hole and SDR-11 or 15 piping for the horizontals. Wells to be grouted with high conductivity (1.2) bentonite grout. 3,150 GPM, 100 HP 6. Five 20,000 CFM ERU’s for the DOAS 7. Five 7,500 CFM large space AHU's, Page 64 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION Mechanical – continued 8. Fan coil units for the entry areas (areas subject to very high infiltration loads). 9. A chilled beam(s) for each remaining occupied room. A typical classroom for 30 students would take three six foot chilled beams. 10. Heating water convectors or hot water unit heaters for restrooms and utility spaces. 11. A DDC Building Management System. 12. Some miscellaneous utility fans (propeller and cabinet type). F. Advantages Some of the advantages of the chilled beam and modular water to water geothermal heat pump system include the following: 1. Superior indoor air quality due to: a. Excellent cooling season relative humidity control. b. The high ventilation effectiveness due to the characteristics of the induction air method. 2. The highest degree of zoning with essentially every occupied space being provided with individual temperature control. 3. Space by space heating or cooling on demand. 4. A reduction in ductwork when compared with a VAV system or ducted water source heat pump system with DOAS. 5. Very high operating efficiency. a. Mass energy storage over time for reuse in the building. b. High efficiency heating and cooling plant at design temperatures (COP = 4+, EER = 14+). These improve dramatically at partial load conditions due to the geothermal characteristics. c. An efficiency improvement from the increased chilled water temperature difference. 6. While the four pipe system arrangement requires a second piping network inside the building, the delta Tee of both systems is greater than 500% larger than the first three options minimizing the cost impact of the additional piping. 7. First cost and maintenance cost savings from the consolidation of all heating and cooling plant equipment into a single unit. This includes: a. Savings from centralized compressor maintenance. b. Savings from the elimination of 85% of the filter maintenance. 8. A first cost and maintenance cost reduction on the electrical power distribution system associated with the elimination of a water source heat pump unit for each room. This eliminates: a branch circuit to each unit, several electrical panel boards, a feeder for each panel board and a switchboard switch for each feeder. Some cost is added back in for the circuiting to the modular water to water heat pump and extra pumps, however, all of those units are located immediately adjacent to the main electrical room. 9. Very low background noise levels due to the elimination of a terminal unit fan. Page 65 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION Plumbing All existing plumbing fixtures will be removed. New fixtures will be provided. New layouts and fixture clearances will comply with the Americans with Disabilities Act. Cold and tempered water will be provided to all lavatories. Hot and cold water will be provided to all sinks. Fixtures will be high efficiency, low flow and lowest water usage available at time of design. All above ground domestic water, sanitary and storm piping will be removed and new piping will be provided. The adequacy of the existing domestic water service needs to be verified according to new layouts, additions, and final fixture count for new design. The entire domestic water system will be brought into compliance with current codes regarding cross connection control and metering will be provided in accordance with the requirements of the local water authority and owner's requirements. The existing underground sanitary and storm water piping will be utilized where possible; however, all new piping will be installed above grade in crawlspace due to major changes planned for toilet partitioning in the building. The domestic water heating system for the main building will be a central system in the main boiler room. Separate, dedicated gas fired water heaters will be provided for the kitchen. The main domestic water heating system being proposed for use in this building is a geothermal heat pump system with new double wall heat exchangers and hot water being stored in the existing storage tank. The existing tank will be cleaned and relined. The kitchen water heater will be gas fired storage type, direct vented, condensing high efficiency heater with piped outside air intake. Fire Protection System Existing fire sprinkler system will remain and a new system will be installed in all unsprinklered areas. Extension of the system will require the installation of a fire pump in order to overcome the friction losses for the greater lengths of piping required. System will be zoned in accordance with NFPA 13, and each zone will follow the boundaries of the fire alarm system zones. Electrical A. Power Distribution System Existing power distribution system including panelboards, transformers and related wiring will be removed and new equipment and wiring will be provided. Also existing wall devices will be removed and based on requirement, new devices will be installed. Existing grounding system including all ground conductors, grounding bonds, connection/connectors, ground rods and terminals will be verified and grounding system resistance will be measured. In case of any issue in the system, appropriate Page 66 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION Electrical – continued correction/modifications will be suggested. In new addition buildings new ground terminals will be provided for equipment ground connections and panelboards. Electrical power in new addition buildings specified in this option, such as new Gymnasium, Auditorium, music and related spaces and cafeteria/kitchen will be distributed via a new panelboard which will be located in each building. For new portable classrooms, a separate distribution panel will be specified to feed power box in each classroom trailer. All these panels will be fed from the existing main distribution panel inside the main electrical room. Existing demand load in the building will be evaluated and new electrical load will be calculated for entire school. Based on new load situation, the existing electrical service will have an upgraded power transformer/substation provided. In order to feed loads related to life safety system and other loads which will required standby power a new power generator with two automatic transfer switches, and related distribution system will be provided. B. Lighting All existing lighting fixtures will be removed and new light fixtures will be provided. Based on new lighting distribution, extra fixtures will be provided as necessary. New lighting control system will be installed in each location. In order to save energy, occupancy sensors will be specified for existing spaces to turn off the lights when it is not in use. Complete new lighting system will be designed for each new addition building. Type of light fixtures in each space will depend on the application and the character of the space. Light fixtures with direct/indirect distribution will be used for all classrooms and teaching spaces. Light fixtures/lamps types, and related controls will be selected such that the system’s energy saving is as much as possible. Occupancy sensors will be provided for all spaces to turn off lights when the space is not in use. Day light harvesting system will be specified for applicable spaces. Light fixtures in gymnasium shall have wire guards. Exit lights and emergency lighting will be provided for exit entrance and all means of egress. New exit lights and emergency fixtures shall include battery back-ups. Battery back-up chargers for these fixtures will be connected to emergency circuits. Fire Alarm System The existing fire alarm system will be removed and a new addressable fire alarm system will be provided to cover entire school including the existing building and new additions. Fire alarm booster panels/sub-panels will be provided if necessary. New initiation and notification devices will be provided for all locations. In each space based on the requirement, notification devices will be audio or visual types or combination of both. In all assembly areas, voice alarm system will be specified. Page 67 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION D: MODERNIZATION Public Address and Sound System A new public address system will be provided for the entire school including the existing building and new additions. Ceiling and wall speakers will be installed in different spaces. Call buttons and volume control devices will be installed as necessary. Voice enhancement systems will be installed in all classrooms. Special sound systems will be provided in the gymnasium, auditorium, and music spaces. The new sound system will include speakers, microphone/jacks and control panels with necessary components/devices. Data, Telephone and Intercommunication Systems New data, telephone, and intercommunication systems located in server rooms/closets will be provided for entire school. These systems include all servers, wireless communication devices and UPS units to maintain the operation of servers and other equips without any interruption in case of power outage. Security System New security system will be provided for entire school. New system includes door contacts, window contacts, motion detectors and security monitoring system with CCTV cameras. This system will be designed by a security consultant and will be installed under supervision of school security personnel. Page 68 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland This page intentionally left blank. Page 69 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION E: REPLACEMENT ‘A’ ASSESSMENT A new building will be constructed in two phases on site so that the existing stadium and track can remain in place. The existing building will remain in full use during the construction of Phase 1. The construction of Phase 2 will require the existing gymnasium and physical education wing to be demolished. During Phase 2 the new gymnasium and physical education spaces will be used. Thus, the school will have to operate out of two buildings during Phase 2. Advantages: 1. 2. 3. 4. 5. 6. 7. 8. 9. New building. Existing track and stadium remain in place. Possible continued use of stadium throughout construction for P.E. Flexible space for future curriculum changes. Interior circulation is efficient. LEED certified building. Full separation of bus queuing and parent drop-off areas. Facility will meet all EdSpec requirements as well as all building, life safety, energy, and accessibility codes and standards. Daylighting in all classrooms. Disadvantages: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Three phases for overall construction process – longer timeframe than Replacement B. Construction and Life-Cycle Costs are higher compared to Replacement B. School will operate out of two buildings during phase two. Partial occupied construction. Possibility that stadium will not be able to be used for athletic events throughout construction, due to access through construction site. No student parking on site for the duration of construction. Track and stadium field are separated from other play fields. Fewer practice and play fields than currently exist. Student parking and parent drop off are not fully separated. New building must be constructed in two phases. Track will remain only six lanes wide. Parking lots for auditorium and gymnasium events in finished facility are not close to the building. Disturbance to neighbors along back property during construction and could continue to be an issue at completion due to shape of building (i.e. site lighting). Page 70 of 112 Severna Park High School Severna Park, Maryland OPTION E: REPLACEMENT ‘A’ SITE PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION E: REPLACEMENT ‘A’ FIRST FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland OPTION E: REPLACEMENT ‘A’ SECOND & THIRD FLOOR PLANS SECOND FLOOR THIRD FLOOR Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION E: REPLACEMENT ‘A’ ANTICIPATED SCOPE OF WORK Architectural A new building will meet all Educational Specifications requirements. Materials and equipment will be designed to meet AACPS Design Guidelines. All classrooms, offices, and common spaces will have abundant daylight. Site The new school will be constructed adjacent to the existing school in the area currently occupied by the grass multi-purpose fields. The existing stadium and track will remain in its current location. The new multi-purpose fields, tennis courts and basketball courts will be constructed in the area currently occupied by the staff/visitor parking. Vehicular access points will remain at their current locations and separation of vehicular and bus traffic has been maximized in addition to separation of vehicular traffic and parent drop off. A new thirty foot (30’) wide drive will be constructed at the Red Oak Drive intersection (currently the access point for the staff/visitor parking). This drive will provide access to the new bus staging loop (26 buses). An emergency vehicle drive will also be constructed off of the main drive to allow for emergency vehicle access to the play field area. A new two way drive will be constructed at the White Oak Drive intersection (currently the bus loop egress). This drive will provide access to the staff and visitor parking. The staff parking areas will be located adjacent to Robinson Road with the visitor parking being located further into the site and adjacent to the new classroom wing. A new parent drop off loop will be constructed utilizing the outer portion (drive) of the visitor parking area. The third access point, at the intersection of Benfield Road and Evergreen Road will remain as access into the student parking and staff parking. Total on-site parking will be capable of supporting 400 vehicles. A new 20’ wide fire access lane will be constructed around the perimeter (sides and rear) of the building. Fire access for the front of the building will be achieved via the new bus staging loop and the parent drop off loop. The fire lane will be accessed from the new bus staging loop and will proceed around the rear of the building and continue eventually terminating at the new student parking area. The 20’ drive (fire lane) located between the existing stadium field/track and the new building will also serve as access to the new service area which will be located at the far northeast side of the new building adjacent to the new food services wing. Multi-purpose field #1 will be located adjacent to the bus staging loop. Immediately east of this field will be the new fenced and lit tennis court area (10 courts) with bleachers for 200 spectators; continuing easterly will be the new basketball courts (3 half courts) and multipurpose field #2 which will be located closest to Robinson Road. Multi-purpose field #3 will be located adjacent (north) of the new fenced tennis courts. The remaining fields, baseball, softball and multi-purpose field #4 will remain in their current location. Page 71 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION E: REPLACEMENT ‘A’ Site – continued Multi-purpose fields #1 through #3 will be 360’ x 200’. One field will be Bermuda grass and the other two fields will be tall fescue fields. All fields will be irrigated. This option will require the permanent relocation of approximately 750 LF of 48” public storm drain and the permanent relocation of approximately 800’ of public 8” sanitary sewer prior to the beginning of the building construction. In addition approximately 320 LF of 24” storm drain and 280 LF of 8” sanitary sewer will be temporarily relocated once the permanent public utility relocation is completed to allow for the existing school to remain operational during construction. Two areas have been identified to construct underground infiltration trenches, six areas have been defined for micro bio-retention areas and an additional four areas have been identified for landscape infiltration areas. The underground trenches range in size from 4,350 SF to 4,750 SF. The areas identified are adjacent to the classroom wing under the visitor parking area and adjacent to the physical education wing. The micro-bio-retention areas range from approximately 1,900 SF to 2,750 SF and are located along the frontage of the site between Robinson Road and Benfield Road, adjacent to the new bus staging loop drive, adjacent to the staff and visitor parking and adjacent to the stadium/track and student parking. The landscape infiltration areas range from 2,400 SF to 3,600 SF and are located between the basketball and tennis courts, within the bus staging loop and within the area between the bus staging loop and multi-purpose field #1. Structural One story Administration offices, Auditorium, Gymnasium, Theatre/Music/Dance, Physical Education, Cafeteria and Kitchen: Load bearing CMU walls with structural steel framed structure. The roof structure at the Auditorium and Gymnasium will consist of long span open web steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck or Tectum deck. The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck. The roof structure at all other areas will consist of open web K-series steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck. Masonry walls at the auditorium and gymnasium will consist of load bearing 12” thick reinforced CMU. Walls less than 18’-0” tall can be 8” thick reinforced CMU. Steel beams and columns will be provided as required by the architectural open space layout. Three story Classroom and Media center wing: The roof structure will consist of open web K-series joists at 5’-0” on center with 1½” deep 22 gauge galvanized roof deck. Page 72 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION E: REPLACEMENT ‘A’ Structural – continued The Second and Third floor construction will consist of 3” thick concrete on a form deck supported by open web joists at 24” to 36” o.c. Majority of the floor structure will be supported by load bearing masonry walls. Interior beams and columns will be used at the media center to provide open space. The mechanical penthouse will consist of 4½” concrete on 2” composite deck. The first floor above the mechanical basement will consist of 4½” thick concrete on 2” composite deck supported by composite beams and girder system with interior columns. Basement wall will be reinforced concrete walls on a continuous footing. If a slab on grade is feasible from a geotechnical standpoint, then a 5” thick concrete slab on grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost effective compared to a framed structure with a crawl space. We anticipate a shallow spread footing foundation system, consistent with the existing building, will be appropriate. However, this must be confirmed by a geotechnical investigation. Mechanical Mechanical system design for a replacement building will use the same approach as that described above in Option C: Revitalization. Plumbing New building will have all new utility services from the public mains. It is suggested that looping the building with a new fire main and hydrants be investigated under the civil portion of the design. All new plumbing fixtures will be provided. New layouts and fixture clearances will comply with the Americans with Disabilities Act. Cold and tempered water will be provided to all lavatories. Hot and cold water will be provided to all sinks. Fixtures will be high efficiency and lowest water usage available at time of design. All materials for domestic water, sanitary and storm piping will be specified in accordance with current code requirements and building practices. The entire domestic water system will be designed to current codes regarding cross connection control. Metering will be provided in accordance with the requirements of the local water authority and owner's requirements. The domestic water heating system for the main building will be a central system in the main boiler room. Separate, dedicated gas fired water heaters will be provided for the kitchen. The main domestic water heating system being proposed for use in this building is a geothermal heat pump system and storage tank with internal heat exchanger. Page 73 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION E: REPLACEMENT ‘A’ Fire Protection System Proper fire sprinkler system will be designed for new building. It is anticipated that a new fire service loop would be provided around the new building serving multiple fire service entrances and fire hydrants on site. The adequacy of flow and pressure available will depend on the configuration, location, elevations, size of footprint, height, and connections to the public system. The sprinkler system will be designed and installed in accordance with all requirements of NFPA 13, and will be hydraulically designed to minimize pipe size requirements and to provide an economical distribution system for the building. Electrical A. Power Distribution System New building will have a new electrical service. New power transformer will be located at the site close as possible to the new main electric room. If secondary substation is required, new vault will be designed for new equipment. Building’s new secondary service will be 480Y/277V, 3-phase, 4-wire. School will have dual voltage systems. All lighting loads, AC system, roof top units and other large equipment will be fed with 480/277V system. All receptacles, computer loads, PA system, Fire Alarm and security control panels and other small loads will be on 208/120 volt system. Building secondary service will be connected to a main distribution panelboard (MDP) inside the new main electrical room. Secondary distribution panels will be located inside electrical closets through-out the building. Each electrical room/closet will have high voltage (480/277V) panels and also low voltage (208/120V) panelboards. Low voltage panels will be fed from high voltage panels via drytype transformers. K-rated transformers will be used for all low voltage panels that feed nonlinear loads such as computers, servers and other electronic equipment. Stand-by generator will be provided for all emergency loads such as exit lights, emergency lighting for means of egress and fire alarm control panels. Automatic transfer switch (ATS) will be used to transfer the power from normal source to generator and vice versa. All loads which are not critical and needed to be fed by stand-by power will be connected to a separate transfer switch. Auto transfer switch related to critical/emergency loads will be located inside a fire rated closet. Emergency loads and other loads which require stand-by power will be connected to separate panels. Loads on stand-by generator will be according to requirements in Ed Spec. Emergency panels will be located inside electric rooms/closet. B. Lighting Proper lighting system will be designed for new building. Type of Light fixtures in each space will depend on the application and the type of the space. Fixtures with direct/indirect distribution will be selected for all classrooms and teaching spaces. Light fixtures/lamps Page 74 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION E: REPLACEMENT ‘A’ types, and related controls will be selected such that the energy efficiency in the system is as high as possible. Occupancy sensors will be provided for all spaces to turn off lights when the space is not in use. Day light harvesting system will be specified for applicable spaces. Special lighting control/dimming system will be specified in auditorium. Light fixtures in gymnasium shall have wire guards. Exit lights and emergency lighting will be provided for exits, entrances, and all means of egress. New exit lights and emergency fixtures shall include battery back-up. Outdoor lighting will be provided for building entrances. Pole mounted fixtures will be specified for all drive ways and parking lights. Bollard fixtures will be selected for walkways and building accesses. Special lighting system will be designed for all sport fields. Fire Alarm System New fire alarm system will be non-coded addressable type with addressable initiation and notification devices. Fire alarm booster panels/sub-panels will be provided, if necessary in different locations. In each space based on requirement, notification devices will be audio or visual types or combination of both. For all assembly areas, voice alarm system will be specified. Fire alarm zoning will be coordinated with sprinkler system in the building. A new annunciator panel will be located at the building’s main entrance. Fire alarm control panel including battery back-ups will be located inside the main electric room. Public Address System A new public address system will be provided for entire school. New ceiling and wall speakers will be installed in different spaces. As required, new call switch and volume controls will be provided inside spaces. Sound Systems New special sound systems will be provided in gymnasium, auditorium and music spaces. New sound system will include speakers, microphone/jacks and control panels with necessary components and devices. Voice enhancement systems will be provided in all classrooms. Data, Telephone and Intercommunication Systems Equipment for these systems will be located inside MDF and IDF closets. Appropriate communication wiring will be provided between MDF and IDF closets. These systems include all servers, wireless communication devices and UPS units to maintain the Page 75 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION E: REPLACEMENT ‘A’ operation of servers and other equips without any interruption in case of power outage. Wall-mounted data/telephone outlets will be installed in every location as required. Security System Security system for new building includes door contacts, window contacts, motion detectors and security monitoring system with CCTV cameras. This system will be designed by a security consultant and will be installed under supervision of school security personnel. Main control panel for this system, security keypads and monitoring equipment will be located in a separate room. Page 76 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland This page intentionally left blank. Page 77 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION F: REPLACEMENT ‘B’ ASSESSMENT A new building will be constructed on site in a single phase with minimal disruption to the operations of the existing facility. The existing building will remain in use during construction. The existing track, stadium, and practice fields will not be available for the duration of construction. Advantages: 1. Entirely new, non-phased building construction allows for the most efficient design. This option will result in the smallest square footage of building, thus lowest overall operational costs. 2. Two phases for overall construction process/building and site – shorter timeframe than Replacement A. 3. Non-occupied construction with full separation of students and construction. 4. All Ed Spec requirements are met including athletic fields and an eight lane track. 5. Minimal disruption to operations during construction. 6. Site circulation and safety. 7. Efficient interior circulation. 8. Better facilitation of inter-discipline instruction. 9. Flexible spaces for future curriculum changes. 10. LEED certified building. 11. Efficient site design, activities are grouped together – curricular and extracurricular. 12. Existing number of athletic fields is maintained. 13. Full separation of bus queuing and parent drop-off areas. 14. Facility will meet all EdSpec requirements as well as all building, life safety, energy, and accessibility codes and standards. 15. Daylighting in all classrooms. 16. Building is constructed in a single phase. 17. Lower construction and life cycle costs than Replacement A, Revitalization, and Modernization options. Disadvantages: 1. Loss of use of outdoor athletic facilities for the duration of construction, with the exception of the baseball and softball fields during phase one. 2. No student parking on site for the duration of construction. 3. Possible loss of interior courtyards as secure outdoor classrooms. 4. Disturbance to neighbors during construction along back property line and could continue due to shape of building. 5. Impact of nighttime athletics on different set of neighbors. 6. Student parking and parent drop off are not fully separated. Page 78 of 112 Severna Park High School Severna Park, Maryland OPTION F: REPLACEMENT ‘B’ SITE PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION F: REPLACEMENT ‘B’ FIRST FLOOR PLAN Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland OPTION F: REPLACEMENT ‘B’ SECOND & THIRD FLOOR PLANS SECOND FLOOR THIRD FLOOR Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION F: REPLACEMENT ‘B’ ANTICIPATED SCOPE OF WORK Architectural A new building will meet all Educational Specifications requirements. Materials and equipment will be designed to meet AACPS Design Guideline All classrooms, offices, and common spaces will have abundant daylight. Site The new school will be constructed in the location currently occupied by the stadium/track and the grass multi-purpose fields. The existing baseball, softball and small multi-purpose fields will remain at their current location. All of the new recreational areas including the new stadium/track, tennis courts, grassed multi-purpose fields, and basketball courts will be constructed in the area currently occupied by school, bus staging loop and staff/visitor parking. Two of the three original vehicular access points will remain at their current location. The existing entry to the site for the staff/visitor parking will be removed. A new access point will be installed adjacent to Holland Road along Benfield Road at the far southwest corner of the site. Separation of vehicular and bus traffic has been maximized in addition to separation of vehicular traffic and parent drop off. A new thirty foot (30’) wide drive will be constructed at the White Oak Drive intersection (currently the bus loop egress). This drive will provide access to the new bus staging loop (26 buses). An emergency vehicle drive will also be constructed off of the main drive to allow for emergency vehicle access to the play field area. The Evergreen Road entry point (currently access to the student parking area) will remain the same and will provide access to a new student parking area, visitor parking area and parent drop off loop The new entry adjacent to Holland Road will provide access to staff parking and service. Total on-site parking will be capable of supporting 400 vehicles. A new 20’ wide fire access lane will be constructed around the perimeter (sides and rear) of the building. Fire access for the front of the building will be achieved via the new bus staging loop and the parent drop off loop. The fire lane will be accessed from the new bus staging loop and will proceed around the rear of the building and continue eventually terminating at the new service yard. A new 20’ drive (emergency vehicle access) will be constructed between the tennis courts and the new grassed multi-purpose field #3. This new drive will be accessed off of the new bus loop drive and will provide access for emergency vehicles during sporting events and maintenance vehicles. The new stadium track will be constructed at the front of the site along Robinson Road in the location currently occupied by the bus loop and front of the existing school. The stadium field will measure 360’x220 and will be an artificial turf field. The field will be surrounded by an eight lane (42” wide) rubberized track. Additional track and field areas will also be Page 79 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION F: REPLACEMENT ‘B’ Site – continued constructed at this location including an area for high jump, long jump, discus and pole vaulting area. Bleachers will also be installed to accommodate 4000 spectators (2,500 home, 1,500 visitors). The new fenced and lit tennis courts (8 courts are currently shown, but 10 will be the goal during development of the site design) will be installed immediately west of the stadium/track. Bleachers will also be installed for up to 200 spectators. Grassed multi-purpose fields #1 through #3 will be located immediately east of the new tennis court area with field #4 being located north of the tennis courts. An emergency vehicle drive will also be constructed between the tennis courts and field #3 and will also allow for access to the new field house. Emergency vehicle access to the remaining field will be via the bus loop and fire lane. One of these fields will be Bermuda grassed and the remaining fields will be tall fescue fields. All fields will contain irrigation systems. Multi-purpose fields #1 through #4 will be 360’ x 200’. The new fenced basketball courts (3 half courts) will be located north of the new building immediately adjacent to the new fire lane. This option will require the permanent relocation of approximately 750 LF of 48” public storm drain and the permanent relocation of approximately 800’ of public 8” sanitary sewer prior to the beginning of the building construction. In addition approximately 320 LF of 24” storm drain and 280 LF of 8” sanitary sewer will be temporarily relocated once the permanent public utility relocation is completed to allow for the existing school to remain operational during construction. Two areas have been identified to construct underground infiltration trenches, eight areas have been defined for micro bio-retention areas and an additional four areas have been identified for landscape infiltration areas. The underground trenches are approximately 11,200 SF each. The areas identified are adjacent to the classroom wing under the student parking area and adjacent to the physical education wing. The micro-bio-retention areas range from approximately 1,520 SF to 2,880 SF and are located along the frontage of the site between Robinson Road and Benfield Road, adjacent to the new bus staging loop drive, and along the far southwest corner of the property adjacent to the staff parking. The landscape infiltration areas range from 900 SF to 4,200 SF and are located along the front of the building, within the parent drop off loop and bus staging loop and between the fire lane and grassed multi-purpose field #1. Structural One story Administration offices, Auditorium, Gymnasium, Theatre/Music/Dance, Physical Education, Cafeteria and Kitchen: Load bearing CMU walls with structural steel framed structure. The roof structure at the Auditorium and Gymnasium will consist of long span open web steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck or Tectum deck. The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck. Page 80 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION F: REPLACEMENT ‘B’ Structural – continued The roof structure at all other areas will consist of open web K-series steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck. Masonry walls at the auditorium and gymnasium will consist of load bearing 12” thick reinforced CMU. Walls less than 18’-0” tall can be 8” thick reinforced CMU. Steel beams and columns will be provided as required by the architectural open space layout. Three story Classroom and Media center wing: The roof structure will consist of open web K-series joists at 5’-0” on center with 1½” deep 22 gauge galvanized roof deck. The Second and Third floor construction will consist of 3” thick concrete on a form deck supported by open web joists at 24” to 36” o.c. Majority of the floor structure will be supported by load bearing masonry walls. Interior beams and columns will be used at the media center to provide open space. The mechanical penthouse will consist of 4½” concrete on 2” composite deck. The first floor above the mechanical basement will consist of 4½” thick concrete on 2” composite deck supported by composite beams and girder system with interior columns. Basement wall will be reinforced concrete walls on a continuous footing. If a slab on grade is feasible from a geotechnical standpoint, then a 5” thick concrete slab on grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost effective compared to a framed structure with a crawl space. We anticipate a shallow spread footing foundation system, consistent with the existing building, will be appropriate. However, this must be confirmed by a geotechnical investigation. Mechanical Mechanical system design for a replacement building will use the same approach as that described above in Option C: Revitalization. Plumbing New building will have all new utility services from the public mains. It is suggested that looping the building with a new fire main and hydrants be investigated under the civil portion of the design. All new plumbing fixtures will be provided. New layouts and fixture clearances will comply with the Americans with Disabilities Act. Cold and tempered water will be provided to all lavatories. Hot and cold water will be provided to all sinks. Fixtures will be high efficiency and lowest water usage available at time of design. Page 81 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION F: REPLACEMENT B Plumbing – continued All materials for domestic water, sanitary and storm piping will be specified in accordance with current code requirements and building practices. The entire domestic water system will be designed to current codes regarding cross contamination control. Metering will be provided in accordance with the requirements of the local water authority and owner's requirements. The domestic water heating system for the main building will be a central system in the main boiler room. Separate, dedicated gas fired water heaters will be provided for the kitchen. The main domestic water heating system being proposed for use in this building is a geothermal heat pump system and storage tank with internal heat exchanger. Fire Protection System Proper fire sprinkler system will be designed for new building. It is anticipated that a new fire service loop would be provided around the new building serving multiple fire service entrances and fire hydrants on site. The adequacy of flow and pressure available will depend on the configuration, location, elevations, size of footprint, height, and connections to the public system. The sprinkler system will be designed and installed in accordance with all requirements of NFPA 13, and will be hydraulically designed to minimize pipe size requirements and to provide an economical distribution system for the building. Electrical A. Power Distribution System New building will have a new electrical service. New power transformer will be located at the site close as possible to the new main electric room. If secondary substation is required, new vault will be designed for new equipment. Building’s new secondary service will be 480Y/277V, 3-phase, 4-wire. School will have dual voltage systems. All lighting loads, AC system, roof top units and other large equipment will be fed with 480/277V system. All receptacles, computer loads, PA system, Fire Alarm and security control panels and other small loads will be on 208/120 volt system. Building secondary service will be connected to a main distribution panelboard (MDP) inside the new main electrical room. Secondary distribution panels will be located inside electrical closets through-out the building. Each electrical room/closet will have high voltage (480/277V) panels and also low voltage (208/120V) panelboards. Low voltage panels will be fed from high voltage panels via drytype transformers. K-rated transformers will be used for all low voltage panels that feed nonlinear loads such as computers, servers and other electronic equipment. Page 82 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION F: REPLACEMENT ‘B’ Electrical – continued Stand-by generator will be provided for all emergency loads such as exit lights, emergency lighting for means of egress and fire alarm control panels. Automatic transfer switch (ATS) will be used to transfer the power from normal source to generator and vice versa. All loads which are not critical and needed to be fed by stand-by power will be connected to a separate transfer switch. Auto transfer switch related to critical/emergency loads will be located inside a fire rated closet. Emergency loads and other loads which require stand-by power will be connected to separate panels. Loads on stand-by generator will be according to requirements in Ed Spec. Emergency panels will be located inside electric rooms/closet. B. Lighting Proper lighting system will be designed for new building. Type of Light fixtures in each space will depend on the application and the type of the space. Fixtures with direct/indirect distribution will be selected for all classrooms and teaching spaces. Light fixtures/lamps types, and related controls will be selected such that the energy saving in the system is as high as possible. Occupancy sensors will be provided for all spaces to turn off lights when the space is not in use. Day light harvesting system will be specified for applicable spaces. Special lighting control/dimming system will be specified in auditorium. Light fixtures in gymnasium shall have wire guards. Exit lights and emergency lighting will be provided for exits, entrances, and all means of egress. New exit lights and emergency fixtures shall include battery back-up. Outdoor lighting will be provided for building entrances. Pole mounted fixtures will be specified for all drive ways and parking lights. Bollard fixtures will be selected for walkways and building accesses. Special lighting system will be designed for all sport fields. Fire Alarm System New fire alarm system will be non-coded addressable type with addressable initiation and notification devices. Fire alarm booster panels/sub-panels will be provided, if necessary in different locations. In each space based on requirement, notification devices will be audio or visual types or combination of both. For all assembly areas, voice alarm system will be specified. Fire alarm zoning will be coordinated with sprinkler system in the building. A new annunciator panel will be located at the building’s main entrance. Fire alarm control panel including battery back-ups will be located inside the main electric room. Public Address System A new public address system will be provided for entire school. New ceiling and wall speakers will be installed in different spaces. As required, new call switch and volume controls will be provided inside spaces. Page 83 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects OPTION F: REPLACEMENT ‘B’ Sound Systems New special sound systems will be provided in gymnasium, auditorium and music spaces. New sound system will include speakers, microphone/jacks and control panels with necessary components and devices. Voice enhancement systems will be provided in all classrooms. Data, Telephone and Intercommunication Systems Equipment for these systems will be located inside MDF and IDF closets. Appropriate communication wiring will be provided between MDF and IDF closets. These systems include all servers, wireless communication devices and UPS units to maintain the operation of servers and other equips without any interruption in case of power outage. Wall-mounted data/telephone outlets will be installed in every location as required. Security System Security system for new building includes door contacts, window contacts, motion detectors and security monitoring system with CCTV cameras. This system will be designed by a security consultant and will be installed under supervision of school security personnel. Main control panel for this system, security keypads and monitoring equipment will be located in a separate room. Page 84 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX A – DETAILED COST ESTIMATES SUMMARY PAT CH & PAIN T DIV. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 CAT EGORY SITE WORK HAZMAT ABATEMENT CONCRETE MASONRY METALS CARPENTRY THERMAL & MOISTURE DOORS & WINDOWS FINISHES SPECIALTIES EQUIPMENT FURNISHINGS SPECIAL CONSTRUCTION CONVEYING SYSTEMS MECHANICAL ELECTRICAL TECHNOLOGY SF BID-DAY CONSTRUCTION COST SUBTOTAL TURF REPLACEMENT NEW STADIUM 0 0 $ 0.13 $ 1,319,500 $ $ 3.29 $ $ 0.22 $ 0.39 $ 0.29 $ 5.48 0.05 $ $ $ 0.03 $ $ $ 0.22 $ 0.16 $ $ 14.73 $ $ - BID-DAY CONSTRUCTION COST WITH FIELDS RELOCATABLES PHASING COSTS GENERAL CONDITIONS CONTINGENCY PREMIUM for OFF-HOURS WORK ESCALATION TO CONSTRUCTION A/E - CM FEES TOTAL CONSTRUCTION COST Project Duration T OT AL SF $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 38,962 1,319,500 974,054 64,937 116,886 84,418 1,623,423 16,234 9,741 64,937 48,703 4,361,794 4,361,794 357,988 1 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 $ $ $ $ $ $ $ 300,000 300,000 429,733 319,624 112,934 - 16 $ 4 $ 54 $ 15% 6% 2% 150,000 75,000 135,000 $ 5,824,086 $ 290 $/SF 296,191 1 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 4 $ 12 $ 10% 6% 2% 75,000 25,000 $ 19.66 REVIT IL IZAT ION 1 Year $/SF $ 26.31 $ 1,319,500 $ 6.30 $ 12.06 $ 12.61 $ 4.22 $ 7.67 $ 9.04 $ 12.06 $ 1.92 $ 3.56 $ 6.58 $ 5.48 $ 0.33 $ 57.00 $ 32.89 $ 3.51 $ 205 1 $ 918,000 0 $ - MODERN IZAT ION T OT AL SF $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 9,418,235 1,319,500 2,256,452 4,316,691 4,512,904 1,510,842 2,746,985 3,237,518 4,316,691 686,746 1,275,386 2,354,559 1,962,132 117,728 20,406,175 11,772,793 1,255,765 73,467,102 918,000 74,385,102 360,688 1 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 $ $ $ $ $ $ $ 2,400,000 300,000 7,290,000 11,157,765 5,731,972 2,025,297 555,000 16 $ 4 $ 66 $ 15% 6% 2% 150,000 75,000 135,000 $ 103,845,136 $ 330 4.5 Years $/SF $ 26.31 $ 1,319,500 $ 8.22 $ 18.64 $ 15.35 $ 5.32 $ 10.14 $ 13.70 $ 16.44 $ 3.01 $ 3.88 $ 7.67 $ 6.03 $ 0.33 $ 58.31 $ 32.89 $ 3.51 $ 233 1 $ 918,000 0 $ - REPL ACEMEN T "A" $ /SF T OT AL SF $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 9,489,268 1,319,500 2,965,396 6,721,565 5,535,407 1,917,623 3,657,322 4,942,327 5,930,793 1,087,312 1,399,667 2,767,703 2,174,624 118,616 21,030,591 11,861,586 1,265,236 84,184,537 918,000 85,102,537 342,517 1 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 $ $ $ $ $ $ $ 2,400,000 300,000 8,910,000 12,578,765 6,482,832 2,290,601 1,110,000 3 $ 48 $ 5% 1% 2% 75,000 135,000 $ 119,174,734 $ 303 5.5 Years $ 36.01 $ 1,015,000 $ 10.86 $ 25.64 $ 25.91 $ 4.53 $ 14.13 $ 14.68 $ 14.89 $ 4.91 $ 4.36 $ 8.13 $ 4.64 $ 0.49 $ 53.47 $ 28.91 $ 3.44 $ 258 1 $ 913,750 0 $ - REPL ACEMEN T "B" T OT AL SF $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 12,333,052 1,015,000 3,718,602 8,782,628 8,876,060 1,550,975 4,839,789 5,026,653 5,101,399 1,681,780 1,494,915 2,784,280 1,588,348 168,178 18,312,714 9,903,815 1,177,246 88,355,435 913,750 89,269,185 333,735 1 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 $ $ $ $ $ $ $ 225,000 6,480,000 4,463,459 1,004,376 2,028,840 277,500 2 $ 42 $ 5% 0% 2% 75,000 135,000 $ 103,748,361 $ 296 4 Years $ /SF $ 35.67 $ 1,015,000 $ 10.76 $ 25.40 $ 25.67 $ 4.49 $ 14.00 $ 14.54 $ 14.76 $ 4.86 $ 4.32 $ 8.05 $ 4.59 $ 0.49 $ 51.89 $ 28.11 $ 3.41 $ 254 0 $ 1 $ 2,130,000 T OT AL $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 11,905,053 1,015,000 3,589,554 8,477,841 8,568,031 1,497,151 4,671,832 4,852,211 4,924,363 1,623,416 1,443,037 2,687,656 1,533,227 162,342 17,316,441 9,379,739 1,136,391 84,783,284 2,130,000 86,913,284 $ $ $ $ $ $ $ 150,000 5,670,000 4,283,016 1,915,267 - $ 98,931,568 3.5 Years Page 85 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland This page intentionally left blank. Page 86 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX A – DETAILED COST ESTIMATES PATCH AND PAINT DIV. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 CAT EGORY SITE WORK HAZMAT ABATEMENT CONCRETE MASONRY METALS CARPENTRY THERMAL & MOISTURE DOORS & WINDOWS FINISHES SPECIALTIES EQUIPMENT FURNISHINGS SPECIAL CONSTRUCTION CONVEYING SYSTEMS MECHANICAL ELECTRICAL TECHNOLOGY $/SF SF 296,191 1 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 296,191 BID-DAY CONSTRUCTION COST SUBTOTAL TURF REPLACEMENT NEW STADIUM 0 0 $ 0.13 $ 1,319,500 $ $ 3.29 $ $ 0.22 $ 0.39 $ 0.29 $ 5.48 $ 0.05 $ $ 0.03 $ $ $ 0.22 $ 0.16 $ $ 14.73 $ $ - BID-DAY CONSTRUCTION COST WITH FIELDS RELOCATABLES PHASING COSTS GENERAL CONDITIONS CONTINGENCY PREMIUM for OFF-HOURS WORK ESCALATION TO CONSTRUCTION AE - CM FEES TOTAL CONSTRUCTION COST T OT AL $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 38,962 1,319,500 974,054 64,937 116,886 84,418 1,623,423 16,234 9,741 64,937 48,703 4,361,794 4,361,794 4 $ 12 $ 10% 6% 2% 75,000 25,000 $ $ $ $ $ $ 300,000 300,000 429,733 319,624 112,934 - $ 19.66 $ 5,824,086 Construction duration: 1 year Page 87 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX A – DETAILED COST ESTIMATES REVITALIZATION DIV. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 CAT EGORY SITE WORK HAZMAT ABATEMENT CONCRETE MASONRY METALS CARPENTRY THERMAL & MOISTURE DOORS & WINDOWS FINISHES SPECIALTIES EQUIPMENT FURNISHINGS SPECIAL CONSTRUCTION CONVEYING SYSTEMS MECHANICAL ELECTRICAL TECHNOLOGY $/SF SF 357,988 1 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 357,988 BID-DAY CONSTRUCTION COST SUBTOTAL TURF REPLACEMENT NEW STADIUM 1 0 $ 26.31 $ 1,319,500 $ 6.30 $ 12.06 $ 12.61 $ 4.22 $ 7.67 $ 9.04 $ 12.06 $ 1.92 $ 3.56 $ 6.58 $ 5.48 $ 0.33 $ 57.00 $ 32.89 $ 3.51 $ 205.22 $ 918,000 $ - $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 9,418,235 1,319,500 2,256,452 4,316,691 4,512,904 1,510,842 2,746,985 3,237,518 4,316,691 686,746 1,275,386 2,354,559 1,962,132 117,728 20,406,175 11,772,793 1,255,765 73,467,102 918,000 74,385,102 $ $ $ 150,000 75,000 135,000 $ $ $ $ $ $ $ 2,400,000 300,000 7,290,000 11,157,765 5,731,972 2,025,297 555,000 $ 290.08 BID-DAY CONSTRUCTION COST WITH FIELDS RELOCATABLES PHASING COSTS GENERAL CONDITIONS CONTINGENCY @ 15% PREMIUM for OFF-HOURS WORK 6% ESCALATION TO CONSTRUCTION 2% AE - CM FEES ABOVE 3.5 YEARS TOTAL CONSTRUCTION COST Construction duration: 4.5 years Page 88 of 112 16 4 54 T OT AL $ 103,845,136 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX A – DETAILED COST ESTIMATES MODERNIZATION DIV. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 CAT EGORY SITE WORK HAZMAT ABATEMENT CONCRETE MASONRY METALS CARPENTRY THERMAL & MOISTURE DOORS & WINDOWS FINISHES SPECIALTIES EQUIPMENT FURNISHINGS SPECIAL CONSTRUCTION CONVEYING SYSTEMS MECHANICAL ELECTRICAL TECHNOLOGY $/SF SF 360,688 1 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 360,688 BID-DAY CONSTRUCTION COST SUBTOTAL TURF REPLACEMENT NEW STADIUM 1 0 $ 26.31 $ 1,319,500 $ 8.22 $ 18.64 $ 15.35 $ 5.32 $ 10.14 $ 13.70 $ 16.44 $ 3.01 $ 3.88 $ 7.67 $ 6.03 $ 0.33 $ 58.31 $ 32.89 $ 3.51 $ 233.40 $ 918,000 $ - $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 9,489,268 1,319,500 2,965,396 6,721,565 5,535,407 1,917,623 3,657,322 4,942,327 5,930,793 1,087,312 1,399,667 2,767,703 2,174,624 118,616 21,030,591 11,861,586 1,265,236 84,184,537 918,000 85,102,537 $ $ $ 150,000 75,000 135,000 $ $ $ $ $ $ $ 2,400,000 300,000 8,910,000 12,578,765 6,482,832 2,290,601 1,110,000 $ 330.41 BID-DAY CONSTRUCTION COST WITH FIELDS RELOCATABLES PHASING COSTS GENERAL CONDITIONS CONTINGENCY @ 15% PREMIUM for OFF-HOURS WORK 6% ESCALATION TO CONSTRUCTION 2% AE - CM FEES ABOVE 3.5 YEARS TOTAL CONSTRUCTION COST 16 4 66 T OT AL $ 119,174,734 Construction duration: 5.5 years Page 89 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX A – DETAILED COST ESTIMATES REPLACEMENT ‘A’ DIV. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 CAT EGORY SITE WORK HAZMAT ABATEMENT CONCRETE MASONRY METALS CARPENTRY THERMAL & MOISTURE DOORS & WINDOWS FINISHES SPECIALTIES EQUIPMENT FURNISHINGS SPECIAL CONSTRUCTION CONVEYING SYSTEMS MECHANICAL ELECTRICAL TECHNOLOGY BID-DAY CONSTRUCTION COST SUBTOTAL TURF REPLACEMENT NEW STADIUM $/SF SF 342,517 1 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 342,517 $ 36.01 $ 1,015,000 $ 10.86 $ 25.64 $ 25.91 $ 4.53 $ 14.13 $ 14.68 $ 14.89 $ 4.91 $ 4.36 $ 8.13 $ 4.64 $ 0.49 $ 53.47 $ 28.91 $ 3.44 $ 257.96 1 $ 913,750 0 $ - BID-DAY CONSTRUCTION COST WITH FIELDS RELOCATABLES PHASING COSTS GENERAL CONDITIONS CONTINGENCY @ 5% PREMIUM for OFF-HOURS WORK 1% ESCALATION TO CONSTRUCTION 2% AE - CM FEES ABOVE 3.5 YEARS TOTAL CONSTRUCTION COST Construction duration: 4 years Page 90 of 112 3 48 $ $ 75,000 135,000 $ 302.90 T OT AL $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 12,333,052 1,015,000 3,718,602 8,782,628 8,876,060 1,550,975 4,839,789 5,026,653 5,101,399 1,681,780 1,494,915 2,784,280 1,588,348 168,178 18,312,714 9,903,815 1,177,246 88,355,435 913,750 89,269,185 $ $ $ $ $ $ 225,000 6,480,000 4,463,459 1,004,376 2,028,840 277,500 $ 103,748,361 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX A – DETAILED COST ESTIMATES REPLACEMENT ‘B’ DIV. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 CAT EGORY SITE WORK HAZMAT ABATEMENT CONCRETE MASONRY METALS CARPENTRY THERMAL & MOISTURE DOORS & WINDOWS FINISHES SPECIALTIES EQUIPMENT FURNISHINGS SPECIAL CONSTRUCTION CONVEYING SYSTEMS MECHANICAL ELECTRICAL TECHNOLOGY BID-DAY CONSTRUCTION COST SUBTOTAL TURF REPLACEMENT NEW STADIUM $/SF SF 333,735 1 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 333,735 $ 35.67 $ 1,015,000 $ 10.76 $ 25.40 $ 25.67 $ 4.49 $ 14.00 $ 14.54 $ 14.76 $ 4.86 $ 4.32 $ 8.05 $ 4.59 $ 0.49 $ 51.89 $ 28.11 $ 3.41 $ 254.04 0 $ 1 $ 2,130,000 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 11,905,053 1,015,000 3,589,554 8,477,841 8,568,031 1,497,151 4,671,832 4,852,211 4,924,363 1,623,416 1,443,037 2,687,656 1,533,227 162,342 17,316,441 9,379,739 1,136,391 84,783,284 2,130,000 86,913,284 $ 75,000.00 $ 135,000 $ $ $ $ $ $ 150,000 5,670,000 4,283,016 1,915,267 - $ $ 98,931,568 BID-DAY CONSTRUCTION COST WITH FIELDS RELOCATABLES PHASING COSTS GENERAL CONDITIONS CONTINGENCY @ 5% PREMIUM for OFF-HOURS WORK 0% ESCALATION TO CONSTRUCTION 2% AE - CM FEES ABOVE 3. 5 YEARS TOTAL CONSTRUCTION COST 2 42 T OT AL 296.44 Construction duration: 3.5 years Page 91 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX B – LIFE-CYCLE COST ANALYSIS LIFE-CYCLE COST ANALYSIS The life-cycle cost presented herein is: a. Calculated on a present value basis. b. Set forth in accordance with IAC direction for feasibility studies. Factor Annual operating cost per square foot Annual maintenance cost per square foot Total annual O&M cost per square foot Estimated square feet Total annual O&M cost Period [years] Patch & Paint $5.06 $2.47 $7.53 296,191 $2,230,319 Revitalization $4.55 $2.22 $6.78 357,988 $2,426,085 Modernization Replacement A Replacement B $4.30 $4.05 $4.05 $2.10 $1.98 $1.98 $6.40 $6.02 $6.02 360,688 $2,308,584 342,517 $2,063,323 333,735 $2,010,420 40 40 40 40 40 5% 5% 5% 5% 5% Present value of O&M expense stream $38,271,000 $41,630,000 $39,614,000 $35,405,000 $34,497,000 Initial Construction Demolition Temporary Student Housing Project cost [a/e construction estimate] $5,824,086 $0 $0 $5,824,086 $101,098,016 $347,120 $2,400,000 $103,845,136 $116,374,734 $400,000 $2,400,000 $119,174,734 $102,448,361 $1,300,000 $0 $103,748,361 $97,746,804 $1,184,764 $0 $98,931,568 $44,095,086 $249,320,272 $277,963,468 $242,901,722 $232,360,136 Assumed interest rate 40-Year Life Cycle Cost Note that the Life-Cycle Cost for the ‘Patch & Paint’ option does not include future costs for the replacement of aging systems. Page 92 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects APPENDIX C – PROJECT SCHEDULES – PATCH AND PAINT Page 93 of 112 Severna Park High School Severna Park, Maryland APPENDIX C – PROJECT SCHEDULES – REVITALIZATION Page 94 of 112 Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects APPENDIX C – PROJECT SCHEDULES - MODERNIZATION Page 95 of 112 Severna Park High School Severna Park, Maryland APPENDIX C – PROJECT SCHEDULES – REPLACEMENT ‘A’ Page 96 of 112 Feasibility Study GWWO, Inc./Architects Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects APPENDIX C – PROJECT SCHEDULES – REPLACEMENT ‘B’ Page 97 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION PROGRAM SUMMARY REVITALIZATION SPECIFICATION # of square rooms footage 1.00.00 ADMINISTRATION 1.01.00 Main Office 1.01.01 Reception 1.01.02 Principal 1.01.03 Principal's Secretary 1.01.04 Assistant Principal 1.01.05 Assistant Principal Reception Area 1.01.06 Conference Room 1.01.07 Workroom - Administration 1.01.08 Administration Storage 1.01.09 Faculty Lounge 1.01.10 Financial Secretary's Office 1.01.11 Attendance Office 1.01.12 Business Manager's Office 950 200 120 700 200 800 400 350 1,000 120 120 120 1.02.00 Other Spaces 1.02.01 Volunteer Office 1.02.02 In School Suspension 1.02.03 Security Room 1.02.04 Special Program Office (signature) 1.02.05 Special Program Conference Room 1 1 1 2 2 400 400 100 200 400 400 400 100 400 800 1.03.00 Evening/Summer School 1.03.01 Program Office 1.03.02 Program Reception 7 1 120 400 840 400 Page 98 of 112 8,420 5,080 1 1 1 5 1 2 1 1 1 1 1 1 950 200 120 140 200 400 400 350 1,000 120 120 120 950 200 120 700 200 800 400 350 1,000 120 120 120 1 1 1 2 2 400 400 100 200 400 400 400 100 400 800 7 1 120 400 840 400 2,100 2,100 1,240 SUPPORT 2.02.00 Guidance 2.02.01 Counselor's Office 2.02.02 Psychologist Office 2.02.03 Student Records 2.02.04 Guidance Reception 2.02.05 Career Room 2.02.06 Guidance Conference Room 2.02.07 Student Support Office 2.02.08 Registrar 2.02.09 Workroom - Guidance 2.02.10 Testing Coordinator 2.02.11 Testing Material Storage subtotal 8,420 5,080 950 200 120 140 200 400 400 350 1,000 120 120 120 Health Room Waiting Nurse's Office Examination Room Rest Area Student Rest Room Treatment/Medication Health Room Storage # of square rooms footage subtotal 1 1 1 5 1 2 1 1 1 1 1 1 2.00.00 STUDENT 2.01.00 Health 2.01.01 2.01.02 2.01.03 2.01.04 2.01.05 2.01.06 2.01.07 REVITALIZATION 1,240 4,430 890 1 1 1 1 2 1 1 150 100 100 200 75 140 50 150 100 100 200 150 140 50 6 1 1 1 1 1 3 1 1 1 1 120 120 250 450 750 300 120 120 100 120 250 720 120 250 450 750 300 360 120 100 120 250 4,430 890 1 1 1 1 2 1 1 150 100 100 200 75 140 50 150 100 100 200 150 140 50 6 1 1 1 1 1 3 1 1 1 1 120 120 250 450 750 300 120 120 100 120 250 720 120 250 450 750 300 360 120 100 120 250 3,540 3,540 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION SPECIFICATION PROGRAM SUMMARY # of square rooms footage 3.00.00 CORE INSTRUCTIONAL PROGRAMS 3.01.00 Classrooms 3.01.01 Classroom Language Arts Mathematics Social Studies 3.01.02 Teacher Planning (per teacher) 3.02.00 Resource 3.02.01 General Resource 3.02.02 Special Education Resource 3.02.03 Speech 3.02.04 ESOL 3.03.00 Special Education 3.03.01 Special Education Classroom (FLS & Hannah More 3.03.02 3.03.03 3.03.04 3.03.05 Storage - Special Education Teacher Planning - Special Education (per tchr) Special Education Conference Room Special Education Office REVITALIZATION # of square rooms footage subtotal subtotal 51,840 38,450 40 14 14 12 900 36,000 49 50 2,450 1 4 800 500 800 2,000 1 0 300 800 300 0 4 900 3,600 1 12 1 2 400 50 300 120 400 600 300 240 56,463 37,926 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1,061 516 781 778 779 518 1,041 784 780 780 792 1,051 1,307 783 780 780 793 1,140 1,215 786 1,304 1,308 740 739 1,301 780 780 1,393 1,205 1,197 1,197 1,264 976 975 908 957 952 900 901 904 270 260 372 341 325 1,061 516 781 778 779 518 1,041 784 780 780 792 1,051 1,307 783 780 780 793 1,140 1,215 786 1,304 1,308 740 739 1,301 780 780 1,393 1,205 1,197 1,197 1,264 976 975 908 957 952 900 901 904 270 260 372 341 325 1 1 1 1 0 1,123 1,306 1,031 1,149 800 1,123 1,306 1,031 1,149 0 1 1 1 1 1 1 1 1 1,162 1,195 1,122 1,213 400 750 600 325 1,162 1,195 1,122 1,213 400 750 600 325 3,100 1,568 4,609 5,140 6,767 Page 99 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION PROGRAM SUMMARY SPECIFICATION # of square rooms footage 3.04.00 Alternative Education 3.04.01 Classroom 3.04.02 3.04.03 3.04.04 3.04.05 Storage - Alternative Education Decision Making Room Clinical Office Teacher Planning - Alt Education (per teacher) 4.00.00 SPECIALIZED INSTRUCTIONAL PROGRAMS 4.01.00 Art 4.01.01 Art Studio 4.01.02 Storage Room - Art 4.01.03 Kiln/Clay Room 4.01.04 Ceramic Art Studio 4.01.05 Communication Art Studio 4.01.04 Teacher Planning - Art (per teacher) 4.02.02 4.02.03 4.02.04 4.02.05 4.02.06 4.03.00 Music 4.03.01 4.03.02 4.03.03 4.03.04 4.03.05 4.03.06 4.03.07 4.03.08 4.03.09 subtotal 5,150 4 900 3,600 1 2 2 7 200 400 100 50 200 800 200 350 5,593 1 1 1 1 1 2 2 1 1,132 1,313 781 785 252 390 100 350 1,132 1,313 781 785 252 780 200 350 140,765 4,700 1,200 200 300 1,400 1,400 50 1,200 200 300 1,400 1,400 200 1 9,650 9,650 Library Media Workroom Library Media Specialist's Office Storage - Library Media Seminar Room Publication Room 1 1 1 1 1 800 200 600 400 900 800 200 600 400 900 General Music Classroom Storage - General Music Instrumental Music Classroom Practice Module Storage - Instrumental Keyboard Music Classroom Ensemble Classroom Storage - Robe and Uniform Teacher Planning - Music (per teacher) 1 1 1 5 1 1 1 1 4 2,000 500 2,400 200 600 1,200 1,200 350 50 2,000 500 2,400 1,000 600 1,200 1,200 350 200 142,320 5,098 1 1 1 1 1 1 1,047 356 360 1,440 1,438 457 1,047 356 360 1,440 1,438 457 1 1 1 1 1 1 1 5,138 6,765 533 148 813 400 544 5,138 6,765 533 148 813 400 544 1 1 1 5 1 1 1 1 4 2,000 500 2,400 200 600 1,200 1,200 350 50 2,000 500 2,400 1,000 600 1,200 1,200 350 200 12,550 14,341 9,450 4.04.00 Physical Education 4.04.01 Gymnasium 4.04.02 Teacher Planning w/ Shower Room 4.04.03 Storage - Gymnasium 4.04.04 Auxiliary Gymnasium 4.04.05 Physical Education Classroom 4.04.06 Fitness Lab 4.04.07 Locker Rooms 4.04.08 Bin Storage 4.04.09 P.E. Laundry 4.04.10 Exterior Storage 4.04.11 Dance Studio 4.04.12 Costume Area 4.04.13 Concessions 4.04.14 Team Rooms 4.04.15 Training Room 4.04.16 Coaches Office 4.05.17 Athletic Directors' Office 4.05.18 Officials' Locker Room Page 100 of 112 # of square rooms footage subtotal 1 1 1 1 1 4 4.02.00 Library Media Center 4.02.01 Library Reading Room REVITALIZATION 9,450 39,820 1 13,000 13,000 1 860 860 2 1,000 2,000 1 5,000 5,000 2 900 1,800 1 4,800 4,800 2 1,600 3,200 1 900 900 1 150 150 1 350 350 1 2,000 2,000 1 350 350 1 150 150 1 3,680 3,680 1 200 200 1 740 740 1 200 200 2 220 440 39,820 1 13,000 13,000 1 860 860 2 1,000 2,000 1 5,000 5,000 2 900 1,800 1 4,800 4,800 2 1,600 3,200 1 900 900 1 150 150 1 350 350 1 2,000 2,000 1 350 350 1 150 150 1 3,680 3,680 1 200 200 1 740 740 1 200 200 2 220 440 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION PROGRAM SUMMARY SPECIFICATION # of square rooms footage 4.05.00 Science 4.05.01 Biology Laboratory/Classroom 7,425 4.05.02 Chemistry Laboratory/Classroom 4.05.03 Earth/Space Laboratory/Classroom 3 2 1,485 1,485 4,455 2,970 4.05.04 Physics Laboratory/Classroom 2 1,485 2,970 1 1 2 2 14 800 200 100 250 50 800 200 200 500 700 4.06.00 Computer Science 4.06.01 Computer Science Laboratory 4.06.02 Computer Science Office 3 2 1,000 75 3,000 150 4.07.00 World & Classical Language 4.07.01 World & Classical Language Lab/Classroom 8 1,000 8,000 1 10 125 50 125 500 1 2 1,625 1,515 1,625 3,030 1 1 1 1 1 1 4 500 500 1,040 800 75 75 50 500 500 1,040 800 75 75 200 4.09.00 Technology Education 4.09.01 Technology Laboratory/Workshop 4.09.02 Fabrication Room 4.09.03 Design Computer Laboratory 4.09.04 Classroom - Technology Education 4.09.05 Storage - Technology 4.09.06 Teacher Planning - Technology (per teacher) 5 1 1 0 1 6 1,450 600 1,200 900 250 50 7,250 600 1,200 0 250 300 4.10.00 Business Education 4.10.01 Business Classroom 4.10.02 Business Computer Laboratory 1 2 900 1,000 900 2,000 1 1 3 500 500 50 500 500 150 4.07.02 Storage - World & Classical Language 4.07.03 Teacher Planning - World & Classical Language 4.08.00 Family and Consumer Science 4.08.01 Multipurpose Laboratory 4.08.02 Food/Nutrition Laboratory 4.08.03 4.08.04 4.08.05 4.08.06 4.08.07 4.08.08 4.08.09 Storage - Family and Consumer Science Food Preparation Area Child Development Laboratory Child Development Classroom Storage - Child Development Exterior Storage - Child Development Teacher Planning - FACS (per teacher) 4.10.03 School Store 4.10.04 Storage - Business 4.10.05 Teacher Planning - Business (per teacher) subtotal 20,220 1,485 Student Project Area Chemical Storage General Science Storage Prep Room Teacher Planning (per teacher) # of square rooms footage subtotal 5 4.05.05 4.05.06 4.05.07 4.05.08 4.05.09 REVITALIZATION 19,438 4 1 3 1 1 1 1 1 1 1 2 1 1,485 1,280 1,485 1,044 1,196 1,276 1,303 800 200 250 390 914 5,940 1,280 4,455 1,044 1,196 1,276 1,303 800 200 250 780 914 3 2 1,000 75 3,000 150 1 1 1 1 1 1 1 1 1 1 795 781 781 781 780 780 780 799 291 374 795 781 781 781 780 780 780 799 291 374 1 1 1 1 1 1 1 1 1 1 1,578 1,416 1,400 650 650 1,069 1,142 75 75 200 1,578 1,416 1,400 650 650 1,069 1,142 75 75 200 5 1 1 0 1 6 1,450 600 1,200 900 250 50 7,250 600 1,200 0 250 300 1 1 1 1 1 1 1,414 1,263 1,594 500 500 200 1,414 1,263 1,594 500 500 200 3,150 3,150 8,625 6,942 7,845 8,255 9,600 9,600 4,050 5,471 Page 101 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY – REVITALIZATION PROGRAM SUMMARY SPECIFICATION # of square rooms footage 4.11.00 Theatre 4.11.01 Auditorium 4.11.02 Stage 4.11.03 Stage Wings 4.11.04 Dressing Room 4.11.05 Set Room 4.11.06 Set Storage 4.11.07 Prop Storage 4.11.08 Projection/Sound Booth 4.11.09 Blackbox Theatre 4.11.10 Video Production 4.11.11 Control Room 4.11.12 Auditorium Office 5.00.00 BUILDING OPERATIONS 5.01.00 Custodial 5.01.01 Custodial Closet 5.01.02 Building Engineer's Office 5.01.03 Can Wash 5.01.04 Book Storage 5.01.05 General Storage 5.01.06 Exterior Storage 5.01.07 Engineer's Shop 5.01.08 Equipment Storage 5.01.09 Custodial Locker Room 5.01.10 Receiving 5.02.00 Food Services 5.02.01 Cafeteria (per src) 5.02.02 Kitchen 5.02.03 Kitchen Managers Office 5.02.04 Food Staff Locker Room 5.02.05 Chair storage 5.02.06 Food Service Laundry Room 5.03.00 Rest Rooms 5.03.01 Public (Adult) Rest Room 5.03.02 Staff Rest Room 5.03.03 Student Rest Room 5.04.00 Mechanical/Electrical 5.04.01 Mechanical Room 5.04.02 Electrical Room 5.04.03 Electrical Closet Page 102 of 112 REVITALIZATION # of square rooms footage subtotal subtotal 20,755 996 1 1 2 1 1 1 2 1 1 1 1 12 11,955 1,800 1,800 1,800 1,800 350 700 500 500 300 300 300 300 200 400 1,800 1,800 900 900 200 200 100 100 20,755 996 1 1 2 1 1 1 2 1 1 1 1 12 11,955 1,800 1,800 1,800 1,800 350 700 500 500 300 300 300 300 200 400 1,800 1,800 900 900 200 200 100 100 33,625 5,470 9 1 1 4 1 1 1 1 1 1 30 100 50 500 1,000 400 200 400 250 800 270 100 50 2,000 1,000 400 200 400 250 800 45,522 5,470 9 1 1 4 1 1 1 1 1 1 30 100 50 500 1,000 400 200 400 250 800 270 100 50 2,000 1,000 400 200 400 250 800 17,095 664 1 1 1 1 1 18 11,955 4,400 4,400 200 200 100 100 400 400 40 40 17,095 664 1 1 1 1 1 18 11,955 4,400 4,400 200 200 100 100 400 400 40 40 3,800 4 14 10 150 50 250 600 700 2,500 1 1 6 2,000 500 35 2,000 500 210 3,800 4 14 10 150 50 250 600 700 2,500 2,710 14,607 1 13,897 13,897 1 500 500 6 35 210 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY – REVITALIZATION PROGRAM SUMMARY SPECIFICATION # of square rooms footage 5.05.00 Telecommunication 5.05.01 Telecommunication Room 5.05.02 Telecommunication Closet 5.06.00 Circulation (sf part of efficiency adjustment unless noted) 5.06.01 Entrance Vestibule 5.06.02 Classroom Corridors 5.06.03 Public Corridors 5.06.04 After-hour Lobby 5.06.05 Gymnasium Lobby GROSS SQUARE FOOTAGE (with Other Areas) subtotal 2,050 1 6 250 300 250 1,800 2,050 1 6 250 300 250 1,800 2,500 1 1 1,000 1,500 1,000 1,500 GROSS SQUARE FOOTAGE Subtotal all programs (including Other Areas) Efficiency adjustment (new facility) # of square rooms footage subtotal Subtotal all programs Efficiency adjustment (new facility) 6.00.00 OTHER AREAS 6.01.00 Ancillary Structure 6.01.01 Concession Building with Rest Rooms 6.01.02 Field House 6.01.03 Maintenance Building REVITALIZATION 0 1 1 2000 5000 1500 2,500 1 1 1,000 1,500 1,000 1,500 239,080 89,655 328,735 257,155 100,833 357,988 6,500 6,500 0 5000 1500 0 1 1 245,580 92,093 337,673 2000 5000 1500 0 5000 1500 263,655 101,367 365,022 Page 103 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION PROGRAM SUMMARY MODERNIZATION SPECIFICATION # of square rooms footage 1.00.00 ADMINISTRATION 1.01.00 Main Office 1.01.01 Reception 1.01.02 Principal 1.01.03 Principal's Secretary 1.01.04 Assistant Principal 1.01.05 Assistant Principal Reception Area 1.01.06 Conference Room 1.01.07 Workroom - Administration 1.01.08 Administration Storage 1.01.09 Faculty Lounge 1.01.10 Financial Secretary's Office 1.01.11 Attendance Office 1.01.12 Business Manager's Office 950 200 120 700 200 800 400 350 1,000 120 120 120 1.02.00 Other Spaces 1.02.01 Volunteer Office 1.02.02 In School Suspension 1.02.03 Security Room 1.02.04 Special Program Office (signature) 1.02.05 Special Program Conference Room 1 1 1 2 2 400 400 100 200 400 400 400 100 400 800 1.03.00 Evening/Summer School 1.03.01 Program Office 1.03.02 Program Reception 7 1 120 400 840 400 Page 104 of 112 8,420 5,080 1 1 1 5 1 2 1 1 1 1 1 1 950 200 120 140 200 400 400 350 1,000 120 120 120 950 200 120 700 200 800 400 350 1,000 120 120 120 1 1 1 2 2 400 400 100 200 400 400 400 100 400 800 7 1 120 400 840 400 2,100 2,100 1,240 SUPPORT 2.02.00 Guidance 2.02.01 Counselor's Office 2.02.02 Psychologist Office 2.02.03 Student Records 2.02.04 Guidance Reception 2.02.05 Career Room 2.02.06 Guidance Conference Room 2.02.07 Student Support Office 2.02.08 Registrar 2.02.09 Workroom - Guidance 2.02.10 Testing Coordinator 2.02.11 Testing Material Storage subtotal 8,420 5,080 950 200 120 140 200 400 400 350 1,000 120 120 120 Health Room Waiting Nurse's Office Examination Room Rest Area Student Rest Room Treatment/Medication Health Room Storage # of square rooms footage subtotal 1 1 1 5 1 2 1 1 1 1 1 1 2.00.00 STUDENT 2.01.00 Health 2.01.01 2.01.02 2.01.03 2.01.04 2.01.05 2.01.06 2.01.07 MODERNIZATION 1,240 4,430 890 1 1 1 1 2 1 1 150 100 100 200 75 140 50 150 100 100 200 150 140 50 6 1 1 1 1 1 3 1 1 1 1 120 120 250 450 750 300 120 120 100 120 250 720 120 250 450 750 300 360 120 100 120 250 4,430 890 1 1 1 1 2 1 1 150 100 100 200 75 140 50 150 100 100 200 150 140 50 6 1 1 1 1 1 3 1 1 1 1 120 120 250 450 750 300 120 120 100 120 250 720 120 250 450 750 300 360 120 100 120 250 3,540 3,540 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION SPECIFICATION PROGRAM SUMMARY # of square rooms footage 3.00.00 CORE INSTRUCTIONAL PROGRAMS 3.01.00 Classrooms 3.01.01 Classroom Language Arts Mathematics Social Studies 3.01.02 Teacher Planning (per teacher) 40 14 14 12 49 3.02.00 Resource 3.02.01 General Resource 3.02.02 Special Education Resource 3.02.03 Speech 3.02.04 ESOL 3.03.00 Special Education 3.03.01 Special Education Classroom (FLS & Hannah More 3.03.02 Storage - Special Education 3.03.03 Teacher Planning - Special Education (per tchr) 3.03.04 Special Education Conference Room 3.03.05 Special Education Office 3.04.00 Alternative Education 3.04.01 Classroom 3.04.02 Storage - Alternative Education 3.04.03 Decision Making Room 3.04.04 Clinical Office 3.04.05 Teacher Planning - Alt Education (per teacher) 4.00.00 SPECIALIZED INSTRUCTIONAL PROGRAMS 4.01.00 Art 4.01.01 Art Studio 4.01.02 Storage Room - Art 4.01.03 Kiln/Clay Room 4.01.04 Ceramic Art Studio 4.01.05 Communication Art Studio 4.01.04 Teacher Planning - Art (per teacher) 4.02.02 4.02.03 4.02.04 4.02.05 4.02.06 4.03.00 Music 4.03.01 4.03.02 4.03.03 4.03.04 4.03.05 4.03.06 4.03.07 4.03.08 4.03.09 subtotal subtotal 51,840 38,450 900 36,000 50 2,450 1 4 1 0 800 500 300 800 800 2,000 300 0 4 1 12 1 2 900 400 50 300 120 3,600 400 600 300 240 4 1 2 2 7 900 200 400 100 50 3,600 200 800 200 350 52,530 36,400 40 910 36,400 49 50 2,450 1 4 1 0 800 500 300 800 800 2,000 300 0 4 1 12 1 2 925 450 50 400 120 3,700 450 600 400 240 4 1 2 2 7 910 200 400 100 50 3,640 200 800 200 350 2,450 3,100 3,100 5,140 5,390 5,150 5,190 140,765 4,700 1 1 1 1 1 4 1,200 200 300 1,400 1,400 50 1,200 200 300 1,400 1,400 200 1 9,650 9,650 Library Media Workroom Library Media Specialist's Office Storage - Library Media Seminar Room Publication Room 1 1 1 1 1 800 200 600 400 900 800 200 600 400 900 General Music Classroom Storage - General Music Instrumental Music Classroom Practice Module Storage - Instrumental Keyboard Music Classroom Ensemble Classroom Storage - Robe and Uniform Teacher Planning - Music (per teacher) 1 1 1 5 1 1 1 1 4 2,000 500 2,400 200 600 1,200 1,200 350 50 2,000 500 2,400 1,000 600 1,200 1,200 350 200 4.02.00 Library Media Center 4.02.01 Library Reading Room MODERNIZATION # of square rooms footage 143,338 4,750 1 1 1 1 1 4 1,200 250 300 1,400 1,400 50 1,200 250 300 1,400 1,400 200 1 1 1 1 1 1 1 5,138 6,765 800 200 600 400 900 5,138 6,765 800 200 600 400 900 1 1 1 5 1 1 1 1 4 2,000 500 2,400 200 600 1,200 1,200 350 50 2,000 500 2,400 1,000 600 1,200 1,200 350 200 12,550 14,803 9,450 9,450 Page 105 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION PROGRAM SUMMARY SPECIFICATION # of square rooms footage 4.04.00 Physical Education 4.04.01 Gymnasium 4.04.02 Teacher Planning w/ Shower Room 4.04.03 Storage - Gymnasium 4.04.04 Auxiliary Gymnasium 4.04.05 Physical Education Classroom 4.04.06 Fitness Lab 4.04.07 Locker Rooms 4.04.08 Bin Storage 4.04.09 P.E. Laundry 4.04.10 Exterior Storage 4.04.11 Dance Studio 4.04.12 Costume Area 4.04.13 Concessions 4.04.14 Team Rooms 4.04.15 Training Room 4.04.16 Coaches Office 4.05.17 Athletic Directors' Office 4.05.18 Officials' Locker Room 4.05.00 Science 4.05.01 Biology Laboratory/Classroom 4.05.02 Chemistry Laboratory/Classroom 4.05.03 Earth/Space Laboratory/Classroom 4.05.04 Physics Laboratory/Classroom 4.05.05 Student Project Area 4.05.06 Chemical Storage 4.05.07 General Science Storage 4.05.08 Prep Room 4.05.09 Teacher Planning (per teacher) 1 13,000 13,000 1 860 860 2 1,000 2,000 1 5,000 5,000 2 900 1,800 1 4,800 4,800 2 1,600 3,200 1 900 900 1 150 150 1 350 350 1 2,000 2,000 1 350 350 1 150 150 1 3,680 3,680 1 200 200 1 740 740 1 200 200 2 220 440 3 2 1,000 75 3,000 150 8 1 10 1,000 125 50 8,000 125 500 4.08.00 Family and Consumer Science 4.08.01 Multipurpose Laboratory 4.08.02 Food/Nutrition Laboratory 4.08.03 Storage - Family and Consumer Science 4.08.04 Food Preparation Area 4.08.05 Child Development Laboratory 4.08.06 Child Development Classroom 4.08.07 Storage - Child Development 4.08.08 Exterior Storage - Child Development 4.08.09 Teacher Planning - FACS (per teacher) 1 2 1 1 1 1 1 1 4 1,625 1,515 500 500 1,040 800 75 75 50 1,625 3,030 500 500 1,040 800 75 75 200 4.09.00 Technology Education 4.09.01 Technology Laboratory/Workshop 4.09.02 Fabrication Room 4.09.03 Design Computer Laboratory 4.09.04 Classroom - Technology Education 4.09.05 Storage - Technology 5 1 1 0 1 1,450 600 1,200 900 250 6 50 Page 106 of 112 39,820 1 13,000 13,000 1 860 860 2 1,000 2,000 1 5,000 5,000 2 900 1,800 1 4,800 4,800 2 1,600 3,200 1 900 900 1 150 150 1 350 350 1 2,000 2,000 1 350 350 1 150 150 1 3,680 3,680 1 200 200 1 740 740 1 200 200 2 220 440 20,220 7,425 4,455 2,970 2,970 800 200 200 500 700 4.09.06 Teacher Planning - Technology (per teacher) subtotal 39,820 1,485 1,485 1,485 1,485 800 200 100 250 50 4.07.00 World & Classical Language 4.07.01 World & Classical Language Lab/Classroom 4.07.02 Storage - World & Classical Language 4.07.03 Teacher Planning - World & Classical Language # of square rooms footage subtotal 5 3 2 2 1 1 2 2 14 4.06.00 Computer Science 4.06.01 Computer Science Laboratory 4.06.02 Computer Science Office MODERNIZATION 20,300 5 3 2 2 1 1 1 2 14 1,500 1,500 1,500 1,500 800 200 100 250 50 7,500 4,500 3,000 3,000 800 200 100 500 700 3 2 1,000 75 3,000 150 8 1 10 1,000 125 50 8,000 125 500 1 2 1 1 1 1 1 1 4 1,625 1,550 500 510 1,050 900 75 75 50 1,625 3,100 500 510 1,050 900 75 75 200 7,250 600 1,200 0 250 5 1 1 0 1 1,450 600 1,200 900 250 7,250 600 1,200 0 250 300 6 50 300 3,150 3,150 8,625 8,625 7,845 8,035 9,600 9,600 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION PROGRAM SUMMARY SPECIFICATION # of square rooms footage 4.10.00 Business Education 4.10.01 Business Classroom 4.10.02 Business Computer Laboratory 4.10.03 School Store 4.10.04 Storage - Business 4.10.05 Teacher Planning - Business (per teacher) 4.11.00 Theatre 4.11.01 Auditorium 4.11.02 Stage 4.11.03 Stage Wings 4.11.04 Dressing Room 4.11.05 Set Room 4.11.06 Set Storage 4.11.07 Prop Storage 4.11.08 Projection/Sound Booth 4.11.09 Blackbox Theatre 4.11.10 Video Production 4.11.11 Control Room 4.11.12 Auditorium Office 5.00.00 BUILDING OPERATIONS 5.01.00 Custodial 5.01.01 Custodial Closet 5.01.02 Building Engineer's Office 5.01.03 Can Wash 5.01.04 Book Storage 5.01.05 General Storage 5.01.06 Exterior Storage 5.01.07 Engineer's Shop 5.01.08 Equipment Storage 5.01.09 Custodial Locker Room 5.01.10 Receiving 5.02.00 Food Services 5.02.01 Cafeteria (per src) 5.02.02 Kitchen 5.02.03 Kitchen Managers Office 5.02.04 Food Staff Locker Room 5.02.05 Chair storage 5.02.06 Food Service Laundry Room 5.03.00 Rest Rooms 5.03.01 Public (Adult) Rest Room 5.03.02 Staff Rest Room 5.03.03 Student Rest Room MODERNIZATION # of square rooms footage subtotal subtotal 4,050 1 2 1 1 3 900 1,000 500 500 50 900 2,000 500 500 150 4,050 1 2 1 1 3 900 1,000 500 500 50 900 2,000 500 500 150 20,755 996 1 1 2 1 1 1 2 1 1 1 1 12 11,955 1,800 1,800 1,800 1,800 350 700 500 500 300 300 300 300 200 400 1,800 1,800 900 900 200 200 100 100 20,755 996 1 1 2 1 1 1 2 1 1 1 1 12 11,955 1,800 1,800 1,800 1,800 350 700 500 500 300 300 300 300 200 400 1,800 1,800 900 900 200 200 100 100 33,625 5,470 9 1 1 4 1 1 1 1 1 1 30 100 50 500 1,000 400 200 400 250 800 270 100 50 2,000 1,000 400 200 400 250 800 45,522 5,470 9 1 1 4 1 1 1 1 1 1 30 100 50 500 1,000 400 200 400 250 800 270 100 50 2,000 1,000 400 200 400 250 800 17,095 664 1 1 1 1 1 18 11,955 4,400 4,400 200 200 100 100 400 400 40 40 17,095 664 1 1 1 1 1 18 11,955 4,400 4,400 200 200 100 100 400 400 40 40 3,800 4 14 10 150 50 250 600 700 2,500 5.04.00 Mechanical/Electrical 5.04.01 Mechanical Room 5.04.02 Electrical Room 5.04.03 Electrical Closet 1 1 6 2,000 500 35 2,000 500 210 5.05.00 Telecommunication 5.05.01 Telecommunication Room 5.05.02 Telecommunication Closet 1 6 250 300 250 1,800 3,800 4 14 10 150 50 250 600 700 2,500 2,710 14,607 1 13,897 13,897 1 500 500 6 35 210 2,050 2,050 1 6 250 300 250 1,800 Page 107 of 112 Severna Park High School Feasibility Study GWWO, Inc./Architects Severna Park, Maryland APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION PROGRAM SUMMARY SPECIFICATION # of square rooms footage 5.06.00 Circulation (sf part of efficiency adjustment unless noted) 5.06.01 Entrance Vestibule 5.06.02 Classroom Corridors 5.06.03 Public Corridors 5.06.04 After-hour Lobby 5.06.05 Gymnasium Lobby MODERNIZATION # of square rooms footage subtotal subtotal 2,500 1 1 1,000 1,500 1,000 1,500 2,500 1 1 1,000 1,500 1,000 1,500 Subtotal all programs 239,080 254,240 Efficiency adjustment (new facility) 89,655 328,735 106,448 360,688 6,500 6,500 GROSS SQUARE FOOTAGE 6.00.00 OTHER AREAS 6.01.00 Ancillary Structure 6.01.01 Concession Building with Rest Rooms 6.01.02 Field House 6.01.03 Maintenance Building Subtotal all programs (including Other Areas) Efficiency adjustment (new facility) GROSS SQUARE FOOTAGE (with Other Areas) Page 108 of 112 0 1 1 2000 5000 1500 0 5000 1500 0 1 1 245,580 92,093 337,673 2000 5000 1500 0 5000 1500 260,740 107,113 367,853 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects APPENDIX E – SUSTAINABLE DESIGN Replacement options will be registered with the US Green Building Council as a LEED® project and will pursue LEED® Silver certification (within the range of 50-59 total points). The design will showcase the incorporation of sustainable techniques and materials. The following outlined categories follow the divisions of the LEED® for Schools rating system and possible points to achieve. 1. Sustainable Sites Integrating building location and sustainable site features will minimize the environmental impact of buildings on the site. Potential Strategies include: a. Minimize site disruption, soil erosion, and air pollution associated with construction activities. b. Appropriate landscaping for energy conservation. c. Planting native trees species. d. Eliminate the use of pesticides in order to promote protection of regional watersheds e. Examining alternative energy systems such as photovoltaic panels for potential use as pedestrian walkway shading and weather protection devices in addition to or instead of roof mounted. f. No “light pollution” since exterior lighting is installed at a minimum (for safety requirements) to allow for view of night sky. g. High albedo roofing to reduce heat island effect. h. Low-emitting and fuel efficient vehicle parking spots. 2. Water Efficiency Water harvesting and water conservation are to be implemented. include: Potential Strategies a. Reduce the need for municipally supplied water and carbon cost of treating that water. b. Maximize water conservation – students, staff, and community can learn about these features – educational tool. i. Eliminate the use of potable water for irrigation. ii. Low flush toilet fixtures iii. Low flow aerators for sink faucets iv. Low flow shower heads v. Recycled water for mechanical system recharge vi. Recycle mechanical system condensate. c. Manage and conserve storm water and reduce storm water runoff i. Harvesting rainwater for many uses including irrigation. ii. Designing pervious parking lots and paved surfaces to capture storm water below paved areas instead of as runoff iii. Using retention and detention ponds as educational tools Page 109 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects 3. Energy and Atmosphere Reduce energy consumption of buildings. Potential Strategies include: a. Computer energy modeling used to inform the design of the building. Annual energy savings and yearly operating cost reduction goal should be a minimum of 30% over the American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE) Standard 90.1 b. The building should be zoned and controlled in a way specific to occupancy and use profiles. These systems will recognize the mass and building characteristics of the building as well as control logic designed to maximize the return on investment. c. All building system components selected will be free of chlorofluorocarbons (CFCs) and hydro chlorofluorocarbons (HCFCs). d. Daylighting should be present in all classrooms and spaces that are regularly occupied by students along with intelligent controls of electric lighting that recognize the amount of useful daylight present in each space. e. Natural ventilation should be used where possible. f. Mechanical ventilation should be decoupled from space conditioning to ensure fresh air and energy recovery independent of space conditioning requirements. g. The project should incorporate full enhanced building system commissioning to insure that the design intent will be met. 4. Materials and Resources Sustainable material choices will reduce use of virgin materials within the building. Potential Strategies: a. Storage and collection of recyclable materials within the school. b. Divert a minimum of 75% of the materials during demolition and construction from the landfills through recycling or salvaging. c. Using new construction materials that have a significant percentage of recycled content. d. Using materials that are harvested, extracted, and manufactured within a 500 mile radius of the project site e. All wood products used on the project are Forest Stewardship Council (FSC) certified products. 5. Indoor Environmental Quality (IEQ) Reducing levels of contaminants, increasing filtered outside air and ventilation, and monitoring humidity all contribute to a more desirable indoor air quality. Potential strategies include: a. Smoke free school zone. b. Classroom spaces will meet a certain STC rating for acoustics - increased insulation, seals and special acoustic ceiling tiles for better communication between teachers and students. c. Low emitting materials including adhesives & sealants, paints & coatings, flooring systems, agrifiber products, furniture, and ceiling & wall systems. Page 110 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects d. Appropriate ventilation and elimination of chemicals and pollutants such as copy machines and tracked-in dirt from the exterior. e. Use outdoor spaces as instructional areas giving students the opportunity for fresh air during the day. f. Carbon dioxide (CO2) monitors that inform the building controls to insure adequate amounts of ventilation where and when needed. g. Designing electric lights to take advantage of natural light in spaces. h. A mold free environment. i. The building additions and renovations or new construction implementing the use of daylight and views throughout. j. Individual temperature regulation of rooms to provide adequate comfort for all occupants. 6. Innovation in Design Incorporating innovative techniques that are unique to SPHS and setting a precedent for other LEED school projects in the future. One potential example of an innovation credit for this project would be: a. Green housekeeping plan for the school – use of non-toxic cleaning and maintenance products and environmentally friendly practices. 7. Regional Priority Severna Park and surrounding Anne Arundel County areas potentially have materials or regional differences that could result in achieving specific Regional Priority credits. More research will be done to determine what sets the area apart and where we could achieve these additional credits. 8. The school as a teaching tool The school building can be used and incorporated as part of the school day curriculum. Students will take part in recognizing how the building works and why the various sustainable features of the building are important for understanding the larger built environment. Page 111 of 112 Severna Park High School Severna Park, Maryland Feasibility Study GWWO, Inc./Architects APPENDIX F – BUILDING SECURITY AND SITE Security will be based on Crime Prevention through Environmental Design (CPTED). These strategies include: Natural Surveillance – A design concept directed primarily at keeping intruders easily observable. Promoted by features that maximize visibility of people, parking areas and building entrances: doors and windows that look out on to streets and parking areas; pedestrian-friendly sidewalks and streets; adequate nighttime lighting. Territorial Reinforcement – Physical design can create or extend a sphere or extend a sphere of influence. Users then develop a sense of territorial control while potential offenders, perceiving this control, are discouraged. Promoted by features that define property lines and distinguish private spaces from public spaces using landscape plantings, pavement designs, gateway treatments, and “CPTED” fences. Natural Access Control – A design concept directed primarily at decreasing crime opportunity by denying access to crime targets and creating in offenders a perception of risk. Gained by designing streets, sidewalks, building entrances and neighborhood gateways to clearly indicate public routes and discouraging access to private areas with structural elements. Target Hardening – Accomplished by features that prohibit entry or access: window locks, dead bolts for doors, interior door hinges. Page 112 of 112