Severna Park High School

Transcription

Severna Park High School
ANNE ARUNDEL COUNTY
PUBLIC SCHOOLS
Severna Park High School
Feasibility Study
January 21, 2011
GWWO, Inc./Architects
800 Wyman Park Drive, Suite 300
Baltimore, MD 21211
410.332.1009
KCI Technologies
Site Engineering Weigand Associates, Inc. M/P/E Engineering Faisant Associates, Inc. Structural Engineering Oak Contracting, LLC Cost Estimating Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
Table of Contents
Study Team ............................................................................................................................ 1
Executive Summary ................................................................................................................. 3
Introduction ............................................................................................................................ 6
Purpose .................................................................................................................................. 8
History .................................................................................................................................... 9
Existing Conditions ................................................................................................................. 10
Code Analysis ......................................................................................................................... 45
Option A – Do Nothing ............................................................................................................. 47
Option B – Patch and Paint....................................................................................................... 48
Option C – Revitalization ......................................................................................................... 50
Option D – Modernization ........................................................................................................ 60
Option E – Replacement ‘A’ ...................................................................................................... 70
Option F – Replacement ‘B’ ..................................................................................................... 78
Appendix A – Detailed Cost Estimates ...................................................................................... 85
Appendix B – Life Cycle Cost Comparison ................................................................................. 92
Appendix C – Project Schedules ............................................................................................... 93
Appendix D – Function and Area Summaries ............................................................................. 98
Appendix E – Sustainable Design ........................................................................................... 109
Appendix F – Building Security and Site .................................................................................. 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
STUDY TEAM
Severna Park High School Representatives
Patrick Bathras
Principal
Kurt Maisel
Assistant Principal
Pat Lynard
Business Manager
Wayne Mook
Athletic Director
Amy Lippincott
Art Department Chair
Marianne Fitzgerald
Media Specialist
Timothy Dunbar
Social Studies Chair
Brad Hill
Technology Education Chair
Andrea Willey
Signature Program Facilitator
Vicki Wuest
Counselor
Taylor Davenport
Student
Colin Heil
Student
Maryland State Department of Education
Gloria Mikolajczyk
School Facilities Architect Supervisor
Community Representatives
Leette Reynolds
Gwen Douma Harring
Terra Snider
Maureen Carr-York
PTSO
CAC
CAC
Greater Severna Park Council
AACPS
Lisa Seaman Crawford
Catherine Herbert
Larry Alberts
Greg Stewart
Mary Patz
Acting Director of Facilities
Regional Assistant Superintendent
Manager of Planning
Senior Manager of Design
Design Architect
Architects and Engineers
Alan Reed
John Easterling
Brian Eschman
Sarah Gratz
Michael Lambert
Michael Weigand
Atul Patel
GWWO, Inc./Architects
GWWO, Inc./Architects
GWWO, Inc./Architects
GWWO, Inc./Architects
KCI, Inc. (Civil)
Weigand Associates, Inc. (MEP)
Faisant Associates, Inc. (Structural)
Construction Manager
Joe Tiberi
Steve Krell
Oak Contracting, LLC (Cost Estimating)
Oak Contracting, LLC (Cost Estimating)
Page 1 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
This page intentionally left blank.
Page 2 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
EXECUTIVE SUMMARY
Constructed in 1957, with a major addition in 1971, Severna Park High School in Severna Park,
Maryland is well maintained and structurally sound. However, it does not provide an optimum
teaching and learning environment for the students of Anne Arundel County. As it exists, the facility
does not meet the current Educational Specifications requirements for a standard Maryland high
school in several categories of program and area. Overall, the physical learning environment at
Severna Park High School is deficient due to a lack of space, inflexibility of the existing spaces, a
dearth of natural light in classrooms, aging building systems, and a sprawling layout. Site safety and
vehicular circulation are difficult to manage as buses line up in the same lanes as parents and wind
through the staff parking lot.
This study was commissioned to assist the Board of Education in assessing its options to improve
Severna Park High School’s facility to meet the approved Educational Specifications. Following
AACPS’s established protocol for feasibility studies, five options were evaluated. Due to the
significance of considering relocating the existing stadium to fully assess Option E - Complete
Replacement On-Site, an alternative on-site replacement scheme was evaluated and is presented in
this study as Option F.
Conclusions:
1. Option A – Do Nothing
In this no cost option, no work would occur on site, or in the building. This option establishes a
base line for comparison to other schemes.
2. Option B – Patch and Paint
This minimum approach will repair some deferred maintenance items and provide a fresh coat of
paint throughout the existing facility. Building and life safety concerns will not be addressed.
Building systems will not be updated or replaced. No site improvements will be made to improve
circulation and safety. Students will remain in the facility during the maintenance work.
3. Option C – Revitalization
Building and life safety issues will be corrected in the existing building. Additions will be
constructed to provide new spaces for a gymnasium, physical education department, auditorium,
theatre, music, some classrooms, and food service areas. Portions of the existing building are
required to be demolished to accommodate the additions. New windows, doors, casework, and
finishes will be provided in the remaining areas of the existing building though no significant
structural changes will be made. Thus, deficiencies will remain with regard to the area
requirements of the Educational Specifications. Site improvements will include a separate lot for
bus stacking. Relocatable classrooms will be required as students will remain in the facility
during construction.
4. Option D – Modernization
This option completely renovates the existing building so that with additions, the facility will
comply with all requirements of the Educational Specifications and current codes. The building
efficiency is equivalent to Revitalization as the general floor plan is the same and remains
expansive. Site circulation and safety are improved with the creation of a separate bus stacking
Page 3 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
lot. Relocatable classrooms will be required as students will remain in the facility for the duration
of construction.
5. Option E – Complete Replacement On-Site ‘A’
A new facility designed in accordance with the Educational Specifications will comply with
current building, life safety, and accessibility codes and standards. Designed to achieve the
United States Green Building Council’s (USGBC) Leadership in Energy and Environmental Design
(LEED™) Silver certification, the new building will provide a safe, healthy, and inspiring learning
environment. To accommodate the existing stadium, the building will be constructed in phases
and located on existing play fields. Students will remain in the existing building during
construction of the new building, but will also have to occupy the first phase of the new building
while the second phase is under construction. Site safety and circulation will be improved.
6. Option F – Complete Replacement On-Site ‘B’
Similar to Option E, this new building will comply with the Educational Specifications, current
codes, and be designed to achieve USGBC LEED™ Silver certification. Relocation of the stadium
in this option allows for the design of the most compact floor plan which optimizes building
efficiency, requires the shortest construction timeframe, minimizes disruptions to school
operations, and allows for optimal solar orientation to maximize daylighting in classrooms. Play
fields and courts are grouped together efficiently. Site safety and circulation will be improved
with full separation of vehicular circulation patterns.
Following, on page five, is a comparison of overall building area, estimated construction cost, and
40-year life cycle operational cost between the options. Refer to Appendices A and B for detailed
analyses of the construction costs and life cycle costs presented.
Page 4 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
PATCH AND PAINT
Construction duration will be 1 year.
Area of Existing Building
Total Estimated Const. Cost*
40-year Life Cycle Cost*
296,191 GSF
$5,824,086
$44,095,086
*Costs for replacement of systems are not included.
REVITALIZATION
Total construction duration will be 4.5 years.
Area of Existing Building
Area of Demolition
Area of Revitalization
Area of New Construction
Total Area
Total Estimate Const. Cost
40-year Life Cycle Cost
MODERNIZATION
Total Estimate Const. Cost
40-year Life Cycle Cost
296,191 GSF
86,780 GSF
209,411 GSF
151,277 GSF
360,688 GSF
$119,174,734
$277,963,468
Total construction duration will be 4 years.
Building construction duration will be 2.75 years.
Area of Existing Building
Area of Demolition
Area of Revitalization
Area of New Construction
Total Area
Total Estimate Const. Cost
40-year Life Cycle Cost
REPLACEMENT B
$103,845,136
$249,320,272
Total construction duration will be 5.5 years.
Area of Existing Building
Area of Demolition
Area of Modernization
Area of New Construction
Total Area
REPLACEMENT A
296,191 GSF
86,780 GSF
209,411 GSF
148,577 GSF
357,988 GSF
296,191 GSF
296,191 GSF
0 GSF
342,517 GSF
342,517 GSF
$103,748,361
$242,901,722
Total construction duration will be 3.5 years.
Building construction duration will be 2.25 years.
Area of Existing Building
Area of Demolition
Area of Revitalization
Area of New Construction
Total Area
Total Estimate Const. Cost
40-year Life Cycle Cost
296,191 GSF
296,191 GSF
0 GSF
333,735 GSF
333,735 GSF
$98,931,568
$232,360,136
Page 5 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
INTRODUCTION
This feasibility study was conducted for Anne Arundel County Public Schools. The Study Committee,
included educators, planners, parents, community members, architects and engineers as well as a
participant from Maryland State Department of Education.
The existing State Rated Capacity of the facility is 1,805 and the current Full Time Enrollment is
1,923. Projected Full Time Enrollment in 2016 is 1,819 with a State Rated Capacity of 1,993 upon
completion of renovations to bring the facility in to compliance with the approved Educational
Specifications.
The focus of this study is to evaluate design options for five approaches to modify Severna Park
High School. These are as follows: No Changes; Patch/Paint; Revitalization; Modernization; and
Replacement School.
GWWO, Inc./Architects would like to thank the members of the Severna Park High School Study
Committee for their time and effort in helping to develop this study. The Committee’s input and
creativity has proved invaluable in understanding and addressing the needs of Severna Park High
School.
Methodology / Process
The Study Committee completed multiple tasks to develop this Feasibility Study. The process
involved multiple meetings to identify project goals, evaluate and identify approaches and individual
schemes. Additional tasks, including field investigations; review of drawings of the existing building;
code/ADA analysis and preliminary reviews were conducted by the Architect/Engineering team to
determine the impact of the existing building systems on the various schemes.
Based on the above analysis, the Study Committee developed advantages, disadvantages and costs
associated with each of the schemes. The Committee then evaluated these factors to consider how
each scheme addressed the project goals and facility needs of Severna Park High School.
AACPS System Goals:
GOAL I – ACADEMIC ACHIEVEMENT
All diploma-bound students will reach high standards, as established by Anne Arundel County Public
Schools and state performance level standards in English/Reading/Writing/, Mathematics, Science
and Social Studies. Achievement disparities among all No Child Left Behind (NCLB) groups of
students will be eliminated.
GOAL II – SAFE AND SUPPORTIVE LEARNING ENVIRONMENT
All students will be educated in a safe, positive, and supportive learning environment with a focus on
security enhancements that support system-wide safety and discipline standards. AACPS will
eliminate disparities among all No Child Left Behind (NCLB) student groups in the referral,
suspension, and expulsion rates for violation of the Code of Student Conduct.
Page 6 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
GOAL III – WORKFORCE QUALITY
Anne Arundel County Public Schools will ensure and maintain a work environment of respect and
mutual collaboration by attracting and retaining a quality work force that demonstrates a
commitment to providing a positive learning environment, values diversity, and reflects the diversity
of the county and the relative labor market.
GOAL IV – COMMUNITY ENGAGEMENT
All Anne Arundel County Public School students will be educated in schools that are family-friendly,
welcoming environments. Anne Arundel County Public Schools will eliminate disparities in parent and
community representation and participation in traditional and non-traditional school-community
activities.
GOAL V – EQUITY
Anne Arundel County Public Schools will address the diversity that students and staff bring to the
learning environment and organize schools and classrooms to support the academic achievement
and success of all students.
AACPS Study Goals:
The major goals of this study are to:

Create a flexible facility to support a contemporary instructional program and enhance
student success through the application of inter-disciplinary instructional approaches.

Identify building concepts which facilitate instructional groupings while fostering intracooperative educational experiences between students and teachers alike.

Create an environment which highlights the identity and image of the school within the
community and encourages stability of the student population, exemplary educational
programs, and positive multi-cultural experiences.

Identify a site layout which respects the surrounding community while providing safe,
organized on-site pedestrian, automotive, and bus circulation patterns.

Improve the security, operational, and maintainability aspects of the facility to increase
resources available to school staff and faculty to focus on student success.

Provide enhanced interior environmental quality through improved building systems and
attractive finishes.

Provide building improvements while maintaining instructional capability on-site throughout
construction.

Identify a capital improvement project which can provide the above goals on a compressed
schedule at optimum cost.
Page 7 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
PURPOSE
The purpose of this feasibility study is to develop instructionally sound and cost effective alternatives
for the improvement of Severna Park High School. The alternatives presented in this study were
influenced primarily by the facility requirements of the Educational Specification, as well as the
tiered scope parameters established by AACPS for the options to be considered.
Six options are presented for consideration:
1.
2.
3.
4.
5.
6.
Option
Option
Option
Option
Option
Option
A – Do Nothing
B – Patch and Paint
C – Revitalization
D – Modernization
E – Replacement A
F – Replacement B
It is expected that the information presented in this study will assist the Board of Education in
determining the most appropriate alternative that satisfies the Ed Spec and optimizes the delivery of
a contemporary instructional program, at a reasonable cost.
Page 8 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
HISTORY
Severna Park High School is a two story masonry building of 296,191 GSF located at the
convergence of Robinson Road and Benfield Road in Severna Park, Maryland. The original building
was constructed in 1957. A major addition in 1971 included a new media center, classrooms, minigymnasium with support space, and new administration offices. In 1982 the cafeteria was
expanded. Other renovations have included HVAC improvements, boiler replacement, roof
replacement, science lab renovations in 2003, and installation of an artificial turf field in 2008. Toilet
rooms were upgraded to meet requirements of the Americans with Disabilities Act (ADA). However,
the remainder of the building has not been renovated to comply with ADA codes.
There is currently one relocatable classroom on site which houses a music class.
The existing building is not known to be historically significant, but the school and local community
take great pride in the high school.
Most of the existing finishes in the school are original. Many of the interior materials, such as
casework, masonry walls, and doors, are in good condition. A good portion of exterior brick veneer
on the original building however is deteriorating due to water infiltration.
The site is just over 40 acres and has approximately 485 parking spaces. The following athletic
facilities are on site: football field, bleachers, tennis courts, practice and multi-purpose fields,
baseball field, softball field, and basketball courts.
Construction History:
Original 1957 building
1971 additions
1982 addition
Page 9 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
EXISTING CONDITIONS
1.0
1.1
Site
Site Description
JENNINGS RD REC. AREA
Severna Park High School resides at 60
N Robinson Road in Severna Park, MD
S
ITE
21146. The site is 40.30 acres and is
WICKLOW
located at the intersection of Benfield
SEVERNA FOREST
Road and Robinson Road, approximately
1,100’ southeast of Governor Ritchie
EVERGREEN Highway (MD Route 2). The property is
ESTATES
also known as parcel 218 on tax map
SEVERNA GARDENS
31, grid 6. The tax account number for
the property is 03-000-00477223. The
site is comprised of several properties
WEST SEVERNA PARK
purchased by the Board of Education of
Anne Arundel County beginning in 1956 and ending in 1977. Deeds for the property can be
found at the Anne Arundel County courthouse at Liber/Folio’s 1052/207, 1107/ 578,
1155/413, 1222/298, 2804/720, 2812/ and 2953/181.
The property is bounded by an Anne Arundel County Recreation and Parks property known
as Cool Pond Park and/or the Jennings Road recreational area (which also currently contains
a portion of the High School’s baseball field and the softball field) and a single family home
residential development known as Wicklow to the east. Robinson Road, Benfield Road and
several single family home residential developments known as Severna Gardens, West
Severna Park and Evergreen Estates to the south. A single family home residential
development known as Severna Forest is located to the west and a single family home
residential subdivision is also located to the north.
1.2
Site Circulation and Parking
There are two access points into the
site. The main entry is located along
Robinson Road and allows for bus and
a majority of the vehicles to access the
school. A loop road is located
approximately 100’ into the site along
the left hand side of the drive. This
loop road parallels the front of the
school and is approximately 650’ long.
The secondary access is via a lighted
intersection at the convergence of
Benfield Road, Evergreen Road and
Robinson Road and allows for access
into the main student parking area.
Page 10 of 112
FACULTY, VISITOR AND STUDENT PARKING
BUS STACKING
N
STUDENT
PARKING
SIGNALIZED
INTERSECTION
MAIN
ENTRY
BUS STACKING
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
Pedestrian access mainly occurs off of Benfield Road and Robinson Road along the entire
property frontage and requires pedestrians to cross vehicular drives to gain access to the
building. The concrete walks and paving throughout the site are in poor condition.
There are three distinct parking areas indentified on site. The main student lot is located off
of the signalized intersection to the west of the building and allows for the parking of 228
vehicles (4 Handicap). The location of this lot is also conducive to parking for sporting events
occurring at the stadium field, tennis courts and/or any of the turf fields. Additional
vehicular access from this lot to other paved areas on site is not available. The second large
parking area is located to the far east of the school and is accessed via the main drive. This
parking lot is mainly used by faculty and visitors and allows for the parking of 203 vehicles
(12 Handicap). There is a third and smaller parking lot located east of this parking area
adjacent to the existing basketball courts which allows for the parking of 54 vehicles (0
handicap spaces). Both of these lots are somewhat conducive to parking for sporting events
that occur at the baseball and softball fields. Vehicles were noticed parked in the service
yard but no striped spaces were observed.
The school is currently served by 26 buses which enter the site via the main entry drive.
Stacking for the buses is awkward and requires the buses to meander through the main
parking lot along the perimeter parking lot drive, eventually ending up at the loop road in
front of the school. The buses begin stacking at the egress of the drive and then continue
stacking along the loop road, back along the perimeter parking lot drive isle located closest
to the school eventually ending at the tech wing. The perimeter drive within this parking lot
is signed one way requiring vehicles that enter to do so directly into the parking bays. Once
in the lot vehicles have the option of driving approximately 300’ and making a left into an
expanded parking area, making a u-turn and exiting or entering the main loop road, or
continuing straight to the tech wing. The remaining two drive isles within the expanded
parking area are both signed two way. The smaller parking area can also be accessed off of
the perimeter drive approximately 575’ into the site. This parking area is not signed although
by design it appears that vehicles proceed in a one way manner looping around the lot in a
right to left manner. The student lot is also signed one way with the entrance into this lot
being directly in the middle requiring vehicles to make a either a left turn or right turn
immediately upon entering the site. Once in the left hand or right hand parking area, drivers
must continue through in a loop to park or exit.
Emergency vehicle access does not meet current code. Although there is perimeter access
around the front and eastern side of the building there is no access that would meet current
standards for the rear and/or western side of the building and/or site.
Consideration should be given to creating a safer environment for vehicles and pedestrian
traffic, while also separating the bus traffic from the main vehicular traffic. In addition,
complete perimeter emergency vehicle access should be added to allow for fire vehicles to
access the building and ambulances to access any of the outdoor sports fields.
1.3
Zoning Information
The school property is currently zoned R-5, single family residential. The properties
surrounding the school site to the north, south, east and west are also zoned R-5. The
Page 11 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
following specific development standards for the R-5
zone (an excerpt from Article 18-Zoning) of the Anne
Arundel County Code are provided for guidance only.
Per Article 18, §18-2-101(a) This article (Zoning)
applies to all land located in the County, except that it
does not apply to land owned or leased and developed
by the County or the Board of Education unless
Federal or State law requires compliance with this
article. Therefore the project would essentially be
exempt from the zoning regulations unless Federal or
State law required compliance. Although the site is
exempt from all local codes it is currently in
compliance.
OS
R2 SITE
N C3 R1 R5 R2 R2 Bulk Zoning Regulations relating to a non residential use in an R-5 are as follows.
Minimum lot size
7,000 square feet
Maximum coverage by structures
40% of gross area
Minimum width at front building restriction line
60 feet
Minimum setbacks for principal structures:
Front lot line
25 feet
Rear lot line
20 feet
Side lot lines
7 feet
Corner side lot line
20 feet
Principal arterial or higher classification road
35 feet
Minimum setbacks for accessory structures other
than sheds that do not exceed 64 square feet in
area and eight feet in height:
Front lot line
50 feet
Side and rear lot lines
7 feet or, for structures less than 8 feet in height (other than
swimming pools, tennis courts, basketball courts, and similar
private recreational facilities accessory to single-family detached,
duplex, or semi-detached dwellings), 5 feet
Corner side lot line
15 feet
Maximum height limitations:
Principal structures
35 feet
Accessory structures
25 feet or the height of the principal structure, whichever is less
Page 12 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
1.4
Site Soils
According to information obtained
from the United States Department of
Agriculture
Natural
Resources
Conservation Service, the site falls
into four (4) distinct soil groups:
DvC
N
UoB
DwB
DvC – Downer-Hammonton complex,
5 to 10 percent slopes.
DwB – Downer-Hammonton complex,
0 to 5 percent slopes.
PgB – Patapsco-Fort Mott-Urban Land
complex, 0 to 5 percent slopes.
UoB – Udorthents loamy, 0 to 5 percent slopes.
PgB Additional information regarding these soils is indentified below:
1.5
Map
Unit
Percent of
Site Area
Hydric
Soils
Dvc
1.2%
No
DwB
2.5%
No
PgB
83.5%
No
UoB
12.8%
No
Classification
Varies by depth
SC, SM, SP, CL, ML
Varies by depth
SC, SM, SP, CL, ML
Varies by depth
SC, SM, SP, CL
Varies by depth
SC, SM, CL, GC, GM, GS, ML
Topsoil
Source
Drainage System
Fair
Well drained
Not rated
Well drained
Poor
Somewhat excessively drained
Poor
Well drained
Site Topography
The site topography generally slopes away from the building in all directions. The building
floor elevations vary between 63.5+ at the main building, to 62.25+ at the media center, to
60.9+ at the tech wing (approximate elevations adjusted to NAD 83). Elevations along the
front (south) of the building range from 63.0+ to and elevation of 56.0+ within Robinson
road with slopes between 0.5% - 2.5%. Elevations along the parking side (east) of the
building range from 62.0+ to an elevation of 46.0+ behind the existing basketball courts.
Slopes within both the staff parking lot and student parking adjacent to the basketball court
are at 1.5% with slopes of 5.0% - 20% in the wooded areas surrounding the basketball
court and associated parking. Elevations at the rear (north) of the building range from
62.0+ to an elevation of 30.0+ located in the forested (outfall) area east of the existing
grassed ball fields with slopes ranging from 1.5% - 20%. Elevations along the track side
(west) of the building range from 63.0+ to an elevation of 54.0+ along the far corner of the
property adjacent the track. In general terms the site was essentially constructed with three
distinct plateaus. The first containing the school, associated parking and grassed ball field,
the second containing the baseball and softball fields and the third containing all of the
remaining sports fields.
Page 13 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
N
LEGEND WATER SEWER STORM GAS ELECTRIC 1.6
Utilities
Water
The site is currently served by a 6” public water line with two fire hydrants located along the
front of the school. One hydrant is located adjacent to the drop off loop road and
gymnasium and the other adjacent to the student parking and grassed ball field. The 6”
waterline is served via an 8” line located within Robinson Road and the meter is located
within the grassed area between the drop off loop and Robinson Road. A smaller water line
tapped from the main building also serves the concession building located adjacent to the
stadium and all of the natural turf fields are irrigated. Any new construction will most likely
require the existing system to be looped around the building and additional fire hydrants
installed to meet current fire code.
Sanitary Sewer
The site is currently served by a public gravity sanitary sewer system. There is a small 6”
gravity line that leaves the building adjacent to the existing cafeteria. Based on our review
of the as-built documents it appears that this line was installed in 1982 and serves the
existing kitchen. This line connects into a manhole located within Robinson Road. The
remainder of the building is served by a gravity system with lines ranging from 6” to 8” and
leaving the building at various points around the building. All of these lines eventually tie
into an existing 8” public line that is buried under the school’s grassed multi-purpose fields.
Page 14 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
The public line enters the site off of Cottonwood Road adjacent to the existing tennis courts,
it then turns and heads in an easterly direction under the fields and then exits the site in the
wooded area north of the existing baseball field. It should be pointed out that the site was
initially served by a private septic system. As-built documents indicate that an existing
50,000 gallon septic tank was abandoned in place behind the school. The school’s original
septic fields were located in the area that is now utilized for the three multi-purpose fields.
Storm Drains
The site is currently served by a closed storm drain
system. Storm drain pipe sizes range from 6” to 48”.
The site is split into two distinct drainage areas. The
first drainage area is approximately 12+ acres and
contains a large portion of the building including
everything with the exception of the rear classroom
and tech wing, the student parking area, main loop
drive and entry. Stormwater within this drainage
area is conveyed in a southerly direction offsite into
a system located within Robinson Road. The second
and much larger drainage area contains the
remainder of the building and site. These areas include the rear classroom and tech wing,
the faculty and visitor parking lots, the stadium, tennis courts and all of the sports fields. A
public storm drain system was installed through the site in the 1970’s; this 48” storm drain is
located under the three existing grassed multi-purpose fields and picks up all of the drainage
area mentioned above in addition to portions of Benfield Road and a majority of the Severna
Gardens subdivision. The total drainage area being conveyed through this public system is
approximately 60 to 80 acres. The outfall for this system is located within the forested area
east of the grassed multi-purpose fields. During our field review which occurred on a warm
sunny day with little to no rain preceding, a constant flow of water was noted exiting the 48”
pipe at the outfall. Based on the level of scouring noted on the concrete it appears that this
flow remains constant and has done so for many years. A request has been made to have
the existing 48” pipe investigated via scoping and video tape in an attempt to determine the
source of the water flow.
Gas, Electric, Cable, Telephone
The site is served via a 3” gas line which enters the site from Benfield Road, traverses the
student parking lot and grass field and then enters the building in the courtyard between the
existing gymnasium and media center. During our field investigation several old gas valves
were noted along with a very large vault. Based on our discussions with the building
superintendant while on site it was unclear whether the meter is located in the vault or
inside the boiler room.
Electric enters the site at the far southeast corner of the property nearest to the visitor
parking. The electric is overhead to a pole located near the entrance to the secondary
parking area located adjacent to the basketball courts. From this pole the electric service is
underground through the faculty parking lot to the east side of the building. See the
mechanical, electrical section of this report for additional information regarding the gas,
electric, cable and telephone.
Page 15 of 112
Severna Park High School
Severna Park, Maryland
1.7
Feasibility Study
GWWO, Inc./Architects
Stormwater Management
Although on site construction has occurred at various points since the school was initially
constructed the site does not contain any stormwater management facilities. A large pond
does exist north of the site adjacent to Thomas Way in the subdivision known as Cool Pond.
This facility was constructed in the early 1980’s and should account for stormwater quantity
management for the large drainage area discussed above. The drainage area to this facility
which traverses the site is a total of 116 acres.
Any new construction that occurs will be required to meet the requirements established by
the Stormwater Act of 2007. These guidelines establish a process by which new
construction needs to utilize sustainable or environmental site design (ESD) to the maximum
extent possible to satisfy water quality requirements. ESD’s include but are not limited to
micro-bioretention, dry and/or wet swales, rain gardens, etc. Attempts should be made to
provide for impervious disconnects and to allow for adequate open space to construct
multiple smaller facilities throughout the site to satisfy these requirements. Based on our
preliminary review of the soils information it appears that infiltration of stormwater should
be achievable on site and cursory conceptual layouts have been reviewed to provide areas
for ESD’s to the maximum extent possible.
1.8
Floodplains, Wetlands and Waterways
The site is not located within the 100 year floodplain as delineated on FEMA flood insurance
rate map 240008-0020-C. The site is located in zone C which means an area of minimal
flooding. A review of NWI mapping indicates the headwaters of a wetland area which is
located within the forested area north of the existing baseball field.
In addition to the continuous flow of water noted in the existing storm drain section of this
report additional discussions have occurred during the committee meetings which also
indicate wet areas during various times along the north side of the site in the vicinity of the
existing grass multipurpose fields, tennis court and track. Additional historical as-built
documentation review performed did not indicate any previous wetland, underground
stream, etc.
A request has been issued to have the Maintenance Department scope and video the
existing storm drain line in an attempt to further determine the source of the water. An
environmental features assessment and if required, wetland delineation should be performed
at the early stage of design of the project.
1.9
Landscape, Trees and Forest Conservation
Landscaping throughout the site consists of lawn and sporadic planting. The planting areas
are mainly concentrated at the front of the school within the open space located between
Robinson Road and the main loop road in addition to an area located between the rear of
the classroom wing and the tech wing. Plantings in both of these areas consist of mature
deciduous trees, several of which are very large. The western and northern sides of the site
Page 16 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
are heavily buffered from the adjoining residential homes by a combination of evergreens
and deciduous trees. Areas north of the existing baseball field are heavily wooded and lead
to the County owned property (Jennings Road Recreational Area) and portions of the site
around the existing basketball court and small parking lot are also wooded.
There are no documented forest conservation easements on site. Any construction
exceeding 40,000 SF will require compliance with the Maryland Forest Conservation Act. A
forest stand delineation should be completed at the beginning of the design phase of the
project to determine the quality of all on site forested areas and to determine if any of the
mature trees qualify as specimen trees. During this time a forest conservation worksheet
should be completed to more adequately determine the forest conservation acreage required
based on the construction option chosen. On site afforestation may likely be required and
could possibly be met at various locations on site. If it is determined that the selected
construction option chosen will not allow for adequate on site afforestation then a fee in lieu
to the County will be required to meet these regulations.
1.10
Site Entrance
There are two entry drives into the site. One
entry point is a signalized intersection at the
convergence of Benfield Road, Evergreen
Road and Robinson Road. This entry allows
for access into the main student parking lot
located west of the building and 700’+ from
the building’s main entry. The second entry
point is 1000’+ easterly heading towards
Governor Ritchie Highway (Maryland Route 2)
and is 300’+ from the building’s main entry.
This entrance allows for access to the
remaining parking (faculty, visitor and
student) in addition to access for the bus
drop off. A loop road is located approximately
100’ into the site that parallels the building as
it heads to the west; the loop road is 650’+
long and allow for egress of the bus traffic.
1.11
Practice Fields /Athletic Fields / Athletic Courts
The stadium track/field is located at the far western corner of the property. The stadium
field was upgraded to artificial turf in 2008. Lighting around the stadium field is very
outdated. It also appears that the bleachers were recently upgraded, although the seating
on the visitor side is much larger than the home side. There are currently 8 tennis courts
located immediately behind the stadium field. The school’s practice field is located between
the school building and stadium field adjacent to the student parking. There are 3 natural
turf multi-purpose fields located east of the tennis courts immediately behind the building.
The school’s baseball field and softball field are located along the east side of the building on
Page 17 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
County owned property and neither
of these fields is lighted. The
basketball courts consist of three full
courts which are located east of the
main parking lot. The court paving
and fencing around the courts is in
poor condition. The school also has
a fenced area for child development
measuring approximately 100’ x 85’
which is located along the side of the
tech wing portion of the building.
MULTI‐
PURPOSE
N BASEBALL
& SOFTBALL FIELD
PRACTICE FIELD TENNIS STADIUM FIELD
BASKETBALL 1.12
Site Educational Adequacy
1. Areas of Program Deficiencies
 Stadium field track should be 8 lanes, it’s currently 6 lanes.
 2 long jump/triple jump sand pits, currently 1.
 Stadium seating includes 1,664 on the home side and 756 on the visitor’s side.
 Tennis courts should be a total of 10, there are currently 8.
 5 natural turf fields, there are currently 4.
 Inadequate pitching warm up areas for home and visiting team.
 Inadequate batting cage area.
 Baseball and softball fields are not lighted.
 No separate bus and vehicular drop off areas.
 No separate perimeter emergency vehicle access.
2. Functional Concerns
 Bus, vehicular and pedestrian traffic are intermingled with no separation between
buses and vehicles.
 No separate defined parent drop off area.
 Baseball and softball fields are located on County owned property.
 No perimeter access for emergency vehicles.
 Dumpsters sporadically located within the service yard; no defined dumpster pad.
 Need to increase seating on the home and visitor sides of the stadium field.
 Need to upgrade lighting at the stadium.
Page 18 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
EXISTING CONDITIONS
2.0
BUILDING
2.1
Exterior
Roof:
The existing roofing is a 4-ply built-up membrane with
aluminum coating on tapered insulation which was
installed in 2000. The overall condition is generally
good although there are existing leaks at various
penetrations. Coping appears to be in good condition.
Replacement of the roofing will be required within five
years.
Exterior Walls:
The original building and additions are brick veneer
on concrete block backup. There is no cavity or
insulation in the walls of the original building. Seals
around stucco panels that replaced original windows
have allowed water to penetrate the envelope in a
significant amount of area. This continuous water
penetration has resulted in failing cast stone sills,
rusting shelve angles, and deterioration of mortar.
Repair of these items is critical. Emergency egress
panels within the in-filled area are located in each
classroom.
Typical roof.
Stucco in-fill panels.
Exterior Windows:
Most of the original window area was in-filled in 1971
with stucco covered panels. Classroom windows
throughout provide a minimum amount of daylight.
All windows are single glazed.
Exterior entrances and storefront:
A number of exterior hollow metal door frames and
metal doors are rusting through and must be
replaced. Doors and hardware have not been
upgraded to meet accessibility requirements. The
single glazed metal frame entrance system at the
main entry and gymnasium lobby should be replaced.
All exterior doors and hardware should be updated.
Exterior cast stone sill.
Metal framed entry system at
gymnasium.
Page 19 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
EXISTING CONDITIONS
2.2
Interior
Ceilings: A mixture of 2x2 and 2x4 acoustical panel
ceiling exist in corridors. Glued on 12x12 acoustic tiles
are found in many of the original classrooms. In the
1971 addition there are mixture of 2x4 acoustical
panel ceilings and exposed ceilings. Overall ceilings
are in fair condition. However, the 2x2 acoustical
panel ceiling in the cafeteria should be replaced.
Flooring: Terrazzo flooring is in good condition in the
corridors of the original building. Cracks were
observed in the terrazzo flooring in the cafeteria.
Classrooms have vinyl composition tile (VCT) flooring.
VCT is also throughout the corridors and classrooms
of the 1971 addition, with the exception of carpet in
the media center. Ceramic tile in the toilet rooms
should be replaced. The stage and gym wood floors
should be reconditioned.
Typical narrow corridor.
Interior Partitions: Typical classroom partitions are
painted CMU with structural glazed tile base. Many
corridor walls are full height structural glazed tile.
Most partitions are in good condition.
Doors/Hardware: Typical door hardware does not
meet accessibility requirements. Corridor classroom
doors in the original building have louvers which do
not comply with current building code requirements
regarding fire ratings and the passage of smoke. Most
corridor doors and hardware should be replaced.
Typical corridor door.
Toilet Rooms: Plumbing fixtures all appear to be
original or dated and beyond their useful life. The
water closets are floor-mounted, urinals are floor and
wall-mounted, and lavatories are individual wall hung
type.
Plumbing fixtures no longer meet code
requirements for water usage and are not properly
configured for ADA accessibility.
Casework and Equipment: Typical classroom
casework is original to the building and is in poor
condition. Science classrooms were renovated in 2003
and do not meet current requirements.
Page 20 of 112
Typical classrom casework.
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
EXISTING CONDITIONS
2.3
Structural System
Severna Park High School is a one/two story structure comprised of a variety of structural
framing systems, including steel frame, cast in place concrete, load bearing masonry, open
web steel joists, and precast plank.
Existing structural drawings for the original building are dated 1957 with subsequent
additions or renovations in 1971, 1982, 1996, 1997 and 2003. Existing structural drawings
indicate that the structure was designed for a roof live load of 30 pounds per square foot.
The 1971 structure classrooms were designed for a live load of 50 pounds per square foot,
corridors for a live load of 75 pounds per square foot and toilet for a live load of 50 pounds
per square foot. The 1971 and 1982 additions were designed for a floor live load of 100
pounds per square foot.
The building is supported by a shallow spread footing foundation system, designed for an
allowable bearing pressure of 4000 pounds per square foot for 1957 building and an
allowable soil bearing pressure for 1971 and 1982 are not available on the drawings.
Building areas indicated in the following descriptions of the existing structural systems refer
to the diagram below:
Part A
The area identified in the existing structural drawings as Part A is a one story structure with
the gymnasium and supporting area having a higher roof elevation. The high roof deck
consists of a 3” thick insulating roof plank and is supported by the 12” deep purlins. The
high roof purlins are supported by 36” deep wide flange steel girders spanning the width of
the gym and supported on each side by wide flange steel columns located in the gym walls.
The low roof deck consists of a 2” poured gypsum on a 1” form board with Bulb-T sub-
Page 21 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
purlins. Framing for the low roofs consists of 14” deep open web steel joists at roughly 42”
to 48” on center supported by the load bearing exterior and interior walls.
The first floor of the gymnasium and other area consists of 6” deep precast concrete planks
with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry
walls are supported on a continuous spread footing. There is a fairly substantial crawl space
under the entire area.
The 1971 addition to Part A is a one story structure. The low roof deck consists of a 3”
Insulrock roof plank with Bulb-T sub purlins. Framing for the roofs consists of steel beams
and open web steel joists supported by the load bearing exterior and interior walls. The floor
consists of 6” deep precast concrete planks with a 2” topping slab over a crawl space,
supported by load bearing masonry walls. The load bearing masonry walls are supported on
a continuous spread footing.
Part B
Part B is a one story classroom wing. The roof deck consists of a 2” poured gypsum on a 1”
form board with Bulb-T sub-purlins. Framing for the roof consists of 14” deep open web
steel joists over the classroom and 8” deep open web joists over the corridor at roughly 48”
on center supported by the load bearing exterior and interior walls.
The first floor consists of 6” deep precast concrete planks with a 2” topping slab, supported
by load bearing masonry walls. The load bearing masonry walls are supported on a
continuous spread footing. There is a fairly substantial crawl space under the entire area.
The 1971 addition to Part B is a one story structure. The roof deck consists of a 3” metal
deck supported by 14” deep wide flange beams on a steel columns and a spread footing
foundation. The slab on grade is a 5” thick concrete slab.
Part C
The area identified in the existing structural drawings as Part C is a one story structure with
the auditorium, cafeteria and supporting area having a higher roof elevation. The high roof
deck over auditorium consists of a 3” thick insulating roof plank and is supported by the 12”
deep purlins. The high roof purlins are supported by about 5’-0” deep open web steel
trusses spanning the width of the auditorium and supported on each side by wide flange
steel columns located in the walls. The low roof deck consists of a 2” poured gypsum on a 1”
form board with Bulb-T sub-purlins. Framing for the roof over cafeteria consists of 32” deep
open web steel joists at roughly 52” on center supported by steel beams and columns at the
exterior walls and the load bearing interior walls. Other low roof framing consists of joists of
various depths and spacing and supported by load bearing walls.
The first floor of the cafeteria and other areas consists of 6” deep precast concrete planks
with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry
walls are supported on a continuous spread footing. There is a fairly substantial crawl space
under the entire area.
Page 22 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
Part D and E
Parts D and E are two story classroom wings. The roof deck consists of a 2” poured gypsum
on a 1” form board with Bulb-T sub-purlins. Framing for the roofs consists of 14” deep open
web steel joists over the classroom and 8” deep open web joists over the corridor at roughly
48” on center supported by the load bearing exterior and interior walls.
The second floor consists of 6” and 8” deep precast concrete planks with 2” topping, and is
supported by load bearing masonry walls.
The first floor consists of 6” deep precast concrete planks with a 2” topping slab, supported
by load bearing masonry walls. The load bearing masonry walls are supported on a
continuous spread footing. There is a fairly substantial crawl space under the entire area.
Part F
Part F is a one story wing with a partial basement. The high and low roof deck consists of a
2” poured gypsum on a 1” form board with Bulb-T sub-purlins. Framing for the roofs consists
of 8” to 18” deep open web steel joists at roughly 48” on center at the high roof and 36” on
center at the low roof. The high roof structure is supported by a combination of steel beam
& columns at the exterior and load bearing interior walls. The low roof structure at the
second floor level is supported by the exterior and interior load bearing walls.
The first floor except the basement area consists of 6” and 8” deep precast concrete planks
with a 2” topping slab, supported by load bearing masonry walls. The load bearing masonry
walls are supported on a continuous spread footing. There is a crawl space under the entire
area.
The first floor over basement consists of 6” deep precast planks with a 2” topping slab
supported by interior concrete beam and columns, and perimeter load bearing walls. The
slab on grade at the basement consists of 5” thick concrete floor on grade. Interior columns
and walls are supported on spread footings.
Part G
This is a two story 1971 media center and classroom addition with a partial basement. The
roof deck consists of a 3” steel deck supported on wide flange purlins and girders.
The second floor consists of 3½” light weight concrete on a 1½” composite steel deck
supported by wide flange beams and girder.
The first floor consists of 5” slab on grade at the media center and 3½” light weight
concrete on a 1½” composite steel deck supported by wide flange beams and girder at other
areas.
The building structure is supported by steel columns on a spread footing foundation.
Page 23 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
1982 addition
This is a small one story addition with a crawl space. The roof structure consists of 1½”
steel roof deck supported by steel joists and girders supported by a load bearing wall. The
floor construction is 3” light weight concrete on a 9/16” form deck supported by open web
steel joists on load bearing walls. The exterior and interior walls are supported on spread
footings.
Existing Conditions
Based on our limited visual observations, the existing structure appears to be in a good
condition.
Observations of the underside of the gypsum roof decks were made in a limited number of
areas. In all instances the deck appeared to be in good condition. It should be noted
however, that AACPS’s experience at other schools undergoing re-roofing or major
renovations has uncovered areas of gypsum roof decks that have deteriorated due to water
infiltration requiring replacement of the deck. The same unforeseen condition is possible
here.
The masonry load bearing walls appear to be in good condition. There were spalling,
cracking, exposed joint reinforcement and loose mortar joints observed at the brick veneer
and window sill at various locations (Photos 1, 2 & 3). In addition, cracks in the terrazzo
floor were observed at the cafeteria and adjacent corridor floor (Photo 4), but not in other
corridor floors. Also, observed settlement at the plaza level pavement, loose rails and
spalling at the retaining walls outside the Gymnasium (Photos 5 & 6).
A lack of an overflow drain or scupper at small area of Part-C roof was observed. In addition,
at the basement mechanical room, leakage was observed through the metal hatch located at
the ground level.
All in all, we found the structure to be in a good condition. Based on our visual observations,
which were limited to those areas that were accessible, we saw no indications of anything
that would cause any concern with respect to the structural integrity of the structure. The
building appears to be structurally sound.
Photo 1: Exterior brick veneer deterioration
Page 24 of 112
Photo 2: Exterior brick veneer deterioration
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
Photo 3: Spalled sill stone
Photo 4: Cracks in Terrazzo floor at
Cafeteria
Photo 5: Plaza level pavement settlement
Photo 6: Loose rails and spalled bricks
Page 25 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
EXISTING CONDITIONS
2.4
Mechanical Systems
2.4.1 History of Mechanical System Installations and Retrofits
The original drawings for the building were completed in 1957. The original HVAC design for
the building was a central heating plant of three boilers supplying hot water to convectors
and unit ventilators throughout the building. Offices were heated with wall to wall
convectors and classrooms were heated and ventilated with unit ventilators. Piping to units
is located in crawl spaces below the first floor. Toilet rooms and storage areas are
exhausted by powered roof fans. Upper floor corridors were ventilated by gravity roof
ventilators. Shop classrooms and arts and crafts classrooms were located on the upper
floors and ventilated by powered roof fans located directly above the space.
In 1971 additions were made to the building. These included a mini gym and support
spaces for the main gymnasium in Area A, a new media center building in Area G, and
additional administrative spaces in area B. The new gymnasium areas are heated by central
station heating-ventilating air handling units. The administrative area is heated and cooled
by three roof top gas fired/packaged DX multi-zone units. Perimeter areas of the
administrative section are heated with convectors on the wall. Incremental conditioners
were installed on the stage support areas. Many classrooms had unit ventilators removed
and new incremental conditioners installed. In the basement of the media center building a
water cooled chiller connected to a cooling tower outside the building and constant volume
terminal reheat air systems were installed. These provide heating and cooling to both floors
on the media center and supporting rooms. The perimeter areas of the building had
convectors to provide additional heating. During these renovations boiler #2 and #3 were
replaced.
In 1993 many of the unit ventilators were replaced. Two of the new unit ventilators (in the
Management and Foods Classrooms) were ceiling mounted horizontal units with split new
roof mounted condensing units.
In 1996 the roof top units on the administrative portion of the building were removed along
with much of the associated ductwork and replaced with new rooftop units. The unit
ventilators for the painting classrooms and the P.E. classroom were also removed and
replaced with new incremental units. All incremental units in the classrooms of Area B were
replaced. The air handling units serving the auditorium were designed to be replaced;
however, it appears that this did not occur since the original design remained when the air
system was reconfigured later. Unit ventilators in the surrounding music rooms were
replaced. The existing cooling tower and chiller were removed and replaced.
In 1982 a cafeteria expansion occurred; a new packaged gas fired DX cool rooftop unit was
installed at this time. There is no mechanical documentation for this period.
In 1997 the science classroom area was renovated, the incremental units were removed,
two new packaged constant volume roof top units with duct mounted hot water heating
coils, and several split systems were installed.
Page 26 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
In 2000 boilers #1, #2, #3 were removed and replaced by two new boilers. All pumps in
the boiler room were replaced as well as the expansion tanks.
In 2002 the kitchen hood was replaced and a new hood, fan, and make-up air unit was
installed.
In 2003 the mechanical equipment serving the auditorium was removed. Two new energy
recovery units with heat recovery wheels were installed to serve auditorium.
2.4.2 Heating Water
Description:
The majority of the building is heated from the
hydronic heating water system. Two nominal 500
horsepower fire tube boilers exist in the boiler
room. The current boilers were installed in 2000
and are the third set of boilers since the original
plant construction in 1957. The boilers are dual fuel
and can be fired on #2 fuel oil or natural gas. We
are unsure if the school is utilizing an interruptible
natural gas service in order to capitalize on the dual
fuel capability of the boilers.
The heating water is circulated through 20
individual heating water zone pump systems. The
portion of the heating water system which services
Area G of the building utilizes a primary-secondary
pumping arrangement. 16 of the 21 pumps were
replaced in the year 2000. The pumps that were not
replaced are all located in Area G and date back to
the original 1971 construction.
The major portions of the heating water piping
system were constructed with the original building
in 1957 and the major addition of 1971. Some runouts have been replaced with the replacement of
the terminal units throughout the years. However,
the majority of the piping is 53 years old with the
next largest portion being 39 years old.
Dual Fuel Fired Boilers
Fuel Oil Pump & Controls
The expansion tanks were replaced in 2000 during
the boiler replacement. All the hydronic specialties
which are not directly attached to the 16 replaced
pumps are original.
2.4.2.1 Condition:
The boilers and the pumps in the boiler room are
relatively new and appear to be in good condition.
The pumps in the Area G mechanical room are
Heating Water Zone Pumps
Page 27 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
operating but are aged significantly beyond their
rated useful life. The condition of the piping is
unknown; however, the majority of the heating
water piping in the building has exceeded its rated
useful life.
2.4.2.2 Efficiency:
Boilers: Fire tube boilers were once considered
highly efficient but have been exceeded by modern
condensing type boilers. While rugged, these
boilers have a maximum efficiency of 85%.
Condensing type boilers can reach operating
efficiencies of 95%+ (if operating in the
condensing water temperature range).
Heating Water Zone Pumps
Pumping Systems: The pumping systems are all
constant volume and thus are inefficient. The
pumps operate with a constant energy draw
circulating a constant flow rate regardless of the
heating load. Modern energy efficient hydronic
systems utilize variable flow with variable
frequency pump drives. The use of the constant
flow arrangement should be discontinued.
2.4.2.3 Recommendation:
The hydronic heating system is subservient to
overall HVAC system configurations. The two
boilers have 15 years of remaining rated useful
life. The selection of a replacement HVAC system
should not focus solely on reuse of these boilers
since there are higher efficiency heating
alternatives. The reuse of the boilers should be
considered in one of the four HVAC system options
that would be studied in a life cycle cost analysis.
However, these boilers may be more valuable
being relocated to another school in need of a
boiler retrofit rather than their reuse at this facility.
Continued long term reuse of the original 1957
piping should be avoided unless the condition of
the piping can be documented through destructive
testing; and even in that case only the largest sizes
should be reused. Reuse of any of the year 2000
replacement pumps should be dependent upon an
overall HVAC system selection and the pumps
capacity.
Page 28 of 112
Heating Water Zone Pumps
Heating Water Zone Pumps
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
2.4.3 Chilled Water
2.4.3.1 Description: Area G of the building, the Media
Center Addition, utilizes a chilled water system
consisting of a 275 ton Carrier water cooled
centrifugal chiller, a single frame mounted end
suction chilled water pump and condenser water
pump, and an induced draft cross flow cooling
tower located in a pit in the court yard. The
cooling tower is has a masonry screening wall
installed on three sides, but a large non-masonry
access area on one side. The tower is not
provided with any attenuation features. The
result is that mechanical noise from the cooling
tower can be heard in the court yard and is very
disruptive. The Area G mechanical room is
provided with a refrigerant leak detection and
evacuation exhaust system per ASHRAE
Standard 15.
2.4.3.2 Condition: The chiller, pumps, and cooling tower
were all replaced in 1996. All appear to be in
good working order. The chiller has 9 years of
remaining rated useful life. The cooling tower
and pumps have 6 years of remaining rated
useful life. The cooling tower lacks proper sound
attenuation. The requisite emergency breathing
apparatus associated with the refrigerant leak
detection system has been removed from the
site; its absence is a life safety hazard.
2.4.3.3 Efficiency:
The chiller itself is reasonably
efficient (although not highly efficient); however,
the system as a whole is inefficient for its class.
The primary issue is that the system design does
not address efficiency at partial cooling load
conditions. The chilled water pump is constant
flow and the cooling tower fan is constant
volume. The system lacks the capacity to reduce
pumping energy and cooling tower fan energy as
is typical for current chilled water system
designs. If the system is to remain in place, as a
minimum it should be retrofitted with two way
control valves on the chilled water coils, and a
variable frequency drive (with associated
controls) on the chilled water pump and cooling
tower fan.
Centrifugal Chiller
Condenser Water Pump
Chilled Water Pump
Page 29 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
2.4.3.4 Recommendation: This chilled water system
services a relatively small portion of the overall
building. A full building HVAC retrofit should
utilize a one system type of the majority of the
building. Thus while a chilled water system may
be a viable solution for the overall building; this
chiller and cooling tower in their current
configuration are too small - the system should
be completely reconfigured. It may be possible
to relocate this chiller to a new central chilled
water plant and use this machine in conjunction
with additional chillers. The cooling tower is not
well located and creates acoustical problems in
the court yard; a new cooling tower location for
a much larger plant (under a chilled water plant
study option) should be considered.
2.4.4 Classroom Incremental Units
2.4.4.1 Description: The majority of the classrooms are
conditioned by self contained incremental cooling
units. These units are DX cooling and utilize hot
water heating coils. Each unit is provided with a
large through the wall louver which draws air
into the condensing section for heat rejection
and also exhausts this same air. In addition, a
portion of the louver is dedicated to outside
ventilation air intake. The units installed in Areas
C, D, and E are currently 17 years old and have
exceeded their rated useful life of 15 years. The
units installed in Area B are 14 years old and will
reach the end of their rated useful life in one
year.
Cooling Tower. Noise Enters Court Yard
Through Chain Link Fence.
A Typical Classroom Incremental Unit
The units do not appear to be classroom unit
ventilator grade in that they appear to lack an
air side economizer. Each unit was designed for
an outside ventilation air supply of 250 CFM
which is significantly below the current standard
of 465 CFM per classroom (based upon
occupancy of 30 students and one teacher at a
rate of 15 CFM of outside air per person).
2.4.4.2 Condition: The classroom incremental units are
generally in poor condition. The installation
method of the retrofit installation of the through
wall louver is problematic on multiple fronts; it is
Page 30 of 112
Classroom Incremental Unit Wall Louvers on
an Elevation.
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
unsightly, and is a source of water infiltration
into the building. A majority of the units have
exceeded their rated useful life and are
experiencing failures, including compressors and
fans. The maintenance staff report that the
parts for condenser fans are long lead items.
During our walk through inspection of the
building we found many units which were either
inoperable or operating at a significantly reduced
capacity. By nature self contained DX cooling
units provide poor relative humidity control at
partial cooling load conditions. The units have a
compressor, evaporator fan, and condenser fan
all contained within one housing with little
opportunity for sound attenuation; the result is a
relatively high background noise level (above
classroom NC target levels).
2.4.4.3 Efficiency: In terms of cooling, the classroom
incremental units are particularly inefficient. This
type of unit is not used in modern high
performance educational facilities.
A Close-up of an Incremental Unit Wall
Louver. Note That Rain Easily Penetrates
the Louver.
2.4.4.4 Recommendation: The units should be removed
and replaced with a modern classroom HVAC
system.
2.4.5 Constant Volume Terminal Reheat Air
Systems
2.4.5.1 Description: The spaces of Area G, including the
Media center, are provided with HVAC service
from a constant volume reheat system. The
system is comprised of five constant volume
central station type air handling units, four of
which utilize separate centrifugal return fans.
Each air handling unit has a hot water heating
coil and chilled water cooling coil. The design
drawings indicate that these units provide a
discharge air temperature of approximately 55
degrees. Each individual temperature control
zone is provided with a constant volume reheat
box with a heating water coil and a space
thermostat. In the cooling mode, once the space
temperature is satisfied the supply air is
reheated to prevent overcooling of the zone.
This obviously is an inefficient method of space
temperature control. There does not appear to
One of the Constant Volume Terminal
Reheat System Air Handling Units.
Page 31 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
be a discriminator control, which would allow for
the discharge air temperature set point to be
reset upward matching the critical zone cooling
load, thus reducing the required reheat energy
load.
2.4.5.2 Condition:
The air handling units are
approaching 40 years old and have exceeded
their rated useful life of 25 years.
The
maintenance staff report that the units have
faulty outside air dampers which tend to cause
coil freezing damage to the water coils. They
report that the fan bearings are in relatively good
condition; however, the overall unit condition
appears to be marginal, with some units missing
panels and shields.
A Return Fan for a Constant Volume
Terminal Reheat Air System
2.4.5.3 Efficiency:
This system type requires the
reheating of air which has been mechanically
cooled in order to prevent over-cooling of
spaces. This is a highly inefficient means of
temperature control.
2.4.5.4 Recommendation:
This system should be
removed and replaced with a modern
educational HVAC system.
2.4.6 Multi-zone Air Systems
2.4.6.1 Description: The administration spaces of Area B
are conditioned by forced air multi-zone systems.
Three rooftop gas fired heating and packaged DX
cooling units service this area. Two of the RTU's
(RTU-1 & 3) have eight zones each and RTU-2
has ten zones. Each zone is provided with a
thermostat and dedicated supply air duct
distribution system. Each RTU has a hot deck
and a cold deck. The controls mix air from each
deck using zone dampers to provide a discharge
air temperature that matches the zone heating
or cooling load. The hot deck and cold deck
discharge air temperature set points are typically
reset to match the heating and cooling load
(respectively) of the critical zones (i.e. a
discriminator control sequence). The rooftop
multi-zone units are currently 14 years old and
have one year of remaining rate useful life.
Whereas the cooling side of the units is
Page 32 of 112
AHU with a Missing Filter Access Door
Three Gas Fired/DX Rooftop Multi-zone Units
over the Administration Office in Area B.
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
packaged DX, these units are not highly energy
efficient. However, the areas they service are
broken into many individual temperature control
zones, allowing the system to modulate its
capacity to provide a fairly high level of occupant
comfort control.
2.4.6.2 Condition: The rooftop multizone air handling units have one year of remaining rated useful
life. The maintenance staff has stated that these rooftop units have been experiencing
problems with the condenser fans.
2.4.6.3 Efficiency: We were not able to ascertain the specific KW per ton energy efficiency;
however the scheduled full load amps of these units in comparison with the rated cooling
capacity is higher than expected for packaged rooftop equipment. Given that packaged DX
system are generally not highly efficient, these units should be considered relatively
inefficient.
2.4.6.4 Recommendation: The area serviced by these multizone units should be retrofitted with a
highly efficient HVAC system in coordination with an overall building HVAC retrofit.
2.4.7 Packaged Rooftop Constant Volume
2.4.7.1 Description: Two science classrooms in Area E
are conditioned by dedicated packaged rooftop
DX air conditioning units with duct mounted hot
water heating coils (one unit per classroom).
Each unit is controlled by a space thermostat.
The units do not have a means to modulate their
cooling capacity at partial cooling load conditions
other than cycling the compressor on/off. This
results in high indoor relative humidities at
partial cooling load conditions.
2.4.7.2 Condition: The units were installed in 1997 and
have two years of remaining service life of their
15 year rated useful life. One of the two units
was inoperable at the time of the building
inspection.
Science Classroom Area Packaged Rooftop
Units
2.4.7.3 Efficiency: The packaged DX cooling system is
inefficient.
2.4.7.4 Recommendation:
These units should be
removed and the classrooms should be provided
with a highly efficient educational grade HVAC
system as part of a total building HVAC retrofit.
Page 33 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
2.4.8 Split Systems
2.4.8.1 Description: The building is provided with a
variety of split DX cooling systems, primarily
located in the Science classrooms of Area E.
These include: ceiling concealed indoor, vertical
indoor unit ventilator, and horizontal console unit
ventilator units, each with a paired outdoor
condensing unit. Similar to other DX cooling
units, these are relatively inefficient systems with
have difficulty maintaining indoor relatively
target levels at partial cooling load conditions.
Ceiling Mounted Split System Indoor Unit
2.4.8.2 Condition: The units were installed in 1997 and
have two years of remaining service life of their
15 year rated useful life. The systems were in
various states of operating conditions during our
walk though, with one vertical unit spilling
condensate on the floor. Many of the classrooms
serviced by these units were particularly humid
and had buckling ceiling tiles.
2.4.8.3 Efficiency: The packaged DX cooling systems
are inefficient.
2.4.8.4 Recommendation:
These units should be
removed and the classrooms should be provided
with a highly efficient educational grade HVAC
system as part of a total building HVAC retrofit.
Split System Vertical Indoor Unit in Science
Classroom. Note the Damage to the Floor
Tile from Repeated Condensate Drainage
Failures.
2.4.9 Window Air Conditioners
Several areas of the building have been
retrofitted with window air conditioning units.
These are inappropriate for an institutional
building, are noisy, inefficient, and should be
removed. These areas should be provided with
an appropriate educational grade HVAC system.
Window Air Conditioning Units in the Dance
Studio
Page 34 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
2.4.10 Hydronic Terminal Heating
2.4.10.1 Description: The building is provided with a
variety of different hydronic terminal heating
units from the original construction of 1957
and 1971. While the majority of the original
1957 hydronic fin tube heating units have been
removed, some other types of units remain.
The remaining unit types from these two
construction periods include: hot water unit
heaters, cabinet unit heaters, and convectors.
2.4.10.2 Condition: Our inspection was conducted
during the summer so we do not have first
hand information on the operating condition of
this equipment. The maintenance personal did
not report any specific system wide problems
with this type of equipment. All of these units
exceeded their rated useful service life decades
ago.
2.4.10.3 Efficiency:
The efficiency of the actual
terminal units depend on the cleanliness of the
heat exchanger; which should be considered
somewhat as it is expected that internal
surfaces of the heat exchanger are coated with
mineral deposits thus diminishing the heat
transfer capacity of the unit. The system
efficiency is also driven by the combustion
efficiency of the boilers.
A Typical Fin Tube Element with End
Removed.
2.4.10.4 Recommendation:
The units should be
replaced under a full building HVAC retrofit.
Fin Tube Heating in a Classroom.
A Hot Water Unit Heater in an Industrial Arts
Classroom.
A wall convector.
Page 35 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
2.4.11 Heating Ventilating Units
2.4.11.1
Description: The main gymnasium and the mini-gym are conditioned by central station
type heating ventilating units, capable of providing 100% outside air for summer time
ventilation, and mixing return air with outside air for heating season service. Each unit is
provided with a hot water heating water coil, mixing box, and filter bank. These units are
original to the 1957 and 1971 construction and are currently 53 and 39 years old;
dramatically exceeding their rated useful service lives of 25 years. These units do not
provide air conditioning service. While this is typical for many public school gymnasiums,
the mechanical supply of un-dehumidified air into the gymnasiums, which are interior to
the building's vapor barrier envelope, introduces a very large dehumidification load onto
the adjacent air conditioned spaces.
2.4.11.2
Condition: The units are operating but appear to be worn.
2.4.11.3
Efficiency: The motor efficiencies are low compared with modern premium efficiency
motors.
2.4.11.4
Recommendation: Replace these units and consider air conditioning the spaces as a
means to aid in maintaining the overall school relative humidity level.
2.4.12 Ventilation & Exhaust Systems
2.4.12.1
Description: The building uses a distributed ventilation and exhaust approach utilizing
approximately 78 individual exhaust fans; nearly all of which appear to be original to the
1957 and 1971 construction. Ten fans were replaced in 1980. The fans range in age
from 53 to 30 years old.
The most typical ventilation method for the classroom areas is that outdoor ventilation
air is introduced into the building via the classroom incremental units and is transferred
into the corridors where it migrates to exhaust air intake locations, many of these being
exhaust registers in the corridor ceilings. Although this was a common ventilation
method at the time the building was originally constructed, this arrangement poses a
significant life safety threat since the system could mechanically force smoke from a
classroom fire into the means of egress. This air transfer method is not allowed by
modern building codes and should be discontinued.
The building also uses roof gravity ventilators for what appear to be both intake and
pressure relief service.
The crawl space under the first floor is provided with several side wall brick vents for air
inlets and several open end vertical ducts terminating at the roof level with gravity
ventilators for air discharge.
2.4.12.2
Condition: The general duty exhaust fans are all long past their rated useful life and are
in various states of physical condition. The Art Room kiln exhaust hood is too small to
Page 36 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
cover all three kilns. The brick vents inlets are in various conditions. The crawl space is
very humid. The gravity vents appear to be in working order.
The general configuration of the ventilation system for the typical classrooms poses a life
safety hazard. The stage exceeds 1,000 square feet in area and is required to be
provided with an emergency ventilation system for smoke control (which is missing).
2.4.12.3
Efficiency: This is a passive ventilation system which does not consume energy.
However, there does not appear to be insulation under the floor, thus the ventilation
system induces a heat transfer load on the building.
2.4.12.4
Recommendation: Nearly all exhaust fans should be replaced. A replacement kiln
exhaust hood should be provided of adequate size to cover all three kilns. The brick
vents inlets are in various conditions; these should be replaced as a whole grouping with
heavy duty vents to provide several decades of continued use. The crawl space is very
humid. The gravity vents could remain in place; consideration should be given to
replacing some roof terminals with power roof ventilator type fans to increase the
ventilation in the crawl space. A radon test should be conducted to determine of the
earth is releasing radon gas into the crawl space. The general ventilation system
configuration poses a life safety concern and should be changed. In addition, a
Dedicated Outside Air System (DOAS) should be incorporated to decouple the treatment
of outside air from space conditioning since there is no relationship between these
functions and it is the primary reason for poor indoor air quality). Provide a stage
emergency ventilation system as required by code.
2.4.13 Kitchen Exhaust & Make-up
2.4.13.1
Description: The kitchen is provided with a gas fired make-up air unit and an upblast
grease exhaust type exhaust fan. These units are provided with basic operational
functioning controls. The system is not provided with the heat sensing controls to
automatically energize the exhaust fan when cooking operations occur as is required by
current code.
2.4.13.2
Condition: The units were installed in 2002 and are in good condition. The make-up air
unit has seven years of remaining rated useful life and the upblast exhaust fan has 12
years of remaining rated life.
2.4.13.3
Efficiency: The motor efficiencies are unknown. The gas fired heater is a conventional
80% efficient type, not a high efficiency condensing type unit.
2.4.13.4
Recommendation: This system should remain in place, but be retrofitted with code
compliant controls.
Page 37 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
EXISTING CONDITIONS
2.5
Electrical Systems
2.5.1 Power
Power Distribution:
Electrical service for the building is provided via several
services in different sections of the building. The main service
is provided via a secondary substation located in a vault next
to the boiler room. The power generation company is ‘PEPCO
Energy Services’ and the power distribution company is ‘BGE’.
According to BGE, total of 3 meters/electric services/accounts
exist in the building. Voltage systems used in the building
are 480Y/277V and 208Y/120V. There is a switchboard with
capacity of 3000A located next to the vault in boiler room
area for the main electric service.
Electrical power throughout the building is distributed via high
voltage and low voltage branch panelboards and dry-type
transformers located in several electrical rooms/closets in
different part of the building. Most of the existing
panelboards/equips seems in a good condition and working
properly. Existing main switchboard in main electric room and
some panelboards are old and have a poor condition.
Power Company pole
Primary service.
Emergency power for building is provided by a 15 KW
generator. The existing generator feeds emergency loads
(mostly lighting) in the building. The unit is located inside the
chiller room.
Uninterruptible power for data racks/equipment in server
rooms are provided by multiple small capacity UPS units in
each location.
Electrical panel board
Page 38 of 112
Electrical panel board
Main Switchboard
Electrical panel board
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
Interior Lighting:
The lighting systems throughout the building are based upon
the original designs. Most of the fixtures are old. The
additions, which were constructed at different times, vary in
lighting design style and fixture selections. The most recent
addition has a design approach which eliminates the
traditional ceiling, paints the underside of the deck above
black, and suspends troffers or pendant fixtures (depending
on the space). There has been some recent luminaire retrofit
activity in which the older T-12 fluorescent lamps and
magnetic ballasts have been replaced by T-8 lamps and
electronic ballasts. Following are the lighting conditions for
some of the areas:

Corridors: mostly 2X4 recessed fixtures with
fluorescent lamps are used. Many of these fixtures
have been retrofitted with the T-8 lamps and
electronic ballasts. These fixtures seem to be in a
good condition.

Classrooms: different fixtures are used. In most
classrooms fixtures are 1X4 surface mounted with
fluorescent lamps. Light fixtures in most of
classrooms are old and are not in a good condition.

Science Labs Addition: Fixtures in this part are
mostly1x4 and 2X4 with fluorescent lamps. This part
of building was renovated recently and light fixtures
in these areas seem in fair condition.

Ceiling Light Fixtures
Ceiling Light Fixtures
Auditorium Lighting
Auditorium: Different down light fixtures and also
fluorescent fixtures are used in this area. Stage
lighting is provided by projector fixtures. Some
projectors are used in audience area. There is a
dimming system to control lighting in auditorium.
Emergency Lighting and Exit Lights:
Auditorium Lighting
Emergency lighting in different parts of the building are
provided by wall mounted double-head battery pack fixtures
or ceiling fixtures with battery ballasts. Most of recently
renovated areas have ceiling fixtures with battery ballasts for
emergency lighting.
Exit Sign
Page 39 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
The existing exit lights throughout the building differ in
appearance and lamping depending upon the age of the
given area of the building and whether the fixture is original
or has been replaced. Generally they are single or double
faced, green LED fixtures. The condition of these fixtures in
renovated areas seems fair.
Power for emergency lighting as part of critical loads is
provided by the existing emergency generator.
Exterior Lighting:
Driveway Lighting
Lighting for parking lots and driveways on the site is provided
by exterior fixtures with HID lamps. Fixtures for Parking lot
areas are mounted on high poles with single or double arms.
Lighting in regular driveways is provided by fixtures with
reflector and lens mounted on top of shorter poles. Some
light fixtures and poles are not in a good condition. It seems
the exterior lighting is controlled via time switch.
2.5.2 Fire Alarm System
Parking Lot Lighting
Existing System:
Building has a conventional fire alarm system with multiple
control panels from manufacturers such as Simplex and
Notifier. Fire alarm control panels are located in different part
of the building. There are 2 main fire alarm annunciator
panels (FAAP) which are located in front of reception area in
the entrance lobby. Both have graphic faceplates showing
building floor plans.
Initiation Devices:
Fire Alarm Control Panel
Fire alarm Pull boxes provided at exit doors. Smoke detectors
installed in some areas of corridors and some classrooms. No
smoke detector provided in front of elevator door, elevator
machine room. Many classrooms even without sprinkler
system have no smoke detector. Pull stations in some
locations are not ADA compliant. They’re installed too high.
Smoke Detector
Page 40 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
Notification Appliances:
Strobes, horns and alarm bells are installed in corridors and
media center. There are no notification devices in classrooms,
bathrooms electric and server rooms. In term of installation,
notification devices in most locations are not ADA compliant.
Audio/Visual Notification
Device
Fire Alarm Control Panel
Fire Alarm Control Panel
Fire Alarm Graphic Annunciator
2.5.3 Public Address System
There is an existing public address (PA) / intercommunication
system in school. Existing PA system has been renovated in
recent years. Existing system includes central control by
TELECOR II, ceiling speakers mostly in corridors, media
center and cafeteria and wall speakers in classrooms and
gymnasium. Call stations are provided in all classrooms. Wall
mounted volume control switches are installed mostly in
office areas. Existing PA system seems generally in fair
condition. Protection cover on some speakers in gymnasium
is broken. Speakers in classrooms are not in a good condition.
PA System Main Control
2.5.4 Data & Wireless Systems
There are 2 server rooms in school. Each includes data racks
and wireless devices. Small size UPS units are provided to
feed data equipment. Data outlets are provided in
classrooms, most of offices and media center. As part of
science lab addition, complete data network is installed for all
locations in this part of building. Air conditioning systems in
both existing server rooms are not working properly.
Server Room
Page 41 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
2.5.5 Security System
There is an existing security system in school. Existing
security system includes security control panel, security
cameras, motion sensors and other initiation and notification
devices. For outdoor security, wall mounted cameras are
installed outside the building. Also security lighting via wall
mounted outdoor type light fixtures with HID lamps is
provided at the perimeter walls of the building. Inside the
building motion detectors are provided mostly in corridors.
Other security devices are provided in other locations
throughout the building. Security system coverage
throughout the building and system operation needs to be
verified.
Security Lighting
Motion Sensor
Security Camera
2.5.6 Grounding and Lightning Protection System
Existing grounding system includes main building grounding
electrodes, main grounding terminal and ground terminals in
several locations in the building. It appears grounding
conductors and bonding are provided for all panelboards and
equipment.
Existing lightning protection system consists of air terminals
at the roof around the building and related bonded copper
conductors. While the air terminals and bonding to copper
conductors at the roof is visible from grade, the balance of Lightning Protection Air Terminal
the system is concealed. Normally the conductors are
connected to the ground via grounding electrodes.
Regarding the age of the system, complete verification of
both systems including all devices and connections necessary
tests and measurement seems necessary.
Page 42 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
EXISTING CONDITIONS
2.6
Plumbing Systems
The building is served by the County water system. The existing 8" water main enters the
front of the site through a meter vault and distributes to two hydrants at the front of the
building. The sprinkler service enters the front of the building at the west end of the
administration wing where an existing water room is located.
The domestic hot water is generated by circulating heating water from the boilers though
tubes of a shell and tube heat exchanger which heats water in the shell of the heat
exchanger. The domestic hot water is drawn out of a large horizontal storage tank through the shell - and back to the tank by in-line circulator pumps. The tank is insulated
and we were not able to locate a nameplate with a size; however, we estimate that the tank
stores approximately 2,500 gallons. The age and capacity of the system is unknown (it was
not documented on the available materials). Natural gas fired water heaters were added in
parallel during the renovation of the science wing in 1997; thus allowing the boilers to be
shut down at the end of the heating season. This installation does not meet current code
requirements. The equipment needs to be modified or replaced and appropriate tempering
valves added to provide tepid water.
Plumbing fixtures all appear to be original or dated and beyond their useful life. The water
closets are floor-mounted, urinals are floor and wall-mounted, and lavatories are individual
wall hung type. Plumbing fixtures no longer meet code requirements for water usage and
are not properly configured for ADA accessibility.
The building has a crawl space throughout, which accommodates accessibility to distribution
and drainage piping for repair, inspection, and replacement. The existing exposed piping in
the crawl spaces can be inspected to determine its condition, allowing significant savings if it
is determined that the piping is in fair to good condition. Since this piping is accessible, a
decision to delay replacement even if only for 5-10 years is not critical because this piping
can be easily replaced. Based on the age of the original building and additions, the existing
water distribution system should be tested for lead content. If tests conclude that lead is
present in unacceptable levels, then the distribution system should be replaced in its
entirety.
Due to the age of the installed plumbing lines, it will be necessary to cut out sections of
sanitary, domestic cold and domestic hot water lines in several locations in the subbasement, and inspect this piping for scale and/or corrosion. The inspection results will
contribute to deciding the scope of piping replacement required during a building
renovation/modernization program.
Minimum recommended actions include:
1.
Replace all domestic water, sanitary and storm piping located outside of existing
crawl spaces.
2.
Replace all plumbing fixtures. New plumbing fixtures will be installed with provisions
for ADA accessibility.
Page 43 of 112
Severna Park High School
Severna Park, Maryland
3.
4.
2.7
Feasibility Study
GWWO, Inc./Architects
The existing sanitary and storm water piping within the crawl space will be utilized
where deemed possible. All risers and branches to new fixture layouts will be new
piping.
New modular high efficiency gas-fired water heaters should be installed. This
domestic water heating system will serve the entire building and will be equipped
with hot water circulators, expansion tank, and tempering valves as required.
Fire Protection System
The building currently is not protected by a full coverage fire sprinkler system. The media
wing and portions of the existing administration wing are protected with automatic fire
sprinklers. If the school is revitalized, modernized, or replaced, a full coverage sprinkler
system will need to be installed in order for the building to be code compliant. The existing
water service is adequate for flow to supply a sprinkler system; however, a fire pump will
need to be added to boost the pressure for distribution to the extremities of the building. An
alternative to the fire pump may be to feed the site from another section of the grid which
would divide the flow and thereby increase pressure available by reducing pressure drop to
the site during flow conditions. This option should be evaluated by the civil engineer for
feasibility.
Recommended minimum actions include:
1.
Provide a fire pump to boost pressure to the building. The sprinkler service and all
zone valves will be located in a new fire pump room.
2.
Extend systems to all parts of the building for a fully sprinklered facility in
accordance with all applicable NFPA standards. Multiple sprinkler zones will be
provided for the building.
3.
The sprinkler system will be hydraulically designed to minimize pipe size
requirements and to provide an economical distribution system for the building.
Page 44 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
CODE ANALYSIS
Accessibility Evaluation:
The existing school is generally accessible in that an accessible ramp at the main entry permits
public access into the school and an elevator installed with the 1971 addition makes the second floor
generally accessible. It was noted that the public entrance to gymnasium is not accessible as there
are exterior steps and no accessible ramp.
A general examination of the existing school found the following areas to be deficient. All must be
further reviewed and addressed during the schematic design phase of this project:
 Accessible entry and exits to and from the school must be added.
 Toilet rooms and stalls must be made accessible, including all plumbing equipment.
 Required clearances at some doors may not be adequate for accessibility.
 Door hardware must generally be replaced with accessible door hardware.
 Height of all pull stations, switches and signage does not comply, and must be fixed.
 Classroom and other public space entries must be reviewed for ADA compliance.
 All egress door swings and clearances must be reviewed and brought into compliance.
 Door closers must be tested, so that force required to open doors is compliant.
 Assistive listening devices will be required in public spaces.
 ADA compliant signage will be required.
Building/Life Safety Code Evaluations:
The existing school is a mixture of concrete masonry bearing wall and steel frame construction types
totaling 296,191 GSF. Only a portion of the building is currently sprinklered. These areas include the
1971 additions of the media center and administration offices. The building can be classified as Type
2C (non-combustible/unprotected) construction in accordance with the 2006 IBC code. The
occupancy classification is Mixed Use, including Educational and Assembly type occupancies. Both of
these classifications must be confirmed with the Anne Arundel County code officials during
schematic design if the Board of Education selects to move forward with either Revitalization or
Modernization.
The existing school is currently non-compliant in terms of area allowed. In the options including
Code Upgrade work, an automatic fire sprinkler system would be added. This will result in the
allowable area limitation being increased. However, given the size of the existing building and the
additions proposed in both the Revitalization and Modernization options, the building will still exceed
the increased area limitations requiring the building be divided into separate fire areas. The
additions will have to be separated from the existing building with a fire wall, making them entirely
separate buildings from a code standpoint.
Special considerations should be given to the following code concerns in future phases:
 The fire alarm system will require upgrading to interface with the new addition(s).
 Assembly uses shall be properly separated from Educational uses.
 Existing Hazardous Materials must be abated.
 Sprinkler system must be installed.
 Fire alarm must be upgraded. Any new fire alarm with the addition must be tied into the
existing system, or the existing system must be replaced.
 Smoke barriers must be installed between the corridors and other spaces.
 A paved fire lane must be installed around the perimeter of the building to enable fire
truck access.
Page 45 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
This page intentionally left blank.
Page 46 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION A: DO NOTHING
Assessment
This is the no-cost option of doing nothing to the existing facility. This option establishes a base line
for comparison to other schemes.
Advantages:
1. School operations will not be disrupted since there will be no construction activities.
Disadvantages:
1. Spatial requirements set forth in the Educational Specifications will not be met by the
existing building.
2. The existing building does not meet current life safety and building codes.
3. The existing building will remain inefficient with regard to energy and water consumption.
4. Maintenance items which have been deferred will remain deferred.
5. Costs will be incurred in the near future to replace many building systems that are reaching,
or are beyond their rated useful lives.
6. Congestion will continue to be an issue in the main corridor during lunch periods and at
dismissal.
7. Bus traffic and parent drop off traffic will remain in conflict.
Page 47 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION B: PATCH AND PAINT
ASSESSMENT
This option provides for a minimal repair and painting of the existing facility, incorporating minor
repairs to systems and construction to provide continuing service for the foreseeable future. No
significant changes to the existing structure will be made to conform to the proposed Educational
Specification or to address building and life safety concerns.
Advantages:
1. Most of this work will be completed during summer break and after hours so school operations
will be minimally disrupted.
2. Deferred maintenance items will be prioritized and completed as the budget allows.
3. Exterior brick veneer will be repaired.
4. Interior finishes will be repaired and in some cases replaced.
5. There is no loss of use of the existing stadium and play fields.
Disadvantages:
1. The existing facility falls short of meeting the program, area, and adjacency requirements of the
Educational Specifications.
2. Indoor air quality and comfort will remain inadequate as the existing distribution system will not
be upgraded to meet current standards.
3. Existing window systems will remain and continue to provide only minimal amounts of daylight
in the classrooms
4. Exterior walls will remain uninsulated, thus the thermal performance will continue to be poor in
relation to a new facility and energy consumption will not be improved.
5. Accessibility, building, and life safety code upgrades will not occur. The majority of the building
will remain unprotected by an automatic fire sprinkler system.
6. Costs will be incurred in the near future to replace many building systems that are reaching, or
are beyond their rated useful lives.
ANTICIPATED SCOPE OF WORK
Architectural – Interior
 Existing interior wall finishes will be repaired and painted.
 Floor finishes will be changed out in those spaces where the Educational Specifications call
for a different finish than exists in a space.
 All acoustical ceiling panels will be replaced and the existing suspended metal grid system
will be repainted.
 Interior doors will be refinished. Existing hardware will be repaired where possible. In some
instances, hardware may be replaced.
 Casework in classrooms and offices will be repaired as required.
 Science classroom equipment and fixtures will be replaced as required.
Page 48 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects Severna Park, Maryland
OPTION B: PATCH AND PAINT
EXISTING SITE PLAN
6 LANE
TRACK
STADIUM
FIELD
TENNIS
COURTS
PLAY
FIELD #1
PLAY
FIELD #2
PLAY
FIELD #3
BASEBALL
SOFTBALL
SEATING:
1,664 HOME
756 VISITORS
FIELD
HOUSE
PLAY
FIELD #4
STUDENT
PARKING
MEDIA
CENTER
GYMNASIUM
STAFF
PARKING/
BUS
STACKING
AUDITORIUM
CAFETERIA
SIGNALIZED INTERSECTION
B-BALL
STUDENT COURTS
PARKING
STAFF &
VISITOR
PARKING/
PARENT
DROP OFF/
BUS
STACKING
BUS STACKING
MAIN ENTRY DRIVE
PLAY
FIELD #5
Severna Park High School
Severna Park, Maryland
OPTION B: PATCH AND PAINT
EXISTING FIRST FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION B: PATCH AND PAINT
EXISTING SECOND FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION B: PATCH AND PAINT
Architectural – Exterior
 Only those areas of the roof which require repair will be repaired.
 The existing brick veneer and cast stone sills will be repaired and re-pointed where required.
 Severely corroded doors and frames will be replaced. All doors and frames will be repainted.
 Windows, doors, and masonry expansion joints will be resealed.
Site

No significant changes will occur.
Structural
 Existing to remain.
HVAC
 Existing to remain; though as noted previously in this report, many system components are
approaching or have surpassed their rated useful life and will need to be replaced in the
near future.
Plumbing
 Existing to remain; though as noted previously in this report, many system components are
approaching or have surpassed their rated useful life and will need to be replaced in the
near future.
Fire Protection System
 The building will remain only partially protected by an automatic sprinkler system.
Electrical
 Existing to remain.
Fire Alarm System
 Existing to remain.
Intercom and Sound System
 Existing to remain.
Voice, Data and Video Systems
 Existing to remain.
Security System
 Existing to remain.
Page 49 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
ASSESSMENT
Revitalization of the existing building will reuse most of the existing building though portions will be
demolished to accommodate new additions that are required to meet programmatic requirements of
the Educational Specifications. Spaces within the additions will meet the area requirements of the
Educational Specifications, but rooms in the existing building will not be structurally modified.
Therefore, most classrooms will continue to be either over or under their specified area.
Advantages:
1.
2.
3.
4.
5.
6.
7.
Program areas are grouped by program/department.
Existing courtyards are kept; two new ones are created.
Stadium remains in existing location.
Existing fields remain in current locations; act as a good buffer.
No further impact on the surrounding neighborhoods.
The facility will meet the EdSpec program requirements, but not all area requirements.
The facility will comply with current building, life safety, and accessibility codes and
standards.
8. Interior circulation is improved through the addition of cross halls and multiple entrances to
the cafeteria.
9. Energy efficient electrical and mechanical systems will be installed in the existing building.
10. Site safety and circulation are improved by separating bus queuing and parent drop off
traffic.
Disadvantages:
1. Multiple phases of construction.
2. Construction staging area must be relocated for phases 3 and 4 with limited staging and
construction parking.
3. Building is occupied during construction activities.
4. Minimum of sixteen relocatable classrooms are needed during construction.
5. Only spaces in the new additions will meet Ed Spec area requirements since there won’t be
structural modifications made to spaces in the existing building.
6. Distance between departments can be great since the building is spread out.
7. Possibility that stadium will not be able to be used for athletic events during the first two
phases of construction.
8. No student parking on site for duration of construction.
9. There will be one less play field than currently exists.
10. Entrance drives for buses and cars are not separated.
11. Narrow hallways in the existing building will remain.
12. Programs and students will be relocated a minimum of two times to facilitate renovations.
13. Daylighting will not be increased in existing classrooms as windows will be replaced in
existing openings.
14. Track will remain only six lanes wide.
15. Limited school activities after hours due to construction.
16. No outside agency use (Parks & Rec) of building during duration of construction.
17. No evening high school.
18. No summer school.
Page 50 of 112
Severna Park High School
Severna Park, Maryland
OPTION C: REVITALIZATION
SITE PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION C: REVITALIZATION
FIRST FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION C: REVITALIZATION
SECOND FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
ANTICIPATED SCOPE OF WORK
Architectural – Interior










Spaces in all additions will be designed to meet the Educational Specifications.
Spaces in the existing building will not be reconfigured as interior walls will remain in place.
Therefore, many of the existing spaces will not comply with the Educational Specifications.
Existing finishes will be upgraded in accordance with the Educational Specifications.
All floor tile, base, ceiling panels, suspended grids, and ceramic tile will be replaced.
All casework will be replaced and redesigned to meet the Educational Specifications.
Interior doors, frames, and hardware will be replaced to meet accessibility requirements.
Existing terrazzo flooring will be maintained.
Lockers will be replaced in accordance with the Educational Specifications.
The existing elevator will be upgraded to meet current codes.
Three sections of the existing building which include the gymnasium, physical education,
food services, music, auditorium, and technology education program spaces will be
demolished to accommodate new additions.
Architectural – Exterior




Site









Failing window sills will be replaced.
Brick will be re-pointed where required and replaced where new flashing is required.
Existing windows and exterior doors will be replaced within existing window openings.
Areas of the existing roof will be repaired.
New bus staging loop capable of supporting 26 buses to be constructed at the front of the
school to allow for the separation of the bus and vehicular traffic.
Reconfiguration of the existing faculty/visitor parking lot. A large portion (approximately
27,000 SF) of the parking lot will be removed to accommodate the new food services wing.
New paved surface will be constructed in the location of the existing auditorium wing. This
paved area will serve as a new designated student drop off as well as to provide visitor
parking.
A new service yard area will be constructed adjacent to the new food services wing.
A 20’ wide paved fire lane will be constructed to connect the staff/visitor parking lot with the
student parking lot and also provide emergency vehicle access to the grassed multi-purpose
fields.
The student parking area will be expanded to accommodate the parking lost for the
construction of the food services wing.
Milling and resurfacing of all existing paved services.
Removal of approximately 500 LF of various sized (15” to 27”) storm drain lines, and
approximately 450 LF of 8” sanitary sewer around the existing gymnasium.
Relocation of the school’s 3” gas service.
Removal of approximately 17,000 SF of concrete sidewalk around the existing gymnasium.
Page 51 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
Site - continued



New concrete sidewalks throughout. Ten foot (10’) wide walks will be constructed along the
front of the school and new bus staging loop, five foot (5’) walks will be constructed around
the perimeter of the remainder of the new construction to allow for pedestrian access
around the campus.
Moderate grading for all construction.
Five areas have been identified to construct underground infiltration trenches and four
additional areas have been identified for micro bio-retention areas. The underground
trenches range in size from 2,040 SF to 8,800 SF. The areas identified are under the
parking adjacent to the new food services wing, behind the existing classroom wing and
adjacent to the new physical education wing. The micro-bio-retention areas range from
approximately 1,500 SF to 2,500 SF and are located along the frontage of the site between
Robinson Road and the new bus staging loop and between Benfield Road and the existing
student parking area.
Structural
Existing building:










Minor repairs as required.
Modify roof and floor framing and provide additional foundation for new fire walls.
Modify and reinforce existing structure for new mechanical units and related work.
Modify and reinforce existing structure for new clerestory at the roof level above the existing
Media center.
New exterior elevator masonry shaft with foundation at upgraded elevator.
Roof structure capacity will be assessed for new roof top mechanical equipment.
Additional structural work will be required to accommodate the anticipated mechanical,
electrical and other upgrades.
Reinforcing of isolated structural elements may be required.
New roof openings will likely need to be framed for new roof penetrations.
Existing abandoned roof penetrations will be patched.
Auditorium, Gymnasium, Physical Education, Tech Ed and Lab, Cafeteria and Kitchen additions:






Tech Ed and Lab addition will be a two story. All other additions will be a single story.
Load bearing CMU walls with structural steel framed structure.
The roof structure at the Auditorium and Gymnasium will consist of long span open web
steel joists at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck or Tectum
deck.
The roof structure at all other areas will consist open web K-series steel joists at 5’-0” on
center with 1-1/2”, 22 gage, galvanized metal roof deck.
The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists
at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck.
Masonry walls at the auditorium and gymnasium will be a load bearing 12” thick reinforced
CMU.
Page 52 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
Structural - continued









Walls less than 18’-0” tall can be 8” thick reinforced CMU.
Second floor construction at the lab addition will consist of 3”concrete on a form deck
supported by open web joists at 24” to 36” on center. This floor structure will be supported
by load bearing masonry walls.
Steel beams and columns will be provided as required by the architectural layout.
The new additions will abut the existing building, which have a framed first floor with a crawl
space. The existing finished floor elevation is close to the exterior grade.
A geotechnical investigation will be conducted during the design phase to determine
foundation recommendations.
If a slab on grade is feasible from a geotechnical standpoint, then a 5” concrete slab on
grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost
effective compared to a framed structure with a crawl space.
However, if the recommendations of the geotechnical report indicate that a slab on grade is
not feasible, and a framed first floor structure be required, 8” precast concrete plank with a
2” lightweight concrete topping slab supported by masonry bearing walls in the crawl space
is a viable option.
Additional deeper foundation walls will likely be required at the juncture of the additions with
the existing to “close off” existing crawl spaces from the backfill.
We anticipate a shallow spread footing foundation system, consistent with the existing
building, will be appropriate. However, this must be confirmed by a geotechnical
investigation.
Mechanical
A. General Overview
The mechanical systems will be designed in compliance with DGS and all industry standards
essentially replacing the entire HVAC system as a means to: bring the system up to current
standards, increase system efficiency, address the user's needs for the next 20+ years, and
improve sustainability. The overall goals of the system retrofit are: provide good indoor air
quality, to be highly energy efficient, to be easily maintainable, to have low first cost as well
as low life cycle costs, and to be cognizant of project construction budget limitations. The
system we are recommending is Active Chilled Beams supplied from Dedicated Outside Air
Systems (DOAS) with a Central Geothermal Water to Water Heat Pump Plant.
B. Ventilation System
The first major component of the proposed overall HVAC system is the Dedicated Outside Air
System (DOAS) which delivers code required outside air directly to the room level. The
purpose of the dedicated ventilation system is to decouple the conditioning of outside air
used for ventilation from the conditioning of room air. The primary advantage of the
decoupling is that the outside air can be properly dehumidified regardless of the sensible
cooling load of the space, assuring improved room relative humidity levels during space
partial cooling load conditions. The use of the DOAS also reduces the operating cost by only
Page 53 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
Mechanical – continued
requiring the conditioning of the quantity of outside air required to meet the sum of all space
ventilation loads.
C. Overhead Active Chilled Beams
The chilled beam provides heating or cooling on demand on a room by room basis. The unit
has no fan; it uses the induction air principal, driven by ventilation air, to cause 3 to 4 times
the air flow rate of the DOAS ventilation air to be drawn up through the perforated panel in
the center of the chilled beam – across the terminal unit coil – and be discharged with the
DOAS ventilation air out the two linear slot diffusers on the perimeter of the chilled beam.
The hydronic arrangement of the system is four pipe. The chilled beams use the return
chilled water from the DOAS unit.
D. Central Geothermal Water to Water Heat Pump Plant
The main component is a modular water to water heat pump which uses multiple nominal
thirty to seventy ton modules. Each module is an independently controlled (staged) heat
pump capable of producing chilled and hot water. The modular unit as a whole can produce
chilled and heating water simultaneously. The source side of the modular unit is piped to a
geothermal well field which provides a heat source/sink.
E. System Equipment
The system is comprised of:
1. A modular geothermal grade water to water heat pump unit with VME valving using
fifteen 70 ton modules. Basis of design: Multistack
2. Two variable volume frame mounted end suction geothermal well field water pumps with
variable frequency drives.
3. Two variable volume frame mounted end suction heating water pumps with variable
frequency drives. 50 HP
4. Two variable volume frame mounted end suction chilled water pumps with variable
frequency drives, 1,700 GPM, 100 HP.
5. One geothermal well field with approximately 180 wells using a depth of 600 feet, using
1-1/4" SDR-9 in the vertical bore hole and SDR-11 or 15 piping for the horizontals. Wells
to be grouted with high conductivity (1.2) bentonite grout. 3,150 GPM, 100 HP
6. Five 20,000 CFM ERU’s for the DOAS
7. Five 7,500 CFM large space AHU's,
8. Fan coil units for the entry areas (areas subject to very high infiltration loads).
9. A chilled beam(s) for each remaining occupied room. A typical classroom for 30 students
would take three six foot chilled beams.
10. Heating water convectors or hot water unit heaters for restrooms and utility spaces.
11. A DDC Building Management System.
12. Some miscellaneous utility fans (propeller and cabinet type).
Page 54 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
Mechanical – continued
F. Advantages
Some of the advantages of the chilled beam and modular water to water geothermal heat
pump system include the following:
1. Superior indoor air quality due to:
a. Excellent cooling season relative humidity control.
b. The high ventilation effectiveness due to the characteristics of the induction air
method.
2. The highest degree of zoning with essentially every occupied space being provided with
individual temperature control.
3. Space by space heating or cooling on demand.
4. A reduction in ductwork when compared with a VAV system or ducted water source heat
pump system with DOAS.
5. Very high operating efficiency.
a. Mass energy storage over time for reuse in the building.
b. High efficiency heating and cooling plant at design temperatures (COP = 4+,
EER = 14+). These improve dramatically at partial load conditions due to the
geothermal characteristics.
c. An efficiency improvement from the increased chilled water temperature
difference.
6. While the four pipe system arrangement requires a second piping network inside the
building, the delta Tee of both systems is greater than 500% larger than the first three
options minimizing the cost impact of the additional piping.
7. First cost and maintenance cost savings from the consolidation of all heating and cooling
plant equipment into a single unit. This includes:
a. Savings from centralized compressor maintenance.
b. Savings from the elimination of 85% of the filter maintenance.
8. A first cost and maintenance cost reduction on the electrical power distribution system
associated with the elimination of a water source heat pump unit for each room. This
eliminates: a branch circuit to each unit, several electrical panel boards, a feeder for
each panel board and a switchboard switch for each feeder. Some cost is added back in
for the circuiting to the modular water to water heat pump and extra pumps, however,
all of those units are located immediately adjacent to the main electrical room.
9. Very low background noise levels due to the elimination of a terminal unit fan.
Plumbing



All existing plumbing fixtures will be removed. New fixtures will be provided. New layouts
and fixture clearances will comply with the Americans with Disabilities Act.
Cold and tempered water will be provided to all lavatories. Hot and cold water will be
provided to all sinks.
Fixtures will be high efficiency, low flow and lowest water usage available at time of design.
Page 55 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
Plumbing – continued





All above ground domestic water, sanitary and storm piping will be removed and new piping
will be provided. The adequacy of the existing domestic water service needs to be verified
according to new layouts, additions, and final fixture count for new design. The entire
domestic water system will be brought into compliance with current codes regarding cross
connection control and metering will be provided in accordance with the requirements of the
local water authority and owner's requirements.
The existing underground sanitary and storm water piping will be utilized where possible;
however, all new piping will be installed above grade in crawlspace due to major changes
planned for toilet partitioning in the building.
The domestic water heating system for the main building will be a central system in the
main boiler room. Separate, dedicated gas fired water heaters will be provided for the
kitchen.
The main domestic water heating system being proposed for use in this building is a
geothermal heat pump system with new double wall heat exchangers and hot water being
stored in the existing storage tank. The existing tank will be cleaned and relined.
The kitchen water heater will be gas fired storage type, direct vented, condensing high
efficiency heater with piped outside air intake.
Fire Protection System


Existing fire sprinkler system will remain and a new system will be installed in all
unsprinklered areas. Extension of the system will require the installation of a fire pump in
order to overcome the friction losses for the greater lengths of piping required.
System will be zoned in accordance with NFPA 13, and each zone will follow the
boundaries of the fire alarm system zones.
Electrical
A. Power Distribution System
Existing power distribution system including panelboards, transformers and related wiring
will be removed and new equipment and wiring will be provided. Also existing wall devices
will be removed and based on requirement, new devices will be installed.
Existing grounding system including all ground conductors, grounding bonds,
connection/connectors, ground rods and terminals will be verified and grounding system
resistance will be measured. In case of any issue in the system, appropriate
correction/modifications will be suggested. In new addition buildings new ground terminals
will be provided for equipment ground connections and panelboards.
Electrical power in new addition buildings specified in this option, such as new Gymnasium,
Auditorium, music and related spaces and cafeteria/kitchen will be distributed via a new
Page 56 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
Electrical – continued
panelboard which will be located in each building. For new portable classrooms, a separate
distribution panel will be specified to feed power box in each classroom trailer. All these
panels will be fed from the existing main distribution panel inside the main electrical room.
Existing demand load in the building will be evaluated and new electrical load will be
calculated for entire school. Based on new load situation, the existing electrical service will
have an upgraded power transformer/substation.
In order to feed loads related to life safety system and other loads which will required standby power a new power generator with two automatic transfer switches, and related
distribution system will be provided.
B. Lighting
All existing lighting fixtures will be removed and new light fixtures will be provided. Based on
new lighting distribution, extra fixtures will be provided as necessary. New lighting control
system will be installed in each location. In order to save energy, occupancy sensors will be
specified for existing spaces to turn off the lights when it is not in use.
Complete new lighting system will be designed for each new addition building. Type of light
fixtures in each space will depend on the application and the character of the space. Light
fixtures with direct/indirect distribution will be used for all classrooms and teaching spaces.
Light fixtures/lamps types, and related controls will be selected such that the system’s
energy saving is as much as possible. Occupancy sensors will be provided for all spaces to
turn off lights when the space is not in use. Day light harvesting system will be specified for
applicable spaces. Light fixtures in gymnasium shall have wire guards. Exit lights and
emergency lighting will be provided for exit entrance and all means of egress. New exit
lights and emergency fixtures shall include battery back-ups. Battery back-up chargers for
these fixtures will be connected to emergency circuits.
Fire Alarm System
The existing fire alarm system will be removed and a new addressable fire alarm system will
be provided to cover entire school including the existing building and new additions. Fire
alarm booster panels/sub-panels will be provided if necessary. New initiation and notification
devices will be provided for all locations. In each space based on the requirement,
notification devices will be audio or visual types or combination of both. In all assembly
areas, voice alarm system will be specified.
Page 57 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION C: REVITALIZATION
Public Address and Sound System
A new public address system will be provided for the entire school including the existing
building and new additions. Ceiling and wall speakers will be installed in different spaces.
Call buttons and volume control devices will be installed as necessary. Special sound systems
will be provided in the gymnasium, auditorium, and music spaces. The new sound system
will include speakers, microphone/jacks and control panels with necessary
components/devices.
Data, Telephone and Intercommunication Systems
New data, telephone, and intercommunication systems located in server rooms/closets will
be provided for entire school. These systems include all servers, wireless communication
devices and UPS units to maintain the operation of servers and other equips without any
interruption in case of power outage.
Security System
New security system will be provided for entire school. New system includes door contacts,
window contacts, motion detectors and security monitoring system with CCTV cameras. This
system will be designed by a security consultant and will be installed under supervision of
school security personnel.
Page 58 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
This page intentionally left blank.
Page 59 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
ASSESSMENT
Modernization will result in a facility that meets the Educational Specifications. It requires a
combination of demolition, renovation, and new construction.
Advantages:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Program areas are grouped by program/department.
Existing courtyards are kept; two new ones are created.
Stadium remains in existing location.
All areas meet all EdSpec requirements.
Existing fields remain in current locations; act as a good buffer.
No further impact on the surrounding neighborhoods.
The facility will comply with current building, life safety, and accessibility codes and
standards.
Interior circulation is improved through the addition of cross halls and multiple entrances to
the cafeteria.
Energy efficiency will be increased with new lighting and mechanical systems installed
throughout the existing building.
Daylighting in existing classrooms will increase as existing window openings will be
increased.
Site safety and circulation are improved by separating bus queuing and parent drop off
traffic.
Disadvantages:
1. Multiple phases of construction.
2. Construction staging area must be relocated for phases 3 and 4 with limited staging and
construction parking.
3. Building is occupied during construction.
4. Minimum of sixteen relocatable classrooms are needed during construction.
5. Distance between departments can be great since the building is spread out.
6. Possibility that stadium will not be able to be used for athletic events during the first two
phases of construction.
7. No student parking on site for duration of construction
8. There will be one less play field than currently exists.
9. Entrance drives for buses and cars are not separated.
10. Narrow hallways in the existing building remain.
11. Programs and students will be relocated a minimum of two times to facilitate major
renovations in the existing building.
12. Longest construction period both overall and within the building in comparison with the
other options.
13. Track will remain only six lanes wide.
14. Limited school activities after hours due to evening construction.
15. No outside agency building use (Parks & Rec) due to evening construction.
16. No evening high school.
17. No summer school.
Page 60 of 112
Severna Park High School
Severna Park, Maryland
OPTION D: MODERNIZATION
SITE PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION D: MODERNIZATION
FIRST FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION D: MODERNIZATION
SECOND FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
ANTICIPATED SCOPE OF WORK
Architectural – Interior









Many interior partitions will be relocated so program areas meet the Educational
Specifications.
All doors and hardware will be replaced and brought into compliance with ADA standards.
Most interior door frames will be replaced.
Existing terrazzo floors will be maintained and repaired.
New acoustical panel ceilings and grids will be installed throughout.
All existing ceramic tile will be replaced.
Lockers will be replaced.
All toilet partitions and accessories will be replaced.
All classroom and office casework will be replaced including science classroom casework.
Interiors within the new additions will comply with AACPS Design Guidelines.
Architectural – Exterior





All exterior windows, doors, and frames will be replaced. New windows will be larger than
the existing to provide more daylight and natural ventilation in classrooms.
Existing deteriorated brick veneer will be either re-pointed, or removed and re-installed.
Roofing systems will be replaced with roof insulation values increased to meet current
energy codes.
Exterior signage will be replaced and updated.
Exteriors of the new additions will be designed to be compatible with the existing building
proportions and materials.
Site








New bus staging loop capable of supporting 26 buses to be constructed at the front of the
school to allow for the separation of the bus and vehicular traffic.
Reconfiguration of the existing faculty/visitor parking lot. A large portion (approximately
27,000 SF) of the parking lot will be removed to accommodate the new food services wing.
New paved surface will be constructed in the location of the existing auditorium wing. This
paved area will serve as a new designated student drop off as well as to provide visitor
parking.
A new service yard area will be constructed adjacent to the new food services wing.
A 20’ wide paved fire lane will be constructed to connect the staff/visitor parking lot with the
student parking lot and also provide emergency vehicle access to the grassed multi-purpose
fields.
The student parking area will be expanded to accommodate the parking lost for the
construction of the food services wing.
Milling and resurfacing of all existing paved services that remains.
Removal of approximately 500 LF of various sized (15” to 27”) storm drain lines, and
approximately 450 LF of 8” sanitary sewer around the existing gymnasium.
Relocation of the school’s 3” gas service.
Page 61 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
Site - continued




Removal of approximately 17,000 SF of concrete sidewalk around the existing gymnasium.
New concrete sidewalks throughout. Ten foot (10’) wide walks will be constructed along the
front of the school and new bus staging loop, five foot (5’) walks will be constructed around
the perimeter of the remainder of the new construction to allow for pedestrian access
around the campus.
Moderate grading for all construction.
Five areas have been identified to construct underground infiltration trenches and four
additional areas have been identified for micro bio-retention areas. The underground
trenches range in size from 2,040 SF to 8,800 SF. The areas identified are under the
parking adjacent to the new food services wing, behind the existing classroom wing and
adjacent to the new physical education wing. The micro-bio-retention areas range from
approximately 1,500 SF to 2,500 SF and are located along the frontage of the site between
Robinson Road and the new bus staging loop and between Benfield Road and the existing
student parking area.
Structural
Existing building:
 Minor repairs as required.
 Modify roof and floor framing and provide additional foundation for new fire walls.
 Modify and reinforce existing structure for new mechanical units and related work.
 Modify and reinforce existing structure for new clerestory at the roof level above the existing
Media center.
 Relocation of interior non-loadbearing walls will require structural reinforcement of existing
floor system.
 New exterior elevator masonry shaft with foundation at upgraded elevator.
 Roof structure capacity will be assessed for new roof top mechanical equipment.
 Additional structural work will be required to accommodate the anticipated mechanical,
electrical and other upgrades.
 Reinforcing of isolated structural elements may be required.
 New roof openings will likely need to be framed for new roof penetrations.
 Existing abandoned roof penetrations will be patched.
Auditorium, Gymnasium, Physical Education, Tech Ed and Lab, Cafeteria and Kitchen additions:
 Tech Ed and Lab addition will be two stories. All other additions will be a single story.
 Load bearing CMU walls with structural steel framed structure.
 The roof structure at the Auditorium and Gymnasium will consist of long span open web
steel joists at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck or Tectum
deck.
 The roof structure at all other areas will consist open web K-series steel joists at 5’-0” on
center with 1-1/2”, 22 gage, galvanized metal roof deck.
 The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists
at 5’-0” on center with 1-1/2”, 22 gage galvanized metal roof deck.
Page 62 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
Structural – continued










Masonry walls at the auditorium and gymnasium will be a load bearing 12” thick reinforced
CMU.
Walls less than 18’-0” tall can be 8” thick reinforced CMU.
Second floor construction at the lab addition will consist of 3”concrete on a form deck
supported by open web joists at 24” to 36” on center. This floor structure will be supported
by load bearing masonry walls.
Steel beams and columns will be provided as required by the architectural layout.
The new additions will abut the existing building, which have a framed first floor with a crawl
space. The existing finished floor elevation is close to the exterior grade.
A geotechnical investigation will be conducted during the design phase to determine
foundation recommendations.
If a slab on grade is feasible from a geotechnical standpoint, then a 5” concrete slab on
grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost
effective compared to a framed structure with a crawl space.
However, if the recommendations of the geotechnical report indicate that a slab on grade is
not feasible, and a framed first floor structure be required, 8” precast concrete plank with a
2” lightweight concrete topping slab supported by masonry bearing walls in the crawl space
is a viable option.
Additional deeper foundation walls will likely be required at the juncture of the additions with
the existing to “close off” existing crawl spaces from the backfill.
We anticipate a shallow spread footing foundation system, consistent with the existing
building, will be appropriate. However, this must be confirmed by a geotechnical
investigation.
Mechanical
A. General Overview
The mechanical systems will be designed in compliance with DGS and all industry standards
essentially replacing the entire HVAC system as a means to: bring the system up to current
standards, increase system efficiency, address the user's needs for the next 20+ years, and
improve sustainability. The overall goals of the system retrofit are: provide good indoor air
quality, to be highly energy efficient, to be easily maintainable, to have low first cost as well
as low life cycle costs, and to be cognizant of project construction budget limitations. The
system we are recommending is Active Chilled Beams supplied from Dedicated Outside Air
Systems (DOAS) with a Central Geothermal Water to Water Heat Pump Plant.
B. Ventilation System
The first major component of the proposed overall HVAC system is the Dedicated Outside Air
System (DOAS) which delivers code required outside air directly to the room level. The
purpose of the dedicated ventilation system is to decouple the conditioning of outside air
used for ventilation from the conditioning of room air. The primary advantage of the
Page 63 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
Mechanical – continued
decoupling is that the outside air can be properly dehumidified regardless of the sensible
cooling load of the space, assuring improved room relative humidity levels during space
partial cooling load conditions. The use of the DOAS also reduces the operating cost by only
requiring the conditioning of the quantity of outside air required to meet the sum of all space
ventilation loads.
C. Overhead Active Chilled Beams
The chilled beam provides heating or cooling on demand on a room by room basis. The unit
has no fan; it uses the induction air principal, driven by ventilation air, to cause 3 to 4 times
the air flow rate of the DOAS ventilation air to be drawn up through the perforated panel in
the center of the chilled beam – across the terminal unit coil – and be discharged with the
DOAS ventilation air out the two linear slot diffusers on the perimeter of the chilled beam.
The hydronic arrangement of the system is four pipe. The chilled beams use the return
chilled water from the DOAS unit.
D. Central Geothermal Water to Water Heat Pump Plant
The main component is a modular water to water heat pump which uses multiple nominal
thirty to seventy ton modules. Each module is an independently controlled (staged) heat
pump capable of producing chilled and hot water. The modular unit as a whole can produce
chilled and heating water simultaneously. The source side of the modular unit is piped to a
geothermal well field which provides a heat source/sink.
E. System Equipment
The system is comprised of:
1. A modular geothermal grade water to water heat pump unit with VME valving using
fifteen 70 ton modules. Basis of design: Multistack
2. Two variable volume frame mounted end suction geothermal well field water pumps with
variable frequency drives.
3. Two variable volume frame mounted end suction heating water pumps with variable
frequency drives. 50 HP
4. Two variable volume frame mounted end suction chilled water pumps with variable
frequency drives, 1,700 GPM, 100 HP.
5. One geothermal well field with approximately 180 wells using a depth of 600 feet, using
1-1/4" SDR-9 in the vertical bore hole and SDR-11 or 15 piping for the horizontals. Wells
to be grouted with high conductivity (1.2) bentonite grout. 3,150 GPM, 100 HP
6. Five 20,000 CFM ERU’s for the DOAS
7. Five 7,500 CFM large space AHU's,
Page 64 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
Mechanical – continued
8. Fan coil units for the entry areas (areas subject to very high infiltration loads).
9. A chilled beam(s) for each remaining occupied room. A typical classroom for 30
students would take three six foot chilled beams.
10. Heating water convectors or hot water unit heaters for restrooms and utility spaces.
11. A DDC Building Management System.
12. Some miscellaneous utility fans (propeller and cabinet type).
F. Advantages
Some of the advantages of the chilled beam and modular water to water geothermal heat
pump system include the following:
1. Superior indoor air quality due to:
a. Excellent cooling season relative humidity control.
b. The high ventilation effectiveness due to the characteristics of the induction air
method.
2. The highest degree of zoning with essentially every occupied space being provided with
individual temperature control.
3. Space by space heating or cooling on demand.
4. A reduction in ductwork when compared with a VAV system or ducted water source heat
pump system with DOAS.
5. Very high operating efficiency.
a. Mass energy storage over time for reuse in the building.
b. High efficiency heating and cooling plant at design temperatures (COP = 4+,
EER = 14+). These improve dramatically at partial load conditions due to the
geothermal characteristics.
c. An efficiency improvement from the increased chilled water temperature
difference.
6. While the four pipe system arrangement requires a second piping network inside the
building, the delta Tee of both systems is greater than 500% larger than the first three
options minimizing the cost impact of the additional piping.
7. First cost and maintenance cost savings from the consolidation of all heating and cooling
plant equipment into a single unit. This includes:
a. Savings from centralized compressor maintenance.
b. Savings from the elimination of 85% of the filter maintenance.
8. A first cost and maintenance cost reduction on the electrical power distribution system
associated with the elimination of a water source heat pump unit for each room. This
eliminates: a branch circuit to each unit, several electrical panel boards, a feeder for
each panel board and a switchboard switch for each feeder. Some cost is added back in
for the circuiting to the modular water to water heat pump and extra pumps, however,
all of those units are located immediately adjacent to the main electrical room.
9. Very low background noise levels due to the elimination of a terminal unit fan.
Page 65 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
Plumbing








All existing plumbing fixtures will be removed. New fixtures will be provided. New layouts
and fixture clearances will comply with the Americans with Disabilities Act.
Cold and tempered water will be provided to all lavatories. Hot and cold water will be
provided to all sinks.
Fixtures will be high efficiency, low flow and lowest water usage available at time of design.
All above ground domestic water, sanitary and storm piping will be removed and new piping
will be provided. The adequacy of the existing domestic water service needs to be verified
according to new layouts, additions, and final fixture count for new design. The entire
domestic water system will be brought into compliance with current codes regarding cross
connection control and metering will be provided in accordance with the requirements of the
local water authority and owner's requirements.
The existing underground sanitary and storm water piping will be utilized where possible;
however, all new piping will be installed above grade in crawlspace due to major changes
planned for toilet partitioning in the building.
The domestic water heating system for the main building will be a central system in the
main boiler room. Separate, dedicated gas fired water heaters will be provided for the
kitchen.
The main domestic water heating system being proposed for use in this building is a
geothermal heat pump system with new double wall heat exchangers and hot water being
stored in the existing storage tank. The existing tank will be cleaned and relined.
The kitchen water heater will be gas fired storage type, direct vented, condensing high
efficiency heater with piped outside air intake.
Fire Protection System


Existing fire sprinkler system will remain and a new system will be installed in all
unsprinklered areas. Extension of the system will require the installation of a fire pump in
order to overcome the friction losses for the greater lengths of piping required.
System will be zoned in accordance with NFPA 13, and each zone will follow the
boundaries of the fire alarm system zones.
Electrical
A. Power Distribution System
Existing power distribution system including panelboards, transformers and related wiring
will be removed and new equipment and wiring will be provided. Also existing wall devices
will be removed and based on requirement, new devices will be installed.
Existing grounding system including all ground conductors, grounding bonds,
connection/connectors, ground rods and terminals will be verified and grounding system
resistance will be measured. In case of any issue in the system, appropriate
Page 66 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
Electrical – continued
correction/modifications will be suggested. In new addition buildings new ground terminals
will be provided for equipment ground connections and panelboards.
Electrical power in new addition buildings specified in this option, such as new Gymnasium,
Auditorium, music and related spaces and cafeteria/kitchen will be distributed via a new
panelboard which will be located in each building. For new portable classrooms, a separate
distribution panel will be specified to feed power box in each classroom trailer. All these
panels will be fed from the existing main distribution panel inside the main electrical room.
Existing demand load in the building will be evaluated and new electrical load will be
calculated for entire school. Based on new load situation, the existing electrical service will
have an upgraded power transformer/substation provided.
In order to feed loads related to life safety system and other loads which will required standby power a new power generator with two automatic transfer switches, and related
distribution system will be provided.
B. Lighting
All existing lighting fixtures will be removed and new light fixtures will be provided. Based on
new lighting distribution, extra fixtures will be provided as necessary. New lighting control
system will be installed in each location. In order to save energy, occupancy sensors will be
specified for existing spaces to turn off the lights when it is not in use.
Complete new lighting system will be designed for each new addition building. Type of light
fixtures in each space will depend on the application and the character of the space. Light
fixtures with direct/indirect distribution will be used for all classrooms and teaching spaces.
Light fixtures/lamps types, and related controls will be selected such that the system’s
energy saving is as much as possible. Occupancy sensors will be provided for all spaces to
turn off lights when the space is not in use. Day light harvesting system will be specified for
applicable spaces. Light fixtures in gymnasium shall have wire guards. Exit lights and
emergency lighting will be provided for exit entrance and all means of egress. New exit
lights and emergency fixtures shall include battery back-ups. Battery back-up chargers for
these fixtures will be connected to emergency circuits.
Fire Alarm System
The existing fire alarm system will be removed and a new addressable fire alarm system will
be provided to cover entire school including the existing building and new additions. Fire
alarm booster panels/sub-panels will be provided if necessary. New initiation and notification
devices will be provided for all locations. In each space based on the requirement,
notification devices will be audio or visual types or combination of both. In all assembly
areas, voice alarm system will be specified.
Page 67 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION D: MODERNIZATION
Public Address and Sound System
A new public address system will be provided for the entire school including the existing
building and new additions. Ceiling and wall speakers will be installed in different spaces.
Call buttons and volume control devices will be installed as necessary. Voice enhancement
systems will be installed in all classrooms.
Special sound systems will be provided in the gymnasium, auditorium, and music spaces.
The new sound system will include speakers, microphone/jacks and control panels with
necessary components/devices.
Data, Telephone and Intercommunication Systems
New data, telephone, and intercommunication systems located in server rooms/closets will
be provided for entire school. These systems include all servers, wireless communication
devices and UPS units to maintain the operation of servers and other equips without any
interruption in case of power outage.
Security System
New security system will be provided for entire school. New system includes door contacts,
window contacts, motion detectors and security monitoring system with CCTV cameras. This
system will be designed by a security consultant and will be installed under supervision of
school security personnel.
Page 68 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
This page intentionally left blank.
Page 69 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION E: REPLACEMENT ‘A’
ASSESSMENT
A new building will be constructed in two phases on site so that the existing stadium and track can
remain in place. The existing building will remain in full use during the construction of Phase 1. The
construction of Phase 2 will require the existing gymnasium and physical education wing to be
demolished. During Phase 2 the new gymnasium and physical education spaces will be used. Thus,
the school will have to operate out of two buildings during Phase 2.
Advantages:
1.
2.
3.
4.
5.
6.
7.
8.
9.
New building.
Existing track and stadium remain in place.
Possible continued use of stadium throughout construction for P.E.
Flexible space for future curriculum changes.
Interior circulation is efficient.
LEED certified building.
Full separation of bus queuing and parent drop-off areas.
Facility will meet all EdSpec requirements as well as all building, life safety, energy, and
accessibility codes and standards.
Daylighting in all classrooms.
Disadvantages:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Three phases for overall construction process – longer timeframe than Replacement B.
Construction and Life-Cycle Costs are higher compared to Replacement B.
School will operate out of two buildings during phase two.
Partial occupied construction.
Possibility that stadium will not be able to be used for athletic events throughout
construction, due to access through construction site.
No student parking on site for the duration of construction.
Track and stadium field are separated from other play fields.
Fewer practice and play fields than currently exist.
Student parking and parent drop off are not fully separated.
New building must be constructed in two phases.
Track will remain only six lanes wide.
Parking lots for auditorium and gymnasium events in finished facility are not close to the
building.
Disturbance to neighbors along back property during construction and could continue to be
an issue at completion due to shape of building (i.e. site lighting).
Page 70 of 112
Severna Park High School
Severna Park, Maryland
OPTION E: REPLACEMENT ‘A’
SITE PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION E: REPLACEMENT ‘A’
FIRST FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Feasibility Study
GWWO, Inc./Architects Severna Park, Maryland
OPTION E: REPLACEMENT ‘A’
SECOND & THIRD FLOOR PLANS
SECOND FLOOR
THIRD FLOOR
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION E: REPLACEMENT ‘A’
ANTICIPATED SCOPE OF WORK
Architectural



A new building will meet all Educational Specifications requirements.
Materials and equipment will be designed to meet AACPS Design Guidelines.
All classrooms, offices, and common spaces will have abundant daylight.
Site












The new school will be constructed adjacent to the existing school in the area currently
occupied by the grass multi-purpose fields.
The existing stadium and track will remain in its current location.
The new multi-purpose fields, tennis courts and basketball courts will be constructed in the
area currently occupied by the staff/visitor parking.
Vehicular access points will remain at their current locations and separation of vehicular and
bus traffic has been maximized in addition to separation of vehicular traffic and parent drop
off.
A new thirty foot (30’) wide drive will be constructed at the Red Oak Drive intersection
(currently the access point for the staff/visitor parking). This drive will provide access to the
new bus staging loop (26 buses). An emergency vehicle drive will also be constructed off of
the main drive to allow for emergency vehicle access to the play field area.
A new two way drive will be constructed at the White Oak Drive intersection (currently the
bus loop egress). This drive will provide access to the staff and visitor parking. The staff
parking areas will be located adjacent to Robinson Road with the visitor parking being
located further into the site and adjacent to the new classroom wing.
A new parent drop off loop will be constructed utilizing the outer portion (drive) of the visitor
parking area.
The third access point, at the intersection of Benfield Road and Evergreen Road will remain
as access into the student parking and staff parking.
Total on-site parking will be capable of supporting 400 vehicles.
A new 20’ wide fire access lane will be constructed around the perimeter (sides and rear) of
the building. Fire access for the front of the building will be achieved via the new bus
staging loop and the parent drop off loop. The fire lane will be accessed from the new bus
staging loop and will proceed around the rear of the building and continue eventually
terminating at the new student parking area.
The 20’ drive (fire lane) located between the existing stadium field/track and the new
building will also serve as access to the new service area which will be located at the far
northeast side of the new building adjacent to the new food services wing.
Multi-purpose field #1 will be located adjacent to the bus staging loop. Immediately east of
this field will be the new fenced and lit tennis court area (10 courts) with bleachers for 200
spectators; continuing easterly will be the new basketball courts (3 half courts) and multipurpose field #2 which will be located closest to Robinson Road. Multi-purpose field #3 will
be located adjacent (north) of the new fenced tennis courts. The remaining fields, baseball,
softball and multi-purpose field #4 will remain in their current location.
Page 71 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION E: REPLACEMENT ‘A’
Site – continued



Multi-purpose fields #1 through #3 will be 360’ x 200’. One field will be Bermuda grass and
the other two fields will be tall fescue fields. All fields will be irrigated.
This option will require the permanent relocation of approximately 750 LF of 48” public
storm drain and the permanent relocation of approximately 800’ of public 8” sanitary sewer
prior to the beginning of the building construction. In addition approximately 320 LF of 24”
storm drain and 280 LF of 8” sanitary sewer will be temporarily relocated once the
permanent public utility relocation is completed to allow for the existing school to remain
operational during construction.
Two areas have been identified to construct underground infiltration trenches, six areas have
been defined for micro bio-retention areas and an additional four areas have been identified
for landscape infiltration areas. The underground trenches range in size from 4,350 SF to
4,750 SF. The areas identified are adjacent to the classroom wing under the visitor parking
area and adjacent to the physical education wing. The micro-bio-retention areas range from
approximately 1,900 SF to 2,750 SF and are located along the frontage of the site between
Robinson Road and Benfield Road, adjacent to the new bus staging loop drive, adjacent to
the staff and visitor parking and adjacent to the stadium/track and student parking. The
landscape infiltration areas range from 2,400 SF to 3,600 SF and are located between the
basketball and tennis courts, within the bus staging loop and within the area between the
bus staging loop and multi-purpose field #1.
Structural
One story Administration offices, Auditorium, Gymnasium, Theatre/Music/Dance, Physical Education,
Cafeteria and Kitchen:






Load bearing CMU walls with structural steel framed structure.
The roof structure at the Auditorium and Gymnasium will consist of long span open web
steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck or
Tectum deck.
The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists
at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck.
The roof structure at all other areas will consist of open web K-series steel joists at 5’-0” on
center with 1-1/2” deep 22 gauge galvanized metal roof deck.
Masonry walls at the auditorium and gymnasium will consist of load bearing 12” thick
reinforced CMU. Walls less than 18’-0” tall can be 8” thick reinforced CMU.
Steel beams and columns will be provided as required by the architectural open space
layout.
Three story Classroom and Media center wing:

The roof structure will consist of open web K-series joists at 5’-0” on center with 1½” deep
22 gauge galvanized roof deck.
Page 72 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION E: REPLACEMENT ‘A’
Structural – continued





The Second and Third floor construction will consist of 3” thick concrete on a form deck
supported by open web joists at 24” to 36” o.c. Majority of the floor structure will be
supported by load bearing masonry walls. Interior beams and columns will be used at the
media center to provide open space.
The mechanical penthouse will consist of 4½” concrete on 2” composite deck.
The first floor above the mechanical basement will consist of 4½” thick concrete on 2”
composite deck supported by composite beams and girder system with interior columns.
Basement wall will be reinforced concrete walls on a continuous footing.
If a slab on grade is feasible from a geotechnical standpoint, then a 5” thick concrete slab on
grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost
effective compared to a framed structure with a crawl space.
We anticipate a shallow spread footing foundation system, consistent with the existing
building, will be appropriate. However, this must be confirmed by a geotechnical
investigation.
Mechanical
Mechanical system design for a replacement building will use the same approach as that
described above in Option C: Revitalization.
Plumbing
New building will have all new utility services from the public mains. It is suggested that
looping the building with a new fire main and hydrants be investigated under the civil
portion of the design.
All new plumbing fixtures will be provided. New layouts and fixture clearances will comply
with the Americans with Disabilities Act. Cold and tempered water will be provided to all
lavatories. Hot and cold water will be provided to all sinks. Fixtures will be high efficiency
and lowest water usage available at time of design.
All materials for domestic water, sanitary and storm piping will be specified in accordance
with current code requirements and building practices. The entire domestic water system will
be designed to current codes regarding cross connection control. Metering will be provided
in accordance with the requirements of the local water authority and owner's requirements.
The domestic water heating system for the main building will be a central system in the
main boiler room. Separate, dedicated gas fired water heaters will be provided for the
kitchen.
The main domestic water heating system being proposed for use in this building is a
geothermal heat pump system and storage tank with internal heat exchanger.
Page 73 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION E: REPLACEMENT ‘A’
Fire Protection System
Proper fire sprinkler system will be designed for new building. It is anticipated that a new
fire service loop would be provided around the new building serving multiple fire service
entrances and fire hydrants on site. The adequacy of flow and pressure available will
depend on the configuration, location, elevations, size of footprint, height, and connections
to the public system.
The sprinkler system will be designed and installed in accordance with all requirements of
NFPA 13, and will be hydraulically designed to minimize pipe size requirements and to
provide an economical distribution system for the building.
Electrical
A. Power Distribution System
New building will have a new electrical service. New power transformer will be located at the
site close as possible to the new main electric room. If secondary substation is required,
new vault will be designed for new equipment. Building’s new secondary service will be
480Y/277V, 3-phase, 4-wire. School will have dual voltage systems. All lighting loads, AC
system, roof top units and other large equipment will be fed with 480/277V system. All
receptacles, computer loads, PA system, Fire Alarm and security control panels and other
small loads will be on 208/120 volt system. Building secondary service will be connected to a
main distribution panelboard (MDP) inside the new main electrical room. Secondary
distribution panels will be located inside electrical closets through-out the building. Each
electrical room/closet will have high voltage (480/277V) panels and also low voltage
(208/120V) panelboards. Low voltage panels will be fed from high voltage panels via drytype transformers. K-rated transformers will be used for all low voltage panels that feed nonlinear loads such as computers, servers and other electronic equipment.
Stand-by generator will be provided for all emergency loads such as exit lights, emergency
lighting for means of egress and fire alarm control panels. Automatic transfer switch (ATS)
will be used to transfer the power from normal source to generator and vice versa. All loads
which are not critical and needed to be fed by stand-by power will be connected to a
separate transfer switch. Auto transfer switch related to critical/emergency loads will be
located inside a fire rated closet. Emergency loads and other loads which require stand-by
power will be connected to separate panels. Loads on stand-by generator will be according
to requirements in Ed Spec. Emergency panels will be located inside electric rooms/closet.
B. Lighting
Proper lighting system will be designed for new building. Type of Light fixtures in each space
will depend on the application and the type of the space. Fixtures with direct/indirect
distribution will be selected for all classrooms and teaching spaces. Light fixtures/lamps
Page 74 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION E: REPLACEMENT ‘A’
types, and related controls will be selected such that the energy efficiency in the system is
as high as possible. Occupancy sensors will be provided for all spaces to turn off lights when
the space is not in use. Day light harvesting system will be specified for applicable spaces.
Special lighting control/dimming system will be specified in auditorium. Light fixtures in
gymnasium shall have wire guards.
Exit lights and emergency lighting will be provided for exits, entrances, and all means of
egress. New exit lights and emergency fixtures shall include battery back-up.
Outdoor lighting will be provided for building entrances. Pole mounted fixtures will be
specified for all drive ways and parking lights. Bollard fixtures will be selected for walkways
and building accesses. Special lighting system will be designed for all sport fields.
Fire Alarm System
New fire alarm system will be non-coded addressable type with addressable initiation and
notification devices. Fire alarm booster panels/sub-panels will be provided, if necessary in
different locations. In each space based on requirement, notification devices will be audio or
visual types or combination of both. For all assembly areas, voice alarm system will be
specified. Fire alarm zoning will be coordinated with sprinkler system in the building. A new
annunciator panel will be located at the building’s main entrance. Fire alarm control panel
including battery back-ups will be located inside the main electric room.
Public Address System
A new public address system will be provided for entire school. New ceiling and wall
speakers will be installed in different spaces. As required, new call switch and volume
controls will be provided inside spaces.
Sound Systems
New special sound systems will be provided in gymnasium, auditorium and music spaces.
New sound system will include speakers, microphone/jacks and control panels with
necessary components and devices. Voice enhancement systems will be provided in all
classrooms.
Data, Telephone and Intercommunication Systems
Equipment for these systems will be located inside MDF and IDF closets. Appropriate
communication wiring will be provided between MDF and IDF closets. These systems
include all servers, wireless communication devices and UPS units to maintain the
Page 75 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION E: REPLACEMENT ‘A’
operation of servers and other equips without any interruption in case of power outage.
Wall-mounted data/telephone outlets will be installed in every location as required.
Security System
Security system for new building includes door contacts, window contacts, motion detectors
and security monitoring system with CCTV cameras. This system will be designed by a
security consultant and will be installed under supervision of school security personnel. Main
control panel for this system, security keypads and monitoring equipment will be located in a
separate room.
Page 76 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
This page intentionally left blank.
Page 77 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION F: REPLACEMENT ‘B’
ASSESSMENT
A new building will be constructed on site in a single phase with minimal disruption to the operations
of the existing facility. The existing building will remain in use during construction. The existing
track, stadium, and practice fields will not be available for the duration of construction.
Advantages:
1. Entirely new, non-phased building construction allows for the most efficient design. This
option will result in the smallest square footage of building, thus lowest overall operational
costs.
2. Two phases for overall construction process/building and site – shorter timeframe than
Replacement A.
3. Non-occupied construction with full separation of students and construction.
4. All Ed Spec requirements are met including athletic fields and an eight lane track.
5. Minimal disruption to operations during construction.
6. Site circulation and safety.
7. Efficient interior circulation.
8. Better facilitation of inter-discipline instruction.
9. Flexible spaces for future curriculum changes.
10. LEED certified building.
11. Efficient site design, activities are grouped together – curricular and extracurricular.
12. Existing number of athletic fields is maintained.
13. Full separation of bus queuing and parent drop-off areas.
14. Facility will meet all EdSpec requirements as well as all building, life safety, energy, and
accessibility codes and standards.
15. Daylighting in all classrooms.
16. Building is constructed in a single phase.
17. Lower construction and life cycle costs than Replacement A, Revitalization, and
Modernization options.
Disadvantages:
1. Loss of use of outdoor athletic facilities for the duration of construction, with the exception
of the baseball and softball fields during phase one.
2. No student parking on site for the duration of construction.
3. Possible loss of interior courtyards as secure outdoor classrooms.
4. Disturbance to neighbors during construction along back property line and could continue
due to shape of building.
5. Impact of nighttime athletics on different set of neighbors.
6. Student parking and parent drop off are not fully separated.
Page 78 of 112
Severna Park High School
Severna Park, Maryland
OPTION F: REPLACEMENT ‘B’
SITE PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION F: REPLACEMENT ‘B’
FIRST FLOOR PLAN
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
OPTION F: REPLACEMENT ‘B’
SECOND & THIRD FLOOR PLANS
SECOND FLOOR
THIRD FLOOR
Feasibility Study
GWWO, Inc./Architects Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION F: REPLACEMENT ‘B’
ANTICIPATED SCOPE OF WORK
Architectural



A new building will meet all Educational Specifications requirements.
Materials and equipment will be designed to meet AACPS Design Guideline
All classrooms, offices, and common spaces will have abundant daylight.
Site











The new school will be constructed in the location currently occupied by the stadium/track
and the grass multi-purpose fields.
The existing baseball, softball and small multi-purpose fields will remain at their current
location.
All of the new recreational areas including the new stadium/track, tennis courts, grassed
multi-purpose fields, and basketball courts will be constructed in the area currently occupied
by school, bus staging loop and staff/visitor parking.
Two of the three original vehicular access points will remain at their current location. The
existing entry to the site for the staff/visitor parking will be removed. A new access point
will be installed adjacent to Holland Road along Benfield Road at the far southwest corner of
the site. Separation of vehicular and bus traffic has been maximized in addition to separation
of vehicular traffic and parent drop off.
A new thirty foot (30’) wide drive will be constructed at the White Oak Drive intersection
(currently the bus loop egress). This drive will provide access to the new bus staging loop
(26 buses). An emergency vehicle drive will also be constructed off of the main drive to
allow for emergency vehicle access to the play field area.
The Evergreen Road entry point (currently access to the student parking area) will remain
the same and will provide access to a new student parking area, visitor parking area and
parent drop off loop
The new entry adjacent to Holland Road will provide access to staff parking and service.
Total on-site parking will be capable of supporting 400 vehicles.
A new 20’ wide fire access lane will be constructed around the perimeter (sides and rear) of
the building. Fire access for the front of the building will be achieved via the new bus
staging loop and the parent drop off loop. The fire lane will be accessed from the new bus
staging loop and will proceed around the rear of the building and continue eventually
terminating at the new service yard.
A new 20’ drive (emergency vehicle access) will be constructed between the tennis courts
and the new grassed multi-purpose field #3. This new drive will be accessed off of the new
bus loop drive and will provide access for emergency vehicles during sporting events and
maintenance vehicles.
The new stadium track will be constructed at the front of the site along Robinson Road in
the location currently occupied by the bus loop and front of the existing school. The stadium
field will measure 360’x220 and will be an artificial turf field. The field will be surrounded by
an eight lane (42” wide) rubberized track. Additional track and field areas will also be
Page 79 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION F: REPLACEMENT ‘B’
Site – continued






constructed at this location including an area for high jump, long jump, discus and pole
vaulting area. Bleachers will also be installed to accommodate 4000 spectators (2,500
home, 1,500 visitors).
The new fenced and lit tennis courts (8 courts are currently shown, but 10 will be the goal
during development of the site design) will be installed immediately west of the
stadium/track. Bleachers will also be installed for up to 200 spectators.
Grassed multi-purpose fields #1 through #3 will be located immediately east of the new
tennis court area with field #4 being located north of the tennis courts. An emergency
vehicle drive will also be constructed between the tennis courts and field #3 and will also
allow for access to the new field house. Emergency vehicle access to the remaining field will
be via the bus loop and fire lane. One of these fields will be Bermuda grassed and the
remaining fields will be tall fescue fields. All fields will contain irrigation systems.
Multi-purpose fields #1 through #4 will be 360’ x 200’.
The new fenced basketball courts (3 half courts) will be located north of the new building
immediately adjacent to the new fire lane.
This option will require the permanent relocation of approximately 750 LF of 48” public
storm drain and the permanent relocation of approximately 800’ of public 8” sanitary sewer
prior to the beginning of the building construction. In addition approximately 320 LF of 24”
storm drain and 280 LF of 8” sanitary sewer will be temporarily relocated once the
permanent public utility relocation is completed to allow for the existing school to remain
operational during construction.
Two areas have been identified to construct underground infiltration trenches, eight areas
have been defined for micro bio-retention areas and an additional four areas have been
identified for landscape infiltration areas. The underground trenches are approximately
11,200 SF each. The areas identified are adjacent to the classroom wing under the student
parking area and adjacent to the physical education wing. The micro-bio-retention areas
range from approximately 1,520 SF to 2,880 SF and are located along the frontage of the
site between Robinson Road and Benfield Road, adjacent to the new bus staging loop drive,
and along the far southwest corner of the property adjacent to the staff parking. The
landscape infiltration areas range from 900 SF to 4,200 SF and are located along the front of
the building, within the parent drop off loop and bus staging loop and between the fire lane
and grassed multi-purpose field #1.
Structural
One story Administration offices, Auditorium, Gymnasium, Theatre/Music/Dance, Physical Education,
Cafeteria and Kitchen:



Load bearing CMU walls with structural steel framed structure.
The roof structure at the Auditorium and Gymnasium will consist of long span open web
steel joists at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck or
Tectum deck.
The roof structure at the Cafeteria and Kitchen will consist of long span open web steel joists
at 5’-0” on center with 1-1/2” deep 22 gauge galvanized metal roof deck.
Page 80 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION F: REPLACEMENT ‘B’
Structural – continued



The roof structure at all other areas will consist of open web K-series steel joists at 5’-0” on
center with 1-1/2” deep 22 gauge galvanized metal roof deck.
Masonry walls at the auditorium and gymnasium will consist of load bearing 12” thick
reinforced CMU. Walls less than 18’-0” tall can be 8” thick reinforced CMU.
Steel beams and columns will be provided as required by the architectural open space
layout.
Three story Classroom and Media center wing:






The roof structure will consist of open web K-series joists at 5’-0” on center with 1½” deep
22 gauge galvanized roof deck.
The Second and Third floor construction will consist of 3” thick concrete on a form deck
supported by open web joists at 24” to 36” o.c. Majority of the floor structure will be
supported by load bearing masonry walls. Interior beams and columns will be used at the
media center to provide open space.
The mechanical penthouse will consist of 4½” concrete on 2” composite deck.
The first floor above the mechanical basement will consist of 4½” thick concrete on 2”
composite deck supported by composite beams and girder system with interior columns.
Basement wall will be reinforced concrete walls on a continuous footing.
If a slab on grade is feasible from a geotechnical standpoint, then a 5” thick concrete slab on
grade reinforced with welded wire mesh will be considered. Slab on grade will be more cost
effective compared to a framed structure with a crawl space.
We anticipate a shallow spread footing foundation system, consistent with the existing
building, will be appropriate. However, this must be confirmed by a geotechnical
investigation.
Mechanical
Mechanical system design for a replacement building will use the same approach as that
described above in Option C: Revitalization.
Plumbing
New building will have all new utility services from the public mains. It is suggested that
looping the building with a new fire main and hydrants be investigated under the civil
portion of the design.
All new plumbing fixtures will be provided. New layouts and fixture clearances will comply
with the Americans with Disabilities Act. Cold and tempered water will be provided to all
lavatories. Hot and cold water will be provided to all sinks. Fixtures will be high efficiency
and lowest water usage available at time of design.
Page 81 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION F: REPLACEMENT B
Plumbing – continued
All materials for domestic water, sanitary and storm piping will be specified in accordance
with current code requirements and building practices. The entire domestic water system
will be designed to current codes regarding cross contamination control. Metering will be
provided in accordance with the requirements of the local water authority and owner's
requirements.
The domestic water heating system for the main building will be a central system in the
main boiler room. Separate, dedicated gas fired water heaters will be provided for the
kitchen.
The main domestic water heating system being proposed for use in this building is a
geothermal heat pump system and storage tank with internal heat exchanger.
Fire Protection System
Proper fire sprinkler system will be designed for new building. It is anticipated that a new
fire service loop would be provided around the new building serving multiple fire service
entrances and fire hydrants on site. The adequacy of flow and pressure available will
depend on the configuration, location, elevations, size of footprint, height, and connections
to the public system.
The sprinkler system will be designed and installed in accordance with all requirements of
NFPA 13, and will be hydraulically designed to minimize pipe size requirements and to
provide an economical distribution system for the building.
Electrical
A. Power Distribution System
New building will have a new electrical service. New power transformer will be located at the
site close as possible to the new main electric room. If secondary substation is required,
new vault will be designed for new equipment. Building’s new secondary service will be
480Y/277V, 3-phase, 4-wire. School will have dual voltage systems. All lighting loads, AC
system, roof top units and other large equipment will be fed with 480/277V system. All
receptacles, computer loads, PA system, Fire Alarm and security control panels and other
small loads will be on 208/120 volt system. Building secondary service will be connected to a
main distribution panelboard (MDP) inside the new main electrical room. Secondary
distribution panels will be located inside electrical closets through-out the building. Each
electrical room/closet will have high voltage (480/277V) panels and also low voltage
(208/120V) panelboards. Low voltage panels will be fed from high voltage panels via drytype transformers. K-rated transformers will be used for all low voltage panels that feed nonlinear loads such as computers, servers and other electronic equipment.
Page 82 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION F: REPLACEMENT ‘B’
Electrical – continued
Stand-by generator will be provided for all emergency loads such as exit lights, emergency
lighting for means of egress and fire alarm control panels. Automatic transfer switch (ATS)
will be used to transfer the power from normal source to generator and vice versa. All loads
which are not critical and needed to be fed by stand-by power will be connected to a
separate transfer switch. Auto transfer switch related to critical/emergency loads will be
located inside a fire rated closet. Emergency loads and other loads which require stand-by
power will be connected to separate panels. Loads on stand-by generator will be according
to requirements in Ed Spec. Emergency panels will be located inside electric rooms/closet.
B. Lighting
Proper lighting system will be designed for new building. Type of Light fixtures in each space
will depend on the application and the type of the space. Fixtures with direct/indirect
distribution will be selected for all classrooms and teaching spaces. Light fixtures/lamps
types, and related controls will be selected such that the energy saving in the system is as
high as possible. Occupancy sensors will be provided for all spaces to turn off lights when
the space is not in use. Day light harvesting system will be specified for applicable spaces.
Special lighting control/dimming system will be specified in auditorium. Light fixtures in
gymnasium shall have wire guards.
Exit lights and emergency lighting will be provided for exits, entrances, and all means of
egress. New exit lights and emergency fixtures shall include battery back-up.
Outdoor lighting will be provided for building entrances. Pole mounted fixtures will be
specified for all drive ways and parking lights. Bollard fixtures will be selected for walkways
and building accesses. Special lighting system will be designed for all sport fields.
Fire Alarm System
New fire alarm system will be non-coded addressable type with addressable initiation and
notification devices. Fire alarm booster panels/sub-panels will be provided, if necessary in
different locations. In each space based on requirement, notification devices will be audio or
visual types or combination of both. For all assembly areas, voice alarm system will be
specified. Fire alarm zoning will be coordinated with sprinkler system in the building. A new
annunciator panel will be located at the building’s main entrance. Fire alarm control panel
including battery back-ups will be located inside the main electric room.
Public Address System
A new public address system will be provided for entire school. New ceiling and wall
speakers will be installed in different spaces. As required, new call switch and volume
controls will be provided inside spaces.
Page 83 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
OPTION F: REPLACEMENT ‘B’
Sound Systems
New special sound systems will be provided in gymnasium, auditorium and music spaces.
New sound system will include speakers, microphone/jacks and control panels with
necessary components and devices. Voice enhancement systems will be provided in all
classrooms.
Data, Telephone and Intercommunication Systems
Equipment for these systems will be located inside MDF and IDF closets. Appropriate
communication wiring will be provided between MDF and IDF closets. These systems
include all servers, wireless communication devices and UPS units to maintain the
operation of servers and other equips without any interruption in case of power outage.
Wall-mounted data/telephone outlets will be installed in every location as required.
Security System
Security system for new building includes door contacts, window contacts, motion detectors
and security monitoring system with CCTV cameras. This system will be designed by a
security consultant and will be installed under supervision of school security personnel. Main
control panel for this system, security keypads and monitoring equipment will be located in a
separate room.
Page 84 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects Severna Park, Maryland
APPENDIX A – DETAILED COST ESTIMATES
SUMMARY
PAT CH & PAIN T
DIV.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
CAT EGORY
SITE WORK
HAZMAT ABATEMENT
CONCRETE
MASONRY
METALS
CARPENTRY
THERMAL & MOISTURE
DOORS & WINDOWS
FINISHES
SPECIALTIES
EQUIPMENT
FURNISHINGS
SPECIAL CONSTRUCTION
CONVEYING SYSTEMS
MECHANICAL
ELECTRICAL
TECHNOLOGY
SF
BID-DAY CONSTRUCTION COST SUBTOTAL
TURF REPLACEMENT
NEW STADIUM
0
0
$
0.13
$ 1,319,500
$
$
3.29
$
$
0.22
$
0.39
$
0.29
$
5.48
0.05
$
$
$
0.03
$
$
$
0.22
$
0.16
$
$
14.73
$
$
-
BID-DAY CONSTRUCTION COST WITH FIELDS
RELOCATABLES
PHASING COSTS
GENERAL CONDITIONS
CONTINGENCY
PREMIUM for OFF-HOURS WORK
ESCALATION TO CONSTRUCTION
A/E - CM FEES
TOTAL CONSTRUCTION COST
Project Duration
T OT AL
SF
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
38,962
1,319,500
974,054
64,937
116,886
84,418
1,623,423
16,234
9,741
64,937
48,703
4,361,794
4,361,794
357,988
1
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
$
$
$
$
$
$
$
300,000
300,000
429,733
319,624
112,934
-
16 $
4 $
54 $
15%
6%
2%
150,000
75,000
135,000
$
5,824,086
$
290
$/SF
296,191
1
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
4 $
12 $
10%
6%
2%
75,000
25,000
$
19.66
REVIT IL IZAT ION
1 Year
$/SF
$
26.31
$ 1,319,500
$
6.30
$
12.06
$
12.61
$
4.22
$
7.67
$
9.04
$
12.06
$
1.92
$
3.56
$
6.58
$
5.48
$
0.33
$
57.00
$
32.89
$
3.51
$
205
1 $ 918,000
0 $
-
MODERN IZAT ION
T OT AL
SF
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
9,418,235
1,319,500
2,256,452
4,316,691
4,512,904
1,510,842
2,746,985
3,237,518
4,316,691
686,746
1,275,386
2,354,559
1,962,132
117,728
20,406,175
11,772,793
1,255,765
73,467,102
918,000
74,385,102
360,688
1
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
$
$
$
$
$
$
$
2,400,000
300,000
7,290,000
11,157,765
5,731,972
2,025,297
555,000
16 $
4 $
66 $
15%
6%
2%
150,000
75,000
135,000
$ 103,845,136
$
330
4.5 Years
$/SF
$
26.31
$ 1,319,500
$
8.22
$
18.64
$
15.35
$
5.32
$
10.14
$
13.70
$
16.44
$
3.01
$
3.88
$
7.67
$
6.03
$
0.33
$
58.31
$
32.89
$
3.51
$
233
1 $ 918,000
0 $
-
REPL ACEMEN T "A"
$ /SF
T OT AL
SF
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
9,489,268
1,319,500
2,965,396
6,721,565
5,535,407
1,917,623
3,657,322
4,942,327
5,930,793
1,087,312
1,399,667
2,767,703
2,174,624
118,616
21,030,591
11,861,586
1,265,236
84,184,537
918,000
85,102,537
342,517
1
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
$
$
$
$
$
$
$
2,400,000
300,000
8,910,000
12,578,765
6,482,832
2,290,601
1,110,000
3 $
48 $
5%
1%
2%
75,000
135,000
$ 119,174,734
$
303
5.5 Years
$
36.01
$ 1,015,000
$
10.86
$
25.64
$
25.91
$
4.53
$
14.13
$
14.68
$
14.89
$
4.91
$
4.36
$
8.13
$
4.64
$
0.49
$
53.47
$
28.91
$
3.44
$
258
1 $ 913,750
0 $
-
REPL ACEMEN T "B"
T OT AL
SF
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
12,333,052
1,015,000
3,718,602
8,782,628
8,876,060
1,550,975
4,839,789
5,026,653
5,101,399
1,681,780
1,494,915
2,784,280
1,588,348
168,178
18,312,714
9,903,815
1,177,246
88,355,435
913,750
89,269,185
333,735
1
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
$
$
$
$
$
$
$
225,000
6,480,000
4,463,459
1,004,376
2,028,840
277,500
2 $
42 $
5%
0%
2%
75,000
135,000
$ 103,748,361
$
296
4 Years
$ /SF
$
35.67
$ 1,015,000
$
10.76
$
25.40
$
25.67
$
4.49
$
14.00
$
14.54
$
14.76
$
4.86
$
4.32
$
8.05
$
4.59
$
0.49
$
51.89
$
28.11
$
3.41
$
254
0 $
1 $ 2,130,000
T OT AL
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
11,905,053
1,015,000
3,589,554
8,477,841
8,568,031
1,497,151
4,671,832
4,852,211
4,924,363
1,623,416
1,443,037
2,687,656
1,533,227
162,342
17,316,441
9,379,739
1,136,391
84,783,284
2,130,000
86,913,284
$
$
$
$
$
$
$
150,000
5,670,000
4,283,016
1,915,267
-
$
98,931,568
3.5 Years
Page 85 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects Severna Park, Maryland
This page intentionally left blank.
Page 86 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX A – DETAILED COST ESTIMATES
PATCH AND PAINT
DIV.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
CAT EGORY
SITE WORK
HAZMAT ABATEMENT
CONCRETE
MASONRY
METALS
CARPENTRY
THERMAL & MOISTURE
DOORS & WINDOWS
FINISHES
SPECIALTIES
EQUIPMENT
FURNISHINGS
SPECIAL CONSTRUCTION
CONVEYING SYSTEMS
MECHANICAL
ELECTRICAL
TECHNOLOGY
$/SF
SF
296,191
1
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
296,191
BID-DAY CONSTRUCTION COST SUBTOTAL
TURF REPLACEMENT
NEW STADIUM
0
0
$
0.13
$ 1,319,500
$
$
3.29
$
$
0.22
$
0.39
$
0.29
$
5.48
$
0.05
$
$
0.03
$
$
$
0.22
$
0.16
$
$
14.73
$
$
-
BID-DAY CONSTRUCTION COST WITH FIELDS
RELOCATABLES
PHASING COSTS
GENERAL CONDITIONS
CONTINGENCY
PREMIUM for OFF-HOURS WORK
ESCALATION TO CONSTRUCTION
AE - CM FEES
TOTAL CONSTRUCTION COST
T OT AL
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
38,962
1,319,500
974,054
64,937
116,886
84,418
1,623,423
16,234
9,741
64,937
48,703
4,361,794
4,361,794
4 $
12 $
10%
6%
2%
75,000
25,000
$
$
$
$
$
$
300,000
300,000
429,733
319,624
112,934
-
$
19.66
$
5,824,086
Construction duration: 1 year
Page 87 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX A – DETAILED COST ESTIMATES
REVITALIZATION
DIV.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
CAT EGORY
SITE WORK
HAZMAT ABATEMENT
CONCRETE
MASONRY
METALS
CARPENTRY
THERMAL & MOISTURE
DOORS & WINDOWS
FINISHES
SPECIALTIES
EQUIPMENT
FURNISHINGS
SPECIAL CONSTRUCTION
CONVEYING SYSTEMS
MECHANICAL
ELECTRICAL
TECHNOLOGY
$/SF
SF
357,988
1
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
357,988
BID-DAY CONSTRUCTION COST SUBTOTAL
TURF REPLACEMENT
NEW STADIUM
1
0
$
26.31
$ 1,319,500
$
6.30
$
12.06
$
12.61
$
4.22
$
7.67
$
9.04
$
12.06
$
1.92
$
3.56
$
6.58
$
5.48
$
0.33
$
57.00
$
32.89
$
3.51
$
205.22
$ 918,000
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
9,418,235
1,319,500
2,256,452
4,316,691
4,512,904
1,510,842
2,746,985
3,237,518
4,316,691
686,746
1,275,386
2,354,559
1,962,132
117,728
20,406,175
11,772,793
1,255,765
73,467,102
918,000
74,385,102
$
$
$
150,000
75,000
135,000
$
$
$
$
$
$
$
2,400,000
300,000
7,290,000
11,157,765
5,731,972
2,025,297
555,000
$
290.08
BID-DAY CONSTRUCTION COST WITH FIELDS
RELOCATABLES
PHASING COSTS
GENERAL CONDITIONS
CONTINGENCY @ 15%
PREMIUM for OFF-HOURS WORK 6%
ESCALATION TO CONSTRUCTION 2%
AE - CM FEES ABOVE 3.5 YEARS
TOTAL CONSTRUCTION COST
Construction duration: 4.5 years
Page 88 of 112
16
4
54
T OT AL
$ 103,845,136
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX A – DETAILED COST ESTIMATES
MODERNIZATION
DIV.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
CAT EGORY
SITE WORK
HAZMAT ABATEMENT
CONCRETE
MASONRY
METALS
CARPENTRY
THERMAL & MOISTURE
DOORS & WINDOWS
FINISHES
SPECIALTIES
EQUIPMENT
FURNISHINGS
SPECIAL CONSTRUCTION
CONVEYING SYSTEMS
MECHANICAL
ELECTRICAL
TECHNOLOGY
$/SF
SF
360,688
1
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
360,688
BID-DAY CONSTRUCTION COST SUBTOTAL
TURF REPLACEMENT
NEW STADIUM
1
0
$
26.31
$ 1,319,500
$
8.22
$
18.64
$
15.35
$
5.32
$
10.14
$
13.70
$
16.44
$
3.01
$
3.88
$
7.67
$
6.03
$
0.33
$
58.31
$
32.89
$
3.51
$
233.40
$ 918,000
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
9,489,268
1,319,500
2,965,396
6,721,565
5,535,407
1,917,623
3,657,322
4,942,327
5,930,793
1,087,312
1,399,667
2,767,703
2,174,624
118,616
21,030,591
11,861,586
1,265,236
84,184,537
918,000
85,102,537
$
$
$
150,000
75,000
135,000
$
$
$
$
$
$
$
2,400,000
300,000
8,910,000
12,578,765
6,482,832
2,290,601
1,110,000
$
330.41
BID-DAY CONSTRUCTION COST WITH FIELDS
RELOCATABLES
PHASING COSTS
GENERAL CONDITIONS
CONTINGENCY @ 15%
PREMIUM for OFF-HOURS WORK 6%
ESCALATION TO CONSTRUCTION 2%
AE - CM FEES ABOVE 3.5 YEARS
TOTAL CONSTRUCTION COST
16
4
66
T OT AL
$ 119,174,734
Construction duration: 5.5 years
Page 89 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX A – DETAILED COST ESTIMATES
REPLACEMENT ‘A’
DIV.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
CAT EGORY
SITE WORK
HAZMAT ABATEMENT
CONCRETE
MASONRY
METALS
CARPENTRY
THERMAL & MOISTURE
DOORS & WINDOWS
FINISHES
SPECIALTIES
EQUIPMENT
FURNISHINGS
SPECIAL CONSTRUCTION
CONVEYING SYSTEMS
MECHANICAL
ELECTRICAL
TECHNOLOGY
BID-DAY CONSTRUCTION COST SUBTOTAL
TURF REPLACEMENT
NEW STADIUM
$/SF
SF
342,517
1
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
342,517
$
36.01
$ 1,015,000
$
10.86
$
25.64
$
25.91
$
4.53
$
14.13
$
14.68
$
14.89
$
4.91
$
4.36
$
8.13
$
4.64
$
0.49
$
53.47
$
28.91
$
3.44
$
257.96
1 $ 913,750
0 $
-
BID-DAY CONSTRUCTION COST WITH FIELDS
RELOCATABLES
PHASING COSTS
GENERAL CONDITIONS
CONTINGENCY @ 5%
PREMIUM for OFF-HOURS WORK 1%
ESCALATION TO CONSTRUCTION 2%
AE - CM FEES ABOVE 3.5 YEARS
TOTAL CONSTRUCTION COST
Construction duration: 4 years
Page 90 of 112
3
48
$
$
75,000
135,000
$
302.90
T OT AL
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
12,333,052
1,015,000
3,718,602
8,782,628
8,876,060
1,550,975
4,839,789
5,026,653
5,101,399
1,681,780
1,494,915
2,784,280
1,588,348
168,178
18,312,714
9,903,815
1,177,246
88,355,435
913,750
89,269,185
$
$
$
$
$
$
225,000
6,480,000
4,463,459
1,004,376
2,028,840
277,500
$ 103,748,361
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX A – DETAILED COST ESTIMATES
REPLACEMENT ‘B’
DIV.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
CAT EGORY
SITE WORK
HAZMAT ABATEMENT
CONCRETE
MASONRY
METALS
CARPENTRY
THERMAL & MOISTURE
DOORS & WINDOWS
FINISHES
SPECIALTIES
EQUIPMENT
FURNISHINGS
SPECIAL CONSTRUCTION
CONVEYING SYSTEMS
MECHANICAL
ELECTRICAL
TECHNOLOGY
BID-DAY CONSTRUCTION COST SUBTOTAL
TURF REPLACEMENT
NEW STADIUM
$/SF
SF
333,735
1
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
333,735
$
35.67
$ 1,015,000
$
10.76
$
25.40
$
25.67
$
4.49
$
14.00
$
14.54
$
14.76
$
4.86
$
4.32
$
8.05
$
4.59
$
0.49
$
51.89
$
28.11
$
3.41
$
254.04
0 $
1 $ 2,130,000
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
11,905,053
1,015,000
3,589,554
8,477,841
8,568,031
1,497,151
4,671,832
4,852,211
4,924,363
1,623,416
1,443,037
2,687,656
1,533,227
162,342
17,316,441
9,379,739
1,136,391
84,783,284
2,130,000
86,913,284
$ 75,000.00
$ 135,000
$
$
$
$
$
$
150,000
5,670,000
4,283,016
1,915,267
-
$
$
98,931,568
BID-DAY CONSTRUCTION COST WITH FIELDS
RELOCATABLES
PHASING COSTS
GENERAL CONDITIONS
CONTINGENCY @ 5%
PREMIUM for OFF-HOURS WORK 0%
ESCALATION TO CONSTRUCTION 2%
AE - CM FEES ABOVE 3. 5 YEARS
TOTAL CONSTRUCTION COST
2
42
T OT AL
296.44
Construction duration: 3.5 years
Page 91 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX B – LIFE-CYCLE COST ANALYSIS
LIFE-CYCLE COST ANALYSIS
The life-cycle cost presented herein is:
a. Calculated on a present value basis.
b. Set forth in accordance with IAC direction for feasibility studies.
Factor
Annual operating cost per square foot
Annual maintenance cost per square foot
Total annual O&M cost per square foot
Estimated square feet
Total annual O&M cost
Period [years]
Patch & Paint
$5.06
$2.47
$7.53
296,191
$2,230,319
Revitalization
$4.55
$2.22
$6.78
357,988
$2,426,085
Modernization
Replacement A Replacement B
$4.30
$4.05
$4.05
$2.10
$1.98
$1.98
$6.40
$6.02
$6.02
360,688
$2,308,584
342,517
$2,063,323
333,735
$2,010,420
40
40
40
40
40
5%
5%
5%
5%
5%
Present value of O&M expense stream
$38,271,000
$41,630,000
$39,614,000
$35,405,000
$34,497,000
Initial Construction
Demolition
Temporary Student Housing
Project cost [a/e construction estimate]
$5,824,086
$0
$0
$5,824,086
$101,098,016
$347,120
$2,400,000
$103,845,136
$116,374,734
$400,000
$2,400,000
$119,174,734
$102,448,361
$1,300,000
$0
$103,748,361
$97,746,804
$1,184,764
$0
$98,931,568
$44,095,086
$249,320,272
$277,963,468
$242,901,722
$232,360,136
Assumed interest rate
40-Year Life Cycle Cost
Note that the Life-Cycle Cost for the ‘Patch & Paint’ option does not include future costs for the
replacement of aging systems.
Page 92 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
APPENDIX C – PROJECT SCHEDULES – PATCH AND PAINT
Page 93 of 112
Severna Park High School
Severna Park, Maryland
APPENDIX C – PROJECT SCHEDULES – REVITALIZATION
Page 94 of 112
Feasibility Study
GWWO, Inc./Architects
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
APPENDIX C – PROJECT SCHEDULES - MODERNIZATION
Page 95 of 112
Severna Park High School
Severna Park, Maryland
APPENDIX C – PROJECT SCHEDULES – REPLACEMENT ‘A’
Page 96 of 112
Feasibility Study
GWWO, Inc./Architects
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
APPENDIX C – PROJECT SCHEDULES – REPLACEMENT ‘B’
Page 97 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION
PROGRAM SUMMARY
REVITALIZATION
SPECIFICATION
# of square
rooms footage
1.00.00 ADMINISTRATION
1.01.00 Main Office
1.01.01 Reception
1.01.02 Principal
1.01.03 Principal's Secretary
1.01.04 Assistant Principal
1.01.05 Assistant Principal Reception Area
1.01.06 Conference Room
1.01.07 Workroom - Administration
1.01.08 Administration Storage
1.01.09 Faculty Lounge
1.01.10 Financial Secretary's Office
1.01.11 Attendance Office
1.01.12 Business Manager's Office
950
200
120
700
200
800
400
350
1,000
120
120
120
1.02.00 Other Spaces
1.02.01 Volunteer Office
1.02.02 In School Suspension
1.02.03 Security Room
1.02.04 Special Program Office (signature)
1.02.05 Special Program Conference Room
1
1
1
2
2
400
400
100
200
400
400
400
100
400
800
1.03.00 Evening/Summer School
1.03.01 Program Office
1.03.02 Program Reception
7
1
120
400
840
400
Page 98 of 112
8,420
5,080
1
1
1
5
1
2
1
1
1
1
1
1
950
200
120
140
200
400
400
350
1,000
120
120
120
950
200
120
700
200
800
400
350
1,000
120
120
120
1
1
1
2
2
400
400
100
200
400
400
400
100
400
800
7
1
120
400
840
400
2,100
2,100
1,240
SUPPORT
2.02.00 Guidance
2.02.01 Counselor's Office
2.02.02 Psychologist Office
2.02.03 Student Records
2.02.04 Guidance Reception
2.02.05 Career Room
2.02.06 Guidance Conference Room
2.02.07 Student Support Office
2.02.08 Registrar
2.02.09 Workroom - Guidance
2.02.10 Testing Coordinator
2.02.11 Testing Material Storage
subtotal
8,420
5,080
950
200
120
140
200
400
400
350
1,000
120
120
120
Health Room Waiting
Nurse's Office
Examination Room
Rest Area
Student Rest Room
Treatment/Medication
Health Room Storage
# of square
rooms footage
subtotal
1
1
1
5
1
2
1
1
1
1
1
1
2.00.00 STUDENT
2.01.00 Health
2.01.01
2.01.02
2.01.03
2.01.04
2.01.05
2.01.06
2.01.07
REVITALIZATION
1,240
4,430
890
1
1
1
1
2
1
1
150
100
100
200
75
140
50
150
100
100
200
150
140
50
6
1
1
1
1
1
3
1
1
1
1
120
120
250
450
750
300
120
120
100
120
250
720
120
250
450
750
300
360
120
100
120
250
4,430
890
1
1
1
1
2
1
1
150
100
100
200
75
140
50
150
100
100
200
150
140
50
6
1
1
1
1
1
3
1
1
1
1
120
120
250
450
750
300
120
120
100
120
250
720
120
250
450
750
300
360
120
100
120
250
3,540
3,540
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION
SPECIFICATION
PROGRAM SUMMARY
# of square
rooms footage
3.00.00 CORE INSTRUCTIONAL PROGRAMS
3.01.00 Classrooms
3.01.01 Classroom
Language Arts
Mathematics
Social Studies
3.01.02 Teacher Planning (per teacher)
3.02.00 Resource
3.02.01 General Resource
3.02.02 Special Education Resource
3.02.03 Speech
3.02.04 ESOL
3.03.00 Special Education
3.03.01 Special Education Classroom (FLS & Hannah More
3.03.02
3.03.03
3.03.04
3.03.05
Storage - Special Education
Teacher Planning - Special Education (per tchr)
Special Education Conference Room
Special Education Office
REVITALIZATION
# of square
rooms footage
subtotal
subtotal
51,840
38,450
40
14
14
12
900 36,000
49
50
2,450
1
4
800
500
800
2,000
1
0
300
800
300
0
4
900
3,600
1
12
1
2
400
50
300
120
400
600
300
240
56,463
37,926
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1,061
516
781
778
779
518
1,041
784
780
780
792
1,051
1,307
783
780
780
793
1,140
1,215
786
1,304
1,308
740
739
1,301
780
780
1,393
1,205
1,197
1,197
1,264
976
975
908
957
952
900
901
904
270
260
372
341
325
1,061
516
781
778
779
518
1,041
784
780
780
792
1,051
1,307
783
780
780
793
1,140
1,215
786
1,304
1,308
740
739
1,301
780
780
1,393
1,205
1,197
1,197
1,264
976
975
908
957
952
900
901
904
270
260
372
341
325
1
1
1
1
0
1,123
1,306
1,031
1,149
800
1,123
1,306
1,031
1,149
0
1
1
1
1
1
1
1
1
1,162
1,195
1,122
1,213
400
750
600
325
1,162
1,195
1,122
1,213
400
750
600
325
3,100
1,568
4,609
5,140
6,767
Page 99 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION
PROGRAM SUMMARY
SPECIFICATION
# of square
rooms footage
3.04.00 Alternative Education
3.04.01 Classroom
3.04.02
3.04.03
3.04.04
3.04.05
Storage - Alternative Education
Decision Making Room
Clinical Office
Teacher Planning - Alt Education (per teacher)
4.00.00 SPECIALIZED INSTRUCTIONAL PROGRAMS
4.01.00 Art
4.01.01 Art Studio
4.01.02 Storage Room - Art
4.01.03 Kiln/Clay Room
4.01.04 Ceramic Art Studio
4.01.05 Communication Art Studio
4.01.04 Teacher Planning - Art (per teacher)
4.02.02
4.02.03
4.02.04
4.02.05
4.02.06
4.03.00 Music
4.03.01
4.03.02
4.03.03
4.03.04
4.03.05
4.03.06
4.03.07
4.03.08
4.03.09
subtotal
5,150
4
900
3,600
1
2
2
7
200
400
100
50
200
800
200
350
5,593
1
1
1
1
1
2
2
1
1,132
1,313
781
785
252
390
100
350
1,132
1,313
781
785
252
780
200
350
140,765
4,700
1,200
200
300
1,400
1,400
50
1,200
200
300
1,400
1,400
200
1
9,650
9,650
Library Media Workroom
Library Media Specialist's Office
Storage - Library Media
Seminar Room
Publication Room
1
1
1
1
1
800
200
600
400
900
800
200
600
400
900
General Music Classroom
Storage - General Music
Instrumental Music Classroom
Practice Module
Storage - Instrumental
Keyboard Music Classroom
Ensemble Classroom
Storage - Robe and Uniform
Teacher Planning - Music (per teacher)
1
1
1
5
1
1
1
1
4
2,000
500
2,400
200
600
1,200
1,200
350
50
2,000
500
2,400
1,000
600
1,200
1,200
350
200
142,320
5,098
1
1
1
1
1
1
1,047
356
360
1,440
1,438
457
1,047
356
360
1,440
1,438
457
1
1
1
1
1
1
1
5,138
6,765
533
148
813
400
544
5,138
6,765
533
148
813
400
544
1
1
1
5
1
1
1
1
4
2,000
500
2,400
200
600
1,200
1,200
350
50
2,000
500
2,400
1,000
600
1,200
1,200
350
200
12,550
14,341
9,450
4.04.00 Physical Education
4.04.01 Gymnasium
4.04.02 Teacher Planning w/ Shower Room
4.04.03 Storage - Gymnasium
4.04.04 Auxiliary Gymnasium
4.04.05 Physical Education Classroom
4.04.06 Fitness Lab
4.04.07 Locker Rooms
4.04.08 Bin Storage
4.04.09 P.E. Laundry
4.04.10 Exterior Storage
4.04.11 Dance Studio
4.04.12 Costume Area
4.04.13 Concessions
4.04.14 Team Rooms
4.04.15 Training Room
4.04.16 Coaches Office
4.05.17 Athletic Directors' Office
4.05.18 Officials' Locker Room
Page 100 of 112
# of square
rooms footage
subtotal
1
1
1
1
1
4
4.02.00 Library Media Center
4.02.01 Library Reading Room
REVITALIZATION
9,450
39,820
1 13,000 13,000
1
860
860
2
1,000
2,000
1
5,000
5,000
2
900
1,800
1
4,800
4,800
2
1,600
3,200
1
900
900
1
150
150
1
350
350
1
2,000
2,000
1
350
350
1
150
150
1
3,680
3,680
1
200
200
1
740
740
1
200
200
2
220
440
39,820
1 13,000 13,000
1
860
860
2
1,000
2,000
1
5,000
5,000
2
900
1,800
1
4,800
4,800
2
1,600
3,200
1
900
900
1
150
150
1
350
350
1
2,000
2,000
1
350
350
1
150
150
1
3,680
3,680
1
200
200
1
740
740
1
200
200
2
220
440
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - REVITALIZATION
PROGRAM SUMMARY
SPECIFICATION
# of square
rooms footage
4.05.00 Science
4.05.01 Biology Laboratory/Classroom
7,425
4.05.02 Chemistry Laboratory/Classroom
4.05.03 Earth/Space Laboratory/Classroom
3
2
1,485
1,485
4,455
2,970
4.05.04 Physics Laboratory/Classroom
2
1,485
2,970
1
1
2
2
14
800
200
100
250
50
800
200
200
500
700
4.06.00 Computer Science
4.06.01 Computer Science Laboratory
4.06.02 Computer Science Office
3
2
1,000
75
3,000
150
4.07.00 World & Classical Language
4.07.01 World & Classical Language Lab/Classroom
8
1,000
8,000
1
10
125
50
125
500
1
2
1,625
1,515
1,625
3,030
1
1
1
1
1
1
4
500
500
1,040
800
75
75
50
500
500
1,040
800
75
75
200
4.09.00 Technology Education
4.09.01 Technology Laboratory/Workshop
4.09.02 Fabrication Room
4.09.03 Design Computer Laboratory
4.09.04 Classroom - Technology Education
4.09.05 Storage - Technology
4.09.06 Teacher Planning - Technology (per teacher)
5
1
1
0
1
6
1,450
600
1,200
900
250
50
7,250
600
1,200
0
250
300
4.10.00 Business Education
4.10.01 Business Classroom
4.10.02 Business Computer Laboratory
1
2
900
1,000
900
2,000
1
1
3
500
500
50
500
500
150
4.07.02 Storage - World & Classical Language
4.07.03 Teacher Planning - World & Classical Language
4.08.00 Family and Consumer Science
4.08.01 Multipurpose Laboratory
4.08.02 Food/Nutrition Laboratory
4.08.03
4.08.04
4.08.05
4.08.06
4.08.07
4.08.08
4.08.09
Storage - Family and Consumer Science
Food Preparation Area
Child Development Laboratory
Child Development Classroom
Storage - Child Development
Exterior Storage - Child Development
Teacher Planning - FACS (per teacher)
4.10.03 School Store
4.10.04 Storage - Business
4.10.05 Teacher Planning - Business (per teacher)
subtotal
20,220
1,485
Student Project Area
Chemical Storage
General Science Storage
Prep Room
Teacher Planning (per teacher)
# of square
rooms footage
subtotal
5
4.05.05
4.05.06
4.05.07
4.05.08
4.05.09
REVITALIZATION
19,438
4
1
3
1
1
1
1
1
1
1
2
1
1,485
1,280
1,485
1,044
1,196
1,276
1,303
800
200
250
390
914
5,940
1,280
4,455
1,044
1,196
1,276
1,303
800
200
250
780
914
3
2
1,000
75
3,000
150
1
1
1
1
1
1
1
1
1
1
795
781
781
781
780
780
780
799
291
374
795
781
781
781
780
780
780
799
291
374
1
1
1
1
1
1
1
1
1
1
1,578
1,416
1,400
650
650
1,069
1,142
75
75
200
1,578
1,416
1,400
650
650
1,069
1,142
75
75
200
5
1
1
0
1
6
1,450
600
1,200
900
250
50
7,250
600
1,200
0
250
300
1
1
1
1
1
1
1,414
1,263
1,594
500
500
200
1,414
1,263
1,594
500
500
200
3,150
3,150
8,625
6,942
7,845
8,255
9,600
9,600
4,050
5,471
Page 101 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY – REVITALIZATION
PROGRAM SUMMARY
SPECIFICATION
# of square
rooms footage
4.11.00 Theatre
4.11.01 Auditorium
4.11.02 Stage
4.11.03 Stage Wings
4.11.04 Dressing Room
4.11.05 Set Room
4.11.06 Set Storage
4.11.07 Prop Storage
4.11.08 Projection/Sound Booth
4.11.09 Blackbox Theatre
4.11.10 Video Production
4.11.11 Control Room
4.11.12 Auditorium Office
5.00.00 BUILDING OPERATIONS
5.01.00 Custodial
5.01.01 Custodial Closet
5.01.02 Building Engineer's Office
5.01.03 Can Wash
5.01.04 Book Storage
5.01.05 General Storage
5.01.06 Exterior Storage
5.01.07 Engineer's Shop
5.01.08 Equipment Storage
5.01.09 Custodial Locker Room
5.01.10 Receiving
5.02.00 Food Services
5.02.01 Cafeteria (per src)
5.02.02 Kitchen
5.02.03 Kitchen Managers Office
5.02.04 Food Staff Locker Room
5.02.05 Chair storage
5.02.06 Food Service Laundry Room
5.03.00 Rest Rooms
5.03.01 Public (Adult) Rest Room
5.03.02 Staff Rest Room
5.03.03 Student Rest Room
5.04.00 Mechanical/Electrical
5.04.01 Mechanical Room
5.04.02 Electrical Room
5.04.03 Electrical Closet
Page 102 of 112
REVITALIZATION
# of square
rooms footage
subtotal
subtotal
20,755
996
1
1
2
1
1
1
2
1
1
1
1
12 11,955
1,800
1,800
1,800
1,800
350
700
500
500
300
300
300
300
200
400
1,800
1,800
900
900
200
200
100
100
20,755
996
1
1
2
1
1
1
2
1
1
1
1
12 11,955
1,800
1,800
1,800
1,800
350
700
500
500
300
300
300
300
200
400
1,800
1,800
900
900
200
200
100
100
33,625
5,470
9
1
1
4
1
1
1
1
1
1
30
100
50
500
1,000
400
200
400
250
800
270
100
50
2,000
1,000
400
200
400
250
800
45,522
5,470
9
1
1
4
1
1
1
1
1
1
30
100
50
500
1,000
400
200
400
250
800
270
100
50
2,000
1,000
400
200
400
250
800
17,095
664
1
1
1
1
1
18 11,955
4,400
4,400
200
200
100
100
400
400
40
40
17,095
664
1
1
1
1
1
18 11,955
4,400
4,400
200
200
100
100
400
400
40
40
3,800
4
14
10
150
50
250
600
700
2,500
1
1
6
2,000
500
35
2,000
500
210
3,800
4
14
10
150
50
250
600
700
2,500
2,710
14,607
1 13,897 13,897
1
500
500
6
35
210
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY – REVITALIZATION
PROGRAM SUMMARY
SPECIFICATION
# of square
rooms footage
5.05.00 Telecommunication
5.05.01 Telecommunication Room
5.05.02 Telecommunication Closet
5.06.00 Circulation (sf part of efficiency adjustment unless noted)
5.06.01 Entrance Vestibule
5.06.02 Classroom Corridors
5.06.03 Public Corridors
5.06.04 After-hour Lobby
5.06.05 Gymnasium Lobby
GROSS SQUARE FOOTAGE (with Other Areas)
subtotal
2,050
1
6
250
300
250
1,800
2,050
1
6
250
300
250
1,800
2,500
1
1
1,000
1,500
1,000
1,500
GROSS SQUARE FOOTAGE
Subtotal all programs (including Other Areas)
Efficiency adjustment (new facility)
# of square
rooms footage
subtotal
Subtotal all programs
Efficiency adjustment (new facility)
6.00.00 OTHER AREAS
6.01.00 Ancillary Structure
6.01.01 Concession Building with Rest Rooms
6.01.02 Field House
6.01.03 Maintenance Building
REVITALIZATION
0
1
1
2000
5000
1500
2,500
1
1
1,000
1,500
1,000
1,500
239,080
89,655
328,735
257,155
100,833
357,988
6,500
6,500
0
5000
1500
0
1
1
245,580
92,093
337,673
2000
5000
1500
0
5000
1500
263,655
101,367
365,022
Page 103 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION
PROGRAM SUMMARY
MODERNIZATION
SPECIFICATION
# of square
rooms footage
1.00.00 ADMINISTRATION
1.01.00 Main Office
1.01.01 Reception
1.01.02 Principal
1.01.03 Principal's Secretary
1.01.04 Assistant Principal
1.01.05 Assistant Principal Reception Area
1.01.06 Conference Room
1.01.07 Workroom - Administration
1.01.08 Administration Storage
1.01.09 Faculty Lounge
1.01.10 Financial Secretary's Office
1.01.11 Attendance Office
1.01.12 Business Manager's Office
950
200
120
700
200
800
400
350
1,000
120
120
120
1.02.00 Other Spaces
1.02.01 Volunteer Office
1.02.02 In School Suspension
1.02.03 Security Room
1.02.04 Special Program Office (signature)
1.02.05 Special Program Conference Room
1
1
1
2
2
400
400
100
200
400
400
400
100
400
800
1.03.00 Evening/Summer School
1.03.01 Program Office
1.03.02 Program Reception
7
1
120
400
840
400
Page 104 of 112
8,420
5,080
1
1
1
5
1
2
1
1
1
1
1
1
950
200
120
140
200
400
400
350
1,000
120
120
120
950
200
120
700
200
800
400
350
1,000
120
120
120
1
1
1
2
2
400
400
100
200
400
400
400
100
400
800
7
1
120
400
840
400
2,100
2,100
1,240
SUPPORT
2.02.00 Guidance
2.02.01 Counselor's Office
2.02.02 Psychologist Office
2.02.03 Student Records
2.02.04 Guidance Reception
2.02.05 Career Room
2.02.06 Guidance Conference Room
2.02.07 Student Support Office
2.02.08 Registrar
2.02.09 Workroom - Guidance
2.02.10 Testing Coordinator
2.02.11 Testing Material Storage
subtotal
8,420
5,080
950
200
120
140
200
400
400
350
1,000
120
120
120
Health Room Waiting
Nurse's Office
Examination Room
Rest Area
Student Rest Room
Treatment/Medication
Health Room Storage
# of square
rooms footage
subtotal
1
1
1
5
1
2
1
1
1
1
1
1
2.00.00 STUDENT
2.01.00 Health
2.01.01
2.01.02
2.01.03
2.01.04
2.01.05
2.01.06
2.01.07
MODERNIZATION
1,240
4,430
890
1
1
1
1
2
1
1
150
100
100
200
75
140
50
150
100
100
200
150
140
50
6
1
1
1
1
1
3
1
1
1
1
120
120
250
450
750
300
120
120
100
120
250
720
120
250
450
750
300
360
120
100
120
250
4,430
890
1
1
1
1
2
1
1
150
100
100
200
75
140
50
150
100
100
200
150
140
50
6
1
1
1
1
1
3
1
1
1
1
120
120
250
450
750
300
120
120
100
120
250
720
120
250
450
750
300
360
120
100
120
250
3,540
3,540
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION
SPECIFICATION
PROGRAM SUMMARY
# of square
rooms footage
3.00.00 CORE INSTRUCTIONAL PROGRAMS
3.01.00 Classrooms
3.01.01 Classroom
Language Arts
Mathematics
Social Studies
3.01.02 Teacher Planning (per teacher)
40
14
14
12
49
3.02.00 Resource
3.02.01 General Resource
3.02.02 Special Education Resource
3.02.03 Speech
3.02.04 ESOL
3.03.00 Special Education
3.03.01 Special Education Classroom (FLS & Hannah More
3.03.02 Storage - Special Education
3.03.03 Teacher Planning - Special Education (per tchr)
3.03.04 Special Education Conference Room
3.03.05 Special Education Office
3.04.00 Alternative Education
3.04.01 Classroom
3.04.02 Storage - Alternative Education
3.04.03 Decision Making Room
3.04.04 Clinical Office
3.04.05 Teacher Planning - Alt Education (per teacher)
4.00.00 SPECIALIZED INSTRUCTIONAL PROGRAMS
4.01.00 Art
4.01.01 Art Studio
4.01.02 Storage Room - Art
4.01.03 Kiln/Clay Room
4.01.04 Ceramic Art Studio
4.01.05 Communication Art Studio
4.01.04 Teacher Planning - Art (per teacher)
4.02.02
4.02.03
4.02.04
4.02.05
4.02.06
4.03.00 Music
4.03.01
4.03.02
4.03.03
4.03.04
4.03.05
4.03.06
4.03.07
4.03.08
4.03.09
subtotal
subtotal
51,840
38,450
900 36,000
50
2,450
1
4
1
0
800
500
300
800
800
2,000
300
0
4
1
12
1
2
900
400
50
300
120
3,600
400
600
300
240
4
1
2
2
7
900
200
400
100
50
3,600
200
800
200
350
52,530
36,400
40
910 36,400
49
50
2,450
1
4
1
0
800
500
300
800
800
2,000
300
0
4
1
12
1
2
925
450
50
400
120
3,700
450
600
400
240
4
1
2
2
7
910
200
400
100
50
3,640
200
800
200
350
2,450
3,100
3,100
5,140
5,390
5,150
5,190
140,765
4,700
1
1
1
1
1
4
1,200
200
300
1,400
1,400
50
1,200
200
300
1,400
1,400
200
1
9,650
9,650
Library Media Workroom
Library Media Specialist's Office
Storage - Library Media
Seminar Room
Publication Room
1
1
1
1
1
800
200
600
400
900
800
200
600
400
900
General Music Classroom
Storage - General Music
Instrumental Music Classroom
Practice Module
Storage - Instrumental
Keyboard Music Classroom
Ensemble Classroom
Storage - Robe and Uniform
Teacher Planning - Music (per teacher)
1
1
1
5
1
1
1
1
4
2,000
500
2,400
200
600
1,200
1,200
350
50
2,000
500
2,400
1,000
600
1,200
1,200
350
200
4.02.00 Library Media Center
4.02.01 Library Reading Room
MODERNIZATION
# of square
rooms footage
143,338
4,750
1
1
1
1
1
4
1,200
250
300
1,400
1,400
50
1,200
250
300
1,400
1,400
200
1
1
1
1
1
1
1
5,138
6,765
800
200
600
400
900
5,138
6,765
800
200
600
400
900
1
1
1
5
1
1
1
1
4
2,000
500
2,400
200
600
1,200
1,200
350
50
2,000
500
2,400
1,000
600
1,200
1,200
350
200
12,550
14,803
9,450
9,450
Page 105 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION
PROGRAM SUMMARY
SPECIFICATION
# of square
rooms footage
4.04.00 Physical Education
4.04.01 Gymnasium
4.04.02 Teacher Planning w/ Shower Room
4.04.03 Storage - Gymnasium
4.04.04 Auxiliary Gymnasium
4.04.05 Physical Education Classroom
4.04.06 Fitness Lab
4.04.07 Locker Rooms
4.04.08 Bin Storage
4.04.09 P.E. Laundry
4.04.10 Exterior Storage
4.04.11 Dance Studio
4.04.12 Costume Area
4.04.13 Concessions
4.04.14 Team Rooms
4.04.15 Training Room
4.04.16 Coaches Office
4.05.17 Athletic Directors' Office
4.05.18 Officials' Locker Room
4.05.00 Science
4.05.01 Biology Laboratory/Classroom
4.05.02 Chemistry Laboratory/Classroom
4.05.03 Earth/Space Laboratory/Classroom
4.05.04 Physics Laboratory/Classroom
4.05.05 Student Project Area
4.05.06 Chemical Storage
4.05.07 General Science Storage
4.05.08 Prep Room
4.05.09 Teacher Planning (per teacher)
1 13,000 13,000
1
860
860
2
1,000
2,000
1
5,000
5,000
2
900
1,800
1
4,800
4,800
2
1,600
3,200
1
900
900
1
150
150
1
350
350
1
2,000
2,000
1
350
350
1
150
150
1
3,680
3,680
1
200
200
1
740
740
1
200
200
2
220
440
3
2
1,000
75
3,000
150
8
1
10
1,000
125
50
8,000
125
500
4.08.00 Family and Consumer Science
4.08.01 Multipurpose Laboratory
4.08.02 Food/Nutrition Laboratory
4.08.03 Storage - Family and Consumer Science
4.08.04 Food Preparation Area
4.08.05 Child Development Laboratory
4.08.06 Child Development Classroom
4.08.07 Storage - Child Development
4.08.08 Exterior Storage - Child Development
4.08.09 Teacher Planning - FACS (per teacher)
1
2
1
1
1
1
1
1
4
1,625
1,515
500
500
1,040
800
75
75
50
1,625
3,030
500
500
1,040
800
75
75
200
4.09.00 Technology Education
4.09.01 Technology Laboratory/Workshop
4.09.02 Fabrication Room
4.09.03 Design Computer Laboratory
4.09.04 Classroom - Technology Education
4.09.05 Storage - Technology
5
1
1
0
1
1,450
600
1,200
900
250
6
50
Page 106 of 112
39,820
1 13,000 13,000
1
860
860
2
1,000
2,000
1
5,000
5,000
2
900
1,800
1
4,800
4,800
2
1,600
3,200
1
900
900
1
150
150
1
350
350
1
2,000
2,000
1
350
350
1
150
150
1
3,680
3,680
1
200
200
1
740
740
1
200
200
2
220
440
20,220
7,425
4,455
2,970
2,970
800
200
200
500
700
4.09.06 Teacher Planning - Technology (per teacher)
subtotal
39,820
1,485
1,485
1,485
1,485
800
200
100
250
50
4.07.00 World & Classical Language
4.07.01 World & Classical Language Lab/Classroom
4.07.02 Storage - World & Classical Language
4.07.03 Teacher Planning - World & Classical Language
# of square
rooms footage
subtotal
5
3
2
2
1
1
2
2
14
4.06.00 Computer Science
4.06.01 Computer Science Laboratory
4.06.02 Computer Science Office
MODERNIZATION
20,300
5
3
2
2
1
1
1
2
14
1,500
1,500
1,500
1,500
800
200
100
250
50
7,500
4,500
3,000
3,000
800
200
100
500
700
3
2
1,000
75
3,000
150
8
1
10
1,000
125
50
8,000
125
500
1
2
1
1
1
1
1
1
4
1,625
1,550
500
510
1,050
900
75
75
50
1,625
3,100
500
510
1,050
900
75
75
200
7,250
600
1,200
0
250
5
1
1
0
1
1,450
600
1,200
900
250
7,250
600
1,200
0
250
300
6
50
300
3,150
3,150
8,625
8,625
7,845
8,035
9,600
9,600
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION
PROGRAM SUMMARY
SPECIFICATION
# of square
rooms footage
4.10.00 Business Education
4.10.01 Business Classroom
4.10.02 Business Computer Laboratory
4.10.03 School Store
4.10.04 Storage - Business
4.10.05 Teacher Planning - Business (per teacher)
4.11.00 Theatre
4.11.01 Auditorium
4.11.02 Stage
4.11.03 Stage Wings
4.11.04 Dressing Room
4.11.05 Set Room
4.11.06 Set Storage
4.11.07 Prop Storage
4.11.08 Projection/Sound Booth
4.11.09 Blackbox Theatre
4.11.10 Video Production
4.11.11 Control Room
4.11.12 Auditorium Office
5.00.00 BUILDING OPERATIONS
5.01.00 Custodial
5.01.01 Custodial Closet
5.01.02 Building Engineer's Office
5.01.03 Can Wash
5.01.04 Book Storage
5.01.05 General Storage
5.01.06 Exterior Storage
5.01.07 Engineer's Shop
5.01.08 Equipment Storage
5.01.09 Custodial Locker Room
5.01.10 Receiving
5.02.00 Food Services
5.02.01 Cafeteria (per src)
5.02.02 Kitchen
5.02.03 Kitchen Managers Office
5.02.04 Food Staff Locker Room
5.02.05 Chair storage
5.02.06 Food Service Laundry Room
5.03.00 Rest Rooms
5.03.01 Public (Adult) Rest Room
5.03.02 Staff Rest Room
5.03.03 Student Rest Room
MODERNIZATION
# of square
rooms footage
subtotal
subtotal
4,050
1
2
1
1
3
900
1,000
500
500
50
900
2,000
500
500
150
4,050
1
2
1
1
3
900
1,000
500
500
50
900
2,000
500
500
150
20,755
996
1
1
2
1
1
1
2
1
1
1
1
12 11,955
1,800
1,800
1,800
1,800
350
700
500
500
300
300
300
300
200
400
1,800
1,800
900
900
200
200
100
100
20,755
996
1
1
2
1
1
1
2
1
1
1
1
12 11,955
1,800
1,800
1,800
1,800
350
700
500
500
300
300
300
300
200
400
1,800
1,800
900
900
200
200
100
100
33,625
5,470
9
1
1
4
1
1
1
1
1
1
30
100
50
500
1,000
400
200
400
250
800
270
100
50
2,000
1,000
400
200
400
250
800
45,522
5,470
9
1
1
4
1
1
1
1
1
1
30
100
50
500
1,000
400
200
400
250
800
270
100
50
2,000
1,000
400
200
400
250
800
17,095
664
1
1
1
1
1
18 11,955
4,400
4,400
200
200
100
100
400
400
40
40
17,095
664
1
1
1
1
1
18 11,955
4,400
4,400
200
200
100
100
400
400
40
40
3,800
4
14
10
150
50
250
600
700
2,500
5.04.00 Mechanical/Electrical
5.04.01 Mechanical Room
5.04.02 Electrical Room
5.04.03 Electrical Closet
1
1
6
2,000
500
35
2,000
500
210
5.05.00 Telecommunication
5.05.01 Telecommunication Room
5.05.02 Telecommunication Closet
1
6
250
300
250
1,800
3,800
4
14
10
150
50
250
600
700
2,500
2,710
14,607
1 13,897 13,897
1
500
500
6
35
210
2,050
2,050
1
6
250
300
250
1,800
Page 107 of 112
Severna Park High School
Feasibility Study
GWWO, Inc./Architects
Severna Park, Maryland
APPENDIX D – FUNCTION AND AREA SUMMARY - MODERNIZATION
PROGRAM SUMMARY
SPECIFICATION
# of square
rooms footage
5.06.00 Circulation (sf part of efficiency adjustment unless noted)
5.06.01 Entrance Vestibule
5.06.02 Classroom Corridors
5.06.03 Public Corridors
5.06.04 After-hour Lobby
5.06.05 Gymnasium Lobby
MODERNIZATION
# of square
rooms footage
subtotal
subtotal
2,500
1
1
1,000
1,500
1,000
1,500
2,500
1
1
1,000
1,500
1,000
1,500
Subtotal all programs
239,080
254,240
Efficiency adjustment (new facility)
89,655
328,735
106,448
360,688
6,500
6,500
GROSS SQUARE FOOTAGE
6.00.00 OTHER AREAS
6.01.00 Ancillary Structure
6.01.01 Concession Building with Rest Rooms
6.01.02 Field House
6.01.03 Maintenance Building
Subtotal all programs (including Other Areas)
Efficiency adjustment (new facility)
GROSS SQUARE FOOTAGE (with Other Areas)
Page 108 of 112
0
1
1
2000
5000
1500
0
5000
1500
0
1
1
245,580
92,093
337,673
2000
5000
1500
0
5000
1500
260,740
107,113
367,853
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
APPENDIX E – SUSTAINABLE DESIGN
Replacement options will be registered with the US Green Building Council as a LEED® project and
will pursue LEED® Silver certification (within the range of 50-59 total points). The design will
showcase the incorporation of sustainable techniques and materials. The following outlined
categories follow the divisions of the LEED® for Schools rating system and possible points to
achieve.
1. Sustainable Sites
Integrating building location and sustainable site features will minimize the environmental
impact of buildings on the site. Potential Strategies include:
a. Minimize site disruption, soil erosion, and air pollution associated with construction
activities.
b. Appropriate landscaping for energy conservation.
c. Planting native trees species.
d. Eliminate the use of pesticides in order to promote protection of regional watersheds
e. Examining alternative energy systems such as photovoltaic panels for potential use
as pedestrian walkway shading and weather protection devices in addition to or
instead of roof mounted.
f. No “light pollution” since exterior lighting is installed at a minimum (for safety
requirements) to allow for view of night sky.
g. High albedo roofing to reduce heat island effect.
h. Low-emitting and fuel efficient vehicle parking spots.
2. Water Efficiency
Water harvesting and water conservation are to be implemented.
include:
Potential Strategies
a. Reduce the need for municipally supplied water and carbon cost of treating that
water.
b. Maximize water conservation – students, staff, and community can learn about these
features – educational tool.
i. Eliminate the use of potable water for irrigation.
ii. Low flush toilet fixtures
iii. Low flow aerators for sink faucets
iv. Low flow shower heads
v. Recycled water for mechanical system recharge
vi. Recycle mechanical system condensate.
c. Manage and conserve storm water and reduce storm water runoff
i. Harvesting rainwater for many uses including irrigation.
ii. Designing pervious parking lots and paved surfaces to capture storm water
below paved areas instead of as runoff
iii. Using retention and detention ponds as educational tools
Page 109 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
3. Energy and Atmosphere
Reduce energy consumption of buildings. Potential Strategies include:
a. Computer energy modeling used to inform the design of the building. Annual energy
savings and yearly operating cost reduction goal should be a minimum of 30% over
the American Society of Heating, Refrigeration and Air-Conditioning Engineers
(ASHRAE) Standard 90.1
b. The building should be zoned and controlled in a way specific to occupancy and use
profiles. These systems will recognize the mass and building characteristics of the
building as well as control logic designed to maximize the return on investment.
c. All building system components selected will be free of chlorofluorocarbons (CFCs)
and hydro chlorofluorocarbons (HCFCs).
d. Daylighting should be present in all classrooms and spaces that are regularly
occupied by students along with intelligent controls of electric lighting that recognize
the amount of useful daylight present in each space.
e. Natural ventilation should be used where possible.
f. Mechanical ventilation should be decoupled from space conditioning to ensure fresh
air and energy recovery independent of space conditioning requirements.
g. The project should incorporate full enhanced building system commissioning to
insure that the design intent will be met.
4. Materials and Resources
Sustainable material choices will reduce use of virgin materials within the building. Potential
Strategies:
a. Storage and collection of recyclable materials within the school.
b. Divert a minimum of 75% of the materials during demolition and construction from
the landfills through recycling or salvaging.
c. Using new construction materials that have a significant percentage of recycled
content.
d. Using materials that are harvested, extracted, and manufactured within a 500 mile
radius of the project site
e. All wood products used on the project are Forest Stewardship Council (FSC) certified
products.
5. Indoor Environmental Quality (IEQ)
Reducing levels of contaminants, increasing filtered outside air and ventilation, and
monitoring humidity all contribute to a more desirable indoor air quality. Potential strategies
include:
a. Smoke free school zone.
b. Classroom spaces will meet a certain STC rating for acoustics - increased insulation,
seals and special acoustic ceiling tiles for better communication between teachers
and students.
c. Low emitting materials including adhesives & sealants, paints & coatings, flooring
systems, agrifiber products, furniture, and ceiling & wall systems.
Page 110 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
d. Appropriate ventilation and elimination of chemicals and pollutants such as copy
machines and tracked-in dirt from the exterior.
e. Use outdoor spaces as instructional areas giving students the opportunity for fresh
air during the day.
f. Carbon dioxide (CO2) monitors that inform the building controls to insure adequate
amounts of ventilation where and when needed.
g. Designing electric lights to take advantage of natural light in spaces.
h. A mold free environment.
i. The building additions and renovations or new construction implementing the use of
daylight and views throughout.
j. Individual temperature regulation of rooms to provide adequate comfort for all
occupants.
6. Innovation in Design
Incorporating innovative techniques that are unique to SPHS and setting a precedent for
other LEED school projects in the future. One potential example of an innovation credit for
this project would be:
a. Green housekeeping plan for the school – use of non-toxic cleaning and maintenance
products and environmentally friendly practices.
7. Regional Priority
Severna Park and surrounding Anne Arundel County areas potentially have materials or
regional differences that could result in achieving specific Regional Priority credits. More
research will be done to determine what sets the area apart and where we could achieve
these additional credits.
8. The school as a teaching tool
The school building can be used and incorporated as part of the school day curriculum.
Students will take part in recognizing how the building works and why the various
sustainable features of the building are important for understanding the larger built
environment.
Page 111 of 112
Severna Park High School
Severna Park, Maryland
Feasibility Study
GWWO, Inc./Architects
APPENDIX F – BUILDING SECURITY AND SITE
Security will be based on Crime Prevention through Environmental Design (CPTED). These strategies
include:




Natural Surveillance – A design concept directed primarily at keeping intruders easily
observable. Promoted by features that maximize visibility of people, parking areas and
building entrances: doors and windows that look out on to streets and parking areas;
pedestrian-friendly sidewalks and streets; adequate nighttime lighting.
Territorial Reinforcement – Physical design can create or extend a sphere or extend a sphere
of influence. Users then develop a sense of territorial control while potential offenders,
perceiving this control, are discouraged. Promoted by features that define property lines and
distinguish private spaces from public spaces using landscape plantings, pavement designs,
gateway treatments, and “CPTED” fences.
Natural Access Control – A design concept directed primarily at decreasing crime opportunity
by denying access to crime targets and creating in offenders a perception of risk. Gained by
designing streets, sidewalks, building entrances and neighborhood gateways to clearly
indicate public routes and discouraging access to private areas with structural elements.
Target Hardening – Accomplished by features that prohibit entry or access: window locks,
dead bolts for doors, interior door hinges.
Page 112 of 112